1. Introduction and Background
Steel reinforcement bar (RFT) is the primary structural material in reinforced concrete building construction, and its price is the most volatile of the major structural cost components faced by building contractors during project planning [
1,
2]. As the dominant material in building frames—from low-rise residential to high-rise commercial and institutional projects—RFT price volatility directly affects contractor cost estimates, tendering margins, and project profitability. In Egyptian building construction, RFT typically represents 12–20% of the total structural budget, making accurate price forecasting critical to bid preparation accuracy and post-contract cost control.
Egypt’s building construction sector is the third-largest employer in the national economy, comprising 13.5% of the total workforce (CAPMAS). When intersectoral linkages are included, this figure rises substantially [
3]. The sector grew by 336% in output between 2016 and 2023 (from EGP 96 billion to EGP 323 billion), yet persistent cost overruns—driven primarily by building material price fluctuations—have reduced investor confidence and damaged contractor cash flows [
4,
5,
6,
7,
8].
Building materials, as traded commodities, are priced through the interaction of demand and supply, although in the Egyptian steel sector this interaction operates under imperfectly competitive conditions: production is concentrated among a small number of large producers, and demand is heavily influenced by state-led megaprojects. The macroeconomic drivers of demand and supply nevertheless remain the fundamental determinants of price movement over time, even where market structure moderates the speed and symmetry of their transmission. According to Brockmann [
9], demand and supply for a commodity depend on the identity of its buyers and sellers. In the building construction sector, the buyers of structural materials are contractors and developers. The factors influencing demand arise from how much they are willing to invest, depending on capital availability and the money lending rate. The factors influencing supply emerge from the inclination to invest in building production—driven by inflation rates, unemployment, producer price index (PPI), and currency exchange rate.
Esam and Ehab [
3] described the interactions linking the building construction sector with other economic sectors, which make it inherently sensitive to macroeconomic and geopolitical events. Geopolitical shocks—including the Russia–Ukraine war, the COVID-19 pandemic, and regional Middle East conflicts—disrupted international trade flows and restricted access to imported construction materials. Building materials supply was severely constrained by the shortage of foreign currency [
9]. As a result, the building materials market reflected the same macroeconomic instability and suffered an unavoidable imbalance in its supply and demand equilibrium [
10]. Price volatility in structural materials is widely cited as a primary driver of building cost overruns in emerging markets [
1,
2,
11,
12].
In such an unstable environment, naïve estimation methods and experience-based judgment cannot reduce forecast uncertainty in building cost planning sufficiently to support reliable procurement decisions. Different statistical methods—including dynamic regression, causal analysis, trend analysis, and correlation—have been applied to construction cost indices in the literature [
13]. This study adopts multivariate time series analysis, incorporating the ARDL model to accommodate both short-term price shocks and long-run equilibrium relationships, which is particularly appropriate for the mixed-stationarity data characteristics of Egyptian economic series.
Despite extensive literature on construction material price forecasting, three critical gaps remain. First, no published study has applied an ARDL cointegration framework to building material prices in the Egyptian market. Second, no prior Egyptian study incorporates global equity market indices (S&P500 and HSI) as leading indicators. This omission is theoretically consequential: the commodity financialization literature documents that, since the mid-2000s, commodity prices have become increasingly correlated with financial market conditions, as index investment and cross-market capital flows transmit financial shocks into physical commodity markets [
14,
15]. Prior Egyptian models, by restricting attention to domestic macroeconomic aggregates, implicitly assumed that steel pricing is insulated from this channel—an assumption difficult to sustain for a market dependent on imported scrap iron priced in international markets. Third, no forecasting framework validated on Egypt’s 2022–2024 period—the most economically volatile episode in the country’s recent history, marked by a depreciation of the Egyptian pound of roughly 50%—has been published.
This study addresses all three gaps by developing and validating an ARDL-based forecasting framework for Egyptian RFT prices, incorporating a structured macroeconomic variable-selection pipeline to identify and validate nine leading price indicators. The framework is designed to produce practical 3-, 6-, and 9-month price forecasts that support budget-setting and procurement decisions at the building project tendering stage.
