Next Article in Journal
Mechanical Characteristics Based on the Microstructure Analysis of Cementitious Composites Incorporating Polypropylene Powder
Previous Article in Journal
Automated Evaluation of Layer Thickness Uniformity in 3D-Printed Cementitious Composites Using Deep Learning and Comparison with Manual Tracing Methods
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Temperature Control of Massive High-Strength Concrete Columns During Curing—A Case Study in Hong Kong

1
China State Construction Engineering (Hong Kong) Limited, Hong Kong, China
2
Department of Civil Engineering, The University of Hong Kong, Hong Kong, China
3
School of Civil Engineering and Transportation, South China University of Technology, Guangzhou 510641, China
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(23), 4256; https://doi.org/10.3390/buildings15234256
Submission received: 9 October 2025 / Revised: 14 November 2025 / Accepted: 23 November 2025 / Published: 25 November 2025
(This article belongs to the Section Building Structures)

Abstract

High-strength concrete generates a significant amount of heat during curing, which can cause delayed ettringite formation and early thermal cracking. Such problems are particularly acute in Hong Kong because of the local practice of designing concrete mixes to have rather high cementitious contents to avoid non-compliance with the stringent strength requirements. Moreover, in Hong Kong, there is still a lack of clear specifications of the temperature control limits to be imposed. Hence, the temperature control of curing high-strength concrete in massive columns/walls has, up to now, remained guess work. In this paper, temperature control limits are proposed, and a case study on temperature control of massive C80 concrete columns during curing is presented. Due to the high cementitious content and large column size, an internal water-cooling system, designed with the help of thermal analysis by the finite element method, was installed. In this system, each pipe was a double-pipe for both water inflow and outflow. It had successfully avoided exceedance of temperature control limits and formation of early thermal cracks. The lessons learned, as summarized in the Conclusions, should be useful for the optimum design of temperature control regimes for massive high-strength concrete members.

1. Introduction

High-strength concrete is generally made with a rather high total cementitious content [1,2,3,4], especially in Hong Kong [5,6]. In the Code of Practice for Structural Use of Concrete [7], i.e., the local concrete code, Clause 4.2.6.1 stipulates that a total cementitious content of up to 550 kg/m3 is allowed for a concrete grade up to C60 and the total cementitious content may exceed 550 kg/m3 for a higher concrete grade. As the chemical reactions of the cementitious materials would generate substantial heat during curing, such a high total cementitious content could lead to a very high temperature rise. This could cause the potential problems of delayed ettringite formation and early thermal cracking [8,9,10].
The adiabatic temperature rise of concrete due to the hydration of cement is usually around 13 °C to 15 °C per 100 kg/m3 of cement, depending on the type of cement and the degree of hydration [8]. Hence, with a cement content of, say, 450 kg/m3, the adiabatic temperature rise could be higher than 60 °C. Relatively, the adiabatic temperature rises due to the pozzolanic reactions of PFA (pulverized fuel ash), GGBS (ground granulated blast-furnace slag), and CSF (condensed silica fume) are much lower, and thus, the addition of PFA, GGBS, and/or CSF to replace part of the cement would significantly reduce the adiabatic temperature rise. Clause 4.2.5.5 of the local concrete code actually allows the use of 25% to 35% PFA or 35% to 75% GGBS. However, some engineers in Hong Kong limit the PFA content at a maximum of 20% and the GGBS content at a maximum of 35%. Added with the high total cementitious content to cope with the heavy penalty of non-compliance with strength requirements, the Hong Kong concretes are really hot.
The adiabatic temperature rise of concrete may be estimated from the concrete mix proportions using empirical formulas derived by regression analysis of test results. However, these empirical formulas give only rough estimates because the adiabatic temperature rise is dependent on the characteristics of the materials used for making concrete. For instance, concrete producers in Hong Kong like to use cementitious materials that would yield higher early strength to enable faster construction. Such cementitious materials would generate heat at faster rates, leading to rapid accumulation of heat within massive concrete members and, thus, higher than usual peak temperatures. Hence, the empirical formulas developed elsewhere may not be applicable in Hong Kong. A better way is to measure the actual adiabatic temperature rise by testing. In fact, Clause 10.3.6.1 of the local concrete code stipulates that, for all concrete mixes of a grade higher than C60, adiabatic curing tests should be carried out.
However, it is not easy to conduct an adiabatic curing test, which demands perfect heat insulation at concrete surfaces to inhibit heat dissipation and adaptive control of the surface temperature to minimize the temperature gradient in the concrete [11,12,13]. Due to the difficulties involved, normally, only a semi-adiabatic curing test with a small degree of unavoidable heat dissipation is carried out. Such a semi-adiabatic curing test is called TRET (temperature rise evaluation test). However, the test results of TRET are dependent on the size of the concrete specimen and the thickness of the heat insulation because of the heat loss through the concrete surfaces. Generally, a larger concrete specimen covered with thicker heat insulation would lead to less heat loss per volume and, thus, a smaller testing error. At the moment, there is no standard for TRET, and different engineers adopt different test methods yielding different test results. Nevertheless, the heat loss can be estimated from the rate of temperature drop after the temperature has reached the peak and put back into the concrete to compensate for the heat loss to improve the accuracy of the TRET [11]. Alternatively, trial casting of a full-scale mock-up could be carried out, and the adiabatic temperature rise could be back-calculated by thermal analysis of the temperature monitoring results.
After estimating the adiabatic temperature rise, thermal analysis is carried out to evaluate the temperature development of the curing concrete, considering the concrete placing temperature, adiabatic temperature rise, ambient temperature, weather condition, heat insulation provided, and internal/external cooling applied. Depending on how complex the shape of the concrete member is, the thermal analysis may be carried out for a simple-shaped member with a uniform section by one-dimensional analysis using the analytical methods given in ACI 207.1R-96 [14], for an irregular-shaped member with a uniform section by two-dimensional finite element analysis, and for a complex-shaped member with a nonuniform section by three-dimensional finite element analysis. Computer programs are available for such analysis, but before use, validation is needed. The proposed temperature control process and the anticipated weather condition is then simulated, as is demonstrated herein.
To avoid delayed ettringite formation and early thermal cracking, it is necessary to impose certain limits on the peak temperature and the temperature differential within the freshly cast concrete pour [8,9]. However, in the local concrete code [7], there is no mentioning of the temperature control limits to be imposed. As a result, different engineers impose different temperature control limits, and it is uncertain which are more suitable for Hong Kong. Moreover, some engineers are still not aware that the risk of delayed ettringite formation is dependent not only on the peak temperature but also on the types and amounts of supplementary cementitious materials added and that the addition of supplementary cementitious materials can help to lower the risk of delayed ettringite formation and, thus, raise the peak temperature limit for easier temperature control.
The next step is to design the temperature control regime such that the imposed temperature control limits would not be exceeded. It should, however, be noted that the temperature control regimes developed for concrete dams [14,15,16,17] are mostly not applicable to building structures [18] and it is necessary to develop specific temperature control regimes for building members because of the following differences: (1) in concrete dams, the concrete mixes are designed to have very low cementitious content and very high PFA content so as to minimize the heat generation, but in building structures, the cementitious content is much higher and the PFA content is at most 35%, and thus, the heat generation can be very large; (2) dams are huge in size, and thus, the boundary surface area to volume ratio and the heat dissipation through boundary surfaces are very small, but in building structures, the heat dissipation through boundary surfaces is quite significant; (3) in building structures, the temperature development is dependent on the minimum dimension of the concrete member, and for relatively small or thin members, the temperature control may be dispensed with if the heat dissipation would reduce the temperature rise to less than about 40 °C.
For the design of the temperature control regimes, the various parameters to be considered include the concrete placing temperature, ambient temperature, surface heat insulation, and internal/external cooling to be applied. Currently, there are still no general guidelines for the design of the temperature control regimes for different weather conditions. What we can do at the moment is to try different parameters and carry out thermal analysis to find out whether any of the temperature control limits would be exceeded. This is rather cumbersome and inefficient. After working on a number of projects on the temperature control of massive high-strength concrete members, it is felt that the presentation of case studies would help to build up experience for guiding the design of temperature control regimes. By the way, a case study on large-diameter bored piles in Hong Kong, revealing that there is a high risk of early thermal cracking in large-diameter bored piles, has recently been published [19].
Extensive studies [20,21,22] have been carried out to develop systematic techniques for optimizing the structural performance of concrete buildings, but there have been only a few studies for optimizing the thermal performance of temperature control regimes to be applied to curing concrete members. In this paper, a case study in Hong Kong on the thermal analysis and temperature control of C80 concrete with a total cementitious content of 580 kg/m3 cast into massive columns is presented. The temperature control limits adopted are based on CIRIA C660 [8] and ACI 201.2R-16 [9]. Due to the high cementitious content of the concrete and the large size of the columns, internal water-cooling pipes were installed. Full-scale trial casting of a 3.0 m-diameter C80 concrete column was carried out to test the effectiveness of the cooling pipes and to verify the thermal analysis. Then, different cooling-pipe arrangements were tried in the thermal analysis, and the cooling-pipe design was optimized by minimizing the peak temperature and temperature differential within the concrete pour. By the time of writing this paper, all concrete casting of the massive C80 columns has been completed, with no exceedance of temperature control limits and no observable thermal cracks.

2. Temperature Control Limits to Be Imposed

The reasons for imposing a maximum peak temperature limit are to avoid delayed ettringite formation (DEF) and to avoid reduction in strength due to high temperatures at the early age. On the other hand, the main reason for imposing a maximum temperature differential limit within the concrete pour is to avoid early thermal cracking due to internal restraint arising from uneven thermal expansion/contraction during curing.

2.1. Risk of Delayed Ettringite Formation

DEF is a form of internal sulphate reaction after the concrete has hardened [23,24]. It occurs in concrete that has experienced high temperatures during curing. The high temperatures decompose the primary ettringite, which is responsible for regulating set, and the ettringite reforms later, causing a slight expansion. The risk of DEF is dependent on both the peak temperature and the added supplementary cementitious materials (SCMs).
CIRIA C660: Appendix A9 [8] recommends that, for ordinary Portland cement concrete, the risk of DEF may be assessed as follows:
  • Peak temperature < 60 °C: no risk;
  • Peak temperature < 70 °C: very low risk;
  • Peak temperature < 80 °C: low risk.
Hence, for ordinary Portland cement concrete with no SCM added, the peak temperature limit may be set as 70 °C to attain a very low risk of DEF. This peak temperature limit may be raised by adding SCM, such as PFA or GGBS. Basically, the addition of at least 20% PFA or at least 40% GGBS would suppress DEF up to a peak temperature of 100 °C and, thus, would allow raising the peak temperature limit to 100 °C.
On the other hand, ACI 201.2R-16: Section 6.2 [9] recommends the following preventive measures for suppressing DEF:
  • Peak temperature ≤ 70 °C: no prevention required;
  • Peak temperature > 70 °C but ≤85 °C: check cement properties or add SCMs;
  • Peak temperature > 85 °C: not allowed under any circumstances.
The details of the above recommended preventive measures are given in Table 6.2.2.2 of the ACI standard [9]. This table stipulates that, if at least 25% PFA is added or at least 35% GGBS is added or at least 5% CSF is added in conjunction with either PFA or GGBS, the peak temperature limit may be raised to 85 °C.
Putting the above recommendations together and adopting the values that would comply with both CIRIA C660 and ACI201.2R-16, it is worked out that the peak temperature limit should be set as 70 °C when no SCM is added and as 85 °C when at least 25% PFA or at least 40% GGBS or at least 5% CSF in conjunction with PFA/GGBS is added.

2.2. Risk of Reduction in Strength

The adverse effect of high temperatures at the early age on strength is dependent on how early is the early age. During the first few hours after casting, high temperatures should be avoided. That is why steam curing is normally applied only after a delay period of about 4 to 6 h, and the temperature is gradually increased to the maximum steam curing temperature in another period of 2 to 3 h. As reviewed by Zeyad et al. [25], with a sufficiently long delay period before applying steam curing, no decrease in strength at later ages would occur. The adverse effect of high temperatures at the early age on strength is dependent also on whether the concrete contains SCM, such as PFA or GGBS. Generally, the addition of PFA or GGBS would remarkably mitigate such adverse effects. For casting of massive high-strength concrete members, since the curing concrete would by itself attain a fairly high temperature, there is no particular reason to apply steam curing. What we should make sure is that no heating should be applied at the early age.
In CIRIA C660: Appendix A9 [8], it is also recognized that the effect of high temperatures at the early age on strength is dependent on whether the concrete contains SCM. It refers to a Concrete Society Study [26], which reported that the performance of concretes containing PFA or GGBS differs significantly from that of Portland cement concretes in two principal respects. Firstly, at 28 days, the in situ strength would not reduce with an increase in the peak temperature, with a trend for a higher in situ strength in those elements achieving the higher peak temperature. Secondly, the development of in situ strength over the long-term would be significantly higher for the PFA and GGBS concretes. Hence, if the concrete contains SCM, such as PFA or GGBS, there is no need to worry about the possible adverse effect of high temperatures at the early age on long-term strength.
Based on the above literature, it may be concluded that the possible adverse effect of high temperatures at the early age on strength is a concern only when the high temperatures occur during the first few hours, or say, during the first 10 h. In reality, temperature monitoring indicated that the peak temperature always occurred after the first day, or in other words, after 24 h. Hence, it is unlikely that there could be any adverse effect on strength due to high temperatures at the early age. If there is any concern, it is suggested to drill some cores from the in situ hardened concrete and check the in situ strength against the specified grade strength. Such core testing should be mandatory if the concrete contains no SCM.

