National Energy and Climate Plan—Polish Participation in the Implementation of European Climate Policy in the 2040 Perspective and Its Implications for Energy Sustainability
Abstract
1. Introduction
2. Materials and Methods
3. Results and Discussion
- The current energy policy assumes electricity production in 2040 of 204,000 GWh, with 60 GW of installed capacity in the NPS. The NECP project assumes, respectively, 307,900 GWh and 135.7 GW of capacity. Why such a difference in forecasts?
- Is the commissioning of the first nuclear units possible before 2035?
- Commissioning of 25 GW of new weather-dependent renewable capacity by 2030. Is it possible to implement?
- Decommissioning of 6 GW of controllable coal capacity by 2030. How to replace it?
- If 30–35 TWh of electricity from gas is assumed (in the period 2030–2040), are more gas units needed? Peak power from coal or gas?
- Will 2 million Mg of coal (4000 GWh of electricity) ensure energy security and sovereignty in 2040?
- What is the alternative scenario if the investment deadlines for offshore wind and nuclear power are moved forward by 5 years?
- In 2024, PSE has tentatively measured electricity demand at 169 TWh and domestic production at 167,000 GWh (Table 1). To this would have to be added prosumer production, which is directly consumed, of about 3–4 TWh. Table 4 assumes gross production in 2025 of 180,200 GWh. There is some difficulty in estimating the sources’ own needs in the changing mix in subsequent years (for new coal-fired power plants, own needs are about 10% of gross production). Also, network and other losses depend on the structure of the network and the distance over which electricity is transmitted. If it is assumed that demand/production in 2025 will remain at the same level as last year or increase slightly, then the difference between gross and net value could be estimated at 12,000–14,000 GWh. The NECP in the WAM version assumes an increase in production/demand in the 2025–2035 decade by 35,700 GWh. While in the 2015–2025 decade, it was 15,000 GWh, twice as much. In the five-year period of 2035–2040, the increase doubles again, reaching 79.6 TWh. (Gross electricity production of 3,079,000 GWh in 2040). In PSE’s 2024 development plan, demand for electricity in 2040 is assumed to be between 2010 and 235,000 GWh, depending on whether the decarbonization/electrification of the economy is more or less dynamic. Expert assessment indicates that the demand for electricity assumed in the NECP is too high. This must be followed by expenditures on new generation sources, which will not be needed in case of lower demand. According to the authors, electricity demand in 2040 should be estimated at the level of PSE’s dynamic scenario, i.e., 235,000 GWh.
- At the beginning of 2025, the status of the first nuclear project, which assumes the construction of three AP1000 nuclear units by Westinghouse, does not indicate the technical or organizational feasibility of meeting the deadline for the commissioning of the first unit envisaged in the current energy policy, i.e., 2033. According to the update of the Polish Nuclear Power Program [19], which is being prepared, commercial operation of the first unit is assumed to begin in 2036, and the subsequent ones will begin in 2037 and 2038. The handover of the construction site to the contractor is to take place in 2025 (!) and the start of the actual work on the nuclear power plant in 2028. It should be recalled at this point that currently, in the project of the first nuclear power plant in Choczewo-Lubiatowo, intensive work is being carried out on the financing model, in particular, the scope of state aid. The Polish side has applied to the EC with proposals for state capital participation in the project at the level of 30%., i.e., PLN 60 billion, according to the current budget estimate, a state guarantee for the remaining outlay raised from the capital market, and a contract for difference formula for the purchase of electricity. The EC is examining the legitimacy and proportionality of the scope of the requested state aid. Domestic experience in the construction of large coal-fired power units in the previous decade indicates that there is a construction cycle of about 10, starting from the decision to initiate the bidding process. More relevant here is the experience from the construction of recent nuclear power plants in Olkiluoto in Finland, Flamanville in France, or Hinkley Point C in the UK. In the latter case, two units with a total capacity of 3.200 MW being built by France’s EdF may be delayed by about five years from the original schedule, and the budget may exceed £40 billion (the original target was to deliver the first unit in 2025, with a budget of £18 billion in total), according to the contractor’s announcements in early 2025 [20,21]. Taking this into account, an expert estimate of the delivery date for the first unit of a nuclear power plant in Poland assumes that it will be possible around 2040.
- Between 2025 and 2030, an increase in renewable capacity of 25 GW has been assumed. The largest increase, by 9.3 GW, is expected to come from photovoltaic power plants, followed by onshore wind power plants, by 7 GW, and on the Baltic Sea, by 5.9 GW. The rest are energy storage plants, assuming that they store surplus renewable energy that would otherwise be lost. Investments in photovoltaic power plants are not complicated, but on the side of ensuring the introduction of electricity produced by them into the grid, the matter looks much more serious. Currently, these are not commercially preferred solutions, unless considered with large-scale storage combined. The cheapest electricity can be produced by onshore wind power plants. Unfortunately, the development of investment in this segment has stagnated, and there is no indication that a compromise on the so-called “distance law” will be reached soon, allowing new locations for these power plants [22]. Retrofits of older wind power plants, with lower towers and capacities, and thus lower efficiency and hours of operation, are also expected soon. There is a serious risk to the feasibility of increasing capacity in this technology by 1.5 GW every year. Offshore wind farms are slowly entering the implementation period. The largest Polish projects of Orlen, PGE, and Polenergia are being implemented with foreign partners. In January 2025, PGE announced the start of a joint investment with Denmark’s Overstate in the 1.5 GW Baltica 2 wind farm, with a budget of PLN 30 billion. It should be mentioned that this project is covered by a contract for difference, with a price guarantee, and that the price is expected to exceed PLN 500 per MWh. While regulatory risk is important in the case of onshore wind farm investments, offshore wind farms will primarily face technological risk. Only the first work on the foundation and installation of the turbines will make it possible to assess the risk of meeting the schedule for building the towers with turbines and generating the power. It is expertly assumed that the implementation of any new technology involves technological and budgetary risks, as well as the occurrence of so-called “childhood diseases.” According to the authors, there is a risk of postponing the commissioning date of offshore wind farms, as well as the capacity of wind power plants commissioned by 2030.
- The draft NECP assumes a rapid reduction in coal-fired capacity in the national mix. It has been assumed that, as a result of the cessation of support from the capacity market for power plants emitting more than 550 kg of carbon dioxide per MWh, most of these units will be decommissioned from mid-2025. Work is currently underway to extend support until 2028, but the annual auction formula proposed in the amendment to the law means that units that do not win support for 2026 will not be willing to wait for the 2027 auction, bringing losses to the operator in the meantime. Analyses carried out in PSE’s Development Plan show that if the 6 GW of controllable coal capacity planned in the NECP is set aside by 2030, despite the commissioning of new gas units, the balance of increasing demand for controllable power in the system is unfavorable. There is a growing risk of the occurrence and prolongation of power outages for customers beyond ENTSOE standards. In the expert assessment for the period 2025–2030, it is necessary to prepare an analysis of the demand for controllable power in the NPS, in specific locations, power volumes, and timeframes, prepared by PSE. If this analysis identifies excess capacity, it should be permanently set aside. For units that are necessary from the point of view of the system operator, financing should be provided under the strategic/balance reserve formula, over and above the existing capacity market, and regardless of the planned capacity market after 2030. According to the authors, in the 2030 perspective, it is necessary to maintain most of the existing reserves in 200 MW class units as controllable power sources.
- The NECP assumes that in 2030, natural gas-fired power plants and CHPs, and after 2035 with the addition of renewable gas fuels, will produce 30.8 TWh of electricity. The maximum production from gas in the 2035 perspective will not exceed 35 TWh. The key issue remains the mode of operation of the planned gas-fired power plants and their role in the NPS. If it is assumed that 6 GW of gas-fired capacity will be operating in the NPS in 2030, they will be more than capable of supplying the NPS with 35 TWh of electricity. However, if it were to be assumed that gas-fired units would be regulatory, then an analysis should be made of the right proportion of coal-fired (existing) and new gas-fired (to be built) capacity to ensure the lowest cost to consumers. According to the authors, in order to mitigate the risk of natural gas availability and price, it is necessary to maintain coal and gas capacity (6 GW in 2030, in the ongoing Ostrołęka, Grudziądz, Rybnik projects). In addition, only open-cycle gas units can be considered as peaking capacity. Investments in new CCGT units will not ensure the profitability of these units and are unjustified.
- The national plan assumes a virtual shift away from coal in the power industry in 2040. The assumed production of 4100 GWh of electricity implies a demand for 2 million Mg of hard coal and implies an accelerated liquidation of domestic mining. Although the WEM version of the plan assumes a scenario with demand for hard coal in 2040 at 10 million Mg, which corresponds to the social agreement signed by the government with the representation of the mining industry, achieving the declared climate goals is possible only with the ambitious scenario. Decarbonization of produced electricity is expected by the domestic industry. According to the authors, any steps towards increasing renewable energy in the energy mix should be prioritized, but with the principles of stability of operation and security of the national system. Expert studies conducted at the Central Mining Institute indicate a demand for thermal coal in 2040 at 10–12 million Mg (Figure 2). The chart presented here includes projections based on the current energy policy (19.1 million Mg of coal in 2040) and the NECP project (2 million Mg). In the scenario of high emission allowance prices and Scenario 3, from June 2023, which was not adopted, the volume of demand oscillates between 10 and 11 million Mg in 2040. The main reason for the differences in demand lies in the risk of delaying investments in nuclear power and offshore wind farms. If the realistic date for the commissioning of the first nuclear unit is estimated to be around 2040, then the question of filling the primary energy sources and the generation gap between 2035 and 2045 will remain open.
- The annual average generation gap between 2035 and 2040 is estimated at 60,000 GWh (with a maximum of 70,000 GWh in 2040).
- Available capacity of coal-fired power plants in 2040 (Kozienice, Opole, Jaworzno, and Turów)—4.2 GW. In addition, some units of the 200 MW class, in particular, the Połaniec power plant, with a capacity of about—1 GW, generate about 35,000 GWh of electricity per year. No new coal-fired units are assumed.
- CAPEX for carbon capture facilities is estimated at EUR 1.2 billion/1 GW.
- Energy storage facilities for storing excess energy from the RES that cannot be fed into the grid will be implemented, with a capacity of about 2.5 GW, in four-hour chemical storage facilities. If pumped storage capacity is built in three locations: Młoty, Tolkmicko, Rożnów, it will also be about 2.5 GW.
- CAPEX for chemical energy storage is estimated at about EUR 1 billion/1 GW, in four-hour storage.
- Capital expenditures for new large-scale gas CCGT units are estimated at about EUR 1.1 billion/1 GW.
- The price of emission allowances will increase in 2035–2040 from EUR 120 to EUR 250 (as assumed by the NECP), averaging EUR 185 per allowance per year.
- Gas scenario with renewable energy surplus storage.
- Coal scenario with energy storage redundant with RES.
- Coal scenario with CCS, with energy storage redundant with RES.
- With a generation gap of about 60,000 GWh per year between 2035 and 2040, only the gas scenario with storage of surplus energy from RES offers the possibility of fully covering this gap.
- Coal scenarios, assuming only necessary upgrades, including the development of CCS facilities for new units, will not provide sufficient generation to cover the gap.
- With the assumed price path for emission allowances, investments in CCS facilities are profitable and can ensure the lowest carbon intensity of the energy produced. The critical path is to prepare the national infrastructure for carbon dioxide transport and storage.
- The least investment and upgrades are required in a carbon scenario without CCS, but it leaves the highest carbon footprint.
- If the coal scenario is chosen, with or without CCS, it will be necessary to fill the generation gap with gas fuel, including the construction of new gas-fired power plants.
- Filling the generation gap with energy from chemical energy storage facilities, in a long-term storage formula, may prove unprofitable and significantly increase the cost of electricity.
- Maintaining energy independence indicates the need, at least in part, to implement one of the carbon scenarios.
- It was assumed that the price of emission allowances would increase from EUR 120 to EUR 250 between 2035 and 2040 (in line with the NECP), averaging EUR 185 per allowance per year. A sharper increase in the price of allowances, i.e., to EUR 400 in 2040, would result in an average of EUR 280 and a 55% increase in the cost of allowances in MWh of generated electricity in all scenarios.
4. Conclusions
- The ambitious transformation of the country’s power and heating industry toward renewable and low-carbon sources is not debatable in terms of direction. What matters is the pace. Increasing the amount of renewable energy from weather-dependent sources injected into the national system is partly possible by improving the flexibility of the NPS by making demand more flexible, increasing storage capacity, including thermal storage, electrification of certain sectors of the economy (sector coupling), and increasing the regulation capacity of existing conventional units. We call for synchronizing the pace of increasing the flexibility of the NPS (including long-term storage) with the implementation of planned investments in renewable sources, so that the output of newly built sources can be maximized.
- Existing coal-fired units are the cheapest reserve of the NPS during the transition period. Throughout the entire period of technological transformation of the energy sector, it is always necessary to ensure a momentary balancing of energy demand with energy supplied to the NPS. The condition for stable operation of the NPS for the next 10–15 years is the maintenance of a sufficient amount of fossil fuel controllable capacity. For this group of units, whose revenues do not cover costs (too short operating time), it is necessary to build financial mechanisms to guarantee coverage of fixed costs (balance/strategic reserve). For new low-carbon controllable sources (gas and other technologies), it is necessary to continue the power market mechanisms. We assumed that the NPS controllable reserve should be maintained mainly on the basis of existing coal-fired power plants and gas-fired sources built so far (the cost and emissivity of the fuel are not significant in peak operation).
- Need to synchronize the coal phase-out program with power generation needs for the transition period. Until the planned nuclear power capacity is built, it is necessary to plan the demand for power capacity and primary energy sources (2025–2045). For such planned capacities in the system, it is necessary to determine the expected volume of production and the necessary primary energy sources, including coal from domestic mines (according to cost and quality ranking). The security and energy sovereignty of the state dictate that minimum domestic primary energy sources and generation resources be secured in case of external threats. We call for reconsideration of the volume of coal demand for energy purposes in 2040 (assumed to be about 2–10 million Mg).
- Distributed generation and local use of electricity. It is most efficient to generate and use energy locally. In the energy policy/NECP and support mechanisms, this area should receive special attention. Previous initiatives to build clusters and local energy communities have proved unsuccessful. We call for building effective mechanisms for this area to reward local energy generation and use.
- Electricity with a low carbon footprint and at a competitive price is a condition for industrial development. The demand for rapid transformation and lowering the carbon footprint of electricity produced is understood and not questioned by energy producers. However, the inertia of the transition away from fossil fuels, especially in controllable units, leads to a renewable energy deficit and high prices. We call for additional analyses to be carried out to determine price and carbon footprint forecasts for electricity and heat over the plan horizon.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
Abbreviations
NECP | National Energy and Climate Plan |
PEP 2040 | Energy Policy of Poland until 2040 |
EC | European Commission |
MoE | Minister of Climate and Environment |
RES | Renewable Energy Sources |
CCS | Carbon Capture and Storage |
CHP | Combined Heat and Power |
CCGT | Combined Cycle Gas Turbine |
SMR | Small Modular Reactor |
PSE | Polish power grids (Polskie Sieci Elektroenergetyczne) |
NPS | National Power System |
ARE | Energy Market Agency |
RED III | Renewable Energy Directive III |
FIT for 55 | Fit for 55 legislative package |
BECCS | Bio-Energy with Carbon Capture and Storage |
TSO | Transmission System Operator |
DSR | Demand Side Response |
GWh | Gigawatt-hour |
TJ | Terajoule |
Mg | Megagram |
PEF | Primary Energy Factor |
References
- The Draghi Report on EU Competitiveness. 2024. Available online: https://commission.europa.eu/topics/eu-competitiveness/draghi-report_en (accessed on 15 March 2025).
- Priorytety Polskiej Prezydencji. 2025. Available online: https://polish-presidency.consilium.europa.eu/pl/program/priorytety-prezydencji/ (accessed on 15 March 2025).
- Krajowy Plan w Dziedzinie Energii i Klimatu. 2024. Available online: https://www.gov.pl/web/klimat/krajowy-plan-na-rzecz-energii-i-klimatu (accessed on 15 March 2025).
- Rozporządzenie Parlamentu Europejskiego i Rady (UE) 2018/1999 z Dnia 11 Grudnia 2018 r. w Sprawie Zarządzania Unią Energetyczną i Działaniami w Dziedzinie Klimatu, Zmiany Rozporządzeń Parlamentu Europejskiego i Rady (WE) nr 663/2009 i (WE) nr 715/2009, Dyrektyw Parlamentu Europejskiego i Rady 94/22/WE, 98/70/WE, 2009/31/WE, 2009/73/WE, 2010/31/UE, 2012/27/UE i 2013/30/UE, Dyrektyw Rady 2009/119/WE i (EU) 2015/652 Oraz Uchylenia Rozporządzenia Parlamentu Europejskiego i Rady (UE) nr 525/2013. Available online: https://eur-lex.europa.eu/eli/reg/2018/1999/oj (accessed on 15 March 2025).
- Projekt Krajowego Planu w Dziedzinie Energii i Klimatu do 2030 r.—Wersja wstępna z 02.2024 r. Available online: https://www.gov.pl/web/klimat/projekt-krajowego-planu-w-dziedzinie-energii-i-klimatu-do-2030-r--wersja-wstepna-z-022024-r (accessed on 15 March 2025).
- Fit for 55, 2021: Pakiet Propozycji Legislacyjnych KE, Lipiec 2021 r. Available online: https://commission.europa.eu/strategy-and-policy/priorities-2019-2024/european-green-deal/delivering-european-green-deal/fit-55-delivering-proposals_en (accessed on 15 March 2025).
- Polityka Energetyczna Polski do 2040 Roku, Załącznik do Uchwały nr 22/2021 Rady Ministrów z Dnia 2 Lutego 2021 r. Available online: https://www.gov.pl/web/klimat/polityka-energetyczna-polski (accessed on 15 March 2025).
- Prekonsultacje Scenariusza nr. 3 Korekty Polityki Energetycznej, Lipiec 2023 r. Available online: https://www.gov.pl/web/klimat/prekonsultacje-w-zkresie-aktualizacji-dokumentow-strategicznych-kpeikpep2040 (accessed on 15 March 2025).
- Raporty ARE. 2025. Available online: https://polskirynekwegla.pl/raporty-dynamiczne (accessed on 15 March 2025).
- Transformacja Energetyczna—Zapotrzebowanie Na Źródła Energii Pierwotnej w Perspektywie 2040 Roku; Tokarski, S., Ed.; Główny Instytut Górnictwa: Katowice, Poland, 2021. [Google Scholar]
- Pylypenko, H.M.; Pylypenko, Y.I.; Dubiei, Y.V.; Solianyk, L.G.; Pazynich, Y.M.; Buketov, V.; Magdziarczyk, M.; Smolinski, A. Social capital as a factor of innovative development. J. Open Innov. Technol. Mark. Complex. 2023, 9, 100118. [Google Scholar] [CrossRef]
- Simla, T.; Stanek, W. Influence of the wind energy sector on thermal power plants in the Polish energy system. Renew. Energy 2020, 161, 928–938. [Google Scholar] [CrossRef]
- Simoes, S.G.; Amorim, F.; Siggini, G.; Sessa, V.; Saint-Drenan, Y.-M.; Carvalho, S.; Mraihi, H.; Assoumou, E. Climate proofing the renewable electricity deployment in Europe-Introducing climate variability in large energy systems models. Energy Strat. Rev. 2021, 35, 100657. [Google Scholar] [CrossRef]
- Lepszy, S. Analysis of the storage capacity and charging and discharging power in energy storage systems based on historical data on the day-ahead energy market in Poland. Energy 2020, 213, 118815. [Google Scholar] [CrossRef]
- Kirkerud, J.; Nagel, N.; Bolkesjø, T. The Role of Demand Response in the Future Renewable Northern European Energy System. Energy 2021, 235, 121336. [Google Scholar] [CrossRef]
- Tokarski, S.; Magdziarczyk, M.; Smolinski, A. Risk Management Scenarios for Investment Program Delays in the Polish Power Industry. Energies 2021, 14, 5210. [Google Scholar] [CrossRef]
- Plan Rozwoju w Zakresie Zaspokojenia Obecnego i Przyszłego Zapotrzebowania na Energię Elektryczną na Lata 2025–2034. Available online: https://www.cire.pl/files/portal/186/news/347185/045da606d26837065c04be4af2035c743a9e50a1424c01903b52981a4a169a4d.pdf (accessed on 15 March 2025).
- Ocena Wystarczalności Zasobów na Poziomie Krajowym 2025–2040. Available online: https://www.pse.pl/dokumenty (accessed on 15 March 2025).
- Aktualizacja Programu Polskiej Energetyki Jądrowej. 2025. Available online: https://www.gov.pl/web/klimat/aktualizacja-programu-polskiej-energetyki-jadrowej-uchwala (accessed on 15 March 2025).
- Strategia Rozwoju Technologii Wychwytu, Transportu, Utylizacji i Składowania CO2 w Polsce Oraz Pilotaż Polskiego Klastra, Projekt Gospostrateg III. Available online: https://ccus.pl/o-projekcie/ (accessed on 15 March 2025).
- World Nuclear Views. 2025. Available online: https://www.world-nuclear-news.org/Articles/EDF-announces-Hinkley-Point-C-delay-and-big-rise-i (accessed on 15 March 2025).
- Ustawa Odległościowa. 2025. Available online: https://samorzad.pap.pl/kategoria/aktualnosci/nowa-wersja-zmiany-ustawy-odleglosciowej-repowering-i-minimalna-odleglosc (accessed on 15 March 2025).
- Tokarski, S.; Magdziarczyk, M.; Smoliński, S. An Analysis of Risks and Challenges to the Polish Power Industry in the Year 2024. Energies 2024, 17, 1044. [Google Scholar] [CrossRef]
- The Clean Industrial Deal, 2025: A Joint Roadmap for Competitiveness and Decarbonisation. Communication From the Commission to the European Parliament, the Council, the European Economic and Social Committee and the Committee of the Regions, Brussels, 26.2.2025 COM (2025) 85 Final. Available online: https://commission.europa.eu/topics/eu-competitiveness/clean-industrial-deal_en (accessed on 15 March 2025).
No. | Specification | December | Cumulative | ||||
---|---|---|---|---|---|---|---|
January to December | |||||||
2023 | 2024 | Changes | 2023 | 2024 | Changes | ||
[GWh] | [GWh] | [(b − a)/a*100] | [GWh] | [GWh] | [(e − d)/d*100] | ||
[%] | [%] | ||||||
[a] | [b] | [c] | [d] | [e] | [f] | ||
1 | Total production (1.1 + 1.2 + 1.3) | 15,626 | 15,427 | −1.27 | 163,629 | 166,990 | 2.05 |
1.1 | Commercial power plants | 12,298 | 12,438 | 1.13 | 128,420 | 124,781 | −2.83 |
1.1.1 | Professional water pp. | 358 | 191 | −46.66 | 3592 | 3057 | −14.89 |
1.1.2 | Professional heat pp | 11,940 | 12,247 | 2.57 | 124,828 | 121,724 | −2.49 |
1.1.2.1 | Hard coal | 7332 | 7157 | −2.38 | 76,607 | 69,112 | −9.78 |
1.1.2.2 | Lignite | 3063 | 3297 | 7.64 | 34,571 | 35,844 | 3.68 |
1.1.2.3 | Natural gas | 1545 | 1792 | 16 | 13,650 | 16,768 | 22.84 |
1.2 | Other renewable | 208 | 280 | 34.95 | 13,209 | 17,334 | 31.23 |
1.3 | Wind (on shore) | 3120 | 2709 | −13.18 | 22,000 | 24,874 | 13.07 |
2 | Foreign exchange balance | −217 | −556 | 156.36 | 3889 | 1966 | −49.46 |
3 | National electricity consumption | 15,409 | 14,870 | −3.49 | 167,518 | 168,956 | 0.86 |
Target | Climate Package2009 | Climate Package2014 | Climate Package—Final Targets 2019 | Fit for 55 July 2021 Package | Polish Targets According to PEP 2040 and NECP February 2021. | REPowerEU May 2022 | Final Fit for 55 February 2024 Targets | Polish Targets According to the NECP Revision (WEM/WAM, October 2024) |
---|---|---|---|---|---|---|---|---|
CO2 reduction [%]. | 20 | 40 | 40 | 55 | 30 | 55 | 55 (minimum) | 35/50.4 |
Increase in RES share—gross consumption [%]. | 20 | 27 | 32 | 40 | 23 | 45 | 42.5 (aiming for 45) | 29.8/32.6 |
Energy efficiency [%]. | 20 | 27 | 32.5 | 36 | 23 | 38.5 | 38.0 11.7 * | 21.8 0.5/4.6 * |
2005 | 2010 | 2015 | 2020 | 2025 | 2030 | 2035 | 2040 | |
---|---|---|---|---|---|---|---|---|
Electricity [GWh] | 157,295 | 158,186 | 165,128 | 158,247 | 180,213 | 192,604 | 228,257 | 307,923 |
District heating [TJ] | 336,292 | 335,831 | 274,357 | 285,870 | 280,425 | 251,724 | 229,116 | 221,327 |
2005 | 2010 | 2015 | 2020 | 2025 | 2030 | 2035 | 2040 | |
---|---|---|---|---|---|---|---|---|
Lignite | 54.8 | 48.7 | 52.8 | 38.1 | 31.2 | 11.4 | 3.0 | 0.0 |
Hard coal * | 88.5 | 89.3 | 79.4 | 70.7 | 64.6 | 31.9 | 16.5 | 4.1 |
Gas fuels ** | 5.2 | 5.1 | 6.4 | 17.4 | 23.4 | 30.8 | 26.9 | 9.9 |
Heating oil | 2.7 | 2.6 | 2.1 | 1.7 | 1.8 | 1.4 | 1.2 | 0.9 |
Nuclear energy | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 9.5 | 58.1 |
Biomass | 1.4 | 5.9 | 9.0 | 6.9 | 6.8 | 7.9 | 7.4 | 7.5 |
Biogas/biomethane | 0.1 | 0.4 | 0.9 | 1.2 | 2.2 | 3.2 | 3.5 | 4.8 |
Hydropower | 2.2 | 2.9 | 1.8 | 2.1 | 2.6 | 2.9 | 3.0 | 3.0 |
From pumped water | 1.6 | 0.6 | 0.6 | 0.8 | 1.2 | 3.9 | 3.9 | 6.6 |
Onshore wind energy | 0.1 | 1.7 | 10.9 | 15.8 | 28.6 | 47.4 | 59.2 | 69.5 |
Offshore wind energy | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 21.7 | 45.5 | 67.4 |
Solar energy | 0.0 | 0.0 | 0.1 | 2.0 | 15.3 | 24.6 | 33.9 | 43.1 |
Geothermal energy | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
Hydrogen | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 6.9 | 17.8 |
Other *** | 0.7 | 1.1 | 1.0 | 1.5 | 2.5 | 2.4 | 2.2 | 1.8 |
Energy storage (Batteries) | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 3.1 | 5.7 | 13.5 |
Total | 157.3 | 158.2 | 165.1 | 158.2 | 180.2 | 192.6 | 228.3 | 307.9 |
2005 | 2010 | 2015 | 2020 | 2025 | 2030 | 2035 | 2040 | |
---|---|---|---|---|---|---|---|---|
Lignite pp | 8197 | 8145 | 8643 | 7445 | 6566 | 6566 | 3344 | 683 |
Hard coal pp | 14,613 | 14,655 | 13,617 | 15,889 | 14,465 | 9136 | 5847 | 4572 |
Gas/Hydrogen pp | 0 | 0 | 0 | 0 | 1332 | 5957 | 5957 | 6703 |
Nuclear pp | 0 | 0 | 0 | 0 | 0 | 0 | 1170 | 6225 |
Nuclear_SMR | 0 | 0 | 0 | 0 | 0 | 0 | 600 | 1200 |
Water pp | 914 | 935 | 964 | 987 | 1008 | 1118 | 1148 | 1178 |
Peak-Pump pp | 1679 | 1679 | 1705 | 1705 | 1767 | 2510 | 2510 | 4235 |
Industrial pp | 6140 | 6126 | 1605 | 1945 | 1814 | 1755 | 1608 | 1110 |
Hard coal chp | 4968 | 5226 | 4578 | 3757 | 2403 | 19 | ||
Gas/Hydrogen chp | 760 | 807 | 928 | 2688 | 3515 | 5071 | 4581 | 4760 |
Biomass pp and chp | 102 | 140 | 513 | 534 | 669 | 983 | 1116 | 1145 |
Biogas/biomethane chp | 216 | 241 | 362 | 509 | 526 | 519 | ||
BECCS | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Wind farms on shore | 121 | 1108 | 4886 | 6499 | 11,996 | 19,028 | 23,042 | 25,816 |
Wind farms offshore | 0 | 0 | 0 | 0 | 0 | 5927 | 12,233 | 17,883 |
Geothermal pp | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Photovoltaics | 0 | 0 | 108 | 1229 | 19,726 | 28,976 | 37,901 | 46,293 |
Peak_gas/hydrogen | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 805 |
Energy storage facilities | 0 | 0 | 0 | 0 | 50 | 1975 | 3690 | 8706 |
DSR/power import | 0 | 0 | 150 | 615 | 1788 | 2864 | 3524 | 3874 |
Total | 32,526 | 33,594 | 33,118 | 39,535 | 69,634 | 96,131 | 111,201 | 135,749 |
No. | Indicators | Gas + Storage Scenario | Scenario Coal + Storage | CCS Coal + Storage Scenario |
---|---|---|---|---|
1 | Capacity of new/existing generation units | 7.0 GW | 5.2 GW | 4.2 GW |
2 | Capital expenditures | EUR 7.0 billion | EUR 0.5 billion | EUR 5.5 billion |
3 | Expenditure on storage | EUR 2.5 billion | EUR 2.5 billion | EUR 2.5 billion |
4 | Electricity production/year | 60,000 GWh | 45,000 GWh | 35,000 GWh |
5 | Fuel requirements | 6.5–7 bcm. gas | 20 million Mg. coal | 20 million Mg. coal |
6 | Emissivity of electricity production/average increase in MWh cost due to emissions | approx. 0.35 Mg/MWh 65 EUR/MWh | approx. 0.80 Mg/MWh 144 EUR/MWh | approx. 0.05 Mg/MWh 9 EUR/MWh |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Tokarski, S.; Urych, B.; Smolinski, A. National Energy and Climate Plan—Polish Participation in the Implementation of European Climate Policy in the 2040 Perspective and Its Implications for Energy Sustainability. Sustainability 2025, 17, 5035. https://doi.org/10.3390/su17115035
Tokarski S, Urych B, Smolinski A. National Energy and Climate Plan—Polish Participation in the Implementation of European Climate Policy in the 2040 Perspective and Its Implications for Energy Sustainability. Sustainability. 2025; 17(11):5035. https://doi.org/10.3390/su17115035
Chicago/Turabian StyleTokarski, Stanisław, Beata Urych, and Adam Smolinski. 2025. "National Energy and Climate Plan—Polish Participation in the Implementation of European Climate Policy in the 2040 Perspective and Its Implications for Energy Sustainability" Sustainability 17, no. 11: 5035. https://doi.org/10.3390/su17115035
APA StyleTokarski, S., Urych, B., & Smolinski, A. (2025). National Energy and Climate Plan—Polish Participation in the Implementation of European Climate Policy in the 2040 Perspective and Its Implications for Energy Sustainability. Sustainability, 17(11), 5035. https://doi.org/10.3390/su17115035