Literature Review
Price forecasting is essential for cost estimation, resource allocation, and procurement planning in building projects. Many studies explore this area with different approaches [
16,
17,
18]. Two recent reviews published in Buildings provide comprehensive overviews of the field: Ma et al. [
1] surveyed data-driven construction materials price forecasting methods, and Altalhoni and Abudayyeh [
2] reviewed forecasting techniques for construction cost indices, identifying leading indicators and methodological trends from 2014 to 2024. Both reviews confirm that econometric time series methods remain underutilised relative to their potential in volatile emerging markets. Organisations in different countries have developed indices to represent the building industry’s price movements, such as the Construction Cost Index (CCI) and Tender Price Index (TPI) [
19,
20]. The literature followed two paths: identifying key variables influencing price movements and developing forecasting models to predict future price values.
Studies focused on identifying key variables utilised statistics and correlation approaches such as the Spearman coefficient, Pearson coefficient, and hypothesis testing [
12,
19], and others followed an econometric approach, such as Granger causality testing [
21]. Akintoye et al. [
22] applied lead–lag analysis to identify the cyclic correlation between material prices and macroeconomic indicators.
The second category concerns modelling and forecasting construction commodity prices, subcategorised into: traditional statistical analysis, econometric modelling, and non-econometric modelling. The former utilised statistical models such as standard, multiple, and dynamic regression [
13,
23,
24]. Gambo and Ashen [
23] applied regression to model the relationship between the construction cost of a one-square-metre building and macroeconomic indicators. Hwang [
13] used dynamic regression to identify the relationship between the CCI and the Consumer Price Index (CPI). Collectively, these regression-based approaches demonstrate meaningful correlations between macroeconomic indicators and building cost indices, but their assumption of stationary, linear relationships breaks down during structural economic shocks—a critical limitation in volatile emerging building markets.
Artificial Neural Network (ANN) methods have been used intensively to model different aspects of the economy [
18,
25,
26]. Cao et al. [
27] used a hybrid machine learning (ML) approach to capture the relationship between proposed indicators and the CCI of Taiwan. Cheng et al. [
28] applied a hybrid intelligence system integrating Least Squares Support Vector Machine Learning (LS-SVM) and Differential Evolution (DE) to identify CCI patterns. Mir et al. [
29] proposed an interval forecasting approach for building material prices using ANN. Shiha et al. [
30] developed ANN models to forecast RFT and Portland cement prices in Egypt using macroeconomic leading indicators, reporting MAPE values of 4–11% on a pre-2020 dataset. ANN and hybrid models consistently outperform regression in stable markets [
27,
28], but require large training datasets and offer limited interpretability—a practical barrier for building cost consultants who need to explain forecasts to clients.
Time series analysis, with single or multiple variables, has become popular in many fields [
31]. ARIMA is a univariate model that reflects a single series on its historical data. The vector autoregressive (VAR) model, a multivariate model, explores a set of simultaneously recorded variables. Hwang [
17] tested the applicability of both univariate and multivariate time series models to forecast the US CCI. Jiang et al. [
16] extended the multivariate analysis to include macroeconomic indicators as independent variables with the PPI as the dependent variable. Xu and Moon [
10] developed a cointegrated Vector Error Correction Model (VECM) to analyse the US CCI.
Regression models suffer from several problems, such as the linear assumption, stationarity requirements, and coefficient biases. ANN, ML, and hybrid models require large samples. The VECM mitigated certain limitations of ANN, making it feasible to work with smaller datasets. However, VECM models require all series to be integrated of the same order—a requirement that breaks down with the mixed I(0)/I(1) data common in emerging economies—making the ARDL bounds testing approach the most suitable established method for handling this characteristic without additional transformation.
2. Materials and Methods
The research follows a two-stage multi-step framework (
Figure 1). The first stage filters available macroeconomic variables to extract those with significant predictive power for building material prices. The second stage analyses the selected variables to model and forecast RFT prices using the ARDL framework. Each stage comprises three sub-processes, described in the subsections below.
The first-stage sub-processes are: (i) literature survey and data collection—candidate macroeconomic indicators are identified from the literature and collected from official Egyptian sources; (ii) data preprocessing—raw data are log-transformed to stabilise variance and normalise distributions; and (iii) variable filtering—the Augmented Dickey–Fuller (ADF) stationarity test, Variance Inflation Factor (VIF) multicollinearity check, and Granger causality test are applied sequentially to reduce the candidate set to statistically significant predictors.
The second-stage sub-processes are: (i) ARDL model specification—bounds testing is used to confirm cointegration and identify the optimal look-back period (LBP); (ii) model diagnostics—stability, linearity, homoscedasticity, and serial correlation tests validate model soundness; and (iii) forecasting evaluation—both in-sample and out-of-sample accuracy metrics assess model performance against OLS and VAR baselines.
An AI language assistance tool was used for copy-editing improvements to phrasing and structure in the preparation of this manuscript. All research content, analysis, results, and conclusions were generated by the authors.
2.1. Data Collection
Steel reinforcement bar is the most price-volatile major structural material in building construction and is extensively used in the literature to represent construction sector cost dynamics [
12,
29,
30,
32]. Given its 12–20% share of the structural budget noted earlier, its price is a critical input for building cost estimation and bid preparation. A pool of potential leading indicators from the published literature was selected as eligible for deployment in this prediction framework (
Table 1).
A study period from October 2009 to March 2024 was selected, containing 173 monthly observations. This period encompasses a range of destabilising events—including political unrest, currency devaluations, fuel price escalation, the COVID-19 pandemic, and geopolitical conflicts—making Egypt a representative case study context for investigating macroeconomic impacts on building material prices in an emerging market. The data were divided into training (October 2009–September 2023) and test (October 2023–June 2024) sets.
As presented in
Table 1, various types of independent variables are employed in the literature, including economic variables such as the PPI, stock market, and M0; financial variables like the loan rate (LR) and discount rate (DR); and international variables like ORE and foreign stock market indexes.
Table 2 presents the available variable records in Egyptian databases.
2.2. Data Preprocessing
Applying a logarithmic transformation to the data helps make the distribution more normal by decreasing skewness, which is particularly useful in time series analysis as it stabilises the variance. The natural logarithm narrows the gap in the data range while preserving valuable information.
Table 3 presents the log-transformed ranges and means.
2.3. Stationarity Test (ADF Test)
Stationarity is the property that describes a series with constant statistical properties such as mean and variance. The ARDL model accommodates a mixed order of integration, handling both stationary I(0) and integrated I(1) series. The Augmented Dickey–Fuller (ADF) test was used to investigate the variables’ order of integration. The null hypothesis H0 is that the series contains a unit root (non-stationary); the alternative Ha assumes the series is stationary.
The test was performed in two sequential iterations. The first iteration tested the original series; if non-stationary, it proceeded to the second iteration in which the first difference was tested. If the difference in the series was stationary, it was classified as I(1). No I(2) variable was detected. Two variables showed stationarity in levels: Trade Balance (TB) and S&P500, both of which are I(0), and can be included in the ARDL without violating any modelling conditions as shown in
Table 4.
2.4. Multicollinearity Test
The Variance Inflation Factor (VIF) was adopted to identify multicollinearity in the model. The proposed full model is presented in Equation (1):
As presented in
Table 5, fuel price variables (gasoline 92 and 80) exceeded VIF > 10 and were excluded. Egyptian stock market sub-indices (EGX70, EZZ, EGST) showed interdependence but did not reach multicollinearity levels; they were excluded following the principle of parsimony.
The VIF > 10 exclusion threshold follows the standard econometric rule of thumb; O’Brien [
38] cautions against mechanically applying stricter cutoffs such as VIF > 5, showing that moderate VIF values do not by themselves invalidate coefficient estimates. In this application, the choice of threshold is, in any case, not binding: all retained indicators exhibit VIF < 4 (
Table 5), comfortably below even the stricter standard.
2.5. Granger Causality Test
The Granger causality test was performed on different lags (2, 4, 6, 8, 10, and 12 months) between RFT and the tested variables. When the test statistics are significant at the 5% level, the independent variable at that specific lag is considered to Granger-cause the dependent variable and can be used to predict future RFT prices. Two design decisions in the lag structure warrant explanation. First, the Granger causality screening was performed at even lags (2, 4, …, 12 months) as a horizon-coverage scan rather than a lag-optimisation exercise: its purpose was to establish whether predictive content exists at short, medium, and long horizons, and coarser spacing preserves test power in a finite sample by limiting the number of estimated coefficients per test. Second, the maximum boundary of 12 months is consistent with the lead–lag horizons reported for construction leading indicators [
22,
30] and with the conventional view that monetary and exchange-rate shocks are transmitted to domestic prices within approximately one year. See
Table 6.
The Granger causality test identified nine significant predictors: PPI, exchange rate (ER), loan rate (LR), discount rate (DR), iron ore prices (ORE), Egyptian Stock Market Index (EGX30), American Stock Market Index (S&P500), Hang Seng Index (HSI), and money supply (M0). The filtering pipeline reduced the candidate variable set to these nine predictors (
Table 7).
2.6. Cointegrated Variable Selection
The Granger causality test captured short-term relationships. For long-term relationships, a cointegration test is required. Cointegration describes the case in which two or more time series share a linear combination that moves stably in the long run [
39,
40]. This research utilised the ARDL model, which accommodates a mixed-order integration process aligned with the collected data characteristics. It offers a flexible lag-selection process using different lags for the dependent and independent variables and can accommodate small samples.
A non-linear extension of the framework (NARDL) was considered, in which positive and negative partial-sum decompositions of the regressors allow asymmetric short- and long-run responses [
41]. Three considerations favoured the linear specification. First, the partial-sum decomposition doubles the number of distributed-lag regressors; with 168 training observations and lag orders of up to twelve, the resulting loss of degrees of freedom would be prohibitive for reliable bounds inference. Second, the dominant source of asymmetry in the sample—the discrete 2022 regime shift—is captured directly by the structural break dummy rather than left to be absorbed by asymmetric slope coefficients. Third, the Ramsey RESET results reported in
Section 3.3 fail to reject the null of correct linear specification for all three look-back periods, providing direct statistical evidence that a linear functional form is an acceptable simplification for this dataset. Asymmetric price transmission—in particular the possibility that RFT prices rise faster than they fall—remains a promising avenue for future work.
The look-back period (LBP) was defined as the lag period between the dependent variable RFT and the independent variables. The candidate LBPs of 3, 6, and 9 months were fixed ex ante on practical rather than statistical grounds: they correspond to the quarterly tender-preparation cycle, the semi-annual budget review, and the typical lead time for bulk procurement scheduling in Egyptian building projects. Pre-specifying the forecast horizons in this way, rather than selecting them by searching over neighbouring values, avoids data-snooping in horizon choice; conditional on each LBP, the lag order of every variable was then selected by minimising the Akaike Information Criterion (AIC). During this variable-selection stage, the framework fixes the LBP to 0, the deterministic variable to an unconstrained constant, the dependent variable lags up to 2, and independent variable lags up to 12.
Table 8 shows the stepwise selection results. The combination of PPI, ER, HSI, S&P500, M0, and LR satisfies the cointegrated ARDL requirements. The resulting model-level AIC values are reported alongside the selected model parameters in
Table 9.
2.7. Deterministic Term Selection
The ARDL model distinguishes between three cases for model parameters: with a trend and constant, with only a constant, and without a trend or constant. According to Jiang et al. [
16], the first and third cases are considered impractical for this dataset. This research relied on the case with only a constant in the model.
2.8. Benchmark Models
To contextualise the ARDL’s forecasting performance, two multivariate benchmarks were estimated on the identical training sample (October 2009–September 2023): an OLS regression and a vector autoregression (VAR). Because the dataset combines I(0) and I(1) series (
Table 4), a levels VAR would be spurious and a VECM inadmissible; the VAR was therefore specified in first differences, with the I(0) S&P500 entered in levels. The endogenous system comprised ΔRFT, ΔPPI, ΔER, ΔHSI, S&P500, ΔM0, and ΔLR, with a constant and the 2022M07 structural break dummy as exogenous terms, mirroring the ARDL treatment. All lag-length criteria (FPE, AIC, SC, HQ) unanimously selected an order of one; a VAR(2) was tested under a pre-committed decision rule and rejected, as it failed to improve the residual autocorrelation profile. All inverse roots of the characteristic polynomial lie inside the unit circle (maximum modulus 0.992, attributable to the persistence of the S&P500 series in levels), satisfying the stability condition. Dynamic out-of-sample forecasts of ΔRFT were cumulated from the September 2023 log-level to reconstruct level forecasts over the test window.
4. Discussion
The ARDL model developed in this study demonstrated strong forecasting capability for Egyptian RFT prices, outperforming the OLS baseline at the 3-month horizon that matters most for tender preparation. The out-of-sample errors must be interpreted relative to building cost management practice rather than as an abstract statistical benchmark. In Egyptian building construction, contingency allowances for structural materials typically range from 10–15% of the structural cost budget. Because all error metrics are computed on natural-log-transformed prices, the reported MAPE overstates the practical forecast error: dividing absolute log-space errors by log-price levels (approximately 8–11) inflates the percentage figure. Back-transforming the out-of-sample errors to price space, the LBP = 3 model’s MAE of 0.0569 log units corresponds to a typical price deviation of approximately 5.9% (exp(0.0569) − 1), and its RMSE of 0.0672 to approximately 7.0%; at the longer horizons, which span the early-2024 surge, the price-space deviations rise to roughly 11.9–13.6% (MAE). At the 3-month horizon most relevant to tender preparation, the expected price deviation of 5.9–7.0% falls within the 10–15% contingency band, leaving a residual-risk margin of roughly 3–9 percentage points; by contrast, the OLS baseline’s back-transformed error (approximately 8.0% MAE and 8.7% RMSE over the full test window) consumes most of that band. At the 6- and 9-month horizons, the expected deviations approach or reach the band itself, so those forecasts inform market direction and procurement timing rather than firm budget figures. The framework thus provides actionable budget guidance rather than precise prediction, which is the appropriate standard for a volatile emerging-market commodity. In contract terms, the 3-month forecast is accurate enough to inform contingency-setting in fixed-price (lump-sum) bids, since the expected deviation sits inside the customary buffer; the 6- and 9-month horizons, with larger price-space errors, are better suited to cost-plus arrangements, feasibility-stage budget sizing, and procurement-timing decisions than to firm price commitments. Egypt experienced approximately 50% Egyptian pound depreciation between 2022 and 2024, a period characterised by unprecedented currency volatility, fuel price escalation, and geopolitical disruption [
3,
11]. Under such conditions, the ARDL framework—which explicitly models the 2022 structural break via a dummy variable—provides a substantially more reliable basis for building cost planning than naïve estimation or static regression. The VAR comparison reinforces this conclusion from a different direction: a differenced VAR, the only admissible VAR specification for mixed-integration data, forfeits the long-run equilibrium information that the ARDL retains, and its forecast accuracy deteriorates accordingly (
Table 21).
Comparison with the closest prior study—Shiha et al. [
30], who applied ANN models to Egyptian RFT and Portland cement prices—reveals important advances. While Shiha et al. reported MAPE values of 4–11%, their dataset (2008–2018) predated the structural breaks of 2022. The present study explicitly models this structural break using a dummy variable, extending the validated framework to the most volatile period in Egypt’s modern economic history. Furthermore, the ARDL framework handles the mixed stationarity of economic time series—a combination of I(0) and I(1) variables—that standard regression and VECM approaches cannot accommodate without additional transformation. This is a fundamental methodological advantage over prior Egyptian market studies.
The selection of international stock indices (S&P500 and HSI) as Granger-causal predictors of Egyptian RFT prices reflects the globalised nature of steel markets. Egyptian steel production depends heavily on imported scrap iron, whose price co-moves with international equity markets. The inclusion of these globally traded indicators distinguishes this framework from Egypt-centric models and improves its sensitivity to external shocks. The PPI and money supply (M0) predictors are consistent with prior international literature [
16,
32], providing external validity to the filtering results.
The cointegrating equations (Equations (2)–(4)) reveal that PPI exerts a positive long-run effect on RFT prices, consistent with the role of production costs in steel pricing. HSI exhibits a negative long-run coefficient, and the financialization channel supplies a concrete mechanism. Egyptian mills rely on imported ferrous scrap and billet priced in US dollars, and the HSI proxies Asian—particularly Chinese—industrial demand conditions. When Asian equity markets rise, signalling expanding industrial activity and global risk appetite, scrap and billet cargoes are bid toward East Asian buyers, raising the landed cost faced by Egyptian importers precisely when foreign-currency availability in Egypt is under pressure. Egyptian steel producers thus compete in the same international scrap market as Chinese demand, and the equity index transmits this competition into domestic RFT prices with a lag—the cross-market transmission mechanism described in the commodity financialization literature [
14,
15]. The speed of adjustment coefficient (−0.248 for LBP = 3) implies that approximately 24.8% of any deviation from long-run equilibrium is corrected each month, returning to equilibrium in approximately 4 months—a practically relevant horizon for contractor procurement planning. To translate this into a contractor’s timeline: consider a bid submitted with a standard 30-day validity window immediately after an adverse price shock, such as a sudden devaluation-driven RFT spike. The estimated adjustment speed implies that only about a quarter of the disequilibrium dissipates within that window, so the contractor cannot rely on prices reverting before award and should price the bid at close to the shocked level, expecting only partial relief over the following quarter. Conversely, a cost consultant advising on procurement timing after such a spike can anticipate that the bulk of the excess will unwind over roughly four months, which argues for deferring non-critical bulk purchases beyond the immediate post-shock period where the programme allows.
In building project delivery, price risk management occurs at three critical stages: schematic design, when the structural material budget is established; tender preparation, when contractors price their bids against current and projected market rates; and procurement, when purchase orders are placed against a fluctuating market. The 3-month ARDL forecast is most applicable at the tender preparation stage, where a forward-looking price estimate enables building contractors to include a data-driven RFT contingency in their bid rather than relying on experience-based judgment. The 9-month forecast supports procurement scheduling—allowing building projects to anticipate market direction and time bulk RFT purchasing to projected lower-price periods. The integration of this model into quantity surveying practice would require only monthly data feeds from CAPMAS and CBE, both of which are publicly available, making operational deployment technically feasible without proprietary data access.
A practical caveat concerns institutional reporting lags. CAPMAS and CBE releases typically become available one to two months after the reference month, so a nominal 3-month-ahead forecast issued from the latest available data is, in real time, an effective 1–2-month forward-looking estimate. Practitioners can navigate this in two ways: for tender preparation, the LBP = 3 model should be run on the most recent complete data vintage and interpreted as a near-term price check on current quotations; for budget-setting and procurement scheduling, the LBP = 6 and LBP = 9 models are more robust to the lag, since a two-month erosion of a 9-month horizon still leaves a genuinely forward-looking 7-month window. Where a single predictor is delayed, its most recent available observation can be carried forward as a nowcast, at the cost of modest additional uncertainty.
The primary limitations of this study are fourfold. First, the model assumes linear and symmetric relationships between macroeconomic indicators and RFT prices; although the RESET tests support this specification in-sample, asymmetric adjustment and regime-switching behaviour during extreme market episodes may not be fully captured, and a NARDL extension [
41] is a natural next step. Second, the dataset ends March 2024; the model’s performance during any subsequent structural break remains unvalidated. Third, forecast errors grow materially with horizon: while the 3-month model’s price-space error (≈5.9% MAE) is comparable to the 4–11% MAPE reported by ANN-based studies on calmer pre-2020 data, the 6- and 9-month errors (≈12–14% MAE) approach the upper bound of customary contingency allowances—a gap that future hybrid ARDL–LSTM approaches could partially close [
42]. Fourth, the framework inherits the publication lag of its inputs, as discussed above, which compresses the effective forecast horizon available to practitioners in real time. Future research should test the framework’s transferability to other building material prices (cement, aggregate, formwork, glazing) and to other emerging-market construction economies where monthly macroeconomic data are available.
5. Conclusions
This study developed and validated an ARDL-based forecasting framework for steel reinforcement bar (RFT) prices in Egypt—a building construction market characterised by severe macroeconomic volatility, mixed-stationarity economic data, and a documented structural break in 2022. The framework provides actionable 3-, 6-, and 9-month price forecasts using nine macroeconomic leading indicators identified through a reproducible variable-selection pipeline (stationarity testing, VIF multicollinearity screening, and Granger causality testing) and validated through comprehensive model diagnostics including CUSUM stability tests, Ramsey RESET specification testing, heteroskedasticity checks, and serial correlation tests.
At the operationally critical 3-month horizon, the ARDL demonstrated superiority over OLS in both understanding data dynamics and capturing the data generation process, achieving, in genuine multi-step evaluation, an out-of-sample price-space error of approximately 5.9% (mean absolute) under crisis-period conditions, versus approximately 8% for the OLS baseline. This superior performance highlights the advantages of the ARDL framework in capturing both short-run dynamics and long-run equilibrium relationships within the complex interplay of macroeconomic variables influencing steel prices. The first-difference VAR(1) benchmark performed worse still (
Table 21), confirming that the long-run cointegrating information retained by the ARDL is central to its forecasting advantage.
For building project teams, the ARDL framework delivers RFT price forecasts at 3-, 6-, and 9-month horizons. The 3-month forecast is most directly applicable at the tender preparation stage of reinforced concrete building projects, where a validated forward price indicator reduces reliance on experience-based contingency setting, improves bid accuracy and competitiveness in volatile procurement markets, and reduces post-contract cost overrun exposure. The 9-month forecast supports bulk procurement scheduling by anticipating market direction. The framework is adaptable to other building structural materials—cement, aggregate, formwork, and glazing—and is transferable to other emerging-market construction economies where monthly macroeconomic data are publicly available.