Visual Evaluation of Construction Schedule Progress by Linking Photographs and 4D Model

and
1
Structural & Seismic Engineering Group, Central Research Institute, Korea Hydro & Nuclear Power Co., Ltd., Daejeon 34101, Republic of Korea
2
Department of Civil Engineering, ERI (Engineering Research Institute), Gyeongsang National University, Jinju-si 52828, Republic of Korea
*
Author to whom correspondence should be addressed.

Abstract

During the construction period, numerous site photographs are routinely captured; however, their use is largely limited to simple visual inspection of construction status. To enhance the practical utilization of such photographic information, this study proposes a 4D-based construction progress management system that visually evaluates schedule progress by integrating site photographs within a BIM-based information management framework. The proposed system synchronizes site photographs with corresponding 4D model images using coordinate linkage and applies deep learning–based object detection to identify matching construction elements. Construction progress is approximately estimated by analyzing bounding box overlap between detected elements in site photographs and planned elements in 4D model images. A case study conducted on a bridge construction project demonstrated that the trained model achieved an overall mAP@0.5 of 0.532, and that the proposed method enables intuitive and approximate progress evaluation. The results indicate that the proposed system can improve the usability of site photographs as supporting information for 4D-based construction progress management.

1. Introduction

During construction, a large number of site photographs are captured and stored as part of routine documentation. Photographs acquired using smartphones are particularly convenient and contain various embedded attributes, such as shooting angle, orientation, and geographic coordinates, which make them potentially valuable resources for construction management. However, in actual construction, they are only used to visually understand the construction work [1,2]. Considering the ease of acquiring and accessing these photographs, it is necessary to establish a plan to utilize the various site images generated at each construction stage more practically. Specifically, the need to utilize site photographs within a building information modeling (BIM) based information management process has increased with the increasing use of BIM in construction projects.
A recently deployed technique that monitors the construction schedule status involves comparing construction information managed through BIM processes with three-dimensional (3D) data obtained using light detection and ranging (LiDAR) and a drone. Although these approaches can provide accurate geometric information, they require specialized equipment, additional costs, and complex data processing workflows. In contrast, site photographs captured using smartphones can be obtained without additional equipment or cost and are already widely available on construction sites. Unlike previous studies that primarily rely on point clouds, UAV imagery, or LiDAR data requiring additional sensing equipment and complex preprocessing, this study explicitly addresses the research gap in practical and low-cost construction progress monitoring by utilizing daily site photographs and directly linking them with 4D models for schedule evaluation.
To enhance the utilization of photographic information in construction site images, this study develops a methodology that visually evaluates the progress of a construction schedule by linking site photographs and 4D models and proposes a 4D-based progress management system based on this methodology. To realize this, we constructed a model that visually captures schedule progress against the plan by employing machine learning (ML), specifically deep learning–based object detection as a subset of artificial intelligence (AI) techniques, to link site photographs, 4D model object coordinates, and viewpoints. Subsequently, we develop a 4D computer-aided design (CAD) system capable of scheduling simulations and deep learning analysis. The developed system synchronized the 4D model of the planned schedule with the coordinates of the site photographs of the actual schedule. The schedule progress rate is estimated by comparing the two images using bounding boxes.
The proposed methodology and system are verified using a bridge project to ensure practical applicability. The system was used to detect the foundations, columns, and copings of the bridge; link them with the corresponding 4D model; detect the degree of performance when compared with that of the plan; and measure the progress rate. By linking construction site photographs with the 4D model, the actual construction schedule status can be intuitively assessed, thereby improving the usability of the site photographs.

3. Division of 3D Model into Activity Unit

3.1. Activity Unit Segmentation of 3D Model for 4D Model Generation

To compare the planned progress based on a 4D model with the actual progress based on smartphone photos, a 3D model representing the completion status of each activity must be pre-built and linked to schedule information. Typically, 3D models are created during the design phase, and these models are based on the external appearance of each structural section. Therefore, to create a 4D model that simulates each activity, a process of dividing the 3D model into activity units is necessary.
This study uses a vertex data-based segmentation technique for 3D model division. The accuracy of this segmentation technique is verified, proposing its applicability as an appropriate segmentation methodology for 4D model simulation. To achieve this, cylinders, square columns, and coping objects were extracted from a bridge pier model, segmented into appropriate equal parts, and the accuracy of the segmentation method was compared by comparing the volumes before and after segmentation.
Compared with mesh-based or voxel-based segmentation approaches, vertex-based segmentation preserves geometric continuity and volume consistency of structural components, which is critical for activity-level 4D simulation. In addition, vertex-based segmentation enables direct linkage between segmented objects and WBS-based schedule activities without introducing discretization artifacts, making it suitable for 4D construction progress simulation.

3.2. Segmentation of 3D Models Based on Vertex Data

Object segmentation based on vertex data means arranging the bounding box generated by the difference between the maximum and minimum values of the X, Y coordinates in the X, Y, Z-axis directions desired by the user on the 3D model, and dividing it into multiple objects based on the generated bounding box. The vertex data-based object segmentation consists of the steps of extracting vertices from a 3D model, organizing vertex data, applying a clustering algorithm, creating a segmentation surface, segmenting objects, and generating parameters. This segmentation method requires extraction of vertex location data of each vertex, and in this study, the Revit Dynamo node is utilized to extract the vertex data of the object.
To verify the segmentation method based on vertex data, a bridge pier model is applied as a case study. For the segmentation of the pier model, the vertex coordinates of the three target models for segmentation are extracted in Excel format through the vertex node of Dynamo script, as shown in Figure 1. Next, the area to be segmented is set based on the coordinate values extracted in Excel format for the target model for segmentation. Using the rectangle node, three segmentation planes are created based on the XY, XZ, and YZ planes, respectively. In order to segment the pier model based on the generated planes, the split node is used to divide the target bridge pier model into eight equal parts.
Figure 1. Vertex data-based object segmentation methodology.

3.3. Verification of the Accuracy of Object Segmentation Based on Vertex Data

First, the result of segmenting cylinders, rectangular columns, and copings using vertex data is as shown in Figure 2. It can be confirmed that the column objects are segmented according to the segmentation planes created in the XY, XZ, and YZ axes based on the center coordinates of the objects. In addition, the results of extracting the volume of each segmented object using Dynamo showed that the smallest value for the cylinder was measured as 28.863374 m3 and the largest value was measured as 28.863390 m3. The smallest value for the rectangular columns was measured as 18.749994 m3 and the largest value was measured as 18.750005 m3.
Figure 2. Vertex data-based object segmentation result.
The comparison results of the volume before and after segmentation showed an average error of 0.001118 m3 for cylinders, and an average error of 0.033039 m3 for lower objects created as curved trapezoids. High accuracy was observed for cylinders and coping lower objects, and the overall error level was around 0.03 m3, confirming that the segmentation accuracy of the 3D model was relatively high.

