Next Article in Journal
Experiences and Future Challenges of Bioleaching Research in South Korea
Previous Article in Journal
Fibrous Platinum-Group Minerals in “Floating Chromitites” from the Loma Larga Ni-Laterite Deposit, Dominican Republic
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimizing Performance of SABC Comminution Circuit of the Wushan Porphyry Copper Mine—A Practical Approach

1
Mine Management Division, Department of Mining & Mineral Resources, Chinalco China Copper Corporation Limited, Beijing 100082, China
2
Department of Mining and Materials Engineering, McGill University, Montreal, QC H3A 0C5, Canada
Minerals 2016, 6(4), 127; https://doi.org/10.3390/min6040127
Submission received: 31 May 2016 / Revised: 1 November 2016 / Accepted: 24 November 2016 / Published: 2 December 2016

Abstract

:
This research is focused on the Phase I SABC milling circuit of the Wushan porphyry copper mine. Improvements to the existing circuit were targeted without any significant alterations to existing equipment or the SABC circuit. JKSimMet simulations were used to test various operating and design conditions to improve the comminution process. Modifications to the SABC comminution circuit included an increase in the SAG mill ball charge from 8% to 10% v/v; an increase in the mill ball charge from 23% v/v to 27% v/v; an increase in the maximum operating power draw in the ball mill to 5800 kW; the replacement of the HP Series pebble crusher with a TC84 crusher; and the addition of a pebble bin. Following these improvements, an increase in circuit throughput, a reduction in energy consumption, and an increase in profitability were obtained.

1. Introduction

In mineral processing, all ores will have an optimum particle size which maximizes the economic benefits from the net smelter return while minimizing the cost of crushing and grinding. If the particle size is too coarse there will be inadequate liberation, limiting recovery (and thus revenue) in the separation stage. If the grind is too fine, the grinding costs will exceed any increment in recovery (and may even reduce recovery depending on the separation process). A standard crushing and grinding circuit is shown in Figure 1. It is commonly referred to as a SABC circuit, for Semi-Autogenous Ball mill Crusher (SABC). This circuit shows a semi-autogenous grinding (SAG)/ball mill circuit where both grinding mills are in closed circuit, with the SAG mill closed with a crusher to control the amount of ‘critical size’ material in the circuit. ‘Critical size’ material, also referred to as pebbles, represents material that does not self-break as readily as other sizes of fractions and therefore would build up in the SAG mill circuit if no crusher was present. The ball mill, the final grind stage, is closed with a hydrocyclone classifier that removes undersized material and sends it to the separation stage.
At the beginning of 1980s, the De Xing copper mine was the first to employ a SABC circuit in China. However, equipment failure during operation was frequent due to the lack of technical specialists in China to assist in circuit design and performance. This led to the shutdown of the SABC circuit in 1987, and subsequently, the application and study of SABC circuits in China was ignored for the following 20 years [1].
In 2009, a pilot-scale test of a SABC circuit was successfully carried out at the Wushan porphyry copper mine. This meant Wushan was the first large-scale non-ferrous mine that successfully made use of a SABC circuit in China. The SABC circuit has been shown to have many advantages including: having a simpler flow sheet; requiring a smaller footprint; allowing easier expansion; and being more environmental friendly and energy efficient. Numerous Chinese mining companies have since followed this trend and installed a SABC circuit [2].
In 1990s, during the design of the Wushan SABC circuit comminution stage, the only information available was the Bond work index, which was calculated with insufficient ore comminution characteristics testing and semi-industrial testing [3,4,5]. This was due to the lack of research in this field in China and the lack of knowledge in SABC circuit design. The sizing of the processing equipment inside of the SABC circuit is typically based on calculations from similar circuits in both domestic and overseas plants. This can lead to problems in equipment selection and operation, which, if left unoptimized, leaves significant space for improvement in both energy consumption and production capacity. Hence, optimization of the energy consumption in the Wushan SABC milling circuit should improve its energy efficiency and production capacity.

