1. Introduction
One of the most significant environmental challenges of the 21st century is the increase in GreenHouse Gas (GHG) emissions. The presence of greenhouse gases is necessary to balance energy on the earth, as they absorb the outgoing infrared radiation and ensure that the earth is at a habitable average temperature. In their absence, the average temperature of the surface of the Earth would be about 33 °C colder, making the planet inhospitable to life. Nevertheless, anthropogenic activities such as deforestation; industrial manufacturing such as power generation, cement production, and steel manufacturing; urbanization; and especially burning of fossil fuels have significantly raised the concentrations of atmospheric GHGs above their natural fluctuation and affected the carbon cycle balance, causing the greenhouse effect [
1].
Among these gases, carbon dioxide (CO
2) is the most dominant, contributing about 73–76% of the global GHG emissions in CO
2 equivalent terms, and it remains the primary target for climate mitigation efforts [
2]. The steel industry is classified as a hard-to-abate sector and alone emitted approximately 2.6 Gt of CO
2 in 2020 [
3], equivalent to 7–9% [
3] of global energy-related CO
2 emissions, with blast furnace–basic oxygen furnace (BF-BOF) systems representing the most carbon-intensive pathway.
Among all the mitigation options in this sector, carbon-capture, utilization, and storage (CCUS) is considered the most mature and directly relevant technology for the current industrial plants, as it can be integrated with existing BF-BOF facilities without requiring a complete overhaul of infrastructure [
4]. Within CCUS technologies, solvent-based post-combustion capture has emerged as the most practical near-term method for flue gas treatment [
5].
A wide range of alternative solvents, including advanced amines [
6], ammonia-based systems, and novel physical or hybrid solvents [
7], have been proposed to address the limitations of conventional amines. However, monoethanolamine (MEA) remains the mostly employed solvent for industrial CO
2 capture due to its ability to capture CO
2 at low partial pressures, extensive operational experience, well-established thermodynamic and kinetic models, and the availability of validated cost data at an industrial scale. Despite drawbacks such as solvent degradation in the oxidizing environment of flue gas, corrosion, and a relatively high regeneration energy demand, MEA continues to serve as the reference technology for evaluating emerging solvents, particularly in retrofit applications within energy-intensive industries, such as steelmaking [
6].
Numerous studies have investigated the application of carbon-capture, utilization, and storage (CCUS) technologies in steel production processes, including solvent-based post-combustion capture, hybrid capture configurations, and membrane-based systems integrated with blast furnace–basic oxygen furnace (BF–BOF) routes [
4,
8,
9,
10,
11,
12,
13]. These investigations approach the subject from diverse and often complementary perspectives. Comprehensive reviews in terms of economic cost, efficiency, and volume of CO
2 captured have examined the technical integration of the carbon-capture technologies within BF–BOF steelmaking and have identified key challenges and opportunities for large-scale implementation [
4,
5]. Systematic techno-economic assessments have evaluated the feasibility of CCS in hard-to-abate industrial sectors, such as iron and steel production, highlighting the roles of capture efficiency, energy penalties, and carbon pricing in project viability [
10,
11]. Additional research has addressed alternative capture technologies, including polymeric membrane separation for blast furnace gas treatment [
8], and the development of novel absorbents tailored for CO
2 capture from steelmaking off-gases [
9].
Previous techno-economic assessments of CCUS integration in steelmaking [
10,
11,
14,
15,
16,
17] have provided insights into the feasibility of MEA-based post-combustion capture systems integrated with BF–BOF routes. However, these studies typically consider capture efficiencies close to 90%, which may no longer be sufficient to achieve deep decarbonization in the steelmaking sector. Consequently, the combined impact of pushing capture efficiencies beyond conventional targets and systematically optimizing key operating parameters remains insufficiently explored, particularly in the context of existing steel plants since the recent European climate policies, including the progressive tightening of the EU Emissions Trading System (EU ETS) and long-term Net Zero objectives [
2], and is driving the need for substantially higher CO
2 abatement levels in existing industrial plants.
