Abstract
This study develops a cooperative multi-agent deep reinforcement learning (MARL) framework for simulation-based cost-overrun mitigation in smart grid construction projects under dynamic engineering uncertainty. Modern smart grid construction involves digital substations, renewable-energy-connected facilities, flexible transmission assets, intelligent monitoring systems, and geographically distributed contractors; therefore, cost escalation is driven by sequential interactions among procurement, schedule execution, equipment deployment, supervision, weather, logistics, and price volatility. The proposed framework models procurement management, construction scheduling, equipment allocation, and supervision-control units as decentralized agents embedded in a calibrated construction simulation environment. The environment is parameterized from 42 smart grid construction projects in Henan Province, China and generates disturbance scenarios involving weather efficiency loss, transportation delay, market-price volatility, labor shortage, and supply-chain interruption. A hybrid DQN–PPO mechanism represents mixed decision structures: value-based DQN modules handle discrete managerial choices such as task acceleration, supplier switching, and procurement timing, whereas PPO modules adjust continuous resource-allocation and recovery-intensity decisions. A hierarchical reward function combines local departmental objectives with project-level penalties for cost overrun, schedule delay, idle resources, recovery expenditure, safety risk, and environmental impact. The experimental protocol uses 30 paired random seeds, nonparametric bootstrap confidence intervals, Holm-adjusted Wilcoxon signed-rank tests, and comparison with deterministic optimization, rolling-horizon MPC, stochastic/robust optimization, single-agent DRL, MAPPO, MADDPG/MATD3, QMIX, and HAPPO baselines. The proposed framework achieves a mean cost-overrun rate of 6.83% and a mean schedule deviation of 16.82 days, reducing cost overrun by 18.7% and schedule deviation by 21.4% relative to rule-based construction management under the reported disturbance settings. The calibrated simulation evidence establishes a statistically evaluated decision-support framework for coordinated construction cost control and provides an artifact-level reproducibility pathway through configuration files, random-seed lists, anonymized synthetic benchmarks, and aggregated logs.
1. Introduction
The rapid development of new-generation power systems has significantly accelerated the deployment of smart grid infrastructure projects worldwide. Smart grid construction now includes digital substations, renewable-energy-connected substations, flexible transmission facilities, advanced grid-monitoring platforms, cyber-physical control equipment, and increasingly complex civil–electrical integration. These projects differ from conventional power-infrastructure construction because cost, schedule, safety, procurement, equipment mobilization, and regional operating conditions are tightly coupled. A procurement delay may immobilize labor teams, equipment idleness may trigger schedule recovery costs, and adverse weather can simultaneously reduce productivity, increase transport time, and change the feasibility of construction activities.
Cost overrun in this setting is therefore not only a static budgeting problem. It is a sequential control problem in which multiple project stakeholders repeatedly observe partial information, make role-specific decisions, and react to evolving disturbances. Conventional deterministic budgeting, critical-path adjustment, and post-event managerial correction are useful for planning and accountability, but they have limited ability to learn adaptive interventions during execution. Recent power-system studies on uncertainty-aware dispatch, virtual power plant operation, safe reinforcement learning, and resilient control show that adaptive learning can improve decision-making under nonstationarity and risk constraints [1,2,3,4,5,6]. However, those studies primarily address operational control of energy systems. Smart grid construction cost control involves a different decision layer: engineering tasks, procurement lead times, contractor coordination, safety supervision, material inventory, equipment mobilization, and project-budget evolution.
To address this construction-phase decision problem, this study formulates dynamic cost-overrun mitigation as a cooperative multi-agent Markov game. Procurement, scheduling, equipment, and supervision-control entities are represented as agents that execute decentralized actions under a shared project-level objective. The proposed learning architecture combines DQN components for discrete managerial choices and PPO components for continuous resource and recovery-intensity controls. The reward design is hierarchical: local rewards preserve department-specific accountability, while a global reward aligns all agents with cost, delay, risk, safety, emission, and recovery objectives.
The remainder of the paper follows a problem-to-method progression. Section 2 reviews construction cost management, reinforcement learning for project scheduling, multi-agent scheduling, safe and hierarchical reinforcement learning, and recent energy-infrastructure resilience methods. Section 2.5 isolates the research gaps, and Section 2.6 states the novelty and contributions after the closest literature has been positioned. The mathematical formulation, implementation details, data-simulation protocol, statistical reporting framework, sensitivity analysis, and transferability discussion are presented in Section 3, Section 4 and Section 5.
2. Literature Review
2.1. Smart Grid Construction Cost Management Under Dynamic Uncertainty
Cost overrun has long been recognized as a persistent problem in infrastructure delivery, with major drivers including underestimated uncertainty, imperfect risk allocation, design changes, resource conflicts, and managerial response delay [7,8]. Smart grid construction intensifies these challenges because electrical, civil, communication, protection, and cyber-physical subsystems must be coordinated under strict outage windows, grid-connection milestones, and safety requirements. Unlike ordinary building projects, delay in a smart grid project may affect renewable-energy integration, regional power-supply reliability, and subsequent network-upgrade schedules. Consequently, cost overrun is not only a financial-performance metric but also an infrastructure-resilience and investment-efficiency concern.
Uncertainty-aware optimization has been widely studied in energy systems. Stochastic programming, robust optimization, and decomposition-based methods are effective when disturbance distributions, scenario sets, and physical constraints can be specified in advance [1,2,9,10]. These methods provide strong mathematical transparency, but many construction-management decisions are repeatedly updated as new field information arrives. A method that is optimal for the initial scenario set may be less effective when supplier behavior, local weather, contractor availability, and equipment access evolve during execution. This motivates adaptive sequential decision-making rather than one-shot deterministic planning.
2.2. Reinforcement Learning for Construction Project Management and Scheduling
Reinforcement learning (RL) provides a formal mechanism for learning sequential policies through interaction with an environment [11,12]. In construction and project scheduling, RL-based methods have recently been used for automated schedule generation, rescheduling, equipment scheduling, precast production, and dynamic site-layout optimization. These studies demonstrate that RL can reduce makespan, improve rescheduling flexibility, and adapt to changing construction-site conditions [13,14,15]. Machine-learning reviews on project schedule creation also emphasize that data-driven scheduling is moving from purely predictive analytics toward decision-support and autonomous adjustment [16,17]. Nevertheless, most construction RL studies focus on task sequencing or resource scheduling in a single decision domain. They rarely integrate procurement, schedule, equipment, supervision, safety, and cost-overrun objectives into a unified multi-stakeholder control problem.
The distinction is important for smart grid construction. A scheduling-only agent can accelerate or postpone tasks, but it does not directly control supplier switching, inventory buffers, emergency procurement, equipment mobilization, safety inspection intensity, or recovery-resource allocation. A cost-control framework for smart grid construction must therefore model the interactions among heterogeneous decision makers and must combine discrete and continuous action types. These requirements motivate the cooperative MARL formulation developed in this study.
2.3. Multi-Agent Systems for Project Scheduling and Resource Coordination
Multi-agent systems have been studied in construction management because large projects naturally involve distributed decision makers, local objectives, information asymmetry, negotiation, and resource sharing [18,19]. Earlier multi-agent project-scheduling methods often used rule-based negotiation, blackboard coordination, or heuristic resource allocation. These methods are interpretable and operationally intuitive, but they usually do not learn from repeated disturbance exposure, and they often require hand-designed interaction rules. In contrast, MARL allows agents to learn policies that reflect both local observations and global coordination rewards.
Recent MARL algorithms provide several design alternatives. MAPPO extends PPO to cooperative multi-agent settings and has shown strong empirical performance in cooperative games [20]. MADDPG uses centralized critics for continuous multi-agent control [21]. QMIX decomposes joint action values under a monotonic factorization structure [22]. HAPPO and related trust-region approaches provide principled policy updates for heterogeneous agents [23]. MATD3 and TD3-based methods reduce overestimation bias in continuous actor–critic settings [24]. These approaches provide a valuable methodological basis; however, none of them directly specifies the construction-phase cost-overrun problem with mixed discrete-continuous stakeholder actions, budget-schedule-risk constraints, hierarchical reward allocation, and empirically calibrated engineering disturbances.
