Next Article in Journal
Research on the Collapse Characteristics of Cavitation Bubbles near a Semi-Cylindrical Groove
Previous Article in Journal
Upper-Limb Dynamic Stability and Functional Symmetry in Experienced Taekwon-Do Athletes
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Adaptive Bi-Level Planning of Photovoltaic Hosting Capacity for Hydro-Dominant Distribution Grids Considering Hydraulic Safety Constraints

1
Lincang Power Supply Bureau, Yunnan Power Grid Co., Ltd., Lincang 677000, China
2
Kunming Power Supply Bureau, Yunnan Power Grid Co., Ltd., Kunming 650000, China
3
Power Planning and Construction Research Center, Yunnan Power Grid Co., Ltd., Kunming 650000, China
4
Zhaotong Power Supply Bureau, Yunnan Power Grid Co., Ltd., Zhaotong 657000, China
5
China Southern Power Grid Internet Service Co., Ltd., Guangzhou 510000, China
6
School of Automation, Central South University, Changsha 410083, China
*
Author to whom correspondence should be addressed.
Symmetry 2026, 18(7), 1079; https://doi.org/10.3390/sym18071079 (registering DOI)
Submission received: 15 May 2026 / Revised: 17 June 2026 / Accepted: 18 June 2026 / Published: 25 June 2026

Abstract

Hydro-dominant distribution grids with high penetrations of distributed photovoltaic (PV) generation exhibit a clear operational asymmetry. PV output changes rapidly at the minute scale, whereas hydropower regulation is constrained by reservoir water balance, turbine ramping capability, and hydraulic safety limits. During high-inflow periods, mandatory hydropower generation further reduces the downward regulation margin and restricts midday PV accommodation. To address this issue, this paper develops an asymmetry-aware adaptive bi-level planning framework for photovoltaic hosting capacity (PVHC) assessment. A db4 discrete wavelet transform is used to decompose PV output into low-frequency energy trends and high-frequency fluctuation components. The upper layer performs hourly economic dispatch while maintaining reservoir water balance, and the lower layer conducts minute-level constrained tracking under ramping and vibration-zone avoidance constraints. A bisection-type capacity-search procedure is then used to identify the PVHC boundary by jointly checking curtailment, ramping, frequency proxy, voltage, line-loading, point-of-common-coupling exchange, and vibration-zone residence constraints. Case studies based on a 15 min PV dataset from a 30 MW station, hydropower operation records, and a modified 15-node feeder in Southwest China show that hydrological asymmetry materially affects PV accommodation. The obtained PVHC ranges from 53.17 MW under the most restrictive high-proxy condition to 65.33 MW under low-proxy operation. Compared with the no-coordination case, representative-month PVHC increases from 49.80 MW to 65.33 MW, while the simulated residence time within the predefined vibration-prone zone decreases from 447 min to 0 min. These results indicate that PVHC evaluation in hydro-dominant feeders should jointly consider electrical constraints, hydrological asymmetry, and hydraulic safety limits.

1. Introduction

Against the backdrop of increasingly urgent low-carbon energy transitions, the development and utilization of renewable energy have become central to power-system planning worldwide [1,2]. Owing to its modular deployment and mature conversion technology, photovoltaic (PV) generation has expanded rapidly in recent years [3]. However, high PV penetration introduces intermittency, steep ramping, voltage rise, and reverse-power-flow risks, which complicate secure operation after large-scale grid integration [4,5,6,7,8]. Therefore, accurately assessing the capacity of a distribution grid to accommodate PV generation, namely photovoltaic hosting capacity (PVHC), has become an important planning problem [9,10].
Among various strategies to smooth PV output fluctuations and improve PVHC, energy storage systems and hybrid storage configurations are widely used because they can provide fast active-power compensation [11,12,13]. Nevertheless, electrochemical storage remains constrained by investment cost, aging, state-of-charge management, and cell-level balancing requirements [14,15]. These limitations motivate the use of existing hydropower flexibility where hydrological and mechanical operating constraints can be represented explicitly.
Hydropower provides a mature and flexible regulating resource with quasi-energy-storage characteristics, because reservoir storage supports long-duration energy balancing and turbine-governor action can supply shorter-term power regulation [16,17,18]. Relying on a hydro-PV hybrid system can therefore mitigate PV volatility while exploiting hydropower flexibility to enlarge feasible PV accommodation scenarios [19,20,21].
Existing studies on hydro-PV hybrid systems primarily address optimization problems at a single time scale, such as day-ahead economic dispatch or fast frequency-control studies [22,23,24]. Nevertheless, PV output volatility presents distinct multi-time-scale features, involving both energy imbalance over long durations and power shocks at short time scales [25]. A single-level control strategy may therefore underestimate the usable flexibility of hydropower resources or overlook hydraulic safety when estimating PVHC.
Hierarchical scheduling has recently been used to separate steady-state economic operation from fast feedback regulation in active distribution networks and renewable microgrids [26,27]. This idea is relevant to hydro-dominant feeders because the low-frequency component of net load is more naturally assigned to reservoir energy management, whereas the high-frequency component is better treated as a power-tracking task. However, directly transferring this architecture to hydropower-dominated systems remains nontrivial, because turbine nonlinearity, hydraulic transients, and operation near vibration-prone zones may increase mechanical risk [28,29,30].
The remaining research gap is therefore not only whether hydropower can smooth PV fluctuations, but how PVHC can be assessed when temporal asymmetry, hydrological asymmetry, and hydraulic safety constraints are represented in the same planning framework. To bridge this gap, this paper proposes an adaptive bi-level planning framework for hydro-dominant distribution grids.
The hydro-PV system studied here is asymmetric in time scale because reservoir energy dynamics evolve slowly, whereas PV fluctuations appear at minute-level resolution; it is also asymmetric in resource availability because high-inflow months force hydropower units toward higher base output and reduce downward regulation margin. The proposed controller is therefore interpreted as a symmetry-restoration mechanism that reallocates low-frequency energy and high-frequency power disturbances while respecting nonconvex hydraulic safety intervals.
The contributions of this paper are as follows:
  • A spectral-decoupled bi-level dispatch framework is proposed to coordinate long-term reservoir energy scheduling and short-term photovoltaic fluctuation smoothing.
  • A vibration-zone avoidance constraint is embedded into the lower-layer control model to reduce operation within predefined disjoint unsafe power regions.
  • An iterative PVHC assessment method is developed by integrating hydropower ramping limits, curtailment constraints, frequency-proxy limits, and distribution-network security constraints.

2. Materials and Methods

To quantify PVHC under multi-time-scale and hydrological asymmetries, this study proposes an asymmetry-aware dispatch-and-tracking framework composed of an hourly energy-management layer, a minute-level power-regulation layer, and a PVHC boundary-search module. As illustrated in Figure 1, the framework decouples the hydro-PV dispatch problem into an upper energy-management layer and a lower power-regulation layer. The upper layer performs hourly predictive dispatch and coordinates reservoir water balance with economic operation, while the lower layer operates at 1 min resolution as a constrained tracking controller for high-frequency PV deviations within the remaining hydropower ramping margin. Embedded in a PVHC boundary-search algorithm, the framework identifies the maximum allowable PV integration level subject to hydraulic coupling, predefined vibration-zone avoidance, and feeder-security constraints. Simulations and graphical post-processing were conducted using MATLAB R2025a (The MathWorks, Inc., Natick, MA, USA).

2.1. PV Uncertainty Decomposition Model

Due to random disturbances such as cloud shading and atmospheric flow, photovoltaic generation exhibits significant non-stationary characteristics. As illustrated in Figure 2a, this behavior is characterized by the superposition of diurnal energy trends (low-frequency components) and stochastic power fluctuations (high-frequency components). Traditional signal decomposition methods often fail to effectively separate these two components. For instance, empirical mode decomposition is prone to mode mixing, whereas variational mode decomposition depends on preset parameters and lacks strict orthogonality.
To address these complexities, this study constructs an uncertainty decomposition model using the discrete wavelet transform based on multi-resolution analysis. Daubechies db4 wavelets are selected because their compact support is suitable for capturing sharp PV transients, and the measured 15 min PV profile from the 30 MW station is interpolated to the 1 min lower-layer control interval before decomposition. The original PV sequence P PV ( t ) is decomposed into the level-J approximation and the reconstructed detail component as
P PV ( t ) = P PV Lf ( t ) + P PV Hf ( t ) = k c J , k ϕ J , k ( t ) + j = 1 J k d j , k ψ j , k ( t ) .
In Equation (1), ϕ J , k and ψ j , k denote the scaling and wavelet functions, respectively. The term P PV Lf ( t ) captures the deterministic energy trend used by the upper-layer dispatch, whereas P PV Hf ( t ) represents minute-scale stochastic deviations that must be handled by fast hydro tracking. The spectral properties and statistical distribution are illustrated in Figure 2b,c.

2.2. Energy-Power Decoupled Hydropower Model

The hydropower plant is represented through an energy-power decoupled abstraction: the reservoir provides slow energy buffering, whereas the turbine-generator unit supplies short-term active-power regulation. This treatment follows the same modeling logic used in hybrid energy-storage coordination, but it keeps the hydraulic constraints that are essential for a hydro-dominant feeder.

2.2.1. Reservoir Energy Balance

As a large-capacity energy buffering unit, the reservoir serves as the core of the upper-layer constraint framework. By regulating the storage and release of water flow over an extended time window, the reservoir achieves the spatiotemporal transfer of hydraulic resources and maintains full-cycle energy balance, as illustrated in Figure 3.
The reservoir continuity equation is expressed by Equations (2) and (3), replacing the former ambiguous reference to “Expression (2–3)”.
V k + 1 = V k + Q i , k Q g , k Q s , k Δ T ,
V min V k V max , 0 Q g , k Q g max , 0 Q s , k Q s max .
Here, V k denotes the reservoir storage at hour k, while Q i , k , Q g , k , and Q s , k represent natural inflow, generation discharge, and spillage, respectively. These equations enforce mass conservation and provide the long-term hydraulic coupling mechanism required for PVHC assessment.

2.2.2. Hydro-Turbine Power Regulation

The hydro-turbine generator serves as the power-regulation element of the system. The hydropower output P H ( t ) is determined by the net head H n ( t ) and generation flow Q g ( t ) , as shown in Figure 4.
Because reservoir storage is large relative to minute-level dispatch adjustments, short-horizon variations in the hydraulic head are assumed to be small in the dispatch layer. Accordingly, the hydropower production relationship is described by
P H ( t ) = η w g H n ( t ) Q g ( t ) k Q g ( t ) ,
where k denotes the local hydropower production coefficient around the operating point. This approximation is used only for dispatch-level PVHC assessment. The corresponding linearization error is summarized in Figure 5.
The power support capability of the hydro-turbine is bounded by capacity limits and ramping limits:
P H , min P H ( τ ) P H , max ,
R d P H ( τ ) P H ( τ 1 ) Δ t R u .
In Equations (5) and (6), Δ t denotes the fast lower-layer time step, which is 1 min in the case study. The simulated hydro unit is rated at 50 MW, the steady-state dispatchable range is 5–50 MW before the hydrological forced-output adjustment, and R u = R d = 2.0 MW/min. The predefined vibration-prone interval is 18–24 MW, so the feasible safe operating zones are [5, 18] MW and [24, 50] MW under the representative setting (Figure 6). The case-study parameters are summarized in Table 1.
The measured PV output data were obtained from an existing 30 MW PV station. For PVHC assessment, the measured profile is first normalized by the station rating and then scaled to each candidate PV capacity in the boundary search. Thus, the reported PVHC is a scalable planning boundary rather than the existing installed capacity.

2.3. Proposed Two-Layer Coupled Control Strategy

To address the spatiotemporal contradiction encountered during PV accommodation, this paper proposes a two-layer cooperative dispatch-and-tracking strategy. The upper layer uses a 24 h rolling horizon with a 1 h scheduling step to maintain reservoir water balance and issue the hourly reference P H r ( k ) . The lower layer then holds the current hourly reference over the corresponding 60 one-minute intervals and corrects it using the high-frequency PV component P PV Hf . In this way, the two layers are coupled through a sample-and-hold reference trajectory and receding-horizon feedback rather than operating as independent optimizers. The control architecture is illustrated in Figure 7.

2.3.1. MPC-Based Upper-Layer Economic Dispatch

The upper-layer energy-management system adopts a rolling-horizon mechanism based on model predictive control. The prediction horizon N p is set to 24 h, and the scheduling time step Δ T is set to 1 h. At each decision instance, the system solves for the optimal control sequence based on the latest state feedback and applies the first dispatch instruction.
The objective function introduces the hydroelectric unit wear cost C w and the energy-curtailment cost C p :
min J = k = t t + N p 1 C w ( k ) + C p ( k ) .
The regulation-wear term is
C w ( k ) = c w P H r ( k ) P H r ( k 1 ) ,
where c w = 0.5 in the normalized simulation objective. For the point-of-common-coupling (PCC) convention, positive P PCC denotes export to the external grid. The exchange corridor is constrained by +35 MW export and −45 MW import limits.
The curtailment and spillage cost is defined as
C p ( k ) = λ s Q s ( k ) + λ c P c ( k ) ,
where P c ( k ) denotes curtailed PV power and Q s ( k ) denotes spillage flow. In the case study, λ s = λ c = 1 after per-unit normalization. Because the final PVHC boundary is determined by explicit security constraints, these weights mainly affect the selection of smooth feasible trajectories rather than the stopping thresholds.
Because the feeder can exchange power with the external utility grid, the upper-layer balance is written through the PCC exchange variable:
P PCC ( k ) = P H r ( k ) + P PV Lf ( k ) P c ( k ) P l ( k ) .
The final output of the upper layer is the reference trajectory P H r ( k ) , which guides the hydropower unit in smoothing PV power fluctuations while maintaining reservoir feasibility.

2.3.2. Lower-Layer Control: Real-Time Fluctuation Smoothing and Turbine Regulation

The lower-layer control operates on a 1 min time scale to address the stochastic high-frequency component of PV power. Its target hydro output is constructed as
P H t ( τ ) = P H r ( τ ) ξ ( τ ) ,
where ξ ( τ ) is the high-frequency PV prediction deviation. Considering hydraulic inertia and mechanical transmission constraints, the actual output approximates the target within the feasible region:
min P H r ( τ ) P H t ( τ ) 2 .
To avoid operation in the vibration-prone interval Ω v , the model imposes
P H r ( τ ) Ω v .
This nonconvex feasible set is represented using binary variables z m { 0 , 1 } :
m = 1 M z m = 1 ,
z m P min , m P H , m ( τ ) z m P max , m ,
P H r ( τ ) = m = 1 M P H , m ( τ ) .
Here, M is the number of safe operating zones and [ P min , m , P max , m ] is the power range of the mth safe zone.

2.4. PVHC Boundary-Search Algorithm

Building upon the bi-level dispatch-and-tracking model, this section evaluates PVHC as a constrained boundary-identification problem. PVHC is defined as the maximum scalable PV active-power capacity that the feeder can accommodate without violating hydraulic safety, curtailment, ramping, frequency proxy, voltage, line-loading, and PCC-exchange constraints. The measured 30 MW PV station is therefore used as a normalized profile source, and the PV capacity is scaled during the search.
The original step-increment description is replaced by a bisection-type boundary search, which is consistent with the exported simulation results and avoids unnecessary iterations near the feasibility boundary. The lower and upper PV capacity bounds are initialized as P low = 0 MW and P high = 150 MW, respectively, and the search tolerance is set to ε = 0.25 MW. In each iteration, the candidate capacity is P mid = ( P low + P high ) / 2 . If all security and economic criteria are satisfied, P low is updated to P mid ; otherwise, P high is updated to P mid . The process stops when P high P low ε , and P low is reported as the PVHC.
Frequency-proxy security is evaluated by a dispatch-level screening proxy rather than a detailed electromechanical transient model. The fast active-power imbalance is obtained by removing a 30 min moving average from PCC exchange power, normalizing it on a 100 MVA base, and propagating it through a first-order response with f 0 = 50 Hz, T f = 3600 s, and D = 1.5 . The adopted threshold is | Δ f proxy | 0.20 Hz. The boundary-search process is summarized in Figure 8.

3. Results

Empirical validation is conducted on a modified 15-node radial distribution feeder, rather than on an abstract test network, so that the PVHC boundary can be assessed under hydropower-dominated operating conditions. The network topology, retained from the submitted manuscript, is shown in Figure 9. It represents a desensitized small-hydropower-dominated distribution system located in Yunnan, Southwest China. Because of the high resistance-to-reactance ratio and restricted upstream transmission corridor, voltage security, line thermal limits, PCC exchange, and hydraulic safety jointly shape the feasible PVHC boundary.

3.1. Seasonal Interplay of Hydro and PV Resources

The hydrological condition is represented by a desensitized inflow proxy derived from nonnegative monthly hydropower operation records after smoothing and robust scaling. Figure 10 has been re-exported with larger axis labels, thicker lines, and a vector source file so that the month labels and dual-axis units remain readable in the final MDPI layout. The results indicate a clear asymmetric resource effect: low-proxy months retain relatively high PVHC, with the representative January value reaching 65.33 MW, whereas the high-proxy August–September period reduces feasible hosting capacity to 55.81 MW and 53.17 MW, respectively.
The hydrological asymmetry indicator is defined as A H = P H , f / P r , where P H , f is the monthly forced minimum hydropower output and P r = 50 MW. As A H increases, forced hydropower output occupies a larger share of unit capacity and reduces downward regulation margin for midday PV accommodation. Based on Table 2, the Pearson correlation coefficient between A H and PVHC is approximately −0.753, indicating a negative relationship between hydrological asymmetry and PV accommodation capability.

3.2. Efficacy of Multi-Scale Spectral Decomposition

The fundamental mechanism of the proposed control architecture relies on the effective spectral decoupling of low-frequency energy flows from high-frequency power fluctuations. Figure 11 verifies this signal decomposition mechanism. The raw photovoltaic power profile exhibits a diurnal envelope with stochastic volatility induced by cloud movements and atmospheric turbulence. Direct injection of such unprocessed stochastic signals into the electrical grid may increase nodal-voltage and power-balance risks.
In contrast, Figure 11c characterizes the high-frequency component comprising zero-mean stochastic fluctuations and rapid ramping events. With amplitudes distributed between approximately −10 MW and +15 MW, this signal requires agile regulation capability. Feeding this component to the lower-layer tracking controller reduces the need to solve the full global optimization problem at every fast control interval.

3.3. Dynamic Power Balance and Grid Safety Verification

Figure 12 presents detailed dispatch results for the representative low-inflow month selected from the simulation outputs. During the midday interval, PV generation surges and hydropower output is guided toward the safe lower operating region, creating accommodation headroom while avoiding excessive residence in the vibration-prone interval. The PCC exchange remains within the adopted export/import corridor after PV curtailment and hydro tracking are applied. The operating security checks are summarized in Table 3.
All indicators remain within the adopted PVHC stopping thresholds. Because PVHC is obtained by bisection boundary identification, the reported value corresponds to the last feasible capacity before any constraint violation occurs. The search accuracy is determined by ε = 0.25 MW. The frequency-proxy sensitivity is quantified in Table 4.
The sensitivity test indicates that a very strict ±0.10 Hz proxy threshold reduces PVHC to 50.83 MW. For thresholds from ±0.15 Hz to ±0.30 Hz, PVHC remains 65.33 MW because curtailment, PCC exchange, and hydraulic constraints become the active limiting conditions. Thus, the reported result is not determined solely by an arbitrary ±0.20 Hz choice. The same trend is visualized in Figure 13.

3.4. Vibration-Zone Avoidance and Mechanical Safety

A key constraint in hydropower operation is the avoidance of nonconvex vibration-prone zones, where hydraulic instability may increase mechanical stress on the turbine runner. Figure 14 verifies the vibration-zone avoidance strategy from both statistical and time-domain perspectives. The predefined prohibited interval of 18–24 MW is treated as a dispatch-level engineering constraint derived from desensitized operation and maintenance restrictions for a representative Francis-type small hydropower unit, rather than as a universal hydraulic-instability boundary.
Figure 14a shows that the hydropower active-power distribution is concentrated in two safe operating regions around the predefined vibration-prone interval. Figure 14b provides a temporal examination of the avoidance mechanism; the controller keeps the accepted operating points outside the 18–24 MW interval and prevents sustained residence within the prohibited zone. The connecting line in the plot is a visual interpolation between minute-level points and should not be interpreted as a physically validated continuous crossing trajectory inside the prohibited region. In the proposed case, the calculated residence time inside the interval is 0 min.
To quantify the gain of the proposed formulation, Table 5 compares four representative PVHC assessment/control cases: no coordinated control, single-layer MPC, bi-level tracking without vibration-zone guidance, and the proposed bi-level method with vibration-zone avoidance. These baselines represent common static or single-layer PVHC screening approaches and an ablation of the proposed hydraulic-safety module.
The proposed method raises representative-month PVHC by 15.53 MW compared with no coordinated control while keeping voltage, line loading, frequency proxy, PCC exchange, ramping, and curtailment within their limits. Although the single-layer MPC obtains a slightly higher PVHC, it leaves 154 min of residence within the predefined vibration-prone zone. The proposed method reduces this residence to zero with only a 0.44 MW, or approximately 0.67%, PVHC reduction relative to the single-layer case. The bi-level tracking case without vibration-zone guidance removes the avoidance mechanism from the tracking controller; its trajectory can therefore trigger other operational constraints earlier, especially the frequency-proxy security constraint, which explains why its PVHC is lower than that of the proposed guided controller. The comparison is further illustrated in Figure 15.

4. Discussion

The proposed two-layer dispatch-and-tracking framework addresses the temporal asymmetry between slow reservoir energy evolution and short-term stochastic PV fluctuations by separating energy scheduling from power tracking. The time-scale indicator A T = 60 confirms that the two layers operate on strongly different temporal resolutions, while the hydrological indicator A H explains why high-inflow months reduce the downward regulation margin. In the symmetry framing, the controller uses this quantified asymmetry to restore long-horizon energy balance and short-horizon power balance subject to hydraulic safety limits.
Simulation results underscore the importance of incorporating hydraulic safety constraints, ramping limits, frequency-proxy security checks, PCC exchange limits, and distribution-network security checks into PVHC assessment. The frequency-threshold sensitivity in Table 4 shows that the adopted ±0.20 Hz proxy is not the sole determinant of the reported PVHC, while the comparison in Table 5 shows that the single-layer MPC obtains a slightly higher PVHC but leaves non-negligible vibration-zone residence. The proposed formulation therefore prioritizes hydraulic safety with negligible sacrifice in hosting capacity, improving the quality of the feasible operating trajectory rather than merely maximizing the installed PV boundary.
Several limitations should be stated explicitly. First, the hydro production function is linearized around the normal operating range, and detailed hydraulic transient dynamics are not fully represented. Second, the vibration-prone zone is modeled as a fixed forbidden interval, whereas its boundary may vary with water head, guide-vane opening, discharge, unit aging, and turbine characteristics. Third, the feeder-security model uses a radial LinDistFlow screening representation and is not equivalent to a full three-phase unbalanced AC power-flow study. Fourth, the frequency-proxy response is a dispatch-level screening model and should not be interpreted as an electromagnetic or electromechanical transient simulation. Fifth, the inflow variable, raw PV measurements, hydropower operation records, and branch-level feeder parameters are desensitized from field records; future work should use measured discharge, reservoir head, vibration, and complete branch-level data when confidentiality restrictions allow.

5. Conclusions

This paper proposes an asymmetry-aware adaptive bi-level planning framework for assessing PV hosting capacity in hydro-dominant distribution grids under hydraulic safety constraints. The framework separates low-frequency PV energy trends from short-term fluctuations, coordinates reservoir energy management in the upper layer, and performs minute-level hydro tracking with ramping and vibration-zone avoidance constraints in the lower layer.
The case study on a modified 15-node feeder indicates that hydrological asymmetry materially affects PV accommodation. In the tested simulation, the proposed method yields 65.33 MW PVHC under the representative low-proxy condition and 53.17–55.81 MW under the most restrictive high-proxy conditions. In the representative comparison month, PVHC increases from 49.80 MW under no coordinated control to 65.33 MW under the proposed method, while modeled vibration-zone residence decreases from 447 min to 0 min.
The engineering implication is that hydropower flexibility can be treated as a dispatch-level resource for PV accommodation only when hydraulic safety and feeder security are modeled explicitly. Future work should validate the framework with larger real feeders, complete AC power-flow data, detailed hydraulic-transient models, hardware-in-the-loop tests, and broader benchmark strategies.

Author Contributions

Conceptualization, R.G. and Z.C.; methodology and software, Z.C.; validation, R.P., Z.Z., W.W., H.L., C.D., X.Z., L.H. and S.D.; resources and data curation, R.G. and R.P.; writing—original draft preparation, Z.C.; writing—review and editing, R.G., R.P., Z.Z., W.W., H.L., C.D., X.Z., Y.C. (Yansong Cui), J.Z., L.H., S.D., Y.C. (Yuan Cao) and Z.C.; supervision, Y.C. (Yuan Cao); project administration and funding acquisition, R.G. and R.P. All authors have read and agreed to the published version of the manuscript.

Funding

The authors declare that this study received funding from the Science and Technology Project of Yunnan Power Grid Co., Ltd. Lincang Power Supply Bureau, grant number YNKJXM202400558. The funder provided project support and access to desensitized field data. The funder was not involved in the independent analysis and interpretation of the data, the writing of this article, or the decision to submit it for publication.

Data Availability Statement

The PV measurements, hydropower operation records, and feeder parameters used in this study are derived from field project data and have been desensitized. Due to confidentiality agreements with the project partners, the complete raw datasets and branch-level feeder parameters cannot be publicly released. Aggregated parameter ranges, normalized profiles, simulation settings, monthly PVHC values, and sensitivity results are provided in the manuscript and supplementary simulation files; processed data may be available from the corresponding author upon reasonable request.

Conflicts of Interest

Authors Ruizhu Guo, Rongwei Peng, and Wenfeng Wang are employed by Lincang Power Supply Bureau, Yunnan Power Grid Co., Ltd. Author Zhenlong Zhu is employed by Kunming Power Supply Bureau, Yunnan Power Grid Co., Ltd. Authors Hongyin Liu and Chong Du are employed by the Power Planning and Construction Research Center, Yunnan Power Grid Co., Ltd. Author Xi Zhang is employed by Zhaotong Power Supply Bureau, Yunnan Power Grid Co., Ltd. Authors Yansong Cui and Jing Zi are employed by China Southern Power Grid Internet Service Co., Ltd. The remaining authors declare no conflicts of interest. The authors declare that this study received funding from the Science and Technology Project of Yunnan Power Grid Co., Ltd. Lincang Power Supply Bureau. The funder and all affiliations did not influence the study design, data analysis, interpretation of results, manuscript writing, or the decision to submit the article for publication.

References

  1. Song, D.; Yousaf, A.; Noor, J.; Cao, Y.; Dong, M.; Yang, J.; Rizk-Allah, R.M.; Elkholy, M.H.; Talaat, M. ANN-Based Model Predictive Control for Hybrid Energy Storage Systems in DC Microgrid. Prot. Control Mod. Power Syst. 2025, 10, 1–15. [Google Scholar] [CrossRef]
  2. Wang, C.; Liu, C.; Zhou, X.; Zhang, G. Flexibility-based expansion planning of active distribution networks considering optimal operation of multi-community integrated energy systems. Energy 2024, 307, 132601. [Google Scholar] [CrossRef]
  3. Yang, Y.; Lee, S.-H.; Choi, Y.-S.; Lee, K.-M. LightGBM Medium-Term Photovoltaic Power Prediction Integrating Meteorological Features and Historical Data. Energies 2025, 18, 5526. [Google Scholar] [CrossRef]
  4. Ma, R.; Wang, H.; Xia, J. Static Voltage Stability Analysis and Control Strategy of Distribution Network with High Proportion Distributed PV Generation During Fault. In Proceedings of the 2025 International Conference on New Power System Technology (PowerCon), Hefei, China, 24–25 September 2025; pp. 1–5. [Google Scholar] [CrossRef]
  5. Liao, J.; Yu, R.; Ye, R.; Xiong, J.; Xia, J. Coordinated Control Method for Low-Voltage Distribution Networks with High-Penetration Residential Photovoltaic. Electr. Power 2025, 58, 110–120. [Google Scholar] [CrossRef]
  6. Yan, Y.; Wang, B.; Xu, W.; Liu, J.; Gong, R. Small-signal stability analysis of power systems with high renewable penetration based on dynamic equivalent model. Int. J. Electr. Power Energy Syst. 2025, 170, 110835. [Google Scholar] [CrossRef]
  7. Chen, P.; Liu, S.; Wang, X.; Kamwa, I. Physics-Guided Multi-Agent Deep Reinforcement Learning for Robust Active Voltage Control in Electrical Distribution Systems. IEEE Trans. Circuits Syst. I Regul. Pap. 2024, 71, 922–933. [Google Scholar] [CrossRef]
  8. Song, G.; Wu, Q.; Jiao, W.; Lu, L. Distributed coordinated control for voltage regulation in active distribution networks based on robust model predictive control. Int. J. Electr. Power Energy Syst. 2025, 166, 110529. [Google Scholar] [CrossRef]
  9. Chen, J.; Wang, Y.; Du, L.; Xu, Q.; Li, M.; Zhang, H. Hosting Capacity Assessment of Distributed Renewable Energy Resources Integrated into Distribution Networks Via Microgrids. In Proceedings of the 2025 International Conference on New Power System Technology (PowerCon), Hefei, China, 24–25 September 2025; pp. 1–6. [Google Scholar] [CrossRef]
  10. Siddique, M.N.I.; Pota, H.; Mekhilef, S. Hosting Capacity Prediction using Spatial-temporal Correlations of Distribution Networks. In Proceedings of the 2024 Energy Conversion Congress & Expo Europe (ECCE Europe), Darmstadt, Germany, 2–6 September 2024; pp. 1–7. [Google Scholar] [CrossRef]
  11. Kumar, G.B.; Palanisamy, K.; Sanjeevikumar, P.; Muyeen, S.M. Analysis of control strategies for smoothing of solar PV fluctuations with storage devices. Energy Rep. 2023, 9, 163–177. [Google Scholar] [CrossRef]
  12. Ramkumar, M.S.; Subramani, J.; Sivaramkrishnan, M.; Munimathan, A.; Michael, G.K.O.; Alam, M.M. Optimal energy management for multi-energy microgrids using hybrid solutions to address renewable energy source uncertainty. Sci. Rep. 2025, 15, 7755. [Google Scholar] [CrossRef] [PubMed]
  13. Yang, X.; Ye, X.; Li, Z.; Wang, X.; Song, X.; Liao, M.; Liu, X.; Guo, Q. Hybrid energy storage configuration method for wind power microgrid based on EMD decomposition and two-stage robust approach. Sci. Rep. 2024, 14, 2733. [Google Scholar] [CrossRef] [PubMed]
  14. Liao, Y.; Zhang, X.; Chen, L.; Li, F.; Wang, C.; Cao, Y.; Hu, Y. Shared-Receiver Battery Equalizer Based on Inductive Power Transfer and Bidirectional DC–DC Converter. IEEE Trans. Power Electron. 2026, 41, 3879–3893. [Google Scholar] [CrossRef]
  15. Wang, C.; Cao, M.; Cao, Y. Battery aging estimation algorithm with active balancing control in battery system. J. Energy Storage 2025, 108, 115055. [Google Scholar] [CrossRef]
  16. Tefera, W.M.; Kasiviswanathan, K. A global-scale hydropower potential assessment and feasibility evaluations. Water Resour. Econ. 2022, 38, 100198. [Google Scholar] [CrossRef]
  17. Maroufpoor, S.; Qin, X. Present and Future Energy Potential of Run-of-River Hydropower in Mainland Southeast Asia: Balancing Climate Change and Environmental Sustainability. Water 2025, 17, 2256. [Google Scholar] [CrossRef]
  18. Tsuanyo, D.; Amougou, B.; Aziz, A.; Nka Nnomo, B.; Fioriti, D.; Kenfack, J. Design models for small run-of-river hydropower plants: A review. Sustain. Energy Res. 2023, 10, 3. [Google Scholar] [CrossRef]
  19. Zhang, H.; Liao, K.; Yang, J.; Yin, Z.; He, Z. Long-Term and Short-Term Coordinated Scheduling for Wind-PV-Hydro-Storage Hybrid Energy System Based on Deep Reinforcement Learning. IEEE Trans. Sustain. Energy 2025, 16, 1697–1710. [Google Scholar] [CrossRef]
  20. Tang, H.; Li, R.; Song, T.; Ju, S. Short-term optimal scheduling and comprehensive assessment of hydro-photovoltaic-wind systems augmented with hybrid pumped storage hydropower plants and diversified energy storage configurations. Appl. Energy 2025, 389, 125787. [Google Scholar] [CrossRef]
  21. Wang, F.; Xu, J.; Wang, Q. Complementary operation based sizing and scheduling strategy for hybrid hydro-PV-wind generation systems connected to long-distance transmission lines. Appl. Energy 2024, 364, 123082. [Google Scholar] [CrossRef]
  22. Bai, Y.; Sui, Y.; Deng, X.; Wang, X. Quantum-inspired robust optimization for coordinated scheduling of PV-hydrogen microgrids under multi-dimensional uncertainties. Sci. Rep. 2025, 15, 29589. [Google Scholar] [CrossRef] [PubMed]
  23. Yang, L.; Liu, T.; Hill, D.J. Distributed MPC-based frequency control for multi-area power systems with energy storage. Electr. Power Syst. Res. 2021, 190, 106642. [Google Scholar] [CrossRef]
  24. Luo, W.; Wang, C.; Zhang, Y.; Zhao, J.; Huang, Z.; Wang, J.; Zhang, C. A deep reinforcement learning approach for joint scheduling of cascade reservoir system. J. Hydrol. 2025, 651, 132515. [Google Scholar] [CrossRef]
  25. Xu, C.; Inuiguchi, M.; Hayashi, N.; Jee Keen Raymond, W.; Mokhlis, H.; Azil Illias, H. Enhancing Reinforcement Learning-Based Energy Management Through Transfer Learning with Load and PV Forecasting. IEEE Access 2025, 13, 43956–43972. [Google Scholar] [CrossRef]
  26. Su, Y.; Teh, J.; Fang, S.; Dai, Z.; Wang, P. Two-stage optimal dispatch framework of active distribution networks with hybrid energy storage systems via deep reinforcement learning and real-time feedback dispatch. J. Energy Storage 2025, 108, 115169. [Google Scholar] [CrossRef]
  27. Li, S.; Zhu, J.; Dong, H.; Zhu, H.; Luo, F.; Borghetti, A. Multi-time-scale energy management of renewable microgrids considering grid-friendly interaction. Appl. Energy 2024, 367, 123428. [Google Scholar] [CrossRef]
  28. Gao, J.; Wang, L.; Yan, J.; Wang, J.; Wang, Y.; Yin, T. A Two-Stage Optimization Strategy for Hybrid Power Systems with Dominated-Hydropower. In Proceedings of the 2025 2nd International Conference on Smart Grid and Artificial Intelligence (SGAI), Changsha, China, 21–23 March 2025; pp. 291–295. [Google Scholar] [CrossRef]
  29. Zhu, Z.; Wang, H.; Lu, X.; Xu, R.; Tan, X.; Li, C. Precise quantification analysis: Power regulation and equipment wear and tear characteristics of hydropower units under multi-energy complementary mode. Energy Convers. Manag. 2025, 336, 119860. [Google Scholar] [CrossRef]
  30. Feng, C.; Sun, N.; Zheng, C.; Zhu, Y.; Zhang, N.; Shan, Y.; Shi, L.; Xue, X. Stability analysis of grid-connected hydropower plant considering turbine nonlinearity and parameter-varying penstock model. Sci. Rep. 2025, 15, 14532. [Google Scholar] [CrossRef] [PubMed]
Figure 1. Comprehensive assessment framework for bi-level PVHC planning under multi-time-scale uncertainties.
Figure 1. Comprehensive assessment framework for bi-level PVHC planning under multi-time-scale uncertainties.
Symmetry 18 01079 g001
Figure 2. Multi-resolution analysis of PV uncertainty based on wavelet transform: (a) time-domain multi-resolution analysis; (b) spectral decoupling mechanism; and (c) uncertainty statistical distribution.
Figure 2. Multi-resolution analysis of PV uncertainty based on wavelet transform: (a) time-domain multi-resolution analysis; (b) spectral decoupling mechanism; and (c) uncertainty statistical distribution.
Symmetry 18 01079 g002
Figure 3. Reservoir energy characteristic curve, where green shading denotes reservoir-filling intervals with inflow exceeding discharge, and red shading denotes reservoir-drawdown intervals with discharge exceeding inflow.
Figure 3. Reservoir energy characteristic curve, where green shading denotes reservoir-filling intervals with inflow exceeding discharge, and red shading denotes reservoir-drawdown intervals with discharge exceeding inflow.
Symmetry 18 01079 g003
Figure 4. Operational characteristics of hydraulic turbines.
Figure 4. Operational characteristics of hydraulic turbines.
Symmetry 18 01079 g004
Figure 5. Steady-state linearization error analysis.
Figure 5. Steady-state linearization error analysis.
Symmetry 18 01079 g005
Figure 6. Schematic of the vibration-zone avoidance constraint formulation.
Figure 6. Schematic of the vibration-zone avoidance constraint formulation.
Symmetry 18 01079 g006
Figure 7. The proposed adaptive bi-level coupled control framework.
Figure 7. The proposed adaptive bi-level coupled control framework.
Symmetry 18 01079 g007
Figure 8. Binary-search PVHC boundary-identification algorithm based on multi-objective security constraints.
Figure 8. Binary-search PVHC boundary-identification algorithm based on multi-objective security constraints.
Symmetry 18 01079 g008
Figure 9. Configuration of the 15-node radial feeder integrating run-of-river hydropower and distributed photovoltaics.
Figure 9. Configuration of the 15-node radial feeder integrating run-of-river hydropower and distributed photovoltaics.
Symmetry 18 01079 g009
Figure 10. Seasonal PV hosting capacity and desensitized inflow-proxy correlation.
Figure 10. Seasonal PV hosting capacity and desensitized inflow-proxy correlation.
Symmetry 18 01079 g010
Figure 11. Spectral decomposition results: (a) original PV profile; (b) low-frequency component; (c) high-frequency component.
Figure 11. Spectral decomposition results: (a) original PV profile; (b) low-frequency component; (c) high-frequency component.
Symmetry 18 01079 g011
Figure 12. Dynamic power balance and grid exchange under the proposed control strategy: (a) power balance; (b) grid interaction.
Figure 12. Dynamic power balance and grid exchange under the proposed control strategy: (a) power balance; (b) grid interaction.
Symmetry 18 01079 g012
Figure 13. Sensitivity of the representative-month PV hosting capacity to the adopted frequency-proxy threshold: (a) PVHC under different frequency-proxy limits; (b) maximum absolute value of the frequency proxy compared with the admissible boundary.
Figure 13. Sensitivity of the representative-month PV hosting capacity to the adopted frequency-proxy threshold: (a) PVHC under different frequency-proxy limits; (b) maximum absolute value of the frequency proxy compared with the admissible boundary.
Symmetry 18 01079 g013
Figure 14. Verification of vibration-zone avoidance for the hydropower unit: (a) output power distribution; (b) operating trajectory under vibration-zone avoidance.
Figure 14. Verification of vibration-zone avoidance for the hydropower unit: (a) output power distribution; (b) operating trajectory under vibration-zone avoidance.
Symmetry 18 01079 g014
Figure 15. Benchmark comparison among different control strategies in the representative month: (a) photovoltaic hosting capacity; (b) residence time within the hydropower vibration-prone operating zone.
Figure 15. Benchmark comparison among different control strategies in the representative month: (a) photovoltaic hosting capacity; (b) residence time within the hydropower vibration-prone operating zone.
Symmetry 18 01079 g015
Table 1. Main hydropower, feeder, and simulation parameters used in the case study.
Table 1. Main hydropower, feeder, and simulation parameters used in the case study.
ParameterValuePurpose or Interpretation
Rated capacity of the measured PV station30 MW nominalUsed to build normalized PV profiles; PVHC is a scalable planning boundary, not the present installed capacity.
Rated capacity of the simulated hydropower unit50 MWRated active-power capacity of the representative hydropower unit.
Basic dispatchable hydropower range5–50 MWSteady-state output range before applying the forced minimum-output adjustment and excluding the vibration-prone interval.
Forced minimum hydro output9.2–17.6 MWMonthly value mapped from the desensitized inflow proxy.
Generation-flow limit70 m3/sMaximum turbine discharge used in the production model.
Head range60–100 mDesensitized operating-head range used for dispatch-level calculation.
Reservoir storage range500–3000 Mm3Upper-layer energy-storage state constraint.
Turbine efficiency0.88Steady-state production coefficient in Equation (4).
Ramp-up/ramp-down rate2.0 MW/minLower-layer turbine response limit.
Vibration-prone interval18–24 MWPredefined prohibited partial-load region for the simulated unit.
Upper/lower time steps1 h/1 minHourly reservoir dispatch linked to minute-level power tracking; A T = 60 .
Frequency-proxy model f 0 = 50 Hz, T f = 3600 s, D = 1.5 , base = 100 MVADispatch-level screening proxy; not an electromechanical transient model.
PCC limits+35 MW export/−45 MW importExternal-grid exchange corridor.
Table 2. Seasonal hydrological asymmetry indicator and proposed PVHC.
Table 2. Seasonal hydrological asymmetry indicator and proposed PVHC.
MonthHydrological Proxy (m3/s) A H Proposed PVHC (MW)
Jan12.230.1965.33
Feb12.000.1864.75
Mar13.420.2065.19
Apr13.190.2063.87
May14.140.2160.35
Jun16.300.2456.69
Jul23.090.3261.67
Aug26.000.3555.81
Sep25.560.3553.17
Oct20.130.2861.38
Nov17.230.2564.31
Dec16.120.2364.45
Table 3. Operating security indicators of the proposed method in the representative month.
Table 3. Operating security indicators of the proposed method in the representative month.
IndicatorValueLimitStatus
Max PCC export35.00 MW35 MWSatisfied
Max PCC import17.00 MW45 MWSatisfied
Max voltage1.039 p.u.1.05 p.u.Satisfied
Min voltage0.981 p.u.0.95 p.u.Satisfied
Max line loading83.33%100%Satisfied
PV curtailment4.93%5%Satisfied
Max frequency-proxy deviation0.143 Hz0.20 HzSatisfied
Ramping violation0.00%1%Satisfied
Vibration-zone residence0 min2% of stepsSatisfied
Runtime0.033 sReportedReported
Table 4. Sensitivity of representative-month PVHC to the adopted frequency-proxy threshold.
Table 4. Sensitivity of representative-month PVHC to the adopted frequency-proxy threshold.
Frequency-Proxy Limit (Hz)PVHC (MW)Max | Δ f proxy | (Hz)Curtailment (%)Max Import (MW)
0.1050.830.1000.0017.0
0.1565.330.1434.9317.0
0.2065.330.1434.9317.0
0.2565.330.1434.9317.0
0.3065.330.1434.9317.0
Table 5. Comparative PVHC and security indices for the representative month.
Table 5. Comparative PVHC and security indices for the representative month.
(a) Capacity and Feeder-Security Indicators
CasePVHC (MW)Curt. (%)Voltage Range (p.u.)Line Loading (%)
No coordination49.804.930.996–1.03683.33
Single-layer MPC65.774.920.995–1.03983.33
Bi-level tracking w/o guidance54.930.400.989–1.03983.33
Proposed65.334.930.981–1.03983.33
(b) Dynamic and Hydraulic-Security Indicators
CaseMax | Δ f proxy | (Hz)PCC Export/Import (MW)Ramp Viol. (%)Vib. (min)
No coordination0.07235.0/0.30.00447
Single-layer MPC0.08835.0/0.20.00154
Bi-level tracking w/o guidance0.20035.0/10.10.00180
Proposed0.14335.0/17.00.000
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Guo, R.; Peng, R.; Zhu, Z.; Wang, W.; Liu, H.; Du, C.; Zhang, X.; Cui, Y.; Zi, J.; He, L.; et al. Adaptive Bi-Level Planning of Photovoltaic Hosting Capacity for Hydro-Dominant Distribution Grids Considering Hydraulic Safety Constraints. Symmetry 2026, 18, 1079. https://doi.org/10.3390/sym18071079

AMA Style

Guo R, Peng R, Zhu Z, Wang W, Liu H, Du C, Zhang X, Cui Y, Zi J, He L, et al. Adaptive Bi-Level Planning of Photovoltaic Hosting Capacity for Hydro-Dominant Distribution Grids Considering Hydraulic Safety Constraints. Symmetry. 2026; 18(7):1079. https://doi.org/10.3390/sym18071079

Chicago/Turabian Style

Guo, Ruizhu, Rongwei Peng, Zhenlong Zhu, Wenfeng Wang, Hongyin Liu, Chong Du, Xi Zhang, Yansong Cui, Jing Zi, Lv He, and et al. 2026. "Adaptive Bi-Level Planning of Photovoltaic Hosting Capacity for Hydro-Dominant Distribution Grids Considering Hydraulic Safety Constraints" Symmetry 18, no. 7: 1079. https://doi.org/10.3390/sym18071079

APA Style

Guo, R., Peng, R., Zhu, Z., Wang, W., Liu, H., Du, C., Zhang, X., Cui, Y., Zi, J., He, L., Deng, S., Cao, Y., & Chen, Z. (2026). Adaptive Bi-Level Planning of Photovoltaic Hosting Capacity for Hydro-Dominant Distribution Grids Considering Hydraulic Safety Constraints. Symmetry, 18(7), 1079. https://doi.org/10.3390/sym18071079

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Article metric data becomes available approximately 24 hours after publication online.
Back to TopTop