As a result, higher capture levels, particularly those targeting 95% CO2 removal and their associated energy and economic implications, are becoming of interest for future industrial deployment, but there are few studies on them. Therefore, this study simulates and optimizes a 95% CO2 capture efficiency and conducts a comparative business plan analysis for both 90% and 95% CO2 removal scenarios.
This process is simulated by using the Aspen Plus
® software (Bedford, MA 01730, USA) for representing the absorber+regeneration system. Furthermore, a techno-economic evaluation was integrated to enable an assessment of the economic feasibility of achieving high-capture performance in the steel plant applications and in storage in a saline aquifer, according to the block flow scheme reported in
Figure 1.
2. Materials and Methods
2.1. Process Scheme
The design of the CO
2 capture process was carried out using Aspen Plus
® V11 as the simulation environment to model an absorption-regeneration system using a 30 wt.% aqueous monoethanolamine (MEA) solution to treat a blast furnace gas (BFG) stream from an integrated steel plant that could be incorporated with CCUS technology. The captured CO
2 is assumed to be transported to a geological storage site in the Adriatic Sea near Ravenna, where a national-scale carbon-capture and storage (CCS) hub is under development [
17]. As the industrial facility under consideration is assumed to be located within the Milan metropolitan area, CO
2 is already present at the urban node of the regional transport network, eliminating the need for intermediate transport modes such as rail. The entire transfer from the steel plant to the injection site is therefore carried out via a dedicated long-distance pipeline, estimated to span approximately 300 km. This configuration constitutes a realistic infrastructure pathway for emitters in Lombardy, the highest industrialized region in Italy, given the absence of suitable local storage formations and the consequent necessity for cross-regional CO
2 transport.
The gaseous stream to be treated is characterized by a flow rate equal to 740.08 t/h, T = 305.15 K, P = 1.05 bar, composition = 21.59 mol% CO
2, 46.51 mol% N
2, 4.2 mol% H
2O [
18], and with no MEA in that feed stream.
The ENRTL-RK model was selected as a thermodynamic property for the MEA-CO
2-H
2O system, where the Electrolyte- Non-Random Two-Liquid (NRTL) model [
19,
20,
21,
22] represented the non-ideal liquid phase behavior arising from chemical reactions and including the presence of charged species (H
3O
+, OH
−, CO
3−2, MEACOO
−, MEAH
+, and HCO
3−), and the Perturbed-Chain Statistical Associating Fluid Theory (PC-SAFT) equation of state [
23,
24,
25,
26,
27,
28] was employed to model the vapor phase with improved accuracy for the systems containing polar compounds, as well as giving a realistic picture of how chain hydrocarbon molecules behave in a solution. The ENRTL–RK combined with PC-SAFT formulation has been applied and validated for reactive amine-based CO
2 capture systems as indicated by AspenTech™, offering a reliable description of vapor–liquid equilibrium, speciation, and thermophysical properties over a wide range of operating conditions.
Figure 2 illustrates the process flow diagram of a steel plant for an MEA-based capture system to achieve 95% CO
2 removal. Both the absorber and the regenerator were modeled as rate-based units, with the integration of thermodynamics, chemical kinetics, and the transport phenomena, which all represent the system in a close approximation to reality. Other equipment, including a process–process heat exchanger, condenser, pumps, and washing section, was incorporated into the system for thermal integration and to minimize the MEA loss through evaporation.
The base case was adopted from the work of Schiattarella and Moioli [
28]; however, the total flow rate of the lean solvent was adjusted to achieve the target CO
2 removal level, serving as the starting point for the designing the optimized process for 95% CO
2 removal. This process begins with the chemical absorption of the CO
2 in the BFG stream by the lean MEA solution introduced at the top of the absorber counter, currently resulting in a rich solvent stream. The rich solvent stream is then pumped to a heat exchanger to raise its temperature and facilitate the desorption process. The regenerated lean solvent stream is then cooled and recycled back to the absorber, while the main CO
2 product stream is obtained from the top through a thermal decomposition reaction driven by the reboiler heat duty in the regeneration column.
A water-wash section is installed at the top of the absorber to minimize the solvent losses and prevent amine carryover into the cleaned gas. This wash section is designed as a packed column in which the demineralized water is used to capture the entrained MEA droplets and ensure the treated flue gas meets the environmental discharge limits while maintaining the overall solvent economy by maximizing the solvent recovery, thereby reducing the solvent makeup cost.
In the present simulation, the washing water is introduced at a temperature of 298.15 K and with a pure-water composition, consistent with common industrial practice for amine-based CO2 capture systems.
2.2. Parameter Selection and Optimization Approach
The optimization process aimed to determine the operating and design conditions that achieve the required 95% CO2 capture efficiency while minimizing the total energy required for the regeneration process.
The first stage of this process focused on the absorber, as its dimensions and operating conditions strongly influence CO2 capture efficiency, solvent circulation rate, and overall energy consumption.
Seven absorber heights were tested (10, 12, 16, 18, 20, and 22 m), each simulated across a range of lean loadings between 0.11 and 0.27 mol CO2/mol MEA, in detail:
from 0.11 to 0.23 [mol CO2/mol MEA] for packing heights of 22 and 20 [m]
from 0.11 to 0.21 [mol CO2/mol MEA] for packing heights of 18 and 16 [m]
from 0.11 to 0.17 [mol CO2/mol MEA] for a packing height of 12 [m]
for only 0.11 [mol CO2/mol MEA] for a packing height of 10 [m].
The 14 m was skipped because the simulation was conducted by considering 10, 16, and 22 m, which means every 6 m of height, then focused on 18 and 20 m to better define the optimal one, but 12 m was only for better understanding the results at shorter heights.
The column diameter was determined for each absorber height and operating conditions based on hydraulic constraints, considering gas and liquid flow rates, packing characteristics, and flooding limits. For this reason, the diameter was not treated as an independent optimization variable but rather as an internally consistent design outcome of the rate-based model.
Once the optimal absorber packing height and lean loading were adjusted, the second stage targeted the regenerator since it is the major energy consumer in the process. The regenerator packing height varied from 6 to 20 m, and the optimal height was determined by balancing the stripper performance and energy consumption.
After that, the regenerator operating pressure was adjusted over the range of 0.6 to 2.5 bar, since regenerator pressure affects the equilibrium temperature and the CO2 partial pressure, ending by varying the lean solvent inlet temperature from 30 to 50 °C.
2.3. Cost Estimation
2.3.1. CO2 Removal
The economic evaluation quantifies how optimized operating conditions affect the capital and operating costs of the MEA-based CO
2 capture process. The methodology is based on recent CCUS techno-economic studies of Moioli et al. [
14] related to the application of a CCS or a CCU section in a WtE plant, with adaptations reflecting the characteristics of an integrated steel plant in Lombardy.
The cost estimation considered 7900 annual operating hours, and all costs are expressed in US dollars. This assessment included all the major units in this process: absorber, regeneration column, condenser, reboiler, process–process heat exchanger, lean–rich heat exchanger, and pumps, and these units were dimensioned using the optimized simulation outputs.
The capital cost estimation was performed according to the method of Guthrie (1974), Ulrich (1984), and Navarrete (1995), which includes the purchased cost and bare module equipment cost.
The purchased cost of a given piece of equipment is calculated based on the previously purchased cost of the same unit, as expressed in Equation (1). The cost of each equipment item was updated using the Chemical Engineering Plant Cost Index (CEPCI).
where
is the known equipment cost at the reference year,
is the adjusted cost for the concerned year, and
and
are the cost indices associated with the respective years. By applying the most recent available CEPCI values at the time of the assessment (June 2024), the equipment cost is updated for the current economic evaluation.
While the Bare Module Cost represents the sum of direct and indirect costs [
29] to convert the basic purchase cost of the equipment into a more realistic estimate:
where
is the purchased cost for base conditions, equipment made of the most common material (carbon steel), and operating at near-ambient pressures,
is the bare module cost factor,
is the pressure factor,
is the material factor, and
and
are coefficients associated with the specific equipment category.
Given the corrosive nature of amine solvents and the fact that the stripper and associated equipment operate at pressures above atmospheric, stainless steel is typically used as the material of construction. Its high resistance to chemical attack and its ability to withstand elevated pressures ensure the reliable and safe operation of CO2 capture units.
The costs of the purchased equipment were estimated using the following formula:
where
is the relevant size parameter (e.g., area, volume), and
,
, and
are correlation constants specified for each equipment type and the economic evaluation year.
To apply these correlations, the necessary cost constants, material factors, and pressure-correction parameters are reported in
Table 1,
Table 2 and
Table 3 corresponding to the equipment classes relevant to this CO
2 capture process. These values allow direct computation of the purchased cost, bare module cost, and the overall total module cost.
The total module cost (CTM) was determined by adding a 15% contingency allowance to the sum of all bare module costs. Additionally, a further 3% of CTM was included to cover permitting and authorization expenses, which include environmental evaluations and regulatory approvals necessary for the installation of a CO2 capture system at this industrial steel facility in Lombardy.
Operating costs (cost of manufacturing, COM) include labor, utilities, and raw materials costs, and these were calculated according to the procedure adapted from Turton et al. [
29], with adjustments introduced to reflect the specific operating conditions and utility costs typical of steelmaking plants in the Milan region. The cost of the solvent was 6.02
$/L [
30] while the demi-water was based on the value of Moioli et al. [
31].
2.3.2. CO2 Sequestration in Saline Aquifer
To estimate the economic impact of the downstream stages illustrated in
Figure 2, this study utilizes the cost correlations and methodological framework established by Stolaroff et al. [
32] for dehydration and compression, for transport by pipelines and for sequestration in saline aquifers.
The literature provides reference values for CO
2 transport under various conditions. For instance, Geo et al. [
33] reported transport costs of approximately 13
$/tCO
2 for a long-distance (600 km) rail scenario, including additional charges for loading operations. Roussanaly et al. [
15] identified transport costs ranging from 4 to 11 €/tCO
2 for pipeline routes between 50 and 200 km, with about 1 €/tCO
2 attributed to terminal handling. Building on these analyses, Stolaroff et al. [
32] included an additional 2
$/tCO
2 to account for the rail transport cost. Reported upper-bound values for extended pipeline corridors reach approximately 24
$/tCO
2.
2.4. Business Plan
A techno-economic business plan was developed to assess the financial feasibility of installing a post-combustion MEA-based CO2 capture unit at the Lombardy steel plant, along with geologic injection of the captured CO2 into the Ravenna saline aquifer.
The business analysis combines capital expenditure (CAPEX) and operational expenditure (OPEX) from
Section 2.3 to evaluate overall project profitability under selected policy and market assumptions.
Economic performance is assessed using net present value (NPV), calculated with a weighted average cost of capital (WACC) consistent with recent industrial energy investment analyses. A WACC of 8.3% is assumed, following the methodology already applied in other Italian industrial decarbonization studies [
34].
The calculation model includes the following annual cost and revenue components:
investment cost of the capture plant, distributed over the project lifetime
operating costs of the CO2 capture plant
mass flow rate of CO2 removed from the BF gas
electricity consumption of the CO2 capture and compression systems, based on the average industrial power cost in Northern Italy
transport and injection cost of CO2 into the Ravenna saline aquifer
the value (or absence) of the EU ETS carbon price, depending on the scenario considered.
For geological storage, the economic impact of CO
2 sequestration was considered a negative overall revenue. This cost was estimated using the literature values for CO
2 injection into saline aquifers, as detailed in
Section 2.3.1.
Accordingly, the total annual revenues of the project were defined as the sum of two main contributions:
- i.
The economic balance associated with CO2 sequestration, which is negative due to transport and injection costs.
