Next Article in Journal
Mesoscale Mechanism Study of Geocell-Reinforced Foundation Under Strip Footing Using PFC3D
Previous Article in Journal
Damage and Capacity Diagnostics of CFRP-Jacketed Non-Ductile RC Frames
Previous Article in Special Issue
Calibrated Physics-Based Dynamic Energy Modelling of an Airport Terminal
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Long-Term Monitoring and Comparison of Control Strategies for Optimizing Energy Consumption in a Plus-Energy Building

Institute for Energy and Building (IEG), Technische Hochschule Nürnberg Georg Simon Ohm, Keßlerplatz 12, 90489 Nuremberg, Germany
*
Author to whom correspondence should be addressed.
Buildings 2026, 16(12), 2370; https://doi.org/10.3390/buildings16122370 (registering DOI)
Submission received: 24 April 2026 / Revised: 8 June 2026 / Accepted: 10 June 2026 / Published: 13 June 2026
(This article belongs to the Special Issue Advances in Energy-Efficient Building Design and Renovation)

Abstract

This paper presents a comprehensive evaluation of control strategies for a highly energy-efficient plus-energy terraced housing complex equipped with photovoltaic generation, modulating ground-source heat pumps, electrical and thermal energy storage systems, and activation of building thermal mass. The study combines long-term monitoring data, annual simulations, and hardware-in-the-loop (HiL) experiments to assess modulating heat-controlled operation (HC), PV-controlled (PVC), and predictive control strategies, including simple predictive control (SPC) and model predictive control (MPC). The simulation results show that the baseline HC operation already achieves a high load cover factor (LCF), defined as the fraction of total electrical demand covered by local PV generation (direct use + battery discharge) of 65.6% and a seasonal performance factor (SPF) of the central heat pumps of 5.8. PVC increases LCF (71.0%) by shifting heat pump operation toward PV-rich periods but leads to elevated storage temperatures up to 5 K and a reduced SPF of 4.8. MPC further enhances LCF by 4–7 percentage points in simulated and HiL environments. However, its real-world performance is strongly influenced by forecast quality and the limited controllability of the heat pump system. In addition, building thermal mass activation is investigated as a complementary flexibility option. Simulation and monitoring results demonstrate that moderate room temperature set-point (2 K) increases during PV availability significantly improve LCF from 20% to 55% while maintaining thermal comfort. Overall, the findings indicate that in highly efficient plus-energy buildings, robust rule-based strategies combined with thermal mass activation can achieve a large share of the attainable benefits, while the added complexity of MPC must be carefully weighed against practical limitations.

1. Introduction

The optimization of energy consumption in buildings is a central element of the European climate protection and sustainability strategy. Positive energy buildings (PEBs), which generate more energy on an annual basis than they consume, are considered a promising approach to significantly reducing both final energy demand and CO2 emissions in the building sector. A key prerequisite for the successful operation of such buildings is efficient energy management that integrates renewable generation, as well as thermal and electrical energy storage systems. Control strategies play a decisive role in this context, as they strongly influence how effectively energy flows from photovoltaic (PV) systems, heat pumps, and storage units are utilized.
The recent revisions of the Energy Performance of Buildings Directive (EPBD) [1] and the Energy Efficiency Directive (EED) [2] introduce new requirements and objectives for the European building stock. In addition to structural efficiency measures, they emphasize the development of emission-free buildings and districts. This highlights the relevance of PEBs and expands the focus toward positive energy districts (PEDs), which aim to integrate energy efficiency, flexibility, and renewable generation at the district level. Several studies [3,4,5] have already called for an adaptation of the EPBD, arguing that earlier versions were incomplete and restrictive, preventing the full potential of PEBs and PEDs from being leveraged in the short term.
The concepts of zero emission neighborhoods, sustainable plus-energy neighborhoods, and PEDs have been discussed extensively in the literature, predominantly from an energy and emission perspective [6]. However, the definitions of the three concepts are not clearly specified within the EPBD and are debated across several studies. Key aspects of the discussion include the role and meaning of PED definitions, virtual and geographical boundaries, requirements for energy efficiency and flexibility, the involvement of different stakeholder groups, assessment approaches, and insights into realized PED projects [7,8,9,10,11]. These definitions influence how projects are classified and whether they qualify as PEDs. Nonetheless, the implementation of PEDs in Europe is still at an early stage, with most initiatives representing pilot projects.
A major topic in current research concerns the technical and economic integration of thermal and electrical storage potentials (e.g., thermal energy storage (TES), building thermal mass, or seasonal storage systems like borehole fields) to better utilize renewable energy. Studies show that multi-criteria optimization approaches and modern modeling and simulation tools offer significant potential for reducing energy consumption and shifting peak loads. At the same time, the transfer of these findings into robust, practical control solutions remains challenging, and user-friendly tools beyond regulatory standard approaches are still lacking. The study presented in [12] demonstrates substantial potential for annual energy savings and peak load shifting through integrated system optimization, while also emphasizing the need for more advanced and accessible tools to promote widespread adoption. In addition, the use of digital twins and building information modeling (BIM)-based approaches for forecasting, system analysis, and operational optimization is gaining importance. One study [13] discusses the foundations of BIM and digital twin technology and their application to building energy optimization. It is expected that advancements in building energy analysis and machine learning technologies will improve forecasting accuracy, enhance energy efficiency, and support management processes.
While predictive control strategies often demonstrate substantial benefits in simulation studies, only a limited number of empirical investigations have examined these strategies in real building operation over extended periods. As a result, evidence is lacking on how effectively different control strategies perform in real PEBs, particularly those with already high baseline efficiencies. Open research questions include the achievable improvements in supply cover factor (SCF) and load cover factor (LCF), impacts on heat supply efficiency, and the role of storage integration under real-world conditions with imperfect forecasts. Numerous studies [14,15,16,17] have investigated model predictive control (MPC) strategies for heatpump-based building energy systems, reporting operating cost savings in the range of 6–30% and increases in PV direct consumption of up to 30%. A simulation study [14] demonstrated cost savings of 6–11% for constant electricity prices and up to 16% for variable electricity prices when comparing MPC to a default rule-based controller. In addition to economic benefits, MPC can significantly enhance the utilization of locally generated PV electricity.
Another simulation study [15] showed in an annual simulation study that targeted MPC control of a heat pump can increase PV direct consumption in a single-family house by up to 30%. Similarly, this simulation study [16] found that applying MPC to heat pump systems leads to a substantial reduction in PV feed-in, with reported decreases of up to 88%. Their study further indicates that, under flexible electricity market conditions in Finland, energy cost reductions of up to 25% can be achieved compared to rule-based control strategies. Another simulation study [17] reported maximum cost savings of 24% for a single-family house in Luxembourg when MPC was combined with market-based variable electricity prices.
Beyond simulation studies, a limited number of experimental and field implementations of MPC have been reported. In an office building [18], a nonlinear MPC maintained comparable or improved thermal comfort while reducing energy costs by over 30% compared to the reference control. A study [19] presents a case example of a retail building in the United Kingdom in which a generalized MPC framework for heating, ventilation and air conditioning (HVAC) was implemented. While the results indicate performance improvement potential, the achieved reduction in operating costs was only 1.7% over two months. In contrast to the comparatively high modeling and implementation effort required for MPC, simplified predictive control approaches offer a lower-complexity alternative while still achieving relevant performance improvements. However, studies on such approaches remain scarce. A simulation study [20] presented a predictive control algorithm developed within a Swedish research project, demonstrating annual energy savings of approximately 10% in single-family houses by forecasting and exploiting solar energy gains.
In contrast to previous studies that predominantly rely on simulations or focus on isolated MPC implementations in real operation, this paper provides a systematic empirical evaluation of advanced control strategies by combining long-term monitoring, annual simulations, and hardware-in-the-loop (HiL) experiments within the same plus-energy building context. By investigating a highly energy-efficient residential system with already high baseline performance, the study enables a differentiated assessment of marginal performance gains, efficiency trade-offs, robustness, and practical limitations of predictive and rule-based control strategies under real-world operating conditions. In particular, only a few long-term field studies quantitatively analyze the trade-off between increased LCF and seasonal performance factor (SPF) and operating costs, or assess how effectively available thermal storage options such as thermal energy storage (TES), thermal building mass (tbm), and battery systems are utilized in practice.
This paper contributes to closing this gap by presenting a four-year monitoring study and a comprehensive comparison of control strategies applied to a plus-energy terraced housing complex, as follows: (i) a conventional heat-controlled strategy (HC), (ii) a PV-controlled (PVC), and (iii) predictive control strategies, namely simple predictive control (SPC) and MPC. The objective is to quantify their impact on PV utilization, operating costs, system efficiency, and robustness. By integrating long-term monitoring data with detailed dynamic simulations and HiL experiments, the study provides both quantitative performance indicators and practical insights for the operation of PEBs and positive energy districts (PEDs).

2. Materials and Methods

2.1. Case Study Building and Energy System

The case study examines a terraced housing complex with eight residential units in Herzogenaurach, Germany, designed as a highly energy-efficient plus-energy building (shown in Figure 1). The energy system integrates PV, heat pumps, and various thermal (TES and thermal building mass (tbm)) and electrical energy storage systems. An overarching energy management system enables the evaluation of different control strategies. Overall, the energy system aims to maximize the share of demand met by local renewable generation while ensuring a highly efficient heat supply.
The building envelope is highly insulated, with exterior wall U-values between 0.13 W/(m2K) and 0.18 W/(m2K) and triple-glazed windows (Ug ≈ 0.7–0.8 W/(m2K)). This low-loss envelope forms the basis for reduced heating loads and supports the plus-energy performance of the complex. A PV system with a peak capacity of 88 kWp and east–west orientation is the main renewable energy source and supplies both household electricity and the electrical demand of the heat pumps.
Space heating is provided by two central ground-source heat pumps (17 kWth each), which are connected to a borehole field. In addition, the borehole field enables free cooling during summer periods. The central heating system is based on modulating heat pumps (MHPs), which can continuously adjust their thermal output to the current heating demand and operating conditions. The concept of the shared energy system is shown in Figure 2.
Domestic hot water (DHW) is prepared decentralized by DHW heat pumps (Booster) in each dwelling, which helps to avoid peak loads in the central system and reduces the thermal demand on the main heat pumps by lowering the supply temperature. In contrast, higher temperatures are always required for DHW preparation, decentralizing its supply improves efficiency, avoids elevated central supply temperatures, and reduces distribution losses while enabling flexible, demand-driven generation.
Multiple storage components provide thermal flexibility, including two TES in the heating circuit, eight DHW tanks, and the tbm. This combination enables load shifting and supports the integration of PV surplus into thermal generation. A battery energy storage system with a capacity of 40 kWhel complements the system.
Through the combination of efficient heat pump technology, extensive PV generation, and thermal and electrical storage systems, the energy system serves as an effective real-world laboratory for evaluating different control strategies in terms of PV integration, energy efficiency, and operating costs. In particular, the system architecture allows for a systematic analysis of how conventional, PV-controlled, and predictive control approaches influence renewable energy utilization and the overall operation of a plus-energy building.

2.2. Monitoring Setup and Data Collection

An extensive monitoring system has been in operation since April 2018, recording electrical and thermal powers, energy flows, temperatures, operating states of the heat pumps, battery state of charge (SOC) and indoor temperatures in selected zones. The monitoring period considered in this paper covers entirely the years 2019 to 2022. Data are acquired in short time intervals and aggregated to 15 min and hourly values for analysis. The monitoring data are stored centrally in an SQL database and undergo plausibility checks and filtering to exclude commissioning phases, sensor faults, or incomplete data segments. Only periods with complete and reliable data coverage are considered in the analysis.
Electrical variables include the power and energy flows of the central MHPs, the decentralized Booster for DHW preparation, household electricity consumption, PV generation, battery charging and discharging power, grid import, and grid feed-in. Thermal variables comprise supply and return temperatures of the heating system, TES temperatures at multiple vertical levels, DHW storage temperatures, borehole source temperatures, and selected room air temperatures. In addition, thermal energy flows are recorded, including the heat extracted from the ground source and the heat delivered on the heating side of the MHPs and Booster, as well as the thermal energy supplied to each dwelling for space heating and DHW preparation. Installed single temperature sensors are Pt100. Thermal energy flow meters are equipped with Pt500 temperature sensors, have a measuring range of 2–180 °C, offer accuracy exceeding the requirements of EN 1434 [21], and are calibrated. Depending on the installation location (MHP, each house), they have a standard flow rate of 1.5 m3/h, 2.5 m3/h, or 15 m3/h. Weather data, such as outdoor air temperature and solar irradiance, are recorded on-site as well. The weather forecast for outdoor air temperature and solar irradiance is provided by a system provider in the field of energy management (efr GmbH, Munich, Germany) and is available online in hourly intervals for the subsequent 48 h. It is updated every 4 h.

2.3. Simulation and Predictive Models

Different modeling approaches represent the energy system with varying levels of detail, leading to different abstractions of component behavior and system dynamics. This raises the question of whether simplified models are sufficiently accurate for performance assessment and control-oriented applications. Nonlinear models reproduce the system behavior and the underlying physical processes with high accuracy, but their complexity makes them difficult to implement and only partly suitable for use in optimization algorithms. In contrast, simplified linear models can be integrated much more easily into optimization routines but raise the question of whether they can represent the real system dynamics adequately.
To further support the implementation of the different modeling approaches and to clearly define the thermodynamic relationships used within the simulations, the underlying heat pump equations applied in this paper are presented in the following section.
Electrical power P i in Equation (1) and thermal power Q ˙ i in Equation (2) of MHP are represented by a polynomial model, as in Type 4010 in TRNSYS (Version 18) [22]. Due to a lack of modulating simulation models for heat pumps in TRNSYS, the existing TRNSYS Type 401 [23] was extended by normalized inverter frequency (modulation speed) and validated for modeling the MHP.
P i = b p 1 + b p 2 φ x , e v , i n , i Y n , i + b p 3 φ x , c o n d , o u t , i + b p 4 Y n , i + b p 5 φ x , e v , i n , i φ x , c o n d , o u t , i Y n , i + b p 6 φ x , e v , i n , i 2 + b p 7 φ x , c o n d , o u t , i 2 + b p 8 Y n , i 2
Q ˙ i = b q 1 + b q 2 φ x , e v , i n , i Y n , i + b q 3 φ x , c o n d , o u t , i + b q 4 Y n , i + b q 5 φ x , e v , i n , i φ x , c o n d , o u t , i Y n , i + b q 6 φ x , e v , i n , i 2 + b q 7 φ x , c o n d , o u t , i 2 + b q 8 Y n , i 2
where b p 1 8 and b q 1 8 represents the coefficients, φ x , e v , i n , i the inlet temperature of the evaporator, φ x , c o n d , o u t , i the outlet temperature of the condenser and Y n , i the normalized inverter frequency (modulation speed).
Electrical power P M H P in Equation (3) and thermal power Q ˙ M H P in Equation (4) of MHP are represented by a characteristic curve, which is used in PV control. Depending on the control strategy, electrical power or thermal power is defined by PV power or thermal load.
P M H P = i = 1 n = 5 q i · Q ˙ M H P n i
Q ˙ M H P = i = 1 n = 7 q i · P M H P n i
where pi and qi represent the constant coefficients of the polynomial.
For the implementation of MPC using a mixed-integer linear programming (MILP) formulation, all component models must be linear. Therefore, the MHP model is represented by a set of discrete operating points, between which linear interpolation is applied to approximate the modulation behavior within the MILP framework. In this work, an MILP-based MPC is implemented in MATLAB (Version R2020a) [24] using GUROBI (Version 8) [25] with a Special Ordered Set (SOS) formulation. The SOS approach enables interpolation between predefined operating points of the MHP, allowing their polynomial performance characteristics to be represented for B5/W35. Consequently, the MHP’s thermal capacity ranges from 4.8 kWth to 18.1 kWth and the electrical power from 1.0 kWel to 4.7 kWel. The genetic algorithm (GA)-based MPC uses the MHP model from Equations (1) and (2) and the TES model from Equation (5), as it is able to handle nonlinear programming.
A stratified TES model is given in Equation (5) [26]. As the TES is stated as the main storage component in the heating system, its energy balance can be calculated as a function of the heat pump heating capacity Q ˙ MHP , the space heating load Q ˙ SH and the storage ambient heat losses Q ˙ loss .
C S N d T S t d t = Q ˙ MHP t Q ˙ SH t Q ˙ loss t
where CS is the storage capacity, N the number of thermal layers and TS the temperature of each layer. The TES is assumed to be fully mixed (no stratification). Thus, it is represented as one single energy node.
In TRNSYS, Type 534 [27] without a heat exchanger is used for modeling TES. This Type also calculates according to Equation (5) but also considers mixing heat transfer between nodes. The two model variants were investigated, differing in model structure, level of detail and solution methods, and are shown in Table 1.
Annual system simulations are carried out for all model variants considering measured time series data for PV generation, building heating load and source load of the decentralized Booster. A battery storage system was not considered. The heat pump operation was controlled in PVC mode. Model performance was evaluated based on SCF, LCF, SPF electrical consumption of the MHPs and operating costs.
Short-term forecasts of the thermal building load and household electricity demand were generated using recurrent neural networks (RNNs) implemented in Python (Version 8) [28] with the TensorFlow library [29]. Both models were trained on 15 months of monitoring data from the terraced housing complex and produced 24 h forecasts with a temporal resolution of 15 min. The RNN used for thermal load prediction consists of three hidden layers with 1024, 64 and 32 neurons, respectively. Input features include date and time information (month, day, hour), outdoor air temperature and horizontal solar irradiance. The RNN for household electricity demand consists of two hidden layers with 128 neurons each. The input variables include date and time information (month, day, hour), outdoor air temperature, and global horizontal irradiance, as well as historical load values from the previous day and the previous week.

2.4. Control Strategies

Four main control strategies are considered in this study:
  • Heat-controlled operation (HC):
Conventional operation where the central heat pumps charge the TES according to a heating curve and temperature set-points derived from outdoor temperature and time schedules. The focus is on thermal comfort and efficient heat pump operation, without explicit consideration of PV generation.
  • PV-controlled (PVC):
A rule-based strategy that increases the charging of the TES when PV surplus is available. The storage temperature set-points are raised (e.g., up to 35–60 °C) to shift electrical heat pump operation to periods of high PV generation. This strategy can also activate the building thermal mass by temporarily increasing indoor temperature set-points during PV surplus.
  • Simple predictive control (SPC):
A predictive, rule-based strategy that uses forecasts of PV generation and thermal and electrical loads to schedule heat pump and storage operation. SPC aims to shift operation into periods of high PV availability while limiting excessive storage temperature levels and avoiding significant efficiency penalties.
  • Model predictive control (MPC):
An optimization-based predictive control strategy that uses dynamic models of heat pumps, TES and battery, combined with forecasts of weather, PV generation and loads. MPC determines optimal control trajectories (e.g., SOC, power of MHPs) over a finite prediction horizon, subject to comfort and technical constraints. Two MPC implementations were developed: a MILP approach based on simplified linear models, and a genetic algorithm (GA) approach using more detailed nonlinear models. Both variants were tested in simulation. Additionally, the MILP-based MPC was implemented in HiL experiments.
The objective function J is defined as the total operating costs associated with the electrical energy consumption of the building and its energy systems. It includes the electricity consumption of the households, the MHPs and the Booster. The costs depend on the source from which the electrical energy is drawn, namely, grid electricity Eel,grid, on-site PV generation E e l , P V , or the battery system E e l , B a t . In addition, a bonus term is included for the electrical energy fed into the grid   E e l , f e e d i n , reflecting the remuneration for PV export.
Accordingly, the objective function can be expressed conceptually in Equation (6) as
min J = t = 1 t e n d E e l , P V , t · c P V + t = 1 t e n d E e l , B a t , t · c B a t + t = 1 t e n d E e l , g r i d , t · c g r i d t = 1 t e n d   E e l , f e e d i n , t · c f e e d i n
where c represents the respective costs for grid, PV and battery electricity, and denotes the feed-in tariff applied to exported PV energy. The MPC minimizes J over the prediction horizon by optimally scheduling MHPs and booster operation, thermal storage charging and discharging, and battery use, while meeting comfort and technical constraints.
The optimization method is realized in MATLAB and the set-points will be transferred via an SQL database to the heat pumps by the energy management system [30]. While PVC reacts to PV availability through rule-based adjustments of storage set-points, MPC employs forecast-driven optimization to schedule heat pump and TES operation more systematically.

2.5. Boundary Conditions in Simulation

2.5.1. Boundary Conditions in Simulation of Different Storage Options

The first simulation study for analyzing different storage options was carried out in TRNSYS. The aim was to analyze the annual system behavior under realistic operating conditions. The model representation of the central MHPs was implemented using Type 4010, which internally applies the characteristic-curve formulations corresponding to Equations (1) and (2). The stratified TES was modeled using Type 534. The simulation was driven exclusively by measured boundary conditions from 2019, including PV generation, space-heating load, DHW demand, household electricity demand, borehole outlet temperature, and meteorological data. These inputs ensured that the dynamic interaction between generation, storage and demand was evaluated under realistic operating profiles.

2.5.2. Boundary Conditions of General Comparison of the Control Strategies

The simulation of general comparison of the control strategies was implemented in MATLAB. The heat pump model follows the characteristic-curve formulations presented in Equations (3) and (4) for HC, PVC and SPC, while the thermal energy storage is represented by the energy-node model given in Equation (5). In MPC simulation, the MHPs are represented by operating points and interpolation. Thermal losses of both the buffer and domestic hot-water storage tanks were derived from an insulation U-value of 0.3 W/(m2·K) and, in addition, the buffer storage tank was represented through a combination of constant and state-dependent loss components, resulting in an effective overall loss factor of 3.66%. Temperature constraints were imposed as follows: 32 °C to 46 °C for the buffer storage and 45 °C to 60 °C for the hot-water storage. The battery efficiency was set to 80%, based on monitoring data. As boundary conditions, the simulation used measured 15 min time series from the year 2020, including PV generation, thermal space-heating load, domestic hot-water load and household electricity demand.

2.5.3. Boundary Conditions in Simulation of Influence of Thermal Building Mass

To assess the potential of the building thermal mass as an additional storage option for PV surplus energy, a dedicated simulation study was carried out using TRNSYS. The simulation focuses on the activation of the thermal mass by temporarily increasing the room temperature set-points during periods of PV surplus generation. This approach allows thermal energy to be stored within the building structure and released later, thereby reducing grid electricity consumption.
Two representative buildings of the terraced house complex—a corner house (CH) and a middle house (MH)—were modeled in detail. Each building was represented room-by-room with multiple thermal zones and an explicitly modeled floor-heating system embedded in a concrete screed layer. The building model accounts for room-specific orientations, floor areas, and window areas, which determine the magnitude of solar heat gains. Living rooms with an area of 41 m2 feature multiple window orientations with west-facing glazing up to 6.8 m2 and east-facing areas of 1.8 m2, while additional south-facing glazing of about 2.1 m2 is present only in the CH. Bedrooms with an area of 21 m2 exhibit smaller window surfaces, primarily west-facing of 3.6 m2, with additional south-facing glazing of up to 1.5 m2 also present only in the CH, resulting in different solar gains and room-specific thermal responses. The buildings are characterized by a high thermal mass and a very well-insulated envelope with U-values of approximately 0.13 W/(m2·K). To realistically represent dynamic building behavior, mechanical ventilation with heat recovery of 60%, including additional heat losses through infiltration and window airing, was included. In addition, window shading depending on solar irradiance of the respective orientation and controlled by a threshold of 160 W/m2, including a hysteresis of 40 W/m2 and a g-value of 0.25, was included. Internal loads from occupants are represented by a presence profile with 60 W per person and a profile of household electricity. Both profiles are time-dependent, reflecting typical residential occupancy patterns. During daytime hours, internal loads from occupants and equipment are assigned to the living room, representing the primary occupied space. During nighttime hours, the internal load profile is redistributed to the bedrooms, reflecting occupancy during nighttime periods. This approach allows a realistic spatial and temporal representation of internal heat gains.
The thermal mass activation strategy was implemented by increasing the room temperature set-points from a base value of 20 °C (24 °C in bathrooms) by increments of 1 K up to a maximum of 6 K whenever a predefined PV surplus threshold was exceeded. This results in seven activation variants, denoted as dT0 to dT6, where dT0 represents the reference case without set-point increase, while dT1–dT6 correspond to temperature increases in steps of 1 K up to a maximum of 6 K.
To avoid conflicts between overheating protection and thermal mass activation, the upper temperature limits were adapted accordingly. Boundary and initial conditions were derived from measured building data, and weather input was taken from the German Weather Service. Annual simulations were performed with a time resolution of 15 min. A full description can be found in [31].

2.6. Hardware-in-the-Loop Test Bench

A HiL test bench is used to investigate a heat pump heating system under realistic, defined, and reproducible laboratory conditions. The experimental setup combines a brine-to-water heat pump with a nominal heating capacity of 10.9 kWth and an electrical power consumption of 2.2 kWel at operating point B0/W35 with a 500 L TES and a battery energy storage providing 8.64 kWhel of usable capacity and up to 6 kWel charging and discharging power. The HiL, as well as the hydraulic and sensor schematic, is shown in Figure 3.
Electrical power consumption, thermal output, battery charging and discharging power, as well as mass flow rates and temperature profiles are recorded using precise sensors and high-resolution energy meters and meet the requirements of DIN EN 14511-3 [32]. Temperature measurements are conducted using Pt100-4L sensors (Class AA according to DIN EN 60751) with a basic tolerance of ±(0.1 + 0.0017·|T|) K. For differential temperature measurements, sensor pairs are used with a pairing tolerance of lower than ±0.05 K. Volume flow is measured using electromagnetic flow meters (OPTIFLUX 2100 C, KROHNE Messtechnik GmbH, Duisburg, Germany) with an accuracy of <0.5% of the measured value for flow rates above 1.5 m3/h. Electrical energy consumption is measured using three-phase direct energy meters (EM2289, Gossen Metrawatt GmbH, Nuremberg, Germany), complying with MID Class B, with an accuracy of ±1% for active power according to the European Measuring Instruments Directive 2014/32/EU (MID).
The hydraulic configuration of the test bench allows for a separate evaluation of the space heating demand and the thermal energy supplied to the storage tank. The real thermal and electrical dynamics of the components—including storage inertia, compressor behavior, and thermal losses—are fully preserved, reflecting the physical boundary conditions under which the MPC strategy must operate. A full description of the HiL can be found in [33].
The HiL setup enables the coupling of real system physics with simulated boundary conditions for load, PV generation, and operating scenarios. This allows the controller’s behavior to be tested under a wide range of conditions while avoiding the risks associated with intervening in an actual building system. The combination of physical components, detailed sensor instrumentation, and flexibly adjustable input signals makes the HiL test bench a central tool for the experimental evaluation of MPC strategies in heat pump heating systems.
While the HiL setup preserves the physical dynamics of the heat pump, thermal storage, and control interfaces, it intentionally represents a reduced system scope compared to the full monitored building in Section 2.1. In particular, domestic hot water demand and building-level thermal interactions are excluded. The HiL experiments therefore aim to isolate control-system behavior under controlled and reproducible conditions rather than to replicate the complete residential energy system in all aspects.
As a validation step, a simulation study was carried out in MATLAB and compared with the HiL measurements. This study examined three control strategies: HC, PVC and MPC. Within the HiL experiments, the thermal and electrical boundary conditions are defined by externally provided load and generation profiles in order to reproduce realistic operating conditions for the heat pump system and are shown in Figure 4. The space-heating load is derived from dynamic building simulations of a single-family house. As a basic system and building concept and heating system described in IEA, SHC Task 32 by Heimrath and Haller [34] is used and adapted to the HiL test bench configuration. The simulated building represents a highly energy-efficient residential standard comparable to the monitored terraced house complex. The building was deliberately selected as a generic reference case to define a transferable and broadly applicable control approach rather than representing a direct one-to-one model of the investigated terraced house complex. DHW demand is not explicitly considered in the HiL study and is therefore excluded from the thermal load signal.
The household electricity demand is represented by a measured residential load profile obtained from the monitored terraced house complex. It includes a characteristic baseload with superimposed peak loads occurring mainly during morning and evening hours.
The PV generation profile is generated based on measured solar irradiance data from the same terraced house complex and represents a rooftop PV system with an area of 40 m2, which results in a peak power of approximately 5 kWp. The PV load is calculated in accordance with an isotropic sky model [35] and on the basis of the horizontal solar irradiance, the PV area (40 m2), the inclination angle (60°, c.f. the slope of the roof of the reference building) and the efficiency of the PV modules (17.9%) and inverter (95.0%).
An MPC-MILP optimization algorithm is used [36], which is based on the simplified system simulation model. The heat pump is represented by one operating point only (B10/W40, 12.94 kWth, 2.45 kWel). The TES model is shown in Equation (5). The MPC is realized in MATLAB. The operating limits are defined by a minimal and maximal storage temperature of 25 °C and 45 °C, respectively, as well as by the complete cover of the thermal and electrical load. The cost function is shown in Equation (6). The optimization horizon is set to 24 h with an optimization time step and optimization interval of 15 min for both. Thus, every 15 min, the MPC is restarted with new initial boundary conditions to generate the subsequent control sequence. As the optimization horizon is set to 24 h and the weather profiles provide a five-day period of data, the experiments and simulations can only last four consecutive days (96 h).

2.7. Key Performance Indicators

The assessment of the four control strategies—HC, PVC, SPC and MPC—is based on a set of quantitative key performance indicators (KPIs). These indicators are applied consistently across monitoring data, annual simulations, and HiL experiments. All KPI definitions correspond to common performance metrics for heat pump-based PEBs.
Energy-related KPIs:
  • Supply cover factor (SCF): Share of on-site PV generation consumed within the building.
  • Load cover factor (LCF): Fraction of total electrical demand covered by local PV generation (direct use + battery discharge).
  • Seasonal performance factor (SPF): Ratio of delivered thermal energy to electrical input of the heat pumps.
  • Total electricity consumption: Sum of electricity used by central heat pumps, booster heat pumps, household loads, and auxiliary systems.
Comfort-related KPIs:
  • Overheating hours: Number of hours during which the room temperature exceeds 26 °C, according to EN ISO 7730 [37], category II in summer, which defines comfort limits of 24.5 ± 1.5 °C.
  • Mean temperature deviations: Deviation from the minimum comfort room temperature of 20 °C, according to EN ISO 7730, category II in winter, which defines comfort limits of 22.0 ± 2.0 °C.
Economic KPIs:
  • Annual energy costs: energy costs for the energy system, including electrical effort of all heat pumps and household electricity. Tariff costs are shown in Table 2.
  • Annuity: Life-cycle cost over 30-year horizon, derived from investment, replacement and operational costs using the annuity method of depreciation in accordance with VDI 2067 [38]. The interest factor for capital-related costs is 1.5%, the price change factor for energy costs is 2.0% and for maintenance 1.0%. Investment costs for PV and battery storage from 2017 (year of construction) as well as boundary conditions for the calculation of operation-related costs are shown in Table 3. Investment costs for the implementation of control strategies are neglected. In the annuity calculation, the PV feed-in remuneration is assumed to be fixed over a period of 20 years and is therefore not subject to any price escalation or de-escalation. Consequently, revenues from PV feed-in are considered only for the first 20 years of the 30-year horizon. Negative values describe costs, while positive values describe a bonus.

3. Results

3.1. Simulation Model Validation and Control Operation in HiL Test Bench

Before analyzing the long-term performance of the different control strategies under annual boundary conditions, the simulation models and control implementations are first validated under controlled and reproducible conditions. This section, therefore, focuses on the verification of the simulation models and the comparison of simulated and HiL results for identical boundary conditions.
The results of the validation of simulation models show that all models reproduce the real system with very high accuracy. Deviations across all key performance indicators remain in the low single-digit percentage range. Differences in SCF, LCF, SPF, electrical consumption of MHP and operating costs are particularly small and shown in Table 4.
Predictive control strategies require reliable short-term forecasts of loads and PV generation. Therefore, RNNs were developed to predict thermal and electrical demand and tested with two (thermal) and three (electrical) months of test data. The results are shown in Table 5. During long-term MPC operation in April 2020, the thermal RNN reached a root mean square error (RMSE) of 3.7 kW and a normalized RMSE (NRMSE) of 19%. The electrical RNN achieved an RMSE of 1.6 kW and an NRMSE of 14%.
A key factor affecting forecast quality is the weather forecast, as it is incorporated into most forecast models. To validate the quality of the weather forecast for solar irradiance and outdoor air temperature, measurements from the DWD [39] at the nearest location, Nuremberg Airport, were used, as significant measurement errors occurred due to the location of the outdoor temperature sensor on the west facade during the evening hours (solar radiation on the sensor). During the validation period from June to October 2020, an RMSE of 48.2 W/m2 and an NRMSE of 8.8% were observed for solar irradiance. For the outdoor temperature, an RMSE of 1.4 °C and an NRMSE of 6.8% were obtained.
While simulation studies and data-driven forecast models provide valuable insights into the potential performance of different control strategies, their practical applicability ultimately depends on how these strategies interact with real system dynamics and control constraints. In particular, aspects such as actuator limitations, internal heat pump control logic, storage inertia, and measurement noise cannot be fully captured in pure simulation environments.
To bridge the gap between simulation-based analysis and real building operation, the control strategies are therefore evaluated using a HiL test bench, using heat pump and TES models validated in Matlab_simple. As shown in Figure 5, for identical boundary conditions, all control strategies show good qualitative agreement between simulation and HiL experiments. In particular, the SCF and the mean SOC of the TES are reproduced with only small deviations between simulation and measurement. For SCF, the deviations between simulated and measured values amount to 0.1 percentage points for MPC and 0.2 percentage points for PVC, while the deviation for HC is slightly higher at 1.7 percentage points. Similarly, the mean SOC shows good agreement, with deviations of 2.3 percentage points for MPC and 0.4 percentage points for HC, while no deviation is observed for PVC. Larger discrepancies occur for the LCF, where measured values are on average approximately four percentage points lower than simulated values, which can be attributed primarily to longer effective heat pump runtimes in the simulation, caused by model simplifications.
The influence of the control strategy on system performance is clearly reflected in the HiL measurements. The MPC strategy achieves the highest performance across all KPIs, with a measured SCF of 30.7%, compared to 28.9% for PVC and 22.1% for HC. This corresponds to a reduction of 5.9% for PVC and 28.0% for HC relative to MPC. A similar hierarchy is observed for LCF, with MPC achieving values up to 39.7%, while PVC and HC reach approximately 39.4% and 31.1%, respectively. The utilization of the TES is also significantly enhanced under MPC operation: the mean SOC increases from 14.5% (HC) to 31.5% (PVC) and reaches 46.2% under MPC.

3.2. Simulation Results

To structure the analysis, two complementary simulation studies are conducted in this section.
The first study (Section 3.2.1) investigates different system design and storage options using annual simulations, with the objective of quantifying the impact of PV integration, battery storage, and tbmon LCF, energy costs, and annuity.
The second study (Section 3.2.2) focuses on the operational comparison of different control strategies—HC, PVC, SPC and MPC—under identical boundary conditions, using simplified component models suitable for optimization-based control.

3.2.1. Simulation of Different Storage Options

The simulation results shown in Figure 6 illustrate the impact of the investigated control strategies on the LCF, energy flows, the resulting annual energy costs and the annuity calculated over a 30-year period. In addition to the conventional HC, the analysis considers several combinations of PV integration, PVC, battery storage, and the use of the building thermal mass.
In the reference case (HC), the entire electrical energy demand is supplied by the grid. When a PV system is integrated, the LCF increases to 42.1%, while the PV-controlled strategy without battery (PVC + PV) reaches a considerably higher value of 51.0%. Switching from HC to PVC therefore leads to an increase in the LCF of 8.9 percentage points. The integration of a battery storage system further amplifies this effect: in HC operation, the LCF increases from 42.1% to 65.6%, and in PVC operation from 51.0% to 69.7%. The tbm affects the LCF differently depending on the control strategy. Under HC operation, its use slightly reduces the LCF (HC + PV + tbm: 39.2%), whereas under PVC operation, it increases the LCF to 54.0%. The highest LCF is achieved by combining PVC, battery storage, and thermal mass. PVC + PV + bat + tbm reaches an LCF of 71.0% and therefore provides the highest share of load coverage from locally available resources.
The effects of these strategies on the annual energy costs are equally pronounced. Starting from the reference case without PV, with annual energy costs of €15,392, the PV variants lead to a substantial reduction. HC + PV reaches €1651, while PVC + PV results in €1499, placing both strategies at a similarly low-cost level.
The integration of a battery further decreases annual energy costs and results in negative net costs due to high PV utilization. HC + PV + bat achieves −€430, whereas PVC + PV + bat leads to −€325, indicating that battery-supported configurations yield the lowest annual energy costs among all investigated operating modes.
The influence of tbm depends on the applied control strategy. Under HC, annual energy costs increase from €1651 to €2202 when tbm is activated (HC + PV + tbm). Under PVC, the impact is noticeably smaller, with costs rising from €1499 to €1506 (PVC + PV + tbm). When battery storage and tbm are combined, annual energy costs amount to −€0.6 for HC + PV + bat + tbm and −€171 for PVC + PV + bat + tbm. Overall, battery-supported variants achieve the lowest annual energy costs, while the additional effect of tbm on annual costs remains comparatively moderate.
The long-term assessment based on a 30-year annuity confirms this trend. Without PV, the annuity amounts to −€20,360. With PV, it improves significantly to −€18,741 for HC + PV, corresponding to a reduction of 8%, and −€18,121 for PVC + PV, corresponding to a reduction of 11%.
Battery-supported variants exhibit more negative annuities due to the additional investment costs, with −€21,146 for HC + PV + bat (+4.0%) and −€21,010 for PVC + PV + bat (+3.2%).
The activation of tbm leads to annuities of −€19,538 for HC + PV + tbm (−3.6%) and −€17,961 for PVC + PV + tbm (−11.8%), indicating that thermal mass activation can improve life-cycle costs, particularly under PVC operation.
When battery storage and tbm are combined, the annuities amount to −€21,776 for HC and −€21,087 for PVC, confirming that while batteries minimize annual energy costs, they increase life-cycle costs compared to PV-only configurations.

3.2.2. Comparison of the Control Strategies

To build upon the findings of the first simulation study, a second investigation was carried out focusing specifically on the evaluation of predictive control strategies. This complementary study was designed to analyze the operational behavior of HC, PVC, SPC and MPC under realistic boundary conditions, using simplified component models suitable for optimization-based control.
The results of the simulation study, shown in Figure 7, compare HC, PVC, SPC, and the MILP-based MPC strategy with respect to total electricity demand, the LCF, annual energy costs, and the annuity. The total electricity consumption remains at a similar level for all strategies, ranging from 49,777 kWh (MPC) to 50,616 kWh (PVC). PVC and SPC show only marginal increases compared to HC, while MPC slightly reduces electricity consumption (−0.3% relative to HC). The LCF increases across all strategies compared to HC. While HC reaches 64.1%, PVC improves the LCF to 66.6%, and SPC achieves 66.0%. The highest value is obtained with the MILP-based MPC strategy (67.0%), corresponding to an improvement of 3.0 percentage points relative to HC. This indicates a more effective utilization of on-site PV generation and battery operation under predictive control.
The annual energy costs decrease progressively from HC to PVC, SPC, and MPC. Starting from €173 (HC), the costs are reduced to €11 under PVC and −€3 under SPC. The lowest energy costs occur with MILP-based MPC (−€194), corresponding to a reduction of 212% compared to HC.
The annuity results follow a similar pattern but show smaller relative differences due to investment-related cost components. While HC yields an annuity of −€22,046, PVC and SPC slightly improve this value (to −€21,706 and −€21,734, respectively). The MPC strategy achieves the most favorable result (−€21,459), corresponding to a relative improvement of 2.7% compared to HC. Although the operational cost reductions of MPC are substantial, the annuity differences remain modest, reflecting the dominant influence of fixed, long-term cost components.

3.2.3. Influence of Thermal Building Mass

Figure 8 summarizes the simulation results of activating the thermal building mass for a corner and a middle house over a set of seven variants (dT0–dT6), corresponding to increasing room temperature set-point shifts during periods of PV surplus. The figure combines indicators for thermal comfort, grid interaction, PV utilization, heating energy demand and operating costs.
The upper row shows overheating hours and grid electricity consumption. With increasing set-point activation, grid consumption is reduced significantly for both buildings, particularly from dT0 to dT2, while overheating hours increase only slightly. A pronounced rise in overheating is observed only for the highest set-point increase (dT6), indicating that moderate activation levels exploit the thermal mass without critical comfort degradation. These effects are influenced by the time- and room-dependent representation of internal heat gains, where primary occupancy and internal loads are assigned to the living room during daytime and redistributed to bedrooms during nighttime hours. This modeling approach contributes to the room-specific thermal responses observed in the simulation results. As a consequence, the impact of overheating hours differs between individual rooms, while the aggregated building behavior reflects the combined response of these representative zones.
The middle row presents the mean absolute room temperature deviation and the LCF. As the set-point rises, the mean temperature deviation increases gradually, remaining within acceptable limits up to approximately dT2–dT3. At the same time, the LCF increases substantially, demonstrating an improved alignment between on-site PV generation and heating demand. For both buildings, the increase in LCF flattens beyond dT2, indicating diminishing returns in PV utilization at higher activation levels.
The bottom row illustrates the annual heating energy demand and the operating costs. While heating demand increases steadily with higher activation levels due to elevated room temperatures, the operating costs decrease markedly at low to moderate set-point increases. For both houses, the operating costs decrease the most around dT2, after which further activation leads to only marginal cost benefits or even cost increases, depending on the tariff scenario.

3.3. Monitoring

3.3.1. On-Site Operation of HC and PVC

To further investigate the operational differences between HC and PVC under real-world conditions in the terraced house complex, two separate 24 h periods with nearly identical demand and PV boundary conditions were selected. In both periods, the profiles of household electricity demand, space-heating load, and DHW demand deviated by no more than ±4 kW at any time, while the PV generation profiles differed by at most ±25 kW. The total daily energy associated with each demand category differed by less than 10% across the selected days. These constraints ensure that the underlying load and generation conditions are sufficiently similar for isolating the effects of the control strategies. The resulting comparison is shown in Figure 9 and Figure 10.
Across both 24 h comparisons, the characteristic distinction between the operating modes is robustly reproduced. Under HC, the heat pump operation follows a temperature-driven and evenly distributed pattern, with moderate compressor activity throughout the day and relatively stable buffer storage temperatures. In contrast, PVC systematically shifts heat pump activity into hours with high PV availability, resulting in clustered compressor operation around midday and higher buffer storage temperatures during PV-rich periods. Specifically, T1 and T2 refer to the upper and lower positions of the first buffer tank, while T3 and T4 correspond to the upper and lower positions of the second buffer tank. This demonstrates the intended use of thermal storage as a sink for surplus PV electricity.
The behavior of the DHW storage also shows consistent differences across both study days. While DHW preparation is dominated by decentralized booster heat pumps for both operating modes, the mean DHW temperature of the eight storage tanks remains stable in each case. However, under PVC operation, the DHW temperature level is systematically elevated by approximately 5 K from the beginning of each comparison period, indicating that the PV-oriented strategy results in a higher set-point level or more frequent DHW recharging, without compromising thermal stability or DHW availability.
This results in the pronounced differences between HC and PVC: SCF increases by 12.4 percentage points, LCF by 9.5 percentage points, and grid import decreases by 23.5%.
In the second comparison period, the situation is different: during the PV-rich hours, the heating load is nearly zero in both HC and PVC. Since no thermal demand is present, the heat pumps cannot provide heating energy during this time, nor can the heating load be supplied directly from PV. In this case, PVC can only influence the buffer charging behavior, leading to a systematic but much smaller difference. During this period, SCF increases by only 1.1 percentage points, and LCF by 1.9 percentage points, and nearly all other energy flows remain very similar between the two strategies.

3.3.2. On-Site Operation of PVC and MPC

Following the detailed comparison between HC and PVC operation, which demonstrated how both strategies differ in their temporal heat pump behavior and interaction with the TES under real demand conditions, a second analysis was conducted to examine how PVC compares to MPC, as shown in Figure 11. To assess these differences under monitored boundary conditions, a 24 h period with comparable PV generation, household electricity demand, space-heating load and DHW demand was selected for both strategies.
In both comparison periods, the temporal distribution of heat pump operation shows a characteristic shift between PVC and MPC. Under MPC, the morning peak of heat pump power occurs noticeably later, aligning more closely with the onset of PV production of the forecast. This indicates that MPC delays part of the morning heating supply until PV power becomes available, as far as thermal comfort constraints and buffer capacity allow. Moreover, towards the end of the PV production, the MPC strategy initiates an additional charging phase, leading to a second, well-timed buffer-charging sequence that stabilizes the thermal state of the system for the evening hours.
Under PVC operation, in contrast, the control strategy triggers a single pronounced buffer-charging cycle around midday, using the full available charging capacity only once. After this midday event, the buffer temperature remains comparatively stable, and no additional coordinated charging phase occurs at the end of the PV production period. This difference highlights the more anticipatory and multi-stage thermal management of MPC, compared to the single-impulse, PV-reactive behavior of PVC.
A quantitative comparison of PVC and MPC operation shows that both strategies respond differently to similar boundary conditions, leading to characteristic deviations across all relevant performance indicators.
Regarding the utilization of PV energy, the SCF increases from 81.3% (PVC) to 87.4% (MPC), corresponding to an absolute improvement of 6.1 percentage points. The LCF, however, is higher under PVC (60.1%) than under MPC (56.3%), resulting in a reduction of 3.8 percentage points. This indicates that MPC increases the share of PV energy directly consumed on-site but does so at the cost of a slightly higher grid dependence over the full 24 h period.
The SPF of the heat pumps also differs between the two strategies. The SPF of MHPs decreases from 4.8 (PVC) to 4.2 (MPC) (−11.4%), and the SPF of Boosters from 4.1 to 3.5 (−13.4%).
To evaluate the real-world performance of the MPC controller, the optimization results were compared to the measured system behavior for two extended MPC operating periods. The first period (8 March to 23 April 2022) applied the MILP-based MPC, while the second period (20 April 2022 to 6 July 2022) was operated with the GA-based MPC. In both cases, deviations between optimization and measurement provide insights into the impact of forecast uncertainty, thermal system dynamics and limited controllability of the real heat pump system. Table 6 summarizes the comparison between optimization and measured operation for the MPC-MILP period (8 March to 23 April 2022), while Table 7 presents the corresponding results for the MPC-GA period (20 April to 6 July 2022).
During the MILP-based MPC operation, the measured PV production was slightly higher than predicted (13.6 MWh vs. 12.7 MWh, +7.1%). The measured electrical energy consumption also exceeded the forecast (6.5 MWh vs. 6.1 MWh, +7.0%). The SCF remained identical (26.3%), while the SCF including battery support was higher in the real system (38.1% vs. 32.8%, +5.3%). Conversely, the LCF was lower than predicted (51.8% vs. 54.9%, −3.1%), and the same applies when including the battery (70.4% vs. 74.3%, −4.0%).
The operating costs in the measurement were significantly lower (−€207 vs. −€408, −49.3%), and the measured SPF of the MHPs decreased from 4.9 to 4.1 (−15.2%).
In the GA-based MPC period, measured PV production was again slightly higher than predicted (28.4 MWh vs. 28.0 MWh, +7.1%). Electrical energy consumption, however, deviated much more strongly (8.4 MWh vs. 5.7 MWh).
The SCF increased in the measured data (20.6% vs. 14.3%, +6.2%), and SCF including battery deviated even more strongly (41.1% vs. 21.8%, +19.4%). The LCF was lower than predicted (65.1% vs. 70.3%, −5.2%), while LCF including battery support was nearly identical (87.6% vs. 87.3%).
Measured operating costs were again clearly lower (−€1837 vs. −€2161, −15.0%). The SPFMHP dropped from 5.0 to 4.0 (−20%), indicating reduced efficiency compared to the expected performance.

3.3.3. On-Site Operation of Thermal Building Mass

Figure 12 illustrates the operation of tbm activation for two representative monitoring periods with different solar and ambient conditions. In both periods, the activation strategy is realized by temporarily increasing the room temperature set-points during times of PV availability, leading to a characteristic interaction between heating power, indoor temperature evolution and solar irradiance.
During Period 1, corresponding to late autumn and early winter conditions, the activation phases are short and occur intermittently around periods of moderate solar radiation. The heating peak loads during the set-point increases reach values of up to 8–10 kW, while the mean indoor temperature increases only slightly, remaining close to the original comfort level. The limited solar irradiation and low ambient temperatures restrict the duration and magnitude of thermal mass activation, resulting in short charging phases of the building mass.
In contrast, Period 2, representing late winter conditions with higher solar availability, shows a markedly different behavior. Here, longer and more frequent activation phases occur, associated with increased solar irradiation and higher ambient temperatures. The mean indoor temperature rises gradually over several days, indicating a sustained charging of the thermal building mass. During this period, heating power during activation is higher and persists for longer durations, while heating demand during evening and nighttime hours is visibly reduced, reflecting the delayed release of stored thermal energy.
Figure 13 provides a longer-term view of thermal mass operation over the entire test phase. The time series shows that repeated set-point increases during PV-rich periods lead to a progressive elevation of the mean indoor temperature, particularly from mid-February onwards, when solar radiation increases. Simultaneously, a clear separation between PV-driven heating and grid-driven heating becomes visible. Heating energy is increasingly shifted into periods with solar availability, while grid-supplied heating is reduced during nighttime and low-PV periods. These observations confirm that the building thermal mass can be used as a short- to medium-term thermal storage, effectively improving the temporal matching between PV generation and heating demand.
Two middle houses are selected as reference cases for comparison with House M, which is also a middle house within the terraced housing complex. This ensures comparable boundary conditions in terms of geometry, envelope characteristics, and system configuration. The selected houses represent comparable building configurations, allowing a good comparison between a thermally activated unit (House M) and reference units (Houses A and B) with different operating conditions, e.g., number of occupants and mean set-point temperatures of 21.84 °C (House A) and 18.24 °C (House B) compared to 19.67 °C (House M).
Table 8 shows the measured heating energy consumption and the corresponding calculated operating costs for the period with thermal mass activation from 11 November 2020 to 31 March 2021. The electricity prices used for the cost calculation are identical to those applied in the simulation study and are listed in Table 1. The conversion from measured thermal energy to electrical energy is based on an average SPF of the MHPs of 5.0, corresponding to monitoring data of the previous operating year.
Although the mean room temperature of the activated House M and the reference House A is very similar, House A exhibits an 18.5% lower heating energy consumption. When operating costs are evaluated with a differentiation between PV-driven and grid-driven heating, the activated House M nevertheless achieves 20.7% lower operating costs compared to House A. This highlights that the increased utilization of locally generated PV electricity can compensate for the higher thermal energy demand associated with thermal mass activation.
A comparison with House B shows a different behavior. Due to a significantly lower heating set-point temperature, House B achieves a 39.5% lower heating energy consumption than House M. However, this reduction in heating demand cannot be fully compensated for by the operation of the set-point increase strategy applied in House M. As a result, the operating costs of House B are 60.7% lower than those of the thermally activated House M.

4. Discussion

The presented results provide important insights into the practical performance of advanced control strategies in highly energy-efficient plus-energy residential buildings.
First, the simulation and HiL validation of the models demonstrate that both detailed nonlinear models and simplified linear models can reproduce the real heat pump system very accurately. The small deviations confirm the suitability of the simplified models for use in optimization-based control strategies, while the detailed MATLAB models and the TRNSYS model offer high physical fidelity and are well suited for analysis and comparison. The RNN-based short-term forecasts show an accuracy level that is comparable to values reported in the literature [40,41] and can be regarded as sufficient for predictive control applications in residential buildings.
Unlike many simulation-based studies, the investigated terraced housing complex already exhibits a high baseline performance under conventional HC. Consequently, the absolute improvement potential of more advanced control strategies is inherently limited and significantly smaller.
The results of this study can be directly contextualized with previous research on MPC strategies for heat pump-driven buildings, as discussed in the introduction. Numerous simulation-based studies report operating cost reductions in the range of 10–30% and increases in SCF of up to 30% when MPC is applied, particularly under idealized conditions with perfect forecasts and full system controllability. While such improvements are reproduced in this work under idealized simulation conditions, the combined simulation, monitoring and HiL analysis reveals important limitations when transferring these concepts to real plus-energy buildings.
Under idealized assumptions, the simulation results show that MPC increases LCF by four percentage points and reduces operating costs by up to 212%, primarily due to generally low baseline energy costs under HC operation. This relative value is higher within the range reported in the literature [14,15,16,17] and highlights the theoretical potential of MPC for optimally scheduling heat pump operation and thermal storage charging.
However, the HiL experiments and long-term monitoring demonstrate that this potential is only partially realized in practice. Although MPC achieves the highest measured SCF (30.7%) and the highest mean thermal storage utilization (SOC of 46.2%), the real-world operation exhibits 15–20% lower heat pump efficiencies and markedly higher operating costs than predicted by optimization results. These deviations are significantly larger than those reported in many purely simulation-based studies [14,15,16,17]. They are caused by forecasting inaccuracies, as well as by the limited controllability of commercially available heat pump systems, which typically accept temperature set-points rather than direct power commands. Consequently, the optimized power profiles cannot be implemented exactly. The monitoring results show that forecast quality is not merely a secondary disruptive factor but a critical performance factor for predictive control. Deviations in forecasts of thermal and electrical load, as well as PV generation, directly affect the temporal coordination of heat pump operation with PV availability and storage temperatures.
These findings help to explain the discrepancy between the large MPC benefits reported in simulation studies [14,15,16,17] and the more moderate performance gains observed in field and HiL experiments. Similar trends are reported in experimental MPC studies for office [19] and residential buildings [20], where improved thermal comfort and energy flexibility are achieved, but economic benefits are reduced once realistic forecast errors and actuator constraints are taken into account. The present results reinforce the conclusion that forecast quality and actuator controllability are critical enablers for MPC performance.
The results further show that the performance gains achieved by the PVC compared to HC are more limited than often suggested in simulation-based studies. In the annual simulation analysis, switching from HC to PVC increases the LCF to an absolute improvement of 4–15 percentage points, depending on the storage options. In terms of annuity, PVC yields only a moderate reduction of total life-cycle costs of approximately 1–8 percentage points compared to HC, depending on the storage options.
The limitations of PVC become even more apparent in on-site operation. In the monitored 24 h comparison periods, PVC improves the LCF relative to HC by 9.5 percentage points in the first period but only by 1.9 percentage points in the second period, despite comparable PV availability. This strong variability indicates that the effectiveness of PVC is highly dependent on the temporal distribution of the heating load. When heating demand coincides with PV-rich hours, PVC can increase direct PV utilization; however, when heating demand during midday is low or absent, the impact of PVC becomes marginal. While PVC can be considered a simple and robust strategy for increasing PV utilization without forecasts, its effectiveness is strongly constrained by load timing, storage losses and reduced SPF. This trade-off illustrates that maximizing PV utilization through increased storage charging or extended heat pump operation during PV-rich periods inevitably leads to higher mean operating temperatures, partial efficiency losses and lower SPF. Consequently, control strategies must be evaluated based on multiple performance indicators rather than optimization toward a single metric such as SCF or LCF.
In contrast, the results for PVC and tbm activation show that simpler and more robust control concepts can already capture a large share of the attainable benefits in highly energy-efficient plus-energy buildings. Both simulation and on-site operation show that moderate increases of indoor temperature set-points (dT2) during periods of PV availability can significantly improve PV utilization. In simulation, PVC increases LCF by strategically shifting heat pump operation into PV-rich periods, while tbm activation achieves substantial increases in LCF (from ~20–25% to more than 45–60%) and reductions in grid-supplied heating energy of nearly 50% at comparable comfort levels. The comfort results indicate that moderate set-point increases (dT2–dT3) remain mainly (96%) within the comfort limits in summer, defined by EN ISO 7730, Category II, and lead to a predicted percentage of dissatisfied under 10%, while higher activation levels lead to increased deviations from the standard. The results also indicate that the effectiveness of tbm activation is dependent on the underlying control strategy. While tbm activation can reduce annuities by up to 12 percentage points under PVC, the reduction under HC is only 4%. In real-life implementation, the tbm-activated house reaches a high LCF of 46.6%. From an economic perspective, the increased utilization of locally generated PV electricity compensates a large share of the additional heating demand. As shown by the comparison with reference houses at similar comfort levels, higher LCF allows the operating costs of the thermally activated building to be reduced (20.7%), even when absolute heating energy consumption is higher. These effects are achieved without the need for complex optimization algorithms or high-quality forecasts. However, the impact of tbm activation on the overall energy system could not be fully assessed in the real-world implementation, as only two of the eight residential units participated in a continuous activation of tbm.
Table 9 provides a structured overview of the relative strengths and limitations of the investigated control strategies across simulation, HiL, and monitoring environments, facilitating a concise comparison of performance, robustness, and implementation effort.
Despite the comprehensive analysis combining simulation, HiL experiments and long-term monitoring, several limitations must be considered when interpreting the results. The study is based on a single-site case study with a specific system configuration and user behavior, which may limit the direct transferability of the findings to other building types, climate conditions, or operational settings. In addition, the activation of the tbm was implemented only in a subset of the residential units, which restricts the assessment of its impact on the overall system performance. Nevertheless, the results provide robust insights into the relative performance of control strategies in highly energy-efficient building systems. Future work should therefore focus on extending the analysis to a wider range of buildings and operating conditions, improving forecast models, and investigating control strategies at the district scale. Furthermore, future work should particularly focus on the integration of dynamic electricity pricing, as variable tariffs are increasingly available and characterized by growing price spreads, offering significant additional flexibility and economic optimization potential for control strategies under real market conditions.
Overall, the discussion of the results relative to the existing MPC literature [14,15,16,17,18,19,20] suggests that while MPC remains a powerful approach under favorable and well-controlled conditions, its additional value over robust rule-based strategies diminishes in highly energy-efficient plus-energy buildings. In such systems, the marginal gains of MPC must be carefully weighed against the increased implementation effort, forecast dependency and robustness requirements. A combination of simple PV-oriented control concepts with selective activation of passive storage options, such as tbm, may therefore represent a more practical and resilient pathway for many real-world applications. However, in the simulation study, the resulting annuity savings remain moderate, with a maximum of 12%, as system efficiency decreases due to higher storage temperature levels and high investment costs for PV plant and battery storage. Nevertheless, the relatively attractive PV feed-in tariff enables an economically viable deployment of the PV system and battery storage.

5. Conclusions

This study presents a comprehensive comparison of heat-controlled (HC), PV-controlled PVC), and both predictive control strategies (SPC and MPC) for a highly energy-efficient plus-energy terraced housing complex based on annual simulations, long-term monitoring, and hardware-in-the-loop (HiL) experiments.
The results show that the baseline HC operation already achieves a high level of performance, with an LCF of approximately 66% and SPF of the central heat pumps of about 5.8, leaving limited additional improvement potential for advanced control strategies. PVC increases PV utilization by shifting heat pump operation into PV-rich periods, leading to increases in the LCF by up to 4–15 percentage points in simulation, and in daily monitoring comparisons, up to 1.1 and 9.5 percentage points. However, this comes at the cost of elevated storage temperatures and efficiency reductions for the heat pumps, resulting in an SPF of 4.8 in simulations.
Predictive control strategies achieve the highest operational performance under idealized conditions. Simulation results show that MPC increases LCF by up to four percentage points and reduces operating costs by up to 212%, assuming perfect forecasts and full controllability of the heat pump system. HiL experiments show that MPC increases LCF to 39.7%, compared to 39.4% for PVC and 31.1% for HC. At the same time, real-world MPC operation exhibits reductions in heat pump efficiency of 15–20% and operating-cost deviations of 40–50% relative to optimization results, primarily due to forecast uncertainty and limited controllability of commercial heat pump systems.
The activation of building thermal mass proves to be a robust complementary flexibility option. Simulation results show that a moderate room set-point increase of about 2 K increases LCF from approximately 20–25% to more than 55–60%, while reducing grid-supplied heating energy by nearly 50% and maintaining acceptable comfort levels. Higher set-point increases result in diminishing energetic benefits and noticeable comfort degradation. Monitoring results confirm a substantial increase in LCF; however, they also show that absolute heating energy demand can increase, with economic benefits arising primarily from higher LCF rather than from reduced total heating energy.
Overall, the results indicate that in highly energy-efficient plus-energy buildings, simple and transparent control strategies combined with selective thermal mass activation can already capture a large share of the achievable flexibility potential. While MPC offers additional benefits under favorable conditions, its practical deployment requires high-quality forecasts, improved actuator controllability, and robust safety concepts to justify the added complexity in real operation.

Author Contributions

Conceptualization, C.B. and A.D.; methodology, C.B., S.H. and A.D.; software, C.B.; validation, C.B. and S.H.; formal analysis, C.B. and S.H.; investigation, C.B.; resources, A.D.; data curation, C.B.; writing—original draft preparation, C.B.; writing—review and editing, C.B., S.H. and A.D.; visualization, C.B.; supervision, A.D.; project administration, C.B.; funding acquisition, C.B. and A.D. All authors have read and agreed to the published version of the manuscript.

Funding

This research presents results from the projects “Herzo Base—Energy storage houses—An energy flexible building and energy concept of tomorrow” (FKZ 03ET1364A) and “Herzo Opt—Monitoring of the building envelope, thermal room comfort and energy system with operational optimization” (FKZ 03ET1641A). The project was funded by the German Federal Ministry for Economic Affairs and Energy on the basis of a decision of the German Bundestag.

Data Availability Statement

The data supporting the conclusions of this article will be made available by the authors on request.

Acknowledgments

The authors would like to thank Raab Baugesellschaft mbH & Co. KG for the realization and the vision of the Herzo Base terraced houses. The authors also gratefully acknowledge the Fraunhofer Institute for Building Physics (IBP) for the constructive collaboration and technical exchange. Furthermore, the authors would like to thank the project partners of the research projects Herzo Base and Herzo Opt: Evonik Industries AG, Schlagmann Poroton GmbH & Co. KG, Franken-Maxit Mauermörtel GmbH & Co., Veit Dennert KG, ait-deutschland GmbH, REHAU AG + Co, ProLeit AG, EFR GmbH, City of Herzogenaurach, HerzoWerke GmbH, and Agenda 21 Herzogenaurach. The authors further acknowledge the Projektträger Jülich for the professional supervision and support of the projects. Special thanks are due to the residents of the Herzo Base terraced houses, whose openness, commitment, and patience made this project possible. During the preparation of this manuscript, the authors used DeepL (version 26.3.1.19750) and Microsoft 365 Copilot, based on the GPT-5 chat model, to support wording and improve text coherence. The authors reviewed and edited all generated content and take full responsibility for the content of the publication.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

The following abbreviations are used in this manuscript:
DHWDomestic Hot Water
EEDEnergy Efficiency Directive
EPBDEnergy Performance of Buildings Directive
GAGenetic Algorithm
HCHeat-Controlled Operation
HiLHardware-in-the-Loop
HVACHeating, Ventilation and Air Conditioning
KPIKey Performance Indicator
LCFLoad Cover Factor
MAEMean Absolute Error
MHPModulating Heat Pumps
MILPMixed-Integer Linear Programming
MPCModel Predictive Control
NMAENormalized Mean Absolute Error
NRMSENormalized Root Mean Square Error
PEBPositive Energy Buildings
PEDPositive Energy District
PVPhotovoltaic
PVCPV-Controlled Operation
RMSERoot Mean Square Error
RNNRecurrent Neural Network
SCFSupply Cover Factor
SOCState of Charge
SPCSimple Predictive Control
SPFSeasonal Performance Factor
TESThermal Energy Storage
tbmthermal building mass

References

  1. The European Parliament and the Council of the European Union. Directive (EU) 2024/825 of the European Parliament and of the Council of 28 February 2024 Amending Directives 2005/29/EC and 2011/83/EU as Regards Empowering Consumers for the Green Transition Through Better Protection Against Unfair Practices and Through Better Information; European Union: Brussels, Belgium, 2024. [Google Scholar]
  2. The European Parliament and the Council of the European Union. Directive (EU) 2023/1791 of the European Parliament and of the Council of 13 September 2023 on Energy Efficiency and Amending Regulation (EU) 2023/955; European Union: Brussels, Belgium, 2023. [Google Scholar]
  3. Tuerk, A.; Frieden, D.; Neumann, C.; Latanis, K.; Tsitsanis, A.; Kousouris, S.; Llorente, J.; Heimonen, I.; Reda, F.; Ala-Juusela, M.; et al. Integrating Plus Energy Buildings and Districts with the EU Energy Community Framework: Regulatory Opportunities, Barriers and Technological Solutions. Buildings 2021, 11, 468. [Google Scholar] [CrossRef]
  4. Hawila, A.A.W.; Pernetti, R.; Pozza, C.; Belleri, A. Plus energy building: Operational definition and assessment. Energy Build. 2022, 265, 112069. [Google Scholar] [CrossRef]
  5. Magrini, A.; Lentini, G.; Cuman, S.; Bodrato, A.; Marenco, L. From nearly zero energy buildings (NZEB) to positive energy buildings (PEB): The next challenge—The most recent European trends with some notes on the energy analysis of a forerunner PEB example. Dev. Built Environ. 2020, 3, 100019. [Google Scholar] [CrossRef]
  6. Brozovsky, J.; Gustavsen, A.; Gaitani, N. Zero emission neighbourhoods and positive energy districts—A state-of-the-art review. Sustain. Cities Soc. 2021, 72, 103013. [Google Scholar] [CrossRef]
  7. Hedman, Å.; Rehman, H.U.; Gabaldón, A.; Bisello, A.; Albert-Seifried, V.; Zhang, X.; Guarino, F.; Grynning, S.; Eicker, U.; Neumann, H.-M.; et al. IEA EBC Annex83 Positive Energy Districts. Buildings 2021, 11, 130. [Google Scholar] [CrossRef]
  8. Derkenbaeva, E.; Halleck Vega, S.; Hofstede, G.J.; Van Leeuwen, E. Positive energy districts: Mainstreaming energy transition in urban areas. Renew. Sustain. Energy Rev. 2022, 153, 111782. [Google Scholar] [CrossRef]
  9. Sareen, S.; Albert-Seifried, V.; Aelenei, L.; Reda, F.; Etminan, G.; Andreucci, M.-B.; Kuzmic, M.; Maas, N.; Seco, O.; Civiero, P.; et al. Ten questions concerning positive energy districts. Build. Environ. 2022, 216, 109017. [Google Scholar] [CrossRef]
  10. Lindholm, O.; Rehman, H.U.; Reda, F. Positioning Positive Energy Districts in European Cities. Buildings 2021, 11, 19. [Google Scholar] [CrossRef]
  11. Chen, X.; Vand, B.; Baldi, S. Challenges and Strategies for Achieving High Energy Efficiency in Building Districts. Buildings 2024, 14, 1839. [Google Scholar] [CrossRef]
  12. Barber, K.A.; Krarti, M. A review of optimization based tools for design and control of building energy systems. Renew. Sustain. Energy Rev. 2022, 160, 112359. [Google Scholar] [CrossRef]
  13. Tahmasebinia, F.; Lin, L.; Wu, S.; Kang, Y.; Sepasgozar, S. Exploring the Benefits and Limitations of Digital Twin Technology in Building Energy. Appl. Sci. 2023, 13, 8814. [Google Scholar] [CrossRef]
  14. Fischer, D.; Bernhardt, J.; Madani, H.; Wittwer, C. Comparison of control approaches for variable speed air source heat pumps considering time variable electricity prices and PV. Appl. Energy 2017, 204, 93–105. [Google Scholar] [CrossRef]
  15. Pichler, M.; Heinz, A.; Rieberer, R. Model Predictive Heat Pump- and Building Control to Maximize PV-Power On Site Use. In Proceedings of 12th IEA Heat Pump Conference; Institute of Thermal Engineering: Graz, Austria, 2017. [Google Scholar]
  16. Salpakari, J.; Lund, P. Optimal and rule-based control strategies for energy flexibility in buildings with PV. Appl. Energy 2016, 161, 425–436. [Google Scholar] [CrossRef]
  17. Bechtel, S.; Rafii-Tabrizi, S.; Scholzen, F.; Hadji-Minaglou, J.-R.; Maas, S. Influence of thermal energy storage and heat pump parametrization for demand-side-management in a nearly-zero-energy-building using model predictive control. Energy Build. 2020, 226, 110364. [Google Scholar] [CrossRef]
  18. De Coninck, R.; Helsen, L. Practical implementation and evaluation of model predictive control for an office building in Brussels. Energy Build. 2016, 111, 290–298. [Google Scholar] [CrossRef]
  19. Bird, M.; Daveau, C.; O’Dwyer, E.; Acha, S.; Shah, N. Real-world implementation and cost of a cloud-based MPC retrofit for HVAC control systems in commercial buildings. Energy Build. 2022, 270, 112269. [Google Scholar] [CrossRef]
  20. Rolando, D.; Madani, H. A Heat Pump System Control Based on Solar Gain Prediction. HPT Magazine, 24 November 2020; pp. 18–21.
  21. EN 1434-1:2022; CEN/TC 176. Thermal Energy Meters—Part 1: General Requirements. European Committee for Standardization: Brussels, Belgium, 2023.
  22. TRNSYS, Version 18.06.0002; Transsolar: Stuttgart, Germany, 2021.
  23. Afjei, T.; Wetter, M. TRNSYS Type 401 Compressor Heat Pump Including Frost and Cycle Losses—Model Description and Implementing into TRNSYS; Zentralschweizerisches Technikum: Horw, Switzerland, 1997. [Google Scholar]
  24. MATLAB, Version 9.8 (R2020a); MathWorks: Natick, MA, USA, 2020. Available online: https://www.mathworks.com (accessed on 14 February 2022).
  25. Gurobi Optimizer Reference Manual, Version Gurobi Version 8; Gurobi Optimization, LLC: Beaverton, OR, USA, 2020. Available online: https://www.gurobi.com (accessed on 14 February 2022).
  26. Becker, R. Optimierung Thermischer Systeme in Dezentralen Energieversorgungsanlagen. Doctoral Dissertation, Fakultät für Elektrotechnik und Informationstechnik der Universität Dortmund, Dortmund, Germany, 2006. [Google Scholar]
  27. Thornton, J.W.; Bradley, D.E.; McDowell, T.P.; Blair, N.J.; Duffy, M.J.; LaHam, N.D.; Naik, A.V. TESSLibs 17-Storage Tank Library Mathematical Reference; Thermal Energy System Specialists, LLC: Madison, WI, USA, 2014. [Google Scholar]
  28. Python Language Reference, Version Version 3.7; Python Software Foundation: Wilmington, DE, USA, 2018. Available online: http://www.python.org (accessed on 1 October 2020).
  29. Abadi, M.; Barham, P.; Chen, J.; Chen, Z.; Davis, A.; Dean, J.; Devin, M.; Ghemawat, S.; Irving, G.; Isard, M.; et al. TensorFlow: A System for Large-Scale Machine Learning. In Proceedings of the 12th USENIX Symposium on Operating Systems Design and Implementation (OSDI 2016), Savannah, GA, USA, 2–4 November 2016; pp. 265–283. [Google Scholar]
  30. Betzold, C.; Dentel, A. Comparison and implementation of MPC and simple predictive control into a heat pump system. In Proceedings of the CLIMA 2022: The 14th REHVA HVAC World Congress, Rotterdam, The Netherlands, 22–25 May 2022. [Google Scholar] [CrossRef]
  31. Dentel, A.; Betzold, C. Activation of the building thermal mass to store PV surplus energy. In Proceedings of the Building Simulation 2021: 17th Conference of IBPSA, Bruges, Belgium, 1–3 September 2021. [Google Scholar] [CrossRef]
  32. EN 14511-3:2022; CEN/TC 113. Air Conditioners, Liquid Chilling Packages and Heat Pumps for Space Heating and Cooling and Process Chillers, with Electrically Driven Compressors—Part 3: Test Methods. European Committee for Standardization: Brussels, Belgium, 2023.
  33. Hummel, S.; Betzold, C.; Dentel, A. Impact of the Weather Forecast Quality on a MPC-driven Heat Pump Heating System. In Proceedings of the CLIMA 2022: The 14th REHVA HVAC World Congress, Rotterdam, The Netherlands, 22–25 May 2022. [Google Scholar] [CrossRef]
  34. Heimrath, R.; Haller, M. The Reference Heating System, the Template Solar System of Task 32; International Energy Agency (IEA): Paris, France, 2007. [Google Scholar]
  35. Shukla, K.N.; Rangnekar, S.; Sudhakar, K. Comparative study of isotropic and anisotropic sky models to estimate solar radiation incident on tilted surface: A case study for Bhopal, India. Energy Rep. 2015, 1, 96–103. [Google Scholar] [CrossRef]
  36. Betzold, C.; Bordin, S.; Dentel, A.; Harhausen, G. Control strategies for modulating heat pumps in a plus energy building. In Proceedings of the 13th IEA Heat Pump Conference 2021, Jeju, Republic of Korea, 26–29 April 2021. [Google Scholar]
  37. EN ISO 7730:2025; CEN/TC 122. Ergonomics of the Thermal Environment—Analytical Determination and Interpretation of Thermal Comfort Using Calculation of the PMV and PPD Indices and Local Thermal Comfort Criteria. International Organization for Standardization: Geneva, Switzerland, 2025.
  38. VDI Society Civil Engineering and Building Services. VDI 2067—1. Economic Efficiency of Building Installations Fundamentals and Economic Calculation; The Association of German Engineers (VDI): Düsseldorf, Germany, 2012. [Google Scholar]
  39. Deutscher Wetterdienst (DWD). 2020. Available online: https://www.dwd.de (accessed on 12 November 2020).
  40. Finck, C.; Li, R.; Zeiler, W. Identification of a dynamic system model for a building and heating system including heat pump and thermal energy storage. MethodsX 2020, 7, 100866. [Google Scholar] [CrossRef] [PubMed]
  41. Amasyali, K.; El-Gohary, N.M. A review of data-driven building energy consumption prediction studies. Renew. Sustain. Energy Rev. 2018, 81, 1192–1205. [Google Scholar] [CrossRef]
Figure 1. Terraced housing complex with eight residential units.
Figure 1. Terraced housing complex with eight residential units.
Buildings 16 02370 g001
Figure 2. Shared energy system. Different color lines represent the various energy flows within the system: light red and light green indicate the ground-source energy flows, light blue and light green represent the cooling flows, while red and blue denote the heat supply for space heating and domestic hot water (DHW). Dashed boxes indicate the boundaries of the main subsystems in each terraced house.
Figure 2. Shared energy system. Different color lines represent the various energy flows within the system: light red and light green indicate the ground-source energy flows, light blue and light green represent the cooling flows, while red and blue denote the heat supply for space heating and domestic hot water (DHW). Dashed boxes indicate the boundaries of the main subsystems in each terraced house.
Buildings 16 02370 g002
Figure 3. HiL test bench for innovative heating systems (left) and hydraulic and sensor schematic (right) of the test bench.
Figure 3. HiL test bench for innovative heating systems (left) and hydraulic and sensor schematic (right) of the test bench.
Buildings 16 02370 g003
Figure 4. Time series of boundary conditions applied in the HiL experiments, including solar irradiance (top), ambient temperature (second row), PV power and household electricity demand (third row), and space-heating demand (bottom), with a temporal resolution of 15 min.
Figure 4. Time series of boundary conditions applied in the HiL experiments, including solar irradiance (top), ambient temperature (second row), PV power and household electricity demand (third row), and space-heating demand (bottom), with a temporal resolution of 15 min.
Buildings 16 02370 g004
Figure 5. Comparison of measured and simulated performance indicators for the hardware-in-the-loop experiments under identical boundary conditions. Shown are the supply cover factor (SCF), the load cover factor (LCF), and the mean state of charge (SOC) of the thermal energy storage for the three control strategies—MPC, PVC and HC.
Figure 5. Comparison of measured and simulated performance indicators for the hardware-in-the-loop experiments under identical boundary conditions. Shown are the supply cover factor (SCF), the load cover factor (LCF), and the mean state of charge (SOC) of the thermal energy storage for the three control strategies—MPC, PVC and HC.
Buildings 16 02370 g005
Figure 6. (Upper panel): Annual energy flows (stacked bars: on-site PV consumption, battery discharge, grid electricity) and LCF (red line) for different control strategies and system design combinations (HC, PVC, with and without PV-based operation, battery storage, and thermal building mass). (Lower panel): annual electricity costs (bars) and relative annuity (red line) for the same strategy combinations.
Figure 6. (Upper panel): Annual energy flows (stacked bars: on-site PV consumption, battery discharge, grid electricity) and LCF (red line) for different control strategies and system design combinations (HC, PVC, with and without PV-based operation, battery storage, and thermal building mass). (Lower panel): annual electricity costs (bars) and relative annuity (red line) for the same strategy combinations.
Buildings 16 02370 g006
Figure 7. Annual energy flows shown in the (upper panel) (stacked bars: on-site PV consumption, battery discharge, grid electricity) and load cover factor (LCF, red line) for different control strategy combinations (HC, PVC, SPC, MPC). (Lower panel): annual electricity costs (bars) and relative annuity (red line) for the same strategy combinations.
Figure 7. Annual energy flows shown in the (upper panel) (stacked bars: on-site PV consumption, battery discharge, grid electricity) and load cover factor (LCF, red line) for different control strategy combinations (HC, PVC, SPC, MPC). (Lower panel): annual electricity costs (bars) and relative annuity (red line) for the same strategy combinations.
Buildings 16 02370 g007
Figure 8. Simulation results of thermal building mass activation for a corner house (left) and a middle house (right) for increasing room temperature set-point shifts (dT0–dT6). The top row shows overheating hours and relative grid electricity consumption, the middle row the mean absolute room temperature deviation and load cover factor (LCF), and the bottom row the annual heating energy demand and resulting relative operating costs. The results illustrate the trade-off between thermal comfort, grid interaction and PV utilization with increasing activation of the building thermal mass.
Figure 8. Simulation results of thermal building mass activation for a corner house (left) and a middle house (right) for increasing room temperature set-point shifts (dT0–dT6). The top row shows overheating hours and relative grid electricity consumption, the middle row the mean absolute room temperature deviation and load cover factor (LCF), and the bottom row the annual heating energy demand and resulting relative operating costs. The results illustrate the trade-off between thermal comfort, grid interaction and PV utilization with increasing activation of the building thermal mass.
Buildings 16 02370 g008
Figure 9. Measured 24 h profiles under HC (left) and PVC (right) operation for the first similar 24 h periods. Shown are PV power and total electrical power (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Figure 9. Measured 24 h profiles under HC (left) and PVC (right) operation for the first similar 24 h periods. Shown are PV power and total electrical power (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Buildings 16 02370 g009
Figure 10. Measured 24 h profiles under HC (left) and PVC (right) operation for the second similar 24 h periods. Shown are PV power and total electrical power (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Figure 10. Measured 24 h profiles under HC (left) and PVC (right) operation for the second similar 24 h periods. Shown are PV power and total electrical power (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Buildings 16 02370 g010
Figure 11. Measured 24 h profiles under PV (left) and MPC (right) operation for the first similar 24 h periods. Shown are PV power, total electrical power and PV power forecast (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Figure 11. Measured 24 h profiles under PV (left) and MPC (right) operation for the first similar 24 h periods. Shown are PV power, total electrical power and PV power forecast (panel 1); household electricity demand, space-heating load, and domestic hot-water (DHW) production (panel 2); electrical power of both central heat pumps and booster heat pump electricity demand (panel 3); buffer storage temperatures at four measurement points (panel 4); and mean DHW temperature of the eight decentralized DHW storage tanks (panel 5).
Buildings 16 02370 g011
Figure 12. Measured operation of thermal building mass activation during two representative monitoring periods. Shown are the heating power together with the mean indoor temperature and the room temperature set-points (top), as well as solar irradiation and ambient temperature (bottom), for Period 1 ((left), November–December 2020) and Period 2 ((right), February 2021).
Figure 12. Measured operation of thermal building mass activation during two representative monitoring periods. Shown are the heating power together with the mean indoor temperature and the room temperature set-points (top), as well as solar irradiation and ambient temperature (bottom), for Period 1 ((left), November–December 2020) and Period 2 ((right), February 2021).
Buildings 16 02370 g012
Figure 13. Measured long-term operation of thermal building mass activation from 11 November 2020 to 31 March 2021. The figure shows the mean indoor temperature and room temperature set-points (top), heating power separated into PV-driven and grid-driven operation (middle), and solar irradiation together with ambient temperature (bottom).
Figure 13. Measured long-term operation of thermal building mass activation from 11 November 2020 to 31 March 2021. The figure shows the mean indoor temperature and room temperature set-points (top), heating power separated into PV-driven and grid-driven operation (middle), and solar irradiation together with ambient temperature (bottom).
Buildings 16 02370 g013
Table 1. Simulation model for energy system.
Table 1. Simulation model for energy system.
ModelHeat PumpTESSoftware
Matlab_simplecharacteristic curveenergy-node modelMATLAB
TRNSYSTYPE 4010TYPE 534TRNSYS
Table 2. Tariff costs overview.
Table 2. Tariff costs overview.
PropertiesValue
Grid electricity costs (€/kWh)0.34
PV feed-in tariff (€/kWh)0.11
Table 3. Investment costs from 2017, depreciation period, and efforts for inspection, servicing, repair, and operation according to VDI 2067.
Table 3. Investment costs from 2017, depreciation period, and efforts for inspection, servicing, repair, and operation according to VDI 2067.
PropertiesInvestment CostsDepreciation
Period
Effort
for Maintenance
Effort
for Servicing
and Inspection
Effort
for
Operation
PV plant€133,60920 years1.0%1%0.0%
Battery€54,80015 years1.0%1.5%0.0%
Table 4. Results of the simulation model validation.
Table 4. Results of the simulation model validation.
PropertiesSCFLCFSPFEl. Consumption of MHPOperating Costs
Matlab_simple6.6%44.2%4.6712.7 MWh€2414
TRNSYS6.7%46.0%4.7812.5 MWh€2287
measurement6.6%45.3%4.6712.5 MWh€2315
Table 5. Deviations of thermal and electrical RNN for test data.
Table 5. Deviations of thermal and electrical RNN for test data.
PropertiesMAENMAEPredicted (Measured) Mean Load
Thermal RNN4.04 kW0.489.2 (8.4) kW
Electrical RNN0.92 kW0.312.7 (3.0) kW
Table 6. MPC-MILP operation from 8 March until 23 April 2022.
Table 6. MPC-MILP operation from 8 March until 23 April 2022.
PropertiesOptimizationMeasurementDifference
PV production12.7 MWh13.6 MWh7.1%
Energy consumption6.1 MWh6.5 MWh7.0%
SCF excl. battery charge26.3%26.3%0.0%
SCF32.8%38.1%5.3%
LCF excl. battery discharge54.9%51.8%−3.1%
LCF74.3%70.4%−4.0%
Operating costs−€408−€207−49.3%
SPFMHP4.94.1−15.2%
Table 7. MPC-GA operation from 20 April until 6 July 2022.
Table 7. MPC-GA operation from 20 April until 6 July 2022.
PropertiesOptimizationMeasurementDifference
PV production28.0 MWh28.4 MWh1.4%
Energy consumption 5.7 MWh8.4 MWh48.0%
SCF excl. battery charge14.3%20.6%6.2%
SCF 21.8%41.1%19.4%
LCF excl. battery discharge70.3%65.1%−5.2%
LCF87.3%87.6%0.3%
Operating costs−€2161−€1837−15.0%
SPFMHP5.04.0−20.5%
Table 8. Comparison of heating energy consumption, mean indoor temperature and LCF between the thermally activated house (House M) and reference houses (House A and House B) under real operating conditions.
Table 8. Comparison of heating energy consumption, mean indoor temperature and LCF between the thermally activated house (House M) and reference houses (House A and House B) under real operating conditions.
PropertiesMean Room TemperatureLCFHeating EnergyEnergy Costs
House M20.59 °C46.6%2934 kWh€51.05
House A20.95 °C20.1%2391 kWh€64.39
House B19.61 °C24.9%1775 kWh€20.07
Table 9. Qualitative comparison of HC, PVC, SPC, and MPC with respect to SCF/LCF, heat pump efficiency, robustness in real operation, and implementation complexity, based on simulation, HiL, and monitoring results.
Table 9. Qualitative comparison of HC, PVC, SPC, and MPC with respect to SCF/LCF, heat pump efficiency, robustness in real operation, and implementation complexity, based on simulation, HiL, and monitoring results.
Control StrategySCF/LCFSPFRobustness in Real OperationImplementation Complexity
HCHighHighVery highVery low
PVCHighReduced due to higher storage temperaturesHighLow
SPCHighSlightly reducedNot shownNot shown
MPCHigh in simulation
and HiL
Reduced in
real operation
Limited by forecast quality and controllabilityHigh
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Betzold, C.; Hummel, S.; Dentel, A. Long-Term Monitoring and Comparison of Control Strategies for Optimizing Energy Consumption in a Plus-Energy Building. Buildings 2026, 16, 2370. https://doi.org/10.3390/buildings16122370

AMA Style

Betzold C, Hummel S, Dentel A. Long-Term Monitoring and Comparison of Control Strategies for Optimizing Energy Consumption in a Plus-Energy Building. Buildings. 2026; 16(12):2370. https://doi.org/10.3390/buildings16122370

Chicago/Turabian Style

Betzold, Christina, Sebastian Hummel, and Arno Dentel. 2026. "Long-Term Monitoring and Comparison of Control Strategies for Optimizing Energy Consumption in a Plus-Energy Building" Buildings 16, no. 12: 2370. https://doi.org/10.3390/buildings16122370

APA Style

Betzold, C., Hummel, S., & Dentel, A. (2026). Long-Term Monitoring and Comparison of Control Strategies for Optimizing Energy Consumption in a Plus-Energy Building. Buildings, 16(12), 2370. https://doi.org/10.3390/buildings16122370

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Article metric data becomes available approximately 24 hours after publication online.
Back to TopTop