From Flexible Workloads to Verifiable Grid Resources: The Next Phase of Electricity–Computing Coordination

,
,
,
and
1
Faculty of Electric Power Engineering, Kunming University of Science and Technology, Kunming 650500, China
2
Faculty of Science, Kunming University of Science and Technology, Kunming 650500, China
*
Author to whom correspondence should be addressed.
This article belongs to the Section Energy Systems

Abstract

Artificial-intelligence (AI) data centres are growing electricity loads and potential sources of demand-side flexibility. Published work establishes that selected workloads can be modulated under specific conditions: a published demonstration on a cluster of 256 graphics processing units (GPUs) reported a 25% power reduction for three hours while maintaining the quality-of-service (QoS) target stated by its authors. That result is cluster-level evidence, not an independently verified whole-facility point-of-common-coupling (PCC) response or firm fleet-wide capacity; much of the wider literature is analytical, simulation-based or trace-based. The unresolved gap is a workload-aware route from potentially shiftable computations to a contractually specified, measured and repeatably deliverable grid service that also accounts for recovery and system impacts. This Perspective makes three contributions: it critically separates nominal potential, observed response and qualified grid delivery; proposes an assessment framework that links task eligibility, service-level agreements (SLAs), component attribution, measurement uncertainty, activation reliability and rebound to established demand-response measurement and verification (M&V); and identifies grid- and emissions-aware validation priorities. A transparent, hypothetical example illustrates why event-level capacity, storage losses, deferred-work rebound and marginal emissions can imply different results. The proposed framework is an agenda for testing and independent verification, not a validated certification standard or demonstrated fleet-wide resource.

1. Introduction: From Facility Efficiency to Grid Service

Artificial-intelligence (AI) demand is turning data centres into consequential electricity users, and it is doing so faster than either the power-system or the computing literature anticipated. Closer coordination of power-system investment and computing infrastructure has become an explicit policy objective [1,2], while surveys of grid integration and data-centre flexibility distinguish the properties often grouped under green computing [3,4]. A lower power usage effectiveness (PUE), a cheap electricity contract or a renewable-energy certificate does not necessarily relieve a congested feeder or reduce the output of the marginal generating unit; capacity-value assessment for aggregated small data centres illustrates why distribution-network location and uncertain participation matter as much as nominal load [5]. Forecasting studies of wind generation, including Yang et al.’s seasonal–trend decomposition using locally estimated scatterplot smoothing (STL) and improved arithmetic optimisation algorithm (IAOA)-tuned iTransformer [6], and of photovoltaic–storage–charging systems [7], provide renewable-availability inputs for dispatch counterfactuals; they do not measure data-centre demand response. Electric-vehicle (EV) Q-network energy management [8] and learning-assisted power-flow control [9] offer adjacent insights into device-level control and protection, rather than evidence of AI workload flexibility. Their relevance here is therefore limited to forecasting inputs and equipment-level safeguards; the central test remains a metered net response at the data-centre point of common coupling (PCC).
Demand-response (DR) measurement and verification (M&V) are not new. Existing practice already uses participant meters, customer baselines, event definitions and performance verification: US Federal Energy Regulatory Commission (FERC) Order No. 745 describes demand response relative to expected consumption and recognises the use of customer-baseline methods by organised markets [10], while the International Performance Measurement and Verification Protocol (IPMVP) provides established approaches for defining measurement boundaries, baselines and adjustments [11,12]. This Perspective does not claim to invent baseline estimation, metering, reliability testing or settlement verification. Its contribution is to adapt and connect these principles for AI data centres, where the eligible resource depends on stochastic job arrivals and task deadlines; a power response must remain within latency, throughput and completion service-level agreements (SLAs); site-level response must be reconciled with information-technology (IT) equipment, cooling, uninterruptible power supply (UPS) reserves, battery energy storage system (BESS) assets and on-site generation; deferred jobs and thermal recovery create post-event rebound; and spatial migration couples sending and receiving nodes through communication capacity, latency and grid constraints. The distinction is operational rather than terminological. IPMVP fixes the measurement boundary, the pre-event baseline and the routine-adjustment procedure [11,12], and FERC Order No. 745 establishes that a demand response is settled against expected consumption [10]; neither instrument needs to be replaced here. What they do not specify is how eligibility should be screened when the eligible resource is a queue of stochastic jobs, how availability should be bounded by latency and completion contracts, how a site-meter response should be decomposed into computing, cooling and storage contributions without double counting, or how deferred work and thermal or storage restoration should be recovered inside the assessment window. The proposed framework therefore adds exactly these four elements—a workload-aware qualification layer—to established M&V practice rather than replacing it.
The remaining research gap is therefore not a lack of optimisation algorithms or baseline formulas, but a lack of an integrated evidence pathway linking computing decisions to qualified grid-facing delivery. Computing studies may establish that jobs can be shifted without testing a registered point-of-common-coupling (PCC) response; cluster, cooling or battery demonstrations may report a local power change without reconciling all subsystems and the full recovery period; and grid or market models may assign value to a response envelope before its repeated SLA-compliant delivery has been demonstrated. These different boundaries are not interchangeable. What is still needed is a contract-specific assessment joining eligibility of stochastic workloads, site-level metering and component attribution, uncertainty-aware repeated activation, and a complete energy and system-impact counterfactual. We propose such a qualification pathway as a Perspective for future field testing; we do not claim to have independently certified it.
This Perspective advances one proposition: electricity–computing coordination should be judged by deliverable flexibility, not by nominally movable workloads. We define deliverable grid-service flexibility as a contractually specified net-load response that (i) is measured at a registered electrical boundary, (ii) respects computing SLAs and network and equipment constraints throughout activation and recovery, and (iii) satisfies pre-declared magnitude, timing and reliability criteria with the associated measurement uncertainty disclosed. The recovery energy and consequential emissions of an intervention must then be evaluated separately against a feasible no-coordination counterfactual: verified grid-service delivery alone does not establish net energy savings or emissions additionality. The definition is deliberately narrower than the vocabulary it replaces. Green computing, efficient hardware and flexible demand are distinct properties; an efficiency improvement, a procurement decision and a grid service should not be reported as interchangeable outcomes merely because each can be expressed in energy or power units. A response that cannot be located, metered and compared with a credible counterfactual remains an optimisation result, not a qualified grid resource.

Scope and Evidence Base

The contemporary evidence base comprises 67 selected sources published between 2024 and 2026: 65 research publications and two agency/standards documents (the International Energy Agency report and the Software Carbon Intensity (SCI) specification). The 67 sources consist of the original 46-source selection and 21 additional research articles published in 2024–2025 that provide relevant evidence and methods for flexible loads, storage, distribution networks, forecasting, control and electricity–carbon coordination. The corpus is purposive rather than exhaustive or systematic. Studies were prioritised when they reported or explicitly modelled (i) an electrical response attributable to computing activity, (ii) workload scheduling or migration under power-system, cooling or SLA constraints, (iii) market, network or carbon consequences relevant to a data-centre response, or (iv) adjacent forecasting and control methods that inform renewable availability and power-system dispatch. Adjacent studies were retained when they supplied a transferable method for flexibility valuation, renewable-generation forecasting, control or system assessment; work on data-centre energy efficiency without a connection to a grid-side quantity was not treated as direct evidence of grid flexibility. The synthesis compares each study by the physical boundary considered, evidence or validation type, principal assumptions and limitations for qualification, rather than by algorithm label alone. Six additional references provide methodological or historical context and are not included in the 67-source contemporary evidence base: demand-response measurement-and-verification regulations, standards and guidance [10,11,12], an earlier geo-distributed workload study [13], and two adjacent intelligent-control studies [8,9]. Thus, the bibliography contains 73 references in total (67 contemporary sources and six contextual references); neither adjacent control literature nor other model-based evidence is counted as verified data-centre PCC delivery.
The 21 newly incorporated 2024–2025 publications are included within—not added on top of—the 67-source contemporary set. They broaden the discussion of flexible-load aggregation, distribution-network constraints, storage, cooling, carbon accounting and grid coordination, including papers from six specialist electricity and energy journals. The review remains purposive, and these adjacent results are interpreted as technical context rather than as additional data-centre field demonstrations or independent verification of the proposed qualification framework.
The perspective adopted here is deliberately more demanding than an efficiency-oriented review. Broader appraisals of AI in power systems provide the adjacent methodological context [14]. We take the rapid growth of optimisation methods as given and ask a different question: what would make their outcomes auditable by a grid operator? We examine measured computing response, the physical constraints that erode its value, and the market design that an owner of computing assets would need in order to assume an obligation, and we then set out a measurement, verification and certification agenda that separates genuine interventions from attractive but non-additional load shifts. Figure 1 distinguishes the physical feeder-to-site power path from the dispatch/control and telemetry path, and identifies the registered PCC meter by a separate dashed measurement-boundary outline. A site-level grid-service claim must be assessed at that metered electrical boundary, not inferred from a computing, cooling or storage submeter alone.
Figure 1. Conceptual electricity–computing architecture with three distinct representations. Orange arrows indicate physical electrical-power pathways (schematically oriented from the feeder toward site demand), teal arrows indicate control commands and telemetry, and the purple dashed outline identifies the registered PCC/site meter as the grid-facing measurement and settlement boundary. IT, cooling and UPS/BESS submeter data support attribution but do not replace the PCC meter. The UPS maintains ride-through and redundancy reserve, while the BESS is the separately attributable dispatchable storage component.
Three limitations bound what follows. First, the evidence base is purposive rather than systematic; it does not claim exhaustive database coverage or a PRISMA-style screening process. Its 67 contemporary references span 2024–2026 and contain both directly relevant data-centre studies and adjacent electricity-system methods; the six supplementary methodological or historical references [8,9,10,11,12,13] are identified separately. Second, field evidence remains thin. The demonstration using 256 graphics processing units (GPUs) [15] is a single cluster-level trial, while many other studies rely on mathematical models, simulation or trace replay; these evidence types answer different questions and should not be treated as equivalent to a whole-facility PCC measurement or an independently settled service. Third, the qualification framework in Section 4 is a proposed design, not a validated certification instrument: its tests have not been run through a complete independent audit and live settlement process, and its implementation costs and market acceptance remain unknown. These boundaries are stated explicitly because a Perspective that overstates its evidence would reproduce the very inferential problem it seeks to address.
Against these limitations, the specific contributions and novelty of this Perspective are:
•
Evidence distinction: We assess studies by validation type and physical measurement boundary, explicitly separating modelled workload potential, cluster-level demonstrations and independently verifiable PCC delivery (Section 2 and Table 1).
•
Workload-aware qualification proposal: We adapt, rather than reinvent, conventional demand-response M&V by linking stochastic job eligibility, SLA limits, metered component attribution, uncertainty, activation reliability and full recovery to a pre-declared grid-service contract (Section 4, Equations (1)–(6), Figure 2 and Table 2).
Figure 2. Proposed closed-loop qualification, activation, measurement and re-certification of AI data-centre flexibility. Pre-event service commitments and the locked M&V protocol inform activation; independently measured delivery, failed requests, SLA outcomes and rebound update future qualification. Grid-service delivery and consequential-emissions assessment are distinct tests. No plotted experimental values are implied.
•
Transparent implications and research priorities: We use hypothetical capacity and energy accounting (Table 3 and Table 4) to separate event delivery from net energy and emissions outcomes, and identify the multi-site, network-constrained and cross-infrastructure tests needed before scale-up (Section 4 and Section 5).