- ii.
The financial benefit arising from avoided CO2 emissions through the allocation of EU ETS certificates. That term is inherently positive, as it reflects the reduction in CO2 emissions released into the atmosphere.
The financial assessment was carried out considering the applicable Italian fiscal framework for industrial facilities located in Lombardy. In particular, the Regional Tax on Productive Activities (Imposta Regionale sulle Attività Produttive, IRAP), equal to 3.9%, and the Corporate Income Tax (Imposta sui Redditi delle Società, IRES), equal to 24%, were applied consistently across all scenarios.
The business plan model calculates the main economic indicators required to evaluate project profitability, including the NPV, while accounting for inflation effects, operating costs, and the impact of ETS-related revenues associated with avoided CO2 emissions. A range of ETS carbon price levels was considered, spanning from 20 to 100 USD per tonne of CO2, with values escalated annually according to the assumed inflation rate. In scenarios where the CO2 sequestration option resulted in a negative NPV, the corresponding breakeven carbon price was also determined in order to identify the minimum ETS value required to achieve economic viability.
To explore the influence of policy conditions on project feasibility, the following scenarios were examined:
Carbon tax (ETS price applied), without CO2 storage.
Absence of carbon tax (ETS price equal to zero), without CO2 storage.
Carbon tax applied, with CO2 transported via pipeline and injected into the Ravenna storage site.
Absence of carbon tax, with CO2 injection into the Ravenna saline aquifer.
The influence of inflation was also considered.
This combined scenario-based and sensitivity-based assessment provides a comprehensive view of the potential financial outcomes of integrating CO2 capture and geological storage at a steel plant under both favorable and constrained policy conditions.
4. Conclusions
In this work, the post-combustion MEA-based CO2 capture process applied to a blast furnace gas stream from a steel plant was optimized to achieve a high capture efficiency of 95%. Process simulations were carried out using Aspen Plus®, focusing on key design and operating variables that strongly influence both the separation performance and the energy demand.
The optimized process configuration was translated into economic terms through a detailed techno-economic assessment, updated using recent CEPCI values, and aligned with European conditions. Compared to a 90% capture scenario, achieving 95% CO2 removal resulted in moderate increases in CAPEX and OPEX. The resulting cost of removed CO2 confirms that high capture efficiencies are technically feasible and economically meaningful for the steel sector, particularly under scenarios that include carbon pricing mechanisms.
A dedicated business plan framework was implemented to quantify the economic performance of the proposed CO2 capture system through the calculation of the Net Present Value (NPV). The analysis explicitly accounts for different policy and market conditions, including the potential application of the EU Emissions Trading System (ETS), as well as the presence of costs or limited revenues associated with CO2 geological storage. By integrating capital and operating expenditures with policy-driven economic factors, the model enables consistent evaluation of the overall project feasibility.
The results clearly highlight the dominant role of the carbon price in determining the economic viability of the system. The project economics are strongly dependent on the ETS value, which represents the primary positive contribution to the cash flow. Under these conditions, a breakeven ETS price was identified, corresponding to the threshold at which the project NPV becomes zero. This outcome confirms that carbon pricing mechanisms are a critical enabler for the deployment of CO2 capture and storage solutions in the steel industry. The breakeven carbon prices (>216 USD/tCO2) exceed the current EU ETS price (65 EUR/tCO2 in 2024), which should facilitate the deployment of high-efficiency carbon-capture technologies.
This techno-economic evaluation relies on assumptions regarding energy prices, solvent costs, and carbon pricing, all of which are subject to significant uncertainty and regional variability. In addition, solvent degradation was accounted for through make-up costs, though a detailed kinetic modeling of MEA degradation and its long-term impact on process performance was beyond the scope of this study. Future research should therefore investigate the sensitivity of the results to energy market fluctuations, and degradation mechanisms, and extend the analysis to alternative capture technologies, for instance with innovative solvents, and to integration strategies for deep decarbonization of steelmaking processes.