Economic Selection and Sequencing of Quality Improvement Projects Under Stochastic Process States: A Taguchi Expected Loss Approach

,
,
,
and
Department of Industrial Engineering, TOBB University of Economics and Technology, Ankara 06560, Türkiye
*
Author to whom correspondence should be addressed.
Appl. Sci.2026, 16(23), 11784;https://doi.org/10.3390/app162311784 
(registering DOI)

Abstract

Six Sigma project selection requires balancing expected quality improvements against implementation costs, durations, and limited resources. This study develops an economic evaluation approach based on Taguchi’s expected quality loss, modeling process mean shifts and dispersion changes as random process states and distinguishing their contributions to the expected loss. The avoided loss of each improvement project is derived according to its effect on these two components and incorporated into a deterministic mixed-integer programming model for budget- and horizon-constrained project selection and sequencing. For any selected portfolio, the optimal implementation order follows the weighted shortest processing time rule. In an illustrative scenario calibrated from published manufacturing cases, the project with the second-largest reduction in standard deviation (a scenario target) is excluded because of its cost and duration, although the budget is not binding. A heterogeneous example further shows that evaluating projects using aggregate quality loss alone can lead to a less valuable portfolio when improvement mechanisms differ. In a computational study of 3600 instances, six conventional prioritization rules fell more than 5% below the optimum in 30–86% of the 3369 instances with a profitable portfolio. The approach provides a reproducible economic criterion that complements multi-criteria project evaluation.

1. Introduction

Continuous quality improvement helps organizations reduce costs and improve competitiveness [1,2,3,4]. However, limited financial, technical, and human resources prevent firms from pursuing every improvement opportunity. Selecting projects that offer the greatest economic benefit is therefore a critical decision, particularly when several projects compete for the same resources [5].
Among quality improvement approaches, Six Sigma has become a widely used data-driven methodology, aiming to reduce process variation to the level at which only 3.4 defects per million opportunities occur through the structured Define–Measure–Analyze–Improve–Control cycle [1,6]. This figure conventionally assumes a 1.5σ long-term mean shift [7,8]. Within this cycle, the Define phase, in which candidate projects are identified and selected, is widely regarded as decisive: because organizations operate under limited time, capital, and specialized personnel, choosing the right projects is repeatedly cited as a critical success factor [5,9], while an unrealistic project scope is reported as one of the most common causes of project failure [5]. To formalize this decision, a substantial part of the literature frames project selection as a multi-criteria decision-making (MCDM) problem, most often addressed with the Analytic Hierarchy Process (AHP) and the Analytic Network Process (ANP), alongside related techniques such as the Technique for Order of Preference by Similarity to Ideal Solution (TOPSIS), failure mode and effects analysis (FMEA), and their fuzzy extensions [10,11]. Taguchi’s quality loss function offers a complementary economic perspective by expressing deviations from target values as monetary losses [12,13].
Despite these advances, two complementary gaps remain. First, prevailing MCDM-based selection methods ultimately rely on criterion weights obtained from the subjective judgments of decision-makers or experts [10]; we argue that, because these weights depend on who is consulted, the resulting rankings may vary across managers or panels, limiting their reproducibility. Second, the classical cost-based alternative, the Taguchi expected loss, is conventionally evaluated at a fixed, known process mean and standard deviation. In practice, no process is perfectly stable: once it leaves statistical control, the mean may drift off target, and the dispersion may change by amounts that are themselves uncertain [14]. Although Six Sigma practice conventionally allows for a fixed, known 1.5σ mean shift, existing cost-based formulations generally treat this shift as a deterministic displacement rather than an uncertain quantity. Among the studies reviewed here, we did not identify a formulation that jointly represents stochastic mean shifts and dispersion scaling within a Taguchi expected-loss framework and connects the resulting measure to project selection and sequencing. Evaluated as a single expectation, such a measure coincides with the classical expected loss of the long-run marginal distribution of the quality characteristic. The gap therefore lies not in the loss value but in how the benefit of an improvement project is derived from it since projects typically reduce the mean shifts and the dispersion to different degrees (see Section 2).
This paper addresses the two gaps in different ways: it addresses the representational gap by separating the expected loss into components attributable to random shifts of the mean and to the dispersion in each process state and by evaluating each project according to the components it reduces; it addresses the methodological gap not by replacing multi-criteria evaluation but by providing a procedurally reproducible economic alternative on the cost dimension, while leaving the strategic-alignment, customer-impact, feasibility, and risk dimensions of MCDM outside its scope. Accordingly, this paper pursues two objectives. The first is to derive a cost-based project-evaluation measure that replaces subjectively derived criterion weights with a small set of explicit, separately documented inputs. These inputs, namely implementation costs, durations, improvement effects, the loss coefficient, and the evaluation horizon, also involve estimation and judgment; unlike criterion weights, however, each of them can be documented separately, updated from process and cost data, and examined in a sensitivity analysis. The second is to build, on this measure, two decision tools for two decision contexts: a selection criterion, namely the net avoided-loss benefit, by which projects with the largest positive values are chosen, and a sequencing criterion that, subject to a budget constraint, jointly selects and orders a subset of candidate projects to maximize the cumulative net benefit.
The contribution of this study is an integration rather than a new optimization method. Taguchi’s expected loss, the law of total expectation, the weighted shortest processing time (WSPT) rule, and the order acceptance and scheduling framework are established tools. What the study adds is a state-resolved evaluation of improvement projects. The expected loss is separated into a between-state component, arising from shifts of the process mean, and a within-state component, arising from the dispersion in each state, and each project is described by the proportions γ and δ in which it reduces the two sources. For projects that reduce both in the same proportion (scale-reduction projects, γ = δ), the aggregate loss suffices; for projects that act on only one source, the avoided loss depends on the share of each component, and evaluating them on the aggregate loss can select a different and less valuable portfolio (Section 6.3). These avoided losses are then used as weights in a budget-constrained selection-and-sequencing model, whose sequencing sub-problem is solved by the WSPT rule. Only the process states are random; the selection and sequencing decisions are deterministic and are optimized on expected values.
The present study focuses on nominal-the-best quality characteristics, for which the resulting expected quality loss decomposes into interpretable components reflecting systematic centering error, centering instability, the squared-mean dispersion-scale term, and dispersion instability.
The remainder of this paper is organized as follows. Section 2 reviews the related literature. Section 3 develops the expected-loss evaluation and the effects of different improvement mechanisms, while Section 4 formulates the selection-and-sequencing problem. Section 5 and Section 6 present the numerical illustration, sensitivity analyses, and computational results. Section 7 and Section 8 discuss the implications and conclusions. Supplementary analyses are provided in the appendices.

2. Literature

This section reviews the Six Sigma methodology and the role of project selection within it, existing approaches to selecting Six Sigma projects, the Taguchi quality loss function as a cost basis for evaluation, and related scheduling models and identifies the gaps that motivate this study.

2.1. Six Sigma

The Six Sigma methodology was developed in the mid-1980s by Motorola engineer Bill Smith [2,3,7] to reduce process variability so that defects fall to 3.4 per million opportunities, moving traditional quality control from isolated operational fixes toward a strategic tool for operational efficiency and customer satisfaction [1,15]. Statistically, the framework requires the process mean to lie at least six standard deviations (6σ) from the nearest specification limit; by allowing for an expected 1.5σ mean shift over time, it controls process variation and minimizes the probability of non-conformance [7,8].
The philosophy of Six Sigma marks a shift from reactive detection to proactive variation reduction. Instead of treating any outcome within the specification limits as equally acceptable, it emphasizes reducing variability around the target itself [7]. In this respect, it aligns with Taguchi’s quality loss function, under which any deviation from the target incurs hidden economic costs and degrades performance [12]. Combined with Lean Management into Lean Six Sigma [2,3], Six Sigma remains the component in which improvement projects require explicit investments whose return must be weighed against their cost and duration, which is the setting of the evaluation proposed here.
To operationalize this, Six Sigma follows the data-driven DMAIC cycle (Define, Measure, Analyze, Improve, Control), a structured roadmap for improvement initiatives [6]. Define identifies customer requirements and selects the project; Measure and Analyze use statistical quality control tools such as Pareto charts and capability analyses to quantify performance and isolate the root causes of variation; Improve then optimizes process parameters, and Control sustains the gains through continuous monitoring [6]. In this way, DMAIC bridges high-level quality philosophy and practical execution [1,15].
Although conceived within high-volume manufacturing, Six Sigma has since transcended its industrial origins, adapting over the past two decades to service industries, healthcare, and finance [3,16,17,18]. This required a shift from controlling machine-driven variance to optimizing complex, human-centric, and transactional processes.

2.2. Strategic Selection of Six Sigma Projects in the Quality Improvement Process

Despite the efficacy of Six Sigma in variance reduction, its success in driving quality improvement depends on the initial selection of projects. Organizations operate under limited resources such as time, capital, and specialized personnel such as Black Belts. Directing these assets toward poorly chosen projects wastes resources and undermines the credibility of the quality initiative [5]. Wrong project selection, together with statistically significant improvements that do not translate into savings commensurate with the investment, is among the reasons for which organizations discontinue Lean Six Sigma initiatives [19]. Oversized projects, moreover, lose valuable time in the Define phase [9]. Project selection is therefore a strategic decision that largely determines whether an improvement effort generates value or merely organizational fatigue.

2.3. Approaches to Six Sigma Project Selection

Because the selection decision governs the return on a Six Sigma initiative, a substantial body of work has sought to formalize how candidate projects are evaluated and prioritized. Projects are assessed against multiple, often competing criteria: expected financial benefit, strategic alignment, customer impact, technical feasibility, resource requirements, and implementation risk [5,20]. Because these criteria are heterogeneous and conflicting, the most common response in the literature has been to frame project selection as a multi-criteria decision-making (MCDM) problem.
Within this stream, MCDM methods account for about one-third of the methods reviewed by Pakdil [11], with the Analytic Hierarchy Process (AHP) [21,22] the single most frequently used technique; its network generalization, the Analytic Network Process (ANP), is also applied [11]. Kumar et al. [5] propose a hybrid method coupling AHP with a project desirability matrix, validated through a case study in a small and medium-sized manufacturer, and note that project selection remained a neglected topic despite its effect on deployment success. Büyüközkan and Öztürkcan [10] combine the Decision-Making Trial and Evaluation Laboratory (DEMATEL) method with the ANP to capture interdependencies among criteria and derive their weights, demonstrating the approach on a logistics company. The literature also draws on TOPSIS, project prioritization matrices, and FMEA, along with fuzzy extensions intended to accommodate the imprecision of expert judgments [5,10,11]. Outside the Six Sigma setting, Uluskan and Beki [23] develop a customized interval type-2 fuzzy ORESTE method for project prioritization and benchmark it against fuzzy TOPSIS on a set of automotive-manufacturing projects. Within Lean Six Sigma, Singh et al. [24] aggregate the judgments of several evaluators with intuitionistic fuzzy operators, derive criterion weights by entropy, and rank eight projects of a manufacturing organization with modified TOPSIS and VIKOR. Despite their adoption, these approaches typically share a common feature: the criterion weights that drive the ranking are, in most formulations, elicited from expert judgments [10], and in practice, project prioritization often still relies on subjective judgment [11,25]. Fuzzy and type-2 fuzzy extensions mitigate the imprecision within a given expert’s judgment, but they do not remove the dependence of the weights on which experts or panels are consulted, which may limit the consistency and reproducibility of the resulting ranking. At the same time, monetary criteria are not free of judgment either since implementation costs, improvement effects, and loss coefficients must also be estimated; the economic criterion developed in this study is therefore positioned as a complement to, rather than a substitute for, these methods (Section 7).
A smaller stream formulates the prioritization as an optimization problem. Aqlan and Al-Fandi [26] rank the work areas of a manufacturing plant and then select improvement projects and assign operators to them with a goal-programming model that maximizes the weighted benefit and minimizes the implementation difficulty under budget and operator-time constraints; the benefit of each project is an input estimated in advance, and its dependence on when the project is completed is not modeled. In project portfolio selection more generally, MCDM methods are commonly combined with mathematical programming when resources are constrained [27]. Cost-of-quality approaches trace quality losses to their root causes and prioritize improvement projects by the net present value, leaving the optimization of the project portfolio to future research [28].

2.4. The Taguchi Quality Loss Function and the Assumption of Fixed Process Parameters

A natural candidate for a criterion-weight-free monetary basis of comparison is the Taguchi quality loss function. Departing from the ‘goalpost’ view, the Taguchi quality loss function models quality loss as a continuous quadratic function of the deviation of a quality characteristic from its target. The loss grows disproportionately as the characteristic drifts from target and, crucially for project evaluation, expresses quality as a monetary cost rather than a binary conforming/non-conforming state [12]. Yacout and Boudreau [13] later apply this formulation to compare alternative quality policies on a common cost basis. More recently, Chen et al. [29] used a process improvement capability index built on the expected Taguchi loss, in which the precision term is weighted by the ratio of the costs of improving accuracy and precision, to evaluate the improvement capability of suppliers with a fuzzy test. Taguchi distinguishes characteristics with a nominal target value from smaller-is-better and larger-is-better characteristics [12]. The Taguchi loss formulation also remains an active basis for recent extensions; Wang et al. [30], for example, develop a quadratic-exponential quality gain–loss function that relaxes the symmetric-quadratic form to accommodate asymmetric loss and non-normal quality characteristics.
The same target-oriented logic underlies loss-based process capability indices. The index Cpm is built on the expected squared deviation from the target, penalizing both process dispersion and off-target centering within a single measure [14,31,32]. As such, Cpm offers a mathematically similar, non-subjective way of jointly penalizing off-target centering and dispersion, though it addresses only the cost dimension and does not substitute for the multi-criteria weighting schemes reviewed in Section 2.3.
The assumption of deterministic process parameters is restrictive, and it is shared by the classical Taguchi loss as originally formulated [12] and by the Cpm index above, each of which plugs in a mean and standard deviation taken as fixed and known. Yacout and Boudreau [13] assume that when an assignable cause occurs the mean shifts by a fixed amount while the standard deviation stays constant. In practice, once a process goes out of control both a shift in the mean and a change in the dispersion occur, and the magnitude of each is uncertain. Treating these parameters as deterministic ignores this uncertainty and limits how well the classical measure reflects the conditions under which projects must be prioritized.
This limitation persists across the streams that come closest to modeling out-of-control behavior. In the economic design of control charts, the occurrence of an assignable cause is treated probabilistically. For instance, Duncan [33] models the assignable cause as occurring after an exponentially distributed waiting time (i.e., as Poisson arrivals); yet each assignable cause shifts the mean by a known amount, and the standard deviation is explicitly held constant, so any change in the dispersion is never represented. An extension to several causes with different known shifts is outlined but not used in the design procedure. Economic design, which chooses the charting parameters so as to minimize the total expected cost, remains one of the three main approaches to the optimization design of control charts, together with statistical and economic-statistical design [34]. No prior study we reviewed links the improvement mechanism of a project to the components of such a loss measure and uses the resulting benefits for project selection and sequencing.
To make the relation to these models precise, consider the special case in which an assignable cause shifts the mean by a fixed ±a standard deviations, the dispersion is unchanged, and a fraction p of the units is produced out of control. In the notation of Section 3.1, where K and Λ denote the standardized mean shift and the dispersion scale of the process state, E[K2] = pa2 and E[Λ2] = 1, and the expected loss of Equation (1) is cσ2(1 + pa2), which is the expected loss per unit of the policy without appraisal or prevention in Yacout and Boudreau [13], with c calibrated at the specification limit as in Section 3.1 ( c = A 0 / Δ 0 2 ) and p the expected out-of-control fraction of the production cycle; the economic model of Duncan [33] rests on the same two-state structure. The present formulation therefore contains these models as a special case and differs from them in three respects. First, the magnitudes of the shift and of the dispersion change are random, so that several out-of-control conditions with different shifts and dispersions can be represented and their moments estimated from statistical process control (SPC) data (Section 3.1). Second, the expected loss is separated into between-state and within-state components; this separation does not change the loss value and is needed only when a project acts on the two components to different degrees (Section 3.2). Third, the resulting benefits are used to select and sequence improvement projects, rather than to design a monitoring scheme or to compare quality policies. Loss-based indices such as Cpm, also called the Taguchi cost loss index [31,32], and its extension with improvement costs [29] account for the sampling uncertainty of estimated parameters through hypothesis tests, confidence intervals, or fuzzy tests, but they evaluate a single stable process and do not represent out-of-control states, budget-constrained choices among projects, or the timing of benefits.
Taken together, the literature reveals two complementary gaps that a single response can address in different ways. The first is methodological: existing MCDM-based selection methods rest on criterion weights derived from decision-makers. The second is representational: the classical cost-based alternatives are, as conventionally formulated, evaluated at fixed, known process parameters and therefore do not represent the joint uncertainty in mean shift and dispersion that characterizes out-of-control processes. Because the expected quality loss is expressed on a single monetary scale, projects can be scored and ordered on the economic dimension without eliciting criterion weights, and the ranking is reproducible given documented inputs.

2.5. Sequencing and Selection of Improvement Projects as a Scheduling Problem

Once a set of improvement projects has been selected, ordering them to maximize a completion-time–weighted benefit is a single-machine sequencing problem: minimizing a weighted sum of completion times is solved optimally by sequencing jobs in non-increasing order of the weight-to-duration ratios, the WSPT rule [35,36]. When not all candidates can be carried out, so that the model must also decide which to accept under a budget, the decision becomes the joint problem of which jobs to accept and how to sequence them, studied in the order acceptance and scheduling (OAS) literature [37,38] and, in the related setting of multi-stage project portfolios, in integrated selection-and-scheduling models [39], as well as in the closely related field of scheduling with rejection [35,40]. Slotnick [37] explicitly situates project selection and sequencing on a single processor within this field. The sequencing sub-problem of this study is reduced to the classical WSPT rule, while the budget-constrained joint model is closely related to OAS and selection problems; what is specific to the present study is the set of weights that drive the ordering rule, derived from the state-resolved expected loss according to the improvement mechanism of each project.
Table 1 compares representative studies across three research streams: quality-loss evaluation, improvement project selection, and integrated selection and scheduling. Existing approaches do not jointly connect process-state-dependent quality losses, project-specific improvement mechanisms, and completion-time-dependent economic benefits. This connection forms the basis of the proposed framework.
Table 1. Representative studies on loss-based process evaluation, the selection of improvement projects and integrated selection, and scheduling, compared with the present study.

3. Analytical Formulation of the Expected Quality Loss

In this section, we express the modified Taguchi quality loss function and the expected quality loss function under quality improvement in closed form, extending the classical Taguchi loss framework to represent process behavior under out-of-control situations and varying dispersion levels. For tractability and notational convenience, the derivations below are presented for a single quality characteristic, denoted by Y; a product with multiple critical-to-quality characteristics (CTQs) is treated in Section 4 by applying this derivation separately to each characteristic. The analysis proceeds in two stages. First, in Section 3.1, we develop the modified Taguchi quality loss function, which quantifies the economic loss arising when the CTQ characteristic deviates from its target value, while incorporating the effects of process mean shifts and varying levels of dispersion. Then, in Section 3.2, we build upon this loss function to derive the expected quality loss function under quality improvement. Together, these derivations provide the analytical foundation for the optimization developed in the remainder of the paper.
In our analysis, Y denotes the quality characteristic, t its target, c the Taguchi loss coefficient, K the standardized mean-shift state, and Λ the dispersion-scaling state.

3.1. Modified Taguchi Quality Loss Function

When a product has multiple quality characteristics, the same derivation applies to each characteristic i separately, with its own Ki, Λi, σi, and ci. To keep the notation light, this characteristic index i is suppressed when there is only one characteristic to evaluate. To model the frequency and magnitude of out-of-control behavior, we represent the mean-shift state K and the dispersion-scaling state Λ ∈ (0,∞) as two random variables.
Let σ > 0 denote the in-control standard deviation of the quality characteristic. Conditional on the process state (K, Λ), the process mean and standard deviation are assumed to be t + Kσ and Λσ, respectively. Let E[K] = μK, Var K = σ K 2 ,  E[Λ] = μΛ, and Var ( Λ ) = σ Λ 2 . Only these first two marginal moments of each state variable are required in the derivation. We refer to μ K ,   σ K 2 ,   μ Λ , and σ Λ 2 as the process-state moments. Values Λ > 1 represent dispersion inflation relative to the in-control state, whereas 0 < Λ < 1 represents dispersion contraction.
The in-control state corresponds to (K, Λ) = (0, 1); thus, the in-control process is assumed to be centered on the target, with mean t and standard deviation σ. Let F K , Λ denote the long-run joint distribution of (K, Λ) over the entire evaluated production horizon. This is an unconditional distribution that includes both in-control and out-of-control production. It assigns probability (1 − p) to the in-control state and the remaining mass p to the out-of-control state; here, p ∈ (0, 1) is the long-run fraction of production in the out-of-control state (OOC) (p = P(OOC)).
The quality loss function is given as C(Y) = c(Y − t)2, and our aim is to compute its expected value under the joint randomness of K and Λ. Here, c > 0 is the quality-loss coefficient, converting squared deviation from the target into monetary loss per unit produced; its value depends on the specific quality characteristic and production context. Applying the law of total expectation over the joint distribution of K and Λ,
E [ C ( Y ) ] = E K , Λ E c ( Y − t ) 2 | K , Λ
Conditional on K and Λ, the quality characteristic has conditional mean [t + Kσ] and conditional variance [(Λσ)2]. By the bias–variance decomposition of mean squared error, which holds for any distribution with finite second moment, the conditional expected loss is the sum of the conditional variance and the squared conditional bias, expressed as
E c ( Y − t ) 2 | K , Λ = c Var ( Y | K , Λ ) + ( E [ Y | K , Λ ] − t ) 2
= c Λ σ 2 + ( K σ ) 2 = c σ 2 ( K 2 + Λ 2 )
Taking the expectation of this conditional loss over the joint distribution of K and Λ and using the linearity of expectation together with E [ K 2 ] = σ K 2 + μ K 2 and E [ Λ 2 ] = σ Λ 2 + μ Λ 2 ,
E [ C ( Y ) ] = E K , Λ c σ 2 ( K 2 + Λ 2 ) = c σ 2 E [ K 2 ] + E [ Λ 2 ]
E [ C ( Y ) ] = c σ 2 ( σ K 2 + μ K 2 ) + c σ 2 ( σ Λ 2 + μ Λ 2 )
Restoring the characteristic index i suppressed during the derivation, this result is written for characteristic i as
E [ C ( Y ) ] i = c i σ i 2 ( σ K 2 i + μ K 2 i + σ Λ 2 i + μ Λ 2 i )
Equation (1) requires only finite second moments of K and Λ; independence is unnecessary because the conditional loss contains no cross term. The unconditional moments include the in-control state (K, Λ) = (0, 1), whose expected loss is cσ2. Finally, μΛ = 1 indicates only the absence of systematic dispersion-scaling bias over the full horizon; it does not imply σ Λ 2 = 0 .
The four terms admit a direct interpretation, grouped by source. The first two concern centering: c σ 2 μ K 2 is the systematic centering error (off-target bias), and c σ 2 σ K 2 the centering instability (variability of the mean shift). The remaining two concern dispersion: c σ 2 σ Λ 2 is the dispersion instability (variability of the dispersion scaling), and c σ 2 μ Λ 2 the squared-mean dispersion-scale term. The dispersion-related contribution is c σ 2 E [ Λ 2 ] = c σ 2 ( σ Λ 2 + μ Λ 2 ) . Because the in-control state has Λ = 1, a perfectly centered in-control process incurs the baseline expected loss cσ2. Accordingly, c σ 2 μ Λ 2 should not be interpreted entirely as additional out-of-control dispersion loss. When μΛ = 1, this term equals cσ2. These components also indicate which type of improvement addresses each part of the loss. Recentering the process acts on the systematic centering error c σ 2 μ K 2 . Eliminating assignable causes or shortening out-of-control episodes acts on the out-of-control part of the loss, which includes the between-state term cσ2E[K2] and the excess of the dispersion term over its in-control value. Reducing common-cause variability acts on the within-state term cσ2E[Λ2], including the in-control baseline cσ2. Section 3.2 formalizes these mechanisms.
When FK,Λ is written as a mixture of the in-control state (K, Λ) = (0, 1), with probability 1 − p, and an out-of-control distribution, with probability p, Equation (1) splits into an in-control part (1 − p)cσ2, which reflects the inherent variability of the process, and an out-of-control part pcσ2E[K2 + Λ2|OOC], which reflects assignable causes. The first part can be reduced only by lowering σ, whereas the second can also be reduced by eliminating assignable causes or by shortening out-of-control episodes, so the split indicates which type of improvement addresses the larger part of the loss.
Evaluated as a single expectation, Equation (1) coincides with the classical Taguchi expected loss of the long-run marginal distribution of Y; the formulation does not produce a different loss value. What the state-resolved form adds is the separation of two sources of deviation from the target: between-state deviation, the displacement Kσ of the conditional mean, and within-state deviation, the conditional dispersion Λσ. Whether this separation matters for project evaluation depends on how a project acts on the two sources, which Section 3.2 examines. The four components additionally carry diagnostic information on which type of improvement addresses the dominant part of the loss.
Because c enters E[C(Y)] as a multiplicative scale factor, the score’s reproducibility and economic meaning remain conditional on the selected value of c. In practice, c can be estimated from quality-cost records, which can be traced systematically to their operational causes [28], in two ways. In the reference-point approach of Taguchi [12], c = A 0 / Δ 0 2 , where Δ0 is the deviation from target at which a unit fails in use (the functional or consumer tolerance), and A0 is the average loss, such as repair, replacement, or warranty cost, incurred at that deviation; in practice, the specification half-width and the corresponding scrap or rework cost are often used instead. In the average-cost approach c = L ¯ / MSD , where L ¯ is the failure cost attributed to the CTQ per unit produced in a reference period, and MSD = σ2(E[K2] + E[Λ2]) is the mean squared deviation from target in the same period, estimated from SPC data as described below. A large discrepancy between the two estimates indicates that the quadratic form describes the cost of deviations poorly. Where no cost records are available, c is treated as a scenario parameter or, as in Section 5.1, back-solved from a target expected loss per unit.
The quantities required by the evaluation can be estimated from routine SPC data at two levels of detail. Suppose that a rational subgroup of size ns is taken from each production block, so that the process state can be regarded as constant within a subgroup, and that σ is the in-control standard deviation from a Phase I study. At the first level, no identification of process states is needed. The within-subgroup variances estimate the within-state component, E ^ [ Λ 2 ] = s ¯ 2 / σ 2 , where s ¯ 2 is the average subgroup variance, and the squared deviations of the subgroup means from the target estimate the between-state component once their sampling error is removed, E ^ [ K 2 ] = 1 J ∑ j = 1 J ( x ¯ j − t ) 2 / σ 2 − E ^ [ Λ 2 ] / n s , where J is the number of subgroups. These expressions weight all subgroups equally, which is appropriate when the production blocks have equal volumes; otherwise, each subgroup term is weighted by the volume of its block, so that the estimates refer to the production-weighted loss. If σ is treated as known, the subgroup size is constant, and the observations within a subgroup are uncorrelated given its state, both estimators are unbiased over the data period and do not depend on when out-of-control episodes start or are detected; they provide everything that is required for scale-reduction projects and for projects described by (γ, δ) (Section 3.2). In finite samples, the corrected estimate of E[K2] can be negative; it should then be set to zero. The truncated estimator is no longer unbiased but has a small upward bias, and Appendix C shows how the sampling uncertainty of both estimates affects the selected portfolio. Without the correction term E ^ [ Λ 2 ] / n s , the sampling variation of the subgroup means would be attributed to shifts of the process, and the between-state component would be overestimated.
At the second level, which is needed only for the split of the loss into its in-control and out-of-control parts and for projects that eliminate assignable causes, production is allocated to process states. An X ¯ or S chart signal marks an out-of-control episode. Because a signal does not identify the onset of the episode, the onset is estimated by backdating with a cumulative sum (CUSUM) statistic, as the period after the CUSUM was last zero [14], and the end of the episode is taken from the logged corrective action. Signals for which no assignable cause is found are treated as false alarms and are not allocated. The share p of production in the out-of-control state and the conditional moments are then computed from the allocated production. Appendix C examines the accuracy of both levels and its effect on project evaluation by simulation.

3.2. Expected Quality Loss Under Process Improvement

Building on the modified Taguchi quality loss function derived in Section 3.1, we now examine how the expected quality loss responds to improvements in process quality. The formulation first treats improvements that reduce the process standard deviation while leaving the standardized state distributions unchanged (scale reduction) and then generalizes to projects that reduce the between-state and within-state deviations in different proportions. Two further mechanisms, recentering the process mean and eliminating assignable causes, change the systematic bias μK and the out-of-control share p, rather than scaling the deviations, and are treated separately (Table 2).
Table 2. Improvement mechanisms and the avoided loss per unit.
Throughout this paper, E[C(Y)] denotes the expected Taguchi quality loss per produced unit. The term “loss” is used in this specific technical sense and is distinct from realized accounting expenses, such as recorded scrap, rework, and warranty expenditures, and from a discrete defect count. Suppose a project is carried out on this quality characteristic that will reduce the process standard deviation σ by a certain percentage. Let Δ (0 < Δ < 1) denote the project’s improvement, treated throughout as a known point estimate rather than a random variable. In this case, the new quality loss for the quality characteristic following the project will be as follows:
E [ C ( Y ) ] imp = c σ 1 − Δ 2 σ K 2 + μ K 2 + σ Λ 2 + μ Λ 2
= c σ 2 σ K 2 + μ K 2 + σ Λ 2 + μ Λ 2 ( 1 − Δ ) 2
This equation can be rewritten as:
E [ C ( Y ) ] imp = E [ C Y ] ( 1 − Δ ) 2
which is the expected quality loss function after quality improvement, written here for a generic characteristic; its per-characteristic economic use, when multiple characteristics are combined, is developed in Section 4. Equation (2) assumes that an improvement reduces both absolute mean shifts and within-state dispersion by the same proportion. This may be appropriate for robust parameter design or equipment renewal when the same disturbances cause both effects. It is less appropriate when the mechanisms differ: improved fixturing may reduce dispersion without changing tool-wear drift, while more frequent tool changes may reduce drift without affecting within-state variation. Such projects require separate improvement parameters, as developed below. The applicability of Equation (2) should therefore be supported by a documented engineering mechanism or by pre- and post-project data.
More generally, a project may shrink the two sources of deviation in different proportions. Let γ denote the proportional reduction of the absolute mean shift Kσ and δ that of the within-state dispersion Λσ, with 0 ≤ γ, δ < 1, not both zero. Equivalently, the project reduces σ to (1 − δ)σ and the standardized shift becomes K(1 − γ)/(1 − δ), so Equation (1) applied to the post-project parameters yields Equation (2a). The expected loss per unit after the project, E[C(Y)]imp, and the avoided loss per unit, e = E[C(Y)] − E[C(Y)]imp are then
E [ C ( Y ) ] imp = c σ 2 1 − γ 2 E K 2 + 1 − δ 2 E [ Λ 2 ]
e = c σ 2 1 − 1 − γ 2 E K 2 + [ 1 − 1 − δ 2 ] E [ Λ 2 ]
Equation (2) is the special case γ = δ = Δ. Such a project shrinks both sources in the same proportion, so K and Λ enter only through the sum E[K2] + E[Λ2], which equals the marginal second moment divided by σ2; in that case, the aggregate loss suffices for project evaluation. When a project shrinks the two sources in different proportions, for example, when it tightens the within-state dispersion but leaves the magnitude of assignable-cause shifts unchanged, E[K2] and E[Λ2] enter Equation (2a) with different coefficients, and the avoided loss can no longer be obtained from the marginal second moment alone (Section 6.3). A dispersion-only project has γ = 0, and a shift-reduction project has δ = 0. Because the selection-and-sequencing model of Section 4 depends on each project only through its avoided loss e, every mechanism enters it unchanged. Table 2 lists the main improvement mechanisms and the avoided loss implied by each. Equation (2a,b) rest on four conditions. First, σ denotes the pre-project in-control standard deviation and serves as a fixed reference unit. Second, δ applies to the within-state dispersion of every state, including the in-control state, and γ applies to every shift, including any systematic bias μK. Third, the project does not change the probabilities of the process states; a change in these probabilities is the assignable-cause mechanism of Table 2. Fourth, like Δ, γ and δ are point estimates; they can be estimated from pre- and post-project data on between-state and within-state variation, for example, from the X ¯ and S charts described in Section 3.1 or derived from the engineering mechanism of the project.

4. Economic Translation and Optimal Sequencing of Quality Improvement Projects

In this section, we translate the expected reduction in quality loss into a practical economic metric: the net avoided-loss benefit (P). Section 4.1 defines this criterion for single projects and extends it to multiple consecutive projects. Section 4.2 then introduces an optimization model that jointly selects a budget-feasible subset of candidate projects and determines their optimal sequence.

4.1. Project Selection: Net Avoided-Loss Benefit for Single and Multiple Projects

This section develops the net avoided-loss benefit criterion in two settings. Section 4.1.1 treats a single project evaluated in isolation. Section 4.1.2 then considers several consecutive projects, each targeting a distinct quality characteristic.

4.1.1. Single-Project Selection

For each candidate project i targeting characteristic i, the model inputs are its baseline expected quality loss per unit, E[C(Y)]i; the constant production rate ρ (units per unit time); a common evaluation horizon H shared by all candidate projects; the project’s effect on the process, given by (γi, δi) or, for a scale-reduction project, by Δi, the implementation cost Ci, and the implementation duration di. We assume H ≥ di for every candidate project, so that each project’s implementation is completed within the evaluation horizon; any project with di > H falls outside this scope and is excluded from consideration. Because production continues during implementation and a project becomes effective only upon completion, the ρH units produced over the horizon split into two parts: Nold,i = ρdi units produced during implementation, which incur the baseline cost E[C(Y)]i, and Nnew,i = ρ(H − di) units produced after completion, which incur the improved cost E[C(Y)]imp,i of Equation (2a). Here P denotes the net avoided-loss benefit (the avoided quality loss minus implementation cost), rather than accounting profit. For a scale-reduction project, it is obtained as follows:
N old , i + N new , i = ρ H
P i = N old , i + N new , i E C Y i − N old , i E C Y i + N new , i E C Y imp , i − C i
= N new , i E C Y i − N new , i E C Y imp , i − C i
= N new , i E C Y i − N new , i E C Y i ( 1 − Δ i ) 2 − C i
= N new , i ( E C Y i − E C Y i 1 − Δ i 2 ) − C i
P i = N new , i E C Y i 2 Δ i − Δ i 2 − C i
Here, E C Y i 2 Δ i − Δ i 2 = E C Y i − E C Y imp , i is the avoided loss per unit ei of a scale-reduction project; for other mechanisms, ei is given by Equation (2b), and Equation (3) holds in the form Pi = Nnew,i ei − Ci.
Thus, Pi > 0 indicates that the project’s avoided quality loss exceeds its implementation cost. Because the number of benefit-bearing units, Nnew,i = ρ(H − di), decreases as duration increases, a longer implementation inherently lowers Pi, with all else being equal. However, when comparing different projects, a longer project can still yield a higher Pi if its avoided loss ei is large enough to offset the shorter horizon.

4.1.2. Cumulative Net Benefit of Sequential Improvement

In this case, production continues while the projects are implemented sequentially. Let i ∈ {1, …, n} index project identity, let m ∈ {1, …, n} index implementation position, and let π(m) denote the project assigned to position m. Thus, the implementation order is represented by the permutation π = (π(1), …, π(n)). The completion time of the project assigned to position m is
T m = ∑ k = 1 m d π ( k )
Let {1, …, n} index both the candidate projects and, through a one-to-one correspondence, the distinct quality characteristics they target, so that project i targets characteristic i. Its expected quality loss per unit is E[C(Y)]i, the baseline loss given by Equation (1). The product’s total expected quality loss is assumed to be economically separable across the quality characteristics.
Each failure-cost event (scrap, rework, warranty, or customer-compensation) is attributed in full to exactly one CTQ; a single event is not shared across multiple characteristics, consistent with the model’s scope in which each project targets a distinct, independent quality characteristic. Costs that cannot be reliably attributed to an individual CTQ are recorded in a separate shared-cost category and excluded from ∑ i E C Y i , so that no failure-cost event enters more than one CTQ loss calculation. Project implementation costs Ci are not included in the calibration data for ci and are subtracted only once in the economic objective. Statistical dependence between the CTQ states is permitted; the required condition is economic cost separability, not statistical independence. This separability holds when failure costs accrue through mechanisms that each CTQ can incur independently, for example, characteristic-specific rework, non-exclusive warranty claims, or customer compensation. It does not hold exactly for physical scrap: a unit scrapped for a deviation in one characteristic is removed from production and cannot generate a separate scrap cost for another characteristic, so the CTQ states share a common physical resource. In scrap-dominated processes, therefore, the sum of the per-characteristic expected losses should be read as an upper bound on the total avoidable loss rather than an exact decomposition. In that case, the avoided loss of a project is overstated and is no longer independent of the other projects: when two characteristics share a scrap event, improving one of them is worth more once the other has also been improved. The benefits er then become portfolio- and order-dependent, and both the selected portfolio and the implementation order can differ from those of the additive model (Appendix B). The present framework is therefore restricted to settings in which failure costs can be attributed to individual CTQs, as described at the beginning of this paragraph.
For each characteristic i, let s ∈ {pre, post} denote its condition before and after the corresponding project. The expected quality loss per unit in condition s is
L i s = c i σ i s 2 σ K , i s 2 + μ K , i s 2 + σ Λ , i s 2 + μ Λ , i s 2 ,   s ∈ pre ,   post .
obtained by evaluating Equation (1) at the process parameters of condition s; in particular, the pre-project loss coincides with the baseline, L i pre = E C Y i .
The avoided expected loss per unit generated by project i is
e i = L i pre − L i post .
In the scale-reduction special case, the project changes only the baseline process standard deviation, such that
σ i post = 1 − Δ i σ i pre ,
while the moments of Ki and Λi remain unchanged. Consequently,
L i post = L i pre 1 − Δ i 2 ,
which yields Equation (2); the avoided loss is then reduced to the closed form e i = E C Y i [ 1 − ( 1 − Δ i ) 2 ] . For other mechanisms, L i post follows from Equation (2a).
Building up from the smallest cases, the net avoided-loss benefit for one and two sequentially implemented projects is
n = 1 : P = ρ e π ( 1 ) ( H − T 1 ) − C π ( 1 ) , T 1 = d π ( 1 )
n = 2 : P = ρ [ e π ( 1 ) ( H − T 1 ) + e π ( 2 ) ( H − T 2 ) ] − C π ( 1 ) − C π ( 2 ) , T 1 = d π ( 1 ) , T 2 = d π ( 1 ) + d π ( 2 )
In the single-project case, only the units produced after completion benefit from the reduction; in the two-project case, units produced after the first completion benefit from the first project, and those after the second completion from both. Generalizing this additive pattern to n projects, in which each project’s contribution ei(H − Ti) is summed rather than multiplied, the following equation is reached:
P = ρ ∑ m = 1 n e π m ( H − T m ) − ∑ m = 1 n C π m
Each term eπ(m)(H − Tm) represents the avoided-loss contribution of characteristic π(m) over the units produced from the moment project π(m) completes until the end of the evaluation horizon. This additive structure holds because each project targets a distinct quality characteristic; two projects acting on the same characteristic would combine multiplicatively (as in Equation (2)) rather than additively. The last project’s contribution, eπ(n)(H − Tn), already captures the units produced after all projects are complete. Changing the implementation order changes which eπ(m) is weighted by which (H − Tm) and hence changes the value of P. This expression assumes Tn ≤ H, so that every project is completed within the evaluation horizon; if the total duration exceeds H, each (H − Tm) term is replaced by max{H − Tm,0}.

4.2. Optimal Sequencing Model

The selection and sequencing decisions are deterministic: they are optimized on the expected avoided losses er, and the randomness of the model is confined to the process states that determine these expectations. This subsection formulates a joint selection-and-sequencing model for a set of candidate quality-improvement projects under a budget constraint. The closed-form ordering rule established later in this subsection solves the sequencing sub-problem optimally for any given selected set; it does not by itself determine which subset to select under the budget constraint. For a small number of candidates, as in the numerical illustration of Section 5, the joint problem can be solved by enumerating feasible subsets and applying the closed-form ordering rule within each. Because the number of feasible subsets grows exponentially with the number of candidates in the worst case, the complete equivalent mixed-integer linear programming (MILP) formulation presented below is provided as a general exact formulation.
The model is based on the following assumptions:
  • Each project r acts on characteristic r through proportional reductions γr of the between-state deviations and δr of the within-state deviations (Section 3.2), which are constant regardless of implementation position; for a scale-reduction project γr = δr = Δr.
  • Production occurs at a constant rate ρ. Each project r has its own implementation duration dr.
  • Only one project is implemented at a time, with no idle time between consecutive projects.
  • Each project becomes effective only upon completion, and its effect remains active during all subsequent periods.
  • Project effects are non-interacting: no two selected projects target the same quality characteristic.
  • Project implementation costs are fixed and independent of implementation order.
  • The baseline expected quality loss per unit, E[C(Y)]r, remains constant for each characteristic throughout the evaluation horizon.
  • For simplicity, the time value of money is not modeled; the discount rate is taken as zero.
This is especially reasonable for the short evaluation horizons typical of quality-improvement projects. With a positive discount rate, however, the present value of each project’s benefit depends nonlinearly on its completion time, which is itself a decision variable, so the MILP of Equations (5)–(18) cannot be retained by discounting its objective coefficients, and the er/dr rule need not remain optimal. An exact linear treatment is possible with a time-indexed formulation over the discrete time grid on which the durations are defined; a piecewise-linear approximation of the discount factor is an alternative but is generally inexact.
Assumption 3 describes organizations in which the candidate projects compete for a single improvement team or for the same equipment, metrology, or maintenance resources, as in the application of Section 5, where four production lines share one improvement team. Idle time is never optimal in this model, since delaying a project only shortens its benefit period, unless projects have release dates. Assumption 4 fits improvements that take effect once they are validated, such as a new fixture or revised process settings; when part of the benefit is realized during implementation, the model understates it, and the project can be represented by successive stages. With several improvement teams, each team is a single machine, so the er/dr rule still orders the projects within each team [41], but assigning projects to teams yields a parallel-machine scheduling problem with rejection [35], which is NP-hard even without selection and with only two teams (see [41] and the references therein); the MILP of Equations (5)–(18) extends to it through team-assignment variables. Partially shared resources lead to a resource-constrained project scheduling problem.
Under these assumptions, the following complete MILP jointly determines which projects are selected and the implementation positions assigned to them. Both the MILP and the closed-form ordering rule depend only on the numerical values of the benefits er, not on how each er is obtained: scale-reduction projects supply er through the closed form e r = E [ C ( Y ) ] r 1 − ( 1 − Δ r ) 2 , while any project with an externally estimated er > 0 enters the same formulation unchanged.
  • Indices:
k , m = 1 , … , n :   implementation   position
r , s = 1 , … , n :   project   identity .
Decision variables:
I mr = 1 , if   project   r   is   implemented   in   position   m , 0 , otherwise .
x r = 1 , if   project   r   is   selected , 0 , otherwise .   r = 1 , … , n
Tm is the completion time of the project in position m. ymr = ImrTm. Both variables are introduced formally where the linearization is presented.
  • Parameters and other values:
  • H: Common evaluation horizon shared by all n projects. H > 0.
  • ρ: Constant production rate (units per unit time). ρ > 0.
  • dr: Implementation duration of project r. dr > 0.
  • Cr: Implementation cost of project r. Cr ≥ 0.
  • B: Total available budget for project implementation. B ≥ 0.
  • γr, δr: Proportional reductions of the between-state and within-state deviations achieved by project r, 0 ≤ γr, δr < 1, not both zero; γr = δr = Δr for scale-reduction projects.
  • E[C(Y)]r: Baseline expected quality loss per unit.
  • er: Avoided-loss benefit per unit contributed by project r once completed, e r = L r pre − L r post , given by Equation (2b); for scale-reduction projects this reduces to e r = E [ C ( Y ) ] r 1 − ( 1 − Δ r ) 2 . Only projects with er > 0 are eligible improvement candidates.
  • P: Total net avoided-loss benefit of the implementation sequence.
All n projects share a single evaluation horizon H, starting at time zero with the beginning of the first project’s implementation. Although implementation order is a decision variable, the calendar duration until all selected projects are completed, ∑ r d r x r , is order-independent, and the horizon must satisfy ∑ r = 1 n d r x r ≤ H .
  • Mathematical model:
Using the completion-time variable Tm and the auxiliary variable ymr = ImrTm, the complete equivalent MILP is formulated as follows:
max I , x , T , y P = ρ ∑ m = 1 n ∑ r = 1 n e r H   I mr − y mr − ∑ r = 1 n C r x r .
subject to
∑ r = 1 n I mr ≤ 1 ,   m = 1 , … , n ,
∑ m = 1 n I mr = x r ,   r = 1 , … , n ,
∑ r = 1 n I m + 1 , r ≤ ∑ r = 1 n I mr ,   m = 1 , … , n − 1 ,
∑ r = 1 n C r x r ≤ B ,  
∑ r = 1 n d r x r ≤ H ,
T m   =   ∑ k = 1 m ∑ s = 1 n I ks d s ,   m = 1 , … , n ,
0 ≤ T m ≤ H ,   m = 1 , … , n ,
y mr ≤ H I mr ,   m , r = 1 , … , n ,
y mr ≤ T m ,   m , r = 1 , … , n
y mr ≥ T m − H 1 − I mr ,   m , r = 1 , … , n
y mr ≥ 0 ,   m , r = 1 , … , n
I mr ∈ 0 , 1 ,   m , r = 1 , … , n ,
x r ∈ 0 , 1 ,   r = 1 , … , n ,
Here, Tm is the completion time associated with implementation position m, and ymr is the exact linearization of ImrTm [42]. Because Imr is binary and 0 ≤ Tm ≤ H, constraints (13)–(16) enforce ymr = ImrTm. Therefore, the formulation in Equations (5)–(18) is a complete MILP.
The joint selection-and-sequencing problem is NP-hard. To see this, consider an arbitrary instance of the 0–1 knapsack problem with integer values vr > 0, integer weights qr > 0, r = 1, …, n, and integer capacity Q. The knapsack problem is NP-hard, and project portfolio selection and order acceptance without scheduling are known to take this form [37,39]. Construct an instance of the present problem with ρ = 1, H = 1, B = Q, Cr = qr, er = vr + qr and equal durations dr = η = 1/(2nM), where M = ∑ r ( v r + q r ) . These avoided losses are attainable within the model: for example, a scale-reduction project with Δr = 1/2 and baseline loss E[C(Y)]r = 4(vr + qr)/3 has e r = E [ C Y ] r 1 − 1 − Δ r 2 = v r + q r . Every subset S then satisfies the horizon constraint since ∑ r ∈ S d r ≤ n η < H , and its net benefit under any order is P = ∑ r ∈ S v r − ε , where ε = ∑ m e π ( m ) T m satisfies 0 ≤ ε ≤ nηM = 1/2. Because the knapsack values are integers, a subset whose total value is smaller by at least one cannot attain a larger net benefit; hence a subset that maximizes P also maximizes ∑ r ∈ S v r subject to ∑ r ∈ S q r ≤ Q . The construction is polynomial in the size of the knapsack instance, so the joint problem is NP-hard, and no polynomial-time algorithm for it is expected unless P = NP. The interchange argument below is unaffected: for any fixed selected set, the optimal order remains the er/dr rule.
Constraint (6) ensures that at most one project occupies each implementation position since not every position needs to be filled once selection is introduced. Constraint (7) links assignment to selection. Constraint (8) fills the positions without gaps. Constraints (9) and (10) enforce the budget and horizon limits, while Constraints (11)–(16) define completion times and linearize the interaction between project assignments and completion times. The remaining constraints specify the variable domains. Implementation costs depend only on the selected portfolio, whereas avoided-loss benefits also depend on project completion times.
The project-cost term depends only on which projects are selected, through xr, and not on their assigned positions, so it is independent of sequencing order. Sequence differences arise instead from the intermediate production periods, during which only the selected projects completed in earlier positions are active.
The optimal order can be characterized directly, without enumeration. Swapping two adjacent projects i and j leaves every other period unchanged since the total duration occupied by these two positions is the same regardless of their order; only the benefit obtained during these two periods differs. Under order (i, j), project i’s benefit ei accumulates over the remaining horizon from its own completion onward, which includes project j’s duration dj in addition to everything after; project j’s benefit ej accumulates only from its own, later completion onward. The difference in total benefit between order (i, j) and order (j, i) is reduced to ρ(eidj − ejdi). Project i should therefore precede j whenever eidj ≥ ejdi, that is, whenever ei/di ≥ ej/dj. Applying this pairwise criterion throughout, the net avoided-loss benefit is maximized by implementing projects in decreasing order of the ratio er/dr. For scale-reduction projects, the ratio is
e r d r = E [ C ( Y ) ] r 1 − ( 1 − Δ r ) 2 d r
For a fixed selected set, ρ H   ∑ r e r and ∑ r C r in Equation (5) are constant, so maximizing P is equivalent to minimizing the weighted completion-time sum ∑ m e π ( m ) T m , where Tm denotes the completion time of the project in position m, with per-project weight er and duration dr. This is the classical single-machine weighted completion-time problem (in the standard scheduling notation 1   | |   ∑ w j C j , with weight wj, processing time pj, and completion time Cj corresponding here to er, dr, and Tm, respectively), whose optimum is the WSPT rule applied to the quality-loss weights: sequence in non-increasing order of er/dr. The interchange argument above is therefore a self-contained specialization of the WSPT rule to the quality-loss weights er.
The ratio balances improvement magnitude against implementation delay: a project is scheduled earlier when it removes more expected loss and when it occupies the line for less time. As a consistency check, consider the special case of scale-reduction projects that share the same baseline loss E[C(Y)]r and equal durations dr = d. The ratio then is reduced to E [ C ( Y ) ] [ 1 − ( 1 − Δ r ) 2 ] / d , which is increasing in Δr. The rule therefore coincides with the largest-improvement-first ordering in this equal-baseline-loss and equal-duration special case. In general, however, durations differ, and the full ratio er/dr governs the optimal order. If two projects have equal ratios, ei/di = ej/dj, relative order between them yields the same net avoided-loss benefit, so the optimal sequence is not unique in that case.

5. Numerical Illustration

5.1. Scenario Definition

A manufacturing firm operates four production lines, each with a critical-to-quality (CTQ) characteristic of the nominal-the-best (NTB) type. The profile below is shared by all four CTQs evaluated in this section. The target value of the characteristic is t = 10 mm, the specification limits are LSL = 9.94 mm and USL = 10.06 mm, and the standard deviation while the process is in control is σ = 0.02 mm. Accordingly, the sigma level is:
u = ( USL − t ) / σ = 0.06 / 0.02 = 3 ,   an   initial   3 − sigma   state
The long-run (unconditional) moments of the process-state variables, which include both in-control and out-of-control production (Section 3.1), are derived from an explicit mixture for illustration. The process is out of control for a fraction p = 0.2 of production; in the in-control state (K, Λ) = (0, 1), and in the out-of-control state, the mean shifts by K = ±2 with equal probability while the dispersion is inflated to Λ = 1.5. This gives μK = 0, σ K 2 = 0.80 , μΛ = 1.10, and σ Λ 2 = 0.04 , so E[K2] + E[Λ2] = 2.05. The mean-shift bias μK = 0 represents a well-calibrated process in which out-of-control excursions are not systematically biased in one direction. The quality cost proportionality constant c is then back-solved using Equation (1) assuming E[C(Y)] = $10/unit as follows:
E [ C ( Y ) ] = c · σ 2 · ( σ K 2 + μ K 2 + σ Λ 2 + μ Λ 2 )
= 12,195.12 × 0.0004 × ( 0.8 + 0 + 0.04 + 1.21 ) = $ 10.00 / unit
In terms of the reference-point calibration of Section 3.1, this value corresponds to a cost of A 0 = c Δ 0 2 = 12,195.12 × 0.06 2 ≈ $ 43.90 for a unit at the specification limit, and it is equivalent to an observed failure cost of $10 per unit for a process with the mean squared deviation of the scenario (0.0004 × 2.05 = 0.00082 mm2). Equation (1) is decomposed into four additive components for this baseline. The systematic centering-error term c σ 2 μ K 2 equals $0.00 since μK = 0. The centering-instability term c σ 2 σ K 2 equals $3.90. The dispersion-instability term c σ 2 σ Λ 2 equals $0.20. The squared-mean dispersion-scale term c σ 2 μ Λ 2 equals $5.90. These components sum to the expected quality loss of $10.00 per unit. Split into the two parts of Section 3.1, the same loss consists of $3.90 per unit in the in-control state and $6.10 per unit from out-of-control episodes. The reference production volume over the evaluated production horizon is N = 200,000 units, so the expected quality loss cost for a single such characteristic over this horizon is:
N × E [ C ( Y ) ] = 200,000 × $ 10 = $ 2,000,000
To raise this initial 3-sigma level, the firm evaluates four candidate Six Sigma improvement projects on four production lines that share a single improvement team, so that only one project can be implemented at a time. Each candidate project targets one CTQ and is represented by a proportional reduction Δi in its baseline process standard deviation. The four CTQs are assigned a common process profile and production rate by design, so that differences among projects arise only from their improvement effects, implementation costs, and durations; neither assumption is required by the model since line-specific rates enter Equations (4) and (5) by replacing ρer with ρrer, in which case, the ordering rule of Section 4.2 uses the ratio ρrer/dr, and line-specific baseline losses enter through E[C(Y)]r. All four projects are scale-reduction projects (γ = δ = Δ), so the decisions in this section depend on the process-state parameters only through the baseline loss of each CTQ and could be reproduced from the aggregate loss alone. Section 6.3 relaxes both features: it assigns CTQ-specific parameters and different improvement mechanisms and shows when the state-resolved evaluation changes the decision.
Project A: Rubber weather strip production line. A small-scale DMAIC project is designed for the weather strip line. It is expected to raise this CTQ’s sigma level from 3-sigma to approximately 3.69-sigma, a proportional improvement of ΔA = 0.186.
Project B: Bead-splice process. An equipment/calibration-focused intervention is planned on the bead-splice line. It is projected to achieve a proportional σ reduction of ΔB = 0.221 (reported by its source as a reduction of the standard deviation rather than a sigma-level shift).
Project C: Bore-taper variance-reduction project. This project reduces bore-taper variation through a broad variance-reduction initiative that lowers the sensitivity of the process to all noise factors. It is projected to raise this CTQ’s sigma level from 3-sigma to approximately 5.89-sigma, a proportional improvement of ΔC = 0.490.
Project D: Bush-diameter production. A major intervention targeting bush-diameter variation is proposed. It is projected to raise this CTQ’s sigma level from 3-sigma to a target of 5.45-sigma, a scenario calibration point (Table 3), corresponding to a proportional improvement of ΔD = 0.450. Project D is assumed to require large-scale equipment renewal and automation, and its investment cost is therefore set higher than those of the other projects; its scope and cost are scenario assumptions rather than values taken from [43].
Table 3. Baseline process, economic, and scheduling parameters used in the numerical illustration.
To parameterize the expected proportional improvements, effect sizes were calibrated from the changes documented in four published Six Sigma case studies (Table 3). Because the sources report different measures, each value was converted according to its own definition. Two sources [44,46] report sigma levels computed from defect rates with the conventional 1.5σ long-term shift; Ref. [44] states this convention explicitly but does not report the number of defect opportunities needed to reproduce its sigma levels from the rejection rates, so its values are used as reported, while the values reported in [46] are reproduced exactly from its rejection rates under the same convention. For these, the shift is removed before the ratio is formed, Δ = 1 − (uold − 1.5)/(unew − 1.5), which follows from u = (USL − t)/σ under a fixed specification width. Sigma levels derived from defect rates also reflect changes in centering, so attributing the whole change to σ is an approximation. For source [45], the reported reduction of the standard deviation (2.17 → 1.69) is used as a conservative scenario value, Δ = 1 − (σnew/σold); the capability indices reported in the same source imply a larger improvement (Cp 1.65 → 2.95, Δ = 0.441), and this value is examined in Section 6.1. Source [43] starts from a far more out-of-control state (Z.Bench 1.40) than the 3-sigma baseline, so its improvement ratio is not transferred directly; Project D is instead calibrated to a target level of 5.45-sigma, a scenario choice just below the 6-sigma level that defines the Six Sigma standard [8,14], which gives ΔD = 1 − 3/5.45 ≈ 0.450. These values calibrate plausible improvement magnitudes for the illustrative scenario and should not be interpreted as directly transferable performance estimates for the hypothetical firm.
Investment costs (C), which are not reported in the sources at a scale transferable to the target firm, are instead treated as illustrative scenario assumptions rather than as observed accounting costs. The numerical application presented in this section is therefore an illustrative composite scenario grounded in four real case studies. It is not based on a single real firm’s data and is chosen to reflect realistic orders of magnitude rather than to empirically validate the proposed model. Table 3 consolidates the baseline process, economic, and scheduling parameters used in the analysis and indicates whether each value is assumed, derived, or obtained from the literature.

5.2. Project Selection

5.2.1. Single-Project Evaluation

The avoided loss of each project follows from Equation (2) as ei = E[C(Y)]i[1 − (1 − Δi)2], and its net avoided-loss benefit Pi from Equation (3); the return on investment, ROIi = Pi/Ci × 100%, expresses this benefit relative to implementation cost. Table 4 reports the results.
Table 4. Single-project net avoided-loss benefit (P) evaluation of candidate projects.
Table 4 shows that the magnitude of the process improvement alone does not determine project attractiveness. Project C has the largest proportional reduction in standard deviation (ΔC = 0.490) and also the largest net avoided-loss benefit because it combines a large improvement with the shortest implementation duration. Project D has the second-largest improvement (ΔD = 0.450), but once its high implementation cost and five-month duration are accounted for, it yields the lowest net benefit and return of the four candidates. Project A, with the smallest improvement (ΔA = 0.186), ranks second because of its low cost. Ranking the projects by Δ (C > D > B > A) therefore produces a different ordering than ranking them by net avoided-loss benefit (C > A > B > D).
Of the four sources, only [44] reports an implementation cost, and that value is not directly transferable to the present scenario; Refs. [45,46] report no implementation cost, while [43] reports only the annual savings. Because Project D has the highest assumed investment cost, a sensitivity analysis is conducted to examine how strongly this assumption affects its ranking.
Even at zero investment cost, Project D would not reach the net benefit of Project C ($813,161 versus $957,849) because its five-month duration shortens its benefit-bearing period. It would match Project B at a cost of $438,537 and Project A at $345,979, and it would enter the optimal portfolio, in place of Project B, only if its cost fell below $282,681, about 60% below the $700,000 assumed in the base case. Its exclusion is therefore robust to substantial uncertainty in the CD estimate and is driven jointly by its cost and its long implementation duration.
The ranking in Table 4 is robust to independent errors in the improvement estimates. When each Δi is changed independently by ±10%, the ranking C > A > B > D is preserved in every combination; at ±20%, only Projects A and B can exchange positions, which requires ΔA to fall and ΔB to rise by at least 10.1% each (Appendix A, Table A1). Section 6.1 examines the stability of the portfolio and of the sequence more broadly.

5.2.2. Multiple Projects: Cumulative Net Benefit of Sequential Improvement

The single-project values in Table 4 evaluate each project independently over the full 12-month horizon. When several projects are implemented sequentially using a common implementation resource, however, these standalone net benefits cannot simply be added. A project’s benefit begins only after its implementation is completed; consequently, projects scheduled later have shorter benefit-bearing periods. Equation (4) captures this timing effect.
To illustrate this effect before optimization, consider Projects A, B, and C implemented in the arbitrary sequence A → B → C, with completion times of 3, 7, and 8.4 months. By Equation (4), this sequence yields $739,247 (Table 5), less than the sum of the three standalone net benefits in Table 4: Project C, which requires only 1.4 months, does not begin generating savings until month 8.4. Section 5.3 determines the implementation order and project subset that maximize cumulative net avoided-loss benefit.
Table 5. Effect of project sequence on cumulative net benefit.

5.3. Project Scheduling Optimization

In this section, we determine the preferred implementation sequence and then the optimal project subset and its implementation sequence. Because only four candidate projects are considered, all feasible subsets are evaluated directly, each sequenced by the er/dr rule and evaluated with Equation (4).

5.3.1. Sequencing a Fixed Project Set

To isolate the effect of implementation order, consider first the fixed project set {A, B, C}. The candidate projects target distinct, economically separable CTQs and are assumed to have non-interacting effects. The optimization uses the production rate ρ, evaluation horizon H, project durations di and budget B summarized in Table 3, and the implementation costs Ci in Table 4. All six possible sequences are evaluated using the project-specific durations and avoided-loss values reported previously. Table 5 presents the resulting cumulative net avoided-loss benefits.
The sequence C → A → B produces the largest cumulative net avoided-loss benefit, $1,432,217, whereas the illustrative sequence A → B → C used in Section 5.2.2 yields $739,247 and the least favorable sequence, B → A → C, yields $710,567. Thus, changing only the implementation order increases the net benefit by $692,970 relative to the illustrative sequence and by $721,650 (about 102%) relative to the least favorable one. This best-versus-worst comparison of the six possible sequences is illustrative and does not represent the gain to be expected in practice. The optimal order is consistent with the WSPT rule derived in Section 4.2: the avoided-loss-to-duration ratios are approximately
e C d C = 5.29 ,   e A d A = 1.13 , e B d B = 0.98 ,
which directly gives the sequence C → A → B.
In practice, projects are often prioritized by a single criterion. Simple rules that rank the projects by largest improvement, lowest cost, shortest duration, highest return on investment, or highest standalone net benefit and add a project if it fits the budget and horizon and recovers its cost reach 51.6% to 100% of the optimal net benefit in this instance; the entire shortfall arises from the implementation order since every rule attains the optimum when its projects are implemented in decreasing order of er/dr. Section 6.5 compares the rules with the optimum on randomly generated instances.

5.3.2. Joint Project Selection and Sequencing

The analysis is next extended to all four candidate projects. Selecting all four projects is infeasible because their combined implementation duration is
3 + 4 + 1.4 + 5 = 13.4   months ,
which exceeds the 12-month evaluation horizon. Their combined implementation cost of $1,240,000 also exceeds the available budget of $1,150,000.
Each remaining feasible subset is therefore evaluated using Equation (4), with the projects within each subset sequenced according to the decreasing ei/di rule. The optimal solution selects Projects A, B, and C and implements them in the order
C → A → B .
The selected portfolio requires an investment of $540,000 and yields a cumulative net avoided-loss benefit of $1,432,217. The next-highest feasible alternative, identified by the same enumeration, is the two-project portfolio {A, C}, sequenced C → A, with a net benefit of $1,346,136.
Project D is not selected despite having the second-largest improvement and the second-highest avoided-loss-to-duration ratio, eD/dD ≈ 1.39; the best feasible portfolio containing it, C → D → A, yields $1,014,898. This illustrates the distinction between sequencing and selection: the ratio ei/di determines the optimal order within a selected set, but portfolio selection also depends on the implementation cost, duration, available budget, and evaluation horizon.
Note that the numerical application is intended to illustrate the proposed decision framework rather than to provide an empirical validation for a specific manufacturing system. Such a validation requires integrated records, namely SPC data, quality-cost records attributed to individual CTQs, and the planned and realized costs and durations of several projects in the same plant, which are rarely available together and could not be obtained for this study. Section 6 therefore examines whether the conclusions hold beyond this scenario: on CTQs with heterogeneous process profiles and improvement mechanisms (Section 6.3), on simulated process data from which the process-state moments are estimated (Appendix C), and on randomly generated instances that vary the number of candidate projects, the budget, the horizon, and the baseline losses (Section 6.5).
The assumed budget of $1,150,000 is not binding at the optimal solution, whose total implementation cost is $540,000. Table 6 therefore reports how the optimal portfolio changes under different budget limits, together with the reason each remaining project is excluded. Below $540,000 the budget restricts the portfolio without necessarily being binding at the optimum in the strict sense: at $500,000, Project B is excluded for budgetary reasons, and C→A is optimal, although it uses only $390,000, and at $350,000, the model prefers Project C alone ($957,849) to the two cheaper Projects A and B ($645,072). Project D is never selected within the twelve-month horizon at any budget: every feasible portfolio that contains it yields a lower net benefit, so it is excluded because of its net benefit within the horizon rather than because of the budget. For the four-project instance, these budget-constrained cases are solved by exhaustive enumeration and by the MILP of Equations (5)–(18), which give identical results; for larger candidate sets, the MILP is solved with an exact solver (Section 6.4).
Table 6. Portfolio changes under different budget limits and reasons for excluding projects (H = 12 months).

6. Results

Section 6 complements the numerical illustration of Section 5. It examines the robustness of the selection and sequencing results (Section 6.1), compares them with an illustrative benchmark based on the conventional 1.5σ shift (Section 6.2), shows when the state-resolved evaluation changes the decision (Section 6.3), verifies the MILP and reports its computational behavior on randomly generated instances (Section 6.4), and compares the optimum with simple prioritization rules in a computational study (Section 6.5).

6.1. Robustness of the Selection and Sequencing Results

The results of Section 5.2 and Section 5.3 involve two different forms of stability. Sequencing stability concerns the order of a given set of projects. Because the order follows the er/dr rule, it is invariant to any change that multiplies all avoided losses by a common factor, such as a change in the loss coefficient c, in the common baseline loss or in the process-state moments. Selection stability concerns which projects are chosen, and it does not hold in general because implementation costs do not scale with avoided losses. In the illustration, the order of {A, B, C} remains C → A → B for every baseline loss, but the portfolio changes: below a baseline loss of $6.36 per unit (c = 7756), Project B is dropped and C → A becomes optimal (for example, $478,068 at $5 per unit), and below $2.85 per unit, only Project A remains worthwhile. Similarly, extending the horizon does not change the order of {A, B, C}, but beyond 20.3 months, Project D enters the portfolio and Project B leaves it (C → D → A at 24 and 36 months), whereas at 6 months, only C → A is selected; the 12-month horizon therefore penalizes Project D’s high investment and long duration.
Independent changes of the inputs confirm this distinction (Supplementary Tables S5 and S6). Changed one at a time, no single parameter alters the portfolio unless it moves far from its base value; the nearest thresholds are a 33% longer duration, a 39% smaller improvement, or a 57% higher cost of Project B, each of which removes B from the portfolio, while Project D enters only if its cost falls by 60% or its duration by 48%. In a Monte Carlo analysis in which the improvement, duration, and cost of every project vary independently by up to ±20%, the portfolio {A, B, C} remains optimal in 96.5% of 5000 draws, whereas the order C → A → B remains optimal in 68.7%; the alternative is almost always C → B → A, because Projects A and B have similar avoided-loss-to-duration ratios (1.13 and 0.98). Implementing the base-case decision in every draw would lose 0.6% of the attainable net benefit on average. If the improvement of Project B were taken from the capability indices of its source (ΔB = 0.441 instead of 0.221; Section 5.1), the portfolio {A, B, C} would remain optimal, and Project D would still be excluded, but B would move ahead of A (C → B → A, $1,726,597) because its avoided-loss-to-duration ratio would rise from 0.98 to 1.72. At the budget levels of Table 6, B → A would then be optimal at $200,000 to $350,000, and C → B at $500,000. If the 1.5σ shift were not removed when converting the source sigma levels (Section 5.1), the optimal solution would be C → B → A with $999,730. Three properties hold in general: the er/dr order within a selected set; its invariance to a common multiplicative change in all er; and the agreement between the aggregate and state-resolved evaluations whenever all projects are scale-reduction projects. The selected portfolio, the project ranking and the thresholds reported in Section 5 and Section 6 are specific to the scenario.

6.2. Sensitivity to the Conventional 1.5σ Shift

To place the proposed evaluation in context, the single-project results are compared with an illustrative benchmark based on the conventional long-term 1.5σ mean shift assumed in Six Sigma practice, applied here as a fixed shift with no dispersion uncertainty. For this, Equation (1) is evaluated at μ K = 1.5 , σ K 2 = 0 , μ Λ = 1 , σ Λ 2 = 0 , rather than at the proposed model’s parameters (Section 5.1).
E C Y = c σ 2 0 + 1.5 2 + 0 + 1 2 = 12 , 195.12 × 0.0004 × 3.25 = $ 15.85 / unit
This benchmark value of $15.85/unit exceeds the proposed model’s $10.00/unit. As Section 3.1 shows, the expected loss depends on the state variables only through E[K2] + E[Λ2], so the difference between the two figures reflects their different second-moment inputs (3.25 versus 2.05 here), not the presence or absence of uncertainty as such: the fixed 1.5σ shift contributes a larger squared-bias term (1.52) than the shift variance assumed under the proposed model ( σ K 2 ) , even though the benchmark omits the dispersion-variance term. Table 7 summarizes the resulting net avoided-loss benefits and project rankings under the proposed stochastic process-state formulation and the deterministic fixed-shift benchmark.
Table 7. Project ranking under the proposed (state-distribution) model versus the fixed-shift benchmark.
Both formulations rank the projects C > A > B > D and select the same portfolio, C → A → B. The higher benchmark loss multiplies every project’s avoided loss by the same factor (15.85/10), which raises the estimated benefits but, in this scenario, changes neither the ranking nor the selection. It does change how close the decision is to switching: under the benchmark, Project D would enter the optimal portfolio if its cost fell below $360,347 rather than $282,681, or if the horizon were extended to 16.3 rather than 20.3 months. Section 6.3 shows, in contrast, that when the components of the loss are distributed differently and projects act through different mechanisms, the decomposition can change the decision itself.
Because both representations enter the loss only through second moments, the effect of the representation itself can be isolated by equalizing these moments. A fixed shift μ K = 1.05 ≈ 1.0247 with Λ = 1 has the same total second moment (2.05) as the mixture of Section 5.1. With scale-reduction projects and the exact value 1.05 , which is used in all calculations, it reproduces Table 4 and Table 5 exactly, so the difference in Table 7 is due entirely to the larger second moment of the conventional 1.5σ shift. The two representations differ only in how the second moment divides between the between-state and within-state components (a between-state share of 0.39 under the mixture and 0.51 under the fixed shift), which matters only for projects that do not act proportionally on both: if all four projects reduced only the within-state dispersion, both would select C → A, but with net benefits of $668,620 and $456,896, respectively.

6.3. Value of the State-Resolved Evaluation

To quantify the effect of the scale-reduction assumption itself, the base case of Section 5 is re-evaluated under the alternative in which every project reduces only the within-state dispersion and leaves the absolute mean shifts unchanged (γ = 0, δ = Δ). Because the within-state component accounts for 61% of the baseline loss (Section 5.1), every avoided loss falls by 39% and, with unchanged costs, the net benefits of Projects A–C fall by 42% to 55%, while that of Project D becomes negative. The optimal portfolio becomes C → A, with a net benefit of $668,620 instead of $1,432,217. The assumption thus mainly affects the size of the estimated benefits; the example below shows a case in which the mechanism also changes the selected portfolio.
To examine when the state-resolved representation changes decisions, the four projects of Section 5 are applied to four CTQs with independently specified process parameters (Table 8). Implementation costs, durations, and improvement magnitudes are those of Section 5; the projects are labeled A′ − D′ to distinguish them from the base case. Each CTQ is described by an explicit mixture as in Section 5.1, with its own σ, c, out-of-control share p, shift magnitude ±a, and dispersion scale λ. CTQ A′ keeps the profile of Section 5.1; CTQ B′ experiences frequent, large shifts, for example, from changes of material batches; CTQ C′ has rare out-of-control episodes with strong dispersion inflation; and CTQ D′ has large shifts from tool wear. Projects A′ and C′ are scale-reduction projects. Project B′ improves setting and measurement procedures and reduces only the within-state dispersion (γ = 0, δ = 0.221). Project D′ shortens the tool-change interval and reduces only the shifts (γ = 0.450, δ = 0); both mechanisms are scenario assumptions.
Table 8. Heterogeneous example: process profiles of the CTQs, improvement mechanisms of the projects and avoided losses under the two evaluations.
Two evaluations are compared. The aggregate evaluation uses only the total expected loss of each CTQ, which can be obtained from the marginal second moment, and therefore applies Equation (2) to every project. The state-resolved evaluation uses Equation (2b). When all four projects are scale-reduction projects, the two evaluations coincide for any CTQ-specific parameters; here both select C′ → A′ → B′ with a net benefit of $1,014,103. With the mechanisms above, the aggregate evaluation overstates the avoided loss of B′ by 166% ($4.44 versus $1.67 per unit) and that of D′ by 52% ($11.64 versus $7.65) because each project acts on only one component of the loss. It selects C′ → A′ → B′, for which it reports $1,014,103 but which realizes $848,109. The state-resolved evaluation drops B′, which is completed in month 8.4 and cannot recover its cost in the remaining 3.6 months, and selects C′ → A′, which yields $897,892.
The decision depends on how the loss of each CTQ is divided between the two components, which the aggregate loss does not reveal. Holding the total loss of each CTQ fixed, the state-resolved evaluation drops B′ once its between-state share exceeds 0.44 (0.62 in Table 8), and the difference between the two evaluations then grows linearly with that share, up to $150,000 when the loss of B′ is entirely between-state. Project D′ enters the state-resolved portfolio only if its between-state share exceeds 0.90 (0.66 in Table 8). Below these thresholds, the two evaluations select the same portfolio, although the benefit reported by the aggregate evaluation remains overstated. The divergence therefore arises from the project mechanisms, not from the heterogeneity of the CTQs. The comparison thus shows the consequence of applying the proportional reduction of Equation (2) to projects for which this assumption is inappropriate; it does not show that every evaluation based on marginal moments must lead to inferior decisions since the two evaluations coincide when all projects are scale-reduction projects, and the size of the difference is specific to the parameters of Table 8. The selected portfolio also differs from that of the homogeneous base case, which confirms that the robustness reported in Section 6.1 is specific to that scenario.

6.4. Computational Verification and Scalability of the MILP

The MILP of Equations (5)–(18) was implemented in Python version 3.10.4 with Pyomo [47] version 6.10.1 and solved with HiGHS [48] (version 1.15.1, default settings) on a laptop with an AMD Ryzen 9 5900HX processor (Advanced Micro Devices, Inc., Santa Clara, CA, USA; 3.3 GHz, 8 cores) and 16 GB of RAM. The implementation was verified in three steps.
First, for the four-project instance of Section 5, the MILP was solved at each budget level of Table 6 and compared with an exhaustive enumeration that evaluates every feasible subset in every order and therefore does not rely on the er/dr rule; both methods returned the same portfolio, sequence, and net benefit (Section 5.3.2).
Second, 200 random instances with n = 5, 6, 7, and 8 candidate projects (50 for each n) were generated. For each project, the proportional reduction Δr was drawn uniformly between 0.10 and 0.55, which covers the improvement magnitudes calibrated in Section 5.1; the baseline expected loss between $5 and $20 per unit; and the implementation duration between 1 and 6 months. The implementation cost was set to Δr × 1.5 × 106 multiplied by a factor drawn uniformly between 0.5 and 1.5, and the budget to a random share between 30% and 100% of the total cost of all candidates, with H = 12 months and ρ as in Section 5.1. In all 200 instances, the MILP and exhaustive enumeration returned the same optimal net benefit and the same portfolio, and the MILP sequence followed the er/dr rule (Table 9). Optimal portfolios contained between one and four projects; in 190 of the 200 instances, they contained at least two projects, so that the sequencing part of the model was exercised as well as the selection part.
Table 9. Verification of the MILP against exhaustive enumeration on 200 random instances (H = 12 months).
Third, five random instances were generated for each n = 10, 20, 30, 40, and 50 with the same parameter ranges and solved with a time limit of 600 s. Reference optimal values were obtained by enumerating feasible subsets in the er/dr order (Section 4.2): a depth-first search adds the candidates in this order and abandons a branch as soon as the cumulative duration exceeds H or the cumulative cost exceeds B, so that every feasible subset is evaluated exactly once, in its optimal order. Because the horizon limits the number of projects in a feasible subset, the number of feasible subsets remains moderate: for 50 candidates, 1.1–2.3 × 105 subsets were evaluated in 0.22–0.55 s per instance (0.39 s on average), and for 40 candidates in at most 0.26 s; the memory requirement is negligible since only the current branch is stored. The MILP solved all instances with up to 40 candidates to optimality; mean wall-clock times increased rapidly with the number of candidates, from 1.6 s for 10 candidates to 318.2 s for 40 candidates (maximum 528.9 s) (Table 10). For 50 candidates, no instance was proven optimal within the limit; the best solution found was optimal in three instances and at least 97.7% of the optimum in the other two, but the optimality gap, defined as (best bound − best solution)/best solution, remained between 19.4% and 82.7%. Solution times and the gaps of instances stopped at the time limit vary between runs; in a repeated run, solution times differed by 15–25%, all instances with up to 40 candidates were again solved to optimality, and one instance with 50 candidates was solved to optimality in 585 s. The open gaps therefore concern the proof of optimality rather than the quality of the solutions found. They are consistent with a weak linear programming relaxation of the position-based formulation and its linearization in Equations (13)–(15) [42]. Because implementation durations of one to six months must fit within the 12-month horizon, optimal portfolios contained two to six projects. Within a given n, instances with larger optimal portfolios tended to take longer.
Table 10. MILP performance on random instances (H = 12 months, five instances per n, time limit 600 s).
For the base model, enumerating feasible subsets in the er/dr order is a faster exact method and was used here to obtain the reference optimal values. Its validity, however, rests on the er/dr rule [36], which no longer determines the optimal order once the model is extended with discounting, parallel improvement teams, precedence relations or sequence-dependent durations. The MILP is presented as the general formulation because it can serve as the basis for such extensions, although not all of them can be represented by additional constraints alone. Precedence relations can be added as constraints, but parallel teams and sequence-dependent durations require additional variables, and discounting changes the objective function because the benefit of a project then depends nonlinearly on its completion time (Section 4.2). A piecewise-linear treatment of continuous discounting is generally an approximation; an exact linear treatment is possible with a time-indexed formulation over a discrete time grid on which the durations are defined. The code, the instance generator, and all results are provided as Supplementary Material (Code S1, Tables S1–S3).

6.5. Computational Study

To examine when the optimization adds value beyond simple prioritization rules, we generated 3600 random instances in a full factorial design: 5, 10, or 20 candidates; a budget of 30%, 60%, or 100% of the total cost of the candidates; a horizon of 6, 12, 24, or 36 months; and homogeneous ($10 per unit) or heterogeneous ($5–20 per unit) baseline losses, with 50 instances per combination. Improvement effects, durations, and costs are drawn from the ranges of the instance generator described in Section 6.4, and the production rate is that of Section 5. Because the optimal order of any selected set follows the er/dr rule, the optimum of each instance can be computed exactly by dynamic programming over the projects in er/dr order. A state represents a partial portfolio by its cumulative duration T, its cumulative cost b and its net benefit v. When project r is considered, each state is either kept unchanged (r not selected) or extended to (T + dr, b + Cr, v + ρer(H − T − dr) − Cr), provided that T + dr ≤ H and b + Cr ≤ B; because the projects are considered in er/dr order, the completion time of r, and hence its benefit, is known when it is added. A state is discarded if another state has no larger duration and cost and no smaller net benefit because every continuation of the discarded state is also feasible for the dominating state and yields at least the same net benefit; the budget is therefore part of the dominance test. The optimum is the largest net benefit v among the final states. The recursion does not require a time grid: the durations of the generated instances are drawn in steps of 0.1 month, and the implementation stores times in these units, which is exact for these instances. For durations of any other resolution, the same recursion remains exact; a finer resolution affects only the number of non-dominated states, which may then be larger. At most 1089 non-dominated states arose, and all 3600 instances, including the evaluation of the six rules below, were solved in about 30 s (Code S2). This procedure reproduced the optimum of exhaustive enumeration in 80 of 80 small instances and that of the MILP in 15 of 15 instances with 10 or 20 candidates. Of the 3600 instances, the 3369 with a profitable portfolio are analyzed below; in the remaining 231, all with a six-month horizon, no portfolio is profitable.
The optimum is compared with six rules: largest improvement Δ, lowest cost, shortest duration, highest return on investment, highest standalone net benefit, and highest ratio er/dr first. Each rule goes down its ranking and adds a project if it fits the remaining budget and horizon and recovers its cost at its scheduled completion; projects are implemented in the order of the ranking. Table 11 and Figure 1 report the gap to the optimum. No single rule is reliably close to the optimum. The best-performing rules, highest standalone net benefit and highest er/dr, fall short by 6.8% and 7.1% on average and by more than 5% in 44% and 30% of the instances; ranking by improvement, a proxy for prioritization by expected variance reduction, falls short by 26.9% on average and by more than 5% in 74%. The gaps grow with the number of candidates and are largest for horizons that admit several projects, whereas with a six-month horizon, in which one or two projects can be completed, the best rules are nearly optimal. Implementing the projects selected by a rule in er/dr order closes a large part of the gap (for example, from 18.6% to 9.8% for ranking by return on investment), which shows the value of the sequencing rule of Section 4.2; the remaining gap arises from the selection and requires the optimization model. Even if the best of the six rules were chosen for each instance after the fact, the gap would exceed 5% in 12.7% of all instances and in 20.4% of those with 20 candidates. The median gaps of the two best rules are small (3.4% and 0.6%), so simple rules often perform well; the value of the optimization lies in avoiding the substantial losses that occur in a large share of instances that cannot be identified in advance. The tightness of the budget has a smaller effect than the number of candidates and the horizon. Even with an ample budget, each additional project starts later and has a shorter benefit-bearing period, so the selection remains a trade-off; the optimal portfolios rarely use more than 90% of the horizon. Finally, these results depend on the assumptions of the instance generator, in particular that the implementation cost of a project is proportional to its improvement Δr up to a random factor between 0.5 and 1.5 (Section 6.4); they show how often simple rules fall short under these conditions and do not establish the performance of the approach under all industrial conditions.
Table 11. Mean gap of six prioritization rules to the optimum (%) by factor level (3369 instances with a profitable portfolio).
Figure 1. Mean gap of six prioritization rules to the optimum by number of candidates and evaluation horizon (3369 instances with a profitable portfolio). The optimum of the proposed model corresponds to a gap of 0%; higher values indicate a larger loss of net benefit relative to it.

7. Discussion

As reviewed in Section 2, Multi-Criteria Decision-Making (MCDM) models, such as AHP and TOPSIS, form the largest identifiable group of methods used to evaluate quality improvement projects [11]. One contribution of this paper is to add, on the cost dimension, an economic criterion that is reproducible given documented inputs rather than elicited weights.
The proposed criterion complements rather than replaces multi-criteria project evaluation. It provides an economic measure based on expected quality losses, implementation costs, and project durations, while strategic alignment, customer impact, feasibility, and risk remain outside its scope. The net avoided-loss benefit can be incorporated into MCDM as a financial-benefit criterion, used to screen economically unattractive projects, or combined with MCDM scores through additional constraints in the selection model. Although its inputs can be estimated from production and accounting data, their uncertainty must still be considered when making decisions.
A second contribution concerns how project benefits are derived from process behavior. The process-state formulation does not change the expected loss itself, which equals the classical Taguchi loss of the marginal distribution. The main value of the state-resolved formulation emerges when improvement projects affect different sources of process variation. In such cases, aggregate expected loss does not provide enough information to determine the avoided loss of each project. The heterogeneous example (Section 6.3) demonstrates that overlooking this distinction can lead to a less valuable portfolio. This finding connects the statistical interpretation of process behavior directly to an economic improvement decision.
For manufacturers with established SPC and quality-cost records, the framework offers a structured basis for prioritizing improvement investments. It distinguishes project selection from sequencing, accounts for the delay before benefits are realized, and identifies situations in which simple prioritization rules may be inadequate. Nevertheless, the economic ranking should inform rather than replace strategic decisions, particularly when product quality or customer requirements take precedence over short-term financial returns.
The model relies on several simplifying assumptions. Project benefits are additive across CTQs, implementation costs and durations are deterministic, projects do not interact, and a single improvement team carries out the selected projects sequentially. Shared failure costs (Appendix B), uncertain improvement effects, and partially shared resources may alter both portfolio selection and implementation order. The present formulation also assumes no discounting, which is reasonable for short horizons but requires modification for longer-term investment decisions (Section 4.2). A further limitation is the absence of empirical validation using integrated production and accounting records (SPC data, CTQ-level quality costs, and planned and actual project costs and durations) from a single manufacturer. Future work should compare predicted avoided losses with those observed after project implementation. Extending the model to interacting project benefits and multiple improvement teams would also improve its applicability to more complex industrial environments. In the tested instances, the position-based MILP solved all instances with up to 40 candidates to optimality but did not prove optimality for most instances with 50 candidates within 600 s (Section 6.4); this is a finding for these instances and this formulation rather than a general threshold. Stronger formulations or decomposition methods for larger candidate sets are a direction for future research.

8. Conclusions

This study developed an economic approach for selecting and sequencing Six Sigma improvement projects using expected Taguchi quality loss under random process mean shifts and dispersion changes. By distinguishing between-state and within-state contributions, the formulation evaluates projects according to the sources of variation they reduce. For scale-reduction projects, aggregate expected loss is sufficient; when improvement mechanisms differ, the separate components become important. The resulting avoided losses are incorporated into a budget- and horizon-constrained selection-and-sequencing model, with the optimal order for any selected portfolio determined by the WSPT rule. Its conclusions differ in the strength of their support, from analytical results to questions that still require empirical validation.
The illustrative application demonstrates that projects with large reductions in standard deviation are not necessarily the most economically attractive. More importantly, the heterogeneous example shows that aggregate-loss evaluation can select a less valuable portfolio when improvements affect process states differently. Computational experiments further show that simple prioritization rules can produce substantial economic losses relative to optimal selection and sequencing, particularly for larger candidate sets. These findings depend on the scenario parameters and on the ranges of the instance generator.
These findings establish the analytical and computational value of the proposed approach, but its practical performance remains to be validated using integrated production and cost data. Future extensions should consider interacting improvement projects, uncertain project outcomes, and more complex resource constraints.

Supplementary Materials

The following supporting information can be downloaded at https://www.mdpi.com/article/10.3390/app162311784/s1, Code S1: Python implementation of the MILP of Equations (5)–(18), the enumeration procedures, and the random instance generator; Code S2: Python scripts that reproduce the numerical results of Section 5 and Section 6 and Appendix A, Appendix B and Appendix C, including the computational study (Section 6.5) and the sensitivity analyses (Section 6.1); Table S1: Results for the four-project instance at the budget levels of Table 6; Table S2: Verification against exhaustive enumeration on 200 random instances; Table S3: Computational results for 10 to 50 candidate projects; Table S4: Results of the computational study for each of the 3600 instances; Table S5: One-at-a-time thresholds of the optimal portfolio and order; Table S6: Monte Carlo analysis with independent changes of the project parameters.

Author Contributions

Conceptualization, A.C.C., S.T., and B.B.; methodology, A.C.C., S.T., and B.B.; software, A.C.C., M.E.K., and E.K.; validation, A.C.C., M.E.K., E.K., S.T., and B.B.; formal analysis, A.C.C., M.E.K., B.B., and E.K.; investigation, A.C.C., M.E.K., and E.K.; data curation, A.C.C., M.E.K., and E.K.; writing—original draft preparation, A.C.C., M.E.K., and E.K.; writing—review and editing, A.C.C., S.T., and B.B.; visualization, A.C.C., M.E.K., and E.K.; supervision, S.T. and B.B.; project administration, S.T. and B.B. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the Scientific and Technological Research Council of Türkiye (TÜBİTAK) under the 1001 program, grant number 125M585.

Institutional Review Board Statement

Not applicable.

Data Availability Statement

The input data of the numerical illustration are reported in the article (Table 3 and Table 8). The Python code that implements the MILP of Equations (5)–(18), the enumeration procedures, and the random instance generator, together with the scripts and results of all computational experiments, is provided as Supplementary Material (Codes S1 and S2, Tables S1–S6). Further inquiries can be directed to the corresponding author.

Acknowledgments

During the preparation of this study, the authors used ChatGPT (GPT-5.6 Luna, OpenAI) and Claude (Opus 4.5, Anthropic) for language editing, proofreading, and checking the internal consistency of the text and citations. The authors have reviewed and edited the output and take full responsibility for the content of this publication.

Conflicts of Interest

The authors declare no conflicts of interest.

Nomenclature

The following symbols are used in this manuscript:
Symbol Description
Process and loss
Y ,   t Quality characteristic (nominal-the-best) and its target
LSL ,   USL Specification limits
Δ 0 Deviation from the target at which a unit fails in use; in practice often replaced by the specification half-width
σ ;   u In-control standard deviation; initial sigma level, (USL − t)/σ
K ,   Λ Standardized mean-shift state and dispersion-scaling state (random variables)
μ K ,   σ K 2 ;   μ Λ ,   σ Λ 2 Mean and variance of K; mean and variance of Λ
F K , Λ Joint distribution of the process states
p Share of production in the out-of-control state (Section 3.1)
a ;   λ Shift magnitude and dispersion scale in the out-of-control state, (K, Λ) = (±a, λ) (Section 2.4 and Section 6.3, Appendix C)
c Taguchi loss coefficient ($/(unit·mm2))
A0Average loss of a unit at deviation Δ0 from the target
L ¯ ;   MSD Observed failure cost per unit produced; mean squared deviation from the target
E [ C ( Y ) ] Expected quality loss per unit (Equation (1))
L pre ,   L post Expected loss per unit before and after a project
Projects and model
i ,   r ;   n Index of a CTQ and of the project that targets it; number of candidate projects
Δ r Proportional reduction in the standard deviation achieved by project r (scale reduction)
γ r ,   δ r Proportional reductions of the between-state and within-state deviations achieved by project r
e r Avoided loss per unit after the completion of project r
C r ,   d r Implementation cost and duration of project r
P r ;   P Net avoided-loss benefit of project r alone; of a portfolio and sequence
ROI r Return on investment of project r, Pr/Cr
N ;   ρ Reference production volume; production rate (units per month)
N old , i , N new , i Units produced during and after the implementation of project i
H ;   B Evaluation horizon; budget
x r ;   I mr 1 if project r is selected; 1 if project r is in implementation position m
m ,   k ;   T m ;   y mr Implementation positions (Equations (5)–(18)); completion time of position m; linearization variable, ImrTm
π ( m ) Project in implementation position m
Estimation (Section 3.1, Appendix C)
x ¯ j , s j 2 ; n s ; J Mean and variance of subgroup j; subgroup size; number of subgroups
E ^ [ · ] Estimate of an expectation from SPC data

Appendix A. Supplementary Sensitivity Results

This appendix reports a supplementary robustness check, Table A1, referenced in Section 5.2.1. The one-at-a-time thresholds and the Monte Carlo analysis of Section 6.1 are given in Supplementary Tables S5 and S6.
Table A1. Sensitivity of single-project net benefit to independent changes of ±10% and ±20% in Δ.
Each project’s Δ is changed independently, so the columns can be combined freely. Even in the least favorable ±10% combination, Project A ($421,156) remains ahead of Project B ($419,910).

Appendix B. Illustration of Shared Scrap Costs

Consider two CTQs, X and Y, of the same product. A unit is scrapped if at least one of the two characteristics is nonconforming, at a cost of $10 per scrapped unit, and the two characteristics are nonconforming independently of each other. The expected scrap cost is then 10 × [1 − (1 − pX)(1 − pY)] per unit, where pX and pY are the nonconformance probabilities, whereas the additive model of Section 4.1.2 uses 10 × (pX + pY).
In the first example, both characteristics are nonconforming with probability 0.30, so that the expected scrap cost is $5.10 per unit, whereas the additive model gives $6.00. Project X reduces pX to 0.10, and Project Y reduces pY to 0.05. Table A2 shows two features. First, the additive model overstates the avoided cost of each project. Second, the avoided cost of a project depends on whether the other project has been implemented: Project X avoids $1.40 per unit on its own but $1.90 once Project Y is in place, and the combined effect of the two projects ($3.65) exceeds the sum of their stand-alone effects ($3.15).
Table A2. Avoided scrap cost per unit, first example (pX: 0.30 → 0.10, pY: 0.30 → 0.05).
The second example shows that these effects can change the decisions themselves. Characteristic X is nonconforming with probability 0.10 and Y with probability 0.40; Project X reduces pX to 0, and Project Y reduces pY to 0.31. Both projects have equal implementation costs and equal durations d. The additive model values Project X at $1.00 and Project Y at $0.90 per unit, whereas under the shared scrap mechanism, Project X avoids $0.60 and Project Y $0.81 (Table A3). If the budget allows only one project, the additive model therefore selects Project X, although Project Y yields the larger net benefit. If both projects are implemented, the additive model and the er/dr rule place Project X first, whereas implementing Project Y first increases the cumulative avoided cost by 0.21ρd. The same mechanism carries over to the expected quality loss when the loss coefficients ci are calibrated from scrap costs (Section 3.1).
Table A3. Avoided scrap cost per unit and resulting decisions, second example (pX: 0.10 → 0, pY: 0.40 → 0.31; equal costs and durations).

Appendix C. Estimating the Process-State Moments: A Simulation

To examine the estimation procedure of Section 3.1, we simulated production histories with known process states. A rational subgroup of size ns is taken from each production block. Out-of-control episodes start at random, shift the mean by ±a, and inflate the dispersion to λ; they are detected by X ¯ and S charts with three-sigma limits and corrected four blocks after the signal, and the start probability is set so that a share p of production is out of control in the long run. Within a state, the observations of a subgroup are independent and normally distributed with mean t + Kσ and standard deviation Λσ. For backdating, a two-sided tabular CUSUM is applied to the standardized subgroup means n s ( x j ¯ − t ) / σ with reference value a n s / 2 ; when a chart signals, the onset is set to the first block of the current run of positive values of the larger CUSUM statistic, and both statistics are reset after the correction. This is a location CUSUM; for episodes that inflate only the dispersion, a CUSUM on the subgroup variances would be used instead. The simulation is implemented in Code S2 (appendixC_estimation.py). For the process of Section 5.1 (p = 0.2, a = 2, λ = 1.5), the first-level estimates are close to the true values: over 300 replications with 1000 subgroups, the estimated between-state share of the loss averages 0.386 (ns = 3) and 0.388 (ns = 5) against a true value of 0.390, with a standard deviation of about 0.03, which doubles with 250 subgroups. Without the sampling correction, the between-state component would be overestimated by 50% (ns = 3) and 30% (ns = 5). At the second level, taking the signal time as the onset misses 12% (ns = 3) and 5% (ns = 5) of the out-of-control production because of the detection delay; backdating with a CUSUM statistic reduces this error (by half for ns = 3), so that the out-of-control share of the loss is estimated at 0.587–0.588 against realized values of 0.604–0.605, whereas counting false alarms as episodes would bias it upwards.
The decision effect is examined on the heterogeneous example of Section 6.3. For each of the four CTQs, a production history is simulated, and the two components are estimated at the first level; the projects are then evaluated with these estimates. With 250 subgroups per CTQ, the state-resolved evaluation selects the optimal portfolio C′ → A′ in 94–96% of the replications and realizes, on average, 98% of the optimal net benefit; with 1000 subgroups, it selects it in every replication. The aggregate evaluation, using the same data, never selects it and realizes 76–80% of the optimum. Because it overstates the benefits of Projects B′ and D′, it regards three portfolios as almost equally valuable (claimed net benefits between $1,002,191 and $1,014,103), whose actual net benefits range from $630,120 to $848,109, so that small estimation errors determine its choice. Table A4 summarizes the results.
Table A4. Estimation of the process-state components from simulated SPC data and its effect on the decision.

References

  1. Kwak, Y.H.; Anbari, F.T. Benefits, Obstacles, and Future of Six Sigma Approach. Technovation 2006, 26, 708–715. [Google Scholar] [CrossRef] [Scilit]
  2. Snee, R.D. Lean Six Sigma—Getting Better All the Time. Int. J. Lean Six Sigma 2010, 1, 9–29. [Google Scholar] [CrossRef] [Scilit]
  3. Antony, J.; Snee, R.; Hoerl, R. Lean Six Sigma: Yesterday, Today and Tomorrow. Int. J. Qual. Reliab. Manag. 2017, 34, 1073–1093. [Google Scholar] [CrossRef] [Scilit]
  4. Sakib, M.N.; Kawsar, M.; Bithee, M.M. Continuous Improvement through Lean Six Sigma: A Systematic Literature Review and Bibliometric Analysis. Int. J. Lean Six Sigma 2025, 16, 1252–1275. [Google Scholar] [CrossRef] [Scilit]
  5. Kumar, M.; Antony, J.; Cho, B.R. Project Selection and Its Impact on the Successful Deployment of Six Sigma. Bus. Process Manag. J. 2009, 15, 669–686. [Google Scholar] [CrossRef] [Scilit]
  6. de Mast, J.; Lokkerbol, J. An Analysis of the Six Sigma DMAIC Method from the Perspective of Problem Solving. Int. J. Prod. Econ. 2012, 139, 604–614. [Google Scholar] [CrossRef] [Scilit]
  7. Montgomery, D.C.; Woodall, W.H. An Overview of Six Sigma. Int. Stat. Rev. 2008, 76, 329–346. [Google Scholar] [CrossRef] [Scilit]
  8. Linderman, K.; Schroeder, R.G.; Zaheer, S.; Choo, A.S. Six Sigma: A Goal-Theoretic Perspective. J. Oper. Manag. 2003, 21, 193–203. [Google Scholar] [CrossRef] [Scilit]
  9. Banuelas, R.; Tennant, C.; Tuersley, I.; Tang, S. Selection of Six Sigma Projects in the UK. TQM Mag. 2006, 18, 514–527. [Google Scholar] [CrossRef] [Scilit]
  10. Büyüközkan, G.; Öztürkcan, D. An Integrated Analytic Approach for Six Sigma Project Selection. Expert Syst. Appl. 2010, 37, 5835–5847. [Google Scholar] [CrossRef] [Scilit]
  11. Pakdil, F. Six Sigma Project Prioritization and Selection Methods: A Systematic Literature Review. Int. J. Lean Six Sigma 2022, 13, 382–407. [Google Scholar] [CrossRef] [Scilit]
  12. Taguchi, G. Introduction to Quality Engineering: Designing Quality into Products and Processes; Asian Productivity Organization: Tokyo, Japan, 1986. [Google Scholar]
  13. Yacout, S.; Boudreau, J. Assessment of Quality Activities Using Taguchi’s Loss Function. Comput. Ind. Eng. 1998, 35, 229–232. [Google Scholar] [CrossRef] [Scilit]
  14. Montgomery, D.C. Introduction to Statistical Quality Control, 8th ed.; John Wiley & Sons: Hoboken, NJ, USA, 2020. [Google Scholar]
  15. Schroeder, R.G.; Linderman, K.; Liedtke, C.; Choo, A.S. Six Sigma: Definition and Underlying Theory. J. Oper. Manag. 2008, 26, 536–554. [Google Scholar] [CrossRef] [Scilit]
  16. Antony, J.; Antony, F.J.; Kumar, M.; Cho, B.R. Six Sigma in Service Organisations: Benefits, Challenges and Difficulties, Common Myths, Empirical Observations and Success Factors. Int. J. Qual. Reliab. Manag. 2007, 24, 294–311. [Google Scholar] [CrossRef] [Scilit]
  17. Hajji, M.K.; Fekih, A.; Bal, A.; Tozan, H. Applying Lean Six Sigma DMAIC to Improve Service Logistics in Tunisia’s Public Transport. Logistics 2025, 9, 159. [Google Scholar] [CrossRef] [Scilit]
  18. McDermott, O.; Antony, J.; Bhat, S.; Jayaraman, R.; Rosa, A.; Marolla, G.; Parida, R. Lean Six Sigma in Healthcare: A Systematic Literature Review on Motivations and Benefits. Processes 2022, 10, 1910. [Google Scholar] [CrossRef] [Scilit]
  19. Sony, M.; Naik, S.; Therisa, K.K. Why Do Organizations Discontinue Lean Six Sigma Initiatives? Int. J. Qual. Reliab. Manag. 2019, 36, 420–436. [Google Scholar] [CrossRef] [Scilit]
  20. Banuelas Coronado, R.; Antony, J. Critical Success Factors for the Successful Implementation of Six Sigma Projects in Organisations. TQM Mag. 2002, 14, 92–99. [Google Scholar] [CrossRef] [Scilit]
  21. Saaty, T.L. The Analytic Hierarchy Process: Planning, Priority Setting, Resource Allocation; McGraw-Hill: New York, NY, USA, 1980. [Google Scholar]
  22. Ho, W.; Ma, X. The State-of-the-Art Integrations and Applications of the Analytic Hierarchy Process. Eur. J. Oper. Res. 2018, 267, 399–414. [Google Scholar] [CrossRef] [Scilit]
  23. Uluskan, M.; Beki, B. Project Selection Revisited: Customized Type-2 Fuzzy ORESTE Approach for Project Prioritization. Int. J. Ind. Eng. Theory Appl. Pract. 2024, 31, 317–339. [Google Scholar] [CrossRef]
  24. Singh, M.; Rathi, R.; Antony, J.; Garza-Reyes, J.A. Lean Six Sigma Project Selection in a Manufacturing Environment Using Hybrid Methodology Based on Intuitionistic Fuzzy MADM Approach. IEEE Trans. Eng. Manag. 2023, 70, 590–604. [Google Scholar] [CrossRef] [Scilit]
  25. Antony, J. Some Pros and Cons of Six Sigma: An Academic Perspective. TQM Mag. 2004, 16, 303–306. [Google Scholar] [CrossRef] [Scilit]
  26. Aqlan, F.; Al-Fandi, L. Prioritizing Process Improvement Initiatives in Manufacturing Environments. Int. J. Prod. Econ. 2018, 196, 261–268. [Google Scholar] [CrossRef] [Scilit]
  27. Kandakoglu, M.; Walther, G.; Ben Amor, S. The Use of Multi-Criteria Decision-Making Methods in Project Portfolio Selection: A Literature Review and Future Research Directions. Ann. Oper. Res. 2024, 332, 807–830. [Google Scholar] [CrossRef] [Scilit]
  28. Bertolini, M.; Castellano, D. Quality Cost Deployment (QCD): A Lean-Inspired Methodology for Systematic Reduction of Total Quality Costs. Int. J. Lean Six Sigma 2026, 17, 133–160. [Google Scholar] [CrossRef] [Scilit]
  29. Chen, K.-S.; Chen, S.-C.; Hsu, T.-H.; Lin, M.-Y.; Wu, C.-F. Fuzzy Evaluation Model of Process Improvement Capability with Costs Consideration. Appl. Sci. 2021, 11, 4344. [Google Scholar] [CrossRef] [Scilit]
  30. Wang, B.; Li, Q.; Yang, Q.; Chen, Z.; Nie, X. Establishment of Quadratic Exponential Quality Gain-Loss Function Model and Design of Process Mean. Heliyon 2024, 10, e36481. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  31. Chan, L.K.; Cheng, S.W.; Spiring, F.A. A New Measure of Process Capability: Cpm. J. Qual. Technol. 1988, 20, 162–175. [Google Scholar] [CrossRef] [Scilit]
  32. Huang, C.-T.; Lai, K.-K. Process Quality Evaluation Model with Taguchi Cost Loss Index. Appl. Sci. 2021, 11, 10182. [Google Scholar] [CrossRef] [Scilit]
  33. Duncan, A.J. The Economic Design of X Charts Used to Maintain Current Control of a Process. J. Am. Stat. Assoc. 1956, 51, 228–242. [Google Scholar] [CrossRef] [Scilit]
  34. Haridy, S.; Maged, A.; Alherimi, N.; Shamsuzzaman, M.; Al-Ali, S. Optimization Design of Control Charts: A Systematic Review. Qual. Reliab. Eng. Int. 2024, 40, 2122–2157. [Google Scholar] [CrossRef] [Scilit]
  35. Shabtay, D.; Gaspar, N.; Kaspi, M. A Survey on Offline Scheduling with Rejection. J. Sched. 2013, 16, 3–28. [Google Scholar] [CrossRef] [Scilit]
  36. Smith, W.E. Various Optimizers for Single-stage Production. Nav. Res. Logist. Q. 1956, 3, 59–66. [Google Scholar] [CrossRef] [Scilit]
  37. Slotnick, S.A. Order Acceptance and Scheduling: A Taxonomy and Review. Eur. J. Oper. Res. 2011, 212, 1–11. [Google Scholar] [CrossRef] [Scilit]
  38. Tarhan, İ.; Oğuz, C. A Matheuristic for the Generalized Order Acceptance and Scheduling Problem. Eur. J. Oper. Res. 2022, 299, 87–103. [Google Scholar] [CrossRef] [Scilit]
  39. Qiu, B.; Dou, Y.; Chen, Z. Optimizing Multi-Stage Project Portfolio Selection Considering Integrating Lifecycle and Interactions. Systems 2024, 12, 414. [Google Scholar] [CrossRef] [Scilit]
  40. Hermelin, D.; Shabtay, D.; Zelig, C.; Pinedo, M. A General Scheme for Solving a Large Set of Scheduling Problems with Rejection in FPT Time. J. Sched. 2022, 25, 229–255. [Google Scholar] [CrossRef] [Scilit]
  41. Kramer, A.; Dell’Amico, M.; Iori, M. Enhanced Arc-Flow Formulations to Minimize Weighted Completion Time on Identical Parallel Machines. Eur. J. Oper. Res. 2019, 275, 67–79. [Google Scholar] [CrossRef] [Scilit]
  42. Glover, F. Improved Linear Integer Programming Formulations of Nonlinear Integer Problems. Manag. Sci. 1975, 22, 455–460. [Google Scholar] [CrossRef] [Scilit]
  43. Kaushik, P.; Khanduja, D.; Mittal, K.; Jaglan, P. A Case Study: Application of Six Sigma Methodology in a Small and Medium-sized Manufacturing Enterprise. TQM J. 2012, 24, 4–16. [Google Scholar] [CrossRef] [Scilit]
  44. Mittal, A.; Gupta, P.; Kumar, V.; Al Owad, A.; Mahlawat, S.; Singh, S. The Performance Improvement Analysis Using Six Sigma DMAIC Methodology: A Case Study on Indian Manufacturing Company. Heliyon 2023, 9, e14625. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  45. Gupta, V.; Jain, R.; Meena, M.L.; Dangayach, G.S. Six-Sigma Application in Tire-Manufacturing Company: A Case Study. J. Ind. Eng. Int. 2018, 14, 511–520. [Google Scholar] [CrossRef] [Scilit]
  46. Srivastava, P.; Alrasheedi, M.; Kaushik, P.; Sharma, S. Reducing the Cost of Poor Quality and Improving Process Output by Adopting a Six Sigma DMAIC Tool: A Case Study. Int. J. Six Sigma Compet. Advant. 2021, 13, 195–216. [Google Scholar] [CrossRef] [Scilit]
  47. Bynum, M.L.; Hackebeil, G.A.; Hart, W.E.; Laird, C.D.; Nicholson, B.L.; Siirola, J.D.; Watson, J.-P.; Woodruff, D.L. Pyomo—Optimization Modeling in Python, 3rd ed.; Springer Optimization and Its Applications; Springer International Publishing: Cham, Switzerland, 2021. [Google Scholar]
  48. Huangfu, Q.; Hall, J.A.J. Parallelizing the Dual Revised Simplex Method. Math. Program. Comput. 2018, 10, 119–142. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.