1.1. The Wushan Mine’s SABC Circuit Flowsheet and Operating Problems

The mineral processing plant of the Wushan copper mine has a production capacity of 30,000 t/d, which is divided into two parallel streams that each treat 15,000 t/d. The plant has the largest grinding capacity in China and has been in production for the last three years. The processing plant operates with a standard SABC comminution circuit (Figure 1), and was the first to use the largest domestic Φ8.8 × 4.8 m SAG mill (‘diameter’ represents nominal diameter, and ‘length’ of the mill represents the effective grinding length inside the end liners and discharge grates), Φ6.2 × 9.5 m overflow ball mill and closed stockpile (maximum storage capacity at 120,000 t, effective storage capacity at 39,000 t).
After three years of operation, continued analysis of the circuit products showed there were considerable performance issues present. Firstly, there was a serious flaw in the power configuration of the SAG mill and ball mill (both rated at 6000 kW with a single pinion drive). The capacity of the SAG mill was not fully utilized, as the actual operating power draw was only 3358 kW. This meant it was only operating at 56% of its maximum power, providing large room for improvement. The load on the ball mill was on the high side, with an actual operating power draw of 5300 kW, meaning it was operating at 90% of its maximum power. The combined power draw of the SAG mill and ball mill was 8658 kW, which caused partial over-grinding. From experience in processing plants outside of China, the power rating of the ball mill should be higher than that of the SAG mill [5].
The pebble crusher had an over-powered configuration. The installed power draw of 630 kW (actual power draw of 213.5 kW) is over-sized and therefore had a low operation efficiency. The crusher remains operational intermittently, which means it is not possible to continuously re-circulate pebbles back to the SAG mill. This causes a higher variation in the feed rate and particle size distribution in the feed to the SAG mill, which results in a greater variation in the SAG mill power draw in the transition period when the pebble crusher is in operation or not.
Overall, the major flaws are caused by the lack of power in the circuit design and this is therefore the main issue to be solved. Improvement to the efficiency of the SABC circuit can be achieved by adjusting and optimizing equipment and process parameters related to the SABC comminution circuit to maintain a more even distribution of equipment capacity.

1.2. Requirement for Circuit Simulation

Over the past decade, methodologies for optimizing grinding and flotation plants using plant data together with semi-empirical sub-process models have been developed by research groups at the Julius Krutschnitt Minerals Research Centre (JKMRC) (Brisbane, Australia), University of Cape Town (Cape Town, South Africa), and McGill University (Montreal, QC, Canada) [6,7,8,9,10,11,12,13]. The culmination of the work done by JKMRC was the JKSimMet simulation model developed by JKTech (the technology transfer company of JKMRC). This program, based upon data collected from numerous mills operating at a range of conditions, contains sub-models for a range of processing equipment including grinding mills, crushers, screens and hydrocyclones. It allows for the user to fully simulate the behavior of a particular comminution circuit, to find improvements in circuit design and operating conditions. This process has been carried out at a number of industrial sites that utilize a SABC circuit [1,14,15].

1.3. Paper Objectives

The primary aim of this work was to perform a diagnostic evaluation of the SABC comminution circuit performance using the JKSimMet simulation model. This included the bench-marking and optimization of the SABC comminution circuit, focusing on the primary (SAG mill) and secondary (ball mill) grinding mills, and estimating the outcomes of changes to circuit operating parameters (e.g., feed rate, mill load, ball charge, etc.).

2. Problem Validation and Analysis

To fully understand the extent of the flaws within the Wushan Phase I SABC comminution circuit design, the process must be assessed by developing a representative computational model of the SAG mill and ball mill in the SABC circuit. After validating the model with circuit survey data and measured parameters of the ore, the model will allow for optimization of the comminution process. The surveys were mass balanced and resultant values formed the basis of the JKSimMet model development. The ore characterization data (for instance, A and b from Table 1 are the ore impact breakage parameters determined by the drop weight test) and the measured equipment data were also used in the model-fitting process (Table 1). The fitted parameters included grinding rates in the SAG and ball mills and operating parameters from the cyclones, screens and pebble crusher. The model fit parameters were determined using the non-linear fitting module in JKSimMet. The calibrated JKSimMet model was then used as the base for the simulations. An example of the simulation results is shown in Figure 2. Table 2 displays a comparison between the existing SABC comminution equipment size and the optimal sizes determined by the model.
According to Table 2, differences between the actual equipment specifications of the comminution process and equipment specification from the JKSimMet simulation were aligned with previous thinking. The installed power draw in the SAG mill is higher than the model suggests is required, and for the ball mill the installed power is slightly lower. Taking into account the combined installed power draw of the SAG mill and ball mill, the difference in installed power draw between the two circuits was 1000 kW with the existing circuit of Wushan having a slightly higher power (by approximately 9%).
This suggests that the SAG mill is oversized for the original circuit design, and therefore is overgrinding. This means it does not produce enough pebble flow to ensure that the pebble crusher is consistently loaded. Under these circumstances, the feed ore is essentially fully ground within the SAG mill. This causes a lower production rate of pebbles (pebble production is 66 t/h), which in turn means the pebble crusher is oversized. This means that in operation, the pebble crusher remains in an intermittent operating state. The size of the ball mill is slightly undersized, which could explain why the circuit is unable to reach the designed product size (115 µm). Furthermore, the operating capacity of the ball mill has reached 90% capacity, running at near full load.
The model produced a coarser P80 (170 µm) with a smaller SAG mill, less power draw (compared to that of the actual circuit) and a coarser transfer size to the ball mill. These results demonstrate that the Wushan comminution circuit has unreasonable design specifications and operating conditions.

3. The Energy Distribution of the SABC Comminution Process

To determine the energy distribution of the SABC comminution circuit, operational data from January 2011 to August 2011 was used. This time period was chosen because the pebble crusher was operating intermittently and therefore the comminution circuit could be analyzed with and without pebble crushing. A statistical analysis was performed on each piece of equipment in the circuit to determine the ratio of energy distribution for each case. The energy distribution for each component of the comminution circuit with and without pebble crushing is shown in Figure 3.
Table 3 shows a comparison of the actual operating power consumption of the SAG and ball mill to the reworked and originally designed SABC circuit model, with the pebble crusher in operation. From Table 3, it can be seen that the reworked model, obtained from the JKSimMet simulation, and the actual operating circuit have a similar SAG-to-ball mill power draw ratio; however, significant discrepancies were observed with the original circuit design. This suggests that the design of the SABC circuit is not appropriate as the SAG mill appears to be oversized.

4. Simulation of Comminution Circuit Based on the Maximum Capacity

The maximum theoretical processing capacity is shown in Figure 4. To simulate the maximum capacity of each grinding mill, the ball charge volume in both the SAG and ball mill were optimized and the actual product size and operating conditions were used. Although the final designed product size of the SABC circuit was 115 µm (P80), a product size of 170 µm (P80) was used for the simulation as this was the actual product size in operation. From Figure 4 it can be seen that the maximum theoretical processing capacity is 20,400 t/d (850 t/h), a 36% increase from the current processing tonnage of 15,000 t/d (625 t/h).
The operating conditions of the SAG and ball mill are shown in Table 4. The power draw of the SAG mill has room for significant improvement. As ball filling in the SAG mill is quite low, additional grinding media would likely increase the processing capacity of the SAG mill; however, the capacity of the ball mill, with installed power for the required product size of 170 µm, has reached its limit. The power draw for the simulated ball mill (5700 kW) is close to its rated motor power (6000 kW), however, greater than the power draw for the actual mill (5268 kW). The increase in power draw is due to an increase in ball volume from 24% v/v (actual) to 27% v/v (simulated). This increase in ball volume results in an increase in productivity, although this occurs at a product size (170 µm) coarser then originally designed (115 µm).

