Abstract
Stakeholder involvement and management is critical to successful outcomes in green construction projects. The objectives of the study were to evaluate stakeholder management strategies for green construction projects in Ghana and to assess the influence of these strategies using an index. Using purposive and snowball sampling techniques, practitioners in the Ghanaian industry with knowledge and understanding of green construction projects were contacted. Using a two-round Delphi survey, 68 respondents partook in both rounds and were required to fill out questionnaires. From the mean score ranking, ‘Develop a project communication plan’, ‘Contractor and subcontractors should communicate on safety risks’, and ‘Early communication with stakeholders on their concerns’ were ranked as having the most perceived significance as strategies. Exploratory factor analysis revealed five components, and fuzzy synthetic analysis evaluated the index of the strategies to be 3.87. This study deepens the understanding of stakeholder management strategies in green projects and sustainable construction delivery.
1. Introduction
A significant driver of creating sustainable value is ensuring that stakeholders are satisfied in the delivery of functional units during projects (Price & Al-Yami, 2008, Adhi & Muslim, 2023). This is done by ensuring all stakeholders and their concerns are managed while conflicting interests are taken care of through negotiation (Yu et al., 2019; Dansoh et al., 2020). For green construction projects to be successful, the interests of the main stakeholders or even all other stakeholders should be considered (Aladpoosh et al., 2012; Chipulu et al., 2019). Scholars researching green construction (Bosher et al., 2007; El-Gohary et al., 2006) have opined that stakeholder involvement and management is critical to successful outcomes in sustainable construction.
The activities of humans have resulted in the adoption of more sustainable and green practices over recent decades (Leaman & Bordass, 2007; Yang & Zou, 2014). The sustainability-related agenda has set the pace for stakeholder negotiations (Asumadu et al., 2022). This agenda incorporates a set of influential goals related to emission targets, life-cycle green-building energy performance, eco-design consideration, urban sustainability, waste, mobility, and energy networks (Nielsen et al., 2019; Hamdan et al., 2021).
Formulating stakeholder management goals that are sustainability-related is not always simple but can be complex (Wen & Qiang, 2022). In some instances, the costs of attaining some sustainability standards may be difficult to achieve and could serve as demotivating factors to investors and further discourage homebuyers (Rossiter & Smith, 2018; Hamdan et al., 2021). When community consultation and engagement is undertaken too late in the process, it derails the formulation of sustainability-related goals (Oliver & Pearl, 2018).
In comparison with traditional construction projects, the extra demands that sustainable measures place on green construction projects have made stakeholder objectives difficult to address (Mok et al., 2018). Green construction projects encompass multiple and interdependent stakeholders who have individual and separate concerns that impact on the management of such projects (Wen & Qiang, 2022). These concerns are highly complex and predisposed to uncertainties, especially in terms of the social aspects of green buildings (Wen & Qiang, 2022; Akomea-Frimpong et al., 2022). Stakeholder Theory emphasizes the identification of stakeholders who can affect or who are affected by organizational and project activities and recognizes the importance of managing the relationships among stakeholders to achieve project and organizational objectives (Kukah et al., 2022b).
There is a distinction between stakeholder management in conventional construction and green construction projects. Green construction projects involve greater interaction among clients, designers, contractors, government and regulatory agencies, environmental professionals, suppliers, communities, occupants, sustainability-certification bodies, and other actors whose interests may differ regarding environmental performance, cost, project time, technology, materials, and long-term building performance (Darko et al., 2017; Mok et al., 2018; Chipulu et al., 2019).
In Ghana, there have been some studies on green construction projects and sustainable buildings. Notable among them are those by Akomea-Frimpong et al. (2022), who researched the financing of green buildings; Darko et al. (2017), who investigated the drivers of green building construction; and Kukah et al. (2022b), who evaluated resource consumption in sustainable buildings. However, there exists a gap in the literature. Although previous studies have examined stakeholder-related issues in construction and sustainability, there remains limited evidence on how stakeholder management strategies can be systematically identified, prioritized, and evaluated within the institutional, economic, and project environments of Ghana.
The objectives of this study are, therefore, to i. evaluate the stakeholder management strategies for green construction projects in Ghana and ii. assess the perceived influence of the strategies in delivering sustainable construction projects using an index. The study starts with an introductory section and continues with a literature review. The methodology is explained in detail, followed by the results and analysis. The concluding section draws the curtain on the research. This study contributes to the knowledge by deepening the understanding of stakeholder management strategies for delivering green construction projects in Ghana. The study also contributes by identifying relevant stakeholder management strategies for green construction projects and systematically evaluating them using the fuzzy synthetic evaluation approach. This provides a structured mechanism for incorporating expert judgement and dealing with the uncertainty and subjectivity associated with evaluating stakeholder management strategies.
2. Literature Review
2.1. Construction Industry in Ghana
According to Frimpong et al. (2020), the construction industry in Ghana is the second-largest contributor to gross domestic product (GDP) in the country. It also serves as a significant enabler of economic endeavors and activities in Ghana. The construction sector in Ghana totals approximately $8 billion, and it encompasses over 15% of the country’s GDP. The Ghanaian construction sector provides employment directly and indirectly to 420,000 people, with active construction and building contractors estimated to total 2500 individuals. Stakeholders in the sector range from micro-firms and individual contractors to international construction and civil-engineering conglomerates (Agyekum et al., 2022a). The Ghanaian construction industry comprises engineers, project consultants, building contractors, quantity surveyors, architects, and other artisans (Akomea-Frimpong et al., 2021; Agyekum et al., 2022b). The Chamber of Construction Industry Ghana is the body responsible for the promotion of activities related to the sector. The industry is currently experiencing an upsurge in significant investments being made in infrastructural development (Ofori-Kuragu et al., 2016). The government is committed to ensuring that the construction sector grows, and, hence, it is being made attractive to both foreign and local investors (Seidu et al., 2022). The Public-Private-Partnership bill has also been passed, and this is expected to drive growth in the industry (Kukah et al., 2022a).
2.2. Stakeholder Management and Stakeholder Theory
Stakeholders are individuals, teams or societies that have an impact on and are affected by a project. Eyiah-Botwe et al. (2016) posited that stakeholders have a significant impact on attaining effective project delivery and success. Stakeholder management implies fulfilling the interests of different stakeholders and developing relationships among these stakeholders (Bourne & Walker, 2005), and this starts with stakeholder mapping and analysis (Freeman, 2007). Detailed planning and analysis lead to identifying and determining the relevant stakeholders in a project (Hu et al., 2019).
The stakeholder management process is essential for projects (Oppong et al., 2017). First, it helps a project become acquainted with its stakeholders. Second, the stakeholder management process ensures balance is achieved between contribution and reward (Osei-Kyei et al., 2018). In addition, the process serves as an official basis for the management of stakeholders (Wuni & Shen, 2020). Fourth, it is a determinant in deciding which persons are to be involved in determining the project’s goals, as well as how the project’s success should be benchmarked (Dansoh et al., 2020).
Stakeholder Theory emphasizes the importance of recognizing and appropriately considering the interests of relevant stakeholder groups in decision making (Oppong et al., 2017). Stakeholder Theory is significant in green construction projects. This is because green construction projects involve objectives that go beyond the conventional project constraints (Kukah et al., 2026a, 2026b). Green construction projects involve environmental targets, including energy efficiency, resource conservation, waste reduction, emissions reduction, sustainable material selection, and improved environmental performance (Akomea-Frimpong et al., 2021; Agyekum et al., 2022b). These objectives generate additional stakeholder interests and potential conflicts (Rizvi et al., 2023). For example, project owners may seek environmental performance while being concerned about capital costs (Hu et al., 2019). Furthermore, contractors may be concerned about the availability, cost, and technical requirements of sustainable materials and technologies, while regulators may emphasize environmental compliance (Jayasuriya et al., 2020).
2.3. Stakeholder Management Strategies for Green Construction Projects
The phases and life cycle of green construction projects have an influence on their stakeholder management strategies adopted (Wen & Qiang, 2022). The life cycle comprises planning, designing, construction, refurbishing and demolition. These stages are different and distinct in terms of processes, practices, and relations among the organizational parties. These differences have an influence on the stakeholder management strategies adopted. In the design stage, communication among stakeholders and how the information is presented to parties are key to stakeholder management affairs (W. H. Collinge & Harty, 2014; Adinyira et al., 2020).
It is essential for stakeholder management strategies to be adopted in green construction projects (Kukah et al., 2022b). Carefully developed, mutually supportive and positive stakeholder relationships foster trust and aid in stimulating collaborations that go a long way toward minimizing time delays and cost overruns in green projects (Maier & Aschilean, 2020). A major stakeholder management strategy is increasing incentives given to stakeholders (Unterhitzenberger et al., 2021). Incentives are important in green projects and drive stakeholders toward implementing sustainable construction (Adhi & Muslim, 2023). Governments can provide incentives for infrastructure that is green in construction. These incentives will aid contractors in adding more value that can be utilized to ensure projects are a success. Incentives, especially at the start of green construction projects, lead to stronger and more substantial impacts on a project success (Adhi & Muslim, 2023).
In green projects, it is essential to prepare a detailed specification of outputs that serve as a basis for bidding. Engaging several stakeholders while the client and consultant are preparing the project brief will ensure fewer problems during the tender’s evaluation and the subsequent stages of the green project (Jayasuriya et al., 2020).
3. Methodology
In addressing the research objective, the first step was conducting a systematic review of the existing literature on the strategies. The Web of Science and Scopus search engines were selected, and the literature was retrieved in the form of journal articles, conference papers and technical reports. The search was conducted in January 2024. The search string adopted was TITLE-ABS-KEY((“green construction” OR “green building*” OR “sustainable construction” OR “sustainable building*”) AND (stakeholder* OR “stakeholder management” OR “stakeholder engagement”) AND (strategies* OR approaches*)). During the first search, 241 documents were retrieved. Filtering was then undertaken. Documents were restricted to the English language. The document types were also limited to journal articles, conference papers and technical reports. There was no limitation in terms of the years of publication. Following this, 64 articles were eliminated, with 177 documents remaining. Some of the documents that were duplicated in the two search engines were deleted. Furthermore, the full texts of the articles were read to ensure they were related to the objective of the study. Following this, additional documents were removed, with a final number of 87 articles remaining. The retrieved documents underwent a content analysis to identify the strategies.
Twenty-one strategies were identified, and 2 experts with rich experience in green building practice and stakeholder management were asked to scrutinize and vet them factors and remove any that were irrelevant. These experts were chosen because they have over 20 years of experience in the Ghanaian construction industry and for their knowledge. One of these experts was an Associate Professor of project management, who also been involved in multiple construction projects and is knowledgeable of green buildings. The second expert was the head of quantity surveying in a construction consultancy firm; he has 28 years of experience in the construction industry. Both experts agreed that the 21 strategies were relevant but recommended the longer statements be shortened for clarity.
A quantitative research strategy was used in this study. According to Wadsworth (1997), quantitative research is a systematic scientific inquiry of quantitative interactions and characteristics (Wadsworth, 1997). A quantitative strategy examines the significance of past actions, documents and words and quantifies the outcome (Creswell, 2014). An advantage for choosing this strategy is that the results can be generalized to a larger population within acceptable error limits.
In this study, a questionnaire survey was used as the main avenue of data collection. Comprehensive literature reviews and confirmation of the variables with industry professionals supported the survey questionnaire that was developed. The study adopted a five-point Likert scale in ranking the variables, where 1 was least significant and 5 very significant.
The population for this study encompassed all practitioners in the Ghanaian industry with knowledge and understanding of green buildings/sustainable construction. Since there was no sampling frame, the sample size was derived using a non-probability sampling technique. This technique is recommended when a random sampling technique cannot be adopted in selecting respondents from a population but the respondents are chosen on the basis of their willingness to partake in the study (Zhao et al., 2015; Owusu-Manu et al., 2018). Thus, purposive and snowball sampling techniques were adopted. Local companies in Ghana that are directly involved in green-building project development were first contacted to identify initial respondents. This study defined green construction projects as those having obtained a LEED certification or Green Star SA certification, as per Darko et al. (2017) and Agyekum et al. (2021). Through snowballing, initial respondents were asked to recommend other knowledgeable respondents through referrals and social networks.
A Delphi survey was adopted for this study. Delphi collects data from panel experts through a series of questionnaires that undergo multiple iterations (Hon et al., 2012). The Delphi process can be repeated indefinitely until a consensus is reached. The number of Delphi rounds aims to achieve consensus while also improving accuracy and precision through feedback. Previous studies that have adopted the 2-round Delphi survey include Chong et al. (2013), who conducted researched into e-dispute resolution in contract administration, and Xia et al. (2013), who studied how to determine the optimal proportion of design in design-build request for proposals. Based on these considerations and previous research findings, a two-round Delphi survey was determined to be appropriate for this study. A total of 100 questionnaires were distributed to study respondents in round one. A total of 68 questionnaires were retrieved after a period of two weeks. All 68 respondents agreed to partake in the second round of the Delphi survey.
In total, 20 respondents, representing 29.4 percent, were project managers; 5 respondents, representing 7.4 percent, were architects; 16 respondents, representing 23.5 percent, were quantity surveyors; 2 respondents, representing 2.9 percent, were civil engineers; 14 respondents, representing 20.6 percent, were sustainability managers; 3 respondents, representing 4.4 percent, were government/regulatory professionals; 6 respondents, representing 8.8 percent, were green building consultants; and the remaining 2 respondents, representing 2.9 percent, were facilities managers. The implication is that the respondents were from diverse backgrounds in green construction management.
In Round 1, the experts evaluated the identified stakeholder management strategies on the Likert scale. After Round 1, the responses were analyzed, and the results were sent back to the experts. The feedback enabled participants to review the overall pattern of the responses, and they were asked to reconsider their assessments where appropriate. The same assessment procedure was then applied in the second round.
The Delphi procedure was designed to comprise two rounds. Accordingly, the data collection concluded upon completion of the second round. The Kendall’s coefficient of concordance (W) was additionally used to assess the degree of agreement among the experts across the two Delphi rounds. As shown in Table 1, the value of W increased from 0.167 in Round 1 to 0.209 in Round 2, indicating an improvement in concordance between the two rounds. Nevertheless, these values represent a relatively weak overall agreement and, therefore, cannot be interpreted as evidence of a strong consensus.
Table 1.
Mean score and distribution of the stakeholder management strategies for green construction projects.
Data analysis was undertaken using the Statistical Package for Social Sciences (SPSS version 28) for the mean score ranking and the R software for the fuzzy synthesis computations. The descriptive statistics were calculated using mean, standard deviation, skewness and kurtosis. In undertaking the fuzzy analysis, an exploratory factor analysis was performed to establish the underlying structures of the variables and group them into components.
4. Data Analysis and Results
This section quantitatively ranks the stakeholder management strategies for sustainable construction projects. From the two-round Delphi survey undertaken, the mean values and indices were derived for used in the ranking. From the five-point grading scale, a strategy was perceived to be significant if the mean value was greater than 3 (≥3.0). Where two or more variables obtained same mean value, the standard deviation was used in the ranking.
A detailed observation of the round-by-round results shows that there were changes in the mean score rankings of the variables. The two-round Delphi survey was, therefore, helpful in letting the respondents reconsider their first scores. From round two of the Delphi, as shown in Table 1, Develop a project communication plan ranked 1st with a mean score of 4.47 and a standard deviation of 0.743. Early communication with stakeholders on their concerns ranked 2nd, with a mean score of 4.44 and a standard deviation of 0.817. Contractor and subcontractors should communicate on safety risks, especially regarding those caused by implementation of green practices ranked 3rd, with a mean score of 4.40 and a standard deviation of 0.626. Measure possible key performance indicators (KPIs) via stakeholder surveys ranked 4th, with a mean score of 4.31 and a standard deviation of 0.833. Building consensus on sustainability ranked 5th, with a mean score of 4.21 and a standard deviation of 0.764. Skewness and kurtosis are also reported to show the normality of the data.
In round two of the Delphi survey, as shown in Table 2 above, a five-factor component was generated using Varimax rotation and in five iterations. This explained 71.612 percent of the total variance explained. Exploratory factor solutions indicated strong item loadings on each factor (0.50 and above). This is above the recommended cut-off value of 0.32. The loading of each stakeholder management strategy indicates the contribution of each to the underlying components. The high factor loadings (above 0.60, except for two variables) show that the sample size is appropriate. The two variables ‘Early consultation with all stakeholders’ and ‘Appoint an independent party to monitor stakeholder matters during operations’ had low factor loadings. They were, therefore, excluded from further analyses.
Table 2.
Factor analysis results of the stakeholder management strategies for green construction projects.
From Table 3, the five principal stakeholder management strategy groups (SMSGs) and their associated factors are interpreted as follows: Component one—Information and understanding strategies; Component two—Consultation and engagement; Component three—Communication strategies; Component four—Meetings and advisory groups; and Component five—Public interest.
Table 3.
Weightings of MSAs and SMAGs of the stakeholder management strategies for sustainable construction projects.
4.1. Fuzzy Synthetic Evaluation of the Stakeholder Management Strategies for Sustainable Construction Projects
Assessing the influence of the stakeholder management strategies (SMSs) involves five SMSGs with different levels of influence. For this study, each SMSG is evaluated by way of its perceived significance to a project after which the overall index can be quantified. The fuzzy synthetic evaluation method (FSEM) was deemed to be the best technique in dealing with this multi-level and multi-factor constraints in the calculation index of the stakeholder management strategies for sustainable construction projects. The prediction of the influence in a project is by nature fuzzy and woolly. It mostly relies on human perception and judgement. Fuzzy theory was, therefore, most appropriate.
4.1.1. Setting Up the Evaluation Index Systems
From the factor analysis, there were five principal factors. Considering the five group classifications (CSFGs), an evaluation index system can be established. The SMSGs are defined as the first-level index system, defined as U = (u1, u2, u3, u4, u5). The stakeholder management strategies (SMSs) within each stakeholder management strategy groups (SMSGs) are the second-level index system, defined as:
| u1 = {u11, u12, u13, u14, u15, u16} u2 = {u21, u22, u23, u24, u25} u3 = {u31, u32, u33, u34} u4 = {u41, u42, u43} u5 = {u51} |
These index systems are used as the input variables for the FSE analysis.
4.1.2. Determining the Membership Functions of the SMSs and SMSGs
To determine the membership functions (MFs) of each SMS and SMSG, a fuzzy set was utilized. The Likert scale for grading the SMSs and SMSGs was on a five-point rating, as V = (1, 2, 3, 4, 5), where v1 = not significant at all; v2 = less significant; v3 = moderately significant; v4 = significant; and v5 = very significant. Hence, the MF of a given SMS, uin, is derived from the following equation (Ameyaw & Chan, 2015):
where: uin represents the nth SMS of a particular SMS, i (i = u1, u2, u3, u4, u5); MFuin is the membership function of a specific SMSG, uin; (j = 1, 2, 3, 4, 5) is the percentage of the Delphi survey respondents who scored j for the degree of the perceived significance of an SMS, uin, which denotes the membership function; is the relation between and its grade alternatives instead of fractions; and + signifies not addition but a notation.
From Equation (1), the membership function of a specific SMS, uin, is expressed as
This ranges between [0, 1]. The sum of MFuin should equal unity:
The membership functions and weightings of all strategies of all SMSGs are combined to derive its MF.
4.1.3. Calculating the Weighting Functions of Each SMS and SMSG
The weightings were obtained from the scores of the respondents and were obtained by normalizing the mean value of each SMS and SMSG. Weighting function wi represents the relative perceived significance of a variable as ranked by the study respondents. It can be derived via three main ways: analytical hierarchy process; tabulated judgement; and normalized mean method. For this study, the normalized mean was used, since it is simple to calculate and has been used in many past notable studies. The formula used was
where Wi is the weighting of the SMS/SMSG, and the weighting set functions is expressed as
where Mi is the mean score rating, and is the sum of the mean ratings.
Wi = {w1, w2, w3,… wn}
4.1.4. Establishing the Multi-Criteria and Multi-Level Fuzzy Synthetic Evaluation (FSE) Model
The process of establishing the influence of the stakeholder management strategies on sustainable construction projects is a multi-criteria and multi-level task. It encompasses three steps. The first step involves establishing the MF and weighting of every SMS, relying on the scores of the Delphi survey. The second step involves establishing the MF and weighting of each SMSG and then ascertaining its influence on sustainable construction projects. The final step is assessing the overall influence by describing it using a single indicator called the Overall Influence Index (OII).
In evaluating the influence of an SMSG on the success of sustainable construction projects, a fuzzy matrix, Di, is created for each of the SMSGs after establishing a fuzzy MF for each SMS. Using the m × n values of the entries and using Equation (2), the MFs of all the SMSs are expressed in a fuzzy matrix as follows:
Its elements are expressed by ; Di is the fuzzy evaluation matrix obtained using the weighting function set; Wi = {w1, w2, w3, … wn} of the SMSs within SMSGs: Di = Wi ● Ri = (din, din,…, din).
where din represents the degree of membership of the grade alternative, vi, regarding a causal group i, and ● represents the fuzzy composite operation.
According to Hsiao (Hsiao, 1998) and Owusu-Manu et al. (2021), the weighted mean method (M(●, ⊕)) is expressed as follows:
The weighted mean method was adopted since it is a widely used method in fuzzy studies, and it also averages the single influence of a specific factor.
When the weighting functions are normalized, the operator “⊕” regresses to the addition of real numbers:
In essence, the operation regresses to M (●, +). The influence of all of the success factors and their groupings are reserved in this, and the weighting functions are also normalized. The evaluation matrices, Di (i = 1, 2, 3, 4, 5), forms the fuzzy matrix, for assessing the overall influence of the stakeholder management strategies on sustainable construction projects.
From the factor analysis, there were five components. Using Equation (7), was normalized further using the weighting function set, (= {w1, w2, w3, w4, w5}), of the SMSGs to gain the fuzzy evaluation matrix.
where i = (CSFs (c) and CSFGs (g)) and I = (D′1, D′2, D′3, D′4, D′5) is the fuzzy evaluation matrix (MF) for the overall likelihood of the influence of the stakeholder management strategies on the sustainable construction projects. The matrix can be assessed using the grade choices (V = 1, 2, 3, 4, 5).
where I is the overall influence level (i = SMSG).
1 ≤ Ii ≤ 5
Equations (1) through (12) apply for both the SMSs and SMSGs. By combining the SMSs and SMSGs, the overall influence index is
where OII is the overall success index. The subscripts c and g are the SMSs and SMSGs, respectively. This is termed defuzzification and converts fuzzy numbers into hard outputs to assist in making decisions.
4.2. Practical Application of the Fuzzy Synthetic Evaluation
The following section demonstrates the use of the fuzzy predictive tool using data from the Delphi questionnaire survey.
4.2.1. Computing the Weighting Functions of the SMSs and SMSGs
The SMSs were second level and the SMSGs were first level while calculating their weightings using the mean score values from the Delphi study. For example, as shown in Table 3, Factor 5 (Meetings and Advisory Groups (u4)) has three factors with mean values of 3.46, 3.56 and 4.06. The total mean value is 11.074. The weightings (win) of u41, u42 and u43 can, therefore, be computed using Equation (4) as
Its normalized weighting function is
The remaining weighting functions in u1, u2, u3, and u5 are also calculated using the same formula.
4.2.2. Determining the Membership Functions for the SMSs and SMSGs
The MF of an SMS is calculated based on the collective scores from the Delphi participants using Equation (1) as a guide.
Using Building consensus on sustainability as an example, the results indicate that ranking of the perceived significance had the following response: 0% as ‘not significant at all’; 1.5% as ‘least significant’; 16.2% as ‘moderately significant’; 42.6% as ‘significant’; and 39.7% as ‘very significant’. Therefore, the MF is expressed as follows:
The MF is expressed as: (0.000, 0.015, 0.162, 0.426, 0.397).
Using similar steps, the MFs of the other SMSs are computed accordingly as shown in Table 4.
Table 4.
Membership function of the stakeholder management strategies for green construction projects.
4.2.3. Quantifying the Success Index of Each SMSG
The fuzzy synthetic evaluation was conducted along three dimensions, from Level 3 to Level 1. Level 3 was derived from the judgement of the Delphi respondents. In evaluating the success index of a particular SMSG, a function matrix was derived first using the results of Level 3.
Using ‘Communication Strategies (CS)’ (u3) as an example, the membership functions (SMSs) of all factors in this category are expressed in a fuzzy matrix as
Similarly, the fuzzy evaluation matrix of u3 of the CSFGs was also computed using the weighting function set and the MFs (Table 4) using Equation (12) as a guide.
| × VT = (0.074, 0.093, 0.294, 0.474, 0.064) × (1, 2, 3, 4, 5) = 3.360 × VT = (0.003, 0.020, 0.190, 0.475, 0.313) × (1, 2, 3, 4, 5) = 4.077 × VT = (0.004, 0.022, 0.077, 0.361, 0.538) × (1, 2, 3, 4, 5) = 4.411 × VT = (0.038, 0.130, 0.182, 0.384, 0.266) × (1, 2, 3, 4, 5) = 3.711 × VT = (0.015, 0.029, 0.500, 0.368, 0.088) × (1, 2, 3, 4, 5) = 3.485 |
4.2.4. Quantifying the Final Influence Index
The fuzzy evaluation matrices, Di(i = u1, u2, u3, u4, u5), of the SMSGs (Level 2) were, again, normalized utilizing their weighting functions to produce the final fuzzy evaluation matrix of the overall influence index (OII) (Level 1). Table 5 presents the final influence indices.
Table 5.
Overall index for the stakeholder management strategies.
The weighting matrix from Section 4.2.1 is {0.277, 0.280, 0.242, 0.152, 0.048}
The overall perceived level of influence of the stakeholder management strategies on sustainable construction projects is quantified as follows:
5. Discussion
5.1. SMSG 1: Information and Understanding Strategies
This stakeholder management strategy group accounted for 24.822% of the total variance. These variables had a combined eigen value of 4.716. It had an index of 3.360 and ranked 5th in the fuzzy evaluation. It consists of six variables (stakeholder management strategies). These strategies are as follows: Have a good understanding of the objectives of the sustainable building; Efficient conflict management system; Honest communication with general community; Consideration of stakeholders in longer-term performance monitoring; Clear and timely information distribution to general community; and Coordination and management of stakeholder network. ‘Efficient conflict management system’ (mean = 3.37; standard deviation = 0.991) was ranked highly by the respondents. Stakeholders have varying interests, expectations and concerns regarding green building projects (Darko et al., 2017). These become competing and lead to conflicts (Choi et al., 2016). It is essential that the leadership and experience of the developer, contractor and project manager on the project are balanced to effectively manage and reconcile any conflicts that may arise (Wuni & Shen, 2020). ‘Have a good understanding of the objectives of the sustainable building system’ (mean = 3.32; standard deviation = 0.921) was also ranked highly by the respondents. In sustainable buildings, stakeholder engagement involves effectively managing relationships among the stakeholders on both short-term and long-term bases (Alizar et al., 2008). This is facilitated by understanding the objectives of the sustainable project (Babon-Ayeng et al., 2022). Giving stakeholders opportunities to express themselves without fear and ensuring there is respect for all opinions will enable stakeholders to influence the resulting actions (Bahadorestani et al., 2020).
5.2. SMSG 2: Consultation and Engagement (CE)
This stakeholder management strategy group accounted for 17.234% of the total variance. These variables had a combined eigen value of 3.274. It had a high index of 4.077 and ranked 2nd in the fuzzy evaluation. It consists of five variables (stakeholder management strategies). These strategies are as follows: Information dissemination to the public; Early consultation with all stakeholders; Client as a funding organization should monitor project schedule on site; Building consensus on sustainability; and Identify relationships among stakeholder issues. ‘Information dissemination to the public’ (mean = 4.26; standard deviation = 0.745) was ranked highly by the respondents. Training is one way of ensuring information dissemination. Stakeholders on green projects with more training are likely to disseminate information to the public through various means such as focus groups using organizational decisionmakers, direct practitioners, and policymakers (Knoepke et al., 2019). ‘Early consultation with all stakeholders’ (mean = 4.01; standard deviation = 0.702) was also ranked highly by the respondents. Successful stakeholder management in projects entails the early identification, planning, and control, as well as engagement, of the requisite stakeholders together with a realization of their expectations of the project (Project Management Institute, 2017).
5.3. SMSG 3: Communication Strategies (CSs)
This stakeholder management strategy group accounted for 14.329% of the total variance. These variables had a combined eigen value of 2.723. It had a high index of 4.411 and ranked 1st in the fuzzy evaluation. It consists of four variables (stakeholder management strategies). These strategies are as follows: Develop a project communication plan; Measure possible key performance indicators (KPIs) via stakeholder surveys; Early communication with stakeholders on their concerns; and Contractor and subcontractors should communicate on safety risks, especially regarding those caused by implementation of green practices. ‘Develop a project communication plan’ (mean = 4.47; standard deviation = 0.743) was ranked highly by the respondents. A communication plan is essential for the success of stakeholder management in green building projects. Communication enhances effective information flow throughout the life cycle of a project. This leads to high levels of commitment and trust in the project (Hu et al., 2019). ‘Measure possible key performance indicators (KPIs) via stakeholder surveys’ (mean = 4.31; standard deviation = 0.833) was also ranked highly by the respondents. KPIs for stakeholder engagement are essential for measuring results over time, as the same KPIs can be regularly reported on to assess growth patterns. KPIs should not leave room for ambiguity but must be objective and quantifiable (Alwaer & Clements-Croome, 2010).
5.4. SMSG 4: Meetings and Advisory Groups (MAGs)
This stakeholder management strategy group accounted for 8.701% of the total variance. These variables had a combined eigen value of 1.653. It had an index of 3.711 and ranked 3rd in the fuzzy evaluation. It consists of three variables (stakeholder management strategies). These strategies are as follows: Strategic stakeholder meetings between service provider and government during operations; On-site engagement meetings with operational staff; and Establish community advisory groups.
‘Strategic stakeholder meetings between service provider and government during operations’ (mean = 3.46; standard deviation = 1.125) was ranked high by the respondents. ‘On-site engagement meetings with operational staff’ (mean = 3.56; standard deviation = 1.138) was also ranked high by the respondents. Through consistent engagement with stakeholders on site, project success can be achieved (Kaharuddin et al., 2020). On green construction projects, supervisors on projects can build excellent working relationships with their staff, clients and consultants, and this facilitates quick and efficient task execution (B. Collinge, 2016).
5.5. SMSG 5: Public Interest (PI)
This stakeholder management strategy group accounted for 6.527% of the total variance. These variables had a combined eigen value of 1.240. It had an index of 3.485 and ranked 4th in the fuzzy index. It consists of one variable (stakeholder management strategy). This strategy was ‘Paying attention to the general public interests’ (mean = 3.49; standard deviation = 0.763), which was ranked high by the respondents. Stakeholder management that incorporates the interests of the public leads to increasing public confidence in green projects (Connolly et al., 2015). This can be done through engaging local stakeholder groups that have a deep knowledge of community needs and the development of projects that have public interest (Leardini et al., 2019).
6. Conclusions
6.1. Main Findings
This study evaluated and then assessed the influence of stakeholder management strategies for sustainable construction projects in Ghana. A review of the past literature revealed 21 strategies. A factor analysis was conducted to establish the underlying relationships among the strategies, which revealed five principal factors. From a fuzzy analysis, the communication strategies component ranked 1st, and the overall perceived level of influence of the strategies on the delivery of sustainable construction was 3.87.
6.2. Implications
This study contributes to knowledge by deepening the understanding of stakeholder management strategies for delivering green construction projects in Ghana. The outcomes and findings in this important study have practical, empirical, and theoretical implications for construction and green building projects. The perspectives of experienced practitioners and respondents were sought. This study is also a pioneering research work in Ghana on stakeholder management strategies for green building projects. The findings highlight perceived significant strategies for managing stakeholders in green construction projects. A fuzzy index was also developed for ascertaining the perceived significance index for these strategies. Practically, this study serves as a guide for practitioners during their practice to identify the stakeholder management practices and priorities perceived as the most significant. According to the fuzzy index, the strategies that ranked the highest should receive more attention by all stakeholders to ensure successful green projects in Ghana and globally. A factor analysis undertaken on the fuzzy set generated five broad stakeholder strategy areas that are essential for green building projects to succeed.
Practitioners can use the evaluation index on a decision-support basis while adapting the implementation sequence to the project’s size, complexity, stakeholder structure, sustainability objectives, and available resources.
From the findings, during the initiation and planning stages, practitioners can identify and map relevant stakeholders, understand their interests and influence, establish communication mechanisms, and incorporate stakeholder expectations into project objectives.
6.3. Limitations
Even though this study has multi-faceted implications, it has some limitations. Firstly, even though adequate, the sample size is small and may limit generalization of the study’s findings. The generalized analysis of the stakeholder management strategies did not consider their peculiarities to different project types, stages and locations. However, this does not diminish the impact of this study in terms of generalizability. The use of purposive, non-probability sampling limits the statistical generalization of the findings. Nevertheless, this approach was appropriate for the Delphi component because the objective was to obtain informed judgements from experts. Other limitations comprise the sampling method and single-country context regarding the generalizability of the findings. Another limitation concerns the perceived rather than the observed outcomes. Finally, another limitation is that the last component was comprised only one variable. The single-item “Public interest” component is a limitation, and even though it has high loading, high loadings alone do not establish the adequacy or stability of the component solution.
6.4. Future Research
Future research should increase the sample size adopted, as well as also explore the interrelationships among the strategies identified in this study using structural equation modelling (SEM). Moreover, sensitivity analyses can be used to examine how variations in criterion weights and membership values influence the fuzzy synthetic evaluation results and to assess the stability of the resulting evaluations under alternative parameter assumptions.
Author Contributions
Conceptualization, A.S.K.K. and E.A.; methodology, A.S.K.K., M.T.T., K.A., I.A.-F.; software, A.S.K.K. and R.M.K.K.; writing—original draft preparation, A.S.K.K. and E.A.; writing—review and editing, K.A., D.B.S., M.T.T., I.A.-F. and R.M.K.K.; formal analysis, A.S.K.K., E.A.; I.A.-F., D.B.S., and R.M.K.K. All authors have read and agreed to the published version of the manuscript.
Funding
This research received no external funding.
Data Availability Statement
All the data used appears in this study.
Acknowledgments
Authors acknowledge anonymous reviewers and editors for their inputs in the article.
Conflicts of Interest
The authors declare no conflict of interest.
References
- Adhi, A. B., & Muslim, F. (2023). Development of stakeholder engagement strategies to improve sustainable construction implementation based on lean construction principles in Indonesia. Sustainability, 15(7), 6053. [Google Scholar] [CrossRef] [Scilit]
- Adinyira, E., Agyekum, K., Danku, J. C., Addison, P., & Kukah, A. S. (2020). Influence of subcontractor risk management on quality performance of building construction projects in Ghana. Journal of Construction in Developing Countries, 25(2), 175–197. [Google Scholar] [CrossRef] [Scilit]
- Agyekum, K., Akli-Nartey, E. E. K., Kukah, A. S., & Agyekum, A. K. (2021). Importance-performance analysis (IPA) of the indoor environmental quality (IEQ) of an EDGE-certified building in Ghana. International Journal of Building Pathology and Adaptation, 41(1), 73–95. [Google Scholar] [CrossRef] [Scilit]
- Agyekum, K., Amos-Abanyie, S., Kumah, V. M. A., Kukah, A. S. K., & Salgin, B. (2022a). Obstacles to the career progression of professional female project managers (PFPMs) in the Ghanaian construction industry. Engineering, Construction and Architectural Management. Advanced online publication. [Google Scholar] [CrossRef] [Scilit]
- Agyekum, K., Kukah, A. S., & Amudjie, J. (2022b). The impact of COVID-19 on the construction industry in Ghana: The case of some selected firms. Journal of Engineering, Design and Technology, 20(1), 222–244. [Google Scholar] [CrossRef] [Scilit]
- Akomea-Frimpong, I., Jin, X., Osei-Kyei, R., & Kukah, A. S. (2021). Public–private partnerships for sustainable infrastructure development in Ghana: A systematic review and recommendations. Smart and Sustainable Built Environment, 12(2), 237–257. [Google Scholar] [CrossRef] [Scilit]
- Akomea-Frimpong, I., Kukah, A. S., Jin, X., Osei-Kyei, R., & Pariafsai, F. (2022). Green finance for green buildings: A systematic review and conceptual foundation. Journal of Cleaner Production, 356, 131869. [Google Scholar] [CrossRef] [Scilit]
- Aladpoosh, H., Shaharoun, A. M., & Saman, M. Z. B. M. (2012). Critical features for project stakeholder management: A systematic literature review. International Journal of Applied Systemic Studies, 4(3), 150–167. [Google Scholar] [CrossRef] [Scilit]
- Alizar, M. A., Rahadini, A., & Love, E. (2008). Engaging local government in promoting good CSR practices and sustainable development through multi-stakeholder engagement. In Proceedings of the Indonesian petroleum association, 32nd annual convention. Indonesian Petroleum Association. [Google Scholar]
- Alwaer, H., & Clements-Croome, D. J. (2010). Key performance indicators (KPIs) and priority setting in using the multi-attribute approach for assessing sustainable intelligent buildings. Building and Environment, 45(4), 799–807. [Google Scholar] [CrossRef] [Scilit]
- Ameyaw, E. E., & Chan, A. P. (2015). Risk allocation in public-private partnership water supply projects in Ghana. Construction Management and Economics, 33(3), 187–208. [Google Scholar] [CrossRef] [Scilit]
- Asumadu, G., Quaigrain, R., Owusu-Manu, D., Edwards, D. J., Oduro-Ofori, E., Kukah, A. S., & Nsafoah, S. K. (2022). Analysis of risk factors associated with construction projects in urban wetlands ecosystem. International Journal of Sustainable Development and World Ecology, 30(2), 198–210. [Google Scholar] [CrossRef] [Scilit]
- Babon-Ayeng, P., Oduro-Ofori, E., Owusu-Manu, D.-G., Edwards, D. J., Kissi, E., & Kukah, A. S. K. (2022). Socio-political factors underlying the adoption of green bond financing of infrastructure projects: The case of Ghana. Journal of Capital Markets Studies, 6(3), 304–319. [Google Scholar] [CrossRef] [Scilit]
- Bahadorestani, A., Naderpajouh, N., & Sadiq, R. (2020). Planning for sustainable stakeholder engagement based on the assessment of conflicting interests in projects. Journal of Cleaner Production, 242, 118402. [Google Scholar] [CrossRef] [Scilit]
- Bosher, L., Dainty, A., Carrillo, P., Glass, J., & Price, A. (2007). Integrating disaster risk management into construction: A UK perspective. Building Research & Information, 35(2), 163–177. [Google Scholar] [CrossRef] [Scilit]
- Bourne, L., & Walker, D. H. (2005). Visualising and mapping stakeholder influence. Management Decision, 43(5), 649–660. [Google Scholar] [CrossRef] [Scilit]
- Chipulu, M., Ojiako, U., Marshall, A., Williams, T., Bititci, U., Mota, C., & Stamati, T. (2019). A dimensional analysis of stakeholder assessment of project outcomes. Production Planning & Control, 30(13), 1072–1090. [Google Scholar] [CrossRef] [Scilit]
- Choi, J. O., O’Connor, J. T., & Kim, T. W. (2016). Recipes for cost and schedule successes in industrial modular projects: Qualitative comparative analysis. Journal of Construction Engineering and Management, 142(10), 04016055. [Google Scholar] [CrossRef] [Scilit]
- Chong, H. Y., Zin, R. M., & Chong, S. C. (2013). Employing data warehouse for contract administration: E-dispute resolution prototype. Journal of Construction Engineering and Management, 139(6), 611–619. [Google Scholar] [CrossRef] [Scilit]
- Collinge, B. (2016). Stakeholder management strategies during construction project work. British Journal of Healthcare Management, 22(8), 394–400. [Google Scholar] [CrossRef] [Scilit]
- Collinge, W. H., & Harty, C. F. (2014). Stakeholder interpretations of design: Semiotic insights into the briefing process. Construction Management and Economics, 32(7–8), 760–772. [Google Scholar] [CrossRef] [Scilit]
- Connolly, C., Hyndman, N., & McConville, D. (2015). UK charity accounting. In Z. Hoque, & L. Parker (Eds.), Performance management in non-profit organizations: Global perspectives (pp. 155–182). Routledge. [Google Scholar]
- Creswell, J. W. (2014). Research design: Qualitative, quantitative and mixed methods approaches. SAGE Publications. [Google Scholar]
- Dansoh, A., Frimpong, S., Ampratwum, G., Dennis Oppong, G., & Osei-Kyei, R. (2020). Exploring the role of traditional authorities in managing the public as stakeholders on PPP projects: A case study. International Journal of Construction Management, 20(6), 628–641. [Google Scholar] [CrossRef] [Scilit]
- Darko, A., Zhang, C., & Chan, A. P. (2017). Drivers for green building: A review of empirical studies. Habitat International, 60, 34–49. [Google Scholar] [CrossRef] [Scilit]
- El-Gohary, N. M., Osman, H., & Ei-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595–604. [Google Scholar] [CrossRef] [Scilit]
- Eyiah-Botwe, E., Aigbavboa, C. O., & Thwala, D. W. (2016). Stakeholder management: A literature review of historical development and current trends. In Emerging trends in construction organisational practices and project management knowledge area—9th CIDB postgraduate conference. UCT Libraries Press. [Google Scholar]
- Freeman, R. E. (2007). Managing for stakeholders. SSRN Electronic Journal, 1–22. [Google Scholar]
- Frimpong, B. E., Sunindijo, R. Y., & Wang, C. (2020). Towards improving performance of the construction industry in Ghana: A SWOT approach. Civil Engineering Dimension, 22(1), 37–46. [Google Scholar] [CrossRef] [Scilit]
- Hamdan, H. A., Andersen, P. H., & de Boer, L. (2021). Stakeholder collaboration in sustainable neighborhood projects—A review and research agenda. Sustainable Cities and Society, 68, 102776. [Google Scholar] [CrossRef] [Scilit]
- Hon, C. K. H., Chan, A. P. C., & Yam, M. C. H. (2012). Empirical study to investigate the difficulties of implementing safety practices in the repair and maintenance sector in Hong Kong. Journal of Construction Engineering and Management, 138(7), 877–884. [Google Scholar] [CrossRef] [Scilit]
- Hsiao, S. W. (1998). Fuzzy logic based decision model for product design. International Journal of Industrial Ergonomics, 21(2), 103–116. [Google Scholar] [CrossRef] [Scilit]
- Hu, X., Chong, H. Y., Wang, X., & London, K. (2019). Understanding stakeholders in off-site manufacturing: A literature review. Journal of Construction Engineering and Management, 145(8), 1–15. [Google Scholar] [CrossRef] [Scilit]
- Jayasuriya, S., Zhang, G., & Yang, R. J. (2020). Exploring the impact of stakeholder management strategies on managing issues in PPP projects. International Journal of Construction Management, 20(6), 666–678. [Google Scholar] [CrossRef] [Scilit]
- Kaharuddin, S. K., Adnan, H., & Baharuddin, H. E. A. (2020). Success factors for stakeholder management for public-private partnerships infrastructure projects. Built Environment Journal, 17(2), 1–10. [Google Scholar] [CrossRef] [Scilit]
- Knoepke, C. E., Ingle, M. P., Matlock, D. D., Brownson, R. C., & Glasgow, R. E. (2019). Dissemination and stakeholder engagement practices among dissemination & implementation scientists: Results from an online survey. PLoS ONE, 14(11), e0216971. [Google Scholar] [CrossRef] [Scilit]
- Kukah, A. S. K., Jin, X., Osei-Kyei, R., & Perera, S. (2026a). Modelling organisational factors in carbon trading for the Australian construction industry: A fuzzy logic-based evaluation technique. Journal of Engineering, Design and Technology, 1–24. [Google Scholar] [CrossRef] [Scilit]
- Kukah, A. S. K., Jin, X., Trinh, M. T., Akomea-Frimpong, I., & Kukah, R. M. K. (2026b). Project management competencies required for carbon emissions reduction in the construction industry: A comprehensive review and future direction. Project Management Horizons, 1(1), 2. [Google Scholar] [CrossRef] [Scilit]
- Kukah, A. S. K., Jnr, A. V. K. B., & Opoku, A. (2022a). Strategies to reduce the impact of resource consumption in the Ghanaian construction industry. International Journal of Real Estate Studies, 16(1), 51–59. [Google Scholar] [CrossRef] [Scilit]
- Kukah, A. S. K., Owusu-Manu, D. G., Badu, E., & Asamoah, E. (2022b). Structural equation model (SEM) for evaluating interrelationships among risks inherent in Ghanaian public–private partnership (PPP) power projects. Engineering, Construction and Architectural Management. Advanced online publication. [Google Scholar] [CrossRef] [Scilit]
- Leaman, A., & Bordass, B. (2007). Are users more tolerant of ‘green’ buildings? Building Research & Information, 35(6), 662–673. [Google Scholar] [CrossRef] [Scilit]
- Leardini, C., Moggi, S., & Rossi, G. (2019). The new era of stakeholder engagement: Gaining, maintaining, and repairing legitimacy in non-profit organizations. International Journal of Public Administration, 42(6), 520–532. [Google Scholar] [CrossRef] [Scilit]
- Maier, A., & Aschilean, I. (2020). Importance of stakeholder management for sustainable construction industry. In Proceedings of the 36th IBIMA conference. International Business Information Management. [Google Scholar]
- Mok, K. Y., Shen, G. Q., & Yang, R. (2018). Stakeholder complexity in large scale green building projects: A holistic analysis towards a better understanding. Engineering, Construction and Architectural Management, 25(11), 1454–1474. [Google Scholar]
- Nielsen, B. F., Baer, D., & Lindkvist, C. (2019). Identifying and supporting exploratory and exploitative models of innovation in municipal urban planning: Key challenges from seven Norwegian energy ambitious neighborhood pilots. Technological Forecasting and Social Change, 142, 142–153. [Google Scholar] [CrossRef] [Scilit]
- Ofori-Kuragu, J. K., Owusu-Manu, D. G., & Ayarkwa, J. (2016). The case for a construction industry council in Ghana. Journal of Construction in Developing Countries, 21(2), 131. [Google Scholar] [CrossRef] [Scilit]
- Oliver, A., & Pearl, D. S. (2018). Rethinking sustainability frameworks in neighbourhood projects: A process-based approach. Building Research & Information, 46(5), 513–527. [Google Scholar] [CrossRef] [Scilit]
- Oppong, G. D., Chan, A. P., & Dansoh, A. (2017). A review of stakeholder management performance attributes in construction projects. International Journal of Project Management, 35(6), 1037–1051. [Google Scholar] [CrossRef] [Scilit]
- Osei-Kyei, R., Chan, A. P., Dansoh, A., Ofori-Kuragu, J. K., & Oppong, G. D. (2018). Strategies for effective management of unsolicited public–private partnership proposals. Journal of Management in Engineering, 34(3), 04018006. [Google Scholar] [CrossRef] [Scilit]
- Owusu-Manu, D.-G., Edwards, D. J., Kukah, A. S., Parn, E. A., El-Gohary, H., & Hosseini, M. R. (2018). An empirical examination of moral hazards and adverse selection on PPP projects: A case study of Ghana. Journal of Engineering, Design and Technology, 16(6), 910–924. [Google Scholar]
- Owusu-Manu, D.-G., Kukah, A. S. K., Edwards, D. J., & Ameyaw, E. E. (2021). Fuzzy synthetic evaluation of moral hazard and adverse selection of public private partnership projects. International Journal of Construction Management, 23(2), 1–10. [Google Scholar] [CrossRef] [Scilit]
- Price, A., & Al-Yami, A. M. (2008, November 15–17). Realizing sustainability through stakeholder management. Joint International Symposium of CIB-W055 & CIB-W065: Transformation Through Construction, Edinburgh, Scotland. [Google Scholar]
- Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute. [Google Scholar] [CrossRef] [Scilit]
- Rizvi, S., Kukah, A. S. K., Jin, X., & Perera, S. (2023). Impacts of COVID-19 pandemic on construction costs in Australia. In International symposium on advancement of construction management and real estate (pp. 505–516). Springer Nature Singapore. [Google Scholar]
- Rossiter, W., & Smith, D. J. (2018). Green innovation and the development of sustainable communities: The case of Blueprint Regeneration’s Trent Basin development. The International Journal of Entrepreneurship and Innovation, 19(1), 21–32. [Google Scholar]
- Seidu, S., Owusu-Manu, D.-G., Kukah, A. S. K., Adesi, M., Oduro-Ofori, E., & Edwards, D. J. (2022). An assessment of the implications of disruptive technologies on the performance of energy infrastructure projects in Ghana. International Journal of Energy Sector Management, 17(5), 887–903. [Google Scholar] [CrossRef] [Scilit]
- Unterhitzenberger, C., Wilson, H., James Bryde, D., Rost, M., & Joby, R. (2021). The stakeholder challenge: Dealing with challenging situations involving stakeholders. Production Planning & Control, 32(11), 926–941. [Google Scholar] [CrossRef] [Scilit]
- Wadsworth, Y. (1997). Do it yourself social research (2nd ed.). Allen & Unwin. [Google Scholar]
- Wen, S., & Qiang, G. (2022). Managing stakeholder concerns in green building projects with a view towards achieving social sustainability: A Bayesian-network model. Frontiers in Environmental Science, 10, 874367. [Google Scholar] [CrossRef] [Scilit]
- Wuni, I. Y., & Shen, G. Q. (2020). Stakeholder management in prefabricated prefinished volumetric construction projects: Benchmarking the key result areas. Built Environment Project and Asset Management, 10(3), 407–421. [Google Scholar] [CrossRef] [Scilit]
- Xia, B., Molenaar, K., Chan, A., Skitmore, M., & Zou, J. (2013). Determining optimal proportion of design in design-build request for proposals. Journal of Construction Engineering and Management, 139(6), 620–627. [Google Scholar] [CrossRef] [Scilit]
- Yang, R. J., & Zou, P. X. (2014). Stakeholder-associated risks and their interactions in complex green building projects: A social network model. Building and Environment, 73, 208–222. [Google Scholar] [CrossRef] [Scilit]
- Yu, T., Liang, X., Shen, G. Q., Shi, Q., & Wang, G. (2019). An optimization model for managing stakeholder conflicts in urban redevelopment projects in China. Journal of Cleaner Production, 212, 537–547. [Google Scholar] [CrossRef] [Scilit]
- Zhao, X., Hwang, B. G., Pheng Low, S., & Wu, P. (2015). Reducing hindrances to enterprise risk management implementation in construction firms. Journal of Construction Engineering and Management, 141(3), 04014083. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.