Quantitative Analysis of Manufacturing Flexibility and Inventory Management: Impact on Total Flow Time in Production System
Abstract
1. Introduction
Related Literature
2. Problem Formulation
3. Experimental Design
3.1. Flexibilities
3.2. Data for the Proposed Manufacturing System
3.3. Assumptions and Considerations of the Models to Simulate
- Machines operate only when a worker has been assigned, and work is available for processing.
- Setup time for operations is not considered.
- The time workers spend moving between machines is omitted.
- The parts to be processed have pre-assigned routes through the machines, thus maintaining route flexibility.
- All workers possess homogeneous skills.
- The production line is balanced in terms of the number of defined workstations.
- Each production batch consists of 36 pieces.
- The buffer size is equivalent to the lot size calculated according to the economic order quantity (EOQ) model.
3.4. Model Verification
4. Results and Discussion
4.1. Preliminary Analysis
4.2. Main Findings and Contributions
- Labor and route flexibility (route flexibility is only present when machine flexibility is enabled);
- machine, labor, and route flexibility;
- machine, route, and volume flexibility (volume flexibility is only present when machine flexibility is enabled); and
- machine, labor, route, and volume flexibility. These interactions reinforce the non-additive nature of the system, where the benefits depend not only on the individual level of each type of flexibility but also on their combination.
5. Conclusions
Future Work
- Introduce variable transportation times between stations, in order to analyze the impact of logistical variability and potential bottlenecks on the system’s responsiveness. It is also relevant to explicitly include setup times and operator movement times, as their omission may overestimate the benefits of labor and routing flexibility. Incorporating these elements would enable the assessment of their effects in scenarios that more accurately represent real industrial operations.
- Implement dynamic buffers whose size can be adjusted according to operational load, demand fluctuations, or actual production requirements. This would allow a more realistic representation of production systems and their behavior under different congestion levels.
- Advance toward a joint time–cost optimization approach, integrating economic metrics such as operating, inventory, and flexibility-related costs. This approach would enable the development of a multi-objective model capable of simultaneously evaluating temporal efficiency and the economic feasibility of the flexible manufacturing system.
- Update the model’s parameterization using databases from contemporary industrial settings, reflecting the technological conditions of digital manufacturing. This would allow the results to be contrasted with current scenarios characterized by advanced automation, IoT integration, and artificial intelligence, thus strengthening the model’s empirical validity and its applicability in intelligent manufacturing systems.
- Empirically validate the model using real data from current production systems, with the aim of comparing the simulation results with observed indicators and reinforcing its external validity and predictive capability in smart manufacturing environments.
- Expand the analysis by incorporating new dimensions of flexibility, particularly product flexibility, with the goal of assessing its impact on overall system performance and enriching the influence diagram developed in this study. In this regard, an explicit hypothesis is proposed: product flexibility may amplify the effect of volume flexibility in the face of variations in product mix and may also interact with routing flexibility by requiring additional or alternative routes to accommodate differentiated operations. These potential synergies or trade-offs justify their evaluation through simulation and statistical analysis, in order to integrate this dimension into the influence diagram and understand its interaction with the four flexibility types currently examined.
- Deepen the study of resource saturation points, with the purpose of identifying the system’s operational limits and optimizing their utilization, thus avoiding inefficiencies associated with overuse or misestimation of flexibility requirements. Additionally, it is proposed to explore the effect of stochastic variability by incorporating uncertainty into critical variables such as demand, processing times, and resource availability, in order to evaluate the model’s robustness under conditions that more accurately reflect complex production environments.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Fenta, E.W.; Tsegaye, A.A.; Abere, A.E.; Tefera, G.T. Opportunities in Flexible Manufacturing Systems in the near Future. Global J. Flex. Syst. Manag. 2025, 26, 247–267. [Google Scholar] [CrossRef]
- Qin, T.; Zhu, J.; Li, Z.; Hu, X.; Mostafa, A.M.M. Path Detectability Verification for Time-Dependent Systems with Application to Flexible Manufacturing Systems. Inf. Sci. 2025, 689, 121404. [Google Scholar] [CrossRef]
- Ullah, A.; Younas, M. Development and Application of Digital Twin Control in Flexible Manufacturing Systems. J. Manuf. Mater. Process. 2024, 8, 214. [Google Scholar] [CrossRef]
- Priyadarshini, J.; Gupta, A.K. Mapping and Visualizing Flexible Manufacturing System in Business and Management: A Systematic Review and Future Agenda. J. Model. Manag. 2024, 19, 19–45. [Google Scholar] [CrossRef]
- Meilanitasari, P.; Shin, S.J. A Review of Prediction and Optimization for Sequence-Driven Scheduling in Job Shop Flexible Manufacturing Systems. Processes 2021, 9, 1391. [Google Scholar] [CrossRef]
- Yadav, A.; Jayswal, S.C. Modelling of Flexible Manufacturing System: A Review. Int. J. Prod. Res. 2018, 56, 2464–2487. [Google Scholar] [CrossRef]
- Elyasi, M.; Altan, B.; Ekici, A.; Özener, O.Ö.; Yanıkoğlu, İ.; Dolgui, A. Production Planning with Flexible Manufacturing Systems under Demand Uncertainty. Int. J. Prod. Res. 2024, 62, 157–170. [Google Scholar] [CrossRef]
- Xiao, Y.; Shao, H.; Feng, M.; Han, T.; Wan, J.; Liu, B. Towards Trustworthy Rotating Machinery Fault Diagnosis via Attention Uncertainty in Transformer. J. Manuf. Syst. 2023, 70, 186–201. [Google Scholar] [CrossRef]
- Ternero, R.; Sepúlveda-Rojas, J.P.; Alfaro, M.; Fuertes, G.; Vargas, M. Inventory Management with Stochastic Demand: Case Study of a Medical Equipment Company. S. Afr. J. Ind. Eng. 2023, 34, 131–142. [Google Scholar] [CrossRef]
- Zhou, T.; Zhang, L.; Han, T.; Droguett, E.L.; Mosleh, A.; Chan, F.T.S. An Uncertainty-Informed Framework for Trustworthy Fault Diagnosis in Safety-Critical Applications. Reliab. Eng. Syst. Saf. 2023, 229, 108865. [Google Scholar] [CrossRef]
- Chang, D.; Shi, H.; Han, C.; Meng, F. Research on Production Scheduling Optimization of Flexible Job Shop Production with Buffer Capacity Limitation Based on the Improved Gene Expression Programming Algorithm. Int. J. Precis. Eng. Manuf. 2023, 24, 2317–2336. [Google Scholar] [CrossRef]
- Bagherian, A.; Chauhan, G.; Srivastav, A.L. Data-Driven Prioritization of Performance Variables for Flexible Manufacturing Systems: Revealing Key Metrics with the Best–Worst Method. Int. J. Adv. Manuf. Technol. 2024, 130, 3081–3102. [Google Scholar] [CrossRef]
- Grassi, A.; Guizzi, G.; Popolo, V.; Vespoli, S. A Genetic-Algorithm-Based Approach for Optimizing Tool Utilization and Makespan in FMS Scheduling. J. Manuf. Mater. Process. 2023, 7, 75. [Google Scholar] [CrossRef]
- Weckenborg, C.; Schumacher, P.; Thies, C.; Spengler, T.S. Flexibility in Manufacturing System Design: A Review of Recent Approaches from Operations Research. Eur. J. Oper. Res. 2024, 315, 413–441. [Google Scholar] [CrossRef]
- Mwangola, W.N.; Mackelprang, A.W.; Burke, G.J. Performing in Uncertain Operating Environments: Buffer Inventory, Volume Flexibility or Both? Int. J. Prod. Econ. 2024, 268, 109115. [Google Scholar] [CrossRef]
- Waseem, M.; Chang, Q. From Nash Q-Learning to Nash-MADDPG: Advancements in Multiagent Control for Multiproduct Flexible Manufacturing Systems. J. Manuf. Syst. 2024, 74, 129–140. [Google Scholar] [CrossRef]
- Newman, W.R.; Hanna, M.; Maffei, M.J. Dealing with the Uncertainties of Manufacturing: Flexibility, Buffers and Integration. Int. J. Oper. Prod. Manag. 1993, 13, 19–34. [Google Scholar] [CrossRef]
- Pagell, M.; Newman, W.R.; Hanna, M.D.; Krause, D.R. Uncertainty, Flexibility, and Buffers: Three Case Studies. Prod. Inventory Manag. J. 2000, 41, 35. [Google Scholar]
- Palominos, P.; Quezada, L.; Moncada, G. Modeling the Response Capability of a Production System. Int. J. Prod. Econ. 2009, 122, 458–468. [Google Scholar] [CrossRef]
- Seebacher, G.; Winkler, H. Evaluating Flexibility in Discrete Manufacturing Based on Performance and Efficiency. Int. J. Prod. Econ. 2014, 153, 340–351. [Google Scholar] [CrossRef]
- Gaiardelli, S.; Carra, D.; Spellini, S.; Fummi, F. Dynamic Job and Conveyor-Based Transport Joint Scheduling in Flexible Manufacturing Systems. Appl. Sci. 2024, 14, 3026. [Google Scholar] [CrossRef]
- Dabwan, A.; Kaid, H.; Al-Ahmari, A.; Alqahtani, K.N.; Ameen, W. An Internet-of-Things-Based Dynamic Scheduling Optimization Method for Unreliable Flexible Manufacturing Systems under Complex Operational Conditions. Machines 2024, 12, 192. [Google Scholar] [CrossRef]
- Liu, Z.; Zha, J.; Yan, J.; Zhang, Y.; Zhao, T.; Cheng, Q.; Cheng, C. An Improved Genetic Algorithm with an Overlapping Strategy for Solving a Combination of Order Batching and Flexible Job Shop Scheduling Problem. Eng. Appl. Artif. Intell. 2024, 127, 107321. [Google Scholar] [CrossRef]
- Ahmed, R.; Heese, H.S.; Kay, M. Designing a Manufacturing Network with Additive Manufacturing Using Stochastic Optimisation. Int. J. Prod. Res. 2023, 61, 2267–2287. [Google Scholar] [CrossRef]
- Amjath, M.; Kerbache, L.; Smith, J.M.G.; Elomri, A. Optimisation of Buffer Allocations in Manufacturing Systems: A Study on Intra and Outbound Logistics Systems Using Finite Queueing Networks. Appl. Sci. 2023, 13, 9525. [Google Scholar] [CrossRef]
- Pourvaziri, H.; Salimpour, S.; Akhavan Niaki, S.T.; Azab, A. Robust Facility Layout Design for Flexible Manufacturing: A Doe-Based Heuristic. Int. J. Prod. Res. 2022, 60, 5633–5654. [Google Scholar] [CrossRef]
- Parker, R.P.; Wirth, A. Manufacturing Flexibility: Measures and Relationships. Eur. J. Oper. Res. 1999, 118, 429–449. [Google Scholar] [CrossRef]
- Katib, I.; Albassam, E.; Sharaf, S.A.; Ragab, M. Safeguarding IoT Consumer Devices: Deep Learning with TinyML Driven Real-Time Anomaly Detection for Predictive Maintenance. Ain Shams Eng. J. 2025, 16, 103281. [Google Scholar] [CrossRef]
- Zhang, J.; Lü, Z.; Ding, J.; Su, Z.; Li, X.; Gao, L. An Effective Local Search Algorithm for Flexible Job Shop Scheduling in Intelligent Manufacturing Systems. Engineering 2025, 50, 117–127. [Google Scholar] [CrossRef]
- Chen, X.; Li, J.; Wang, Z.; Chen, Q.; Gao, K.; Pan, Q. Optimizing Dynamic Flexible Job Shop Scheduling Using an Evolutionary Multi-Task Optimization Framework and Genetic Programming. IEEE Trans. Evol. Comput. 2025, 29, 1502–1516. [Google Scholar] [CrossRef]
- Brill, P.H.; Mandelbaum, M. Measurement of Adaptivity and Flexibility in Production Systems. Eur. J. Oper. Res. 1990, 49, 325–332. [Google Scholar] [CrossRef]
- Brill, P.H.; Mandelbaum, M. On Measures of Flexibility in Manufacturing Systems. Int. J. Prod. Res. 1989, 27, 747–756. [Google Scholar] [CrossRef]
- Sethi, A.K.; Sethi, S.P. Flexibility in Manufacturing: A Survey. Int. J. Flex. Manuf. Syst. 1990, 2, 289–328. [Google Scholar] [CrossRef]
- Palominos, P. Modelling the Response Capacity of the Production System in the Apparel Industry. Ph.D. Thesis, University Polytechnic of Catalonia, Barcelona, Spain, 1996. Volume 66. [Google Scholar]
- Box, G.E.P.; Cox, D.R. An Analysis of Transformations. J. R. Stat. Soc. Ser. B Stat. Methodol. 1964, 26, 211–243. [Google Scholar] [CrossRef]













| Labor Flexibility (Multi-Skilled Worker) | Machine Flexibility | Volume Flexibility (Use of Production Lines for Products) | Route Flexibility (Alternative Production Lines for Products) | |
|---|---|---|---|---|
| L | 1 sewing machine | 1 product | 1 production line | 1 production line |
| M | 2 sewing machines | 2 different products | 2 production lines | 2 production lines |
| H | 4 sewing machines | 3 different products | 4 production lines | 4 production lines |
| Products | Technological Sequence | |
|---|---|---|
| Product 1 | Mach11—Mach12—Mach13 | Line 1 |
| Product 2 | Mach21—Mach22—Mach23 | Line 2 |
| Product 3 | Mach31—Mach32—Mach33 | Line 3 |
| Product 4 | Mach41—Mach42—Mach43 | Line 4 |
| Type of Flexibility | Low | Medium | High |
|---|---|---|---|
| Machine | Each machine performs only its assigned operation. No flexibility (1 operation per machine). | Machines in L1 and L2 can perform operations with each other; the same applies to those in L3 and L4 (2 operations per machine). | Each machine can perform any operation in the system (4 operations per machine). |
| Labor | Each operator only operates their assigned machine. No flexibility. | Operators can operate machines in their own line and one adjacent line (6 machines). | All operators can operate any machine in the system (12 machines). |
| Volume | Up to 25% of capacity is allocated to high-demand products. | Up to 50% can be adapted to more in-demand products. | Up to 100% of capacity can be allocated to high-demand products. |
| Route (C)↓/Machine (A)→ | High | Medium | Low |
|---|---|---|---|
| Low | F | F | F |
| Medium | F | F | |
| High | F |
| Resource | Production | Failure | Absenteeism | Consolidation | Total |
|---|---|---|---|---|---|
| First resource | 5 | 43 | 1229 | 304 | 1580 |
| Bottleneck | 20 | 43 | 1229 | 304 | 1595 |
| Third resource | 5 | 43 | 1229 | 304 | 1580 |
| Total | 4756 |
| Replication | Time | Replication | Time |
|---|---|---|---|
| 1 | 8312 | 6 | 8197 |
| 2 | 8854 | 7 | 7908 |
| 3 | 8572 | 8 | 8192 |
| 4 | 9084 | 9 | 8803 |
| 5 | 9010 | 10 | 8175 |
| Volume Flexibility (D) | ||||||||||||
| Low | Medium | High | ||||||||||
| Route Flexibility (C) | ||||||||||||
| L | M | H | L | M | H | L | M | H | ||||
| Machine Flexibility (A) | Hight | Labor Flexibility (B) | H | 4760 3757 | 5308 4812 | 5086 5205 | 1359 1058 | 3082 2655 | 5184 5040 | 3689 2798 | 4759 4365 | 4588 4198 |
| M | 4697 3984 | 5329 5119 | 5050 4872 | 1400 933 | 3663 2634 | 5278 5035 | 3705 2903 | 3705 4912 | 4827 4165 | |||
| L | 7808 7961 | 8361 8691 | 8416 8200 | 7843 7889 | 9002 8825 | 8845 8618 | 7961 8029 | 9303 8822 | 8785 9012 | |||
| Medium | H | 10,517 9739 | 10,153 10,165 | - | 10,602 11,810 | 10,153 10,095 | - | - | - | - | ||
| M | 11,152 11,127 | 9405 9576 | - | 10,877 11,889 | 10,276 10,301 | - | - | - | - | |||
| L | 11,177 10,842 | 10,733 9555 | - | 9925 10,025 | 11,028 11,094 | - | - | - | - | |||
| Low | H | 6673 6595 | - | - | - | - | - | - | - | - | ||
| M | 6518 6599 | - | - | - | - | - | - | - | - | |||
| L | 8511 1242 | - | - | - | - | - | - | - | - | |||
| (a) Kolmogorov–Smirnov Test | |||
| Time | |||
| Sample size (n) | 810 | ||
| 1620 | |||
| Normal parameters (μ,σ) | Mean | 7768 | |
| 7318 | |||
| Standard deviation | 2569 | ||
| 3018 | |||
| Kolmogorov–Smirnov Z | 1.699 | ||
| 3.128 | |||
| Significance (p-value) | 0.006 | ||
| <0.001 | |||
| (b) Levene’s Test for Equality of Error Variances | |||
| Dependent variable: flow time (T) | |||
| F | gl1 | gl2 | Significance (p-value) |
| 7.24 | 80 | 729 | <0.001 |
| 6.411 | 161 | 1458 | <0.001 |
| Source | Sum of Squares | Degrees of Freedom | Mean Square | F0 | Critical F-Value | p-Value (<) |
|---|---|---|---|---|---|---|
| Corrected model | 0.2572 | 80 | 0.0032 | 209.7833 | 1.44 | 0.001 |
| A | 0.0415 | 2 | 0.0208 | 1355.2626 | 4.63 | 0.001 |
| B | 0.1224 | 2 | 0.0612 | 3995.5954 | 4.63 | 0.001 |
| C | 0.0045 | 2 | 0.0022 | 146.8369 | 4.63 | 0.001 |
| D | 0.0042 | 2 | 0.0021 | 137.2908 | 4.63 | 0.001 |
| A*B | 0.0299 | 4 | 0.0075 | 487.0396 | 3.34 | 0.001 |
| A*C | 0.0011 | 4 | 0.0003 | 18.7203 | 3.34 | 0.001 |
| A*D | 0.0023 | 4 | 0.0006 | 37.6651 | 3.34 | 0.001 |
| B*C | 0.0111 | 4 | 0.0028 | 180.8323 | 3.34 | 0.001 |
| B*D | 0.0089 | 4 | 0.0022 | 145.2168 | 3.34 | 0.001 |
| C*D | 0.0054 | 4 | 0.0014 | 88.2663 | 3.34 | 0.001 |
| A*B*C | 0.0035 | 8 | 0.0004 | 28.5094 | 2.54 | 0.001 |
| A*B*D | 0.0057 | 8 | 0.0007 | 46.3647 | 2.54 | 0.001 |
| A*C*D | 0.0021 | 8 | 0.0003 | 16.8971 | 2.54 | 0.001 |
| B*C*D | 0.0091 | 8 | 0.0011 | 74.5020 | 2.54 | 0.001 |
| A*B*C*D | 0.0054 | 16 | 0.0003 | 21.9714 | 2.02 | 0.001 |
| Error | 0.0111 | 729 | 0.000015 | 0.001 | ||
| Total | 137.541611 | 810 | ||||
| Corrected total | 0.2683 | 809 |
| Source | Sum of Squares | Degrees of Freedom | Mean Square | F0 | Critical F-Value | p-Value (<) |
|---|---|---|---|---|---|---|
| Corrected model | 0.2572 | 80 | 0.0032 | 209.7833 | 1.44 | 0.001 |
| A | 0.0415 | 2 | 0.0208 | 1355.2626 | 4.63 | 0.001 |
| B | 0.1224 | 2 | 0.0612 | 3.995.5954 | 4.63 | 0.001 |
| C | 0.0045 | 2 | 0.0022 | 146.8369 | 4.63 | 0.001 |
| D | 0.0042 | 2 | 0.0021 | 137.2908 | 4.63 | 0.001 |
| A*B | 0.0299 | 4 | 0.0075 | 487.0396 | 3.34 | 0.001 |
| A*C | 0.0011 | 4 | 0.0003 | 18.7203 | 3.34 | 0.001 |
| A*D | 0.0023 | 4 | 0.0006 | 37.6651 | 3.34 | 0.001 |
| B*C | 0.0111 | 4 | 0.0028 | 180.8323 | 3.34 | 0.001 |
| B*D | 0.0089 | 4 | 0.0022 | 145.2168 | 3.34 | 0.001 |
| C*D | 0.0054 | 4 | 0.0014 | 88.2663 | 3.34 | 0.001 |
| A*B*C | 0.0035 | 8 | 0.0004 | 28.5094 | 2.54 | 0.001 |
| A*B*D | 0.0057 | 8 | 0.0007 | 46.3647 | 2.54 | 0.001 |
| A*C*D | 0.0021 | 8 | 0.0003 | 16.8971 | 2.54 | 0.001 |
| B*C*D | 0.0091 | 8 | 0.0011 | 74.5020 | 2.54 | 0.001 |
| A*B*C*D | 0.0054 | 16 | 0.0003 | 21.9714 | 2.02 | 0.001 |
| Error | 0.0111 | 729 | 0.000015 | 0.001 | ||
| Total | 137.541611 | 810 | ||||
| Corrected total | 0.2683 | 809 |
| Source | Sum of Squares | Degrees of Freedom | Mean Square | F0 | Critical F-Value | p-Value |
|---|---|---|---|---|---|---|
| Corrected model | 13,911,032,716 | 161 | 86,403,930 | 150.21 | 1.30 | <0.001 |
| A | 412,293,172 | 2 | 206,146,586 | 358.37 | 4.62 | <0.001 |
| B | 7,992,509,380 | 2 | 3,996,254,690 | 6.947.23 | 4.62 | <0.001 |
| C | 41,990,097 | 2 | 20,995,049 | 36.50 | 4.62 | <0.001 |
| D | 15,632,602 | 2 | 7,816,301 | 13.59 | 4.62 | <0.001 |
| E | 328,077,415 | 1 | 328,077,415 | 570.34 | 6.65 | <0.001 |
| A*B | 2,364,612,193 | 4 | 591,153,048 | 1.027.68 | 3.33 | <0.001 |
| A*C | 7,282,311 | 4 | 1,820,578 | 3.16 | 3.33 | 0.0133 |
| A*D | 25,733,378 | 4 | 6,433,345 | 11.18 | 3.33 | <0.001 |
| A*E | 520,672,109 | 2 | 260,336,055 | 452.58 | 4.62 | <0.001 |
| B*C | 209,302,505 | 4 | 52,325,626 | 90.96 | 3.33 | <0.001 |
| B*D | 101,910,484 | 4 | 25,477,621 | 44.29 | 3.33 | <0.001 |
| B*E | 473,508,631 | 2 | 236,754,315 | 411.58 | 4.62 | <0.001 |
| C*D | 39,934,322 | 4 | 9,983,580 | 17.36 | 3.33 | <0.001 |
| C*E | 9145 | 2 | 4573 | 0.01 | 4.62 | 0.9921 |
| D*E | 1,815,506 | 2 | 907,753 | 1.58 | 4.62 | 0.2067 |
| A*B*C | 45,711,657 | 8 | 5,713,957 | 9.93 | 2.52 | <0.001 |
| A*B*D | 66,943,077 | 8 | 8,367,885 | 14.55 | 2.52 | <0.001 |
| A*B*E | 1,072,857,009 | 4 | 268,214,252 | 466.27 | 3.33 | <0.001 |
| A*C*D | 12,629,858 | 8 | 1,578,732 | 2.74 | 2.52 | 0.052 |
| A*C*E | 1,495,401 | 4 | 373,850 | 0.65 | 3.33 | 0.6270 |
| A*D*E | 1,572,184 | 4 | 393,046 | 0.68 | 3.33 | 0.6035 |
| B*C*D | 64,934,599 | 8 | 8,116,825 | 14.11 | 2.52 | <0.001 |
| B*C*E | 3,206,424 | 4 | 801,606 | 1.39 | 3.33 | 0.2339 |
| B*D*E | 5,710,233 | 4 | 1,427,558 | 2.48 | 3.33 | 0.0421 |
| C*D*E | 4,991,511 | 4 | 1,247,878 | 2.17 | 3.33 | 0.0703 |
| A*B*C*D | 67,054,074 | 16 | 4,190,880 | 7.29 | 2.01 | <0.001 |
| A*B*C*E | 2,900,395 | 8 | 362,549 | 0.63 | 2.52 | 0.7529 |
| A*B*D*E | 4,448,855 | 8 | 556,107 | 0.97 | 2.52 | 0.4603 |
| A*C*D*E | 6,944,575 | 8 | 868,072 | 1.51 | 2.52 | 0.1491 |
| B*C*D*E | 3,755,594 | 8 | 469,449 | 0.82 | 2.52 | 0.5883 |
| A*B*C*D*E | 10,594,022 | 16 | 662,126 | 1.15 | 2.01 | 0.3016 |
| Error | 838,684,685 | 1458 | 575,230 | |||
| Total | 101,510,801,041 | 1620 | ||||
| Corrected total | 14,749,717,401 | 1619 |
| Source | Sum of Squares | Degrees of Freedom | Mean Square | F0 | Critical F-Value | p-Value |
|---|---|---|---|---|---|---|
| Corrected model | 14,818.88 | 161 | 92.04 | 265.80 | 1.30 | <0.001 |
| A | 121.38 | 2 | 60.69 | 175.26 | 4.62 | <0.001 |
| B | 6109.51 | 2 | 3054.76 | 8821.63 | 4.62 | <0.001 |
| C | 108.99 | 2 | 54.49 | 157.37 | 4.62 | <0.001 |
| D | 71.38 | 2 | 35.69 | 103.07 | 4.62 | <0.001 |
| E | 531.58 | 1 | 531.58 | 1535.11 | 6.65 | <0.001 |
| A*B | 3362.91 | 4 | 840.73 | 2427.88 | 3.33 | <0.001 |
| A*C | 24.51 | 4 | 6.13 | 17.70 | 3.33 | <0.001 |
| A*D | 48.97 | 4 | 12.24 | 35.36 | 3.33 | <0.001 |
| A*E | 770.26 | 2 | 385.13 | 1112.19 | 4.62 | <0.001 |
| B*C | 328.27 | 4 | 82.07 | 237.00 | 3.33 | <0.001 |
| B*D | 212.59 | 4 | 53.15 | 153.48 | 3.33 | <0.001 |
| B*E | 738.58 | 2 | 369.29 | 1066.44 | 4.62 | <0.001 |
| C*D | 88.68 | 4 | 22.17 | 64.03 | 3.33 | <0.001 |
| C*E | 1.22 | 2 | 0.61 | 1.76 | 4.62 | 0.1722 |
| D*E | 0.21 | 2 | 0.10 | 0.30 | 4.62 | 0.7419 |
| A*B*C | 94.29 | 8 | 11.79 | 34.04 | 2.52 | <0.001 |
| A*B*D | 121.78 | 8 | 15.22 | 43.96 | 2.52 | <0.001 |
| A*B*E | 1743.23 | 4 | 435.81 | 1258.54 | 3.33 | <0.001 |
| A*C*D | 24.96 | 8 | 3.12 | 9.01 | 2.52 | <0.001 |
| A*C*E | 2.59 | 4 | 0.65 | 1.87 | 3.33 | 0.1136 |
| A*D*E | 2.02 | 4 | 0.50 | 1.45 | 3.33 | 0.2136 |
| B*C*D | 162.18 | 8 | 20.27 | 58.54 | 2.52 | <0.001 |
| B*C*E | 6.09 | 4 | 1.52 | 4.39 | 3.33 | 0.0016 |
| B*D*E | 4.28 | 4 | 1.07 | 3.09 | 3.33 | 0.0152 |
| C*D*E | 3.66 | 4 | 0.92 | 2.64 | 3.33 | 0.0322 |
| A*B*C*D | 105.30 | 16 | 6.58 | 19.01 | 2.01 | <0.001 |
| A*B*C*E | 5.01 | 8 | 0.63 | 1.81 | 2.52 | 0.0716 |
| A*B*D*E | 4.05 | 8 | 0.51 | 1.46 | 2.52 | 0.1664 |
| A*C*D*E | 5.78 | 8 | 0.72 | 2.09 | 2.52 | 0.0343 |
| B*C*D*E | 4.63 | 8 | 0.58 | 1.67 | 2.52 | 0.1010 |
| A*B*C*D*E | 10.02 | 16 | 0.63 | 1.81 | 2.01 | 0.0255 |
| Error | 504.88 | 1458 | 0.35 | |||
| Total | 536.83 | 1620 | ||||
| Corrected total | 15,323.75 | 1619 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Palominos, P.; Moncada, G.; Fuertes, G.; Quezada, L. Quantitative Analysis of Manufacturing Flexibility and Inventory Management: Impact on Total Flow Time in Production System. Mathematics 2026, 14, 202. https://doi.org/10.3390/math14010202
Palominos P, Moncada G, Fuertes G, Quezada L. Quantitative Analysis of Manufacturing Flexibility and Inventory Management: Impact on Total Flow Time in Production System. Mathematics. 2026; 14(1):202. https://doi.org/10.3390/math14010202
Chicago/Turabian StylePalominos, Pedro, German Moncada, Guillermo Fuertes, and Luis Quezada. 2026. "Quantitative Analysis of Manufacturing Flexibility and Inventory Management: Impact on Total Flow Time in Production System" Mathematics 14, no. 1: 202. https://doi.org/10.3390/math14010202
APA StylePalominos, P., Moncada, G., Fuertes, G., & Quezada, L. (2026). Quantitative Analysis of Manufacturing Flexibility and Inventory Management: Impact on Total Flow Time in Production System. Mathematics, 14(1), 202. https://doi.org/10.3390/math14010202

