Next Article in Journal
A Microbial Screening in Silico Method for the Fitness Step Evaluation in Evolutionary Algorithms
Next Article in Special Issue
A Clustering-Based Bubble Method for Generating High-Quality Tetrahedral Meshes of Geological Models
Previous Article in Journal
Application of Adaptive Tuned Magneto-Rheological Elastomer for Vibration Reduction of a Plate by a Variable-Unbalance Excitation
Previous Article in Special Issue
Influence of Tunnel Boring Machine (TBM) Advance on Adjacent Tunnel during Ultra-Rapid Underground Pass (URUP) Tunneling: A Case Study and Numerical Investigation
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Deformation Characteristics and Control Method of Kilometer-Depth Roadways in a Nickel Mine: A Case Study

1
Key Laboratory of Shale Gas and Geoengineering, Institute of Geology and Geophysics, Chinese Academy of Sciences, Beijing 100029, China
2
Innovation Academy for Earth Science, CAS, Beijing 100029, China
3
University of Chinese Academy of Sciences, Beijing 100049, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2020, 10(11), 3937; https://doi.org/10.3390/app10113937
Submission received: 14 April 2020 / Revised: 6 May 2020 / Accepted: 18 May 2020 / Published: 5 June 2020
(This article belongs to the Special Issue Advances in Geotechnical Engineering)

Abstract

:
Deformation failure and support methods of roadways have always been critical issues in mining production and safety, especially for roadways buried in complex engineering geological conditions. To resolve these support issues of kilometer-depth roadways under high ground stress and broken rock mass, a case study on the roadways in the No. 2 mining area of Jinchuan Mine, China, is presented in this paper. Based on a detailed field survey, the deformation characteristics of the roadways and failure modes of supporting structures were investigated. It was found that the horizontal deformations were serious, and the primary support was not able to control the surrounding rock well. Additionally, a broken rock zone test was carried out, which indicated that a zonal disintegration phenomenon occurred around the roadways and the maximum depth of the fractured zone was more than 4.8 m. In order to effectively limit the deformation in the roadways, a new support scheme called the “multistage anchorage + concrete-filled steel tube” was put forward. To further assess the support behavior of the new method, we selected a test roadway in the research area, and numerical simulations and in-situ monitoring were conducted. The findings suggest that the roadway’s serious deformation under high ground stress and broken rock mass could be successfully controlled by the new control method, which can provide a reference for other engineering solutions under similar geological conditions.

1. Introduction

Due to fast economic growth, the status of mineral resources in the national economy and the need for mineral resources has been increasing. In mining production, controlling roadway deformation is an important task for maintaining enduring and effective supports that directly affect safety and high-efficient production. Controlling roadway deformation using appropriate support measures has become a critically important focus area in the study of rock mechanics and mining [1].
Recently, the deformation characteristics of roadways have been a hot research topic and have received considerable attention. Coggan et al. [2] and Huang et al. [3] investigated the effect of a soft interlayer on the deformation of roadways. They found that the weak interlayer had an important effect on the degree of failure, causing asymmetrical stress. Tu et al. [4] presented a mechanical roadway model based on a theoretical analysis and predicted the stress distribution around the roadway. Yan et al. [5] explored the fault’s influence on the deformation mechanism of a roadway and found that roadway convergence increased with activation of the fault. Furthermore, Yu et al. [6] studied the deformation laws in a goaf heading face based on a numerical simulation and field survey method. Chang et al. [7] and Gao et al. [8] discussed the characteristics of roadway deformations. They pointed out that high ground stress, mining-induced stress and low strength rock cause large deformation of roadways. Chen et al. [9], Kang et al. [10] and Yang et al. [11] used numerical simulations to investigate a deep roadway’s deformation failure characteristics, including Universal Distinct Element Code (UDEC), Fast Lagrangian Analysis of Continua in 3 Dimensions (FLAC3D) and LDEAS 1.0. Moreover, Shen [12] divided roadway failures into roof sags, rock falls, beam failures, rib failures, skin failures and shearing failures.
Meanwhile, traditional supporting methods, such as the use of spray-bolt-mesh, can no longer effectively control the large deformation of roadways under high geo-stress and broken rock mass. Researchers are thus paying more attention to the development of new materials and combined support schemes.
He et al. [13] and Sun et al. [14] developed bolts with a constant resistance; Li et al. [15] found a high-strength cable; Srivastava and Singh [16] developed a grouted bolt; and Gao et al. [17], Li et al. [18] and Zhang et al. [19] proposed round, square, and D-shaped concrete-filled steel tubes. Furthermore, Aksoy et al. [20] put forward a non-deformable support system (NDSS). Shen et al. [21] experimentally analyzed the characteristics of five concrete-filled steel tube arches used in deep roadways based on theory and numerical simulation. Additionally, Yang et al. [22] presented a support method, including double-layer-truss and bolt-mesh-cable, which can effectively control rheological deformation. Guo et al. [1] designed a coupled truss support scheme including anchors, anchor bolts, and shotcrete. Moreover, Meng et al. [23] used U-shaped steel to limit the floor heave. Wang et al. [24] put forward a novel reinforcement technology (whole section anchor-grouting) for roadways in rock mass with fractures. Lv et al. [25] adopted square steel confined concrete to control surrounding rocks with high stress. Additionally, Lu et al. [26] put forward a highly resistant and yielding support system for long-term control. Barla et al. [27] provided a hybrid system with yielding steel ribs and Yang et al. [11] developed a hybrid system with bolt, cable, mesh, shotcrete and shell.
Although many researchers have studied the deformation and support of roadways which has resulted in a series of achievements, most of the solutions are based on coal mines and many support methods that cannot be widely used because of their high cost. Few studies have been conducted in large metal mines, especially those with a kilometer depth characterized by broken rock mass and high in-situ stresses.
Therefore, the Jinchuan nickel mine in China was selected as the research area in this study and a detailed field investigation into the deformation and support of deep roadways under broken rock mass was performed. We then conducted a broken rock zone test in this area to assess the primary control method’s supporting effect. Moreover, to compensate for its disadvantages, a new hybrid control system with multistage anchorage and a concrete-filled steel tube (CFST) was designed. Numerical calculations using the Fast Lagrangian Analysis of Continua in 3 Dimensions (FLAC3D) were performed for a simulation and comparison of the evolutionary processes of the deformation, as well as the stress of roadways and support structures. Additionally, on-site experiments, field monitoring and economic analyses were performed to assess the new support scheme’s control effect.

2. Geological Environment and Engineering Properties

As China’s biggest nickel production base, Jinchuan Mine is situated in Jinchang City, Gansu Province, as shown in Figure 1. It consists of four mining zones, where the No. 2 mining area has the largest ore body, with an overall length of approximately 3000 m, a surface outcrop length of about 2500 m, a mean breadth of 380 m, and a downward extension of over 1000 m. The No. 2 mining area is situated in the desert at the southern edge of the Chaoshui basin, surrounded by the Longshou mountains in the southwest, as shown in Figure 2. The terrain is rugged, with an average altitude of 1750 m, so the influence of the arid climate and simple hydrogeological conditions is negligible.
This mining area has a rather complicated history with regard to the geological background. It has experienced many geological tectonic activities, such as Indosinian movement, Yanshan movement and Lvliang movement. Many kinds of magma activities are also frequent in this area. The mining area’s main structure consists of monoclines with a southwest tendency, and between the layers folds propagate, frequently forming small anticlines and synclines. These difficult geological conditions, crisscrossed structural surface, weak rock strength and high ground stress all hinder the stability of the rock surrounding the roadway.
In the No. 2 mining area, the current state of the on-site stress is compressive stress, with horizontal stress being the maximum principal stress. In the shallow part, within a depth of about 30 m from the surface, the maximum principal compressive stress is approximately 3 MPa. When the depth increases, the stress value increases. The maximum principal stress reaches 30 MPa and the highest value is 52.2 MPa between a depth of 400 and 800 m. Its direction is mostly NE–NNE, practically vertical to the ore body’s orientation, and there is a large difference between the minimum and maximum principal stress [28,29,30].
A downward filling mining method with a subsection height of 20 m is adopted in the Jinchuan Mine. Each subsection is further divided into five layers with a height of 4 m and the ore body buried at 900 m is the main mining area at present. Trackless transport is used in the stope, so it is necessary to construct transport roadways with large sections. The main object of this study is the transport roadway, which is often a permanent project and needs to provide long-term stable support.

3. Roadway Deformation Characteristics

3.1. Field Test

Conducting a field investigation is a suitable way to understand the deformation failure characteristics of roadways visually and in detail. In this study, it was performed on the Jinchuan No. 2 Mine’s panel (814 m above sea level with a burial depth of approximately 1000 m). To provide tangible data for the adoption of appropriate support measures, the investigation included the rock mass strength, support patterns, ground stress, construction methods and other factors that impact the stability of deep roadways.
There are five main lithology types in the survey area, and Table 1 shows the mechanical and physical parameters of these intact rocks and rock masses. It can be seen that the intact rock has a high strength compared to that of the rock mass. Therefore, the roadway is very weak. Furthermore, the ultrabasic rock mass has better engineering geological conditions than the marble rock mass.
Wu et al. [31] studied the geo-stress in Jinchuan mining for several years, based on a hollow inclusion strain gauge. They measured six points in the study area, and Table 2 displays the stress parameters of each point. It is illustrated that the maximum principal stress reaches 46.6 MPa and the gap between the minimum and maximum principal stress is huge, which indicates a high shear stress.
The test roadway’s initial support was a compound support scheme. It consisted of a bolt-mesh-anchor (double layer) and U-shaped steel, as depicted in Figure 3. The cement mortar anchor rod was constructed with secondary rebar (spacing, 1000 × 1000 mm; length, 2250 mm; diameter, 22 mm). An ordinary steel plate (thickness,10 mm; size, 200 × 200 mm) was utilized to make an anchor plate. Concrete (25 MPa compressive strength) was used for the shotcrete lining, which had a 100 mm thick single layer. U36 steel was used for the U-shaped steel support [32].
Moreover, a judgment criterion, which is named the LG criterion and is used for determining the degree of roadway deformation under the supporting structure is proposed in this paper. If the axial deformation exceeds the distance of the supporting structure by two times or the radial deformation exceeds the maximum elongation of the supporting structure, it is considered severe deformation. The spacing of the supporting structure in this study area is 1 m and the maximum elongation of the bolt is 45 cm. Therefore, a deformation failure point with an axial deformation exceeding 200 cm or radial deformation exceeding 45 cm is defined as severe, based on the LG criterion. Roadways that were about 700 m long were examined and 48 deformation points were found, as shown in Figure 4.

3.2. Deformation Characteristics of Roadways

Figure 5 shows that the roadway deformation failure modes in this area can be sorted into six groups including roof falling, roof cracking, unsymmetrical pressure, floor heaving, side cracking and rib spalling. Additionally, each mode’s occurrence time and the total percentage were calculated, as illustrated in Figure 6 [33].
Based on the figures above, we conducted comprehensive analyses of the field investigation results, and can conclude the following with regard to the roadway’s deformation failure characteristics.

3.2.1. Maximum Principal Stress Plays a Dominant Role

In the research area, the ground stress is very high, while the horizontal stress is three times higher than the vertical stress. Figure 6 shows that the roof cracking, rib spalling and side cracking which are all involved in horizontal stress, account for more than 80% of the total deformation points. When the roadway is under a horizontal squeezing force, the weak structural surfaces in the original rock mass move towards the free face and tension fissures occur if this force surpasses the resistance strength of the supporting body. In particular, as the tunnel direction is vertical to the direction of the principal stress, the deformation of roadways becomes more serious. Moreover, we can see from Figure 4 that the unsymmetrical pressure’s direction is almost accordant with the maximum principal stress’s strike and there is very little roof falling since σ1 is almost horizontal.

3.2.2. Prominent Time Effects

The time effects of the roadway deformation include three aspects: a quick deformation rate in the initial stage, a high deformation speed and a lengthy deformation duration (Figure 7). When the roadway is excavated, unloading of the surrounding rock mass is fierce because of the intensive on-site stress. The deformation occurring during the initial stage is able to account for over 40% of the surrounding rock’s entire deformation, although it only continues for a few weeks. Due to the high ground stress in the research area, the maximum deformation rate can reach more than 6 mm/d, according to the field measurement. Additionally, some roadways fail to achieve stability for a couple of years because the rock mass is generally soft, and the broken rock has significant rheology.

3.2.3. Significant Space Effects

The space effects of the roadway deformation include two aspects, universality and differences. Among the major systems in the study area, including transportation system engineering, segmented mining and quasi engineering, different chamber engineering, and so forth, practically all of the roadways have been deformed and destroyed. In order to meet the production needs, roadways are distributed in different areas, and the deformation and damage of these roadways show obvious differences. In terms of the same area, the roadway’s convergence deformation in the ore body’s upper wall is generally larger than that in the foot wall, and in terms of the same roadway, the amount of horizontal deformation is generally greater than the amount in the vertical direction due to the high horizontal ground stress value.

3.3. Failure Modes of Supporting Structures

Although a combined support is employed to prevent deformation, influenced by high ground stress and broken rock mass, it is still rather common to observe severe failure of the support structure. In the field study, four support failure modes were detected: (1) bolt pulled out and slipped; (2) wire mesh twisted and snapped; (3) shotcrete cracked and extruded; and (4) U-shaped steel extruded and bent. These are depicted in Figure 8.
Most of the failure bolts found in the investigation converged toward the air face of the roadway with the surrounding rock and only a small number were damaged on the steel plate and buried in the rock mas, which indicated that the bolts did not fully function in terms of supporting the surrounding rock. If the bolt length is greater than the fractured surrounding rock’s depth, the end steel plate will be torn instead of being pulled out when the roadway has large convergence deformation. The shotcrete lining was broken and produced a cavity under the effects of severe rib spalling and sidewall squeezing. Based on the failure characteristics, the mechanical principle was shear failure or tension failure. The phenomenon of U-shaped steel being squeezed and bent often happened, especially on the rib spalling’s failure point. It extruded and exposed the surrounding rock, and there was also an entire row of steel arches squeezed on the sidewall foot.

3.4. Rock Mass’s Zonal Disintegration around the Roadways

Excavation of the roadway in the primary rock mass destroyed the original stress balance of the surrounding rock and redistributed the stress. On one hand, its radial stress decreased, and the tangential stress increased, which led to stress concentration. On the other hand, the surrounding rock stress state changed from triaxial to approximately biaxial, and the rock strength decreased. If the concentrated stress was less than the declined rock strength, the surrounding rock would carry itself and maintain an elastic state, that is, the support was unnecessary. Otherwise, the surrounding rock would gradually crack from the periphery to the inside, until it reached another new triaxial stress equilibrium state. At this time, an annular fractured zone occurred around the excavation space, which was the broken rock zone. Owing to the fact that the rock mass’s mechanical properties were seriously influenced by the stress environment, the rock with an elastic state in the shallow part displayed elastic–plastic or plastic deformation characteristics in the deep area, and the convergence deformation mechanism of the deep roadway was quite different from that of the shallow roadway. Hence, the distribution characteristics of the broken rock zone of the deep roadway were more complex, and accurately grasping the range of the broken rock zone was crucial for support selection.
Therefore, four sections in the study area were selected to conduct the broken rock zone test, as shown in Figure 4. Four measurement points were chosen for each section, two points on the spring line and two points on the spandrel. In order to improve the efficiency, a single-emission and double-receiving measurement method based on the ultrasonic wave was adopted, as shown in Figure 9. Waves emitted by the acoustic emission transducer T slid along the wall of the borehole, and they were then refracted back into the holes and received by the receiving transducers R1 and R2. The calculation formula of the rock mass’s longitudinal wave velocity Vp is as follows [34]:
V p = Δ L t 2 t 1 ,
where Δ L is the distance between the two receiving transducers and t1 and t2 are the times when transducers R1 and R2 receive the wave, respectively.
The rock mass integrity is characterized by the integrity coefficient Kv of the rock mass, which is calculated as follows:
K v = ( V p 1 V p 2 ) 2 ,
where Vp1 is the rock mass’s longitudinal wave velocity and Vp2 is the intact rock’s longitudinal wave velocity. The intact marble’s longitudinal wave velocity in the test roadway was approximately 6.5 km/s.
Based on the national standard, which classifies the rock mass in engineering (GB50218-94), the relationship between the rock mass integrity indicators Kv and Vp is shown in Table 3.
Field measurements indicated that the characteristics of the four sections were similar and the results in Section 1 are shown in Figure 10. The rock mass below a medium integrity was considered to be the broken zone in this paper (that is, Kv < 0.55), and the broken rock zone in Section 1 is shown in Figure 11.
The figures above show that zonal disintegration phenomena occurred in the test roadway, which could be divided into three broken zones. The first one was within the range of 0–1.8 m from the roadway surface, with the largest scope and the most serious surrounding rock deformation. It exhibited a close relationship with roof falling and collapsing during the process of roadway excavation. This zone can be considered the broken rock zone in the traditional sense. A depth of about 2–2.8 m represents the second zone. This had a similar length as the 2.25 m bolt, which can explain the bolt failures found in the field survey. The third broken zone appeared at a distance of 3–4.8 m from the surface, and the zone on the spandrels was the largest, which was consistent with the frequent cracking on the spandrels. As the deepest borehole in this test was only 5.1 m, it is not known whether there was another zone with a distance greater than 5.1 m from the roadway. However, the discovery of zonal disintegration was enough to prove that the anchoring method used in the original support was not reasonable and the bolt could not fully play its role, which needed to be further optimized.

4. “Multistage Anchorage System + CFST” Combined Support Technology

4.1. Establishment of the New Support Method

According to the above analysis, the disadvantages of the initial support are as follows:
  • The U-shaped steel strength is insufficient under broken rock and high ground stress, as the steel tended to bend and even began to break, especially on the straight wall foot.
  • Owing to the large fractured zone and zonal disintegration, the surrounding rock was not pierced completely for coupling as the bolts were not sufficiently long, which resulted in a low anchorage force and easy failure.
  • There is no feasible measure to handle the floor deformation where the roadway deformation occurs and gradually develops.
Therefore, to make up for the defects of the initial support method, a “multistage anchorage system + CFST” joint support scheme is presented herein. The compound supporting structure includes a multistage anchorage system (bolt, cable, mesh, shotcrete) and, later, a high-strength rigid supporting structure (CFST). The design of the new support is displayed in Figure 12.

4.1.1. Multistage Anchorage System

The multistage anchorage system in the new support scheme includes short bolts, long bolts, cables and their correlated wire mesh and shotcrete, as follows:
  • Short bolts: 2.25 m full-length mortar bolts, with spacing of 1 m × 2 m, which are applied immediately after the roadway excavation and equipped with a 10 cm concrete spraying layer. The short bolts pass through the first complete rock mass layer, fixing the outermost broken zone to prevent roof falling and collapse during the construction process. This kind of flexible support can also release the original rock stress to some extent, diminishing the pressure for the forthcoming rigid support.
  • Long bolts: 3 m full-length mortar bolts, with spacing of 1 m × 2 m. On the basis of the results of the broken rock zone test, the long bolts are able to pass through two broken zones and one intact zone to reach the second intact zone and fix this part of the rock together to completely exploit the rock mass’s self-bearing capacity.
  • Cables: 7 m, installed on the haunches, spandrels and corners on which large deformations frequently occur, to fully regulate the horizontal deformation of the roadways. Moreover, cables are connected with the surrounding rock reinforced by shallow combined bolts, forming a support system with a strong anti-deformation ability and greatly improving the stability and integrity of the surrounding rock.
Shallow broken surrounding rocks have a poor stress transfer ability. Through the multistage anchoring system, effective superposition of the surrounding rock stress is achieved and the synergistic effect is depicted in Figure 13. The multistage anchoring system combines the roadway surrounding rocks to form a reliable bearing structure. It also fully mobilizes the capacity of deep, stable surrounding rocks and restrains the development of harmful deformation. Engineering practice of the study area is taken into account when the length and raw materials of the bolts and cable are selected. For example, the anchor rod used in the study area is made of spiral steel with a 9 m standard length. Therefore, the bolt length (2.25 and 3 m) can effectively reduce the cost because there is no material waste.

4.1.2. CFST

CFST consisting of steel pipes and filled concrete is a passive support structure used to control roadway stability, especially in the case of terrible geological conditions, such as soft rock mass and high ground stress. The regional stability of the thin-walled steel tube is maintained by the inner concrete. In turn, the tube has a confining effect on the concrete, causing a tri-direction stress state and enhancing its strength. Therefore, the CFST has a high bearing capacity and can better control the surrounding rock mass’s deformation.
The short column’s ultimate bearing capacity (N0) of CFSTs under axial compression can be measured using the following formula [17]:
{ θ = A s f s / ( A c f c ) N 0 = A c f c ( 1 + θ + 1.1 θ ) ,
where Ac is the cross-sectional area of the concrete (23,778 mm2), fc is the strength of the concrete (25 N/mm2), θ is the steel coefficient of the casing hoop, As is the cross-sectional area of the tube (5780 mm2) and fs is the steel material yield limit of 215 N/mm2. Taking a reduction factor of 0.78 into account, the N0 value obtained was 2012 kN.
Moreover, as illustrated in Figure 14, the supporting force (σ) can be calculated by:
s π / 4 π / 2 sin θ σ R d θ = N 0 cos π 4 ,
where s is the steel tubes’ distance and the tube radius is R.
Through substitution, we obtained a result of 0.76 MPa for σ, which is greater than the 0.45 MPa supporting force of the U-shaped steel. Therefore, CFST is a better choice in this study area and makes up for the low strength of the U-shaped steel.
After CFST construction, supporting structures and the surrounding rock mass formed a hierarchical support system that cooperated and worked together to deal with roadway deformation, that is, the spray layer and the CFST formed the first level, which provided a normal constrained force for the surrounding rock on the face of the roadways. The bolt’s second level improved the shallow broken rock mass’s performance and the third level was formed of cables, which developed a continuous bearing structure through effectively connecting the shallow fractured rock and the deep intact rock.

4.2. Numerical Simulations

The numerical simulation test was conducted using FLAC3D, so as to verify the new support method’s supporting effect. As this software is good at simulating large deformation and the progressive failure process, it was selected herein.

4.2.1. Constitutive Models

Yang et al. [22] suggested that the surrounding rock’s strength parameters will be noticeably nonlinearly decreased in an excavation. This is due to the micro-crack’s constant expansion in the rock (i.e., strain-softening). When the peak strength is reached, the deterioration phenomenon will be more obvious when the deformation is still increasing. Yan et al. [5] and Yang et al. [11] found that the widely used material parameters in the Mohr–Coulomb model are preset constants, failing to show the surrounding rock’s softening effect due to the variation of surrounding rock parameters. The failure criterion of Mohr–Coulomb, as well as the element’s stress–strain relation in the strain-softening model, are illustrated in Figure 15 and Figure 16. Following Zhang et al. [19], in the elastic phase, it can be observed that the element strain is merely elastic strain (ε_e), that is,
ε = ε e .
The element strain comprises elastic strain ( ε e ) and plastic strain ( ε p ) when it is going to yield, that is,
ε = ε e + ε p .
The element yield function is,
{ f t = σ 3 σ t f s = σ 1 σ 3 N φ + 2 c N φ ,
where f s = 0 is the shear failure, f t = 0 is the tensile failure, σ 1 , σ 2 is the maximum and minimum principal stress, respectively, σ t is the tensile strength, C is the cohesion, φ is the internal friction angle and N φ = ( 1 + sin φ ) / ( 1 sin φ ) .
Therefore, the strain-softening model is used herein to depict the weak rock’s nonlinear mechanical properties around the roadway.

4.2.2. Numerical Models

On the basis of the test roadway’s practical standard size, a numerical model is constructed, as shown in Figure 17. The model dimension was 60 m × 20 m × 60 m (length × width × height). There were 199,080 grid points and 192,000 zones in the model. We set the displacement boundary in six different directions to regulate the normal displacement and applied the triaxial ground stresses in the model based on Table 2. Table 1 shows the marble rock mass’s mechanical parameters in the test roadway. On the basis of the software’s structural unit, the support structures were simulated: the beam unit was simulated for CFST, the cable unit was simulated for the bolt and cable, and the shell unit was simulated for the concrete spray layer. Each support structure’s detailed parameters are referenced in Li et al. [33].

4.2.3. Simulation Results

In order to highlight the effect of the new support scheme, a comparative test was carried out to simulate the deformation of a roadway without support.
When a roadway is excavated without support, the simulation calculation cannot converge or balance, and the surrounding rock deformation will continue. Figure 18 and Figure 19 show the results of the 5000 step calculation. It can be seen that the deformation of a roadway surrounding rocks is large, with the deformation on the two sides exceeding 70 cm and the deformation on the top and bottom exceeding 60 cm. A wide range of surrounding rock is affected by the roadway excavation and the distribution of the plastic zone is roughly an ellipse, with a long axis radius of 15 m and a short axis radius of 12 m. The direction of the long axis is nearly parallel to the Z axis, which is closely related to the great horizontal ground stress. The surrounding rocks in the plastic zone all experienced a shear yield state, and the surrounding rocks in the depth range of 2 m from the roadway surface experienced a tensile shear state, which is very unfavorable for the stability of the roadway.
Figure 20 depicts the simulation results of the surrounding rock mass’s horizontal and vertical displacement under the new support scheme.
It can be seen that the new support method can effectively control the roadway’s convergence deformation. Especially in the vertical direction, the vault and floor’s maximum deformation is only about 2 and 1.8 cm, respectively, and the scope of the deformation influence is rather small. Meanwhile, a 4 cm cumulative deformation appears on both sides, which is also an acceptable deformation in a deep roadway.
Figure 21 displays the surrounding rock’s plastic zone distribution. Around the roadway, the plastic zone has a uniform distribution, and the maximum influence distance is approximately 2 m on the two sides and 3 m on the vault and floor. Moreover, tension shear failure only took place on the roadway surface and nearly became stable. All of the numerical simulation results suggest the effectiveness of the new support scheme’s control effect.

4.3. Field Monitoring

Except for numerical simulations, the surface convergence of the tentative roadway and the deformation of the CFST was monitored after the new support method had been applied. We chose five convergence monitoring sections (spacing = 10 m) in the tentative roadway and selected six monitoring points for each section. Only horizontal convergence was measured because the previous analysis showed that horizontal deformation was serious in the study area. Moreover, six CFSTs were selected, and four steel string strain gages were installed in each of these. The measurements lasted nearly 500 days and more than 20 groups of data were obtained.
The average displacement curves of the surrounding rocks after maintenance are shown in Figure 22a, from which it is possible to see that the roadway shrank rapidly in the first 80 days and deformation then attenuated, after which it tended to become stable after about 320 days. At the last measurement, the two sides moved close to 75 to 90 mm, which is in agreement with the results of the numerical simulation. Moreover, Figure 22b reveals that the displacement of the CSFTs increased with time and the maximum deformation occurring on the left was only about 28 mm, which indicates that the tubes supply a support force and remain stable after more than 400 days.
The results of the numerical simulation and field monitoring and the photographs of the tentative roadway before and after the novel support scheme (depicted in Figure 23), show that the improved support “multistage anchorage + CFST” is able to control the surrounding rock’s deformation in the deep roadway under high ground stress and broken rock mass and ensure that the roadway is stable.

5. Conclusions

This paper has discussed a case study on the characteristics of deformation and the control technology of deep roadways under broken high ground stress and rock mass in Jinchuan No. 2 Mine. On the basis of a detailed field investigation, the deformation failure types and characteristics in the roadway under primary support have been outlined. Additionally, a numerical simulation and field monitoring were performed to assess the influence of the improved support in the test roadway. The main conclusions of the research are as follows:
(1)
The roadway deformation failure types could be sorted into six types, including roof cracking, floor heaving, unsymmetrical pressure, roof falling, side cracking and rib spalling, among which rib spalling is the most severe. Moreover, the main features of roadway deformation include prominent time effects and significant space effects, and the maximum principal stress plays a dominant role.
(2)
The broken rock zone test found that zonal disintegration phenomena occur in the test roadway and there are three broken rock zones whose depths are approximately 0–1.8, 2–2.8, and 3–4.8 m. The zonal disintegration proves that the anchoring method used in the original support is not feasible.
(3)
An improved combined supporting scheme called the “multistage anchorage + CFST” has been put forward and assessed. The supporting structures and surrounding rock mass formed a hierarchical support system which could cooperate and work together. The results of the numerical simulation and field monitoring indicate the effectiveness of the new support scheme’s control effect.

Author Contributions

Data curation, G.L.; Formal analysis, G.L., H.Z. and F.M.; Methodology, G.L., and F.M.; Software, G.L. and J.G.; Writing—original draft, G.L. and J.G. All authors have read and agreed to the published version of the manuscript.

Funding

The research was funded by the National Natural Science Foundation of China (Grant Nos. 41831293, 41877274, and 41772341). Grateful appreciation is expressed for the support.

Acknowledgments

The authors would like to express their sincere gratitude to Jinchuan mine for their data supports. In addition, the authors are grateful to assigned editor and three anonymous reviewers for their enthusiastic help and valuable comments which have greatly improved this paper.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Guo, Z.; Yang, X.; Bai, Y.; Zhou, F.; Li, E.; Guo, Z.; Yang, X.; Bai, Y.; Zhou, F.; Li, E. A study of support strategies in deep soft rock: The horsehead crossing roadway in Da qiang coal mine. Int. J. Min. Sci. Technol. 2012, 22, 665–667. [Google Scholar] [CrossRef]
  2. Coggan, J.; Gao, F.; Stead, D.; Elmo, D. Numerical modelling of the effects of weak immediate roof lithology on coal mine roadway stability. Int. J. Coal Geol. 2012, 90, 100–109. [Google Scholar] [CrossRef]
  3. Huang, F.; Zhu, H.H.; Zhu, Q.W.; Xu, Q.W. The effect of weak interlayer on the failure pattern of rock mass around tunnel-Scaled model tests and numerical analysis. J. Tunn. Undergr. Space Technol. 2013, 35, 207–218. [Google Scholar] [CrossRef]
  4. Hong-sheng, T.; Shi-hao, T.; Chen, W.; Ding-yi, H.; De-fu, Z. Mechanical analysis of a vertical-wall, semicircular-arch roadway and a repair technique using double-shell support. Environ. Earth Sci. 2018, 77, 509. [Google Scholar] [CrossRef]
  5. Yan, S.; Bai, J.B.; Li, W.F.; Chen, J.G.; Li, L. Deformation mechanism and stability control of roadway along a fault subjected to mining. Int. J. Min. Sci. Technol. 2012, 22, 559–565. [Google Scholar] [CrossRef]
  6. Yu, Y.; Bai, J.; Wang, X.; Zhang, L. Control of the Surrounding Rock of a Goaf-Side Entry Driving Heading Mining Face. Sustainability 2020, 12, 2623. [Google Scholar] [CrossRef] [Green Version]
  7. Chang, Q.L.; Zhou, H.Q.; Xie, Z.H.; Shen, S.P. Anchoring mechanism and application of hydraulic expansion bolts used in soft rock roadway floor heave control. Int. J. Min. Sci. Technol. 2013, 23, 323–328. [Google Scholar] [CrossRef]
  8. Gao, F.Q.; Stead, D.; Kang, H.P. Numerical simulation of squeezing failure in a coal mine roadway due to mining-induced stresses. Rock Mech. Rock Eng. 2015, 48, 1635–1645. [Google Scholar] [CrossRef]
  9. Chen, X.; Guo, H.; Zhao, P.; Peng, X.; Wang, S. Numerical modeling of large deformation and nonlinear frictional contact of excavation boundary of deep soft rock tunnel. J. Rock Mech. Geotech. Eng. 2011, 3, 421–428. [Google Scholar]
  10. Kang, Y.S.; Liu, Q.S.; Xi, H.L. Numerical analysis of THM coupling of a deeply buried roadway passing through composite strata and dense faults in a coal mine. Bull. Eng.Geol. Environ. 2014, 73, 77–86. [Google Scholar] [CrossRef]
  11. Yang, S.Q.; Chen, M.; Jing, H.W.; Chen, K.F.; Meng, B. A case study on large deformation failure mechanism of deep soft rock roadway in Xin’An coal mine, China. Eng. Geol. 2017, 217, 89–101. [Google Scholar] [CrossRef]
  12. Shen, B.T. Coal mine roadway stability in soft rock: A case study. Rock Mech. Rock Eng. 2014, 47, 2225–2238. [Google Scholar] [CrossRef]
  13. He, M.C.; Guo, Z.B. Mechanical properties and engineering application of anchor bolt with constant resistance and large deformation. Chin. J. Rock Mech. Eng. 2014, 33, 1297–1308. [Google Scholar]
  14. Sun, X.M.; Wang, D.; Wang, C.; Liu, X.; Zhang, B.; Liu, Z.Q. Tensile properties and application of constant resistance and large deformation bolts. Chin. J. Rock Mech. Eng. 2014, 33, 1765–1771. [Google Scholar]
  15. Li, S.C.; Shao, X.; Jiang, B.; Wang, Q.; Wang, F.Q.; Ren, Y.X.; Wang, D.C.; Ding, G.L. Study of the mechanical characteristics and influencing factors of concrete arch confined by square steel set in deep roadways. J. Chin. Univ. Min. Technol. 2015, 44, 400–408. [Google Scholar]
  16. Srivastava, L.P.; Singh, M. Effect of fully grouted passive bolts on joint shear strength parameters in a blocky mass. Rock Mech. Rock Eng. 2015, 48, 1197–1206. [Google Scholar] [CrossRef]
  17. Gao, Y.F.; Wang, B.; Wang, J. Test on structural property and application of concrete-filled steel tube support of deep mine and soft rock roadway. Chin. J. Rock Mech. Eng. 2010, 29, 2604–2609. (In Chinese) [Google Scholar]
  18. Li, S.C.; Wang, Q.; Li, W.T.; Wang, D.C.; Li, Z.; Jiang, B.; Wang, H.P.; Wang, H.T. Comparative field test study of pressure relief anchor box beam support system in deep thick top coal roadway. Chin. J. Rock Mech. Eng. 2012, 31, 656–666. [Google Scholar]
  19. Zhang, J.; Liu, L. R & D and application of curved D-shape concrete-filled steel tube support in roadway support. Geotech. Geol. Eng. 2018, 36, 551–566. [Google Scholar]
  20. Aksoy, C.O.; Ogul, K.; Topal, I.; Ozer, S.C.; Ozacar, V.; Posluk, E. Numerical modeling of non-deformable support in swelling and squeezing rock. Int. J. Rock Mech. Min. Sci. 2012, 52, 61–70. [Google Scholar] [CrossRef]
  21. Shen, J.; Huang, W.; Yang, X.; Shi, J.; Zheng, K. Stressing State Analysis of CFST Arch Supports in Deep Roadway Based on NSF Method. Appl. Sci. 2019, 9, 4238. [Google Scholar] [CrossRef] [Green Version]
  22. Yang, J.; Wang, D.; Shi, H.Y.; Xu, H.C. Deformation failure and countermeasures of deep tertiary extremely soft rock roadway in Liuhai coal mine. Int. J. Min. Sci. Technol. 2015, 25, 231–236. [Google Scholar] [CrossRef]
  23. Meng, Q.; Han, L.; Chen, Y.; Fan, J.; Wen, S.; Yu, L.; Li, H. Influence of dynamic pressure on deep underground soft rock roadway support and its application. Int. J. Min. Sci. Technol. 2016, 26, 903–912. [Google Scholar] [CrossRef]
  24. Wang, F.T.; Zhang, C.; Wei, S.F.; Zhang, X.G.; Guo, S.H. Whole section anchor-grouting reinforcement technology and its application in underground roadways with loose and fractured surrounding rock. Tunn. Undergr. Space Technol. 2016, 51, 133–143. [Google Scholar]
  25. Lv, Z.; Qin, Q.; Jiang, B.; Luan, Y.; Yu, H. Comparative study on the mechanical mechanism of confined concrete supporting arches in underground engineering. PLoS ONE 2018, 13, e0191935. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  26. Lu, Y.L.; Wang, L.G.; Zhang, B. An experimental study of a yielding support for roadways constructed in deep broken soft rock under high stress. Min. Sci. Technol. 2011, 21, 839–844. [Google Scholar] [CrossRef]
  27. Barla, G.; Bonini, M.; Semeraro, M. Analysis of the behaviour of a yield-control support system in squeezing rock. Tunn. Undergr. Space Technol. 2011, 26, 146–154. [Google Scholar] [CrossRef]
  28. Zhao, H.; Ma, F.; Zhang, Y.; Guo, J. Monitoring and mechanisms of ground deformation and ground fissures induced by cut-and-fill mining in the Jinchuan Mine 2, China. Environ. Earth Sci. 2013, 68, 1903–1911. [Google Scholar] [CrossRef]
  29. Ma, F.; Zhao, H.; Yuan, R.; Guo, J. Ground movement resulting from underground backfill mining in a nickel mine (Gansu Province, China). Nat. Hazards 2015, 77, 1475–1490. [Google Scholar] [CrossRef]
  30. Lu, R.; Ma, F.; Guo, J.; Zhao, H. Analysis and monitoring of roadway deformation mechanisms in nickel mine, China. Concurr. Comput. Pract. Exper. 2018, 31, e4832. [Google Scholar] [CrossRef]
  31. Wu, M.L.; Ma, Y.; Liao, C.T. Study on recent state of stress in depth 1 000 m of Jinchuan mine. Chin. J. Rock Mech. Eng. 2008, 27 (Suppl. 2), 3785–3790. (In Chinese) [Google Scholar]
  32. Li, G.; Ma, F.; Liu, G.; Zhao, H.; Guo, J. A Strain-Softening Constitutive Model of Heterogeneous Rock Mass Considering Statistical Damage and Its Application in Numerical Modeling of Deep Roadways. Sustainability 2019, 11, 2399. [Google Scholar] [CrossRef] [Green Version]
  33. Li, G.; Ma, F.; Guo, J.; Zhao, H.; Liu, G. Study on deformation failure mechanism and support technology of deep soft rock roadway. Eng. Geol. 2020, 264, 105262. [Google Scholar] [CrossRef]
  34. Liu, Y.; Ye, Y.; Wang, Q.; Liu, X.; Wang, W. Predicting the Loose Zone of Roadway Surrounding Rock Using Wavelet Relevance Vector Machine. Appl. Sci. 2019, 9, 2064. [Google Scholar] [CrossRef] [Green Version]
Figure 1. Engineering geological background of the Jinchuan Mine. (a) Jinchuan Mine’s location and geology. (b) Jinchuan No.2 Mine’s geological section along an exploratory line.
Figure 1. Engineering geological background of the Jinchuan Mine. (a) Jinchuan Mine’s location and geology. (b) Jinchuan No.2 Mine’s geological section along an exploratory line.
Applsci 10 03937 g001
Figure 2. Tectonic map of Jinchuan.
Figure 2. Tectonic map of Jinchuan.
Applsci 10 03937 g002
Figure 3. Primary support method used in the test roadway.
Figure 3. Primary support method used in the test roadway.
Applsci 10 03937 g003
Figure 4. Field investigation of the panel at the burial depth of approximately 1000 m.
Figure 4. Field investigation of the panel at the burial depth of approximately 1000 m.
Applsci 10 03937 g004
Figure 5. Deformation failure modes: (a) Unsymmetrical pressure, (b) Roof falling, (c) Roof cracking, (d) Floor heaving, (e) Side cracking, (f) Rib spalling.
Figure 5. Deformation failure modes: (a) Unsymmetrical pressure, (b) Roof falling, (c) Roof cracking, (d) Floor heaving, (e) Side cracking, (f) Rib spalling.
Applsci 10 03937 g005
Figure 6. Times and percentage of various failure modes.
Figure 6. Times and percentage of various failure modes.
Applsci 10 03937 g006
Figure 7. A typical convergence rate–time curve of studied roadways.
Figure 7. A typical convergence rate–time curve of studied roadways.
Applsci 10 03937 g007
Figure 8. Support failure modes: (a) Bolt pulled out and slipped, (b) Wire mesh twisted and snapped, (c) Shotcrete cracked and extruded, (d) U-shaped steel extruded and bent.
Figure 8. Support failure modes: (a) Bolt pulled out and slipped, (b) Wire mesh twisted and snapped, (c) Shotcrete cracked and extruded, (d) U-shaped steel extruded and bent.
Applsci 10 03937 g008
Figure 9. Operation principle of the single-emission and double-receiving measurement method.
Figure 9. Operation principle of the single-emission and double-receiving measurement method.
Applsci 10 03937 g009
Figure 10. Longitudinal wave velocity curves in Section 1. (a) Measurement points on the spring line. (b) Measurement points on the spandrel.
Figure 10. Longitudinal wave velocity curves in Section 1. (a) Measurement points on the spring line. (b) Measurement points on the spandrel.
Applsci 10 03937 g010
Figure 11. The zonal disintegration monitored in Section 1.
Figure 11. The zonal disintegration monitored in Section 1.
Applsci 10 03937 g011
Figure 12. New support scheme layout.
Figure 12. New support scheme layout.
Applsci 10 03937 g012
Figure 13. Synergistic effect of the multistage anchorage system.
Figure 13. Synergistic effect of the multistage anchorage system.
Applsci 10 03937 g013
Figure 14. Mechanical model of a concrete-filled steel tube (CFST) arched support force schematic.
Figure 14. Mechanical model of a concrete-filled steel tube (CFST) arched support force schematic.
Applsci 10 03937 g014
Figure 15. Failure criterion of Mohr–Coulomb.
Figure 15. Failure criterion of Mohr–Coulomb.
Applsci 10 03937 g015
Figure 16. Element’s stress–strain relation.
Figure 16. Element’s stress–strain relation.
Applsci 10 03937 g016
Figure 17. Numerical model of the initial support.
Figure 17. Numerical model of the initial support.
Applsci 10 03937 g017
Figure 18. The surrounding rock mass’s displacement without the support scheme: (a) Horizontal displacement., (b) Vertical displacement.
Figure 18. The surrounding rock mass’s displacement without the support scheme: (a) Horizontal displacement., (b) Vertical displacement.
Applsci 10 03937 g018
Figure 19. The surrounding rock’s plastic zone distribution without the support scheme.
Figure 19. The surrounding rock’s plastic zone distribution without the support scheme.
Applsci 10 03937 g019
Figure 20. The surrounding rock mass’s displacement under the new support scheme: (a) Horizontal displacement, (b) Vertical displacement.
Figure 20. The surrounding rock mass’s displacement under the new support scheme: (a) Horizontal displacement, (b) Vertical displacement.
Applsci 10 03937 g020
Figure 21. The surrounding rock’s plastic zone distribution under the new support scheme.
Figure 21. The surrounding rock’s plastic zone distribution under the new support scheme.
Applsci 10 03937 g021
Figure 22. Results of the site monitoring: (a) Curves of convergent deformation, (b) Displacement curves of CFST.
Figure 22. Results of the site monitoring: (a) Curves of convergent deformation, (b) Displacement curves of CFST.
Applsci 10 03937 g022
Figure 23. Schematic of the test roadway before and after the novel support scheme: (a) Construction period, (b) Current situation.
Figure 23. Schematic of the test roadway before and after the novel support scheme: (a) Construction period, (b) Current situation.
Applsci 10 03937 g023
Table 1. Mechanical and physical parameters of rocks and rock masses.
Table 1. Mechanical and physical parameters of rocks and rock masses.
LithologyTypeDensity
(g·cm−3)
Tensile Strength
(MPa)
Compressive Strength
(MPa)
Cohesion
(MPa)
Internal Friction Angle
(°)
Elastic Moduli
(GPa)
Poisson’s RatioRMR
MarbleIntact rock2.8611.00104.09.542.064.00.16-
Rock mass2.400.8015.00.735.06.00.2639.56
MigmatiteIntact rock2.739.0951.915.532.055.00.15-
Rock mass2.451.0017.00.835.06.40.2540.27
Ultrabasic rockLherzolite2.9313.00150.011.543.595.00.23-
Rich ore3.029.6073.510.045.070.00.22-
Poor ore3.056.6070.07.043.565.00.31-
Rock mass2.502.2025.00.838.07.00.2443.23
Table 2. Ground stress parameters.
Table 2. Ground stress parameters.
No.Lithologyσ1σ2σ3
Value (MPa)Direction (°)Dip Angle (°)Value (MPa)Direction (°)Dip Angle (°)Value (MPa)Direction (°)Dip Angle (°)
G1Marble42.5434315.898−2711.3171−28
G2Ultrabasic rock43.828−2116.7131−2812.08753
G3Marble46.61936525.389719.1176−25
G4Marble44.42242131.8−45324.2232−68
Table 3. Relationship between the rock mass integrity, Kv and Vp.
Table 3. Relationship between the rock mass integrity, Kv and Vp.
Rock Mass IntegrityExcellentGoodMediumPoorBroken
Kv>0.750.75–0.550.55−0.350.35−0.15<0.15
Vp (km/s)>56305630−48204820−38453845−2517<2517

Share and Cite

MDPI and ACS Style

Li, G.; Ma, F.; Guo, J.; Zhao, H. Deformation Characteristics and Control Method of Kilometer-Depth Roadways in a Nickel Mine: A Case Study. Appl. Sci. 2020, 10, 3937. https://doi.org/10.3390/app10113937

AMA Style

Li G, Ma F, Guo J, Zhao H. Deformation Characteristics and Control Method of Kilometer-Depth Roadways in a Nickel Mine: A Case Study. Applied Sciences. 2020; 10(11):3937. https://doi.org/10.3390/app10113937

Chicago/Turabian Style

Li, Guang, Fengshan Ma, Jie Guo, and Haijun Zhao. 2020. "Deformation Characteristics and Control Method of Kilometer-Depth Roadways in a Nickel Mine: A Case Study" Applied Sciences 10, no. 11: 3937. https://doi.org/10.3390/app10113937

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop