Abstract
Construction schedule compression requires balancing project-duration reduction against direct, indirect, and risk-related cost increases under uncertain activity performance. Many construction time–cost trade-off models still rely on deterministic durations or predefined execution modes, which limits their ability to represent practical activity-level crashing decisions under uncertainty. This study develops a stochastic risk-aware time–cost optimization framework for construction scheduling using bounded integer crash-day decision variables. Activity durations are represented using triangular distributions based on optimistic, most-likely, and pessimistic estimates, while Monte Carlo simulation is used to propagate uncertainty through the precedence network. Expected and Conditional Value-at-Risk-oriented indicators are integrated into risk-adjusted duration and cost measures, which are then combined through a nonlinear normalized objective function. A Hybrid Genetic Algorithm–Gray Wolf Optimizer is implemented to solve the resulting discrete stochastic optimization problem and is benchmarked against seven metaheuristic algorithms under identical evaluation conditions. The framework is demonstrated using a 30-activity construction project reconstructed from Microsoft Project data. The proposed Hybrid GA–GWO reduced the deterministic project duration from 895 to 699 working days and achieved the best descriptive objective performance across 30 independent runs. However, after Bonferroni correction, its differences from the Genetic Algorithm and MPGWO-DLL were not statistically significant, indicating that these methods remain competitive alternatives. Additional Monte Carlo convergence, tornado sensitivity, correlated-duration sensitivity, and computational-time analyses were added to evaluate the stability, parameter dependence, and practical applicability of the framework. The findings show that the proposed framework can support risk-aware construction schedule-crashing decisions by identifying activity-level acceleration plans while explicitly accounting for downside schedule and cost risk. Broader validation in larger and more diverse real-world projects remains necessary.
1. Introduction
Construction projects are frequently affected by competing pressures related to completion time, budget control, contractual obligations, and uncertainty in activity execution. Project delays may increase indirect costs, disrupt resource coordination, and expose contractors to liquidated damages; whereas, aggressive schedule compression often requires additional labor, equipment, subcontracting capacity, or overtime. Consequently, construction planners must determine which activities should be accelerated and how much crashing is economically justified without causing excessive cost escalation. This decision-making challenge is commonly formulated as a time–cost trade-off problem, in which project duration and total project cost are optimized under precedence and execution constraints [1,2,3].
Traditional time–cost trade-off models often represent activities using predefined execution modes, where each mode has a fixed duration and cost. Although this representation is mathematically convenient, it does not always reflect practical schedule crashing. In many real construction projects, a planner may reduce an activity by a specific number of days within an allowable crash limit rather than select from a small set of discrete execution alternatives. Integer crash-day decisions therefore provide a practical representation of activity-level schedule compression because they directly indicate how many days should be removed from each activity and how much additional crash cost is incurred [3,4].
Another limitation of many construction scheduling models is the assumption that activity durations are deterministic. In practice, construction durations are influenced by productivity variation, weather conditions, material delivery uncertainty, site restrictions, subcontractor coordination, and technical complexity. As a result, two crash plans with similar deterministic durations may have different risk profiles when uncertainty is considered. Stochastic scheduling approaches address this limitation by evaluating project performance over a distribution of possible outcomes rather than relying on a single estimated completion time [5,6].
Monte Carlo simulation is widely used for this purpose because it allows uncertain activity durations to be propagated through the project network to generate distributions of project completion time and total cost. In construction planning, this is especially useful when activity durations can be described using three-point estimates, such as optimistic, most-likely, and pessimistic values. Simulation-based assessment enables planners to examine not only expected project duration and cost, but also unfavorable scenarios associated with schedule overrun and cost escalation [5,7,8].
However, expected values alone may not be sufficient for risk-aware construction decision-making. A crash plan with an acceptable mean duration may still expose the project to severe upper-tail outcomes, such as unusually long completion times or high total costs. Conditional Value-at-Risk provides a useful downside-risk measure because it evaluates the severity of unfavorable outcomes beyond a selected confidence level. Incorporating CVaR-oriented indicators into construction time–cost optimization can therefore help discourage solutions that appear attractive on average but are vulnerable to adverse tail-risk behavior [9,10].
The complexity of stochastic time–cost optimization has encouraged the use of metaheuristic algorithms. Genetic Algorithms, Particle Swarm Optimization, Gray Wolf Optimizer, arithmetic-optimization-based methods, and hybrid metaheuristics have been applied to construction scheduling and engineering optimization problems because they can search large, nonlinear, and combinatorial solution spaces without requiring strict convexity assumptions [11,12,13,14]. Nevertheless, the performance of metaheuristic algorithms is problem-dependent. Therefore, fair comparison requires that competing algorithms be evaluated using the same project data, decision variables, uncertainty model, objective function, and statistical testing protocol.
Hybrid metaheuristics have received particular attention because they can combine complementary search behaviors. Genetic Algorithms are effective in maintaining population diversity through selection, crossover, and mutation; whereas, the Gray Wolf Optimizer uses leader-guided search to intensify the search around promising solutions. Combining these mechanisms can improve the balance between global exploration and local exploitation, which is important for discrete crash-day scheduling problems where near-optimal solutions may differ by small integer changes in only a few activities [3,13,15].
Based on these considerations, this study develops a stochastic risk-aware time–cost optimization framework for construction schedule crashing. The proposed model uses integer crash-day decision variables, where each activity can be accelerated by a bounded number of days according to its allowable crash limit. The cost model includes direct activity cost, crash cost per day, indirect project cost, and liquidated damages. Activity durations are modeled using triangular distributions, and Monte Carlo simulation is used to estimate stochastic project duration and cost outcomes. Expected and CVaR-oriented indicators are combined into risk-adjusted duration and cost measures, which are then integrated into a nonlinear normalized objective function.
To solve the resulting discrete stochastic optimization problem, this study proposes a Hybrid Genetic Algorithm–Gray Wolf Optimizer. The algorithm combines genetic selection, crossover, mutation, elite preservation, wolf-guided refinement, and local search around the best crash plan. Its performance is benchmarked against seven algorithms: Genetic Algorithm, Discrete Particle Swarm Optimization, Differential Evolution, Gray Wolf Optimizer, MPGWO-DLL, RAOA, and EA-PGWO. All algorithms are evaluated using identical stochastic simulation settings to ensure a fair comparison.
The framework is demonstrated and internally validated using a 30-activity construction project reconstructed from Microsoft Project data, where the imported precedence logic exactly reproduced the original Microsoft Project baseline duration. The original baseline duration is 895 days, and the revised baseline total cost is USD 13.9825 million. The optimized solutions are evaluated deterministically and stochastically, and algorithmic robustness is assessed over 30 independent runs using descriptive statistics, Friedman ranking, Wilcoxon signed-rank tests, and objective-value distribution analysis.
The main contribution of this study is the development and computational validation of an integrated stochastic risk-aware decision-support framework for construction time–cost trade-off analysis using practical integer crash-day decisions. Rather than presenting the Hybrid GA–GWO as a stand-alone algorithmic breakthrough, the study positions the method as part of a unified framework that combines bounded activity-level crashing, triangular duration uncertainty, Monte Carlo simulation, CVaR-oriented downside-risk evaluation, direct and indirect cost modeling, liquidated-damage assessment, and nonlinear normalized time–cost optimization. This formulation allows construction planners to identify not only whether a schedule should be accelerated, but also which activities should be crashed and by how many days. The framework is benchmarked using eight metaheuristic algorithms under identical data, uncertainty, objective-function, and statistical-testing conditions. To strengthen the reliability of the computational findings, the revised study further includes 30 independent runs, Friedman ranking, Wilcoxon signed-rank testing with Bonferroni correction, Monte Carlo convergence analysis, tornado parameter-sensitivity analysis, correlated-duration sensitivity analysis, and computational-time comparison. Accordingly, the contribution of the study lies in providing a reproducible and practically interpretable stochastic schedule-crashing framework, while acknowledging that broader validation on larger and more diverse project networks is required before generalizing the findings.
The remainder of this paper is organized as follows. Section 2 reviews construction time–cost optimization, stochastic scheduling, risk-aware evaluation, and metaheuristic methods. Section 3 presents the proposed stochastic crash-day optimization model and its objective function. Section 4 describes the Hybrid GA–GWO algorithm and the benchmark methods. Section 5 introduces the case-study data, experimental settings, parameter choices, and reproducibility details. Section 6 presents the deterministic and stochastic results, statistical comparison, sensitivity analyses, computational-time assessment, and practical implications. Section 7 discusses limitations and future research directions. Section 8 concludes the study.
2. Literature Review and Research Gap
2.1. Construction Time–Cost Trade-Off Optimization
The construction time–cost trade-off problem has been widely studied because schedule acceleration usually reduces project completion time while increasing direct execution cost. Classical time–cost models aim to identify an economical balance between activity-duration reduction and the additional resources needed for acceleration. Early studies used mathematical, heuristic, and evolutionary methods to solve this problem, with Genetic Algorithms becoming one of the most widely applied approaches in construction schedule compression [1,2]. Later studies extended the problem toward discrete activity alternatives, where each activity can be executed using different time–cost modes [3,4].
Recent reviews confirm that time–cost optimization remains an active topic in construction management. ElSahly et al. reviewed construction time–cost optimization models and classified the literature into exact methods, approximate methods, metaheuristics, and hybrid approaches, emphasizing the need for models that are computationally efficient and practically applicable [16]. More recent optimization studies have further extended the field by applying Particle Swarm Optimization, Rao algorithms, arithmetic optimization, hybrid multi-verse optimization, and other population-based approaches to construction time–cost decision problems [17,18,19,20]. These studies show that metaheuristic optimization remains useful for solving nonlinear, discrete, and large-search-space scheduling problems.
Although discrete mode selection is useful, it does not fully represent how schedule crashing is often implemented in practice. In many real projects, planners do not simply choose from a small set of fixed execution modes; instead, they decide how many days can be reduced from selected activities within practical and contractual limits. Integer crash-day decision variables therefore provide a more direct and interpretable representation of schedule compression because they indicate the exact number of days assigned to each activity. This improves the managerial usefulness of the optimization output and allows project teams to translate the results into activity-level acceleration actions.
2.2. Stochastic Scheduling and Risk-Aware Evaluation
A major limitation of deterministic time–cost trade-off models is the assumption that activity durations and project outcomes are fixed. In real construction environments, activity durations are affected by labor productivity, weather conditions, supply-chain delays, site restrictions, subcontractor coordination, and technical uncertainty. Therefore, a deterministic optimum may perform poorly when uncertainty is considered. Stochastic time–cost research has emphasized the need to evaluate construction schedules using uncertain duration and cost outcomes rather than relying only on single-point estimates [5,6].
Monte Carlo simulation is commonly used in construction risk analysis because it converts uncertain activity-level inputs into project-level distributions of duration and cost. This allows decision-makers to evaluate not only expected project outcomes, but also the probability and severity of unfavorable delay and cost scenarios. Feng et al. integrated simulation and Genetic Algorithms for stochastic time–cost trade-off analysis [5], while Yang proposed a distribution-free stochastic approach that considered correlation and stochastic dominance [6]. Sobieraj and Metelski further demonstrated the usefulness of Monte Carlo simulation and Time-at-Risk for construction schedule-risk assessment [21]. These studies support the use of simulation-based evaluation when construction schedules are exposed to uncertainty.
However, expected values alone may be insufficient for risk-aware decision-making. A crash plan with an acceptable mean duration may still expose the project to severe upper-tail delay or cost outcomes. Conditional Value-at-Risk provides a useful downside-risk measure because it evaluates unfavorable outcomes beyond a selected confidence level. Recent stochastic project-scheduling and time–cost–quality studies have shown that reliability, risk, and tail-performance indicators can improve the realism of construction planning decisions [21,22,23]. This motivates the use of CVaR-oriented risk-adjusted duration and cost measures in the present framework.
2.3. Metaheuristic and Hybrid Optimization Methods
The time–cost trade-off problem becomes computationally challenging when precedence constraints, crash limits, stochastic evaluations, nonlinear cost structures, and risk-adjusted objective functions are included. For this reason, metaheuristic algorithms are widely used because they can search large and nonlinear solution spaces without requiring convexity or differentiability assumptions. Genetic Algorithms, Particle Swarm Optimization, Differential Evolution, Gray Wolf Optimizer, Rao-type methods, arithmetic optimization, and hybrid models have all been applied to construction scheduling and engineering optimization problems [11,12,13,14,15,17,18,19,20].
Hybrid metaheuristics are especially relevant because they combine complementary search behaviors. Genetic Algorithms support population diversity through selection, crossover, mutation, and elitism, while Gray Wolf Optimizer uses leader-guided exploitation based on the alpha, beta, and delta solutions [14]. This makes GWO attractive for refining promising solutions, but standard GWO may suffer from premature convergence or limited diversity in discrete search spaces. Hybridization with GA operators can therefore improve the balance between exploration and exploitation, especially in integer crash-day scheduling problems where near-optimal solutions may differ by small activity-level adjustments.
Recent construction-management research also shows increasing interest in combining optimization algorithms with data-driven and artificial-intelligence models. Wang et al. proposed a VMD-ISO-BiGRU framework for construction safety accident forecasting, integrating variational mode decomposition, improved snake optimization, and bidirectional gated recurrent units to capture nonlinear and multiscale accident patterns [24]. Another recent ECAM study introduced a VMD-GWO-BiGRU framework for forecasting the architecture billings index, showing how Gray Wolf Optimizer can support parameter optimization in construction-related forecasting models [25]. Although these studies focus on forecasting rather than time–cost trade-off optimization, they confirm the growing role of hybrid optimization and intelligent decision-support methods in construction management.
Gray Wolf Optimizer has received particular attention because of its simple leader-guided mechanism, in which the best solutions guide the search process. This structure is attractive for construction scheduling because it can intensify the search around promising crash plans while maintaining population-based exploration [14]. However, standard GWO may still suffer from premature convergence or insufficient diversity in discrete problems. Hybridization with Genetic Algorithm operators can address this limitation by combining GA’s selection, crossover, and mutation mechanisms with GWO’s leader-guided refinement. This provides the methodological basis for developing the Hybrid GA–GWO algorithm in the present study.
As summarized in Table 1, previous studies have significantly advanced construction time–cost trade-off optimization through Genetic Algorithms, Particle Swarm Optimization, Differential Evolution, Rao algorithms, arithmetic optimization, hybrid metaheuristics, stochastic scheduling, and simulation-based risk analysis. However, most existing studies focus on only one or two parts of the broader problem. Some studies optimize deterministic time–cost alternatives, while others evaluate stochastic schedule risk without directly optimizing activity-level crash decisions. In addition, many discrete models rely on predefined execution modes rather than practical integer crash-day variables. Although Monte Carlo simulation and downside-risk measures have been used in project-risk research, their integration with CVaR-oriented construction crash optimization remains limited. Therefore, the present study addresses this gap by combining bounded integer crash-day decisions, triangular activity-duration uncertainty, Monte Carlo simulation, CVaR-oriented risk-adjusted indicators, a nonlinear normalized objective function, and a Hybrid GA–GWO algorithm benchmarked against seven metaheuristic methods under identical evaluation conditions.
Table 1.
Comparative review of selected studies on construction time–cost optimization, stochastic scheduling, risk-aware evaluation, and metaheuristic methods.
2.4. Research Gap and Positioning of the Present Study
The reviewed literature shows that construction time–cost optimization has advanced significantly, but several limitations remain. First, many studies represent activity acceleration through predefined execution modes rather than bounded integer crash-day decisions. This can reduce practical interpretability because construction planners often need to know exactly how many days should be removed from specific activities. Second, although stochastic scheduling has been widely studied, many models still rely mainly on expected values, percentiles, or reliability indicators rather than integrating downside tail-risk measures directly into the optimization objective. Third, Monte Carlo simulation is frequently used for project-risk analysis, but its integration with CVaR-oriented activity-level crash optimization remains limited. Fourth, many algorithmic studies compare a small set of methods or evaluate algorithms under inconsistent assumptions, making it difficult to determine whether performance differences arise from the algorithm or from differences in model formulation and evaluation settings.
To address these gaps, this study develops a stochastic risk-aware construction time–cost optimization framework based on bounded integer crash-day variables. Activity durations are modeled using triangular distributions, and Monte Carlo simulation is used to estimate project duration and total cost distributions. Expected and CVaR-oriented indicators are combined into risk-adjusted time and cost measures, which are integrated into a nonlinear normalized objective function. A Hybrid GA–GWO algorithm is implemented to solve the resulting discrete stochastic optimization problem and is benchmarked against seven alternative metaheuristics under identical project data, crash-day bounds, uncertainty assumptions, objective-function settings, and statistical-testing procedures. The contribution is therefore positioned as an integrated and reproducible decision-support framework for risk-aware construction schedule crashing, rather than as a claim of universal algorithmic superiority.
3. Stochastic Risk-Aware Crash-Day Optimization Model
This section presents the stochastic risk-aware construction time–cost optimization model used in this study. The model determines the number of crash days assigned to each activity while considering project precedence constraints, direct activity costs, crash costs, indirect costs, liquidated damages, stochastic activity durations, and downside risk. Unlike fixed-mode time–cost trade-off models, the proposed formulation uses integer crash-day decision variables, allowing each activity to be partially accelerated within its allowable crash limit. The novelty of the formulation lies in the integration of four elements within one construction schedule-crashing framework: bounded integer crash-day decisions, stochastic triangular activity-duration simulation, CVaR-oriented downside-risk evaluation, and nonlinear normalized time–cost optimization. The standard project-network precedence relationships are used only to propagate activity durations through the schedule; the main modeling contribution is the way candidate crash-day vectors are evaluated under uncertainty and converted into risk-adjusted decision-support indicators.
To improve clarity and reproducibility, Figure 1 summarizes the overall computational structure of the proposed framework. The process begins with the Microsoft Project (2016) schedule and activity-level crash data, reconstructs the precedence network, evaluates candidate integer crash-day vectors, propagates stochastic activity durations through Monte Carlo simulation, computes expected and CVaR-oriented performance indicators, and finally assigns a nonlinear normalized objective value to each candidate crash plan.
Figure 1.
Overall structure of the proposed stochastic risk-aware crash-day optimization framework.
3.1. Project Network and Crash-Day Decision Variables
The construction project is represented as a precedence-constrained activity network:
where is the set of project activities, and is the set of precedence relationships between activities. Each activity is characterized by its baseline most-likely duration, optimistic duration, pessimistic duration, base direct cost, crash cost per day, and maximum allowable crash duration.
G = (N,E),
Let the integer decision variable represent the number of crash days assigned to activity . The crash-day decision is bounded by:
where is the maximum allowable number of crash days for activity . Therefore, a complete construction crashing plan is represented by the vector:
A value of means that no acceleration is applied to activity , while means that the activity is crashed to its maximum allowable limit.
After crashing, the deterministic most-likely duration of activity is calculated as:
where is the baseline most-likely duration of activity . The project duration is then obtained by propagating the crashed activity durations through the precedence network. For a Finish-to-Start relationship between predecessor activity and successor activity , the precedence condition is:
where is the start time of activity , is the finish time of activity , and is the time lag between the two activities. Since:
the Finish-to-Start constraint becomes:
For a Start-to-Start relationship, the precedence condition is:
The deterministic project duration for a crash plan x is defined as the maximum finish time among all activities:
This ensures that the optimized project duration respects the activity network and all precedence constraints.
3.2. Cost Model
The total project cost includes three components: direct activity cost, indirect project cost, and liquidated damages. The direct cost of each activity increases according to the number of crash days assigned to it. Therefore, the direct cost of activity is:
where is the baseline direct cost of activity , and is the crash cost per day. The total direct cost is:
Indirect cost depends on the total project duration. If is the indirect cost per project day, the indirect cost is:
Liquidated damages are applied only when the project duration exceeds the contractual duration threshold . Let denote the liquidated damages per delayed day. The liquidated damages cost is:
The total deterministic project cost is therefore:
Or:
This cost structure captures the main economic consequences of crashing. Increasing raises the direct crash cost, but it may reduce indirect project cost by shortening the schedule. If the optimized duration remains below the contractual duration threshold, liquidated damages are avoided.
3.3. Stochastic Duration and Monte Carlo Simulation
Construction activity durations are uncertain because they are affected by productivity variation, weather conditions, material delivery, site restrictions, coordination delays, and other project-specific factors. Therefore, this study models activity durations using triangular distributions based on three-point estimates: optimistic, most-likely, and pessimistic durations. This approach is suitable when detailed historical probability distributions are unavailable but expert-based duration ranges can be estimated [5,6].
For activity , let:
represent the optimistic, most-likely, and pessimistic duration estimates, respectively. After applying crash days, the triangular distribution parameters become:
For Monte Carlo replication , the stochastic duration of activity is sampled as:
The sampled activity durations are then propagated through the project precedence network to obtain the simulated project duration:
The corresponding stochastic total cost for replication is:
After Monte Carlo replications, the model generates two outcome distributions:
And:
3.4. Risk-Adjusted Duration and Cost Measures
The expected stochastic project duration is calculated as:
Similarly, the expected stochastic project cost is:
Although expected values are useful, they do not fully capture severe adverse outcomes. For this reason, the model incorporates Conditional Value-at-Risk-oriented measures to represent upper-tail duration and cost risk. At confidence level , the CVaR-oriented project duration is calculated from the worst upper-tail duration outcomes:
where is the -quantile of the simulated project duration distribution.
Similarly, the CVaR-oriented project cost is:
where is the -quantile of the simulated project cost distribution. CVaR-oriented measures are useful because they evaluate the severity of unfavorable tail outcomes rather than only average project performance [9,10].
The risk-adjusted project duration is then defined as
where is the duration risk-aversion coefficient. Likewise, the risk-adjusted project cost is:
where is the cost risk-aversion coefficient. Higher values of and give greater importance to unfavorable tail outcomes, while lower values place more emphasis on expected performance.
3.5. Nonlinear Normalized Objective Function
To combine project duration and total cost into a single objective function, the risk-adjusted indicators are normalized relative to the no-crash stochastic baseline. Let represent the no-crash baseline plan. The normalized risk-adjusted duration is:
and the normalized risk-adjusted cost is:
The proposed nonlinear objective function is formulated as:
where and are the weights assigned to risk-adjusted duration and cost, respectively; and are nonlinear penalty exponents; and is the interaction penalty coefficient. The first two terms penalize high normalized duration and cost values, while the interaction term discourages solutions that simultaneously produce high duration and high cost.
The complete optimization problem is therefore:
subject to:
and all project precedence constraints. The objective seeks the best risk-aware balance between schedule compression and cost escalation. A feasible solution is therefore not selected only because it is the fastest or cheapest, but because it provides the best compromise between risk-adjusted duration, risk-adjusted cost, and downside exposure.
4. Optimization Methodology and Algorithmic Framework
This section describes the computational optimization procedure used to solve the stochastic risk-aware crash-day model formulated in Section 3. The Hybrid GA–GWO is used as the proposed solver, while seven benchmark algorithms are implemented to provide a consistent comparative evaluation. The purpose of the algorithmic comparison is not to claim universal superiority of one metaheuristic across all construction projects, but to examine how different search mechanisms perform when applied to the same integer crash-day decision space, stochastic simulation engine, risk-adjusted objective function, and case-study data. Therefore, all algorithms are evaluated under identical crash bounds, uncertainty assumptions, Monte Carlo settings, objective-function parameters, and final reporting procedures.
4.1. Overall Optimization Workflow
Each candidate solution represents a complete construction schedule-crashing plan:
where is the number of crash days assigned to activity . The decision variables are integer-valued and bounded by the maximum allowable crash days of each activity:
For each candidate crash plan, the optimization workflow follows the same evaluation steps. First, the candidate vector is repaired to satisfy the integer crash-day bounds. Second, the deterministic crashed activity durations are calculated. Third, the project schedule is propagated through the precedence network. Fourth, direct cost, indirect cost, and liquidated damages are computed. Fifth, Monte Carlo simulation is used to generate stochastic duration and cost outcomes. Sixth, expected and CVaR-oriented risk-adjusted duration and cost measures are calculated. Finally, the nonlinear normalized objective value is computed and used as the fitness value.
This common evaluation workflow ensures that all candidate crash plans are judged using the same deterministic scheduling logic, stochastic duration simulation, CVaR-oriented risk measures, and nonlinear normalized objective function. Consequently, differences among algorithms reflect differences in search behavior rather than differences in model formulation or evaluation criteria.
4.2. Integer Encoding and Feasibility Repair
All algorithms use the same integer crash-day encoding. Since some metaheuristic update rules generate continuous values, each candidate vector is converted into a feasible integer crash plan using a repair operator. For a generated value , the repaired crash-day value is calculated as:
This repair procedure guarantees that every candidate solution satisfies the activity-specific crash limits. The same repair rule is applied after crossover, mutation, particle updates, differential mutation, gray-wolf movement, arithmetic updates, and hybrid candidate generation. This common representation is important because it ensures that differences in algorithmic performance are caused by search behavior rather than by different feasibility-handling mechanisms.
This repair operator is especially important because several benchmark algorithms naturally generate continuous-valued updates; whereas, the construction decision required by the proposed framework is an integer number of crash days for each activity.
4.3. Proposed Hybrid GA–GWO Algorithm
The proposed solver is a Hybrid Genetic Algorithm–Gray Wolf Optimizer designed for the bounded integer crash-day search space. The hybrid structure combines GA-based population diversification with GWO-based leader-guided refinement. Genetic Algorithms have been widely used in construction time–cost optimization because they can handle discrete search spaces through selection, crossover, mutation, and elitism [1,2,3]. Gray Wolf Optimizer uses leader-guided search based on the alpha, beta, and delta solutions, which can help intensify the search around promising candidate solutions [14]. In this study, the purpose of hybridizing GA and GWO is to improve the balance between exploration and exploitation for the proposed stochastic crash-day formulation. However, the empirical superiority of the method is interpreted cautiously and is evaluated through single-run results, 30 independent runs, non-parametric statistical testing, and Bonferroni-adjusted pairwise comparisons.
At the beginning of the algorithm, an initial population of feasible crash-day vectors is randomly generated. Each candidate is evaluated using the stochastic objective function defined in Section 3. The best three candidates are identified as , , and , and they guide the refinement of the search population. At each iteration, the algorithm preserves elite solutions, selects parent solutions through tournament selection, generates offspring using uniform crossover, applies adaptive mutation, and then refines selected offspring using GWO-based leader guidance. Periodic local search is also performed around the current best solution to improve fine-scale integer crash-day adjustments.
The GWO-based guidance stage follows the leader-directed mechanism of the original Gray Wolf Optimizer [14]. For a candidate solution , three leader-guided proposal vectors are generated using the alpha, beta, and delta solutions:
The GWO proposal is then calculated as:
where and are coefficient vectors controlling the search direction and exploration intensity. In the proposed Hybrid GA–GWO, this GWO proposal is not used alone. Instead, it is blended with the offspring generated by the GA operators. For an offspring vector , the hybrid candidate is obtained as:
where is a blending coefficient that controls the contribution of the genetic offspring and the GWO-guided proposal. The resulting vector is rounded and repaired to satisfy all integer crash-day bounds.
To further improve exploitation, the algorithm performs local search around the current best solution. A neighboring candidate is generated by modifying one selected activity by one crash day:
where
The candidate is accepted only if it improves the stochastic objective value and satisfies the feasibility constraints. This local search is useful because near-optimal crash plans may differ by only small integer changes in a limited number of activities.
The proposed Hybrid GA–GWO can be summarized as presented in Algorithm 1.
| Algorithm 1. Hybrid GA–GWO solver for the proposed stochastic crash-day optimization framework. |
|
|
|
|
|
|
|
|
|
|
|
|
|
4.4. Benchmark Algorithms
Seven benchmark algorithms are implemented to evaluate the proposed solver under a consistent computational setting. The benchmark set includes classical evolutionary, swarm-based, wolf-based, and advanced hybrid/metaheuristic methods: Genetic Algorithm, Discrete Particle Swarm Optimization, Differential Evolution, Gray Wolf Optimizer, MPGWO-DLL, RAOA, and EA-PGWO. These algorithms were selected because they represent different search mechanisms commonly used in nonlinear and discrete optimization, including selection–mutation search, swarm memory, differential variation, leader-guided search, multi-population refinement, arithmetic search, and hybrid evolutionary–wolf-based guidance [11,12,13,14,15,17,18,19,20].
The Genetic Algorithm is used as a classical evolutionary baseline because it naturally supports chromosome-based search and has been widely applied to construction time–cost optimization [1,2,3]. Discrete Particle Swarm Optimization is included as a swarm-intelligence comparator, with continuous particle positions rounded and repaired to satisfy integer crash-day bounds. The original Particle Swarm Optimization was introduced by Kennedy and Eberhart [26]. Differential Evolution is included as a variation-driven evolutionary comparator, with trial vectors converted into feasible integer crash-day solutions after mutation and crossover. The original Differential Evolution algorithm was introduced by Storn and Price [27]. Gray Wolf Optimizer is included as the base wolf-based method because it provides the leader-guided search mechanism used in the proposed hybrid solver [14].
Three advanced comparators are also included to strengthen the benchmark set. MPGWO-DLL represents a multi-population GWO-family method with local learning. RAOA is included because arithmetic-optimization-based and repulsion-enhanced mechanisms have recently been applied to construction time–cost optimization [20]. EA-PGWO is included as an evolutionary and particle-guided GWO comparator. Including these methods provides a stronger evaluation than comparing the proposed solver only with basic algorithms.
The inclusion of EA-PGWO and MPGWO-DLL is also supported by recent cross-domain optimization research, where hybrid Gray Wolf and evolutionary schemes were applied to non-convex energy-efficiency optimization in dense 5G device-to-device networks. Although that application differs from construction scheduling, it provides methodological support for using evolutionary–wolf-based hybridization, population-based global exploration, and local refinement in complex constrained optimization problems [28].
All benchmark algorithms solve the same stochastic crash-day optimization problem. They use the same project data, activity-specific crash bounds, integer repair operator, Monte Carlo simulation procedure, CVaR-oriented risk-adjusted indicators, and nonlinear normalized objective function. Therefore, the benchmark comparison evaluates solver behavior under the proposed framework rather than comparing different mathematical models. Model-level sensitivity and additional validation analyses are reported separately in the Section 6.
Table 2 summarizes the algorithms implemented in the present study and their role in the comparative analysis.
Table 2.
Optimization algorithms implemented in the present study.
4.5. Fairness of the Comparative Framework
To ensure a fair comparison, all algorithms are evaluated using the same project dataset, crash-day bounds, stochastic duration model, Monte Carlo simulation settings, objective function, and final evaluation procedure. Each algorithm searches the same solution space and minimizes the same nonlinear risk-adjusted objective value. Therefore, the comparison reflects differences in algorithmic search behavior rather than differences in problem formulation or evaluation assumptions.
For each algorithm, the following outputs are recorded: best objective value, optimized crash-day vector, deterministic project duration, deterministic total project cost, mean stochastic duration, risk-adjusted duration, mean stochastic cost, risk-adjusted cost, and convergence history. In addition, each algorithm is executed over 30 independent runs to evaluate robustness. The resulting objective values are later analyzed using descriptive statistics, Friedman ranking, Wilcoxon signed-rank testing, and objective-value distribution analysis.
This methodological design provides a consistent computational basis for comparing conventional, advanced, and hybrid metaheuristic algorithms for stochastic construction schedule crashing.
4.6. Interpretation of Algorithmic Comparison
Because metaheuristic performance is problem-dependent, the algorithmic comparison is interpreted using both descriptive and statistical evidence. Single-run results are used to illustrate representative crash plans and convergence behavior, while 30 independent runs are used to assess robustness. Friedman ranking is used to compare the overall ordering of the algorithms, and pairwise Wilcoxon signed-rank tests with Bonferroni correction are used to determine whether the proposed solver differs significantly from each benchmark method. Accordingly, the revised manuscript avoids claiming universal dominance of the Hybrid GA–GWO. Instead, the results are interpreted in terms of descriptive performance, statistical significance, and practical decision-support value under the adopted case-study and parameter settings.
To support practical applicability, computational execution time is also recorded for each algorithm and reported in the Section 6. This allows the quality of the obtained solutions to be interpreted together with the computational effort required to obtain them.
5. Case Study and Experimental Settings
This section presents the case-study project, input data, cost assumptions, stochastic simulation settings, objective-function parameters, algorithmic settings, computational environment, and statistical evaluation protocol used to test the proposed framework. The purpose of the case study is to demonstrate and internally validate the proposed stochastic risk-aware crash-day optimization procedure using a realistic precedence-constrained construction schedule. The implementation was developed in MATLAB R2024b, and all scheduling, simulation, optimization, statistical testing, and plotting procedures were manually coded to ensure transparency and reproducibility. The additional validation analyses requested during peer review, including Monte Carlo convergence, tornado parameter sensitivity, correlated-duration sensitivity, and computational-time assessment, are reported in the Section 6.
5.1. Case-Study Project Description
The proposed framework was tested using a building-construction project schedule exported from Microsoft Project. The activity list represents a multi-stage building project that includes site mobilization, mass excavation, shoring and bracing, piling and deep foundation works, underground utilities, grade beams and slab, multi-level superstructure activities, roofing, exterior glass walls, fire sprinkler works, plumbing, electrical works, HVAC, elevator installation, interior framing, drywall, MEP trim, ceiling, flooring, cabinetry, painting, doors, lobby finishes, site paving, system testing, and final cleaning. This activity structure reflects a realistic building-construction sequence from enabling works and structural construction to MEP, architectural finishes, commissioning, and handover. The figure-generation code also confirms these activity labels, including L1–L20 superstructure, MEP, elevator, finishes, testing, and final clean activities.
The original Microsoft Project export contained 32 task rows, including two summary tasks and 30 executable construction activities. Only executable activities were retained in the optimization model. The predecessor relationships were extracted from the Microsoft Project file and reconstructed in MATLAB. The final network contained 35 precedence links, including mainly Finish-to-Start and Start-to-Start relationships with possible lags. Before applying optimization, the MATLAB scheduling engine was validated against the original Microsoft Project baseline. The reconstructed no-crash schedule reproduced the original baseline duration of 895 working days, confirming that the imported durations and precedence logic were correctly represented before optimization.
The case study was selected because it contains the main elements required to evaluate the proposed stochastic crash-day optimization framework: a precedence-constrained activity network, activity-level crash limits, direct activity costs, crash cost per day, indirect project cost, contractual duration threshold, and optimistic, most-likely, and pessimistic duration estimates. Therefore, the case study provides an internally validated demonstration instance for testing the feasibility and comparative performance of the proposed framework. However, because the validation is based on one real project instance, the results should be interpreted as evidence of feasibility and internal validity rather than universal generalizability. Broader external validation using larger and more diverse construction projects is identified as a future research direction.
Table 3 is the summery of case study project dataset that it is available fully in the Supplementary File S1.
Table 3.
Summary of the case-study project dataset.
5.2. Input Dataset and Transparency
The input dataset includes activity identifiers, activity names, baseline most-likely durations, optimistic and pessimistic duration estimates, baseline direct activity costs, maximum allowable crash days, crash cost per day, and predecessor relationships. These inputs define the decision space, stochastic duration model, cost model, and precedence constraints used by all optimization algorithms. The MATLAB implementation imports the Microsoft Project task, resource, and assignment CSV files and then applies the updated cost-crash-risk dataset before running the deterministic and stochastic evaluations. The code explicitly checks that the executable activity IDs match the expected sequence and verifies the consistency between imported durations and the revised most-likely durations before optimization.
To improve transparency without disclosing the full proprietary project file, the manuscript reports the key reproducibility information needed to understand the computational experiment, including the number of imported task rows, number of executable activities, number of precedence links, baseline duration, cost parameters, crash-cost range, stochastic duration assumptions, algorithmic settings, and statistical-testing protocol. The original Microsoft Project file and full activity-level dataset are not publicly shared because they contain project-specific scheduling and cost information. However, the main assumptions, model equations, aggregated case-study characteristics, parameter settings, and all reported optimization results are provided in the manuscript.
5.3. Cost and Crash-Data Settings
The project schedule was supplemented with activity-level cost and crash data. For each executable activity, the dataset included the baseline direct cost, maximum allowable crash days, crash cost per day, optimistic duration, most-likely duration, and pessimistic duration. The updated most-likely durations were checked against the imported Microsoft Project durations, and the maximum consistency error was zero. This ensured that the stochastic duration model was aligned with the original schedule.
In addition to activity-level direct and crash costs, the model included project-level economic parameters. The indirect project cost was calculated as a daily cost multiplied by the project duration. Liquidated damages were applied only when the simulated or deterministic project duration exceeded the contractual duration threshold. The adopted project-level cost parameters are shown in Table 4.
Table 4.
Project-level economic parameters.
Because the no-crash baseline duration was equal to the contractual duration threshold, no liquidated damages were incurred in the baseline case. Therefore, the revised baseline total cost was USD 13,982,500, consisting of USD 11,745,000 direct cost and USD 2,237,500 indirect cost.
The cost parameters represent the economic consequences of acceleration and delay in the case-study schedule. Direct activity cost is increased when crash days are assigned to an activity, while indirect cost is proportional to total project duration. Liquidated damages are activated only when simulated or deterministic project duration exceeds the contractual duration threshold. In the present case, the contractual duration threshold was set equal to the original 895-day project baseline, so the no-crash deterministic baseline does not incur liquidated damages. These parameters are case-study-specific and are used to demonstrate the decision-support capability of the framework rather than to define universal construction cost values.
5.4. Stochastic Simulation Settings
Activity-duration uncertainty was represented using triangular distributions. This distribution was selected because the available project information consisted of three-point estimates: optimistic, most-likely, and pessimistic durations. For each candidate crash plan, the selected number of crash days was subtracted from the three duration estimates of each activity, and Monte Carlo simulation was then used to generate stochastic activity durations. These sampled durations were propagated through the precedence network to obtain simulated project duration and total project cost outcomes. The MATLAB code implements this by sampling triangular activity durations after crash-day reduction and propagating them through the reconstructed project network.
A CVaR confidence level of 0.90 was used to represent upper-tail schedule and cost risk. The duration and cost risk-aversion coefficients were both set to 0.50, giving equal importance to expected performance and unfavorable tail outcomes. During optimization, 150 Monte Carlo replications were used for fitness evaluation to balance computational cost and stochastic accuracy. After optimization, the best solution obtained by each algorithm was re-evaluated using 1000 Monte Carlo replications to obtain more stable final reporting values. A separate Monte Carlo convergence analysis using 150, 500, 1000, and 5000 replications was added in the Section 6 to verify the stability of the final stochastic evaluation.
Table 5 presents stochastic simulation settings used as the simulation parameters for the study case.
Table 5.
Stochastic simulation settings.
5.5. Objective-Function Settings
All algorithms minimized the nonlinear normalized objective function defined in Section 3. The objective combines normalized risk-adjusted project duration and normalized risk-adjusted project cost. Equal weights were assigned to time and cost in the baseline scenario to represent a balanced decision-maker preference in which schedule compression and cost control are treated with the same importance. The time and cost exponents were both set to 2.00 to penalize large deviations more strongly than small deviations. The interaction coefficient was set to 0.25 to discourage solutions that simultaneously produce high normalized duration and high normalized cost.
These baseline values were not intended to represent universal parameter settings for all construction projects. Instead, they define a balanced reference scenario for evaluating the proposed framework. To address parameter dependence, a tornado sensitivity analysis was added in the Section 6. The sensitivity analysis varies the CVaR confidence level, risk-aversion coefficient, time–cost weights, and interaction coefficient around the baseline values to examine whether the reported results are overly dependent on the selected parameters.
Table 6 presents the objective function parameter settings used in the simulation.
Table 6.
Objective-function parameter settings.
These settings give balanced importance to schedule compression and cost control. The quadratic penalty terms discourage excessive worsening of either duration or cost, while the interaction term penalizes solutions with simultaneously poor time and cost performance.
5.6. Algorithmic Parameter Settings
Eight optimization algorithms were evaluated: Genetic Algorithm, Discrete Particle Swarm Optimization, Differential Evolution, Gray Wolf Optimizer, Hybrid GA–GWO, MPGWO-DLL, RAOA, and EA-PGWO. To maintain a fair comparison, all algorithms used the same project dataset, crash-day bounds, stochastic simulation settings, objective-function parameters, and final evaluation procedure. Similar population sizes and iteration limits were used to keep the computational budget broadly comparable across algorithms. Each generated candidate solution was repaired before evaluation to satisfy the activity-specific integer crash-day bounds.
The parameter values were selected to provide a common computational budget rather than to perform exhaustive hyperparameter tuning for each algorithm. This choice avoids favoring one algorithm through extensive tuning while allowing the study to compare search behavior under a consistent experimental setting. The main algorithmic settings are summarized in Table 7.
Table 7.
Algorithmic parameter settings.
The selected parameters were kept consistent across experiments to support fair comparison. The proposed Hybrid GA–GWO used the same general population and iteration scale as the benchmark algorithms, while adding wolf-guided refinement and local search to improve exploitation in the integer crash-day space.
5.7. Computational Environment and Runtime Recording
All simulations were implemented in MATLAB R2024b without relying on specialized optimization or statistical toolboxes. The algorithms, repair operators, stochastic evaluation functions, non-parametric tests, and plotting routines were manually implemented to maintain full control over the computational workflow. For practical interpretability, execution time was recorded for each algorithm using MATLAB timing functions. The runtime values are reported in the Section 6 together with the solution-quality indicators so that algorithmic performance can be interpreted in relation to computational effort.
Table 8 illustrates the computational environment and the hardware used for the simulation.
Table 8.
Computational environment and runtime-recording settings.
The best crash-day vector produced by each algorithm was evaluated in two ways. First, a deterministic evaluation was performed using the most-likely crashed activity durations. This produced the deterministic project duration, deterministic direct cost, deterministic indirect cost, deterministic liquidated damages, and deterministic total project cost.
Second, a stochastic evaluation was performed using Monte Carlo simulation and triangular activity-duration uncertainty. This evaluation generated the mean project duration, standard deviation of duration, P90 duration, CVaR90 duration, risk-adjusted duration, mean project cost, standard deviation of cost, P90 cost, CVaR90 cost, risk-adjusted cost, and final nonlinear objective value.
Using both deterministic and stochastic evaluation allows the optimized crash plans to be interpreted from two perspectives. The deterministic analysis shows the planned schedule compression under most-likely durations, while the stochastic analysis shows how each plan performs under duration uncertainty and downside-risk exposure.
5.8. Statistical Robustness Protocol
To assess algorithmic robustness, each optimization algorithm was executed over 30 independent runs. Each run used a different random seed, and the final nonlinear objective value was recorded. The 30-run results were then analyzed using descriptive statistics and non-parametric statistical tests.
The Friedman test was used to compare the overall ranking of the algorithms across the 30 runs. Pairwise Wilcoxon signed-rank tests were then applied to compare the proposed Hybrid GA–GWO with the benchmark methods. Bonferroni adjustment was used to reduce the risk of false positive conclusions caused by multiple comparisons.
The statistical tests were used to avoid overinterpreting small descriptive differences among stochastic metaheuristic algorithms. Because multiple pairwise comparisons were performed, Bonferroni correction was applied to reduce the probability of false positive conclusions. Therefore, algorithmic superiority is interpreted only when supported by both descriptive performance and corrected statistical evidence. When corrected pairwise differences are not significant, the corresponding algorithms are described as statistically comparable rather than inferior.
6. Results and Discussion
6.1. Baseline Validation and Deterministic Single-Run Comparison
The first stage of the analysis verified whether the imported construction schedule was correctly reconstructed in MATLAB. The no-crash baseline schedule reproduced the original Microsoft Project duration of 895 working days, confirming that the activity durations and precedence relationships were correctly represented before optimization. The baseline total project cost was USD 13.9825 million, consisting of USD 11.745 million in direct activity cost and USD 2.2375 million in indirect project cost. Since the baseline duration was equal to the contractual duration threshold, no liquidated damages were incurred.
To evaluate the deterministic impact of schedule crashing, the best single-run crash plan generated by each algorithm was evaluated using the most-likely activity durations. Figure 2 compares the deterministic project duration and total project cost for the no-crash baseline and the eight optimized solutions.
Figure 2.
Deterministic comparison of the single-run best crash plans: (a) project duration; (b) total project cost.
As shown in Figure 2a, all optimization algorithms substantially reduced the deterministic project duration compared with the no-crash baseline. The proposed Hybrid GA–GWO achieved the shortest deterministic duration of 699 days, representing a reduction of 196 days, or approximately 21.9%, relative to the baseline duration of 895 days. D-PSO, GWO, and EA-PGWO also produced short deterministic schedules, with durations between 701 and 702 days, while Differential Evolution produced the longest optimized deterministic duration of 710 days.
Figure 2b shows the cost effect of schedule compression. All optimized solutions increased the deterministic total project cost compared with the no-crash baseline because crashing requires additional direct acceleration cost. The proposed Hybrid GA–GWO produced a deterministic total cost of approximately USD 15.14 million. This cost was higher than the baseline but remained competitive compared with the other optimized solutions. Therefore, the deterministic results show that all optimized crash plans reduce the baseline duration, but this reduction is achieved through additional acceleration cost. The Hybrid GA–GWO solution produced the shortest deterministic schedule, reducing the project duration from 895 to 699 working days. This represents a reduction of 196 days, or approximately 21.9%, relative to the no-crash baseline. However, the optimized total cost increased compared with the baseline because crashing adds direct acceleration cost. Therefore, the deterministic comparison should be interpreted as evidence of schedule-compression capability rather than simultaneous minimization of both duration and cost.
6.2. Single-Run Stochastic Algorithm Comparison
Although deterministic evaluation provides a useful planning view, it does not capture uncertainty in construction activity durations. Therefore, the best solution obtained by each algorithm was also evaluated using Monte Carlo simulation, CVaR-oriented risk measures, and the nonlinear normalized objective function. Table 9 presents the representative single-run stochastic comparison of the eight optimization algorithms.
Table 9.
Statistical evaluation protocol.
Table 10 presents the representative single-run stochastic comparison of the eight algorithms. The Hybrid GA–GWO achieved the lowest nonlinear objective value in this representative run, indicating the best combined risk-adjusted time–cost compromise under the adopted objective-function settings. However, the differences among the leading methods were relatively small. Therefore, this single-run result is used mainly to illustrate representative behavior and crash-plan interpretation, while the more reliable algorithmic comparison is based on the 30 independent runs reported later.
Table 10.
Representative single-run stochastic comparison of the eight optimization algorithms.
To visualize the ranking of the algorithms more clearly, Figure 2 presents the final nonlinear stochastic objective value obtained by each method in the representative single-run experiment.
Figure 3 confirms the ranking reported in Table 10. The proposed Hybrid GA–GWO achieved the lowest final objective value, followed closely by GA, EA-PGWO, MPGWO-DLL, and GWO. The weaker performance of D-PSO and DE indicates that aggressive duration reduction or cost reduction alone is not sufficient under the proposed nonlinear risk-aware objective. The results suggest that the hybridization of genetic operators with gray-wolf leader guidance improved the balance between exploration and exploitation in the stochastic crash-day search space.
Figure 3.
Final single-run nonlinear stochastic objective-value comparison.
6.3. Convergence Behavior
After evaluating the final single-run outcomes, the convergence behavior of the algorithms was analyzed to understand how quickly and consistently each method improved the nonlinear stochastic objective value. Figure 4 shows the best objective value obtained by each algorithm over 70 iterations or generations.
Figure 4.
Convergence comparison of the eight algorithms.
Figure 4 shows the convergence behavior of the eight algorithms using the best nonlinear objective value across iterations. The convergence curves indicate how rapidly each method improves its candidate crash plans under the same stochastic evaluation procedure. The Hybrid GA–GWO reached a competitive final objective value while maintaining stable convergence behavior. Nevertheless, convergence curves are interpreted descriptively because metaheuristic trajectories depend on random initialization, population dynamics, and stochastic fitness evaluation. For this reason, the final algorithmic conclusions are based on both convergence behavior and 30-run statistical robustness.
6.4. Risk-Adjusted Time–Cost Trade-Off
The risk-adjusted time–cost trade-off plot provides a component-level interpretation of the scalar objective value. Algorithms located toward the lower-left region provide a more favorable combination of risk-adjusted duration and risk-adjusted cost. Some algorithms produced shorter risk-adjusted durations but higher risk-adjusted costs, while others reduced cost at the expense of longer duration. This confirms that the proposed objective function does not select the fastest or cheapest solution alone, but evaluates the balance between time, cost, and downside risk as shown in Figure 5.
Figure 5.
Risk-adjusted stochastic time–cost trade-off among the optimization algorithms.
6.5. Selected Activity-Level Crash-Day Plan
The previous subsections focused on project-level performance. However, a useful construction optimization model should also provide interpretable activity-level decisions.
Figure 6 presents the selected crash-day vector of the Hybrid GA–GWO best plan. The result shows that the optimized solution does not simply crash every activity to its maximum allowable limit. Instead, crash days are assigned selectively to activities where acceleration contributes more effectively to the overall risk-adjusted objective. This is important from a construction-management perspective because the output is not only an abstract objective value; it provides activity-level decisions that indicate which activities should be accelerated and by how many days. Such information can support planning discussions related to resource allocation, subcontractor coordination, overtime planning, and cost-risk trade-off evaluation.
Figure 6.
Selected activity-level crash-day plan of the final Hybrid GA–GWO solution.
6.6. Stochastic Duration and Cost Distribution Analysis
The stochastic distribution comparison between the no-crash baseline and the Hybrid GA–GWO crash plan illustrates the effect of optimization under duration uncertainty. The optimized crash plan shifts the project-duration distribution substantially to the left, indicating shorter expected completion time and lower upper-tail duration exposure. In contrast, the cost distribution shifts upward because schedule acceleration requires additional direct crash expenditure. This confirms the central time–cost trade-off in the proposed framework: the optimized plan reduces schedule duration and downside duration risk, but it does so by accepting a controlled increase in total project cost. Therefore, the framework should be interpreted as a risk-aware schedule-compression decision-support tool, not as a pure cost-minimization model.
Figure 7a shows that the proposed Hybrid GA–GWO shifted the simulated project-duration distribution substantially to the left compared with the no-crash baseline. This indicates that the optimized crash plan reduced not only the deterministic project duration but also the stochastic completion-time distribution under uncertainty. The no-crash baseline remained centered around a much longer duration range, while the Hybrid GA–GWO distribution was concentrated around shorter simulated completion times.
Figure 7.
Stochastic distribution comparison between the no-crash baseline and the proposed Hybrid GA–GWO: (a) simulated project duration; (b) simulated total project cost.
Figure 7b shows the corresponding cost effect. The Hybrid GA–GWO cost distribution shifted to the right compared with the no-crash baseline because the optimized plan introduced additional direct crash costs. This confirms the expected trade-off between time reduction and cost escalation. Therefore, the proposed method should be interpreted as a risk-aware schedule-compression approach rather than a cost-minimization-only strategy. The main benefit of the method is its ability to achieve substantial schedule reduction while controlling the increase in risk-adjusted cost.
6.7. Thirty-Run Descriptive Robustness Analysis
To evaluate robustness beyond a representative single run, each algorithm was executed over 30 independent runs using different random seeds. The final nonlinear objective value was recorded for each run, and descriptive statistics were calculated. The Hybrid GA–GWO achieved the best mean objective value and showed strong worst-case robustness across the 30 runs. However, the distributions of the leading algorithms partially overlap, especially for Hybrid GA–GWO, GA, and MPGWO-DLL. This indicates that the proposed method is descriptively strong, but its superiority should be interpreted together with the statistical tests reported in the following subsections.
Table 11 shows that the proposed Hybrid GA–GWO achieved the lowest mean objective value across the 30 independent runs. It also achieved the lowest median objective value and the lowest worst-case objective value among all tested algorithms. This indicates that the proposed method was not only effective in the representative single-run experiment but also robust across repeated stochastic trials. MPGWO-DLL and the Genetic Algorithm formed the closest competing group, with mean objective values of 1.092570 and 1.092641, respectively. In contrast, Discrete PSO produced the highest mean objective value and the largest standard deviation, indicating weaker stability for this stochastic integer crash-day optimization problem.
Table 11.
Objective-value summary statistics across 30 independent runs.
To visualize the distribution of objective values across the 30 independent runs, Figure 8 presents the boxplot and individual run-level objective values for all algorithms.
Figure 8.
Objective-value distribution across 30 independent runs.
Figure 8 confirms the descriptive results reported in Table 11. The proposed Hybrid GA–GWO, MPGWO-DLL, and Genetic Algorithm produced the strongest objective-value distributions, with relatively low median values and compact interquartile ranges. Although Gray Wolf Optimizer achieved the lowest single best objective value in one run, its average and median performance were weaker than those of the proposed Hybrid GA–GWO. This shows why robustness analysis is necessary: the best isolated result does not necessarily indicate the most reliable algorithm. Discrete PSO exhibited the widest spread and the highest median objective value, confirming that it was the least stable method in the 30-run comparison.
6.8. Friedman Ranking Analysis
After the descriptive robustness analysis, the Friedman ranking test was applied to compare the algorithms across the 30 independent runs. Since the objective function is minimized, lower objective values received better ranks in each run. Table 12 presents the sum rank and mean rank obtained by each algorithm.
Table 12.
Friedman ranking results across 30 independent runs.
Table 12 shows that the proposed Hybrid GA–GWO achieved the best overall Friedman mean rank of 1.8500. MPGWO-DLL ranked second with a mean rank of 2.6000, followed very closely by the Genetic Algorithm with a mean rank of 2.6167. The ranking confirms that the proposed method was the most consistently competitive algorithm across the 30 independent runs. Discrete PSO ranked last, which is consistent with its high mean objective value and wide distribution shown in Table 12 and Figure 8.
The Friedman ranking analysis confirms that the Hybrid GA–GWO achieved the best overall mean rank across the 30 independent runs. MPGWO-DLL and GA ranked second and third, respectively, with close mean ranks. This result supports the descriptive robustness of the proposed solver. However, the closeness of the leading ranks also suggests that post hoc pairwise testing is necessary before making claims about statistical superiority.
6.9. Wilcoxon Signed-Rank Pairwise Analysis
Because the Friedman test indicated statistically significant differences among the algorithms, pairwise Wilcoxon signed-rank tests were conducted to compare the proposed Hybrid GA–GWO with each benchmark algorithm. Bonferroni adjustment was applied to control the family-wise error rate caused by multiple comparisons. Table 13 summarizes the key pairwise comparisons involving the proposed method.
Table 13.
Wilcoxon signed-rank pairwise comparisons between the proposed Hybrid GA–GWO and benchmark algorithms.
The Wilcoxon signed-rank analysis provides a more cautious interpretation than the descriptive rankings alone. After Bonferroni correction, the Hybrid GA–GWO significantly outperformed D-PSO, Differential Evolution, Gray Wolf Optimizer, RAOA, and EA-PGWO. However, its differences from the Genetic Algorithm and MPGWO-DLL were not statistically significant after correction. Therefore, the revised interpretation is that Hybrid GA–GWO achieved the best descriptive performance and best Friedman rank under the adopted experimental setting, but GA and MPGWO-DLL remain statistically competitive alternatives. Accordingly, the results support the effectiveness of the proposed framework and the competitiveness of the proposed solver, but they do not justify a claim of universal algorithmic dominance.
6.10. Computational-Time Comparison
Computational time was recorded for each optimizer using MATLAB tic and toc during the single-run experiment. The reported values represent the optimization runtime required by each algorithm under the same project data, crash-day bounds, stochastic simulation settings, and objective-function parameters. Figure 9 and Table 14 report the single-run runtime together with the final objective value and risk-adjusted performance indicators, while Figure 9 provides a visual comparison of the runtime values. The total single-run computational pipeline required approximately 31.31 min, including the execution of all eight optimization algorithms and related reporting steps.
Figure 9.
Single-run computational-time comparison across the eight optimization algorithms.
Table 14.
Single-run computational time and final risk-adjusted performance of the optimization algorithms.
Runtime was measured in minutes using MATLAB tic and toc under the same case-study data, stochastic simulation settings, crash-day bounds, and objective-function parameters.
The computational-time results show that the standard algorithms, including Gray Wolf Optimizer, Genetic Algorithm, Discrete PSO, and Differential Evolution, required approximately 2.86–2.91 min in the single-run experiment. The proposed Hybrid GA–GWO required 3.07 min, which is only slightly higher than the fastest standard methods while producing the best single-run objective value. MPGWO-DLL required 3.87 min, while EA-PGWO and RAOA required longer runtimes of 5.85 and 6.85 min, respectively. These results indicate that the proposed Hybrid GA–GWO provides a favorable balance between solution quality and computational effort for the tested case study. However, because runtime depends on hardware, implementation details, and project size, the values should be interpreted as case-study-specific computational evidence rather than universal runtime performance.
6.11. Validation and Sensitivity Analyses
6.11.1. Monte Carlo Convergence Analysis
To verify the stability of the stochastic evaluation, a Monte Carlo convergence analysis was conducted for the final Hybrid GA–GWO crash plan. The same crash plan was re-evaluated using 150, 500, 1000, and 5000 simulation replications. Table 15 and Figure 10 show that the objective value becomes stable as the number of replications increases. The difference between the 1000-replication and 5000-replication evaluations was only approximately 0.003%, indicating that the final stochastic reporting values are stable. Therefore, 150 replications were used during optimization to reduce computational burden, while 1000 replications were used for final reporting and the 5000-replication case was used as a convergence reference.
Table 15.
Monte Carlo convergence results for the final Hybrid GA–GWO crash plan.
Figure 10.
Monte Carlo convergence of the final Hybrid GA–GWO stochastic objective value: (a) objective values; (b) relative difference from the 5000-run reference.
The convergence results show that increasing the number of simulations from 1000 to 5000 produces a negligible change in the final objective value. This confirms that the 1000-replication final evaluation is sufficiently stable for reporting. The 150-replication setting is therefore justified as a computationally efficient choice for repeated fitness evaluation during the optimization search.
6.11.2. Tornado Parameter-Sensitivity Analysis
A tornado sensitivity analysis was conducted to evaluate whether the objective value is overly dependent on the selected parameter settings. The analysis varied the CVaR confidence level, risk-aversion coefficient, time–cost weights, and interaction coefficient around the baseline scenario while holding the remaining settings fixed. The tornado chart ranks the parameters according to their influence on the final objective value. The results show that the optimized crash plan remains within a narrow objective-value range across the tested parameter changes. This indicates that the reported result is not caused by one isolated parameter choice. At the same time, the analysis confirms that different decision-maker preferences can shift the emphasis between schedule compression and cost control. Figure 11 visualizes the tested scenarios in the normalized risk-adjusted time–cost space, while Table 16 summarizes the one-at-a-time sensitivity results around the baseline parameter setting. The analysis shows that changes in the CVaR confidence level and risk-aversion coefficient produce only small variations in the final objective value. Changes in the time–cost weights and interaction coefficient affect the scalar objective more directly because they modify the preference structure of the objective function itself.
Figure 11.
Objective-parameter sensitivity of the Hybrid GA–GWO crash plan.
Table 16.
One-at-a-time objective-parameter sensitivity summary for the final Hybrid GA–GWO crash plan.
The sensitivity results indicate that the CVaR confidence level and risk-aversion coefficient do not substantially change the evaluated objective value around the baseline setting. The time–cost weight variation changes the objective value because the optimized crash plan has a normalized duration below 1.0 and a normalized cost above 1.0; therefore, assigning greater weight to time favors the accelerated plan, while assigning greater weight to cost penalizes it. The interaction coefficient also changes the objective value by design because it controls the penalty applied to the joint time–cost term. These findings show that the selected baseline parameters represent a balanced reference scenario, while alternative parameter settings can be used to reflect different managerial preferences.
6.11.3. Correlated Activity-Duration Sensitivity Analysis
A correlated-duration sensitivity analysis was performed to examine whether the independence assumption in activity-duration simulation may underestimate project-level tail risk. Three equi-correlation scenarios were tested: ρ = 0.00, ρ = 0.20, and ρ = 0.40. As expected, the risk-adjusted duration increased as correlation increased, from 844.73 days under independent activity durations to 867.43 days at ρ = 0.20 and 880.71 days at ρ = 0.40. This confirms that positive activity-duration correlation increases upper-tail schedule risk. However, the objective value remained relatively stable, changing from 1.0931 to 1.0933 and 1.0947 across the three scenarios. These results show that the framework remains applicable under correlated-duration assumptions, while also confirming that the independence assumption should be interpreted cautiously.
Table 17 and Figure 12 show that the Hybrid GA–GWO risk-adjusted duration increases as positive correlation is introduced among activity durations. This confirms that correlated activity delays increase upper-tail schedule risk and should be considered in future extensions of the framework.
Table 17.
Correlated activity-duration sensitivity results for the Hybrid GA–GWO crash plan.
Figure 12.
Sensitivity to equicorrelation among activity durations: (a) risk-adjusted project duration; (b) nonlinear objective value and risk-adjusted project cost.
The results confirm that positive activity-duration correlation increases downside schedule risk. The Hybrid GA–GWO risk-adjusted duration increased from 844.73 days under the independent-duration case to 867.43 days at ρ = 0.20 and 880.71 days at ρ = 0.40. However, the final objective value remained relatively stable, increasing only from 1.093070 to 1.094738. This suggests that the proposed framework remains applicable under correlated-duration scenarios, although the independence assumption should be interpreted cautiously because it can underestimate upper-tail schedule exposure.
6.12. Practical and Managerial Implications
The proposed framework provides several practical implications for construction planning. First, it produces activity-level crash-day decisions rather than only project-level time–cost curves. This allows planners to identify which activities should be accelerated and how much acceleration is recommended. Second, the framework evaluates crash plans under stochastic duration uncertainty, allowing decision-makers to compare not only expected project duration and cost, but also unfavorable upper-tail outcomes. Third, the inclusion of CVaR-oriented measures supports risk-aware decision-making by penalizing solutions that appear attractive on average but expose the project to severe delay or cost outcomes. Fourth, the use of direct cost, indirect cost, and liquidated damages allows the framework to represent the economic consequences of both acceleration and delay. Therefore, the approach can support negotiation and planning decisions related to overtime, subcontractor mobilization, resource allocation, and contractual delay-risk management.
6.13. Overall Discussion of Results
Overall, the results demonstrate that the proposed stochastic risk-aware framework can generate interpretable and practically useful crash plans for construction schedule compression. The deterministic results show that substantial duration reduction can be achieved, while the stochastic results show how this compression affects expected performance and downside risk. The 30-run analysis confirms that Hybrid GA–GWO achieved the best descriptive performance and best Friedman rank under the adopted experimental setting. However, the Wilcoxon signed-rank tests with Bonferroni correction show that GA and MPGWO-DLL remain statistically competitive. Therefore, the main value of the study lies not only in the proposed solver, but in the integrated decision-support framework that combines integer crash-day decisions, stochastic triangular duration simulation, CVaR-oriented risk adjustment, nonlinear time–cost optimization, and reproducible statistical evaluation.
7. Limitations and Future Work
Although the proposed framework provides a practical stochastic risk-aware approach for construction schedule crashing, the results should be interpreted within the scope of the adopted modeling assumptions, case-study data, and computational setting. The framework was demonstrated using a 30-activity construction project reconstructed from Microsoft Project data. This case study was suitable for internal validation because it included a precedence-constrained activity network, activity-level crash limits, direct activity costs, crash costs, indirect project cost, contractual duration threshold, and stochastic duration estimates. The reconstructed schedule also reproduced the original 895-working-day Microsoft Project baseline, confirming that the scheduling logic was correctly represented before optimization. However, because only one project was used, the results should be interpreted as evidence of feasibility and internal validity rather than broad external generalizability. Larger and more diverse construction projects are required to confirm the scalability and robustness of the framework across different project types, network structures, activity densities, and contractual conditions.
7.1. Limitations
The first limitation concerns the case-study scope. The project contains 30 executable activities, which is sufficient to demonstrate the proposed integer crash-day formulation and stochastic evaluation procedure, but it does not fully represent the complexity of very large construction projects with hundreds or thousands of activities. Larger projects may increase the dimensionality of the crash-day decision vector, the number of precedence relationships, and the computational burden of repeated Monte Carlo evaluations. Therefore, the computational-time results reported in this study should be interpreted as case-study-specific rather than universal runtime evidence.
The second limitation concerns the representation of activity-duration uncertainty. The model uses triangular distributions based on optimistic, most-likely, and pessimistic duration estimates. This choice is practical when detailed historical activity-duration data are unavailable, but it remains an approximation of real construction uncertainty. Other distributions, such as beta, lognormal, empirical, or data-driven distributions, may be more suitable when historical productivity or activity-performance data are available. In addition, the main simulation assumes activity-duration independence, although the added correlated-duration sensitivity analysis shows that positive correlation can increase upper-tail schedule risk. Therefore, future applications should account for activity correlation when reliable information about shared risk factors is available.
The third limitation relates to parameter dependence. The baseline model uses a CVaR confidence level of 0.90, equal duration and cost risk-aversion coefficients, balanced time–cost weights, squared objective-function penalties, and a positive interaction coefficient. These settings define a balanced decision-maker preference, but they do not represent all possible managerial priorities. The added sensitivity analysis reduces this concern by showing how the final crash plan behaves under alternative parameter settings. Nevertheless, different projects or stakeholders may require different weights, risk-aversion levels, or objective-function structures.
The fourth limitation concerns algorithmic generalization. The Hybrid GA–GWO achieved the best descriptive performance and best single-run objective value in the adopted case study, but the statistical results show that GA and MPGWO-DLL remain competitive alternatives after Bonferroni correction. Therefore, the findings should not be interpreted as proof that Hybrid GA–GWO is universally superior across all construction scheduling problems. Instead, the proposed solver should be viewed as a competitive search method within the broader stochastic risk-aware crash-day decision-support framework.
The fifth limitation concerns the cost model. The current formulation includes direct activity cost, crash cost per day, indirect project cost, and liquidated damages. This structure captures the main economic consequences of schedule acceleration and delay, but it does not explicitly model resource availability, labor crew constraints, subcontractor capacity, cash flow, material procurement uncertainty, quality trade-offs, safety impacts, or carbon emissions. These factors may influence whether a theoretically optimal crash plan is fully feasible in practical project execution.
7.2. Future Research Directions
Future research can extend the proposed framework in several directions. First, the model should be tested on multiple real construction projects with different sizes, project types, network complexities, crash-cost structures, resource constraints, and contractual conditions. This would allow stronger evaluation of scalability, external validity, and algorithmic robustness. Benchmarking the framework on larger projects would also help determine how computational time increases with the number of activities, precedence links, Monte Carlo replications, and candidate solutions.
Second, future studies can extend the stochastic duration model by using historical project data, productivity records, weather data, supply-chain records, and subcontractor performance data to estimate empirical or data-driven duration distributions. This would reduce dependence on expert-based three-point estimates. Future work can also include correlated uncertainty models, where activities affected by common causes, such as weather, labor shortage, or material delay, are simulated using correlated duration structures.
Third, the current scalar objective function can be expanded into a true multi-objective optimization model. Instead of combining risk-adjusted duration and cost into one normalized objective value, future research can generate Pareto fronts that allow decision-makers to compare alternative trade-offs among project duration, total cost, downside risk, quality, safety, resource utilization, carbon emissions, and supply-chain disruption. This would be especially useful when different stakeholders assign different priorities to time, cost, and risk.
Fourth, resource allocation and resource leveling can be integrated into the crash-day optimization model. The current formulation determines how many days should be crashed for each activity, but it does not explicitly assign labor crews, equipment, overtime, or subcontractor resources. Adding resource constraints would improve practical feasibility because some crash plans may require more labor, equipment, or subcontractor capacity than is available on site.
Fifth, future work can connect the proposed framework with Building Information Modeling, digital-twin platforms, and real-time construction monitoring systems. Such integration would allow the optimization model to update activity durations, costs, and risk parameters as new site information becomes available. This would support adaptive crash-plan recommendations during project execution rather than limiting the model to pre-construction planning. The current manuscript already identifies BIM and digital-twin integration as a promising direction for real-time schedule updating and adaptive recommendations.
Finally, future research can investigate additional solver designs and hybridization strategies. The proposed Hybrid GA–GWO can be compared with decomposition-based methods, surrogate-assisted optimization, adaptive sampling, reinforcement learning, and machine-learning-assisted metaheuristics. Such methods may reduce computational burden when Monte Carlo simulation is expensive, especially for large project networks.
8. Conclusions
This study developed a stochastic risk-aware construction time–cost optimization framework for schedule crashing using bounded integer activity-level crash-day decisions. The framework was designed to support practical construction planning by allowing each activity to be partially accelerated within its allowable crash limit, rather than relying only on predefined execution modes. The model integrates direct activity cost, crash cost, indirect project cost, liquidated damages, triangular activity-duration uncertainty, Monte Carlo simulation, CVaR-oriented downside-risk indicators, and a nonlinear normalized time–cost objective function. In this way, the proposed framework evaluates not only the expected duration and cost of a crash plan, but also its exposure to unfavorable upper-tail schedule and cost outcomes.
The framework was implemented using a construction project schedule reconstructed from Microsoft Project data. The reconstructed no-crash schedule reproduced the original 895-working-day baseline, confirming that the precedence logic and activity-duration data were correctly represented before optimization. In the deterministic single-run comparison, the proposed Hybrid GA–GWO solution reduced the project duration from 895 to 699 working days, corresponding to a reduction of 196 days, or approximately 21.9%. However, this reduction was achieved through additional crash cost, confirming that the optimized solution should be interpreted as a schedule-compression strategy with controlled cost escalation rather than as a pure cost-minimization solution.
The stochastic results further showed that the optimized crash plan shifted the project-duration distribution toward shorter completion times compared with the no-crash baseline. This indicates that the acceleration benefit remained visible under duration uncertainty. The activity-level crash-day output also demonstrated that the model does not simply crash all activities to their maximum limits. Instead, it identifies targeted acceleration decisions that contribute more effectively to improving the risk-adjusted time–cost objective within the project precedence network.
The algorithmic comparison showed that the proposed Hybrid GA–GWO achieved the best descriptive performance and the best Friedman rank across the 30 independent runs. It also achieved the best single-run objective value with a moderate computational time of 3.07 min. Nevertheless, the statistical interpretation must remain cautious. After Bonferroni correction, the Hybrid GA–GWO significantly outperformed D-PSO, Differential Evolution, Gray Wolf Optimizer, RAOA, and EA-PGWO, but its differences from the Genetic Algorithm and MPGWO-DLL were not statistically significant. Therefore, the results support the competitiveness and practical usefulness of the Hybrid GA–GWO solver under the adopted case-study conditions, but they do not justify a claim of universal superiority over all alternative algorithms.
Additional validation analyses strengthened the reliability of the revised framework. The Monte Carlo convergence analysis showed that the final stochastic evaluation was stable when the number of simulations was increased. The objective-parameter sensitivity analysis clarified how CVaR confidence level, risk-aversion settings, time–cost weights, and interaction penalty influence the final objective value. The correlated-duration sensitivity analysis showed that positive activity-duration correlation increases upper-tail schedule risk, confirming that the independence assumption should be interpreted carefully. Together, these analyses improve the credibility of the computational results and provide a clearer basis for managerial interpretation.
Overall, the main contribution of this study is not only the use of a Hybrid GA–GWO algorithm, but the development of an integrated stochastic risk-aware decision-support framework for construction schedule crashing. The framework provides project managers with interpretable activity-level crash decisions while accounting for time, cost, and downside risk. The findings demonstrate the feasibility and internal validity of the proposed approach on the tested construction project. Broader validation on larger and more diverse projects remains necessary before generalizing the results across the construction industry.
Supplementary Materials
The following supporting information can be downloaded at: https://www.mdpi.com/article/10.3390/buildings16153091/s1, Table S1: Case study project dataset.
Author Contributions
Conceptualization, M.A.V. and S.P.; methodology, M.A.V. and A.E.Ö.; software, M.A.V. and S.P.; validation, M.A.V.; investigation, M.A.V.; resources, A.E.Ö.; data curation, M.A.V.; writing—original draft preparation, M.A.V.; writing—review and editing, S.P.; visualization, S.P.; supervision, A.E.Ö.; project administration, A.E.Ö. All authors have read and agreed to the published version of the manuscript.
Funding
This research received no external funding.
Data Availability Statement
The activity-level dataset required to reproduce the case-study optimization is provided as Supplementary Material S1. Additional inquiries can be directed to the corresponding author.
Conflicts of Interest
The authors declare no conflicts of interest.
Abbreviations
The following abbreviations are used in this manuscript:
| BIM | Building Information Modeling |
| CSV | Comma-Separated Values |
| CVaR | Conditional Value-at-Risk |
| D-PSO | Discrete Particle Swarm Optimization |
| DE | Differential Evolution |
| DLL | Derivative Local Learning |
| EA-PGWO | Evolutionary Algorithm-Enhanced Particle-Guided Gray Wolf Optimizer |
| FS | Finish-to-Start |
| GA | Genetic Algorithm |
| GWO | Gray Wolf Optimizer |
| Hybrid GA–GWO | Hybrid Genetic Algorithm–Gray Wolf Optimizer |
| MC | Monte Carlo |
| MPGWO-DLL | Memetic Particle-Guided Gray Wolf Optimizer with Derivative Local Learning |
| P90 | 90th Percentile |
| PSO | Particle Swarm Optimization |
| RAOA | Repulsive Arithmetic Optimization Algorithm |
| SS | Start-to-Start |
| TaR | Time-at-Risk |
| TCTO | Time–Cost Trade-Off |
| USD | United States Dollar |
| VaR | Value-at-Risk |
References
- Feng, C.W.; Liu, L.; Burns, S.A. Using genetic algorithms to solve construction time-cost trade-off problems. J. Comput. Civ. Eng. 1997, 11, 184–189. [Google Scholar] [CrossRef] [Scilit]
- Hegazy, T. Optimization of construction time-cost trade-off analysis using genetic algorithms. Can. J. Civ. Eng. 1999, 26, 685–697. [Google Scholar] [CrossRef]
- Sonmez, R.; Bettemir, O.H. A hybrid genetic algorithm for the discrete time-cost trade-off problem. Expert Syst. Appl. 2012, 39, 11428–11434. [Google Scholar] [CrossRef] [Scilit]
- Aminbakhsh, S.; Sonmez, R. Pareto front particle swarm optimizer for discrete time-cost trade-off problem. J. Comput. Civ. Eng. 2017, 31, 04016040. [Google Scholar] [CrossRef] [Scilit]
- Feng, C.W.; Liu, L.; Burns, S.A. Stochastic construction time-cost trade-off analysis. J. Comput. Civ. Eng. 2000, 14, 117–126. [Google Scholar] [CrossRef] [Scilit]
- Yang, I.T. Stochastic time-cost tradeoff analysis: A distribution-free approach with focus on correlation and stochastic dominance. Autom. Constr. 2011, 20, 916–926. [Google Scholar] [CrossRef] [Scilit]
- Chen, L.; Lu, Q.; Li, S.; He, W.; Yang, J. Bayesian Monte Carlo simulation-driven approach for construction schedule risk inference. J. Manag. Eng. 2021, 37, 04020113. [Google Scholar] [CrossRef] [Scilit]
- Hussein, M.; Eltoukhy, A.E.E.; Darko, A.; Eltawil, A. Simulation-optimization for the planning of off-site construction projects: A comparative study of recent swarm intelligence metaheuristics. Sustainability 2021, 13, 13551. [Google Scholar] [CrossRef] [Scilit]
- Zhang, Z.; Chronopoulos, M.; Dimitrova, D.S.; Andiappan, V. Risk assessment and optimal scheduling of serial projects. OR Spectr. 2024, 46, 709–736. [Google Scholar] [CrossRef] [Scilit]
- Fu, F.; Liu, S.; Yang, J.; Liu, M. Robustifying the resource-constrained project scheduling against uncertain durations. Expert Syst. Appl. 2024, 238, 122002. [Google Scholar] [CrossRef] [Scilit]
- Elbeltagi, E.; Hegazy, T.; Grierson, D. Comparison among five evolutionary-based optimization algorithms. Adv. Eng. Inform. 2005, 19, 43–53. [Google Scholar] [CrossRef] [Scilit]
- Toğan, V.; Eirgash, M.A. Time-cost trade-off optimization of construction projects using teaching-learning-based optimization. KSCE J. Civ. Eng. 2019, 23, 10–20. [Google Scholar] [CrossRef] [Scilit]
- Toğan, V.; Berberoğlu, N.; Dede, T. Optimizing of discrete time-cost in construction projects using new adaptive weight formulations. KSCE J. Civ. Eng. 2022, 26, 511–521. [Google Scholar] [CrossRef] [Scilit]
- Mirjalili, S.; Mirjalili, S.M.; Lewis, A. Grey Wolf Optimizer. Adv. Eng. Softw. 2014, 69, 46–61. [Google Scholar] [CrossRef] [Scilit]
- Boussaïd, I.; Lepagnot, J.; Siarry, P. A survey on optimization metaheuristics. Inf. Sci. 2013, 237, 82–117. [Google Scholar] [CrossRef] [Scilit]
- ElSahly, O.M.; Ahmed, S.; Abdelfatah, A. Systematic review of the time-cost optimization models in construction management. Sustainability 2023, 15, 5578. [Google Scholar] [CrossRef] [Scilit]
- Son, P.V.H.; Nguyen Dang, N.T. Solving large-scale discrete time-cost trade-off problem using hybrid multi-verse optimizer model. Sci. Rep. 2023, 13, 1987. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Yılmaz, M.; Dede, T. Multi-objective time–cost trade-off optimization for the construction scheduling with Rao algorithms. Structures 2023, 48, 798–808. [Google Scholar] [CrossRef] [Scilit]
- Türkoğlu, H.; Arditi, D.; Polat, G. Augmented time–cost trade-off optimization using particle swarm optimization. J. Constr. Eng. Manag. 2024, 150, 04024031. [Google Scholar] [CrossRef] [Scilit]
- Sulub, A.S.; Eirgash, M.A.; Toğan, V. An arithmetic optimization algorithm based on opposition jumping rate for time cost trade-off optimization problems. Asian J. Civ. Eng. 2025, 26, 867–886. [Google Scholar] [CrossRef] [Scilit]
- Sobieraj, J.; Metelski, D. Project risk in the context of construction schedules—Combined Monte Carlo simulation and Time at Risk (TaR) approach: Insights from the Fort Bema Housing Estate Complex. Appl. Sci. 2022, 12, 1044. [Google Scholar] [CrossRef] [Scilit]
- Wang, J.; Wang, Z.; Liu, H. Multi-objective stochastic time-cost-quality optimization for construction projects based on the reliability theory. KSCE J. Civ. Eng. 2023, 27, 4545–4556. [Google Scholar] [CrossRef] [Scilit]
- Tran, D.H.; Long, L.D. Project scheduling with time, cost and risk trade-off using adaptive multiple objective differential evolution. Eng. Constr. Archit. Manag. 2018, 25, 623–638. [Google Scholar] [CrossRef] [Scilit]
- Wang, J.; Qu, Z.; Zhang, R.; Skitmore, M. Predicting construction safety accidents using VMD-BiGRU architecture with improved snake optimization algorithm. Eng. Constr. Archit. Manag. 2026, ahead of print. [Google Scholar] [CrossRef] [Scilit]
- Wang, J.; Qu, Z.; Zhang, R.; Chileshe, N.; Ji, Z. Forecasting the architecture billings index using a variational mode decomposition–bidirectional gated recurrent unit framework based on Grey Wolf Optimizer. Eng. Constr. Archit. Manag. 2026, ahead of print. [Google Scholar] [CrossRef] [Scilit]
- Kennedy, J.; Eberhart, R. Particle swarm optimization. In Proceedings of ICNN’95—International Conference on Neural Networks, Perth, WA, Australia, 27 November–1 December 1995; IEEE: Piscataway, NJ, USA, 1995; Volume 4, pp. 1942–1948. [Google Scholar] [CrossRef] [Scilit]
- Storn, R.; Price, K. Differential evolution—A simple and efficient heuristic for global optimization over continuous spaces. J. Glob. Optim. 1997, 11, 341–359. [Google Scholar] [CrossRef] [Scilit]
- El Mohamad, A.; Toycan, M.; Öztoprak, H. Energy-aware 5G device-to-device optimization using hybrid Grey Wolf and evolutionary schemes. Electronics 2026, 15, 1448. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.