Abstract
Photovoltaic (PV) expansion concentrates balancing pressure in the evening hours of receiving-end cities, and flexibility planning needs a benchmark that connects extreme ramping demand with deliverable resource capability. Existing adequacy practice compares installed capacity with peak load, so the evening operating window remains unpriced when installed capacity appears sufficient. Here we establish an evening net-load-ramp coverage-margin model, whose coverage margin equals deliverable resource capability, spanning power output, sustained energy, and interday replenishment, minus the annual 99th-percentile daily evening net-load ramp. In City A, the annual extreme evening ramp rose from 2610 MW in 2023 to 4328 MW in 2025, with the 2025 resource portfolio already at the coverage boundary ( MW under the historical-response capability convention), and specified 2030 scenarios span a 3338 MW interval between resource-lag shortfall and coordinated-development surplus. A held-out check confirms the cross-year stability of this state within the City A dataset. Portfolios with equal single-day power margins diverge over consecutive high-ramp days, because storage duration and interday replenishment determine whether coverage persists. These findings shift flexibility planning from static capacity matching toward coordinated configuration of power, deliverable energy per window, storage duration, and recoverable energy, and external validation in other receiving-end cities follows local recalibration.