2. Recent Progress: From Scheduling Models to Physical Response

The literature has moved, in roughly three years, from describing how efficiently data centres consume electricity to modelling how they might behave as grid assets. Recent commentary on the barriers to scaling electricity–computing coordination reinforces the importance of verifiable grid-side outcomes [16]. The four strands reviewed below differ less in their mathematics than in what they treat as measured and what they treat as assumed, and that distinction, rather than the method itself, determines how much of each result transfers to an operator’s problem. The order of the subsections follows the physical object of study: the facility, the network, the market, and finally the evidence base itself.

2.1. Quantifying Controllable Computing Demand

The clearest published field evidence remains a single demonstration. Colangelo et al. tested software-based power orchestration on a 256-GPU cluster running representative AI workloads in a hyperscale cloud facility in Phoenix, Arizona, and reported a 25% reduction in power use for three hours while maintaining the quality-of-service target stated by the authors [15]. The reported experimental object is the 256-GPU cluster; the published description does not establish that the 25% value is a whole-facility reduction independently measured at the facility PCC or a quantity accepted for market settlement. It therefore demonstrates feasibility for the tested cluster and operating conditions, not firm reserve for a fleet. Chance-constrained flexibility assessment and workload-based models [17,18,19] explain why this envelope cannot be transferred to another site without accounting for workload mix, service limits and operating conditions. Liquid-cooled facility studies [20] and data-centre storage analysis [21,22] further show that thermal and storage contributions must be distinguished from computing-originated response.
Envelopes should be measured under stressed as well as normal operation. A training checkpoint that is movable during a quiet hour may become non-deferrable during a burst of interactive inference or an accelerator failure; thermal inertia allows a short cooling reduction, but deferred compressor work may return as a second peak; and battery response is fast but energy-limited. A credible experiment therefore needs time-synchronised metering at the registered electrical boundary and at relevant subsystems, an observation window long enough to contain recovery, and disclosure of the computing service actually received. The 25%/three-hour result in [15] should remain attached to the tested 256-GPU cluster and should not be recast as a site-wide or fleet-wide percentage. A single cluster trial also cannot establish the response distribution during heat waves, high inference demand, communications failures or repeated activations. The operative question is not whether accelerator utilisation is below 100%, but what fraction of demand can be controlled for a specified event without violating the associated service contract.
The appropriate unit of evidence is a time-indexed net-load profile at a declared electrical boundary paired with a workload-service profile. For a site-level grid service, the registered PCC or designated revenue-grade site import meter should determine the settled response; IT, cooling, pumps, power conversion, UPS/BESS and on-site generation submeters explain attribution but cannot replace that boundary meter. Before dispatch, investigators should fix the notification time, requested reduction, delivery interval, baseline procedure and recovery window; after dispatch, they should report the achieved trajectory, event energy, rebound energy, task completion statistics, SLA outcomes and failed attempts, with timestamps aligned between the orchestrator and electrical meters [10,11,12,17,18,19,20,21,22]. Thermal flexibility depends on ambient conditions, inlet-temperature thresholds, cooling configuration and rack thermal history, while battery response is bounded by state of charge, power rating and conversion losses. Identical PCC responses can therefore imply different computational inconvenience, recovery profiles and repeatability [13,20,21,22]. Studies should publish a response envelope as a function of notice, duration, ambient conditions and permitted SLA risk, with uncertainty bands from repeated activations and unsuccessful attempts retained.
Recent evaluations of cooling systems across computing hubs illustrate the dependence of facility efficiency and water use on location and operating conditions [23]. Battery modelling and diagnostic perspectives also underline why storage energy, state of charge and restoration requirements must be tracked separately from computing-originated load shifts [24]. Neither form of evidence alone establishes a repeatable grid-service rating at the PCC.
The transferability of any measured response envelope must be assessed along at least four interacting dimensions, rather than inferred from the 256-GPU demonstration as a universal percentage. First, climate and season alter economiser availability, ambient cooling demand and the coincident electrical peak; a response established on a mild day may not remain feasible during heat or humidity stress. Second, air- and liquid-cooling configurations differ in thermal inertia, pump and chiller electricity, water dependence and the size and timing of post-event recovery; neither architecture can be assigned a universally larger flexibility value. Third, grid topology and point-of-connection location determine whether a given PCC reduction actually relieves the limiting feeder or transformer and whether a receiving site can absorb migrated work without violating line or voltage constraints. Fourth, workload mix and service conditions matter: checkpoint-tolerant training and batch jobs may be deferred, whereas interactive inference can be constrained by latency, bursty arrivals and stricter completion guarantees. A transferable result therefore requires re-testing, or at minimum a validated conditional response model, at the destination site and season using the same pre-registered request, PCC boundary, baseline, recovery horizon and SLA criteria; it must report uncertainty and failed activations rather than simply multiplying an earlier percentage by the new site load [13,15,17,18,19,20,21,22,25,26].

2.2. From Local Efficiency to Network-Aware Coordination

System models have begun to place computing constraints alongside regional reserve supply. A multi-region dispatch model assesses aggregated data-centre reserve together with cross-region transmission capability [25], while a joint formulation co-designs power dispatch and communication transmission for data-centre-based virtual power plants (VPPs) [26]. Other studies couple computing load to microgrid capacity [27], integrate workload transfer with energy-system operation [28], or model electrothermal scheduling in edge facilities [29]. Spatial–temporal migration models add locational prices, risk constraints and coordination among receiving sites [30,31,32]. Earlier geo-distributed data-centre research had already shown that ambient temperature and cooling efficiency vary by location and can materially change workload-routing decisions [13]. Together, these studies establish that electricity, computing, cooling and communications cannot be optimised independently; however, most system-level benefits remain model-based and depend on assumptions about available workload, destination capacity and network feasibility.
Related 2024–2025 studies examine aggregation envelopes for heterogeneous flexible loads [33], coordinated day-ahead and intraday demand response [34], and source-load optimisation using dynamic carbon considerations [35]. Distribution-loss reviews, converter-assisted network regulation and energy-hub security-region analysis provide complementary ways to represent location-dependent feasibility [36,37,38]. These are useful modelling precedents, not operational verification of AI data-centre response.
A spatial transfer must be evaluated at both the sending and receiving nodes. The sending site may reduce its import, but the receiving site incurs additional IT and cooling demand; the transfer also consumes bandwidth and energy, introduces propagation, transmission and processing delay, and may increase congestion or losses on the destination feeder. A feasible assessment should therefore include both nodes in the same counterfactual, enforce thermal ratings, voltage limits and transfer-capacity constraints, and account for data replication, migration energy, jurisdictional restrictions and the destination site’s pre-existing peak. A lower tariff or regional average carbon factor is not sufficient evidence that a transfer is useful during a stressed grid condition. The reserve-envelope analysis [25] and joint power-communication formulation [26] make these interdependencies explicit, but model feasibility should not be mistaken for operational validation.
Multi-site flexibility is also affected by common-mode and correlated conditions. Workload arrivals may rise simultaneously because of shared business cycles, product releases or common AI-service demand; ambient temperature can increase cooling loads across several sites at once; and a regional weather event can reduce both thermal headroom and grid reserve. Communication congestion or a common network outage can further prevent an otherwise feasible transfer. Consequently, the firm aggregate response is not generally the arithmetic sum of independently estimated site capacities. Qualification and planning should use synchronised multi-site activation records or stress scenarios that preserve correlations among workload demand, temperature, cooling requirements, communication availability and grid conditions. The relevant outputs include the joint distribution of delivered response, the frequency of simultaneous non-delivery, the receiving-site headroom and the recovery profile. A practical architecture separates advance scheduling from real-time safety: the advance layer reserves workload windows, storage headroom and destination capacity, while independent-site controllers retain authority to reject instructions that threaten SLA, thermal or feeder limits.

2.3. Market Mechanisms and Operating Governance

Flexible loads are not worth the same amount across ancillary-service products. Work on dynamic aggregation of heterogeneous loads emphasises the multidimensional nature of response capability [39]; studies of uncertain interprovincial procurement and of locational-capacity pricing show why service location, scarcity and settlement are material [40,41]; transactive demand response and rolling outage management add a distribution-system perspective [42]; and low-carbon tariff design, digital protection infrastructure and joint electricity–carbon management supply adjacent tools, none of which verifies a data-centre response [43,44,45]. A product requiring a response within seconds differs from a scheduled shift with hours of notice. A congested distribution node may value a local decrease that is nearly worthless at a distant data centre, and price arbitrage can reward shifting that does not relieve the constrained line at all, so product rules need node-specific eligibility, telemetry sampling, duration, recovery limits and non-delivery penalties, and an operator should not be paid twice for one physical response attributed simultaneously to cooling, storage and workload control. A second source of confusion is the treatment of all demand flexibility as interchangeable: frequency response, emergency curtailment, peak avoidance and energy arbitrage impose different requirements on notification time, telemetry resolution, sustained magnitude and post-event behaviour. Multi-service aggregation [39] shows how heterogeneous resources can be assembled, and locational-capacity and purchasing studies [40,41] show why location and risk matter, but those studies supply a design vocabulary rather than a licence to assume that a data centre automatically qualifies for every existing flexibility market.
Market-facing analogues include uncertainty-aware virtual-power-plant participation in frequency regulation [46], capacity-market treatment of long-duration storage [47], thermal-inertia-aware integrated-energy planning [48], and flexible-load dispatch or coordinated aggregation studies [49,50]. They motivate service-specific contracts and capability screens, while leaving the AI workload and PCC verification questions addressed here unresolved.
A market-ready computing service needs an explicit baseline and a deliverability test at the applicable connection point. The buyer must know whether capacity is reserved throughout an availability window and whether activation energy settles separately, and the seller must know how failures are treated when the computing business experiences exceptional demand; distribution-system coordination [42], commercial-load carbon scheduling [43] and joint electricity–carbon management [45] provide context for such contracts, but service-specific obligations for complex AI workloads remain underdeveloped. There is also a governance boundary. Grid operators need enough telemetry to validate performance, whereas computing providers must protect tenant activity, trade secrets and service logs, and signed aggregate meter curves, limited categorical workload metadata and pre-committed baseline parameters narrow the gap. A certificate that reports megawatts without a node, a tested duration or a confidence level is inadequate for procurement and for settlement alike. The market value of flexibility should track physical location and verified reliability, not the marketing claim that tasks can move.

2.4. Interpreting Methodological Progress and Evidence Strength

Table 1 compares a purposive set of representative studies along four dimensions: the type of evidence or validation reported, the physical or model boundary, the principal modelling assumptions, and the limitation that remains relevant to grid-service qualification. “Field demonstration” is reserved for a reported physical trial; “trace-based” identifies analyses driven by historical workload traces; and “simulation/model” identifies analytical or computational studies whose results depend on model assumptions. A study may contain more than one evidence component, but a simulation result is not upgraded to a field result merely because it uses realistic traces. Likewise, a measured response at a GPU cluster is not equivalent to a PCC measurement, and a modelled multi-region benefit is not an independently delivered ancillary service. The table is intended to make these distinctions visible, not to rank studies by the size of their reported improvement.
Table 1. Representative electricity–computing studies and adjacent system-method studies compared by evidence type, physical boundary, principal assumptions and remaining limitations for grid-service qualification.
The comparison reveals a recurring gap between operational sophistication and verifiability. Optimisation studies can represent tariffs, nodal prices, workload migration and participation risk in depth [17,25,26,30,31,51,52], while still relying on assumed response envelopes; trace-based studies test workload patterns but do not by themselves establish a contemporaneous electrical response; and a field demonstration establishes physical feasibility only within its tested hardware, site, workload and duration [15,19]. Reciprocal validation is therefore needed: measured workload-to-power envelopes should calibrate network-aware scheduling, and network and market results should identify which response dimensions require further testing. For each site-level study, readers should be told whether net load includes cooling, batteries and on-site generation; for distributed studies, whether line constraints represent actual or benchmark networks; for migration studies, the delay distribution and data-transfer overhead; and for carbon studies, whether accounting is attributional or consequential. Where the source does not report a boundary or validation detail, the table states that limitation rather than inferring it.

3. Misconceptions and System-Level Risks

Four inferential errors recur across otherwise careful studies, and they share a common structure: each substitutes a partial indicator—a bill, a nominal capability, a private objective, an assumed baseline—for the system-level quantity that the claim actually requires. Each is individually plausible, and each survives review because the substitution is invisible in the units reported. Naming them separately is a precondition for the certification argument that follows: the four subsections below state each error, identify the evidence that would expose it, and indicate the corresponding obligation on a certificate.

3.1. Cost Reduction Is Not Decarbonisation

The first and most consequential error is to read a cost saving as decarbonisation. A power-system analysis finds that temporal data-centre flexibility can lower system cost while raising emissions under some generation mixes [51], while carbon-aware computing with probabilistic performance guarantees addresses computing-side service risk but does not by itself establish consequential system emissions [52]. A defensible consequential assessment compares two feasible dispatch cases under the same demand, weather, network and resource assumptions: a reference case without the workload intervention and a coordinated case with it. For each time interval and electrical node, the analyst should calculate the change in grid import and apply a location- and time-specific marginal-emissions factor where available, or disclose a defensible proxy and sensitivity range. The accounting must include the sending-site reduction, receiving-site increase, transmission/distribution losses, data-transfer and communication energy, battery round-trip losses, cooling recovery, delayed job execution and any additional on-site generation. Delayed consumption is not avoided energy; it must be counted when it occurs within the defined assessment horizon. Software Carbon Intensity reporting [53] is useful as an accounting convention, but should not be interpreted as an independently measured marginal-generation effect. Annual renewable certificates or average annual grid factors may support attributional reporting, but they do not establish that a short-term dispatch action displaced marginal emissions. The sign and magnitude of the result should be tested across plausible dispatch and congestion counterfactuals [11,12,51,52,54].
Flow-based grid carbon accounting provides an additional methodological comparison for separating changes in electricity flows from claims about marginal or consequential emissions [55]. Such accounting still requires location-specific counterfactual data when applied to migrating computing workloads.

3.2. Shiftability Is Not Reliability

The second error is to treat shiftability as reliability. Inference latency, checkpoint overhead, heat waves, network failures and correlated demand spikes can remove response precisely during scarcity. Privacy-preserving electricity–carbon coordination [56] and device-level power-electronic studies [57] are relevant adjacent developments, but neither establishes firm fleet-wide data-centre reserve. Reliability must be estimated from all valid activation requests, including refusals, partial deliveries and failures, and should be reported with a confidence interval rather than a point estimate alone. At fleet scale, common-mode effects matter: multiple facilities may experience the same weather, workload surge, cooling stress, communication outage or market signal. A portfolio that appears diversified under independent-site assumptions may have a much smaller lower-tail response when these dependencies are represented. Multi-site tests should therefore report site-level and aggregate delivery distributions, conditional availability during stress events, reasons for non-delivery and whether the receiving site remained feasible after workload transfer.
Partitioned storage coordination and hierarchical wind–storage frequency regulation [58,59], together with state-of-charge-sensitive inverter control [60], are further adjacent examples of device-limited response. They reinforce the need to specify duration, restoration and equipment constraints without treating a storage-originated response as workload flexibility.

3.3. Facility Optimisation Is Not System Welfare

The third error is to equate facility optimisation with system welfare. Geo-distributed scheduling [61], cluster energy sharing [62], carbon-aware market coordination [63] and co-optimised peak management and ancillary services [64] widen the design space, but a site can still reduce its bill while exporting congestion, losses, emissions or reinforcement costs to other users. A system-level comparison should model the sending and receiving nodes jointly and enforce the relevant transmission or distribution constraints, including line and transformer thermal limits, voltage limits, transfer capacity and congestion. It should report incremental network losses and the effect on the receiving site’s coincident peak, not only the reduction at the originating meter. Where the actual network model is unavailable, the use of a representative feeder or benchmark system must be stated and results should be presented as scenario-based rather than as a prediction for a specific utility. Facility economics, system operating cost, reliability and consequential emissions should be evaluated over a common time horizon, with storage-only, fixed-workload and no-coordination cases used as comparators. The closed-loop qualification protocol proposed in Section 4 (Figure 2) operationalises this comparison: a pre-registered service offer and locked measurement-and-verification inputs flow into activation and independent metering, and observed non-delivery, SLA performance and rebound inform subsequent re-qualification without retrospectively changing an event baseline. It is a conceptual framework, not a plot of measured or simulated numerical outcomes.

3.4. Counterfactual Specification Is the Central Analytical Challenge

The fourth error is to let an assumed counterfactual stand in for a specified one. If a facility delays 1 MWh of work from an expensive hour to a cheaper one, its bill may fall even when consumption rises through longer equipment run-time, less efficient cooling or data-transfer overhead; the climate effect depends on which generators change output at each affected node and time. The comparison that matters is between a feasible coordinated dispatch and an otherwise equivalent no-coordination dispatch, with identical exogenous demand, weather, network availability and resource assumptions. A location- and time-specific marginal-emissions series is preferable where it can be defended; where network or dispatch data are unavailable, authors should identify the proxy, report sensitivity to alternative factors and avoid describing the result as measured consequential emissions. The assessment window must extend through the recovery of deferred workloads and storage, otherwise rebound and delayed consumption are omitted. This is why an SLA-compliant workload schedule [52] and a lower electricity bill do not, by themselves, prove system-level decarbonisation.
User-side cloud-storage scheduling under time-of-use tariffs and state-of-charge constraints illustrates why economic dispatch decisions and storage accounting must be separated from a verified site-level load reduction [65].

4. Our Perspective: A Workload-Aware Qualification Framework for Deliverable Flexibility

The framework advanced here adapts established demand-response measurement and verification (M&V) to AI data centres, rather than proposing a new market-wide mathematical standard. Its purpose is to distinguish workloads that are theoretically movable from an electrical response that a grid operator can request, measure, assess against computing service-level agreements (SLAs), and—subject to the applicable market rules—settle. Figure 2 presents the proposed pre-event qualification, activation, verification and re-certification loop. The definitions below are intentionally limited to the indicators needed to make that Perspective operational; they are not represented as a field-validated certification protocol.

4.1. Grid-Facing Service Specification and Deliverable Response

A service offer must specify the registered electrical boundary (normally the point of common coupling, PCC, or a designated revenue-grade site import meter), its network location, notice and ramp requirements, minimum response, activation duration, recovery window, and the workloads and SLA conditions under which capacity is offered. Nominal workload flexibility denotes the screening estimate of candidate shiftable jobs; it is not a firm power rating. When illustrating a whole-site service, a separately identified nominal site-response envelope may include potential IT, cooling and storage actions, without assuming that their individual capacities can simply be added. The available site-response envelope is the smaller service-specific capability remaining after task deadlines, inference latency, thermal headroom, UPS/BESS reserves, feeder limits and migration constraints are imposed. Neither quantity is a metered grid service.
For activation k and metering interval t, the pre-registered counterfactual PCC import is P k , t 0 , the measured PCC import is P k , t m , and the requested reduction is rk,t. With grid import defined as positive, the signed net-load response and the response eligible for credit (capped at the request) are:
Δ P k , t   =   P k , t 0   −   P k , t m d k , t   =   min r k , t ,   max 0 ,   Δ P k , t
where ΔPk,t is the signed net-load response and dk,t is the non-negative credited reduction, both in MW; P k , t 0 and P k , t m are baseline and metered PCC import (MW), and rk,t is the operator-requested reduction (MW). Subscripts k and t identify the activation and measurement interval. A reduction is credited only within the requested magnitude, so an unrequested surplus is not counted as additional contracted capacity.
The event-average credited response is obtained by integrating the interval-level credit over the activation window:
C del , k   =   1 T e   Σ t   ∈   I e   d k , t   Δ t
where Cdel,k is the event-average delivered capacity (MW); Ie is the set of event metering intervals, Δt is their duration (h), and Te is total activation duration (h), equal to the sum of interval durations. Each dk,t is in MW, so its product with Δt is in MWh. This is an event delivery measure, not a reliability-adjusted certified rating.
Beyond the credited power magnitude, qualification must report response onset, ramp rate, time to a pre-agreed target (e.g., 90% of the request), and consecutive minutes above the contracted threshold. A GPU or cooling submeter alone cannot establish grid-facing delivery.

4.2. Baseline Validation and Measurement Uncertainty

The baseline method, eligible predictors and exclusion rules should be fixed before dispatch. Matched non-event days, pre-trained regression or a credible control group can provide counterfactuals, with workload arrivals, job mix, deadlines, ambient temperature, cooling demand and scheduled maintenance treated as potential predictors. Out-of-sample checks should report baseline bias, root-mean-square error (RMSE) and prediction-interval coverage. No post-event variable caused by the dispatch should be used to improve the locked baseline, and placebo tests and signed logs should discourage gaming.
The uncertainty of the interval-level net-load response follows from baseline prediction error, meter error and their covariance. Independence should not be presumed:
σ Δ P , t 2   =   σ base , t 2   +   σ meter , t 2   −   2   Cov ( e base , t ,   e meter , t )
where σ Δ P , t 2 denotes the variance of the estimated interval response (MW2), σ base , t 2 the baseline prediction-error variance (MW2), and σ meter , t 2 the meter-error variance (MW2). The last term is twice the covariance between baseline error ebase,t and meter error emeter,t (MW2), with both errors defined consistently as estimate minus true value. It vanishes only when their covariance can justifiably be taken as zero.
The event-average uncertainty must also account for correlation between measurement intervals, using an event-level error covariance matrix or a suitable block bootstrap. Under a stated one-sided normal approximation, a conservative event-level lower capacity bound is:
C L , k   =   max 0 ,   C del , k   −   z 1 − α   σ C , k
where CL,k is the one-sided event-level lower capacity estimate (MW), Cdel,k is the credited event-average delivery (MW), and σC,k is the standard uncertainty of that event-average estimate (MW), accounting for temporal error correlation. The factor z 1 − α is the standard-normal quantile for confidence level 1 − α. The maximum with zero prevents a negative event-level lower-bound estimate. Normality and the estimated uncertainty must be justified; this bound is not a guarantee of capacity in future activations.
A resource-wide rating should use a pre-specified lower-tail statistic across repeated activations; its estimation method, minimum sample size and assumptions need to be disclosed. The same pre-registered baseline and exclusion rules must apply to successful and unsuccessful events. Invalid baseline conditions or insufficient telemetry make an event non-verifiable, and material workload or control changes require re-certification rather than retrospective adjustments.
Equation (3) propagates baseline and meter errors for the unbounded signed PCC response, whereas Equation (4) uses an approximate event-average standard uncertainty to construct a one-sided lower bound for the credited response. This normal approximation is defensible only when its uncertainty and temporal-correlation assumptions have been checked and the zero floor and requested-reduction cap in Equation (1) are not materially active. Because clipping can create boundary mass and a non-normal credited-response distribution even with approximately Gaussian underlying errors, Equation (4) should not be treated as a calibrated lower bound near either limit without further validation. In those cases, a pre-specified block bootstrap or validated bounded simulation should preserve time dependence, reapply the Equation (1) clipping in each replicate, aggregate responses using Equation (2), and estimate the one-sided bound directly. Report resampling design, out-of-sample coverage and sample limitations; if a defensible bound cannot be established, the corresponding event remains NOT VERIFIABLE.

4.3. Resource Attribution, Rights and Auditable Governance

The total PCC response should be reconciled, without double counting, against synchronised component meters and their pre-defined component baselines. Those contributions include IT workload control, cooling, BESS, on-site generation and any other auxiliaries, with an explicit balance residual for metering mismatch. A site offering 1.8 MW at the PCC may attribute 1.1 MW to IT workload control, 0.2 MW to cooling and 0.5 MW to BESS; in that case the site-level service is 1.8 MW, not 3.6 MW, and the computing-originated portion is only 1.1 MW. This reconciliation is an accounting procedure, not a new independent settlement equation.
UPS reserves are first constrained by ride-through and redundancy duties and must not automatically be marketed as dispatchable battery capacity. A workload orchestrator and facility energy manager may coordinate eligible jobs, cooling and BESS, but independent safety interlocks retain override authority. The EV-management and power-flow-control studies [8,9] are cited here solely as adjacent evidence for device-level control and protection, not as demonstrations of data-centre workload flexibility or grid-service verification; this distinction reinforces the need for independent equipment safety interlocks. Verifiable records should include time-synchronised PCC and component meter traces, signed dispatch and override logs, pre-registered baseline versions, and privacy-preserving SLA summaries. Availability compensation should be distinguished from activation compensation according to the applicable service contract.

4.4. Qualification, Pass/Fail Decisions and Re-Certification

We propose contractual gates rather than an invented universal numerical threshold. The boundary/data-quality gate confirms the registered node, meter, time synchronisation and pre-event baseline. The capacity and timing gate requires a conservative delivered-capacity estimate, ramp, onset and sustained duration to meet the contracted service. The computing-quality gate checks agreed task deadline misses, latency percentiles and the SLA violation proportion, defined as the number of violating eligible tasks divided by the total eligible tasks. These SLA metrics and permitted limits must be specified before testing, rather than selected after an event.
Activation reliability is calculated from the full ledger of valid dispatch requests, retaining refused, partially delivered and failed events:
p success   =   N success N requested .
where psuccess is the observed activation-success fraction (dimensionless), Nsuccess is the number of activations meeting every pre-declared magnitude, timing, SLA and safety condition, and Nrequested is the total number of valid requests, including refusals, partial deliveries and failures. Qualification compares an uncertainty-aware lower confidence bound for reliability—not this point estimate alone—with the contractual threshold.
A one-sided Wilson lower confidence bound, or an alternative pre-registered reliability interval suited to the data, should be used for contractual qualification. The recovery gate is separate: over the declared recovery and full assessment windows, rebound and signed net energy response are:
E reb   =   Σ t   ∈   I r   max 0 ,   P t m   −   P t 0   Δ t E net   =   Σ t   ∈   I e   ∪   I r   P t 0   −   P t m   Δ t
where Ereb is positive rebound energy during recovery (MWh), Enet is the signed net reduction over the combined event and recovery windows (MWh), and Ie and Ir are the respective sets of intervals. P t 0 and P t m are baseline and metered PCC import (MW), and Δt is interval length (h). Rebound counts only excess import above baseline; net energy retains positive and negative contributions and is therefore not the same as rebound energy or an emissions saving.
The recovery gate must include deferred jobs, thermal restoration and battery recharge, not only the event-period meter trace. Consequential CO2 claims additionally require a feasible no-coordination dispatch covering sending and receiving nodes, marginal generation, transfer losses, migration overhead, storage losses and delayed execution. Network feasibility and emissions additionality are separate from grid-service delivery. Settlement must follow the rules of the specific contracted product rather than a universal payment formula. For an energy-settled product, the credited event energy is the event-average delivered capacity of Equation (2) multiplied by event duration (MWh), valued at the agreed energy rate; capacity or availability payments require a separately specified qualified rating and contract. The uncertainty bound in Equation (4) can inform qualification but does not, by itself, determine a payment, and failed activations are subject only to pre-agreed penalties. Recovery energy from Equation (6) is disclosed and reconciled where required by the applicable service terms, without retrospectively altering the locked event baseline. The qualification gates and the associated reporting requirements are summarised in Table 2.
A final qualified capacity rating also requires a pre-registered rule for combining repeated activations. Before testing, the service contract should specify the operating conditions or strata to be covered, the required number of representative requests, the event-level uncertainty method, the lower-tail capacity quantile and confidence level, and the reliability, SLA, timing, network, safety and recovery thresholds. For each verifiable activation, first obtain an event-level conservative delivered-capacity estimate using Equation (4) only when justified, or the boundary-aware method described in Section 4.2. From the resulting repeated-event estimates within each declared operating stratum, estimate a one-sided confidence lower bound for the pre-specified lower-tail capacity quantile, denoted here as Cqual (MW). This multi-event lower-tail bound, rather than the mean, maximum or a single event-level value, is the proposed qualified capacity rating. The estimation must account for sample size and dependence between events; performance in untested operating strata cannot be assumed. To avoid success-only selection bias, every valid request with partial or zero delivery must enter the repeated-event capacity sample at its measured conservative outcome (including zero); data-invalid requests are disclosed and handled through the independent data-quality gate, not silently discarded.
Table 2. Workload-aware measurement, verification and contractual decision criteria for the proposed deliverable-flexibility qualification.
The illustrative joint decision rule is conjunctive: PASS requires sufficient auditable evidence, Cqual at least as large as the offered capacity Coffer (both in MW), a one-sided activation-reliability lower bound no smaller than the contractual minimum, and satisfaction of every pre-declared SLA, response-time, duration, safety, network and recovery gate. If a gate is demonstrably violated, the offered capacity FAILS and must be reduced or the resource remediated and re-tested. Insufficient representative events, an invalid baseline, missing telemetry or incomplete recovery evidence yield NOT VERIFIABLE rather than PASS. All dispatch requests, failures and exclusions must remain in the audit ledger; data-quality exclusions must not be used to conceal non-delivery. The rating, thresholds and decision categories describe a proposed contract-dependent qualification procedure, not a universal existing certification rule.
Repeated qualification has material implementation and opportunity costs, even when the underlying workload controller already exists. These costs include revenue-grade PCC and component metering, time synchronisation, secure retention of job and SLA logs, baseline-model validation, third-party auditing, integration with grid-operator telemetry, and tests performed under representative high-load and high-temperature conditions. Test activations may displace billable computing, increase queue latency or cooling duty, consume BESS cycle life, or require temporary reservation of storage and computing headroom. These are costs and operational risks to be estimated and disclosed for each service and site; no universal cost or certification fee is assumed here.
An implementable programme should therefore define in advance who pays for tests, meter calibration and independent verification, which operational data can be shared without exposing tenant information, and when a resource must be re-qualified. Useful re-qualification triggers include material changes in GPU mix or workload/SLA composition, cooling equipment or climatic operating range, battery capacity or state-of-health, PCC configuration, feeder constraints, communications infrastructure, and repeated partial or failed activations. A risk-based testing cadence can reduce unnecessary disruption, but a previously demonstrated response cannot simply be carried forward after such a change; the complete request and non-delivery ledger must remain auditable. The net economic value of offering flexibility should be assessed after these monitoring, testing, energy-recovery and foregone-computing costs, rather than assuming qualification is costless.

