Reducing Carbon Emissions Through Rolling Scheduling Optimization of a City-Level Virtual Power Plant Considering External Power Dominance and Multi-Resource Flexibility Aggregation: A Case Study of Guangzhou, China

,
,
,
,
and
1
Guangzhou Power Supply Bureau, Guangdong Power Grid Co., Ltd., Guangzhou 510620, China
2
Guangzhou Institute of Energy Conversion, Chinese Academy of Sciences, Guangzhou 510640, China
*
Author to whom correspondence should be addressed.

Abstract

Import-dependent megacities must decarbonize while accommodating distributed photovoltaics (PV) under constrained local-generation and interchange boundaries. This study develops a full-year, hourly, 48 h rolling mixed-integer linear programming model for coordinated city-level scheduling in Guangzhou, China. The VPP-controlled portfolio includes distributed PV, grid- and user-side battery energy storage systems, demand response, and aggregated electric vehicles, whereas local generators and inter-regional imports are represented as system-operator coordination variables. After correcting the energy balances of flexible resources and recalibrating the hourly interchange boundary, the baseline scheduled-import share is 68.68%, only 0.64 percentage points above the measured schedule. Across four policy-defined PV anchors, combined annual operating-and-carbon cost decreases from CNY 75.01 to 65.50 billion, carbon intensity declines from 467.9 to 412.2 g CO2/kWh, and import share falls from 68.68% to 63.92%. A dense 0–12 GW sweep at 0.5 GW intervals reveals a continuous response: curtailment first exceeds 1 MWh at 4.0 GW but remains only 0.006%, providing no evidence of a unique breakpoint. A conventional time-of-use tariff reduces import share by 0.58 percentage points while increasing carbon intensity by 1.25 g CO2/kWh. These results are conditional on the deterministic supply construction, calibrated interchange boundary, adopted emission factors, and operating-cost scope.

1. Introduction

Under China’s carbon peaking and carbon neutrality goals, the construction of new power systems is shifting the locus of flexibility from large centralized units toward aggregated distributed resources. In March 2025, the National Development and Reform Commission and the National Energy Administration jointly issued the Guiding Opinions on Accelerating the Development of Virtual Power Plants, which establish virtual power plants (VPPs) as new market entities that aggregate distributed generation, adjustable loads, and energy storage, and set national VPP regulation-capability targets of more than 20 GW by 2027 and 50 GW by 2030 [1]. For load-center megacities, however, the value and the operating logic of a VPP differ fundamentally from those in generation-rich regions: the supply structure is dominated by an inter-regional import boundary governed by dispatch plans and long-term contracts, the local thermal fleet is small and tightly constrained by security requirements, and rooftop photovoltaics (PV) are expanding at double-digit rates inside the city. How much a city-level VPP can actually substitute imported power, reduce carbon intensity, and support the evening peak in such a setting is an open quantitative question.
Guangzhou is an archetype of this class of city. In 2025, its gross domestic product reached CNY 3203.9 billion with a tertiary-industry share of 74.95% [2]; whole-society electricity consumption was 132.3 TWh, and the system peak load reached 25.11 GW. Roughly two-thirds of the electricity serving the city is imported across the boundary of the China Southern Power Grid, while local generation consists mainly of gas-fired and coal-fired units subject to minimum-output security constraints. Distributed PV is the fastest-growing local source: installed capacity reached 2975.5 MW by January 2025 after 77.8% year-on-year growth in 2024 [3]. The municipal action plan for high-quality distributed-PV development sets cumulative capacity targets of more than 5 GW by 2027 and 8 GW by 2030 [3], while a rooftop-resource assessment identifies a technical ceiling of 14,860 MW and estimates grid absorption capability for newly added distributed PV of 20,689 MW by 2027 and 24,153 MW by 2030, with local reverse-flow risks flagged for generation-concentrated districts such as Zengcheng and Panyu [4]. These planning milestones provide natural, policy-relevant anchors for scenario design—anchors that are rarely used in the VPP scheduling literature.
A substantial body of work has developed optimization methods for VPP scheduling. Comprehensive reviews trace the evolution from concept validation to hierarchical aggregation and market participation [5,6]. Classic formulations established bidding and medium-term dispatch frameworks [7,8] and day-ahead scheduling of renewable-based VPPs [9], and recent studies have advanced real-time disaggregation among heterogeneous resources [10], multi-objective MILP scheduling [11], robust aggregator-prosumer games [12], and multistage scheduling under distributed locational marginal prices [13]. Network-aware studies have also coordinated VPPs with active distribution grids under voltage-security constraints [14], disseminated dynamic operating boundaries for congestion and voltage management [15], and co-optimized active networks and VPP portfolios while representing storage degradation and controllable loads [16]. These studies make clear that an interchange or network boundary is not novel by itself. The narrower contribution pursued here is to examine how a measured, import-dominated metropolitan supply boundary interacts with policy-defined PV milestones and aggregated flexibility. Chinese studies have embedded environmental benefits, internal pricing, and storage configuration in VPP dispatch [17,18,19], while carbon-quantification studies motivate time-varying rather than annual-average emission factors [20,21,22,23,24,25,26]. Storage valuation [27], demand response [28], vehicle-to-grid capacity [29], renewable curtailment [30,31], carbon-market design [32], and battery-swapping participation [33] provide additional methodological context.
Against this backdrop, three gaps remain for external-power-dominated load centers. First, many VPP models optimize resources behind a single point of interconnection, whereas a metropolitan planning model must also represent the system operator’s import schedule and local security-constrained generation. The ownership and control boundary must therefore be explicit. Second, policy-defined PV milestones and hosting limits are rarely used as scenario anchors, although they are directly relevant to municipal planning. Third, storage, demand response, and electric-vehicle flexibility are often simplified in ways that obscure energy conservation, temporal availability, rebound causality, and interactions with time-varying carbon intensity. This study addresses these gaps as a centralized planning surrogate; it does not claim that a VPP operator owns or directly dispatches the local thermal fleet or inter-regional interchange.
This paper addresses these gaps with a full-year, hourly, planning-anchored rolling MILP model of Guangzhou. The main contributions are threefold. (1) The model separates VPP-controlled distributed resources from system-operator coordination variables and represents the external-power band, midnight ramp continuity, local security limits, physically balanced BESS, demand response, and aggregate-EV states, and hourly carbon factors in one optimization. (2) Scenarios are anchored to Guangzhou’s official distributed-PV milestones (+2025 MW, +5025 MW, and +11,885 MW), using a full calendar year of measured-load data and transparently constructed November–December supply profiles. (3) The scenario comparison quantifies conditional operating-cost, carbon, import-share, tariff, and flexibility responses. Because only four planning anchors are evaluated in the submitted dataset, changes in slope are described as scenario-to-scenario nonlinearities rather than as an identified threshold. Section 2 defines the data, control boundary, formulation, rolling algorithm, and reporting metrics; Section 3, Section 4 and Section 5 present results, discussion, and conclusions.