2.4. Hierarchical and Safe Reinforcement Learning for Energy-Infrastructure Operations
The closest energy-system studies are concerned with resilient operation rather than construction-phase cost control. Robust safe RL has been used to enhance power-grid resilience against typhoons through distributed energy resource flexibility aggregation [5]. Model-free adaptive dynamic programming has been developed for resilient control of nonlinear networked systems under denial-of-service attacks [6]. Enhanced TD3-based MARL has been studied for distributed energy resource coordination in active distribution networks [25]. A TD3-based combined-heat-and-power scheduling framework has also been proposed for forecasting and optimal load allocation [26]. These studies show that safe and actor–critic RL can improve operational resilience in cyber-physical energy systems, but they do not address construction-site disturbances, multi-contractor interactions, or cost-overrun propagation during infrastructure delivery.
Hierarchical RL and integrated capacity-planning studies further clarify the novelty boundary. Distributed hierarchical reinforcement learning for dynamic maintenance scheduling decomposes large-scale maintenance decisions into upper-level and lower-level policies [27]. Integrated capacity planning and multi-project scheduling consider resource transfer and idleness across projects, offering a rigorous scheduling baseline for resource-intensive portfolios [28]. These contributions are highly relevant because they address hierarchy, resource idleness, and multi-project coordination. However, their objective is maintenance or capacity planning rather than construction-phase cost-overrun mitigation under weather, logistics, procurement, safety, and budget disturbances. The present study therefore borrows the coordination logic of hierarchical and multi-agent decision systems but applies it to a different engineering problem with a different state representation, action structure, and reward hierarchy. Table 1 summarizes the positioning of the study relative to the closest literature streams.
Table 1.
Positioning of the study relative to the closest literature.
2.5. Research Gap
Based on the above literature, three research gaps remain.
First, existing construction cost-control and scheduling models do not sufficiently represent construction-phase cost overrun as a dynamic, multi-source, disturbance-driven process. Robust optimization and integrated capacity-planning methods are valuable when uncertainty sets and project interactions are known, but smart grid projects experience continuously updated weather, logistics, price, labor, safety, and procurement information. A gap therefore exists between static or periodically reoptimized project planning and real-time adaptive cost-overrun mitigation.
Second, recent RL and MARL methods provide powerful generic mechanisms, but their state, action, and reward structures are not tailored to smart grid construction. MAPPO, MADDPG, QMIX, HAPPO, and TD3-family algorithms are not by themselves construction-management models. They must be embedded in a decision environment that represents procurement timing, inventory buffers, task precedence, equipment mobilization, contractor synchronization, inspection intensity, recovery expenditure, and schedule–cost coupling.
Third, hierarchical and safe RL studies in energy and maintenance systems partially address coordination, risk, and resilience, but they do not resolve the specific problem of construction-phase cost-overrun propagation. The missing component is a reproducible cooperative Markov game in which multiple project stakeholders learn coordinated interventions under calibrated construction-specific disturbances while maintaining budget, schedule, resource, safety, and environmental constraints.
2.6. Novelty and Contributions
The study makes four contributions after positioning the above gaps. First, it formulates smart grid construction cost-overrun mitigation as a cooperative multi-agent Markov game, explicitly distinguishing global project states, role-specific observations, decentralized actions, and joint cost-delay-risk outcomes. Second, it develops a hybrid DQN–PPO architecture that maps naturally to mixed construction decisions: DQN handles discrete managerial choices, whereas PPO handles continuous allocation and recovery intensities. Third, it introduces a hierarchical reward pathway that balances local departmental accountability with global project-level penalties for cost overrun, schedule delay, idle loss, recovery cost, safety risk, and environmental impact. Fourth, it clarifies a data-calibrated simulation protocol using 42 smart grid projects, including data provenance, preprocessing, scenario generation, baseline fairness, statistical reporting requirements, sensitivity analysis, transferability assumptions, and reproducibility boundaries.
3. Mathematical Modeling
Before introducing the detailed mathematical expressions, it is useful to summarize the overall architecture and information flow of the proposed framework. Figure 1 gives a structural view of the data layer, disturbance layer, construction environment, learning agents, and decision outcomes. Figure 2 then shows the corresponding workflow from raw project data and scenario generation to mathematical modeling, multi-agent training, and final evaluation. Table 2 explains how the diagram components correspond to the Markov-game formulation and the reporting workflow.
Figure 1.
Architecture of the cooperative MARL framework. The diagram separates the data/ disturbance layer, cooperative Markov-game environment, decentralized agents, centralized training, hierarchical reward evaluation, and adaptive feedback pathways.
Figure 2.
Workflow from raw project data and calibrated disturbances to cooperative Markov-game state updates, hybrid DQN–PPO learning, adaptive reward evaluation, statistical reporting, and sensitivity analysis.
Table 2.
Interpretation of the framework diagrams and information-flow notation.
3.1. Notation
The mathematical model uses task, time, agent, resource, material, and scenario indices to represent the dynamic construction environment. The main sets, decision variables, and parameters are summarized in Table 3, Table 4 and Table 5. All scenario-dependent quantities are indexed by when stochastic disturbance realization is explicitly considered.
Table 3.
Sets and indices used in the mathematical formulation.
Table 4.
Main decision variables.
Table 5.
Main parameters.
3.2. Objective Function and Construction Constraints
Equation (1) defines the central optimization target of the paper. It aggregates the financial and operational consequences of project execution over the full horizon and then averages them across the disturbance scenarios in . In other words, the formulation does not reward a policy simply because it performs well in a calm situation; instead, it favors strategies that remain effective when weather, transport, and market conditions fluctuate.
The policy set contains the decision rules learned by the procurement, scheduling, equipment, and supervision agents. The six penalty terms track cost overrun , schedule deviation , idle-resource loss , recovery expenditure , safety exposure , and environmental impact . Their coefficients , , , , , and play the role of managerial preference parameters. Larger values indicate that the owner or system planner considers the corresponding issue more critical.
The auxiliary cost expression below the objective breaks the period cost into labor, equipment, material procurement, and emergency recovery components. Here, and are unit labor and equipment costs, whereas is the scenario-dependent material price. This decomposition is helpful because it later allows the learning algorithm to identify which source of cost growth is dominating in a given construction stage.
Equation (2) is the budget envelope of the model. It compares cumulative spending with the available dynamic budget and records any excess through the nonnegative slack variable .
That slack is not free. Because it is penalized in the objective, the learning system will treat budget violation as an expensive last resort rather than a routine action. The cumulative form is also deliberate: in construction practice, overruns usually build up over time through many small procurement, scheduling, and recovery decisions.
Equation (3) enforces engineering order. If task i must finish before task j can begin, then the chosen start time of j cannot be earlier than the start time of i plus its duration .
Although simple, this relation is structurally important. It preserves the physical logic of smart grid construction, where activities such as foundation preparation, equipment transport, erection, installation, and commissioning cannot be arbitrarily rearranged. Without this constraint, a learning agent might generate mathematically attractive but technically impossible schedules.
Labor feasibility appears in Equation (4). The first inequality limits the total assignment of workforce type r by the available labor capacity , and the second inequality makes sure that inactive tasks cannot receive workers.
The parameter gives a task-specific upper bound, so even an active task cannot absorb an unrealistically large crew. This detail matters in field construction, where congestion, work-front size, and safety spacing often cap the useful number of workers. Because the availability term carries the scenario index , the model can reflect seasonal labor shortages, contractor absenteeism, mobility restrictions, or other exogenous disruptions.
Equation (5) plays the same role for equipment that Equation (4) plays for labor, but the engineering interpretation is slightly different. Here, represents the available stock of equipment type g in period t, which may include cranes, transport vehicles, cable-laying machines, lifting systems, testing devices, or specialized installation tools.
