Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm
Abstract
1. Introduction
2. Materials and Methods
2.1. Analysis of the Production for Precast Concrete Components for Highway Project
2.1.1. Flow Shop Production for Precast Concrete Components
2.1.2. Layout of Production Lines
2.1.3. Production Characteristics of Precast Concrete Components for Highway Projects
2.2. Optimization Model for the Allocation of Production Equipment for Precast Concrete Components for Highway Projects
2.2.1. Basic Assumptions for the Allocation Model of Production Equipment
- (a)
- A machine is capable of processing only one part of a component at a time.
- (b)
- There is no priority in the processing of different components.
- (c)
- No other component process can be inserted while the current component is being processed.
- (d)
- Once a process is started, it must be completed before the next process can be carried out.
- (e)
- The processing sequence of components must follow the production flow.
- (f)
- No consideration is given to unexpected situations, such as machinery breakdown and maintenance.
- (g)
- The adjustment time for machinery and equipment and the transportation time of components between adjacent processes are included in the processing time of the corresponding process.
2.2.2. Optimization Model for the Allocation of Production Equipment
- (1)
- Constraints of the production machinery:
- (2)
- Constraints of the completion time
- (1)
- A the process that is interruptible and can only be performed during working hours: processing (M1), reinforcement assembling (M2), steel moldboard installation (M3), and moldboard hydraulic stripping (M5). Production tasks that are not completed during working hours are scheduled to continue the next day, and this is formulated in Equation (6).
- (2)
- A process that is not interruptible and can only be performed during working hours: concrete pouring and vibrating (M4) and grouting (M7). Production tasks that are not completed during working hours will not be scheduled on the initial day, but will be scheduled for the next day in terms of starting production. This situation is described in Equation (7).
- (3)
- A process that is not interruptible and is allowed to take place during non-working hours: steam curing (M6). Whereas the next process needs to be carried out during work hours, the end time for a production task completed during non-working hours will be set as the start time of the next day. The end time for a production task completed during work hours remains the same. Equation (8) expresses this case (Figure 4).
2.3. Improved Differential Evolution for the Optimization Model
2.3.1. Encoding
2.3.2. Population Initialization
2.3.3. Mutation Operations
2.3.4. Crossover Operation
2.3.5. Select Operation
3. Case Study
3.1. Case Profile
3.2. Simulation Analysis
3.2.1. Experimental Preparation
3.2.2. Experimental Results and Analysis
4. Discussion
5. Conclusions
5.1. Scientific Results
5.2. Applied Engineering Results
5.3. Limitations and Risks
5.4. Future Prospects
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Appendix A
Appendix A.1. Schedule Adjustments
| Time/h | Schedule/Month | Workpiece/Size | Amount of Equipment |
| [2, 3, 1, 1.5, 14, 16, 1] | 15 | 1920 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 15.5 | 1920 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 16 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 16.5 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 17 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 17.5 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18.5 | 1920 | [1, 2, 1, 1, 4, 4, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 19 | 1920 | [1, 2, 1, 1, 4, 4, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 19.5 | 1920 | [1, 2, 1, 1, 4, 4, 1] |
Appendix A.2. Adjustment of Component Quantity
| Time/h | Schedule/Month | Workpiece/Size | Amount of Equipment |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 1920 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 1950 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2000 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2050 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2100 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2150 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2200 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2250 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2300 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2320 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2330 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2335 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2350 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2400 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 18 | 2450 | [2, 2, 1, 2, 6, 6, 1] |
Appendix A.3. Production Efficiency in April
| Time/h | Schedule/Month | Workpiece/Size | Amount of Equipment |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 200 | [3, 4, 2, 3, 9, 9, 2] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 195 | [3, 4, 2, 3, 9, 9, 2] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 190 | [3, 4, 2, 3, 9, 9, 2] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 185 | [2, 3, 1, 2, 8, 8, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 180 | [2, 3, 1, 2, 8, 8, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 175 | [2, 3, 1, 2, 8, 8, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 170 | [2, 3, 1, 2, 8, 8, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 165 | [2, 3, 1, 2, 8, 8, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 160 | [2, 3, 1, 2, 7, 7, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 155 | [2, 3, 1, 2, 7, 7, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 150 | [2, 3, 1, 2, 7, 7, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 145 | [2, 3, 1, 2, 7, 7, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 140 | [2, 3, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 135 | [2, 3, 2, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 130 | [2, 3, 2, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 125 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 120 | [2, 2, 1, 2, 6, 6, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 115 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 110 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 105 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 100 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 95 | [2, 2, 1, 2, 5, 5, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 90 | [1, 2, 1, 1, 4, 4, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 85 | [1, 2, 1, 1, 4, 4, 1] |
| [2, 3, 1, 1.5, 14, 16, 1] | 30 | 80 | [1, 2, 1, 1, 4, 4, 1] |
References
- CPC Central Committee and State Council. Outline of the Construction of a Strong Transportation Country; CPC Central Committee and State Council: Beijing, China, 2019. [Google Scholar]
- China Speeds Up Building Modern Highway System; People’s Republic of China: Beijing, China. 2023. Available online: https://www.gov.cn/lianbo/bumen/202312/content_6921054.htm (accessed on 19 November 2025).