4.5. Illustrative Application: A Three-Hour Demand-Response Event

Consider a hypothetical site with a 3.0 MW nominal whole-site candidate response envelope from potentially controllable IT workloads, cooling and BESS, of which 2.2 MW remains as a site-level available envelope after workload SLAs, thermal limits, storage reserves and electrical constraints. These are hypothetical screening envelopes rather than computing-only ratings or sums of independently qualified components. A site is asked to reduce PCC import by 2.0 MW for three hours. The pre-registered baseline is 10.0 MW and measured PCC import is 8.2 MW, yielding 1.8 MW of event-average credited delivery. Table 3 summarises the illustrative progression; none of these values are taken from the reported 256-GPU experiment or any new field trial.
For illustration, assume that baseline and meter standard uncertainties for the event-average response are 0.12 and 0.08 MW and are independent. Their quadrature combination is approximately 0.144 MW. With a one-sided 95% normal bound (z = 1.645), the event-level conservative delivery is 1.8 − 1.645 × 0.144 ≈ 1.56 MW. Hence, this event exceeds a hypothetical 1.5 MW capacity threshold; however, one event cannot establish a repeatable certified rating. If the 1.8 MW PCC response is attributed to 1.1 MW IT control, 0.2 MW cooling and 0.5 MW BESS, only the 1.1 MW is computing-originated.
The illustrative 1.56 MW value is a plug-in normal-approximation calculation, not a calibrated capacity rating for a request-capped response. Here the 1.80 MW delivered mean lies only 0.20 MW below the 2.00 MW request cap, so the effect of clipping on the response distribution cannot be dismissed from the stated assumptions alone. Before an actual qualification decision, the event-level bound should be checked or replaced using the boundary-aware resampling procedure described in Section 4.2.
Table 3. Illustrative progression from a nominal whole-site-response envelope to a conservative event-level PCC capacity estimate (hypothetical values).
The three-hour event reduces PCC import relative to the locked baseline by 5.40 MWh, but this event-period reduction is not automatically a net energy saving. To close the energy balance, assume that the 1.1 MW IT contribution represents 3.30 MWh of deferred computing demand that must be completed after the event at unchanged electrical efficiency; that the temporary 0.2 MW cooling reduction requires 0.60 MWh of later thermal restoration; and that the 0.5 MW BESS contribution for three hours discharges 1.50 MWh. With a hypothetical 90% BESS round-trip efficiency, full grid recharge to the initial state of charge requires 1.50/0.90 = 1.67 MWh, including about 0.17 MWh of storage losses. Assuming all three recovery contributions are incremental to the matched no-action PCC baseline and fully captured in the declared recovery window, total rebound is 3.30 + 0.60 + 1.67 = 5.57 MWh, and signed net energy reduction over the complete event-plus-recovery horizon is 5.40 − 5.57 = −0.17 MWh (Equation (6)). The recovery horizon must be long enough to finish deferred work and restore the BESS state of charge; a short observation window that omits either would overstate net energy savings. All recovery quantities are hypothetical simplifications, not field observations.
Renewable-energy availability can change the system consequence even when the same 1.80 MW PCC response is delivered. For illustration only, assume a marginal-emissions intensity of 0.60 t CO2/MWh during the three-hour event; compare a recovery period with abundant low-carbon marginal supply (0.10 t CO2/MWh) against one with scarce renewable availability and higher-emitting marginal supply (0.70 t CO2/MWh). For these deliberately simplified two-period cases, illustrative avoided emissions equal 5.40 MWh multiplied by the event marginal factor minus the complete recovery import multiplied by the recovery marginal factor. Table 4 also varies round-trip BESS efficiency and cooling rebound while holding the initial PCC delivery unchanged. These assumed marginal factors are not derived from a measured renewable share, and renewable availability alone does not determine the marginal generating unit; an actual consequential study requires network- and dispatch-consistent marginal estimates.
The illustrative service-quality and reliability tests are separate from the energy and carbon accounting. Suppose 97 of 100 valid dispatch requests were successful and 99.7% of eligible tasks met their SLAs. Observed activation reliability would be 97%, with a one-sided 95% Wilson lower bound of approximately 92.7%; an illustrative 90% reliability threshold and 99.5% SLA-compliance requirement would therefore be met. Even in that case, a single 1.56 MW event-level lower bound does not establish a repeatable qualified capacity. Qualification remains contingent on pre-declared multi-event lower-tail testing, complete telemetry and restoration, network constraints and independent verification. None of the inputs, thresholds or emissions values in this subsection represents an industry-wide standard or an observed data-centre trial. In this hypothetical screening example, the 97 successful requests are assumed to meet the pre-declared activation magnitude, timing, SLA and safety checks; that assumption does not establish the distinct multi-event capacity-tail and independently verified recovery gates.
Table 4. Hypothetical sensitivity of complete recovery energy and avoided emissions to renewable availability, storage efficiency and cooling rebound.
Under the proposed joint rule, this hypothetical example is NOT VERIFIABLE as a final capacity rating. The illustrative 1.56 MW single-event bound exceeds a 1.50 MW screening threshold, and the 92.7% reliability lower bound and 99.7% task compliance exceed the assumed 90% and 99.5% limits, respectively. However, the example provides neither a pre-registered, uncertainty-adjusted lower-tail capacity bound across representative repeated events nor a contractual recovery limit with independently verified restoration records. Therefore, the apparent success of these individual gates is not a joint PASS, and neither 1.56 MW nor 1.50 MW is claimed as certified capacity. All values and thresholds remain hypothetical.

5. Research Agenda: Evidence Before Scale

The evidence reviewed above supports four complementary research workstreams, ordered by the uncertainties they would resolve rather than by the speed with which they could be demonstrated. A common evidence ladder runs from analytical and simulation studies through trace replay, hardware experiments and repeatable facility tests to location-specific grid trials and contractual delivery. At every level, the comparison should include no coordination, storage-only intervention and price-only workload shifting. Negative results—such as no net emissions benefit after recovery or loss of response under correlated stress—are as informative as positive results because they identify where coordination should not be deployed. Broader reviews of flexibility technologies and AI-enabled integrated energy-system scheduling [66,67] provide methodological comparators but not substitutes for site-level qualification tests. The workstreams address four linked tasks: defining workload-aware response under network constraints, establishing consequential accounting and independent verification, assembling multi-site evidence, and testing cross-infrastructure dependencies.

5.1. Benchmarks and Network-Constrained Control

The first task begins with a shared workload-to-power benchmark. Public suites should cover training, fine-tuning, batch analytics and interactive inference, and describe accelerator type, task deadlines, sensitivity to throttling, dependency chains, checkpoint overhead and data-transfer requirements. Because commercial traces are sensitive, published trace statistics or protected replay interfaces can substitute for raw data, but testbeds should report measured electrical power and quality of service rather than infer watts from requested GPU utilisation. The benchmark should publish response envelopes across seconds, minutes and hours, with confidence bounds, SLA outcomes and recovery energy. Network-constrained controllers should then be tested under common scenarios that include site location, feeder limits, weather, communication delay, correlated workload and cooling stress, and common-mode failures. They should be judged on delivered response, constraint violations, missed deadlines, receiving-site feasibility and cost, with held-out stress events used for validation. Facility interlocks must retain override authority, and non-delivery caused by an override should remain in capability ratings rather than disappear from the evaluation.
Recent distribution-network storage-dispatch studies using mixed-integer programming and reinforcement learning [68], and hierarchical flexibility-oriented scheduling for renewable-heavy systems [69], offer candidate tools for stress-test scenarios. Their simulated improvements should be assessed against the same meter, network and service-quality gates before any grid-service qualification is claimed.

5.2. Consequential Accounting and Independent Verification

The second task determines what must be counted and how it is checked. Protocols should compare coordination against a clearly defined no-intervention baseline and report the timing and location of generation responses. The accounting boundary should include the sending and receiving nodes, network losses, data-transfer and communication energy, battery round-trip losses, cooling rebound, deferred workload completion and any additional on-site generation. Where marginal emissions are estimated rather than observed, the source, temporal and spatial resolution, dispatch assumptions and sensitivity range must be disclosed; average annual factors should not be presented as marginal factors. Verification should test baseline accuracy, privacy-preserving telemetry, contractual duration, response reliability and recovery in realistic market simulations and live pilots. Availability payments and activation payments should be separated, and settlement should use metered delivery at the registered boundary rather than assumed workload shiftability.

5.3. A Multi-Site Evidence Programme

The third task is a multi-site evidence programme that publishes failure as readily as success. Pilots should span different climates, cooling technologies, grid topologies, workload portfolios and communication environments. Each should publish an activation ledger containing requests, accepted instructions, telemetry completeness, delivered response, duration, recovery, SLA outcomes and reasons for failed events. The programme should test common-mode stress explicitly—for example, a regional heat wave that simultaneously raises cooling demand and reduces thermal headroom, or a workload surge that affects several facilities at once. Industry participants can protect tenants while enabling external audit of aggregated physical outcomes. Evidence that a resource is unavailable during a heat event, or that it raises net emissions after recovery, is as useful for procurement rules as a successful response. Multi-owner coordination and energy-sharing studies [70] provide useful modelling comparators, but simulated benefits should not be treated as certified computing flexibility. Figure 3 maps the reviewed studies by publication year and evidence theme.
Figure 3. FigSelected literature by publication year and evidence theme (2024–2026). Sources shown in the figure, given as author–year with the corresponding bibliography number: Ruan et al. (2024) [56]; ISO/IEC 21031:2024 [53]; Zeng et al. (2025) [5]; Zhou et al. (2025) [18]; Guo et al. (2025) [28]; Hall et al. (2025) [52]; Colangelo et al. (2026) [15]; Jin et al. (2026) [25]; Wu et al. (2026) [26]; Chen et al. (2026) [20]; Senga et al. (2026) [51]. Original icons schematically illustrate the study topics and do not reproduce experimental results. The 256-GPU demonstration is cluster-level field evidence, not whole-facility PCC certification.
To identify which results generalise, a multi-site programme should pre-register a transferability matrix with four principal axes: climatic conditions (including high-temperature and humidity stress), cooling configuration (air- and liquid-cooled, including water limitations), electrical topology (unconstrained and congested feeders at identified PCC nodes), and workload portfolio (batch/training-dominant versus latency-sensitive inference). Where a fully crossed field design is impractical, the covered combinations and exclusions should be disclosed explicitly. Each test location should apply comparable event notices, durations, baseline-validation rules, SLA thresholds and full recovery windows, while preserving its real local operating constraints. The outcomes should include site-specific constrained availability, metered delivered MW, repeated-activation lower-tail reliability, response and recovery energy, workload non-delivery reasons and network-feasibility outcomes. Paired normal/stress tests and held-out periods can expose optimistic transfer from mild weather or low utilisation; synchronised multi-site events should also probe correlations in climate, job arrivals and communication availability. Transfer to a new site is warranted only within the documented climate–cooling–network–workload operating domain, with material changes triggering re-qualification. Such evidence would make “flexible AI demand” a conditional, location-specific claim rather than a capacity fraction extrapolated from one cluster [15,20,25,26].

5.4. Six-Network Convergence as an Infrastructure-Scale Test

A concrete application for the six-network convergence concept is the planning and operation of a water-constrained, liquid-cooled AI data-centre campus located near a congested distribution feeder. The six boundaries interact but are not interchangeable. The water network determines available cooling-water volume, quality, intake restrictions and drought-related curtailment; the electricity network determines PCC import, feeder and transformer loading, voltage, losses and time- and location-dependent marginal emissions; the computing network determines GPU capacity, job arrivals, task deadlines, queue backlog and SLA compliance; and the communications network determines available bandwidth, end-to-end latency, packet loss, data-replication energy and the feasibility of workload migration. Underground utility corridors constrain the co-location, routing and capacity of power cables, fibre and cooling-water pipes, and can create shared failure or maintenance dependencies. The logistics network determines delivery and repair lead times for servers, pumps, batteries and cooling equipment, as well as emergency access and replacement-related life-cycle impacts.
Cross-sector discussions of artificial-intelligence-assisted vehicle–charging-station–grid coordination [71] provide an analogy for information, control and infrastructure interactions; they do not constitute evidence that the six-network data-centre framework has been independently validated.
A common analytical framework should represent these six networks as coupled constraints over the same location- and time-indexed scenario, rather than as six separate scores that can be added together (Figure 4). Its operational decisions could include workload pacing or migration, cooling and pump dispatch, admissible water use and storage operation, subject simultaneously to task completion and latency SLAs, PCC/feeder and voltage limits, cooling-water restrictions, thermal headroom, communication bandwidth and receiving-site capacity. Planning and recovery decisions would separately include the routing and redundancy of underground power, fibre and water corridors, the availability of critical spare equipment and maintenance or access lead times. The common output of the feasibility layer is a conditional, SLA-compliant PCC response envelope; it is not equivalent to the sum of presumed flexibility in the individual networks. The framework should link this envelope to two distinct tests: contractual grid-service deliverability at the registered electrical boundary, and system-level water, energy, emissions, cost and restoration consequences. The controls operate at different timescales, so corridor and logistics decisions alter the feasible operating domain and restoration risk rather than functioning as second-by-second load controls.
Figure 4. Conceptual six-network analytical framework for a water-constrained, liquid-cooled AI data-centre campus. Water, electricity, computing, communications, underground utility corridors and logistics jointly constrain site-level availability. A common feasibility model feeds matched integrated versus electricity-and-computing-only scenarios; grid-service deliverability at the PCC is evaluated separately from water, network, emissions, cost and restoration impacts. All connections and outputs are conceptual, not results of a measured six-network pilot.
One bounded test case is a heat wave accompanied by drought restrictions, feeder congestion and loss of a communications link to a potential receiving data centre. In that case, constrained water availability can reduce heat-removal headroom and narrow the set of workload-control actions that satisfy both equipment temperature limits and task deadlines. Feeder congestion determines whether a reduced site import has local value, while limited communications can prevent migration even when the remote site has spare GPUs. A shared underground-corridor outage can affect power, fibre and cooling-water assets together, and delayed repair or replacement logistics can lengthen the period of reduced availability. These dependencies would be represented as common scenario constraints, not as six independent flexibility products. The analytical comparison should evaluate an integrated six-network design against an otherwise feasible electricity-and-computing-only design under identical exogenous weather, water availability, workload arrivals, network conditions and asset states. The system boundary includes the campus PCC and its feeder, water intake and discharge, relevant communication links and receiving sites, shared corridors and repair logistics. Disclosed outputs should include qualified PCC capacity (MW), delivered and rebound energy (MWh), SLA violations and completion delay, water withdrawal and consumption (m3), feeder/voltage violations, transfer latency and bandwidth, losses, consequential emissions based on a defensible counterfactual, restoration time and total cost. No result is claimed for this case: integrated planning would be preferable only where these outputs demonstrate a better feasible outcome without transferring uncounted costs or impacts to other nodes. Related geo-distributed workload, liquid-cooling, power–communication and multi-vector planning studies offer ingredients [13,20,26,29,72], but do not independently validate a six-network data-centre certification protocol; multi-owner incentives require separate treatment [73].

6. Conclusions

The main conclusion from the published evidence is bounded: controllability of selected AI workloads has been demonstrated under particular hardware, workload and operating conditions, whereas a repeatable, settled grid resource has not been established by that evidence. The reported 256-GPU trial observed a 25% power reduction over three hours at the tested cluster while maintaining the service-quality target stated by its authors [15]; it did not establish whole-facility PCC delivery, an independently audited capacity rating or fleet-wide reliability. Most other studies remain analytical, trace-based or simulation-based, and their claims must retain their respective model, meter and experimental boundaries. This difference in evidence level is not resolved by increasingly sophisticated scheduling alone.
This Perspective therefore contributes a synthesis and a proposed workload-aware qualification pathway, rather than a new measurement standard or a validated market product. The framework connects task eligibility and SLA limits with locked PCC baselines, component attribution without double counting, uncertainty-aware delivered capacity, full recovery and repeated-activation performance (Section 4, Equations (1)–(6), Figure 2 and Table 2). Its illustrative three-hour example exposes a consequential distinction: an assumed 1.80 MW PCC response produces 5.40 MWh of event-period reduction, but 5.57 MWh of complete deferred-work, cooling and BESS recharge energy leaves −0.17 MWh of signed net energy; alternative recovery-period marginal-emissions assumptions can even reverse the emissions conclusion (Table 3 and Table 4). Those figures are hypothetical, not evidence of a tested facility or certified capacity. Accordingly, the illustrative 1.56 MW single-event lower bound cannot be promoted to a final qualified rating: the worked example remains NOT VERIFIABLE without representative repeated-event capacity-tail evidence and independently checked recovery criteria.
The open questions are empirical and institutional. Independent repeated PCC tests must establish reliability across climates, cooling technologies, workload mixes, stress conditions and receiving-site network constraints, including failed requests and correlated site outages. Market pilots must test baseline gaming resistance, SLA-preserving dispatch, settlement and the material costs of telemetry, audits, reserved headroom and re-certification. Consequential-emissions claims require feasible node- and time-specific dispatch counterfactuals that include recovery, storage losses, migration and any transferred peak. The six-network framework in Figure 4 is an additional planning hypothesis: water, underground corridors and logistics may constrain a site’s feasible operating envelope, but their value has not been demonstrated through a six-network field trial. The next step is pre-registered multi-site validation with transparent costs, water use, restoration times and system effects—not an assumption that nominally shiftable compute load is already a dependable grid asset.

Author Contributions

Conceptualization, H.L. and B.Y.; methodology, H.L.; investigation, H.L., Z.L. and J.Y.; writing—original draft preparation, H.L.; writing—review and editing, B.Y., Z.L., J.Y. and S.L.; visualisation, Z.L.; supervision, B.Y.; funding acquisition, B.Y. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Natural Science Foundation of China (grant number 62663026).

Institutional Review Board Statement

Not applicable.

Data Availability Statement

No new empirical datasets were generated or analysed for this Perspective. All numerical inputs and results in Section 4.5 and Table 3 and Table 4 are hypothetical illustrative assumptions and calculations reported in the manuscript; no underlying experimental dataset is associated with these examples.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. International Energy Agency. Key Questions on Energy and AI; IEA: Paris, France, 2026; Available online: https://www.iea.org/reports/key-questions-on-energy-and-ai (accessed on 27 October 2026).
  2. Tong, J.; Ding, H.; Chen, H.; Dai, J.; Dai, H.; Zhang, W. Electricity-computing power synergy: Connotation, architecture, technologies, and practice. Proc. CSEE 2026, 46, 5687–5707. [Google Scholar] [CrossRef]
  3. Ginzburg-Ganz, E.; Lifshits, P.; Machlev, R.; Belikov, J.; Krieger, Z.; Levron, Y. Technical Challenges of AI Data Center Integration into Power Grids—A Survey. Energies 2026, 19, 137. [Google Scholar] [CrossRef] [Scilit]
  4. Crozier, C.; Liska, M. The Potential of Data Center Energy Demand To Provide Grid Flexibility. Curr. Sustain./Renew. Energy Rep. 2025, 12, 12. [Google Scholar] [CrossRef] [Scilit]
  5. Zeng, B.; Xu, X.; Yang, F. Assessing the capacity value of demand flexibility from aggregated small Internet data centers in power distribution systems. Glob. Energy Interconnect. 2025, 8, 460–473. [Google Scholar] [CrossRef] [Scilit]
  6. Yang, Z.; Yang, B.; Liu, W.; Li, M.; Wang, J.; Jiang, L.; Sang, Y.; Pan, Z. Short-Term Wind Power Forecast Based on STL-IAOA-iTransformer Algorithm: A Case Study in Northwest China. Energy Eng. 2025, 122, 405–430. [Google Scholar] [CrossRef] [Scilit]
  7. Guo, D.; Yang, Z.; Dong, X.; Meng, X.; Yu, G.; Zheng, Y. Cloud-Edge Collaborative Forecasting for Industrial Photovoltaic-Storage-Charging Systems. Chin. J. Electr. Eng. 2026, 12, 171–184. [Google Scholar] [CrossRef] [Scilit]
  8. Kotla, R.W.; Madhavi, S.V.; Yarlagadda, S.R. Intelligent physics-aware deep Q-network controller for resilient and battery-sustainable electric vehicle energy management. Discov. Comput. 2026, 29, 642. [Google Scholar] [CrossRef] [Scilit]
  9. Srikanth, K.; Kunta, S.; Kotla, R.W.; Anil, N. Learning-assisted model reference adaptive control of unified power flow controller for enhanced power quality. J. Inst. Eng. (india) Ser. B 2026, 107, 1283–1298. [Google Scholar] [CrossRef] [Scilit]
  10. Federal Energy Regulatory Commission (FERC). Demand Response Compensation in Organized Wholesale Energy Markets, Order No. 745, 134 FERC ¶ 61,187; FERC: Washington, DC, USA, 2011.
  11. Efficiency Valuation Organization (EVO). International Performance Measurement and Verification Protocol (IPMVP): Core Concepts 2022; EVO: Washington, DC, USA, 2022. [Google Scholar]
  12. Gabaldón, A.; García-Garre, A.; Ruiz-Abellón, M.C.; Álvarez-Bel, C.; Fernandez-Jimenez, L.A.; Martínez-Ramos, J.L.; Valero-Verdú, S.; Rodríguez-García, J. Measurement and verification of demand response: The customer load baseline. In Industrial Demand Response: Methods, Best Practices, Case Studies, and Applications; Institution of Engineering and Technology: London, UK, 2024. [Google Scholar] [CrossRef] [Scilit]
  13. Xu, H.; Feng, C.; Li, B. Temperature aware workload management in geo-distributed data centers. IEEE Trans. Parallel Distrib. Syst. 2015, 26, 1743–1753. [Google Scholar] [CrossRef] [Scilit]
  14. Bessa, R.J.; Chatzivasileiadis, S.; Zhang, N.; Kang, C.; Hatziargyriou, N. Current and future applications of artificial intelligence in power systems: A critical appraisal. J. Mod. Power Syst. Clean Energy 2026, 14, 23–36. [Google Scholar] [CrossRef] [Scilit]
  15. Colangelo, P.; Coskun, A.K.; Megrue, J.; Roberts, C.; Sengupta, S.; Sivaram, V.; Tiao, E.; Vijaykar, A.; Williams, C.; Wilson, D.C.; et al. AI data centres as grid-interactive assets. Nat. Energy 2026, 11, 254–261. [Google Scholar] [CrossRef] [Scilit]
  16. Luo, A.; Tian, N.; Guo, Q. Why Computing-Electricity Coordination Has Not Scaled in Practice. Energy Internet 2026, 3, 81–85. [Google Scholar] [CrossRef] [Scilit]
  17. Wang, P.; Liu, W.; Yan, Y.; Cao, Y.; Wang, Z.; Dehghanian, P.; Ding, Z. Demand Flexibility Quantification for Data Centers: A Chance Constrained Bi-Level Model. IEEE Trans. Ind. Appl. 2026, 62, 5079–5090. [Google Scholar] [CrossRef] [Scilit]
  18. Zhou, Y.; Wei, F.; Li, S.; Wang, Z.; Liu, J.; Yu, D. Data center load modeling through optimal energy consumption characteristics: A path to simultaneously enhance energy efficiency and demand response quality. Appl. Energy 2025, 393, 126095. [Google Scholar] [CrossRef] [Scilit]
  19. Caprara, A.; Yu, Y.; Teng, F.; Junyent-Ferré, A.; Bullich-Massagué, E.; Aragüés-Peñalba, M. Data center workload flexibility for power system demand response: Evidence from Alibaba traces. Int. J. Electr. Power Energy Syst. 2026, 178, 111940. [Google Scholar] [CrossRef] [Scilit]
  20. Chen, C.; Ye, C.; Ding, Y.; Xiong, K.; Tang, X. Exploring the Demand Response Potential of Liquid-Cooled Data Centers. Appl. Energy 2026, 412, 127679. [Google Scholar] [CrossRef] [Scilit]
  21. Yu, Y.; Shan, K.; Tang, H.; Wang, S. Reliability and economic impacts of utilizing battery energy storage in data centers for energy flexibility services in smart grids. Energy Convers. Manag. 2025, 339, 119951. [Google Scholar] [CrossRef] [Scilit]
  22. Yu, Y.; Shan, K.; Li, H.; Wang, S. Quantitative impacts of energy system flexibility provision and design/operation on data center reliability and the key influential parameters. Appl. Energy 2026, 415, 127904. [Google Scholar] [CrossRef] [Scilit]
  23. Ling, L.; Song, D.; Hu, Q.; Xiang, Z.; Zhang, Z. Comprehensive index evaluation of the cooling system with the level loop thermosyphon system in different computing hub nodes in China. Energy Eng. 2025, 122, 3309–3328. [Google Scholar] [CrossRef] [Scilit]
  24. Yang, B.; Qian, Y.; Xu, J.; Ren, Y.; Chen, Y. Key issues for modelling, operation, management and diagnosis of lithium batteries: Current states and prospects. Energy Eng. 2024, 121, 2085–2091. [Google Scholar] [CrossRef] [Scilit]
  25. Jin, T.; Lu, Y.; Bai, L.; Chen, X.; Wen, J.; Zhang, Y. Renewable Energy Integration Enhancement by Exploiting Reserve Supply Capabilities of Data Centers and Cross-region Systems in Multi-region System Dispatch. J. Mod. Power Syst. Clean Energy 2026, 14, 833–844. [Google Scholar] [CrossRef] [Scilit]
  26. Wu, J.; Liu, S.; Bu, X.; Liu, C.; Liu, Y. Power Dispatch and Communication Transmission Co-Design for Frequency Regulation in Multiple Virtual Power Plants Based on Data Center Aggregation. Prot. Control Mod. Power Syst. 2026, 11, 68–80. [Google Scholar] [CrossRef] [Scilit]
  27. Yang, H.; Si, Y.; Liu, Y.; Mu, S.; Huang, J.; Luo, Y. Capacity optimization of data center microgrid coupling computing-power and electricity consumption. Glob. Energy Interconnect. 2026, in press. [Google Scholar] [CrossRef] [Scilit]
  28. Guo, H.; Yu, H.; Wang, M.; Liu, C.; Li, C. Integrated management of workloads and energy system for data centers. Energy 2025, 327, 136400. [Google Scholar] [CrossRef] [Scilit]
  29. Wen, Y.; Cheng, Z.; Liu, X.; Sun, Y.; Song, W.; Zhang, Y. Energy optimization management of edge data centers considering computing power-electrothermal coupling. Proc. CSEE 2026, 46, 186–197. [Google Scholar] [CrossRef]
  30. Ye, Y.; Ma, D.; Wu, Y.; Hu, H.; Zhang, X.; Liu, C.; Xu, D. Harvesting spatial-temporal load migration flexibility of data centers: A chance-constrained bi-level optimization model with endogenously formed risk-reflective locational prices. Appl. Energy 2026, 402, 126971. [Google Scholar] [CrossRef] [Scilit]
  31. Chen, C.; Pang, A.; Wang, Y.; Chen, F.; Xie, S.; Chen, Y.; Shao, Z.; Lin, Z. Triple-Stage Collaborative Optimization Method for Cross-Regional Data Centers Considering Optimal Coalition Matching. IEEE Trans. Smart Grid 2026, 17, 2946–2963. [Google Scholar] [CrossRef] [Scilit]
  32. Tu, C.; Pan, X.; Wang, H.; Meng, Y.; Dai, J.; Wang, X. Optimization of computing power and electricity synergy considering diverse green electricity consumption modes and spatio-temporal flexibility. Electr. Power Constr. 2026, 47, 1–13. [Google Scholar] [CrossRef]
  33. Lin, Y.; Lu, Z.; Qiao, Y.; Chen, R. Flexible region aggregation of adjustable loads via an adaptive convex hull strategy. Glob. Energy Interconnect. 2025, 8, 106–120. [Google Scholar] [CrossRef] [Scilit]
  34. Pan, T.; Li, C.; Yang, C.; Meng, Z.; Wang, Z.; Zhu, Z. Multiagent, multitimescale aggregated regulation method for demand response considering spatial–temporal complementarity of user-side resources. Glob. Energy Interconnect. 2025, 8, 240–257. [Google Scholar] [CrossRef] [Scilit]
  35. Wang, G.; Jiang, B.; Liu, Y.; Wang, L.; Zhang, Y.; Yan, J.; Wang, K. Source-load coordinated optimization framework for distributed energy systems using quasi-potential game method. Prot. Control Mod. Power Syst. 2025, 10, 103–122. [Google Scholar] [CrossRef] [Scilit]
  36. Sadiq, E.H.; Antar, R.K. Minimizing power losses in distribution networks: A comprehensive review. Chin. J. Electr. Eng. 2024, 10, 20–36. [Google Scholar] [CrossRef] [Scilit]
  37. Yang, X.; He, H.; Zhu, J.; Yang, H.; Zheng, Y.; Lei, Y.; Long, Z.; Xu, Y. A discrete-continuous two-layer optimization methodology for distribution networks considering power converter embedded hybrid on-load regulator transformers. Chin. J. Electr. Eng. 2025, 11, 105–118. [Google Scholar] [CrossRef] [Scilit]
  38. Ma, R.; Zhou, Q.; Liu, S.; Yan, Q.; Shi, M. Security distance analysis of active distribution network considering energy hub demand response. Glob. Energy Interconnect. 2025, 8, 160–173. [Google Scholar] [CrossRef] [Scilit]
  39. Cao, D.; Yao, L.; Yuan, R.; Xu, Y.; Tian, S.; Xu, J.; Liao, S. A dynamic aggregation method for flexible load resources participating in demand response considering multiple ancillary service scenarios regulation requirements. J. Glob. Energy Interconnect. 2026, 9, 133–147. [Google Scholar] [CrossRef]
  40. Zeng, K.; Zhang, S.; Wang, Y.; Ye, J.; Jiang, X.; Lin, Z.; Yang, L. Optimal power purchase decision-making for receiving-end power system considering uncertainties in two-level inter-provincial and intra-provincial electricity markets. Energy Convers. Econ. 2025, 6, 281–294. [Google Scholar] [CrossRef] [Scilit]
  41. Xiao, Y.; Zhu, Y.; Qu, Y.; Zhao, J.; Xie, H.; Wang, X.; Wang, X. Locational marginal capacity pricing for power system resilience. Energy Convers. Econ. 2025, 6, 410–421. [Google Scholar] [CrossRef] [Scilit]
  42. Li, G.; Wu, H.; Zhang, R.; Hou, K.; Jia, H.; Chen, H. Coordinating Transactive Demand Response and Rolling Outage Management of Diverse Loads to Enhance Resilience of Distribution Systems. J. Mod. Power Syst. Clean Energy 2026, 14, 980–990. [Google Scholar] [CrossRef] [Scilit]
  43. Huang, Q.; Zhuang, Z.; Duan, M.; Yang, S.; Sheng, J.; Huang, Y. A Stackelberg game-based model for low-carbon scheduling of commercial building loads considering lifecycle unit carbon-emission factors. Energy Convers. Econ. 2025, 6, 39–53. [Google Scholar] [CrossRef] [Scilit]
  44. Pashaei, M.; Kauhaniemi, K.; Laaksonen, H.; Hatziargyriou, N. Development of Virtualized Centralized Protection and WAMPAC Systems: A Review. Prot. Control Mod. Power Syst. 2026, 11, 1–25. [Google Scholar] [CrossRef] [Scilit]
  45. Ding, Y.; Sun, X.; Zhao, Y.; Lyu, C.; Chen, J.; Li, X.; Shi, W.; Ruan, J.; Xu, Z. Multi-stage Electricity-carbon Joint Management with Decision-oriented Predict-then-optimize Method. J. Mod. Power Syst. Clean Energy 2026, 14, 1100–1112. [Google Scholar] [CrossRef] [Scilit]
  46. Qin, W.; Li, X.; Jing, X.; Zhu, Z.; Lu, R.; Han, X. Multi-temporal optimization of virtual power plant in energy-frequency regulation market under uncertainties. J. Mod. Power Syst. Clean Energy 2025, 13, 675–687. [Google Scholar] [CrossRef] [Scilit]
  47. Yang, Y.; Mou, Y.; Li, J.; Wang, B.; Li, C.; Yang, X. Impact of capacity market mechanism on high renewable penetration systems with long-term energy storage. Energy Convers. Econ. 2025, 6, 295–307. [Google Scholar] [CrossRef] [Scilit]
  48. Li, S.; Zhang, J.; He, Y.; Lv, G.; Liu, Y.; Hu, X.; Wang, Z.; Ao, X. Two-stage capacity allocation optimization method for user-level integrated energy systems considering user satisfaction and thermal inertia. Glob. Energy Interconnect. 2025, 8, 300–315. [Google Scholar] [CrossRef] [Scilit]
  49. Ge, W.; Wang, X. Study of source-load interaction in demand response considering the potential of flexible load dispatch. Chin. J. Electr. Eng. 2024, 10, 141–151. [Google Scholar] [CrossRef] [Scilit]
  50. Xiao, C. Research on flexible load aggregation and coordinated control methods considering dynamic demand response. Energy Eng. 2025, 122, 2719–2750. [Google Scholar] [CrossRef] [Scilit]
  51. Senga, J.R.L.; Wang, S.; Knittel, C.R. Flexible data centers reduce power system costs but can increase emissions. iScience 2026, 29, 116497. [Google Scholar] [CrossRef] [Scilit]
  52. Hall, S.; Micheli, F.; Belgioioso, G.; Radovanović, A.; Dörfler, F. Carbon-Aware Computing for Data Centers with Probabilistic Performance Guarantees. IEEE Trans. Power Syst. 2025, in press. [Google Scholar] [CrossRef] [Scilit]
  53. ISO/IEC 21031:2024; Software Carbon Intensity (SCI) Specification. Green Software Foundation: London, UK, 2024. Available online: https://greensoftware.foundation/standards/sci/ (accessed on 27 October 2026).
  54. Wang, J.; Wen, J.; Long, C.; Yang, B.; Jiang, L. Global electricity-carbon market nexus: A systematic review of synergistic efforts towards a net-zero power sector. Appl. Energy 2026, 402, 126992. [Google Scholar] [CrossRef] [Scilit]
  55. Chen, X.; Chao, H.; Shi, W.; Li, N. Towards carbon-free electricity: A flow-based framework for power grid carbon accounting and decarbonization. Energy Convers. Econ. 2024, 5, 396–418. [Google Scholar] [CrossRef] [Scilit]
  56. Ruan, J.; Zhu, Y.; Cao, Y.; Sun, X.; Lei, S.; Liang, G.; Qiu, J.; Xu, Z. Privacy-Preserving Bi-Level Optimization of Internet Data Centers for Electricity-Carbon Collaborative Demand Response. IEEE Internet Things J. 2024, 11, 24948–24959. [Google Scholar] [CrossRef] [Scilit]
  57. Zhang, Z.; Du, Y.; Yang, F.; Xing, Y.; Wu, H. Current-Sensor-Less Control with Fast Transient Response for Pulsed Power Load. Chin. J. Electr. Eng. 2026, 12, 134–145. [Google Scholar] [CrossRef] [Scilit]
  58. Lin, Y.; Luo, H.; Chen, Y.; Yang, Q.; Zhou, J.; Chen, X. Enhancing participation of widespread distributed energy storage systems in frequency regulation through partitioning-based control. Prot. Control Mod. Power Syst. 2025, 10, 76–89. [Google Scholar] [CrossRef] [Scilit]
  59. Cai, Z.; Liu, X.; Li, C.; Tai, N.; Huang, W.; Huang, S.; Wei, J. Dual alternative iteration algorithm-based hierarchical MPC strategy for frequency regulation control and active power allocation of wind-storage coupling system. Prot. Control Mod. Power Syst. 2025, 10, 160–175. [Google Scholar] [CrossRef] [Scilit]
  60. Liu, P.; Feng, Z.; Wei, P.; Li, H.; Liu, Q.; Chen, Y. Optimal control strategy for frequency response of V2G grid-connected inverter considering SOC characteristics. Chin. J. Electr. Eng. 2025, 11, 127–145. [Google Scholar] [CrossRef] [Scilit]
  61. Xue, L.; Wang, J.; Li, H.; Yong, W.; Zhang, Y. Online energy conservation scheduling for geo-distributed data centers with hybrid data-driven and knowledge-driven approach. Energy 2025, 322, 135714. [Google Scholar] [CrossRef] [Scilit]
  62. Bian, Y.; Xie, L.; Ma, L.; Cui, C. A novel two-stage energy sharing model for data center cluster considering integrated demand response of multiple loads. Appl. Energy 2025, 384, 125454. [Google Scholar] [CrossRef] [Scilit]
  63. Zhu, D.; Liu, S.; Yang, B.; Deng, H.; Wu, Y.; Dong, Z.Y. Energy optimization for data centers via carbon-aware multi-energy market coordination. Appl. Energy 2026, 409, 127371. [Google Scholar] [CrossRef] [Scilit]
  64. Cui, R.; Hu, C.; Yang, R.; Cui, X.; Hou, F.Y. Co-Optimization of Coincident Peak Management and Ancillary Services for Flexible Data Centers. IEEE Trans. Smart Grid 2026, 17, 5405–5417. [Google Scholar] [CrossRef] [Scilit]
  65. Ma, Y.; Wang, H.; Yu, W.; Cao, F.; Cheng, S.; Yang, A. User-side cloud energy storage configuration and operation optimization considering time-of-use pricing and state-of-charge management. Energy Convers. Econ. 2025, 6, 65–82. [Google Scholar] [CrossRef] [Scilit]
  66. Qiu, D.; Strbac, G.; Zhang, C.; Dong, Z.Y. Flexibility technologies in clean energy systems. Nat. Rev. Clean Technol. 2026, in press. [Google Scholar] [CrossRef] [Scilit]
  67. Yang, B.; Luo, Z.; Yao, W. A Review of Artificial Intelligence-Based Optimal Scheduling for Integrated Energy Systems. Comput. Mag. CCF 2025, 1, 39–48. [Google Scholar] [CrossRef]
  68. Hou, S.; Salazar, E.M.; Palensky, P.; Chen, Q.; Vergara, P.P. A mix-integer programming based deep reinforcement learning framework for optimal dispatch of energy storage system in distribution networks. J. Mod. Power Syst. Clean Energy 2025, 13, 597–608. [Google Scholar] [CrossRef] [Scilit]
  69. Li, C.; Sun, J.; Li, Q.; Guo, Q.; Li, J.; Yu, S.; Wang, J.; Li, W. Hierarchical optimal scheduling strategy for high proportion new energy power systems considering balanced response to grid flexibility. Energy Eng. 2025, 122, 3055–3077. [Google Scholar] [CrossRef] [Scilit]
  70. Li, J.; Yang, B.; Zhou, Y.; Shu, H.; Li, H.; Gao, D.; Jiang, L. Coordinated low-carbon economic scheduling of integrated electricity-heat-gas-hydrogen-methanol multi-microgrids considering electricity-methanol transaction. Expert Syst. Appl. 2026, 298, 129701. [Google Scholar] [CrossRef] [Scilit]
  71. Yang, B.; Jiang, Z.; Wen, J.; Yang, N.; Qu, K.; Zhou, S. AI-driven interaction and collaborative optimization of vehicle, charging station and grid: Challenges and prospects. Energy Eng. 2025, 122, 2187–2195. [Google Scholar] [CrossRef] [Scilit]
  72. Yang, B.; Zhou, Y.; Yan, Y.; Su, S.; Li, J.; Yao, W.; Li, H.; Gao, D.; Wang, J. A critical and comprehensive handbook for game theory applications on new power systems: Structure, methodology, and challenges. Prot. Control Mod. Power Syst. 2025, 10, 1–27. [Google Scholar] [CrossRef] [Scilit]
  73. Yang, B.; Zhou, G.; Zhou, S.; Hu, Y.; He, B.; Guo, Z.; Luo, Z.; Li, H.; Gao, D.; Wang, J.; et al. Multi-objective optimal bi-level scheduling of hybrid mobile-stationary energy storage systems for flexible distribution network. J. Clean. Prod. 2025, 525, 146534. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.