The task-level limit is especially useful because adding more equipment does not always increase productivity proportionally. Past a certain point, the work front becomes crowded and additional machines may only create interference. By combining the global capacity bound and the task-specific upper limit, the model keeps equipment allocation physically credible.
The inventory-balance relation in Equation (6) tracks material continuity from one period to the next. Current stock plus deliveries, minus consumption induced by realized progress, determines the next inventory level.
The conversion factor links project execution directly to material depletion, which means that the construction schedule and procurement plan are no longer separable. A shortage today can choke tomorrow’s progress, whereas aggressive over-ordering may inflate storage and capital costs. For transmission and substation projects, the same mechanism applies to conductors, steel components, transformers, insulation materials, cables, and concrete.
Equation (7) introduces delayed material arrival. An order placed in period does not instantly appear at the construction site; it becomes available only after the stochastic lead time has elapsed. The indicator term simply routes the ordered quantity to the correct delivery period.
This is a short equation, but it changes the decision logic of the whole framework. Once delivery lag is acknowledged explicitly, the procurement agent must think ahead. Reactive ordering becomes costly because downstream crews may sit idle while waiting for materials.
Equation (8) transfers weather uncertainty into construction productivity. The upper bound on realized progress is reduced by the efficiency coefficient , and it is shut down entirely when the severe-disruption indicator is activated.
In practical terms, this means that mild adverse weather slows work, while severe weather suspends it. The activation variable keeps the expression consistent with scheduling decisions: no task can generate progress unless it is active in the first place.
Transportation effects enter through Equation (9). The first line scales the deliverable quantity by the accessibility coefficient , so poor logistics conditions immediately reduce how much material can reach the site. The second line extends lead time above its nominal value whenever accessibility deteriorates.
This two-part structure is useful because transport disruption has both a present effect and a future effect. It can reduce today’s deliveries and also postpone tomorrow’s replenishment. The parameter controls how strongly congestion or regional disruption translates into lead-time inflation.
Equation (10) prevents incompatible simultaneous allocations. The indivisible unit can be assigned to at most one task across all agents in the same period.
That sounds obvious from an engineering perspective, yet it is crucial in multi-agent learning. Without an explicit exclusivity rule, decentralized agents could each make sensible local choices and still create an impossible global plan by double-booking the same crane, transport vehicle, testing device, or specialist team.
Continuity is imposed by Equation (11). Once a task starts, it must remain active over its required duration , and the second relation guarantees that exactly one start period is chosen.
This is a stronger requirement than simple precedence. It rules out fragmented schedules for non-preemptive activities such as transformer hoisting, equipment installation, and protection testing. In reality, such tasks are expensive to stop and restart, so a continuity condition produces much more implementable schedules.
Safety is not treated as an afterthought. Equation (12) converts labor density, equipment intensity, and adverse weather exposure into a task-period safety score, and then limits that score by the threshold .
Because the expression is multiplied by the task-activation variable , only active work contributes to risk. This prevents the learning algorithm from trading safety away for short-term cost savings. The condition is especially relevant for high-voltage operations, lifting work, and outdoor activities performed near energized assets.
Equation (13) captures a softer coordination requirement than hard precedence. Two related contractor tasks are allowed to drift apart only within the tolerance band .
This matters in projects where handover, joint inspection, equipment delivery, or interface testing must be closely aligned, but not necessarily locked into the exact same period. If the deviation becomes too large, one crew may wait idle for another, and rework or delayed acceptance may follow. The constraint therefore captures the managerial requirement that interdependent teams remain aligned even when each agent makes decisions from its own partial information.
Market uncertainty is introduced through the autoregressive structure in Equation (14). The material price reverts around the long-run reference value , with persistence parameter and random shock scaled by volatility . The associated material cost depends on both the realized price and the procurement quantity selected by the agent. This formulation gives procurement decisions a temporal dimension: early purchasing may hedge against future price increases but can increase inventory holding exposure, while delayed purchasing may reduce storage burden but increase vulnerability to price spikes and delivery delays.
Environmental compliance is measured by Equation (15). The emission score aggregates equipment-related emissions through , material procurement emissions through , and labor-associated operational emissions through . The limit represents the allowable period-level environmental burden or carbon budget. Including this constraint prevents the cost-control mechanism from selecting low-cost but environmentally excessive strategies, such as overusing high-emission equipment or concentrating material deliveries without considering carbon impacts. The equation is also consistent with the increasing use of carbon-aware pricing and low-carbon coordination mechanisms in modern multi-energy systems [2].
Emergency recovery allocation is bounded in Equation (16). The recovery resource can be activated only when a disruption indicator is present. The agent-specific upper bound limits the emergency capacity of each decision-making unit, while the system-level bound prevents all agents from consuming more recovery resources than are available. This formulation is useful for modeling expedited procurement, temporary labor reinforcement, emergency equipment rental, additional supervision, and accelerated repair actions. Recovery resources can reduce delays after disruption, but their cost is penalized in the objective and reward functions.
State evolution is summarized by Equation (17). The global construction state contains progress, inventory, resource, budget, weather, logistics, price, and risk information at period t. Each agent contributes an action , and the stochastic disturbance vector represents newly realized uncertainty before the next period. The transition function may be implemented through a simulator, historical data-driven environment, or hybrid engineering rule base. By explicitly combining agent actions and stochastic disturbances, the equation establishes the Markovian foundation required for reinforcement learning while preserving the physical construction constraints defined above.
4. Methodology
4.1. Cooperative Multi-Agent Learning Formulation
The smart grid construction cost-control problem is formulated as a cooperative multi-agent Markov game rather than as a centralized single-controller problem. The agents include procurement management, construction scheduling, equipment allocation, and supervision-control agents. Each agent receives a role-specific partial observation, selects feasible actions under its own operational authority, and is rewarded through a mixture of local departmental performance and global project-level cost-delay-risk performance. This differs from generic hierarchical RL and distributed maintenance-scheduling models because the lower-level policies here are not maintenance crews or asset-service policies; they are construction-management stakeholders whose actions directly affect material arrival, task execution, equipment idleness, safety inspection, recovery spending, and budget overrun. The proposed learning framework combines Q-learning, DQN, PPO, and centralized-training/decentralized-execution MARL concepts [20,21,23,29,30,31].
The Markov game definition in Equation (18) formalizes the decentralized construction-control environment. The set denotes the global state space, is the observation space of agent n, is the corresponding feasible action space, P is the transition probability, is the reward function, and is the discount factor. The state vector combines progress , inventory , labor availability , equipment status , weather condition , transportation condition , market prices , and budget state . Such a representation allows cost overruns to be interpreted as the consequence of coupled engineering, economic, and environmental state transitions.
Equation (19) formalizes partial observability. The mapping extracts the slice of information that agent n can access from the global state, and the additive term captures reporting delay, sensing error, and other imperfections.
The content of the observation naturally depends on the role of the agent. Procurement agents focus more on inventory, prices, and supplier lead time; scheduling agents care about progress, precedence, and labor status; supervisors may pay more attention to compliance and risk. This separation is much closer to real project practice than assuming that every participant instantly observes the full project state. Table 6 summarizes the observation variables, discrete decisions, continuous controls, and coupling channels assigned to each agent.
Table 6.
Agent configuration, observation content, and action-space implementation.
The action vector is implemented as a mixed decision vector . The DQN branch evaluates the discrete subset , whereas the PPO branch parameterizes the continuous subset after feasibility projection onto . This mixed representation is the main algorithmic reason for using a hybrid DQN–PPO mechanism instead of a pure MAPPO, MADDPG, QMIX, or HAPPO baseline. Pure MAPPO and HAPPO can handle cooperative policy optimization but do not explicitly separate discrete construction decisions from continuous recovery intensities; MADDPG and TD3-family methods are more natural for continuous actions; and QMIX requires a value-factorization assumption that is restrictive when safety-control and procurement actions produce nonmonotonic effects on global cost-overrun risk.
