Abstract
Uzbekistan began building its first nuclear plant, at Farish, in 2026 while moving from a single-buyer model to a wholesale electricity market. Part of the plant’s value may accrue to the single buyer, which procures peaking capacity outside the market, and not to its owner. This study quantifies that division. A PLEXOS capacity-expansion model for 2026–2035 was linked to a two-stage Nash–Cournot game solved for every hour, and the plant’s welfare effect was split among owner, single buyer, other producers, and consumers under three procurement rules. The planned units displaced 1700 MW of open-cycle gas turbine capacity and raised system cost by USD 892 million at a 10% real cost of capital and USD 17 million at 4%. Of a gross system value of USD 884 million, before USD 1765 million of fixed charges, the owner’s operating profit was USD 496 million and the single buyer saved USD 460 million. When procurement was held fixed, the owner captured almost all of a smaller value. What the owner does not capture reflects unremunerated capacity value, which incumbent market power narrowed slightly. Within the model, concessional finance plus a capacity payment equal to the avoided procurement covered the owner’s 2026–2035 funding shortfall.
1. Introduction
Uzbekistan generates most of its electricity from natural gas, which supplied 87.8% of the 66.5 TWh generated in 2020 [1]. Demand is projected to rise from 81 TWh in 2023 to 131–151 TWh by 2035 [2]. In June 2026 construction of the country’s first nuclear power plant (NPP) was launched at Farish. The plant comprises two VVER-1000 units and two RITM-200N small modular reactors of 55 MW each, at a reported base cost of USD 9.5 billion [3,4]. The plant is being built while the power sector moves from a single state buyer toward a wholesale market of separate generating companies [5,6].
The decision to build the plant rests on energy security and supply diversification [4]. The question that remains open is how the plant will be remunerated in the market now being created. In a single-buyer system, a nuclear plant creates value not only by displacing fuel but also by reducing the peaking capacity that the buyer must procure to meet demand. The second component is not necessarily reflected in the revenue the plant earns from energy sales. Any part of that value not captured by the plant’s owner, Uzatom, could only reach it from outside the market, by the state budget or by a long-term contract. Which of the two fits depends on why the value is not captured.
The distinction between the value of a plant to the system and the revenue it earns is well established. Levelized cost metrics omit the effect of a plant on the rest of the system [7], and system studies value firm low-carbon capacity by the fuel and peaking plant it avoids [7,8]. In an energy-only market, by contrast, a generator is paid for energy alone, and the price it earns declines as capacity is added, as shown for wind and solar [9]. Where scarcity prices are capped or capacity is procured outside the market, generators do not recover the full value of the capacity they provide, a problem known as missing money [10,11].
Market power introduces a second source of divergence. Equilibrium models of capacity expansion show that strategic producers invest less than a central planner [12] and that firms already withholding output gain little from additional capacity [13]. Once investors are risk-averse, investment also moves away from capital-intensive technologies [14]. Suski and Chattopadhyay applied an open-loop Nash–Cournot capacity-expansion model to Ukraine, which replaced its single-buyer model with a wholesale market in 2019, and compared strategic with price-taking investors [15]. For nuclear power specifically, a chronological simulation of the Greek market found that small modular reactors would generally earn positive results at European gas and carbon prices [16]. A bilevel model of a test system showed that adding reserve and capacity markets to an energy-only market raised producer surplus and social welfare [17].
Table 1 places these studies alongside the existing assessments of Uzbekistan. The cost-optimal expansion studies of the Uzbek system did not select nuclear capacity although it was available as a candidate [18,19], and a later study did not consider it [20]. These studies optimized a single planner and did not address who would receive the value of a plant in a market. The market-based studies of nuclear power concern liberalized markets or test systems, none of which has a single buyer procuring capacity beside the market. To the authors’ knowledge, the division of a nuclear plant’s value between its owner and a procuring single buyer, and the effect of incumbent market power on that division, have not been quantified.
Table 1.
Position of this study relative to related work.
The aim of this study is to quantify the system value of the planned Farish units and its distribution between the plant’s owner and other parties during Uzbekistan’s transition to a wholesale market. The study examines how the planned units change the open-cycle gas turbine (OCGT) capacity procured by the single buyer and why their value to the system differs from the operating profit captured by their owner. It also examines how financing terms and the market power of the incumbent thermal company affect that difference. A PLEXOS capacity-expansion model was linked to a two-stage Nash–Cournot game in which generating companies, defined by ownership, first invest and then compete in output in every hour of the same system. Both tools are established, and the contribution of the study lies in how they are combined and in the question they answer. First, the welfare effect of the plant is decomposed exactly under alternative procurement rules. Comparing the rules separates the capacity value retained by the procurer from the effect of market power, a distinction that neither a planning model nor a market model can draw on its own. Second, the planner and the game share the same data and the same 87,600 h, and the market stage was checked against an independent PLEXOS solution. The difference between the two valuations of the plant therefore reflects market structure and not differences in inputs or resolution. Third, the study provides, to the authors’ knowledge, the first market-based assessment of nuclear entry into a gas-dominated Central Asian power system with a single buyer. It also expresses the result as the support that a capacity payment or a contract for difference would need to provide.
2. Materials and Methods
2.1. Study System
Installed capacity in Uzbekistan reached 27.8 GW at the end of 2025, of which 17.7 GW was thermal, 2.4 GW hydropower, 5.9 GW solar, and 1.7 GW wind [21]. The government plans to retire about 5.9 GW of obsolete thermal capacity by 2030 [22], including the Syrdarya steam plant once new combined-cycle units on its site are in operation [23]. Gas for power generation is sold at a regulated price [24].
The two RITM-200N units of the Farish plant are scheduled for 2029 and the two VVER-1000 units for 2033 and 2035 [25]. Of the base cost of USD 9.5 billion [3], the 110 MW small-reactor plant has been put at under USD 1 billion [26]. A loan from Russia is under negotiation, and no interest rate has been published [27]. Comparable Rosatom export projects were financed by state credit, at a rate capped at 4% for Rooppur in Bangladesh [28,29] and at 3.95–4.95% for Paks II in Hungary [30].
Since 2019 the former vertically integrated utility has been unbundled into generation, transmission, and distribution companies [5]. The Electricity Law of 2024 provides for a wholesale market with bilateral contracts, a day-ahead segment, and balancing [6]. Until that market opens, Uzenergosotish purchases electricity as single buyer, and independent producers have entered under take-or-pay purchase agreements of 20 to 25 years, not as merchant investors [5,31]. The largest generator is JSC Thermal Power Plants, the state thermal company, and a few large generators are expected to dominate the new market until more competitors enter [31].
2.2. Analytical Framework
The study combines two models built on the same data (Figure 1). A least-cost capacity-expansion and dispatch model, built in PLEXOS [32], determines what a planner would build, and at what cost, with and without the planned Farish units. A two-stage Nash–Cournot game determines what the owners of the same system would build and earn. The planner’s Baseline run supplies the reference prices and loads that calibrate demand in the game, together with the hydropower and coal-fired schedules that the game takes as given. A procurement rule sets how much OCGT capacity the single buyer adds outside the market. Table 2 summarizes the main settings.
Figure 1.
Analytical framework of the study. NPP, nuclear power plant; OCGT, open-cycle gas turbine.
Table 2.
Main model settings.
2.3. Capacity-Expansion Model
The planner model represents Uzbekistan as a single node and was solved in PLEXOS 10 with Gurobi 11. The long-term plan minimizes the present value of capital and operating costs with no unserved energy allowed, and a short-term schedule dispatches the resulting fleet and sets the system price. Both phases were solved on every hour of the horizon, so that the hours which determine the need for firm capacity are represented explicitly.
The existing fleet is that of the end of 2025. The Syrdarya steam units (3165 MW) retire from 2027, and Tashkent units 4–12 (1410 MW) and part of the Navoi plant (780 MW) from 2030 [22,23]. Committed projects enter on their announced dates, and the planner may add combined-cycle gas turbines (CCGTs), OCGT, solar, and wind. Table 3 lists the technical and economic parameters of each technology. The overnight cost of the VVER-1000 is the reported base cost less the small-reactor plant. Interest during construction is added, and because capital is charged as an annuity only in the operating years inside the horizon, costs and benefits after 2035 are both excluded.
Table 3.
Technical and economic parameters of the generating technologies.
Three nuclear settings were run: Baseline, without the Farish units; NPP planned, with the units on the announced schedule; and NPP optional, in which the planner may choose each unit. The extra cost of the program is the difference in system cost between NPP planned and Baseline. Each setting was repeated under one alternative assumption at a time (Section 3.1).
2.4. Two-Stage Market Game
The game keeps the planner’s fleet but replaces the single decision-maker with companies, assigned by ownership and decision-making authority (Table 4). Its two stages follow the closed-loop structure of [12], in which capacity is chosen first, in anticipation of the market outcome it produces. JSC Thermal Power Plants and Uzatom are strategic. Independent producers under purchase agreements, Uzbekhydroenergo, and the procured OCGT are price-takers, and a renewable fringe may build solar and wind with free entry, as in [15]. Cournot competition was chosen because it requires only capacities, costs, and a demand slope, which suits a market with no record of bids [40]. Of the two strategic players, JSC Thermal Power Plants, the largest generator [31], holds most of the market power, while Uzatom sells little until its large units enter service.
Table 4.
Assignment of generating assets to players.
In the market stage, a Cournot equilibrium is solved for each of the 87,600 h of 2026–2035, with 29 February merged into 28 February. The payoff of player i is
where δt is the discount factor, pt the price, ci the marginal cost, qit the output in hour t, and Fi the present value of the capital and fixed operating costs of new capacity inside the horizon.
Three measures of a player’s financial position are distinguished throughout. Revenue is the discounted value of its energy sales. Operating profit is revenue less variable cost, the first term of Equation (1). The payoff πi, the final financial result, also deducts the fixed charges Fi, so a negative payoff is the funding shortfall that market revenue leaves uncovered.
Demand in each hour is linear, p = A − BQ, and passes through the price and load of the planner’s Baseline run [35]. Because Uzbekistan has no record of wholesale prices, the elasticity at that point could not be calibrated. The value of 0.25 lies between the average short-term and long-term price elasticities of electricity demand in a meta-analysis of international studies, 0.126 and 0.365 [41], and the sensitivity range of 0.10–0.50 covers both. The lower value equals the household elasticity used for Uzbekistan in [2]. Each strategic player must produce, in every hour, at least 70% of the output it would supply competitively at the same capacities. This is how PLEXOS applies the strategic property of its companies [35], and like a forward contract it limits withholding [42]. Until the market opens, the single buyer purchases all output, and the roadmap for the market converts the existing purchase agreements into two-way contracts for difference [31]. A large contracted share is therefore plausible in the first years of the market, and 70% is a central value within the range of 50–90% that was tested. At equal marginal cost, contracted independent producers are dispatched before JSC Thermal Power Plants, and the reverse order was run as a sensitivity.
The equilibrium was found by best response from three starting points (no new investment, the planner’s build, and the largest build) in two player orders, followed by a check of every unilateral deviation on the grid. For the fringe the check is an entry condition: each vintage it builds covers its cost, and the next 2000 MW step does not. A benchmark solves the same market at the same capacities with every generator as a price-taker, and the difference between the strategic market and the benchmark is taken as the effect of market power [15,43].
2.5. Procurement Rules and Value Decomposition
Procured OCGT is dispatched as a price-taker. Its quantity is set by the procurement rule and is not an investment decision of any player in the game, and its market margin less its annualized fixed cost is a net position of the single buyer. Under rule A, procurement adjusts to the plan. The single buyer procures the OCGT that the planner chooses for the same nuclear setting: 1300 MW in 2027 and 2800 MW in 2031 without the Farish units, and 1200 MW in each year with them. Under rule B, procurement is held at the Baseline level of 1300 and 2800 MW with the planned units in service, so that the effect of the plant is separated from that of the smaller procurement. Under rule C, no OCGT is procured and the market is energy-only. Rule A is the central case because it describes a single buyer that continues to procure capacity according to a least-cost plan. Rules B and C are not alternative calibrations. They are counterfactuals that isolate the part of the plant’s value that works through procurement.
For each rule and market structure, the case with the planned units was compared with the case without them. The system value of the plant is the change in welfare plus the plant’s own fixed charges FN, and it splits exactly into four parts,
where πNop is Uzatom’s operating profit from the Farish units, ΔΠB the change in the single buyer’s net position on procured capacity, ΔΠO the change in the payoffs of all other producers, and ΔCS the change in consumer surplus. Since welfare is consumer surplus plus all payoffs, Equation (2) holds by construction. All terms are present values at 10% over the same horizon, and the value-capture gap is the system value less πNop.
The system value is a gross measure. It is what the plant saves the rest of the system before its own fixed charges are deducted, so a positive system value does not imply a net benefit. The net change in welfare is ΔW, the system value less FN, and the owner’s funding shortfall is FN less πNop. Section 3.3 reports the three measures side by side. None of them includes benefits or costs that the models do not price, such as energy security or ancillary services beyond the reserve requirements tested by the planner; emissions enter only through the carbon-price cases.
2.6. Financing and Break-Even Capital Cost
Financing enters only through the fixed charges. No interest rate has been published for the Russian loan [27], so the two rates bracket it: 10% represents commercial terms, and 4% is close to the state credits for Rooppur and Paks II [28,29,30]. At 4% real the annuity of the nuclear capital falls, while every operating result is unchanged and payoffs are still discounted at 10%. The break-even capital cost is the overnight cost at which the program exactly pays: for the planner, where its extra system cost is zero, and for Uzatom, where its payoff is zero. Both are converted to overnight cost through the same 60-year annuity. The premium per MWh that would cover the owner’s funding shortfall is its negative payoff divided by its discounted output, which is equivalent to the strike price of a two-way contract for difference less the average price received.
Because capital is charged as an annuity over a 60-year life, the horizon carries only part of the investment. At 10%, the operating years inside 2026–2035 are charged with 48.8% of the capitalized investment of the RITM-200N units, 25.0% of that of the first VVER-1000, and 9.1% of that of the second. The remainder is assigned to years after 2035, which are excluded together with their revenues. The results therefore describe the balance of costs and revenues over 2026–2035. They are not a valuation of the plant over its life, which would require projections of demand and of the generating fleet to the 2090s. The runs to 2040 test how far the conclusions depend on where the horizon ends.
2.7. Cases and Validation
Each game case was solved without and with the planned units. The core case uses an elasticity of 0.25, cover of 70%, and rule A, and the sensitivity cases changed one setting at a time (Section 3.5). The market stage was validated in four ways. With no strategic players at the Baseline capacities, the game had to reproduce the planner’s prices and energy. PLEXOS solved the same Nash–Cournot market for the two core equilibria as an independent check. Every search had to converge and pass the deviation check. The fourth check guarded against implausible markups: a case in which the realized Lerner index of a strategic unit operating inside its limits exceeded 0.8 was reported separately as a stress case. Two-firm test models solved by hand, in Python 3.12, and in PLEXOS 10 were used to check the method beforehand and are included in the data archive. The Python code of the market game and of its checks was written with the assistance of Claude Opus 5.5 (Anthropic), a generative AI tool. Its results were verified against the hand-solved test models and the PLEXOS solution of the same market (Section 3.5).
3. Results
3.1. Effect of the Planned Units on Complementary Procurement
The planned units reduced the OCGT capacity procured by the planner by 1700 MW, or 41%, and most of this reduction took place before the large units entered service (Figure 2a). Without the Farish units the planner built 1300 MW of OCGT in 2027 and 2800 MW in 2031; with them, it built 1200 MW in each year. The reduction of 1600 MW in 2031 came two years before the first VVER-1000. In both runs OCGT was the only new capacity chosen, and no CCGT, solar, or wind was added beyond the committed projects (Table 5).
Figure 2.
Procurement and prices without and with the planned units: (a) procured open-cycle gas turbine (OCGT) capacity and Farish capacity in service; (b) average price in the strategic market, under procurement rules A and B.
Table 5.
Core results of the planner, 2026–2035.
The planned units raised system cost by USD 892.0 million, or 5.0%. Inside the horizon they carried USD 1765.0 million of fixed charges, of which USD 1408.9 million was capital and USD 356.0 million fixed operation and maintenance. They saved the rest of the system USD 873.0 million in fuel and avoided OCGT. With nuclear capital at 4%, the capital charge fell to USD 534.1 million and the extra cost to USD 17.2 million. The units saved 7.34 billion cubic meters (bcm) of gas and 15.69 Mt of CO2, mostly after 2032. Because less OCGT was procured, the firm capacity margin was lower with the plant from 2031 to 2034. Neither run reached the 15–20% margin recommended in [2], although demand was met in every hour. For comparison, the levelized cost of the VVER-1000 at 10% was USD 114.7 per MWh, against USD 54.5 for CCGT, and it fell to USD 65.9 per MWh at 4%.
The substitution of nuclear for procured capacity held under every adequacy setting. With a 15% firm reserve margin, OCGT fell from 8400 to 6900 MW and 100 MW of CCGT was no longer built. With a spinning reserve equal to the largest unit, OCGT fell from 4700 to 3200 MW. Over 2026–2040 the plant replaced the 1700 MW of CCGT that the planner would otherwise have built in 2036, and it reduced the OCGT built over the whole horizon by 300 MW.
The extra cost of the program remained positive in all thirteen cases, ranging from USD 17.2 million to USD 1295.2 million (Table 6). It was most sensitive to financing and the gas price, whereas demand, imports, and reserve requirements changed it by less than USD 100 million. When the units were optional, the planner never chose the RITM-200N units or the first VVER-1000. In seven cases it chose only the second VVER-1000, which operates for one year inside the horizon, and over 2026–2040 it chose no unit at either rate.
Table 6.
Extra system cost of the planned program and the planner’s choice when the units were optional, 2026–2035.
3.2. Market Outcomes and Market Power
Market power raised the average wholesale price by about 16–17% in both core cases, while the planned units left the average price almost unchanged (Table 7). Strategic behavior raised the price from USD 38.12 to 44.36 per MWh without the plant and from USD 38.02 to 44.47 with it. JSC Thermal Power Plants produced 30% less than in the benchmark, and its contract floor was binding in 97.6% of hours. The consumers’ wholesale bill rose by USD 3321.5 million, or 12.4%. Consumers lost USD 4777.1 million of surplus, producers gained USD 4237.0 million, and the deadweight loss amounted to USD 540.1 million, a figure the plant reduced only to USD 536.9 million.
Table 7.
Core cases in the market, with and without market power, 2026–2035 (rule A).
The small change in the average price results from two opposing effects (Figure 2b). In 2035 the units produced 15.71 TWh and lowered the strategic price by USD 2.15 per MWh. In 2031 and 2032, when only the RITM-200N units were running but procurement had already been reduced, prices were USD 1.51 and 1.82 per MWh higher than without the plant. With procurement held at the Baseline level (rule B), the plant lowered the average price over the horizon from USD 44.36 to 43.15 per MWh.
Figure 3 shows in which hours the two effects occur. In 2032 the duration curve with the plant lay above the curve without it across roughly the most expensive quarter of hours. The price exceeded in 1% of hours rose from USD 71.8 to 80.7 per MWh, and hourly prices were higher by more than USD 0.50 per MWh in 2327 h and lower in only 125. The curve moved down once both VVER-1000 units were running. In 2035 prices fell by more than USD 0.50 per MWh in 5856 h and rose in none, and the largest reductions came in mid-merit and off-peak hours, not at the peak. The scarcity rents created by the early cut in procurement thus arose in years when Uzatom had only 110 MW to sell, whereas its large units entered a market whose prices they themselves lowered.
Figure 3.
Price duration curves of the strategic market without and with the planned units under rule A: (a) 2032, when only the RITM-200N units are in service; (b) 2035, with all four units in service.
No player invested beyond the procured OCGT and the Farish units in the core cases. The most profitable alternative for JSC Thermal Power Plants, 500 MW of CCGT in 2031, would have reduced its payoff by USD 193.6 million without the plant and by USD 204.9 million with it. The nearest entry step for the fringe, 2000 MW of solar in 2031, fell short of its cost by about USD 40,000 per MW in present value.
3.3. Allocation of the Plant’s Value
The system value of the planned units was about USD 880 million under rule A, and the owner received about half of it (Table 8, Figure 4). This value is gross of the units’ own fixed charges of USD 1765.0 million. Net of those charges, welfare fell by USD 881.1 million in the strategic market and by USD 884.2 million in the benchmark, close to the planner’s extra system cost of USD 892.0 million, and Uzatom’s payoff was −USD 1268.9 million. The system value thus measures what the plant saves the rest of the system and how that saving is shared, not a net benefit. Uzatom’s operating profit was 46% of the system value in the benchmark and 56% in the strategic market. The value-capture gap, USD 473.2 million and USD 387.8 million, was close to the gain of the single buyer, USD 501.0 million and USD 460.0 million, which no longer had to procure 1700 MW of OCGT.
Table 8.
Value of the planned units and its allocation, 2026–2035 (USD million, present value at 10%).
Figure 4.
Allocation of the system value of the planned units by recipient under the three procurement rules, in the benchmark and the strategic market. Diamonds mark the system value; labels give the owner’s share.
The comparison across rules identifies the source of the value-capture gap. With procurement held at the Baseline level, the system value fell to USD 408.5–426.1 million, because the OCGT that the plant would have replaced was still built. The owner then received 96% of it in the benchmark and 109% in the strategic market. Without procurement, the owner received 94% and 118%. The difference between the system values under rules A and B, USD 472.2 million in the benchmark and USD 457.8 million in the strategic market, measures the capacity value of the plant. It accounts for just over half of the plant’s total value. Under rule A this capacity value accrued to the single buyer, while the energy price passed almost all of the remaining value to the owner.
The rules also distributed the effect of the plant differently among consumers. Consumers gained USD 360–730 million under rules B and C, when the plant lowered prices, but lost USD 5–150 million under rule A, when the reduced procurement raised prices in 2031 and 2032.
3.4. Financing, Market Power, and the Owner’s Break-Even
Market power increased the owner’s operating profit, whereas financing determined whether that profit covered the fixed charges (Table 9, Figure 5). Uzatom’s units ran at full available output in all but 100 h and sold at prices raised by the withholding of JSC Thermal Power Plants. Selling at those prices raised their operating profit above the benchmark by USD 88.5 million under rule A, USD 68.9 million under rule B, and USD 125.8 million under rule C. Financing at 4% reduced the fixed charges from USD 1765.0 million to USD 890.2 million and Uzatom’s funding shortfall from USD 1268.9 million to USD 394.1 million, but it left the system value and the value-capture gap unchanged. When offered the choice, Uzatom built none of the Farish configurations at either rate; the full program reduced its payoff by USD 1302.3 million at 10% and by USD 427.5 million at 4%.
Table 9.
Break-even capital cost of the Farish units and the support required to cover the owner’s funding shortfall, 2026–2035.
Figure 5.
Break-even overnight capital cost of the Farish program for the planner and for Uzatom, as a share of the project-case capital cost, with nuclear capital financed at 10% and 4%.
The planner’s break-even for the whole program was 36.7% of the project-case capital cost at 10% and 96.8% at 4%, so with concessional finance the program was close to break-even for the system. The VVER-1000 units broke even at USD 5002 per kW at 4%, 18% above the project case, whereas the RITM-200N units would have needed to cost about half as much. Uzatom’s break-even was much lower, 9.9% of the project-case capital cost at 10% and 26.2% at 4%.
Covering the owner’s funding shortfall through energy sales alone would require a premium of USD 82.6 per MWh at 10% or USD 25.6 per MWh at 4%. Added to the average discounted price received by the units, USD 43.5 per MWh, these premiums correspond to strike prices of about USD 126 and 69 per MWh. If the single buyer’s saving on procurement were paid to the plant as a capacity payment, the premium required at 10% would fall to USD 52.6 per MWh. At 4% no premium would be needed, and Uzatom would end USD 65.9 million ahead.
3.5. Robustness and Validation
The direction of the results was unchanged across the sensitivity cases (Table 10). Uzatom’s payoff was negative in every case, and in every rule-A case over 2026–2035 its share of the system value remained between 50% and 66%. Contract cover affected prices more than any other market setting: at 90% cover the strategic price fell from USD 44.36 to 40.02 per MWh, and at 50% it rose to 47.14. The export-parity gas price was the only case in which any player invested. The fringe then built 12,000 MW of solar and wind with and without the plant, against 18,300 MW built by the planner at the same gas price. It was also the only one of the 22 game cases with two equilibria. Both contain 8000 MW of solar and wind in 2026 and 4000 MW in 2031, and they differ only in whether the 2031 vintage is all wind or half solar and half wind (Table 10). In both, the plant lowered welfare, by USD 391.0 million and USD 461.4 million, Uzatom’s payoff stayed below −USD 900 million, and its share of the system value was 61% and 65%. JSC Thermal Power Plants built no CCGT in any case. Over the horizon to 2040 it also left unbuilt the 1700 MW that the planner added in 2036, since its best alternative, 500 MW, would have reduced its payoff by USD 104.4 million. Over 2026–2040 the owner’s share rose to 74%, and the premium required remained close to its 2035 value, at USD 78.4 per MWh at 10% and USD 25.1 at 4%. The single buyer’s saving did not grow with the horizon: over 2026–2040 it was USD 395.2 million, against USD 460.0 million over 2026–2035. Paid as a capacity payment, it would cover about 40% of Uzatom’s funding shortfall at 4%, USD 962.2 million, and leave a premium of about USD 15 per MWh.
Table 10.
Results of the game under the sensitivity cases.
All validation checks were passed. With no strategic players, the game reproduced the planner’s price within 0.08% and its energy within 0.02% in every year from 2026 to 2040, and 99.5% of hourly prices lay within USD 0.50 per MWh (Figure 6a). For the two core equilibria, all 22 comparisons of price, energy, output, and operating profit by company between the game and PLEXOS agreed within 0.0006%, and every hourly price within USD 0.01 (Figure 6b). All 132 searches converged within three rounds, and every equilibrium passed the deviation check. The realized Lerner index of JSC Thermal Power Plants reached at most 0.68 in the core cases and 0.80 in any case. Only the case with an elasticity of 0.10 and the planned units exceeded the screen: Uzatom’s index reached 0.815 in the 10,535 h in which one of its units operated inside its limits. That case is reported as a stress case. In it, the plant raised the average strategic price from USD 50.76 to 51.73 per MWh, and Uzatom’s payoff was −USD 1213.7 million. The owner’s share of the system value was 66%, and these results agree in direction with every other case.
Figure 6.
Validation of the market stage on every hour of 2026–2035: (a) prices of the game without strategic players against the PLEXOS planner, Baseline; (b) prices of the Python game against the PLEXOS Nash–Cournot solution for the two core equilibria. Dashed lines mark equality.
4. Discussion
4.1. Sources of the Value-Capture Gap
The results indicate that the planned units act mainly as a substitute for procured peaking capacity. The planner reduced its OCGT procurement by 1700 MW, and this substitution held under every adequacy setting tested. Just over half of the value of the plant to the system arises from this substitution. Under the present arrangement the corresponding saving accrues to the single buyer, while the energy price passes nearly all of the remaining value to the owner. The gap between system value and the owner’s operating profit is thus institutional in origin. It resembles the missing-money problem described in [10,11], but it arises because capacity is procured outside the market, not because scarcity prices are capped. This division does not depend on how the plant’s own capital is charged. The system value and every term of Equation (2) exclude the fixed charges of the Farish units, so the annuity applied to them and their financing rate change only those charges and the owner’s payoff. The horizon does matter: over 2026–2040 the owner’s share rose to 74%, probably because more years of energy sales fall inside it.
Financing and market power affect the owner’s position through different channels. Financing changes only the fixed charges, so it determines the size of the owner’s funding shortfall but leaves the value-capture gap unchanged. Market power raises the owner’s operating profit, because a unit operating at full output sells at the price raised by the incumbent’s withholding, and it imposes a large cost on consumers irrespective of the plant. Market power thus appears primarily as a consumer-protection issue and not as the reason the plant fails to recover its costs. Since the game was deterministic and its players risk-neutral, the funding shortfall arose without any risk premium. Risk aversion shifts investment away from capital-intensive plant [14], so the reported shortfall is more likely to understate than to overstate the divergence between the owner’s and the planner’s valuations.
4.2. Comparison with Previous Studies
The planner’s result is consistent with the earlier least-cost studies of Uzbekistan, which did not select nuclear capacity at international gas prices, a carbon price of USD 75 per t, and reserve margins of 10–15% [18,19]. In the present study the program was also rejected at the regulated gas price, without a carbon price or a reserve requirement. The rejection therefore does not depend on the price basis. What the plant replaces does: OCGT and gas-fired output at the regulated price, and solar and wind at export parity, where the planner built them even without the plant.
The owner’s result differs from that of the Greek study, in which small modular reactors generally earned positive results in the wholesale market [16]. That study assumed gas at EUR 35 per MWh and carbon prices of EUR 86–180 per t, whereas gas here is priced at a regulated USD 4.44 per GJ with no carbon price. The resulting difference in wholesale price levels is the likely explanation for the contrast. The importance of capacity remuneration is consistent with the bilevel analysis of [17], in which adding capacity and reserve markets raised producer surplus and welfare. Published capital costs for comparable units range from about USD 2271–2296 per kWe for Rosatom units built inside Russia [44] to USD 5.4–6 billion per VVER unit estimated for Kazakhstan [45]. Uzatom’s break-even at 4%, about USD 1110 per kW in VVER-1000 terms, lies below this entire range, so the negative result for the owner does not depend on the capital cost assumed.
The strategic results agree with the international literature. In Ukraine, new thermal units were not an attractive investment for the incumbent producers despite available room for new capacity [15], and JSC Thermal Power Plants likewise built no CCGT, even where the planner did. Bushnell and Ishii attribute such reluctance to the effect of new capacity on the price earned by existing plants [13]. The price effect of market power was smaller than in Ukraine, where a single strategic renewable entrant withholding investment raised the wholesale purchase cost in 2040 from USD 53.0 to 84.3 per MWh [15]. In the present core case, market power raised the average price from USD 38.12 to 44.36 per MWh. The smaller effect found here is consistent with a contract floor that was binding in 97.6% of hours.
4.3. Policy Implications
Within the modeled assumptions, part of the value needed to sustain the plant already exists in the system but accrues to the single buyer as avoided procurement. A capacity payment from the single buyer equal to this saving would be a transfer that leaves welfare unchanged: it would change who bears the cost of the program, not its size. Combined with concessional finance at 4%, such a payment covered the owner’s funding shortfall over 2026–2035, although it would not do so at 10%. Over 2026–2040 it would cover about 40% of the shortfall at 4%, so a longer horizon would also require a premium on the plant’s energy, of about USD 15 per MWh. These are results of the model, not tests of an instrument. Whether such a payment can work depends on conditions the model does not represent. The single buyer must be able to finance it, through tariffs or the budget. A regulator must also tie it to the capacity the plant actually displaces, since evidence from Poland indicates that a general capacity market may reward existing plants far more than new ones [46]. A two-way contract for difference on the plant’s energy, of the kind proposed for Uzbekistan’s existing purchase agreements [31], could serve the same purpose. Over the modeled horizon it would require a strike price of about USD 69 per MWh at 4% and USD 126 at 10%. These values cover only the years inside the horizon and should be regarded as indicative.
Two existing contracts show what such instruments look like. For the Rosatom plant at Akkuyu in Turkey, built on a build–own–operate basis, the state trading company guaranteed to buy 70% of the output of the first two units at 12.35 US cents per kWh for 15 years [47]. In nominal terms this USD 123.5 per MWh is close to the strike price of about USD 126 per MWh estimated here at 10%, although the two are not on the same price basis. Hinkley Point C in the United Kingdom holds a 35-year contract for difference at GBP 92.50 per MWh in 2012 prices, and the expected present value of its top-up payments rose from about GBP 6 billion in 2013 to GBP 30 billion in 2016 as projections of wholesale prices fell [48]. Neither model, in the authors’ view, suits Farish well. Both pay for the plant per MWh, so its capacity value is recovered through the energy price, whereas the results here place that value in procurement the single buyer no longer needs. A payment sized to the avoided OCGT draws on a saving the single buyer already makes, and with finance at 4% it requires no guarantee on the energy price over 2026–2035.
Whatever instrument is chosen, its timing relative to construction matters. The planner reduced procurement in 2031, two years before the first VVER-1000, and in the market this raised prices in 2031 and 2032 and lowered the firm capacity margin until 2034. A delay to the large units would extend this period, so procurement decisions should be tied to the actual progress of construction.
Consumer protection in the new market depends more on the contract cover of the incumbent than on the nuclear plant. Raising that cover from 70% to 90% lowered the average strategic price from USD 44.36 to 40.02 per MWh, a larger effect than that of the plant itself. A larger contracted share is also among the remedies proposed for Ukraine, together with more competition and the divestiture of dominant players [15].
4.4. Limitations
The system was represented as a single node with fixed net imports, so transmission limits and the location of the plant were not considered. Solar and wind followed a single weather year, and hydropower followed the planner’s monthly schedule. The water–energy links of the Central Asian river basins, including irrigation releases, were therefore not represented, and no run faced a dry year. The demand elasticity could not be calibrated, because Uzbekistan has no record of wholesale prices, so it was carried as a range. Competition was represented by Cournot quantities and not by bids, which suits a market without a bidding history [40] but cannot reproduce strategic bidding in a day-ahead auction. The contract floor and the dispatch order at equal cost are modeling devices. The players were risk-neutral and the analysis deterministic; as argued in Section 4.1, risk aversion would more likely widen the owner’s funding shortfall than narrow it. The discrete investment grid shows that each equilibrium is stable against any single change on the grid, but not that it is unique, and one case had two equilibria (Section 3.5). Several inputs rest on secondary sources, including press reports of the plant’s cost [3,26], and the rate of the Russian loan is unpublished [27]; the break-even capital costs and the two financing rates were reported for this reason. The horizon ends two years after the first large unit enters service. The 2040 runs did not change the direction of any conclusion, although a capacity payment alone no longer covered the owner’s shortfall at 4% (Section 3.5). They also rest on demand extrapolated beyond the published forecast, and neither horizon amounts to a valuation over the plant’s life. The assumption most likely to fail, in the authors’ view, is the construction schedule itself: the announced dates were taken as given, and any slippage of the VVER-1000 units would lengthen the period of reduced margin found for 2031–2034. System services were represented only through the reserve requirements of the planner, and the game had no reserve or balancing market. The security benefits of the plant, including the gas it saves and the diversity it adds, were measured in physical units but not valued in money, and the political considerations behind the program lie outside the scope of the models.
5. Conclusions
Applied to the same hourly system for 2026–2035, the PLEXOS planner and the Nash–Cournot game showed that the planned units displaced 1700 MW of the OCGT capacity the single buyer would otherwise procure, most of it in 2031, before the large units enter service. They raised system cost by USD 892.0 million at a 10% real cost of capital and by USD 17.2 million at 4%. A least-cost planner did not select the full program in any case examined. The system value of the units, about USD 880 million, was divided almost evenly between the owner’s operating profit and the single buyer’s saving on procurement. This value is gross of the units’ fixed charges of USD 1765.0 million, and net of them welfare fell by about USD 880 million, close to the planner’s extra cost. When procurement did not respond to the plant, the owner captured 94–118% of a smaller value, which identifies the gap between system value and the owner’s operating profit as unremunerated capacity value.
Financing and market power acted through different channels. Concessional finance reduced the owner’s funding shortfall from USD 1268.9 million to USD 394.1 million without changing the value-capture gap. Incumbent market power raised the owner’s operating profit by USD 69–126 million and cost consumers USD 4.8–4.9 billion of surplus, with or without the plant. Under the modeled assumptions, energy-market revenues alone would neither induce investment in the Farish program nor recover its annualized costs. Within the model, concessional finance combined with a payment for the capacity the plant displaces covered the owner’s funding shortfall over 2026–2035. Over 2026–2040 the payment covered about 40% of it, and a premium of about USD 15 per MWh would also be needed. Whether such a payment can be financed and regulated in practice was not tested.
These results describe the balance of costs and revenues over 2026–2035, a period in which the Farish units were charged with between 9% and 49% of their capitalized investment at 10%. They do not assess the payback of the whole investment. The extension to 2040 did not change the direction of the conclusions, and the premium required per MWh stayed close to its 2035 value; the share of the shortfall that a capacity payment could cover, however, fell. A valuation over the plant’s 60-year life would require projections of demand and of the fleet that are not available for Uzbekistan.
Two extensions would test these conclusions most directly: risk-averse investors, who would probably widen the owner’s funding shortfall, and construction delays. A valuation over the full life of the plant, and a social cost–benefit analysis that prices gas and emissions, would carry the comparison beyond the modeled horizon and beyond system cost. Once the wholesale market publishes prices, the demand elasticity and contract cover can be calibrated instead of assumed.
Author Contributions
Conceptualization, D.T. and K.-w.C.; methodology, D.T., K.-w.C., and S.-j.P.; software, D.T.; validation, D.T. and S.-j.P.; formal analysis, D.T.; investigation, D.T.; data curation, D.T.; writing—original draft preparation, D.T.; writing—review and editing, K.-w.C. and D.T.; visualization, D.T.; supervision, K.-w.C.; resources and funding acquisition, S.-j.P. All authors have read and agreed to the published version of the manuscript.
Funding
This research was supported by the 2026 Research Fund of the KEPCO International Nuclear Graduate School (KINGS), the Republic of Korea.
Data Availability Statement
The models, input data, scripts, and results that support this study are openly available in Zenodo at https://doi.org/10.5281/zenodo.23750009, under the CC BY 4.0 license. The PLEXOS models require a PLEXOS license to run; their run logs and solution files are included.
Acknowledgments
This article is based on the first author’s master’s thesis at KEPCO International Nuclear Graduate School. During the preparation of this study, the authors used Claude Opus 5.5 (Anthropic) to write and check the analysis code, and for language editing. The authors have reviewed and edited the output and take full responsibility for the content of this publication.
Conflicts of Interest
The authors declare no conflicts of interest.
Abbreviations
The following abbreviations are used in this manuscript:
| bcm | billion cubic meters |
| CCGT | combined-cycle gas turbine |
| NPP | nuclear power plant |
| OCGT | open-cycle gas turbine |
References
- International Energy Agency. Uzbekistan 2022 Energy Policy Review; IEA: Paris, France, 2022. [Google Scholar]
- Mork, J.; Saparova, D.; Bilek, P. Uzbekistan’s Electricity Demand Forecasting: An Outlook Until 2035; Policy Study No. 02/2024; German Economic Team, Berlin Economics: Berlin, Germany, 2024. [Google Scholar]
- Presidents of Uzbekistan, Russia Launch Construction of Nuclear Power Plant in Uzbekistan. Gazeta.uz, 5 June 2026. Available online: https://www.gazeta.uz/en/2026/06/05/nuclear-power-station-uzb/ (accessed on 17 October 2026).
- Uzbekistan Progressing Work on First Nuclear Power Plant. World Nuclear News, 2 December 2025. Available online: https://wnn.world-nuclear.org/articles/uzbekistan-progressing-work-on-first-nuclear-plant (accessed on 17 October 2026).
- Asian Development Bank. Republic of Uzbekistan: Power Sector Reform Program (Subprogram 1)—Validation Report; Ref. PVR-1094; ADB: Manila, Philippines, 2024. [Google Scholar]
- Asadov, K.S.; Halmurzayev, A.A. Reformirovanie energeticheskogo rynka Uzbekistana i dostignutye rezul’taty [Reforming Uzbekistan’s energy market and the results achieved]. Evraziiskie Issled. 2026, 2, 61–77. (In Russian) [Google Scholar] [CrossRef] [Scilit]
- OECD Nuclear Energy Agency. The Costs of Decarbonisation: System Costs with High Shares of Nuclear and Renewables; NEA No. 7299; OECD Publishing: Paris, France, 2019. [Google Scholar]
- Sepulveda, N.A.; Jenkins, J.D.; de Sisternes, F.J.; Lester, R.K. The role of firm low-carbon electricity resources in deep decarbonization of power generation. Joule 2018, 2, 2403–2420. [Google Scholar] [CrossRef] [Scilit]
- Hirth, L. The market value of variable renewables: The effect of solar wind power variability on their relative price. Energy Econ. 2013, 38, 218–236. [Google Scholar] [CrossRef] [Scilit]
- Joskow, P.L. Capacity payments in imperfect electricity markets: Need and design. Util. Policy 2008, 16, 159–170. [Google Scholar] [CrossRef] [Scilit]
- Newbery, D. Missing money and missing markets: Reliability, capacity auctions and interconnectors. Energy Policy 2016, 94, 401–410. [Google Scholar] [CrossRef] [Scilit]
- Murphy, F.H.; Smeers, Y. Generation capacity expansion in imperfectly competitive restructured electricity markets. Oper. Res. 2005, 53, 646–661. [Google Scholar] [CrossRef] [Scilit]
- Bushnell, J.B.; Ishii, J. An Equilibrium Model of Investment in Restructured Electricity Markets; CSEM Working Paper WP-164; University of California Energy Institute: Berkeley, CA, USA, 2007. [Google Scholar]
- Ehrenmann, A.; Smeers, Y. Generation capacity expansion in a risky environment: A stochastic equilibrium analysis. Oper. Res. 2011, 59, 1332–1346. [Google Scholar] [CrossRef] [Scilit]
- Suski, A.; Chattopadhyay, D. Game-theoretic capacity expansion analysis under carbon emission constraints. IEEE Trans. Power Syst. 2023, 38, 5570–5584. [Google Scholar] [CrossRef] [Scilit]
- Simoglou, C.K.; Kaissas, I.M.; Biskas, P.N. Assessing the implications of integrating small modular reactors in modern power systems. Energies 2025, 18, 2578. [Google Scholar] [CrossRef] [Scilit]
- Ji, P.; Liu, Y.; Li, N.; Tan, Z. A bilevel multi-market coupling optimization framework for nuclear power integration: Joint modeling of energy, reserve, and capacity markets. Energies 2026, 19, 1276. [Google Scholar] [CrossRef] [Scilit]
- Bilek, P.; Stubbe, R. How Much Gas Power Plant Capacity Does Uzbekistan Need? A 2030 Scenario Analysis Using the Government’s Electricity Demand Forecast; Policy Study No. 01/2022; German Economic Team, Berlin Economics: Berlin, Germany, 2022. [Google Scholar]
- Bilek, P.; Stubbe, R. Transforming Uzbekistan’s Electricity System While Maintaining Stability: What Could a Cost-Optimal Power Plant Park Look Like in 2030? Policy Briefing No. 03/2023; German Economic Team, Berlin Economics: Berlin, Germany, 2023. [Google Scholar]
- Bilek, P.; Moiz, A.; Sosa Marquina, D.; Saparova, D.; Walter, W. Modelling Uzbekistan’s Power System in 2030 and 2035; Policy Study No. 01/2025; German Economic Team, Berlin Economics: Berlin, Germany, 2025. [Google Scholar]
- International Renewable Energy Agency. Renewable Capacity Statistics 2026; IRENA: Abu Dhabi, United Arab Emirates, 2026. [Google Scholar]
- Ministry of Energy of the Republic of Uzbekistan. Concept Note for Ensuring Electricity Supply in Uzbekistan in 2020–2030; Ministry of Energy: Tashkent, Uzbekistan, 2020.
- World Bank. Project Appraisal Document on a Proposed IBRD Payment Guarantee of up to US$29 Million to the Republic of Uzbekistan for the Syrdarya Efficient Power Generation Project; Report No. 181195-UZ; World Bank: Washington, DC, USA, 2023. [Google Scholar]
- Cabinet of Ministers of the Republic of Uzbekistan. Resolution No. 243 of 15 May 2026. Available online: https://lex.uz/uz/docs/8195731 (accessed on 17 October 2026). (In Uzbek)
- Uzbekistan Breaks Ground on 2.1 GW Jizzakh NPP under a $9.5 Billion Rosatom Partnership. Construction Review Online, 8 June 2026. Available online: https://constructionreviewonline.com/uzbekistan-breaks-ground-on-2-1-gw-jizzakh-npp-under-a-9-5-billion-rosatom-partnership/ (accessed on 17 October 2026).
- Uzbekistan’s 110 MW Nuclear Plant to Cost under $1 Billion. The Caspian Post, 9 October 2025. Available online: https://caspianpost.com/uzbekistan/uzbekistan-s-110-mw-nuclear-plant-to-cost-under-1-billion (accessed on 17 October 2026).
- Uzbekistan May Attract Russian Loan for Nuclear Plant. UzDaily, 5 June 2026. Available online: https://www.uzdaily.uz/en/uzbekistan-may-attract-russian-loan-for-nuclear-plant/ (accessed on 17 October 2026).
- $11.38b Loan Deal Signed for Nuclear Power Plant. The Daily Star, 27 July 2016. Available online: https://www.thedailystar.net/business/1138b-loan-deal-signed-nuclear-power-plant-1259944 (accessed on 17 October 2026).
- World Nuclear Association. Nuclear Power in Bangladesh. Information Library, Updated 13 October 2026. Available online: https://world-nuclear.org/information-library/country-profiles/countries-a-f/bangladesh (accessed on 17 October 2026).
- European Commission. Commission Decision (EU) 2017/2112 of 6 March 2017 on the measure/aid scheme/State aid SA.38454—2015/C (ex 2015/N) which Hungary is planning to implement for supporting the development of two new nuclear reactors at Paks II nuclear power station. Off. J. Eur. Union 2017, L 317, 45–118. [Google Scholar]
- Tahmisoğlu, Y.; Saparova, D.; Bilek, P.; Walter, W. Integration of Existing Power Purchase Agreements into Uzbekistan’s Upcoming Wholesale Market; Policy Briefing No. 06/2025; German Economic Team, Berlin Economics: Berlin, Germany, 2025. [Google Scholar]
- Energy Exemplar. PLEXOS Energy Modeling Software. Available online: https://www.energyexemplar.com/plexos (accessed on 17 October 2026).
- Pfenninger, S.; Staffell, I. Long-term patterns of European PV output using 30 years of validated hourly reanalysis and satellite data. Energy 2016, 114, 1251–1265. [Google Scholar] [CrossRef] [Scilit]
- Staffell, I.; Pfenninger, S. Using bias-corrected reanalysis to simulate current and future wind power output. Energy 2016, 114, 1224–1239. [Google Scholar] [CrossRef] [Scilit]
- Energy Exemplar. Competition Modelling in PLEXOS: The Nash-Cournot Model. PLEXOS Xpert Learning Portal (Registered Users). Available online: https://xpert.energyexemplar.com/ (accessed on 17 October 2026).
- U.S. Energy Information Administration. Capital Cost and Performance Characteristics for Utility-Scale Electric Power Generating Technologies; Report prepared by Sargent & Lundy; EIA: Washington, DC, USA, 2024. Available online: https://www.eia.gov/analysis/studies/powerplants/capitalcost/pdf/capital_cost_AEO2025.pdf (accessed on 17 November 2026).
- International Energy Agency; OECD Nuclear Energy Agency. Projected Costs of Generating Electricity—2020 Edition; OECD Publishing: Paris, France, 2020. [Google Scholar]
- Voronin, S.A.; Musabekov, D.K.; Arzumanyan, S.Y.; Azimova, F.M.; Alimova, A.S. Ugol’naya promyshlennost’ Uzbekistana: Sostoyanie otrasli i puti ee razvitiya [Coal industry in Uzbekistan: Current state and paths for development]. Ugol’ 2025, 7, 41–44. (In Russian) [Google Scholar] [CrossRef] [Scilit]
- Kavkatbekov, M.M.; Babakhodzhaev, R.P. Research of the influence of physical and chemical properties of coal on the gasification process using the example of Angren brown coal. Tech. Sci. Innov. 2024, 2024, 14–18. [Google Scholar] [CrossRef]
- Hakam, D.F. Market power modelling in electricity market: A critical review. Int. J. Energy Econ. Policy 2018, 8, 347–356. [Google Scholar]
- Labandeira, X.; Labeaga, J.M.; López-Otero, X. A meta-analysis on the price elasticity of energy demand. Energy Policy 2017, 102, 549–568. [Google Scholar] [CrossRef] [Scilit]
- Allaz, B.; Vila, J.-L. Cournot competition, forward markets and efficiency. J. Econ. Theory 1993, 59, 1–16. [Google Scholar] [CrossRef] [Scilit]
- Borenstein, S.; Bushnell, J.B.; Wolak, F.A. Measuring market inefficiencies in California’s restructured wholesale electricity market. Am. Econ. Rev. 2002, 92, 1376–1405. [Google Scholar] [CrossRef] [Scilit]
- Rothwell, G. Projected electricity costs in international nuclear power markets. Energy Policy 2022, 164, 112905. [Google Scholar] [CrossRef] [Scilit]
- Batyrbekov, E.; Vityuk, V.; Zarva, D.; Sharipov, M. Conceptual view of the implementation of the nuclear energy program in the Republic of Kazakhstan. Energies 2024, 17, 5788. [Google Scholar] [CrossRef] [Scilit]
- Komorowska, A.; Kaszyński, P.; Zamasz, K.; Kinelski, G.; Kamiński, J. Capacity market and (the lack of) new investments: Evidence from Poland. Energies 2021, 14, 7843. [Google Scholar] [CrossRef] [Scilit]
- Russian Plant for Turkey’s Akkuyu. World Nuclear News, 13 May 2010. Available online: https://www.world-nuclear-news.org/Articles/Russian-plant-for-Turkey-s-Akkuyu (accessed on 29 October 2026).
- National Audit Office. Hinkley Point C; Report HC 40, Session 2017–18; NAO: London, UK, 2017.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |