1. Introduction
With the continuous expansion of China’s infrastructure construction, especially the rapid development of highways, railways, ports, and urban underground spaces, foundation treatment technology has become a key link to ensure the safety and stability of projects. Liu and Zhao [
1] systematically reviewed the progress of foundation treatment technology and theoretical research in China, pointing out that a batch of new technologies and new processes with distinctive features have emerged in recent years, and standardization of construction has gradually improved, providing important support for engineering practice under complex geological conditions. At the same time, engineering safety issues have increasingly drawn attention. Wen et al. [
2] analyzed the severity of truck accidents on mountain highways and their influencing factors, revealing the critical role of road conditions, alignment design, and protective measures in accident risk, further highlighting the foundational support role of foundation treatment technology in improving overall road safety.
In the field of foundation treatment, in addition to traditional drainage consolidation and chemical reinforcement methods, some innovative treatment technologies have been developed in recent years. Lu et al. [
3] proposed an explicit analytical solution considering stress variations with depth for the consolidation problem of vertical drainage wells under multi-level loads, analyzed well resistance and smear effects, and explored three attenuation patterns of horizontal permeability coefficients, providing a theoretical basis for the design of drainage consolidation. Shen et al. [
4] studied the application mechanism of the gas injection desaturation method in sand liquefaction resistance by physical experiments and two-phase flow simulations. Sun et al. [
5] invented the Soil Continuous Solidification Pile Group (SCS group piles). Indoor half-model experiments showed that its ultimate compressive bearing capacity is four to nine times higher than that of traditional pile groups and provided design recommendations for continuous solidification depth. These technologies enrich the methods of foundation treatment, but each has specific applicable conditions and limitations.
As one of the most widely used techniques in soft foundation treatment, cement–soil mixing piles have made significant progress in recent years in pile type innovation, construction process optimization, and bearing mechanism research. Lyv et al. [
6] optimized the pile layout parameters of cement–soil mixing piles through indoor mix ratio and on-site pile formation tests, focusing on coastal soft foundations, proposing a four-mix–four-spray process and a cement mass fraction of 16–18%, which can effectively shorten construction time while ensuring pile quality. Liu et al. [
7] developed a bidirectional cement–soil mixing pile, and comparative on-site tests demonstrated that its pile body strength and socio-economic benefits are superior to those of conventional mixing piles. Yi et al. [
8] further developed variable-diameter bidirectional cement–soil mixing piles, used to treat multi-layer weak foundations where the intermediate soft soil layer is located. Field test piles confirmed that this process can form a new type of pile with an enlarged intermediate section.
In terms of variable cross-section piles, Liu et al. [
9] proposed the T-shaped deep soil-cement mixing pile (TDM pile). Through field tests, it was found that, compared with traditional constant-section piles, TDM piles not only reduce settlement and improve stability but also lower costs. Yi et al. [
10,
11,
12] studied the vertical bearing mechanism, failure modes, and composite foundation bearing capacity of T-shaped piles in soft soil through indoor model tests, full-scale field tests, and numerical simulations, finding that stress concentration and failure are prone to occur in the slender section below the enlarged head, and, based on this, proposed a simplified method for calculating ultimate bearing capacity. Zhou et al. [
13] analyzed the effects of wall thickness, pile diameter, and pile length on bearing performance through laboratory tests and numerical models, suggesting that piles with a diameter of 600 mm have the optimal unit volume bearing capacity. Yi et al. [
14] used three-dimensional numerical simulations to study the behavior of variable-section mixing piles reinforcing layered weak foundations under embankment loads and found that there is an optimal pile diameter ratio that minimizes surface settlement.
In the research and application of new types of mixing piles, Wu et al. [
15] studied the bearing characteristics of spiral core mixing piles through laboratory model tests and numerical simulations, finding that their bearing capacity is 1.44 times higher than that of traditional circular core piles, and explored the optimal value of the thread height ratio. Li et al. [
16] conducted field tests on Deep Mixing Jet (DMJ) integrated cement–soil mixing pile groups targeting the silty soil regions of the Yellow River floodplain, analyzing the effects of displacement rate and pile spacing on settlement control and bearing capacity. Wang et al. [
17] studied the temperature field changes during the process of reinforcing soft soil with cement–soil mixing piles, providing a new perspective for understanding the impact of cement hydration heat on pile performance. Yan et al. [
18] combined field static load tests with a DEM-FDM coupled model to investigate the relative displacement characteristics at the pile–cement–soil interface for different core pile types (pipe piles, square piles, and nodal piles), and proposed the principle of relative displacement superposition. Su et al. [
19], based on the theory of elastic dynamics, derived the analytical solution of dynamic impedance for concrete-core cement–soil mixing piles under horizontal dynamic loads and analyzed the effects of pile radius, elastic modulus, and soil density on dynamic response. Xia et al. [
20] compared the reinforcement effects of bidirectional mixing (BDM) and the conventional unidirectional mixing process, confirming that BDM can significantly enhance pile strength and reduce energy consumption. Chen et al. [
21] revealed the shielding effect of deep cement–soil mixing pile rows on anchored sheet pile wharves in soft clay through centrifuge experiments and three-dimensional numerical simulations, elucidating the soil arching effect and stress transfer mechanism. Zhao et al. [
22,
23] conducted field tests and numerical simulations on bidirectional helical mixing piles (BHCM) and fiber-reinforced helical mixing piles (FHSCM) in marine soft soil, showing that the new pile types significantly improved both vertical and horizontal bearing performance and had superior economic efficiency, with PVA fibers physically bridging to enhance the cement–soil’s crack resistance and toughness. Singh et al. [
24] proposed a multi-wing deep cement–soil mixing pile and analyzed its failure mode through three-dimensional numerical simulation, indicating that reasonable shape factors and wing spacing design can effectively improve pile bearing capacity. Zhang et al. [
25] studied the seismic performance of pile groups with cement–soil mixing piles at different reinforcement depths in liquefiable sand through shaking table tests, finding that DCM piles can significantly suppress excess pore water pressure accumulation and reduce structural displacement and pile bending moments.
Although cement–soil mixing piles, T-shaped piles, and screw piles have achieved certain results in foundation treatment, each still has obvious limitations. Traditional cement–soil mixing piles use in situ mixing technology, and the uniformity of the pile body is greatly affected by variations in soil layers, often resulting in quality issues such as strength dispersion and core sample breakage. T-shaped piles (such as nail-shaped mixing piles), while increasing bearing capacity through variable cross-section design, rely on complex retractable mixing blades for construction, and the uniformity problem caused by in situ mixing has not been fundamentally resolved. Screw piles rely on helical blades for load bearing, and their bearing capacity is sensitive to soil conditions and construction torque, with a tendency to become unstable in soft soils. To address these issues, this paper proposes the Pre-mixed Slurry-Solidified Pile (PSP)—a technology that pre-mixes soil, solidifying agents, and water on the surface into a flowable solidified soil, which is then injected through pre-drilled holes. This method can solve the unevenness and insufficient pile quality caused by in situ cement–soil mixing and significantly increase the pile’s bearing capacity. Compared with traditional techniques such as borehole grouting, cement–soil replacement, and cemented soil applications, the pre-mixed fluid-solidified soil pile (PSP) has fundamental differences. Borehole grouting involves an additional post-grouting process on a concrete pile foundation, whereas the PSP directly uses pre-mixed flowable cemented soil to form a pile in a single press-injection, without an independent concrete core. The cement–soil replacement method emphasizes in situ soil extraction and surface mixing followed by backfilling, usually forming piles with a uniform cross-section. Although PSPs also use pre-mixed soil, they employ a spraying and press-injection process that can simultaneously create variable cross-section structures, and the mixture is strictly proportioned flowable cemented soil, offering superior homogeneity and strength stability. Cement–soil piles often adopt in situ mixing processes, where the uniformity of the pile is greatly affected by soil layer variations. PSPs may address the uniformity issue through pre-mixing, and due to high-quality pile, variable cross-section structures can be introduced to achieve enhanced performance. Pre-mixed fluid-solidified soil piles (PSPs), as a new technology, still require further development in terms of theoretical research and design systems. Therefore, this research provides a preliminary introduction to the technical principles and processes of the new technology, its characteristics and advantages, and the construction machinery involved. It also conducts testing of pile integrity and load-bearing capacity in conjunction with on-site engineering applications, and derives calculation equations for the bearing capacity and settlement deformation of composite foundations based on existing standards.
2. Test Preparation
2.1. Setups
The principle of pre-mixed fluid-solidified soil piles (PSPs) is to use a rotary drilling rig to excavate the natural foundation soil to form a hole, and then pour pre-mixed, uniform flowable solidified soil to replace the foundation soil in its original position. Since the two have similar unit weights, the additional stress caused is minimal, thus enabling replacement in the original position. Therefore, the adopted fluid-solidified soil is pre-mixed, and the flowable soil is stirred uniformly to ensure that the completed piles are intact, uniform, and consistent. Due to the good fluidity of the fluid-solidified soil, the self-weight and fluidity of the solidified soil guarantee the compaction of the poured flowable solidified soil.
The construction machine and equipment required for the implementation of pre-mixed flow-solidified soil piles are shown in
Figure 1, and mainly include: a rotary drilling rig; rotary drill rods with lengths ranging from 8 to 20 m; a solidification slurry mixer; a flowable solidified soil mixer; a pump with a pressure of not less than 10 MPa; and an excavator (for on-site soil transportation). By combining drill rods of different diameters and lengths, it is possible to construct uniform cross-section piles, as well as piles with variable cross-sections. The combination of drill rods used in this in situ test is shown in
Figure 2.
2.2. Materials and Pile Parameters
Three types of piles (CMP, uniform-section PSP, and variable-section PSP) were tested, with three repetitions for each type. All piles had a length of 10 m and a base diameter of 500 mm, with the same mix ratio (water:binder:soil = 1:1.12:4.94 by mass) and were cured for 28 days. The variable-section PSP featured an enlarged section (2 m long, 700 mm in diameter). Core sampling, unconfined compressive strength (UCS) tests, and static load tests were conducted on each pile.
Table 1 presents the complete test matrix from the field experiments, as shown below.
2.3. Experimental Procedure
To ensure the uniform mixing of flowable solidified soil, a two-step mixing method is adopted. In the first step, the cement slurry is mixed. The cement slurry is prepared with a water–cement ratio of 0.89. After the cement slurry is prepared, it is poured into the flowable solidified soil mixer, and the soil is added while stirring, continuing until the flowable solidified soil reaches a uniformly fluid state. It should be noted that during the preparation of the cement slurry, the water–cement ratio should be adjusted according to the flowable solidified soil mix and taking into account the natural water content of the on-site foundation soil.
The technology of pre-mixed fluid-solidified soil piles uses long spiral drilling to pre-establish the borehole. During the drilling process, the rotation of the spiral blades of the long spiral drill rod drives the screw into the foundation soil under its own weight. The vertical radial expansion force generated by the power rotation presses the soil, loosening it, and then the soil is discharged to the surface, along the spiral blades of the drill rod, forming the borehole. Once the spiral drill rod reaches the designed elevation at the pile base, drilling is stopped, and the drill rod remains in the borehole. At this time, the drill rod provides certain support to the borehole, preventing the collapse of the borehole walls. At the same time as the drilling, fluid-solidified soil is mixed. Water is thoroughly stirred with cement or other solidifying materials in a cement slurry mixing tank, then conveyed to a fluid soil mixing tank, to which the soil cuttings from the helical drilling machine are added and mixed until achieving a uniform flowable state. This mixture is pumped through the pump and the inner conduit of the drill rod into the borehole. During the grouting process, the drill rod is gradually lifted, and after the fluidized solidified soil has been poured to the designed pile tip elevation, a pile is formed. The test site mainly consists of silty clay and silt, which have good self-stability, and no collapse was observed during the drilling process. In addition, PSPs adopt the method of forming piles by pouring pre-mixed flowable solidified soil, and the mix ratio used provides the mixture with good fluidity and self-compacting properties. Core sampling results on-site indicate that the PSP cores are uniform and dense, with no obvious stratification.
The specific construction process includes: site entry → site leveling → measurement and staking (while completing the installation and debugging of construction machinery) → marking pile positions → positioning the drilling rig → starting the drilling rig and drilling with the drill rod (while preparing the flowable solidified soil) → drilling to the designed elevation at the pile base (pre-hole completion) → pouring flowable solidified soil, simultaneously lifting the drill rod to the designed pile tip elevation during pouring → completion of a single pile, cleaning the drill rod → moving the piling rig to construct the next pile. The construction process flow is shown in
Figure 3.
It is noteworthy that when conducting tests on pre-mixed fluid-solidified soil piles (PSPs), the flowable cemented soil should first have the cementitious stabilizer evenly mixed with water. The water-to-cement ratio (by mass) should be controlled within the range of 1.0 ± 0.1, adjusted dynamically according to the moisture content of the borehole spoil. The water-to-solid ratio (mass ratio of water to dry soil and stabilizer) should be controlled within 45% ± 3%, and the slump of the flowable cemented soil should be 200 mm ± 30 mm. The amount of curing agent added to the flowable solidified soil should not be less than 15%. It is recommended that the mass ratio of the flowable solidified soil be water:dry soil:curing agent = 1.00:4.94:1.12. During lifting the drill rod to pour the flowable solidified soil, the rod should be lifted slowly, keeping the guide pipe level with the surface of the flowable solidified soil to ensure a dense pour. The pouring process of the flowable solidified soil should be continuous to ensure the pile is cast in one go. If there is a pause of more than 1.5 h, the drill rod should be lifted slowly 2–3 times, with a lifting distance of 0.2–0.3 m, before continuing the pouring to ensure the integrity of the joint position. The pumping pressure is regulated by the hydraulic system of the concrete delivery pump, and a pressure gauge is installed at the pump outlet for real-time monitoring. During normal pouring, the pump pressure is controlled between 0.3 and 0.6 MPa. When encountering variable cross-section construction, the pump pressure temporarily increases to 0.8–1.2 MPa, working in conjunction with the drill bit’s jet expansion device to achieve pile end enlargement. It should be noted that the actual grouting volume is determined by recording the total amount of slurry discharged from the mixing station. Before constructing each pile, the theoretical grouting volume is calculated, and after construction, it is compared with the actual total amount pumped. The pile construction results indicate that the deviation of the actual grouting volume in this test from the theoretical value is within ±5%, and the piles are well filled. The drilling process of the spiral drill rod should be conducted at a uniform and continuous speed, with a drilling rate of 2.0–3.0 m/min and a lifting rate of 1.5–2.0 m/min. After the construction of the pre-mixed flowable grouting-reinforced soil piles is completed, a 300–500 mm thick cement–soil cushion with a cement content of 4% should be placed on top of the piles, with a compaction degree of no less than 90%. It is advisable to set a layer of reinforcement at the bottom of the cushion.
7. Conclusions
As an efficient foundation reinforcement technique, pre-mixed fluid-solidified soil piles have easily controllable pile quality, rapid construction speed, and high bearing capacity. This technology holds significant potential for promotion and broad application in the reinforcement of weak foundations for high-grade highways. This research focuses on the foundation treatment technology using pre-mixed fluid-solidified soil piles, conducting in situ test, as well as theoretical derivations of the bearing capacity and settlement deformation of composite foundations. The main conclusions are as follows.
(1) Based on the core samples, the use of the flowable solidified soil pre-mixing and pre-formed hole grouting process has significantly improved the quality of the reinforced soil piles compared to the traditional in situ mixing method, with better overall integrity and uniformity of the core samples. Excavation results at the pile heads indicate that the formed variable-section pre-mixed fluid-solidified soil piles have transition body dimensions consistent with the design, with clear contours and neat interfaces, achieving the desired effect.
(2) The bearing capacity of pre-mixed fluid-solidified soil pile has been significantly improved. The characteristic bearing capacity of the PSP with a uniform cross-section is 252 kN, meeting the design requirement of 130 kN. In terms of ultimate bearing capacity, the PSP with a uniform cross-section shows a significant increase of 177% compared to the CMP with a uniform cross-section. The variable cross-section PSP further increases by 153% compared to the PSP with a uniform cross-section, indicating that the variable cross-section configuration has a more prominent effect on enhancing bearing capacity.
(3) The bearing capacity of composite foundations treated with pre-mixed fluid-solidified soil piles (PSPs) has been significantly improved compared to the bearing capacity characteristics of the original cement–soil mixing pile composite foundations. The characteristic value of the foundation bearing capacity for a PSP with a uniform-section is 2.01 times the original design value. After being treated with a variable-section PSP, the characteristic value of the foundation bearing capacity is further increased by 14% compared to the uniform-section case.
(4) Based on existing standards, equations for the bearing capacity and settlement deformation of composite foundations treated with pre-mixed fluid-solidified soil piles were derived considering both uniform and variable cross-sections. The proposed equations require a few parameters and have clear physical significance, making them suitable for on-site application of this technology.