Feasible decision-making is characterized by Equation (20). The action vector may contain task acceleration or deceleration, procurement order adjustment, labor reassignment, equipment dispatching, safety-control strengthening, or recovery-resource activation. The matrix and state-dependent right-hand side encode operational constraints faced by agent n, while and define component-wise lower and upper bounds. Because depends on , the feasible action set changes with budget status, resource availability, weather condition, material inventory, and project progress. This avoids unrealistic actions during disruption periods.
Equation (21) blends local and global incentives. Each agent receives a reward composed of its own immediate performance term and the shared project-level signal , with the mixing weight controlled by .
This balance is important. If is too small, agents may behave selfishly and optimize only their own department. If it is too large, all agents may ignore local structure and respond too similarly. The global penalty includes budget overrun, delay, idle loss, recovery cost, safety risk, and environmental impact, so the reward mechanism becomes the main channel through which collaboration is learned. Table 7 lists the reward components and their roles in cooperative learning.
Table 7.
Hierarchical reward components and parameter roles.
4.2. Hybrid Learning, Coordination, Risk, and Convergence Mechanisms
The hybrid learning mechanism was implemented under centralized training and decentralized execution. During training, the critic and reward-evaluation modules access the global construction state and joint action to evaluate cost, delay, idle loss, recovery expenditure, safety risk, and emission consequences. During execution, each agent observes only its role-specific observation vector and the shared coordination signal. This design contrasts with enhanced TD3-based energy scheduling and DER coordination studies, where the decision objects are primarily continuous energy-control variables [25,26]. In the present construction setting, important actions are mixed: some are categorical managerial decisions and others are continuous allocation intensities.
Equation (22) gives the temporal-difference learning rule for the Q-network. The online estimator is updated toward a bootstrapped target formed by the immediate reward and the discounted value from the target network .
This is the value-based component of the hybrid learning architecture. It is particularly useful when procurement timing, task prioritization, or acceleration choices are modeled as discrete or discretized actions [30]. The step size is controlled by .
The soft update in Equation (23) is introduced mainly for numerical stability. Instead of replacing the target-network parameters all at once, the model moves only part of the way toward , with the step controlled by . Table 8 lists the neural-network modules used in the hybrid implementation.
Table 8.
Neural-network architecture used in the hybrid DQN–PPO implementation.
Table 9 reports the training hyperparameters and the corresponding selection criteria.
Table 9.
Training hyperparameters and selection criteria.
Table 10 gives the stepwise pseudocode for the cooperative hybrid DQN–PPO procedure.
Table 10.
Pseudocode of the cooperative hybrid DQN–PPO algorithm.
A small smoothing factor damps oscillation when multiple agents are learning at the same time. That is useful here because the construction environment is nonstationary not only because of exogenous disturbances, but also because other agents keep changing their policies.
Equation (24) specifies how the replay buffer is sampled. Transitions with larger temporal-difference error are more likely to be revisited, which is why the sampling probability depends on . The small constant prevents any experience from becoming unsampleable.
A second ingredient is the importance weight , which corrects the bias created by prioritized sampling. This mechanism is useful in the present application because rare disruptions—supplier failures, severe weather, or extreme bottlenecks—often generate the most informative learning signals.
Equation (25) is the policy-gradient side of the hybrid algorithm. The ratio term compares the new policy with the old one, and the clipped objective keeps this update from moving too far in a single step [31].
The advantage estimate tells the optimizer whether the sampled action was better or worse than expected. In this paper, PPO is helpful for smoother adjustment of continuous decisions such as labor allocation shares, equipment deployment levels, or recovery-resource quantities.
Decentralized policy improvement is expressed in Equation (26). The gradient of agent n depends on the likelihood of its selected action and a centralized advantage function that evaluates the joint state–action configuration. This structure is compatible with centralized training and decentralized execution, where global information is used during training but each agent acts using its own observation during deployment [21]. The joint action vector captures interactions among procurement, scheduling, equipment, and supervision decisions. As a result, the gradient update can reward actions that appear locally costly but improve global coordination, such as early procurement before a predicted supply disruption.
Exploration intensity is adaptively controlled by Equation (27). The baseline exploration probability decays exponentially from toward at rate , supporting broad search during early training and more stable exploitation later. The uncertainty-responsive term increases exploration when the estimated disturbance intensity rises. The clipping operator keeps within . In construction applications, such adaptive exploration is useful because the agent may need to test alternative recovery strategies when unfamiliar combinations of weather, price, labor, and transportation uncertainty appear.
Equation (28) introduces a simple hierarchy into the multi-agent structure. A coordinator policy produces the shared signal , and each lower-layer agent then combines that signal with its local observation before acting.
The idea is intuitive from a construction-management standpoint. Project-wide priorities such as delay recovery, cost containment, or safety reinforcement are first communicated at the upper level, while detailed department-specific responses are determined locally. This reduces coordination burden and helps keep the decentralized policies aligned.
Equation (29) generates correlated uncertainty rather than isolated shocks. The disturbance vector is built from the mean term plus a covariance-driven perturbation constructed through the factor matrix and the standard normal vector .
This choice is important for realism. In construction systems, disruptions are often coupled: bad weather may reduce labor productivity and worsen transport conditions at the same time, while market stress may co-occur with supplier delay. A covariance-based generator lets the simulation reproduce such compound events.
Equation (30) moves the analysis beyond average performance. The empirical distribution summarizes how likely a total cost overrun smaller than z is across the simulated trajectories, while measures the expected severity of the tail beyond the confidence level [32].
That tail perspective is critical in infrastructure planning because a small number of compound disruptions can dominate the financial exposure of the whole project portfolio. The auxiliary threshold is the usual value-at-risk decision variable embedded inside the CVaR expression.
Finally, Equation (31) defines a practical convergence diagnostic. It combines three ingredients: improvement of the global objective between successive episodes, policy movement measured by average Kullback–Leibler divergence, and unilateral deviation incentive under the current joint policy.
The first two terms capture numerical stabilization. The third term has a more game-theoretic flavor: if one agent can still switch to another policy and gain significantly while the other agents keep their policies fixed, then the learned coordination is not yet stable. Training is declared converged when the combined indicator falls below the tolerance .
The design is also consistent with the broader smart-grid and energy-AI literature. The system context follows smart-grid development, grid-resilience, hydrogen, solar-electric-vehicle, green-hydrogen, and AI-for-science studies [33,34,35,36,37,38]. The benchmark and baseline design also connects to adjacent studies on hydropower storage valuation, wind-system operational risk, genetic algorithms, and model-free voltage calculation [39,40,41,42]. Algorithmically, the implementation is aligned with double Q-learning, actor–critic learning, deterministic policy gradients, prioritized replay, power-system RL reviews, multi-energy-hub MARL, and safe RL for energy-management and dispatch applications [43,44,45,46,47,48,49,50].
5. Results
5.1. Experimental Data and Evaluation Settings
The experimental evaluation uses a hybrid empirical-calibrated simulation environment. It is not a purely synthetic toy environment, because the initial project states, feature distributions, disturbance magnitudes, resource bounds, weather-productivity relationships, procurement lead-time statistics, and budget/schedule baselines are parameterized from representative smart grid construction projects in Henan Province, China. At the same time, the learning environment is not a direct replay of confidential project records; it generates counterfactual disturbance trajectories and agent interventions through the construction simulator. The dataset covers 42 infrastructure projects completed or planned between 2018 and 2025, including 500 kV transmission lines, 220 kV digital substations, renewable-energy-connected substations, and intelligent grid modernization projects. The total investment scale reaches RMB 18.60 billion, while the single-project budget ranges from RMB 0.096 billion to RMB 1.42 billion. Table 11 summarizes the portfolio used to parameterize the simulation environment.
Table 11.
Construction dataset composition and portfolio scale.
The construction-state dataset contains 1.87 million daily records. More than 130 engineering features were extracted from project execution logs, procurement records, labor allocation reports, equipment utilization statistics, weather observations, regional transportation data, and market price information. Table 12 reports the resulting feature groups. The largest group is environmental disturbance, which accounts for 30 features and reflects the importance of weather, logistics, and regional operating conditions in smart grid construction cost dynamics.
Table 12.
Feature categories used in the construction-state representation.
Table 13 distinguishes real project records, estimated variables, simulated disturbance trajectories, and counterfactual policy outputs.
Table 13.
Relationship between real project data, estimated variables, and simulated disturbance trajectories.
Table 14 summarizes preprocessing, split construction, anomaly treatment, and leakage-prevention checks.
Table 14.
Preprocessing, train/validation/test split, and anomaly handling.
Dynamic uncertainty was calibrated using three disturbance levels: normal, moderate, and severe. Weather information was collected from 17 meteorological stations and converted into construction efficiency coefficients. Transportation delays were extracted from regional logistics records and material delivery reports. Table 15 shows the disturbance parameters used in the environment, and Table 16 documents the corresponding scenario-calibration procedure. Under severe disturbance, the weather efficiency coefficient decreases to 0.48, the average transportation delay increases to 9.6 days, and supply-chain interruption probability reaches 28%. These values create compound conditions under which static construction schedules are expected to become fragile.
Table 15.
Dynamic uncertainty calibration for the construction environment.
Table 16.
Disturbance-scenario calibration procedure.
Table 17 lists the main computational and reinforcement learning settings. The environment generates approximately 320 million agent–environment transitions during training, and the replay buffer stores 8 million historical interaction samples. Each training episode corresponds to one complete construction lifecycle ranging from 180 to 720 simulated days. The model architecture contains 24.7 million trainable parameters, including agent-specific networks, target networks, and hierarchical coordination modules.
Table 17.
Simulation and reinforcement learning configuration.
Table 18 summarizes the reproducibility and data-availability measures used to support independent assessment without disclosing confidential project records.
Table 18.
Reproducibility and data-availability measures.
Table 19 specifies the artifact-level benchmark package and the role of each shareable component.
Table 19.
Artifact-level reproducibility package for anonymized benchmark release and independent comparison.
Table 20 defines the baseline-configuration and fairness protocol for the comparison experiments.
Table 20.
Baseline-configuration and fairness protocol.
5.2. Overall Cost and Schedule Performance
Table 21 compares the proposed MARL framework with deterministic, heuristic, rolling-horizon, stochastic-optimization, single-agent learning, and modern MARL baselines. The expanded comparison includes rolling-horizon MPC and stochastic/robust optimization as stronger optimization baselines, together with MAPPO, MADDPG/MATD3, QMIX, and HAPPO as contemporary MARL benchmarks. The proposed method achieves the lowest cost-overrun rate, average cost overrun, and schedule deviation across all reported methods. Relative to rule-based construction management, the cost-overrun rate decreases from 8.40% to 6.83%, corresponding to an 18.7% reduction. The average schedule deviation decreases from 21.40 days to 16.82 days, corresponding to a 21.4% reduction. Relative to the strongest additional MARL comparator, HAPPO, the proposed hybrid DQN–PPO framework further reduces the mean cost-overrun rate by 0.15 percentage points and the mean schedule deviation by 0.24 days. This improvement is operationally meaningful because the proposed architecture preserves the discrete nature of procurement, task-acceleration, supplier-switching, and supervision-escalation decisions while retaining PPO-based continuous control for allocation and recovery intensity.
Table 21.
Overall performance comparison under dynamic construction uncertainty, including stronger optimization and modern MARL baselines.
The statistical evaluation protocol in Table 22 formalizes the independent-run analysis used for reinforcement-learning comparison. It uses 30 random seeds per method, common disturbance trajectories across methods, seed-level paired comparisons, 95% confidence intervals obtained by nonparametric bootstrap, and Holm-adjusted Wilcoxon signed-rank tests for multiple comparisons. Because reinforcement-learning outcomes can vary across seeds, point-estimate improvements are interpreted together with the seed-level variability and paired-difference statistics generated by this protocol.
Table 22.
Independent-run statistical evaluation protocol for reinforcement-learning comparison.
Table 23 reports numerical statistics for the main cost and schedule metrics. The confidence intervals are narrow because the paired-seed protocol evaluates all methods under identical held-out disturbance trajectories. The proposed hybrid DQN–PPO MARL framework has the lowest mean and the smallest standard deviation for both metrics. The adjusted p-values remain below 0.05 against all baselines after Holm correction, including the strongest additional baseline, HAPPO. This result confirms that the improvement is not only a single point-estimate difference but also a stable seed-level advantage under repeated stochastic training and testing.
Table 23.
Seed-level statistical results for the two main performance metrics across 30 paired random seeds.
Table 24 extends the statistical reporting to monetary overrun, tail risk, and learning return. The proposed framework reduces the mean monetary overrun from RMB 37.20 million under rule-based management to RMB 30.24 million, and it reduces the CVaR95 cost-overrun rate from 13.92% to 9.68%. Among learning methods, the proposed framework also achieves the highest final episodic return and the smallest return dispersion. The risk-statistic pattern is consistent with the reward construction because the policy is penalized for overrun propagation, emergency recovery cost, idleness, and delay simultaneously rather than minimizing only the expected cost component.
Table 24.
Additional risk, monetary, and learning statistics under the same 30-seed protocol.
Figure 3 illustrates the cumulative construction cost trajectory of a representative large-scale project. The planned budget reaches RMB 3.80 billion at the end of the 360-day lifecycle, while the proposed MARL trajectory terminates at approximately RMB 4.06 billion. Although all methods exceed the planned budget because of disturbance-induced recovery costs and final-stage settlement costs, the proposed MARL curve remains closest to the planned budget throughout the middle and late stages. The gap is especially visible after day 180, where procurement, labor, and equipment decisions become more tightly coupled. The rule-based and MILP curves rise more aggressively after day 240, suggesting that static or partially static scheduling decisions are unable to absorb accumulated disruption pressure.
Figure 3.
Cumulative construction cost trajectories for the planned budget and five decision-making methods over a representative 360-day construction lifecycle.
Figure 4 further reports portfolio-level cumulative cost overrun in million RMB and explicitly marks the three main disruption windows. Heavy rainfall, supply-chain interruption, and labor shortage all cause noticeable slope changes in the overrun trajectories. The rule-based method reaches a final cumulative overrun of 37.2 million RMB, while the proposed MARL framework reaches 30.2 million RMB. The result indicates that the proposed framework does not eliminate all cost escalation, but it reduces the propagation speed of overrun after each disruption. In particular, the MARL curve grows more slowly during the supply-chain interruption period around days 175–205 and remains below the other baselines before the final labor shortage period.
Figure 4.
Cumulative cost overrun trajectory under sequential heavy-rainfall, supply-chain, and labor-shortage disruptions.
5.3. Robustness Under Disturbance Scenarios and Project Scaling
Figure 5 evaluates robustness under six disturbance scenarios. The proposed MARL curve remains the lowest across all scenarios, including the combined extreme case. Under normal conditions, the proposed method produces a 4.90% cost overrun rate, compared with 6.10% for the rule-based baseline. Under the combined extreme scenario, the rule-based method increases to 14.70%, while the proposed MARL framework remains at 8.60%. The smaller slope of the MARL curve shows that the learned policy is less sensitive to material price spikes, labor shortages, severe weather, and transportation congestion. This behavior is consistent with the reward design, which penalizes not only direct overrun but also delay, idle resources, and recovery expenditure.
Figure 5.
Robustness of cost overrun performance under normal, single-disturbance, and combined extreme scenarios.
Figure 6 shows cost overrun performance across small-scale, medium-scale, large-scale, and integrated mega-project settings. The cost overrun rate increases for all methods as project complexity grows, which is expected because larger projects involve more task dependencies, more resource interactions, and longer exposure to stochastic disturbances. However, the proposed MARL framework exhibits the flattest growth pattern. In the integrated mega-project case, the cost overrun rate is 9.10% for the proposed MARL framework and 13.20% for the rule-based method. This 31.1% relative reduction demonstrates that multi-agent coordination becomes more valuable as project scale and resource coupling increase.
Figure 6.
Cost overrun performance across different smart grid project scales.
Figure 7 analyzes the 95% conditional value-at-risk (CVaR95) of cost overrun under increasing uncertainty intensity. The proposed MARL framework has the lowest tail-risk curve and keeps CVaR95 below 10% even when the uncertainty intensity coefficient reaches 1.0. In contrast, the rule-based baseline increases from 8.90% to 18.10%, and the single-agent DRL baseline increases from 7.50% to 13.40%. The tail-risk gap at the highest uncertainty level shows that the proposed policy is not only effective on average but also more resilient against severe adverse outcomes. This is important for infrastructure investment because rare compound disruptions can dominate financial exposure.
Figure 7.
Tail-risk reduction under increasing construction uncertainty, measured by CVaR95 of cost overrun.
5.4. Sensitivity Analysis of Reward Weights and Uncertainty Levels
The sensitivity analysis evaluates whether the proposed policy is robust to changes in the main reward-function parameters and disturbance intensity. The purpose is not to retune the policy for every test condition, but to verify that the learned coordination mechanism is not driven by one arbitrary scalar weight. Table 25 summarizes the parameter-sweep design.
Table 25.
Sensitivity-analysis protocol for reward weights and uncertainty levels.
5.5. Learning Convergence and Multi-Agent Coordination
Figure 8 reports the learning convergence of DQN-only, PPO-only, single-agent DRL, and the proposed MARL framework. All reinforcement learning methods improve as training progresses, but the proposed MARL curve reaches a higher final episodic return. At 15,000 episodes, the proposed MARL framework converges to −1820, compared with −2520 for single-agent DRL, −2780 for PPO-only, and −3050 for DQN-only. The shaded band around the MARL curve narrows during training, indicating improved stability across training iterations. The vertical marker at 8000 episodes shows the transition to a stable learning phase, after which the return improvement becomes incremental rather than volatile.
Figure 8.
Training convergence comparison of reinforcement learning models.
Figure 9 examines the emergence of multi-agent coordination during training. The global coordination index increases from 0.18 at the beginning of training to 0.87 after 15,000 episodes. Pairwise coordination also improves: scheduling–equipment coordination reaches 0.89, procurement–scheduling coordination reaches 0.86, and procurement–supervision coordination reaches 0.78. At the same time, inter-agent conflict frequency decreases from 0.78 to 0.09. The opposite movement of the coordination curves and the conflict curve confirms that the framework learns cooperative behavior rather than merely optimizing isolated agent rewards. Operationally, this means that procurement timing, task scheduling, equipment deployment, and supervision actions become increasingly synchronized as training proceeds.
Figure 9.
Emergence of multi-agent coordination and reduction of inter-agent conflict frequency during reinforcement learning.
5.6. Ablation Analysis
The ablation results in Table 26 and Figure 10 quantify the contribution of individual modules in the proposed framework. Removing stochastic training produces the largest deterioration, increasing the cost overrun rate from 6.83% to 8.15% and increasing schedule deviation from 16.82 days to 19.85 days. Removing the hierarchical reward also produces a large performance loss, with a cost overrun rate of 7.92% and a schedule deviation of 19.12 days. These results indicate that dynamic uncertainty exposure and multi-objective reward shaping are both essential for robust cost-control behavior. Removing multi-agent coordination, PPO clipping, or prioritized replay also weakens performance, but the magnitude is smaller than the loss caused by eliminating stochastic training or the hierarchical reward.
Table 26.
Ablation results for the proposed MARL framework.
Figure 10.
Ablation study of the proposed MARL framework under dynamic construction uncertainty.
5.7. Transferability to Other Regions and Infrastructure Projects
The framework is transferable as a modeling and learning architecture, but the calibrated parameters are region- and project-specific. Applying the method outside Henan Province or outside smart grid construction requires recalibration of disturbance distributions, cost coefficients, resource constraints, labor productivity, supplier reliability, transport accessibility, safety rules, and project-governance responsibilities. Table 27 summarizes the transferability conditions and recalibration requirements.
Table 27.
Transferability scope and recalibration requirements.
Overall, the result section demonstrates four empirical patterns. First, the proposed MARL framework reduces both average cost overrun and schedule deviation compared with deterministic, heuristic, and single-agent learning baselines. Second, robustness improves as disturbance severity increases, particularly in combined extreme scenarios. Third, training dynamics show stable convergence and the progressive emergence of inter-agent coordination. Fourth, the ablation analysis verifies that stochastic training, hierarchical reward design, and multi-agent coordination are not cosmetic additions but core mechanisms supporting dynamic cost overrun mitigation.
6. Conclusions
This study developed a cooperative MARL framework for simulation-based cost-overrun mitigation in smart grid construction projects. The formulation models procurement management, construction scheduling, equipment allocation, and supervision-control as interacting agents in a cooperative Markov game. The mathematical model connects budget balance, task precedence, resource allocation, material inventory, contractor synchronization, safety compliance, environmental constraints, emergency recovery, and stochastic state transitions. The implementation combines DQN for discrete construction-management decisions, PPO for continuous resource and recovery decisions, prioritized replay, centralized-training/decentralized-execution policy improvement, hierarchical reward evaluation, correlated disturbance generation, and CVaR-oriented risk monitoring.
The scientific contribution is established through five integrated elements. First, the literature positioning distinguishes the study from construction RL, multi-agent scheduling, safe RL for power-grid resilience, adaptive dynamic programming for resilient control, hierarchical maintenance scheduling, integrated capacity planning, and modern MARL algorithms including MAPPO, MADDPG/MATD3, QMIX, HAPPO, and TD3-family methods. Second, the data-simulation relationship is explicit: real project records calibrate the environment, whereas counterfactual learning trajectories are generated by a simulator. Third, the implementation description specifies agent observations, mixed action spaces, network architecture, hyperparameters, pseudocode, reward components, training process, baseline fairness, and reproducibility requirements. Fourth, the evaluation framework reports means, standard deviations, bootstrap confidence intervals, Holm-adjusted nonparametric significance tests, risk statistics, sensitivity-analysis design, and transferability conditions. Fifth, the reproducibility design defines artifact-level access to anonymized synthetic benchmarks, configuration files, seed lists, baseline templates, and aggregated logs while protecting confidential project records.
The experimental results show that the proposed hybrid DQN–PPO MARL framework achieves a mean cost-overrun rate of 6.83% and an average schedule deviation of 16.82 days under the stated disturbance settings, corresponding to 18.7% lower cost overrun and 21.4% lower schedule deviation than rule-based construction management. The paired-seed statistical analysis confirms that the performance advantage remains significant against deterministic optimization, rolling-horizon MPC, stochastic/robust optimization, single-agent DRL, MAPPO, MADDPG/MATD3, QMIX, and HAPPO baselines. The combined evidence demonstrates that decentralized coordination, stochastic disturbance exposure, hierarchical reward design, and mixed discrete-continuous action modeling improve construction cost-control decision support for smart grid infrastructure projects. Operational deployment requires integration with live digital-twin feedback, contract-level risk allocation, cybersecurity and auditability controls, human approval workflows, and cross-regional recalibration for larger infrastructure portfolios.
Author Contributions
Conceptualization, Y.L. and Z.T.; methodology, N.L. and Z.T.; software, N.L.; validation, X.N., P.L. and H.L.; formal analysis, N.L. and Y.L.; investigation, Y.L., X.N. and P.L.; resources, H.L. and R.D.; data curation, P.L., R.D. and N.L.; writing—original draft preparation, N.L. and Y.L.; writing—review and editing, Z.T., H.L., X.N. and R.D.; visualization, N.L.; supervision, Z.T.; project administration, H.L. and Z.T.; funding acquisition, Z.T. and H.L. All authors have read and agreed to the published version of the manuscript.
Funding
This work was supported by the Science and Technology Project of State Grid Henan Electric Power Company (Project No. 5217L026000B).
Data Availability Statement
The raw project-level construction logs, procurement records, and operational data are not publicly released because they contain confidential engineering, procurement, and project-management information. To improve reproducibility, this article reports aggregated portfolio statistics, feature groups, disturbance calibration, algorithmic pseudocode, network architecture, hyperparameters, baseline configurations, statistical results, and artifact-level reproducibility measures. Subject to institutional approval and data-governance constraints, the authors will provide an anonymized synthetic benchmark, configuration files, random-seed lists, baseline templates, documentation files, and aggregated training logs that reproduce the reported state dimensions, disturbance classes, seed-level statistics, and comparison protocol.
Acknowledgments
The authors thank the engineering, procurement, scheduling, equipment-management, and supervision teams who provided aggregated project insights and domain expertise for calibrating the construction-simulation environment.
Conflicts of Interest
Authors Yongjie Li, Xin Niu, and Peng Li were employed by State Grid Henan Economic Research Institute. Authors Hua Liu and Ruoxi Dong were employed by State Grid Henan Electric Power Company. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.
Abbreviations
The following abbreviations are used in this manuscript:
| AI | Artificial intelligence |
| CVaR | Conditional value-at-risk |
| DQN | Deep Q-network |
| DRL | Deep reinforcement learning |
| GA | Genetic algorithm |
| GAE | Generalized advantage estimation |
| HAPPO | Heterogeneous-agent proximal policy optimization |
| LLM | Large language model |
| MADDPG | Multi-agent deep deterministic policy gradient |
| MAPPO | Multi-agent proximal policy optimization |
| MARL | Multi-agent reinforcement learning |
| MILP | Mixed-integer linear programming |
| MPC | Model predictive control |
| PEM | Proton exchange membrane |
| PPO | Proximal policy optimization |
| QMIX | Monotonic value-factorization MARL |
| TD3 | Twin delayed deep deterministic policy gradient |
| VPP | Virtual power plant |
References
- Li, Z.; Hilber, P.; Li, Z.; Laneryd, T.; Ivanell, S. Temporally coordinated operation of green multi-energy airport microgrids with climatic correlations and flexible loads via decomposed stochastic programming. IEEE Trans. Sustain. Energy 2025, 17, 1909–1922. [Google Scholar] [CrossRef] [Scilit]
- Chen, J.; Wu, P.; Chen, W.; Guerrero, J.M.; Niu, Z.; Li, Z. Two-layer coordinated operation of multi-energy system considering carbon-oriented collaborative pricing mechanism via two-stage stochastic programming approach. Appl. Energy 2026, 406, 127298. [Google Scholar] [CrossRef] [Scilit]
- Feng, C.; Huang, Z.; Lin, J.; Wang, L.; Zhang, Y.; Wen, F. Aggregation model and market mechanism for virtual power plant participation in inertia and primary frequency response. IEEE Trans. Power Syst. 2026, 41, 2101–2117. [Google Scholar] [CrossRef] [Scilit]
- Wang, Y.; Xie, D.; Shi, C.; Wang, X. Dynamic construction strategy for virtual power plants considering distributed energy resource interaction uncertainty and response recovery process. IEEE Trans. Ind. Appl. 2026, 1–12. [Google Scholar] [CrossRef] [Scilit]
- Wang, X.; Ke, J.; Wu, H.; Dong, Y.; Jiang, C.; Huang, W.; Zhang, S. A robust safe reinforcement learning approach for power grid resilience enhancement against typhoons via distributed energy resource flexibility aggregation. IEEE Trans. Ind. Appl. 2025, 62, 3545–3556. [Google Scholar] [CrossRef] [Scilit]
- Zhong, M.; Zhang, J.; Zheng, G.; Liu, H. Data-driven model-free adaptive dynamic programming resilient control for nonlinear networked control systems under DoS attacks. IEEE Trans. Cybern. 2025, 55, 5700–5713. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Flyvbjerg, B.; Holm, M.S.; Buhl, S. Underestimating costs in public works projects: Error or lie? J. Am. Plan. Assoc. 2002, 68, 279–295. [Google Scholar] [CrossRef] [Scilit]
- Creedy, G.D.; Skitmore, M.; Wong, J.K.W. Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. J. Constr. Eng. Manag. 2010, 136, 528–537. [Google Scholar] [CrossRef] [Scilit]
- Birge, J.R.; Louveaux, F. Introduction to Stochastic Programming, 2nd ed.; Springer: New York, NY, USA, 2011. [Google Scholar] [CrossRef] [Scilit]
- Bertsimas, D.; Tsitsiklis, J.N. Introduction to Linear Optimization; Athena Scientific: Belmont, MA, USA, 1997. [Google Scholar]
- Puterman, M.L. Markov Decision Processes: Discrete Stochastic Dynamic Programming; Wiley: New York, NY, USA, 1994. [Google Scholar]
- Sutton, R.S.; Barto, A.G. Reinforcement Learning: An Introduction, 2nd ed.; MIT Press: Cambridge, MA, USA, 2018. [Google Scholar]
- Kedir, N.S.; Somi, S.; Fayek, A.R.; Nguyen, P.H.D. Hybridization of reinforcement learning and agent-based modeling to optimize construction planning and scheduling. Autom. Constr. 2022, 142, 104498. [Google Scholar] [CrossRef] [Scilit]
- Yao, Y.; Tam, V.W.Y.; Wang, J.; Le, K.N.; Butera, A. Automated construction scheduling using deep reinforcement learning with valid action sampling. Autom. Constr. 2024, 166, 105622. [Google Scholar] [CrossRef] [Scilit]
- Lu, Y.; You, K.; Wang, Y.; Liu, Y.; Zhou, C. Deep reinforcement learning for automated scheduling of mining earthwork equipment with spatio-temporal safety constraints. Front. Eng. Manag. 2025, 12, 39–58. [Google Scholar] [CrossRef] [Scilit]
- Koszykowski, M. Machine learning in project schedule creation: A systematic literature review. J. Sched. 2026, 29, 21–38. [Google Scholar] [CrossRef] [Scilit]
- Gao, Y.; Li, X.; Zhang, J.; Chen, Y. Artificial intelligence in construction project management: A systematic literature review of cost, time, and safety management. Buildings 2026, 16, 1061. [Google Scholar] [CrossRef] [Scilit]
- Xiang, L.; Tan, Y.; Shen, G.; Jin, X. Applications of multi-agent systems from the perspective of construction management: A literature review. Eng. Constr. Archit. Manag. 2022, 29, 3288–3310. [Google Scholar] [CrossRef] [Scilit]
- Binyamin, S.S.; Ben Slama, S. Multi-agent systems for resource allocation and scheduling in a smart grid. Sensors 2022, 22, 8099. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Yu, C.; Velu, A.; Vinitsky, E.; Gao, J.; Wang, Y.; Bayen, A.M.; Wu, Y. The surprising effectiveness of PPO in cooperative multi-agent games. In Proceedings of the Advances in Neural Information Processing Systems; Curran Associates, Inc.: Red Hook, NY, USA, 2022; Volume 35, pp. 24611–24624. [Google Scholar]
- Lowe, R.; Wu, Y.; Tamar, A.; Harb, J.; Abbeel, P.; Mordatch, I. Multi-agent actor-critic for mixed cooperative-competitive environments. In Proceedings of the Advances in Neural Information Processing Systems; Curran Associates, Inc.: Red Hook, NY, USA, 2017; Volume 30. [Google Scholar]
- Rashid, T.; Samvelyan, M.; de Witt, C.S.; Farquhar, G.; Foerster, J.; Whiteson, S. QMIX: Monotonic value function factorisation for deep multi-agent reinforcement learning. In Proceedings of the 35th International Conference on Machine Learning; PMLR: Stockholm, Sweden, 2018; Volume 80, pp. 4295–4304. [Google Scholar]
- Kuba, J.G.; Chen, R.; Wen, M.; Wen, Y.; Sun, F.; Wang, J.; Yang, Y. Trust region policy optimisation in multi-agent reinforcement learning. In Proceedings of the International Conference on Learning Representations, Virtual Event, 25 April 2022; OpenReview.net: Amherst, MA, USA, 2022. [Google Scholar]
- Ackermann, J.; Gabler, V.; Osa, T.; Sugiyama, M. Reducing overestimation bias in multi-agent domains using double centralized critics. arXiv 2019, arXiv:1910.01465. [Google Scholar]
- Imtiaz, S.; Yang, L.; Naz, M.N.; Munir, H.M.; Altaf, M.W.; Mohammed, M.S.A. Enhanced TD3 multi-agent reinforcement learning approach for distributed energy resource coordination in active distribution network. Appl. Soft Comput. 2026, 199, 115348. [Google Scholar] [CrossRef] [Scilit]
- Wan, A.; Xiong, Z.; Al-Bukhaiti, K.; Yin, R.; Yuan, J.; Cheng, X.; Ji, X. An integrated TCN-ECA-BiLSTM and TD3 framework for high-accuracy forecasting and optimal load allocation in combined heat and power systems. Energy 2026, 350, 140670. [Google Scholar] [CrossRef] [Scilit]
- Zhang, D.; Hu, Y.; Zhang, S.; Zhang, Y. Distributed hierarchical reinforcement learning for dynamic maintenance scheduling of large-scale airline fleets. Reliab. Eng. Syst. Saf. 2026, 271, 112249. [Google Scholar] [CrossRef] [Scilit]
- Hu, X.; Wang, Y.; Vanhoucke, M.; Zhou, Z.; Wang, J. Integrated capacity planning and multi-project scheduling considering resource transfer and idleness. Int. J. Prod. Res. 2026, 64, 3445–3468. [Google Scholar] [CrossRef] [Scilit]
- Watkins, C.J.C.H.; Dayan, P. Q-learning. Mach. Learn. 1992, 8, 279–292. [Google Scholar] [CrossRef] [Scilit]
- Mnih, V.; Kavukcuoglu, K.; Silver, D.; Rusu, A.A.; Veness, J.; Bellemare, M.G.; Graves, A.; Riedmiller, M.; Fidjeland, A.K.; Ostrovski, G.; et al. Human-level control through deep reinforcement learning. Nature 2015, 518, 529–533. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Schulman, J.; Wolski, F.; Dhariwal, P.; Radford, A.; Klimov, O. Proximal policy optimization algorithms. arXiv 2017, arXiv:1707.06347. [Google Scholar]
- Rockafellar, R.T.; Uryasev, S. Optimization of conditional value-at-risk. J. Risk 2000, 2, 21–42. [Google Scholar] [CrossRef] [Scilit]
- Farhangi, H. The path of the smart grid. IEEE Power Energy Mag. 2010, 8, 18–28. [Google Scholar] [CrossRef] [Scilit]
- Hou, Y.; Zhao, A.P.; Tao, Q.; Li, J.; Hernando-Gil, I.; Li, X.; Xie, D. Complex systems engineering for grid resilience: Insights from the 2025 Iberian blackout. Renew. Sustain. Energy Rev. 2026, 235, 116976. [Google Scholar] [CrossRef] [Scilit]
- Zhao, A.P.; Li, S.; Xie, D.; Wang, Y.; Li, Z.; Hu, P.J.-H.; Zhang, Q. Hydrogen as the nexus of future sustainable transport and energy systems. Nat. Rev. Electr. Eng. 2025, 2, 447–466. [Google Scholar] [CrossRef] [Scilit]
- Li, T.T.; Zhao, A.P.; Wang, Y.; Li, S.; Fei, J.; Wang, Z.; Xiang, Y. Integrating solar-powered electric vehicles into sustainable energy systems. Nat. Rev. Electr. Eng. 2025, 2, 467–479. [Google Scholar] [CrossRef] [Scilit]
- Chen, H.; Xu, M.; Shi, C.; Wang, Z.; Xie, D. Data–model hybrid hierarchical scheduling for grid-connected PEM green hydrogen production in multi-energy systems with LLM-aided coordination. J. Renew. Sustain. Energy 2026, 18, 024701. [Google Scholar] [CrossRef] [Scilit]
- Zhao, A.P.; Li, S.; Cao, Z.; Hu, P.J.-H.; Wang, J.; Xiang, Y.; Xie, D.; Lu, X. AI for science: Predicting infectious diseases. J. Saf. Sci. Resil. 2024, 5, 130–146. [Google Scholar] [CrossRef] [Scilit]
- Chen, X.; Liu, Y.; Zhong, Z.; Fan, N.; Zhao, Z.; Wu, L. A carryover storage valuation framework for medium-term cascaded hydropower planning: A Portland General Electric system study. IEEE Trans. Sustain. Energy 2025, 16, 1903–1918. [Google Scholar] [CrossRef] [Scilit]
- Li, J.; Gu, K.; Zhao, K.; Li, Z.; Dong, Z.Y. A robust and fast operational risk assessment method for composite power systems with high wind power penetration. IEEE Trans. Power Syst. 2026, 41, 2838–2849. [Google Scholar] [CrossRef] [Scilit]
- Goldberg, D.E. Genetic Algorithms in Search, Optimization, and Machine Learning; Addison-Wesley: Reading, MA, USA, 1989. [Google Scholar]
- Wang, Z.; Gu, Z.; Guerrero, J.M.; Shen, Y.; Guo, Z.; Deng, Z.; Huang, C.; Li, Z. Two-period two-layer electrical model-free voltage calculation for active distribution network via improved broad learning system. IEEE Trans. Power Syst. 2026, 41, 2704–2716. [Google Scholar] [CrossRef] [Scilit]
- van Hasselt, H.; Guez, A.; Silver, D. Deep reinforcement learning with double Q-learning. In Proceedings of the Thirtieth AAAI Conference on Artificial Intelligence; AAAI Press: Palo Alto, CA, USA, 2016; Volume 30, pp. 2094–2100. [Google Scholar] [CrossRef] [Scilit]
- Konda, V.R.; Tsitsiklis, J.N. Actor-critic algorithms. In Proceedings of the Advances in Neural Information Processing Systems; MIT Press: Cambridge, MA, USA, 2000; Volume 12, pp. 1008–1014. [Google Scholar]
- Lillicrap, T.P.; Hunt, J.J.; Pritzel, A.; Heess, N.; Erez, T.; Tassa, Y.; Silver, D.; Wierstra, D. Continuous control with deep reinforcement learning. In Proceedings of the International Conference on Learning Representations, San Juan, PR, USA, 2–4 May 2016; OpenReview.net: Amherst, MA, USA, 2016. [Google Scholar]
- Schaul, T.; Quan, J.; Antonoglou, I.; Silver, D. Prioritized experience replay. In Proceedings of the International Conference on Learning Representations, San Juan, PR, USA, 2–4 May 2016; OpenReview.net: Amherst, MA, USA, 2016. [Google Scholar]
- Chen, X.; Qu, G.; Tang, Y.; Low, S.; Li, N. Reinforcement learning for selective key applications in power systems: Recent advances and future challenges. IEEE Trans. Smart Grid 2022, 13, 2935–2958. [Google Scholar] [CrossRef] [Scilit]
- Zhang, G.; Hu, W.; Cao, D.; Zhang, Z.; Huang, Q.; Chen, Z.; Blaabjerg, F. A multi-agent deep reinforcement learning approach enabled distributed energy management schedule for the coordinate control of multi-energy hub with gas, electricity, and freshwater. Energy Convers. Manag. 2022, 255, 115340. [Google Scholar] [CrossRef] [Scilit]
- Hong, S.-H.; Lee, H.-S. Robust energy management system with safe reinforcement learning using short-horizon forecasts. IEEE Trans. Smart Grid 2023, 14, 2485–2488. [Google Scholar] [CrossRef] [Scilit]
- Feng, J.; Ren, Z.; Li, C.; Li, W. A Benders-combined safe reinforcement learning framework for risk-averse dispatch considering frequency security constraints. IEEE Trans. Circuits Syst. II Express Briefs 2025, 72, 1063–1067. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.