- Wang, Z.J.; Hu, H.; Gong, J. Framework for modeling operational uncertainty to optimize offsite production scheduling of precast components. Autom. Constr. 2018, 86, 69–80. [Google Scholar] [CrossRef]
- Ko, C.H.; Wang, S.F. Precast production scheduling using multi-objective genetic algorithms. Expert Syst. Appl. 2011, 38, 8293–8302. [Google Scholar] [CrossRef]
- Tengilimoglu, O.; Akyuz, U. Experimental study on hybrid precast tunnel segments reinforced by macro-synthetic fibres and glass fibre reinforced polymer bars. Tunn. Undergr. Space Technol. 2020, 106, 103612. [Google Scholar] [CrossRef]
- Jiang, W.; Wu, L.J. Flow shop optimization of hybrid make-to-order and make-to-stock in precast concrete component production. J. Clean. Prod. 2021, 297, 126708. [Google Scholar] [CrossRef]
- Ballard, G.; Harper, N.; Zabelle, T. Learning to see work flow: An application of lean concepts to precast concrete fabrication. Eng. Constr. Archit. Manag. 2003, 10, 6–14. [Google Scholar] [CrossRef]
- Huo, Z.; Wu, X.; Cheng, T. Scheduling Model for Prefabricated Component Assembly, Production, and Transportation Stage Based on GA for Prefabricated Buildings. IEEE Access 2024, 12, 60826–60838. [Google Scholar] [CrossRef]
- Heo, T.; Mallapragada, D.S.; Macdonald, R. A decomposition algorithm using multiple linear approximations to solve integrated design and scheduling optimization frameworks—Case study of nuclear based co-production of electricity and hydrogen. Comput. Chem. Eng. 2025, 202, 109213. [Google Scholar] [CrossRef]
- He, Q.-C.; Hong, T. Integrated facility location and production scheduling in multi-generation energy systems. Oper. Res. Lett. 2018, 46, 153–157. [Google Scholar] [CrossRef]
- Hong, J.K.; Shen, G.Q.; Mao, C.; Li, Z.D.; Li, K.J. Life-cycle energy analysis of prefabricated building components: An input-output-based hybrid model. J. Clean. Prod. 2016, 112, 2198–2207. [Google Scholar] [CrossRef]
- Liang, Y.; Xu, Z. Intelligent inspection of appearance quality for precast concrete components based on improved YOLO model and multi-source data. Eng. Constr. Archit. Manag. 2025, 32, 1691–1714. [Google Scholar] [CrossRef]
- Wang, Q.; Guo, Z.; Mei, T.; Li, Q.; Li, P. Labor crew workspace analysis for prefabricated assemblies’ installation: A 4D-BIM-based approach. Eng. Constr. Archit. Manag. 2018, 25, 374–411. [Google Scholar] [CrossRef]
- Zhang, H.; Yu, L. Dynamic transportation planning for prefabricated component supply chain. Eng. Constr. Archit. Manag. 2020, 27, 2553–2576. [Google Scholar] [CrossRef]
- Du, J.; Xue, Y.; Sugumaran, V.; Hu, M.; Dong, P. Improved biogeography-based optimization algorithm for lean production scheduling of prefabricated components. Eng. Constr. Archit. Manag. 2023, 30, 1601–1635. [Google Scholar] [CrossRef]
- Wang, S.Q.; Tang, J.; Zou, Y.Q.; Zhou, Q.H. Research on production process optimization of precast concrete component factory based on value stream mapping. Eng. Constr. Archit. Manag. 2020, 27, 850–871. [Google Scholar] [CrossRef]
- Weng-Tat, C.; Hao, H. An application of genetic algorithms to precast production scheduling. Comput. Struct. 2001, 79, 1605–1616. [Google Scholar] [CrossRef]
- Xie, L.-L.; Li, D.; Wu, S.; Chang, R.-D. Solving multi-mode resource-constrained scheduling problem of prefabricated construction using genetic algorithm. Eng. Constr. Archit. Manag. 2025; ahead of print. [Google Scholar] [CrossRef]
- Qin, X.; Fang, Z.; Zhang, Z. Multi-objective optimization for production scheduling of precast components considering resource constraints. Comput. Integr. Manuf. Syst. 2021, 27, 2248–2259. [Google Scholar]
- Leu, S.S.; Hwang, S.T. GA-based resource-constrained flow-shop scheduling model for mixed precast production. Autom. Constr. 2002, 11, 439–452. [Google Scholar] [CrossRef]
