A System Architecture Framework for BIM-to-Robot Information Exchange in Construction

,
and
1
Department of Architectural Engineering, Pennsylvania State University, University Park, PA 16802, USA
2
Department of Civil and Environmental Engineering, University of Virginia, Charlottesville, VA 22904, USA
*
Author to whom correspondence should be addressed.

Abstract

The adoption of robotics in construction has progressed more slowly than in many other sectors. Building information models (BIMs) contain information that can support construction robotics, while robots require task-specific project data, such as geometry, location, material, sequence, and operating constraints, that may not be readily available in a directly usable form. This study proposes a conceptually integrated system architecture for BIM-to-robot information exchange comprising Task Planning, Task Decomposition, and anticipated Robot Task Execution linked by two information exchanges. A 20-concrete-masonry-unit (CMU) wall case study demonstrates selected information-preparation and documentation portions of the architecture. A low-LOD Revit wall was decomposed into individual CMUs using Dynamo, and component location (X, Y, Z, and orientation), material type, and identification (I.D.) information were extracted and formatted as robot-oriented task information. Because the available robotic platform lacked manipulation capability, a human worker interpreted the exported task information and constructed the wall, while a Husky A200 robot collected site images for dense point-cloud reconstruction. The reconstruction was superimposed on the source Revit model to qualitatively assess consistency between the constructed wall and the intended BIM-derived layout. The case study therefore demonstrates BIM-derived information generation and extraction, worker interpretation and use of the task information, and robot-assisted documentation, but it does not verify autonomous robotic construction. The primary contribution is the architectural integration of prior information-exchange and parametric-modeling methods across the end-to-end BIM-to-robot workflow, including explicit information requirements and exchange points; the term end-to-end refers to architectural scope rather than end-to-end experimental validation.

1. Introduction

While the construction industry has historically lagged behind other sectors, such as manufacturing, in adopting new technologies, particularly in the realm of robotics (Hasan Abid et al., 2018 [1]), the ongoing shift toward Construction 4.0 is ushering in a new era through a range of new applications including artificial/virtual reality (AR/VR), cyber security, big data analytics, laser scanning, automation, and robotics (Sawhney et al., 2020 [2]). Certain robots, such as the Semi-Autonomous Mason (SAM) (SAM, 2023 [3]), stand out for their task-specific design and capability of efficiently laying between 2000 and 3000 bricks daily (Madsen, 2019 [4]), while TyBot, developed by Advanced Construction Robotics, ties rebar intersections together to limit repetitive work, which is beneficial for extensive undertakings like bridges (Advanced Construction Robotics, 2023 [5]). Equally noteworthy is the emergence of additive manufacturing as an autonomous construction approach (Duballet et al., 2019 [6]). Additive manufacturing interprets the geometry from a model and places material into the correct location, significantly automating the building process (Tay et al., 2017 [7]). These robots, among many others, were designed for a specific case.
Within this broader Construction 4.0 context, BIM has increasingly been integrated with virtual, augmented, and extended reality environments to improve access to model information, visualization, coordination, design review, and construction decision making. Recent reviews show that BIM-XR workflows depend on transferring model geometry and associated information into downstream visualization platforms, making data exchange and interoperability central concerns in these applications (Bressan et al., 2024 [8]). Recent BIM-VR research similarly illustrates the value of connecting information-rich BIMs with immersive environments for design evaluation and decision support (Shehadeh et al., 2025) [9]. Sharafat et al. (2026) [10] further demonstrated an interoperable digital-twin workflow integrating BIM, finite-element modeling, and virtual reality through an IFC4.3-compliant ontology for design and assembly-process simulation. These developments provide a useful parallel to BIM-to-robot integration because each requires project information to be transformed and exchanged in a form that downstream digital or cyber-physical systems can interpret and use.
In contrast, other robots are designed and built to handle more general tasks, such as Spot (Spot, 2023) [11] or Husky (Clearpath Robotics, 2023) [12], which are flexible mobile platforms intended to address labor shortages and safety concerns and apply to numerous construction tasks.
Nonetheless, transitioning from craft labor to robots requires a fundamental reconsideration of construction information flow. A robot must receive, interpret, and apply task information that a craft worker would otherwise infer from drawings, specifications, experience, and site conditions. This creates a need for a system architecture that defines how information is generated, transformed, exchanged, and interpreted across BIM and robotic systems. System architecture provides a conceptual model of a system’s views, behavior, and structure (Jaakkola and Thalheim, 2011) [13] and should identify relevant hardware, software, data exchanges, and process requirements. BIM standards likewise emphasize structured information exchange and interoperability across project processes (National Institute of Building Sciences, 2015) [14].
The primary objective of this research is to develop a system architecture framework that connects BIM-based construction information with robot-oriented task preparation and identifies the information requirements at each exchange point. The framework is informed by a targeted review of construction system architectures, BIM-to-robot studies, and robotic system architectures. It is then demonstrated through a controlled masonry-wall proof of concept in which component-level information is generated and extracted from Revit, formatted as robot-oriented task information, interpreted by a worker to construct a 20-CMU wall, and documented through Husky A200 image collection and photogrammetric reconstruction. The physical placement step is intentionally treated as a surrogate for robotic manipulation because the available Husky platform was not equipped to place CMUs. Accordingly, the case study evaluates selected information-exchange and robot-assisted documentation portions of the architecture rather than the anticipated Robot Task Execution stage.
Accordingly, this study addresses three research questions: (RQ1) What task-specific information requirements and exchange points are needed to connect BIM-based task planning and task decomposition with anticipated robotic task execution? (RQ2) How can BIM information be supplemented, decomposed, and formatted into robot-oriented construction task information? (RQ3) What portions of the proposed architecture can be demonstrated through a small-scale masonry proof of concept, and what limitations remain before autonomous robotic execution can be validated?
This study builds on two preceding studies while making a distinct architectural contribution. McClymonds et al. (2022) [15] introduced the initial concept of BIM-to-robot information exchange and identified the need to prepare BIM-derived information for robotic construction. McClymonds et al. (2024) [16] subsequently developed the Dynamo-based parametric modeling method used to generate component-level masonry geometry and extract CMU information. These elements are inherited by the present study. The new contribution of this manuscript is the formalization of these prior elements within a conceptually integrated system architecture spanning the end-to-end BIM-to-robot workflow, explicitly connecting Task Planning, Interpret Model Information, Task Decomposition, Prepare Task Information, and anticipated Robot Task Execution and identifying the information requirements and exchange points between these stages. Experimentally, the present study demonstrates only a subset of this architecture: generation and extraction of BIM-derived CMU information, formatting and sequencing of task information, interpretation and use of that information by a human worker to construct the mock wall, and robot-assisted image capture followed by qualitative photogrammetric comparison with the BIM. Autonomous robot interpretation, navigation, manipulation, CMU placement, and closed-loop feedback were not experimentally demonstrated. Thus, end-to-end refers to the architectural integration of workflow stages and not to an experimentally validated end-to-end robotic workflow.

2. Literature Review

This review was conducted as a targeted narrative review rather than a formal systematic literature review. Its purpose was to identify representative studies that inform the proposed framework across three connected areas: construction and BIM system architectures, BIM information exchange and model development, and robotic system architectures/BIM-to-robot integration. The review therefore emphasizes recurring information requirements, interoperability limitations, robot planning and control needs, and feedback mechanisms rather than attempting an exhaustive census of the literature. Recent studies were added where they directly extend BIM-ROS integration, semantic interoperability, linked building data, digital twins, and robot task planning.
Findings from the literature are summarized in Table 1 and used to develop the proposed framework. Figure 1 presents the high-level architectural workflow, which is organized into three primary steps: Task Planning, Task Decomposition, and anticipated Robot Task Execution.
Figure 1. High-Level Architectural Workflow; Robot Task Execution Represents an Anticipated Stage.
The first two steps of the framework are primarily informed by construction and BIM system architectures, while the third conceptual step draws from robotic planning, sensing, execution, and feedback architectures. Robot requirements must nevertheless be considered throughout the process. Task Planning establishes the geometric, material, specification, and platform information needed for the selected construction task. Task Decomposition combines this model information with sequencing, fabrication, and logistical requirements to create robot-oriented task information. Anticipated Robot Task Execution then represents a future planning-sensing-execution-feedback loop. The case-study-specific rationale for model development and the method used to derive and assess information requirements are consolidated in the Task Planning subsection.

2.1. System Architecture in the Construction Industry

Researchers have investigated system architectures that promote interoperability among programs and applications in construction. Kim and Russell (2003) [17], for example, identified task planning, task execution, and human control/feedback as key components of an intelligent earthwork architecture. Aleksandrov et al. (2019) [18] proposed a system architecture for BIM and 3D geographic information, noting that model data may require preprocessing or transformation before geometric analysis and that information can be lost during IFC-based exchange. Bilal et al. (2016) [19] similarly showed that system architectures may need to manage large and heterogeneous data sources. Dakhli et al. (2019) [20] used an ontology-based approach to structure information for smart construction sites and categorized relevant resources such as cost, time, weather, materials, equipment, space, workers, and subcontractors.
The information processed by a construction system architecture varies with the task and project context. Banerjee and Nayaka (2021) [21] showed that BIM-integrated cyber-physical architectures require different parameters across construction domains. Ren and Zhang (2021) [22] highlighted interoperability inconsistencies and information loss when transferring information between architectural and structural models and file formats. Sanguinetti et al. (2012) [23] linked their BIM system architecture to analysis type, structure, and model development and noted the effort required to supplement models with additional information. Ibrahim et al. (2017) [24] likewise identified extraction, integration, analysis, and interpretation as key stages when combining BIM, GIS, sensors, and asset databases.
Model detail is another recurring issue. The BIM Forum LOD Specification describes progressively more developed model representations for different project uses (Bedrick et al., 2020) [25]. Lower LOD models are generally more conceptual, while higher LOD models can contain information supporting coordination, fabrication, assembly, and installation. Banfi (2016) [26] similarly emphasized that higher model development can support more detailed downstream uses but also increases modeling effort and information-management requirements. For BIM-to-robot applications, LOD alone is not a universal measure of robot readiness; the model must be assessed against the specific geometric, material, identification, sequencing, and other information required by the selected robotic task.
Research has therefore explored ways to supplement or transform BIM information for downstream applications. McClymonds et al. (2022) [15] investigated information-exchange requirements for BIM-to-robotic construction and identified computational modeling as one approach for supplementing low-LOD models. McClymonds et al. (2024) [16] subsequently used Dynamo to generate component-level CMU information from a masonry wall. Davtalab et al. (2018) [27] developed a BIM-integrated platform for robotic construction in additive manufacturing, while Girardet and Boton (2021) [28] showed how parametric modeling tools such as Grasshopper can support model generation and interoperability. Collectively, these studies demonstrate that task-specific preprocessing may be necessary before BIM information can be used by automated or robotic systems.
Recent openBIM developments also provide more formal mechanisms for defining and checking information requirements. The buildingSMART Information Delivery Specification (IDS) is a machine-readable standard for specifying and automatically checking alphanumeric IFC information requirements, including entities, classifications, materials, properties, quantities, values, and relations; IDS 1.0 does not define geometric requirements (buildingSMART International, 2024) [29]. Kładź and Borkowski (2025) [30] demonstrate how IDS and the buildingSMART Data Dictionary (bSDD) can support automated information exchange and verification in BIM workflows. For BIM-to-robot applications, these standards provide a pathway for formalizing machine-checkable alphanumeric requirements while geometric, sequencing, and robot-operational requirements must be treated through complementary mechanisms.
These construction-focused studies establish the importance of model development, information transformation, and interoperability, but they provide limited detail on how prepared information is translated into robot-oriented tasks and execution feedback. This gap motivates linking BIM information preparation with robotic planning and control rather than treating either domain in isolation.

2.2. BIM-to-Robotics System Architectures

Robotic system architectures also vary with the use case and platform, making it important to identify both high-level process requirements and platform-specific constraints. BIM can serve as a primary source of project geometry and component information, but the robot still requires task, environment, and control information in a representation that its software stack can interpret. Oesterreich and Teuteberg (2016) [31] identified robotics as an important component of Industry 4.0 in construction and noted the potential for BIM-derived information to support precise and repeatable robotic work.
Jahn et al. (2019) [32] emphasized that a robot must extract, integrate, analyze, and interpret information from multiple data sources, including onboard sensors. Leng et al. (2017) [33] organized swarm-robot control into human/computer interaction, planning, and execution layers and highlighted the importance of task decomposition. Ruiz and Chandrasekaran (2020) [34] similarly structured robotic interaction around data collection, feasibility assessment, task execution, and feedback. Kim et al. (2021) [17] moved closer to construction-specific integration by linking BIM with the Robot Operating System (ROS) for simulated drywall-painting task planning, while noting that schedule information alone was insufficient for execution. More recent research has addressed the data representation and semantic layer between BIM and robotics. Pauwels et al. (2023) [35] demonstrated BIM-to-digital-twin-to-robot data flows using RDF and JSON for robot navigation. Zhu et al. (2024) [36] proposed the Robot Construction Action Node as a middleware layer between BIM-based smart components and ROS and evaluated the approach using Linked Building Data. Bahreini et al. (2024) [37] developed an ontology that links robot, building, navigation, and inspection concepts for BIM-based robotic tasks. Oyediran et al. (2025) [38] integrated 4D BIM with robot task planning for action-level simulation, while Skoury et al. (2024) [39] developed a digital-twin architecture for collective robotic construction. These studies demonstrate growing integration between BIM and robotic systems but also show that construction information, robot capabilities, and execution feedback must be connected through explicit data and task mappings.
Related digital-twin and construction-sensing research further illustrates how heterogeneous model and field information can support downstream decision making. Sharafat and Tanoli (2026) [40] distinguish model-derived project-intent information from monitoring-derived project-status information within a structured digital-twin framework, providing an example of model-monitoring integration and updating. Cho et al. (2025) [41] combine RGB and point-cloud inputs for automated excavator activity recognition, demonstrating a construction-specific approach to multimodal sensing and machine interpretation of changing site states. These studies are relevant to the proposed architecture’s future feedback layer, although neither represents experimental validation of the BIM-to-robot workflow examined here.

2.3. Current Research Gaps

The literature reveals several recurring requirements and gaps. First, robot sensors and actuators create data that must be interpreted within a platform-specific control architecture. Second, construction-task information must be prepared before execution, but conventional BIM and schedule representations do not necessarily contain all action-level information required by a robot. Third, semantic and linked-data approaches can preserve relationships among building elements, tasks, and robot actions more effectively than flattened task files, but these approaches remain application-specific and are not yet a universal BIM-to-robot exchange standard. Finally, robotic execution typically relies on an iterative planning, sensing, execution, and feedback loop. Table 1 summarizes the studies reviewed in this section.
Table 1. Comparison of Recent Papers Concerning System Architectures for BIM and Robotics.
The literature review reveals that existing studies commonly address isolated portions of the BIM-to-robot workflow rather than the complete information-exchange process. Construction-focused architectures emphasize interoperability, model development, and data management but provide limited consideration of robot requirements and task execution. Robotic architectures emphasize planning, sensing, execution, and feedback but often assume that suitable task information has already been prepared. Recent BIM-ROS and semantic-interoperability studies narrow this gap, yet they remain focused on specific tasks, platforms, or data representations. To connect these areas, the proposed architecture is organized into three primary steps: Task Planning, which identifies project requirements and robot-relevant information needs; Task Decomposition, which converts BIM-derived information into constructible robot-oriented task information by incorporating logistical, fabrication, and sequencing requirements; and anticipated Robot Task Execution, which conceptually interprets, executes, senses, and provides feedback on construction activities. Two information exchanges connect these stages by transforming model and task information into forms suitable for the next process. The complete sequence is end-to-end in architectural scope; the present case study does not experimentally validate every stage.

3. System Architecture Framework Development

Building upon the gaps identified in the literature review, this section presents the proposed BIM-to-robot system architecture and defines the information exchanges required to connect construction planning with robot-oriented task preparation and anticipated execution. The framework is intentionally high-level so that its information requirements can be tailored to different robots, construction tasks, and project conditions. The process begins by identifying the construction task, model information, technical specifications, and robot constraints. It then supplements and extracts model information, decomposes the construction task using fabrication, logistics, and sequencing requirements, prepares the resulting information in a robot-oriented representation, and finally defines the anticipated task-execution and feedback loop. The framework is conceptually integrated across the end-to-end BIM-to-robot workflow, but end-to-end denotes architectural scope rather than complete experimental implementation. The 20-CMU masonry case study demonstrates selected portions of this process as a proof of concept; autonomous robot interpretation, navigation, manipulation, placement, and closed-loop feedback were not evaluated. Figure 2 summarizes the three major steps and the two intervening information exchanges.
Figure 2. Proposed BIM-to-Robot System Architecture (Architectural Scope).
The proposed system architecture framework identifies the high-level process of transferring information from a BIM toward construction-robot use and provides insight into the required stages and exchanges. The information-exchange points are intended to be format-independent at the architectural level: they define the information content and transformations required between stages rather than prescribing a particular file structure, serialization method, or middleware. The specific exchange representation may therefore vary with the robotic platform, software environment, task complexity, and interoperability requirements. CSV and PNG are implementation choices used in the masonry proof of concept and are not inherent requirements of the architecture. The following subsections define the steps and information exchanges in greater detail. It should also be noted that the detailed information required for each step varies with the selected construction task and robotic platform.

3.1. Task Planning

The Task Planning step establishes the information needed to support the selected construction activity before model sufficiency is assessed. To answer RQ1 systematically, the study separates requirement derivation from LOD assessment. Requirements are first derived from the construction method, system and assembly characteristics, geometry, technical specifications, and relevant robotic-platform constraints. Each requirement is then classified as geometric, alphanumeric, sequencing/logistical, or operational and assigned to the exchange point at which it must become available. The source BIM is subsequently checked against those task-specific requirements. Machine-checkable alphanumeric BIM requirements can be formalized through IDS when an IFC-based workflow is used, whereas geometric requirements require complementary assessment because IDS 1.0 does not specify geometry (buildingSMART International, 2024 [29]; Kładź and Borkowski, 2025 [30]). The BIM Forum LOD Specification is therefore used as a secondary reference for model-development sufficiency rather than as the primary mechanism for deriving robotic information requirements. Figure 3 presents the Task Planning workflow.
Figure 3. Task Planning Workflow Diagram.
For the masonry case study, task analysis identified the need for component type/material, component I.D., design location and orientation, sequencing information, site/logistical information, and relevant technical or operating constraints. The source wall representation was then compared with these requirements. LOD 400 was used as a case-specific target information state because fabrication/assembly-level representation is consistent with representing individual masonry components and their component-level attributes (Bedrick et al., 2020) [25]. Importantly, LOD 400 was not used to define what the robot-oriented task required and should not be interpreted as an inherent or universal LOD requirement for robotic construction. Instead, the required information content was derived from the task, and the LOD specification was used only as a reference for whether the geometric/model representation was sufficiently developed. Missing information was recorded as a supplementation requirement for the Interpret Model Information exchange. Table 2 summarizes the resulting information-requirement categories and their treatment in the case study.
Table 2. Task-Specific Information Requirements and Exchange Points for the Masonry Case Study.

3.2. Interpret Model Information

Information exchange is defined as how information or data gets translated from one entity to another (Messner et al., 2019) [46]. The first information exchange identified by the system architecture occurs between task planning and decomposition. This step seeks to supplement model geometry, if required, and extract information to enable the next steps of the system architecture. The process utilized in this step is depicted in Figure 4.
Figure 4. Interpret Model Information Workflow Diagram.
This study used Dynamo to generate and extract model information, forming a bridge between the task planning and task decomposition phases. To begin the information exchange, the geometric layout information and any system or additional components that interact with the system must be analyzed with computational modeling, for example, openings and lintels. The overall system geometry is used to identify the locations of the components that construct the wall system. Additionally, the relationships and components of the adjacent systems are identified to determine if they impact the construction process for the chosen system. Any supplementary information requirements determined in the task planning step are transferred and combined with any additional requirements specified from analyzing the layout and relationships. From there, if the model does not require supplemental information, then the required information is gathered and extracted for the task decomposition step. However, if the model requires additional information, those requirements are added, and the computational modeler can access a material content library to import the necessary components to construct the wall. The material content library is a repository of components imported into the BIM and placed in design locations. The computational modeler is then responsible for gathering all the required components and building information for the following step, Task Decomposition. Additional studies are underway to determine the methods for analyzing the geometry and generating model content to facilitate this process, such as a study that used Dynamo to generate CMUs based on the geometry of a wall developed in Revit (McClymonds et al., 2024) [16].

3.3. Task Decomposition

This study defines decomposition as breaking down the task into manageable size components. The components for this step are logistical, fabrication, and scheduling information, and the workflow is represented in Figure 5. Task decomposition further investigates the construction task and site to create a more comprehensive view of robotic construction.
Figure 5. Task Decomposition Workflow Diagram.
At this stage, each component related to the task has the following information extracted: orientation, site location, type of material, and component I.D., which was generated in the previous step. From there, logistical information is defined as the planning, coordinating, and managing of resources in the construction process, including material management, site hazard management, and site coordination. Material management includes the locations of designated storage locations and inventory management to ensure that the materials are available to support this step. In addition, construction sites consist of dynamic and static hazards, where dynamic hazards such as moving equipment continually change on the site. Additionally, weather is a dynamic hazard that must be considered in the process to ensure the operating conditions of the construction robot are met. Static hazards are consistent elements on the site, such as the building footprint or site perimeter. Site coordination considers the relationship between the robot’s task and other ongoing construction tasks, which is essential for the robot’s navigation and ensures workers’ safety. Based on the logistical information, an occupancy grid that denotes static hazards and informs the robot about material storage locations, terrain variations, or site hazards can be generated. Fabrication information refers to components or systems requiring preassembly before the robot’s installation, which captures the construction methods of building systems and interactions to determine fabrication needs. In current processes, the specifics for fabrication are often determined by craft laborers; however, to mirror the construction process, it must be considered for robots. To determine the requirement, both the technical specifications and construction methods must be reviewed.
The final part of the task decomposition step is to determine the scheduling, which incorporates sequencing information for the task and corresponding components by analyzing the construction method and its relation to the information extracted from the BIM. The schedule defines logistical information, including location and fabrication information, to accurately reflect the traditional installation process. The analysis considers the overall systems and how the subsystems related to the task, including duration, resources, and imposed site constraints, must be considered when creating robotic tasks. For most tasks on the construction site, the schedule will not contain enough detail and must be supplemented for each building system component. Once all information is determined, it is gathered and sent to the following step in the system architecture: prepared task information.

3.4. Prepare Task Information

Information exchange aims to prepare the necessary information for each task for the anticipated Robot Task Execution stage. There are two main components associated with this information exchange. First, the task decomposition and task planning information are combined to form a coherent set of instructions. Then, the information is formatted based on the requirements of the robotic platform. The workflow diagram is shown in Figure 6.
Figure 6. Prepare Task Information Workflow Diagram.
First, decomposition information is combined with the logistical information. Each Revit component has an I.D. that can associate component information with sequencing and task requirements. The combined information must then be encoded in a file, message, graph, or other representation that the selected robotic platform can interpret. This representation is an implementation decision rather than an architectural requirement. For the masonry proof of concept, a comma-separated value (CSV) file generated through Dynamo was selected because the component/task data were relatively simple and tabular and because the representation could be readily parsed within a ROS-oriented workflow. Other implementations may use JSON, linked data, ontologies, databases, middleware messages, or other structured representations depending on task and platform needs.
The CSV representation is intentionally lightweight and task-specific, but it flattens BIM information and does not preserve the full semantic relationships among building elements, construction processes, site conditions, and robot actions. It should therefore be interpreted as the implementation format used in this proof of concept rather than a general interoperability solution or a requirement of the proposed architecture. Semantic and linked-data approaches provide richer alternatives: BIM-derived graph data can be transferred to robots through RDF/JSON workflows (Pauwels et al., 2023) [35], Linked Building Data can connect BIM components to ROS-based construction actions (Zhu et al., 2024) [36], and ontologies can explicitly represent relationships among buildings, robots, navigation, and inspection tasks (Bahreini et al., 2024) [37]. Sharafat et al. (2026) [10] similarly demonstrate interoperable exchange across BIM, analysis, and immersive simulation using an IFC4.3-compliant ontology. Future implementations should evaluate such representations where richer machine-interpretable relationships, automated requirement checking, or dynamic information updates are needed. The architecture is format-independent conceptually, but interoperability across alternative representations was not experimentally validated in the present study.

Proposed Robot Task Execution

The proposed Robot Task Execution stage is the final architectural step, in which a future robotic platform would receive prepared task information, convert that information into executable actions, and perform the task. This conceptual stage builds on robotic planning and feedback concepts described by Ibrahim et al. (2017) [24] and Sanguinetti et al. (2012) [23]. It was not experimentally implemented in the present masonry case study. The anticipated workflow is shown in Figure 7.
Figure 7. Proposed Robot Task Execution Workflow (Conceptual).
In the proposed architecture, Robot Task Execution contains three interacting functions: task creation/planning, physical execution, and control/feedback. A future robotic platform would receive the prepared task information, interpret it within its control software, and formulate an executable plan. During execution, onboard localization and perception sensors would support navigation, obstacle avoidance, and monitoring of task progress. Occupancy-grid and site information could guide movement between material storage and work locations. After each action, the system would record progress and evaluate whether the observed state remains consistent with the planned task. When tasks are complete, the system could generate construction-progress, quality-control, tolerance, and error information for project personnel and subsequent planning updates. None of these autonomous execution functions were experimentally validated in the present case study.
An anticipated function of Robot Task Execution is the ability to respond to deviations between planned BIM-derived conditions and the observed field state. In a fully autonomous implementation, geometric deviations detected through onboard sensing, site imaging, or point-cloud reconstruction would be compared with task-specific tolerances derived from the technical specifications. Deviations within allowable tolerance could be documented while execution continues; deviations exceeding tolerance would update the current site state and trigger re-evaluation of subsequent component locations, construction sequence, navigation path, or placement actions. If the deviation could not be resolved within the robot’s operating or safety constraints, execution would be paused and human intervention requested. Digital-twin research that explicitly compares model-intent information with monitoring-derived status information provides a related precedent for this type of model-monitoring feedback (Sharafat and Tanoli, 2026) [40], while multimodal RGB and point-cloud activity recognition illustrates how changing construction states may be interpreted automatically (Cho et al., 2025) [41]. This closed-loop feedback and replanning behavior remains conceptual in the present architecture and was not experimentally implemented.

4. Implementation for Masonry Wall Construction

This section demonstrates selected components of the proposed architecture using a small-scale masonry wall. The objective is to generate component-level information from an Autodesk Revit model, combine that information with task-decomposition requirements, and format it as robot-oriented task information. The implementation directly evaluates task planning, model-information interpretation, task decomposition, task-information preparation, worker-executed placement, and robot-assisted documentation. Autonomous robotic interpretation, navigation, manipulation, and placement were not evaluated. Instead, a worker interpreted the task information and placed the CMUs, and the Husky A200 was used to collect site images for reconstruction. The implementation should therefore be interpreted as a proof of concept for selected information-exchange and documentation components rather than validation of an end-to-end autonomous robotic workflow. Additional details on the image-collection process are reported in McClymonds et al. (2026) [45].

4.1. Scope

For this case study, masonry wall systems were chosen for the following reasons:
  • Masonry walls are modeled using a low LOD model, which requires supplemental information to locate each masonry unit that constructs the wall.
  • Masonry construction follows a linear progression, simplifying the integration of sequence-based information.
  • Masonry construction has minimal fabrication requirements compared to other systems.
  • The small-scale setup supports repeatable proof-of-concept testing; scalability to larger and more dynamic construction sites is not evaluated in this study.
  • Masonry units use standard configurations and forms in wall construction.
Masonry construction was selected because it provides a structured case for examining component-level information generation, sequencing, and task preparation. The case study uses 20 CMUs to support repeatable construction and reconstruction. First, wall information is generated and extracted from the BIM and formatted as robot-oriented task information. A worker then interprets that information and constructs the wall, serving as a surrogate for the physical placement step that the available robot could not perform. The Husky A200 is teleoperated to collect images of the completed wall for point-cloud reconstruction and qualitative comparison with the source model. Accordingly, the case study demonstrates task planning, model-information interpretation, task decomposition, task-information preparation, worker-executed placement, and robot-assisted documentation, but it does not verify autonomous Robot Task Execution. Navigation and documentation constraints are informed by the Husky platform, whereas actual CMU manipulation would require a different robot or a manipulator-equipped mobile platform.

4.2. Task Planning

Masonry wall construction is the selected case-study task; therefore, the first step is to identify the information required to prepare the task for future robotic use. The traditional construction method was reviewed, together with the model, specifications, and relevant platform constraints, to establish the task-specific information requirements shown in Table 2. Figure 8 summarizes the construction method used to inform this Task Planning process.
Figure 8. Construction Method for Masonry Construction.
The construction method and technical requirements define the information needed for task preparation. Each masonry unit must be identified by type and design location; the case study uses 8 in. × 8 in. × 16 in. CMUs. The modeled wall contains 20 CMUs and is positioned relative to the local Revit/site coordinate system. The source wall is represented at approximately LOD 200, where the masonry pattern is conveyed primarily as a material/texture rather than as individual construction units. After the task-specific requirements were identified, the model was supplemented to an LOD 400 target so that individual CMUs could be represented with the component-level type, I.D., location, and orientation required by the case-study task. LOD 400 is therefore a case-specific information target and not evidence that LOD 400 is inherently required for robotic construction. Technical specifications also contribute task constraints, such as allowable materials and joint/tolerance requirements. The CMUs were dry-set in this experiment using nominal dimensions. A Husky A200 running ROS Melodic was used for image collection and navigation-related constraints; because it lacks a manipulator, it was not used for physical CMU placement.

4.3. Interpret Model Information

Based on the Task Planning phase, the model requires supplemental information, transforming the wall into components so that component-level information can be extracted. In the case-study model, individual CMUs are generated from geometric constraints. A Dynamo script integrated with Revit interprets the model geometry and locates points along the wall where CMUs are placed. Reference edges are extracted from the wall and used to locate the first CMU; the unit length is then used to determine the locations of the remaining blocks in the first course. An array based on block height and wall height locates subsequent courses, and an offset is applied to represent the running-bond pattern. Components imported from the material content library are placed at the generated points and rotated according to wall direction, resulting in individual CMUs with the required parameters, including material name, location, orientation, I.D., and type. In a future robotic-placement implementation, a robotic system would require this information to plan and execute block placement relative to the intended design location and orientation. In the present experiment, the worker interpreted and used the exported information for placement. The model developed by this script is shown in Figure 9. McClymonds et al. (2024) [16] provide a more detailed description of the Dynamo method.
Figure 9. Masonry Wall Constructed from Individual Units Generated with Computational Modeling.
Additionally, multiple robotic systems require an occupancy grid developed from the BIM. This grid would provide information about the construction site, including storage location for the CMUs, site barriers, and other static obstacles. The robot will be equipped with various sensors and hardware that aid navigation and prevent collision with fixed objects within the construction zone. An occupancy grid was developed for this model, which presents a black border around the edge of the construction site. A stockpile location for masonry units, the base station used for navigation, and the robot are shown in Figure 10. The base station is located at the site origin point, and the stockpile location is 0.91 m (3 feet) on the Y-axis and 7.62 m (25 feet) on the X-axis.
Figure 10. 2-D Occupancy Grid of Simple Masonry Wall on Construction Site.
At this stage, location information is extracted for the CMUs. For the present case study, this information was subsequently formatted as a CSV implementation file, with Dynamo generating records for all 20 wall elements. The architecture itself does not require CSV; another robotic platform or task may use a different structured exchange representation. The script is being assessed on larger models and wall configurations; however, the small model is used here to demonstrate proof of concept.

4.4. Task Decomposition

Because the case-study wall is a straight, small-scale assembly of standard CMUs, no fabrication or preassembly was required. This branch of the framework was therefore not tested. On larger or more complex building systems, interactions with openings, interfaces, or adjacent systems could introduce fabrication requirements that would need to be identified during task decomposition. Logistical information for the present experiment included the wall location, stockpile location, local site geometry, weather conditions, and operating constraints relevant to image collection.
Robot operating constraints must also be incorporated into task decomposition. For the Husky A200 used for image collection, environmental limitations and the protection of onboard sensing equipment constrained when data collection could occur (Clearpath Robotics, 2023) [12]. The Husky used in this study was not equipped with a robotic arm and could not construct the wall. Potential dynamic hazards, such as moving vehicles or workers, would need to be detected by the robot or communicated through updated site information in a full-scale implementation. Sequencing for the 20-CMU wall was developed manually from the traditional masonry construction method and the extracted block locations. Because neither autonomous navigation nor automated sequencing was evaluated, these elements are treated as framework requirements rather than validated capabilities in this case study.

4.5. Prepare Task Information

Task information was prepared by combining the manually developed sequence with the extracted component locations and identifiers. For the masonry proof of concept, the resulting information was serialized as a CSV file because it provided a lightweight tabular representation that could be parsed within a ROS-oriented workflow. Table 3 presents a representative excerpt containing 6 of the 20 component records in the complete case-study dataset. The sequence was organized manually from the left corner of the wall; automation of sequencing would be required for larger or more complex tasks. As discussed in the framework section, CSV is an implementation choice rather than an architectural requirement and does not preserve the full semantic structure of the BIM.
Table 3. Representative Excerpt of Formatted and Sequenced BIM-Derived Task Information (6 of 20 Component Records Shown).
Second, the occupancy grid is formatted for the robot as a Portable Network Graphics File (.PNG). The grid should be updated periodically as the construction site is dynamic. The PNG file was chosen because the Husky robot can create an occupancy grid in this format. Other formats are potentially usable and have not been analyzed by this study.

4.6. Anticipated Robot Task Execution (Not Experimentally Evaluated)

This step was not experimentally evaluated and represents anticipated behavior for a future robot or mobile-manipulation platform capable of handling CMUs. Such a platform would receive the prepared component information, including task sequence, component I.D., type, and target location, and would translate those inputs into pick, transport, and placement actions. Navigation would use site maps, sensing, and updated obstacle information, while the manipulation system would require an end effector, reach, payload capacity, placement accuracy, and safety controls appropriate to masonry construction. The Husky A200 used in this experiment provides an example of mobility and sensing constraints that must be considered, but it was not equipped with a manipulator and its chassis payload specification should not be interpreted as a demonstrated CMU-placement capability. During future autonomous execution, sensing and feedback would be used to confirm progress, detect deviations, and trigger replanning or human intervention as described in the conceptual framework. The present study therefore does not claim experimental verification of Robot Task Execution.

4.7. Qualitative Verification Criteria

Because the point-cloud/model comparison was intended as qualitative verification rather than geometric accuracy assessment, successful verification was evaluated using explicit visual criteria. The criteria were: (1) consistency of the reconstructed wall’s overall location and orientation with the BIM-derived layout; (2) substantial visual correspondence between the reconstructed wall geometry and the BIM-defined wall envelope over the wall length and height; (3) absence of gross systematic translation, rotation, or course-level misalignment; and (4) discrepancies outside the BIM-defined wall envelope being localized rather than continuous or systematic. These criteria were used only to judge whether the constructed configuration was visually consistent with the intended BIM-derived layout. They do not establish dimensional tolerances or quantify either construction accuracy or photogrammetric reconstruction accuracy. Visible BIM-to-reconstruction differences can arise from physical placement as well as image coverage, point-cloud reconstruction, noise, and registration, and those sources were not independently quantified in the original experiment.

5. Results and Discussion

The proof-of-concept implementation demonstrates selected information-generation and task-preparation components of the proposed architecture. Dynamo generated 20 individual CMUs aligned with the source wall geometry, and the resulting components were manually inspected in Revit to confirm that the generated units did not overlap and were positioned consistently with the modeled wall profile. Component information was then extracted in the local Revit coordinate system. Because the wall required no fabrication, the Task Decomposition step focused on logistics and sequencing. The stockpile and wall locations were represented relative to the site coordinate system, and a simple sequence was developed manually from the traditional construction method. The resulting sequence and component information were exported as a CSV file and interpreted by the worker during the present case study. The same information structure was developed as a robot-oriented task representation that could be adapted for interpretation by a suitable robotic platform in future implementation.
A worker used the exported task information to construct the wall because the available robot could not perform CMU placement. After construction, the Husky A200 collected site images and a 3D point-cloud reconstruction of the wall was developed using methods consistent with prior construction-reconstruction research (Golparvar-Fard et al., 2015 [47]; Stephans et al., 2022 [48]). The reconstruction was superimposed on the Revit model and evaluated using the qualitative criteria defined in Section 4.7. The comparison was not designed as a quantitative geometric-accuracy experiment and was not used to independently assess construction quality or photogrammetric reconstruction quality. Figure 11 summarizes the experimentally implemented process.
Figure 11. Implementation of Experimentally Demonstrated Architecture Components.
Because the robot did not perform the physical placement step, Figure 11 labels the final experimentally performed stage as worker-executed task execution rather than Robot Task Execution. In the final comparison, the green highlighted regions represent the model area associated with the Revit-derived blocks, while red regions show reconstructed geometry extending beyond the nominal wall/block boundaries. Applying the Section 4.7 criteria, the reconstructed wall was considered qualitatively consistent with the BIM-derived layout because it occupied the intended overall wall location and orientation, showed substantial visual correspondence with the BIM-defined wall envelope, and did not exhibit an obvious systematic translation, rotation, or course-level misalignment. Geometry extending beyond the nominal BIM envelope was localized rather than continuous across the wall. These localized discrepancies cannot be assigned solely to construction placement: they may reflect worker placement or movement of the lightweight foam CMUs, but they may also result from photogrammetric reconstruction uncertainty, image coverage, point-cloud noise, or model-to-reconstruction registration. Because those sources were not independently quantified, the comparison supports qualitative verification of the BIM-derived information-generation/layout process and robot-assisted documentation, but it does not constitute an independent assessment of construction accuracy, photogrammetric reconstruction accuracy, or autonomous robotic construction.
Quantitative point-to-model deviation statistics, such as mean and maximum deviation, were not calculated as part of the original experiment and are therefore not reported retrospectively. This limits the strength of geometric-accuracy conclusions that can be drawn from the reconstruction. Future evaluations should retain the registered point-cloud/model data and report quantitative measures such as mean absolute deviation or RMSE together with a robust maximum measure (for example, a high-percentile deviation) to separate information-exchange performance from reconstruction and placement error.
Accordingly, the case study should be interpreted as an experimental demonstration of selected information-generation, task-preparation, worker-use, and robot-assisted documentation portions of a broader BIM-to-robot architecture, rather than experimental validation of the complete BIM-to-robot workflow. BIM-derived task information was exported, interpreted by a worker, used to construct a mock masonry wall, and documented through robot-assisted image capture and point-cloud reconstruction. The robot did not interpret the CSV for execution, transport or place the CMUs, navigate autonomously, or close the sensing-feedback loop. In addition, the experiment used a straight 20-CMU wall, did not require fabrication, relied on manual sequencing, and did not evaluate autonomous occupancy-grid navigation. The evidence therefore supports the selected information-exchange and documentation components demonstrated in the case study while the full end-to-end sequence remains an architectural integration requiring future experimental validation.
Future work should evaluate the framework with manipulator-capable robotic platforms, larger and more complex building systems, automated sequencing, and active-site navigation. A full implementation should also close the feedback loop by updating the site state and task plan when sensing identifies geometric or environmental deviations. Related digital-twin work demonstrates how model-intent information can be compared with monitoring-derived status information to support structured updating (Sharafat and Tanoli, 2026) [40], while multimodal construction sensing using RGB and point-cloud data illustrates a potential path for automated interpretation of evolving site states (Cho et al., 2025) [41]. Semantic, linked-data, and machine-readable requirement representations should be evaluated alongside lightweight task files so that component relationships, process context, and robot actions can be preserved as information changes during execution.

6. Conclusions

This study developed a conceptually integrated system architecture for BIM-to-robot information exchange that spans Task Planning, Task Decomposition, anticipated Robot Task Execution, and two intervening information exchanges. The framework extends earlier work on BIM-to-robot information exchange and Dynamo-based masonry model generation by formalizing how model-information preparation, construction-task requirements, and future robotic execution needs connect across the architectural workflow. In the 20-CMU proof of concept, Dynamo generated component-level masonry information, a manual sequence was combined with the extracted locations and identifiers, and the resulting task information was exported as CSV. A worker interpreted that information and constructed the wall, while a Husky A200 collected images for point-cloud reconstruction. The reconstruction provided qualitative evidence that the BIM-derived task information could support a constructed configuration consistent with the intended layout and could be documented through robot-assisted image collection. The study therefore experimentally demonstrates selected information-exchange, worker-use, and documentation components of the architecture; it does not constitute end-to-end experimental validation of autonomous robotic construction.
Several limitations affect the interpretation and generalizability of the results. First, the source wall required supplementation from a low-LOD representation to component-level information. The information needed for this transformation is task-specific; LOD 400 was a case-specific target for the masonry application and should not be treated as a universal requirement for robotic construction. Second, CSV was useful as a lightweight proof-of-concept task format but is not an architectural requirement and does not preserve the full semantic relationships available in BIM. The proposed exchange points are format-independent conceptually, while the present study experimentally demonstrates only the CSV-based implementation. Future work should evaluate linked-data, ontology-based, IDS-supported, and other structured representations that can maintain richer relationships and machine-checkable information requirements. Third, the Husky A200 was teleoperated for image collection and lacked a robotic arm, so autonomous interpretation, navigation, transport, placement, and closed-loop feedback were not tested.
The experiment was also intentionally small and controlled. The straight 20-CMU wall did not require fabrication, automated sequencing, or autonomous occupancy-grid navigation, and the test environment did not reproduce the full variability of an active construction site. Scaling the architecture will require evaluation of dynamic obstacles, worker and equipment interactions, site congestion, material logistics, changing weather, communication reliability, multiple concurrent systems, safety constraints, and more complex construction sequences. Quantitative point-to-model deviation metrics should also be collected in future validation studies. These limitations define the next stage of research: implementation on a manipulator-capable platform and evaluation across larger, more complex, and dynamically changing construction tasks.

Author Contributions

Conceptualization, A.D.M. and R.M.L.; methodology, A.D.M., S.A. and R.M.L.; investigation, A.D.M.; formal analysis, A.D.M.; visualization, A.D.M.; resources, R.M.L.; writing—original draft, A.D.M.; writing—review and editing, A.D.M., S.A. and R.M.L.; supervision, S.A. and R.M.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Science Foundation under Grant 1928626.

Data Availability Statement

Data and code supporting this study can be found here: https://github.com/austinmcclymonds/Robot-Data-Collection (accessed on 9 July 2026).

Acknowledgments

The authors acknowledge the support and resources that enabled the experimental work. Any opinions, findings, conclusions, or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of the National Science Foundation.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Hasan, A.; Baroudi, B.; Elmualim, A.; Rameezdeen, R. Factors affecting construction productivity: A 30-year systematic review. Eng. Constr. Archit. Manag. 2018, 25, 916–937. [Google Scholar] [CrossRef] [Scilit]
  2. Sawhney, A.; Riley, M.; Irizarry, J. Construction 4.0—An Innovation Platform for the Built Environment; Routledge: New York, NY, USA, 2020. [Google Scholar]
  3. SAM. Construction Robotics. Available online: https://www.construction-robotics.com/ (accessed on 29 January 2022).
  4. Madsen, A. The SAM100: Analyzing Labor Productivity. Bachelor’s Thesis, California Polytechnic State University, San Luis Obispo, CA, USA, 2019. [Google Scholar]
  5. Advanced Construction Robotics. Rebar Equipment|Construction Robots|Home of TyBot and IronBot. Available online: https://www.constructionrobots.com (accessed on 6 October 2022).
  6. Duballet, R.; Baverel, O.; Dirrenberger, J. Space Truss Masonry Walls with Robotic Mortar Extrusion. Structures 2019, 18, 41–47. [Google Scholar] [CrossRef] [Scilit]
  7. Tay, Y.W.D.; Panda, B.; Paul, S.C.; Noor Mohamed, N.A.; Tan, M.J.; Leong, K.F. 3D printing trends in building and construction industry: A review. Virtual Phys. Prototyp. 2017, 12, 261–276. [Google Scholar] [CrossRef] [Scilit]
  8. Bressan, N.M.; Scarpa, M.; Peron, F. Case studies of eXtended reality combined with Building Information Modeling: A literature review. J. Build. Eng. 2024, 84, 108575. [Google Scholar] [CrossRef] [Scilit]
  9. Shehadeh, A.; Alshboul, O.; Taamneh, M.M.; Jaradat, A.Q.; Alomari, A.H.; Arar, M. Advanced integration of BIM and VR in the built environment: Enhancing sustainability and resilience in urban development. Heliyon 2025, 11, e42558. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  10. Sharafat, A.; Tanoli, W.A.; Yoo, S.-H.; Seo, J. Digital Twin Framework for Cutterhead Design and Assembly Process Simulation Optimization for TBM. Appl. Sci. 2026, 16, 1865. [Google Scholar] [CrossRef] [Scilit]
  11. Spot. Boston Dynamics. Available online: https://bostondynamics.com/products/spot/ (accessed on 9 August 2023).
  12. Clearpath Robotics. Husky UGV—Outdoor Field Research Robot by Clearpath. Available online: https://clearpathrobotics.com/husky-unmanned-ground-vehicle-robot/ (accessed on 26 October 2021).
  13. Jaakkola, H.; Thalheim, B. Architecture-driven modelling methodologies. In Information Modelling and Knowledge Bases XXII; IOS Press: Amsterdam, The Netherlands, 2011; pp. 97–116. [Google Scholar]
  14. National Institute of Building Sciences. National BIM Standard-United States Version 3; National Institute of Building Sciences: Washington, DC, USA, 2015; Available online: https://nibs.org/nbims/v3/ (accessed on 9 July 2026).
  15. McClymonds, A.; Asadi, S.; Wagner, A.; Leicht, R.M. Information Exchange for Supporting BIM-to-Robotic Construction. Am. Soc. Civ. Eng. 2022, 2022, 839–848. [Google Scholar] [CrossRef] [Scilit]
  16. McClymonds, A.D.; Asadi, S.; Leicht, R.M. Development of a Parametric Modeling Method for Masonry Wall Systems to Support Robotic Construction. In Computing in Civil Engineering 2023, Presented at the ASCE International Conference on Computing in Civil Engineering 2023; American Society of Civil Engineers: Corvallis, OR, USA, 2024; pp. 398–406. [Google Scholar] [CrossRef] [Scilit]
  17. Kim, S.; Peavy, M.; Huang, P.-C.; Kim, K. Development of BIM-integrated construction robot task planning and simulation system. Autom. Constr. 2021, 127, 103720. [Google Scholar] [CrossRef] [Scilit]
  18. Aleksandrov, M.; Diakité, A.; Yan, J.; Li, W.; Zlatanova, S. Systems Architecture for Management of BIM, 3D GIS and Sensors Data. ISPRS Ann. Photogramm. Remote Sens. Spat. Inf. Sci. 2019, IV-4/W9, 3–10. [Google Scholar] [CrossRef] [Scilit]
  19. Bilal, M.; Oyedele, L.O.; Akinade, O.O.; Ajayi, S.O.; Alaka, H.A.; Owolabi, H.A.; Qadir, J.; Pasha, M.; Bello, S.A. Big data architecture for construction waste analytics (CWA): A conceptual framework. J. Build. Eng. 2016, 6, 144–156. [Google Scholar] [CrossRef] [Scilit]
  20. Dakhli, Z.; Danel, T.; Lafhaj, Z. Smart Construction Site: Ontology of Information System Architecture. In Proceedings of the Modular and Offsite Construction (MOC) Summit; University of Alberta Library: Edmonton, AB, Canada, 2019; pp. 41–50. [Google Scholar] [CrossRef] [Scilit]
  21. Banerjee, A.; Nayaka, R.R. A comprehensive overview on BIM-integrated cyber physical system architectures and practices in the architecture, engineering and construction indFustry. Constr. Innov. 2021, 22, 727–748. [Google Scholar] [CrossRef] [Scilit]
  22. Ren, R.; Zhang, J. A New Framework to Address BIM Interoperability in the AEC Domain from Technical and Process Dimensions. Adv. Civ. Eng. 2021, 2021, e8824613. [Google Scholar] [CrossRef] [Scilit]
  23. Sanguinetti, P.; Abdelmohsen, S.; Lee, J.; Lee, J.; Sheward, H.; Eastman, C. General system architecture for BIM: An integrated approach for design and analysis. Adv. Eng. Inform. 2012, 26, 317–333. [Google Scholar] [CrossRef] [Scilit]
  24. Ibrahim, K.; Abanda, H.; Vidalakis, C.; Wood, G. Bim big data system architecture for asset management: A conceptual framework. In Proceedings of the Joint Conference on Computing in Construction (JC3); European Council on Computing in Construction: Sint-Niklaas, Belgium, 2017; pp. 289–296. [Google Scholar]
  25. Bedrick, J.; Ikerd, W.; Reinhardt, J. Level of Development Specification—BIM Forum. Available online: https://bimforum.org/resource/lod-level-of-development-lod-specification/ (accessed on 24 March 2023).
  26. Banfi, F. Building Information Modelling—A Novel Parametric Modeling Approach Based on 3D Surveys of Historic Architecture. In Digital Heritage. Progress in Cultural Heritage: Documentation, Preservation, and Protection; Ioannides, M., Fink, E., Moropoulou, A., Hagedorn-Saupe, M., Fresa, A., Liestøl, G., Rajcic, V., Grussenmeyer, P., Eds.; Springer International Publishing: Cham, Switzerland, 2016; pp. 116–127. [Google Scholar] [CrossRef] [Scilit]
  27. Davtalab, O.; Kazemian, A.; Khoshnevis, B. Perspectives on a BIM-integrated software platform for robotic construction through Contour Crafting. Autom. Constr. 2018, 89, 13–23. [Google Scholar] [CrossRef] [Scilit]
  28. Girardet, A.; Boton, C. A parametric BIM approach to foster bridge project design and analysis. Autom. Constr. 2021, 126, 103679. [Google Scholar] [CrossRef] [Scilit]
  29. buildingSMART International. Information Delivery Specification (IDS). Available online: https://www.buildingsmart.org/standards/bsi-standards/information-delivery-specification-ids/ (accessed on 2 September 2026).
  30. Kładź, M.; Borkowski, A.S. IDS Standard and bSDD Service as Tools for Automating Information Exchange and Verification in Projects Implemented in the BIM Methodology. Buildings 2025, 15, 378. [Google Scholar] [CrossRef] [Scilit]
  31. Oesterreich, T.D.; Teuteberg, F. Understanding the implications of digitisation and automation in the context of Industry 4.0: A triangulation approach and elements of a research agenda for the construction industry. Comput. Ind. 2016, 83, 121–139. [Google Scholar] [CrossRef] [Scilit]
  32. Jahn, U.; Wolff, C.; Schulz, P. Concepts of a modular system architecture for distributed robotic systems. Computers 2019, 8, 25. [Google Scholar] [CrossRef] [Scilit]
  33. Leng, Y.; Yu, C.; Zhang, W.; Zhang, Y.; He, X.; Zhou, W. Task-oriented hierarchical control architecture for swarm robotic system. Nat. Comput. 2017, 16, 579–596. [Google Scholar] [CrossRef] [Scilit][Green Version]
  34. Ruiz, A.Y.R.; Chandrasekaran, B. Implementation of a Sensor Fusion Based Robotic System Architecture for Motion Control using Human-Robot Interaction. In 2020 IEEE/SICE International Symposium on System Integration (SII); IEEE: New York, NY, USA, 2020; pp. 405–409. [Google Scholar]
  35. Pauwels, P.; de Koning, R.; Hendrikx, B.; Torta, E. Live semantic data from building digital twins for robot navigation: Overview of data transfer methods. Adv. Eng. Inform. 2023, 56, 101959. [Google Scholar] [CrossRef] [Scilit]
  36. Zhu, A.; Pauwels, P.; Torta, E.; Zhang, H.; de Vries, B. Data linking and interaction between BIM and robotic operating system (ROS) for flexible construction planning. Autom. Constr. 2024, 163, 105426. [Google Scholar] [CrossRef] [Scilit]
  37. Bahreini, F.; Nasrollahi, M.; Taher, A.; Hammad, A. Ontology for BIM-Based Robotic Navigation and Inspection Tasks. Buildings 2024, 14, 2274. [Google Scholar] [CrossRef] [Scilit]
  38. Oyediran, H.; Turner, W.; Kim, K.; Barrows, M. Integration of 4D BIM and Robot Task Planning: Creation and Flow of Construction-Related Information for Action-Level Simulation of Indoor Wall Frame Installation. J. Inf. Technol. Constr. 2025, 30, 352–374. [Google Scholar] [CrossRef] [Scilit]
  39. Skoury, L.; Leder, S.; Menges, A.; Wortmann, T. Digital twin architecture for the AEC Industry: A case study in collective robotic construction. In Proceedings of the ACM/IEEE 27th International Conference on Model Driven Engineering Languages and Systems; Association for Computing Machinery: New York, NY, USA, 2024; pp. 413–418. [Google Scholar] [CrossRef] [Scilit]
  40. Sharafat, A.; Tanoli, W.A. Digital Twin-Based Multi-Scale Framework for Seismic Integrity Assessment of Deep Underground Caverns. Sci. Rep. 2026, 16, 25599. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  41. Cho, H.S.; Latif, K.; Sharafat, A.; Seo, J. Multi-Modal Excavator Activity Recognition Using Two-Stream CNN-LSTM with RGB and Point Cloud Inputs. Appl. Sci. 2025, 15, 8505. [Google Scholar] [CrossRef] [Scilit]
  42. Kim, S.-K.; Russell, J.S. Framework for an intelligent earthwork system: Part I. System architecture. Autom. Constr. 2003, 12, 1–13. [Google Scholar]
  43. Liang, C.-J.; Kamat, V.R.; Menassa, C.C. Teaching robots to perform quasi-repetitive construction tasks through human demonstration. Autom. Constr. 2020, 120, 103370. [Google Scholar] [CrossRef] [Scilit]
  44. Borrmann, A.; Bruckmann, T.; Dörfler, K.; Hartmann, T.; Smarsly, K.; Brinkhoff, M.; Das, A.; Esser, S.; Hassan, M.; Jeziorek, C.; et al. The information backbone of robotized construction: Principles, procedures, and software architecture. In International Symposium on Automation and Robotics in Construction (ISARC) Proceedings, 43rd ISARC; IAARC: Singapore, 2026; Volume 2026, pp. 2353–2360. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  45. McClymonds, A.D.; Stephans, T.; Asadi, S.; Leicht, R.M.; Wagner, A.R. Evaluation of Parameters that Impact Data Collection for Robot Progress Detection of a Masonry Wall. J. Comput. Civ. Eng. 2026, 40, 04025150. [Google Scholar] [CrossRef] [Scilit]
  46. Messner, J.; Anumba, C.; Dubler, C.; Goodman, S.; Kreider, R.; Leicht, R.; Saluja, C.; Zikic, N. BIM Project Execution Planning Guide Version 3.0; Pennsylvania State University: State College, PA, USA, 2019; p. 143. [Google Scholar]
  47. Golparvar-Fard, M.; Peña-Mora, F.; Savarese, S. Automated Progress Monitoring Using Unordered Daily Construction Photographs and IFC-Based Building Information Models. J. Comput. Civ. Eng. 2015, 29, 04014025. [Google Scholar] [CrossRef] [Scilit]
  48. Stephans, T.; McClymonds, A.; Leicht, R.; Wagner, A.R. Automated material selection based on detected construction progress: 39th International Symposium on Automation and Robotics in Construction, ISARC 2022. In Proceedings of the 39th International Symposium on Automation and Robotics in Construction, ISARC 2022; International Association for Automation and Robotics in Construction (IAARC): Bogotá, Colombia, 2022; pp. 406–413. [Google Scholar] [CrossRef] [Scilit] [PubMed]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.