2.3. Risk of Early Thermal Cracking

The temperature differential limits within the same concrete pour being imposed in Hong Kong range from 20 °C to 25 °C. There is still no standardized temperature differential limit in Hong Kong, and that is why different engineers adopt different temperature differential limits. Actually, the limit to be imposed on the temperature differential within the same concrete pour can be worked out as in Clause 7.1 of CIRIA C660 [8]. As depicted in Table 7.1 of Clause 7.1, the temperature differential limit to be imposed should not be a constant but should be dependent on the type of aggregate because the type of aggregate has a certain effect on the tensile strain capacity of the concrete. According to this table, for granite aggregate concrete, the temperature differential limit to be imposed should be 28 °C. Hence, the temperature differential limits being imposed in Hong Kong are on the conservative side. Nevertheless, to play it safe, it is suggested that we should keep the limit conservatively at 25 °C until sufficient field data has been accumulated for review.

3. The C80 Concrete and Massive Concrete Members Cast

The C80 high-strength concrete had a total cementitious content of 580 kg/m3. It contained 25% PFA and 5.9% CSF. The cement used was an Ordinary Portland Cement of grade 52.5. Both the fine and coarse aggregates used were crushed granitic rock. To attain the required grade strength of 80 MPa, it was designed to have a rather low W/C ratio of 0.25. The QC test results revealed that the actual mean 28-day cube strength was as high as 100 MPa. To achieve the design slump of 200 mm, a fairly high dosage of superplasticizer of more than 9 kg/m3 (adjustable) was added. Using the design charts given in Section 4.2 of CIRIA C660 [8], it was estimated that the adiabatic temperature rise of the C80 concrete is about 64.5 °C, and the heat generation per total cementitious content is about 267 kJ/kg. These are, however, only approximate values.
The C80 high-strength concrete columns to be cast include circular columns up to 3.0 m in diameter and noncircular columns up to 2.0 m thick. It was decided right at the beginning that internal water cooling of the curing concrete would have to be provided, but to optimize the design for better constructability, the water-cooling system of each column was separately designed to have the minimum number of cooling pipes because the installation of cooling pipes could cause congestion within the formwork and difficulties in rebar fixing and concrete casting. Then, the cooling pipe arrangement in each column was designed by a trial-and-error process of trying different arrangements and conducting thermal analysis to find out if any of the temperature control limits would be exceeded.
A full-scale trial concrete casting of the biggest 3.0 m-diameter circular column was carried out, as shown in Figure 1, to check the constructability after adding the cooling pipes and to test the effectiveness of the cooling pipes. The trial column was cast to a height of 5.0 m. It was provided with six cooling pipes to draw out the heat and a total of 25 thermo-couples (at five evenly spaced cross-sections and with five in each cross-section) to monitor the temperature distribution and variation with time. Thermal analysis of this trial column by the finite element method was carried out to verify the applicability of the computer program used and to back-calculate the adiabatic temperature rise of the C80 concrete.
Regarding temperature control for avoiding DEF, since the C80 concrete has a PFA content of 25% and a CSF content of 5.9%, the peak temperature limit for avoiding DEF was set as 85 °C. Regarding temperature control for avoiding reduction in strength, since the C80 concrete contains SCM and no heating would be applied, no specific temperature control limit was imposed during the early age (the first 10 h). Nevertheless, six 75 mm-diameter cores were drilled from the trial column cast and tested in accordance with the Hong Kong Construction Standard CS1: 2010 [27] to find out if there might have been any reduction in strength. The core test results revealed that the in situ equivalent cube strength of the six cores was at least 99.5 MPa, thus confirming that there was no reduction in strength due to high temperatures at the early age. Lastly, regarding temperature control for avoiding early thermal cracking, the temperature differential limit was set as 25 °C, which is more conservative than the recommended value of 28 °C for granite aggregate concrete depicted in Table 7.1 of CIRIA C660 [8].

4. Thermal Analysis by the Finite Element Method

For thermal analysis of freshly cast concrete, the finite element method is the most versatile [28,29]. Since the concrete members to be cast are elongated and have uniform sections, only two-dimensional finite element analysis was carried out. The computer program used was HACON, developed by Lund University [30]. HACON is a finite element analysis program for simulation of temperature and stress development in hardening concrete. Using HACON, we can estimate the risk of early thermal cracking and find out the most effective measures to avoid crack development. The most updated version of the computer program, HACON 3.1, was used for the thermal analysis. Although this program can also be used to perform post-crack analysis, no post-crack analysis was carried out because it was expected that, with proper temperature control, there should be no early thermal cracking. In fact, our target was to completely eliminate rather than just to minimize early thermal cracking.
Before use, the computer program HACON was first validated by comparing the HACON analysis results of some examples in CIRIA C660 [8] with the respective values in the design charts presented in CIRIA C660. The examples analyzed were those given in Figure 4.3 and Figure 4.5 of CIRIA C660. All parameters used in the analysis were exactly the same as those in the examples. Table 1 depicts the comparison between the analysis results obtained by HACON with the respective values in the design charts presented in CIRIA C660. From this table, it can be seen that, on average, the difference in peak temperature is about 1.83 °C, and the difference in temperature differential is about 0.55 °C. Bearing in mind that the values given in the examples and the design charts in CIRIA C660 are not really exact values, such differences were considered small enough to be regarded as admissible. Hence, the HACON passed the validation.
HACON was then used to analyze the trial column cast, with temperature monitoring results available for checking to further verify the applicability and accuracy of the computer program, and the suitability of the parameters used in the thermal analysis. As mentioned before, the trial column was provided with six cooling pipes. Each cooling pipe has an outer diameter of 75 mm. The inlet temperature of the cooling water was controlled at 20 °C by adding ice to the cooling water tank, and the flow rate was adjusted by a valve at the inlet such that the outlet temperature was always kept at around 22 °C. Although the water temperature in each cooling pipe varied between 20 °C and 22 °C, it was assumed to be 21 °C in the thermal analysis. Meanwhile, a total of 25 thermo-couples, five in each cross-section, were installed to monitor the temperature distribution and variation with time. The layouts of the cooling pipes and thermo-couples are shown in Figure 2.
The material properties of the C80 concrete used in the thermal analysis are summarized in Table 2. These material properties are either the actual measured values or the estimated values based on CIRIA C660.
On the other hand, the boundary parameters used, which are dependent on the ambient temperature, weather condition, type of formwork before striking of formwork at 48 h, and plastic sheet wrapping provided after removal of formwork at 48 h, are summarized in Table 3. These parameters are the boundary temperature adopted in the temperature control and the typical thermal conductivity values of the steel formwork and polythene sheets used.
The measured temperature at Point A (center of column section) and the analyzed temperature at Point A by HACON are compared in Figure 3. It is noted that the measured temperature at Point A increased to 72.2 °C at 25.3 h after casting, whereas the analyzed temperature at Point A by HACON increased to 71.0 °C at 30.6 h after casting. Hence, the measured peak temperature and the analyzed peak temperature agreed quite well with each other. However, the analysis results revealed that the maximum temperature across the column section actually did not occur at Point A but rather at Point M, as marked in Figure 2, which was at somewhere further away from the cooling pipes than Point A. At Point M, the analyzed peak temperature was 73.6 °C, which was 2.6 °C higher than the analyzed peak temperature at Point A of 71.0 °C. This indicates that temperature monitoring by installing thermo-couples may not give the maximum temperature because the maximum temperature may not occur at any of the thermo-couples installed. Thermal analysis by the finite element method is more useful for determining the maximum temperature across the column section and the maximum peak temperature. On the other hand, the measured maximum temperature differential was 24.0 °C, whereas the analyzed maximum temperature differential was 24.7 °C. Such maximum temperature differentials have not exceeded the allowable limit of 25 °C but seem a bit marginal. It was thus considered better to redesign the cooling pipe arrangement to reduce the temperature differential.
Overall, the analyzed temperature results by HACON agreed quite well with the measured temperature results by the thermo-couples, with an average error of around 1 °C (the order of magnitude of the experimental errors) up to the time the peak temperature was reached. Hence, it is again verified that HACON and the parameters used in the analysis are sufficiently accurate for its intended application of thermal analysis of massive concrete members installed with an internal water-cooling system. Somehow, the error at the post-peak cooling stage was relatively large due partly to the significant variation in ambient temperature during the curing period and partly to the larger than expected heat dissipation after removal of formwork. Nevertheless, the error at the post-peak stage is not critical because the time at which the peak temperature would occur and the time at which the maximum temperature differential would occur have already passed.
Lastly, since the analyzed temperature results and the measured temperature results are already quite close to each other and it appears that the actual adiabatic temperature rise should be just about 1 °C higher than the originally assumed value, it was decided not to carry out the cumbersome back-calculation of the adiabatic temperature rise, which requires iterative adjustment of its value until the best agreement between the analyzed and measured temperature results is achieved. For this particular C80 concrete, the originally assumed adiabatic temperature rise of 64.5 °C and heat generation of 267 kJ/kg estimated using the design charts in CIRIA C660 [8] are already good estimates.

5. Optimum Design of Temperature Control Regime

The trial column casting and the thermal analysis revealed that the cooling pipes installed are effective in reducing the peak temperature and temperature differential, but the actual effectiveness is dependent on the arrangement and spacing of the cooling pipes. As revealed by the thermal analysis, the point of maximum temperature, i.e., the hottest spot within the column section, generally occurs at somewhere furthest away from the cooling pipes and the boundary surfaces. Hence, it is better to arrange the cooling pipes such that there are no such particularly hot spots. In principle, the cooling pipes should be evenly located such that there is no region in the column section that is too far away from both the cooling pipes and the boundary surfaces. Based on this principle, it was considered that the original six-pipe cooling system was not good and needed to be redesigned.
Another issue is the large difficulty and high cost of lowering the concrete placing temperature to 22 °C. In Hong Kong, the ambient temperature could be higher than 30 °C, and lowering the concrete placing temperature to 22 °C would require the addition of a large amount of ice to the concrete mix and, thus, render the concrete mixing a lot more difficult and the cost of concrete production a lot higher. Hence, consideration should be given to the feasibility of raising the concrete placing temperature to 25 °C or even 30 °C by enhancing the cooling effect of the water-cooling system. Yet another issue is the high cost of providing cooling water at 20 °C for the cooling pipes 24 h a day. This would require the addition of a large amount of ice into the water tanks from which the cooling water is pumped into the cooling pipes. Hence, consideration should also be given to the feasibility of raising the temperature of the cooling water to 25 °C or even 30 °C again by enhancing the cooling effect of the water-cooling system.
After raising the concrete placing temperature and the cooling water temperature to reduce cost, it may be necessary to put in more cooling pipes to increase the effectiveness of the water-cooling system. However, as the installation of more cooling pipes would cause difficulties in rebar fixing and concrete casting, the number of cooling pipes should be kept to the minimum necessary. For instance, for the 3.0 m-diameter column, the number of cooling pipes needs to be increased from six to either seven or eight. To find out the optimal solution, both the seven-pipe cooling system and the eight-pipe cooling system are tried, and their effectiveness in suppressing the peak temperature and temperature differential to avoid non-compliance with the temperature control limits is analyzed by HACON. Then, the complying system with the minimum number of cooling pipes is adopted. For the other massive columns, the same strategy can be applied to design the water-cooling system of each member.
Regarding the number of cooling pipes, one may query how the number of cooling pipes could be an odd number. In the conventional design of cooling pipes, the cooling pipes are arranged in pairs, with each pair comprising an inlet pipe and an outlet pipe. The cooling water flows from the inlet pipe to the outlet pipe through a U-bend connecting the inlet pipe and the outlet pipe together at their far ends. In effect, each pair of cooling pipes is a U-tube, and therefore, the number of cooling pipes is always an even number. This conventional design has the problem that, in some cases, such as the case of the 3.0 m-diameter column, despite the sufficiency of providing seven cooling pipes, we have to provide eight cooling pipes because we cannot put in an odd number of cooling pipes. More importantly, the installation of the U-bends and U-tubes is often obstructed by the rebars, and to avoid conflict, the installation of the U-bends and U-tubes has to be carried out together with the fixing of the rebars. Due to such difficulty in installation of cooling pipes, many engineers do not like internal water cooling and prefer to pay for the higher cost of alternative measures.
In order to overcome the above problems, the construction team has developed an innovative double-pipe design of cooling pipes. In this double-pipe design, each cooling pipe is a double-pipe with a smaller pipe inside the cooling pipe, and the cooling water would flow into the smaller pipe and then out through the annular space between the smaller pipe and the cooling pipe. In effect, both the inflow and outflow of cooling water are through the same cooling pipe, and there are no more U-bends. This would allow the rebars to be fixed first and then the cooling pipes to be inserted into the rebar cage for installation at a later time. Hence, there is the major advantage of a much easier and faster installation. Moreover, the number of cooling pipes can now be an odd number for better optimization. This double-pipe design is, at the moment, patent pending, and no further details can be given here.
Regarding the optimum design of temperature control regime, it was just by means of a trial-and-error process of trying different concrete placing temperatures, different cooling water temperatures, and a different number and arrangement of cooling pipes, and conducting thermal analysis to find out if satisfactory results could be obtained. To cater for concrete casting over several months under moderate or hot weather conditions, the thermal analysis was carried out twice, with the ambient temperature set first as 20 °C in moderate weather and then as 30 °C in hot weather. After several rounds of thermal analysis, it was decided to raise the concrete placing temperature to 30 °C and the cooling water temperature to 25 °C in order to reduce cost. Afterwards, the number of cooling pipes was varied to find out the minimum number needed to comply with the temperature control limits.
Frankly speaking, the above iterative optimization process is quite cumbersome and time consuming. In the longer term, further research should be carried out to establish design guidelines for quicker choices of concrete placing temperature, cooling water temperature, number of cooling pipes, spatial arrangement of the cooling pipes, etc. Consideration should also be given to the possibility of developing a fully computerized and automated method for the design of temperature control regimes. The use of artificial intelligence for this purpose could be an interesting and impactful research project.
Some of the optimum designs so arrived at are depicted in Figure 4 and Figure 5 for circular section columns, Figure 6 and Figure 7 for rectangular section columns, and Figure 8 and Figure 9 for irregular section columns. In these designs, the locations and spacings of the cooling pipes have been adjusted iteratively by small steps until the peak temperature and temperature differential values are minimized for best overall thermal performance. The minimized values so attained of the peak temperature and temperature differential within each column section under the moderate and hot weather conditions are presented in each of these figures to elucidate the ample margins provided in each column section for ensuring compliance with the temperature control limits.
From Figure 4, it can be seen that, for a 3.0 m-diameter circular section column, the provision of seven symmetrically arranged cooling pipes, with six located at the vertices of a hexagon and one located at the center of the section, is already sufficient for complying with the temperature control limits. Compared to an earlier scheme of providing eight cooling pipes, the number of cooling pipes has been reduced by one. In Figure 5, it can be seen that, for a 2.0 m-diameter circular section column, the provision of four symmetrically arranged cooling pipes located at the vertices of a square is already sufficient.
In Figure 6, it can be seen that, for a 1.5 m-thick rectangular section (2.5 m × 1.5 m) column, three evenly spaced cooling pipes along the longer axis need to be provided for complying with the temperature control limits. In Figure 7, however, it can be seen that, for a 0.7 m-thick rectangular section (2.6 m × 0.7 m) column, no cooling pipe needs to be provided. Hence, for rectangular section columns, the thickness is the governing factor in the design of the water-cooling system. In fact, it has been found that all the rectangular section columns with a thickness ≤ 0.7 m do not need any cooling pipe.
In Figure 8, it can be seen that, for a 2.0 m-thick irregular section (2.9 m × 2.0 m) column whose section comprises a rectangle and two semi-circles, six cooling pipes need to be provided for complying with the temperature control limits. In Figure 9, it can be seen that, for a 1.6 m-thick irregular section (2.4 m × 1.6 m) column whose section comprises a rectangle and two semi-circles, four cooling pipes need to be provided. The experience gained is that, without thermal analysis by the finite element method, it is almost impossible to work out these optimum designs for irregular section columns.
One important point to note is that the above specifically designed temperature control regimes are only for concrete casting under moderate or hot weather conditions because these are the weather conditions that would be encountered during concrete casting. For concrete casting under cold weather conditions, the temperature control regimes need to be redesigned. Basically, for cold weather concreting at an ambient temperature of around 10 °C, the concrete placing temperature and the cooling water temperature should be set lower. Actually, at an ambient temperature of around 10 °C, there is no need to add ice anymore, and thus, lowering the concrete placing temperature and the cooling water temperature would not incur additional cost. The design of temperature control regimes for cold weather concreting may follow the same steps as for moderate and hot weather concreting as demonstrated herein.
Another important point to note is that bad weather, such as heavy rain and strong wind, could cause rapid surface cooling of the columns and thus increase the temperature differential between the maximum temperature within the column section and the surface temperature at the column section. Hence, at times of bad weather, the freshly cast columns should be protected by covering with polythene sheets sealed at their edges.

6. Lessons Learned and Discussions

The above internal water-cooling systems, optimally designed with the help of thermal analysis by the finite element method, have been implemented for temperature control of the massive C80 concrete columns, and the casting and curing of the concrete columns were all completed. After scrutiny of the temperature monitoring records and close inspection of the finished concrete columns, it was confirmed that there was no exceedance of temperature control limits and no observable early thermal cracks. So, the internal water-cooling systems performed satisfactorily. This was achieved after raising the concrete placing temperature to 30 °C and the cooling water temperature to 25 °C to reduce cost. Such cost savings were made possible by rearranging the cooling pipes to be more evenly located to avoid having hot spots in the concrete sections so as to enhance their effectiveness. The optimization methodology developed herein may be considered as a basis for the design of temperature control regimes and internal water-cooling systems for the casting and curing of massive high-strength concrete elements of grade C80 and up to a cross-section size of 3.0 diameter.
Another achievement is the development of a double-pipe design of cooling pipes. With this design, each cooling pipe has a smaller pipe inside so that the cooling water would flow into the smaller pipe and then out through the annular space between the smaller pipe and the cooling pipe. As both the inflow and outflow of cooling water are through the same cooling pipe, U-bends are not needed anymore, and each cooling pipe is a straight pipe, which can be inserted into the rebar cage after rebar fixing. This allows easier and faster installation and the number of cooling pipes to be an odd number for better optimization.
While celebrating the success of the above temperature control regimes, it is felt that there is still room for improvement. Actually, the key factor is the heat generation of the concrete. If the C80 concrete could be redesigned to have lower total cementitious content and higher PFA content, its heat generation could be reduced to ease the temperature control. There are many ways to do so. Firstly, volumetric proportioning should be adopted for more accurate proportioning in order to achieve better optimization, as Domone and Soutsos suggested [1]. Secondly, the packing density of the aggregate should be optimized by aggregate proportioning to reduce the volume of voids to be filled with paste so as to reduce the paste volume and total cementitious content [31]. Thirdly, more PFA or GGBS should be added to reduce the cement content and the heat generation. It has been found that the use of 45% PFA to produce high-strength concrete could substantially reduce the heat generation [32]. Such a PFA content of 45% may seem a bit too high, but increasing the PFA content to the allowable limit in the local concrete code of 35% would already significantly reduce the heat generation. Lastly, there is also an effective method of adding a powder filler to reduce the cementitious paste volume, total cementitious content, and heat generation [33,34].
Regarding whether the proposed temperature control regimes may also be applied to massive concrete elements cast of C100 concrete, the basic principles for designing the temperature control regimes are the same, and the methodologies developed herein, such as the finite element analysis method and the internal water-cooling method, should also be applicable to C100 concrete. It is only that C100 concrete usually has a higher total cementitious content and, thus, would generate more heat. Hence, the temperature control of C100 concrete is more difficult and critical. Chances are that more ice would be needed to lower the concrete placing temperature to say 25 °C, more cooling pipes would be needed, and cooler water would have to be used for the internal water cooling. But first of all, effort should be made to reduce the total cementitious content of the C100 concrete so that less heat would be generated.

7. Summary and Conclusions

A case study in Hong Kong on the temperature control of C80 concrete with a rather high total cementitious content of 580 kg/m3 cast into massive columns up to 3.0 m diameter has been presented. The work performed and lessons learned are summarized as follows:
(1)
A set of temperature control limits complying with both the CIRIA C660 and ACI201.2R-16 has been proposed, wherein the peak temperature limit is set as 70 °C when no SCM is added and as 85 °C when at least 25% PFA or 40% GGBS is added and the temperature differential limit is set as 25 °C for granite aggregate concrete.
(2)
Based on CIRIA C660, this C80 concrete was estimated to have an adiabatic temperature rise of 64.5 °C and a heat generation per total cementitious content of 267 kJ/kg.
(3)
Full-scale trial concrete casting of a 3.0 m-diameter C80 concrete column with internal cooling pipes installed was carried out. The concrete placing temperature was 22 °C, and the cooling water temperature was 20 °C. The trial casting was to evaluate the constructability and effectiveness of the cooling pipes and to provide temperature results for verifying the accuracy of the thermal analysis.
(4)
The computer program HACON was used for the thermal analysis. It was first applied to analyze examples in CIRIA C660 for validation. Then, it was applied to analyze the temperature distribution and development in the trial column cast to verify the accuracy of HACON and the parameters used in the analysis. The HACON results revealed that the maximum temperature may not occur at the thermo-couples but tends to occur at a point furthest away from the cooling pipes and boundary surfaces.
(5)
The temperature control regimes for the massive columns to be cast were designed by trying different concrete placing temperatures, different cooling water temperatures, and a different number and arrangement of cooling pipes and then performing thermal analysis to check compliance with the temperature control limits. After several rounds of thermal analysis, it was decided to raise the concrete placing temperature and cooling water temperature to 30 °C and 25 °C, respectively, in order to save cost.
(6)
For optimum design of the cooling pipes, first, the minimum number of cooling pipes needed was determined by increasing or decreasing the number of cooling pipes until thermal analysis indicated just sufficient cooling for compliance. Because of the adoption of a newly developed double-pipe design of cooling pipes, the number of cooling pipes could be an odd or even number for better optimization, and the cooling pipes could be inserted into the rebar cage for better constructability.
(7)
The next step in the optimum design of the cooling pipes was to locate the cooling pipes such that there are no hot spots in the column section and then adjust their spacing until thermal analysis indicated that the peak temperature and temperature differential have been minimized for best overall thermal performance. After such optimization, the concrete placing temperature and cooling water temperature should be reviewed to find out if there is any possibility of raising these temperatures to save cost.
(8)
Some optimized cooling pipe designs for column sections of various size and shape are shown in Figure 4, Figure 5, Figure 6, Figure 7, Figure 8 and Figure 9. These, together with the temperature control regimes, have been implemented, and the concrete casting and curing were satisfactorily completed, with no exceedance of temperature control limits and no observable early thermal cracks. At the end, it is concluded that the water-cooling systems and the temperature control regimes have good constructability, economy, and reliability.
(9)
Lastly, it is suggested that, for a high-strength concrete to be cast in massive concrete members, it is better to first redesign the concrete mix to have lower heat generation by decreasing the total cementitious content and increasing the PFA/GGBS content, so as to ease the temperature control before starting to design the temperature control regimes. This may further improve the constructability and reduce the cost.

Author Contributions

Methodology, X.Z. and K.-h.K.; software, Y.L.; validation, W.L., Z.Z. and C.Y.; investigation, Z.Z. and C.Y.; resources, Y.L.; writing—original draft preparation, K.-h.K., W.H. and W.L.; writing—review and editing, X.Z.; visualization, W.H.; supervision, X.Z. and J.H.; project administration, J.H.; funding acquisition, W.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data presented in this study are available on request from the corresponding author. The data are not publicly available due to privacy restrictions.

Acknowledgments

We would like to express our sincere gratitude to Daniel Kan, a structural engineer from the Structures Research Hub of China State Construction Engineering (Hong Kong) Limited, as well as K.Y.Ng and W.C.Mak, structural engineers from the Chai Wan Road Residential Project Team of China State Construction Engineering (Hong Kong) Limited, for their invaluable support.

Conflicts of Interest

Authors Xiaokang Zou, Jiang Huang, Wenjin Hu, Wenjie Lu, Zhen Zhao, Chen Yang are employed by the China State Construction Engineering (Hong Kong) Limited. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Domone, P.L.J.; Soutsos, M.N. Approach to the proportioning of high-strength concrete mixes. Concr. Int. 1994, 16, 26–31. [Google Scholar]
  2. Donza, H.; Cabrera, O.; Irassar, E.F. High-strength concrete with different fine aggregate. Cem. Concr. Res. 2002, 32, 1755–1761. [Google Scholar] [CrossRef]
  3. ACI 363R; High-Strength Concrete Reported by ACI Committee 363. ACI: Farmington Hills, MI, USA, 2005.
  4. Caldarone, M.A. High-Strength Concrete: A Practical Guide; Taylor & Francis: New York, NY, USA, 2009. [Google Scholar]
  5. Chan, S.Y.N.; Anson, M. High-strength concrete: The Hong Kong experience. Mag. Concr. Res. 1994, 46, 235–236. [Google Scholar] [CrossRef]
  6. Kwan, A.K.H.; Cai, Y.B.; Chan, H.C. Development of very high strength concrete for Hong Kong. Trans. Hong Kong Inst. Eng. 1995, 2, 9–16. [Google Scholar] [CrossRef]
  7. Code of Practice for Structural Use of Concrete 2013, 2020 ed.; Buildings Department, Hong Kong SAR Government: Hong Kong, China, 2020.
  8. CIRIA C660; Early-Age Thermal Crack Control in Concrete. CIRIA: London, UK, 2007.
  9. ACI 201.2R-16; Guide to Durable Concrete Reported by ACI Committee 201. ACI: Farmington Hills, MI, USA, 2016.
  10. CIRIA C766; Control of Cracking Caused by Restrained Deformation in Concrete. CIRIA: London, UK, 2018.
  11. Ng, P.L.; Ng, I.Y.T.; Kwan, A.K.H. Heat loss compensation in semi-adiabatic curing test of concrete. ACI Mater. J. 2008, 105, 52–61. [Google Scholar] [CrossRef]
  12. Lim, C.-K.; Kim, J.-K.; Seo, T.-S. Prediction of concrete adiabatic temperature rise characteristic by semi-adiabatic temperature rise test and FEM analysis. Constr. Build. Mater. 2016, 125, 679–689. [Google Scholar] [CrossRef]
  13. Ramu, Y.K.; Akhtar, I.; Santhanam, M. Use of adiabatic calorimetry for performance assessment of concretes. Adv. Cem. Res. 2016, 28, 485–493. [Google Scholar] [CrossRef]
  14. ACI 207.1R-96; Mass Concrete Reported by ACI Committee 207. ACI: Farmington Hills, MI, USA, 1996.
  15. Zhu, B. Thermal Stresses and Temperature Control of Mass Concrete; Tsinghua University Press: Beijing, China; Elsevier: Amsterdam, The Netherlands, 2014. [Google Scholar]
  16. Liu, P.; Li, Q.; Jia, P. A real time temperature data transmission approach for intelligent cooling control of mass concrete. Math. Probl. Eng. 2014, 2014, 514606. [Google Scholar] [CrossRef]
  17. Zhou, H.; Zhou, Y.; Zhao, C.; Wang, F.; Liang, Z. Feedback design of temperature control measures for concrete dams based on real-time temperature monitoring and construction process simulation. KSCE J. Civ. Eng. 2018, 22, 1584–1592. [Google Scholar] [CrossRef]
  18. Gajda, J.; Vangeem, M. Controlling temperatures in mass concrete. Concr. Int. 2002, 24, 58–62. [Google Scholar]
  19. Wen, T.-H.; Yuen, T.Y.P.; Li, V.K.S.; Yeung, A.T. A case study on early-age cracking of high-strength concrete construction by coupled thermal-mechanical analysis and field monitoring. Case Stud. Constr. Mater. 2024, 21, e03436. [Google Scholar] [CrossRef]
  20. Zou, X.K.; Chan, C.M. Optimal seismic performance-based design of reinforced concrete buildings using nonlinear pushover analysis. Eng. Struct. 2005, 27, 1289–1302. [Google Scholar] [CrossRef]
  21. Zou, X.K.; Chan, C.M.; Li, G.; Wang, Q. Multiobjective optimization for performance-based design of concrete structures. J. Struct. Eng. 2007, 133, 1462–1474. [Google Scholar] [CrossRef]
  22. Christensen, P.W.; Klarbring, A. An Introduction to Structural Optimization; Springer Science & Business Media: Berlin/Heidelberg, Germany, 2008; 214p. [Google Scholar]
  23. Taylor, H.F.W.; Famy, C.; Scrivener, K.L. Review: Delayed ettringite formation. Cem. Concr. Res. 2001, 31, 683–693. [Google Scholar] [CrossRef]
  24. Thomas, M.; Folliard, K.; Drimalas, T.; Ramlochan, T. Diagnosing delayed ettringite formation in concrete structures. Cem. Concr. Res. 2008, 38, 841–847. [Google Scholar] [CrossRef]
  25. Zeyad, A.M.; Tayeh, B.A.; Adesina, A.; de Azevedo, A.R.G.; Amin, M.; Hadzima-Nyarko, M.; Agwa, I.S. Review on effect of steam curing on behavior of concrete. Clean. Mater. 2022, 3, 100042. [Google Scholar] [CrossRef]
  26. Concrete Society Project Report No.3: In-Situ Strength of Concrete—An Investigation into the Relationship Between Core Strength and the Standard Cube Strength; BCA: Surrey, UK, 2004.
  27. Construction Standard CS1: 2010; Testing Concrete Volume 1 of 2. Civil Engineering and Development Department, Hong Kong SAR Government: Hong Kong, China, 2010.
  28. Huang, Y.; Liu, G.; Huang, S.; Rao, R.; Hu, C. Experimental and finite element investigations on the temperature field of a massive bridge pier caused by the hydration heat of concrete. Constr. Build. Mater. 2018, 192, 240–252. [Google Scholar] [CrossRef]
  29. Xie, Y.; Du, W.; Xu, Y.; Peng, B.; Qian, C. Temperature field evolution of mass concrete: From hydration dynamics, finite element models to real concrete structure. J. Build. Eng. 2023, 65, 105699. [Google Scholar] [CrossRef]
  30. HACON—A Program for Simulation of Hardening Concrete; Division of Structural Mechanics, Department of Construction Sciences, LTH Faculty of Engineering, Lund University: Lund, Sweden, 2015; Available online: https://www.byggmek.lth.se (accessed on 2 January 2024).
  31. Kwan, A.K.H.; Ling, S.K. Lowering paste volume of SCC through aggregate proportioning to reduce carbon footprint. Constr. Build. Mater. 2015, 93, 584–594. [Google Scholar] [CrossRef]
  32. Poon, C.S.; Lam, L.; Wong, Y.L. A study on high strength concrete prepared with large volumes of low calcium fly ash. Cem. Concr. Res. 2000, 30, 447–455. [Google Scholar] [CrossRef]
  33. Zhang, N.; Zuo, W.; Xu, W.; Song, S. A new approach for designing fluid concrete with low cement content: Optimization of packing density of aggregate. Material 2020, 13, 4082. [Google Scholar] [CrossRef]
  34. Han, F.; Zhu, Z.; Li, Y.; Pu, S.; Zhang, Z. Effect of ultrafine limestone powder on the hydration heat and rheological properties of Portland cement paste. Powder Technol. 2025, 454, 120717. [Google Scholar] [CrossRef]
Figure 1. Photographs of full-scale 3.0 m-diameter trial column.
Figure 1. Photographs of full-scale 3.0 m-diameter trial column.
Buildings 15 04256 g001
Figure 2. Layouts of cooling pipes and thermo-couples in trial column.
Figure 2. Layouts of cooling pipes and thermo-couples in trial column.
Buildings 15 04256 g002
Figure 3. Variation in temperature at Point A in trial column with time.
Figure 3. Variation in temperature at Point A in trial column with time.
Buildings 15 04256 g003
Figure 4. Temperature control regime for PC32 (a 3.0 m-diameter circular section column).
Figure 4. Temperature control regime for PC32 (a 3.0 m-diameter circular section column).
Buildings 15 04256 g004
Figure 5. Temperature control regime for PC31 (a 2.0 m-diameter circular section column).
Figure 5. Temperature control regime for PC31 (a 2.0 m-diameter circular section column).
Buildings 15 04256 g005
Figure 6. Temperature control regime for PC41 (a 1.5 m-thick rectangular section column).
Figure 6. Temperature control regime for PC41 (a 1.5 m-thick rectangular section column).
Buildings 15 04256 g006
Figure 7. Temperature control regime for PC30 (a 0.7 m-thick rectangular section column).
Figure 7. Temperature control regime for PC30 (a 0.7 m-thick rectangular section column).
Buildings 15 04256 g007
Figure 8. Temperature control regime for PC18 (a 2.0 m-thick irregular section column).
Figure 8. Temperature control regime for PC18 (a 2.0 m-thick irregular section column).
Buildings 15 04256 g008
Figure 9. Temperature control regime for PC27 (a 1.6 m-thick irregular section column).
Figure 9. Temperature control regime for PC27 (a 1.6 m-thick irregular section column).
Buildings 15 04256 g009
Table 1. Comparison of HACON results with respective values in CIRIA C660.
Table 1. Comparison of HACON results with respective values in CIRIA C660.
Example No.Wall Thickness (mm)Formwork TypePeak Temperature (°C)Temperature Differential (°C)
CIRIA C660HACONDifferenceCIRIA C660HACONDifference
1500Steel43.043.20.215.015.50.5
2500Plywood51.153.52.49.09.20.2
31000Steel59.762.02.328.329.00.7
41000Plywood64.066.42.418.519.30.8
Average 1.83 0.55
Table 2. Material properties of the C80 concrete assumed in the thermal analysis.
Table 2. Material properties of the C80 concrete assumed in the thermal analysis.
Material PropertyValueRemark
Placing temperature22 °CSpecified placing temperature and measured on site
Total cementitious content580 kg/m3Concrete mix design, according to concrete producer
Heat generation per cementitious content267 kJ/kgEstimated based on CIRIA C660
Mass density2400 kg/m3Concrete mix design, according to concrete producer
Thermal conductivity2.1 W/(m·°C)Estimated based on CIRIA C660
Specific heat capacity1000 J/(kg·°C)Estimated based on CIRIA C660
Table 3. Boundary parameters assumed in the thermal analysis.
Table 3. Boundary parameters assumed in the thermal analysis.
Boundary ParametersValueRemark
Boundary temperatureIncreases gradually to 20 °C above ambient temperature at 24 h after castingNo temperature control would be applied to the boundary surfaces. Under normal weather conditions, the boundary temperature would gradually increase to about 20 °C higher than the ambient temperature at 24 h after casting
Formwork4 mm-thick steel formworkActual formwork provided until 48 h
Thermal conductivity of steel formwork45 W/(m·°C)Typical value
Wrapping after removal of formwork1.5 mm-thick
polythene sheet
After striking of formwork at 48 h, polythene sheet wrapping is provided to avoid rapid cooling and drying
Thermal conductivity of polythene sheet0.38 W/(m·°C)Typical value
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Zou, X.; Huang, J.; Kwan, K.-h.; Hu, W.; Lu, W.; Zhao, Z.; Yang, C.; Liu, Y. Temperature Control of Massive High-Strength Concrete Columns During Curing—A Case Study in Hong Kong. Buildings 2025, 15, 4256. https://doi.org/10.3390/buildings15234256

AMA Style

Zou X, Huang J, Kwan K-h, Hu W, Lu W, Zhao Z, Yang C, Liu Y. Temperature Control of Massive High-Strength Concrete Columns During Curing—A Case Study in Hong Kong. Buildings. 2025; 15(23):4256. https://doi.org/10.3390/buildings15234256

Chicago/Turabian Style

Zou, Xiaokang, Jiang Huang, Kwok-hung Kwan, Wenjin Hu, Wenjie Lu, Zhen Zhao, Chen Yang, and Yaopeng Liu. 2025. "Temperature Control of Massive High-Strength Concrete Columns During Curing—A Case Study in Hong Kong" Buildings 15, no. 23: 4256. https://doi.org/10.3390/buildings15234256

APA Style

Zou, X., Huang, J., Kwan, K.-h., Hu, W., Lu, W., Zhao, Z., Yang, C., & Liu, Y. (2025). Temperature Control of Massive High-Strength Concrete Columns During Curing—A Case Study in Hong Kong. Buildings, 15(23), 4256. https://doi.org/10.3390/buildings15234256

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop