Abstract
The fundamental goal of a construction project is to complete the construction phase within budget, but in practice, planned cost estimates are often exceeded. The causes of overruns can be due to insufficient preparation and planning of the project, changes during construction, activation of risky events, etc. Also, construction costs are often calculated based on experience rather than scientifically based approaches. Due to the challenges, this paper investigates the potential of several different machine learning methods (linear regression, decision tree forest, support vector machine and general regression neural network) for estimating construction costs. The methods were implemented on a database of recent high-rise construction projects in the Republic of Croatia. Results confirmed the potential of the selected assessment methods; in particular, the support vector machine stands out in terms of accuracy metrics. Established machine learning models contribute to a deeper understanding of real construction costs, their optimization, and more effective cost management during the construction phase.
1. Introduction
The success of the construction phase of a construction project generally implies completion within the planned budget, with the achievement of the planned construction deadline and satisfactory quality of the work performed [1]. Due to frequent overruns of planned construction costs and failure to complete within the planned budget [2,3], construction projects are often perceived as financially unsuccessful.
The financial aspects of construction are defined in the construction contract. The contract defines the relations and obligations between the client/investor and the contractor and, as one of its components, contains the price of the works, which is usually derived from the estimate of construction costs in the planning phase [4]. This estimate allows for the assessment of the feasibility of the projects; it is one of the main factors for making decisions in the earlier phases and is the basis for effective cost management. The estimate can impact the investor’s decision on whether to move forward with the project or not. In addition, for many investors, finalizing the construction within an allocated budget is the most important factor in their satisfaction with the project implementation. Inaccurate cost estimates can have a significant financial impact and negatively affect investor trust in other construction participants [5], since investors bear the project’s largest financial burden. Other negative consequences of cost overruns include unprofitability, delays, legal problems, reduced productivity, reduced project quality, reduced quality of subsequent services, etc. [6]. To minimize deviations and enable efficient project implementation regarding financial aspects, careful and thorough planning and control, i.e., overall construction cost management, are key elements.
Construction costs in current construction practice are most often calculated on a flat rate basis or according to unit prices and quantities of work [7]. Estimates of this type can be exposed to human errors, either during analysis or due to subjective, biased judgments [8]. It is also not uncommon for data on construction costs to be delivered quickly under various pressures and requirements, while uncertainties and risks are ignored, leading to actual costs exceeding initial estimates [7]. Risks are phenomena that can jeopardize the achievement of defined project goals [9].
Given these considerations, the construction industry requires an accurate and dependable tool for estimating project construction costs.
The literature points out the capability of machine learning for these purposes, using various linear and nonlinear techniques and algorithms that learn patterns and relationships in data. Simple techniques, such as regression analysis (simple, multiple, logistic), to more advanced methods such as various types of neural networks, decision trees, support vector machines, expert systems, gradient boosting, fuzzy logic, and others [10,11,12,13] are used. The methods mentioned differ in how they process data, the types of knowledge they extract from the data to predict desired outcomes, and the complexity of the models.
Machine learning methods are most simply defined as computer systems that learn from data [10]. By using a database and applying machine learning methods, it is possible to develop computer models for more accurate estimates of construction costs [14].
Various machine learning methods have been used worldwide to predict the construction costs of different types of buildings, with varying levels of accuracy. Some of the more recent authors and studies are listed in references [15,16,17,18,19,20,21,22,23,24,25,26,27], where model errors, expressed as mean absolute percentage errors (MAPE) and coefficients of determination (R2), range mainly from about an MAPE of 10% to 30%, and R2 above 0.900. An explanation of these metrics of model accuracy is provided in Section 3.
Some of the prominent research on predicting the construction costs of building projects is highlighted below.
The authors [15] used the Extreme Gradient Boosting algorithm to estimate construction costs. The developed model gave an R2 of 0.952 and an MAPE of 9%. The size of inflation in the observed period proved to be the most significant variable for estimating costs. The same algorithm is also used by the authors [27] for estimating construction renovation costs. Based on 45 input variables, they developed a model with an MAPE of 9%, and the price of crude oil was identified as the most significant variable. The authors [22] predicted construction costs of renovation projects using an artificial neural network model, which yielded an R2 of about 0.980. The authors [23] used an artificial neural network and obtained an MAPE of 11.65%. The authors [24] used a hybrid neural network and a Dung beetle optimizer, achieving a MAPE of 17.56% with 20 input variables. The above-ground area of buildings is identified as the most significant input variable. The authors [25] developed a hybrid model combining a neural network and Building Information Modelling (BIM), achieving an R2 of 0.950. Authors [21] compared the performance of several machine learning methods, and the support vector machine model was identified as optimal, achieving an R2 of 0.897 and a MAPE of 23.70%. The variable with the greatest influence in the model is the total floor area. The authors [26] used 10 different machine learning methods to estimate construction costs. The optimal model was developed using HistGradient Boosting Regression, and the most influential variable is the unit price of the formwork.
As can be seen, studies covering the research topic are numerous. However, further research is needed to examine the effectiveness of different machine learning algorithms, identify best practices for feature selection, and test the generalizability of these methods on selected types of construction projects [17]. It is also worth examining different sets of input data to obtain better, more reliable results through experimental approaches across studies. Also, since the research results of the mentioned authors relate to areas outside the Republic of Croatia, they are not necessarily applicable in that area. The construction sector in the Republic of Croatia is characterized by following: a relatively small and open market dominated by small and medium-sized enterprises, dependence on public investments and European Union funds, sensitivity to macroeconomic changes, uneven regional development, lack of labor force, price instability of construction materials, rising labor costs, regulatory requirements and restrictions, difficult administrative procedures related to spatial planning and issuing permits, as well as specific geological and seismic conditions. All these characteristics affect the size, structure, and unpredictability of building costs, creating difficulties in planning. Due to the aforementioned characteristics and differences across countries, it is useful to conduct local studies to develop customized planning and project management practices [28].
For the above reasons and due to data availability, the research covered in this work is limited to the territory of the Republic of Croatia. For the purposes of developing the machine learning models, the available database of construction projects in the mentioned area will be used.
According to some studies, construction cost overruns in the Croatian context are typically around 40% [3,7,29].
Several authors have developed machine learning models for estimating construction costs in Croatia, as listed in references [3,7,9,29,30]. The authors [7] developed predictive models based on a database of 24 different high-rise construction projects, using contracted construction costs as input variables. The most suitable model was a regression model, which gave a MAPE of 13.82%. The authors [30] used 57 road construction projects, using the length and width of the road, the planned duration, and construction costs as input variables. Different types of neural network architecture were used to develop the models, and the optimal model achieved an MAPE of 10.22%. The authors [3] used a database of 25 road projects and developed several models (linear regression, neural network, support vector machine) based on planned costs; the most accurate was a neural network, with an MAPE of 25.65%. The author [9] developed a multiple regression model to estimate construction costs of high-rise projects, using a database of 34 projects. The area of buildings and the planned construction costs proved to be significant input variables, and the model gave an MAPE of 6.14%. The authors [29] developed neural network models to estimate construction cost overruns using 5 recent high-rise and low-rise construction projects across different construction phases. As input, a set of variables was used that determines the project’s success, but the experimental approach failed to yield a model with satisfactory accuracy. The most accurate model gives an MAPE of as much as 166.76%, which emphasizes the need for further refinement of the models.
All mentioned foreign and domestic studies show that machine learning methods are a promising approach to estimating construction costs in the Republic of Croatia. What is evident is that the number of recent studies in the Republic of Croatia is small, especially for recent high-rise construction projects, which confirms the need for research that would contribute to the development and improvement of machine learning models for estimating the construction costs of these projects in the Croatian context. The purpose of this paper is to obtain precise estimates using a more recent database of construction projects in the Republic of Croatia, focusing on high-rise projects, and to compare several machine learning methods experimentally to test different approaches and obtain the best possible results. The newer and more comprehensive the database, the better the model reflects current costs and construction conditions, increasing the precision and reliability of predictions for future projects.
The main research objective of this study is to determine how effectively selected machine learning methods can estimate construction costs of high-rise construction projects in the Republic of Croatia, using recent project data.
The aim of this paper is to examine the potential of applying several selected machine learning methods to estimate the actual construction costs of high-rise construction projects, using a recent database. Based on the available database, predictive models will be developed to analyze this approach for estimating construction costs. The paper will show to what extent machine learning methods can contribute to more precise and reliable cost estimates before the execution of works and the conclusion of a construction contract. The main task of the model is to help with proactive decision-making and decrease the risk of an inconsistency between planned and actual construction costs.
The structure of the paper is organized as follows: the Section 1 introduces the research, the rationale for its implementation, a brief overview of the relevant literature, and the objective of the research. The Section 2 discusses in detail the applied research methodology. The Section 3 and Section 4 present and discuss the results obtained. The Section 5 brings concluding considerations.
2. Materials and Methods
2.1. Data Collection and Processing
The data were collected as part of a scientific project for young scientists at the University of Rijeka (uniri-mz-25-71), which is thematically related to the development of computer models as support for the management of construction projects. The collection of relevant information took place through expert visits to active construction sites and a review of available project documentation. The data cover projects from the territory of the Republic of Croatia, primarily Primorje-Gorski Kotar County. Looking at the time context, the data collection was carried out from mid-2020 to mid-2025, thus forming a current database with data on more recent construction projects.
For the purposes of this paper, data on high-rise construction projects that were in the middle stage of construction at the time of data collection, i.e., in the phase of execution of construction and installation works, were extracted from the broader available database. High-rise construction includes the construction of buildings for various residential, public, and commercial purposes [31], which in Croatia make up most projects.
The task of the prediction models in this research is to examine the possibility of estimating more realistic construction costs, with an emphasis on the accuracy and ease of application of the developed models, using the limited available dataset. Details of the available data (variables) are presented in Table 1 below.
Table 1.
Available variables for modeling actual construction costs.
The database presented includes a set of information, i.e., independent variables, based on which the cost estimation model will be defined. The database contains all variables for which data could be collected from available sources, with the aim of determining the impact of individual variables on construction costs and the possibility of developing accurate predictive models. In addition to the technical characteristics of buildings, such as floor area, height, number of floors, and planned cost and time as the main determinants of the construction contract, the database also includes the basic characteristics of the contractor company, which is not the case in previous studies. Since the focus of this research is the construction phase, where the main participant and executor of the works is the contractor, it is worth including its characteristics through experience and human capacities and investigating whether these characteristics affect the observed cost performance, i.e., whether they contribute to the development of accurate predictive models. The structure and number of variables used are considered adequate for the development of a construction cost estimation model, considering the research objective, data availability, the analyzed type of buildings, and the analyzed phase of the project life cycle. There is no generally accepted number or type of variables for the development of such models, but it is necessary to determine through an experimental approach whether such a combination provides reliable and more accurate models. The set of input variables presented here encompasses key technical, contractual, and organizational factors that can be collected early and before signing the contract, thereby increasing the applicability of the obtained results to practice. Accordingly, the included predictors were selected primarily based on data availability, theoretical basis, relevance, and previous studies [3,7,9,30].
Variable Y represents the dependent (target) variable that is to be estimated in this case. Variables X1–X9 serve as input variables, based on which the target variable is estimated; they represent predictors or independent variables.
Given that the data were collected during the middle phase of construction, the actual construction costs in this case refer to the minimum costs that will arise during construction, and if no major problems arise in the execution by the end of the works, or corrective actions are not taken that may affect the course of the works. The data presented in this way certainly provides a more objective insight and a more realistic picture of actual costs, allowing informed decisions to be made with the aim of improving cost management in the subsequent phases of the construction project. In this way, it will also be possible to reduce the size of the total cost overrun at the end of the project.
The database that will be processed contains 47 project samples, which represent a larger set of data on high-rise construction projects than those used in previous Croatian studies. Such a database can serve as a basis for model development, testing the applicability of machine learning methods, gaining insight into their potential accuracy and reliability, and identifying directions for future research.
Database processing was performed in Microsoft Excel 2021, and the descriptive statistics of the sample are shown in Table 2.
Table 2.
Basic descriptive statistics of the sample.
The minimum budget is 97,783.69 euros, while the maximum budget is 70,840,682.88 euros. The average actual construction costs are 8,886,958.94 euros. The minimum actual costs are 106,178.25 euros, while the maximum reached 92,092,887.74 euros.
All data on the projects presented indicate their diversity in terms of characteristics, complexity, dynamics, and finances, as well as the challenges in their cost management, providing insight into a broader spectrum of construction projects in Croatia. Looking at the statistical indicators of the data set, a small number of projects showed deviations from most projects, especially in terms of the size of planned and actual construction costs. Such deviations (outliers) indicate projects with special financial characteristics. Outliers were not excluded from the database to preserve the diversity of real projects and reflect real market conditions. Their removal would further reduce the already limited database and lead to the loss of valuable information about rare but economically significant projects. Retaining the deviant data increased the data’s variability and model applicability. Possible negative impacts, such as deviations from normality, reduced stability, reduced interpretability, were mitigated by using transformation functions.
The indicators highlight the requirement for careful planning, tracking, and control to secure more successful project realization in terms of cost efficiency. All cost deviations, regardless of their extent, jeopardize the successful completion of the project. Additional financial resources are not always easy to secure, so construction costs need to be carefully and properly planned and managed effectively. Good planning contributes to more informed decision-making, increases efficiency, ensures the use of resources, and leads to a sustainable project outcome [3].
2.2. Machine Learning Models Development
Machine learning is a field of computer science that mimics human intelligence by learning from the environment [32]. It is one of the fastest-growing technical fields today, located at the crossroads of computer science and statistics and at the center of artificial intelligence and data science [33]. The main advantages of these techniques are the ability to work under uncertain conditions, handle incomplete data, and make decisions and infer new cases based on experience with previous cases [10].
For the development of predictive machine learning models, powerful, precise software tools are used that employ sophisticated algorithms to build, train, and validate the model. In this work, DTREG Predictive Modeling Software (https://www.dtreg.com/) was used, which supports a range of predictive modeling methods. The software is characterized by simplicity and the intuitiveness of its application. The interface of the mentioned software is easy to use, allows for quick training, validation, and modification of the model without the need for coding; therefore, its application is suitable for a wide range of users and facilitates implementation in practice.
Given the capabilities of the software, the availability of different types of prediction methods within the software, and the size of the database, the linear regression (LR), decision tree forest (DTF), support vector machine (SVM), and general regression neural network (GRNN) methods were selected to create prediction models. The selected methods are more suitable for limited databases [3,34]. These methods allow for relatively simple learning, generalize well despite the limited number of samples, and reduce the risk of overfitting. The four selected machine learning methods for estimating of high-rise construction costs have not been compared in global or Croatian studies to date, as far as the author of this paper is aware.
LR is a statistical method used to examine the association between variables. Regression models are relatively simple and efficient predictive models, and are based on a clearly defined mathematical approach (formula) with the ability to interpret the relationships between dependent and independent variables, as well as the measures and strengths of their mutual influence [35,36].
DTF consists of a set of decision trees whose predictions are combined to obtain an overall prediction [34]. By building a forest, the errors of one decision tree are compensated for by the other decision trees in the forest [37]. Each tree learns from a random subset of the data, and the final prediction is obtained by averaging their predictions [34].
SVM is a method that uses a nonlinear transformation of the original training data to map it into a higher-dimensional space. SVM then searches for a linear optimal separating hyperplane, which is the border that separates the data into classes. The optimal hyperplane is found using support vectors (the most significant data points in training) and margins (defined by the support vectors). After the learning process, the model can use the learned limit for prediction, that is, it can determine to which class the new unknown data belongs [38]. SVM models are close relatives of classical neural networks [34].
Artificial neural networks are mathematical models of the processes carried out by networks of neurons in the brains of living beings. They consist of interrelated, artificially created neurons and mathematical functions that transmit information between neurons and participate in the process of knowledge creation [39]. The network first learns from input data, then predicts new data. There are several types of neural networks that differ in architecture, learning methods, and other parameters; GRNN was used here. GRNN is a simple single-pass associative memory feed-forward type of artificial neural network, which has a high generalization ability [30].
A comparative overview of the methods used in this work, including basic general characteristics, is provided in Table 3.
Table 3.
General characteristics of the machine learning methods used [34,40,41].
By implementing several machine learning methods, the aim was to test how adequate some of them are for estimating construction costs, and to obtain the most precise results of the output models using an experimental approach. The relationship between the predictor and target variables is unknown; therefore, by testing several types of methods, the optimal prediction model can be identified [42]. It is almost impossible to know in advance which model will give the best results [43]; therefore, this experimental approach is recommended.
Due to a limited database, variability of standard deviation, outliers, and deviations of data from normality (Shapiro–Wilk Test; p-value < 0.05, normal: no), a logarithmic transformation was applied to the data before the software application, which reduced asymmetry and deviations. The application of transformation functions can reduce the complexity of the research problem, improve learning performance, enhance the stability and accuracy of the model, and improve the quality and interpretation of the model [44,45]. The implementation of the logarithmic function is common in research of this type, and its application to cost data can yield robust and reliable models [9,42,44,45,46].
The database imported into DTREG is in CSV format, with one data sample per row and one column per variable.
3. Results
3.1. Model Performance Metrics
The developed models will be evaluated and compared with respect to the magnitude of the resulting error in the estimation of the target variable. The model error was measured using the coefficient of determination (R2), root mean square error (RMSE), mean absolute error (MAE), and mean absolute percentage error (MAPE). These metrics are standard estimators of model precision and are suitable for data with high-cost values, as is the case here [47]. The formulas for calculating the individual accuracy estimators are shown in Table 4.
Table 4.
Formulas (1)–(4) of applied model performance metrics.
The R2 indicates the general suitability of the prediction model and the extent to which it explains the data [36,51]. R2 indicates how much of the proportion of the target variable’s variability can be explained by the predictor variables [52]. R2 values are in the interval of [0, 1] [53]. The closer R2 is to 1, the more representative and reliable the prediction model is. RMSE provides an overall picture of prediction errors and plays an important role in model assessment [54]. MAE measures the average absolute error in predictions, is very easy to calculate and interpret, and provides an unambiguous measure of the magnitude of the average error [43]. The lowest possible RMSE and MAE values are desirable. MAPE is included as a measure of model accuracy because it provides an easy-to-interpret measure of prediction accuracy and is expressed as a percentage. It is particularly suitable for comparing the efficiency of cost forecasting in construction [47]. In cost forecasting models, MAPE values of up to 21% indicate good model performance. All MAPE values below 10% indicate very accurate estimates [55,56].
3.2. Model Performance Comparison
The developed models gave the results shown in Table 5.
Table 5.
Results of developed construction cost prediction models.
In order to obtain a real picture of the value of the model’s precision, all metrics of the model’s accuracy were observed after returning to the real values of the costs, in such a way that an inversion of the logarithmic transformation function of the estimated costs was made, which were then compared with the real value of the costs in the original form.
The above results were obtained using an experimental approach, where the parameter settings that determine how the model trains on the data (learning rate, model complexity, smoothness parameter, kernel function, optimization method, etc.) were changed in the models to obtain results of the highest possible accuracy. It is also important that the models do not show signs of serious overfitting, which is a common problem in machine learning. An overfitted model cannot generalize to new data. The model performs well on the training set but adapts poorly to the validation and test sets. This is because an overfitted model has difficulty recognizing new patterns that differ from those in the training sample. Instead of learning general rules and relationships in the data, such a model memorizes all the data and random noise from the training sample and therefore performs poorly on new samples [57]. Model overfitting was assessed by comparing the performance of the models on the training and independent validation sets. Relatively small differences in the values of R2, RMSE, MAE, and MAPE between the training and validation sets indicate good generalization ability of the models. Also, the use of multiple performance metrics and an independent validation set ensures that the models did not learn noise from the training data. Given the results and the difference between training and validation in the developed models, which is expected given the size of the construction costs, the models are sufficiently stable and generalize well to new data, with no serious overfitting.
Slightly weaker results are observed only with the DTF model, which is probably a consequence of the size of the data set; therefore, in further research of develop a reliable DTF model, it is necessary to use larger data sets to reduce variance between decision trees.
The developed LR model is a multiple regression model. The validation method used is 10-fold V-fold cross-validation. The initial dataset is randomly divided into 10 approximately equal-sized groups. The procedure is iterative: 9 groups are used as the training set in each iteration, and the developed model is tested on the remaining group, which serves as the test set. The procedure is repeated 10 times, so that each group serves as the test set once [34]. Cross-validation is an optimal choice for limited data sets [3,34]. By checking the value of the Variance Inflation Factor (VIF) in the model, the presence of multicollinearity is excluded. In the presence of multicollinearity, the regression results can be unreliable, unstable, and difficult to interpret, but this is not the case here. VIF values up to 4 indicate satisfactory results [58]. In the developed model, the VIF ranges from 1.47 to 2.25, and the independent variable X7, which was highly correlated with variable X6 (k = 0.811), was excluded from the model. The other independent variables did not show a high level of mutual correlation (−0.800 < k > 0.800) [45]. In other machine learning models, independent variables were not excluded since they are not sensitive to the problem of multicollinearity.
The best results for the DTF model were obtained by experimentally setting the number of trees to 200, the minimum split node size to 4, and the maximum tree depth to 20. Table 5 does not show the training results for the DTF because the applied software does not show training metrics since the OOB validation is used in the DTF as a standard way of checking the accuracy of the model. OOB validation allows independent testing without requiring a separate data set or retaining rows during tree construction. When constructing and training each tree, about a third of the data does not enter that tree. Such data is OOB and used as test cases. In this way, all the data are used for learning, and the DTF model evaluates itself to determine how well it performs without a separate test set [34].
The developed SVM is a regression epsilon model. The chosen epsilon value within the model is a tolerance factor that controls when to stop the iterative optimization process [34]. A value of 0.001 was selected. Several options are available for selecting the kernel function. The kernel function converts the input data into a form more suitable for further processing [34]. Optimal results were obtained by applying a linear function that linearly separates the data into classes. To optimize the parameters of the model, the option of minimizing total error is selected in the software. The SVM model was validated using 10-fold cross-validation.
The created GRNN consists of 4 layers. The minimum error occurred with 30 neurons in the model. The optimal number of hidden-layer neurons is 18. The most important parameter of the GRNN model is the sigma value. Sigma determines how narrowly or broadly the model reacts to the input data; that is, it controls the extent of influence of each training data sample on the model. The model developed here is adjusted so that a separate sigma value is computed for each predictor. In the DTREG software, the conjugate gradient algorithm is used to calculate optimal sigma values and neuron weights [34,41]. The best results for the GRNN model were obtained by experimentally adjusting the sigma parameter, with a minimum of 0.05 and a maximum of 10. The Gaussian function was used as the kernel function in the model. The Gaussian function generates weights that are then used to calculate the predicted output. Validation of the model was carried out using the cross-validation method, where one sample was omitted (leave one out, LOO). The validation method can be presented as follows: N is the total number of initially available data samples (47). If one sample is omitted in each of the N iterations, the model is developed based on N − 1 (46) samples and then tested on the remaining sample [34].
3.3. Predictor Sensitivity Analysis
Sensitivity analyses were conducted for all developed models to assess the importance of each predictor for the overall model quality. The average importance of the predictor variables across all models is shown in Table 6.
Table 6.
Average importance of predictor variables.
The values shown represent the percentage significance of the predictors in the models used to predict the target variable. The values of each variable were randomized, and the impact of each on the quality of the model was measured [34]. It can be noted that the dominant predictor for predicting actual construction costs is information on planned construction costs (X9). This result is not surprising, as planned costs already incorporate most of the project characteristics captured by other predictors. Other predictors have a significantly smaller individual impact on the target variable and affect the model through minor corrections to the basic estimate. Their exclusion from the models reduces predictive performance, indicating that their contribution is not negligible. Specifically, in the SVM model, excluding remaining predictors led to a deterioration in model performance on the validation set. RMSE increased by about 18%, MAE by about 8%, R2 dropped by over 1%, and MAPE remained at a comparable level. According to the above, the model, with the included variables, has higher predictive accuracy and stability. Since large sums of cost are involved in construction projects, even small improvements in estimation accuracy have significant practical significance.
The set of retained predictors provides additional information not fully contained in the X9 variable, and their inclusion increases the precision and robustness of the model, as well as the model’s ability to generalize to new data, by leveraging a broader context of input information. The results shown indicate that the model does not reproduce planned costs but learns systematic deviations between planned and actual cost values, with the other predictors providing a finer adjustment of the estimate.
4. Discussion
The developed models have shown they can estimate actual construction costs with high accuracy and explain a significant proportion of the variability of the actual construction costs. According to the results presented, all models produced usable results. DTF turned out to be somewhat more unstable, with the lowest R2 values and the largest errors during validation, but MAPE is still within the limits of good prediction. The other three models are very close in terms of MAPE values; therefore, for performance comparison, other performance metrics should also be considered. The best validation results for R2, RMSE, and MAE were achieved by the SVM model, while its MAPE is the third best, very close to those of the GRNN and LR models. Since the other LR and GRNN metrics show larger deviations, we can say that SVM outperformed them overall. Considering the results presented, SVM provides the most stable combination of high accuracy and the smallest error, with no signs of overfitting, and the training and validation metrics are very close. Its application is especially recommended for the reliable prediction of construction costs in the planning phase.
Possible differences in model performance may be due to the nature, structure, and complexity of the database. The performance of different machine learning models may vary depending on the nature of the problem, which is determined by the characteristics of the data set. It is therefore advisable to test several types of models to detect the most suitable one for the given problem and available input data [41].
Compared with prominent recent studies that used some of the machine learning methods for modeling and estimating construction costs [3,7,9,15,16,17,18,19,20,21,22,23,24,25,26,27,29,30], the developed models achieved similar or better results in terms of estimation accuracy. This emphasizes the value, methodological robustness, and applicability of the results obtained here.
In practice, it is appropriate to implement the models at the end of the planning phase, and before signing the construction contract, when the values of the predictor variables are known. In this way, it is possible to obtain more reliable estimates of construction costs, thereby avoiding large overruns and related problems. For precise cost estimation, variables were used that are relatively easy to obtain before the start of construction, and the signing of the construction contract, and software was used that is very intuitive, which is very important for those working in the operational sector, as they are often non-technical users. The advantages of simpler predictive models are multiple, and include reducing the risk of data overfitting, simpler application and interpretation, as well as faster calculation and data analysis [59,60].
The research results indicate the advantages of using machine learning methods in the construction cost planning process in high-rise construction projects. Machine learning provides more accurate predictions compared to traditional cost calculation methods, which can be of crucial assistance to project managers and other project stakeholders in making project decisions, which ultimately leads to better project results and more efficient projects. Increased prediction accuracy enables more effective risk management, as project managers gain better insights and can identify factors that influence cost overruns, enabling appropriate preventive measures to be applied. Measures can, for example, include allocating additional resources to riskier projects or modifying cost plans to account for risk impacts. Machine learning can therefore improve resource use in a project by providing a basis for more precise reallocation based on the magnitude of predicted costs. This can lead to fewer losses and better project performance, contributing to cost savings and more successful construction projects. Also, analysis of the importance of input variables in models reveals which aspects of project managers should focus on to ensure a high-quality initial estimate and to timely identify circumstances that may lead to deviations from planned cost values [17].
In conclusion, developed models can potentially contribute to the accuracy of initial cost estimates, more efficient use of resources, more informed project decision-making, reducing the size of financial risks, increasing transparency, increasing the responsibility of project participants, and thus becoming a valuable instrument for more efficient management of the construction process. A prerequisite for their positive impact is the availability of quality and standardized data and their integration into existing project management processes. The application of models can reduce the risk of cost overruns, although it cannot eliminate the uncertainty inherent in construction projects. The greatest value of models is as a support for expert judgment, not a replacement for it.
While the research produced strong results, several limitations should be acknowledged.
The analysis and model development rely on a limited sample of high-rise construction projects from a specific region and time period, which may restrict the generalizability of the findings to other project types, regions, or market conditions. Additionally, the analyses focus on projects up to the mid-construction stage. While these results offer valuable insights and indicate potential trends, final outcomes and costs may differ from those reported.
The sensitivity analysis revealed that planned construction cost (X9) is the most influential predictor, which limits the model’s applicability in early initial project stages when this information is unavailable. Although advanced models such as SVM and GRNN achieved high accuracy, their limited interpretability makes it challenging to understand the relationships between individual predictors and actual costs.
Future research should expand the database by increasing the number of projects, improving regional representation, extending the time span, and collecting comprehensive final cost data. Systematic data collection will help develop more reliable models. The current results provide a strong foundation for research on larger datasets and for creating decision-support tools for planning and contracting. Increasing the data set size and diversity could enable a more complex model architecture. Researchers should also focus on models that do not rely primarily on planned costs and incorporate additional technical, organizational, market, and regulatory factors. Leveraging emerging technologies such as artificial intelligence, machine learning, and big data analytics, including multimodal and explainable AI approaches, offers a promising direction. These methods can model complex relationships, learn continuously from new data, and improve cost and overrun predictions, thereby reducing financial risks and enhancing decision support in the construction industry.
5. Conclusions
This paper develops a model to forecast construction costs of high-rise projects in Croatia using several machine learning methods.
Based on the database, the following predictive models were developed using the DTREG software: LR, DTF, SVM, and GRNN. The database used includes 9 predictor variables and one target variable (actual construction costs). To achieve the most reliable, high-quality outputs, the model variables were transformed using a logarithmic function, thereby improving predictive power. The accuracy of the developed models was measured by standard performance metrics: R2, RMSE, MAE, and MAPE, with valuable results obtained in all developed models. A comparison of the results showed that the highest accuracy of construction cost estimation is achieved with SVM, with a MAPE of 7.09% during validation, and very good other accuracy indicators.
Although numerous studies have examined the application of machine learning methods to estimate construction costs, this paper makes several original contributions. The research was conducted on the largest and most recent database of high-rise construction projects in the Republic of Croatia. All projects are from the period 2020–2025, reflecting the current Croatian market and regulatory conditions. In addition, data on actual construction costs collected during the construction phase were used, providing a more realistic, operationally relevant cost estimate. The data also includes characteristics of contractors, which have not been observed in previous research. An important contribution of the paper is the development and comparison of four machine learning models for estimating construction costs, which have not been analyzed simultaneously to date, with results showing that SVM provides the most accurate and stable estimates. The obtained results advance knowledge about the application of machine learning methods in the construction industry.
Construction cost overruns are a complex problem that often occurs in construction projects. They cause significant financial and operational difficulties that have direct consequences for contractors and investors. The results of this research have beneficial effects on construction practice in this problematic area. By applying the models, it is possible to obtain more precise estimates of actual construction costs, thereby avoiding large overruns and related problems. The developed models have the potential to improve the process of planning, managing, and implementing construction projects, which contributes to increasing efficiency, reducing the impact of risk, and achieving better financial results.
Funding
This research was funded by the European Union–NextGenerationEU through a contract between the University of Rijeka and the Ministry of Science, Education and Youth of the Republic of Croatia, under the project “Computer models as support for construction project management”, (uniri-mz-25-71).
Institutional Review Board Statement
Not applicable.
Informed Consent Statement
Not applicable.
Data Availability Statement
The datasets presented in this article are not readily available because the data are part of an ongoing project. The data presented in this study are available on request from the corresponding author.
Acknowledgments
During the preparation of this manuscript, the author used Grammarly (https://app.grammarly.com/) for proofreading the author’s written text.
Conflicts of Interest
The author declares no conflicts of interest.
References
- San Cristobal, J.R. Time, cost, and quality in a road building project. J. Constr. Eng. Manag. 2009, 135, 1271–1275. [Google Scholar] [CrossRef] [Scilit]
- Radujković, M. Izvor prekoračenja rokova i proračuna građevinskih projekata. Građevinar 1999, 51, 159–165. (In Croatian) [Google Scholar]
- Car-Pušić, D.; Tijanić Štrok, K.; Petruseva, S.; Zileska-Pancovska, V. Comparative Analysis of Linear Regression and Soft Computing Methods for Estimating Highways Construction Time and Cost in the Republic of Croatia. In Proceedings of the 15th International Conference Organization, Technology and Management in Construction, Cavtat, Croatia, 21–24 September 2022. [Google Scholar]
- Zhang, Y.; Thomas, N.S. An ant colony system-based decision support system for construction time-cost optimization. J. Civ. Eng. Manag. 2012, 18, 580–589. [Google Scholar] [CrossRef] [Scilit]
- Matel, E.; Vahdatikhaki, F.; Hosseinyalamdary, S.; Evers, T.; Voordijk, H. An artificial neural network approach for cost estimation of engineering services. Int. J. Constr. Manag. 2022, 22, 1274–1287. [Google Scholar] [CrossRef] [Scilit]
- Lovrinčević, M.; Vukomanović, M. Reasons for Cost Overruns in the Construction of Highways in Croatia. In Proceedings of the 15th International Conference Organization, Technology and Management in Construction, Cavtat, Croatia, 21–24 September 2022. [Google Scholar]
- Car-Pušić, D.; Mlađen, M. Early stage construction cost prediction in function of project sustainability. In Proceedings of the 15th International Conference on Durability of Building Materials and Components, Barcelona, Spain, 20–23 October 2020. [Google Scholar]
- Strömbäck, A.; Tärnell, E. Evaluation and Learning about Social Sustainability in the Real Estate Industry: A Qualitative and Quantitative Study of How Real Estate Companies Can Contribute to Society and Profitability. Available online: https://www.diva-portal.org/smash/record.jsf?pid=diva2%3A1676969&dswid=-7423 (accessed on 1 December 2025).
- Tijanić Štrok, K. The path to more efficient construction: Mathematical model for cost estimation in high-rise construction. In Proceedings of the 20th Interdisciplinary Management Research, Osijek, Croatia, 24–25 October 2024. [Google Scholar]
- Hashemi, S.T.; Ebadati, O.M.; Kaur, H. Cost estimation and prediction in construction projects: A systematic review on machine learning techniques. SN Appl. Sci. 2020, 2, 1703. [Google Scholar] [CrossRef] [Scilit]
- Ghadbhan Abed, Y.; Hasan, T.M.; Zehawi, R.N. Machine learning algorithms for constructions cost prediction: A systematic review. Int. J. Nonlinear Anal. Appl. 2022, 13, 2205–2218. [Google Scholar]
- Mahpour, A. Building maintenance cost estimation and circular economy: The role of machine-learning. Sustain. Mater. Technol. 2023, 37, e00679. [Google Scholar] [CrossRef] [Scilit]
- Ali, H.; Daanish, M. The influence of artificial intelligence on practices in construction cost estimation. Tech. J. 2024, 3, 930–937. [Google Scholar]
- Meharie, M.G.; Mengesha, W.J.; Gariy, Z.A.; Mutuku, R.N. Application of stacking ensemble machine learning algorithm in predicting the cost of highway construction projects. Eng. Constr. Archit. Manag. 2022, 29, 2836–2853. [Google Scholar] [CrossRef] [Scilit]
- Ali, Z.H.; Burhan, A.M. Hybrid machine learning approach for construction cost estimation: An evaluation of extreme gradient boosting model. Asian J. Civ. Eng. 2023, 24, 2427–2442. [Google Scholar] [CrossRef] [Scilit]
- Antoniou, F.; Aretoulis, G.; Giannoulakis, D.; Konstantinidis, D. Cost and Material Quantities Prediction Models for the Construction of Underground Metro Stations. Buildings 2023, 13, 382. [Google Scholar] [CrossRef] [Scilit]
- Aung, T.; Liana, S.R.; Htet, A.; Bhaumik, A. Using machine learning to predict cost overruns in construction projects. J. Technol. Innov. Energy 2023, 2, 1–7. [Google Scholar] [CrossRef] [Scilit]
- Coffie, G.H.; Cudjoe, S.K.F. Using extreme gradient boosting (XGBoost) machine learning to predict construction cost overruns. Int. J. Constr. Manag. 2024, 24, 1742–1750. [Google Scholar] [CrossRef] [Scilit]
- Juszczyk, M.; Hanák, T.; Výskala, M.; Pacyno, H.; Siejda, M. Early fast cost estimates of sewerage projects construction costs based on ensembles of neural networks. Appl. Sci. 2023, 13, 12744. [Google Scholar] [CrossRef] [Scilit]
- Simić, N.; Ivanišević, N.; Nedeljković, Đ.; Senić, A.; Stojadinović, Z.; Ivanović, M. Early Highway Construction Cost Estimation: Selection of Key Cost Drivers. Sustainability 2023, 15, 5584. [Google Scholar] [CrossRef] [Scilit]
- Aslay, S.E. Estimating contract value using structural parameters: A machine learning approach with data preprocessing. Dicle Univ. Eng. J. 2024, 15, 755–765. [Google Scholar] [CrossRef] [Scilit]
- Papadimitriou, V.E.; Aretoulis, G.N. A final cost estimating model for building renovation projects. Buildings 2024, 14, 1072. [Google Scholar] [CrossRef] [Scilit]
- Saeidlou, S.; Ghadiminia, N. A construction cost estimation framework using DNN and validation unit. Build. Res. Inf. 2024, 52, 38–48. [Google Scholar] [CrossRef] [Scilit]
- Wang, R.; Salleh, H.; Li, K.; Abdul-Samad, Z. A conceptual cost estimation model for building construction projects by hybrid Back-Propagation Neural Network and Dung Beetle Optimizer algorithm. J. Asian Archit. Build. Eng. 2025, 24, 5520–5542. [Google Scholar] [CrossRef] [Scilit]
- Zhang, Y.; Mo, H. Intelligent building construction cost optimization and prediction by integrating BIM and Elman neural network. Heliyon 2024, 10, e37525. [Google Scholar] [CrossRef] [Scilit]
- Chen, L.; Xu, C.; Lim, W.H.; Sharma, A.; Tiang, S.S.; Chong, K.S.; El-Kenawy, E.-S.M.; Alhussan, A.A.; Eid, M.M.; Khafaga, D.S. Transparent and reliable construction cost prediction using advanced machine learning and explainable AI. Eng. Sci. Technol. Int. J. 2025, 70, 102159. [Google Scholar] [CrossRef] [Scilit]
- Yamusa, M.A.; Lawal, H.S.I.; Abdulrahman, R.S.; Salisu, A.S.; Saka, A.; Abubakar, M.; Abdullahi, M. A machine-learning model for estimating construction renovation costs. Int. J. Build. Pathol. Adapt. 2025; ahead of print.
- Tijanić Štrok, K. An overview of the relations within the iron triangle on a sample of construction projects in Croatia. J. Appl. Eng. Sci. 2025, 23, 131–140. [Google Scholar] [CrossRef] [Scilit]
- Galjanić, K.; Marović, I.; Hanak, T. Performance Measurement Framework for Prediction and Management of Construction Investments. Sustainability 2023, 15, 13617. [Google Scholar] [CrossRef] [Scilit]
- Tijanić, K.; Car-Pušić, D.; Šperac, M. Cost estimation in road construction using artificial neural network. Neural Comput. Appl. 2020, 32, 9343–9355. [Google Scholar] [CrossRef] [Scilit]
- Hrvatska Enciklopedija. Visokogradnja. Available online: https://www.enciklopedija.hr/clanak/visokogradnja (accessed on 1 December 2025). (In Croatian)
- El Naqa, I.; Murphy, M.J. What Is Machine Learning? In Machine Learning in Radiation Oncology; El Naqa, I., Li, R., Murphy, M., Eds.; Springer: Cham, Switzerland, 2015; pp. 3–11. [Google Scholar]
- Jordan, M.I.; Mitchell, T.M. Machine learning: Trends, perspectives, and prospects. Science 2015, 349, 255–260. [Google Scholar] [CrossRef] [Scilit]
- Sherrod, P.H. DTREG Predictive Modeling Software. Manual for DTREG. Available online: https://www.dtreg.com/methodology/view/download-dtreg-manual (accessed on 1 December 2025).
- Sodikov, J. Cost estimation of highway projects in developing countries: Artificial neural network approach. J. East. Asia Soc. Transp. Stud. 2005, 6, 1036–1047. [Google Scholar] [CrossRef]
- Obradović, D. A Contribution to Increasing the Efficiency of Sewerage Systems Maintenance by Applying a Maintenance Cost Estimation Model. Ph.D. Thesis, Josip Juraj Strossmayer University of Osijek, Faculty of Civil Engineering and Architecture, Osijek, Croatia, March 2022. (In Croatian) [Google Scholar]
- Rokach, L. Decision Forest: Twenty years of research. Inf. Fusion 2016, 27, 111–125. [Google Scholar] [CrossRef] [Scilit]
- Cosma, G.; Brown, D.; Archer, M.; Khan, M.; Pockley, A.G. A survey on computational intelligence approaches for predictive modeling in prostate cancer. Expert Syst. Appl. 2017, 70, 1–19. [Google Scholar] [CrossRef] [Scilit]
- Sušanj, I. Development of the Hydrological Rainfall-Runoff Model Based on Artificial Neural Network in Small Catchments. Ph.D. Thesis, University of Rijeka, Faculty of Civil Engineering, Rijeka, Croatia, January 2017. (In Croatian) [Google Scholar]
- Dudek, G. Generalized Regression Neural Network for Forecasting Time Series with Multiple Seasonal Cycles. Adv. Intell. Syst. Comput. 2015, 323, 839–846. [Google Scholar] [CrossRef] [Scilit]
- Tijanić Štrok, K. Artificial Neural Networks Application for the Croatian School Maintenance Cost Estimation. Tech. J. 2025, 19, 192–202. [Google Scholar] [CrossRef] [Scilit]
- Car-Pušić, D.; Petruseva, S.; Zileska Pancovska, V.; Zafirovski, Z. Neural network-based model for predicting preliminary construction cost as part of cost predicting system. Adv. Civ. Eng. 2020, 1, 8886170. [Google Scholar] [CrossRef] [Scilit]
- Gudac Hodanić, I. Life Cycle Cost Estimation Model of Pontoons as a Support for Marina Management System. Ph.D. Thesis, Josip Juraj Strossmayer University of Osijek, Faculty of Civil Engineering and Architecture, Osijek, Croatia, September 2019. (In Croatian) [Google Scholar]
- Ibrahim, M. Understanding Data Transformation. Why and Which One to Use? Available online: https://medium.com/@muhammadibrahim_54071/why-and-which-data-transformation-should-i-use-cfb9e31923cf (accessed on 1 December 2025).
- Tijanić Štrok, K. Estimation of Maintenance Cost in Elementary Schools of Primorje-Gorski Kotar County, Croatia. In Proceedings of the 19th Interdisciplinary Management Research, Osijek, Croatia, 28–30 September 2023. [Google Scholar]
- Lee, D.K. Data transformation: A focus on the interpretation. Korean J. Anesthesiol. 2020, 73, 503–508. [Google Scholar] [CrossRef] [Scilit]
- Begić Juričić, H.; Krstić, H. Predicting Water Consumption for School Buildings in Osijek-Baranja County, Croatia, Using MLR and ANN. J. Water Resour. Plann. Manag. 2025, 151, 05025011. [Google Scholar] [CrossRef] [Scilit]
- Papic, M. Primijenjena Statistika u MS Excelu za Ekonomiste, Znanstvenike i Neznalice; Zoro: Zagreb, Croatia, 2005. (In Croatian) [Google Scholar]
- Sobol, M.G. Validation strategies for multiple regression analysis: Using the coefficient of determination. Interfaces 1991, 21, 106–120. [Google Scholar] [CrossRef] [Scilit]
- Chicco, D.; Warrens, M.J.; Jurman, G. The coefficient of determination R-squared is more informative than SMAPE, MAE, MAPE, MSE and RMSE in regression analysis evaluation. PeerJ Comput. Sci. 2021, 7, e623. [Google Scholar] [CrossRef] [Scilit]
- Serdar, V. Udžbenik Statistike; Školska Knjiga: Zagreb, Croatia, 1966. (In Croatian) [Google Scholar]
- EITCA. Što Mjeri Koeficijent Determinacije (R-Kvadrat) u Kontekstu Testiranja Pretpostavki? Available online: https://hr.eitca.org/artificial-intelligence/eitc-ai-mlp-machine-learning-with-python/programming-machine-learning/testing-assumptions/examination-review-testing-assumptions/what-does-the-coefficient-of-determination-r-squared-measure-in-the-context-of-testing-assumptions/ (accessed on 1 December 2025). (In Croatian)
- Petruseva, S.; Zileska-Pancovska, V.; Car-Pušić, D. Implementation of process-based and data-driven models for early prediction of construction time. Adv. Civ. Eng. 2019, 1, 7405863. [Google Scholar] [CrossRef] [Scilit]
- Chandanshive, V.; Kambekar, A.R. Estimation of building construction cost using artificial neural networks. J. Soft Comput. Civ. Eng. 2019, 3, 91–107. [Google Scholar] [CrossRef] [Scilit]
- Lewis, C.D. Industrial and Business Forecasting Methods; Butterworths: London, UK, 1982. [Google Scholar]
- Moreno, J.J.M.; Pol, A.P.; Abad, A.S.; Blasco, B.C. Using the R-MAPE index as a resistant measure of forecast accuracy. Psicothema 2013, 25, 500–506. [Google Scholar] [CrossRef] [Scilit]
- Ying, X. An overview of overfitting and its solutions. J. Phys. Conf. Ser. 2019, 1168, 022022. [Google Scholar] [CrossRef] [Scilit]
- Tharu, R.P. Multiple regression model fitted for job satisfaction of employees working in saving and cooperative organization. Int. J. Stat. Appl. Math. 2019, 4, 43–49. [Google Scholar]
- Obi Tayo, B. Simplicity vs. Complexity in Machine Learning—Finding the Right Balance. Available online: https://medium.com/data-science/simplicity-vs-complexity-in-machine-learning-finding-the-right-balance-c9000d1726fb (accessed on 1 December 2025).
- Obradović, D.; Marenjak, S.; Šperac, M. Estimating Maintenance Costs of Sewer System. Buildings 2023, 13, 500. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the author. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.