- Johnson, S.M. Optimal two- and three-stage production schedules with setup times included. Nav. Res. Logist. 1954, 1, 61–68. [Google Scholar] [CrossRef]
- Wang, Z.J.; Hu, H. Improved Precast Production-Scheduling Model Considering the Whole Supply Chain. J. Comput. Civ. Eng. 2017, 31, 04017013. [Google Scholar] [CrossRef]
- Ma, Z.L.; Yang, Z.T.; Liu, S.L.; Wu, S. Optimized rescheduling of multiple production lines for flowshop production of reinforced precast concrete components. Autom. Constr. 2018, 95, 86–97. [Google Scholar] [CrossRef]
- Cribbs, J.; Root, S. Defining an existing prefabrication workflow to identify measures for increased labour time utilization rates. IOP Conf. Ser. Mater. Sci. Eng. 2021, 1141, 012031. [Google Scholar] [CrossRef]
- Dan, Y.R.; Liu, G.W. Integrated scheduling optimization of production and transportation for precast component with delivery time window. Eng. Constr. Archit. Manag. 2024, 31, 3335–3355. [Google Scholar] [CrossRef]
- Wang, Z.J.; Hu, H.; Gong, J. Modeling Worker Competence to Advance Precast Production Scheduling Optimization. J. Constr. Eng. Manag. 2018, 144, 04018098. [Google Scholar] [CrossRef]
- Weng-Tat, C.; Tan Heng, W. A multiheuristic GA for schedule repair in precast plant production. In Proceedings of the Thirteenth International Conference on Automated Planning and Scheduling, Trento, Italy, 9–13 June 2003; pp. 236–245. [Google Scholar]
- Ko, C.H. Production control in precast fabrication: Considering demand variability in production schedules. Can. J. Civ. Eng. 2011, 38, 191–199. [Google Scholar] [CrossRef]
- Wang, Z.J.; Liu, Y.S.; Hu, H.; Dai, L. Hybrid Rescheduling Optimization Model under Disruptions in Precast Production Considering Real-World Environment. J. Constr. Eng. Manag. 2021, 147, 04021012. [Google Scholar] [CrossRef]
- Ying, K.-C.; Pourhejazy, P.; Lin, S.-C. An exploration of the shift work consideration in production scheduling. J. Comput. Sci. 2025, 92, 102724. [Google Scholar] [CrossRef]
- Wu, L.; Zhao, T.; Cai, X.; Cui, Z.; Chen, J. Dynamic multi-objective optimization for uncertain order insertion green shop production scheduling. Appl. Soft Comput. 2025, 182, 113573. [Google Scholar] [CrossRef]
- Du, Y.; Li, J.-Q.; Duan, P.-Y.; Geng, X.-X. A deep reinforcement learning driven bi-population evolutionary optimization for precast concrete scheduling with production transportation. Comput. Ind. Eng. 2025, 207, 111354. [Google Scholar] [CrossRef]
- Khalili, A.; Chua, D.K. Integrated Prefabrication Configuration and Component Grouping for Resource Optimization of Precast Production. J. Constr. Eng. Manag. 2014, 140, 04013052. [Google Scholar] [CrossRef]
- Yang, Z.T.; Ma, Z.L.; Wu, S. Optimized flowshop scheduling of multiple production lines for precast production. Autom. Constr. 2016, 72, 321–329. [Google Scholar] [CrossRef]
- Li, S.H.A.; Tserng, H.P.; Yin, S.Y.L.; Hsu, C.W. A production modeling with genetic algorithms for a stationary pre-cast supply chain. Expert Syst. Appl. 2010, 37, 8406–8416. [Google Scholar] [CrossRef]
- Ko, C.H.; Wang, S.F. GA-based decision support systems for precast production planning. Autom. Constr. 2010, 19, 907–916. [Google Scholar] [CrossRef]
- Glover, F. Tabu search. ORSA J. Comput. 1989, 1. Available online: https://link.springer.com/book/10.1007/978-1-4615-6089-0 (accessed on 19 November 2025). [CrossRef]
- Holland, J.H. Adaptation in Natural and Artificial Systems; University of Michigan: Ann Arbor, MI, USA, 1975; pp. 529–530. [Google Scholar]
- Dorigo, M.; Maniezzo, V.; Colorni, A. Ant system: Optimization by a colony of cooperating agents. IEEE Trans. Syst. Man Cybern. Part B 1996, 26, 29–41. [Google Scholar] [CrossRef]
- Chan, W.T.; Hu, H. Production scheduling for precast plants using a flow shop sequencing model. J. Comput. Civ. Eng. 2002, 16, 165–174. [Google Scholar] [CrossRef]
- Zhang, J.Q.; Sanderson, A.C. JADE: Adaptive Differential Evolution with Optional External Archive. IEEE Trans. Evol. Comput. 2009, 13, 945–958. [Google Scholar] [CrossRef]
- Storn, R.; Price, K. Differential Evolution—A Simple and Efficient Heuristic for global Optimization over Continuous Spaces. J. Glob. Optim. 1997, 11, 341–359. [Google Scholar] [CrossRef]
- Vincent, A.M.; Parthasarathy, K.S.S.; Jidesh, P. Flood susceptibility mapping using AutoML and a deep learning framework with evolutionary algorithms for hyperparameter optimization. Appl. Soft Comput. 2023, 148, 110846. [Google Scholar] [CrossRef]
- Tian, Y.; Li, T. Power optimization method for wireless power transmission system based on improved differential evolution algorithm. IOP Conf. Ser. Mater. Sci. Eng. 2020, 768, 042035. [Google Scholar] [CrossRef]
- Mayo, M. Identifying Market Price Levels Using Differential Evolution. In Applications of Evolutionary Computation: Proceedings of the 16th European Conference (EvoApplications 2013), Vienna, Austria, 3–5 April 2013; Springer: Berlin/Heidelberg, Germany, 2012; pp. 203–212. [Google Scholar]
- Seng, J.; Zhang, L. ESG ratings and corporate clean production from the perspective of evolutionary game theory: Evidence from A-share listed companies. Energy Econ. 2025, 152, 108989. [Google Scholar] [CrossRef]
- Cao, G.; Zhang, Q.; Zhang, P. Multicore-based parallelized differential evolution for image registration. Comput. Eng. Appl. 2017, 53, 166–172. [Google Scholar] [CrossRef]
- Tian, S.; Zhao, Z.; Du, S. Energy-saving optimal scheduling based on improved multiobjective differential evolution algorithm. Eng. J. Wuhan Univ. 2019, 52, 1091–1096+1105. [Google Scholar]
- Dugast, F.; Bénac, S.; Marty, P.; Chessé, P. Multiple optimal solutions in synthesis, design and operation optimization of a marine energy system with the differential evolution algorithm. Ocean Eng. 2025, 328, 121064. [Google Scholar] [CrossRef]
- Chi-Hua, T.; Meng-Hui, C.; Chia-Yu, H.; Pei-Chann, C. Differential evolutionary algorithms with novel mutation operator for solving the permutation flowshop scheduling problem. In Proceedings of the 2015 International Conference on Control, Automation and Robotics, Singapore, 20–22 May 2015. [Google Scholar]
- Qi, X.; Wang, H.; Chen, F.; Tang, Q.; Sun, Y. Novel quantum differential evolutionary algorithm for blocking flow-shop scheduling. J. Comput. Appl. 2015, 35, 663–667. [Google Scholar]
- Wenbo, L. An improved differential evolution for permutation flowshop scheduling problem with total flowtime criterion. In Proceedings of the 2012 3rd International Conference on System Science, Engineering Design and Manufacturing Informatization, Chengdu, China, 20–21 October 2012. [Google Scholar]
- Babu, B.V.; Chakole, P.G.; Syed Mubeen, J.H. Multiobjective differential evolution (MODE) for optimization of adiabatic styrene reactor. Chem. Eng. Sci. 2005, 60, 4822–4837. [Google Scholar] [CrossRef]
- Xu, B.; Cheng, W.; Qian, F.; Huang, X. Self-adaptive differential evolution with multiple strategies for dynamic optimization of chemical processes. Neural Comput. Appl. 2019, 31, 2041–2061. [Google Scholar] [CrossRef]
- Hruschka, E.R.; Campello, R.J.; Freitas, A.A. A Survey of Evolutionary Algorithms for Clustering. IEEE Trans. Syst. Man Cybern. Part C 2009, 39, 133–155. [Google Scholar] [CrossRef]
- Cui, Z.; Zhao, B.; Zhao, T.; Cai, X.; Chen, J. An adaptive differential evolution algorithm based on archive reuse. Inf. Sci. 2024, 668, 120524. [Google Scholar] [CrossRef]
- Bu, X.; Zhang, Q.; Gao, H.; Zhang, H. Multi-strategy differential evolution algorithm based on adaptive hash clustering and its application in wireless sensor networks. Expert Syst. Appl. 2024, 246, 123214. [Google Scholar] [CrossRef]
- Zhao, H.; Zhan, Z.-H.; Lin, Y.; Chen, X.; Luo, X.-N.; Zhang, J.; Kwong, S.; Zhang, J. Local Binary Pattern-Based Adaptive Differential Evolution for Multimodal Optimization Problems. IEEE Trans. Cybern. 2020, 50, 3343–3357. [Google Scholar] [CrossRef]
- Zhang, Q.; Meng, Z. Adaptive differential evolution algorithm based on deeply-informed mutation strategy and restart mechanism. Eng. Appl. Artif. Intell. 2023, 126, 107001. [Google Scholar] [CrossRef]
- Tan, Z.; Li, K.; Wang, Y. Differential evolution with adaptive mutation strategy based on fitness landscape analysis. Inf. Sci. 2021, 549, 142–163. [Google Scholar] [CrossRef]
- Mostafa, R.R.; Khedr, A.M.; Al Aghbari, Z.; Afyouni, I.; Kamel, I.; Ahmed, N. An adaptive hybrid mutated differential evolution feature selection method for low and high-dimensional medical datasets. Knowl. Based Syst. 2024, 283, 111218. [Google Scholar] [CrossRef]
- Chen, B.; Ouyang, H.; Li, S.; Ding, W. Dual-stage self-adaptive differential evolution with complementary and ensemble mutation strategies. Swarm Evol. Comput. 2025, 93, 101855. [Google Scholar] [CrossRef]
- Zeng, N.S.; Ye, X.L.; Liu, Y.; König, M. BIM-enabled Kanban system in construction logistics for real-time demand reporting and pull replenishment. Eng. Constr. Archit. Manag. 2024, 31, 3069–3096. [Google Scholar] [CrossRef]
- Jaspers, F. Case study research: Some other applications besides theory building. J. Purch. Supply Manage. 2007, 13, 210–212. [Google Scholar] [CrossRef]






| No. | Authors | Methodology | Limitations to Consider in Scheduling | Research Topics |
|---|---|---|---|---|
| 1 | [21] | Easy, correct algorithms | - | Investigation of optimal two- and three-stage production scheduling strategies, including setup times |
| 2 | [40] | GA | - | Model of flow shop sequencing, to ensure on-time delivery of PCs |
| 3 | [35] | GA and branch-and-bound method | Labor and inventory | Optimization of precast production costs subject to internal resource constraints |
| 4 | [30] | GA | Production stations | Proposal of a decision support system to optimize production plans |
| 5 | [33] | Mixed integer linear programming model | Molds | Proposal of an integrated prefabrication configuration and component grouping approach for resource optimization in precast production |
| 6 | [28] | GA | Molds | Proposal of an optimized flow shop scheduling method for multiple production lines in precast production |
| 7 | [26] | GA | - | Consideration of demand variability using a pure optimization model |
| 8 | [6] | Whale optimization algorithm | - | Investigation of flow shop optimization methods for hybrid make-to-order and make-to-stock production in precast concrete component manufacturing |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Qian, Y.; Mao, N.; Yu, J.; Shi, Q. Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm. Buildings 2025, 15, 4226. https://doi.org/10.3390/buildings15234226
Qian Y, Mao N, Yu J, Shi Q. Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm. Buildings. 2025; 15(23):4226. https://doi.org/10.3390/buildings15234226
Chicago/Turabian StyleQian, Yelin, Nianzhang Mao, Jingyu Yu, and Qingyu Shi. 2025. "Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm" Buildings 15, no. 23: 4226. https://doi.org/10.3390/buildings15234226
APA StyleQian, Y., Mao, N., Yu, J., & Shi, Q. (2025). Optimization of Precast Concrete Production with a Differential Evolutionary Algorithm. Buildings, 15(23), 4226. https://doi.org/10.3390/buildings15234226
