Next Article in Journal
Lateral Performance of Semi-Rigid Steel Frames with Precast Knee Bracing Systems: Testing and Finite Element Analysis
Previous Article in Journal
Intelligent Prediction and Optimization of Concrete Resource Mismatch in China’s Construction Industry—An Explainability Analysis Based on XGBoost-SHAP
Previous Article in Special Issue
Tri-Objective Optimization of Metro Station Underground Structures Considering Cost, Carbon Emissions, and Reliability: A Case Study of Guangzhou Station
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Spatiotemporal Evolution and Deformation Mechanism of Deep Foundation Excavation in Water-Rich Sand Strata: A Comparative Study of Monitoring and Simulation

1
China Communications Construction Second Engineering Bureau No. 3 Co., Ltd., Xi’an 710018, China
2
School of Urban Planning and Municipal Engineering, Xi’an Polytechnic University, Xi’an 710600, China
*
Author to whom correspondence should be addressed.
Buildings 2026, 16(2), 317; https://doi.org/10.3390/buildings16020317
Submission received: 27 November 2025 / Revised: 25 December 2025 / Accepted: 6 January 2026 / Published: 12 January 2026

Abstract

Deep foundation excavation in water-rich sand strata presents complex deformation characteristics driven by fluid–solid interaction, which distinguishes it from excavations in cohesive soft clay. This study investigates the spatiotemporal evolution and deformation mechanisms of retaining structures through a comparative analysis of field monitoring data and 3D numerical simulation, based on a subway station project in Xi’an. While the numerical simulation predicted a continuous “bulging” deformation mode, field monitoring revealed a distinct transition from a “bulging” profile to a “step-like” deformation pattern as the excavation deepened. Quantitatively, while the simulation captured the spatial trend, the measured maximum surface settlement (7.8 mm) exceeded the simulated value (1.2 mm), highlighting the dominant role of seepage consolidation. Detailed analysis indicates that this discrepancy—and the unique step-like evolution—is primarily driven by two mechanisms: the rapid stress relaxation of cohesionless sand during the time lag of support installation, and the superimposed seepage forces induced by continuous dewatering, which are often simplified in standard elastoplastic models. The study further identifies that the vertical displacement of the pile top is governed by the combined effects of basal heave and the “kick-out” deformation at the pile toe. These findings demonstrate that in high-permeability water-rich sand, deformation control depends critically on minimizing the unsupported exposure time of the excavation face. This research provides a theoretical basis for optimizing the spatiotemporal sequencing of excavation in similar geological conditions.

1. Introduction

With the rapid economic development and urbanization in China, the construction of urban rail transit systems has surged, leading to an increasing number of deep foundation pit projects in complex urban environments. In the current construction landscape, subway stations are often characterized as “long, large, and deep”. When these excavations traverse complex hydrogeological environments, particularly water-rich sand strata, the interaction between groundwater seepage and soil deformation poses significant threats to construction safety and surrounding infrastructure. Historical cases indicate that in such strata, hydraulic instability can rapidly lead to catastrophic failures, such as sand boiling, quicksand formation, and the sudden collapse of supporting structures, which account for over 30% of foundation pit accidents in water-rich regions. Therefore, strictly controlling settlement and understanding the deformation mechanism in such strata is critical [1].
Over the years, extensive research has been conducted on the design and monitoring analysis of foundation pit excavations. Peck [2] pioneered the theoretical analysis of settlement profiles, establishing a framework that is still widely used. Sugimoto et al. [3] derived empirical formulas for predicting maximum surface settlement based on distance from the pit edge. Building on these classical theories, recent studies have increasingly combined field monitoring with numerical simulation to address complex geological conditions. Li et al., Wu et al., and Ye et al. [4,5,6] utilized finite element methods (FEMs) to analyze horizontal displacement rules, generally finding that simulation trends coincide with measured data, though accuracy is often limited by environmental factors and spatiotemporal effects.
However, excavation in water-rich strata presents unique challenges compared to dry soils due to high permeability and fluid–solid coupling effects. In water-rich sand strata, the presence of groundwater significantly impacts the shear strength parameters of the soil. The lubrication effect of water reduces the inter-particle friction, and the generation of pore water pressure under dynamic construction disturbance reduces the effective stress. Consequently, this leads to a degradation in both the internal friction angle (φ) and cohesion (c), making the stratum more susceptible to deformation during excavation.
Recently, scholars have paid closer attention to the spatiotemporal evolution and hydraulic risks in these specific strata. For instance, Ren et al. [7] analyzed the temporal and spatial evolution of earth pressure and settlement in water-rich sand layers, highlighting the sensitivity of sandy strata to construction disturbances. Similarly, Feng et al. [8] investigated the excavation response of metro stations in water-bearing strata adjacent to tall buildings, emphasizing the impact of excavation on the surrounding environment. Regarding the specific risks induced by groundwater, Tian et al. [9] combined on-site investigation with simulation to study leakage effects in water-rich strata, verifying that numerical methods can effectively capture the hydraulic response of underground structures. Furthermore, Xu et al. [10] deepened the understanding of failure mechanisms by studying water and sand leakage using CFD-DEM coupling, revealing how seepage forces drive microscopic particle loss and macroscopic deformation.
Despite these advances, a significant gap remains in understanding the dynamic transition of deformation modes in water-rich sand foundation pits. Most existing numerical simulations assume ideal elastoplastic behavior and often fail to capture the “step-like” deformation pattern observed in practice, which typically results from the combined effect of rapid stress relaxation in cohesionless sand and the time lag in support installation. Standard simulations tend to predict a continuous “bulging” shape, leading to a discrepancy between design expectations and actual monitoring data.
To bridge this gap, this paper takes a subway station project in Xi’an Metro—located in a typical water-rich sand stratum—as a case study. Using the 3D finite element program Midas/GTS NX (2022), we established a dynamic excavation model to perform a comparative analysis with field monitoring data. Unlike previous studies that focus primarily on final deformation values, this research specifically investigates the spatiotemporal evolution mechanism that drives the enclosure structure from a “bulging” to a “step-like” profile. In this study, this ‘transition’ is quantitatively defined as the vertical migration of the point of maximum horizontal displacement (Hmax) from the deep soil depth (typical of the ‘bulging’ mode) to the very top of the pile (typical of the ‘step-like’ or ‘kick-out’ mode).
By elucidating the discrepancy between simulation and measurement, this study provides a theoretical basis for optimizing excavation sequences and support timing in similar high-permeability geological conditions.

2. Project Overview

2.1. Station Pit Overview

Xi’an Metro Line 10 Dongfeng Road Station is located at the intersection of Yangguang Avenue and Dongfeng Road, and the station is arranged along Yangguang Avenue in a north–south direction under the road. Dongfeng Road Station is an underground two-story island station, which is constructed by open excavation method, and in order to reduce the impact on traffic, the middle part of the station is constructed by cover excavation and semi-reverse construction, as shown in Figure 1 below. The length of the station pit is 228 m, the depth of the bottom plate is about 16.0–17.5 m, and the thickness of the top plate cover is 3.55 m.
In order to minimize the disturbance of deformation and settlement of water-rich sand layer by pit excavation, the principle of layered block excavation is adopted, with excavation from both sides to the middle, each time at a depth of 2 m, and step-by-step excavation for construction, with transverse and longitudinal slopes of not more than 45°, and the depth of pulling groove at about 2.5 m, combined with timely support and efficient precipitation measures, which effectively reduces the risk of pit settlement and lateral shift during construction.

2.2. Geological Conditions

The geomorphological unit of the proposed Dongfeng Road Station area belongs to Weihe River floodplain, the site topography is flat, the stratum is dominated by highly permeable medium and fine sands, locally mixed with silt and clay, the contact between soil particles is loose and the shear strength is low, it is easy to cause local stratum subsidence due to precipitation, and it is necessary to strengthen the monitoring of the water level and the deformation of the ground layer in the process of excavation. The ground elevation is generally 370.62~373.85 m. The groundwater of the proposed site belongs to the pore phreatic water of the Quaternary system, mainly distributed in the strong permeability of the sand layer. The groundwater has a significant impact on the soil consolidation and settlement and the stability of the enclosure structure, and it is necessary to take targeted precipitation and reinforcement measures. The survey period is a flat water level period. The depth of the groundwater level is 6.8–14.8 m, and the elevation of the groundwater level is 359.67–368.08. Considering the influence of the rise in the water level of the Wei-Ba River, it is determined that the annual variation in the groundwater level of the proposed site is 1.0–2.0 m. The information interval of the site’s soil stratum is shown in Figure 2, Table 1 and Table 2 below. The physical and mechanical parameters presented in Table 1 and Table 2 were determined based on the detailed Geotechnical Engineering Investigation Report of the project. The values were derived from a combination of laboratory soil tests (including direct shear tests and consolidation tests) and in situ tests (such as the Standard Penetration Test) conducted at the site.

2.3. Monitoring Scheme

For the enclosure pile monitoring point, it is laid along the periphery of the foundation pit and close to the inner side of the enclosure structure of the soil body, and the horizontal spacing is taken as 30 m (while the vertical resolution of inclinometers within the pile is 0.5 m to capture detailed deformation profiles); respectively, monitoring points are arranged at the midpoint of each side, the convex corners, sections with depth variations, the part of the complex geological conditions, and other important parts [11].
For surface monitoring points, parallel to the edge of the pit, they are laid not less than two rows; the first row of measurement points is not more than 2 m away from the edge of the pit, and the spacing of each row of measurement points is 10 m~20 m. We set up transverse monitoring sections at representative parts of the pit edge line, and each monitoring section has no less than five measurement points; the starting monitoring section is close to the initial section for monitoring the top of the perimeter piles’ displacements, and a monitoring section is set up about every 30 m.
Due to the preliminary data comparison, the overall deformation of the pit was found to be a north–south symmetric trend, so only from the south side of the pit, select a number of representative monitoring points for data analysis. The following Figure 3 shows the station pit around the surface and enclosure structure monitoring bit measurement point schematic diagram.

3. Numerical Model and Parameters

3.1. Calculation Parameters

In this paper, the finite element program Midas/GTS 3D finite element simulation is used for numerical calculation [12,13]. In the model from the construction point of view, comprehensive consideration of the soil layering, soil nonlinearity, support application, and other factors, the station pit excavation process is numerically simulated, the concrete structure is selected elasticity of the principal model, and the calculation of the soil layer is selected to modify the Moore–Coulomb (MMC) principal model for the numerical simulation of the specific simulation parameters, which are shown in the above Table 1 and Table 2. The simulation of the station pit dimensions is shown in Figure 4, and the enclosure structure is shown in Figure 5. To eliminate the influence of boundary effects on the simulation results, the model dimensions were determined based on Saint-Venant’s principle. The distance from the excavation edge to the model boundary was set to approximately 3 to 4 times the excavation depth (H). The vertical depth of the model extended well below the base of the pile to ensure stability.
According to the theoretical calculation method of equivalent stiffness of the foundation in the engineering manual, the pile body is converted as shown in Figure 6. The bored pile is converted into a slab unit for calculation according to Equations (1) and (2).
1 12 D + t h 3 = 1 64 π D 4
h = 0.838 D · 1 / 1 + t D 3
  • where
  • D—isolation pile diameter, mm;
  • t—pile clear distance, mm;
  • h—equivalent plate thickness, mm.
Figure 6. Pile body stiffness conversion.
Figure 6. Pile body stiffness conversion.
Buildings 16 00317 g006
Step-by-step calculation using project parameters:
In this project, the enclosure piles are arranged in a single row with D = 800 mm and t = 300 mm (center-to-center spacing = D + t = 1100 mm).
Substitute into Equation (1) the following:
Left side (slab stiffness per unit width): 1 12 ( D + t ) h 3 = 1 12 × 1100 × h 3
Right side (single pile stiffness): π D 4 64 = π × 80 0 4 64
However, the simplified Equation (2) derived from Equation (1) is commonly used in engineering practice:
h = 0.838 × 800 × 1 / ( 1 + 300 800 ) 3 = 670.4 × 1 / ( 1.375 ) 3 603   m m

3.2. Calculation of Working Conditions

The simulation of pit excavation conditions is achieved by utilizing the functions of passivation and activation of units in the Midas/GTS construction simulation step [14]. After balancing the initial stress field, the construction envelope, columns, and internal supports were activated sequentially according to the sequence of pit construction; the passivated excavated soil simulated the step method of excavation, with every 2 m as a step until the excavation reached the footing, as shown in Figure 7 below.

4. Numerical Simulation Results

In the process of pit excavation, the deformation of the enclosure structure and the surrounding ground surface is important and has guiding significance for engineering construction. The station pit to be excavated is long and narrow, and the construction excavation steps are complex and the scale of the project is large, so representative working conditions such as working condition 1 (the early stage of pit excavation, excavation on both sides of the pit), working condition 2 (the middle stage of pit excavation, continuous excavation to the middle and a certain digging depth), and working condition 3 (the end of pit excavation, excavation is completed to the basement) are selected to be analyzed in detail.

4.1. Analysis of Horizontal Displacement Results of the Enclosure Structure

In order to effectively simulate the construction process of the shield structure passing through the high-speed railway, reasonable calculation assumptions are adopted:
Taking the envelope as a whole as the object of study, Figure 8 below shows the displacement cloud in the horizontal direction under working conditions 1 to 3.
As can be seen from Figure 8, with the continuous excavation of the soil body, the horizontal displacement of the enclosure structure gradually increased from the initial 1 mm to about 6 mm, and, affected by the excavation sequence, the deformation was big at both ends and small in the middle, and lasted until the end of the excavation; at the same time, the implementation of the internal support erection made the location of the maximum horizontal displacement of the enclosure structure with the working conditions 1~3, from the pile head to the body of the pile gradually moved. When excavating to the bottom of the foundation pit, the maximum horizontal displacement is stably located in the middle of the pile, about 0.5–0.75 H of the foundation pit (H is the depth of excavation), and the maximum horizontal displacement is 6.00 mm. The lateral displacement pattern of the enclosure structure changes continuously [15], and the overall deformation pattern evolves from a ‘bulging’ profile to a ‘step-like’ pattern. The deformation profile transitions continuously, shifting from a ‘bulging’ shape to a combined mode, and, finally, settling into a distinct ‘step-like’ configuration, and then to “stepped belly”, wherein the end side is subject to the local corner effect and the construction surface is long and the soil layer stress release is not synchronized, resulting in the enclosure structure lateral displacement in a certain depth range of the unsmooth decrease.

4.2. Surrounding Surface Settlement and Deformation Analysis

It is usually believed that the surface settlement around the foundation pit is influenced by a combination of factors such as lateral movement of the enclosing structure, consolidation of the soil outside the foundation pit, and soil uplift inside the foundation pit. Excessive surface settlement may cause uneven settlement of the surrounding building foundations or underground pipelines, leading to accidents such as cracking and pipeline breakage, which seriously affect their normal use and structural safety [16].
Figure 9 below shows the displacement cloud map carried out after excavation in the z-direction at the location of the model measurement point for working conditions 1 to 3.
It can be analyzed from Figure 9 that the vertical deformation of the surrounding ground surface manifests as both heave and settlement, and these two conditions often exist simultaneously, according to the working conditions of the pit construction. From working conditions 1 to 3, the magnitudes of both surface settlement and heave increase progressively, and, when excavating to the bottom, the maximum settlement reaches 1.2 mm, and the starting point of the settlement is gradually moving outward from the edge of the pit, and, finally, tends to be stabilized. The main influence range of the settlement is in an area of about 15 m from the pit. The influence range of the surface heave is mainly concentrated at the edge of the pit, with the maximum heave occurring directly adjacent to the edge, and the maximum basal heave is straight to the edge. About 15 m from the foundation pit, the influence range of surface bulging deformation is mainly at the edge of the foundation pit, the maximum bulging is 7.2 mm, and the enclosure structure is subjected to an upward deformation trend by the action of the soil at the bottom of the foundation. Further, there is a trend of deformation to the outside of the foundation pit by the action of the supporting axial force; under the action of the two kinds of force at the same time, the enclosure structure takes the bottom of the pile foundation in the ground as the rotating center, and there is a trend of counterclockwise rotation, which leads to the upper part of the soil body to appear bulging deformation. The soil on the upper part of the enclosure will be bulged and deformed.
According to the Code for Monitoring Measurement of Urban Rail Transit Engineering GB 50911-2013 [17], the widely accepted alert limit for surface settlement in this type of excavation is typically 0.2% to 0.3% of the excavation depth (approx. 30–40 mm for this project). The simulated maximum settlement (1.2 mm) and the field-measured maximum settlement (7.8 mm) are both well within the safety control standards, indicating that the overall stability of the foundation pit is effectively controlled.

5. Field Monitoring Results

According to the monitoring around the pit on site, the deformation of the enclosure structure and the deformation of the surface subsidence of the pit under different construction conditions were analyzed using the measured data. The monitoring data was obtained using manual measurements at set frequencies. The horizontal and vertical displacements of the pile tops were measured using a Leica high-precision Total Station (TS06) with prism targets. Surface settlement was monitored using a digital level (Leica DNA03) based on established control network points.
To ensure data integrity, a strict data quality control protocol was implemented. Singular outliers caused by non-structural factors (e.g., collision with construction machinery or optical obstruction) were identified and filtered using the 3σ criterion. No significant instrument failures occurred during the monitoring period; minor data gaps (less than 5% of the dataset) were filled using linear interpolation from adjacent temporal records.

5.1. Enclosure Deformation Analysis

As the main enclosing structure, the enclosing piles work together with the steel supports to provide structural support for the foundation pit and maintain the deformation of the surrounding soil. Data from four measurement points near a representative monitoring section are selected for analysis, as shown in Figure 3, and the monitoring points are ZQC/S-1, ZQC/S-2, ZQC/S-3, and ZQC/S-4, which are distributed on both sides of the foundation pit.
Figure 10 shows the changes in vertical displacement of the top of the pile with the excavation of the pit at each time point.
Figure 10 shows that the vertical displacement of pile tops is mainly bulging and wavy, and the bulging trends of the four measurement points are highly coincident. With the unloading of the excavation, the soil inside the pit releases its own gravity, the enclosure structure is deformed upward by the subsoil pressure, and deformed to the outside of the pit under the push of the multi-channel support axial force, and the two forces work together to make the enclosure structure bulge upward as a whole, and the maximum bulging occurs in the middle and late stages of the excavation, which is 6.2 mm. The maximum uplift occurs in the middle and late stages of excavation, which is 6.2 mm. Comparing the displacement changes in the pit edge of the model, it is found that both of them have a high degree of approximation and similar displacement values, which indicates that this numerical simulation analysis can simulate the construction situation better.
At the same time, the author analysis shows that the value of the bulge is reduced in the late stage of excavation, and the main reason is that after the soil excavation stress release stabilization, the station floor, side walls, and other construction processes are carried out to limit the change in the subsoil of the foundation pit and inhibit the upward soil pressure effect makes the bulge reduced, which shows that in the process of the station construction, it is necessary to follow up the construction progress in a timely manner, and through the process itself to complete the control of the displacement in order to achieve the purpose of safety. During the whole excavation process, the vertical displacement of the top of the enclosing piles is much smaller than the cumulative deformation control value of the vertical displacement of the top of the piles, and the settlement difference is normal, which meets the construction control requirements.
Horizontal deformation of the enclosing structure is one of the important indices for judging the stability of the foundation pit, and monitoring the deformation in the longitudinal direction of the support system can control the deformation status of the foundation pit in real time and take corresponding measures to prevent and control it. Figure 11 shows the horizontal displacement of the pile top in each time period. Figure 11 shows that the horizontal displacement measurement points ZQS1 and ZQS3/4 are on the east and west sides of the foundation pit, and the overall displacement of the pile is shifted to the east side of the foundation pit with the center axis of the foundation pit as the base, showing the rule of change in the “anti-bending type”. The overall displacement of the pile top is mostly shifted to the outside of the foundation pit, and the maximum deformation value is within 6–8 mm. There are two reasons: (1) the high compressibility of miscellaneous fill and loess soil, and the soil body behind the perimeter piles is very easy to be compressed after being pushed outward by the gantry crane erected on the crown beam; and (2) under the influence of the construction, the steel support started to be erected after the crown beam is applied, and in order to reach the preset axial force, the perimeter piles will produce a large horizontal outward pushing force and outward thrust [18].
According to the tracking analysis of the excavation process of the pit construction, comparing the measurement points ZQS4 and ZQS3, it is found that with the excavation of the pit, the horizontal displacement of the top of the enclosure pile becomes larger and larger, and the deformation value of the measurement point ZQS4 is larger than that of ZQS3 in the middle and late stages of the excavation, which is due to the fact that the measurement point ZQS4 is excavated to the bottom of the pit first and the subsequent stages of the construction will still have an impact. The decrease in pile top displacement in the later stage is mainly due to the horizontal force exerted at the bottom of the foundation pit by the construction of the station floor and other structures, which makes the displacement of the pile bottom increase to the outside, and the top of the pile shrinks and deforms horizontally to the inside.
The sudden decrease in displacement deformation values all occurred at the time nodes of the three steel support erections, indicating that the support erection is very important for displacement control in the process of foundation pit excavation construction, so it is important to support the erection in time to effectively control the deformation of the enclosure structure during the construction process [19].

5.2. Analysis of Surface Deformation

The two points in Figure 3 are distributed along the longitudinal direction of the foundation pit, in which multiple measurement points of each monitoring point are arranged with a spacing of about 2 m from the edge of the foundation pit to the outside. Further, it is known from Figure 12 and Figure 13 that the measurement points near the edge of the foundation pit in the early stage of the excavation are mainly bulging, with the deformation value ranging from 2 to 5 mm. The further out the deformation is mainly settlement, and the farther away from the foundation pit, the greater the settlement. The settlement value is increased from 0 to 8 mm, and the overall trend is almost the same as that in the numerical simulation; in the late stage of the excavation, there is obvious settlement and deformation of the surrounding surface. The overall trend of change is approximately the same as that of the numerical simulation; in the late excavation, the surrounding surface’s overall obvious settlement deformation, with a maximum settlement deformation value of 7.8 mm. The reason is that the greater the depth of excavation, the more the depth of pit precipitation increases, and, when the precipitation increases to the water-rich sand layer, the drop in water level has a greater effect on the soil consolidation settlement [20]. Further, in the open excavation of the enclosure structure to the outside of the side of the top of the big shift, enclosure structure rigidity, the bottom of the pit to the inside of the lateral shift occurs, making its pile back to the side, and the bottom of the pile back to the outside, and the bottom of the pit to the inside of the pit. Lateral shift occurs, so that its post-pile stratum stress release presents a trapezoidal distribution, and surface displacement is mostly manifested as settlement; at the same time, the construction of the station structure makes the soil stress redistributed, and the combination of multiple factors makes it appear the phenomenon of rapid growth of the settlement rate, and then the soil stress gradually reaches equilibrium, and the overall settlement tends to be stabilized [21].
Therefore, in the construction of similar strata, the precipitation factor has a greater influence, and more attention should be paid to the settlement deformation brought by the water-rich soil layer; each step of the construction process will have an influence on each other, and it is necessary to consider all the relevant factors in advance during the construction, so as to ensure the construction safety [22,23,24,25]. From the statistical analysis of the monitoring data, the cumulative surface settlement and deformation values of other measurement points in the vicinity are less than 10 mm, which meet the requirements of pit deformation control.
To further investigate the root cause of the observed “step-like” deformation and the discrepancy between simulation and measurement, it is essential to scrutinize the actual construction timing. The spatiotemporal evolution of the retaining structure in water-rich sand is highly sensitive to the duration of the unsupported state. Table 3 presents the reconstructed construction sequence and detailed time logs for the representative monitoring section. As indicated in the table, the unsupported exposure time during the critical sand layer excavation reached approximately 18–24 h. This significant time lag between excavation and support installation provides a quantitative basis for analyzing the stress relaxation mechanism discussed in the following section.

6. Discussion: Mechanism of Deformation Divergence

While the numerical simulation captures the general trend of the excavation behavior, a critical comparison with field monitoring data reveals significant divergences in deformation modes. As shown in Figure 14, the field data exhibits a distinct “step-like” horizontal displacement and larger surface settlement compared to the smooth “bulging” curves predicted by the simulation. This section analyzes the mechanical origins of these discrepancies, focusing on the rheological properties of the water-rich sand layer and fluid–solid coupling effects.

6.1. Mechanism of “Step-like” Deformation Evolution

The most notable discrepancy is the transition of the pile deformation mode from “bulging” (simulation) to “step-like” (monitoring). In the numerical model, the excavation and support installation are simulated as instantaneous steps within a continuous elastoplastic continuum. However, in the actual construction of water-rich sand strata, the soil exhibits distinct “time-dependent stress relaxation” characteristics.
Sand, being a cohesionless material, is highly sensitive to the stress release path. During the time interval between excavation and the pre-loading of the steel support (the “unsupported exposure time”), the retaining piles undergo rapid inward displacement driven by the active earth pressure. As noted by Ren et al. [7], the earth pressure in sandy layers adjusts dynamically with time. When the support is finally installed, the upper part of the pile is already displaced, while the lower part (embedded in the soil) remains relatively fixed, creating a “kick-out” or “step” point at the excavation interface. Notably, the vertical position of these steps correlates strongly with the excavation layer thickness (2 m), suggesting that the depth of each ‘kick-out’ is physically determined by the height of the unsupported excavation face. The standard Modified Mohr–Coulomb model used in the simulation simplifies this time-dependent plastic flow, thus producing a smoother, idealized curve. Furthermore, real-world geological discontinuities, such as localized uneven sand density or the presence of lenticular inclusions, can cause stress concentrations that differ from the homogeneous isotropic assumptions in the numerical model, contributing to the slight asymmetry and fluctuations observed in the field displacement distribution. This finding suggests that in high-permeability sand, shortening the exposure time is more critical for deformation control than merely increasing support stiffness.

6.2. Impact of Seepage and Dewatering on Settlement

Regarding ground settlement, the measured values (up to 7.8 mm) exceed the numerical predictions (approx. 3–4 mm). This underestimation is primarily attributed to the simplification of the fluid–solid coupling effect in the simulation. The simulation mainly considers the mechanical unloading of the soil mass. However, in this project, continuous dewatering was required to maintain a dry working face in the water-rich sand layer.
According to Terzaghi’s effective stress principle (σ’ = σ − u), the reduction in pore water pressure (u) due to dewatering leads to a corresponding increase in the effective stress (σ’) of the soil skeleton. This increase causes additional consolidation settlement of the soil outside the pit, which is superimposed onto the settlement caused by excavation unloading. Tian et al. [9] and Xu et al. [10] demonstrated that in permeable strata, seepage forces induced by hydraulic gradients can significantly amplify microscopic particle migration and macroscopic deformation. The “step-like” deformation of the retaining wall further exacerbates this by creating localized volume loss zones behind the piles, leading to the observed “trapezoidal” settlement profile (Figure 12) rather than the standard “peck-type” settlement.

6.3. Limitations and Future Work

While this study elucidates the mechanism of step-like deformation, several limitations should be acknowledged. First, the numerical simulation utilized the Modified Mohr–Coulomb (MMC) model. While effective for engineering design, the MMC model does not fully capture the intrinsic time-dependent creep behavior of sand, which could be better represented by rheological models (e.g., the Burger model) in future theoretical studies. Second, due to site constraints, pore water pressure and pile toe displacement were not directly monitored; their contributions were inferred from surface settlement and pile top displacement, respectively. Finally, the influence of alternative excavation sequences (e.g., center-to-sides) on suppressing step-like deformation warrants further investigation through comprehensive parametric simulations.

7. Conclusions

Based on the field monitoring data and 3D numerical simulation of a deep foundation pit in Xi’an, this study investigated the deformation characteristics and spatiotemporal evolution mechanism of excavations in water-rich sand strata. The main conclusions are as follows:
  • Deformation Mode Transition: Unlike the continuous “bulging” deformation predicted by ideal elastoplastic simulations, the actual retaining structure in water-rich sand exhibits a distinct “step-like” deformation mode. This mode is characterized by a “kick-out” displacement at the excavation interface, driven by the rapid stress relaxation of the cohesionless sand during the unsupported exposure time.
  • Mechanism of Divergence: The discrepancy between measurement and simulation reveals that standard models often underestimate the impact of spatiotemporal effects. The time lag between excavation and support installation allows for significant plastic flow in sandy strata, transforming the deformation profile from smooth to stepped.
  • Fluid–Solid Coupling Effect: Groundwater plays a critical role in deformation control. The measured surface settlement (up to 7.8 mm) exceeded numerical predictions, confirming that the increase in effective stress caused by continuous dewatering induces additional consolidation settlement, which is superimposed on the mechanical unloading settlement.
  • Engineering Implications: In deep excavations within high-permeability water-rich sand, managing the exposure duration of the excavation face is paramount, arguably outweighing the impact of support stiffness alone. To mitigate the risk of step-like deformation, the excavation sequence must be optimized to minimize the lag between soil removal and support installation. Empirical evidence from this study suggests that maintaining the unsupported exposure time within a critical 12 h window is essential for ensuring stability in similar hydrogeological conditions.

Author Contributions

Methodology, Y.S., K.Z., J.R., and T.Y.; Software, D.G. and T.Y.; Validation, Y.S., D.G., and T.Y.; Investigation, J.R.; Resources, Y.X.; Data Curation, K.Z. and J.R.; Writing—Original Draft, Y.S. and Y.X.; Writing—Review and Editing, Y.S.; Supervision, K.Z.; Project Administration, Y.X. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in the study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors Yongming Si, Ying Xiao, Kaiqiang Zhu, Jirong Ran, and Dengrui Gao were employed by the company China Communications Construction Second Engineering Bureau No. 3 Co., Ltd. The remaining author declares that the research was conducted in the absence of any commercial or financial relationships that could be construed as potential conflicts of interest.

References

  1. Meng, G.Z.; Nong, Z.J.; Wu, B. Deformation and numerical simulation analysis of deep foundation pit excavation in metro station. J. Saf. Sci. Technol. 2020, 16, 145–151. [Google Scholar]
  2. Peck, R.B. Earth pressure measurements in open cuts, Chicago Subway. Trans. ASCE 1943, 108, 34–48. [Google Scholar] [CrossRef]
  3. Sugimoto, T. Prediction for the maximum settlements of ground surface by open cut. Doboku Gakkai Ronbunshu 1986, 373, 113–120. [Google Scholar] [CrossRef] [PubMed]
  4. Li, L.; Duan, B.F. Monitoring and measurement and numerical simulation of deep foundation pit engineering in subway stations. Chin. J. Rock Mech. Eng. 2013, 32, 2684–2691. [Google Scholar]
  5. Wu, Y.Q.; Zhu, Y.P. Research on monitoring and numerical simulation of deformation pattern of deep foundation pit of subway station in wet subsided loess area of Lanzhou city. Chin. J. Geotech. Eng. 2014, 36, 404–411. [Google Scholar]
  6. Ye, S.H.; Ding, S.H.; Gong, X.N. Monitoring and numerical simulation analysis of deep foundation pit in a subway station in Lanzhou. Chin. J. Geotech. Eng. 2018, 40, 177–182. [Google Scholar]
  7. Ren, H.; Chen, J.; Wang, H.; He, Y.; Fang, X.; Wang, L. Analysis of the Temporal and Spatial Evolution Behavior of Earth Pressure in the Shield Chamber and the Ground Settlement Behavior During Shield Tunneling in Water-Rich Sand Layers. Buildings 2025, 15, 2935. [Google Scholar] [CrossRef]
  8. Feng, W.; Xu, J.; Zhang, R.; Yan, Z.; Fu, L.; Zhu, Y.; Zhang, G.; Chen, Z. Study on Excavation Response of Metro Station Foundation Pit in Water-Bearing Strata Adjacent to Tall Buildings. Buildings 2025, 15, 3982. [Google Scholar] [CrossRef]
  9. Tian, X.; Mei, Y.; Han, F.; Tang, J. Research on the Leakage Effect of Shield Tunnels in Water-Rich Silty Clay Strata Based on On-Site Investigation and Numerical Simulation. Buildings 2025, 15, 3867. [Google Scholar] [CrossRef]
  10. Xu, S.; Zhang, X.; Wang, L.; Yue, C.; Chen, X.; Luo, Z.; Zhang, J.; Fu, L. Study on the Mechanism of Water and Sand Leakage in a Foundation Pit Retaining Structure Based on the Computational Fluid Dynamics–Discrete Element Method. Buildings 2024, 14, 724. [Google Scholar] [CrossRef]
  11. Wang, W.D.; Xu, Z.H.; Zong, L.D.; Chen, Y.C. Measured analysis of deformation properties of ultra-deep large foundation pit project in Shanghai International Finance Center. Build. Struct. 2020, 50, 126–135. [Google Scholar]
  12. Li, C.; Li, S.Y.; Yuan, H. Numerical simulation and construction technology research on foundation pit excavation of Lingdingyang Bridge East Anchor of Shenzhen-China Corridor. Highway 2021, 66, 130–134. [Google Scholar]
  13. Zhou, Y.; Ye, W.N.; Gao, S. Analysis of deformation characteristics of deep foundation pit excavation in a station of Lanzhou subway. Chin. J. Geotech. Eng. 2018, 40, 141–146. [Google Scholar]
  14. Li, G.; Li, Q.; Wang, J. The deformation characteristics of a 40-m-deep excavation supported by a suspended diaphragm wall in rock and soil composite ground. KSCE J. Civ. Eng. 2022, 26, 1040–1050. [Google Scholar] [CrossRef]
  15. Wu, C.Z.; Zhou, L.; Yi, L.; Chen, M.; Yu, J.; Liu, Z.Q. Analysis of deformation properties of anode corner region of deep foundation pit and influence of excavation on pile foundation outside the pit. Build. Struct. 2021, 51, 138–143. [Google Scholar]
  16. Liu, H.; Li, K.; Wang, J. Numerical simulation of deep foundation pit construction under complex site conditions. Adv. Civ. Eng. 2021, 2021, 6669466. [Google Scholar] [CrossRef]
  17. GB 50911-2013; Code for Monitoring Measurement of Urban Rail Transit Engineering. China Architecture & Building Press: Beijing, China, 2013.
  18. Ding, Z.; Jin, J.; Han, T.C. Analysis of the zoning excavation monitoring data of a narrow and deep foundation pit in a soft soil area. J. Geophys. Eng. 2018, 15, 1231–1241. [Google Scholar] [CrossRef]
  19. Ren, X.M.; Liu, J.J.; Liu, J.W.; Wang, C. Deformation of deep foundation pit excavation for subway station in coastal swamp area. J. Lanzhou Univ. Technol. 2023, 49, 138–143. [Google Scholar]
  20. Liu, J.C.; Tan, Y.; Song, X.H.; Fan, D.D.; Liu, T.R. Influence of seepage from water-rich sandy soil foundation pit on sidewall deformation and surrounding environment. J. Zhejiang Univ. (Eng. Sci.) 2023, 57, 530–541. [Google Scholar] [CrossRef]
  21. Ng, S.M. Analysis and reinforcement of deep foundation pit deformation in the north sales section of Zhongshui Plaza. Geotech. Investig. Surv. 2022, 50, 13–18. [Google Scholar]
  22. Wang, R.S.; Guo, C.C.; Lin, P.Y.; Wang, F.M. Analysis of excavation response of assembled retrievable support for water-rich chalk pit. Rock Soil Mech. 2023, 44, 843–853. [Google Scholar]
  23. Zhu, S.; Yao, H.; Cheng, Y.C.; He, Z.J. Innovative design and practice of complex deep large soft soil deep foundation pit. Geotech. Investig. Surv. 2022, 50, 43–50. [Google Scholar]
  24. Li, Z.Y.; Zhang, J.; Chu, F.P. Measured analysis of shield spanning over tunnel pit and research on protection scheme. Chin. J. Undergr. Space Eng. 2022, 18, 1979–1988. [Google Scholar]
  25. Li, L.; Li, B.; Liu, D.; Han, X. Impact of deep and large shaped pit excavation on adjacent structures in deep and thick soft soil area. J. Changjiang River Sci. Res. 2023, 40, 140–145. [Google Scholar]
Figure 1. Map of the station’s geographical location.
Figure 1. Map of the station’s geographical location.
Buildings 16 00317 g001
Figure 2. Schematic diagram of foundation soil and enclosure structure.
Figure 2. Schematic diagram of foundation soil and enclosure structure.
Buildings 16 00317 g002
Figure 3. Schematic diagram of some monitoring points.
Figure 3. Schematic diagram of some monitoring points.
Buildings 16 00317 g003
Figure 4. Numerical calculation model.
Figure 4. Numerical calculation model.
Buildings 16 00317 g004
Figure 5. Enclosing structure.
Figure 5. Enclosing structure.
Buildings 16 00317 g005
Figure 7. Schematic diagram of simulated excavation of foundation pit.
Figure 7. Schematic diagram of simulated excavation of foundation pit.
Buildings 16 00317 g007
Figure 8. (a) Case 1 horizontal displacement cloud diagram; (b) Case 2 horizontal displacement cloud diagram; (c) Case 3 horizontal displacement cloud diagram.
Figure 8. (a) Case 1 horizontal displacement cloud diagram; (b) Case 2 horizontal displacement cloud diagram; (c) Case 3 horizontal displacement cloud diagram.
Buildings 16 00317 g008
Figure 9. (a) Case 1 cloud map of ground surface displacement; (b) Case 2 cloud map of ground surface displacement; (c) Case 3 cloud map of ground surface displacement.
Figure 9. (a) Case 1 cloud map of ground surface displacement; (b) Case 2 cloud map of ground surface displacement; (c) Case 3 cloud map of ground surface displacement.
Buildings 16 00317 g009
Figure 10. Vertical displacement diagram of the pile top.
Figure 10. Vertical displacement diagram of the pile top.
Buildings 16 00317 g010
Figure 11. Diagram of horizontal displacement of pile top.
Figure 11. Diagram of horizontal displacement of pile top.
Buildings 16 00317 g011
Figure 12. Displacement diagram of ground deformation monitoring point DBC1.
Figure 12. Displacement diagram of ground deformation monitoring point DBC1.
Buildings 16 00317 g012
Figure 13. Displacement diagram of ground deformation monitoring point DBC2.
Figure 13. Displacement diagram of ground deformation monitoring point DBC2.
Buildings 16 00317 g013
Figure 14. Comparison of ground deformation.
Figure 14. Comparison of ground deformation.
Buildings 16 00317 g014
Table 1. Site soil 1.
Table 1. Site soil 1.
Stratigraphic InformationPhysical and Mechanical Parameters of the Soil Layer
Moisture Content
W/%
Proportion
Gs
Cohesive Forces
c/kPa
The Angle of Internal Friction
φ / ( ° )
Compression Modulus
Es/MPa
Permeability
k (m/d)
1-1 Miscellaneous fill (Q4ml)14.6-1317.83.651.20
2-1 Loess-like soil (Q4al)15.62.702520.07.30.25
2-4-1 Silty clay (Q4al)15.42.642.328.09.00.45
2-4-2 Fine sand (Q4al)15.92.642.230.010.04.50
2-5 Medium sand (Q4al)15.82.634.233.214.818.00
Table 2. Site soil 2.
Table 2. Site soil 2.
Calculated Parameters for Soil Simulation
stratigraphic informationPoisson’s ratioγ/kN/m3K0Cohesion, angle of internal friction, and compression modulus are the same as the physical and mechanical parameters of the soil layer in the computational simulation.
1-1 Miscellaneous fill (Q4ml)0.3817.50.75
2-1 Loess-like soil (Q4al)0.3017.30.42
2-4-1 Silty clay (Q4al)0.3018.00.41
2-4-2 Fine sand (Q4al)0.3117.70.39
2-5 Medium sand (Q4al)0.3119.40.37
Table 3. Construction sequence and time log of the typical monitoring section.
Table 3. Construction sequence and time log of the typical monitoring section.
Construction StageDate (Reconstructed)Activity DescriptionUnsupported Exposure Time (Hours)Remarks
Stage 126 October–2 NovemberExcavation of the 1st layer (0–2 m) and Crown Beam construction.Surface clearance and prep.
Stage 23 NovemberInstallation of 1st Steel Support (at ~2 m depth).18 hCorresponds to the first drop in Figure 11.
Stage 34 November–18 NovemberExcavation of the 2nd and 3rd layers (2–8 m).20 h (Avg.)Rapid stress release in sand layer.
Stage 419 NovemberInstallation of 2nd Steel Support (at ~8 m depth).24 hDelayed support led to distinct deformation step.
Stage 520 November–12 DecemberExcavation of the 4th and 5th layers (8–14 m).16 h (Avg.)Dewatering continued; “step-like” pattern formed.
Stage 613 December Installation of 3rd Steel Support (at ~14 m depth).12 hTimely support reduced further deformation.
Stage 714 December–6 JanuaryExcavation to pit bottom (~17 m) and Base Slab construction.Final excavation stage.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Si, Y.; Xiao, Y.; Zhu, K.; Ran, J.; Gao, D.; Yang, T. Spatiotemporal Evolution and Deformation Mechanism of Deep Foundation Excavation in Water-Rich Sand Strata: A Comparative Study of Monitoring and Simulation. Buildings 2026, 16, 317. https://doi.org/10.3390/buildings16020317

AMA Style

Si Y, Xiao Y, Zhu K, Ran J, Gao D, Yang T. Spatiotemporal Evolution and Deformation Mechanism of Deep Foundation Excavation in Water-Rich Sand Strata: A Comparative Study of Monitoring and Simulation. Buildings. 2026; 16(2):317. https://doi.org/10.3390/buildings16020317

Chicago/Turabian Style

Si, Yongming, Ying Xiao, Kaiqiang Zhu, Jirong Ran, Dengrui Gao, and Tao Yang. 2026. "Spatiotemporal Evolution and Deformation Mechanism of Deep Foundation Excavation in Water-Rich Sand Strata: A Comparative Study of Monitoring and Simulation" Buildings 16, no. 2: 317. https://doi.org/10.3390/buildings16020317

APA Style

Si, Y., Xiao, Y., Zhu, K., Ran, J., Gao, D., & Yang, T. (2026). Spatiotemporal Evolution and Deformation Mechanism of Deep Foundation Excavation in Water-Rich Sand Strata: A Comparative Study of Monitoring and Simulation. Buildings, 16(2), 317. https://doi.org/10.3390/buildings16020317

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop