Optimization-Based Scheduling for Rapid Repair of Disrupted Airport Pavements

,
and
Air Force Engineering University, Xi’an 710038, China
*
Author to whom correspondence should be addressed.
This article belongs to the Section Civil Engineering

Abstract

Sudden localized pavement damage can disrupt airport operations and create substantial delay costs. This study models repair scheduling as a two-level planning–execution problem that extends the multi-mode resource-constrained project scheduling problem with crew and equipment limits, precedence, release times, transfer-path occupancy, and evolving obstacles. A constraint programming–simulation collaborative framework (CSC-SF) combines CP-SAT constraint-programming planning with deterministic spatiotemporal execution evaluation. Across 90 synthetic benchmark instances, CSC-SF yields the lowest mean simulated repair-completion time (195.45 min) among five compared algorithms and the best or tied-best result on 82 instances. Compared with the one-shot CP-SAT baseline (BASE), CSC-SF achieves a 30.54 min lower mean simulated makespan; all four prespecified pairwise comparisons with the external baselines are statistically significant after global Holm adjustment. On three small instances, 40 s solutions match the incumbents found in 4 h reference runs; independently optimized planning-relaxation lower bounds yield a posteriori relative optimality-gap upper bounds of 0.30–0.80% under the modeled planning-to-execution relationship. Adding selected bottleneck resource groups reduced mean simulated makespan by approximately 14–26 min in the tested engineering scenarios, and fixed-parameter sweeps describe sensitivity to travel speed and processing time. The findings support computational decision-making for airport pavement repair, subject to calibration and field validation.

1. Introduction

Airports operate under growing pressure to keep airside infrastructure available. The aviation sector accounts for about 5% of the U.S. gross domestic product, and the Infrastructure Investment and Jobs Act of 2021 allocated 25 billion dollars to airports, funding construction and expansion projects, including runways, taxiways, and terminals [1]. Pavements nevertheless age and fail; sudden localized structural failures can render runway or taxiway segments unusable, and how quickly they are reopened becomes critical to airport operations. The stakes of closure duration are well documented. Adverse weather caused 4.8 million minutes of en-route air traffic flow management delay in Europe in 2018, a 124% increase over 2017, with delay unit costs estimated at 100 euros per minute [2]. Airline delay is valued at 1500 to 4500 dollars per aircraft-hour depending on aircraft class [1]. Beyond physical reconstruction, the speed of restoration therefore depends on how repair crews, equipment, and materials are scheduled, and on whether the schedule respects the spatiotemporal realities of the airside work environment.
After airport pavement damage, rapid completion of repair operations can reduce one component of closure duration; curing, inspection, and formal authorization may still be required before operations resume. Damage assessment of airport pavements and selection of the minimum usable runway segment are prerequisite steps for repair operations, and existing studies have provided methods for strip selection, damage assessment, and repair-hours prediction [3,4,5,6]. Once the damage locations and geometric information are determined, the core difficulty of repair scheduling shifts to resource organization. Established airside damage-assessment and repair practice provides rules for damage spot classification and repair quality. Because damage spots differ in damage type, geometric size, and spatial position [5], the admissible repair processes and resource combinations differ among damage spots. Each process consists of several operations, and completing one operation requires multiple equipment units and related personnel to work simultaneously. Different configurations of personnel, equipment, and materials constitute different resource groups, whose performance differences directly affect operation completion times. The same operation can also be performed by different resource groups, and the specific equipment instances of a resource group must satisfy spatiotemporal constraints such as release times, spatial positions, travel paths, and corridor occupancy. Therefore, modeling only at the resource-group level cannot adequately capture the spatiotemporal feasibility of equipment execution.
Structurally, the problem contains the three core elements of the multi-mode resource-constrained project scheduling problem (MRCPSP): multi-mode selection, renewable resource constraints, and precedence constraints. Multi-mode selection means that each damage spot can be repaired by different processes and the same operation can be executed by different resource groups. Renewable resource constraints mean that each repair crew has fixed quantities of equipment and personnel, and that the concurrent use of the same resource type by parallel operations cannot exceed the total within the repair crew. Precedence constraints mean that operations within each process follow a strict sequence. Hartmann and Briskorn surveyed the RCPSP and its variants [7] and pointed out that these problems form a large family of NP-hard problems whose solution difficulty grows combinatorially with the numbers of modes, resource types, and operations. This provides a theoretical basis for not resorting solely to exact solution methods for airport repair scheduling on large-scale instances. Klein formulated an integer programming model for the MRCPSP [8] and gave the mathematical expressions of multi-mode selection and resource capacity constraints. The process selection, repair crew assignment, and resource capacity constraints in the planning layer of this paper are formulated on this basis, and the model further embeds equipment-level spatial resources and path constraints, defining a spatially constrained subclass of the MRCPSP family. On the solution side, Fernandes and de Souza combined mathematical programming with heuristics to solve the MRCPSP [9]. Van Peteghem and Vanhoucke solved preemptive and nonpreemptive MRCPSPs with genetic algorithms combined with local search, and compared the performance of metaheuristics for this class of problems through experiments [10,11]; Luo et al. [12] recently solved a multi-skill variant with flexible resource profiles using a hybrid multi-objective metaheuristic validated by orthogonal parameter design and statistical testing. However, the standard MRCPSP captures only the coupling at the resource and duration levels and does not incorporate equipment-level spatial constraints such as path occupancy, obstacle detours, and collision avoidance. For uncertain operation durations, existing studies have proceeded along two lines, namely surveys of scheduling under uncertainty [13] and robust optimization approaches [14], but neither approach simultaneously covers equipment-level spatiotemporal feasibility. Therefore, this paper models airport pavement repair scheduling as an MRCPSP extension with time-space constraints, focusing on the generation and optimization of static repair operation plans.
In airport operation scheduling, methods combining constraint programming (CP) with simulation have been validated for robust apron operation scheduling. Gök et al. handled the multi-resource coupling and uncertainty in airport apron operations with a CP framework [15]. Wang et al. performed tracking, collision detection, and scheduling optimization for airport ground support equipment [16]. Padron et al. scheduled airport ground support vehicles with a bi-objective approach [17]. Shone et al. proposed a simheuristic approach for stochastic runway sequencing [18], and Hancerliogullari et al. studied mathematical models and heuristic algorithms for runway rescheduling [19]. For post-disaster recovery scenarios, Li and Teo established multi-level programming models for post-disaster road network repair and relief logistics [20]; Liu et al. [21] formulated an RCPSP-based emergency repair scheduling model for road networks using constraint programming and an explicit rescheduling feature. Their idea of coupling repair scheduling with logistics support is similar to the two-level structure of this paper, which couples scheduling with execution verification. For airport repair scenarios, Dong et al. established a resource allocation model for multi-zone and multi-process airport pavement repair based on polychromatic sets theory [22], but focused on the resource allocation level without addressing the operation sequencing and equipment-level spatiotemporal execution. In the direction of path computation for repair equipment, Li et al. studied symmetry reasoning and conflict coordination in multi-agent path finding, and Shen et al. further generalized it to forms of symmetry reasoning beyond the pairwise level [23,24]. These studies provide a theoretical basis for the multi-equipment path conflict analysis in the execution layer of this paper. Wang et al. employed an improved A* algorithm for robot path planning, and its grid-based environment and bidirectional JPS strategy provide a methodological reference for equipment detour path computation in this paper [25]. Unlike the approach in [21], which schedules road-network repair with an explicit rescheduling feature, this paper targets airside pavement repair under evolving obstacles and transfer-path occupancy and closes the planning–execution loop with simulation feedback; these structural differences—modeling scope, transfer-path occupancy, obstacle evolution, and the execution-feedback layer—define the distinct contribution of this work.
In the air transport management literature, optimization-based decision support is well established, ranging from arrival synchronization and flow management [26] to aircraft ground-time schedule recovery under uncertain arrival times, itself built on resource-constrained project scheduling [27]. It extends to facility reassignment under graded closure severity [28] and to construction-phasing plans that minimize operational disruption during airport expansion [1]. A recent systematic review of airport ground operations optimization further identifies adaptability to uncertainty and disruptions, together with the integration of subdomains, among its key research directions [29]. Decision-support systems have been reported for airport pavement maintenance management [30] and for numerical damage assessment of runway pavements [31]. To the best of our knowledge, however, no optimization approach in the airside emergency-response literature has been reported for emergency repair scheduling of airfield pavements themselves, that is, for scheduling multiple damage spots, multiple repair processes, and equipment-level spatiotemporal execution to minimize repair-completion time. The closest CP-based formulation [21] addresses road-network repair under a different problem structure. In the broader infrastructure restoration literature, recovery scheduling is dominated by network-level objectives such as accessibility or resilience trajectories [32,33], with restoration-completion (makespan-type) objectives adopted in robust post-disaster route restoration [34]. None of these models resolves the equipment-level spatiotemporal execution of the repair activities themselves.
The above methods differ in emphasis between solution speed and plan quality. CP and metaheuristic methods can produce schedules under computational time limits, but short runs alone do not establish global optimality or verify all execution-level constraints. Decomposition methods can offer finite-convergence and optimality guarantees when their cuts are globally valid. Logic-based Benders decomposition (LBBD) provides a framework for this kind of coupled optimization, in which the master problem determines the plan and the subproblem verifies its quality; the master-subproblem iteration is a classical method for mixed-integer programming [35]. Hooker and Ottosson extended the Benders idea to the case where the subproblem is an arbitrary decidable problem and laid the theoretical foundation of LBBD [36]. They proved that when the Benders cuts generated by the subproblem are globally valid, the algorithm converges to the global optimum within a finite number of steps. Hooker applied LBBD to planning and scheduling problems and gave the decomposition paradigm of master-problem decision and subproblem verification [37]. He further pointed out that the convergence speed of pure LBBD can be limited when closed-form expressions are difficult to write for the subproblems [38]. This limitation motivates the use of simulation feedback in this study. When spatiotemporal constraints such as equipment travel and path conflicts make closed-form subproblems difficult to formulate, constructing strictly globally valid Benders cuts can be challenging, and pure LBBD may be computationally demanding under the short response budgets considered here. The reviewed work does not provide a single framework for multi-zone, multi-process pavement repair that integrates operation sequencing with equipment-level spatiotemporal execution.
More broadly, disruption recovery and operational resilience have also been investigated in supply chain management, particularly in relation to organizational capabilities, resource reallocation, and resilient network design [39,40]. Although these studies address supply chain systems rather than airport pavement maintenance, they provide a broader perspective on resource coordination and recovery under disruptive conditions, which motivates the resource-oriented formulation adopted in this paper.
Despite these advances, three gaps remain. First, the airport-pavement studies reviewed above concentrate on damage assessment and maintenance management; they do not jointly formulate multi-spot, multi-process emergency repair with equipment-level spatiotemporal execution as an optimization problem. Second, the closest CP-based emergency repair formulation [21] addresses road networks and does not model evolving airside obstacles, transfer-path occupancy, or simulation-based execution feedback. Third, exact decomposition methods require globally valid subproblem cuts and can be computationally demanding under short response budgets; the LBBD-style configuration and small-instance long runs in this study illustrate the tension between computation time and the quality of available bounds. These gaps motivate a framework that couples CP-based planning with execution-layer simulation feedback while retaining the guarded analytic cuts as its lower-bound component.
Based on the above analysis, this paper constructs an MRCPSP model with time-space constraints and proposes a Constraint Programming–Simulation Collaborative Framework (CSC-SF). CSC-SF performs global search with the CP-SAT solver [41] at the planning layer and verifies equipment travel and path conflicts through spatiotemporal simulation at the execution layer. In the D90 finite-budget implementation, guarded analytic lower-bound inequalities and simulation-guided local repair support the iterative search; an optional assumption-dependent assignment restriction is confined to the separate 4 h LBBD reference configuration. The simheuristic paradigm combining simulation with metaheuristics has been developed in stochastic combinatorial optimization [42]. Constraint-based feedback from simulation to planning has likewise been applied in airport apron operations [15], and CSC-SF follows this line in spirit. Its execution layer, however, is a deterministic spatiotemporal replay rather than a stochastic simulator, so the feedback derives from feasibility and conflict verification rather than statistical estimation.
The contributions of this paper are threefold. (1) At the model level, the MRCPSP is extended into a two-level model with time-space constraints. (2) At the algorithm level, CSC-SF combines two guarded analytic lower-bound families with simulation-guided feedback, and configuration-level ablations quantify the observed effects of B-type and C-type feedback. (3) At the experimental level, a two-level test set D90/C20 is constructed and a rigorous statistical protocol is adopted, consisting of the Friedman test, Wilcoxon–Holm correction, global Holm correction, and Monte Carlo power analysis. On three small instances, independently optimized planning-relaxation bounds provide a separate a posteriori assessment of solution quality. At the application level, these results are translated into repair-schedule visualization and resource-provisioning decision support for disrupted airport pavement operations.
The remainder of this paper is organized as follows. Section 2 constructs the two-level scheduling model with time-space constraints. Section 3 designs the CSC-SF algorithm and discusses the validity conditions and stopping behavior of B-type feedback. Section 4 completes the static algorithm comparison, ablation analysis, and small-instance reference checks. Section 5 presents the engineering application. Section 6 concludes the paper and outlines future research directions.

2. Model Formulation for Repair Scheduling

2.1. Problem Description and Basic Assumptions

The scenario studied in this paper involves repair scheduling for pavement damage within the work area. The following conditions are assumed: the minimum usable runway segment has been designated, the work zone has been secured and cleared, and the damage locations and geometric information are known. Damage spot repair on airport pavements is not a single task but consists of several operations with precedence relations, including access route opening and debris removal, repair scope determination, pavement cutting, base course backfilling, and surface repair. The differences among repair processes are mainly reflected in base course backfilling and surface repair.
The research objective of this paper is to jointly determine the process mode of each damage spot, the repair crew assignment, the resource group configuration, the operation sequencing, and the equipment execution process. These decisions are made with limited repair crew and equipment resources and under spatial passage constraints on equipment travel, so as to complete the repair of all damage spots in the shortest possible time. Throughout this paper, the optimized quantity is the repair makespan, defined as the completion time of all modeled repair operations, including the associated equipment withdrawal activities represented in the execution-layer simulation. This quantity represents the repair-controlled component of pavement recovery rather than the actual time required for operational reopening. Post-repair curing, inspection, and operational authorization are not included in the optimization objective; their relationship to reopening time is clarified in Remark 2 of Section 5.2. The present study considers the completion of all repair work within the designated work area, while phased reopening of the minimum operable airside area remains a direction for future research, as discussed in Section 6.
To highlight the core scheduling conflicts in airport repair, this paper focuses on the initial static scheduling case and makes the following assumptions:
(1)
Each repair crew owns a fixed equipment pool with identical composition and identical quantities, and the pools are independent of one another. Equipment may be reused only within its own repair crew and may not be borrowed across repair crews.
(2)
All equipment of each repair crew is assumed to depart from the same staging area.
(3)
At the start of the initial scheduling, the damage spots, the repair crew, and equipment configuration, the resource group composition, and the parameters of each process are all known. The scheduling model does not consider external disturbances such as newly added damage, weather changes, or equipment failures. In structural terms, the scheduling problem defined above extends the multi-mode resource-constrained project scheduling problem (MRCPSP) [7,8] with equipment release times, transfer-path occupancy, and evolving spatiotemporal obstacles.
This paper adopts a two-level modeling approach. The planning-layer master problem generates a system-wide schedule at the resource-group level by minimizing the modeled repair makespan. The execution-layer subproblem evaluates the schedule by simulating equipment-level travel, path conflicts, waiting, and withdrawal under the specified movement rules. The two layers are coordinated iteratively: the planning layer generates candidate schedules, and execution-layer feedback guides subsequent search. For the initial static scheduling problem, the execution layer checks modeled executability; it does not reproduce all physical or operational processes at an airport.

2.2. Damage Spot Classification and Process Mode Selection

Let u and v denote any two original damage spots. If the clear distance between their edges satisfies the following condition:
p u − p v 2 − d u + d v 2 < δ
then the two damage spots are regarded as the same continuous damage object. Here, pu and pv are the coordinates of the two damage spots, and du and dv are their diameters, respectively. δ is set to 0.61 m (2 ft), taken as a conservative representative spacing for safe access of compact repair equipment between adjacent damage spots; the merging practice itself, in which damage spots too close to be repaired separately are treated as one repair, follows U.S. expedient crater and spall repair practice [43], and the threshold is an adjustable scenario parameter of the model; this threshold delineates the extent of a contiguous damage cluster: damage spots whose damaged areas are within this distance are treated as one continuous damage object. Accordingly, the original damage spots can be divided into several connected components, and the processed damage spot set is denoted as O.
If object o ∈ O consists of only one original damage spot, it is regarded as a discrete object; otherwise, it is a continuous object. For a discrete object, its geometric shape is approximated by a circle, as shown in Figure 1; for a continuous object, its work area is approximated by the convex hull of the union of its member damage spots, and the area Ao, volume Vo, and repair-surface diameter Do of object o are further defined.
Figure 1. Example of damage spot classification.
Based on damage spot size and geometric shape, the set of allowed processes Ko for each damage spot is defined as
K o = { k ∈ K ∣ φ k o = 1 }
where φk(o) is the determination function of process k for damage spot o, as shown in Table 1. When damage spot o satisfies the implementation requirements of process k, φk(o) = 1; otherwise, φk(o) = 0.
Table 1. Damage spot classification and process mode selection.
Meanwhile, for any process k ∈ Ko, its operation set is fixed as S = {1,2,3,4,5}, s ∈ S, as shown in Figure 2. Operations 1 to 3 are common operations that all processes must execute, while Operations 4 and 5 vary with the specific process mode. For any operation s ∈ S, the set of candidate resource groups Rks for the operation is given in advance.
Figure 2. Process–operation–resource group–equipment relationship mapping.

2.3. Planning-Layer Master Problem

2.3.1. Decision Variables

y ok = 1 , crater   o   selects   process   k , 0 , otherwise ,   o ∈ O ,   k ∈ K o
z om = 1 , crater   o   is   assigned   to   repair   team   m , 0 , otherwise ,   o ∈ O ,   m ∈ M
x osmkr u = 1 , operation   s   of   crater   o   is   executed by   repair   team   m   using   resource   group   r under   process   k   w i t h   e x e c u t i o n   u n i t   u 0 , otherwise , o ∈ O ,   s ∈ S ,   m ∈ M ,   k ∈ K o ,   r ∈ R ks , u ∈ U m r

2.3.2. Consistency Constraints on Process, Repair Crew, and Execution Mode

Each damage spot selects exactly one process and is the responsibility of exactly one repair crew:
∑ k ∈ K o y ok = 1 ,   ∑ m ∈ M z om = 1 ,   ∀ o ∈ O
Each operation adopts exactly one execution mode:
∑ m ∈ M ∑ k ∈ K o ∑ r ∈ R ks ∑ u ∈ U mr x osmkru = 1 ,   ∀ o ∈ O ,   s ∈ S
The execution mode of each operation must remain consistent with the process selection and the repair crew assignment:
x osmkru ≤ y ok ;   x osmkru ≤ z om ,   ∀ o , s , m , k , r , u

2.3.3. Operation Duration Calculation and Precedence Constraints

Let poskr denote the processing time of operation s of damage spot o under process k executed by resource group r; the operation duration is calculated by the following formula:
p oskr = f ksr + α ksr q os
where fksr is the fixed preparation time, αksr is the time coefficient per unit workload, and qos is the workload corresponding to the operation, which can be calculated by perimeter, area, or volume. The specific time parameters take engineering empirical values.
Thus, the operation completion time satisfies the following condition:
C os = S os + ∑ m ∈ M ∑ k ∈ K o ∑ r ∈ R ks ∑ u ∈ U mr p oskr x osmkru ,   ∀ o ∈ O ,   s ∈ S
The operations of the same damage spot must satisfy the precedence constraints:
S o , s + 1 ≥ C os ,   ∀ o ∈ O ,   s = 1 , 2 , … , S − 1

2.3.4. Straight-Line Travel Constraints for Resource-Group Execution Units

The planning layer further considers the straight-line travel time of the same resource group when it successively executes different operations. Let doo′ denote the straight-line distance between the center points of damage spot o and damage spot o′, and let λr denote the travel speed of resource group r. Since a resource group is usually composed of multiple types of equipment, its speed takes the minimum traveling speed among the equipment required within the group. The straight-line travel time of resource group r is then:
τ oo ′ ru = d oo ′ λ r
To describe the execution sequence of two operations on the same resource-group execution unit, sequencing variables are defined as follows:
η os , o ′ s ′ mru = 1 , operation   o , s   is   executed   before   operation   o ′ , s ′   by   execution   unit   u   of   resource   group   r within   repair   team   m 0 , otherwise
For any two distinct operations assigned to the same repair crew, the same resource group, and the same execution unit, the sequencing constraints with straight-line travel time must be satisfied.
When operation (o,s) is executed before operation (o′,s′):
S o ′ s ′ ≥ C os + τ oo ′ ru − M 1 − η os , o ′ s ′ mru − M 2 − x osmkru − x o ′ s ′ mk ′ ru
When operation (o′,s′) is executed before operation (o,s):
S os ≥ C o ′ s ′ + τ o ′ o ru − M 1 − η o ′ s ′ , os mru − M 2 − x osmkru − x o ′ s ′ mk ′ ru
where M is a sufficiently large constant. Equations (14) and (15) indicate that the planned start time of the latter operation should be at least later than the sum of the completion time of the preceding operation and the straight-line travel time.

2.3.5. Personnel and Equipment-Type Capacity Constraints

Let E denote the set of equipment types, Bme the quantity of equipment of type e owned by repair crew m, and aekr the demand of resource group r for equipment of type e under process k. Then, for any repair crew at any time t, the concurrent demand for the same type of equipment cannot exceed the quantity owned within the team, i.e.,
∑ o ∈ O ∑ s ∈ S ∑ k ∈ K o ∑ r ∈ R ks ∑ u ∈ U mr a ekr x osmkru { S os ≤ t ≤ C os } ≤ B me ,   ∀ m ∈ M ,   e ∈ E
Let Nm denote the number of personnel of repair crew m, and nkr the number of personnel required by resource group r under process k; the personnel capacity constraint is
∑ o ∈ O ∑ s ∈ S ∑ k ∈ K o ∑ r ∈ R ks ∑ u ∈ U mr n kr x osmkru { S os ≤ t ≤ C os } ≤ N m ,   ∀ m ∈ M
In the CP-SAT implementation, Equations (16) and (17) are not realized by enumerating continuous time points. Instead, each operation is modeled as an optional interval variable, which is combined with the resource capacity constraints and the no-overlap constraint of the same execution unit. This ensures that the occupancy of each type of equipment and personnel at any time does not exceed the capacity within the repair crew.

2.3.6. Planning-Layer Objective Function

The planning-layer objective is to minimize the total duration:
min C max ,   C max ≥ C o , S ,   ∀ o ∈ O
Note that Cmax, the planned makespan, is characterized only at the resource-group level and already includes the straight-line travel time when the same resource group executes tasks consecutively, but it does not yet consider actual spatial constraints such as equipment detours around obstacles, path conflicts, and waiting and yielding.

2.4. Execution-Layer Spatiotemporal Simulation Verification Model

After the planning layer produces a schedule, its executability is evaluated through a deterministic spatiotemporal simulation of equipment movement under the specified obstacle and conflict rules. Throughout this paper, “simulation” refers to this deterministic replay for executability verification, not to Monte Carlo sampling of stochastic outcomes.

2.4.1. State Description and Environment Construction

For each equipment unit, its current state is recorded, and the damage spot center is assumed to be the target point for executing the operation. Considering equipment size, let the safety radius of each equipment type be ρe; the obstacle region that a damage spot forms for this equipment type is then:
P ~ o e = { x ∣ dist x , P o ≤ ρ e }
where Po is the geometric region of the damage spot; before the damage spot is fully repaired, its obstacle region always exists. The obstacle region applies to equipment that is not working at that damage spot: the equipment executing an operation at the spot, as well as its departure spot, is exempt from the corresponding obstacle regions during its own transfer.

2.4.2. Travel Time Calculation

Travel time is computed during the execution-layer simulation. When the equipment and personnel head for the next target point, it is first determined whether the straight-line path between the current position and the target point is blocked by obstacles; if not blocked, the equipment runs along the straight line; if blocked, a grid map between the equipment and the obstacles is constructed and the A* algorithm is used to solve for the travel path, as shown in Figure 3. Let d e * denote the obtained path length and λe the speed of equipment e. The path travel time is then calculated as:
τ e , os move = d e * λ e
Figure 3. Schematic diagram of transfer path.
When the straight-line segment is blocked, the transfer path is planned by a grid-based A* planner (with local and global search stages) around obstacle polygons buffered by equipment body radii, and the obstacle field evolves as repairs open damaged objects. Path plans are recomputed whenever the obstacle field changes, so that subsequent transfers use paths found on the updated grid under the modeled obstacle and corridor-occupancy constraints. These paths are not asserted to satisfy continuous-geometry vehicle kinematics.
However, merely ensuring that the equipment can detour around obstacles is not sufficient to avoid collisions during parallel multi-equipment scheduling. Li et al. proposed symmetry-breaking techniques for narrow corridor occupancy and head-on conflicts [23], and Shen et al. studied more general multi-agent spatial conflict problems from the perspective of going beyond pairwise reasoning [24]. Inspired by these works, this paper adopts a simplified conflict-resolution mechanism in the equipment spatiotemporal simulation, based on mutually exclusive path-occupancy time windows and the selection of the better of waiting and detouring. Movement is therefore conflict-free under the adopted discrete path-occupancy semantics rather than under a full geometric collision check, and personnel transfers are treated at the aggregate crew level.
The path obtained by the A* algorithm is discretized into an ordered set of line segments consisting of adjacent nodes, i.e.,
P eg = { p 0 , p 1 , p 1 , p 2 , … , p G − 1 , p G }
Let W denote the length along the (pw,pw+1)-th path lw; the time required for equipment e to traverse this path is:
t w = l w v e
If the planned departure time of equipment e is t e dep , its expected occupancy time on path (pw,pw+1) can be written as explained below.
When multiple equipment units travel in parallel, if the occupancy times of two equipment units on the same path overlap, i.e.,
I e , w = t e dep + ∑ k = 0 w − 1 t k ,   t e dep + ∑ k = 0 w t k
I e , w ∩ I e ′ , w ≠ ⌀
then, for a path segment already occupied by other equipment, subsequent equipment must not enter it simultaneously. In this case, the two alternatives of waiting with delayed departure and replanning the path are compared, and the one that reaches the next destination fastest is selected. Here, the waiting time qe incurred by equipment e due to the conflict can be computed; if waiting is chosen, its actual departure time is corrected to:
t ^ e dep = t e dep + q e

2.4.3. Recovery of Simulated Times

The real start and completion times are affected by multiple factors:
An operation can start only after all equipment and personnel in its required resource group have arrived at the work position.
Equipment may be affected by road occupancy during travel.
After an operation is finished, the related equipment and personnel still need to withdraw from the damage spot before the next operation can be performed. The simulated clearance time of an operation is defined as:
C ^ os = max r ∈ R ks E r , os exit
where E r , os exit is the withdrawal completion time of resource group r for this operation.
The simulated start time of an operation is defined as:
S ^ os = max S os , C ^ o , s − 1 , max r ∈ R os A r , os
where Ar,os denotes the time at which resource group r arrives at the position of this operation.
A damage spot is considered truly open and is no longer treated as an obstacle if and only if its last operation is completed and all related equipment and personnel have withdrawn. The opening time of o is defined as T o open , and the simulated makespan of the problem is then
C ^ max = max o ∈ O T o open

3. Solution Algorithm

To handle the complex constraints involved in emergency airside pavement repair scheduling, this study develops a constraint programming–simulation collaborative framework (CSC-SF). CSC-SF generates candidate schedules at the planning layer with CP-SAT and verifies their executability through spatiotemporal simulation at the execution layer. In the finite-budget CSC-SF experiments, B-type feedback consists of two guarded analytic lower-bound cut families, with bounded exact no-good diversification in the iterative CP search; C-type feedback supplies simulation-guided local repair. A separate long-run LBBD reference configuration also uses an assumption-dependent simulation-based assignment restriction, which is discussed in Section 3.2 but is not part of the D90 finite-budget CSC-SF implementation.
With C-type feedback disabled, the implemented finite-budget CSC-SF stage loop reduces to the CP-LC ablation: its B-type component comprises two guarded analytic cut families and bounded exact no-good diversification, without the assignment-level simulation cut. CP-LC is an LBBD-style internal CP variant rather than a separately implemented external LBBD comparator or an unconditional exact algorithm. Assumption A1, discussed below, governs an optional assignment-level cut in the separate long-run reference configuration; it is unproved and does not affect the D90 finite-budget CSC-SF and CP-LC runs. The full CSC-SF uses C-type heuristic feedback to improve simulation-evaluated schedules under a finite wall-clock budget and is evaluated as a simulation-guided matheuristic.

3.1. Solving the CP-SAT Master Problem

Constraint programming continuously performs constraint propagation over variable domains, thereby progressively shrinking the search space. The modeling and solving capabilities of constraint-based scheduling techniques have been established [44]. Constraint scheduling solvers such as CP Optimizer have been widely applied in industrial scheduling [45]. The combination of constraint programming with constructive heuristics has been validated on parallel machine scheduling with sequence-dependent setups and shared resources [46]. For the emergency repair scheduling problem, this study employs the constraint programming solver CP-SAT [41] to further handle the coupling of multiple constraints such as operation precedence, process mode selection, and resource capacity limits.
At the planning layer, under the constraints of the master problem, the constraint programming model makes three decisions: the repair crew, the process type, and the resource group. The generated schedule is shown in Figure 4.
Figure 4. Example of the scheduling scheme.
In this schedule, damage spot 2 serves as an example: it is repaired using process 1, with resource groups 1, 3, and 5 employed in sequence under the responsibility of repair crew 1. The schedule sequence from left to right indicates the execution order of the operations.

3.2. B-Type Feedback: Analytic Lower Bounds and an Optional Assignment Restriction

The implemented finite-budget CSC-SF and CP-LC stage loops feed back two analytically motivated, conditionally activated lower-bound cut families [35,37]: resource workload lower bounds and ordered execution-unit lower bounds. A bounded exact no-good pool also diversifies successive CP-SAT searches but does not itself establish an optimality certificate. A separate 4 h LBBD reference configuration additionally uses a simulation-derived assignment-level restriction, whose validity is conditional on an unproved ordering-dominance assumption (A1); it is analyzed here for transparency but is not enabled in the finite-budget D90 main comparison or Table 9 ablations. This approach draws on logic-based Benders decomposition [36], while distinguishing guarded analytic inequalities from assumption-dependent restrictions. Related relaxation-based cuts have been used in planning and scheduling [47].
(1)
Resource workload lower-bound cut
The resource workload lower-bound cut characterizes the necessary working time under limited resources and prevents the planning layer from underestimating the makespan caused by resource contention.
Let F(me) denote the set of operation execution modes in the current candidate schedule that are performed by repair crew m and occupy equipment type e. Let i ∈ F(me), and let ωi denote the workload that these execution modes impose on equipment type e. The resource workload lower bound is then given by:
L me = ∑ i ∈ F me ω i B me
Correspondingly, if the planning layer again selects all execution modes in the set F(me), the following condition must be satisfied:
∑ i ∈ F me x i = F me ⇒ C max ≥ L me
This constraint can be interpreted in the algorithm as follows: if the next CP-SAT round assigns this group of operations to the same repair crew with the same equipment again, then the planning-layer makespan cannot be lower than Lme. An analogous capacity lower-bound constraint of the same form can be constructed for personnel resources.
(2)
Execution-unit lower-bound cut for the same resource group
The execution-unit lower-bound cut for the same resource group prevents the planning layer from underestimating the time required for continuous operation on the same execution unit. If multiple operations are assigned to the same resource group execution unit, they must be performed sequentially in a certain order.
Let p o j s j k j r j denote the processing time of the j-th operation on the execution unit, and let the minimum straight-line travel time of resource group r from damage spot oj to damage spot oj+1 be denoted analogously. The shortest-time lower bound corresponding to this execution chain is then given by:
L H = ∑ j = 1 n p o j s j k j r j + ∑ j = 1 n − 1 τ o j o j + 1 r
If the planning layer again retains this operation chain on the same execution unit together with its precedence order, the following condition must be satisfied:
C max ≥ L H
This constraint can be interpreted in the algorithm as follows: if the next CP-SAT round again assigns the same resource group execution unit to operate continuously in the original order, then the planning layer must regard this sequence as requiring a time of at least LH.
In the finite-budget implementation, the two analytic cut families are injected into CP-SAT with explicit activation guards. Each guarded constraint is enforced only when the relevant resource assignment or ordered execution chain is selected, using the OnlyEnforceIf conditional-constraint interface. The distinct assignment-level simulation restriction described next is used only by the separate long-run LBBD reference implementation; it is not the third B-type cut in the main D90/CP-LC stage-loop configurations.
(3)
Guarded simulation-based assignment cut
The optional simulation-based assignment restriction, used in the separate long-run LBBD reference variant and not in the D90 stage loop, feeds an execution-layer simulated makespan back to the planning-layer master problem. The simulation value of the evaluated ordering is a feasible execution value, not an unconditional lower bound on all reorderings of that assignment; the cut is therefore applied as an assumption-dependent search restriction rather than as an analytically established Benders optimality cut. For each candidate schedule evaluated by the execution-layer simulation, let the master-problem assignment σ be the value combination of all process, repair crew, and execution mode variables; the following conditional cut is then injected:
σ ⇒ C max ≥ C ^ max
When a subsequent planning solution repeats the implemented mode-key guard, the restriction sets its planned makespan no lower than the previously simulated value; when a guarded key differs, the cut is inactive. The 4 h reference variant also uses a bounded pool of exact no-good signatures to diversify candidate solutions. The execution-layer value comes from a fixed wait-versus-detour policy, with no separate optimization of conflict-resolution choices. Its applicability to other configurations satisfying the guard is examined below.
Scope of cut validity and stopping behavior:
(1)
The unstrengthened master problem is a relaxation of the modeled execution-evaluated scheduling problem. For any feasible simulated schedule that is representable within the master decision domains, a planning-layer counterpart can be constructed by preserving each operation’s selected mode and its implied processing duration, repair-crew assignment, resource-group assignment, execution-unit assignment, precedence relations, and within-unit operation order, and by setting the planning start times equal to the simulated operation start times. Because the simulated schedule already respects the modeled crew and resource capacities and operation precedence, the counterpart satisfies the corresponding master constraints. The planning-layer transfer time is calculated by dividing the straight-line distance by the minimum travel speed among the equipment required by the resource group. At least one required unit attains this minimum speed, and its feasible simulated path is no shorter than the straight-line distance; because the operation can start only after the required equipment has arrived, the corresponding simulated group-transfer duration is therefore no shorter than the planning-layer transfer time. Simulation-induced waiting and clearance delays are nonnegative. The counterpart consequently satisfies the planning-layer timing constraints and has a makespan no greater than that of the simulated schedule. Therefore, the optimum of the unstrengthened master problem is a lower bound on the minimum simulated makespan over the modeled domain. This argument depends on the stated planning-to-execution correspondence and does not validate the A1-dependent assignment restriction. The guarded analytic cut families preserve this lower-bound relation only when their activation guards impose the corresponding necessary resource-workload and ordered-chain conditions.
(2)
The two analytic cut families impose necessary resource-workload and ordered-chain lower bounds when their activation guards encode the corresponding resource demands and operation sequences. The simulation-based assignment restriction requires a stronger condition (A1): the evaluated execution makespan must be no greater than the makespan of every feasible alternative ordering and physical-equipment realization satisfying its guard. The implemented guard can preserve mode, crew, and resource-group keys without fixing physical equipment instances. Travel time depends on visiting order, device assignment, and feasible routes, even without obstacles, so the required dominance does not follow from the model. A1 remains unproved, and the restriction is used only as a heuristic in the long-run reference search.
A master-model lower bound can be used for a global optimality certificate only if all active strengthening cuts are globally valid for the objective being certified and the master problem is solved to the required exactness. These conditions have not been demonstrated for the present assignment-level simulation cut, and a finite wall-clock stopping rule does not imply that lower and upper bounds meet. The reported study therefore makes no claim of unconditional finite-time convergence to a global optimum.
Remark 1
(conditional interpretation of the long-run assignment restriction). Only if the evaluated simulated makespan is no larger than the value of every other feasible ordering and physical-equipment realization matching the implemented guard can it serve as a valid lower bound for all schedules for which that guard activates the cut. This is stronger than dominance over alternative orderings under one fully specified equipment realization. No such ordering-and-equipment dominance condition has been proved for the present model. Even if it held, only globally valid remaining cuts, an exactly solved master relaxation, and complete search could support an original-problem optimality certificate. The observed solver gaps and the time-limited CSC-SF results are not presented as such certificates.
The pseudocode is as follows (Algorithm 1):
Algorithm 1: Logical lower-bound cut generation
1 Input: Current CP-SAT solution Π, processing times p, transfer lower bounds τ, resource capacities B, incumbent upper bound UB.
2 Output: Logic lower-bound cut set CB.
3 Initialize CB ← ∅.
4 Extract selected task modes and planned orders from Π.
5 Build resource workload groups F from selected task modes.
6 for each F do
7 Calculate the resource workload lower bound Lme.
8 if Lme is valid then
9 Generate a certificate-valid workload cut.
10 Add the cut to CB.
11 end if
12 end for
13 Build same-unit ordered chains H from Π.
14 for each H do
15 Calculate the same-unit chain lower bound LH.
16 if LH is valid then
17 Generate a certificate-valid chain cut.
18 Add the cut to CB.
19 end if
20 end for
21 Remove duplicated and weak cuts from CB.
22 for each cut in CB do
23 if its lower bound is not smaller than UB then
24 Mark it as a pruning cut.
25 end if
26 end for
27 Return CB.

3.3. Simulation-Guided Heuristic Repair

In the finite-budget experiments, B-type feedback consists of the two guarded analytic lower-bound families, alongside bounded exact no-good diversification in the iterative CP search. The separately investigated assignment-level simulation restriction remains A1-dependent and is not enabled in this stage-loop configuration. The spatiotemporal execution simulation identifies delays induced by space-time constraints and local structures responsible for the deterioration of simulated makespan. The effectiveness of this C-type feedback depends on path selections, equipment release times, and obstacle states; it guides heuristic repair rather than creating an additional unconditional optimality cut. This use of simulation feedback follows the simheuristic paradigm [42].
For any operation (o,s), its start delay is defined as follows:
δ os = max { 0 , S ^ os − S os }
If δos > 0, the operation may be affected by various delays. A group of mutually related delayed objects in the execution-layer simulation is denoted as a local structure h. For example, if an operation starts late because of equipment waiting and several subsequent operations on the same execution unit are postponed in turn, then these operations together with their associated waiting relations jointly constitute a local structure.
The delayed operations contained in local structure h are enumerated in sequence as follows:
o 1 , s 1 , o 2 , s 2 , … , o n , s n
The feedback intensity of the local structure is then defined as:
Γ h = δ o 1 s 1 + δ o 2 s 2 + ⋯ + δ o n s n
Equation (36) represents the cumulative value of all related delays within local structure h; the larger this value, the more pronounced the influence of the local structure on the actual execution performance of the current plan. When there are many feedback items, several local structures with higher priority can be selected into the feedback pool in descending order of this value, thereby avoiding an excessively large repair scope. This feedback form is not used to directly exclude any class of schedules; rather, it guides the subsequent heuristic repair.
The algorithm first adjusts the schedules of the related operations around these local structures and locally rearranges the travel relations with evident path waiting. The newly repaired schedule is denoted Π′ and must again enter the execution-layer simulation. If its simulation-based makespan outperforms the existing upper bound, the current upper bound is updated:
UB ← min { UB , C ^ Π ′ }
This study treats it merely as a simulation-derived heuristic feedback used to guide the repair search, generate candidate schedules, and improve the upper bound. The pseudocode is as follows (Algorithm 2):
Algorithm 2: Simulation-derived heuristic feedback generation
1 Input: Current CP-SAT solution Π and the execution-layer simulation results.
2 Output: Heuristic feedback set Ωh.
3 Initialize Ωh ← ∅.
4 Calculate the start delay δos of each task from the simulation result.
5 if all δos are equal to zero then
6 Return Ωh.
7 end if
8 Identify delayed tasks, waiting events, path conflicts, and delay propagation relations.
9 Build local delayed structures h.
10 for each h do
11 Calculate the feedback strength Γh.
12 if Γh is greater than zero then
13 Add h to Ωh.
14 end if
15 end for
16 Sort Ωh by Γh in descending order.
17 Keep the most important feedback records in Ωh.
18 Return Ωh.

3.4. Algorithm Procedure

The finite-budget CSC-SF algorithm combines guarded B-type analytic lower bounds and simulation-guided C-type repair within an iterative CP-SAT stage loop. A bounded exact no-good pool supports search diversification. The separate A1-dependent assignment restriction is not added to this finite-budget algorithm. The steps below describe the actual stage-loop configuration used for the D90 comparisons.
The steps of the algorithm are as follows:
(1)
Initialization
Analyze the geometric features of the damaged pavement and complete the clustering of continuous damage spots, select the candidate process modes of each damage spot, and simultaneously construct the grid environment for spatial path search and the equipment pools.
(2)
Generate the planning-layer candidate schedule
Map the variables and constraints of the repair operations into the logical semantics of CP-SAT and use the solver to conduct a global search to obtain the initial schedule. If the current constraints are infeasible, the algorithm terminates.
(3)
Execution-layer simulation evaluation
Input the schedule into the execution-layer simulation model to restore the real spatiotemporal constraints and obtain the simulation-based makespan.
(4)
Update the feedback information
Generate new logic-based lower-bound cuts according to the current schedule and update the cut set. Extract new heuristic feedback from the execution-layer simulation results and update the heuristic feedback set.
(5)
Perform local repair search
Select the local structures to be repaired preferentially according to Ωh, adjust the repair crews, execution units, or local operation sequences to obtain a repaired candidate schedule, simulate this candidate again, and determine whether the upper bound should be updated.
(6)
Evaluate the termination condition
After each evaluated CP-SAT candidate, the algorithm updates the guarded analytic cuts and heuristic feedback, then performs a local repair search (Algorithm 3, lines 27–35). If the CP-SAT sub-budget returns no new feasible incumbent (INFEASIBLE or UNKNOWN), a fallback repair is invoked using the latest feedback information (Algorithm 3, lines 17–19). The loop continues until the wall-clock budget T is exhausted.
The flowchart of the algorithm is shown in Figure 5.
Figure 5. Flowchart of the CSC-SF algorithm.
The pseudocode is as follows:
Algorithm 3: Overall CSC-SF algorithm
1 Input: O, S, K, M, R, U, B, p, τ, and time budget T.
2 Output: Current best simulation-validated feasible schedule Π and incumbent upper bound UB.
3 Initialize C_B ← ∅, Ω_h ← ∅, N ← ∅, and UB ← +∞.
4 Preprocess damage objects, candidate modes, resource groups, equipment pools, and path environment.
5 Generate an initial CP-SAT solution Π.
6 if no feasible Π is found then
7 Stop and report the solver status (INFEASIBLE or UNKNOWN).
8 end if
9 Run   the   execution - layer   simulation   for   Π ,   obtaining   true   makespan   C ^ max
10 In the D90 finite-budget stage loop, do not generate an assignment-level simulation cut.
11 Record the initial simulated candidate and add its complete assignment-and-ordering signature to N when applicable.
12 Update   UB   with   C ^ max and record Π as the best schedule.
13 Run Algorithm 2 for Π and obtain Ωh.
14 Run Algorithm 1 for Π and update CB.
15 while the time budget T is not exhausted do
16 Solve the CP-SAT master problem with C_B and N.
17 if no feasible candidate Π is found then
18 Use Ωh to guide local repair.
19 end if
20 Run   the   execution - layer   simulation   for   the   current   Π ,   obtaining   true   makespan   C ^ max .
21 Record the simulated candidate and update N with its complete assignment-and-ordering signature when applicable.
22 Retain the guarded analytic B-type cuts; do not add an assignment-level simulation lower bound.
23 Run Algorithm 2 for the current Π and obtain new Ωh.
24 if   C ^ max is smaller than UB then
25 Update   UB   with   C ^ max and record the current Π as the best schedule.
26 end if
27 Run Algorithm 1 for the current Π and update CB.
28 Select priority local structures from Ωh.
29 Generate a repaired schedule Π′.
30 Run   the   execution - layer   simulation   for   Π ′ ,   obtaining   true   makespan   C ^ max .
31 Update simulation-based delay feedback for the repaired candidate (C-type).
32 Do not create an assignment-level simulation cut for this repaired candidate.
33 if   C ^ max is smaller than UB then
34 Update   UB   with   C ^ max Π ′ and record Π′ as the best schedule.
35 end if
36 end while
37 Return the Π and UB.

4. Computational Experiments

4.1. Experimental Design

4.1.1. Two-Tier Test Set

To accommodate both large-scale benchmark comparison and fair parameter tuning, this study adopts the construction principle of “base scenarios plus controlled transformations” that is commonly used in benchmark suite design [48]. A two-tier test set is accordingly built, comprising a static benchmark set D90 and a calibration set C20.
D90 comprises 90 static benchmark instances. Following the severity-graded scenario design common in disruption studies [28], the base instances A1–A9 are classified into light, moderate, and severe disruption tiers, and their damage spot compositions differ markedly, as shown in Table 2. The damage classification and its geometric parameters are anchored in published airport pavement repair practice. Full-scale damage geometries, together with the contrast between cast-in-place rapid-hardening and prefabricated repair processes, are documented in field and numerical tests [31]. Airport-wide rehabilitation projects confirm closure duration as the core operational metric of pavement repair decisions [49], and damage assessment and condition rating provide the upstream input to such decisions [50]. The operation-time parameters themselves remain engineering empirical values, as declared in Section 6.
Table 2. Case settings of base instances A1–A9.
Building on the base instances, size-and-position variants (B1–B21) are defined to capture the effects of damage spot size and spatial location. Starting from seven base scenarios (A2, A3, A5, A6, A7, A8, and A9), the damage spot diameter, depth, and coordinate spacing of each scenario are scaled up synchronously to 1.2, 1.4, and 1.6 times their original sizes, with one variant per scaling factor. This scaling yields three variants per scenario and 21 variants in total over the seven base scenarios. These variants are used to test the stability of the algorithms under changes in the spatial layout. Because these 21 variants are deterministic rescalings of their seven parent scenarios, the 90 evaluation instances are not fully independent, and the significance results are accordingly read as comparisons over the generated instance family rather than over independent draws.
Resource competition exerts a considerable influence on the final makespan during scheduling. To capture this factor, resource-competition variants (C1–C60) are constructed in addition to the size-and-position variants. In each instance, the number of repair crews is drawn at random with equal probability from 2 or 3, and the numbers of large, medium, and small damage spots are drawn at random in tiers defined by the planned resource-competition ratio.
Large and medium damage spots can be repaired only by process 2 or process 4, both of which require the R7 and R8 resource groups, and each repair crew is equipped with only one set of each; these damage spots must therefore be repaired serially. The resource-competition ratio RT is defined as the sum of the numbers of large and medium damage spots divided by the number of repair crews, and reflects the average number of damage spots that each repair crew must repair serially. Competition-intensity tiers are defined according to this ratio, and 60 instances are generated at random, as shown in Table 3.
Table 3. Scenario settings of instances C1–C60.

4.1.2. Compared Algorithms and Budget Settings

Four efficient metaheuristics are selected for comparison: ALNS-VND, Memetic/GA + LS, GVNS, and matheuristic. These methods have been extensively validated in airport ground operation scheduling, integrated runway scheduling, and dynamic resource allocation. They are selected as representative neighborhood-, population-, and matheuristic-based baselines belonging to standard metaheuristic families for resource-constrained scheduling [9,11,51,52], and all five algorithms share the same hard wall-clock budget, single-thread configuration, per-run seeds, and simulation-based evaluation protocol, so that the comparison isolates the search strategy itself. In addition, CP- and LBBD-family behavior is examined internally: the ablation configuration CP-LC isolates the LBBD-style iteration, and the 4 h long-run reference solutions are produced by the LBBD configuration, which together quantify the decomposition-based branch within the tested budgets.
ALNS-VND builds on the adaptive large neighborhood search framework established by Ropke and Pisinger for the pickup and delivery problem with time windows [53]. Graf combined this framework with variable neighborhood descent for the multi-period vehicle and technician routing problem [54]. GVNS is grounded in the variable neighborhood search principles systematically formulated by Hansen and Mladenović [55], and Dahite et al. applied it to joint maintenance scheduling and personnel routing [56]. Matheuristic follows the solution paradigm that combines mathematical programming with heuristic search: Vanhoucke and Coelho used it to solve the RCPSP [51], and Ball provided a systematic survey of this paradigm [57]. Memetic/GA + LS adopts the population-search-with-local-improvement design of Rahman et al. for the RCPSP [52].
For a common evaluation, the four external comparator families are represented by implementations adapted to the same scheduling objective; exact equivalence to separate reference-code implementations has not been established. All of them are implemented in a unified Python/OR-Tools framework, following the unified-implementation practice of earlier airport ground operations studies [17]. All algorithms are tuned uniformly on the calibration set C20, which consists of the 20 C-series instances C2, C4, C6, C8, C9, C11–C14, C16, C17, C19, and C21–C24, C26–C29 (12 drawn from the low-competition tier and 8 from the medium-competition tier, none from the high-competition tier; this subset is distinct from the C1–C20 tier boundary in Table 3), and the calibrated parameters are applied directly to the D90 experiments without further adjustment. The final makespans of all algorithms are evaluated by the same execution-layer simulation, and the compared algorithms do not use the B-type or C-type feedback. As a robustness check, C20 is removed from the evaluation set: CSC-SF still attains the lowest mean makespan of 204.75 min on the remaining 70 instances, the Friedman test still rejects the hypothesis of no differences, and CSC-SF achieves the best or tied-best result on 63 of the 70 instances. The main conclusions therefore do not depend on the calibration instances. The Friedman test at the tuning stage is reported in Table 4: CSC-SF has the best mean rank, and the ranking of the algorithms is consistent with the D90 main experiment.
Table 4. Friedman test on the calibration set C20.
All experiments were conducted in the same computing environment: Intel Core i7-12700H CPU, 16 GB RAM, Windows 11 64-bit, Python 3.12, and OR-Tools 9.15. Each instance is solved repeatedly under 10 fixed random seeds (20260101–20260110). All CP-SAT solves and all four compared algorithms run single-threaded, and all five algorithms use the same execution-layer simulation as their search-time objective and acceptance criterion. Results are first aggregated within seeds per instance, and the cross-instance tests at the instance level (n = 90) form the primary statistical evidence; the 900 instance-seed paired observations are retained only as a secondary sensitivity analysis, and the ablation effect tests in Section 4.3 are reported at the instance level. In line with the operational requirement to produce an executable repair schedule within minutes rather than hours, the time budget is set according to the disruption tier: 40 s for light damage, 80 s for moderate damage, and 120 s for severe damage. The B series inherits the tier of its base scenario, and the C series takes 80 s or 120 s depending on the number of repair crews. The proposed algorithm is denoted CSC-SF. No public repository for the instance generator or full computational records is identified in this revision. The instance-generation settings, input instances, and underlying experimental records should be requested from the corresponding author, as stated in the Data Availability Statement.

4.1.3. Statistical Protocol

To control the family-wise error rate across the multiple comparisons, the following statistical testing scheme is used for the reported results; external preregistration is not asserted.
H1 
(static algorithm comparison). The Friedman test [58] combined with the Iman–Davenport correction [59] is used to assess the overall differences among the five algorithms. Pairwise comparisons are conducted with CSC-SF as the reference using the Wilcoxon signed-rank test [60] (one-sided, with the directional hypothesis that CSC-SF is superior) combined with the Holm correction [61], and the paired rank-biserial correlation is reported as the effect size (within the broader nonparametric effect-size framework of [62]).
H2 
(ablation analysis). A 2 × 2 factorial design with two-sided Wilcoxon signed-rank tests is used to examine the LC main effect, the SF main effect, and the LC × SF interaction effect.
After all of the above tests are completed, the four comparisons of H1 and the three effects of H2 are merged into a single family of seven tests for a global Holm correction. A Monte Carlo power analysis then assesses the adequacy of the sample size.

4.2. Static Algorithm Comparison

On the 90 instances of D90, CSC-SF attains the lowest mean makespan of 195.45 min among the five algorithms (Matheuristic 227.82, GVNS 228.16, Memetic/GA + LS 229.72, and ALNS-VND 232.36) and obtains the best or tied-best solution on 82 of the 90 instances, as shown in Table 5. The no-feedback CP-SAT variant (BASE, 226.00 min in Table 9) already attains a lower mean than the four metaheuristics, which is consistent with the strength of modern CP-SAT solvers on tightly constrained scheduling problems. The four metaheuristics therefore serve as representatives of prevalent scheduling practice rather than as the yardstick of solver capability, and the net contribution of the proposed feedback mechanisms amounts to a further mean reduction of 30.54 min over BASE (Section 4.3).
Table 5. Mean makespan and Friedman ranks of the algorithms on D90.
Under light damage (A1–A3), the five algorithms perform fairly closely, yet CSC-SF remains the best, as shown in Table 6. This indicates that all algorithms can obtain high-quality solutions on small-scale instances. The gaps widen under the moderate (A4–A6) and severe (A7–A9) scenarios, reaching 12.31 min and 14.25 min relative to the best-performing compared algorithm at the tier level (the Matheuristic and the GVNS, respectively). As the number of damage spots grows and multi-team parallel operation intensifies, the coupling among resource occupancy, operation sequencing, and equipment travel becomes more pronounced, and the advantage of CSC-SF expands further.
Table 6. Per-instance and grouped mean makespans on D90.
The performance profiles in Figure 6 further supplement these results. The curve of CSC-SF rises steeply at the far left, which indicates that it is at or very close to the within-instance best on the vast majority of instances. The four compared algorithms require much larger gap ratios to cover the same proportion of instances, consistent with the makespan gaps in Table 5.
Figure 6. Performance profiles of the five algorithms on D90.
The Friedman test rejects the null hypothesis that the five algorithms do not differ (χ2 = 199.58, p = 4.62 × 10−42; Iman–Davenport F = 110.73, Table 7). The mean rank of CSC-SF is 1.333 and its median rank is 1.0. Its lead thus spans all instance groups rather than being driven by a few scenarios.
Table 7. Friedman test results.
Table 8 reports the results of the Wilcoxon signed-rank tests with the Holm correction using CSC-SF as the reference. The paired mean differences of CSC-SF against ALNS-VND, Memetic/GA + LS, GVNS, and Matheuristic are 36.91, 34.27, 32.70, and 32.37 min, respectively, with rank-biserial effect sizes of 0.987 to 1.000; all comparisons are significant after the Holm correction. Against ALNS-VND, the record is 80 wins, 10 ties, and 0 losses, where ties correspond to zero differences and are excluded from the signed ranks. Against GVNS, Matheuristic, and Memetic/GA + LS, CSC-SF loses on only 6, 3, and 5 instances, respectively.
Table 8. Paired Wilcoxon signed-rank tests with Holm correction.
The critical difference (CD) diagram in Figure 7 (CD = 0.643) further shows that the mean-rank differences between CSC-SF and the other four algorithms (the smallest being 1.33) all far exceed the Nemenyi critical difference. Among the four compared algorithms, the differences between GVNS and Memetic/GA + LS (rank difference 0.61) and between Memetic/GA + LS and Matheuristic (rank difference 0.04) are not significant. The rank difference between GVNS and Matheuristic (0.65 versus a critical difference of 0.643) exceeds the threshold by a narrow margin (Nemenyi-corrected p = 0.046, borderline significance). The four compared algorithms thus occupy a relatively narrow band of mean ranks, whereas CSC-SF is separated from every comparator by a much larger margin. Matheuristic attains the second-best mean makespan (227.82 min) yet only the fourth mean Friedman rank (3.317), reflecting that Friedman ranks aggregate per-instance orderings whereas means aggregate magnitudes. The Wilcoxon–Holm results are therefore taken as the primary criterion, and the CD diagram serves as a visual supplement.
Figure 7. Critical difference diagram of the Friedman–Nemenyi test.
To further examine the influence of the time budget setting on the comparison conclusions, Figure 8 shows the evolution of the mean best-so-far makespan of each algorithm with solution time in the two budget groups T = 80 s and T = 120 s. Within each group, instances and seeds are paired and then averaged. Limited by the availability of trajectory records, the two groups cover 13 and 14 instances, respectively; the end-of-budget leads plotted in Figure 8 are therefore smaller than the corresponding full-set values reported in Section 4.2 and should not be read as population estimates. In the T = 80 s group, CSC-SF is essentially on a par with the best compared algorithm during the first 20 s (leading by about 0.3 min); after 40 s its advantage widens progressively, reaching a lead of 36.8 min at the end of the budget. In the T = 120 s group, CSC-SF trails the best compared algorithm by about 4 min between 20 s and 40 s, overtakes it from about 75 s onward, and leads by 15.3 min at 120 s.
Figure 8. Mean best-so-far makespan over time in the two budget groups.
In both groups, the lead of CSC-SF generally widens as the budget increases. The remaining improvement of the four compared algorithms after 20 s never exceeds 2.4 min, whereas the improvement of CSC-SF over the same period reaches 20.3 to 38.6 min. Across all 37 (80 s budget) and 44 (120 s budget) instances, the mean leads at the end of the budget are 44.5 min and 24.9 min, respectively. These values are consistent in direction with Figure 8 and larger in magnitude, indicating that the main comparison conclusions are not driven by the tight budget setting or by the composition of the trajectory subsets. Figure 8 is accordingly read as a descriptive illustration of the bound-evolution process rather than as a sampling-based estimate. This contrast is consistent with the typical anytime behavior differences between decomposition-with-feedback and pure metaheuristic search on multi-mode resource-constrained scheduling [11].

4.3. Ablation Experiments

The comparisons above show the empirical advantage of CSC-SF over the four implemented metaheuristic baselines. To investigate the contributions of its two feedback components, three internal CP configurations are compared with the full algorithm: CP-SAT (BASE, one planning-layer solve without iterative feedback), CP-LC (iterated stage loop with two guarded analytic B-type cut families but without C-type feedback), and CP-SF (iterated stage loop with C-type feedback but without B-type analytic cuts). The latter three configurations also employ bounded exact no-good diversification. None of these D90 configurations uses the A1-dependent assignment-level simulation cut. The ablations cover all 90 D90 instances with 10 seeds per instance. The reported 2 × 2 contrasts are useful descriptive configuration comparisons, but the one-shot BASE differs in search-loop architecture from the three iterative variants; thus the contrasts do not isolate component-only causal effects.
The full-algorithm row reuses the main-experiment runs in Section 4.2, whereas the other three configurations were run separately under the stated per-instance computation budgets; their returned schedules were evaluated by the same execution-layer simulator. The no-feedback CP-SAT baseline performs one master solve followed by simulation of its returned schedule. It does not use the common initial schedule as an injected CP incumbent in the manner of the iterative stage-loop variants. Consequently, the baseline results are reported as simulated outcomes of its returned CP schedules, without attributing stagnation to a common-initial-incumbent mechanism that the baseline does not implement. The comparison measures the performance of these four finite-budget configurations, subject to the architecture difference noted above.
Table 9 presents the mean makespans for the four cells and the test results for each effect. Under the per-instance × seed paired basis (a main effect is defined as the mean of [(BASE − LC) + (SF − FULL)]/2), the LC main effect is 14.12 min (p < 0.001 after Holm correction) and the SF main effect is 16.42 min (p < 0.001 after Holm correction). Both average main effects are significantly positive, indicating that each feedback mechanism yields a significant average improvement across the configurations in which it is present or absent.
The LC × SF interaction contrast is also significant (+24.53 min, p < 0.001 after Holm correction). The sum of the average gains from enabling each feedback configuration alone is approximately 55.1 min, whereas the gain of the full configuration over one-shot BASE is 30.54 min. These improvement paths overlap markedly: enabling either mechanism alone captures 86% to 94% of the observed joint gain. The additional improvement from combining both is only 1.9 to 4.2 min relative to the respective single-feedback settings. After aggregating the 10 seed-level replications to each instance (n = 90), all three contrast distributions remain significant under two-sided Wilcoxon tests (all raw p < 1.0 × 10−7). Means were computed from unrounded data and can differ by up to 0.01 min from differences of rounded Table 9 cell means. The raw two-sided p-values for the LC, SF, and LC × SF contrasts are, respectively, 1.76 × 10−10, 6.78 × 10−12, and 9.93 × 10−8. These are comparisons between implemented configurations, not factorial estimates free from the BASE-versus-stage-loop architecture difference.
Table 9. Cell means of the ablation study and 2 × 2 factorial tests.
The structure of the roles played by the two feedback types becomes further visible at the per-instance level. The per-instance analysis in Figure 9 shows that deleting either type of feedback from the full configuration has a clearly polarized effect: deleting the C-type feedback degrades the result by less than 1 min on 66.7% of the instances, while deleting the B-type feedback does so on 71.1% of the instances, and the instance-level median degradations are both 0.0 min. The 90th percentiles are about 16.0 min (deleting C-type) and 15.3 min (deleting B-type), and the maximum degradations reach 91.6 min (Case C54, deleting C-type) and 58.6 min (Case C8, deleting B-type), with both maxima occurring in difficult instances of larger scale or with intense resource competition.
Figure 9. Ablation results and per-instance degradation analysis.
The relative performance of a single mechanism and the full algorithm is scenario-dependent. On 27 (CP-LC) instances and 31 (CP-SF) instances, the 10-seed mean of the single mechanism outperforms the full algorithm, with the advantage exceeding 5 min on 11 and 13 instances, respectively, and reaching about 64 min at most (Case C43, where CP-SF is better). On three instances, the configuration with only B-type cuts, and on three instances, the configuration with only C-type feedback, perform even worse than the completely feedback-free CP-SAT (by about 33 min and 29 min at most). This indicates mutual interference between the two feedback types in some scenarios. The full algorithm retains both improvement paths and maintains robust performance across scenarios; this tail analysis is exploratory in nature and was not included in the reported statistical testing scheme.
The ablation results show statistically detectable configuration-level differences for the LC and SF factorial-average contrasts and their interaction. The feedback pathways have overlapping effects: the full stage loop improves mean performance compared to either single-feedback variant, although the gain is not superadditive and individual instances can favor one pathway. Because BASE uses a one-shot CP solve while the other configurations use iterative stage loops, these contrasts describe implemented configurations rather than isolated component-only causal effects. None of the D90 configurations includes the A1-dependent assignment restriction; this ablation therefore does not measure that restriction’s effect. A symmetric, architecture-controlled factorial study would be needed for a component-only causal interpretation.

4.4. Small-Instance Solution-Quality Validation and Power Analysis

To assess small-instance solution quality, the 40 s CSC-SF runs on A1–A3 yield simulation-feasible makespans of 7550, 7420, and 5871 s, respectively; each value is identical across the 10 seeds for its instance (standard deviation 0). These values match the incumbents of the separate 4 h LBBD reference runs (Table 10). Independently, A1-free planning-relaxation solves terminate with status OPTIMAL in under one second, with objective values (lower bounds) of 7526, 7398, and 5824 s. Using the CSC-SF simulation-feasible makespans as upper bounds, the a posteriori relative gap upper bound is calculated as (UB − LB)/UB × 100%, giving 0.32%, 0.30%, and 0.80%, respectively. These values are derived from the independently optimized relaxation bounds and the feasible simulated schedules; they are distinct in meaning from the solver-reported master-model gaps of the 4 h reference runs, even where the displayed values coincide. The separate 4 h reference configuration reports its own solver status and master-model gap in Table 10. These solver diagnostics are not used to calculate the A1-free a posteriori gap upper bounds. The independent A1-free relaxation bounds provide a separate a posteriori solution-quality assessment under the planning-to-execution correspondence established in Section 3.2. The comparison does not isolate the restriction’s effect on the 4 h search trajectory or prove exact global optimality.
Table 10. Small-instance solution-quality comparison for A1–A3.
Table 11 summarizes the global Holm correction across the family of seven tests reported in Section 4.1.3. The four H1 comparisons use directional, one-sided Wilcoxon tests on the 90 instance-level paired means, while the three H2 contrasts use two-sided Wilcoxon tests on the 90 instance-level factorial-average differences. After combining the four H1 and three H2 raw p-values, Holm adjustment is applied in ascending order within this single family. All seven adjusted p-values remain below 0.05; table rows are grouped by hypothesis rather than sorted by significance.
Table 11. Global Holm correction across the family of seven tests.
The Monte Carlo power analysis in Table 12 assesses prospective sensitivity under four prespecified difference distributions. At n = 90 and α = 0.05, the estimated power for a medium effect (d = 0.5) is 0.991 on average and 0.980 in the least favorable (symmetric heavy-tailed) scenario; for a large effect (d = 0.8), it is 1.000 in all four scenarios. These simulations quantify power under the specified hypothetical effect sizes and distributional assumptions; they do not estimate the standardized effect sizes observed in the ablation experiments or provide a retrospective power analysis. The three ablation contrasts remain statistically significant after instance-level aggregation (n = 90), as reported in Table 11.
Table 12. Monte Carlo power analysis (n = 90, α = 0.05).
In sum, the D90 results show that CSC-SF achieves the lowest mean simulated makespan among the five compared algorithms, and all four prespecified pairwise comparisons remain significant after global Holm adjustment. The Monte Carlo analysis indicates high prospective sensitivity under the specified hypothetical effect sizes. For A1–A3, the 40 s CSC-SF solutions match the incumbents of the separate 4 h reference runs. Independently optimized A1-free planning-relaxation lower bounds yield a posteriori relative gap upper bounds no larger than 0.80% under the planning-to-execution correspondence established in Section 3.2. These bounds provide an assessment of solution quality over the modeled domain but do not establish exact global optimality of the original simulation-evaluated problem.

5. Engineering Application

The preceding sections have addressed repair scheduling through model formulation, algorithm design, and numerical experiments. To illustrate the engineering use of the model, this section presents two forms of decision support: repair-schedule visualization and resource-provisioning analysis. The generated schedules provide process-level information that airside operations managers can inspect when comparing repair plans and resource-support options.

5.1. Repair Schedule Visualization

In engineering practice, a repair schedule should communicate not only the overall makespan but also the planned timing and sequence of individual operations. Figure 10 presents the Gantt chart generated by the proposed model; the horizontal axis denotes repair time, and different colors denote different operations. The chart allows decision makers to inspect the planned sequence, identify operations scheduled in late time windows, and assess potential resource bottlenecks. It provides a static view of the planned schedule. For consistency with the figures, the damage spots in Figure 10 retain their original crater identifiers.
Figure 10. Gantt chart of the repair schedule for Case A5.
Taking Case A5 as an example, Figure 10 shows that the two repair crews are assigned successive tasks across multiple damage spots. Decision makers can use the planned sequence to identify critical damage spots and operations that may affect the overall makespan. When several subsequent operations of a repair crew are concentrated in a late time window, the corresponding resources may become a scheduling bottleneck and warrant attention during plan review.

5.2. Resource Provisioning Analysis

Beyond repair schedule visualization, the proposed model can also support pre-repair plan analysis and resource-support decisions. In practice, decision makers often need to determine whether the overall repair makespan changes appreciably after the quantity of equipment or the resource-group configuration is adjusted. Verifying this solely through field exercises is not only costly but also makes it difficult to compare multiple candidate plans quickly. Without actually organizing repair operations, the proposed model can rerun the planning-layer scheduling and the execution-layer simulation with modified equipment pools and resource-group configurations, providing a quantitative basis for selecting a support plan.
Figure 11 presents the sensitivity analysis of resource-group enhancement for all nine resource groups across four representative instances: the moderate-damage Case A5, the severe-damage Case A8, the medium-competition Case C25, and the high-competition Case C45. The enhancement adds one set of the equipment belonging to the corresponding resource group to each repair crew (the equipment composition is shown in Figure 2). For the analysis in this section, the baseline and enhanced plans were regenerated with a dedicated set of 20 random seeds, and each enhanced plan inherits its corresponding baseline plan seed by seed. The figure reports the mean reduction in effective makespan relative to the baseline plan together with the 95% confidence intervals. Averaged across instances, R1, R7, and R4 are the three resource groups with the largest enhancement benefits, with mean effective reductions of approximately 25.59 min, 23.49 min, and 14.37 min, respectively, whereas the remaining groups yield less than 4 min.
Figure 11. Cross-instance sensitivity analysis of resource-group enhancement.
The results show that the composition of bottleneck resources varies across scenarios: R1 yields the highest benefit in A5 and C25, R7 overtakes it as the top-ranked group in C45, where resource competition is more intense, and the three resource groups yield comparable benefits in A8. In some scenarios, enhancing a non-bottleneck resource brings zero benefit. After R4 and R9 are enhanced in C45, for example, the plans remain unchanged under all 20 seeds, indicating that enhancement translates into makespan benefits only when it acts on the current scheduling bottleneck. R1, R7, and R4 constitute the constraints in most of the tested scenarios, so a limited enhancement of these groups yields fairly stable time savings. Accordingly, decision makers can prioritize resource groups when configuring support plans and can input the operation times and equipment requirements of new processes or new configurations into the model to rapidly screen candidate plans under the same damage scenario.
Because the model minimizes the completion time of the modeled repair operations, the reported reductions quantify improvements in repair makespan and, at most, the repair-controlled component of modeled closure time. They are not direct estimates of aircraft delay savings or monetary benefits. Published delay-cost estimates cited in this paper may provide contextual benchmarks, but monetizing avoided closure time requires an airport-specific model linking each closure interval to affected flights, their delay reductions, and the applicable cost per unit of delay. Accordingly, Figure 11 supports an operational ranking and a time-based screening of candidate equipment enhancements for repair-capacity planning, rather than a quantified economic appraisal.
Remark 2
(post-processing extension). The repair-completion time optimized above is not the operational reopening time. For a repair region i, a post-processing chain can extend it as follows: curing completion Ri ≥ Ci + Li,cure, inspection completion Ii ≥ Ri + Pi,inspect, and authorization completion Oi ≥ Ii + Li,approval, where Ci is the repair-completion time of region I, and Li,cure, Pi,inspect, and Li,approval denote the curing, inspection, and authorization durations. A zone S reopens no earlier than Topen ≥ max{i∈S} Oi. These stages involve material properties and regulatory procedures beyond the scheduling decisions considered here and are therefore treated as exogenous offsets in this extension rather than being re-optimized.

5.3. Static Parameter Sensitivity Analysis

To quantify how systematic changes in the model’s core input parameters affect scheduling performance, a controlled parameter sweep is conducted on the C20 subset (20 instances). Two parameter families are examined: equipment travel speed (five levels: v/v0 ∈ {0.8, 0.9, 1.0, 1.1, 1.2}) and repair processing time (five levels: t/t0 ∈ {1.00, 1.0625, 1.125, 1.1875, 1.25}). Each cell uses a single fixed seed (20260101) under the same hard wall-clock budget and single-thread protocol as the main experiments, yielding 180 unique parameter–instance combinations. The nominal baseline (v0, t0) is shared by both families. Results are reported as the paired percentage change in simulation-validated makespan relative to the nominal schedule of the same instance (Δ% = (Z(p) − Z(p0))/Z(p0) × 100). Of the 180 parameter-perturbation runs attempted, 176 returned feasible solutions within the prescribed solver budget; four runs involving travel-speed perturbations (two for C19 and one each for C21 and C27) did not yield a feasible solution within that budget and are excluded from the corresponding summary statistics.
Figure 12 summarizes the results. Processing-time inflation produces a monotonic increase in median relative makespan: a 6.25% increase yields a median degradation of +5.2%, a 12.5% increase yields +10.5%, a 18.75% increase yields +16.1%, and a 25% increase yields +22.9% (mean +24.5%). Equipment speed reduction produces a more heterogeneous response at the tested perturbation levels: v × 0.8 yields a mean degradation of +10.4% (median +4.4%). Speed increases above the nominal level yield a mean improvement of −7.1% at v × 1.1; increasing travel speed further from 1.1 to 1.2 times the baseline did not produce an additional reduction in the observed mean relative makespan (−6.7%). The wide interquartile ranges in the speed family show substantial variation across the tested instances. Because each condition was run with one fixed seed and four runs failed to produce a feasible incumbent, these summaries are conditional on successful solves and may understate deterioration in more difficult parameter settings.
Figure 12. Static parameter sensitivity of CSC-SF schedules on the C20 subset: the left panel shows equipment travel speed and the right panel shows processing time.

6. Conclusions and Future Work

Based on the modeling, solution, and validation results of this study, the following conclusions are drawn:
(1)
To meet the repair scheduling requirements involving multiple damage spots and multiple processes in complex repair scenarios, a two-level planning–execution multi-mode resource-constrained project scheduling model with time-space constraints was formulated. The planning layer uniformly captures process-mode selection, repair crew configuration, operation sequencing, and resource occupancy constraints, while the execution layer further accounts for equipment travel, passage occupancy, and spatial conflicts, thereby providing a systematic description of the on-site recovery operations.
(2)
CSC-SF combines CP-SAT planning, two guarded analytic lower-bound cut families, and simulation-guided local repair within finite computation budgets. The D90 implementation does not use the optional A1-dependent assignment restriction, which is confined to the separate 4 h LBBD reference configuration. Across the 90 synthetic D90 instances, CSC-SF achieves a mean simulated repair-completion time of 195.45 min and a best-or-tied result among the five algorithms on 82 instances, with paired mean leads of 32.4–36.9 min. The Friedman test and four pairwise tests after global Holm correction support its empirical lead in this benchmark family; a separate Monte Carlo calculation explores sensitivity under specified hypothetical differences.
(3)
The four-cell ablation identifies statistically significant configuration-level B-type, C-type, and interaction contrasts (instance-level two-sided Wilcoxon raw p = 1.76 × 10−10, 6.78 × 10−12, and 9.93 × 10−8, respectively; all remain significant after global Holm adjustment). Each single-feedback setting captures approximately 86–94% of the full-versus-BASE mean gain. The full configuration improves mean makespan by 30.54 min relative to BASE; removing B-type or C-type feedback from the full stage loop increases it by 1.87 or 4.16 min, respectively. The factorial-average contrasts are 14.12 min (B-type) and 16.42 min (C-type), with a 24.53 min interaction; because BASE uses a one-shot solve, these are configuration contrasts rather than isolated causal effects. On difficult instances, losses from removing feedback reach 91.6 min (C54) and 58.6 min (C8). On A1–A3, 40 s CSC-SF outcomes match the 4 h reference incumbents; A1-free planning-relaxation optima provide 0.30–0.80% a posteriori relative gap upper bounds under the modeled Section 3.2 conditions, without establishing exact global optimality. All seven reported statistical tests use 90 paired instance-level observations rather than treating seed replications as independent instances.
(4)
The engineering application analysis shows that the model outputs can be used to generate Gantt charts of the repair process and to conduct cross-instance resource sensitivity analyses. The composition of bottleneck resources varies with the damage scenario; averaged across instances, R1, R7, and R4 rank as the top three in enhancement benefits (mean effective reductions of 14 to 26 min), which can inform priority-based equipment support analysis. This analysis relies on engineering-experience parameters, and the absolute benefit values await calibration with measured data. A one-factor-at-a-time parameter sweep on the C20 subset further quantified sensitivity to processing durations and travel speeds: increasing processing times by 25% resulted in a median instance-wise relative makespan increase of 22.9%, while reducing travel speed by 20% resulted in a mean increase of 10.4% among successfully solved cases.
From the perspective of practitioners, the proposed framework can serve as a decision-support tool for airport operations centers and maintenance units. Given a damage survey, it can generate a crew-and-equipment schedule screened for feasibility by the simplified execution simulator within the tested computation budgets, can identify critical damage spots governing the repair makespan, and can enable what-if screening of equipment provisioning plans within the modeled scenarios. As a proposed deployment pathway rather than a demonstrated field result, the tool could initially operate in parallel with existing manual planning, with equipment movement assumptions and time parameters calibrated against observed repair records before operational use.
The evidence here concerns deterministic repair-completion scheduling on synthetic instances with engineering-derived parameters; field data are needed to calibrate equipment travel, operation durations, and the transferability of the reported performance. The computational comparisons cover four implemented metaheuristic baselines and internal ablations, but not an independently implemented CP/LBBD comparator. The C20 one-factor sensitivity study uses one seed per condition and summarizes feasible-run outcomes, excluding four budget-limited runs without incumbents; its conclusions do not extend directly to stochastic disruptions. The execution model approximates machinery movement using envelope-buffered corridor occupancy rather than explicit turning-radius kinematics or detailed work-zone traffic organization. It also focuses on repair completion, without modeling curing and inspection, phased reopening of the minimum operable area, or downstream delay and capacity reallocation. Further work can combine field-calibrated inputs with richer movement constraints, stochastic equipment availability and weather, and evaluation of longer search budgets and phased reopening objectives.
Future research will proceed along two directions. First, the framework will be extended to uncertain environments by introducing methods such as buffer trade-offs, proactive baseline scheduling, and robust bi-objective formulations [63,64,65]. Second, to address execution disturbances such as equipment failures, road failures, and newly detected damage spots, an inheritance-based online rescheduling mechanism will be established, and the relevant results will be reported in a separate paper.

Supplementary Materials

The following supporting information can be downloaded at: https://www.mdpi.com/article/10.3390/app162311634/s1. The per-instance results on the D90 benchmark are provided in the supplementary file (Supplementary_D90_per_instance_results.docx).

Author Contributions

Conceptualization, J.S. and W.X.; methodology, J.S.; software, J.S.; validation, J.S. and Z.D.; formal analysis, J.S.; investigation, J.S. and Z.D.; data curation, J.S.; writing—original draft preparation, J.S.; writing—review and editing, W.X. and Z.D.; visualization, J.S.; supervision, W.X.; project administration, W.X. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Data Availability Statement

The per-instance D90 results were supplied as Supplementary_D90_per_instance_results.docx with the original submission. The instance-generation configuration, input instances, and further computational records are available from the corresponding author on reasonable request; no public repository link is asserted in this revision.

Acknowledgments

ChatGPT (GPT-6) was used during manuscript preparation for language editing and drafting of text. The authors reviewed and revised all AI-assisted text and take responsibility for the final manuscript. The AI-assisted schematic included in the original submission was removed during revision and is not retained in this version.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Al-Ghzawi, M.; El-Rayes, K. Machine learning and multi-objective optimization methodology for planning construction phases of airport expansion projects. J. Air Transp. Manag. 2024, 115, 102550. [Google Scholar] [CrossRef] [Scilit]
  2. Jardines, A.; Soler, M.; García-Heras, J. Estimating entry counts and ATFM regulations during adverse weather conditions using machine learning. J. Air Transp. Manag. 2021, 95, 102109. [Google Scholar] [CrossRef] [Scilit]
  3. He, M.; Dong, Y.; Wang, Q.; Lu, N.; Yang, Y. Decision-making for airport minimum operating strip scheme based on cumulative prospect theory. Shanxi Archit. 2017, 43, 143–145. (In Chinese) [Google Scholar]
  4. Yeung, C.; Tan, W. Forecasting airport pavement repair hours. J. Air Transp. Manag. 2022, 105, 102283. [Google Scholar] [CrossRef] [Scilit]
  5. Zhang, D.; Song, G.; Chen, K.; Li, L.; Xu, Y. Damage assessment method for airport runway targets based on functional recovery time. Command Control Simul. 2023, 45, 94–98. (In Chinese) [Google Scholar]
  6. Zhang, T.; Li, Z.; Xu, Y. Selection of airport emergency taking-off and landing strip based on TOPSIS method. Traffic Eng. Technol. Natl. Def. 2012, 10, 28–30. (In Chinese) [Google Scholar]
  7. Hartmann, S.; Briskorn, D. An updated survey of variants and extensions of the resource-constrained project scheduling problem. Eur. J. Oper. Res. 2022, 297, 1–14. [Google Scholar] [CrossRef] [Scilit]
  8. Klein, N. Integer programming for multi-mode resource-constrained project scheduling. Ann. Oper. Res. 2025, 366, 1513–1540. [Google Scholar] [CrossRef] [Scilit]
  9. Fernandes, G.A.; De Souza, S.R. A matheuristic approach to the multi-mode resource constrained project scheduling problem. Comput. Ind. Eng. 2021, 162, 107592. [Google Scholar] [CrossRef] [Scilit]
  10. Van Peteghem, V.; Vanhoucke, M. A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem. Eur. J. Oper. Res. 2010, 201, 409–418. [Google Scholar] [CrossRef] [Scilit]
  11. Van Peteghem, V.; Vanhoucke, M. An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances. Eur. J. Oper. Res. 2014, 235, 62–72. [Google Scholar] [CrossRef] [Scilit]
  12. Luo, X.; Guo, S.; Du, B.; Luo, X.; Guo, J. Multi-objective multi-skill resource-constrained project scheduling considering flexible resource profiles. Appl. Sci. 2024, 14, 1921. [Google Scholar] [CrossRef] [Scilit]
  13. Herroelen, W.; Leus, R. Project scheduling under uncertainty: Survey and research potentials. Eur. J. Oper. Res. 2005, 165, 289–306. [Google Scholar] [CrossRef] [Scilit]
  14. Chakrabortty, R.K.; Sarker, R.A.; Essam, D.L. Resource constrained project scheduling with uncertain activity durations. Comput. Ind. Eng. 2017, 112, 537–550. [Google Scholar] [CrossRef] [Scilit]
  15. Gök, Y.S.; Padrón, S.; Tomasella, M.; Guimarans, D.; Ozturk, C. Constraint-based robust planning and scheduling of airport apron operations through simheuristics. Ann. Oper. Res. 2023, 320, 795–830. [Google Scholar] [CrossRef] [Scilit]
  16. Wang, S.; Che, Y.; Zhao, H.; Lim, A. Accurate tracking, collision detection, and optimal scheduling of airport ground support equipment. IEEE Internet Things J. 2021, 8, 572–584. [Google Scholar] [CrossRef] [Scilit]
  17. Padrón, S.; Guimarans, D.; Ramos, J.J.; Fitouri-Trabelsi, S. A bi-objective approach for scheduling ground-handling vehicles in airports. Comput. Oper. Res. 2016, 71, 34–53. [Google Scholar] [CrossRef] [Scilit]
  18. Shone, R.; Glazebrook, K.; Zografos, K.G. A new simheuristic approach for stochastic runway scheduling. Transp. Sci. 2024, 58, 520–539. [Google Scholar] [CrossRef] [Scilit]
  19. Hancerliogullari Koksalmis, G.; Rabadi, G.; Kharbeche, M.; Al-Salem, M. A mathematical model and heuristic approaches for runway rescheduling. Aeronaut. J. 2025, 129, 1851–1885. [Google Scholar] [CrossRef] [Scilit]
  20. Li, S.; Teo, K.L. Post-disaster multi-period road network repair: Work scheduling and relief logistics optimization. Ann. Oper. Res. 2019, 283, 1345–1385. [Google Scholar] [CrossRef] [Scilit]
  21. Liu, S.-S.; Arifin, M.F.A.; Chen, W.T.; Huang, Y.-H. Emergency repair scheduling model for road network integrating rescheduling feature. Appl. Sci. 2021, 11, 1447. [Google Scholar] [CrossRef] [Scilit]
  22. Dong, W.; Xu, W.; Zhang, J. A multi-process resource allocation model for rapid repair of multiple bomb craters on airport pavements based on polychromatic set theory. Model. Simul. 2025, 14, 297–308. (In Chinese) [Google Scholar] [CrossRef]
  23. Li, J.; Harabor, D.; Stuckey, P.J.; Ma, H.; Gange, G.; Koenig, S. Pairwise symmetry reasoning for multi-agent path finding search. Artif. Intell. 2021, 301, 103574. [Google Scholar] [CrossRef] [Scilit]
  24. Shen, B.; Chen, Z.; Li, J.; Cheema, M.A.; Harabor, D.D.; Stuckey, P.J. Beyond pairwise reasoning in multi-agent path finding. In Proceedings of the 33rd International Conference on Automated Planning and Scheduling, Prague, Czech Republic, 24–30 July 2023; AAAI Press: Palo Alto, CA, USA, 2023; pp. 384–392. [Google Scholar] [CrossRef] [Scilit]
  25. Wang, F.; Sun, W.; Yan, P.; Wei, H.; Lu, H. Research on path planning for robots with improved A* algorithm under bidirectional JPS strategy. Appl. Sci. 2024, 14, 5622. [Google Scholar] [CrossRef] [Scilit]
  26. Hardell, H.; Otero, E.; Polishchuk, T.; Smetanová, L. Optimizing air traffic management through point merge procedures: Minimizing delays and environmental impact in arrival operations. J. Air Transp. Manag. 2025, 123, 102706. [Google Scholar] [CrossRef] [Scilit]
  27. Evler, J.; Asadi, E.; Preis, H.; Fricke, H. Airline ground operations: Optimal schedule recovery with uncertain arrival times. J. Air Transp. Manag. 2021, 92, 102021. [Google Scholar] [CrossRef] [Scilit]
  28. Poyraz, D.D.; Azizoğlu, M. An airport gate reassignment problem with gate closures. J. Air Transp. Manag. 2024, 115, 102529. [Google Scholar] [CrossRef] [Scilit]
  29. Dahanayaka, M.; Prak, D.; Mes, M. From gate to runway: A systematic review of airport ground operations optimization. J. Air Transp. Manag. 2026, 135, 103013. [Google Scholar] [CrossRef] [Scilit]
  30. Roh, S.; Lee, J.; Urbino, I.J.; Lin, W.; Cho, Y. Airport pavement maintenance decision-making system with condition cases optimization. Appl. Sci. 2023, 13, 13167. [Google Scholar] [CrossRef] [Scilit]
  31. Han, J.; Kim, S.; Hwang, I. Numerical assessment and repair method of runway pavement damage due to CBU penetration and blast loading. Appl. Sci. 2022, 12, 2888. [Google Scholar] [CrossRef] [Scilit]
  32. Saei, S.; Tajik, N. Time-dependent restoration routing problem: An efficient initial solution. Findings 2022. [Google Scholar] [CrossRef] [Scilit]
  33. Canbilen Sütiçen, T.; Batun, S.; Çelik, M. Integrated reinforcement and repair of interdependent infrastructure networks under disaster-related uncertainties. Eur. J. Oper. Res. 2023, 308, 369–384. [Google Scholar] [CrossRef] [Scilit]
  34. Caunhye, A.M.; Aydin, N.Y.; Duzgun, H.S. Robust post-disaster route restoration. OR Spectr. 2020, 42, 1055–1087. [Google Scholar] [CrossRef] [Scilit]
  35. Benders, J.F. Partitioning procedures for solving mixed-variables programming problems. Numer. Math. 1962, 4, 238–252. [Google Scholar] [CrossRef] [Scilit]
  36. Hooker, J.N.; Ottosson, G. Logic-based Benders decomposition. Math. Program. 2003, 96, 33–60. [Google Scholar] [CrossRef] [Scilit]
  37. Hooker, J.N. Planning and scheduling by logic-based Benders decomposition. Oper. Res. 2007, 55, 588–602. [Google Scholar] [CrossRef] [Scilit]
  38. Hooker, J.N. Logic-based Benders decomposition for large-scale optimization. In Large Scale Optimization in Supply Chains and Smart Manufacturing; Springer: Cham, Switzerland, 2019; pp. 1–26. [Google Scholar] [CrossRef] [Scilit]
  39. Pellegrino, R.; Gaudenzi, B. Supply chain resilience as a viable way to cope with disruptions: An empirical analysis of Italian firms. Rev. Manag. Sci. 2026, 20, 1459–1489. [Google Scholar] [CrossRef] [Scilit]
  40. Rohaninejad, M.; Vahedi-Nouri, B.; Jelodari Mamaghani, E.; Foumani, M.; Battaïa, O. Viable supply chain network design: Machine learning-derived chance-constrained programming. Ann. Oper. Res. 2026. [Google Scholar] [CrossRef] [Scilit]
  41. Perron, L.; Didier, F.; Gay, S. The CP-SAT-LP solver. In Proceedings of the 29th International Conference on Principles and Practice of Constraint Programming (CP 2023), Melbourne, Australia, 29 August–2 September 2023; Schloss Dagstuhl: Wadern, Germany, 2023. [Google Scholar]
  42. Juan, A.A.; Faulin, J.; Grasman, S.E.; Rabe, M.; Figueira, G. A review of simheuristics: Extending metaheuristics to deal with stochastic combinatorial optimization problems. Oper. Res. Perspect. 2015, 2, 62–72. [Google Scholar] [CrossRef] [Scilit]
  43. Department of the Air Force. AFTTP 3-32.17: Rapid Airfield Crater and Spall Repair; U.S. Air Force: Montgomery, AL, USA, 2023. [Google Scholar]
  44. Baptiste, P.; Le Pape, C.; Nuijten, W. Constraint-Based Scheduling: Applying Constraint Programming to Scheduling Problems; Kluwer Academic Publishers: Dordrecht, The Netherlands, 2001. [Google Scholar]
  45. Laborie, P.; Rogerie, J.; Shaw, P.; Vilím, P. IBM ILOG CP optimizer for scheduling: 20+ years of scheduling with constraints at IBM/ILOG. Constraints 2018, 23, 210–250. [Google Scholar] [CrossRef] [Scilit]
  46. Heinz, V.; Novák, A.; Vlk, M.; Hanzálek, Z. Constraint programming and constructive heuristics for parallel machine scheduling with sequence-dependent setups and common servers. Comput. Ind. Eng. 2022, 172, 108586. [Google Scholar] [CrossRef] [Scilit]
  47. Elçi, Ö.; Hooker, J.N. Stochastic planning and scheduling with logic-based Benders decomposition. Inf. J. Comput. 2022, 34, 2428–2442. [Google Scholar] [CrossRef] [Scilit]
  48. Kolisch, R.; Sprecher, A. PSPLIB—A project scheduling problem library. Eur. J. Oper. Res. 1997, 96, 205–216. [Google Scholar] [CrossRef] [Scilit]
  49. Di Mascio, P.; Moretti, L. Implementation of a pavement management system for maintenance and rehabilitation of airport surfaces. Case Stud. Constr. Mater. 2019, 11, e00251. [Google Scholar] [CrossRef] [Scilit]
  50. Wesołowski, M.; Iwanowski, P. APCI evaluation method for cement concrete airport pavements in the scope of air operation safety and air transport security. Int. J. Environ. Res. Public Health 2020, 17, 1663. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  51. Vanhoucke, M.; Coelho, J. A matheuristic for the resource-constrained project scheduling problem. Eur. J. Oper. Res. 2024, 319, 711–725. [Google Scholar] [CrossRef] [Scilit]
  52. Rahman, H.F.; Chakrabortty, R.K.; Ryan, M.J. Memetic algorithm for solving resource constrained project scheduling problems. Autom. Constr. 2020, 111, 103052. [Google Scholar] [CrossRef] [Scilit]
  53. Ropke, S.; Pisinger, D. An adaptive large neighborhood search heuristic for the pickup and delivery problem with time windows. Transp. Sci. 2006, 40, 455–472. [Google Scholar] [CrossRef] [Scilit]
  54. Graf, B. Adaptive large variable neighborhood search for a multiperiod vehicle and technician routing problem. Networks 2020, 76, 256–272. [Google Scholar] [CrossRef] [Scilit]
  55. Hansen, P.; Mladenović, N. Variable neighborhood search: Principles and applications. Eur. J. Oper. Res. 2001, 130, 449–467. [Google Scholar] [CrossRef] [Scilit]
  56. Dahite, L.; Kadrani, A.; Benmansour, R.; Guibadj, R.N.; Fonlupt, C. Multi-objective model and variable neighborhood search algorithms for the joint maintenance scheduling and workforce routing problem. Mathematics 2022, 10, 1807. [Google Scholar] [CrossRef] [Scilit]
  57. Ball, M.O. Heuristics based on mathematical programming. Surv. Oper. Res. Manag. Sci. 2011, 16, 21–38. [Google Scholar] [CrossRef] [Scilit]
  58. Demšar, J. Statistical comparisons of classifiers over multiple data sets. J. Mach. Learn. Res. 2006, 7, 1–30. [Google Scholar]
  59. Iman, R.L.; Davenport, J.M. Approximations of the critical region of the Friedman statistic. Commun. Stat.-Simul. Comput. 1980, 9, 571–595. [Google Scholar] [CrossRef] [Scilit]
  60. Wilcoxon, F. Individual comparisons by ranking methods. Biom. Bull. 1945, 1, 80–83. [Google Scholar] [CrossRef] [Scilit]
  61. Holm, S. A simple sequentially rejective multiple test procedure. Scand. J. Stat. 1979, 6, 65–70. [Google Scholar]
  62. Vargha, A.; Delaney, H.D. A critique and improvement of the CL common language effect size statistics of McGraw and Wong. J. Educ. Behav. Stat. 2000, 25, 101–132. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  63. Liu, H.; Qu, S.; Li, R.; Raza, H. Bi-objective robust project scheduling with resource constraints and flexible activity execution lists. Comput. Ind. Eng. 2021, 156, 107288. [Google Scholar] [CrossRef] [Scilit]
  64. Van de Vonder, S.; Demeulemeester, E.; Herroelen, W.; Leus, R. The use of buffers in project management: The trade-off between stability and makespan. Int. J. Prod. Econ. 2005, 97, 227–240. [Google Scholar] [CrossRef] [Scilit]
  65. Van de Vonder, S.; Demeulemeester, E.; Herroelen, W. Proactive heuristic procedures for robust project scheduling: An experimental analysis. Eur. J. Oper. Res. 2008, 189, 723–733. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.