5. Circuit Modification and Performance

To improve the energy efficiency of the circuit, various operating conditions were modified, with the goal of increasing the processing capacity from 15,000 to 20,000 t/d, in weekly increments of 1000 t/d. The ball filling rate of the SAG mill was increased from 8% to 10% v/v and monitoring settings in the central control room were temporally set to have no upper limit. The pebble crusher was reduced in size and the pebble bin capacity was increased to allow for a more consistent flow into the pebble crusher. Uncrushed pebbles were returned directly to the SAG mill, bypassing the pebble crusher, to further improve circuit efficiency. The ball filling rate of the ball mill was set at 27% v/v and the mill’s efficiency was set to automatic monitoring, with the upper limit set to 5800 kW (the maximum efficiency (obtained from consultation with the manufacturer)).
If the SABC circuit could operate normally and the capacity of each piece of equipment in the circuit could exceed its design requirements, the 20,000 t/d target could have been reached without any impediment arising from major issues. However, a number of different problems emerged during production which required attention.
One major issue was the operation of the SAG mill caused vibration at an amplitude of up to 11 mm (on the mill foundation) and therefore it could not be operated at a production rate above 15,000 t/d. To eliminate this issue the mill foundation base was reinforced, effectively eliminating the vibrations and allowing for stable production at about 18,000 t/d (a 20% increase in processing capacity) to 19,000 t/d (a 27% increase in processing capacity).
A second issue was that domestic-made grinding media and wear-resistant materials are of much lower quality compared to foreign-made products. The ideal ball charge volume for a SAG mill is 12% v/v [16], according to the design objective, and the maximum ball size has a diameter of 150 mm. During operation, however, breakage rates of the shell liners and lifters become extremely high, with a lifespan of only one month when a ball charge volume of 12% v/v was used. Increasing the ball charge volume or ball size caused more damage to the shell liners and lifters. After further test work, it was determined that a ball diameter of 120 mm could be used, but the ball charge volume could not exceed 10% v/v. Following these adjustments, the lifespan of the liners and lifters could be expected to increase to three months.
The initial problem with pebble crushing was the over-sized HP800 crusher which resulted in the intermittent recirculation of pebbles on a frequency of 2 h of operation per shift, or 4.5 h per shift with a replacement HP400 crusher. Both crushers operated with their load controller activated to maintain a constant feed rate at maximum current, which becomes intermittent in the absence of sufficient pebble flow and a feed bin. To solve this issue, the HP Series crusher was replaced with a smaller TRIO TC84 crusher (450 kW, without a load controller, Shanghai TRIO Engineered Products Inc., Shanghai, China), and a reduced feed rate and a 100 m3 capacity feed bin were used to ensured continuous operation on a 24 h basis. In addition, some plant test work was performed without the pebble crusher in the circuit. While stable operation was achieved initially, after one month, the load of uncrushed pebbles inside the SAG mill accumulated to an extent which caused over-loading of the mill power draw. Accordingly, it was decided that elimination of the pebble crusher in the circuit was not viable.
The discharge grates of the SAG mill were identified as a key component in the SABC circuit, and their design is a crucial factor in the mill’s performance [17,18,19,20,21]. The initial design of the grate section caused a serious accumulation of pebbles within the SAG mill which contributed to a decreased grinding efficiency. The grates were designed with 18 inner sections, with a 25 mm grate slot width, and 18 outer sections, with only four sections having pebble ports (slot width of 60 mm). The rate of pebble production was 5% of the mill’s feed rate, compared to the design objective of 17%. This resulted in operational variability in the entire SABC process (i.e., cyclic variability of mill load with peaks and frequent grind-outs). Based on plant test work, the open area of the 36 grate sections was increased by changing all 18 outer sections to have pebble ports (60 mm), while retaining a 25 mm slot width in the 18 inner sections. These changes contributed to an increase in the discharge rate of pebbles, the efficiency of the SAG mill, and the processing capacity of fresh ore.

6. Plant Performance after Improvements

The final plan was to increase the ball charge in the SAG and ball mill to 10% v/v and 27% v/v, respectively; set the upper limit of the operating power in the ball mill to 5800 kW; use a TRIO TC Series crusher (without a power-/feed rate–controlling device, but with a feed bin) to crush pebbles for recirculation back to the SAG mill feed; and change the number of pebble ports in the SAG mill grate sections. As a result of these changes, a 20% improvement (an increase from 15,000 to 19,000 t/d) in the productivity of the Wushan comminution circuit was achieved. The potential for achieving a processing capacity of 20,000 t/d was also demonstrated, but was only obtainable after optimization of the SAG mill grate sections, ball size, and volumetric loading of balls. In addition, the benefits of this study have given strategic directions for the construction of Phase II, which is likely to decrease the amount of capital investment required.

7. Conclusions

The simulated results produced in this work, using the JKSimMet program, allowed for the investigation into the performance of the Wushan Phase I SABC comminution circuit. The main conclusions are as follows:
(1)
SABC circuits are well suited to Chinese nonferrous mines, especially large-scale deposits. Their implementation will be important for the development of China’s large-scale deposits in the future.
(2)
At the Wushan mine, increased productivity was achieved at a decreased specific power consumption, without any significant changes to the existing SABC circuit.
(3)
The production experience gained from this work indicates that the successful design and operation of grinding circuits can be accomplished by coupling scientific theories with known ore characteristics.
(4)
China still lacks experience in the research and operation of SABC circuit technology and requires continued research in this field.

Acknowledgments

The author would acknowledge Frank Cappuccitti, Joshua Sovechles and Chris Marion for their thought-provoking comments, and the assistance with the English text editing and modification.

Conflicts of Interest

The author declares no conflict of interest.

