Next Article in Journal
Visualisation and Thermovision of Fuel Combustion Affecting Heat Release to Reduce NOx and PM Diesel Engine Emissions
Next Article in Special Issue
Running Dynamics of Rail Vehicles
Previous Article in Journal
A Review and Case Analysis on Biaxial Synchronous Loading Technology and Fast Moment-Matching Methods for Fatigue Tests of Wind Turbine Blades
Previous Article in Special Issue
Acoustic Signature and Impact of High-Speed Railway Vehicles in the Vicinity of Transport Routes
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Use of Hybrid Photovoltaic Systems with a Storage Battery for the Remote Objects of Railway Transport Infrastructure

by
Olexandr Shavolkin
1,
Iryna Shvedchykova
1,
Juraj Gerlici
2,
Kateryna Kravchenko
2,* and
František Pribilinec
2
1
Department of Computer Engineering and Electromechanics, Institute of Engineering and Information Technologies, Kyiv National University of Technologies and Design, Nemyrovycha-Danchenka Street, 2, 01011 Kyiv, Ukraine
2
Department of Transport and Handling Machines, Faculty of Mechanical Engineering, University of Žilina, Univerzitná 8215/1, 0102632 Zilina, Slovakia
*
Author to whom correspondence should be addressed.
Energies 2022, 15(13), 4883; https://doi.org/10.3390/en15134883
Submission received: 25 May 2022 / Revised: 27 June 2022 / Accepted: 30 June 2022 / Published: 2 July 2022
(This article belongs to the Special Issue Running Dynamics of Rail Vehicles)

Abstract

:
The use of a grid-tied photovoltaic system with a storage battery to increase the power of objects of railway transport infrastructure above the limit on consumption from the grid with the possibility of energy saving is considered. The methods of analysis of energy processes in photovoltaic systems with a storage battery are used. They are added via the processing of archival data of power generation of a photovoltaic battery and computer modeling results. A technique of system parameter calculation to increase the power according to the given load schedule of the object at constant and maximum possible degree of power increasing is developed. The values of the average monthly generation of a photovoltaic battery at the location point of the object based on archival data are used. The principle of the control of power, consumed from the grid, according to the given values of the added and total load is developed. Using the basic schedule of added load power in connection with the graph of photovoltaic battery generation allows reducing the installed power of the storage battery. The additional reduction in the installed power of the photovoltaic and storage batteries is possible at the corresponding choice of the degree of power load increasing. The joint formation of current schedules with reference to the added power value and state of charge of the battery according to the short-term forecast of the generation of a photovoltaic battery is proposed. The value of added power at certain intervals of time is set according to the graph of actual generation of the photovoltaic battery, which contributes to the maximum use of its energy. With the average monthly generation of a photovoltaic battery in the spring–autumn period, the discharge of the battery during the hours of the morning load peak is not used. This reduces the number of deep discharge cycles and extends the battery life. The description of energy processes in steady-state conditions for the daily cycle of system functioning is formalized. On this basis, a mathematical model is developed in MATLAB with an estimation of the costs of electricity consumed from the grid. When modeling, archival data are used for days when the generation of a photovoltaic battery over time intervals is close to average monthly values. This makes it possible to evaluate the effectiveness of system management under conditions close to real during the year.

1. Introduction

Photovoltaic systems (PVSs) are the most common in the “green” energy sector. A considerable share of PVSs falls on local objects (LO) for various purposes, where hybrid solar power plants with connection to the alternating current distribution grid (DG) are used. This corresponds to the current trend of localizing consumption at the generation site [1].
The issue of localization of the consumption of energy, generated by PV, can be solved when using a PVS to increase the load power of the LO above the limit on consumption from the grid. Such an application of PVS can be in demand during the development (expansion) of facilities with an increase in consumption, when the possibilities of increasing the capacity of the existing connection to the power grid are exhausted.
PVS application can be useful for railway infrastructure facilities remote from the transformer substation, including those with the seasonal nature of the load (consumption). The simplified structure of the power supply of LO with a PVS and storage battery (SB) is shown in Figure 1. The implementation of this option may be cheaper than laying a new power transmission line and replacing DG equipment. The advantage of this solution is the possibility of reducing the cost of paying for consumption from the DG during the term of operation of the PVS and the possibility of autonomous operation in the case of DG disruptions.
This also applies to objects of extensive railway transport infrastructure, including remote objects on sections of the grid that are not currently electrified. The main task when using PVS for such facilities is to provide for their own needs. At the same time, the possibility of increasing their power when using existing DG is limited by the consumption limit. The issue of energy saving remains relevant. First of all, this concerns the reduction in electricity consumption from DG. The use of storage batteries in the PVS with modern methods of energy management [2] allows rationally redistributing the energy in the system in time. This also achieves a reduction in consumption from DGs and an increase in the reliability of the power supply of LO. Improving the performance of systems with renewable sources of electricity is an urgent task, which contributes to the further development of energy with distributed sources of electricity.

2. Literature Review and Problem Statement

The demand for the use of hybrid PVS with SB is confirmed by the fact that the electrical market is widely represented by various solutions of hybrid inverters [3,4], which are designed for LO. They have all the equipment for connecting a photovoltaic battery (PV) and SB, as well as sufficiently powerful software. They are designed for self-consumption of LO while reducing consumption from DG, and they provide an uninterruptible power supply function.
With a power consumption of LO in excess of 10 kW, it is advisable to use three-phase multifunctional inverters while maintaining a power factor close to 1 at the point of common coupling (PCC) to the grid [5,6,7,8,9,10,11,12]. This allows to unload the grid from reactive power and ensures the symmetry of loading the phases of the grid at an unbalanced load [9,10,11,12]. A previous study [13] presented a three-phase PVS with an SB with four converters with a common link of direct current (DC). In the DC link, a proportional–integral (PI) voltage controller (VC) was used. The controller set the currents of the battery and supercapacitor. The “multiconverter” provided a given active power with the proper quality of electricity, PV operation with tracking the maximum power point (MPPT), and extended battery life with hybrid storage. In [10,11], the structure of the control system of a multifunctional inverter of a PVS with an SB with voltage stabilization in the DC link with three VCs was considered. The VC controls the currents of the SB and PV, as well as current in the PCC. The structure changes in accordance with the mode of operation, and only one of the VCs is always used. Ensuring the efficiency of the use of hybrid PVS with energy storage for LO is usually associated with a reduction in the cost of consuming electricity from the grid and an increase in the reliability of the power supply [14]. With a wide range of changes in PV generation during the year, cost reduction is achieved by overestimating the power of PV relative to the load power. This allows providing acceptable indicators in cloudy weather and winter.
PV generation changes significantly during the day and year. Therefore, the increase in the efficiency of PVS energy management is associated with the use of the forecast of PV generation [15,16,17,18,19]. The issues with obtaining an accurate forecast were considered in a number of studies, particularly [15,16]. Recently, web resources have been made available that provide a forecast with a discreteness of 0.5 h or less, including an individual one at the location [20,21]. For the application without generation to the grid, the main purpose of the forecast is load planning for the next day and the possibility of adjustment when it changes [19].
Certain opportunities to reduce the cost of paying for electricity consumed by LO from DG are provided by taking into account the tariffication of payment [19,22,23,24,25]. Features of the implementation of PVS in the application of static and dynamic tariffs were considered in [22].
When using PV for the needs of LO (without generating electricity to the grid), it is achievable to reduce the cost of electricity consumption from DG by up to five times at one tariff rate (up to seven times at wo rates) in the summer [19,26]. In winter, the reduction is insignificant—around 1.2 times. A general estimation of cost reduction for the year is not given. In [27], along with meeting the needs of the LO, the use of the planned generation of electricity in the grid during peak hours was considered. This allowed significantly reducing electricity costs. Overall estimation of cost reduction during the year was not given. Regardless, there was still an underutilization of PV energy in the summer.
An effective tool for assessing the efficiency of the energy management of a PVS with an SB is mathematical modeling [26,27,28,29]. Modeling of a hybrid system with a supercapacitor for the PV generation period was considered in [29]. Modeling of energy processes in the daily cycle with an estimate of the cost of paying for electricity consumed from the DG was considered in [26,27]. The use of archival data on PV generation [30] allowed studying the operation of the system in different weather conditions with an estimation of the cost of electricity, consumed from the DG.
The possibilities of PVS use for power increase for infrastructure objects, remote from the transformer substation, over the limit of consumption have not been sufficiently studied. This is related to the determination of parameters and limiting capabilities in different seasons of the year, the features of the formation of the SB state of charge in the process of operation, and the realization of the principles of added power formation at maximum use of PV energy. In this case, it is possible to reduce the installed power of the PV and the battery. An important role in assessing the capabilities of the system is performed by mathematical modeling.
Thus, the purpose of the article is to develop principles for the use of PVS with SB to increase the power of the LO above the power limit for consumption from the grid with the maximum use of PV generation.
The main objectives of the research are as follows:
-
to study the possibilities of increasing the load power of the LO above the power limit for consumption from the grid during the year;
-
to justify the choice of PVS parameters with the formation of the graph of added power according to the accepted load schedule of the LO with a decrease in the installed power of the PV and battery;
-
to develop principles for the implementation of the management of PVS using the forecast of PV generation;
-
to perform an assessment of the system’s capabilities in the daily mode for different seasons of the year using mathematical modeling.

3. Methodology of Research

A study of ways to improve the control mechanism of the PVS with an SB for increasing the power of the LO was carried out on the basis of analytical methods in electrical circuits. The results of processing statistical data on the PV generation for a given point of location of the object were also used. A proportional increase in power to the original load schedule was adopted. As original, the load schedule characteristic of objects with a predominance of day loads, with peak loads in the morning and evening and a decrease in the load at night, was considered. The basic schedule of power, added and provided by the PVS, was adopted in accordance with the PV generation schedule. The maximum value of the power increase factor in winter takes into account the possibility of ensuring the battery charge within the power limit for consumption from the grid. On this basis, the energy capacity of the battery was determined, followed by an assessment of the possibilities for increasing the load power, taking into account the average monthly PV generation. The choice of a fixed value of the degree of power increase was carried out while taking into account the use of PV energy and cost reduction. The control system of the PVS converter unit was implemented on the basis of a classic double-loop structure with voltage stabilization in the DC link. When forming the SOC(t) (state of charge) of the SB schedule, a limit of DOD ≤80% (depth of discharge) was introduced with one deep discharge per day in the spring–summer–autumn period. The technique to calculate the reference of added power for maximum use of PV energy was realized on the basis of an analysis of the average monthly PV generation by time intervals for the taken load schedule. Analysis of energy processes in the system “DG–PVS with SB–LO load” was carried out for the daily cycle without taking into account transient processes and higher harmonics in energy converters. Energy losses were accounted for through efficiency. The properties of the SB were considered in accordance with the characteristics of the manufacturer. PV generation was estimated on the basis of monthly average values for given time intervals during the day. Data of PV generation were obtained for the location point of the object when processing archival data for 5 years. The modeling of energy processes was performed using MATLAB software package using real archive graphs of PV generation. The days were chosen when PV generation by time intervals was close to the average monthly values. The model was completed on the basis of analytical expressions for steady-state operating modes, which correspond to generally accepted proven calculation methods. When the operating modes of the system changed, the corresponding calculated expressions were used at time intervals per day.

