1. Introduction
The problem of determining the favorable inductive influence of surrounding metal installations on the relevant characteristics of power lines passing through urban and/or suburban areas, during normal operation, as well as in fault conditions, was considered for a long time as an unsolvable one in the professional and scientific public. The main reason for this was the objective limitations, i.e., the impossibility of collecting all relevant data concerning many known and unknown underground metal installations situated in the immediate vicinity of these lines. The possibility of determining the actual impedances and other characteristics of power distribution lines appeared for the first time with the appearance and development of contemporary synchrophasor measurement technology. The idea of representing alternating electrical quantities using phasors first appeared back in 1893 in the research publications of the American scientist Ch. P. Steinmetz [
1]. Almost a century later, in 1988, Dr A.G. Phadke and J.S. Thorp from Virginia Polytechnic Institute invented the Phasor Measurement Unit (PMU)),USA. The prototypes were built later in the same institute [
2]. This was soon followed by the progressively increasing use of PMU in power systems, especially for monitoring transmission lines, and it played a significant role in preventing catastrophic failures. Also, a very large number of research papers have been published before achieving the current level of diverse and valuable applications of this tool. For illustration purposes, some of them have been discussed in review papers [
3,
4]. Developed methods based on the synchrophasor measurement can be classified into Two-Point (Dual-PMU) and Single-Point (Pseudo-Two Point) methods. In addition to these, some methods are not based on synchronous measurements (PMUs or µPMUs). They can be classified as Multi-Measurement Regression, Probabilistic, and Data-Driven Methods. All these methods have enabled great progress in monitoring and controlling the operation of large distribution systems. A fundamental application is the sufficiently accurate estimation of line impedance parameters (resistance and reactance). The values of these impedances are important for fault location, state estimation, adaptive protection, and Volt-VAR optimization. To regulate the application of synchrophasor measurements in modern distribution systems, appropriate technical standards have been developed that require a certain level of accuracy of the quantities that define the phasors of alternating voltages and currents [
5,
6].
By using the results of synchronous measurements of voltages and currents at the ends of an HV or EHV cable line, the actual impedances of a cable line under normal operation and fault conditions can be determined directly, that is, by using Ohm’s law, in each concrete case, e.g., ref. [
7]. Certainly, such a way of determining enables taking into consideration the influence of all relevant factors and parameters, including the inductive influence of surrounding metal installations. However, in this way, it is not possible to gain insight into the magnitude of influence and significance of individual relevant factors and parameters. In addition, the cable line characteristics thus obtained in many cases were significantly different from those that could be obtained by the scientific methods known at the time. Because of that, the characteristics of power distribution lines, determined in that way, are without the necessary scientific foundations. Based solely on the results of experimental investigation [
8] and the developed methodology versions [
8,
9,
10,
11,
12], it becomes possible to gain an insight into the factors and parameters that influence the obtained results of synchronous measurements in each concrete case.
One of the effects considered in inductive interaction, the inductive influence of power lines on different nearby metal installations, has been a research subject for over six decades. As a result, hundreds of papers, including national and international directives [
13], have been published. It was necessary to enable determining this influence in different practically possible conditions and circumstances. However, the developed methods were applicable only in a relatively small and limited number of practical cases.
That is mainly the case where a scenario of the right-of-way is relatively simple and where all relevant data are available. However, even in such cases, the problem can be so complex that its solution is impossible without the corresponding software and the possibility of modern computers, e.g., refs. [
14,
15].
The papers [
8,
9,
10,
11,
12] show that the favorable effects of the mentioned interaction are so pronounced that it can be said that Tesla’s alternating currents in urban conditions are significantly more favorable from the following standpoints:
These are better than it was known and utilized before.
The previous versions of the mentioned methodology were based on the introduction of an equivalent cable line sheath, which replaces, from the standpoint of its inductive influence, all surrounding metal installations, including all three metal sheaths of the considered cable line [
9,
10,
11]. This equivalent conductor is defined by two relevant parameters that are necessary to determine in each concrete case. One of them is its longitudinal resistance, while the other is its mean radius. Somewhat later, it is shown that this equivalent conductor/sheath can be substituted by an equivalent sheath but defined by only one relevant parameter. That is its longitudinal resistance [
12]. By introducing these so-called effective sheaths into the previously developed methodology, it is achieved that the considered cable line remains unchanged as seen from the outside. Thanks to this, the determinations of all the effects of the inductive interaction between one cable line and the surrounding metal installations are reduced to the simplest cases, which are solvable using standard and well-known calculation procedures [
13,
16,
17,
18]. It is taken into consideration that HV and EHV cable lines are, as a rule, equipped with applied cross-bonding [
19].
In this paper, it is shown that by using the results of synchronous measurements, as well as the concept of effective sheaths, it is possible to determine the actual characteristics of that line in ground fault conditions, as well as its inductive influence on any of the surrounding metal installations during normal operation and during ground fault conditions. Thanks to this, the results of the simulated ground fault and corresponding test measurements can be substituted with the results of synchronous measurements easily accessible at any time. This is especially important because the surrounding metal installations cannot be considered as something that will remain unchanged. Over time, old and outdated metal installations are abolished, and new ones with the same or similar functions are introduced. For example, nowadays, there is a very pronounced tendency to replace steel water pipes with plastic pipes. Those changes can significantly affect the actual reduction factor of the feeding cable line, that is, the safety conditions within and in the vicinity of the supplied HV substations, and the magnitude of the inductive influence of an HV or EHV cable line. Therefore, the possibility of obtaining timely information about the current value of the reduction factor of each HV or EHV distribution cable line and about its inductive influence is highly desirable.
This methodology enables determining the series and sequential impedances, as well as the actual reduction factor of HV and EHV cable lines and their inductive influence on any of the surrounding metal installations.
It differs from present methods based on synchrophasor measurements because it enables determining the sequential impedances of lines by using measurement results obtained during normal operation. As these results are, as a rule, more accurate and can be obtained at any time, this fact means a certain advantage for the presented methodology in comparison to the present methods. Most importantly, the developed methodology allows for the determination of the actual reduction factor of the power cable line and its inductive influence on any of the surrounding metal installations. This is not possible by using any of the known methods based on synchronous measurements. In view of this, it can be said that the methodology presented here significantly expands the otherwise wide field of applications of synchrophasor measurements, that is, PMUs and micro-PMUs.
Finally, in comparison with its version based on the test measurements during a simulated ground fault, the presented methodology can be applied at any time.
The presented methodology is entirely accurate when the input data on voltages and currents at the ends of a cable line under normal operating conditions are also accurate.
2. Problem Description
Electric power distribution networks delivering electrical energy to large urban agglomerations contain, inter alia, a larger number of HV and EHV cable lines passing through urban and/or suburban areas. These areas are, as is well known, also possessed of various other metal installations typical of urban environments. Distribution cable lines, together with them, share the same space strictly determined by the width of streets and sidewalks along which they are laid. Because of such a strictly defined and narrow space, a fluctuating magnetic field is created by currents in the cable line, which induces a certain electromotive force in each of the surrounding metal installations. In this way, each of the surrounding metal installations grounded at its ends, together with the ground as a common return path, spontaneously forms one electrical circuit while all of them, including those formed by the conductors of the inducing cable line, together form a spacious and complex electric circuit with many inductively and conductively coupled elements. Each of the induced currents creates its own fluctuating magnetic field, which acts in such a way that it reduces the currents in all other elements of this spontaneously formed circuit. As a result, the intensity of the spacious electromagnetic field that is formed around and along each power distribution cable line is also reduced. As a final effect, the need to produce reactive energy and its transmission through the transmission network and the HV and EHV cable lines, as well as the losses of electrical energy caused by its transmission, are reduced. Of course, this effect is very favorable because, to the extent that the transmission of reactive energy is reduced, transmission capacities are released that can be used for increased transmission of useful active energy.
During a ground fault in an HV distribution substation, large currents and raised potentials appear at places where they normally do not exist. At the place of a ground fault, the fault current leaves the phase conductor and returns to the power system by using all available paths. Because of that, a ground-fault current in an HV distribution substation divides into many smaller current flows. However, for the practice in contemporary power distribution companies, only two fractions of the total ground fault currents are of great importance. One of them is dissipated into the surrounding earth through the grounding system of the supplied substation, while the other is induced in the metal installations surrounding the feeding line.
The currents induced in the surrounding metal installations reduce the fraction of the ground fault current dissipated through the grounding system of the supplied substation into the surrounding earth that produces all potential and potential differences (touch and step voltages) relevant for safety conditions within and in the vicinity of this substation. Thus, without correctly determining the value of this current, it is not possible to put the grounding problem of any HV substation into realistic frameworks and find adequate solutions in each concrete case.
However, the voltages and currents induced in the surrounding metal installations during a ground fault, as well as during normal operation, can cause, in the first case, an electric shock to the workers who maintain the metal installations and other people who may touch them, while in the second case, they can be a threat to the integrity of cathodic protection equipment, pipeline coating, or pipeline steel, including their temporary or lasting dysfunction. Also, the voltages and currents induced by an HV or EHV cable line can cause interference to neighboring communication and control systems. Therefore, the permissible magnitude of voltages induced in the surrounding metal installations is strictly determined by the corresponding technical standards, e.g., ref. [
20].
For correct protection from the undesirable consequences, it is necessary to determine, as much as possible, the exact values of the induced voltages and currents, as well as all factors affecting them. However, when we wanted to do this, it was necessary to know all elements of the complete, spontaneously formed electrical circuit and all their relevant parameters. However, usually, only the following was known about the surrounding metal installations:
Their structure and spatial disposition are different from case to case;
Some of them are in direct and continuous contact with the earth;
Due to the mandatory applied TN (terra-neutral) grounding system in the LV networks and consumer installations, some of them are interconnected and grounded at certain places, mainly in each of the buildings arranged along the streets;
Most of them are, through metal sheaths of MV cable lines, conductively connected to the substation grounding electrodes at the ends of HV and EHV distribution lines;
Some of their sections are not at the same distance or completely in parallel in relation to the considered cable line and in relation to some other of the surrounding metal installations.
Therefore, the problem under consideration can also be treated as a problem of the deficiency of many relevant but unknown data about the surrounding metal installations. To gain a more complete insight into the problem, we will, for a moment, assume the surrounding metal installations do not exist, and the single-core cables belonging to the considered cable line are laid in a flat formation that, in the general case, from the standpoint of their positions, is shown in
Figure 1.
The used notation has the following meaning:
d—distance between two adjacent single-core cables;
rsh—mean radius of the cable sheaths.
For our idea of the spatial position of the metal sheaths of a cable line to be complete, it is necessary to know that contemporary HV and EHV cable lines have applied the cross-bonding [
19]. One such cable line can be presented during a ground fault by the equivalent circuit shown in
Figure 2.
The used notation has the following meaning:
A (B)—supply (supplied) substation,
If—ground fault current when the fault occurs in the supplied substation,
I1, I2, and I3—currents induced in the cable line sheaths along corresponding line sections.
0, 1, 2 and 3—denote the conductors involved with the inductive interaction.
The electrical circuit that is spontaneously formed around and along one HV or EHV distribution cable line during an actual or simulated ground fault in a supplied substation encompasses a certain number of known and unknown metal installations, typical of an urban environment. By certain simplifications and idealizations, this circuit can be, according to [
11], presented as shown in
Figure 3.
Although complete from the standpoint of the number of surrounding metal installations, this equivalent circuit is not without any idealizations and approximations of the actual electrical circuit. First, it has been disregarded that some of these installations are grounded at each of the buildings arranged along the same streets as the considered HV cable line. However, this fact is not of importance to the problem considered because the induced currents circulate only in the axial direction through these installations. The situation is similar to the one that emerges when one determines the reduction factor of an overhead line equipped with one or two ground wires. In that case, one does not take into consideration the fact that the ground wires are grounded at each line tower, e.g., ref. [
16].
The used notation has the following meaning:
Uph—phase voltage;
Un0,
Un1,
Un2, …,
UnN—voltages induced in an arbitrary (n-th) circuit (installation) by the currents in all other circuits presented in
Figure 3;
If—ground fault current through one of the phase conductors of the considered cable line;
Ie—currents dissipated into the earth through the grounding system of the supplied substation B;
I1—current through the sheath of the single-core cable carrying current It,
I2, I3—currents through the sheaths of the other two single-core cables;
I4, I5, …, In, …, IN—currents induced in the individual metal installations;
Zph—self-impedance of the phase conductor of the considered cable line;
Z1, Z2, Z3—self-impedances of the metal sheaths of the considered cable line;
Z4, Z5, Z6, …, ZN—self-impedances of the individual metal installations;
ZA(ZB)—impedance of the grounding system of the supply (supplied) substation;
N—arbitrarily large number representing the total number of surrounding metal installations, including the cable line sheaths.
Additionally, in practice, each of the surrounding metal installations usually has some sections that are not in parallel in relation to the considered HV cable line and in relation to some other surrounding metal installations. Furthermore, in the presented equivalent circuit, the metal installations that are laid along only one section of the considered cable line have not been shown. However, these facts are not relevant in the analytical procedure of methodology development, as will be seen in the next section.
Also, the soil around and along an HV cable line is normally heterogeneous, but when we calculate the self and mutual impedances presented in
Figure 3, we assume that it is homogeneous and that its resistivity is equal to its equivalent resistivity. Besides that, as is well known, none of the existing methods enable us to measure the equivalent soil resistivity in urban conditions. It can only be approximately estimated based on the main geological characteristics of the soil surrounding the considered HV cable line. Fortunately, the favorable fact is that cable line impedances are only slightly dependent on equivalent soil resistivity, e.g., ref. [
10]. Additionally, it is important to know that for the necessary calculations, a value of the equivalent soil resistivity is somewhat lower than the one approximately estimated. In this way, we are obtaining final results that are slightly less favorable from the standpoint of HV line power transfer capacity [
10] and slightly on the side of increased safety when determining the actual reduction factor of cable line [
11] and its inductive influence on the surrounding metal installations [
9].
Disregarding the inductive influence of metallic installations surrounding an HV or EHV cable line when determining the ground fault currents in the HV substation(s) leads to ground fault currents whose values are somewhat lower than the actual ones [
10]. However, taking into account the influence of surrounding metal installations was not possible by using the well-known calculation procedure, e.g., ref. [
18]. It can only be conducted by using the method based on the corresponding test measurements during the simulated ground fault in the supplied substation [
10]. However, to apply this method, one or even two HV substations needed to be out of service, which, as is known, is possible only in rare situations foreseen by the regular maintenance of the HV distribution networks. Also, the reduction factor of HV or EHV cable lines can be determined by using the analytical expression given in [
16]. However, by using these analytical expressions, it is not possible to take into account the inductive influence of the surrounding metal installations. This was not possible even using methods based on the capabilities of modern computers [
21]. It was later shown that the analytical expressions for the reduction factor of a cable line without cross-bonding can also be used for a cable line with cross-bonding [
22].
The value of the reduction factor obtained without taking into account the inductive influence of the surrounding metal installations can be, depending on the degree of urbanization of the surrounding area, greater than the actual one [
8]. Since all potential and all potential differences, including step and touch voltages on the grounding system of the supplied substations, are proportional to this factor, this fact dramatically changed our earlier perception of the magnitude of the grounding problem with these substations. Therefore, determining the actual reduction factor puts the grounding problems of HV distribution substations into realistic frameworks that enable easy and economical solutions, i.e., solutions that are in accordance with the needs in each specific case.
Determining the actual reduction factor of the feeding cable line is possible by using the methodology based on the test measurements during a simulated ground fault in a newly built HV substation, prepared to start operation. However, in the design stage of an HV substation, its feeding cable line is usually not completely constructed, and this fact represents a certain practical difficulty in determining the actual reduction factor at that relevant moment. The possibility of overcoming this problem was considered in [
11], and, inter alia, it is suggested that the formation of a database on the values of the reduction factor for all existing cable lines in a certain urban area. The creation of such a database would be significantly facilitated by using the presented methodology version based on synchronous measurements.
In cases where there are no transit HV substations between the HV supply and one transit and the supplied substation, the value of the actual reduction factor allows us to correctly periodically test the safety conditions within and in the vicinity of a supplied substation. However, when there is at least one transit substation between the supply HV substation and the supplied one due to a practical problem (interrupting the electricity supply to a large number of consumers), it is not possible to obtain permission to perform the necessary test measurements, so we cannot obtain the value of the actual reduction factor in these cases. Therefore, in such cases, we are forced to make a preliminary assessment of safety conditions, which in some critical cases may be insufficient for a definitive assessment concerning safety conditions in the supplied substation [
22].
In addition, forming a file with data on the values of the actual reduction factor of all existing cable lines belonging to a certain HV or EHV cable network, with the aim of a more accurate assessment of the reduction factor in the design stage of future substations, requires a relatively long time. With the present procedure for obtaining permission for the necessary test measurements, the complete formation of such a file would take many years and perhaps even several decades in the case of huge cities, so-called megalopolises, existing in the contemporary world. Thus, there is need for the methodology that would accelerate and facilitate the procedure for obtaining such file.
One version of the methodology based on test measurements also enables solving the problem of inductive influence in the most complex cases, where an inducing line is an HV or EHV distribution cable line [
9]. In that case, there are many different induced metal installations laid along the same streets and typical of urban surroundings. However, when the number of these installations is greater, because of the screening effect, the inductive influence on each of them, seen individually, is smaller.
Quantitative analysis based on experimental investigations [
9] shows that in the areas of an average degree of urbanization, the induced currents and voltages in any of the surrounding metal installations during normal operation, as well as during a ground fault in the supplied substation (critical place [
9]), are due to the screening effect of other surrounding metal installations, multiple times smaller than previously estimated. Thus, just by taking into account this effect, it becomes possible to put this problem in a realistic framework and find an adequate solution in each specific case. Since the actual induced voltages are less than previously possible to know, it practically means that in many concrete cases, the protection measures used against too high (dangerous and/or harmful) induced voltages or currents are redundant. The practical problem in the application of this methodology version appeared because, to determine any of the unknown induced currents, it is necessary to determine separately the corresponding equivalent sheath of the considered cable line. That practically means that it is necessary to perform the test measurements with a simulated ground fault for each of the surrounding metal installations [
9].
All considered problems are even more difficult to solve in practice since the surrounding metal installations do not belong to the electrical distribution company, so these companies cannot count on their favorable effects forever. Therefore, it is very important to have the possibility of timely determination of the effects of relevant changes concerning the surrounding metal installations. A more significant reduction in the number of surrounding installations may be a reason for repeating some of these measurements. However, such measurements in an HV or EHV distribution network are practically possible only during periodic testing of safety conditions in the supplied substation or during major renovations in that substation, which most frequently means once every five or more years. Thus, the present version of the methodology for determining the currents in surrounding metal installations is almost inapplicable in practical conditions.
4. Determination of Effective Sheaths
By introducing the concept of effective sheaths of cable lines [
12], each cable line, including the surrounding metal installations, can be presented in
Figure 6.
The used notation has the following meaning:
URA, USA, UTA, URB, USB, and UTB—voltages of the phase conductors R, S, and T on the receiving and sending ends of the presented cable line,
IRA, ISA, ITA, IRB, ISB, and ITB—currents in the phase conductors at both ends of the presented cable line.
By introducing the effective sheaths, the appearance of the cable line seen from outside remains unchanged, and the determination of the relevant characteristics of one distribution cable line is reduced to the simplest and well-known case. We have such a case under the unreal assumptions that there are no other metal installations in the entire environment, and that cross-bonding is not applied to the considered cable line [
18]. Since HV and EHV cable lines are with applied cross-bonding, the induced currents in each sheath of the cable line cancel each other out, so that induced currents in the cable line sheaths practically do not exist. The same case is with the capacitive currents in each sheath. As a result, the currents in the actual sheaths of the cable line are negligibly small, so the presence of these sheaths when it comes to their inductive influence can be disregarded. This means that the effective sheaths of the cable line with applied cross-bonding represent, during normal operation, the substitution only for the surrounding metal installations from the standpoint of their inductive influence. Embedding modern technologies and systems for synchronized measurements in large power distribution networks, it has become possible to obtain data on voltage and current phasors at both ends of an HV or EHV cable line at the same instant, e.g., ref. [
7]. If we obtain these data for a certain cable line, we can determine the self-impedance of the effective sheaths using the following system of equations:
where
IRB, ISB, and ITB—currents in the phase conductors in the supplied substation B;
ΔUR, ΔUS, and ΔUT—voltage drops along individual phase conductors due to currents
IRB, ISB, and ITB, respectively;
ΔUCR, ΔUCS, and ΔUCT—voltage drops along individual phase conductors due to the corresponding capacitive currents;
I1, I2, and I3—currents in the effective sheaths of the cable line that correspond to the phase conductors R, S, and T, respectively;
Zph—self-impedance of the phase conductors;
Zeff1, Zeff2, and Zeff3—self-impedance of the effective sheaths of the cable line that correspond to the phase conductors R, S, and T, respectively;
Zrs (Zsr), Zrt (Ztr), and Zst (Zsr)—mutual impedances between the individual phase conductors;
Z12 (Z21), Z13 (Z31), and Z23 (Z32)—mutual impedances between the individual effective sheaths of the considered cable line;
Zr1 (Z1r), Zr2 (Z2r), and Zr3 (Z3r)—mutual impedances between phase R and the sheath of each of the single-core cables of the considered cable line;
Zs1 (Z1s), Zs2 (Z2s), and Zs3 (Z3s)—mutual impedances between phase S and the sheath of each of the single-core cables of the considered cable line;
Zt1 (Z1t), Zt2 (Z2t), and Zt3 (Z3t)—mutual impedances between phase T and the sheath of each of the single-core cables of the considered cable line.
Voltage drops Δ
URAB, Δ
USAB, and Δ
UTAB are determined by
Since the capacitive currents at the beginning of the lines are equal to zero and since they increase linearly with the length of the line, voltage drops Δ
UCR, Δ
UCS, and Δ
UCT are determined by:
However, these capacitive currents are relatively small in practical conditions. For example, on one 110 KV cable line, 4.2 km long in the distribution network of Beograd, measurements made on only one phase conductor at both ends showed that this current is significantly less than one percent of the current through this phase conductor at the beginning of the line. In addition, based on the analysis performed, e.g., in [
10], these capacitive currents in the phase conductors of a cable line do not influence the currents induced in the surrounding metal installations.
The longitudinal impedance of any of the phase conductors that we will denote in general, as
Z′ph is, according to [
16], determined by the following equation:
whereas the longitudinal mutual impedance between the phase conductor and its metal sheath, denoted, in general, as Z′
m, is determined by the following equation:
The longitudinal mutual impedance between the sheaths of two adjacent single-core cables laid in a flat formation and denoted, in general, as
Z′
m1, is determined by the following equation:
whereas the longitudinal mutual impedance between sheaths of the cables laid in outside positions (
Figure 1) and denoted as
Z′
m2, is determined by the following equation:
where
R′ph—longitudinal resistance of the phase conductor (Ω/km);
rph—radius of the phase conductor (m);
rsh—mean radius of the single-core cable sheaths (
Figure 1);
d—distance between two adjacent single-core cables (
Figure 1);
ω—angular network frequency, 2πf;
µ0—magnetic permeability of vacuum, 4π·10−7 Vs/Am;
µr—relative magnetic permeability of the phase conductor.
Since the surrounding metal installations in urban areas act as additional neutral conductors of power distribution lines (
Figure 3), the longitudinal self-impedance of an arbitrary, n-th, surrounding metal installation with a cylindrical form is, according to [
16], determined by the following equation:
whereas in the case of installations with a full metal cross-section, it is:
The longitudinal mutual impedance between two arbitrary, n-th and m-th, surrounding metal installations is:
where
R′n—longitudinal resistance of an arbitrary, n-th, surrounding metal installation, (Ω/km);
rn—mean radius of an arbitrary, n-th, surrounding metal installation (m);
dnm—the distance between two arbitrary, n-th and m-th, surrounding metal installations (m);
µr—relative magnetic permeability of the metal that is used for the considered (n-th) installation.
The equivalent earth penetration depth is determined by the following equation:
where
ρ—equivalent soil resistivity along and around the considered cable line (Ωm), and
f—power network frequency.
Based on the results of synchronous measurements, the known quantities in (2) are URA, USA, UTA, URB, USB, UTB, IRA, ISA, ITA, IRB, ISB, and ITB, whereas based on the introduced effective sheaths, the known quantities are also all presented as mutual impedances.
Thus, the only unknown quantities are currents in the effective cable sheaths, or
I1,
I2, and
I3, as well as resistances of the effective sheaths, or
Reff1,
Reff2, and
Reff3, that represent a fictive quantity expressed by a complex number [
12]. Accordingly, by solving the system of Equation (2), all unknown quantities can be determined.
By determining the effective sheaths (Reff1, Reff2, and Reff3), the inductive influence of an arbitrarily large number of surrounding metal installations grounded at both ends is taken into consideration by only one fictitiously changed parameter of a considered HV or EHV cable line. At this, the constructive characteristics and spatial position of these installations do not have to be known to us at all. The same can be said for the metal sheaths of the considered cable line. Also, it does not matter whether cross-bonding is applied or not and whether the cross-bonding is perfectly implemented so that there are no induced currents at all through the sheaths, or some small, induced currents circulate through them. All relevant data on the surrounding metal installations are implicitly involved through the measured values of the currents in the phase conductors. In other words, the returned inductive influence from all induced currents is embraced through the data on the measured values of these currents. This enables us to continue the procedure of determining the characteristics of the considered cable line as if only this line exists in the entire environment, that is, as if the surrounding metal installations do not exist.
During normal operation conditions, an unbalanced current passes through the phase conductors and leaves them through the grounded neutral point(s) in the supplied HV substation. It passes through the grounding system of this substation, and its further path toward the sources in the power system continues through the earth and surrounding metal installations. The distribution of this current between the earth and the surrounding metal installations must remain unchanged by the introduction of effective sheaths.
Since the analytical expression for the calculated reduction factor of cable line is known, e.g., ref. [
12], this condition can be defined by the following equation:
where
rmi—reduction in the unbalanced current through the grounding system by the currents through the effective sheaths, i.e., only through the surrounding metal installations;
R′eff—longitudinal effective resistance.
Also, when we determine the currents
I1,
I2, and
I3 by solving (2), the condition defined by (13) can be defined in another way, i.e., by the following equation:
At this, the sum of the currents through the phase conductors is determined based on the measurement of these currents at the line end (
Figure 6), whereas the sum of the currents through the effective sheaths is a result of the calculations performed by (2). Thus, the parameter of the cable lines, denoted as
rmi, can be defined as the ratio of the current that is dissipated through the grounding system of the supplied substation into the surrounding earth and the unbalanced current that passes through the phase conductors of the feeding line in normal operating conditions. If this parameter is smaller, the intensity of a fluctuating magnetic field around and along the feeding line during normal operation conditions is smaller. As a result, we have a very desirable increase in the transfer capacity of the feeding line, as well as a reduction in the feeding cable line reduction factor and inductive influence on any of the surrounding metal installations during normal operation of the cable line. All these effects enable us to find easy and economical solutions to the grounding problem of the supplied HV substations, accurately determine and utilize the actual transfer capacity of the feeding cable lines, and achieve adequate protection of the surrounding metal installations in each critical case.
By introducing the concept of an effective sheath, a simple model of the cable line and surrounding metal installations is obtained that is externally indistinguishable from the considered cable line. However, Equation (2) shows us that such a model of the cable line cannot be physically realized. The imaginary part of the real part of the self-impedances of the effective sheaths tells us that no real sheath can enable the formation of a magnetic field such as that formed by the cable line and the surrounding metal installations together. So, with Equation (2), we obtain a mathematical model for which there is no corresponding physical model. However, that is quite sufficient. Our aim is to determine by calculations the characteristics of cable lines in urban conditions.
From the standpoint of mathematics, it has been shown that there are some problems that are solved with complex numbers, but only become solvable when we also treat the real part of a certain complex number as a complex number.
8. General Considerations
The application of the presented methodology enables taking into consideration the electromagnetic interactions between cable lines and surrounding metal installations in determining the following:
The actual transfer capacity of any HV or EHV distribution cable line;
The actual reduction factor of any HV or EHV distribution cable line;
A more accurate value of the total ground fault current in the supplied substations;
The actual inductive influence of power lines on any of the surrounding metal installations;
The safety conditions in all HV substations located in urban areas;
Total current induced in surrounding metal installations during normal operation.
Over a hundred years since the massive use of Tesla’s alternating currents began, a methodology has been developed that demonstrates these currents have even more advantages for electric power delivery because of metal installations, which in urban conditions are in the immediate vicinity of power cable lines. By applying this methodology, the beneficial effects of the electromagnetic interaction between these installations and a certain cable line can be determined in each specific case. The only adverse effect of the surrounding metal installations is a slight increase in the ground fault current in the supplied substation [
10]. This should also be taken into account, especially when setting the protection relays. All favorable effects of surrounding metal installations are more pronounced when the cable line passes through areas with a higher degree of urbanization, that is, where our needs for such effects are greater. Also, they are more pronounced when the specific soil resistivity of the surrounding soil is higher, i.e., where our needs for such effects on the reduction factor and inductive influence of an HV or EHV cable lines are greater.
The solution to the problems considered was reached by introducing into the well-known calculation procedure the concept of the effective metal sheath(s) of HV and EHV distribution cable lines. The concept of the effective sheaths enables taking into consideration the inductive influence of all known and unknown surrounding metal installations by using the results of synchronous measurements at the ends of these cable lines.
These measurements are enabled by contemporary synchrophasor technology and telecommunications systems embedded into large electric power networks to continuously monitor, control, and protect them, e.g., ref. [
7].
The introduced equivalent sheaths were named the effective sheaths, and, seen from the outside, they are identical to the actual sheaths of the considered cable line. However, their longitudinal resistance is such that the inductive influence of all surrounding metal installations, incorporating all three actual sheaths of the considered cable line, is encompassed within them. The value of their longitudinal reactance is expressed by a complex number, which, of course, does not correspond to the physical nature of this parameter of electrical conductors. However, the introduction of such a sheath reduces the number of unknown quantities concerning the surrounding metal installations, which enables the solution of the problems.
From the standpoint of the considered electromagnetic phenomenon, the effect of the surrounding metal installations is the same as if the actual cable line sheaths were laid in soil with lower equivalent resistance compared to the soil in which the phase conductors of the cable lines considered are laid, and as if their longitudinal resistance is lower than the real one. In other words, the inductive influence of surrounding metal installations on the actual sheaths of HV and EHV cable lines is equivalent to a certain decrease in their longitudinal resistances as well as the equivalent resistivity of the surrounding soil [
12].
In the analytical procedure used to develop the presented methodology, there are no approximations or simplifications that could affect its accuracy. Thus, any inaccuracy that may arise in its application can only be a consequence of the inaccuracy of input data. Like other methods based on synchronous measurements, the presented methodology can be used to determine the series and sequential impedances of distribution lines. Compared to these methods, the methodology presented here has slightly higher accuracy in determining sequential impedances because it is based on measurement results in normal operating conditions. However, its main advantage over these methods is that it also enables the determination of the actual reduction factor of cable lines as well as their impact on surrounding metal installations. This is not the case with the aforementioned methods, so it can be said that the application of this methodology expands the field of application of synchronous measurements.
Compared to the previous methodology version based on test measurements during a simulated ground fault, the methodology presented here has the advantage that it can be applied at any time, i.e., when there are needs for the data that can be obtained by its application. Also, its application does not require the engagement of people trained in the test measurements. Finally, by using the presented methodology, it is possible for the designers of future HV substations to obtain a very useful file with the data about the value of the actual reduction factor of HV and EHV distribution cable lines of a certain urban area.
With the aim of more efficient delivery of electrical energy, the favorable effects of the surrounding metal installations are welcome and should be used as much as possible. However, the surrounding metal installations do not belong to the electrical distribution companies, so these companies cannot permanently count on their favorable effects. Over time, old and outdated metal installations are abolished, and new ones with the same or a similar function are introduced. For example, nowadays there is a very pronounced tendency to replace steel water pipes with plastic ones. Those changes can significantly affect the actual reduction factor of some feeding lines, that is, the safety conditions within and in the vicinity of the supplied HV substations, as well as voltages induced in the surrounding metal installations. Therefore, in the event of a reduction in the number of surrounding metal installations, electricity distribution companies must be aware of the effects of these changes in a timely manner, which in critical cases may mean repeated necessary measurements. However, this is not possible with the application of the previous version of this methodology because determining these effects requires performing appropriate test measurements. Such measurements in an HV or EHV distribution network are practically possible only on rare occasions during periodic testing of safety conditions in the supplied substation or during major renovations in this substation, which most frequently means once every five or more years.
Since the value of the equivalent soil resistivity in urban conditions can only be approximately estimated, the problem of certain arbitrariness in its determination in engineering practice is effectively solved by adopting these values of the equivalent soil resistivity that give final results on the side of increased safety. That means that for the necessary calculations, the adopted value of the equivalent soil resistivity should be somewhat lower than the roughly estimated one when we determine the transfer capacity and reduction factor of a certain cable line, as well as its inductive influence [
9,
10,
11]. When it comes to the accuracy of the contemporary synchrophasor measurements, they are now so accurate that they can be used directly for calculations [
5,
6].
It should also be mentioned that by applying this methodology, due to the different spatial positions of individual phase conductors in relation to the surrounding metal installations, slightly different longitudinal resistance values of the effective sheaths can be obtained. When determining the favorable effects of the surrounding metal installations, this means that we should adopt for further calculation the effective sheath in which the inductive influence of surrounding metal installations is the smallest, e.g., ref. [
10].
The effects of temporary circumstances, such as maintenance work on some of the surrounding metal installations or the decommissioning of a parallel power line, can also be considered in the same way as the effects of changes in the number of surrounding metal installations previously considered. However, how should these effects be treated? This question should be answered separately in each specific case.
The presented methodology can be applied in a relatively short time, that is, without any investments in the new embedded systems and new equipment, as well as in educated personnel for the operation and maintenance of these systems and equipment.
Of course, the same effects also exist with distribution overhead and MV cable lines, but in these cases, they are less pronounced and are not of such importance for practice in modern electrical transmission and distribution.
The considered metal installations in urban conditions exist regardless of our needfor more efficient electric power delivery. Thus, all we have to do is apply the methodology presented here in each concrete case of HV or EHV distribution cable line.