Time-Based Reconstruction, Uncertainty Assessment, and Prediction of Concurrent Water Supply Interruptions and Repair Work for Maintenance Engineering

,
and
1
Faculty of Civil and Environmental Engineering and Architecture, Rzeszow University of Technology, Al. Powstańców Warszawy 6, 35-029 Rzeszów, Poland
2
Consultant, 91400 Orsay, France
*
Author to whom correspondence should be addressed.

Abstract

Weekly counts and total durations can conceal overlapping water supply interruptions and repair work. Using 4885 entries from a municipal utility database in southeastern Poland (2004–2025), we assess aggregation loss (RQ1), sensitivity of reconstructed overlap (RQ2) and predictive reliability for maintenance planning (RQ3). Among 56 groups of weeks with identical counts and accumulated interruption and repair-work durations, 40 contain weeks differing in peak concurrency or threshold exposure. Associated repair work remains active at restoration in 96.86% of interruption episodes. The repair-work maximum of nine is reproduced by every fixed-count reference path. In separate sensitivity analyses, the maximum falls to seven after hypothetical grouping and to four after excluding 2007. The full-database maximum remains nine under endpoint changes of up to 30 min within recorded dates. OR (1,2) exposure spans 683.92–1572.25 h around 1061.42 h nominally. Five simulators show uneven calibration across January, April, July and October origins. For nominal 90% prediction intervals, the five-year-donor NB2 model covers 62.5% of monthly counts in the frozen assessment and 28.6% of annual counts across 14 January origins. Chronology supports audits of concentrated work and restoration timing; staffing decisions require verified job identifiers and resource data.

1. Introduction

Weeks with identical event counts and total interruption and repair-work durations can differ in overlap. Occupancy models describe active entries from interval boundaries [1,2,3], while performability and resilience approaches assess whether counts remain within limits over a finite period [4,5,6].
Water distribution studies address maintenance-related unmet demand [7], vulnerability [8], reliability [9], flood impacts [10] and supply safety [11].
Network reliability and resilience [12,13], multimodal recovery under recurrent hazards [14], pipe condition and maintenance costs [15,16,17], and failure prediction [18,19] address complementary targets that cannot be inferred from temporal overlap alone.
For this utility, earlier work examined pipe-group burdens [20] and monthly seasonality [21]. Event-log research distinguishes possible timestamps from probabilities [22]; our database audit checks timing and completeness [23].
Maintenance optimisation under dependent recurrent hazards links intervention timing to availability, resilience and risk preferences [24]. Applying these approaches requires reliable links between database entries and operational performance.
A remaining gap is the joint assessment of aggregation loss, entry definitions, timestamp uncertainty and predictive calibration in water supply maintenance databases. Reconstructed overlap must be evaluated against these observation and modelling choices.
We reconstruct linked interruption and repair-work timelines from one municipal database and compare weekly aggregation, calendar references, endpoint scenarios and retrospective forecasts. This empirical application of established methods addresses three questions.
RQ1. What overlap and restoration-to-repair timing information is lost in aggregate counts and durations?
RQ2. How do reconstructed findings change with calendar references, entry definitions, exclusion of the peak year and endpoint uncertainty?
RQ3. How reliably do the simulators predict overlap across horizons and calendar origins, and what maintenance decisions can the results support?

2. Materials and Methods

2.1. Database and Unit of Analysis

Figure 1 links database preparation and interval reconstruction to overlap and uncertainty analysis, predictive validation and maintenance interpretation in three stages and nine steps.
Figure 1. Three stages and nine steps linking the database audit and interval reconstruction, concurrency and uncertainty assessment, and predictive comparison with maintenance interpretation.
The database comprises the utility’s compiled workbook for 2004–2025. Each administrative item is an entry and may contain several dated intervals. Of 4885 entries, 4860 have known repair-work durations and 4839 have a known interruption duration or explicit confirmation of supply continuity.
The repair-work fields in the source database describe actual work; timestamp accuracy, entry identity and crew attendance were not independently verified. Interruption duration runs from recorded supply loss to restoration, including waiting, repair, testing and reconnection. Where timestamps permit, we also measure the intervals from shutoff to repair start and from restoration to repair end.
A dated repair interval contributes to the repair timeline even when interruption status is unknown. A known duration with uncertain dates contributes to duration summaries and, when alternative dates can be assigned, to timing sensitivity scenarios. Missing durations remain missing. Only explicit confirmation that supply remained on is coded as zero interruption duration. Joint simulations of both timelines use entries with dated repair work and either dated interruption intervals or confirmed uninterrupted supply, so the relative timing is observed.

2.2. Timestamp Reconstruction and Observation Audit

Intervals were reconstructed in integer minutes of the recorded civil calendar. Explicit dates take precedence over clock-time rules. A documented end earlier than a start is treated as an overnight interval only where the source permits that interpretation. When start and end clock times are identical and the day is undocumented, the duration is treated as ambiguous. Multiple ranges are retained when their dates are identifiable; ambiguous second ranges are excluded from the main reconstruction. We merge overlapping or touching intervals within the same entry and process. Each entry counts once at a given time. Distinct entries that overlap remain separate in the concurrency measure. These counts describe timing. Estimating costs or staffing would require crew or resource data.
The observation unit is an administrative database entry. One intervention may generate several entries, and one entry may involve multiple people or tasks. Without linked dispatch logs, stable incident identifiers, crew assignments or customer interruption data, active-entry counts and entry-hours cannot be converted into crew demand, labour hours or distinct pipe failures.
We reconstruct repair-work and interruption intervals independently. In 209 entries, some interruption time falls outside the recorded repair-work intervals. We examine clock-time concentration and test sensitivity to whole-entry shifts and endpoint uncertainty.

2.3. Parallel Start and End Processes

Let I ir denote the union of reliably dated intervals for entry i and process r, where r ∈ {D,W} represents interruption and recorded repair work. Its disjoint components are the half-open intervals [sijr,eijr). A half-open interval includes its start and excludes its end. The cumulative counting-process approach follows Carrington et al. [25]. The cumulative start and end counts are given by Equation (1), where a is the start time of the observation window:
O r a t = i , j :   a ≤ s ijr ≤ t , E r a t = i , j :   a ≤ e ijr ≤ t .
In Equation (1), i indexes entries and j indexes their disjoint intervals. The symbol # denotes the number of elements in a set. Starts and ends at the observation origin are included in the boundary update. In Equation (2), qr(a−) counts entries active immediately before the origin.
Q r t = q r a − + O r a t − E r a t = # i :   t ∈ I ir ,   t ≥ a .
For interruptions and repairs, we update all starts and ends at the same timestamp together. The initial count is zero for the full observation period and the 2024–2025 test period.

2.4. Burden, Episodes and Continuation After Restoration

For a window [a,b), Equation (3) gives accumulated burden and the total time with at least one active entry.
A r a , b = ∫ a b Q r t   d t = ∑ i I ir ∩ | a , b | , B r a , b = | t ∈ a , b :   Q r t > 0 | .
The measure |⋅| denotes the total length of a set of times in hours. Equation (3) clips each interval to the observation window. Two entries lasting two hours each with one hour of overlap contribute four entry-hours and three calendar hours. Ar is measured in entry-hours and Br in calendar hours with at least one active entry. Their difference quantifies accumulated overlap above one active entry.
An episode is a maximal connected component of the set where Qr(t) > 0. Touching intervals produce a continuous episode under the simultaneous-update convention. Equation (4) defines three measures for each episode.
L rl = b l − a l ,   M rl = sup a l ≤ t < b l Q r t , F rl = min i , j ∈ J rl e ijr − a l .
Here, al and bl bound the episode, and J rl contains the participating interval indices. The three quantities are episode duration, peak occupancy and time to the first participating interval end. Windows that truncate an episode retain its censoring status.
For an interruption episode ending at b l , let S l be its associated source-entry identifiers.
C l = # i ∈ S l :   b l ∈ I iW .
Here, C l counts linked entries whose repair work is active at restoration. Repair work starting at restoration also counts as active. Continuing repair-work entry-hours integrate those active intervals after b l ; later-starting repair-work intervals are tabulated separately. The elapsed span includes gaps between intervals, whereas active duration excludes them. Episode-linked totals can include the same entry more than once.
Entry-level duration distributions pool the whole network without stratification by pipe diameter. Each duration is the total length of the within-entry interval union for the relevant process. Histograms use one-hour bins. Empirical distribution functions give the observed fraction at or below each duration, and reported percentiles use linear interpolation of ordered observations. Comparisons between entries and connected episodes use process-specific chronology-eligible entries.

