5.1. Load Shifting First, Export Second
The most robust result of the application is structural, rather than numerical: of the 11.3 kVA of flexibility value that enrolment brings to the peak (Equation (18)), more than nine tenths come from the vehicle not charging and less than one tenth from the vehicle discharging, because the energy the vehicle can spare, not the charger, limits sustained export to about 2.3 kW over a four-and-a-half-hour peak (
Section 3.4). The rank-correlation analysis of
Section 4.6 says the same thing from the other side: none of the parameters that govern export, whether the location shares, the plug-in rates, the charger rating, the usable margin, or the efficiency, has a measurable influence on the regional result, whereas the participation rate and the fleet size explain almost all of its variance.
Two consequences follow. The first concerns programme design. For a distribution network whose constraint is the coincident evening and late-morning peak, the priority is to enrol vehicles in managed charging; bidirectional capability adds value, but it is a second-order increment whose cost, still several thousand euros per unit at the time of the largest domestic trial [
17], must be justified by services other than peak relief, such as tariff arbitrage, frequency response, or building self-consumption.
Table 6 puts a figure on the increment: with export removed altogether, the 2028 regional shortfall probability rises by five percentage points and the expected 2030 deficit by about 13,000 kVA, or 5%. For peak relief alone, therefore, an operator has no case for financing bidirectional hardware; the case rests on the other services, on the larger batteries and shorter peaks discussed below, and on the observation that a bidirectional contract raises the plug-in rate of enrolled vehicles [
17], which benefits managed charging as well. This is consistent with the observation that participants value operational flexibility and recurring payments in managed charging and monetary compensation in V2G [
21]. The second consequence concerns measurement. If a distribution operator or a municipality wishes to reduce the uncertainty of an assessment of this kind, the parameters worth measuring first are the enrolment rate and the fleet trajectory; refining the estimates of vehicle location and plug-in behaviour, however interesting in themselves, would not change the answer.
This ordering may weaken as batteries grow: the sustained export of a 75 kWh vehicle would be about 3.5 kW, rather than 2.3 kW, but
Section 4.6 shows that at 65 kWh the regional shortfall probability moves by about one percentage point, and the export term would remain a third of the load-shifting term.
5.2. Municipal Heterogeneity and Reinforcement Planning
The earlier study found that the aggregate result concealed municipalities in very different positions, and the present one confirms it in terms of participation rates. In 2030, a 20% participation rate is sufficient with high probability in the Ave municipalities whose substations have the largest headroom relative to their fleet, is marginal in an intermediate group, and is insufficient in the Sousa and Tâmega municipalities that were already critical from 2026 in the earlier study. No municipality has a break-even rate above one, so the fleet is, in principle, large enough to neutralise its own peak everywhere; but the rates required in the critical cluster, between a third and a half of the fleet, are three to five times the enrolment observed in real programmes.
The deferral metric of Equation (20) translates this into planning terms. Under the planning bound, bidirectional flexibility at the participation rates supported by current evidence buys one year in eleven municipalities and none in the other nine; under the expected case, one year in thirteen. That is not negligible for an operator sequencing investments across the twenty municipalities, but it is not a substitute for reinforcement in the critical cluster, where the first critical year remains 2026 or 2027, under the planning bound. The stationary-storage bound of
Table 7, about 790 MWh to close the residual 2030 gap at a 20% participation rate under worst-case simultaneity, makes the same point in a different unit: second-life batteries in buildings can contribute, but a volume equivalent to some fifteen thousand vehicle batteries is not a near-term option for a region of this size.
Table 10 translates the results into recommended actions by municipality cluster, with the quantities from
Section 4.5 and
Section 4.7 that justify them. The clusters are defined by the 2030 median break-even rate under the planning bound and by the shortfall probability with flexibility under the expected case. Marco de Canaveses and Vila Nova de Famalicão, which
Section 4.5 grouped with the critical municipalities on the planning-bound criterion alone, are placed in the intermediate group here because their expected-case shortfall probabilities (7% and 9%) are close to the tolerance, and their break-even rates lie at the boundary between the two groups.
A full cost comparison between flexibility and reinforcement is outside the scope of the study, because reinforcement costs are specific to the assets of each municipality and are held by the operator. An order of magnitude for the flexibility side can, however, be given from the evidence used to calibrate the participation rate. The managed-charging programme validated in [
21] reached 10% enrolment with a payment of USD 40 per month; at that rate, enrolling 20% of the scenario-3 regional fleet in 2030 (about 23,000 vehicles) would cost of the order of EUR 10 million per year in participant payments, before hardware. Whether that compares favourably with reinforcement depends on the deferral it buys: one year in most municipalities under either coincidence case, and avoidance of reinforcement altogether in the Ave and intermediate groups under the expected case. The comparison is, therefore, favourable where the network is close to its limits and unfavourable where it is far beyond them, which is the pattern of
Table 10, and it should be carried out municipality by municipality, with the operator’s own reinforcement costs.
5.5. Implications for Actors
For the distribution operator, the framework offers three things that the earlier study did not: a break-even participation rate per municipality and year, which can be compared with enrolment as it is observed; a deferral metric in years, which can be entered directly into an investment sequence; and an ordering of the uncertainties, which says where measurement effort pays. The update rule of Equation (25) turns the first of these into a monitoring instrument: as enrolment and plug-in telemetry accumulate, the priors of
Table 2 are replaced, and the break-even tables are regenerated without changing the model.
For aggregators and energy suppliers, the results indicate that the product with the largest network value in a constrained region is managed charging with an availability commitment, and that bidirectional capability should be marketed on other value streams. The plug-in rate of enrolled vehicles, which trials show to be raised substantially by a contract [
17], is the behavioural variable most directly under their influence.
For building owners and employers, the V2B channel is currently small because bidirectional workplace charging is rare, not because vehicles are absent from buildings during the peak; the location shares of
Table 2 place a quarter of the fleet at buildings during the peak blocks. The cap of Equation (11) never binds at present rates, which means that the non-residential load of every municipality could absorb far more vehicle export than is available. Workplace bidirectional charging, coupled with building photovoltaics, is therefore the channel with the largest unexploited headroom, and the corporate composition of the fleet makes it accessible.
For the regulator, two settings determine how much of the flexibility described here can be realised: the definition of the tariff periods, which fixes
and the interpretation of the location shares, and the treatment of export from vehicles and buildings, which determines whether the cap of Equation (11) applies. The framework makes both explicit, so that their effect can be quantified [
51,
54].
5.6. Limitations and Further Work
The limitations of the framework fall into four groups. The first is inherited from the earlier study, and was discussed there: the representative vehicle is a composite of three models whose market shares have changed; the daily energy need is derived from two representative routes; the regional fleet is allocated by population share, which ignores differences in purchasing power and in the spatial distribution of corporate fleets; and the network is described by an apparent-power balance per municipality, without power flow. The last point deserves emphasis in the present context: bidirectional export at low voltage raises voltage-rise and protection questions that a kVA balance cannot see, and the different building types of the consumer substations (pole-mounted, high-cabin and low-cabin stations) will respond differently to reverse flows. The results of
Section 4 should, accordingly, be read as an upper bound on usable flexibility (
Section 3.7), not as a demonstration that the credited load shifting and export are admissible on every feeder. A power-flow study on representative feeders of each substation type, of the kind performed with tools such as OpenDSS in the hosting-capacity literature [
12,
13,
15], is the natural next step; it requires feeder topologies, conductor data and phase allocations that are held by the operator and were not available for this study, and it is the layer in which the modest reverse injections quantified in
Section 3.7 would be checked against voltage-rise, protection and unbalance limits. The intra-municipal allocation of
Section 3.2 belongs to the same group;
Section 4.6 shows its effect to be below 10 kVA in any municipality.
The second group concerns the temporal resolution. Two tariff periods are coarse. The peak is modelled as a single block of four to five hours with time-weighted location shares, whereas, in reality, the morning and evening blocks have different fleet locations, different building loads and different export potential. An hourly formulation would change little in the structure of Equations (16)–(20), but would allow the V2B and V2G channels to be separated by block, which is where the corporate-fleet question of
Section 5.4 would be resolved.
The third group concerns the behavioural parameters. The priors of
Table 2 are drawn from trials and surveys in the United Kingdom, the United States, the Netherlands and other European markets; no Portuguese trial of bidirectional charging with published enrolment or availability figures was found, and the mobility survey used to support the location model covers the Porto metropolitan area, rather than the study region. The rank-correlation analysis shows that most of these parameters do not affect the result, which limits the damage; but the participation rate does, and a stated-preference study of BEV owners and fleet managers in the region, distinguishing private from corporate vehicles, would be the most valuable single piece of new evidence. The authors intend to pursue this. The participation rate is also held constant across years in the headline case; the ramp sensitivity shows that the mid-decade benefit depends on how fast enrolment builds, which is itself a question for such a study. Three considerations bound the consequences of transferring priors from other markets. The location shares and plug-in rates, which are the parameters most likely to differ between markets, have rank correlations with the result below 0.07 in absolute value, so an error of the size of the difference between markets would not change the conclusions. The participation rate, which does matter, is drawn from a range whose lower end is the intrinsic enrolment measured among United States owners and whose upper end exceeds the enrolment reached with payment in the programme that validated that measure [
21], so that the Portuguese value is more likely to lie within the range than outside it, and the corporate composition of the Portuguese fleet argues, if anything, for a higher value (
Section 4.8). The update rule of Equation (25) is the mechanism by which these priors are replaced by local telemetry as it accumulates, without altering the model. What the transfer cannot guarantee is the shape of the distributions within their ranges, and the shortfall probabilities of
Section 4 should be read with that qualification.
The two-segment model of
Section 4.8 is a first approximation: the corporate share of the fleet, the corporate participation rate, and the corporate location profile are all drawn from assumed ranges, rather than observed ones, and a corporate fleet is not homogeneous, since pool vehicles, assigned company cars and light commercial vehicles behave differently.
The fourth group concerns what is outside the model: prices and markets, battery degradation costs, plug-in hybrids, public fast charging, and the regulatory status of vehicle and building export in Portugal. Public fast charging deserves a specific note. The model assigns every vehicle a home charging point, as the earlier study did; vehicles that charge mainly at public fast chargers do not add to the coincident residential load and are absent from the bidirectional pool, so their omission is conservative for the peak balance of the municipalities, but overstates the fleet available for flexibility, and a growing fast-charging network shifts load from the low-voltage feeders modelled here to medium-voltage connections that are outside the scope of the study. None of these changes the network balance, but all of them condition the participation rate, and a fuller treatment would model as an outcome of contract design, rather than as an exogenous distribution.
Battery degradation deserves a specific note, because it is the cost most often cited by owners who decline to enrol [
24,
25], and the model does not price it. Its order of magnitude follows from the export quantities of
Section 4.3. An enrolled vehicle exports about 10.4 kWh on each peak in which it is plugged in and, at the plug-in and location rates of
Table 2a, does so on about two fifths of the roughly 250 working days of a year, some 1100 kWh per year. With a pack cost of EUR 120 per kWh and a cycle life of 2000 equivalent full cycles, illustrative values for current lithium-ion packs, the wear cost of that throughput is about EUR 0.06 per kWh, or EUR 65 per vehicle and year, against the USD 480 per year that secured 10% enrolment in the programme used to calibrate the participation rate [
21]. Two implications follow. Priced explicitly, degradation would reduce the net compensation of an enrolled owner by roughly one seventh and, within a discrete-choice model of enrolment such as that of [
21], would lower the participation rate accordingly; the priors of
Table 2a are drawn from observed enrolment, rather than from stated intentions, and therefore already embody the owners’ own, and usually larger, perception of that cost. And because more than nine tenths of the flexibility value comes from not charging, which adds no cycling, the result for a fleet that shifts its charging but declines to export is bounded by the managed-charging-only row of
Table 6. A participation model in which the rate responds to compensation net of degradation is the natural extension, and belongs to the stated-preference study proposed above.
Against these limitations stands the property that motivated the study: the framework runs on a network description of the kind that most distribution operators hold on public fleet statistics, and on literature priors, and it reproduces the deterministic model it extends as a special case. It can be replicated in any region with the equivalent of Table A1 of the earlier study, and its outputs improve as local telemetry is fed into Equation (25).