References

  1. Napier-Munn, T.J.; Morrell, S.; Morrison, R.; Kojovic, T. Mineral Comminution Circuits: Their Operation and Optimisation; Julius Kruttschnitt Mineral Research Centre, University of Queensland: Brisbane, Australia, 1996. [Google Scholar]
  2. Siddall, G.B. Analysing power efficiency for crushing and grinding. In Proceedings of the IIR SAG Mill Conferences, Perth, Australia, 29–31 March 1997.
  3. Liu, H.J.; Sun, C.B.; Zhao, L.C.; Wang, B.; Luo, S.K.; Lu, Z.F. The design and application of SABC crushing & grinding process for treatment of Copper-Molybdenum ore of Wushan Mine. Nonferr. Met. Miner. Process. Sect. 2013, 3, 66–68. [Google Scholar]
  4. Austin, L.G.; Klimpel, R.R.; Luckie, P.T. Process Engineering of Size Reduction: Ball Milling; SME/AIME: New York, NY, USA, 1984. [Google Scholar]
  5. Barratt, D.J.; Allan, M.J. Testing for autogenous and semi-autogenous grinding: A designer’s point of view. Miner. Metall. Process. 2012, 3, 65–74. [Google Scholar]
  6. Stark, S.; Perkins, T.; Napier-Munn, T.J. JK drop weight parameters—A statistical analysis of their accuracy and precision and the effect on SAG mill comminution circuit design. In Proceedings Metallurgical Plant Design and Operating Strategies; The Australasian Institute of Mining and Metallurgy: Melbourne, Australia, 2008. [Google Scholar]
  7. Coleman, R.G.; Urtubia, H.E.; Alexander, D.J. A comparison of BHP-Billiton’s minera escondida flotation concentrators. In Proceedings of the 38th Annual Canadian Mill Operators Conference, Ottawa, ON, Canada, 17–19 January 2006; Canadian Institute Mining, Metallurgy and Petroleum: Ottawa, ON, Canada, 2006. [Google Scholar]
  8. Schwarz, S.; Alexander, D.; Coleman, R. Characteristics of modern copper flotation circuits. In Proceedings of the 6th International Copper-Cobre Conference, Toronto, ON, Canada, 25–30 August 2007.
  9. Bailey, C.; Lane, G.; Morrell, S.; Staples, P. What can go wrong in comminution circuit design? In Proceedings of the 10th Mill Operators’ Conference, Adelaide, Australia, 12–14 October 2009; The Australasian Institute of Mining and Metallurgy: Melbourne, Australia, 2009. [Google Scholar]
  10. Zhang, W.; Kolahdoozan, M.; Nesset, J.E.; Finch, J.A. Use of frother with sampling-for-imaging bubble Sizing Technique. Miner. Eng. 2009, 22, 513–515. [Google Scholar] [CrossRef]
  11. Zhang, W.; Nesset, J.E.; Finch, J.A. Water recovery and bubble surface area flux in flotation. Can. Metall. Q. 2010, 49, 353–362. [Google Scholar] [CrossRef]
  12. Zhang, W.; Nesset, J.E.; Rao, S.R.; Finch, J.A. Characterizing frothers through critical coalescence concentration (CCC)95-hydrophile-lipophile balance (HLB) relationship. Minerals 2012, 2, 208–227. [Google Scholar] [CrossRef]
  13. Zhang, W. The Effects of frothers and particles on the characteristics of pulp and froth properties in flotation—A critical review. J. Miner. Mater. Charact. Eng. 2016, 4, 251–269. [Google Scholar] [CrossRef]
  14. Strohmayr, S.; Valery, J.W. SAG mill circuit optimisation at Ernest Henry Mining. In Proceedings of the SAG 2001 Conference, Vancouver, BC, Canada, 30 September–3 October 2001.
  15. Atasoy, Y.; Price, J. Commissioning and optimisation of a single stage SAG mill grinding circuit at Lefroy gold plant—St. Ives gold mine—Kambalda/Australia. In Proceedings of the SAG 2006 Conference, Vancouver, BC, Canada, 23–27 September 2006.
  16. Cole, J.; Seidel, J.; Orlich, J. The design, start-up and operation of the Phoenix project SAG mill. In Proceedings of the SAG 2006 Conference, Vancouver, BC, Canada, 23–27 September 2006.
  17. Powell, M.; Smit, I. Startling effect of Ball scat removal on SAG mill performance. In Proceedings of the International Conference on Autogenous and Semiautogenous Grinding Technology, Vancouver, BC, Canada, 24–27 September 1996.
  18. Rantanen, S.; Lahtinen, M.; Schumacher, W. Operation of “outogenius” type grinding at Forrestania Nickel Mines. In Proceedings of the International Conference on Autogenous and Semiautogenous Grinding Technology, Vancouver, BC, Canada, 24–27 September 1996.
  19. Stieger, D.; Plummer, R.; Latchireddi, S. SAG mill liner design improvements at Cortez Gold Mines. In Proceedings of the 2005 Annual SME Conference, Salt Lake City, UT, USA, 17–22 February 2005.
  20. Hart, S.; Valery, W.; Clements, B.; Reed, M.; Song, M.; Dunne, R. Optimisation of the Cadia Hill SAG mill circuit. In Proceedings of the SAG 2001 Conference, Vancouver, BC, Canada, 30 September–3 October 2001.
  21. Nicoli, D.; Morrell, S.; Chapman, B.; Latchireddi, S. The development and installation of the twin chamber pulp lifters at Alcoa. In Proceedings of the SAG 2001 Conference, Vancouver, BC, Canada, 30 September–3 October 2001.
Figure 1. Wushan Phase I SABC circuit layout and equipment specifications.
Figure 1. Wushan Phase I SABC circuit layout and equipment specifications.
Minerals 06 00127 g001
Figure 2. JKSimMet screen snapshot of the Wushan Phase I SABC circuit simulation (key is provided at the top middle section of diagram).
Figure 2. JKSimMet screen snapshot of the Wushan Phase I SABC circuit simulation (key is provided at the top middle section of diagram).
Minerals 06 00127 g002
Figure 3. Energy distribution in the SABC comminution circuit.
Figure 3. Energy distribution in the SABC comminution circuit.
Minerals 06 00127 g003
Figure 4. Configuration and performance of the SABC circuit if maximum theoretical processing capacity is reached (key is provided at the top middle section of diagram).
Figure 4. Configuration and performance of the SABC circuit if maximum theoretical processing capacity is reached (key is provided at the top middle section of diagram).
Minerals 06 00127 g004
Table 1. Model parameters.
Table 1. Model parameters.
ItemUnitOptimized DataOriginal Data
Grinding systemProjected daily operation capacityt/d15,000-
Projected hourly operation capacityt/h625-
Designed margin factor-1.10-
Designed hourly operation capacityt/h688-
SAG millOperation capacityt/h688-
Feed sizemm110118
Number of unit-1-
Ball millOperation capacityt/h688-
Feed sizeµm~15002250
Product sizeµm~114170
Number of unit-1-
Ore characteristicsSAGt/m32.62-
A-63.08-
b-1.08-
A × b-68.13-
Drop Weight Index (DWi)kWh/m33.72-
Fineness Index (ta)-0.61-
Bond Work Index (BWi)kWh/t14.32-
Table 2. Actual equipment specification of Wushan Phase I comminution process and proposed equipment specification from the JKSimMet simulation.
Table 2. Actual equipment specification of Wushan Phase I comminution process and proposed equipment specification from the JKSimMet simulation.
ItemUnitActual UnitRemodeled Unit
SAG millSpecification (F/F)mΦ8.8 × 4.8Φ8.0 × 4.0
Installed power drawkW60004200
Designed operation capacityt/h688688
Ball millSpecification (F/F)mΦ6.2 × 9.5Φ6.2 × 10.0
Installed power drawkW60006800
Designed operation capacityt/h688688
Design product sizeμm115115
Comminution systemTotal installed power drawkW12,00011,000
Table 3. Comparison of the conditions between the actual operation and reworked circuit model.
Table 3. Comparison of the conditions between the actual operation and reworked circuit model.
ComparisonSAG MillBall MillSAG/Ball Mill Ratio
Average operating power draw/kW332650140.66
Installed power of the reworked model/kW420068000.62
Original designed power draw/kW600060001
Table 4. Operating conditions for maximum theoretical processing capacity.
Table 4. Operating conditions for maximum theoretical processing capacity.
MillMaximum Processing CapacityBall FillingTotal FillingCalculated Power Draw
(t/h)(% v/v)(% v/v)(kW)
SAG8508254300
Ball85027-5700

Share and Cite

MDPI and ACS Style

Zhang, W. Optimizing Performance of SABC Comminution Circuit of the Wushan Porphyry Copper Mine—A Practical Approach. Minerals 2016, 6, 127. https://doi.org/10.3390/min6040127

AMA Style

Zhang W. Optimizing Performance of SABC Comminution Circuit of the Wushan Porphyry Copper Mine—A Practical Approach. Minerals. 2016; 6(4):127. https://doi.org/10.3390/min6040127

Chicago/Turabian Style

Zhang, Wei. 2016. "Optimizing Performance of SABC Comminution Circuit of the Wushan Porphyry Copper Mine—A Practical Approach" Minerals 6, no. 4: 127. https://doi.org/10.3390/min6040127

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop