BDERL: A Reinforcement Learning-Enhanced Differential Evolution for the Earliness–Tardiness RCPSP

,
and
1
School of Mathematics and Computer Science, Hanoi National University of Education, 136 Xuan Thuy, Ha Noi 100000, Vietnam
2
Faculty of Engineering Technology, Hung Vuong University, Phu Tho 35000, Vietnam
3
Faculty of Economic Information System and E-Commerce, Thuong Mai University, 79 Ho Tung Mau, Ha Noi 100000, Vietnam
*
Author to whom correspondence should be addressed.

Abstract

This paper introduces the ETMS-RCPSP (Earliness–Tardiness Multi-Skill Resource-Constrained Scheduling Problem)—a novel problem derived from the MS-RCPSP by adding constraints on project completion time or actual production contracts. The goal of the new problem is to control the project completion time as closely as possible to reality—this differs from the original MS-RCPSP, which aimed to minimize project execution time. The objective of the problem is of greater practical significance in ensuring project completion on schedule while also addressing related issues, such as the ability to receive finished products on time as stipulated in the contract. The ETMS-RCPSP is an NP-hard problem whose result can be used for resource allocation in project execution or for resource arrangement in production lines to fulfill economic contracts. To address the ETMS-RCPSP, the paper proposes a new evolutionary algorithm, BDERL (Balanced Differential Evolution with Reinforcement Learning), that combines differential evolution with a problem-specific decoding mechanism and an adaptive parameter control strategy based on reinforcement learning (Q-learning). The proposed algorithm is evaluated on benchmark instances derived from the iMOPSE dataset and the TNG company dataset—a real-world dataset from manufacturing and contract-driven environments. Experimental results demonstrate that the approach consistently reduces total production costs compared to baseline heuristics while maintaining competitive computational efficiency. The findings underscore the efficacy of adaptive hybrid optimization techniques in solving intricate production scheduling problems characterized by limited resources and varied skill competencies.

1. Introduction

In modern production systems with contract-based production lines and operating environments, increasingly stringent delivery deadlines make resource-allocation planning a critical factor in operational efficiency. In particular, the allocation of multi-skilled human resources plays a central role in ensuring on-time order fulfillment, improving job performance, and enhancing overall productivity. Among the scheduling models studied, the multi-skilled resource-constrained project scheduling problem (MS-RCPSP) has attracted significant attention due to its high applicability and computational complexity. The difficulty of this problem stems from the need to simultaneously satisfy multiple closely related constraints, including skill match, resource limitations, and the precedence relationships between tasks. The MS-RCPSP [1] is an extension of the classical resource-constrained project scheduling problem (RCPSP), in which each resource can possess multiple skills, and each job can be performed only when all required skills are feasible. Thanks to its wide applicability across many practical fields, such as skilled human resource management, flexible manufacturing systems, and production planning, MS-RCPSP has become an important research topic in the scientific community [2,3]. In recent years, this problem has continued to receive much attention through the application of modern optimization methods such as genetic algorithms, reinforcement learning, and other advanced metaheuristic techniques [4].
From a practical perspective, completing a job too early is not always beneficial, even though it may appear positive visually. Completing orders or projects ahead of schedule can lead to undesirable consequences such as increased inventory and storage costs. Conversely, late completion often results in contractual penalties, customer dissatisfaction, and reputational damage. This problem is common not only in manufacturing systems but also in large-scale project-based industries. Numerous real-world examples clearly illustrate the severity of the impacts caused by delays. For instance, the London Crossrail project [5] was commissioned in 2022 after more than three years of delays and was over budget by approximately £4 billion. Similarly, the Panama Canal expansion project [6] was completed in 2016 after 2 years of delays, amid major legal disputes over billions of dollars in additional costs. Berlin Brandenburg Airport (BER) [7] was delayed by at least 8 years and incurred billions of dollars in overruns. In the manufacturing environment, similar phenomena have been observed, where delays in production scheduling directly lead to penalty costs, reduced productivity, and lost customers [8]. Furthermore, a recent study [9] analyzed over 1200 cases of construction industry delays in Kuwait, based on data from the Ministry of Justice. As shown in Figure 1, the financial impact of these cases was significant, with the total project budget reaching 154,198,977 KD and the total compensation value claimed accounting for 16.95% of the initial budget, equivalent to 26,135,726 KD.
Figure 1. Comparison between the total project budget and the claimed compensation amount for the analyzed construction projects.
Based on the above practical issues, this study proposes a new variant of the MS-RCPSP, called the early-lag multi-skill resource-constrained project scheduling problem (ETMS-RCPSP). This new problem adds the constraint that the project/contract completion time must adhere to the deadline; the less deviation from the deadline, the better the fulfillment of the initial project or contract agreements. In the ETMS-RCPSP considered in this study, lag (tardiness) represents the degree of completion after the deadline, while earliness represents the degree of completion before the deadline. Both of these factors have significant practical implications in production scheduling problems and contract-based operating environments.
The main contributions of this paper are:
(1)
Specifically state the ETMS-RCPSP based on specific mathematical constraints and present some practical applications of this problem.
(2)
To solve the ETMS-RCPSP, a smart hybrid optimization algorithm called BDERL was built, which combines differential evolution (DE) with two main improvements: a free task balancing strategy to effectively minimize the infeasible search space and a Q-learning-based reinforcement learning mechanism to control the adaptive parameter.
(3)
To demonstrate that the proposed method improves the quality and durability of the solution, especially in complex and constrained production scheduling scenarios, experiments were conducted on standard datasets (iMOPSE) and real-world production datasets (TNG).
The rest of the paper is structured as follows: Section 2 presents studies on the MS-RCPSP and existing solutions. Section 3 states the ETMS-RCPSP, introduces the new system model, and provides an illustrative example. Section 4 describes the proposed BDERL algorithm. Section 5 presents comprehensive experiments evaluating the proposed BDERL algorithm. Finally, Section 6 summarizes the paper’s main results and outlines future research directions.

3. The ETMS-RCPSP Formulation

The ETMS-RCPSP is an extended variant of the MS-RCPSP, in which a manufacturing project comprises a set of production tasks that must be executed by a limited number of renewable workforce resources, subject to multiple constraints, including task precedence, skill compatibility, and resource assignment. Each task has a fixed processing duration and requires one or more specific skills at defined proficiency levels. Moreover, task execution must adhere to precedence relationships, wherein a task cannot begin until all its predecessor tasks have been completed. A task may have multiple predecessors or successors. Each resource can execute only one task at a time and is defined by a skill profile that specifies which tasks it is qualified to perform.
Diverging from the classical focus on makespan minimization, the ETMS-RCPSP aims to minimize the total earliness and tardiness of production task completions with respect to their specified due dates. Specifically, tardiness is defined as the positive deviation from the due date when a task’s completion time exceeds its due date. In contrast, earliness is the time by which a task completes before its due date.
E i = m a x 0 ,   h i − f i , L i = m a x 0 ,   f i − h i
h i denote the actual completion time of task i , and f i represents the specified due date for that task. Earliness ( E i ) quantifies how much earlier a task is completed relative to its due date, while tardiness ( L i ) measures the delay beyond the allowed completion time. The objective function thus aims to minimize the sum of these temporal deviations across all scheduled tasks.
Figure 2 presents a visual example of a production schedule comprising five production tasks, where each task’s actual completion time is shown alongside its deviation from the assigned due date. Green bars represent completion times, while blue and pink segments correspond to earliness and tardiness, respectively. For example, T1 and T2 are completed 6 and 8 h early, respectively, whereas T4 and T5 are delayed by 15 and 6 h. The total deviation across all tasks equals 40 h, illustrating the cumulative scheduling inefficiency under the given production constraints. This example underscores a critical aspect of real-world manufacturing project scheduling: deviations from due dates, whether early or late, can lead to substantial operational, financial, and legal contractual consequences. Early completions may result in resource idling, additional storage costs, or workflow imbalances, while delays often trigger contractual penalties, disputes, cascading production disruptions, and reputational damage. Therefore, minimizing total earliness and tardiness is not simply a theoretical optimization objective, but rather a practical imperative for the effective planning and execution of large-scale, resource-constrained manufacturing project environments. The mathematical formulation of the ETMS-RCPSP relies on the notation defined in Table 2.
f X = ∑ j = 1 t c o u n t e j × E j + l j × L j
where e j : weights for evaluating the early completion of the task j ; l j : weights for evaluating the late completion of the task j ; E j , L j are the earliness and tardiness values of task j and are defined in Equation (1).
Figure 2. Project schedule showing task completion times with earliness (blue) and tardiness (pink) deviations from assigned due dates. Total scheduling inefficiency: 40 h across five tasks, with T4 showing the largest delay (15 h) and T1, T2 completing ahead of schedule.
Table 2. Mathematic symbols.
The objective of the ETMS-RCPSP is to find a feasible schedule X   ∈   X a l l that minimizes the total earliness and tardiness across all tasks, that is, f X → m i n . The obtained schedule must satisfy the following constraints to ensure feasibility with respect to precedence relations, resource availability, and skill requirements:
S k ≠ ∅     ∀ R k ∈ R
d m k ≥ 0   ∀   T m ∈ T ,     R k     ∈   R
C i ≥ 0   ∀   T i ∈ T
C i ≤ B k ,   ∀ T k ∈ T ,   k ≠ 1 , T i   ∈ P k  
∀ T i ∈ T k ,   ∃ S q   ∈ S k : g S q = g A i   & , r S q ≥ r A i  
∀ R k ∈ R ,   ∀ q ∈ B T f i s t X ,   C T l a s t X :   ∑ i = 1 t c o u n t V i , k q ≤ 1
∀ T i ∈ T ,   ∀ q ∈ B T f i s t X ,   C T l a s t X ,   ∃ ! R k ∈ R :   V i , k q = 1 ,   w h e r e   V i , k q ∈ 0 , 1  
The aforementioned constraints can be interpreted as follows. Constraint (3) requires that each resource possess at least one skill from the global skill set, ensuring that every resource is capable of performing at least one task. Constraints (4) and (5) impose non-negativity on task durations. Although task durations are strictly positive in real-world scenarios, zero-duration values are introduced solely to model dummy tasks representing the start and end points of the project schedule. Constraint (6) enforces precedence relationships, meaning that a predecessor task i must be completed before its successor task k can start. Constraint (7): For every task T i ∈ T k (executable by a resource k ), there must exist at least one skill A i   ∈ S k such that the skill type corresponds to the requirement of the task i , and the resource’s proficiency level is no less than the required level. Constraint (8) ensures that at each time slot ( q ), each resource is assigned to no more than one task. That is, for a given resource k , the sum of its assignments at time q must be either 0 (not assigned) or 1 (assigned to exactly one task). Constraint (9) requires that each task is allocated to exactly one resource and be processed exclusively by that resource throughout its execution period.
Example 1: An online retail system development project consists of four tasks, T = {T1—UI Design, T2—Payment Module, T3—Product Catalog, T4—System Integration}. The project is executed by three resources, R = {R1, R2, R3}. The skill set is defined as S = {S1—Designer, S2—Frontend Dev, S3—Backend Dev, S4—Developer}. Project information is provided in Table 3.
Table 3. Project information.
Based on the information in Table 3, a feasible schedule X can be constructed as illustrated in Figure 3. Tasks T2 and T3 are scheduled to run in parallel immediately after T1 completes at time 2, assigned to resources R2 and R3, respectively. Task T4 is assigned to R3 and begins at time 5, once both predecessors T2 (ending at time 4) and T3 (ending at time 5) have finished. The resulting schedule yields an objective value of 0 + 1 + 1 + 1 = 3 days, since T1 meets its due date exactly, T2 and T4 complete earlier than their assigned deadlines (earliness of 1 day each), whereas T3 is completed later than its due date (tardiness of 1 day).
Figure 3. Feasible schedule X.
As shown in Table 4, the ETMS-RCPSP and the MS-RCPSP share equivalent constraints. The primary distinction lies in their objective functions: whereas the MS-RCPSP minimizes the project makespan, the proposed ETMS-RCPSP focuses on minimizing the total deviation of task completion times, including both earliness and tardiness, relative to predefined deadlines.
Table 4. Key differences between the ETMS-RCPSP and the MS-RCPSP.
Lemma 1:
The ETMS-RCPSP is formulated using the Graham notation framework [32]:
  α     β   γ  
where α denotes the machine environment or resource configuration, β represents the job characteristics and associated constraints, and γ specifies the objective or optimization criterion.
In the context of the ETMS-RCPSP, the notation components are instantiated as follows: α corresponds to a limited set of renewable resources shared among project activities. β characterizes precedence relationships among tasks, where each task can only commence once all of its predecessor tasks have been completed, reflecting a strict parent-child dependency structure. γ refers to the objective function, which in this case is the minimization of total project delay or makespan deviation. Therefore, the ETMS-RCPSP can be accurately modeled and classified within the Graham notation framework as shown in (10). This representation enables a standardized and concise description of the problem, facilitating comparison with other scheduling problems in the literature.
Lemma 2:
The ETMS-RCPSP problem is NP-hard.
The MS-RCPSP has been shown to be NP-hard [33]. Notably, the underlying assumptions and constraint structures of the ETMS-RCPSP are analogous to those of the MS-RCPSP. The primary difference lies in the objective function: while the MS-RCPSP focuses on minimizing the makespan, the ETMS-RCPSP aims to minimize the total deviation between actual task completion times and predefined deadlines. Given the structural similarity between the two problems, the computational complexity of the ETMS-RCPSP is at least equivalent to that of the MS-RCPSP. Therefore, if the MSRCPSP is NP-hard, it follows that the ETMS-RCPSP is also NP-hard by reduction.
As the ETMS-RCPSP is NP-hard, it precludes the existence of a polynomial-time exact algorithm unless P   =   N P . Consequently, exact solution methods become computationally prohibitive for large-scale instances. This complexity necessitates the adoption of metaheuristic strategies to secure high-quality solutions within viable computational timeframes. In particular, evolutionary algorithms such as GA, DE, and PSO have demonstrated superior performance, further motivating the development of the BDERL method proposed in this study.

4. BDERL Algorithm

To effectively solve the ETMS-RCPSP, this paper presents an optimization algorithm. BDERL (Balanced Differential Evolution with Reinforcement Learning) algorithm integrates Differential Evolution with the representation and FTB (Free Task Balancing) technique with Q-learning based intelligent selection of F and CR based on optimization state. BDERL uses intelligent parameter selection through reinforcement learning. Details follow in subsequent subsections.

4.1. Individual Representation and Objective Function Evaluation

In the evolutionary algorithm designed to solve the ETMS-RCPSP, the population evolves over multiple generations to minimize the total earliness and tardiness of production project tasks. Each individual in the population is represented as a vector, where each element corresponds to one of the manufacturing project’s production tasks. The value at each position in the vector indicates the index of the workforce resource assigned to execute the corresponding task. An example of this individual representation in vector form is shown in Table 5 below:
Table 5. Solution representation showing task-resource assignment pairs for a 15-task scheduling problem. Upper row: task indices (1–15); lower row: assigned resource index for each task.
Table 5 represents an individual as a vector, in which the index denotes the order of tasks to be performed, and the corresponding value indicates the index of the resource assigned to execute each task. Figure 4 illustrates the schedule of an individual with a resource assignment vector [1,2,2,1,1,2,1,2,2,1,1,2,1,2,1], where 15 tasks are allocated sequentially to two resources (R1, R2) without overlap.
Figure 4. Gantt chart for an individual (a schedule).
To evaluate the objective function of an individual, the study follows these steps: Step 1: Before execution, a standard individual is created, with the corresponding task completion times presented. Step 2: During the evolutionary process, a corresponding evolved individual is obtained, and its task completion times are shown in Table 6. Step 3: The objective function is calculated as follows: For each task, compute the deviation in completion time compared to the standard individual. Then, sum the absolute values of these deviations across all tasks to obtain the objective function value. An example of this calculation is illustrated in Table 6. After computation, the objective function value corresponding to the evolved individual is: 135 h.
Table 6. Optimized task schedule after evolutionary algorithm, displaying actual completion times with earliness and tardiness penalties. Total deviation: 105 h across all tasks.

4.2. Free Task Balancing Technique

One distinctive feature of the MS-RCPSP is the presence of tasks without precedence constraints, commonly called free tasks. These tasks are not dependent on the completion of any other tasks and can therefore be scheduled independently. To exploit this property, a technique called Free Task Balancing (FTB) is proposed to reduce the search space and enhance computational efficiency during scheduling.
The core idea of FTB is to identify all free tasks in advance and assign fixed resources to them before the optimization process, assuming that all resources possess sufficient skill levels to perform these tasks. By preprocessing and solving unconstrained resource allocation tasks, the proposed algorithm can focus on tasks with more complex constraints. This approach effectively decomposes the problem and facilitates faster convergence by simplifying scheduling decisions during the early stages of the optimization process. For instance, Figure 5 presents a project comprising 15 tasks and two resource types (R1 and R2), fully capable of executing all tasks. Applying the FTB technique significantly reduces the complexity of the initialization phase, thereby enabling the optimization algorithm to focus more computational effort on regions of the solution space characterized by higher levels of task dependency and resource interaction. This strategy is particularly advantageous in the context of evolutionary algorithms such as GA and DE, which are known to be highly sensitive to the quality of the initial population. By simplifying early-stage scheduling decisions, FTB enhances the algorithm’s ability to converge more efficiently and reliably in the subsequent optimization stages.
Figure 5. Task dependency tree organized into four hierarchical levels based on precedence depth. Arrows indicate which tasks must complete before others can start.
Example 2: There are 15 tasks in total, of which 7 are free. Figure 5 illustrates their dependencies.
In the FTB technique, the first step is to identify the set of all tasks without precedence constraints, i.e., those that do not require any parent tasks in the project dependency graph. These free tasks can be processed directly during the initialization phase without affecting the overall logical structure of the project schedule. Once the set of free tasks is identified, suitable resources are assigned to each task based on skill compatibility and availability. However, to ensure efficient resource utilization and maintain workload balance during project execution, a carefully designed resource allocation mechanism is required. The goal is to avoid imbalance scenarios in which certain resources are overloaded while others remain underutilized or idle. Balanced assignment can be achieved using lightweight optimization strategies such as (i) evenly distributing the number of free tasks among eligible resources, (ii) prioritizing resources with lower current load at the time of assignment, and (iii) employing cost functions that minimize the average load or standard deviation of workload across resources to guide task allocation. Applying the FTB technique during the initialization stage not only reduces the computational burden in the main optimization process (e.g., the evolutionary loop in metaheuristic algorithms) but also improves the quality of the initial solution. This, in turn, improves the convergence speed and the overall quality of the final scheduling outcome. Table 7 illustrates the resource fixation strategy implemented for free tasks.
Table 7. Resource assignments for seven free tasks (tasks without predecessors).
Algorithm 1 describes the FTB technique.
Algorithm 1: FTB
Input: Individual C, which represents a feasible project schedule.
Output: C’, where free tasks have been assigned to resources for execution.
Begin
1: for (i = 0; i < len(C); i++) do
2:  if (isFreeTask(C[i])) then
3:   C’ = AssignFreeTaskToResource(Res, C[i]);
4:  end if
5: end for
6: return C’;
End
where: len(C) is a function that calculates the length of individual C; isFreeTask(Jobi): A function that checks whether task Jobi is a free task; AssignFreeTaskToResource(Res, Jobi): A function that assigns resource Res to perform free task Jobi, ensuring that the assignment complies with all problem-specific constraints.
The application of the FTB technique offers several tangible benefits during the project scheduling optimization process. Specifically, since resources are pre-assigned to tasks without precedence constraints at the initialization stage, the variation in execution times among these tasks tends to be minimal. This improves schedule stability and reduces the computational time required during the evolutionary phase of metaheuristic algorithms. In addition, FTB significantly reduces the algorithm’s search space by eliminating redundant resource assignment choices for tasks whose execution has already been fixed. As a result, the algorithm can focus its exploration efforts on the more complex, constraint-driven portions of the schedule. Both proposed algorithms in this study incorporate the FTB technique as part of their initialization strategy.
Figure 5, the project tasks are divided into 4 levels: Level 0 contains a dummy task representing the project start; Level 1 has 7 free tasks: T1, T2, T3, T8, T10, T11, and T14; Level 2 consists of four tasks: T4, T5, T6, T7 and T13; Level 3 includes 3 tasks: T9, T12, and T15. Assuming there are only 2 available resources to implement this project, there are two options for scheduling the execution: Option 1: Assign resources to all 15 tasks without any optimization, resulting in a solution space of 32,768 possible schedules; Option 2: Apply the FTB technique to reduce the solution space. This method significantly narrows the possibilities down to only 256 schedules. Comparing the two approaches, it is evident that the FTB technique is highly effective, reducing the solution space from 32,768 to just 256 schedules (128-fold reduction).

4.3. Algorithm BDERL

Reinforcement Learning is a learning paradigm in which an agent learns by interacting with an environment to maximize cumulative rewards over time. As Barto [34] describes, RL focuses on learning how to act by mapping states to actions that maximize expected future returns. The BDERL algorithm minimizes the objective function of the ETMS-RCPSP through adaptive parameter control. The algorithm synergistically integrates the FTB technique with DE [35], incorporating reinforcement learning-based intelligent selection of the scaling factor (F) and crossover rate (CR). By continuously monitoring the optimization state, the reinforcement learning component adaptively tunes these control parameters, while the FTB technique ensures efficient resource allocation and satisfaction of all constraints. In this study, we used the Q-learning algorithm integrated into BDERL. The Q-learning algorithm is defined in terms of its action space, state space, and reward as follows:
-
Action space: Each action corresponds to selecting a pair (F, CR), where F is the mutation factor and CR is the crossover rate. Specifically, F ∈ [0.4, 0.9] and CR ∈ [0.6, 1.0], with increments of 0.1. This results in a discrete action space comprising 30 combinations.
-
State space: Each state represents the level of improvement in the objective function between successive generations. The state classification logic is implemented in the GetState() function.
-
Reward: The reward is defined as the improvement level, i.e., the difference between the objective value of the previous generation and that of the current generation. This formulation directly reflects the effectiveness of an action.
The Q-learning component proceeds through the following steps:
-
Step 1: Initialize the Q-table Q[s, (F, CR)] = 0 for all possible states s and actions (F, CR).
-
Step 2: Define the number of training episodes as equal to the total number of generations in the evolutionary process.
-
Step 3: For each generation, perform the following sub-steps:
+
Determine the current state s.
+
Select an action (F, CR) based on the ϵ—greedy policy.
+
Apply mutation and crossover using the selected parameter pair (F, CR).
+
Receive a reward signal r and transition to the next state s′.
+
The Q-table is updated according to Equation:
Q s ,   F , C R ←   Q s ,   F , C R + α   ∗ [ r + γ × max ( Q s ′ ,   a ′ − Q s ,   F , C R            
+
Update state.
-
Step 4: Repeat Step 3 until the predefined number of generations is reached.
-
Step 5: Utilize the learned Q-table to select optimal parameter configurations in subsequent runs or experimental evaluations.
In addition to the functions and variables shared with the BDERL variant incorporates several additional components: UpdateQ(): the Q-value update is performed when transitioning to a new state; Reward(): returns a reward upon execution; GetState(): produces the next state resulting from applying an action to the current state; ChooseAction(): selects an action by referencing the Q-table given the current state. Figure 6, Algorithm 2 presents the detailed steps of BDERL.
Figure 6. BDER flowchart.
Algorithm 2 shows the integration of the FTB technique at line 17, and the incorporation of Q-learning at lines 5–6 and 37–40 within the BDERL algorithm. Since the state and action spaces are finite and bounded, the additional Q-learning update step contributes O(1) per iteration. Therefore, the overall complexity remains O(G × N × D). Compared to standard DE, the Q-learning component adds only a constant-time update step per iteration (O(1)), leaving the overall complexity unchanged at O(G × N × D). GA and PSO share the same asymptotic complexity but incur higher constant factors in practice due to their operator overhead, GA from crossover and selection operators, PSO from velocity and position update computations for each particle, which is consistent with the empirical runtime differences observed in Section 5. Parallelization of the population evaluation loop (lines 7–12 in Algorithm 2) is architecturally straightforward and could yield significant speedups, particularly for large-scale instances; this is left as a direction for future work.
Algorithm 2: BDERL
Input: dataset, numGen: number of generations.
Output: the best individual and the minimum value of earliness and tardiness.
Begin
1: Load and valid dataset
2: P ← Init population, RLQ ← Init Q-learning
3: count = 0; Calculate fitness, pBest, etBest;
4: while (count < numGen) do
5:   s = RLQ.getState();
6:   (F, CR) = RLQ.chooseAction(s);
7:   for (i = 0; i < len(P); i++) do
8:    Fitness[i] = Evaluate(P[i]);
9:    if (Fitness[i] < etBest) then
10:      etBest = Fitness[i]; pBest = P[i];
11:    end if
12:   end for
13:  Irand = randbetw(1, tcount);
14:  for (i = 0; i < len(P); i++) do
15:   c = P[i]; random k1 ≠ k2 ≠ k3 ≠ i ∈ (0,len(P));
16:   x1 = P[k1]; x2 = P[k2]; x3 = P[k3];
17:   V = FTB(c)
18:   for (k = 0; k < tcount; k++) do
19:    if (!isFreeTask(c[k])) then
20:     V[k] = x1[k] + F ∗ (x2[k] − x3[k]);
21:    end if
22:   end for
23:   for (j = 0; j < tcount; j++) do
24:    if (rand() ≥ CR || i == Irand) then
25:     u[j] = V[j];
26:    else
27:     u[j] = c[j];
28:    end if
29:   end for
30:   ETc = Evaluate(u);
31:   if (ETc < Fitness[i]) then
32:    P[i] = u; Fitness[i] = ETc;
33:   end if
34:   if (ETc < etBest) then
35:    etBest = ETc; pBest = u;
36:   end if
37:  end for
38:  update bestFitnessCurrent; reward = RLQ.Reward();
39:  newState = RLQ.getState();RLQ.UpdateQ();
40:  count++;
41: end while
42: return pBest and etBest;
End
where: etBest: best objective function value; pBest: best individual; len(P): population size; Fitness: contains the objective function values of all individuals in the population.

5. Performance Analysis

The performance of the proposed BDERL algorithm is rigorously evaluated on both the iMOPSE benchmark dataset and the real-world manufacturing TNG dataset. This section first describes the experimental setup, followed by a comprehensive analysis of the results, including a comparative evaluation against state-of-the-art metaheuristics such as GA, DE, and PSO, for total earliness–tardiness minimization in production scheduling environments.

5.1. Experimental Settings

The proposed algorithm was implemented and executed in the Visual Studio 2022 environment using C#. Experiments were conducted on a Windows 10 system with an Intel Core i5 2.4 GHz processor and 8 GB RAM. The evolutionary process was evaluated across four generations: 1000, 3000, 5000, and 10,000 iterations. The population size is adjustable, and a value of 50 was used in the experiments. To ensure statistical reliability, each algorithm was independently executed 30 times per instance and generation configuration. All mean objective values and statistical metrics in Section 5.2.3 (Wilcoxon signed-rank test, Cohen’s d, and CLES) were computed over these 30 independent runs. To validate the effectiveness of the proposed algorithms, experiments were conducted on the iMOPSE dataset [36], a widely recognized benchmark for the MS-RCPSP and adopted by several prior studies [2,28]. In the iMOPSE dataset, a total of 30 benchmark instances were selected and categorized into two production problem sizes: 15 instances with 100 production tasks and 5, 10, or 20 workforce resources; and 15 instances with 200 production tasks and 10, 20, or 40 workforce resources. These instances were designed with diverse levels of precedence constraints and skill requirements, thereby capturing varying degrees of complexity inherent in multi-skilled production scheduling problems with workforce constraints. The iMOPSE dataset is frequently used as a standard benchmark for evaluating algorithmic performance in recent MS-RCPSP research. In addition to the iMOPSE benchmark dataset, this study also uses the TNG dataset [37], collected directly from the production lines of the TNG garment factory in Thai Nguyen, Vietnam. The TNG dataset is digitized from real-world industrial production data in the textile and garment manufacturing sector. It consists of eight subsets, grouped into two product categories: 71 tasks (T1 to T4) and 137 production tasks (T5 to T8). The number of precedence constraints between tasks is 1026 for the first group and 1894 for the second. The dataset also includes six levels of worker skills, with each worker (i.e., workforce resource) potentially possessing multiple skills.

5.2. Results and Analysis

5.2.1. Experimental Results of the BDERL Algorithm

The BDERL algorithm was tested on the iMOPSE dataset with reinforcement learning parameters set as follows: exploration rate (ϵ) = 0.2, learning rate (α) = 0.5, and discount factor (γ) = 0.9.
To justify this configuration, a one-factor-at-a-time sensitivity analysis was conducted by independently varying each parameter while holding the remaining two at their default values. Each configuration was evaluated on five representative iMOPSE instances (iM1–iM5), and results are summarized in Table 8.
Table 8. Sensitivity analysis of Q-learning hyperparameters on iMOPSE instances.
As shown in Table 8, the exploration rate ε exhibits the strongest asymmetric sensitivity: ε = 0.1 degrades average performance by 26.2%, indicating insufficient exploration leads to premature convergence, while ε = 0.3 causes a milder 8.4% degradation due to excessive random action selection. For the learning rate α, the value 0.3 causes a 42.7% degradation, confirming that slow Q-value updates prevent the agent from adapting to the evolving reward signal; α = 0.7 produces only 5.8% degradation, indicating moderate robustness to higher values. For the discount factor γ, the value 0.99 degrades performance by 16.8% by over-weighting distant future rewards that are less informative within the per-generation feedback structure of BDERL. Based on these results, the configuration (ε = 0.2, α = 0.5, γ = 0.9) was adopted as the final setting.
The configuration with 10,000 generations continued to yield optimal results, with objective function values approaching the ideal range and exhibiting low variance. This indicates strong convergence stability and high-quality solutions. In contrast, the 1000-generation configuration demonstrated a significant performance decline, characterized by a greater number of outliers and a wider distribution of values—an indication of premature convergence. With the BDERL algorithm, an enhanced version that integrates reinforcement learning for adaptive control of evolutionary parameters, the results revealed higher stability in low-generation configurations, particularly on small-scale problem instances. Figure 7 illustrates the experimental results of BDERL on the iMOPSE dataset under varying numbers of generations. In the 1000-generation configuration, BDERL recorded a few poor solutions (e.g., objective values near 25,000); however, these were isolated and did not form clusters.
Figure 7. Box plot of BDERL objective function values on the iMOPSE dataset for four generation settings (Gen1000, Gen3000, Gen5000, Gen10,000). Y-axis shows earliness/tardiness time. Box elements display median, quartiles, and outliers.
Overall, the algorithm achieved its best performance when a sufficient number of generations was allowed. However, BDERL demonstrated superior robustness, especially under constraints related to evolutionary time or problem size. These findings underscore the importance of reinforcement learning–based dynamic parameter adaptation, which enhances responsiveness to search-space fluctuations, mitigates premature convergence, and reduces the occurrence of poor-quality solutions during the early stages of optimization.

5.2.2. Performance Evaluation of the Proposed Method

The experiments were conducted across four generations (1000, 3000, 5000, and 10,000) to evaluate the performance of four algorithms: BDERL, DE, GA, and PSO. Figure 8 shows comparative results of the algorithms on iMOPSE at 1000 and 10,000 generations. The algorithms were compared based on average objective function values, the presence of outliers, and stability, as visualized by the length of the error bars.
Figure 8. Box plot comparison of four algorithms (BDERL, DE, GA, PSO) on the iMOPSE benchmark dataset at 1000 generations (left) and 10,000 generations (right).
The BDERL algorithm consistently demonstrated superior performance, with the lowest average runtime and a tight distribution of data, reflecting its robustness and scalability as the number of generations increased. These findings suggest that both variants are well-suited for problems that demand real-time or near-real-time optimization. In contrast, the standard DE algorithm, while associated with higher average runtimes, maintained relatively stable performance distributions compared to the remaining methods. On the other hand, GA and PSO showed poor performance, characterized by longer execution times, numerous outliers, and high variance, especially under the 10,000-generation configuration. This indicates that GA and PSO are not only slower but also less stable in large-scale execution environments. Increasing the number of generations improved average performance across all methods. However, BDERL consistently emerged as the most effective algorithm across both runtime efficiency and solution stability.
In contrast, GA and PSO are not recommended for scenarios requiring high computational efficiency. These results validate the effectiveness of combining differential evolution with reinforcement learning to enhance both solution quality and algorithmic robustness. Table 9 presents the average performance results of the algorithms over 10,000 generations.
Table 9. Average objective function values for four algorithms on iMOPSE instances at 10,000 generations. Bold values indicate best performance per instance.
The results across datasets iM1 to iM30 show that the proposed BDERL algorithm consistently achieves the best or near-best objective values, demonstrating strong robustness and high solution quality. BDERL also performs competitively, frequently outperforming the algorithms DE, GA, and PSO. Notably, DE, GA, and PSO exhibit higher average objective values and significantly worse worst-case results in multiple instances, indicating instability and inconsistent convergence. Specifically, DE, GA, and PSO recorded the worst performance in the iM12, iM10, and iM8 datasets, respectively, whereas BDERL showed far fewer poor outcomes. These findings emphasize the superior effectiveness and reliability of the proposed algorithms, particularly in solving complex ETMS-RCPSPs. In addition to their superior execution speed, BDERL also demonstrated high runtime consistency across all datasets. The variation in runtime across instances was minimal, with no abnormal spikes observed. Conversely, DE, GA, and PSO exhibited frequent runtime anomalies, particularly in datasets such as iM16, iM24, and iM27, suggesting lower stability and greater sensitivity to input characteristics. Figure 9 shows the standard deviation in the algorithms’ performance across generations on the iMOPSE dataset.
Figure 9. Trend of average standard deviation across generations for four algorithms on the iMOPSE dataset. Lower standard deviation indicates more stable convergence behavior.
The trend of the average standard deviation over generations highlights a clear difference between the algorithms. GA, DE, and PSO exhibit relatively high variability, with PSO showing the highest overall standard deviation and the most pronounced variability. GA and DE also exhibit an irregular trend, either increasing or unstable, indicating less reliable convergence behavior in production scheduling optimization. In contrast, the proposed algorithms, BDERL, consistently exhibit significantly lower standard deviations, indicating greater solution stability across diverse production instances. Although BDERL shows a slight upward trend, its variability remains significantly lower than that observed with traditional algorithms.
Table 10 presents the average performance of the algorithms on the TNG production dataset after 10,000 generations. The results demonstrate that the BDERL algorithm consistently achieves relatively low and stable objective values across most datasets, including both small instances (TN1–TN4) and larger ones (TN5–TN8), indicating good convergence behavior and optimization efficiency across varying production problem scales. The DE, GA, and PSO algorithms generally yield inferior results with greater variability compared to BDERL, particularly on larger production datasets, further highlighting BDERL’s superior stability and adaptability in real-world manufacturing scheduling scenarios. Overall, BDERL outperforms traditional algorithms in terms of solution quality and convergence, particularly in complex production scenarios, demonstrating the effectiveness of the proposed approaches in multi-skill production scheduling. Among them, BDERL stands out as the most effective method, offering robust stability and fast execution. In contrast, although DE, GA, and PSO are well-established and widely used metaheuristics, their performance on the TNG production datasets was less consistent. Specifically, in the ETMS-RCPSP, these algorithms demonstrated noticeably inferior results compared to the proposed methods, highlighting their limitations in handling complex scheduling production scenarios.
Table 10. Average objective function values for four algorithms on TNG dataset instances at 10,000 generations.

5.2.3. Statistical Validation of the Experimental Results

To further evaluate the performance of the proposed algorithms, statistical effect size measures were employed. Specifically, to assess whether the observed differences between the proposed algorithm (BDERL) and the baseline methods (DE, GA, and PSO) are statistically significant, we conducted the Wilcoxon signed-rank test on the iMOPSE dataset under the 10,000-generation configuration. To quantify practical significance beyond statistical significance, we calculated effect sizes using Cohen’s d and Common Language Effect Size (CLES). The comprehensive statistical analysis results are summarized in Table 11.
Table 11. Pairwise statistical comparison of algorithms on the iMOPSE dataset (Wilcoxon test, Cohen’s d, CLES, win rate).
-
Cohen’s d: Most comparisons yield d > 1.0, indicating a “large” effect size according to Cohen’s criterion. For instance, BDERL compared with DE achieves d = 1.195, and compared with GA achieves d = 1.325. These results demonstrate not only statistical significance but also substantial practical impact.
-
CLES: This measure represents the probability that a random outcome from BDERL outperforms the baseline algorithm. For example, CLES = 0.927 against GA indicates a 100% chance that BDERL achieves superior results.
-
Win Rate: This provides additional insight into the frequency of head-to-head wins, with BDERL achieving win rates of 97–100% against most baseline algorithms.
The results demonstrate that the proposed algorithm achieved large effect sizes (Cohen’s d > 1.1) compared to all baseline methods, indicating substantial practical significance. BDERL performed slightly better, with median improvements ranging from 76.7–85.8% and effect sizes between 1.195 and 1.346. CLES values further indicate that both proposed algorithms outperformed baselines in 82–93% of pairwise comparisons, demonstrating consistent superiority across diverse problem characteristics.

6. Conclusions

This study introduces the ETMS-RCPSP, a tool designed for practical application in production planning and enterprise manufacturing scheduling to ensure on-time order completion and enhance operational efficiency. We propose a novel multi-skill production scheduling model that minimizes the total earliness and tardiness of orders, providing a more accurate reflection of actual time-based costs than the traditional makespan objective. To address this NP-hard problem, we develop the BDERL algorithm, which integrates a balanced non-predecessor-constrained task selection strategy with Q-learning-based adaptive parameter control. This design enables a dynamic balance between exploration and exploitation while ensuring computational tractability.
Experimental results on both the benchmark iMOPSE dataset and the industrial TNG dataset from Vietnam’s garment manufacturing industry demonstrate that BDERL significantly outperforms traditional metaheuristics such as DE, GA, and PSO in terms of solution quality, convergence speed, and stability. These improvements are particularly pronounced in large-scale production instances with tight resource and skill constraints. This research not only advances theory but also provides practical tools for production planning in manufacturing enterprises, where strict deadline compliance is critical to operational efficiency and competitive advantage.
Several limitations of BDERL should be noted. The Q-learning state space is defined based on inter-generation improvement levels, which may not fully capture complex search landscape dynamics in very large instances. The FTB technique assigns resources to free tasks subject to skill compatibility constraints, so its workload-balancing effect may be reduced in highly specialized environments with few eligible resources. Additionally, the Q-learning hyperparameters (ε, α, γ) were tuned on the iMOPSE dataset and may require re-tuning when applied to other problem domains.
Future research directions include: (i) extension to dynamic production environments with time-varying orders, resources, and deadlines; (ii) integration of advanced techniques such as deep reinforcement learning, hyper-heuristics, and adaptive hybrid methods; and (iii) exploration of non-linear penalty functions to more accurately model heterogeneous manufacturing cost structures; (iv) systematic comparison with recent high-performing MS-RCPSP algorithms—which currently target makespan minimization—by adapting their fitness functions to the earliness–tardiness objective; and (v) rigorous benchmarking against self-adaptive and improved variants of evolutionary algorithms—such as jDE, SaDE, and adaptive GA—adapted to the E/T objective, which would provide a stronger evaluation of BDERL’s contribution beyond classical baselines. These directions promise to expand the applicability of the ETMS-RCPSP to broader industrial and production domains and diverse shop-floor requirements.

Author Contributions

The study was conceptualized by H.N.T., L.N.T. and H.D.Q. L.N.T. and H.N.T. designed the methodology and performed the formal analysis. H.N.T. and H.D.Q. were responsible for software development, investigation, and data curation. The manuscript was initially drafted by H.N.T. and L.N.T., and subsequently revised and edited by them. Supervision was provided by L.N.T., and project administration was handled by H.N.T. All authors have read and agreed to the published version of the manuscript.

Funding

This study was supported and funded by the science and technology project no. HV13-2025. The authors gratefully acknowledge the Hung Vuong University (HVU), Phu Tho Province, Vietnam.

Institutional Review Board Statement

Not applicable.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors confirm that there are no conflicts of interest. The funding sources did not influence the study design, data collection, analysis or interpretation, manuscript preparation, or the decision to submit the work for publication.

References

  1. Afshar-Nadjafi, B. Multi-skilling in scheduling problems: A review on models, methods and applications. Comput. Ind. Eng. 2021, 151, 107004. [Google Scholar] [CrossRef] [Scilit]
  2. Myszkowski, P.B.; Laszczyk, M. Investigation of benchmark dataset for many-objective multi-skill resource constrained project scheduling problem. Appl. Soft Comput. 2022, 127, 109253. [Google Scholar] [CrossRef] [Scilit]
  3. Snauwaert, J.; Vanhoucke, M. A solution framework for multi-skilled project scheduling problems with hierarchical skills. J. Sched. 2025, 28, 289–310. [Google Scholar] [CrossRef] [Scilit]
  4. Sallam, K.M.; Chakrabortty, R.K.; Ryan, M.J. A reinforcement learning based multi-method approach for stochastic resource constrained project scheduling problems. Expert Syst. Appl. 2021, 169, 114479. [Google Scholar] [CrossRef] [Scilit]
  5. Sandle, P. London’s $24 Billion Crossrail Finally Opens. Reuters, 23 May 2022. Available online: https://www.reuters.com/world/uk/londons-24-billion-crossrail-finally-opens-2022-05-23 (accessed on 6 June 2025).
  6. Pretel, E.; Moreno, E. Panama Opens Canal Extension Amid Growth Risks, Cost Battle. Reuters, 26 June 2016. Available online: https://www.reuters.com/article/business/panama-opens-canal-extension-amid-growth-risks-cost-battle-idUSKCN0ZC0Q8/ (accessed on 6 June 2025).
  7. Bowlby, C. Berlin Brandenburg: The Airport with Half a Million Faults. BBC News, 29 June 2019. Available online: https://www.bbc.com/news/world-48527308 (accessed on 6 June 2025).
  8. Kim, J.G.; Jun, H.B.; Bang, J.Y.; Shin, J.H.; Choi, S.H. Minimizing Tardiness Penalty Costs in Job Shop Scheduling under Maximum Allowable Tardiness. Processes 2020, 8, 1398. [Google Scholar] [CrossRef] [Scilit]
  9. Alrasheed, K.A.; Soliman, E.M.; Al-Bader, H.B. Delay dispute cases: Comparative analysis and claimed value prediction model. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2024, 16, 04523048. [Google Scholar] [CrossRef] [Scilit]
  10. Bellenguez-Morineau, O.; Néron, E. A branch-and-bound method for solving multi-skill project scheduling problem. RAIRO Oper. Res. 2007, 41, 155–170. [Google Scholar] [CrossRef] [Scilit]
  11. Myszkowski, P.B.; Skowroński, M.E.; Olech, Ł.P.; Oślizło, K. Hybrid ant colony optimization in solving multi-skill resource-constrained project scheduling problem. Soft Comput. 2015, 19, 3599–3619. [Google Scholar] [CrossRef] [Scilit]
  12. Javanmard, S.; Afshar-Nadjafi, B.; Niaki, S.T.A. Preemptive multi-skilled resource investment project scheduling problem: Mathematical modeling and solution approaches. Comput. Chem. Eng. 2017, 96, 55–68. [Google Scholar] [CrossRef] [Scilit]
  13. Maghsoudlou, H.; Afshar-Nadjafi, B.; Niaki, S.T.A. Multi-skilled project scheduling with level-dependent rework risk: Three multi-objective mechanisms based on Cuckoo Search. Appl. Soft Comput. 2017, 54, 46–61. [Google Scholar] [CrossRef] [Scilit]
  14. Li, Y.-Y.; Lin, J.; Wang, Z.-J. Multi-skill resource constrained project scheduling using a multi-objective discrete Jaya algorithm. Appl. Intell. 2022, 52, 5718–5738. [Google Scholar] [CrossRef] [Scilit]
  15. Cai, J.; Peng, Z.; Ding, S.; Sun, J. Problem-specific multi-objective invasive weed optimization algorithm for reconnaissance mission scheduling problem. Comput. Ind. Eng. 2021, 157, 107345. [Google Scholar] [CrossRef] [Scilit]
  16. Bahroun, Z.; As’ad, R.; Tanash, M.; Athamneh, R. The multi-skilled resource-constrained project scheduling problem: A systematic review and an exploration of future landscapes. Manag. Prod. Eng. 2024, 32, 108–132. [Google Scholar] [CrossRef] [Scilit]
  17. Torba, R.; Dauzère-Pérès, S.; Yugma, C.; Gallais, C.; Pouzet, J. Solving a real-life multi-skill resource-constrained multi-project scheduling problem. Ann. Oper. Res. 2024, 338, 69–114. [Google Scholar] [CrossRef] [Scilit]
  18. Khoshjahan, Y.; Najafi, A.A.; Afshar-Nadjafi, B. Resource constrained project scheduling problem with discounted earliness–tardiness penalties: Mathematical modeling and solving procedure. Comput. Ind. Eng. 2013, 66, 293–300. [Google Scholar] [CrossRef] [Scilit]
  19. Otten, M.; Braaksma, A.; Boucherie, R.J. Minimizing earliness/tardiness costs on multiple machines with an application to surgery scheduling. Oper. Res. Health Care 2019, 22, 100194. [Google Scholar] [CrossRef] [Scilit]
  20. Akande, S.; Ajisegiri, G. Three classes of earliness-tardiness (E/T) scheduling problems. Fuel Commun. 2022, 10, 100047. [Google Scholar] [CrossRef] [Scilit]
  21. Li, X.; Ventura, J.A.; Bunn, K.A. A joint order acceptance and scheduling problem with earliness and tardiness penalties considering overtime. J. Sched. 2021, 24, 49–68. [Google Scholar] [CrossRef] [Scilit]
  22. Sung, I.; Choi, B.; Nielsen, P. Reinforcement learning for resource constrained project scheduling problem with activity iterations and crashing. IFAC-PapersOnLine 2020, 53, 10493–10497. [Google Scholar] [CrossRef] [Scilit]
  23. Cai, H.; Bian, Y.; Liu, L. Deep reinforcement learning for solving resource constrained project scheduling problems with resource disruptions. Rob. Comput. Integr. Manuf. 2024, 85, 102628. [Google Scholar] [CrossRef] [Scilit]
  24. Zhao, X.; Song, W.; Li, Q.; Shi, H.; Kang, Z.; Zhang, C. A deep reinforcement learning approach for resource-constrained project scheduling. In Proceedings of the 2022 IEEE Symposium Series on Computational Intelligence (SSCI), Singapore, 4–7 December 2022; IEEE: Piscataway, NJ, USA, 2022; pp. 1226–1234. [Google Scholar] [CrossRef] [Scilit]
  25. Chang, J.; Yu, D.; Hu, Y.; He, W.; Yu, H. Deep reinforcement learning for dynamic flexible job shop scheduling with random job arrival. Processes 2022, 10, 760. [Google Scholar] [CrossRef] [Scilit]
  26. Myszkowski, P.B.; Olech, Ł.P.; Laszczyk, M.; Skowroński, M.E. Hybrid Differential Evolution and Greedy Algorithm (DEGR) for solving Multi-Skill Resource-Constrained Project Scheduling Problem. Appl. Soft Comput. 2018, 62, 1–14. [Google Scholar] [CrossRef] [Scilit]
  27. Maghsoudlou, H.; Afshar-Nadjafi, B.; Niaki, S.T.A. A framework for preemptive multi-skilled project scheduling problem with time-of-use energy tariffs. Energy Syst. 2021, 12, 431–458. [Google Scholar] [CrossRef] [Scilit]
  28. Nguyen, T.L.; Dang, Q.H.; Nguyen, T.H. GIRCS: An effective evolutionary scheme to solve SBM-RCPSP scheduling problems for industrial production planning. Intell. Syst. Appl. 2025, 200522. [Google Scholar] [CrossRef] [Scilit]
  29. Perron, L.; Didier, F.; Gay, S. The CP-SAT-LP Solver. In Proceedings of the 29th International Conference on Principles and Practice of Constraint Programming (CP 2023); Schloss Dagstuhl: Dagstuhl, Germany, 2023; Volume 280, pp. 3:1–3:2. [Google Scholar] [CrossRef]
  30. Nickel, S.; Steinhardt, C.; Schlenker, H.; Burkart, W. Decision Optimization with IBM ILOG CPLEX Optimization Studio; Springer: Berlin/Heidelberg, Germany, 2022. [Google Scholar] [CrossRef] [Scilit]
  31. Xin, L.; Song, W.; Cao, Z.; Zhang, J. NeuroLKH: Combining deep learning model with Lin-Kernighan-Helsgaun heuristic for solving the traveling salesman problem. In Advances in Neural Information Processing Systems 34 (NeurIPS 2021); Curran Associates: Red Hook, NY, USA, 2021; pp. 7440–7452. [Google Scholar]
  32. Chaouch, R.; Ghorbel, H.; Khalfallah, S. Model for the classification of scheduling problems based on ontology. Procedia Comput. Sci. 2021, 181, 890–896. [Google Scholar] [CrossRef] [Scilit]
  33. Ding, H.; Zhuang, C.; Liu, J. Extensions of the resource-constrained project scheduling problem. Autom. Constr. 2023, 153, 104958. [Google Scholar] [CrossRef] [Scilit]
  34. Sutton, R.S.; Barto, A.G. Reinforcement Learning: An Introduction, 2nd ed.; MIT Press: Cambridge, MA, USA, 2018. [Google Scholar]
  35. Binh, H.T.T.; Thanh, P.D. Evolutionary Computation; Bach Khoa Publishing House: Hanoi, Vietnam, 2024. [Google Scholar]
  36. Myszkowski, P.B.; Laszczyk, M.; Nikulin, I.; Skowroński, M. iMOPSE: A library for bicriteria optimization in multi-skill resource-constrained project scheduling problem. Soft Comput. 2019, 23, 3397–3410. [Google Scholar] [CrossRef] [Scilit]
  37. HuuDQ. TNG Dataset. Available online: https://github.com/huudqtmu/dataset/blob/main/TNGDEF.zip (accessed on 6 June 2025).
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.