2.5. Joint Thresholds and the Information Lost by Aggregation

Illustrative thresholds kD and kW are the limits for simultaneous interruption and repair-work entries. Equation (6) defines the indicator and the time spent above either limit.
Z k t = 1 , if   Q D t > k D   ∨   Q W t > k W 0 , otherwise , V k a , H = ∫ a a + H Z k t   d t .
The vector k = (kD,kW) gives the largest counts allowed under each scenario. OR exposure includes every instant when either limit is exceeded, including instants when both are exceeded. AND exposure includes only instants when both limits are exceeded. We evaluated four illustrative pairs, (1,2), (2,3), (3,4) and (4,6). The utility’s capacity and contractual service limits were unavailable.
The four pairs form a nested sensitivity grid from low-count overlap to rarer high-count conditions. Separate repair-work limits allow examination of work continuing after restoration. We report active-entry maxima, hours above either or both limits, horizon-wide no-crossing probabilities, and first-crossing and return times. Operational triggers require independently specified service criteria or verified job-to-resource mappings; the illustrative pairs provide no capacity guarantee or optimal operating standard.
For the simulated paths, Equation (7) gives the probability that both counts stay within their limits throughout the specified horizon.
P k a , H = Pr Q D t ≤ k D ,   Q W t ≤ k W   for   every   t ∈ a , a + H | C .
The conditioning set C contains the calendar, fitted specification, donor construction and initial state. The calendar origin a is explicit because the process is nonstationary. The historical clock-time fraction instead measures the share of observed time within both limits. Equation (8) defines the first violation and subsequent return.
τ k = inf u ≥ 0 :   Z k a + u = 1 , R k = inf v > 0 :   Z k a + τ k + v = 0 .
Here, τ is the time from the horizon origin to the first violation, and R is its duration until both occupancies return within limits. A path without a violation is right-censored at the horizon. Return duration is evaluated after a violation.
Aggregate summaries cannot identify concurrency. Two entries with the same positive durations of repair work and interruption can be placed sequentially or simultaneously inside a sufficiently long window. Both arrangements preserve entry count and accumulated durations but can produce different maxima and threshold exposure. Thus, (n,AD,AW) does not uniquely determine (MD,MW,Vk). The extent of this information loss was assessed by enumerating exact matches among complete, closed Monday-to-Sunday weeks containing at least three entries. Closed weeks have neither outgoing nor incoming intervals across their boundaries. Aggregate equality is checked in integer minutes. The comparison is descriptive. Pairs sharing a week are statistically dependent.

2.6. Calendar-Conditioned References and the Observation Unit

Two references retain the full timing pattern of each entry’s repair-work and interruption intervals, including clock times, interval lengths, relative offsets, multiplicity and documented uninterrupted supply. In the first, an entry is relocated independently to a uniformly chosen anchor day with the same year, month and weekday. This preserves calendar-stratum totals but randomises daily counts. In the second, existing anchor days are permuted among entries within the same year, month, weekday and dated-process eligibility class. This preserves the number of anchored entries on every day, separately for entries with dated repair work and dated positive interruptions. It changes the allocation of geometries to those days. Neither reference represents a causal scheduling intervention or an observed physical failure mechanism.
Independent relocation tests how daily accumulation and interval allocation jointly affect overlap within each calendar stratum. Fixed daily counts isolate interval allocation by holding accumulation constant. Their comparison distinguishes high entry counts from unusually overlapping timing patterns. Both are descriptive benchmarks: exchangeability and a physical hazard mechanism remain unverified.
Placements must retain all available intervals inside the full observation window. No entry in this database requires restricting the eligible calendar days for that boundary condition. All simulated paths preserve accumulated interruption and repair-work entry-hours exactly. Each reference uses 1000 paths. We also evaluate the paths after excluding 2007 entries because both observed maxima occur that year.
The upper-tail calculation in Equation (9) uses the finite-simulation correction discussed by Phipson and Smyth ([26], Section 6.2). Let Tobs be the observed statistic and Tb the statistic for simulated path b, with B paths in total. The indicator equals one when its condition holds and zero otherwise.
p + = 1 + ∑ b = 1 B 1 { T b ≥ T obs } B + 1 ,   p − = 1 + ∑ b = 1 B 1 { T b < T obs } B + 1 , p 2 = min 1 ,   2 min p + , p − .
Ties enter the upper tail only. If every simulated value equals the observation, the strict lower tail is empty and the two-sided score is 2/(B + 1). Small two-sided scores can therefore reflect the tie convention. We compare seven outcomes across the two processes, including both occupancy maxima and both episode counts, the longest interruption episode, OR (1,2) exposure and AND (1,2) exposure. Upper-tail and exploratory two-sided areas are adjusted separately by the Holm procedure [27], within each reference and cohort. Holm adjustment accounts for the seven comparisons under valid individual tests. Because exchangeability of the entries is unverified and some comparisons were chosen retrospectively, we interpret the tail areas and quantiles descriptively against the specified references.

2.7. Candidate Chronological Simulators

Daily counts are anchored at the first recorded repair-work date of jointly complete entries. A Poisson calendar model is an independent reference. For a continuous Poisson arrival process with independent durations, Equation (10) gives the expected occupancy.
m r t = ∫ − ∞ t λ r u   G r t − u   |   u   d u .
Here, λr(u) is arrival intensity and G ¯ r is the duration survival function [1]. The reference simulator implements this idea with discrete daily counts and sampled timing patterns. It represents concurrent entries as an occupancy process with no crew constraint.
The NB2 parameterisation follows Hilbe [28]. Poisson and NB2 candidates are fitted by maximum likelihood. Equation (11) defines the NB2 count model and its calendar predictor.
N d ∼ NB 2 μ d ,   α ,   Var N d   |   x d = μ d + α μ d 2 , log   μ d = β 0 + β s   sin ϕ d + β c   cos ϕ d + ∑ j = 1 6 γ j χ dow d = j + β t ξ d .
In the annual harmonic, md is the calendar month, so ϕd = 2π(md − 0.5)/12 is constant within each month. Monday is the weekday reference. For any condition, χ equals 1 when the condition holds and 0 otherwise. The trend covariate is ξd = [yd + (hd − 1)/365.25 − 2015]/10, where yd is the calendar year and hd the day of year. Level-only candidates omit this term. These effects describe entry frequency without scaling it by network length or asset exposure.
The randomised probability integral transform [29] is defined in Equation (12) using the fitted daily cumulative distribution Fd.
U d = F d N d − 1 + V d F d N d − F d N d − 1 , V d ∼ Uniform 0 , 1 .
Ljung–Box diagnostics at lags 7, 14 and 28 use the Gaussian residuals Φ−1(Ud), where Φ is the standard normal distribution function [30]. The chi-square approximation is used for these diagnostics after parameter fitting and residual randomisation. For serial simulation, transforms from the latest five training years are converted to empirical ranks. Contiguous blocks beginning on the target weekday are sampled and mapped through each target day’s inverse count distribution. This preserves a limited empirical dependence structure without making it a condition for model eligibility.
A mark contains all repair work and interruption intervals of one entry, expressed as offsets from midnight on its first repair-work date. Sampling a mark retains clock times, interval lengths, internal gaps, relative process timing and the documented no-interruption status. Individual marks are sampled with replacement from month–weekday pools with at least 20 entries; fallback pools use month and then the complete allowed donor period. Whole-day marks retain all entries anchored on one donor day and additionally match simulated daily count. Pools require five donor days at the month–weekday or month level before falling back to all days with that count. Counts absent from the donor data use individual marks. Neither construction extrapolates interval durations beyond observed donor support.
All 13 candidate specifications are documented in Table A1, with their count family, trend, count-training period, interval-donor period, residual block length and 2022–2023 validation score. Five were retained for detailed retrospective comparison: the Poisson calendar benchmark, the independent eight-year NB2 validation leader with five-year individual donors, and three eight-year NB2 variants sharing three-year donors. The latter provide controlled comparisons of individual versus whole-day marks and independent versus seven-day count blocks. These five are not simply the five lowest validation scores. The initial model selection was restricted to a serial-block subset motivated by training residual dependence; the expanded comparison includes independent alternatives and does not use that restriction as evidence of superiority. The remaining eight candidates are retained in the model inventory, without claiming a complete later-period assessment for them.

2.8. Predictive Protocols and Uncertainty

Candidate fitting, donor pools and score scales initially use data through 2021. Validation covers 2022–2023, with 500 two-year paths per candidate. The frozen protocol generates 1500 paths for 2024–2025 using the same 2021 fits and pools. It assesses a fixed-origin model across the intervening validation period. Annual refitting uses data through 2023 to assess 2024 and through 2024 to assess 2025, with 1500 paths per annual fit. Candidate settings and the score scales estimated from data through 2021 remain fixed. Intervals carry forward across monthly boundaries within each simulated path. Recorded occupancy is zero at each assessed January origin. Repair-work entries are generated from the origin onward. Their sampled interruption intervals retain their timing relative to the start of repair work, including interruptions that start earlier.
These comparisons are retrospective. Additional specifications, annual refitting and sensitivity analyses were introduced after some 2024–2025 outcomes had been inspected. Model fitting uses only data from before each assessment period.
We score predictive distributions using the continuous ranked probability score (CRPS) [31]. For each forecast target, x1,…,xM are the values obtained from the M equally weighted simulated paths, and y is the corresponding observed value. Equation (13) gives the CRPS.
CRPS = 1 M ∑ b = 1 M x b − y − 1 2 M 2 ∑ b = 1 M ∑ c = 1 M x b − x c .
A lower CRPS indicates a more accurate predictive distribution. Equation (14) averages the weighted CRPS over J evaluation windows, with each outcome v divided by its training scale.
S = 1 J ∑ j = 1 J ∑ v = 1 5 w v CRPS jv s v , w 1 , … , w 5 = 0.25 ,   0.20 ,   0.20 ,   0.20 ,   0.15 .
The five composite outcomes are monthly entry count, maximum interruption occupancy, maximum repair-work occupancy, the 90th percentile of interruption-episode duration and OR (1,2) exposure. The training interquartile ranges (IQRs), floored at one, are 11, 1, 1, 2.4125 and 5.125, respectively. We assess ranking sensitivity with equal weights and with five variants that each omit one outcome. The longest interruption episode is reported separately. Mean absolute error (MAE), empirical coverage of nominal 90% prediction intervals and Brier scores for threshold satisfaction provide additional diagnostics.
Paired circular-block resampling of 24 monthly loss differences uses 10,000 repetitions with one-, three- and six-month blocks. Three-month blocks are used for the main comparison. The same draws assess ranking sensitivity. The descriptive resampling intervals condition on the fitted ensembles and exclude uncertainty from refitting, model selection and finite ensemble size.
The additional annual-origin backtest follows the rolling-origin principle [32] and compares the same five fixed specifications at 1 January of 2012–2025. This gives 14 origins after at least eight complete calendar years of available history. Each fit, residual pool and mark donor period ends in the previous year. The candidate set was assembled retrospectively and held fixed at every origin. The targets summarise each full forecast window of 1, 3 or 12 calendar months from 1 January. Each model–origin fit generates 1000 annual paths; nested horizons use the same paths and retain intervals across monthly boundaries. Joint recorded occupancy is zero at all evaluated origins. This initial backtest assesses January issuance.
For this backtest, each origin and horizon uses scales computed from the IQR of same-horizon January aggregates in 2004 through the previous year, with the original floor of one and weights. Thus, scaling never uses a future assessment year. The original 2024–2025 monthly scores retain their original 2021 scales and are not pooled with the aggregate-horizon scores. Unscaled CRPS, MAE, signed prediction bias, central 90% coverage and interval width are reported by outcome, horizon and the two seven-origin eras 2012–2018 and 2019–2025. Early entries contribute to training and historical targets wherever they satisfy the applicable eligibility criteria.
Paired annual loss contrasts use 10,000 circular-block repetitions with one-, two- and three-origin blocks; two-origin blocks define the main descriptive intervals. The three nested horizons are not treated as independent cases. Conditional Monte Carlo standard errors use five delete-200-path jackknife replicates for each 1000-path ensemble; mean-score errors combine independent ensemble errors in quadrature. They exclude uncertainty from parameter estimation, observation quality and retrospective specification choices. Section 2.10 summarises reproducibility checks. The backtest broadens retrospective evidence without creating an untouched test.
To assess issuance in other seasons, we additionally evaluate 1 April, 1 July and 1 October in 2012–2025: 42 origins at 1- and 3-month horizons, and 39 origins in 2012–2024 at 12 months so every outcome window is complete by December 2025. The same five specifications remain fixed. At each origin, count fitting, the residual pool and fully observed interval donors end on the preceding day; NB2 count fits use eight preceding years and Poisson fits up to 22 years; donor windows retain their stated lengths. Each model–origin fit generates 1000 paths. Joint recorded occupancy is zero at every added origin. Score scales use fully observed historical windows with the same origin month and horizon, available by issuance, with an IQR floor of one. Scores are reported separately by origin month. Overlapping annual forecast windows and nested horizons preclude interpreting these as independent replications (Table A2).
Conditional simulations use the seven-day serial specification fitted through 2025 to illustrate horizon-wide threshold satisfaction, first passage and imposed path transformations. This specification remains fixed for these illustrations and is not selected from the 2024–2025 assessment scores. Equation (15) gives the fraction of the M paths that stay within both limits over the horizon and its Monte Carlo SE.
P ^ k a , H = # b :   sup t Q D b t ≤ k D ,   sup t Q W b t ≤ k W M , SE MC = P ^ 1 − P ^ M .
Wilson intervals [33] quantify conditional Monte Carlo error. Calendar-pair block refits [34] assess additional parameter sensitivity without guaranteed coverage under nonstationarity. First-passage curves account for horizon censoring [35]. Rare-event probabilities under annual refitting remain uncertain. These conditional illustrations use the 2026 calendar.

2.9. Conservative Envelopes for Dated-Endpoint Uncertainty

The endpoint analysis retains each explicitly dated component before within-entry union. For recorded endpoints s,e, let [s−,s+] and [e−,e+] be their integer-minute uncertainty ranges. Each range is the intersection of [t − δ, t + δ] and the set of minutes on that endpoint’s recorded calendar date. Every feasible component retains positive length. Documented no-interruption states, entry identity and chronology eligibility remain fixed; interruption intervals are not forced to lie within repair work. Equation (16) defines a core and an expanded interval for each component.
I − = s + , e − if   s + < e − ∅ otherwise , I + = s − , e + ,   I − ⊆ I θ ⊆ I + .
For every feasible endpoint configuration θ, form entry-level unions I ir − and I ir + before counting entries. Equation (17) follows from interval inclusion.
Q r − t = # i :   t ∈ I ir − ≤ Q r θ t ≤ Q r + t = # i :   t ∈ I ir + .
Integrals, occupancy maxima and increasing threshold predicates preserve this ordering. Equation (18) gives the resulting bounds for peak occupancy and threshold exposure.
sup t Q r − t ≤ M r θ ≤ sup t Q r + t , V k − ≤ V k θ ≤ V k + .
These outer bounds contain all feasible outcomes. The endpoints may be unattainable, and different outcomes may reach their extrema under different timestamp configurations. The longest connected active duration is also monotone under active-set inclusion. Episode counts, mean lengths and length quantiles are not monotone and are not bounded by this calculation. Scenarios use δ = 0, 5, 15, 30 min over the fixed 2004–2025 window, with and without 2007. The ranges are specified for sensitivity analysis without assuming a probability distribution or calibration against utility clocks. Changing endpoints can change burden as well as overlap; nominal source durations remain separate. Existing calendar references retain nominal endpoints, so their tail areas are not propagated through these envelopes.

2.10. Observation Sensitivity and Reproducibility

We assess sensitivity to four choices. We shift all intervals in an entry together by up to 5, 15 or 30 min, consider same-day or next-day placement for excluded ambiguous ranges, draw donors from all available years, and group entries with the same normalised location and identical repair-work intervals. In the grouping scenario, each group counts as one unit. Matching fields alone cannot establish that the original entries are duplicates.
We also apply three hypothetical transformations to the simulated paths. We remove entries independently with probability 0.20, shorten interruption intervals by 25% or shorten continuing repair-work segments by 50%. A combined scenario applies all three. Intervals are rounded to integer minutes and retain a minimum positive length. The comparisons describe changes under these assumptions.
The original analyses retain seeds 20261010–20261013. The seasonal backtest uses seed 20261110 with reproducible origin- and model-specific streams. Consistency checks cover joint-boundary occupancy, within-entry unions, carry-over, entry-hour preservation and endpoint envelopes. These checks verify the interval analysis, without independently validating utility clocks or physical incidents.

3. Results

3.1. Audit and Completeness

The results address three distinct findings: exact weekly aggregation can conceal overlap (RQ1); peak and exposure measures respond differently to reference and observation assumptions (RQ2); and predictive interval calibration remains uneven across forecast protocols (RQ3). Descriptive reconstruction, sensitivity results and predictive evidence are presented separately below.
Of the 4885 database entries, 4860 have known repair-work durations. For water supply interruption, 3788 have known positive durations, 1051 explicitly indicate that supply remained on and 46 have an unknown status. The reconstruction uses 4851 entries with dated repair work and 3779 entries with dated positive interruptions. After merging overlaps within entries, these yield 4856 repair-work intervals and 3780 interruption intervals. The joint simulation uses 4818 entries (98.63% of the database, Table 1).
Table 1. Joint eligibility and reconstructed activity burdens in the audited database.
The share of entries eligible for joint simulation was 84.90% in 2005, the lowest annual share in 2004–2025. It was 100% in each validation and test year from 2022 to 2025. Repair-work chronology covers 90.20% of 2005 entries and 97.72% of 2004 entries. Nine entries with known repair-work duration and nine with known positive interruption duration cannot be placed on the timeline unambiguously. Some entries may appear in both groups. Excluded chronology accounts for 168.50 repair-work entry-hours and 110.00 interruption entry-hours. The known-duration and chronology-eligible means are close for repair work (7.960 versus 7.940 h), but the similar means give no information about when the undated work occurred or why its dates are missing.
Concentration at certain clock times can reflect both work schedules and recording practices. The database cannot separate the effects of scheduling, the mix of incidents and the resolution of timestamps. The patterns motivate calendar-conditioned simulation and donor-era sensitivity.

3.2. Occupancy and Linked Episodes

The interruption process contains 3381 episodes and the repair-work process 3607 episodes. Maximum active-entry counts are six and nine, respectively. Both processes attain their largest recorded concurrency on 29 May 2007. The interruption episode on that date involves nine source entries, lasts 14 h and accumulates 51 interruption entry-hours. The first interruption ends 4.5 h after episode onset. Four associated repair-work entries remain active when all its interruption intervals have ended (Figure 2).
Figure 2. Recorded concurrency of water supply interruptions and repair work on 29 May 2007: (a) active-entry counts and (b) cumulative interval starts and ends.
On the peak day, eight of nine associated repair-work entries start at 07:00. Three share a location and the same 07:00–23:00 repair interval, but have different interruption starts. These patterns may reflect simultaneous interventions, separately documented tasks or common recording times. The database and available external evidence cannot establish the physical cause. Excluding 2007 therefore tests the influence of the peak year; it does not correct a proven error or remove an identified hazard year.
The total interruption burden is 11,637.20 entry-hours, while interruption-active calendar duration is 10,890.12 h. Corresponding repair-work measures are 38,515.58 entry-hours and 33,377.67 h. During periods with at least one active entry, the average simultaneous count was 1.154 for repair work and 1.069 for interruption.
Across all known durations, positive interruptions have mean 3.101 h, median 3.00 h and 90th percentile 5.00 h, whereas recorded repair-work durations have mean 7.960 h, median 8.00 h and 90th percentile 9.50 h (Table 2). Including the 1051 entries with confirmed uninterrupted supply gives a mean interruption duration of 2.428 h and a median of 2.00 h. The 46 unknown interruption states contribute to neither distribution.
Table 2. Entry-level, episode and restoration-linked duration statistics for the whole network in 2004–2025.
For chronology-eligible entries, the repair-work-duration mean is 7.940 h and its 90th percentile is 9.00 h; the corresponding episode measures are 9.254 and 16.00 h. Positive interruption entries have mean 3.079 h, compared with 3.221 h for interruption episodes, while both 90th percentiles are 5.00 h (Figure 3). For Figure 3, the one-hour histograms use all 3788 known positive interruption durations and 4860 known repair-work durations. The empirical distribution functions use dated entries and connected episodes. The interruption curves use positive durations, and the dotted line marks the 90th percentile.
Figure 3. Duration distributions for interruption and repair work, 2004–2025: (a) interruption-duration and (b) repair-work-duration histograms with one-hour bins; (c) interruption and (d) repair-work empirical distribution functions for entries and connected episodes.
Median durations were 3 h for interruption episodes and 8 h for repair-work episodes, with maxima of 26 and 39 h, respectively (Table 2). Associated repair work is active at the final interruption endpoint in 3275 episodes, representing 96.86% of interruption episodes. Continuing related repair work totals 11,220.50 episode-linked entry-hours; later-starting-related intervals add 158.50 such hours. Because the same entry can link to multiple episodes, these totals measure relationships rather than unique repair-work burden.
The joint (1,2) condition is violated for 1061.42 h over the 192,864 h observation period, or 0.5503% of recorded calendar time. Simultaneous exceedance of both limits lasts 124.00 h. The higher threshold pairs (2,3), (3,4) and (4,6) are exceeded for 113.83, 14.00 and 8.00 h, respectively.

3.3. Exact Aggregate Matching

Exact matching identifies 709 complete, closed weeks among 773 candidate weeks containing at least three source entries. There are 56 groups with identical entry count and both accumulated durations, comprising 163 unique weeks and 205 pairwise comparisons. Forty groups exhibit variation in at least one of interruption maximum, repair-work maximum or (1,2) exposure. Ninety-five pairs differ in one or more of those metrics.
The weeks beginning 24 May 2021 and 3 November 2025 both contain five entries, 40.00 repair-work entry-hours and 15.50 interruption entry-hours. Their respective (MD,MW) values are (1,1) and (2,3), while (1,2) exposure is zero versus 4.00 h. Their repair-work-active calendar duration is 40.00 versus 31.00 h (Figure 4).
Figure 4. Minute-resolved occupancy in matched weeks: (a) 24–30 May 2021 and (b) 3–9 November 2025. The upper and lower rows show repair-work and interruption occupancy, respectively.
The second week concentrates the same burden into fewer active hours and includes exposure above the (1,2) limits. This identifies periods for reviewing job separation, access, shared equipment and coordination of planned shutdowns and supply restoration. Scheduling changes require verified, reschedulable jobs and compliance with hydraulic service constraints.
In Figure 4, categorical colour intensity indicates the exact number of active entries in each calendar segment; white indicates zero. Red outlines identify interruption counts above one or repair-work counts above two. Identical categorical legends are used in both weeks.

3.4. Reference Conditioning and the Observation Unit

Independent calendar relocation gives mean (1,2) exposure of 1362.04 h, with a central 95% reference range of 1251.32–1481.31 h. The observed 1061.42 h is 22.07% below that mean. When daily anchor counts are fixed, the mean is 1250.57 h (1179.74–1319.78 h), and the observed exposure remains 15.13% lower. The two-sided Holm-adjusted scores equal 0.0140, except for the interruption maximum (0.1239) and the number of repair-work episodes (0.1818). These scores are interpreted descriptively against the specified references. Simultaneous AND exceedance is also below both reference ranges. The accumulated-overlap finding survives the change in calendar conditioning (Table 3).
Table 3. Independent calendar relocation with Holm adjustment. Obs., observed value; Ref. mean, mean of 1000 reference paths; Central 95% ref., central 95% simulation reference range; Upper Holm, Holm-adjusted upper-tail area.
The longest interruption episode lasted 26 h. This was the minimum value under independent relocation and occurred in 759 of the 1000 paths. Peak repair-work concurrency depends on the reference construction. Repair-work occupancy of nine is unusual in the upper tail under independent relocation (upper-tail area 0.0010, Holm-adjusted 0.0070). Under fixed daily anchor counts, all 1000 paths reproduced the observed maximum of nine. The upper-tail area for fixed counts is 1.0000. The two-sided Holm score of 0.0140 arises because the strict lower tail is empty (Table 4 and Figure 5) except for the interruption maximum after excluding 2007 (0.3916). These comparisons do not identify why the entries accumulated on that date.
Table 4. Conditioning on observed daily counts and sensitivity to excluding 2007 (1000 paths per cohort), where D is the interruption occupancy; W is the repair-work occupancy; OR and AND refer to the joint (1,2) limits.
Figure 5. Recorded values and calendar-conditioned reference ranges: (a) maximum active repair-work entries and (b) time exceeding the (1,2) OR limit (h).
Removing all 2007 entries reduces both observed maxima to four. Remaining OR exposure is 1000.92 h, compared with reference means 1284.57 h under relocation and 1185.18 h under fixed daily counts. The lower-exposure contrast persists. Every simulated repair-work maximum was at least four under both references. The empty strict lower tails give a two-sided Holm score of 0.0140 in both cases. This sensitivity check targets the year with the recorded maxima. For the year-exclusion scenario under independent relocation, the two-sided Holm-adjusted area for (1,2) OR exposure is 0.0140 within the seven-outcome family. The OR and AND metrics are evaluated against fixed joint threshold counts.
Two location/repair-work-interval groups comprise two entries in 2005 and three in 2007. Hypothetical union reduces the full-period repair-work maximum from nine to seven, leaves the interruption maximum at six and reduces OR exposure by 9.00 h. Under independent calendar relocation of the hypothetical grouped units, the repair-work-maximum upper-tail area is 0.0549 and its seven-outcome Holm-adjusted directional area is 0.3297. The entries cannot be established as duplicates from location text alone.

3.5. Predictive Performance with Frozen Fits

The validation leader is the independent eight-year NB2 model with five-year individual marks (score 0.3089). Independent whole-day and individual-mark alternatives score 0.3108 and 0.3129; the seven-day serial model scores 0.3142. Residual autocorrelations of 0.118 (lag one) and 0.057 (lag seven) motivate dependence checks but do not change the ranking. The leader ranks first in only 36.54% of fixed-loss three-month resamples.
Table 5 reports validation and assessment scores for all five specifications. With frozen fits, the validation leader scores 0.3585, the serial variant 0.3764 and the Poisson reference 0.3511. In the matched three-year whole-day ablation, adding serial blocks increases loss by 0.0069; the descriptive paired interval using three-month blocks is 0.0011–0.0130. The serial-minus-leader contrast is 0.0180 (0.0047–0.0315). The paired intervals condition on the fitted ensembles. Both assessment protocols use the fixed candidate settings and original score scales described in Section 2.8.
Table 5. Five predictive specifications under both assessment protocols. Values are the composite score S defined in Equation (14); lower values indicate better predictive performance.
The frozen validation leader predicts 10.51 entries per month versus 13.71 observed (23.34% deficit), with 62.50% coverage of nominal 90% count intervals (15 of 24 assessed months). Predicted mean OR exposure is 2.13 h versus 3.39 h observed, and the longest interruption episode averages 7.06 h versus 8.17 h (Figure 6). The four panels compare observed outcomes, the leader and the seven-day serial model; shading shows the leader’s pointwise 5th–95th percentiles from 1500 frozen-fit paths. This coverage is the fraction of observations contained in the prediction intervals, not the fraction of count variance explained. Count-interval coverage below the nominal 90% level limits the operational interpretation of the composite score.
Figure 6. Frozen 2024–2025 monthly assessment: (a) entry counts, (b) longest interruption episode, (c) maximum active repair-work entries and (d) OR (1,2) exposure.
Poisson retains the lowest frozen score under equal weights and all five leave-one-outcome-out alternatives, while the serial model remains fifth.

3.6. Predictive Performance with Annual Refitting

Annual refitting yields composite scores of 0.3541 (validation leader), 0.3734 (serial) and 0.3482 (Poisson). Serial-minus-independent whole-day loss is −0.0013 (paired interval −0.0055–0.0035); serial-minus-leader loss is 0.0193 (−0.0012–0.0413). The two fitting protocols therefore give different estimates of the effect of serial blocks (Figure 7). Positive serial-minus-reference values favour the independent comparator. Intervals use three-month circular blocks.
Figure 7. Serial-minus-reference composite-loss contrasts under (a) frozen fitting and (b) annual refitting, where points denote mean differences and whiskers denote 95% paired circular-block bootstrap intervals based on 10,000 resamples with three-month blocks.
Poisson also leads the original and equal-weight annual-refit comparisons; the serial model ranks fourth. The independent whole-day alternative leads validation under some outcome omissions, showing that the validation ranking is sensitive to the composition of the score.
For the validation leader, annual refitting raises predicted monthly count from 10.51 to 11.45, still 16.48% below the observed mean of 13.71. Count coverage increases to 70.83%, and mean OR exposure rises to 3.00 h against 3.39 h observed. Predicted longest-episode duration remains 7.03 h against 8.17 h, with 75.00% coverage (Table 6). The count CRPS changes only from 3.652 to 3.645 entries, while MAE increases from 4.40 to 4.75 entries. Updating reduces mean bias without improving every measure of accuracy.
Table 6. Validation-leader marginal predictions and empirical coverage of nominal 90% prediction intervals.
Mean monthly (1,2) satisfaction probabilities are 0.496 (frozen) and 0.385 (refit), versus 0.375 observed; Brier scores are 0.2114 and 0.2097. Annual refitting brings the mean probability closer to the observed fraction, although count and episode duration errors persist.
Whole-entry shifts of ±5, ±15 and ±30 min preserve interruption and repair-work maxima (six and nine) but may separate touching intervals and alter episode counts. Placing excluded ambiguous ranges on the next day increases the longest interruption episode from 26.0 to 37.5 h. These shifts were specified for sensitivity analysis.

3.7. Conditional Path Illustrations

The fixed seven-day serial model fitted through 2025 illustrates 2026 horizon-wide satisfaction probabilities (Figure 8). With recent versus all-year marks, annual (2,3) satisfaction is 0.517 versus 0.733. Annual (1,2) satisfaction occurs in only one of 1500 paths, precluding a stable refit range. Figure 8 distinguishes fixed-input Monte Carlo precision from 200 calendar-pair refits with 300 inner paths. These probabilities depend on the fitted simulator, chosen donor pool, calendar and initial state.
Figure 8. Conditional horizon-wide threshold satisfaction probabilities for (a) (1,2) and (b) (2,3), calculated from 1 January 2026. Points are fixed-input estimates; orange intervals show 95% Wilson intervals for Monte Carlo error and blue intervals show central 95% ranges across calendar-pair refits. Fixed-input estimates use 1500 paths; refit ranges use 200 refits with 300 inner paths each. No refit range is shown for the annual (1,2) case because threshold satisfaction was too rare.
The simulated transformations show the sensitivity of the results to fewer entries and shorter intervals. Under annual (2,3), 20% entry thinning raises simulated satisfaction from 0.517 to 0.706; 25% shorter interruption intervals leave it at 0.517 but reduce mean OR (1,2) exposure from 30.33 to 20.46 h. The combined transformation gives 0.718 and 11.22 h. Feasibility and causal effects remain unknown.
Product-limit first-passage curves retain horizon-censored paths, while return distributions include only paths with a crossing (Figure 9). These measures refer to the return of simulated entry counts within the specified limits.
Figure 9. Product-limit estimates for the conditional annual ensemble: (a) time to first threshold crossing and (b) return duration following a crossing.
A zero crossing count in a finite ensemble does not establish a zero physical probability.

3.8. Dated-Endpoint Uncertainty Changes Exposure More than the Repair-Work Peak

The core and expanded envelopes at ±5 and ±15 min both have D and W maxima of six and nine. At ±30 min, the D maximum has outer bounds five to six, while the W maximum remains exactly nine for every feasible path in this scenario. Without 2007, the ±30-min W bounds are four to five. Thus, the full-period repair-work peak is robust to these limited endpoint scenarios, despite its sensitivity to the observation unit and year inclusion (Table 7).
Table 7. Conservative path bounds under independent dated-endpoint uncertainty.
OR (1,2) exposure envelopes widen from 1061.42 h nominally to 996.92–1145.25 h at ±5 min, 868.08–1312.75 h at ±15 min and 683.92–1572.25 h at ±30 min. At ±30 min, AND exposure spans 72.83–180.00 h around 124.00 h nominally, and the longest interruption episode spans 25.00–27.00 h around 26.00 h. Interruption and repair-work burdens span 7865.82–15,414.17 and 33,661.08–43,369.65 entry-hours, respectively.
The ±30-min OR envelope includes both nominal reference means from Section 3.4 but does not repeat reference testing under uncertain timestamps.

3.9. Predictive Evidence Across January and Seasonal Origins

The lowest descriptive composite scores at 1-, 3- and 12-month horizons are, respectively, 0.6080 for the five-year individual NB2 model, 0.4965 for the three-year individual NB2 model, and 0.4476 for the seven-day serial model. Table 8 reports scores on the origin-specific scales described in Section 2.8.
Table 8. Annual-origin composite scores (S ± one conditional Monte Carlo standard error). Lower scores indicate better predictive performance. Standard errors describe finite-ensemble Monte Carlo precision conditional on the fitted models.
Horizon-specific calibration is uneven (Table A3). For January-origin aggregate counts, empirical coverage of nominal 90% prediction intervals for the independent five-year NB2 model is 64.3%, 64.3% and 28.6% over 1, 3 and 12 months; for the longest interruption episode, it is 78.6%, 78.6% and 71.4%. The seven-day serial alternative attains 64.3%, 71.4% and 42.9% for aggregate counts. Each rate is based on only 14 retrospective origins. The 28.6% annual count coverage corresponds to 4 of 14 annual observations inside nominal 90% intervals; “five-year” identifies the interval-donor history, not the length of the assessment period. These percentages do not measure explained variance.
At three months, the NB2 model with three years of individual-entry donors has a composite score 0.0003 lower than the Poisson score. The difference is smaller than its conditional Monte Carlo SE of about 0.0039.
Controlled whole-day serial-minus-independent losses at 1, 3 and 12 months are −0.0016 (−0.0194 to 0.0163), −0.0003 (−0.0141 to 0.0111) and −0.0080 (−0.0263 to 0.0055). These are descriptive intervals from two-origin blocks. The corresponding conditional Monte Carlo SEs are approximately 0.0034–0.0039.
For five-year individual NB2, the annual count CRPS is 26.62 entries, MAE 33.68, bias +8.81 and mean interval width 48.23 entries. The longest annual interruption episode has a CRPS of 4.02 h. Poisson annual count coverage is 21.4%, also below the nominal 90% level.
Annual count coverage for five-year individual NB2 rises from 14.3% (2012–2018) to 42.9% (2019–2025), with only seven origins per era.
For the added seasonal origins, the lowest descriptive composite scores at one month are April: NB2 whole-day block 7 (0.4661); July: Poisson calendar (0.4274); October: Poisson calendar (0.6024). At three months, they are April: NB2 whole-day block 7 (0.3661); July: NB2 whole-day block 7 (0.4790); October: NB2 whole-day block 7 (0.5226). The complete five-model comparison, conditional Monte Carlo standard errors and count coverage appear in Table A2.
At 12 months, the corresponding seasonal leaders are April: NB2 whole-day block 7 (0.7156); July: NB2 individual 3-year (0.6215); October: NB2 individual 3-year (0.4174). There are 13 annual windows per added origin month, compared with 14 at the shorter horizons. Across all five specifications and the three added origin months, annual count interval coverage ranges from 23.1% to 61.5%. These retrospective, overlapping windows broaden calendar coverage but do not establish prospective reliability or independent evidence for a universal model ranking.

3.10. Robustness of the Main Findings

RQ1 follows directly from matched aggregates and linked timestamps: weekly counts and burdens conceal overlap, and restoration commonly precedes completion of associated work. These findings concern the audited database and its defined entries.
For RQ2, the full-period repair-work peak of nine persists across the imposed endpoint ranges, but changes under entry grouping and exclusion of 2007; its exceptional status also changes with the calendar reference. At nominal timestamps, lower OR (1,2) exposure than the reference mean persists across both references and the targeted year exclusion. This contrast cannot be confirmed for every uncertain timestamp configuration: the ±30-min exposure bounds include both nominal reference means.
For RQ3, count prediction intervals show undercoverage across multiple retrospective protocols. Relative scores depend on horizon, calendar origin and fitting strategy. Conditional path probabilities and transformed-path scenarios therefore remain model-based illustrations, rather than validated service assurances.

4. Discussion

4.1. The Empirical Contribution of Chronology

Exact weekly matching shows that an audit based on counts and total durations can miss concentrated activity. Retaining event-level timestamps allows the utility to locate the overlapping periods and examine the underlying entries. This complements the burden summaries used in earlier work [20,21].
Repair-work occupancy and continuing work after restoration describe recorded intervals. The database gives no separate cleanup, equipment-use or crew-attendance times; the 96.86% linkage result therefore identifies a timing distinction, rather than a measure of additional staffing demand.
Connected repair-work episodes had a substantially longer upper duration tail than individual entries (Table 2). The episode durations help assess how long maintenance activity can continue across multiple entries.

4.2. Influence of Reference Construction on Peak Concurrency Assessment

Grouping five entries into two hypothetical units changed the repair-work peak while reducing OR exposure by less than 1%. Varying endpoints produced the opposite pattern: the full-period repair-work peak stayed constant while OR exposure covered a wide range. Scheduling, field constraints and recording practices could all shape the observed patterns. The database cannot establish what the clustered entries on the peak day represent.
The 2007 exclusion measures one year’s influence on the full-period maximum. It neither establishes an error nor estimates a secular trend. Planning should retain the complete database, report this sensitivity analysis and prioritise peak-day entries for verification.

4.3. Predictive Performance and Model Updating

The matched NB2 comparisons isolate within-day timing through whole-day donors and cross-day dependence through residual blocks.
Annual refitting reduced some mean biases, but count intervals continued to cover too few observations and predicted interruption episodes remained short. Count-interval coverage is 62.5% in the frozen monthly assessment and 28.6% for January-origin annual forecasts, below the nominal 90% level. Using these ensembles to size reserves, certify capacity or establish interruption guarantees requires improved calibration and prospective validation.
The predictive comparison gives no consistent advantage to the tested forms of dependence. Extrapolated trends, limited donor pools, changes in registration practices and other forms of dependence may contribute to the errors. Operational validation requires a new prospectively specified assessment period.

4.4. Conditional Probabilities and Operational Meaning

The January and additional seasonal backtests show that forecast error extends beyond Monte Carlo variation within a fitted ensemble. More simulated paths can improve numerical precision; model bias, limited donor support and changing registration practices require separate evaluation.
With so few annual paths meeting the (1,2) limits, the inner ensembles were too small to characterise refit uncertainty reliably. Rare-event extrapolation would need validated assumptions. Imposed thinning and shortening scenarios are not estimates of policy feasibility, cost or effect.
The thresholds apply to simultaneous database entries. To translate them into operational limits, a utility would need to link entries to crew assignments and customer impacts or assess hydraulic consequences using network topology, demand and pressure data. Performability approaches [4,5] and maintenance models [7] illustrate how service criteria can be defined when such data are available.
Resilience-based restoration policies for recurrent dependent hazards have been developed for decision-makers with different risk preferences [36]. The recorded interruption and repair-work trajectories could inform related water utility decision models after objectives, costs, resource constraints and hydraulic consequences have been defined and validated.

4.5. Observation Limits and Transferability

Sewer-condition benchmarking [37] and blockage-event modelling [38] illustrate the value of stable asset identifiers and independent evaluation.
Early coverage is incomplete, timestamps cluster at certain clock times, and daylight-saving annotations are unavailable. The imposed endpoint ranges do not cover all missing dates, shared recording errors or possible changes in registration practice. Transferability should be checked in another utility with documented entry definitions, linked work orders and verifiable timestamps.

4.6. Engineering Implications for Water Utility Maintenance

Operational use requires separate shutoff, repair-start, restoration and repair-end timestamps, linked through stable incident identifiers to work orders and crew assignments. Entries belonging to one intervention must be reconciled before counts represent operational workload.
Concentrated hours identified by the matched-week comparison can guide reviews of shared equipment, access and interacting shutdowns. Scheduling changes require verified job durations and hydraulic constraints. Monitoring restoration separately from repair completion supports coordination; service consequences additionally require affected-demand or customer data.
Operational alerts require documented resource or service objectives. Economic objectives are explicit in maintenance-policy development for self-service fleets [39]; similar clarity is needed before interpreting overlap limits as a water utility policy. Maxima describe peaks, exposure describes duration, and crossing probabilities require acceptable predictive calibration before operational use.
Prospective evaluation must specify observation rules, models, horizons and seasonal issuance dates before outcomes become available. Count bias, CRPS, interval coverage and concurrency errors then indicate whether forecasts support the defined maintenance application.

5. Conclusions

RQ1. Weeks with identical counts and accumulated interruption and repair-work durations differ in maxima or threshold exposure within 40 of 56 matched groups. Associated work remains active at restoration in 96.86% of interruption episodes, supporting separate monitoring of restoration and repair completion.
RQ2. The full-database repair-work maximum of nine is stable under the imposed ±30-min endpoint scenarios. In separate sensitivity analyses, the maximum falls to seven after hypothetical grouping and to four after excluding 2007. Its assessment changes when daily counts are conditioned upon. Lower nominal OR exposure persists across the inspected calendar references and year exclusion, while timestamp envelopes prevent claiming that contrast for every feasible timing configuration.
RQ3. Five chronological simulators show horizon-, origin- and protocol-dependent performance. For the five-year-donor NB2 model, observed coverage falls below the nominal 90% level in both the frozen monthly assessment (62.5%) and January-origin annual forecasts (28.6%). Additional seasonal origins broaden the assessment without establishing an operationally reliable model or a consistent benefit from the tested dependence structures.
For maintenance engineering, the immediate uses are auditing concentrated activity, verifying the entries behind peaks, and coordinating restoration and remaining work through linked work orders. Utilities should establish job and resource mappings, justify alert limits and prospectively validate forecasts before using these measures for staffing or service commitments.

Author Contributions

Conceptualization, K.P.-U.; methodology, K.P.-U. and M.E.; validation, K.P.-U. and M.E.; formal analysis, K.P.-U. and M.E.; investigation, K.P.-U.; resources, K.P.-U.; data curation, K.P.-U.; writing—original draft preparation, K.P.-U.; writing—review and editing, K.P.-U., M.E. and B.T.-C.; supervision, K.P.-U., M.E. and B.T.-C.; project administration, K.P.-U. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A. Model Specifications and Predictive Diagnostics

Appendix A.1. Candidate Models

Model selection and assessment limitations are described in Section 2.7.
Table A1. Thirteen candidates fitted through 2021 and validated in 2022–2023 using 500 two-year paths.

Appendix A.2. Additional Seasonal Forecast Origins

Table A2. Seasonal forecasts. Each cell reports S ± conditional Monte Carlo SE on the first line and empirical coverage of nominal 90% count prediction intervals (%) on the second line. Lower S indicates better predictive performance. IDs refer to Table A1; each month has 14 one- and three-month windows and 13 annual windows.

Appendix A.3. Count Prediction Interval Calibration

Coverage measures containment, not explained variance. Small samples and overlapping windows limit precision; a lower S does not ensure adequate calibration (Section 3.9).
Table A3. Coverage of nominal 90% count prediction intervals: % (contained/assessed). Frozen/refit: 24 months in 2024–2025; January horizons: 14 outcomes in 2012–2025.

References

  1. Eick, S.G.; Massey, W.A.; Whitt, W. The physics of the Mt/G/∞ queue. Oper. Res. 1993, 41, 731–742. [Google Scholar] [CrossRef] [Scilit]
  2. Massey, W.A.; Whitt, W. Networks of infinite-server queues with nonstationary Poisson input. Queueing Syst. 1993, 13, 183–250. [Google Scholar] [CrossRef] [Scilit]
  3. Massey, W.A.; Whitt, W. Peak congestion in multi-server service systems with slowly varying arrival rates. Queueing Syst. 1997, 25, 157–172. [Google Scholar] [CrossRef] [Scilit]
  4. Meyer, J.F. On evaluating the performability of degradable computing systems. IEEE Trans. Comput. 1980, C-29, 720–731. [Google Scholar] [CrossRef] [Scilit]
  5. Trivedi, K.S.; Bobbio, A. Reliability and Availability Engineering: Modeling, Analysis, and Applications; Cambridge University Press: Cambridge, UK, 2017. [Google Scholar] [CrossRef] [Scilit]
  6. Ghosh, R.; Kim, D.S.; Trivedi, K.S. System resiliency quantification using non-state-space and state-space analytic models. Reliab. Eng. Syst. Saf. 2013, 116, 109–125. [Google Scholar] [CrossRef] [Scilit]
  7. Carnevali, L.; Tarani, F.; Vicario, E. Performability evaluation of water distribution systems during maintenance procedures. IEEE Trans. Syst. Man. Cybern. Syst. 2020, 50, 1704–1720. [Google Scholar] [CrossRef] [Scilit]
  8. Berardi, L.; Ugarelli, R.; Røstum, J.; Giustolisi, O. Assessing mechanical vulnerability in water distribution networks under multiple failures. Water Resour. Res. 2014, 50, 2586–2599. [Google Scholar] [CrossRef] [Scilit]
  9. Liu, W.; Song, Z.; Wan, Z.; Li, J. Lifecycle operational reliability assessment of water distribution networks based on the probability density evolution method. Probabilistic Eng. Mech. 2020, 59, 103037. [Google Scholar] [CrossRef] [Scilit]
  10. Arrighi, C.; Tarani, F.; Vicario, E.; Castelli, F. Flood impacts on a water distribution network. Nat. Hazards Earth Syst. Sci. 2017, 17, 2109–2123. [Google Scholar] [CrossRef] [Scilit]
  11. Tchórzewska-Cieślak, B.; Rak, J.; Pietrucha-Urbanik, K.; Piegdoń, I.; Boryczko, K.; Szpak, D.; Żywiec, J. Water supply safety assessment considering the water supply system resilience. Desalin. Water Treat. 2023, 288, 26–36. [Google Scholar] [CrossRef] [Scilit]
  12. Sirsant, S.; Hamouda, M.A.; Shaaban, M.F. Advances in assessing the reliability of water distribution networks: A bibliometric analysis and scoping review. Water 2023, 15, 986. [Google Scholar] [CrossRef] [Scilit]
  13. Carneiro, J.; Loureiro, D.; Cabral, M.; Covas, D. Comprehensive resilience assessment framework for water distribution networks. Water 2024, 16, 2611. [Google Scholar] [CrossRef] [Scilit]
  14. Wei, Y.; Cheng, Y.; Liao, H.; Elsayed, E.A. Resilience modeling for an engineered network with multimodal performance under multiple recurrent hazards. Reliab. Eng. Syst. Saf. 2026, 266, 111640. [Google Scholar] [CrossRef] [Scilit]
  15. Cabral, M.; Gray, D.; Brentan, B.; Covas, D. Assessing pipe condition in water distribution networks. Water 2024, 16, 1318. [Google Scholar] [CrossRef] [Scilit]
  16. Raspati, G.S.; Bruaset, S.; Bosco, C.; Mushom, L.; Johannessen, B.; Ugarelli, R. A risk-based approach in rehabilitation of water distribution networks. Int. J. Environ. Res. Public Health 2022, 19, 1594. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  17. Mansyur, E.J.; Soemardi, B.W.; Wirahadikusumah, R.D. Structure equation model for costs and benefits of distribution pipe rehabilitation in reactive maintenance. Water 2024, 16, 3097. [Google Scholar] [CrossRef] [Scilit]
  18. Chen, G.; Xie, H.; Ma, Y.; Zhu, R.; Li, B. Risk assessment methods for urban water distribution networks: A state-of-the-art review of indicator, statistical, and machine learning approaches. Appl. Sci. 2026, 16, 3443. [Google Scholar] [CrossRef] [Scilit]
  19. de Sousa Medeiros, V.; dos Santos, M.D.; Brito, A.V. Case study for predicting failures in water supply networks using neural networks. Water 2024, 16, 1455. [Google Scholar] [CrossRef] [Scilit]
  20. Pietrucha-Urbanik, K. Resource-oriented prioritisation of water-supply pipe groups using repair and service-interruption burdens. Resources 2026, 15, 114. [Google Scholar] [CrossRef] [Scilit]
  21. Pietrucha-Urbanik, K.; Rak, J.R. Seasonality and repair time analysis of water distribution system failures. Sustainability 2026, 18, 3950. [Google Scholar] [CrossRef] [Scilit]
  22. Pegoraro, M.; van der Aalst, W.M.P. Mining uncertain event data in process mining. In Proceedings of the 2019 International Conference on Process Mining (ICPM), Aachen, Germany, 24–26 June 2019; pp. 89–96. [Google Scholar] [CrossRef] [Scilit]
  23. Pietrucha-Urbanik, K.; Tchórzewska-Cieślak, B.; Eid, M. Water network-failure data assessment. Energies 2020, 13, 2990. [Google Scholar] [CrossRef] [Scilit]
  24. Wei, Y.; Cheng, Y.; Liao, H. Optimal maintenance of a critical infrastructure subject to dependent recurrent hazards. Sustain. Resilient Infrastruct. 2026, 11, 446–470. [Google Scholar] [CrossRef] [Scilit]
  25. Carrington, N.K.; Dobson, I.; Wang, Z. Extracting resilience metrics from distribution utility data using outage and restore process statistics. IEEE Trans. Power Syst. 2021, 36, 5814–5823. [Google Scholar] [CrossRef] [Scilit]
  26. Phipson, B.; Smyth, G.K. Permutation P-values should never be zero: Calculating exact P-values when permutations are randomly drawn. Stat. Appl. Genet. Mol. Biol. 2010, 9, 39. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  27. Holm, S. A simple sequentially rejective multiple test procedure. Scand. J. Stat. 1979, 6, 65–70. Available online: https://www.jstor.org/stable/4615733 (accessed on 1 June 2026).
  28. Hilbe, J.M. Negative Binomial Regression, 2nd ed.; Cambridge University Press: Cambridge, UK, 2011. [Google Scholar]
  29. Dunn, P.K.; Smyth, G.K. Randomized quantile residuals. J. Comput. Graph. Stat. 1996, 5, 236–244. [Google Scholar] [CrossRef] [Scilit]
  30. Ljung, G.M.; Box, G.E.P. On a measure of lack of fit in time series models. Biometrika 1978, 65, 297–303. [Google Scholar] [CrossRef]
  31. Gneiting, T.; Raftery, A.E. Strictly proper scoring rules, prediction, and estimation. J. Am. Stat. Assoc. 2007, 102, 359–378. [Google Scholar] [CrossRef] [Scilit]
  32. Tashman, L.J. Out-of-sample tests of forecasting accuracy: An analysis and review. Int. J. Forecast. 2000, 16, 437–450. [Google Scholar] [CrossRef] [Scilit]
  33. Wilson, E.B. Probable inference, the law of succession, and statistical inference. J. Am. Stat. Assoc. 1927, 22, 209–212. [Google Scholar] [CrossRef]
  34. Künsch, H.R. The jackknife and the bootstrap for general stationary observations. Ann. Stat. 1989, 17, 1217–1241. [Google Scholar] [CrossRef] [Scilit]
  35. Kaplan, E.L.; Meier, P. Nonparametric estimation from incomplete observations. J. Am. Stat. Assoc. 1958, 53, 457–481. [Google Scholar] [CrossRef]
  36. Wei, Y.; Cheng, Y.; Liao, H. Optimal resilience-based restoration of a system subject to recurrent dependent hazards. Reliab. Eng. Syst. Saf. 2024, 247, 110137. [Google Scholar] [CrossRef] [Scilit]
  37. Scheidegger, A.; Hug, T.; Rieckermann, J.; Maurer, M. Network condition simulator for benchmarking sewer deterioration models. Water Res. 2011, 45, 4983–4994. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  38. Rodríguez, J.P.; McIntyre, N.; Díaz-Granados, M.; Maksimović, Č. A database and model to support proactive management of sediment-related sewer blockages. Water Res. 2012, 46, 4571–4586. [Google Scholar] [CrossRef] [Scilit] [PubMed]
  39. Wei, Y.; Cheng, Y.; Liao, H. A quantitative maintenance policy development framework for a fleet of self-service systems. Nav. Res. Logist. 2025, 72, 750–767. [Google Scholar] [CrossRef] [Scilit]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Article Metrics

Citations

Article Access Statistics

Multiple requests from the same IP address are counted as one view.