2. Materials and Methods

2.1. Study Area and Data

The study object is a centralized city-level coordination model containing two distinct layers. The VPP-controlled layer aggregates existing and newly added distributed PV, grid-side and user-side BESS, demand response (DR), and electric-vehicle charging with V2G capability. The system-operator layer represents local coal, gas, biomass, and hydro generation together with the external interchange schedule of the China Southern Power Grid. The latter variables are included to calculate a feasible city-wide planning counterfactual and are not assumed to be owned or directly controlled by the VPP aggregator. The study period is the full calendar year 2025 (1 January–31 December, 8760 h). Figure 1 presents the control boundary and rolling algorithm; Figure 2 presents the annual data and distinguishes the constructed winter supply segment.
Figure 1. Control boundary and rolling-solution algorithm for the city-level coordinated VPP planning model.
Figure 2. Monthly 2025 energy composition, dispatch energy, and raw scheduled-import share. Shading identifies November–December, for which load is measured but supply-side profiles are constructed.
The hourly dataset is assembled as follows. (i) Load. Dispatch and system load are taken from official 15 min metering files for the full year and converted by selecting each on-the-hour record; dispatch energy is 125.99 TWh and the hourly peak is 23,944 MW. One missing 15 min dispatch-load value (28 November, 01:15) does not enter the hourly model. (ii) Supply, January–October. Local generation by source, scheduled interchange, and distributed-PV output are measured utility-platform series. A 24 h local-generation telemetry gap on 3 February is filled from the same hours in the adjacent week. (iii) Supply, November–December. The corresponding measured 2024 source profiles are scaled by January–October cumulative-energy ratios (coal 1.0395, gas 0.9082, biomass 1.0895, hydro 0.8624, and PV 2.2740); interchange is scaled hour by hour by the corresponding 2025/2024 measured-load ratio (mean 1.0257). (iv) Interchange calibration. The raw schedule is retained for validation, while the optimization upper-bound baseline adds only the positive hourly balance residual after all observed local availability and medium-voltage PV are counted. The adjustment is 0.809 TWh over 6534 h (maximum 899.0 MW). (v) Carbon factors. Two physically invalid September gas-factor records (0.0000 and 2.2297 kg CO2/kWh) are excluded and that month is averaged from the remaining six valid units; external power is assigned 0.45 kg CO2/kWh, and biomass, hydro, and PV are treated as zero operational emissions. (vi) PV split. Existing low-voltage PV is inferred from the positive system-load minus dispatch-load gap and capped by total PV; added PV is reported as 45% low voltage and 55% medium voltage. Table 1 lists the items and provenance.
Table 1. Data items, temporal resolution, and sources.
Figure 2 converts the dense hourly series into an auditable monthly energy view. Scheduled imports remain the largest source in every month, while their raw monthly share ranges from 60.31% in March to 72.06% in August. The seasonal energy pattern also makes the measured January–October and constructed November–December supply segments explicit. Annually, the raw scheduled interchange equals 68.04% of dispatch energy. After the transparent hourly balance adjustment and optimization, the baseline reaches 68.68%, a difference of +0.64 percentage points (+0.808 TWh). Source-wise annual errors are −1.20% for coal, −0.50% for gas, 0.00% for biomass and hydro, and +0.94% for imports; the hourly root mean square deviation between the optimized import dispatch and the raw scheduled-interchange reference is 159.5 MW.

2.2. Hourly Dynamic Carbon Intensity

To characterize hour-to-hour variation in electricity carbon content, Equation (1) defines a reporting metric: the supply-weighted system average. Let S denote supply sources, Ws,t the delivered energy of source s in hour t, and Es,t its associated CO2 emissions. Equation (1) is not a second objective function. The optimization in Equation (2) instead applies the source-specific hourly factors directly to each dispatch decision; the solved dispatch is then evaluated with Equation (1).
γ t = ∑ s ∈ S E s , t ∑ s ∈ S W s , t = ∑ s ∈ S γ s , t W s , t ∑ s ∈ S W s , t
where γs,t is the source emission factor (kg CO2/kWh, numerically equal to t CO2/MWh). Monthly plant factors are mapped to hourly parameters. Existing PV output is treated as an exogenous supply parameter; utilized newly added PV is a decision variable.

2.3. MILP Formulation of the City-Level VPP

The coordinated city model is formulated as a MILP over an H-hour rolling horizon with time step Δ t   = 1   h . Continuous variables include conventional generation, import, new-PV utilization and curtailment, BESS charge/discharge and energy, DR curtailment/rebound and deferred-energy state, aggregate-EV charging/V2G and energy, unserved load, and two constraint-relaxation slacks. Binary variables enforce mutually exclusive BESS, DR, and EV operating modes. Time-varying availability, load, existing PV, import schedule, emission factors, and connected-EV energy bounds are parameters. Section 2.3.1 defines the model notation. MILP is appropriate because all costs, balances, ramps, and energy-state transitions are linear, while mutually exclusive BESS, DR, and EV operating modes require binary decisions. The formulation therefore retains a tractable global optimum for the stated linearized planning boundary without relying on heuristic search.

2.3.1. Sets, Parameters, and Decision Variables

Table 2 defines the sets, parameters, and decision variables used in the MILP formulation, together with their units.
Table 2. Sets, parameters, decision variables, and units used in the MILP formulation.

2.3.2. Objective Function

The objective minimizes operating-and-carbon cost over the rolling horizon. It includes variable local-generation and import-procurement costs, carbon charges, BESS throughput cost, DR and EV flexibility-call costs, and penalties for unserved load or relaxed security boundaries. Because powers are in MW and non-carbon cost coefficients are in CNY/kWh, the factor 103 in Equation (2) converts MWh to kWh. The carbon term needs no such factor because γ is expressed in t CO2/MWh. Added-PV and BESS capital costs and fixed O&M are excluded; consequently, Z is not a total system cost or net planning benefit.
m i n Z = ∑ t ∈ T 10 3 ∑ g c g P g , t + c t i m p P t i m p + c c y c ∑ k ( P k , t c h + P k , t d i s ) + c d r ( P t d r , d n + P t d r , u p ) + c v 2 g P t v 2 g + M U E u t + M i m p s t i m p + M c o a l s t c o a l π C O 2 ∑ g γ g , t P g , t γ t i m p P t i m p Δ t
Equation (2) explicitly includes DR and V2G call costs and three distinct penalty terms. The variable ut is unserved load in the power balance, stimp relaxes only the interchange upper bound, and stcoal relaxes only the coal-security floor. Separating ut from stimp prevents the same slack from being counted as both physical supply and corridor relaxation. All slacks are reported in MW and MWh together with their penalty contributions in the diagnostic outputs of Section 2.6.

2.3.3. Constraints

(1) Power balance. In every hour, existing PV, utilized new PV, local generation, imports, BESS discharge, V2G discharge, downward DR, and unserved-load slack balance demand, BESS charging, EV charging, and DR rebound. The import-band slack does not enter the balance.
P t p v , 0 + P t p v + ∑ g ∈ G P g , t + ∑ k ∈ K P k , t d i s + P t i m p + P t v 2 g + P t d r , d n + u t = L t + ∑ k ∈ K P k , t c h + P t e v + P t d r , u p           ∀ t
Because dispatch load is measured at the supply side, internal network losses are embedded in Lt. Storage and EV conversion losses are represented explicitly in their energy-state equations.
(2) Unit availability and thermal ramping. Each local unit is bounded by its measured hourly availability, and coal and gas units are ramp-limited:
0 ≤ P g , t ≤ A g , t m a x         ∀ g ∈ G ,         ∀ t
− R g P g c a p ≤ P g , t − P ~ g , t − 1 ≤ R g P g c a p           ∀ g ∈ G T H ,         ∀ t
(3) Newly added PV: availability, curtailment, and grid absorption. Utilized plus curtailed new-PV output equals the available output, which follows the measured profile of the existing fleet scaled to the added capacity; utilized output is further capped by the grid absorption capability P a b s of the corresponding planning year:
P t p v + P t c u r = A t p v ,       P t p v ≥ 0 ,     P t c u r ≥ 0         ∀ t
P t p v , 0 + P t p v ≤ P a b s       ∀ t
(4) Fuel-structure security constraints. The gas fleet is capped at a share ξ of the load (fuel-supply security), and thermal output is floored at ρ^min of the load (voltage/inertia support), with a penalized slack:
∑ g ∈ G g a s P g , t ≤ ξ L t         ∀ t
∑ g ∈ G c o a l P g , t + s t c o a l ≥ ρ m i n L t           ∀ t
(5) External power boundary. The interchange must stay within an asymmetric band around the scheduled baseline Bt—a narrow upward margin δ+ reflecting corridor headroom and a wide downward margin δ− reflecting curtailability of purchases—and its hourly change is ramp-limited in proportion to the baseline:
( 1 − δ − ) B t ≤ P t i m p ≤ ( 1 + δ + ) B t + s t i m p         ∀ t
− ρ i m p B t ≤ P t i m p − P ~ t − 1 i m p ≤ ρ i m p B t           ∀ t
(6) Battery energy storage. The energy state of each BESS follows the standard efficiency-corrected dynamics, is bounded by the operating SOC window, and—this being the defining MILP feature—charging and discharging are mutually exclusive through the binary state y k , t :
E k , t + 1 = ( 1 − σ k ) E k , t + η k c h P k , t c h Δ t − P k , t d i s Δ t η k d i s         ∀ k , t
S O C k m i n E k c a p ≤ E k , t ≤ S O C k m a x E k c a p         ∀ k , t
0 ≤ P k , t c h ≤ y k , t P k c a p , 0 ≤ P k , t d i s ≤ ( 1 − y k , t ) P k c a p , y k , t ∈ { 0 , 1 }       ∀ k , t
A daily BESS throughput limit restricts equivalent cycling. Daily state closure is not imposed because it would make inter-day handoff redundant. Instead, the implemented terminal state of each 24 h control step initializes the next rolling window, and a year-end closure condition prevents terminal depletion. Midnight thermal and interchange ramps use the last implemented dispatch of the preceding day.
∑ t ∈ d P k , t d i s Δ t ≤ N k c y c E k c a p         ∀ k , d
E k , d + 1 , 0 = E k , d , 24 i m p l             ∀ k , d < D ;           E k , D , 24 = E k , 1 , 0
(7) Demand response and aggregate electric vehicles. DR is represented by a deferred-energy state Qt: curtailment increases Qt, rebound decreases it, rebound cannot precede curtailment, and Qt returns to zero at the end of each service day. A binary variable prevents simultaneous curtailment and rebound. The aggregate-EV state Etev accounts for charging efficiency, V2G discharge efficiency, and exogenous driving-energy withdrawals. The controlled fleet is represented as a deviation from charging already embedded in the measured load: a baseline overnight charging profile is removed and optimized charging is added back. The implemented assumptions are a 4 h aggregate energy capacity at rated V2G power, 1 full-power hour of daily driving withdrawal split between 08:00 and 18:00, 70% and 50% pre-departure energy requirements, time-varying charging/V2G power availability, mutually exclusive modes, and a 2 h daily V2G budget.
Q t + 1 = Q t + ( P t d r , d n − P t d r , u p ) Δ t       ∀ t
0 ≤ P t d r , d n ≤ z t d r κ d r α L t ,       0 ≤ P t d r , u p ≤ ( 1 − z t d r ) κ d r α L t ,           z t d r ∈ { 0 , 1 }
Q d , 0 = Q d , 24 = 0 ,         0 ≤ Q t ≤ Q m a x             ∀ d , t
E t + 1 e v = E t e v + η e v c h P t e v Δ t − P t v 2 g Δ t η e v d i s − D t d r i v e           ∀ t
0 ≤ P t e v ≤ z t e v a t e v P e v c a p ,             0 ≤ P t v 2 g ≤ ( 1 − z t e v ) a t e v P e v c a p ,                     z t e v ∈ { 0 , 1 }
E t e v , m i n ≤ E t e v ≤ E t e v , m a x ,           E τ e v ≥ E τ r e q ∀ τ ∈ T d e p ,                   ∑ t ∈ d P t v 2 g Δ t ≤ H v 2 g P e v c a p
E d + 1 , 0 e v = E d , 24 e v , i m p l ∀ d < D ;         E D , 24 e v = E 1 , 0 e v

2.4. Rolling-Solution Strategy and Parameterization

The implemented rolling scheme uses a 48 h look-ahead and a 24 h control step. At the start of day d, inputs for hours d through d + 1 and the implemented BESS, DR, EV, thermal, and interchange states initialize the model. Only the first 24 h are retained; energy states and the final implemented coal, gas, and interchange values initialize day d + 1. The final 24 h window enforces year-end BESS and EV closure. The largest fully flexible window contains 1226 registered variables, including 166 active binary variables after zero-availability modes are removed, and 1751 constraints. Across the 11 core annual cases, CBC returned optimal with a reported gap of 0, total solve time of 23–48 s per scenario, and peak process working set of 93–138 MB. Maximum power-balance residual was 0.0006 MW and maximum state-equation residual was below 0.0001 MWh. The implemented techno-economic parameters and their provenance are summarized in Table 3.
Table 3. Key techno-economic parameters, implemented values, and provenance.

2.5. Planning-Anchored Scenario Design

The policy scenarios retain the three official planning anchors: +2025 MW, +5025 MW, and +11,885 MW over the January 2025 stock [3,4]. To test whether the sparse anchors concealed a breakpoint, an additional PV-only sweep evaluates 0–12 GW at 0.5 GW increments. One-at-a-time sensitivity cases vary the interchange upper margin (0%, 5%, 10%), coal floor (4%, 8%, 12%), import emission factor (0.35, 0.45, 0.55 kg CO2/kWh), BESS efficiency (90%, 95%, 98%), BESS size (0.5×, 1.0×, 1.5×), DR participation (0%, 30%, 60%), V2G budget (1, 2, 3 h/day), and all slack penalties (0.5×, 1.0×, 2.0×). Table 4 summarizes the anchor scenarios.
Table 4. Planning-anchored scenario design.

2.6. Evaluation Metrics and Diagnostic Outputs

Annual indicators are calculated from implemented hourly decisions using Equations (24)–(30). Their denominator is annual dispatch energy unless stated otherwise. Equation (31) defines the maximum absolute hourly power-balance residual used for numerical feasibility checks.
S i m p = 100 ∑ t P t i m p Δ t ∑ t L t Δ t
S g r e e n = 100 ∑ t ( P t p v , 0 + P t p v + P h y d r o , t ) Δ t ∑ t L t Δ t
C I = 10 3 ∑ t [ ∑ g γ g , t P g , t + γ t i m p P t i m p ] Δ t ∑ t L t Δ t         [ g   C O 2 / k W h ]
R c u r = 100 ∑ t P t c u r Δ t ∑ t A t p v Δ t
N k e q = ∑ t P k , t d i s Δ t E k c a p
E U E = ∑ t u t Δ t
E k l o s s = ∑ t ( 1 − η k c h ) P k , t c h + ( 1 η k d i s − 1 ) P k , t d i s           Δ t
R b a l = m a x t P t p v , 0 + P t p v + ∑ g P g , t + ∑ k P k , t d i s + P t i m p + P t v 2 g + P t d r , d n + u t − L t − ∑ k P k , t c h − P t e v − P t d r , u p
For every final scenario, the results package reports source-wise annual energy, cost components, new-PV availability and curtailment, BESS charge/discharge/losses, DR curtailed and rebound energy, EV charging, driving withdrawal and V2G energy, all three slacks, solver status, gap, memory, model size, residuals, and binding-hour counts. The core feasibility and flexibility diagnostics are summarized in Section 3.4; complete hourly dispatch, cost components, source balances, and window-level solver records are provided in Supplementary File S1 .

3. Results

3.1. Performance Along the PV Planning Pathway

Table 5 reports the absolute outcomes for the four policy anchors, while Figure 3 normalizes the change between successive anchors by each increment of added PV. Annual operating-and-carbon cost decreases from CNY 75.01 billion in S0 to CNY 65.50 billion in S3, carbon intensity falls from 467.9 to 412.2 g CO2/kWh, scheduled-import share declines from 68.68% to 63.92%, and green-power share rises from 3.29% to 14.88%.
Table 5. Full-year results along the PV planning pathway after model correction and recalculation.
Figure 3. Marginal reductions per incremental GW of added PV between successive policy-defined planning anchors. Cost values exclude PV/BESS capital cost and fixed O&M.
The marginal operating-and-carbon cost reduction declines from CNY 0.94 to 0.73 billion/GW and the marginal carbon-intensity reduction from 6.65 to 4.15 g CO2/kWh per GW across successive intervals. In contrast, marginal scheduled-import displacement strengthens from 0.061 to 0.564 percentage points/GW. This divergence shows why absolute four-point levels are insufficient to infer a unique threshold and motivates the dense sweep in Section 3.2.

3.2. Scenario-to-Scenario Response of the External Power Share

Figure 4 reports the 25-point PV-only sweep. Scheduled-import share declines continuously from 68.677% at 0 GW to 63.860% at 12 GW. Curtailment first exceeds 1 MWh at 4.0 GW but is only 0.006%; it then rises smoothly to 5.423% at 12 GW. The segment slope of import-share ranges from −0.022 to approximately −0.61 percentage points/GW and approaches a plateau at high capacity. These results support a gradual strengthening of marginal import substitution, not a unique mathematical breakpoint.
Figure 4. Dense 0–12 GW PV-only sweep at 0.5 GW increments. The dashed marker identifies the first capacity at which annual curtailment exceeds 1 MWh; it is not a formally estimated breakpoint.
The binding-hour diagnostics explain the smooth response. Import-upper-bound hours decrease from 8732 at 0 GW to 6352 at 12 GW, while coal-floor binding hours increase from 294 to 3758. Early PV additions therefore displace available local thermal output in a small number of hours; larger additions increasingly compress scheduled imports and create midday curtailment as the security floor binds more often. The mechanism remains conditional on the calibrated interchange baseline and the 8% coal floor.

3.3. Marginal Contributions of Flexibility Resources

Table 6 reports the absolute F1–F4 outcomes, whereas Figure 5 isolates the mechanisms. Grid BESS cuts annual new-PV curtailment from 9.59 to 4.28 GWh and removes 591 MWh of import-bound relaxation; user BESS reduces curtailment further to 3.47 GWh. Mobility-constrained EV scheduling then provides the largest incremental carbon-intensity reduction, 0.102 g CO2/kWh relative to PV only, without V2G discharge. DR remains unused at CNY 0.35/kWh. Flexibility therefore improves feasibility and curtailment, but its annual cost and carbon effects remain small at the 2030 PV level.
Table 6. Stepwise decomposition of flexibility resources under the recalculated 2030 configuration.
Figure 5. Mechanism-based decomposition under the 2030 PV configuration: new-PV curtailment energy, import-bound relaxation, and carbon-intensity reduction relative to PV only.

3.4. Carbon Price and Time-of-Use Tariff Sensitivity

Table 7 reports the corrected carbon-price and tariff cases. The 60–120 CNY/t carbon-price sweep changes annual carbon-accounting cost but leaves carbon intensity (440.67 g CO2/kWh) and import share (67.793%) unchanged to the reported precision. Structural boundaries and the existing marginal-cost ordering therefore dominate dispatch in this tested price range.
Table 7. Carbon-price and tariff cases under the recalculated 2030 configuration.
Table 8 and Table 9 expose the quantities used to verify feasibility and energy conservation in the four policy-anchor cases. All cases have zero unserved energy and zero reported optimality gaps. Import-bound relaxation falls to zero by S2, while the 1.898 GWh coal-floor relaxation is common to the 8% security-floor calibration and is examined separately in the coal-floor sensitivity.
Table 8. Solver and feasibility diagnostics for the four policy-anchor scenarios.
Table 9. Annual flexibility-energy diagnostics for the four policy-anchor scenarios.
The time-of-use tariff lowers scheduled-import share by 0.582 percentage points, from 67.793% to 67.211%, but raises carbon intensity by 1.25 g CO2/kWh because some high-price peak imports are replaced by higher-emission local thermal output. Grid-BESS discharge increases from 5.65 to 10.03 GWh, but the tariff remains a price-shifting signal rather than a carbon-aligned signal. This is a conditional counterfactual, not evidence that time-of-use tariffs generally increase emissions.

3.5. Parameter Robustness

Figure 6 summarizes the one-at-a-time sensitivity results around S2. The import upper margin is the strongest dispatch parameter: increasing it from 0% to 5% and 10% raises import share to 70.77% and 73.49% while lowering carbon intensity under the 0.45 kg CO2/kWh import factor. The 4% coal-floor case eliminates coal slack, whereas the 12% case requires 1.094 TWh of slack and is therefore a stress test rather than an equally feasible calibration. Import-factor changes alter reported carbon intensity from 372.9 to 508.5 g CO2/kWh without changing dispatch. BESS efficiency and size produce small effects at the 2030 PV level; DR participation, V2G budget, and penalty scaling do not change the principal dispatch indicators because DR/V2G remain non-binding and all physical slacks are already near zero.
Figure 6. One-at-a-time sensitivity of S2 carbon intensity and scheduled-import share. Green and red markers denote the lower and higher tested values, respectively; the vertical line is the base case.

3.6. Typical-Day Operation

Figure 7 and Figure 8 illustrate 21 December 2025 under S3, the day with the largest annual curtailed energy. Dispatch load peaks at 13,866 MW at 21:00. Available new PV totals 85.72 GWh, of which 40.07 GWh (46.75%) is curtailed. Grid BESS charges 2.15 GWh during the afternoon surplus and discharges 1.94 GWh during the evening ramp; user BESS charges 0.54 GWh and discharges 0.48 GWh. DR and V2G remain zero, while EV charging is scheduled to meet mobility requirements.
Figure 7. Hourly power balance on the largest-curtailment day (21 December 2025, S3). Upper panel: supply stack, dispatch load, and available PV. Lower panel: signed flexibility power; charging is negative and discharge is positive.
Figure 8. Hourly system carbon intensity and grid/user BESS state of charge on 21 December 2025 under S3.
Hourly carbon intensity ranges from 229.6 g CO2/kWh at 13:00 to 511.0 g CO2/kWh at 01:00, a 281.4 g CO2/kWh swing. Grid BESS begins at its 10% lower bound, reaches 95% after charging at 15:00–16:00, and returns to 10% after evening discharge. This behavior shifts otherwise-curtailed PV within the energy-state and year-end constraints; it does not imply that the modest annual BESS activity at the 2030 anchor provides a general investment case because capital costs are outside the objective.

4. Discussion

Planning implications: The dense sweep reveals a continuous, capacity-dependent transition rather than a discrete threshold. Curtailment first becomes measurable at 4.0 GW of added PV but remains negligible, whereas import displacement strengthens progressively as import-upper-bound hours decline and coal-floor constraints bind more frequently. Planning decisions should therefore rely on the full response curve and location-specific network studies rather than on a single threshold. Relative to the calibrated baseline, the 11.885 GW rooftop case reduces import share by 4.75 percentage points and carbon intensity by 55.8 g CO2/kWh while curtailing 4.06% of available new PV.
Tariff-carbon coordination and robustness: The corrected time-of-use case shows that peak-relief and decarbonization objectives can diverge, although the increase in carbon intensity is limited to 1.25 g CO2/kWh. Sensitivity analysis identifies the import boundary and import emission factor as the dominant determinants of this result. Increasing the import upper margin from 0% to 10% raises import share from 67.79% to 73.49% and lowers modeled carbon intensity because imported electricity is assumed to be less carbon intensive than marginal local thermal generation. Conversely, varying the import factor from 0.35 to 0.55 kg CO2/kWh substantially changes reported carbon intensity without changing dispatch. Figure 6 summarizes these conditional dependencies.
Why engineering constraints matter: The revised formulation treats the import band, unserved load, coal-floor relaxation, BESS state continuity, causal energy-neutral DR, and mobility-backed EV energy as distinct physical concepts, thereby preventing feasibility slacks or aggregated vehicles from creating energy. Network-aware VPP studies likewise show that operating boundaries and distribution constraints materially affect feasible schedules [14,15,16]. Nevertheless, the present single-node model remains a planning surrogate rather than a distribution-network power-flow model.
Comparison with related work: Unlike resource-disaggregation models [10] and multi-objective or robust VPP schedules [11,12], this study combines a metropolitan import schedule with policy-defined PV anchors within a centralized planning boundary. Network-aware studies [14,15,16] represent voltage, congestion, ownership, and bilevel coordination more explicitly, whereas the present model exchanges that spatial detail for a full-year case based on measured data. Direct numerical ranking would therefore be misleading because system scale, ownership boundaries, tariffs, emissions accounting, and network constraints differ. The contribution is an empirically grounded interpretation of planning scenarios under a documented city-wide boundary, not a claim of universally superior optimization performance.
Limitations: First, the deterministic model omits forecast uncertainty. Second, the November–December supply series are constructed from scaled 2024 telemetry. Third, hourly balance calibration adds 0.809 TWh to the raw scheduled-interchange upper-bound series; annual source errors are small, but the hourly root mean square deviation for imports is 159.5 MW. Fourth, plant factors were transcribed from utility records marked as not independently checked, and two invalid September gas values were excluded using a documented plausibility rule. Fifth, the single-node representation omits intra-city voltage and congestion limits. Sixth, the objective excludes annualized PV/BESS capital costs and fixed O&M and therefore cannot establish a net planning benefit. Finally, the 12% coal-floor stress test requires 1.094 TWh of slack, indicating that high security floors are incompatible with the observed availability envelope. These limitations define the scope within which the results should be interpreted.

5. Conclusions

This study presents a recalculated full-year, hourly rolling MILP planning surrogate for Guangzhou, an import-dependent megacity. The model distinguishes VPP-controlled resources from system-operator variables and enforces separate feasibility slacks, inter-day storage continuity, causal energy-neutral DR, and mobility-constrained aggregate-EV operation. The analysis supports four principal conclusions.
(1)
Across the four policy anchors, combined annual operating-and-carbon cost decreases from CNY 75.01 to 65.50 billion, while carbon intensity falls from 467.9 to 412.2 g CO2/kWh. These values exclude PV/BESS capital costs and fixed O&M.
(2)
Scheduled-import share declines from 68.68% to 63.92%. The 25-point sweep exhibits a continuous response: curtailment begins near 4.0 GW but remains negligible at that point, and no unique breakpoint is identified.
(3)
At the 2030 anchor, BESS primarily removes a small import-bound relaxation and reduces new-PV curtailment from 0.149% to 0.054%. Causal DR and V2G are not economically dispatched, whereas mobility-constrained EV charging is rescheduled without creating energy.
(4)
The time-of-use case lowers import share by 0.58 percentage points but raises carbon intensity by 1.25 g CO2/kWh. Import-boundary and emission-factor sensitivities demonstrate that this result is conditional and should not be generalized beyond the stated assumptions.

Supplementary Materials

The following supporting information can be downloaded at: https://www.mdpi.com/article/10.3390/en19184431/s1. Supplementary File S1: Core Results, Dense-Sweep and Sensitivity Summaries, and Rolling-Window Solver Diagnostics.

Author Contributions

Conceptualization, S.K.; methodology, S.K.; software, S.K.; validation, H.D. and Y.G. (Yanna Gao); formal analysis, S.K.; investigation, Y.G. (Yanna Gao) and L.H.; resources, Y.G. (Yanna Gao) and Y.G. (Yuqun Gao); data curation, Y.G. (Yanna Gao) and F.Z.; writing—original draft preparation, S.K.; writing—review and editing, H.D., F.Z., Y.G. (Yuqun Gao) and L.H.; visualization, S.K.; supervision, S.K.; project administration, Y.G. (Yanna Gao); funding acquisition, Y.G. (Yanna Gao). All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Special Project on Power Grid Planning of the Guangzhou Power Supply Bureau, Guangdong Power Grid Co., Ltd. (grant number 030100QQ00250004).

Data Availability Statement

The raw dispatch-load, system-load, generation, external-interchange, and network-loss records were provided by the Guangzhou Power Supply Bureau of Guangdong Power Grid Co., Ltd. under a confidentiality agreement and are available from the corresponding author on reasonable request with permission from the data owner. The scenario configurations, result summaries, and solver diagnostics needed to reproduce the reported calculations are provided in Supplementary File S1.

Acknowledgments

The authors thank the Guangzhou Power Supply Bureau for data support.

Conflicts of Interest

Authors Yanna Gao, Hong Dong, Fanhong Zeng, Yuqun Gao and Liujun Hu are employed by Guangdong Power Grid Co., Ltd. The remaining author declares that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest. The authors declare that this study received funding from the Special Project on Power Grid Planning of the Guangzhou Power Supply Bureau, Guangdong Power Grid Co., Ltd. (grant number 030100QQ00250004). The funder was not involved in the study design, the collection, analysis, or interpretation of the data, the writing of this article or the decision to submit it for publication.

References

  1. National Development and Reform Commission; National Energy Administration. Guiding Opinions on Accelerating the Development of Virtual Power Plants; NDRC Energy [2025] No. 357; NDRC: Beijing, China, 2025. Available online: https://www.ndrc.gov.cn/xxgk/zcfb/tz/202504/t20250411_1397162.html (accessed on 27 July 2026). (In Chinese)
  2. Guangzhou Municipal Bureau of Statistics. Statistical Communique of Guangzhou on the 2025 National Economic and Social Development; Guangzhou Municipal Bureau of Statistics: Guangzhou, China, 2026. Available online: https://tjj.gz.gov.cn/zzfwzq/tjkx/content/post_10804061.html (accessed on 27 July 2026). (In Chinese)
  3. Guangzhou Municipal Development and Reform Commission. Action Plan for the High-Quality Development of Distributed Photovoltaics in Guangzhou (2024–2030); Sui-Fa-Gai [2024] No. 68; Guangzhou Municipal Development and Reform Commission: Guangzhou, China, 2024. (In Chinese)
  4. Guangzhou Power Supply Bureau. Recommended Planning and Layout Scheme for Distributed Photovoltaic Projects in Guangzhou; Internal Report; Guangdong Power Grid Co., Ltd.: Guangzhou, China, 2025. (In Chinese)
  5. Nafkha-Tayari, W.; Ben Elghali, S.; Heydarian-Forushani, E.; Benbouzid, M. Virtual Power Plants Optimization Issue: A Comprehensive Review on Methods, Solutions, and Prospects. Energies 2022, 15, 3607. [Google Scholar] [CrossRef]
  6. He, S.; Zhang, J.; Gu, Z.; Shi, X.; Jiang, H. Overview of Virtual Power Plant Modeling and Optimization Control for Distributed Resource Aggregation and Control. Shandong Electr. Power 2024, 51, 11–24, 45. (In Chinese) [Google Scholar]
  7. Mashhour, E.; Moghaddas-Tafreshi, S.M. Bidding strategy of virtual power plant for participating in energy and spinning reserve markets-Part I: Problem formulation. IEEE Trans. Power Syst. 2011, 26, 949–956. [Google Scholar] [CrossRef]
  8. Pandzic, H.; Kuzle, I.; Capuder, T. Virtual power plant mid-term dispatch optimization. Appl. Energy 2013, 101, 134–141. [Google Scholar] [CrossRef]
  9. Zamani, A.G.; Zakariazadeh, A.; Jadid, S. Day-ahead resource scheduling of a renewable energy based virtual power plant. Appl. Energy 2016, 169, 324–340. [Google Scholar] [CrossRef]
  10. Chen, Q.; Lyu, R.; Guo, H.; Su, X. Real-time operation strategy of virtual power plants with optimal power disaggregation among heterogeneous resources. Appl. Energy 2024, 361, 122876. [Google Scholar] [CrossRef]
  11. Aoun, A.; Adda, M.; Ilinca, A.; Ghandour, M.; Ibrahim, H. Optimizing Virtual Power Plant Management: A Novel MILP Algorithm to Minimize Levelized Cost of Energy, Technical Losses, and Greenhouse Gas Emissions. Energies 2024, 17, 4075. [Google Scholar] [CrossRef]
  12. Yin, S.; Ai, Q.; Li, Z.; Zhang, Y.; Lu, T. Energy management for aggregate prosumers in a virtual power plant: A robust Stackelberg game approach. Int. J. Electr. Power Energy Syst. 2020, 117, 105605. [Google Scholar] [CrossRef]
  13. Nadeem, F.; Goswami, A.K.; Tiwari, P.K.; Pushkarna, M.; Bandhu, D.; Alhazmi, M. Multistage Scheduling of VPP under Distributed Locational Marginal Prices and LCOE Evaluation. IEEE Access 2024, 12, 132236–132253. [Google Scholar] [CrossRef]
  14. Yang, T.; Wang, J.; Liang, Y.; Xiang, C.; Wang, C. Economic Dispatch between Distribution Grids and Virtual Power Plants under Voltage Security Constraints. Energies 2024, 17, 117. [Google Scholar] [CrossRef]
  15. Gholami, K.; Arif, M.T.; Haque, M.E. Dynamic Boundary Dissemination to Virtual Power Plants for Congestion and Voltage Management in Power Distribution Networks. Energies 2025, 18, 518. [Google Scholar] [CrossRef]
  16. Li, Q.; Dong, F.; Zhou, G.; Mu, C.; Wang, Z.; Liu, J.; Yan, P.; Yu, D. Co-Optimization of Virtual Power Plants and Distribution Grids: Emphasizing Flexible Resource Aggregation and Battery Capacity Degradation. Appl. Energy 2025, 377, 124519. [Google Scholar] [CrossRef]
  17. Wang, C.; Li, P.; Yu, H. Economic optimal dispatch of virtual power plant considering environmental benefits. Adv. New Renew. Energy 2015, 3, 370–375. (In Chinese) [Google Scholar]
  18. Li, M.; Dong, Z. Pricing mechanism and optimal dispatch of a virtual power plant with distributed renewables and demand-response loads. Integr. Intell. Energy 2024, 46, 12–17. (In Chinese) [Google Scholar]
  19. Wei, L.; Zhao, B.; Wu, H.; Zhang, X. Optimal configuration model of energy-storage system considering large-scale distributed photovoltaics in virtual power plants. Autom. Electr. Power Syst. 2015, 39, 66–74. (In Chinese) [Google Scholar]
  20. Siler-Evans, K.; Azevedo, I.L.; Morgan, M.G. Marginal emissions factors for the U.S. electricity system. Environ. Sci. Technol. 2012, 46, 4742–4748. [Google Scholar] [CrossRef] [PubMed]
  21. Ben Amor, S.; Sgarciu, S.; Batz Lineiro, T.; Musgens, F. Advanced models for hourly marginal CO2 emission factor estimation: A synergy between fundamental and statistical approaches. Appl. Energy 2025, 397, 126265. [Google Scholar] [CrossRef]
  22. Wang, Z.; Wang, X.; Kong, S.; Sun, B.; Ji, Z.; Sun, W. Coordinated dispatch of virtual power plant and distribution network considering multi-time scale carbon emission factors. Electr. Power 2026, 59, 14–26. (In Chinese) [Google Scholar] [CrossRef]
  23. Wang, Y.; Xu, J.; Pei, W.; Wang, H.; Zhang, Z. Low-carbon economic scheduling of virtual power plant considering carbon emission flow and demand response. Front. Energy Res. 2024, 12, 1398655. [Google Scholar] [CrossRef]
  24. Zhang, F.; Gong, Y.; Zhang, X.; Liu, F.; Zhou, Q. A multi-objective stochastic optimization model for a combined heat and power virtual power plant considering carbon recycling and utilizing. Front. Energy Res. 2024, 12, 1363360. [Google Scholar] [CrossRef]
  25. Hittinger, E.S.; Azevedo, I.M.L. Bulk energy storage increases United States electricity system emissions. Environ. Sci. Technol. 2015, 49, 3203–3210. [Google Scholar] [CrossRef] [PubMed]
  26. Craig, M.T.; Jaramillo, P.; Hodge, B.-M. Carbon dioxide emissions effects of grid-scale electricity storage in a decarbonizing power system. Environ. Res. Lett. 2018, 13, 014004. [Google Scholar] [CrossRef]
  27. Sioshansi, R.; Denholm, P.; Jenkin, T.; Weiss, J. Estimating the value of electricity storage in PJM: Arbitrage and some welfare effects. Energy Econ. 2009, 31, 269–277. [Google Scholar] [CrossRef]
  28. Albadi, M.H.; El-Saadany, E.F. A summary of demand response in electricity markets. Electr. Power Syst. Res. 2008, 78, 1989–1996. [Google Scholar] [CrossRef]
  29. Kempton, W.; Tomic, J. Vehicle-to-grid power fundamentals: Calculating capacity and net revenue. J. Power Sources 2005, 144, 268–279. [Google Scholar] [CrossRef]
  30. Denholm, P.; Hand, M. Grid flexibility and storage required to achieve very high penetration of variable renewable electricity. Energy Policy 2011, 39, 1817–1830. [Google Scholar] [CrossRef]
  31. Bird, L.; Lew, D.; Milligan, M.; Carlini, E.M.; Estanqueiro, A.; Flynn, D.; Gomez-Lazaro, E.; Holttinen, H.; Menemenlis, N.; Orths, A.; et al. Wind and solar energy curtailment: A review of international experience. Renew. Sustain. Energy Rev. 2016, 65, 577–586. [Google Scholar] [CrossRef]
  32. Zhang, D.; Karplus, V.J.; Cassisa, C.; Zhang, X. Emissions trading in China: Progress and prospects. Energy Policy 2014, 75, 9–16. [Google Scholar] [CrossRef]
  33. Hu, X.; Huang, Y.; Huang, Y.; Zhao, Y.; Huang, Z.; Liang, Y. Operation Optimization of Electric Vehicle Battery Swapping Stations via Virtual Power Plant and Carbon Trading. Energies 2026, 19, 2341. [Google Scholar] [CrossRef]
  34. Ministry of Ecology and Environment of the People’s Republic of China. National Carbon Market Operated Steadily and Orderly in 2025 and Completed Its Annual Development Tasks. 1 January 2026. Available online: https://www.mee.gov.cn/ywgz/ydqhbh/wsqtkz/202601/t20260101_1139528.shtml (accessed on 17 August 2026). (In Chinese)
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.