3.4. Comparison of 3D Model Segmentation Results Using Synchro

The Figure 3 compares the model segmentation function in Synchro Pro (Ver. 6.5.5), a software tool for 4D model simulation, with the segmentation results obtained using vertex data. The initial volumes of the coping and column before segmentation are 76.650 m3 and 20.191 m3, respectively.
Figure 3. Comparison of Synchro Pro’s segmentation function [27].
The segmentation method using Synchro Pro’s subdivision function creates a flat layer between the coping and the column joint, sets start and end points, and then segments the coping. While the segmentation appears to accurately segment the coping and the column, the bottom of the coping reveals that the top of the column is included in the coping, increasing the volume of the coping containing part of the column by 4.185 m3. Vertex data-based segmentation creates a segmentation plane equal to the size of the bottom of the coping, where the coping and column joint are located, and separates the coping and the column. Since the interfering area between the coping and the column is segmented during object segmentation, the volume of the coping containing the top of the column increases by 1.31 m3. Any segmentation method can be applied to 4D simulation to segment a 3D object into activity units, but a method with high segmentation accuracy is preferable. Compared to Synchro Pro, the 3D model segmentation method using vertex data was proven to be an appropriate segmentation method. Therefore, this study used a vertex data-based segmentation method to divide the 3D model into activity units. A schedule was then linked to each activity model to create a 4D model. The 4D model based on the planned progress generated in this way is used to verify the progress by comparing it with the actual progress objects extracted from smartphone photos using deep learning.

4. Progress Management Based on Construction Site Photographs and 4D Model

4.1. Monitoring the Progress Rate Through Synchronized Photographs and 4D Model

Site photographs captured using smartphones can be used as objective data for progress management. In this study, we propose a method for estimating the progress rate by comparing site photographs with a planned 4D model. The overall research process is illustrated in Figure 4.
Figure 4. Progress rate monitoring model based on deep learning applied to site photographs and 4D model.
(1)
Obtaining attribute information from construction site photographs
As indicated in step A of Figure 4, most photographs captured at construction sites were captured using smartphones equipped with GPS features. Along with an image, a photograph can provide information such as location, angle, azimuth, and height. If the screen of the 4D model is adjusted to the same size and angle as the site photographs, the progress status of the actual schedule against the plan can be determined by matching the corresponding information with the viewpoint information of the 4D model and comparing it with a structural object.
(2)
Synchronization of photograph information and 4D model coordinates
The GPS collects shooting information in the form of latitude and longitude coordinates, as shown in step B of Figure 4. These data must be translated into transverse Mercator (TM) coordinates, which are plane rectangular coordinates, to link them to a 4D model. Additionally, when connecting camera information from a scene, it may be necessary to resolve issues in which shooting information such as focal length cannot be transferred to the parameters of the 4D model viewer. Therefore, as indicated in step B of Figure 4, it is important to match the site photographs and composition of the 4D model by connecting the coordinates and shooting information obtained through several procedures to the viewpoint information of the 4D model. By synchronizing the viewpoint of the 4D model with information from site photographs, a 4D model identical to the structural object in the photograph can be obtained. At this stage, the on-site photograph taken on a specific date was compared with the corresponding 4D model reflecting the progress up to that date. This comparison enabled the assessment of the actual progress status against the planned schedule by analyzing the structural elements.
(3)
Structural image detection using deep learning
Site photographs are simple images that contain only shooting information. Structural components can be detected in site photographs by comparing these simple images with 4D models and converting them into data. A 4D model image is obtained from the associated 4D viewer to compare the scheduling status of each part, as shown in step C in Figure 4. The same image was compared by feeding it into a deep learning–based object detection model alongside the field image.
(4)
Progress rate calculation by overlapping deep learning images and 4D models
Upon detecting the structural object, the site photograph and 4D model are processed by the learning model, which represents the region of the structure as a bounding box in the image along with its corresponding class, as shown in step D of Figure 4. Next, the bounding box coordinate values obtained by applying the deep learning model to site photographs and individual 4D model images are compared, allowing researchers to estimate the approximate progress rate based on the length and width of the bounding box.

4.2. Obtaining Attribute Information from Construction Site Photographs

Smartphones are commonly used to capture images depicting the scheduling status of construction sites. However, these images often lack detailed information about the objects photographed, as well as the time and location of capture. Smartphone cameras can record information other than shooting date and time. For instance, the default photograph attribute values include the field of view (FOV) and focal length of the smartphone camera as in Figure 5. The FOV and focal length are inversely proportional, with the FOV expanding and focal length contracting as the lens moves closer to the film.
Figure 5. FOV and focal length in the photographs.
Conversely, as the lens moves away from the film, the FOV narrows and focal length increases. The information acquired when taking a photograph with a smartphone camera can be used in the BIM software to connect the same BIM to the structure in the photograph.
In addition to the basic attribute information of the camera built into a smartphone, additional information can be obtained based on sensors. Information about the shooting location can be obtained using GPS, and the obtained information includes the smartphone’s latitude, longitude, and altitude information, as shown in Figure 6. Furthermore, orientation information of the smartphone at the time of image capture, including yaw, pitch, and roll angles, is obtained using inertial sensors. These orientation parameters represent the camera viewing direction and tilt, and are used to reconstruct the camera viewpoint within the 4D CAD environment. By combining positional and orientation information, the proposed system enables alignment of the virtual camera in the 4D model with the actual shooting conditions of the site photograph.
Figure 6. Information acquired from smartphone sensors.

4.3. Synchronization of Photograph Information and 4D Model Coordinates

4.3.1. Linkage with the 4D Model Viewer

As shown in Step C of Figure 4, the positions of the photographer and virtual camera of the 4D viewer were matched to link the information obtained from the photograph with the virtual camera. The virtual camera represented the viewpoint of the 4D model. To link the same object to a 4D viewer as a site photograph, the location of the virtual camera in the 4D viewer and camera property information must be adjusted. The first step in this process is to acquire X, Y, and Z coordinate values, which represent the location information of the virtual camera, using photographic data. The latitude and longitude coordinates were then transformed into X and Y values using TM coordinate transformation. Next, the position coordinates of the virtual camera are linked using the derived TM coordinates, and the height information of the virtual camera is linked using the elevation values collected during camera capture.

4.3.2. Adjustment of 4D Model Viewer Region

After linking the location coordinates of the virtual camera to the 4D viewer, the same object in the site photograph was connected to the 4D viewer by adjusting the camera’s property information. The method of adjusting the virtual camera or view may vary depending on the implementation environment of the 4D model. In this study, a coordinate linkage method was developed between the site photograph coordinates and a virtual camera based on the concept of a virtual camera in Autodesk’s Revit and Navisworks programs. The viewer’s area in Revit can be adjusted by altering the size of the crop box, indicating the size of the view. The cropping screen size can be adjusted at the location of the virtual camera, which is specified between the maximum and minimum values of the crop box, as illustrated in Step B of Figure 4.
Additionally, the viewer’s FOV, focal length, film dimensions, and screen aspect ratio (e.g., 3:4 and 16:9) can be used to adjust the viewer’s region without using the focal length parameters. The FOV can be calculated using the following equations for the focal length, FOV, and film dimensions:
F o c a l   l e n g t h = 1 2 ∗ f i l m   d i m e n s i o n t a n F O V 2
The default values of the Revit viewer included an FOV of 50°, a fixed focal length of 38.6 mm, and film dimensions of 36 mm. The default crop box area was 150 mm × 113 mm, with an aspect ratio of 4:3. For example, let us assume that a photograph, captured at a construction site, has an FOV of 60°. In this case, the process for calculating the crop box can be expressed as:
F o c a l   l e n g t h = 1 2 ∗ 36   mm t a n 60 ° 2 = 31.2   mm
150   m m   : 31.2   m m = x   : 38.6   m m   ∴ x = 185.6   m m
4   : 3 = 185.6   : y ∴ y = 139.2
When shooting FOV is 60°, the focal length is 31.2 mm. When the focal length is set to 38.6 mm in Revit, the horizontal length of the crop box is calculated to be 185.6 mm, as shown in Equation (2). Using a 4:3 aspect ratio, the vertical length of the crop box is calculated as 139.2 mm. In 4D model implementation environments, such as Autodesk’s Revit and Navisworks, the crop box area can be modified to 185.6 × 139.2 mm using the steps outlined above. The user can link the same 4D model to the object in the site photograph using the same view as the FOV captured in the site photograph. When the focal length is set to 28 mm, and the aspect ratio is 4:3, the crop box value is 206.78 mm × 155.085 mm, as shown in the bottom-right panel of Figure 7.
Figure 7. Linkage of site photographs and 4D viewpoints with changes in the coordinates.

4.3.3. Conversion of the Coordinate System of Photograph Information

Figure 7 illustrates the process of linking viewpoint coordinates with the smartphone’s longitude and latitude coordinates, and the camera’s elevation, inclination, and focal length or FOV information by matching the camera’s basic property information. The location information obtained from the smartphone’s built-in GPS provided latitude and longitude coordinates on a polyhedral plane. However, these coordinates must be converted into the planar Cartesian coordinate system to match the coordinate system used in the 4D model. To this end, a projection equation, utilizing a conversion equation, published by the Korean National Geographic Information Institute (NGII) was employed to transform the longitude and latitude data on an ellipsoidal plane into Cartesian plane coordinates.
For example, if the shooting location has longitude and latitude values of 36.639346 and 127.305626, respectively, as indicated in the bottom-left panel of Figure 7, then they are transformed into TM coordinates using the Korean control point. The X and Y values obtained by translating the longitude and latitude values into TM coordinates using the conversion formula are 449,049.28616 and 227,328.99574, respectively, as shown in the bottom-right panel of Figure 7. Once translated into 4D model coordinates, the object within the 4D model, corresponding to the planned schedule for the shooting date of 5 April 2021, was identified. In this study, the accuracy of coordinate linkage between site photographs and the 4D model was verified qualitatively through visual correspondence rather than through quantitative metrics such as reprojection error. The synchronization level is intended to be sufficient for visual progress comparison rather than precise geometric alignment.

4.4. Structural Image Detection Using Deep Learning

4.4.1. Evaluation Procedure of Deep Learning

The process of developing a bridge structure detection model based on image deep learning largely consists of three stages: image collection and data organization, YOLO v3-based image training, and model evaluation as in Figure 8. The first stage involves collecting images for deep learning training and annotating the collected images for supervised learning. The second stage involves deep learning training using the constructed dataset. Variables such as learning parameters were specified, and transfer learning and data augmentation were used to improve learning accuracy. The third stage involves evaluating the trained deep learning model. The model is evaluated using the test dataset, which was divided into training and test data in Step 1.
Figure 8. Deep learning application for image detection.
The structures in the field image can be detected, and their areas can be marked by learning the structures in the site photographs. Various machine learning (ML) based object detection algorithms, specifically deep learning approaches using convolutional neural networks (CNNs), have been developed, including regions with CNN (RCNN), You Only Look Once (YOLO), and Faster R-CNN. To understand the progress rate of a construction site when compared to that of a 4D model based on site photographs, the ability to detect and infer the type of structure in a photograph is necessary. In this study, we employed deep-learning algorithms to identify structural objects from site photographs, with the target application limited to bridge facilities. The proposed approach focuses on intuitive and approximate visual evaluation of construction progress through comparison between site photographs and 4D images, rather than fine-grained object recognition. For this purpose, YOLOv3 was adopted due to its stable inference performance and computational efficiency, which are suitable for repeated application in practical construction site environments [28].

4.4.2. Image Composition for Deep Learning

To construct deep learning training images, images of the target to be trained must be collected, data that influences training must be filtered, and then each image must be labeled and annotated for supervised learning. Construction site images can be collected through various methods. Construction site images can be used for training using ImageNet, web crawling (Google image search), image collection through search, and construction site photos. The collected images go through a filtering process to filter out images that negatively influence training or are redundant, as shown in Figure 8 [29]. The filtered images are then annotated using an image labeling tool, which assigns bounding boxes and classes to objects in the images. The annotated images are divided into a training dataset and a test dataset.
To perform image deep learning, the target object must be selected and the image dataset required for training must be constructed. A large amount of image data is required to achieve good training results. While ImageNet can be used to obtain annotated images, this study selected a bridge as a construction structure and aimed to build a model to detect objects by element. Because pre-training data for each bridge element using ImageNet is difficult to collect for image deep learning, various methods must be used to collect images and a preprocessing process to annotate each image. Web crawling, used in this study to collect images, involves gathering various types of data from the web. This study collects images based on keywords.
The web crawling process utilizes the BeautifulSoup library based on Python 3.7, and images of bridge structures are collected from Google. Keywords such as “bridge,” “construction bridge,” “pier,” and “girder” were selected in both Korean and English to collect images. As shown in Figure 9, over 2000 images were collected. The collected images were selected to identify completed and ongoing bridge construction. As shown in Figure 9, images with low relevance to the bridge, duplicate images, low-resolution images, and other images that could affect deep learning were filtered out to create a training dataset. The final image data consisted of 523 images, filtered to only those that could identify specific elements of the bridge.
Figure 9. Image filtering for deep learning.

4.4.3. Training Dataset

Image deep learning relies on supervised learning to learn label data for objects within images. Data collected through ImageNet is annotated with object information, allowing it to be directly utilized in deep learning training. However, if only image files are collected, such as through web crawling, object annotations must be performed. The image file preprocessing process is illustrated in Figure 10.
Figure 10. Preprocessing procedure for collected images.
Within an image, user can specify the object classes they want to identify and use a labeling tool to annotate the objects within the image. In this study, classes were classified to conduct image deep learning training on bridges. As shown in Figure 10, six classes were classified: foundation, pier, coping, girder, slab, and tower. The LabelImg tool was used to label objects within the image based on the classified classes. Image annotation involves loading an image into the labeling tool, designating a bounding box for the object within the image, and entering a class. The bounding box consists of the coordinates of the upper left and lower right vertices within the image. Figure 11 shows the LabelImg tool being used to load an image of a bridge, designating a girder area within the image, and entering a Girder class value. Images annotated according to their classes are divided into training data for image deep learning and test data for evaluating learning models. In this study, 418 datasets (80%) of the 523 datasets were divided into training datasets and 105 datasets (20%) were divided into testing datasets.
Figure 11. Input screen for label data.
To address the limited availability of training data, data augmentation techniques were applied during training. Specifically, image scaling, horizontal flipping, and brightness variation were employed to improve robustness against viewpoint and lighting changes. Transfer learning was adopted to enhance training efficiency using a limited dataset. For object detection, site images were first collected and annotated with bounding boxes corresponding to target structural components. The labeled images were then used to train the deep learning model, and training parameters were adjusted to improve detection performance. When an image is input into the trained model, the model identifies object classes and outputs bounding box coordinates for each detected object, as illustrated in Figure 12.
Figure 12. Object detection.

4.4.4. Application of the YOLO-Based Image Detection Learning Model

Table 2 presents the results of the YOLO v3 model training using the collected data. The mAP index, which examines the object detection algorithm, was used to evaluate the performance of the model. The mAP@0.5 index is the average precision calculated by assuming that the intersection over the union value, which shows the degree of matching of the bounding boxes, is 0.5 or greater. As indicated in Table 2, the mAP@0.5, of all classes was 0.532, with the pier having the highest value (0.713), and the slab having the lowest value (0.274). These detection results were used to compare the schedules of the photographs and 4D model.
Table 2. Results of the learning model by bridge class.
The deep learning–based object detection model was implemented using the PyTorch framework (version 1.12.1) and TensorFlow (version 2.3) in a 64-bit Windows environment with Python 3.7. YOLOv3 was used for structural object detection and executed in a CPU-based environment. The confidence threshold was set to 0.3. The model was trained for 300 epochs with a batch size of 5. The initial learning rate was set to 0.01 and reduced to 0.0005, with momentum and weight decay values of 0.937 and 0.0005, respectively. HSV-based color augmentation and basic geometric transformations were applied to improve robustness under varying site conditions.

4.5. Progress Rate Calculation by Overlapping Deep Learning Images and 4D Models

4.5.1. Comparison Between Site Photographs and 4D Model Information

To compare the site photographs and 4D model, their viewpoints were synchronized and connected using the same 4D viewer. However, this synchronization did not account for the shooting date. Therefore, after viewpoint synchronization, shooting date information from the field must be used to link the 4D model to the same date as the site photographs. As shown at the top of Figure 13, the viewpoint coordinates and 4D model viewer were synchronized to match the screen angle of the site photographs using the location and shooting information of the photograph captured on 13 February 2021.
Figure 13. Comparison of site photographs and 4D models.
The progress status of the schedule can be visually compared by synchronizing the coordinates of the site photographs and viewpoints of the 4D model, and searching for the 4D model based on the shooting date. Images of the site photographs and those of the 4D model are compared, as illustrated in Figure 13. This is the same image that was discovered using the 4D model and object detection technique on 13 February 2021. As shown in the photographs on the left side of Figure 13, the girder schedule is in progress as of 13 February 2021. However, the 4D image on the right side of Figure 13 shows that the girder schedule based on the same date is not in progress. Therefore, the girder schedule as of 13 February 2021, was considered an excess schedule. The progress status of the on-site structural object can be assessed as normal, delayed, or in excess when compared to the planned schedule if the coordinate values of the structural object in the site photographs and 4D model of the planned schedule are in agreement.

4.5.2. Progress Rate Calculation by Overlapping Photographs and 4D Models

To estimate the progress rate of the timetable, the deep learning results of the site photograph, where the actual work was performed, and the 4D model images were compared based on the planned schedule. To accomplish this, the object location must be described as a bounding box following object detection in the image of the site photographs and the 4D model using the trained deep learning model, as shown in Figure 13. In Figure 14, Pier 1 is excluded from the progress rate analysis because there is no overlapping position in either photograph. Conversely, pier 2 was subjected to a progress rate analysis because its location overlapped. The degree of overlap between the bounding boxes in both photographs was used to calculate the progress rate.
Figure 14. Search for the overlapped images of site photographs and 4D models via deep learning.
The schedule status information can be quantified by comparing the field image and 4D model after extracting the 4D model for each WBS code to compare the field image and 4D model and link the result to the 4D schedule information. This process is illustrated in Figure 15. The progress rate calculation system considers the bounding box values of the 4D model and those of the site photographs, which are output as ’WBS code names of the 4D model. The number of bridge structures detected in the image is equal to the bounding box value of the site photograph. Next, the overlap is calculated using the bounding box value to determine whether there is a structure in the site photographs at the same position as the bounding box of the detected structure in each image of the 4D model.
Figure 15. Process of progress measurement by comparing construction site images and the 4D model.

4.5.3. Calculation of Bounding Box Overlap

If the bounding boxes of the field image and BIM object image do not overlap, then the objects are considered different. Moreover, if no value overlaps with the bounding box value of the field image, it is assumed that the schedule has not yet proceeded and is classified as a delayed schedule. However, if overlapping areas exist where the bounding boxes intersect, they are considered to be the same object. The intersection points of the bounding boxes are used to determine the overlapping areas of the bounding boxes, as shown on the right side of Figure 15. The overlapping area shown in yellow in the figure can be computed as (a2 − a1) × (b2 − b1) using the values of points (a1, b1) and (a2, b2), where the bounding boxes of the blue 4D model image and bounding box of the orange site photograph image cross. The overlap can be calculated using the ratio of the overlapping area, where the bounding boxes of the 4D model image and site photograph cross based on the area of the 4D model image.

4.5.4. Calculating the Degree of Overlap Between Deep Learning Images and 4D Models

When structures overlap because of the shooting angle, multiple bounding boxes within the site photograph may overlap. Additionally, even when comparing overlaps with the 4D images, the bounding box in the 4D model image and several bounding boxes in the site photograph image may overlap.
In this situation, given that the progress rate is measured based on the 4D model, according to the planned date, the schedule progress rate can be estimated by determining whether an object with a large overlapping region based on the 4D model is the same as the corresponding 4D model. A comparison of the overlap between the object found in the field image and that found in the 4D image revealed that they are the same object, and the progress rate can be estimated by comparing the horizontal and vertical lengths or widths of the bounding boxes. The computed progress rate is then used in conjunction with the stored WBS code to derive individual photographs of the 4D model. The site photograph can be compared with that of the 4D model to obtain numerical information regarding schedule progress status.
The progress rates derived from bounding box overlap represent approximate indicators rather than exact physical quantities. Minor errors in camera pose estimation or object detection may affect overlap ratios; however, the method is intended as a decision-support tool for visual schedule monitoring.

4.6. Case Study of Progress Rate Calculation by Overlapping Deep Learning Images and 4D Models

The top-left corner panel of Figure 16 shows the viewpoint of the 4D model using the shooting information of the photograph captured at a resolution of 1280 × 960 pixels. The first panel in Figure 16 (bottom left) shows an image file generated individually for each WBS code of the pier sphere in the 4D model. The file name of the image was outputted as the WBS code for the pier sphere. The 4D model for each object’s WBS code was compared with the site photograph, and the progress value was entered for each object separated by the WBS code. If the 4D model is not separated into piers and copings, the two bounding boxes of the piers and copings are derived from a single image, as illustrated in the first panel at the bottom left of Figure 16.
Figure 16. Viewpoint link for progress measurement.
The bridge pier structure used in this case study is a circular concrete structure with copings. The pier span is approximately 30m, and it is a multi-span railway bridge composed of concrete girders. Because the on-site construction had to be photographed and a 4D model prepared, only a few projects met the criteria. In terms of bounding box accuracy based on photographic information, the relative ease of measuring concrete structures was considered.
Figure 16 displays the deep learning model results for the site photograph in the top-right corner and individual photographs of the 4D model in the bottom panel. Girders and piers were identified and retrieved separately from the third 4D image. However, the bridge pier was misidentified in the BIM implementation environment and had no overlapping values, which led to its exclusion. Table 3 and Table 4 present the object detection results for the individual photographs of the 4D model and object detection results of site photographs, respectively. The WBS code A1.B1.2.03.2, listed in the last row of Table 3, was used to identify the girder. The top-left coordinate value of the bounding box for the identified girder was (0, 27), and the bottom-right coordinate value was (395, 314). To generate an equivalent 4D model, the same object was identified by comparing the bounding box coordinate values of the site photographs listed in Table 4.
Table 3. Object detection results of 4D model images.
Table 4. Object detection results of construction site photographs.
The objects in the field image were analyzed based on their overlap values, which revealed that the piers and copings were not considered to be the same objects owing to their low overlap values of 0.8% and 1.2%, respectively. The object with the highest overlap value was the girder located at the top-left corner of the field image with coordinates (0, 10) and (395, 327). The girder in the 4D model with a WBS code of A1.B1.2.03.2, and the girder in the site photograph with an overlap of 90.5% were considered the same object because they belonged to the same class.
The bounding box of the 4D model girder had an area of 125,215, horizontal length of 395, and vertical length of 317. In comparison, the bounding box detected by the girder in the field image had an area of 113,365, horizontal length of 395, and vertical length of 287. The progress status of the schedule was estimated as 90.5%, 100%, and 91.1% based on the area, horizontal length, and vertical length, respectively. If the horizontal length had the highest value, then the progress of the schedule was considered complete. Based on the area with the smallest value, we determined that at least 90.5% of the schedule was completed.

5. Development of a Progress Comparison System for Site Photographs and 4D Model

5.1. System Architecture

In this section, we present a system design that graphically compares the scheduling status by matching site photographs with a 4D model. This increases the utilization of site photographs of construction projects using the methods described above. This system uses a 4D CAD system that compares a simulated plan 4D model with site photographs from the same date using deep learning. Figure 17 illustrates the main architecture of the system.
Figure 17. System architecture of synchronized 4D CAD system with photo coordinates.
The system synchronizes the 4D model with the structure of the site photographs by linking the shooting information from the site photographs to the viewpoint of the system. This coordinate linkage allows for the extraction of 4D model images and detection of objects in the images using site photographs. Furthermore, the system applies deep-learning models to 4D images. By examining the overlap between the site photographs of the deep-learning model and bounding box created in the 4D model, an approximate progress rate can be estimated by determining the same objects and analyzing the overlap size of the bounding box.
As illustrated in Figure 17, the proposed system consists of several interconnected modules, including a data input module, a 4D model linking module, a deep-learning image module, a progress quantification module, and a viewer module for synchronized visualization. First, site photographs and associated shooting information are provided through the data input module. The shooting information, including spatial location and orientation parameters, is transformed within the 4D model linking module and linked to the viewpoint coordinates of the 4D CAD system. This process enables the system to search for and extract individual 4D model images corresponding to the same shooting date and camera viewpoint as the site photographs.
Next, both the site photographs and the extracted 4D model images are processed by the deep learning image module to detect structural objects. The detection results are represented as bounding boxes and stored as deep learning outputs. The progress quantification module then compares bounding boxes detected in the site photographs with those derived from the corresponding 4D model images. By analyzing geometric relationships such as overlap area and bounding box size, the system determines object correspondence and estimates an approximate construction progress rate. Finally, the viewer module visualizes the synchronized site photographs and 4D model images, along with bounding box overlays and progress information, allowing users to intuitively verify the estimated schedule status.

5.2. Configuration of Synchronized 4D CAD System with Photograph Coordinates

5.2.1. Basic Functions of Synchronized 4D CAD System with Photograph Coordinates

The 4D CAD system used in the study utilizes the linear 4D CAD system developed by the research team in a previous study [30]. This system uses a linear schedule chart to simultaneously display activity schedule and location information, enabling simulations based on construction dates. The basic system layout is shown in Figure 18.
Figure 18. Linear 4D CAD system [30].
In this study, a functional module for synchronizing and comparing site photos and 4D models was added to the previously developed system. The main modules of the system developed in this study are the data input module, 4D model linking module, viewer module, deep learning image module, and quantification module, as shown in Figure 17.
Data Input Module
The image data input module is designed to input and manage site photos and shooting information taken for progress measurement. Site photos images are input as .jpg files, and site shooting information files are input as .csv files. This module stores data required for progress measurement, including shooting date, location, and camera tilt.
4D Model Linking Module
The 4D model linking module utilizes the shooting information data entered through the image data input module and links it to 4D viewpoint coordinates. Since the coordinates in the 4D implementation environment and the coordinate system of the site photo shoot information are not identical, a detailed function for converting them is included, and a function for compensating for this according to the accuracy of the GPS sensor is included. The coordinate information converted to suit the 3D environment is linked with the viewpoint of the 4D viewer to align the structure in the field photos with the 4D model. After linking the 4D model with field photos, a function is included to search for the 4D model according to the shooting date of the site photo and display it in the 4D viewer.
Viewer Module of Site Image and 4D Image
The site photo and 4D image viewer module consist of a viewer that allows users to view inputted site photos within the system, and a viewer that extracts and displays screen images from the 4D viewer, matched by the 4D model linking module, within the system. The module requires functionality for inputting site photos and extracting and linking 4D images with the same field shooting date from the 4D viewer. When outputting individual images, the file information is linked to the 4D model’s WBS code. Since the construction progress is estimated based on the bounding boxes of the site photos and 4D models, the resolution of the photos and 4D models must be matched during image input and output. Accurate estimation of construction progress using deep learning-based structural object detection models is challenging. If an object is not detected, the user must be able to compare the site photo viewer with the 4D image viewer. To achieve this, the system allows simultaneous viewing of both the site photo viewer and the 4D image viewer, allowing users to understand the construction progress.
Deep Learning Image Module
To compare field images with 4D images, the image deep learning module uses individual or all site photos and 4D images as input data to run a deep learning model and output a text file indicating the area and class of objects detected in the images. By applying deep learning to site images and 4D images, structures within the images can be compared. Furthermore, the output text file is used to quantify the progress of the construction project.
Quantification Module of Progress Status
The progress status comparison and measurement module use bounding box information contained in the text file for each image derived from the deep learning module as input data. It first compares the bounding boxes in each field image with the bounding box coordinates in the 4D model image to calculate the degree of overlap between the bounding boxes in the images. After calculating the degree of overlap, objects with a high degree of overlap are identified as identical. The progress status is then quantified by comparing the length and width of the bounding boxes. Construction projects consist of activities with a sequential relationship. Even if a deep learning model does not detect an object, if a subsequent activity is determined to be in progress or completed, a function capable of compensating for the status of the preceding activity is needed. In cases where a deep learning object detection model fails to recognize a foundation pile, for example, if the object detection model recognizes a preceding activity, such as a pier, coping, or girder, the preceding activity is considered complete.

5.2.2. Layout Scheme of Synchronized 4D CAD System

The main screen of the image object synchronization system is shown in Figure 19. The left side of the main screen is configured with an image data input module for loading photos taken at the construction site. As shown in Figure 19, the center of the screen features a viewer that allows users to enlarge and view the selected image. Based on the shooting information entered with the image, a 4D model corresponding to the viewer coordinates and shooting date is linked in the 4D CAD system, and the viewer image can be viewed in the 4D image viewer on the right side. The input images and their corresponding shooting information can be viewed in the lower left, and the shooting information for the image can be checked according to the selected image. Furthermore, a function for correcting X, Y, and Z values is configured in the lower left corner to compensate for errors that may occur during GPS sensor errors or automatic conversion from latitude and longitude coordinates to TM coordinates. By applying a deep learning model to the input image, the system can also verify the objects and bounding box values derived from the site image and 4D image. To individually review 4D model images, the ON/OFF function for objects is utilized based on the WBS code. By linking the site photo coordinates with the 4D image’s viewpoint coordinates, the site photos and 4D model can be synchronized, allowing for visual comparison of the progress of the project.
Figure 19. Layout of synchronized 4D CAD system with photograph coordinates.

5.3. 4D Model of Shooting Information and Application of Deep Learning

5.3.1. Synchronization for 4D Model with Photograph Coordinates

To apply the 4D model synchronization system for site images developed in this study, due to some difficulties in selecting projects currently in progress, we applied the system to completed projects, using archived photographic images from the corresponding dates, based on their progress. The application scenario is shown in Figure 20.
Figure 20. Process of synchronization for 4D model with photograph coordinates.
Scenario implementation can be broadly divided into three steps. First, site photos and shooting information are input into the system for automatic coordinate conversion. The converted coordinates and shooting information are then linked to the camera coordinates within the 4D system. This allows the viewer to be linked from the same angle as the site photos and search for a 4D model with the same shooting date. Second, the linked 4D model is compared with the site photos, and each 4D model is extracted as an individual image and stored. The resolution of the site images and individual 4D images is adjusted to match, and the results are then applied to the trained deep learning model. Third, bounding box values are used to calculate the overlap between objects in the site images and the 4D model, determining whether they are identical. The length and width of the boxes are then compared to provide the user with a rough estimate of the progress of the construction. Site photos were captured using an Android-based app to obtain GPS information and shooting information. The captured images and the captured shooting information are saved as a CSV file with the same file name as the photo file and entered into the system. The CSV file contains the shooting date, shooting location based on latitude and longitude coordinates, shooting altitude, azimuth, and camera tilt values, and is used when linking to viewpoint coordinates within the 4D CAD system.
Through this process, the proposed method enables the reconstruction of the camera viewpoint at which a site photograph was captured within the 4D CAD environment. By transforming the shooting location and orientation information into corresponding viewpoint parameters, the system automatically generates a 4D model image that closely matches the spatial perspective of the site photograph.
The synchronized site photograph and 4D model image are then processed using a deep learning–based object detection model to identify structural components. Bounding box overlap and geometric comparison between detected objects are subsequently used to estimate construction progress in an automated manner. This workflow allows the proposed system to replace manual visual comparison with a repeatable and systematic procedure for photo-to-model synchronization and progress estimation.

5.3.2. Synchronization of the Photograph Image and 4D Model

To match the shooting information of on-site photographs with the 4D viewpoint, the photographed images are input into the photo and 4D CAD-based progress status comparison system, as shown in Figure 21. A CSV file with the same name as the input site photographs is also input along with the site photographs. The input images and shooting information files can be viewed within the system, as shown in Figure 21. The shooting information in the CSV file is automatically converted to TM coordinates and displayed within the system.
Figure 21. Automatic coordinate transformation.
Figure 22 shows the site photo viewer, showing the 2 October 2015 photo selected for comparison among the multiple input site photos. When the user selects the desired site photo, the shooting information coordinates of the site photo are linked to the 4D CAD system, as shown in Figure 22. As shown in the lower right corner of Figure 22, the 4D model corresponding to the date of the site photo, 2 October 2015, can be viewed in the 4D viewer. The 4D model viewed in the 4D viewer can be linked to the image viewer for visual comparison with the site photo, as shown in the top of Figure 22.
Figure 22. Synchronization with construction site photographs and 4D model.

5.3.3. Application of the Deep Learning Image Model

When site photographs and 4D models were linked by synchronizing 4D viewpoint coordinates and shooting dates, the object structures in the images were compared between the site photographs and 4D model images using deep learning. The upper panel in Figure 23 shows the effect of applying the 4D model image synchronized with the site photos to the deep learning image model. The detected class and bounding box are expressed and shown as a consequence of the object detection in the input image. Additionally, bounding box coordinates and object classes were provided as text files. In addition, coordinate information of the bounding box can also be confirmed in the system. As shown in Figure 23, the bounding box coordinate values of the field image and 4D image, which are the results of deep learning application, are linked to the photo analysis information and displayed together with the image deep learning viewer image.
Figure 23. Object detection result in the progress comparison system.
The top of Figure 23 displays images of the actual construction progress at the site, while the right screen displays a 4D model of the planned construction progress as of the date the photo was taken. The center of Figure 23 compares the progress status of the photo with the 4D model, based on a photo taken on 17 October 2015. While the left-side photo shows the completion of the pier and coping work, the pier and coping are highlighted in red in the 4D model image on the right, indicating that the work was still in progress as of 17 October 2015. Therefore, comparing the 4D model with the photo showing the planned progress as of 17 October 2015, confirms that the pier and coping work in the site photo has been completed, indicating that this represents an over-construction.
The bottom of Figure 23 compares the 4D model with a photo taken on 16 March 2017. The construction site photo on the left confirms that the girders, piers, and copings have been completed. In the lower right screen of Figure 23, some girders are highlighted in red, indicating ongoing construction as of 16 March 2017. While the site photo visually identifies objects in completed construction and provides bounding boxes, the 4D model confirms that the girders highlighted in red are not identified by object detection.

5.4. Quantification of the Schedule Status Using the Results of the Deep Learning Model

5.4.1. Calculation of the Progress Rate of the Case Project

The process of quantifying the schedule status involves obtaining visual comparison information of the schedule status by synchronizing site photographs and 4D model, which can be computed as numerical schedule status data and used by the schedule manager. Figure 24 illustrates the selection of a site photograph from a list of input site photographs to quantify the scheduling status. In Step ②, the viewpoint coordinates of the 4D system and 4D model are automatically synchronized and linked to the 4D viewer image. The 4D model was linked individually based on the WBS code and saved under the WBS code name, and WBS codes A1.B1.1.03.2 and A1.B1.1.02.2 are saved and inputted individually, as shown in the 4D viewer screen in ④.
Figure 24. Comparison between the actual and planned progress.
In the case project, the pier spheres are represented by WBS codes A1.B1.1.03.2 and A1.B1.1.02.2 of the 4D model. Given that the lower levels were not classified into piers and copings, the progress rates of the piers and copings were calculated separately, and the average of the two was used to calculate the overall progress rate of the concrete piers. The bounding box values of the 4D object images for each WBS code are compared, as shown in Figure 24, to determine whether they overlapped. In the case of overlapping objects, the user is provided with a numerical representation of the schedule status based on the ratios of the horizontal length, vertical length, and area of the bounding box in the 4D image.
The object considered as a pier in the site photographs had bounding box values of (304, 351, 364, and 434), and the object considered as a pier in the 4D model image has bounding box values of (322, 333, 376, and 440). The two bounding boxes overlapped, and the ratios of the area of the bounding box of the site photographs to the bounding box of the 4D model were 100% and 77% for the horizontal length, and 86% for the vertical length.
Since the area ratio of the bounding box is larger than the length and width, the area ratio value is calculated as the progress rate of the pier sphere (WBS code A1.B1.1.03.2). In addition, in the lower left of Figure 24, when the area, length, and width ratios were calculated using the bounding box coordinate values of the object detected by the coping, it can be confirmed that the progress rate was calculated as 100% in all three cases. Therefore, the progress rate of WBS code A1.B1.1.03.2 is entered as 100%, which is the average value of the pier progress rate of 100% and the coping progress rate of 100%. This means that when comparing the on-site photo taken on 17 October 2015 with the 4D model, the system can confirm that the construction progress corresponding to WBS code A1.B1.1.03.2 is an object that has completed progress as of the shooting date.

5.4.2. Schedule Status Based on the Progress Rate

Once the same site photographs and 4D model are identified, the progress rate can be calculated using the progress rate calculation function in the system, as illustrated in Figure 25.
Figure 25. Update of the progress measurement with the WBS code.
The overlapping size ratio between identical images is used to determine the approximate progress rate, and the calculated value is used as the progress status for each work type based on the actual WBS code. The progress of the schedule was grasped with the WBS code A1.B1.1.03.2 based on the shooting date of the site photograph on 17 October 2015. However, the code’s planning end date was 5 November 2015. The progress status of the schedule obtained from the deep-learning image results was considered complete and could be visually validated through direct visual inspection. Therefore, photograph image comparison technology and deep learning of 4D photographs can be used to intuitively determine the scheduling status. The estimated progress rate represents a practical engineering indicator for interpreting whether construction activities are generally on schedule, delayed, or substantially completed, rather than a precise measurement for contractual purposes. Furthermore, when schedule management practitioners must quantify the progress rate, the procedure above can be used to calculate the approximate progress rate and incorporate it into scheduling management practices.

6. Conclusions

In this study, we propose a methodology and system for intuitively analyzing the construction schedule progress and completeness using deep learning techniques to compare the property values of site photographs and 4D model frames corresponding to the same time point. Images of the bridge structures were collected using a web crawling technique, and 523 images were used for training the model. After the final learning model was evaluated, mAP@0.5 value for all classes of the trained model was 0.532. Among the different classes considered, the bridge pier had the highest mAP@0.5 value of 0.713, whereas the slab had the lowest value with an mAP@0.5 of 0.274. The piers were considered to exhibit high index values for each bridge class because the shape of the object did not vary significantly based on the angle and there were numerous standardized shapes. Conversely, the slabs had low index values because the features of the object images varied substantially based on the angle, thus requiring numerous images for training.
We propose using a coordinate system transformation and viewer area designation process to link the information acquired from site photographs with the viewpoint information of a 4D model viewer. Consequently, a visual comparison of the scheduling status was enabled by linking the same location and shooting conditions as viewpoints, and automatically searching for the planned 4D model and actual image objects at the same time point. In this study, a 4D CAD system integrating deep learning-based analysis and automatic coordinate synchronization was developed to link 4D models and site photographs for comparing actual construction progress with planned schedules. The developed system intuitively compares the schedule status for the same time point of the site photographs and 4D model using deep learning analysis results. Furthermore, the system enables verification of the process of extracting the progress rate by synchronizing site photographs and the 4D model by applying it to an actual bridge.
A method for quantifying the image-based progress status and using it as a progress rate was built into the 4D CAD system to use visualization technology to compare progress statuses by linking site photographs with the 4D model. When the schedule progress was estimated for the case project using the deep learning model and bounding box coordinate values, progress rates of 90.5%, 100%, and 91.1% were calculated based on the bounding box size, horizontal length, and vertical length, respectively.
The detection rate may be poor based on the shooting angle of the image and presence or absence of obstacles such as temporary equipment. When the structures overlap, the image detection rate may decrease toward the back [31]. Consequently, more images must be learned to improve the object detection rate. The progress rate presented in this study was calculated based on the degree of overlap between the site photograph and 4D model. Therefore, the estimated progress rate should be interpreted as an approximate indicator rather than an exact quantitative measure. Despite being a rough progress measurement, the current progress management status can be easily visualized by comparing the actual construction progress in the on-site photos with the planned progress in the 4D model. This advantage offers greater on-site usability compared to numerical data-based progress management methods.
This study has limitations, including validation on a single bridge project and the absence of explicit uncertainty quantification. When applying the trained model to other construction sites, detection performance may degrade due to differences in structural configurations and construction sequences that were not represented in the training data. In addition, detection accuracy may be affected by occlusions caused by temporary facilities or equipment, variations in lighting conditions, and differences in camera viewpoints, which are common in practical construction environments. Future work will focus on expanding the training dataset to cover a wider range of structural types, improving detection robustness and quantifying uncertainty in progress estimation.

Author Contributions

Conceptualization, L.-S.K.; writing—original draft preparation, S.-M.P. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Research Foundation of Korea project grant number RS-2025-21882984.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors on request.

Acknowledgments

Part of this study is based on the research results of the National Research Foundation of Korea project (RS-2025-21882984).

Conflicts of Interest

Author Sang-Mi Park was employed by the company Korea Hydro & Nuclear Power Co. Ltd. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Golparvar-Fard, M.; Peña Mora, F.; Savarese, S. D4AR―A 4-dimensional augmented reality model for automating construction progress-monitoring data collection, processing and communication. J. Inf. Technol. Constr. 2009, 14, 129–153. [Google Scholar]
  2. Yoon, S.W.; Chin, S.Y. An information framework for the derivation of process context from construction site digital images. Korean. J. Constr. Eng. Manag. 2005, 6, 80–91. [Google Scholar]
  3. Asadi, K.; Ramshankar, H.; Noghabaei, M.; Han, K. Real-time image localization and registration with BIM using perspective Alignment for Indoor Monitoring of Construction. J. Comput. Civ. Eng. 2019, 33, 04019031. [Google Scholar] [CrossRef] [Scilit]
  4. Kang, S.H.; Jung, Y.S. Data acquisition technology (DAT) selection algorithm for automated progress measurement and management. J. Constr. Eng. Manag. 2012, 13, 77–86. [Google Scholar] [CrossRef] [Scilit]
  5. Behnam, A.; Wickramasinghe, D.C.; Ghaffar, M.A.A.; Vu, T.T.; Tang, Y.H.; Isa, H.B.M. Automated progress monitoring system for linear infrastructure projects using satellite remote sensing. Autom. Constr. 2016, 68, 114–127. [Google Scholar] [CrossRef] [Scilit]
  6. Anwar, N.; Najam, F.; Izhar, M.A. Construction monitoring and reporting using drones and unmanned aerial vehicles (UAVs). In The Tenth International Conference on Construction in the 21st Century (CITC-10), Colombo, Sri Lanka, 2–4 July 2018; CITC Global: Colombo, Sri Lanka, 2018; pp. 2–4. [Google Scholar]
  7. Pučko, Z.; Šuman, N.; Rebolj, D. Automated continuous construction progress monitoring using multiple workplace real time 3D scans. Adv. Eng. Inform. 2018, 38, 27–40. [Google Scholar] [CrossRef] [Scilit]
  8. Puri, N.; Turkan, Y. Bridge construction progress monitoring using lidar and 4D design models. Autom. Constr. 2020, 109, 102961. [Google Scholar] [CrossRef] [Scilit]
  9. Han, K.K.; Golparvar-Fard, M. Appearance-based material classification for monitoring of operation-level construction progress using 4D BIM and site photologs. Autom. Constr. 2015, 53, 44–57. [Google Scholar] [CrossRef] [Scilit]
  10. Lin, J.J.; Han, K.K.; Golparvar-Fard, M. A framework for model-driven acquisition and analytics of visual data using UAVs for automated construction progress monitoring. In Proceedings of the 2015 International Workshop on Computing in Civil Engineering, Austin, TX, USA, 21–23 June 2015; ASCE: Reston, VA, USA, 2015; pp. 156–164. [Google Scholar] [CrossRef] [Scilit]
  11. Neuville, R.; Pouliot, J.; Billen, R. Identification of the best 3D viewpoint within the BIM model: Application to visual tasks related to facility management. Buildings 2019, 9, 167. [Google Scholar] [CrossRef] [Scilit]
  12. Turkan, Y.; Bosche, F.; Haas, C.T.; Haas, R. Automated progress-tracking using 4D schedule and 3D sensing technologies. Autom. Constr. 2012, 22, 414–421. [Google Scholar] [CrossRef] [Scilit]
  13. Braun, A.; Tuttas, S.; Borrmann, A.; Stilla, U. Improving progress-monitoring by fusing point clouds, semantic data and computer vision. Autom. Constr. 2020, 116, 103210. [Google Scholar] [CrossRef] [Scilit]
  14. Vincke, S.; Vergauwen, M. Vision based metric for quality control by comparing built reality to BIM. Autom. Constr. 2022, 144, 104581. [Google Scholar] [CrossRef] [Scilit]
  15. Omar, T.; Nehdi, M.L. Data-acquisition technologies for construction-progress tracking. Autom. Constr. 2016, 70, 143–155. [Google Scholar] [CrossRef] [Scilit]
  16. Chen, J.; Liu, D.; Li, S.; Hu, D. Registering georeferenced photos to a building information model to extract structures of interest. Adv. Eng. Inform. 2019, 42, 100937. [Google Scholar] [CrossRef] [Scilit]
  17. Deng, H.; Hong, H.; Luo, D.; Deng, Y.; Su, C. Automatic indoor construction process monitoring for tiles based on BIM and computer vision. J. Constr. Eng. Manag. 2020, 146, 04019095. [Google Scholar] [CrossRef] [Scilit]
  18. Fang, Q.; Li, H.; Luo, X.; Ding, L.; Rose, T.M.; An, W.; Yu, Y. A deep learning-based method for detecting non-certified work on construction sites. Adv. Eng. Inform. 2018, 35, 56–68. [Google Scholar] [CrossRef] [Scilit]
  19. Gong, J.; Caldas, C.H.; Gordon, C. Learning and classifying actions of construction workers and equipment using Bag-of-Video-Feature-Words and Bayesian network models. Adv. Eng. Inform. 2011, 25, 771–782. [Google Scholar] [CrossRef] [Scilit]
  20. Koo, B.S.; Jung, R.K.; Yu, Y.S. Automatic classification of wall and door BIM element subtypes using 3D geometric deep neural networks. Adv. Eng. Inform. 2021, 47, 101200. [Google Scholar] [CrossRef] [Scilit]
  21. Wang, Z.; Zhang, Q.; Yang, B.; Wu, T.; Lei, K.; Zhang, B.; Fang, T. Vision-based framework for automatic progress monitoring of precast walls by using surveillance videos during the construction phase. J. Comput. Civ. Eng. 2021, 35, 04020056. [Google Scholar] [CrossRef] [Scilit]
  22. Panah, R.S.; Kioumarsi, M. Application of building information modelling (BIM) in the health monitoring and maintenance process: A Systematic Review. Sensors 2021, 21, 837. [Google Scholar] [CrossRef] [Scilit]
  23. Wei, W.; Lu, Y.; Zhong, T.; Li, P.; Liu, B. Integrated vision-based automated progress monitoring of indoor construction using mask region-based convolutional neural networks and BIM. Autom. Constr. 2022, 140, 104327. [Google Scholar] [CrossRef] [Scilit]
  24. Ekanayake, B.; Wong, J.K.W.; Fini, A.A.F.; Smith, P.; Thengane, V. Deep learning-based computer vision in project management: Automating indoor construction progress monitoring. Proj. Leadersh. Soc. 2024, 5, 100149. [Google Scholar] [CrossRef] [Scilit]
  25. Tran, S.V.-T.; Lee, D.; Bao, Q.L.; Yoo, T.; Khan, M.; Jo, J.; Park, C. A human detection approach for intrusion in hazardous areas using 4D-BIM-based spatial-temporal analysis and computer vision. Buildings 2023, 13, 2313. [Google Scholar] [CrossRef] [Scilit]
  26. Chua, W.P.; Cheah, C.C. Deep-learning-based automated building construction progress monitoring for prefabricated prefinished volumetric construction. Sensors 2024, 24, 7074. [Google Scholar] [CrossRef] [Scilit]
  27. Hwang, J.Y.; Lee, J.H.; Kang, L.S. A study on the utilization of BIM model using vertex data-based Division method. LHI J. 2023, 14, 123–134. [Google Scholar] [CrossRef]
  28. Redmon, J.; Farhadi, A. Yolov3: An incremental improvement. arXiv 2018, arXiv:1804.02767. [Google Scholar] [CrossRef] [Scilit]
  29. Park, S.M.; Lee, J.H.; Kang, L.S. A framework for improving object recognition of structural components in construction site photos using deep learning approaches. KSCE J. Civ. Eng. 2023, 27, 1–12. [Google Scholar] [CrossRef] [Scilit]
  30. Lee, J.H.; Park, S.M.; Kim, S.K.; Kang, L.S. Linear 4D system using schedule-location charts for infrastructure projects. Autom. Constr. 2022, 141, 104413. [Google Scholar] [CrossRef] [Scilit]
  31. Park, S.M. Development of Visualization System for Deep Learning-Based Progress Comparison Using the Real Image of Construction Site and 4D Model. Ph.D. Thesis, Gyeongsang National University, Jinju, Republic of Korea, 2021. [Google Scholar]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.