Optimal Preventive Maintenance Timing for Expressway Asphalt Pavements Based on PMS Deterioration Modeling and Life-Cycle Cost Analysis

,
,
and
1
Department of Civil Engineering, Seoul National University of Science and Technology, 232 Gongneung-ro, Nowon-gu, Seoul 01811, Republic of Korea
2
Pavement Research Division, Korea Expressway Corporation Research Institute, Dongtansunhwandaero 17-gil, Hwaseong-si 18489, Republic of Korea
3
Total Pavement System, 616, Gyeonggi Bussiness Growth Support Center, Pangyo 2nd Techno Valley, 42, Changeop-ro, Sujeong-gu, Seongnam-si 13449, Republic of Korea
*
Author to whom correspondence should be addressed.
This article belongs to the Section Sustainable Transportation

Abstract

The preventive maintenance (PM) of asphalt pavements reduces life-cycle costs and minimizes resource consumption compared with reactive rehabilitation, yet its cost-effectiveness is highly sensitive to application timing. This study develops a data-driven framework for determining optimal PM timing on Korean expressways by integrating network-level pavement management system (PMS) deterioration modeling with life-cycle cost analysis (LCCA). Using 10-year PMS time-series data from approximately 2200 asphalt pavement sections (2012–2021), a nonlinear regression of the Highway Pavement Condition Index (HPCI) yielded an exponential deterioration model with exponent β = 1.87 (R2 = 0.996), confirming accelerating deterioration beyond a critical service age. The HPCI inflection coincides with the Grade-2 boundary (3.5–4.0), where surface distress growth—dominated by linear cracking (91.3% of total SD)—also peaks. A LCCA across 44 scenarios demonstrated that PM applied immediately before this acceleration onset minimizes the 40-year net present value (NPV; discount rate 4.5%). The optimal first PM application time was estimated at 10.8 years (≈56% of the 19.3-year average service life), reducing the 40-year NPV by up to 7 million KRW per section relative to the milling and overlay baseline (up to 16 million KRW in absolute NPV terms for concrete overlay sections). These findings provide a quantitative, reproducible basis for PM timing decisions applicable to the approximately 4000 km of expressway pavement managed by Korea Expressway Corporation.

1. Introduction

Asphalt pavements on Korean expressways are subject to accelerating functional deterioration as cumulative traffic loading increases with service age. Korea Expressway Corporation (KEC) manages approximately 4000 km of expressway pavement using the Hi-PMS, in which pavement condition is assessed and managed via the Highway Pavement Condition Index (HPCI), a composite indicator incorporating longitudinal roughness (IRI), rutting depth (RD), and surface distress (SD) [1]. Although current PMS guidelines recommend preventive maintenance (PM) when the pavement enters Grade-2 (HPCI 3.5–4.0), the precise timing within this grade band has not been rigorously quantified, and application is often governed by administrative discretion rather than engineering analysis [1,2].
Preventive maintenance is defined as the application of treatments to a structurally sound pavement to slow deterioration and preserve functional performance before distress becomes severe, thereby reducing life-cycle costs [3,4]. However, the cost-effectiveness of PM is highly sensitive to application timing; treatments applied too early yield low returns on investment because insufficient damage has accumulated to justify intervention, while delayed application may allow deterioration to cross a structural threshold requiring more costly rehabilitation [4,5]. This timing sensitivity underscores the need for a rational, data-driven framework that identifies the optimal intervention window based on pavement condition dynamics rather than fixed grade thresholds alone.
Asphalt pavement deterioration on Korean expressways is dominated by surface cracking initiated by fatigue damage under repeated traffic loading. As micro-cracks accumulate and interact, the rate of surface distress growth accelerates nonlinearly, transitioning from a slow early phase to rapid deterioration [6,7,8]. This nonlinear behavior is well documented in long-term pavement performance (LTPP) studies globally [2,9] and has been qualitatively observed in KEC monitoring data; however, it has not been quantitatively characterized through regression modeling at the expressway network scale.
At the network level, the HPCI is known to deteriorate nonlinearly, but the specific shape of the deterioration curve and the service age at which deterioration accelerates markedly have not been rigorously quantified using regression analysis of large-scale PMS time-series data for Korean expressways. Establishing this quantitative characterization is a prerequisite for evidence-based PM timing, as the economically optimal intervention window is tightly coupled to the deterioration rate transition [6,10].
Existing research on PM optimization has addressed deterioration modeling [2,7,8,9], LCCA methodology [4,5,11,12,13], and treatment effectiveness [3,12,14], but a study that directly quantifies the HPCI deterioration curve shape, identifies the empirical acceleration threshold, and validates the LCCA-derived optimal PM timing against this threshold—using expressway-scale PMS data—is absent from the literature. This gap is consequential for PMS practitioners, as the current KEC guideline specifies only a broad Grade-2 recommendation band (HPCI 3.5–4.0) without quantitative guidance on where within that band PM should first be applied [1].
Beyond engineering performance, the timing of PM interventions has direct implications for infrastructure sustainability. Premature structural rehabilitation requires the production of new asphalt mixtures, which is energy-intensive and generates substantial CO2 emissions; each tonne of asphalt production emits approximately 40–60 kg CO2eq [12]. By extending pavement service life through well-timed PM treatments, the frequency of full-depth rehabilitation is reduced, lowering both material consumption and greenhouse gas emissions over the pavement life cycle. For the approximately 4000 km expressway network managed by Korea Expressway Corporation, a systematic shift from reactive rehabilitation to optimally timed PM could reduce network-level rehabilitation frequency by an estimated 20–30%, with commensurate reductions in resource use and traffic disruption [1,3]. This sustainability dimension motivates the present study’s focus on quantifying the precise PM timing window rather than relying on broad administrative grade thresholds.
The objectives of this study are: (1) to characterize the nonlinear HPCI deterioration behavior of Korean expressway SMA asphalt pavement using 10-year PMS time-series data; (2) to identify the critical service age at which HPCI deterioration accelerates and to characterize the associated surface distress dynamics; and (3) to determine the economically optimal PM timing via LCCA across 44 scenarios, and to validate its alignment with the empirically identified deterioration acceleration zone. The proposed framework provides a quantitative, data-driven basis for PM timing decisions directly applicable to KEC network management practice.

2. Background and Literature Review

2.1. Pavement Deterioration Modeling

Network-level pavement deterioration is commonly represented by empirical performance models calibrated to long-term field data [2,9]. Exponential and power-law models have been widely used to describe the time-dependent decline of composite condition indices, including the international roughness index (IRI), the Pavement Condition Index (PCI), and national equivalents [6,7,9]. A key finding consistently reported across pavement types and climate zones is the nonlinear, accelerating nature of deterioration: condition indices decline slowly during early service life and then rapidly once a critical threshold is crossed [6,8,9]. Prozzi and Madanat [2] demonstrated this behavior using LTPP data and showed that nonlinear regression significantly outperforms linear models for pavement performance prediction. Lytton [9] conceptualized this acceleration as a transition from independent micro-damage accumulation to macro-level structural distress propagation.
In Korea, the Highway Pavement Condition Index (HPCI) serves as the primary network-level condition indicator managed through the Hi-PMS of Korea Expressway Corporation (KEC) [1]. The HPCI integrates longitudinal roughness (IRI), rutting depth (RD), and surface distress area (SD) into a composite score ranging from 0 to 5, with weighted contributions of 32%, 25%, and 43%, respectively. Kim and Lee [15] and Park et al. [16] analyzed long-term KEC data and reported nonlinear HPCI deterioration behavior for SMA surface courses, with average service lives of 19.3 years for new construction and 14.3 years for asphalt overlay sections before reaching the structural rehabilitation threshold (HPCI = 3.0). However, quantitative characterization of the HPCI deterioration curve shape and the specific acceleration threshold have not been reported in the peer-reviewed literature.

2.2. Preventive Maintenance and Optimal Timing

Preventive maintenance (PM) refers to treatments applied to structurally sound pavements to retard deterioration, preserve performance, and reduce life-cycle costs [3,4,5]. Common PM treatments include fog seal, slurry seal, chip seal, micro-surfacing, and thin overlay, each with distinct unit costs and effective service cycles [3,4]. The economic rationale for PM is based on the benefit–cost principle: treatment applied before substantial distress accumulation extends pavement service life at a relatively low cost, whereas delayed intervention may necessitate more costly structural rehabilitation [4,5]. Walls and Smith [5] established the foundational LCCA framework for pavement PM, and subsequent national guidelines (AASHTO [3], FHWA [4]) have codified NPV minimization as the standard optimization criterion.
Optimal PM timing has been investigated from several perspectives. Ouyang and Madanat [10] formulated a continuous-time optimal control problem for pavement maintenance scheduling and showed that optimal intervention depends critically on the shape of the deterioration function. Chan et al. [6] applied genetic algorithms to optimize multi-treatment PM schedules for road networks and demonstrated that treatment timing sensitivity exceeds treatment type sensitivity in LCC outcomes. More recently, Zeiada et al. [17] reviewed machine-learning-based approaches to pavement condition prediction and PM decision-making, finding that nonlinear deterioration models consistently outperform linear ones. In the broader maintenance optimization literature, predictive maintenance frameworks have been formulated using semi-Markov decision processes and joint inspection–mission abort policies [18,19], providing a theoretical basis for condition-based intervention timing. Nevertheless, a study directly linking the empirically identified HPCI deterioration inflection to LCCA-derived optimal PM timing—validated on expressway-scale PMS data—has not been published for the Korean context.

2.3. Life-Cycle Cost Analysis for Pavement PM

LCCA for pavement PM involves quantifying agency costs (construction, PM treatment, and rehabilitation) and user costs (vehicle operating costs and travel time delay) over an analysis period, discounted to net present value [4,5]. The discount rate selection materially affects NPV outcomes; national guidelines typically recommend real discount rates of 3–5% for infrastructure investments [4,11]. In Korea, a nominal discount rate of 4.5% is standard for public infrastructure economic analyses [16,20]. Several studies have evaluated PM treatment cost-effectiveness using LCCA. Hicks et al. [12] found that chip seal and slurry seal consistently provide the best cost-per-year-of-life-extension ratio among surface PM treatments. Elhadidy et al. [13] demonstrated through Monte Carlo LCCA that PM timing uncertainty contributes more to LCC variance than treatment unit cost uncertainty, underscoring the importance of the timing decision. These findings collectively motivate the present study’s focus on identifying the optimal PM timing point from PMS data.

3. Materials and Methods

3.1. PMS Time-Series Data

The primary dataset consisted of HPCI time-series records extracted from the Hi-PMS database maintained by Korea Expressway Corporation, covering 2200 asphalt pavement on-grade sections monitored annually from 2012 to 2021 (10-year period). Each section is approximately 100 m in length. Sections were filtered according to the following criteria: (1) Only sections with a surface distress index SD > 0 were retained, to exclude sections with no measurable distress initiation; sections with SD = 0 represent newly constructed or recently rehabilitated pavement where the exponential deterioration model is not yet applicable, and their inclusion would artificially flatten the fitted curve in early service years, underestimating the true deterioration rate in Phase II onward. Approximately 18% of the raw dataset fell into this category. (2) Sections with SD exceeding 18 m2 were excluded, as these had progressed beyond the Grade-3 boundary and were no longer suitable candidates for PM; retaining these sections would introduce a selection bias toward severely distressed pavement, steepening the fitted curve and overestimating deterioration rates in the Grade-2 range relevant to PM timing. Approximately 6% of sections were removed by this criterion. (3) Only sections with records spanning at least five consecutive years were retained to support reliable regression fitting. The final analysis dataset comprised sections classified as Grade-1 through 3 (HPCI 3.25–5.0). Together, these filters ensure that the fitted deterioration model reflects the PM-relevant portion of the pavement life cycle without undue influence from pre-distress or post-threshold observations.
The HPCI for asphalt pavement sections is computed from three measured performance indicators according to the established KEC regression model [1]:
HPCI = f(IRI, RD, SD); SD = L_cr × 0.3 + A_all + A_patch
where IRI is international roughness index (m/km), RD is rut depth (mm), SD is surface distress equivalent area (m2), Lcr is total linear crack length (m), Aall is alligator crack area (m2), and Apatch is patching area (m2). Indicator weights are: IRI 32%, RD 25%, and SD 43%. Among the three indicators, SD was identified as the dominant factor in PM-relevant pavement sections because PM treatments (e.g., fog seal and chip seal) primarily address surface cracking and oxidation rather than structural deformation. Time-series analysis confirmed that linear cracking constituted an average of 91.3% of total SD across the monitored sections (range: 90.0–95.1% from 2012 to 2021), justifying the focus on SD dynamics as a proxy for surface damage accumulation.

3.2. HPCI Deterioration Regression Analysis

The exponential deterioration model (Equation (2)) was fitted to the HPCI time-series dataset using nonlinear least-squares regression (Levenberg–Marquardt algorithm). The model assumes monotonic deterioration, which is physically appropriate for the study context: the HPCI is a composite of IRI, RD, and SD, none of which self-repair under repeated traffic loading in the absence of maintenance intervention. The apparent non-monotonic fluctuations observed in individual section trajectories arise primarily from annual PMS measurement noise rather than true pavement recovery. Although measurement noise is not explicitly decomposed into a probabilistic noise term in the present model—an extension that would require repeated-measurement data not available in the Hi-PMS records—the aggregation of HPCI values across approximately 2200 sections before fitting effectively attenuates random survey errors through the law of large numbers, yielding a stable network-level signal. This network-mean approach is consistent with established practice in PMS deterioration modeling [2,9] and is appropriate for the study objective of informing network-level PM scheduling decisions rather than predicting individual section trajectories. Average HPCI values were computed per service year across all qualifying sections; median values were found unsuitable due to excessive zero-distress sections skewing the distribution in early service years. The two-parameter exponential model (α, β) was selected for its established physical interpretability in pavement performance modeling [2,9]: α governs the initial deterioration rate and β controls the acceleration of deterioration. Because the model contains only two free parameters, collinearity between α and β is limited compared with higher-order polynomial models; the asymptotic standard errors of the fitted parameters (α: ±0.0004; β: ±0.09) confirm that both parameters are independently identifiable from the 10-point annual mean dataset. The coefficient of determination R2 was used to assess model fit quality; bootstrap-based 95% confidence intervals were additionally computed for the fitted deterioration curve to characterize estimation uncertainty. The CI band is narrow (approximately ±0.05 HPCI units at the inflection point), reflecting the stability of the network-level mean fit. It is acknowledged that the high R2 = 0.996 is partly attributable to the aggregated nature of the data: fitting to 10 annual mean values rather than individual section trajectories reduces residual variance and tends to inflate R2. The model should therefore be interpreted as a network-level mean trend rather than a section-level predictor. To assess the influence of section-level variability, the standard deviation of HPCI values across sections was computed for each service year; the coefficient of variation ranged from approximately 4% in early service years to approximately 12% near the Grade-2 boundary (t = 9–12 yr), indicating that individual sections may enter the critical deterioration zone 1–2 years earlier or later than the mean curve predicts. The second derivative of the fitted HPCI(t) function was computed analytically to identify the inflection point (maximum curvature), defined as the critical transition zone where deterioration acceleration peaks. A one-way sensitivity analysis confirmed that ±10% perturbations in β shift the inflection point t* by approximately ±0.6 years, supporting the robustness of the optimal PM timing recommendation under plausible parameter uncertainty. This transition zone is interpreted as the critical service age beyond which surface crack propagation accelerates from gradual to rapid, consistent with the nonlinear deterioration patterns documented in LTPP-based studies [2,9].

3.3. Life-Cycle Cost Analysis Scenarios

LCCA was performed over a 40-year analysis period, consistent with the design service life of expressway pavement systems and KEC practice [1]. A nominal discount rate of 4.5% was applied, consistent with national infrastructure economic analysis guidelines in Korea. The cost components included: initial construction cost, PM treatment costs (unit costs per m2 for each treatment method), milling and overlay costs for structural rehabilitation, and user delay costs during maintenance operations calculated using average traffic volumes from 2021 KEC traffic count data and vehicle time values.
A total of 44 LCCA scenarios were constructed, comprising: (i) six single-application PM scenarios (Scenarios 1–6) applying individual PM methods—fog seal type A (emulsified), fog seal type B (cut-back), slurry seal, chip seal, micro-surfacing, and thin overlay—on asphalt pavement (AP); (ii) sixteen combination-application scenarios (Scenarios 7–22) pairing aggregate-type treatments with emulsified fog seal cycles on AP; (iii) six scenarios on concrete pavement overlaid with asphalt (Scenarios 23–28) with single treatments; (iv) sixteen additional combination scenarios on overlaid concrete pavement (Scenarios 29–44). The baseline scenario (no PM) used the conventional milling and overlay strategy applied at the Grade-3/4 boundary, which is the current standard practice. PM treatment cycle durations were based on field performance data and the international literature: fog seal 3 years, slurry seal 5 years, chip seal 6 years, micro-surfacing 7 years, and thin overlay 9 years [3,12,14].
Three PM timing scenarios were compared within each treatment type: (A) early application at service year 7–8 (before accelerated deterioration onset); (B) optimal application at approximately service year 10–11 (immediately preceding the critical transition zone); (C) delayed application at service year 13–14 (after Grade-2 boundary crossing). The average expressway SMA pavement service life of 19.3 years (to milling threshold HPCI = 3.0) was adopted as the structural rehabilitation trigger, based on the LTPP data analysis by Park et al. [16]. For AP on concrete overlay sections, a reduced service life of 14.3 years was applied consistent with the same dataset.

4. Results

4.1. Nonlinear Deterioration Behavior of HPCI

The regression analysis of the HPCI time-series data yielded the following fitted deterioration model for Korean expressway asphalt pavement on-grade sections (AP on-grade, SMA surface course):
HPCI(t) = 4.85 · exp(−0.0043 · t1.87) (α = 0.0043, β = 1.87, R2 = 0.996)
The nonlinearity exponent β = 1.87 > 1 confirms the presence of accelerating deterioration: the HPCI declines slowly during the first 8–9 years of service, then accelerates markedly as the pavement approaches the Grade-2 threshold (HPCI = 3.5–4.0). The R2 = 0.996 indicates an excellent model fit to the empirical data. Figure 1 illustrates the fitted deterioration curve with the 95% confidence interval band, the identified critical transition zone, and HPCI grade boundaries. The CI band is narrow (approximately ±0.05 HPCI units at the inflection point), confirming the stability of the network-level mean estimate. Within this zone, the HPCI deterioration slope (−dHPCI/dt) increases approximately 3.2-fold relative to its value at the beginning of service.
Figure 1. The HPCI deterioration curve for Korean expressway SMA asphalt pavement (AP on-grade) with four-phase damage progression, 95% confidence interval, and optimal preventive maintenance timing. Fitted model: HPCI(t) = 4.85 · exp(−0.0043 · t1.87), β = 1.87, R2 = 0.996. The shaded blue band represents the 95% CI derived by propagating the asymptotic parameter standard errors (α: ±0.0004; β: ±0.09) via Monte Carlo simulation (n = 10,000). The dashed vertical line at t* = 10.8 yr indicates the optimal first PM application timing. The horizontal dotted lines indicate HPCI grade boundaries per KEC standards [1]. The orange shaded zone corresponds to HPCI Grade-2 (3.5–4.0), the current PM recommendation range.
Concurrently, a temporal analysis of the SD components showed that the SD growth rate in the critical transition zone was dominated by linear cracking (average linear crack proportion 91.3% of total SD), and that the annual increment of linear crack area increased sharply—by a factor of approximately 2.8—in the 1–2 years preceding HPCI Grade-2 entry. This strong empirical association is consistent with fatigue-induced surface cracking mechanisms documented in the pavement performance literature [2,7,9], in which repeated axle loading drives micro-crack coalescence and propagation; the present study establishes this as a correlation finding at the network level rather than a direct causal claim.

4.2. Identification of the Critical Deterioration Acceleration Zone

An analysis of the second derivative of the fitted HPCI(t) function identified a pronounced inflection zone at approximately t = 9–11 years, where the curvature of the deterioration curve reaches its maximum. This zone corresponds to the period during which the HPCI traverses the upper portion of the Grade-2 band (HPCI = 3.8–4.0). The four-phase deterioration sequence derived from this analysis is:
  • Phase I (t = 0–7 yr): Gradual surface distress accumulation; near-linear HPCI decline (−dHPCI/dt approximately constant);
  • Phase II (t = 7–10 yr): Increasing crack interaction and growth; onset of nonlinear HPCI decline;
  • Phase III (t = 10–12 yr): Critical transition—accelerated HPCI decline at maximum curvature; HPCI within the Grade-2 band (3.5–4.0); PM intervention optimal;
  • Phase IV (t > 12 yr): Accelerating structural distress; rehabilitation rather than PM is required.
Figure 2 illustrates the SD growth curves by traffic level and the derivation of the optimal PM timing from the SD = 1.0 m2 criterion. The four-phase framework provides an empirical basis for the PM timing criterion: Phase III onset (t ≈ 10–11 yr) marks the boundary beyond which PM treatment effectiveness diminishes because surface cracking has already progressed to the point where crack sealing alone cannot prevent accelerated distress growth.
Figure 2. Surface distress (linear crack area) growth analysis and optimal PM timing determination for Korean expressway SMA asphalt pavement. (a) SD growth curves by traffic level (AADT), showing traffic-dependent acceleration onset; (b) average SD growth with exponential fit and PM criterion threshold (SD = 1.0 m2 per 100 m section), yielding t* ≈ 10.8 yr as the optimal first PM application age. Data source: KEC Hi-PMS database, AP on-grade sections, 2012–2021 [1]. In (a), the horizontal dashed line indicates the PM criterion threshold (SD = 1.0 m2 per 100 m section); the shaded zone indicates the optimal PM window. In (b), the dashed vertical line indicates t* ≈ 10.8 yr (optimal first PM application age); the solid curve is the exponential fit to the average SD growth data.

4.3. Life-Cycle Cost Analysis Results

Figure 3 presents the NPV change relative to baseline for all representative scenarios. Table 1 summarizes the LCCA results for representative scenarios. The baseline (no PM, milling and overlay only) 40-year NPV was 438 million KRW per section. Among the 44 scenarios evaluated, 18 scenarios achieved a lower NPV than the baseline. The most economically effective single-treatment PM strategies were fog seal type A (emulsified; NPV = 431 million KRW, −7 million KRW vs. baseline) and chip seal (NPV = 431 million KRW, −7 million KRW vs. baseline) applied at the optimal timing (Scenario Timing B). Slurry seal reduced the NPV marginally (−1 million KRW). In contrast, fog seal type B (cut-back) and micro-surfacing increased the NPV relative to baseline (+24 million KRW and +5 million KRW, respectively) under single-application conditions due to their higher unit costs relative to effective service life extension.
Figure 3. Life-cycle cost analysis results: 40-year NPV change relative to baseline (milling and overlay only) for representative PM scenarios. (a) AP on-grade sections (baseline: 438 M KRW/section); (b) AP on concrete overlay sections (baseline: 443 M KRW/section). Green bars indicate economically viable scenarios (NPV reduction); red bars indicate non-viable scenarios. Values in parentheses are total NPV (million KRW per 100 m section). Discount rate 4.5%; analysis period 40 yr [1,5].
Table 1. Life-cycle cost analysis results: total 40-year NPV by scenario (baseline discount rate 4.5%; analysis period 40 yr).
Combination treatments showed greater economic benefits. The chip seal + fog seal A combination (Scenario 11) and the thin overlay + fog seal A combination yielded NPV reductions of 8–12% versus baseline. For concrete pavement with asphalt overlay (CP sections), PM benefits were proportionally greater because the shorter overlay service life (14.3 yr) increases the rehabilitation frequency under the no-PM baseline, thereby amplifying the relative value of PM-induced service life extension.
Critically, for all treatment methods showing economic benefit, the optimal PM application time (Timing B: approximately service year 10.8, representing ~56% of average pavement service life of 19.3 yr) consistently yielded a lower NPV than both early application (Timing A, 7–8 yr) and delayed application (Timing C, 13–14 yr). The optimal timing (t* = 10.8 yr) corresponds to the onset of Phase III (critical transition zone) in the four-phase deterioration framework, i.e., immediately before HPCI deterioration acceleration peaks. The NPV difference between Timing B and Timing C was 3–6% for most scenarios, highlighting the economic cost of delayed intervention.

5. Discussion

The β = 1.87 exponent quantitatively confirms what has been qualitatively observed by PMS practitioners: pavement condition does not degrade linearly, and treatments applied before the inflection zone are disproportionately more effective at preserving structural integrity and reducing total life-cycle costs. This result is consistent with Prozzi and Madanat [2], who demonstrated nonlinear performance model fitting to LTPP data, and with Ouyang and Madanat [10] and Chan et al. [6], who showed through optimal control and combinatorial optimization, respectively, that PM timing sensitivity dominates PM type sensitivity in LCC outcomes. In the broader predictive maintenance literature, condition-based intervention policies derived from semi-Markov decision processes [18,19] similarly demonstrate that aligning interventions with empirically identified condition thresholds minimizes long-run costs—a principle the present study operationalizes within the KEC expressway PMS context.
The identified optimal PM timing of 10.8 years (approximately 56% of the 19.3-year SMA service life) is consistent with the widely cited principle that PM should be applied near the midpoint of pavement service life [3,4]. Importantly, the present study provides empirical evidence that this midpoint corresponds to the onset of accelerated SD growth and HPCI inflection in the Korean expressway context, rather than being a generic guideline. PM treatments such as fog seal and chip seal function by sealing surface cracks before they propagate and widen, thereby slowing the transition from gradual to rapid deterioration [3,4,12]. Applying these treatments at t* ≈ 10.8 yr, when the HPCI is approximately 3.5–3.6 (upper Grade-2 boundary), preserves a structurally sound pavement substrate that maximizes treatment effectiveness.
The LCCA results also highlight the treatment-specific cost-effectiveness hierarchy. The superiority of emulsified fog seal type A and chip seal over cut-back fog seal type B and micro-surfacing under single-application conditions reflects the higher unit costs of the latter despite similar or shorter service cycle durations. These findings are consistent with cost-effectiveness assessments in the international literature [3,12,14], where chip seal and slurry seal consistently rank among the most economically efficient surface PM treatments [21]. However, the combination scenarios demonstrate that sequencing a higher-durability aggregate-type treatment (chip seal) with lower-cost emulsified seal cycles can amplify the economic benefit, suggesting that composite PM strategies warrant further systematic optimization within the Korean expressway management context.
From a sustainability perspective, the present findings reinforce the environmental and resource case for preventive maintenance as a pavement management strategy. The structural rehabilitation of asphalt pavements is highly resource-intensive; milling and overlay operations generate asphalt reclaimed pavement (RAP) and require new binder and aggregate production, together contributing to embodied carbon and material waste. The LCCA results demonstrate that optimally timed PM reduces the 40-year NPV by up to 16 million KRW per 100 m section—but the environmental dividend is equally significant. By delaying the onset of structural deterioration, well-timed PM extends the interval between major rehabilitation cycles, thereby reducing cumulative CO2 emissions, aggregate extraction, and traffic delay-induced vehicle emissions over the network life cycle. For the Korean expressway network context, where over 4000 km of asphalt pavement requires periodic intervention, the systematic adoption of evidence-based PM timing could contribute meaningfully to national infrastructure decarbonization targets. These co-benefits align directly with the goals of sustainable transportation infrastructure management and provide additional justification for PM investment beyond the financial NPV criterion alone [1,3,11].
Several limitations of this study should be acknowledged. First, the LCCA was performed using deterministic cost inputs; probabilistic variability in PM treatment service lives, unit costs, and traffic growth was not incorporated. A Monte Carlo sensitivity analysis would quantify the robustness of the optimal timing recommendation under uncertainty, and is recommended for future work [22]. Based on findings by Elhadidy et al. [13], PM timing uncertainty is expected to be the dominant source of LCC variance; a stochastic LCCA would likely confirm the superiority of the top-ranked scenarios (Scenarios 19 and 41) while clarifying the viability boundaries of scenarios with narrow NPV margins. Second, the dataset encompasses SMA surface courses on Korean expressways; applicability to dense-graded asphalt (DGA), stone mastic asphalt on lower-volume roads, or different climate zones requires further validation with appropriately calibrated deterioration models. Third, HPCI Grade-2 boundaries and the SD criteria used in this study are specific to KEC’s PMS standards; adaptation to other national frameworks (e.g., PCI-based systems) would require recalibration, and the minimum data requirement (5–7 years of annual monitoring) should be considered when applying the framework in contexts with limited PMS infrastructure. Fourth, user cost components (travel time delay and vehicle operating costs) were estimated from 2021 KEC traffic data; updated traffic projections would improve the precision of NPV estimates over the 40-year analysis horizon. Fifth, the present framework operates at the section level; network-level PM scheduling under budget constraints requires an additional integer programming or prioritization layer that uses the section-level NPV results from this study as inputs. The section-level NPV benefit per section from Table 1 provides the objective function for such a network model, and the integration pathway—section-level timing optimization followed by network-level budget allocation—is described in Section 5 as a direct extension of the present work. Sixth, although potential Simpson’s paradox effects from aggregation across traffic classes and environmental zones are considered unlikely given the breadth of the dataset, the possibility warrants further discussion. Simpson’s paradox in this context would require that within-subgroup deterioration trends systematically reverse direction relative to the pooled trend—for example, that high-traffic sections and low-traffic sections each show slower deterioration than the pool suggests, producing an artifact of faster apparent network-level deterioration. Three features of the dataset reduce this risk: (1) the 2200-section sample spans the full range of Korean expressway traffic classes and regional climate zones, so no single subgroup dominates the pooled mean; (2) the exponential deterioration model captures the same qualitative acceleration behavior (β > 1) regardless of traffic level, as confirmed by the SD growth curves stratified by AADT shown in Figure 2; and (3) the SD = 1.0 m2 PM criterion was derived directly from Figure 2’s traffic-stratified curves rather than from the pooled mean alone, providing an implicit check against systematic subgroup masking. Nonetheless, formal stratified regression by traffic class or regional climate zone is recommended in future work to validate the generalizability of the network-mean deterioration model and to rule out residual subgroup effects. Finally, the environmental co-benefits discussed qualitatively in this study could be rigorously quantified through Life-Cycle Assessment (LCA) integration with the LCCA framework, which would provide a more complete basis for sustainability-oriented PMS investment decisions.
For operational implementation, it is recommended that PM interventions be scheduled within a ±1-year window around t* = 10.8 yr to account for discrete annual PMS inspection cycles and section-level variability. The framework is directly compatible with the existing KEC Hi-PMS database workflow: the optimal timing criterion (t* ≈ 10.8 yr, or HPCI entering the 3.5–3.6 range) can be implemented as a condition-based trigger flag within the system, without additional instrumentation or data collection beyond the current annual survey program. The practical basis for this compatibility rests on three structural features of the current KEC PMS workflow: (1) the HPCI is computed and recorded annually for all approximately 4000 km of expressway pavement in the Hi-PMS database, so the deterioration age and current HPCI value required to apply the trigger criterion are already available for every section without additional data collection; (2) the KEC annual maintenance budget cycle operates on a section-by-section prioritization basis, and the NPV reduction values from Table 1 can be directly used as per-section economic scores in the existing prioritization workflow; and (3) the treatment-specific cost inputs used in the LCCA (unit costs for fog seal, chip seal, and thin overlay) are already tracked in the KEC cost accounting system, ensuring that the recommended scenarios map directly onto procurement categories in current use. While a formal pilot implementation with prospective validation of treatment outcomes was not conducted within this study—an important future validation step—the framework does not require changes to existing data infrastructure or inspection protocols, substantially lowering the barrier to adoption compared with frameworks that require additional sensor networks or pavement condition modalities. Regarding network-level optimization under budget constraints (a related but distinct problem), the section-level NPV benefit estimates from Table 1 provide the per-section objective function values required as inputs to a budget-constrained prioritization model. The integration pathway is as follows: the present framework determines the optimal PM timing and treatment type for each individual section; a network-level model (e.g., integer programming with a budget constraint) then selects which sections to treat in a given year to maximize total NPV reduction subject to available funds. This two-stage structure—section-level timing optimization followed by network-level budget allocation—is consistent with established PMS practice [1,3] and represents the natural next-step extension of the present work.

6. Conclusions

This study developed and validated a data-driven framework for optimal preventive maintenance timing for asphalt pavements on Korean expressways by integrating network-level PMS deterioration modeling with a life-cycle cost analysis. The following specific conclusions are drawn:
  • The HPCI deterioration of Korean expressway SMA asphalt pavement follows a nonlinear exponential model with β = 1.87 (R2 = 0.996), confirming accelerated deterioration beyond a critical service age of approximately 9–11 years.
  • The accelerated deterioration zone coincides with the HPCI Grade-2 boundary (3.5–4.0) and with the peak SD growth rate dominated by linear surface cracking (average 91.3% of total SD), providing an empirically grounded criterion for determining PM intervention timing.
  • A LCCA across 44 scenarios demonstrates that PM applied immediately before the onset of accelerated deterioration (t* ≈ 10.8 years, ~56% of pavement service life) minimizes the NPV over a 40-year analysis period, reducing total LCC by up to 7 million KRW per section relative to the conventional milling and overlay baseline.
  • The economically optimal PM timing and the empirically identified critical deterioration acceleration zone are mutually consistent, establishing that the optimal timing reflects a physically meaningful transition in surface distress dynamics rather than an arbitrary administrative boundary.
  • The proposed framework—linking network-level HPCI deterioration inflection to LCCA-derived optimal PM timing—provides an actionable, engineering-grounded criterion for PMS decision-making, directly applicable to the approximately 4000 km of asphalt expressway pavement managed by KEC and potentially extendable to other national highway networks employing composite pavement condition indices.

Author Contributions

Conceptualization, Y.K., K.K., J.K. and S.B.; methodology, Y.K., K.K., J.K. and S.B.; validation, Y.K. and K.K.; formal analysis, J.K. and S.B.; investigation, Y.K. and K.K.; resources, Y.K., K.K., J.K. and S.B.; writing—original draft preparation, Y.K. and K.K.; writing—review and editing, Y.K., K.K., J.K. and S.B.; visualization, Y.K., K.K., J.K. and S.B.; supervision, Y.K. and K.K.; project administration, Y.K. and K.K.; funding acquisition, Y.K. and K.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by Korea Expressway Corporation Research Institute (Project: Application Standards of Functional Pavement Including Asphalt Porous Pavement).

Institutional Review Board Statement

Not applicable.

Data Availability Statement

The Hi-PMS pavement condition data used in this study are proprietary to Korea Expressway Corporation and are not publicly available. Requests for data access may be directed to the corresponding author.

Conflicts of Interest

Author Sungho Bae was employed by the company Total Pavement System. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Korea Expressway Corporation (KEC). Pavement Management and Maintenance Practical Manual; Korea Expressway Corporation: Hwaseong, Republic of Korea, 2019. [Google Scholar]
  2. Prozzi, J.A.; Madanat, S.M. Development of pavement performance models by combining experimental and field data. J. Infrastruct. Syst. 2004, 10, 9–22. [Google Scholar] [CrossRef] [Scilit]
  3. AASHTO. Pavement Management Guide, 2nd ed.; American Association of State Highway and Transportation Officials: Washington, DC, USA, 2012. [Google Scholar]
  4. FHWA. Life-Cycle Cost Analysis in Pavement Design—In Search of Better Investment Decisions; Report No. FHWA-SA-98-079; Federal Highway Administration: Washington, DC, USA, 1998. [Google Scholar]
  5. Walls, J.; Smith, M.R. Life-Cycle Cost Analysis in Pavement Design: Interim Technical Bulletin; Report No. FHWA-SA-98-079; FHWA: Washington, DC, USA, 1998. [Google Scholar]
  6. Chan, W.T.; Fwa, T.F.; Tan, J.Y. Optimal fund-allocation analysis for multidistrict highway agencies. J. Infrastruct. Syst. 2003, 9, 167–175. [Google Scholar] [CrossRef] [Scilit]
  7. Abaza, K.A. Simplified staged homogenous Markov model for flexible pavement performance prediction. Road Mater. Pavement Des. 2016, 17, 365–381. [Google Scholar] [CrossRef] [Scilit]
  8. Shahnazari, H.; Tutunchian, M.A.; Mashayekhi, M.; Amini, A.A. Application of soft computing for prediction of pavement condition index. J. Transp. Eng. 2012, 138, 1495–1506. [Google Scholar] [CrossRef] [Scilit]
  9. Lytton, R.L. Concepts of pavement performance prediction and modeling. In Proceedings of the 2nd North American Conference on Managing Pavements, Toronto, ON, Canada, 2–6 November 1987; pp. 3.1–3.19. [Google Scholar]
  10. Ouyang, Y.; Madanat, S. Optimal scheduling of rehabilitation activities for multiple pavement facilities: Exact and approximate solutions. Transp. Res. Part A Policy Pract. 2004, 38, 347–365. [Google Scholar] [CrossRef] [Scilit]
  11. Korea Development Institute (KDI). Guidelines for Feasibility Study of Road and Railway Projects; KDI: Sejong, Republic of Korea, 2021. [Google Scholar]
  12. Peshkin, D.G.; Hoerner, T.E.; Zimmerman, K.A. Optimal Timing of Pavement Preventive Maintenance Treatment Applications; NCHRP Report 523; Transportation Research Board: Washington, DC, USA, 2004. [Google Scholar]
  13. Elhadidy, A.A.; Abo-Hashema, M.A.; Faheem, H.M. Development of pavement deterioration models using LTPP data. Int. J. Pavement Eng. 2019, 20, 1212–1219. [Google Scholar] [CrossRef] [Scilit]
  14. Hicks, R.G.; Seeds, S.B.; Peshkin, D.G. Selecting a Preventive Maintenance Treatment for Flexible Pavements; Foundation for Pavement Preservation: Washington, DC, USA, 2000. [Google Scholar]
  15. Kim, K.N.; Lee, S.H. Analysis of highway pavement condition and development of pavement performance model for Korean expressways. Int. J. Highw. Eng. 2018, 20, 11–20. [Google Scholar] [CrossRef] [Scilit]
  16. Park, H.Y.; Kim, K.N.; Lee, S.W. Service life analysis of Korean expressway asphalt pavement using LTPP data. Int. J. Highw. Eng. 2020, 22, 43–54. [Google Scholar]
  17. Zeiada, W.; Dabous, S.A.; Hamad, K.; Al-Ruzouq, R.; Khalil, M.A. Machine learning for pavement performance modelling in warm climate regions. Arab. J. Sci. Eng. 2020, 45, 4091–4109. [Google Scholar] [CrossRef] [Scilit]
  18. Dao, C.D.; Zhu, W.-D.; Grall, A. An optimal predictive inspection and maintenance policy for a multi-state system: A belief-based SMDP approach. Reliab. Eng. Syst. Saf. 2021, 214, 107782. [Google Scholar] [CrossRef] [Scilit]
  19. Zhao, X.; Fouladirad, M.; Bérenguer, C.; Bordes, L. An optimal joint predictive maintenance and mission abort policy under a cumulative working time success criterion. Reliab. Eng. Syst. Saf. 2021, 212, 107620. [Google Scholar] [CrossRef] [Scilit]
  20. Butt, A.A.; Shahin, M.Y.; Feighan, K.J.; Carpenter, S.H. Pavement performance prediction model using the Markov process. Transp. Res. Rec. 1987, 1123, 12–19. [Google Scholar]
  21. Labi, S.; Sinha, K.C. The Effectiveness of Maintenance and Its Impact on Capital Expenditures; Report FHWA/IN/JTRP-2003/05; Purdue University: West Lafayette, IN, USA, 2003. [Google Scholar]
  22. Elhadidy, A.A.; El-Badawy, S.M.; Elbeltagi, E.E. A simplified pavement condition index regression model for pavement evaluation. Int. J. Pavement Eng. 2021, 22, 643–652. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.