4. The Results of the Research on the Use of PVS with SB to Increase the Power of LO

The option of PVS with an SB with a grid multifunctional inverter VSI (Figure 2) was considered. The middle pin (n) of the VSI link DC was connected to the neutral connection point of the DG. This allowed ensuring the equalization of power consumption from the grid by phases under unbalanced load LO [9,10,11]. This also made it possible to control the active power Pg in the PCC. The structure of the PVS included the following elements: a DC voltage converter PV (CPV) with a transistor key for measuring the current of the PV short-circuit [10], and a DC voltage converter battery (CSB). The converter unit was controlled by a control unit (CU) connected to the programmable control unit (PCU). Communication with the web resource to obtain forecast data was provided by a Wi-Fi WFM module.
When solving the issue of increasing the power of the LO, the general approach changes somewhat; the DG becomes an auxiliary source of energy of limited power. As originally proposed, the use of a load schedule was considered in accordance with the standard distribution of peak loads [19,26] for objects of the utility sector and the nondomestic sector with a single-shift mode of operation. The following distribution of load intervals was accepted: night tariff zone in the period May–August (t7 = 24.00, t1 = 7.00), day tariff (t1 = 7.00, t2 = 8.00), (t3 = 11.00, t5 = 20.00), (t6 = 23.00, t7 = 24.00), peak load zones (t2 = 8.00, t3 = 11.00), and (t5 = 20.00, t6 = 23.00); in the period autumn–winter–spring (t1 = 7.00, t2 = 8.00, t3 = 10.00, t5 = 17.00 and 18.00, t6 = 17.00 and 18.00, t7 = 24.00). An additional point of time t4, was also used, corresponding to the transition to an evening decrease in PV generation. This time during the year varied from t4 = 16.00 in June to t4 = 14.00 in December.
Increasing the power of the LO load in the daytime assumes that the total power PLC of the LO load is defined as PLC = PLg + PC (where PLg is the power which is provided by consumption from the grid (PLg does not exceed the limit on consumption PLIM), and PC is the added power, generated by the inverter due to the energy of PV and SB). We can take PLg = PLIM; then, with an increase in PL; the possible value of PLC grows with constant consumption from the grid. If the actual load power is less than PLC, the electricity consumption from the grid is reduced.
The value of the energy generated by PV during the year varies widely (Table 1). Table 1 shows the data [30] on the average monthly generation of PV per day WPVAVD at power PPVR = 1 kW for the Kyiv location: latitude (decimal degrees)—50.451, longitude (decimal degrees)—30.524. Similar data are given for the city of Žilina WPVAVDZ (latitude (decimal degrees)—49.224, longitude (decimal degrees)—18.748). In winter, the PV generation in Žilina is slightly higher. In Table 1 (in parentheses), monthly energy values per day (W*PVAVD) and at time intervals during the day (WPV23, WPV34, and WPV45) are also presented for Kyiv. The energy values without parentheses correspond to the selected days when the generation was close to the monthly average. These values were obtained from archival data of PPV generation in Kyiv [30] for the period 2012–2016.
The value of the added load power PC was determined on the basis of the average monthly daily generation of WPVAVD ≈ 2500 W in the transitional seasons of the year (Table 1): October and March. In November–February, the load, provided by PV, decreased. The average value of power in the daytime (PAVD = WPVAVD/tD, where tD is the length of the day) was about 200 W.
We took the basic load schedule (average PL values by time intervals) taking into account peak loads in the morning and evening with a decrease in load after t4 until the evening peak, e.g., PL23B = 200 W (PLAVD), PL34B = 180 W (0.9 PLAVD), PL45B = 160 W (0.8 PLAVD), and PL56B = 200 W (PLAVD). The total night load of LO could be taken from the condition PLg62 = PLIM − PB (we took PLIM equal to the peak power PLIM = PL23B = 200 W, PB = UBIB—power, consumed from the grid to charge the SB (UB and IB—voltage and current of the SB)). At the same time, PLg62 ≥ PLMIN, PLgMIN = 0.2PL56 in summer, and PLgMIN = 0.3PL56 in winter. The total energy transmitted by the inverter to increasing power (PL) at the interval (t2, t6) was WL26 = 2740 Wh in summer, WL26 = 2580 Wh in autumn–spring, and WL26 = 2410 Wh in winter.
The effective use of the SB’s capabilities for the redistribution of energy in the system involves the formation of the SOC(t) dependency Q ( t ) ( Q = 100 Q / Q R , Q = Q 0 + I B d t , Q R = CB—the rated value (100%) or capacity (Ah) of the battery, Q 0 —the initial value). Increasing the power during peak hours in the morning and evening, when the PV generation is small, implies a deep discharge of the SB. That is, we have two deep discharges per day. In these conditions, the use of lithium-ion batteries is preferable.
Two variants of implementation were considered: (1) with a maximum increase in power in accordance with PV generation, which is available for the consumers with seasonal load; (2) with a constant increase in power during the year.
For variant (1), it was assumed that the planning of load using the day-ahead forecast was possible.
For calculation of the value of SB energy capacity, in the interval (t4, t6), the PV generation WPV45 is small, and the increase in power is achieved mainly due to the energy of the SB. At the same time, the energy balance is determined by the following expression:
0.01 Δ Q 46 W B η C η B = P C 45 ( t 5 t 4 ) + P C 56 ( t 6 t 5 ) W P V 45 η C ,
where WB is the SB energy capacity (WB = UBCB), Δ Q 46 = Q 4 Q 6 , ηC is the general efficiency of the SB voltage converter and grid inverter, and ηB is the efficiency of the SB.
WB is calculated from the condition of the functioning of the added power of the load during the evening peak hours (t5, t6) and on the intervals (t4, t5), when PV generation is significantly reduced. This is most typical in winter, with a longer evening peak (4 h). The limitation is to ensure the possibility of the battery charge and the operation of the load at night within the framework of PLIM. When WPV46 = 0, the value of the energy capacity of the battery SB is
W B = W C 46 0.01 Δ Q 46 * η C η B ,
where WC46 = WL46 (ρ − 1); ρ > 1 indicates the degree of increase in the load power.
It was assumed that the night load in winter also proportionally increases PLg = ρ 0.3 PLIM. The possible value for the battery charge in the framework of limit is denoted as
Δ W B 62 = ( t 2 t 6 ) P L I M ( 1 0.3 ρ ) .
Alternatively,
Δ W B 62 = W L 46 ( ρ 1 ) Δ Q * 62 Δ Q * 46 ( η C η B ) 2 .
The maximum value ρMAX in the interval (t4, t6) can be determined in accordance with Equations (2) and (3). In this case, at DOD6 ≤ 80%, ρMAX = 1.721. Accepting ρ = 1.7, WB = 1164 Wh. At DOD6 ≤ 90%, the value is WB = 1034 Wh. The average value WB = 1099 Wh (corresponding to, for example, CB = 43 Ah at UB = 25.6 V) can be accepted. The resulting value is sufficient to ensure the added power at ρMAX = 1.7 and average monthly PV generation in December in the interval (t2, t6).
However, for the same value PLC = ρPL and PLg ≤ PLIM, the different variants of reference of the added power PC for the interval (t2, t6) (in Table 2, data are presented for ρ = 1.7) are possible. This allows planning PC(t) according to the conditions.
Above the variant, va was considered. At minimal PV generation (in winter), variant vb ensured the biggest value ρ, whereby PC26(t) = ρPL26(t)PLIM. In this case, WC46 = ρWL46 − PLIM(t6 − t4), and the value ΔWB62 can be expressed as
Δ W B 62 = P L I M ( 6 ρ ( t 6 t 4 ) ) Δ Q * 62 Δ Q * 46 ( η C η B ) 2 .
We get values ρMAX = 1.78 and WB = 968 Wh (corresponding to, for example, CB = 37.8 Ah at UB = 25.6 V). The advantage of this variant is the minimal value of PC in the interval (t4, t6) when the PV generation is minimal.
Variant vc is included in Table 2. This variant is more tied to the PV generation schedule during the day.
There are days in winter when WPVD 60 Wh. In this case, it is possible to use a night charge of the battery up to 100%, followed by a discharge during the day (from 8:00 a.m. to 9:00 p.m.) at DOD6 = 10%. This allows using the energy ΔWB26 = 768 Wh (at WB = 968 Wh) in the load. Accordingly, ρ = (ΔWB26 + WL26LIM)/WL26LIM = 1.3. At small values of WPVD (for example, at WPVD 300 Wh), there is the possibility to redistribute the energy of SB by intervals. For example, the degree of increase in power in peak hours can be saved without increasing from 10:00 a.m. to 5:00 p.m. Then, for example, 0.3 ΔWB26 can be used in the morning peak, and, taking into account the duration, 0.6ΔWB26 can be used in the evening peak. This allows ensuring ρ ≈ 1.6 in intervals (t2, t3) and (t5, t6).
In the period spring–autumn, there is the possibility to increase ρ. Determination of ρ is carried out in the accordance with forecast data of PV generation on the next day on the basis of the balance of energy in the intervals (t2, t6) and (t4, t6).
It is possible to calculate ρ for the interval (t2, t6) as follows:
ρ 26 = W P V 26 η C + Δ W B 26 W g R 26 + P L I M 26 W L 26 ,
where WgR26 indicates a decrease in energy consumption from the grid, and W L I M 26 = P L I M ( t 6 t 2 ) .
Depending on the PV generation, the implementation is possible (a) with the discharge of the SB without a decrease in consumption from the grid, (b) without the discharge of the SB and a decrease in consumption from the grid, (c) with minimal discharge of the SB and a decrease in consumption from the grid, or (d) without the discharge of the SB and a decrease in consumption from the grid. Variant (a) is specific to winter with small PV generation, when ρMAX = 1.7 is accepted.
For interval (t4, t6),
ρ 46 = k W P V 46 η C + Δ W B 46 W g R 46 + P L I M 46 W L 46 ,
where k is a coefficient, taking into account the use of PV energy for consumption, and ΔWB46 corresponds to DOD = 80%.
The value of k takes into account that, when the SB is fully charged by the time t4, only part of the PV energy is used for consumption by the load. The rest of the energy provides a reduction in consumption from the grid. Thus, k = 1 is accepted if WPV45 · ηC < WC45, while k = 0.5 is accepted if WPV45 · ηCWC45.
Furthermore, ρ46 can be defined at the decrease in consumption in Equation (6) when WgR46 = 0. For March (Table 1), ρ46 = 1.8. Compared with the value ρ26 = 2.02 according to Equation (6) for option (b), we accept the smaller value. In this case, with ρ = 1.8, it is possible to implement option (c). Thus, for ρ = 1.8, we find the following value:
Δ Q * 23 = W P V 23 η C W C 23 0.01 W B η C η B .
For March ΔQ*23 = 17% > 0, i.e., the SB state of charge increases, and the night battery charge is not needed. Then, in accordance with Equation (6), we have a decrease in consumption on the order of 572 Wh. With the average monthly values of PV generation for the summer period, ρ = 1.95 is achievable.
A graph of the added power PC(t) and the state of charge of the SB Q*(t) is presented in Figure 3 in accordance with the obtained value of ρ. We consider options vb and vc when using the PV energy WPV forecast data over time intervals. At the same time, it is desirable to (1) use the lowest possible power consumption at night (until 8:00 a.m.) per battery charge, and (2) ensure the condition Q*4 → 100%, taking into account the reduction in PV generation in the evening. A prerequisite is the maximum use of PV energy.
Reference to the initial value Q*2R is carried out in accordance with values ΔQ*23 and ΔQ*24 (calculated similarly to Equation (8)). If ΔQ*24 ≤ 0, then Q*2R = 100% (curves 1, 5, and 6 in Figure 3). In this case, when ΔQ*24 > 0 and ΔQ*23 ≤ 0, then Q*2R = (100 − ΔQ*24) ≥ 40% (curve 2 in Figure 3). If ΔQ*24 > 0, ΔQ*23 > 0, and WPV23 · ηC/W1C23 < 1.5 (W1C23 is the value for the basic schedule with given ρ), then Q*2R = (100 − ΔQ*24) ≥ (Q*6 + δ) (curve 3 in Figure 3, δ = 10–15%). In all cases, the reference of the added power is PC23 = P1C23.
If ΔQ*24 > 0, ΔQ*23 > 0, and WPV23 · ηC/W1C23 ≥ 1.5, then PLC23 ≥ (PC23 = PPV23 · ηC) ≥ P1C23, which is given in accordance with PV generation. In this case, the SB charge (curve 4 in Figure 3) is not carried out. It also does not use the battery charge at night, but there may be some battery charge before 8:00 a.m. (sunny morning).
The PC34 value in the interval (t3, t4) is P C 34 = W P V 34 η C 0.01 Δ Q * 34 W B η C η B ( t 4 t 3 ) P L C 34 , where ΔQ*34 is defined using values Q*2R and ΔQ*23, as described above.
In the interval (t4, t5) with a large PV generation, the state of SB charge can increase (curve 7 in Figure 3), be unchanged (≈100%), or decrease. The possibility of an increase is excluded by increasing the PC45, which is carried out automatically. The formation of the degree of discharge in the interval (t5, t6) is carried out in the mode of regulation of the SB current.
The battery charge when Q* ≥ Q*d = 90–92% is reached at a constant value of the voltage [31]. In this case, the battery current is determined by the charge curve and is significantly reduced. Thus, the ability of the SB to receive energy is limited. Therefore, when Q* ≥ Q*d, the value of PC is set according to the actual PV generation as PLCPC = (PPV · ηC − PB) ≥ P1C. The limitation PLCPC is implemented by reducing the PV generation. The introduction of this mode allows ensuring more complete use of the PV energy, particularly when the calculated value of PC34 is less than required.
Figure 3 also shows a graph for the case when the PV energy is not enough to charge the battery up to 100% (curve 5) and for the case when the PV generation is close to 0 (curve 6). In these cases, the task is realized to support the load during peak hours.
Consider the variant with the constant increase of power during the year. For the choice of value ρ, consider the option vb with reference to the added power when the value WB is minimal. According to Equations (2) and (5), when ρ increases, WB also increases. An important issue is the underutilization of the installed PV power at high solar activity in the summer. To estimate, we introduce the PV energy utilization factor,
k P V = W C 26 + W g R 26 Δ W B 26 m P W P V 26 η C ,
where WgR26 indicates a decrease in energy consumption from the grid, WC26 is the energy consumed by the added load, and mP is a coefficient of PV power recalculation relatively installed power PPVR = 1 kW.
The value of WgR26 can take place during hours of high daytime solar activity tda, when PPV·ηC > PC + PB (PB = UBIB is the power of SB charging). To exclude the generation of energy into the grid, the restriction PgR ≤ PLIM is used, which is achieved by regulating (reducing) the PV generation. In the limited case, WgR26 = PLIM · tda (tda = 6 h, from 10:00 a.m. to 4:00 p.m.).
The value of ΔWB26 in the summer period with the average monthly PV generation is taken as equal to ΔWB26 = 0 (nighttime battery charging is not required).
To assess the efficiency, we use the coefficient of cost reduction for electricity consumed from the grid (at one tariff rate and full use of PV energy). For the winter period (December), when the power increase in the interval (t2, t6) is achieved while maintaining the consumption from the grid within the limit,
k E = W L C W g = W L C W L C + Δ W B 26 / ( η C η B ) 2 m P W P V η C ,
where W L C = W L C 62 + W C 26 + P L I M ( t 6 t 2 ) is the total energy consumed by the load.
At mP = 1, with an increase in ρ and, accordingly, WC26, the value of kE decreases, and the value of kP increases. If the installed power (mP < 1) is reduced, then there is a reverse change in the coefficients.
Consider the option with ρ = 1.6 in comparison with the variant for ρ = 1.7 discussed above. This allows reducing the WB value from 968 Wh to 800 Wh (by 21%). Almost the same value of kE for December, in this case, can be obtained with mP = 0.86 and an increase in kP to 0.71 instead of 0.679 (in June). If we recalculate to the same load power, we get a decrease in the installed PV power by 9.4% and in the energy capacity WB of the SB by 14%. At the same time, it remains possible to increase the power to ρ = 1.8.
The reference of the value of added power and the formation of a graph of the state of charge of the SB are carried out according to the method discussed above.
A simplified structure of the PVS control system is shown in Figure 4. The system of automatic control of the CU converter unit is implemented according to well-known principles with voltage stabilization in the DC link Ud at the VSI input [10,13]. This is provided by three proportional–integral (PI) voltage controllers (VCs): VCIPV forms the PV current reference; VCIB forms the SB current reference; VCIg forms the reference of the current at the point of common coupling to the grid. The system (Figure 4) contains three channels:
  • PV generation control. This channel contains a control unit CPV (CSCPV), which provides the processing of the reference value of the current I1PV, current limiting unit LU1 with adjustable limit, and switch S2 for current settings in mode MPPT (position 2) or from VCIPV when regulating generation (position 1). Current limiting at the level IPVM = (0.9 ÷ 0.92)ISQ excludes PV operation in the short-circuit mode [10];
  • Charge control of SB. This channel contains a control unit CSB (CSCSB), which provides the processing of the reference value of the current I1B, current limiting unit LU3 charge and discharge of SB, and switch S3 for current settings from VCIB (position 2) or PCU (position 1);
  • Grid current Ig control (reference of power consumed from the grid). This channel contains a reference current unit and an inverter current control loop iC (RCU + CCL) and input of reference of the amplitude of the grid current (I1gm), which, via switch S1, connects to VCIg (position 2) or PCU (position 1). Limitation unit LU2 has a lower I1gm≥ 0, top I1gmLIM limits. Unit (RCU + CCL) provides ig in PCC taking into account the phase currents of the inverter iCa,b,c, and load iLa,b,c [10,11].
The control of switches in the structure and the formation of current references are carried out by the PCU. The PCU also processes the prediction data according to the WFM block signal and the specified time intervals (TH). The phase lock loop (PLL) and offline control PVS channel when the mains voltage is turned off in Figure 4 are not shown (current reference of inverter phases i1Ca,b,c; in this case, a separate load voltage controller is set [10]).
The control principle (Table 3) is based on the control of active power, consumed from the grid (in PCC) Pg = PLC − P1C (P1C is the value of the added load power at the current time interval, and PLCi is the value of the active load power according to the measured values of currents and phase voltages) at PLIM ≥ Pg 0. The initial parameters are the recommended schedule (maximum average value) PLCR(t) and the base schedule PCB(t) for the accepted value of ρ, and the calculated schedule P1C(t). There is a possible situation when PLC ≠ PCR. With this in mind, deviation compensation ΔPLC = (PLCPLCR) ≥ 0 is used in the reference P1C = P1C + ΔPLC. The operating modes of the control system by intervals and the used controllers are given in Table 3. Calculation expressions for steady modes are given in the description of the model of energy processes.
Consider the functioning of the system, starting from the intervals (t2, t3). PV operates in maximum power mode (MPPT). The SB current is set by the controller VCIBI1B. Then, I1gm = √2Pgi/3Ugph (Ugph—phase voltage of the grid) is defined according to Pg = PLC − P1C23 and is supplied to the input of the current set unit RCU + CCL. When the load is reduced, Pg decreases; when the load is increased, Pg also increases. If WPV23·ηC/WC23 ≥ 1.5, then the value of PC is set by PV generation under the condition PCL ≥ (PC = PPV · ηC) ≥ P1C23. In this case, at PPV·ηC < P1C23, there is PC = P1C23. At PPV · ηCP1C23, there is PPVηC = PC and the current of SB charge decreases to 0; when PPVηCPLC, the SB charge is restored.
When switching to the interval (t3, t5) and Q* < Q*d, the operating mode is saved. When Q*Q*d = 90–92%, the SB current is determined by the charging characteristic IB(Q*); if the set value I1B > IB(Q*), then VCIB goes into saturation. The battery cannot consume all the energy. This leads to an increase in the voltage Ud on the capacitors in the DC link of the inverter. If PLC > PCPCB, then, upon reaching the switching threshold (Ud + ΔU), the VCIg controller (g4 mode) is activated and reduces I1gm (Pg). If PPVηCPLC, then the VCIPV controller (g3 mode) is activated and I1PV (PPV) is reduced. Thus, we have two conditions for switching of controllers (excluding the influence of transients).
In the interval (t5, t6), the discharge of SB is carried out with current (given by controller VCIB).
I B 56 R = 0.01 C B ( Q * 5     Q * 6 ) ( t 6 t 5 ) .
The added power is set in accordance with an average value of SB voltage UBAV as PC56 = IB56R·UBAV + ΔPLC, if ΔPLC = (PLCPLCR) > 0.
For the night period in the interval (t6, t2), the reference of the current of SB charge is
I B 62 R = 0.01 C B ( O * 2     Q * t ) ( t t 2 ) ,
where Q*t is the current measured value, for example, with a resolution of 1 h.
In the period spring-autumn, the SB charge in the morning is possible from PV at PPV·ηC ≥ 0.
Referencing of the value Q*2R and planning of the recommended (maximum) load PLCR is carried out according to the forecast for the next day. The given values of the added power in the intervals are specified at the beginning of the day in accordance with the current forecast of PV generation. Subsequently, with an interval of 1 h, the adjustment is carried out.

5. Modeling of Energy Processes in the Daily Cycle

The initial data for modeling were from an archive of PV generation on the mode of maximum power PPVM(t). Accordingly, the values of ρ, Q*2R, the base PCB(t) schedule for the accepted value of ρ, and the calculated P1C(t) schedule were calculated. The load power values of the recommended PLCR(t) and the actual values of PLC(t), PCB(t), P1C(t) are given in tabular form. The time intervals are given by the variables t12, t23, t34, t45, t56, t67, and t71, which take on the value 1 at the corresponding time. The following auxiliary variables are also used:
q = { 1 ,   if   Q * Q * d   0 ,   if   Q * < Q * d   , p v = { 1 ,   if   P P V M η C P 1 C   0 ,   if   P P V M η C < P 1 C   , l c = { 1 ,   if   P C P L C   0 ,   if   P C < P L C   ,
c = { 1 ,   if   P LC P P V M η C P 1 C 23   0 ,   if   P LC < P P V M η C < P 1 C 23   , s = { 1 ,   if   P P V M η C > 0   0 ,   if   P P V M η C 0   , h = { 1 ,   if   ( P L C P L C R ) > 0   0 ,   if   ( P L C P L C R ) 0   ,
q c = { 1 ,   if   P L C > P C   0 ,   if   P C P L C   ,   w = { 1 ,   if   W P V 23 η C / W C B 23 1.5 0 ,   if   W PV 23 η C / W C B 23 < 1.5  
The variable w is precalculated. To measure the values of Q*t, Q*5, sample-and-hold schemes are used.
The current PV generation takes into account the following regulation:
P P V η C = P P V M η C ( q ¯ + q c ) + ( P C + P B ) q l c ,  
where PB = UBIB.
The value of added power is
P C = P L C t 62 + P 1 C ( t 23 w ¯ + t 34 q ¯ + t 45 p v ¯ ) + P C 56 t 56 + ( P 1 C 23 c ¯ + + P L C c ¯ l c + P P V M η C c ) w t 23 + ( ( P P V M η C P B ) q l c ¯ + P L C q l c ) ( t 34 + t 45 ) ,
where PC56 = IB56R·UBAV + h(PLC − PLCR).
The power consumed from the grid is P g = ( P L C P C ) t 26 + ( P L C + P B ) t 62 .
The current of the SB is
I B = t 62 ( I B 62 R s ¯ + P P V η C U B s ) + ( q ¯ + q c ) t 25 P P V η C P C U B + I B ( Q * ) q q c ¯ t 25 + t 56 P C 56 U B .
The SB model is constructed according to the principles set in [26,27]. Data sheets given by the manufacturer were used [31]: charge characteristics IBC( Q ) and UBC( Q ) at IB 0 and discharge characteristic UBR( Q ) at IB < 0, set in tabular form. The current can be calculated as
I B = { I B ,   if   Q * < Q * d   I B ( Q * ) ,   if   Q * Q * d .
The SB state of charge (SOC) taking into account energy losses is
Q = Q 0 + I 1 B d t ,
where I1B = IB · ηB if IB ≥ 0, and I1B = IB/ηB if IB < 0.
To estimate the reduction in electricity costs at a single tariff rate (taking its value equal to 1), the kE = WL/Wg coefficient was used ( W L = 0 24 P L C d t is the energy consumed by the LO load per day (without taking into account the energy on the SB charge at night), and W g = 0 24 P g d t is the energy consumed by LO from the grid).

6. Simulation Results

To set the PV generation, archival data were used [30] with the selection of days when the generation by intervals was close to the average monthly generation (Table 1). These days correspond to the energy values without parentheses in Table 1. Values Q 6 , kE, and ρ for the case when PLC 2PLIM and the actual value of total load power PLC = PLCR are given in Table 4.
Oscillograms PLC, PLCR, Pc, PPVM, PPV, Q , IB, and Pg (for clarity, Pg is shown as negative) are given as described below.
  • In Figure 5 for the December day with a total generation twice below the average (WPV = 500 Wh). In this case, kE = 1.04, p = 1.5 (PPVR = 0.86 kW, WB = 800 Wh);
  • In Figure 6 for the July day with a total generation in 3.3 times below the average (WPV = 1320 Wh). In this case, kE = 1.22, p = 1.6 (PPVR = 0.86 kW, WB = 800 Wh);
  • In Figure 7a for the May day with the generation, corresponding to the average monthly values at PLC = PLCR, PPVR = 1 kW, WB = 968 Wh, and at limit values ρ = 1.95 with kE = 2.618;
  • In Figure 7b for the May day with the generation, corresponding to the average monthly values at PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and at limit values p = 1.8 with kE = 2.356;
  • In Figure 7c for the May day with the generation, corresponding to the average monthly values at PLCPLCR, PPVR = 0.86 kW, WB = 800 Wh, and p = 1.6 with kE = 2.795;
  • In Figure 8 for the September day with the generation, corresponding to the average monthly values at PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and ρ = 1.6 with kE = 2.
Changing the reference of the added power PC23 in the interval (t2, t3) from a fixed calculated value to the value corresponding to the actual PV schedule in the spring–autumn period allows increasing kE by 2–4% with the exclusion of SB discharge.

7. Discussion of the Results of the Study on Increasing the Power of the LO Using PVS with SB

Increasing the load power of the LO above the limit of power consumption from the grid while reducing the installed power of PV and SB and decreasing the cost of paying for electricity, consumed by the LO, from the DG is possible due to the following:
-
Use of the basic schedule of added power, tied to the PV generation. This reduces the energy required for its implementation. This allows increasing the degree of power increase while reducing the energy capacity of the SB;
-
Limiting the degree of power increase at an intermediate value with a decrease in the installed power of the PV and SB. This provides an improvement in the use of PV energy without increasing the cost of electricity, consumed from the grid;
-
Referencing the current value of the added load power and the SOC value of the battery at time intervals, taking into account the predicted and actual PV generation. Due to the change in certain time intervals of the added power reference from the calculated value to a value that repeats the law of the change in the PV generation power, this contributes to more complete use of the PV energy;
-
Exclusion of the SB charge at night with the average monthly PV generation in the spring–summer–autumn period helps to reduce electricity consumption from the grid. This excludes battery discharge during the hours of the morning load peak, which helps to reduce the number of battery discharge cycles and increase its service life.
This article is a development of previous studies [19,26], which considered increasing the efficiency of hybrid PVS with SB for the needs of local facilities. This was achieved by reducing the cost of electricity consumed from the grid when using the PV generation forecast. A common problem is the significant overestimation of the PV power in relation to the load power of the LO, which is necessary for use in conditions of low PV generation.
As a result, even with medium PV generation, there is a significant underutilization of PV energy with the need for regulation of PV generation. A feature of the proposed solutions is a change in the general approach to the use of PV and SB energy when the load power, added to the limit, is formed. Directed formation of the graph of added power allows reducing the installed power of PV and SB.
There are certain limitations regarding the use of the results of the work, as described below.
-
An object was considered with the main load in the daytime in the presence of peak loads in the morning and evening hours. At the same time, it is possible to charge the SB at night within the limit on consumption from the grid;
-
The possibilities of increasing power are seasonal in nature with a maximum value in the period spring–summer–autumn;
-
The optimal choice of values for the degree of increase in power (ρ) and the installed PV power (mP) involves taking into account many factors, including the costs of acquisition and ongoing maintenance. Such a task was not set in this work, and the approach was simplified for evaluation;
-
The assessment of a possible reduction in the cost of paying for electricity during the year was somewhat simplified and was performed for one tariff rate. We considered the days when the PV generation corresponds to the average monthly values for the accepted time intervals;
-
The implementation of the control system assumes an “open” structure of the relevant channels of control;
-
When modeling, it was assumed that the graph of the power generated by the PV corresponds to the forecast and does not change during the day.
Further development of this work is connected with the optimization of system parameters. It is also required to study the possibilities of correction of deviations in the values of the actual PV generation according to the forecast data and possible changes in the current forecast during the day.

8. Conclusions

With the selected parameters of the PVS, it is possible to increase the power of the LO over the limit for consumption from the grid up to 1.7–1.95 times. This depends on the average monthly PV generation of during the year. Limiting the degree of power increase to a value of 1.6, when choosing the parameters, allows reducing the installed power of the PV and SB. The possibility of increasing the degree of power increase to a value of 1.8 (if necessary) remains in this case.
It is advisable to select the parameters of the PVS on the basis of the data on the average monthly PV generation for the taken schedule of the load. It is possible to use archival data from web resources with open access at any point location of the object. The ratio of PV power and added load power is determined on the basis of PV generation in the transitional seasons (in this case, March and October). The energy capacity of the SB is determined by the power of the added load from the condition of the sufficiency of its operation in the pre-evening hours and evening peak hours with a given limitation of the DOD battery. The use of the basic schedule of the added power with reference to solar activity, while maintaining the resulting power of the LO, makes it possible to reduce the energy capacity of the SB. Therefore, when setting the degree of power increase ρ = 1.7 for winter, the energy capacity can be reduced by 13.5%. Limiting the value of ρ at the level of ρ = 1.6 allows reducing the installed power of the PV and the SB. When converted to the same total load power, the reduction for PPVR is 9.4%, and that for WBR is 14%.
The principle for controlling the power consumed by the LO from the grid in accordance with the reference value of the added load power and the total load power of the LO was developed. The reference of the value of the added power can be determined from the condition for the formation of the SOC(t) graph of the SB according to the PV generation forecast data.
At the same time, at certain time intervals, reference of the value of the added power can be carried out according to the schedule of the PV generation. This contributes to the maximum use of its energy. With the average monthly PV generation in the spring–autumn period, the SB discharge during the hours of the morning load peak is not used. Accordingly, the nighttime SB charge from the grid is not used. This helps to reduce consumption from the grid and reduce the number of deep discharge cycles, which contributes to longer battery life.
On the basis of a formalized description of energy processes in steady-state conditions for the daily cycle of the system’s functioning, the simulation of the system was completed. The simulation results showed that choosing the PVS parameters on the basis of ρ = 1.7 by setting ρ = 1.7–1.95 depending on the average monthly PV generation reduced the cost of electricity, consumed from the grid, for one rate of payment by 1.1 to 2.68 times. When choosing the PVS parameters on the basis of ρ = 1.6 and a constant degree of power increase during the year, it is possible to reduce electricity costs by up to 7% in the summer.

Author Contributions

Conceptualization, O.S., I.S. and J.G.; methodology, O.S., I.S. and J.G.; validation, O.S. and I.S.; formal analysis, I.S. and K.K.; investigation, O.S., I.S., K.K. and F.P.; resources, I.S. and K.K.; data curation, O.S. and I.S.; writing—original draft preparation, O.S., I.S. and F.P.; writing—review and editing, J.G.; visualization, I.S. and K.K.; supervision, J.G. All authors have read and agreed to the published version of the manuscript.

Funding

This publication was issued thanks to support from the Cultural and Educational Grant Agency of the Ministry of Education of the Slovak Republic through the projects “Implementation of modern methods of computer and experimental analysis of properties of vehicle components in the education of future vehicle designers” (Project No. KEGA 036ŽU-4/2021) and “Development of advanced virtual models for studying and investigation of transport means operation characteristics” (Project No. KEGA 023ŽU-4/2020). This research was also supported by the Slovak Research and Development Agency of the Ministry of Education, Science, Research, and Sport of the Slovak Republic in Educational Grant Agency of the Ministry of Education of the Slovak Republic through the project “Investigation of the properties of railway brake components in simulated operating conditions on a flywheel brake stand” (Project No. VEGA 1/0513/22).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Acknowledgments

This work was supported by the Ministry of Education and Science of Ukraine in the joint Ukrainian–Slovak R&D project “Energy management improvement of hybrid photovoltaic systems of local objects with storage batteries” (0122U002588).

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Rao, B.H.; Selvan, M.P. Prosumer Participation in a Transactive Energy Marketplace: A Game-Theoretic Approach. In Proceedings of the IEEE International Power and Renewable Energy Conference, Karunagappally, India, 30 October–1 November 2020. [Google Scholar]
  2. Khezri, R.; Mahmoudi, A.; Aki, H. Optimal planning of solar photovoltaic and battery storage systems for grid-connected residential sector: Review, challenges and new perspectives. Renew. Sustain. Energy Rev. 2022, 153, 111763. [Google Scholar] [CrossRef]
  3. ABB Solar Inverters. Product Manual REACT-3.6/4.6-TL (from 3.6 to 4.6 kW). Available online: https://www.abb.com/solarinverters (accessed on 9 March 2022).
  4. Conext, S.W. Hybrid Inverter. Available online: https://www.se.com/ww/en/product-range-presentation/61645-conext-sw/ (accessed on 9 March 2022).
  5. Zeng, Z.; Yang, H.; Zhao, R.; Cheng, C. Topologies and control strategies of multi-functional grid-connected inverters for power quality enhancement: A comprehensive review. Renew. Sustain. Energy Rev. 2013, 24, 223–270. [Google Scholar] [CrossRef]
  6. Ma, T.-T. Power quality enhancement in micro-grids using multifunctional DG inverters. Lect. Notes Eng. Comput. Sci. 2012, 2196, 996–1001. [Google Scholar]
  7. Shavelkin, A.; Jasim, J.M.J.; Shvedchykova, I. Improvement of the current control loop of the single-phase multifunctional grid-tied inverter of photovoltaic system. East.-Eur. J. Enterp. Technol. 2019, 6, 14–22. [Google Scholar] [CrossRef]
  8. Belaidi, R.; Haddouche, A. A multi-function grid-connected PV system based on fuzzy logic controller for power quality improvement. Przeg. Elektr. 2017, 93, 118–122. [Google Scholar] [CrossRef] [Green Version]
  9. Vigneysh, T.; Kumarappan, N. Grid interconnection of renewable energy sources using multifunctional grid-interactive converters: A fuzzy logic based approach. Electr. Power Syst. Res. 2017, 151, 359–368. [Google Scholar] [CrossRef]
  10. Shavolkin, O.; Shvedchykova, I. Improvement of the Three-Phase Multifunctional Converter of the Photoelectric System with a Storage Battery for a Local Object with Connection to a Grid. In Proceedings of the 25th IEEE International Conference on Problems of Automated Electric Drive. Theory and Practice, PAEP 2020, Kremenchuk, Ukraine, 21–25 September 2020; pp. 1–6. [Google Scholar]
  11. Shavolkin, O.; Shvedchykova, I.; Demishonkov, Y. Energy Management of Hybrid Three-Phase Photoelectric System with Storage Battery to Meet the Needs of Local Object. In Proceedings of the 20th IEEE International Conference on Modern Electrical and Energy Systems, MEES 2021, Kremenchuk, Ukraine, 21–24 September 2021. [Google Scholar]
  12. Lliuyacc, R.; Mauricio, J.M.; Gomez-Exposito, A.; Savaghebi, M.; Guerrero, J.M. Grid-forming VSC control in four-wire systems with unbalanced nonlinear loads. Electr. Power Syst. Res. 2017, 152, 249–256. [Google Scholar] [CrossRef] [Green Version]
  13. Guerrero-Martinez, M.A.; Milanes-Montero, M.I.; Barrero-Gonzalez, F.; Miñambres-Marcos, V.M.; Romero-Cadaval, E.; Gonzalez-Romera, E. A smart power electronic multiconverter for the residential sector. Sensors 2017, 17, 1217. [Google Scholar] [CrossRef] [Green Version]
  14. Luthander, R.; Widén, J.; Nilsson, D.; Palm, J. Photovoltaic self-consumption in buildings: A review. Appl. Energy 2015, 142, 80–94. [Google Scholar] [CrossRef] [Green Version]
  15. Yang, X.; Jiang, F.; Liu, H. Short-term power prediction of photovoltaic plant based on SVM with similar data and wavelet analysis. Prz. Elektrotech. 2013, 89, 81–85. [Google Scholar]
  16. Mellit, A.; Pavan, A.M.; Lughi, V. Deep learning neural networks for short-term photovoltaic power forecasting. Renew. Energy 2021, 172, 276–288. [Google Scholar] [CrossRef]
  17. Zsiborács, H.; Pintér, G.; Vincze, A.; Birkner, Z.; Baranyai, N.H. Grid balancing challenges illustrated by two European examples: Interactions of electric grids, photovoltaic power generation, energy storage and power generation forecasting. Energy Rep. 2021, 7, 3805–3818. [Google Scholar] [CrossRef]
  18. Michaelson, D.; Mahmood, H.; Jiang, J. A Predictive Energy Management System Using Pre-Emptive Load Shedding for Islanded Photovoltaic Microgrids. IEEE Trans. Ind. Electron. 2017, 64, 5440–5448. [Google Scholar] [CrossRef]
  19. Shavolkin, O.; Shvedchykova, I.; Jasim, J.M.J. Improved control of energy consumption by a photovoltaic system equipped with a storage device to meet the needs of a local facility. East.-Eur. J. Enterp. Technol. 2021, 2, 6–15. [Google Scholar] [CrossRef]
  20. Forecast. Solar. Available online: https://forecast.solar/ (accessed on 9 March 2022).
  21. Iyengar, S.; Sharma, N.; Irwin, D.; Shenoy, P.; Ramamritham, K. SolarCast—An open web service for predicting solar power generation in smart homes. In Proceedings of the 1st ACM Conference on Embedded Systems for Energy-Efficient Buildings, BuildSys 2014, Memphis, TN, USA, 3–6 November 2014; pp. 174–175. [Google Scholar]
  22. Nicolson, M.L.; Fell, M.J.; Huebner, G.M. Consumer demand for time of use electricity tariffs: A systematized review of the empirical evidence. Renew. Sustain. Energy Rev. 2018, 97, 276–289. [Google Scholar] [CrossRef]
  23. Davis, M.J.M.; Hiralal, P. Batteries as a Service: A New Look at Electricity Peak Demand Management for Houses in the UK. Procedia Eng. 2016, 145, 1448–1455. [Google Scholar] [CrossRef]
  24. Lorenzi, G.; Silva, C.A.S. Comparing demand response and battery storage to optimize self-consumption in PV systems. Appl. Energy 2016, 180, 524–535. [Google Scholar] [CrossRef]
  25. Badawy, M.O.; Cingoz, F.; Sozer, Y. Battery storage sizing for a grid tied PV system based on operating cost minimization. In Proceedings of the 2016 IEEE Energy Conversion Congress and Exposition, Milwaukee, WI, USA, 18–22 September 2016. [Google Scholar]
  26. Shavelkin, A.A.; Gerlici, J.; Shvedchykova, I.O.; Kravchenko, K.; Kruhliak, H.V. Management of power consumption in a photovoltaic system with a storage battery connected to the network with multi-zone electricity pricing to supply the local facility own needs. Electr. Eng. Electromech. 2021, 2, 36–42. [Google Scholar] [CrossRef]
  27. Shavolkin, O.; Shvedchykova, I.; Demishonkova, S.; Pavlenko, V. Increasing the efficiency of hybrid photoelectric system equipped with a storage battery to meet the needs of local object with generation of electricity into grid. Przeg. Elektr. 2021, 97, 144–149. [Google Scholar] [CrossRef]
  28. Traore, A.; Taylor, A.; Zohdy, M.; Peng, F. Modeling and Simulation of a Hybrid Energy Storage System for Residential Grid-Tied Solar Microgrid Systems. J. Power Energy Eng. 2017, 5, 28–39. [Google Scholar] [CrossRef] [Green Version]
  29. Miñambres-Marcos, V.M.; Guerrero-Martínez, M.Á.; Barrero-González, F.; Milanés-Montero, M.I. A grid connected photovoltaic inverter with battery-supercapacitor hybrid energy storage. Sensors 2017, 17, 1856. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  30. Photovoltaic Geographical Information System. Available online: https://re.jrc.ec.europa.eu/pvg_tools/en/tools.html#SA (accessed on 9 March 2022).
  31. Data Sheet. Lithium Iron Phosphate (LiFePo4) Battery 12.8 V 150 Ah. Available online: https://www.enix-energies.com (accessed on 9 March 2022).
Figure 1. Simplified structure of power supply of LO load.
Figure 1. Simplified structure of power supply of LO load.
Energies 15 04883 g001
Figure 2. Structure of hybrid PVS with SB.
Figure 2. Structure of hybrid PVS with SB.
Energies 15 04883 g002
Figure 3. Formation of schedule of state of the charge of SB.
Figure 3. Formation of schedule of state of the charge of SB.
Energies 15 04883 g003
Figure 4. Structure of the control system of PVS.
Figure 4. Structure of the control system of PVS.
Energies 15 04883 g004
Figure 5. Oscillograms PLC, PC, PPV, Q , IB, and Pg for a December day with general generation WPV = 500 Wh ( Q and IB values are shown at scale 2 and 10, respectively).
Figure 5. Oscillograms PLC, PC, PPV, Q , IB, and Pg for a December day with general generation WPV = 500 Wh ( Q and IB values are shown at scale 2 and 10, respectively).
Energies 15 04883 g005
Figure 6. Oscillograms PLC, PC, PPV, Q , IB, and Pg for a July day with general generation WPV = 1320 Wh ( Q and IB values are shown at scale 2 and 10, respectively).
Figure 6. Oscillograms PLC, PC, PPV, Q , IB, and Pg for a July day with general generation WPV = 1320 Wh ( Q and IB values are shown at scale 2 and 10, respectively).
Energies 15 04883 g006
Figure 7. Oscillograms PLC, PLCR, PC, PPVM, PPV, Q , IB, and Pg for the May day with a generation corresponding to the monthly average ( Q and IB values are shown at scale 2 and 10, respectively): (a) PLC = PLCR, PPVR = 1 kW, WB = 968 Wh, and at limit values ρ = 1.95 with kE = 2.618; (b) PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and at limit values p = 1.8 with kE = 2.356; (c) PLCPLCR, PPVR = 0.86 kW, WB = 800 Wh, and p = 1.6 with kE = 2.795.
Figure 7. Oscillograms PLC, PLCR, PC, PPVM, PPV, Q , IB, and Pg for the May day with a generation corresponding to the monthly average ( Q and IB values are shown at scale 2 and 10, respectively): (a) PLC = PLCR, PPVR = 1 kW, WB = 968 Wh, and at limit values ρ = 1.95 with kE = 2.618; (b) PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and at limit values p = 1.8 with kE = 2.356; (c) PLCPLCR, PPVR = 0.86 kW, WB = 800 Wh, and p = 1.6 with kE = 2.795.
Energies 15 04883 g007aEnergies 15 04883 g007b
Figure 8. Oscillograms PLC, PLCR, PC, PPVM, PPV, Q , IB, and Pg for the September day with the generation, corresponding to the average monthly values at PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and ρ = 1.6 with kE = 2 ( Q and IB values are shown at scale 2 and 10, respectively).
Figure 8. Oscillograms PLC, PLCR, PC, PPVM, PPV, Q , IB, and Pg for the September day with the generation, corresponding to the average monthly values at PLC = PLCR, PPVR = 0.86 kW, WB = 800 Wh, and ρ = 1.6 with kE = 2 ( Q and IB values are shown at scale 2 and 10, respectively).
Energies 15 04883 g008
Table 1. Average monthly PV generation during the year.
Table 1. Average monthly PV generation during the year.
JanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecember
Average monthly generation of PV per day for Kyiv location WPVAVD, kWh
1.171.812.873.884.274.434.384.243.852.571.140.91
Average monthly generation of PV per day for Žilina location WPVAVDZ, kWh
1.2722.0532.8113.7993.763.9144.0733.843.4342.61.4181.25
Energy values for selected days when the PV generation was close to the average monthly generation per day in Kyiv
(PV generation calculated using archival data for the period 2012–2016) W*PVAVD, kWh
0.85
(0.98)
1.81 (1.81)2.57 (2.83)3.89 (3.83)4.25 (4.26)4.47 (4.48)4.36 (4.37)4.036 (4.16)3.4 (3.52)2.44 (2.49)0.798 (0.96)1
(1.03)
Energy values for selected days when the PV generation is close to the average generation at time interval (t2, t3)
in Kyiv (PV generation calculated using archival data for the period 2012–2016) WPV23, kWh
0.144 (0.166)0.31 (0.36)0.5 (0.55)0.62 (0.52)1.06 (1.15)1.26 (1.17)1.17 (1.13)0.581 (1.08)0.41 (0.56)0.34 (0.33)0.225 (0.22)0.166
(0.21)
Energy values for selected days when the PV generation is close to the average generation at time interval (t3, t4)
in Kyiv (PV generation calculated using archival data for the period 2012–2016) WPV34, kWh
0.643 (0.78)1.31 (1.36)1.83 (1.84)2.09 (2.38)2.43 (2.43)2.51 (2.27)2.46 (2.5)2.78 (2.45)2.25 (2.27)1.95 (1.74)0.535
(0.69)
0.806 (0.8)
Energy values for selected days when the PV generation is close to the average generation at time interval (t4, t5)
in Kyiv (PV generation calculated using archival data for the period 2012–2016) WPV45, kWh
0.061 (0.038)0.16 (0.083)0.22 (0.32)0.79 (0.84)0.539 (0.53)0.62 (0.63)0.57 (0.61)0.66 (0.53)0.65 (0.72)0.148 (0.39)0.036 (0.03)0.03 (0.021)
Table 2. Variants of the reference PC and PLg at ρ = 1.7.
Table 2. Variants of the reference PC and PLg at ρ = 1.7.
Interval(t2, t3)(t3, t4)(t4, t5)(t5, t6)
VariantPLC, W340306272340
vaPC, W140126112140
PLg, W200180160140
vbPC, W14010672140
PLg, W200200200200
vcPC, W14020072140
PLg, W200106200200
Table 3. Operating modes of the PVS with SB.
Table 3. Operating modes of the PVS with SB.
Interval(t2, t3)(t3, t5)(t5, t6)(t6, t2)
Modeg1g2g3g4g5g6g7
Reference
I1gm
Pg = PLC − PC,
Pgi → I1gm ≥ 0
Pg = PLC − PC,
Pg → I1gm ≥ 0,
Pg = PLC − PC,
Pg → I1gm ≥ 0,
VCIgI1gm ≥ 0Pg = PLC − PC,
Pg → I1gm ≥ 0,
Pg = PLC − PC,
Pgi → I1gm ≥ 0
Pg = PLC − PC,
Pgi → I1gm ≥ 0
Reference
I1PV
MPPTMPPTPPVηCPLCVCIPVI1PVI1PVPPVFPLC > PCPCB,
MPPT
PCBPCMPPTMPPTMPPT
Reference
I1B
VCIBI1BVCIBI1BI1B = IBR > IB(Q)
IB = IB(Q)
I1B = IBR>IB(Q)
IB = IB(Q)
VCIBI1BVCIBI1BVCIBI1B
SOCQ* ≤ Q*dQ* ≤ Q*dQ* > Q*dQ* > Q*dQ* ≤ Q*dQ* < Q*dQ*6→ Q*2
Table 4. Simulation results.
Table 4. Simulation results.
IndicatorsJanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecember
Possibilities of power increase PPVR = 1 kW, WB = 968 Wh
ρ1.71.71.81.91.951.951.951.951.91.751.71.7
kE1.1051.41.6362.1282.6182.6842.7672.2911.9181.5861.0961.149
Q*6, %17.52019.818.518.519.3202019.219.61420
Constant value of power degree ρ = 1.6 (PPVR = 0.86 kW, WB = 800 Wh)
kE1.0981.3541.6082.3162.8212.8042.9462.32121.5231.0881.133
Q*6, %18.720.420.6202120202020.7201520
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Shavolkin, O.; Shvedchykova, I.; Gerlici, J.; Kravchenko, K.; Pribilinec, F. Use of Hybrid Photovoltaic Systems with a Storage Battery for the Remote Objects of Railway Transport Infrastructure. Energies 2022, 15, 4883. https://doi.org/10.3390/en15134883

AMA Style

Shavolkin O, Shvedchykova I, Gerlici J, Kravchenko K, Pribilinec F. Use of Hybrid Photovoltaic Systems with a Storage Battery for the Remote Objects of Railway Transport Infrastructure. Energies. 2022; 15(13):4883. https://doi.org/10.3390/en15134883

Chicago/Turabian Style

Shavolkin, Olexandr, Iryna Shvedchykova, Juraj Gerlici, Kateryna Kravchenko, and František Pribilinec. 2022. "Use of Hybrid Photovoltaic Systems with a Storage Battery for the Remote Objects of Railway Transport Infrastructure" Energies 15, no. 13: 4883. https://doi.org/10.3390/en15134883

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop