Next Article in Journal
Thermal Performance of LSF Wall Systems with Vacuum Insulation Panels
Previous Article in Journal
Behaviour of Lightweight Concrete Wall Panel under Axial Loading: Experimental and Numerical Investigation toward Sustainability in Construction Industry
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Analysis of Formwork System Selection Criteria for Building Construction Projects: A Comparative Study

Department of Civil Engineering, Istanbul Technical University, Istanbul 34469, Turkey
*
Author to whom correspondence should be addressed.
Buildings 2021, 11(12), 618; https://doi.org/10.3390/buildings11120618
Submission received: 1 November 2021 / Revised: 30 November 2021 / Accepted: 2 December 2021 / Published: 6 December 2021
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

:
The formwork system (FWS) in reinforced concrete (RC) construction is a critical component. The appropriate FWS is selected based on a number of conflicting and compromising criteria, and the selection of the FWS is carried out by construction professionals with different technical and/or administrative backgrounds. The perspectives and perceptions of construction professionals and companies involved in the FWS selection process may vary depending on their motives. In addition, some building structural parameters may have a significant impact on the FWS selection criteria. Most of the former studies investigated the FWS selection criteria from only the perspective of contractors and neglected the potential differences in the perspectives and perceptions of different construction professionals (i.e., owners (CO), project managers (PM), construction managers (CM), site engineers (SE), planning engineers (PL), procurement engineers (PR), technical office engineers (TO), and formwork design and/or formwork sales engineers (FD/FSL)) and companies specialized in different fields (i.e., project management service (PMS), engineering and design (ENG/DSG), formwork and scaffolding (FW/SCF), and general and/or sub-contractor (GC/SC)) regarding this issue. Moreover, the impact of building structural parameters on the FWS selection criteria has not been investigated. This study aims to fill this knowledge gap through analysing the FWS selection criteria for building construction projects while comparing the perspectives and perceptions of different groups of construction professionals and companies and investigating how FWS selection criteria are affected by the building structural parameters. Based on a comprehensive literature review, 35 FWS selection criteria were identified and a questionnaire was developed. The questionnaire data obtained from 222 Turkish construction professionals were statistically analysed using mean score analysis, the Kruskal–Wallis test, and the Mann–Whitney U test. According to the study’s findings, the FD/FSL group presented significant statistical differences regarding the FWS selection criteria as compared to the CO, PM/CM/SE, and PL/PR/TO groups. Moreover, the total area of building construction and total building height significantly affected the FWS selection criteria. This study serves to underscore the perspectives of various groups of construction professionals and the critical connection between the structural parameters and FWS selection criteria. The findings of this study may guide construction professionals to select the appropriate FWS for their building construction projects.

1. Introduction

RC construction involves repetitive activities, with formwork, rebar, and concrete being the main components of these activities in building construction projects [1]. Formwork accounts for a major part of the RC structure’s cost [2]. For instance, the selected FWS may contribute to up to two-thirds of the entire cost of the RC structural frame [3] and 10% of the total construction cost [4]. In Turkey, the labour cost of formwork accounts for 10 to 15% of the total cost of a building construction project [5]. Advancements in formwork engineering may significantly reduce the cost and material waste while improving the potential of a project’s success [6]. In addition, the selected FWS may have a significant impact on the project’s overall duration [7] as well as the safety and quality of a building construction project [8]. Therefore, as RC construction developed, construction professionals in the field of formwork engineering were required to provide solutions by developing new FWSs [9]. The FWS may be selected based on a variety of criteria, some of which are interdependent [10]. Furthermore, the relative importance level of the FWS selection criteria, and thus the selection of the appropriate FWS, may depend on the perception of different project stakeholders, such as contractors [11], or on the perception of different construction professionals, such as formwork planning engineers [12].
Most of the previous studies in the relevant literature identified, ranked, and analysed FWS selection criteria based on a certain group of construction professionals or stakeholders [7,11,12]. In addition, few studies have compared the perspectives and perceptions regarding the relative importance level of FWS selection criteria among a particular group of respondents (e.g., contractors) [13]. However, no prior study has investigated whether there are any significant statistical differences/disagreements in the relative importance of FWS selection criteria among different groups of construction professionals and/or companies. Moreover, some building structural parameters (e.g., total building area, total building height) of the building construction project may significantly affect the FWS design and selection [14,15]. Hence, the effects, if any, of the building structural parameters on the FWS selection criteria may reveal some valuable insights for construction professionals in their decision-making process.
As the selection of the FWS is considered as a difficult task and requires the early involvement of all the stakeholders in the early phases of a project (e.g., formwork fabricator (FWF)) [16], analysing the perspectives and perceptions of different groups of construction professionals and companies regarding the FWS selection criteria may improve the project performance factors. The main objectives of this study include (1) comparing the perspectives and perceptions of the different groups of construction professionals and companies on the FWS selection criteria, and (2) identifying the effects of the building structural parameters on the FWS selection criteria. The results of this study can also be used by decision-makers and construction professionals involved in the selection process of FWSs.

2. Literature Review

Throughout the twentieth century, formwork engineering developed in lockstep with the expansion of concrete construction [17]. The developments and technological advancements in formwork engineering led to the widespread use of industrial FWSs across the world [18]. Since there are many FWSs available, the selection of the appropriate FWS depends on various compromising and conflicting criteria [7,19]. Therefore, a number of quantitative and qualitative criteria have been identified in previous studies that may affect the selection of FWSs in building construction projects. The majority of these studies have identified and/or ranked the FWS selection criteria [13,20], while others have employed multi-criteria-decision-making (MCDM) methods to solve the FWS selection problem [2,21]. The following is a brief chronological summary of these studies.
Initially, Hanna [22] identified 38 factors for the FWS selection problem in building construction projects in the United States and grouped them into four categories based on expert opinion: building design, job specification, local conditions, and supporting organisation. Then, Hanna and Sanvido [23] developed an interactive expert system for the vertical FWS selection problem, specifically for contractors, based on Hanna’s [22] factors and FWS alternatives. Analogously, the study by Hanna et al. [24] provided a rule-based expert system for decision-makers and formwork design engineers to select the most appropriate FWS (e.g., horizontal and vertical FWS) in building construction projects. Building structural parameters, such as the total building height, total area of building construction, and typical building floor area, were introduced as factors affecting the FWS selection [20,22,23,24]. Selecting the appropriate FWS can be a complex process [7]. Therefore, neural network (NN) models [2,25,26,27] and decision tree (DT) models [7,28] have been developed to solve the FWS selection problem based on the factors identified by Hanna’s [22] study. In these studies, additional building structural parameters affecting the FWS selection, such as floor area and number of floors, were incorporated into the relevant literature. Hanna [20] introduced labour productivity as an additional factor to the relevant literature in an extended version of the previously stated rules and guidelines for selecting FWSs. Proverbs et al. [13] analysed and compared the relative importance levels of nine factors affecting FWS selection among contractors and planning engineers from the UK, France, and Germany and determined the degree of agreement between them. Jarkas [29] measured the labour productivity of the selected FWS based on building structural parameters. Elbeltagi et al. [21] and Elbeltagi et al. [30] presented fuzzy logic models to select horizontal and vertical FWSs, respectively, based on the five most important FWS selection factors for Egyptian formwork engineering experts.
From 1989 to 2012, the majority of the studies regarding the FWS selection problem focused on the FWS selection criteria under the four main groups presented by Hanna [24]. Novel challenges in architectural and structural design, such as those in free-form concrete buildings with irregular and curved geometries, required new developments in formwork technology [31]. In addition, the popularity of industrial FWSs in building construction projects throughout the world, along with the introduction of new FWSs [32], prompted the inclusion of additional FWS selection criteria in the years that followed. For example, Krawczyska-Piechna [33], Krawczyska-Piechna [34], and Krawczyska-Piechna [35] extended the relevant literature by proposing FWS flexibility, durability, compatibility, safety, and weight as additional criteria focusing on contractor preferences in Poland. In the context of the FWS safety criterion, since on-site formwork activities (e.g., erecting, stripping, or moving of the FWS) are associated with a high level of accidents [36], research on the safety aspects of these activities [37] and the safety of the FWS has gained more importance in the field of construction management. Furthermore, the compatibility and durability of the FWS may be critical factors when selecting an appropriate FWS [38]. Jiang et al. [39] introduced floor-to-floor height as a building structural parameter to the literature and used it for developing a DT model for the FWS selection problem. Martinez et al. [40] utilized the Choosing by Advantages (CBA) method with 14 selection factors for the FWS selection problem in Ecuador based on the knowledge of a team of project managers, planning engineers, and procurement engineers. FWS complexity and FWS size were added into the literature as new FWS selection factors. Radziejowska and Sobotka’s [41] study incorporated the expertise of site managers and contractors in Poland, and eight FWS selection criteria for vertical FWS were identified. In their study, some criteria were related to the characteristics of the FWS, such as FWS durability, weight, and size. Hence, the majority of these recently identified criteria may be grouped under a new category, namely FWS characteristics, because they describe the different properties of the FWS. Loganathan and Viswanathan [42] evaluated the effects of FWS alternatives on the cost, time, and quality performance of high-rise building construction projects in India.
As material waste in RC construction is common [43,44], the sustainability of the FWS has become an important factor in recent years [45]. In addition, building information modelling (BIM) applications used in formwork engineering can greatly improve the sustainability of a project [46]. Therefore, some recent studies introduced the degree of formwork material recycling (i.e., FWS sustainability) and the degree of BIM applications for FWSs (i.e., FWF BIM support) to the relevant literature [4]. For instance, Singh et al. [47] used a BIM approach to automate the design and selection process of the FWS by utilizing some building structural parameters (e.g., floor height) in their model. Basu and Jha [12] used factor analysis to group the FWS selection criteria identified by Hanna et al. [24] and analytical hierarchy process (AHP) to determine the most significant FWS selection criterion groupings for formwork planning engineers in India. Similarly, Rajeshkumar and Sreevidya [48] and Rajeshkumar et al. [17] identified and grouped 40 FWS selection criteria into five categories by utilizing factor analysis and investigated the degree of agreement regarding the FWS selection criteria among clients, contractors, and consultants in the Indian building construction sector. Transportation cost was also introduced as a new criterion for selecting FWSs. Pawar et al. [49] and Teja et al. [50] determined the relative importance index (RII) of previously identified FWS selection criteria for different FWS alternatives commonly used in India. Lohana’s [51] study revealed that the productivity criterion for selecting FWSs in building construction projects can be quantified as a function of cost, cycle time, and the degree of repetition of FWS. Ray et al. [52] performed a break-even analysis on two commonly used industrial FWSs in India, considering the total cost of the FWS by incorporating the degree of repetition, initial cost, and maintenance cost of the FWS in their calculation. Huszar and Lubloy [53] compared the cost of the FWS to the total cost of a building construction project while citing the initial cost of the FWS, speed of construction, FWS flexibility, and FWS safety as attributes of the selected FWS. Rajeshkumar et al. [54] compared the cost, time, productivity, and quality performance factors of three commonly used FWSs in building construction projects. Terzioglu et al. [10] carried out a critical review of the literature on FWS selection criteria for building construction projects, identifying 35 FWS selection criteria in total and demonstrating that several structural design criteria are interdependent with FWS characteristics-related criteria.
In the literature, several researchers focused on identifying the FWS selection criteria and/or determining their relative importance levels through interviews with experts and questionnaire surveys conducted in different countries, such as Korea, UK, France, Germany, India, Egypt, and Ecuador [7,13,17,21,30,40]. However, there has been no study conducted in order to identify and/or rank the FWS selection criteria in the Turkish building construction sector. The Turkish construction sector has an annual GDP share of 5 to 6.5% and an employment share of 5 to 7% [55]. In addition, Turkish contractors have completed 10,725 projects in 128 countries, with a total value of 424.5 billion US dollars from 1971 to 2021 [56]. In 2020, Turkish contracting companies have undertaken 348 projects in 57 countries with a total value of 15.1 billion US dollars [56]. Moreover, according to Engineering News-Record (ENR), 44 Turkish construction companies were listed among the top 250 international contractors in 2020, placing Turkish contractors in the second place after China [57]. Therefore, there is a need to identify and/or rank the FWS selection criteria in the Turkish building construction sector. This issue raises a research question:
-
Q1: Which of the identified FWS selection criteria are being considered by the companies and construction professionals in their decision-making process, and what are the relative importance levels of these FWS selection criteria in the Turkish building construction sector?
The supply chain activities associated with formwork and the selection of the FWS may be performed by different project stakeholder groups (e.g., engineer, contractor, FWF) at different phases of a building construction project [16]. In addition, stakeholders, such as contractors, may be more inclined to minimize the cost and maximize the quality and safety of the FWS [3], while FWFs may mostly be concerned with the technical and design aspects of the FWS [58]. Therefore, FWS selection may vary depending on the perspectives and perceptions of the different project stakeholder groups. However, the majority of the former studies concentrated solely on the contractors or their employees as project stakeholder groups [11,13,33,34,35]. Moreover, none of these studies have investigated if any disagreements exist among different groups of construction professionals and/or companies regarding the importance level of the FWS selection criteria. Potential differences in the perspectives and perceptions of different project stakeholder groups (i.e., construction professionals and companies) on the importance levels of the FWS selection criteria raise two important questions.
-
Q2: What are the differences, if any, in the relative importance levels of FWS selection criteria according to the “professional title” of the construction professionals?
-
Q3: What are the differences, if any, in the relative importance levels of FWS selection criteria according to the “field of specialization” of the companies?
These are legitimate research questions to address because identifying the agreements or disagreements regarding FWS selection criteria among all the stakeholder groups can improve the selection process and thereby the overall project performance by taking their perspectives and perceptions into account at the early phases of the project.
It is generally claimed that building structural parameters (i.e., typical building floor area, total area of building construction, typical building floor-to-floor height, total building height) play a significant role in the FWS selection process [7,26,30,50]. For example, conventional FWSs are suitable for buildings with a total building height up to 36.5 m (i.e., low-rise buildings) [2,24] and a floor-to-floor height less than 5 m [30]. As another example, modern and modular FWSs (i.e., industrial FWSs) are typically suitable for a total building height greater than 36.5 m (i.e., mid-rise and/or high-rise buildings) [4,20,24,25,49] and a floor-to-floor height greater than 4–5 m [14,20]. Similarly, conventional FWSs are usually selected if the total area of construction is less than 20,000 m2, and industrial FWSs are selected if the total area of construction is more than 20,000 m2 [20,26]. As a result, changes in the values of the building structural parameters have a significant impact on the FWS selection process.
The selection of an appropriate FWS is based on a number of conflicting and compromising criteria. Therefore, changes in the values of the building structural parameters may affect the importance levels of the FWS selection criteria. However, no research has been conducted to investigate how the importance levels of FWS selection criteria differ depending on the changes in the values of the building structural parameters. This is a research gap. This potential relationship raises another research question:
-
Q4: What are the differences, if any, in the relative importance levels of FWS selection criteria according to the changes in the values of the “building structural parameters” (e.g., building type, total building area, total building height, typical building floor area, typical building floor-to-floor height)?
Finally, the most critical FWS selection criteria should be identified. In this context, the final research question is:
-
Q5: What are the critical FWS selection criteria in building construction projects?
The main objective of this study is to answer these research questions and to fill the important knowledge gap by comparing the perspectives and perceptions of different construction professionals and stakeholder groups in building construction projects in Turkey, and analysing the FWS selection criteria in relation to some building structural parameters and to determine how the importance levels of the FWS selection criteria differ according to the changes in the values of the building structural parameters.

3. Research Methodology

Initially, a thorough review of the relevant literature was conducted to identify the FWS selection criteria for building construction projects. Then, a questionnaire was developed as the main research instrument to answer the aforementioned five research questions. This section describes the research methodology for analysing the FWS selection criteria in building construction projects in Turkey. The research methodology of this study consists of five main stages, which are: (1) identification of FWS selection criteria, (2) design of the questionnaire, (3) data collection, (4) data analysis, and (5) discussion. The flowchart of the research methodology is shown in Figure 1.

3.1. Identification of FWS Selection Criteria

Following a comprehensive review of the literature, a list of 35 FWS selection criteria for building construction projects was identified. Figure 2 illustrates the identified FWS selection criteria from the literature review along with their related ID numbers and the number of citations. The study by Terzioglu et al. [10] provides a detailed description of each of these FWS selection criteria, as well as a critical review of the relevant literature. In addition, Terzioglu et al. [10] validated the identified FWS selection criteria through face-to-face interviews with several experts from the Turkish construction sector. As a result, the FWS selection criteria of this study are based on the findings of Terzioglu et al. [10], which include all previously identified FWS selection criteria in a single body of knowledge.

3.2. Design of the Questionnaire

Questionnaires are frequently used in construction management studies [59,60] as an effective tool for researchers to collect quantitative data and utilize statistical methods to gain insights into personal perceptions and organisational policies and practices [61,62]. The questionnaire was developed using the FWS selection criteria identified through the literature review. The demographic information was presented at the beginning of the questionnaire to provide insight on the respondents’ and company background (e.g., “professional title”, “field of specialization”) and ensure accurate responses.
The questionnaire’s main body was divided into two sections. The first section was intended to obtain specific qualitative (e.g., building type) and quantitative (e.g., typical building floor area, typical building floor-to-height) information on the building construction project in which the respondents are presently working. In the second section, respondents were asked to rank the relative importance of each of the 35 FWS selection criteria in respect to the current building construction project on which they are participating. To evaluate the relative importance of each FWS selection criterion in the decision-making process, an ordinal six-point Likert scale was adopted (0—not considered, 1—not important, 2—slightly important, 3—moderately important, 4—very important, and 5—extremely important). Using a six-point Likert scale in questionnaires results in higher convergent validity when compared to four-point or five-point Likert scales [63,64]. In addition, there is a slight difference in the response rates between six-point and seven-point Likert scales [65]. Hence, this study adopted a six-point Likert scale, which was successfully used in the construction management studies, e.g., [66].
The questionnaire was designed using Google Forms, which is a prominent and frequently used online survey system in managerial sciences [59,67]. Then, the questionnaire was reviewed by three experts, who have more than 20 years of international experience in both technical and administrative aspects of formwork engineering, before distributing the questionnaires. The experts were asked to validate the identified FWS selection criteria and approve the appropriateness of the questionnaire structure and questions. The suggestions of these experts related to the applicability of the FWS selection criteria, and the appropriateness of the questionnaire’s structure and questions were carefully considered by the authors. Necessary revisions were made in the questionnaire when applicable. The questions were kept simple, and leading questions were avoided. The wording and the order of the questions were checked by the authors and these experts in order to minimize the response bias.

3.3. Data Collection

The targeted respondents of this study included the construction professionals, who may be in charge of selecting the FWSs in the Turkish building construction sector. These professionals may be company owners (CO), project managers (PM), construction managers (CM), site engineers (SE), planning engineers (PL), procurement engineers (PR), technical office engineers (TO), and formwork design and/or formwork sales engineers (FD/FSL). Moreover, these construction professionals may be the employees of companies specialized in different fields (i.e., stakeholder groups), such as project management service (PMS), engineering and design (ENG/DSG), formwork and scaffolding (FW/SCF), and general and/or sub-contractor (GC/SC). It should be noted that COs may own either PMS, ENG/DSG, FW/SCF, or GC/SC companies.
The population number in this study is extracted from the statistics produced by Turkish Statistical Institute (TUIK), which indicate that the number of paid employees in the building construction sector in Turkey is 890,000 [68]. In this study, random sampling technique, which is widely used in the construction management field and where the sample is randomly selected from the population based on non-zero probability, was used for selecting the participants [69]. This sampling technique is found to be effective as the sample represents the population accurately by avoiding any voluntary response bias [70].
The sample size formula (Equation (1)) [71] is a widely used equation to determine sample sizes in the field of construction management [72]. Utilizing the sample size formula, with a population size of 890,000, a significance level of α = 0.05, a sample proportion of 0.5, and a 7% margin of error, the required sample size was determined to be n = 196.
n r e q = Ζ 2 p ( 1 p ) e 2 = 1.96 2 × 0.5 × 0.5 ( 0.07 ) 2 = 196
where nreq is the required sample size, Z is the critical value of the normal distribution at α/2, p is the sample proportion (i.e., expected prevalence), and e is the margin of error (i.e., precision). Although 5% margin of error is commonly used, researchers may increase this value depending on the characteristics of the research [73] up to 9% [68]. Margin of error higher than 5% was adopted by researchers in the field of construction management [69,72].
The survey link was delivered electronically to over 2500 respondents in Turkey through the Union of Chambers of Turkish Engineers and Architects (UCTEA) and the Association of Formwork and Scaffold Manufacturers (IKSD). A total of 244 responses were obtained, and, out of 244 responses, 22 questionnaires were eliminated due to invalid responses (i.e., all FWS selection criteria were ranked with the same importance level), resulting in a total of 222 valid questionnaires with a response rate of 9% for data analysis. Since a sample size of n = 222 is higher than the required sample size of 196, the sample size was found to be satisfactory for data analysis. In general, response rates can be low in questionnaires related to construction management studies [74,75]. For example, Fahmy et al. [76] and Goh and Abdul-Rahman [77] reported response rates 4.1% and 7.5%, respectively. In addition, the relatively low response rates may be attributed to the fact that FWS selection is dependent on the experience of decision-makers in the field of formwork engineering, which may be not as common as other types of construction experience. When compared to previous related studies on FWS selection criteria, this sample size may be regarded as acceptable [17,30]
The data from the questionnaire were grouped into certain groups of “professional titles” based on the respondents’ similar demographic backgrounds. In building construction projects, for instance, since the PM, CM, and SE usually execute the project as employees of the contractor (e.g., GC/SC group) on-site, they may be considered an on-site construction team (i.e., PM/CM/SE group and/or GC/SC group). In contrast, the PL, PR, and TO engineers can be considered technical and administrative support, and thus an off-site team (i.e., PL/PR/TO group) [78]. Moreover, in building construction projects, the organisational structure typically separates the off-site design team (i.e., TO) from the on-site construction team [79]. The demographic information of the respondents and respondents’ company are provided in Table A1 and Table A2, respectively.
In addition to the demographic background information, the respondents were asked to provide quantitative information on the “building structural parameters” (e.g., typical building floor area, typical building floor-to-height) of the construction project in which the respondents are presently working. The information on the “building structural parameters” is shown in Table A3.

3.4. Data Analysis

The valid questionnaire data were stored and analysed with the Statistical Package for Social Sciences (IBM SPSS, Version 28.0). In general, non-parametric tests are used to infer the population distribution of a known sample of data with an unknown distribution [80]. In addition, non-parametric tests can be used when the independently sampled groups have unequal sizes of respondents [81]. Since the data from the questionnaire were collected on an ordinal measurement scale (e.g., Likert scale) and had a non-normal distribution with unequal sizes of independently sampled groups, non-parametric statistical tests were employed to analyse the data [82]. A 95% confidence level (or 5% significance level) was considered in the non-parametric test utilized in this study. The following are brief descriptions of the methods and statistical tests utilized in this study:

3.4.1. Reliability and Validity Analysis of the Questionnaire

The reliability and validity of a questionnaire can be used to analyse its characteristics as a measuring instrument [83]. Reliability refers to the degree to which a measurement instrument is biased or conveys accurate and consistent results [84]. Cronbach’s α is an internal consistency measure that is commonly used in reliability testing [82,85]. This study used Cronbach’s α coefficient to test the reliability of the questionnaire data, and it was determined using Equation (2):
α = k k 1 ( 1   σ i 2 σ x 2 )
where k is the total number of items, σ i 2 is the item variance, and σ X 2 is the variance of the sum of scores. The Cronbach’s α coefficient was calculated for the 35 FWS selection criteria. Cronbach’s α coefficient values typically range from 0 to 1, with a value larger than 0.70 being considered acceptable [86]. The Cronbach’s α coefficient for all 35 FWS selection criteria is 0.973 (i.e., α > 0.70), which is considered to indicate excellent internal consistency in the dataset [87].
Validity is the extent to which research is accurate [88]. Content validity and construct validity are two of the most prominent types of validity in business research [83,84]. Content validity can be provided by developing the questionnaire based on previous studies [59]. Hence, an extensive literature review on the FWS selection criteria provides content validity in this study’s questionnaire. In addition, the questionnaire was distributed after a review by three experts in formwork engineering, ensuring the questionnaire’s content validity.
Construct validity is a method of determining whether a questionnaire instrument measures what it intends to measure [89]. To ensure construct validity, the Kaiser–Meyer–Olkin (KMO) test and Bartlett’s test of sphericity were used to evaluate sampling adequacy and justify that the data obtained were adequate for succeeding data analysis. For further data analysis, Kaiser [90] suggests a KMO value larger than 0.60, but some studies indicate that a KMO value larger than 0.50 may also be acceptable [91]. The KMO test results revealed a value of 0.942 for the 35 FWS selection criteria, which indicates adequate intercorrelations. The Bartlett’s test of sphericity results provided a chi-square value of 6966.708, and the corresponding level of significance is p = 0.000, which demonstrates that the correlation matrix is not an identity matrix [92]. Consequently, the questionnaire data confirm construct validity and are acceptable for further data analysis.

3.4.2. Mean Score Analysis

The purpose of mean score analysis in quantitative research is to rank the relative importance of factors [93], such as the FWS selection criteria. This method is commonly used in the field of construction management to rank the relative importance levels of different factors among respondent groups [82]. Hence, to answer the research question Q1, this study uses the mean score analysis to measure the relative importance of the FWS selection criteria of the respondents. First, the overall ranking of the 35 FWS selection criteria were calculated for 222 respondents. Then, based on the demographic results of the questionnaire, the rankings of the FWS selection criteria were categorized into two parts, with each part consisting of four groups of respondents: part (a) “professional title” of respondents (CO, PM/CM/SE, PL/PR/TO, and FD/FSL) and part (b) “field of specialization” of the companies (PMS, ENG/DSG, FW/SCF, and GC/SC). The mean score for each FWS selection criterion in each group was calculated and compared to determine how different respondent groups perceived their importance.

3.4.3. Development of the Hypotheses

Based on the research questions (i.e., Q2, Q3, and Q4) explicitly described in the Literature Review section, the following null hypotheses for FWS selection criteria in building construction projects were developed:
Hypothesis 1 (H1).
No significant differences exist in FWS selection criteria in building construction projects among the “professional titles” of the respondents.
Hypothesis 2 (H2).
No significant differences exist in FWS selection criteria in building construction projects among the “field of specialization” of the respondents’ companies.
Hypothesis 3 (H3).
The changes in the values of the “building structural parameters” have no significant effects on the importance levels of the FWS selection criteria in building construction projects.
Hypotheses 1 and 2 are intended to compare the level of importance of FWS selection criteria among different demographic backgrounds, whereas Hypothesis 3 is intended to compare the differences in the importance levels of the FWS selection criteria according to the changes in the values of the “building structural parameters”.

3.4.4. Validation of the Hypotheses (Kruskal–Wallis Test and Mann–Whitney U Test)

The main objective of this study is to investigate and compare the perspectives and perceptions of construction professionals and stakeholder groups as well as the effects of “building structural parameters” towards FWS selection criteria in building construction projects in Turkey. Therefore, the ranking perceptions of the identified groups can be studied by means of non-parametric statistical tests applicable to ordinal data. In general, the following two hypotheses are tested for each identified group:
Hypothesis 0 (H0).
Null hypothesis: there is no difference between the groups; therefore, they possess the same mean (e.g., H0: CO = PM/CM/SE = PL/PR/TO = FD/FSL).
Hypothesis 1 (H1).
Alternative hypothesis: there is a difference between the groups; therefore, there exist different means (e.g., H1: CO ≠ PM/CM/SE = PL/PR/TO = FD/FSL).
The Kruskal–Wallis test can be used for evaluating Likert scale responses (i.e., ordinal data) and in circumstances when the assumption of normality is unjustified [94]. In addition, this test is utilized to determine whether there are any significant mean differences among three or more independently sampled groups [95,96]. This test statistic has a distinct distribution regarded as the chi-square distribution [97]. The Kruskal–Wallis formula is shown in Equation (3):
K W = 12 n ( n + 1 ) (   R i 2 n i ) 3 ( n + 1 )
where n is the total sample size, ni is the sample size of the i-th group, and Ri is the sum of the ranks of the i-th group.
In the context of this study, first, the Kruskal–Wallis test was conducted to test Hypothesis 1 and Hypothesis 2 and to determine which, if any, of the FWS selection criteria had statistically significant difference among the four response groups in each category. Then, Mann–Whitney U test (Wilcoxon rank) was utilized to conduct a pairwise comparison among two response groups [98]. In addition, only the Mann–Whitney U test was performed to test Hypothesis 3 as there were only two response groups in each “building structural parameter” category. A 0.05 (5%) level of significance was considered to represent a statistically significant difference in ranking among the groups for both tests.

3.4.5. Determination of Critical FWS Selection Criteria (Kendall’s Concordance Analysis (W) and Spearman’s Rank Correlation (R))

The combined perception of all respondent groups can be used to determine the critical FWS selection criteria in building construction projects (i.e., research question Q5). For this purpose, initially, Kendall’s concordance analysis is conducted to determine the degree of agreement on rankings within a group of respondents [99]. Kendall’s coefficient of concordance W value ranges from 0 to 1, with 1 indicating total agreement, 0 indicating no agreement, and 0.05 indicating general agreement within the group on the ranking of specified variables [100]. An acceptable agreement is found among a group of respondents if the Kendall’s coefficient of concordance W value is significant at the level of 0.05 [101]. The results of the Kendall’s concordance analysis revealed a W value of 0.147 and a significance level of less than 0.001 for the rankings of the 35 FWS selection criteria among all respondents. Thus, there was a significant agreement among all respondents’ groups.
The correlations among the identified groups were determined using Spearman’s rank correlation, a non-parametric test that is widely used to determine the degree of agreement between two groups of ranking [93,102]. The Spearman’s rank correlation coefficient ρ can be calculated using Equation (4) [103]:
ρ = 1 6   D 2 n ( n 2 1 )
where ρ is the Spearman’s rank correlation coefficient, D is the difference between ranks assigned to each factor (e.g., FWS selection criteria), and n is the number of respondents. The Spearman’s rank correlation coefficient ranges between +1 and −1, where −1 represents perfect negative relationship (disagreement), 0 signifies no correlation, and +1 denotes perfect positive relationship (agreement) [104]. The Spearman’s rank correlation coefficients were calculated among pairs of groups to demonstrate the agreement among them. Subsequently, the top five ranked FWS selection criteria, previously identified using the mean score analysis, were compared among the different groups to determine the critical FWS selection criteria.

4. Results

This section provides the results of the mean score analysis, Kruskal–Wallis test, Mann–Whitney U test, and Spearman’s rank correlation.

4.1. Results of Mean Score Analysis

Mean score analysis is a method for determining the relative importance levels among several factors [105,106]. In addition, using the findings of a mean score analysis, the similarities in ranking among different groups of respondents can be identified [107]. Hence, in this study, the relative importance levels of the FWS selection criteria were measured using mean scores (i.e., mean ranking). Initially, for the 222 respondents, the overall ranking of the 35 FWS selection criteria was calculated based on the mean score of each FWS selection criterion. Then, utilizing mean score analysis, the rankings of the FWS selection criteria of different groups under the “professional title” category and the “field of specialization” category were determined. The results of the mean score analysis for the “professional title” and “field of specialization” categories are shown in Table 1 and Table 2, respectively.
According to the results of the mean score analysis for the overall respondents (Table 1), “initial cost of the FWS” (ID 18), “speed of construction” (ID 12), “degree of repetition of the FWS” (ID 6), “type of structural slab” (ID 1), and “type of structural lateral loads-supporting system” (ID 2) were ranked as the top five FWS selection criteria in descending order. All four groups under the “field of specialization” category (e.g., CO, PM/CM/SE, PM/CM/SE, PL/PR/TO, and FD/FSL) ranked “degree of repetition of the FWS” (ID 6) and “initial cost of the FWS” (ID 18) among the top five FWS selection criteria. In addition, “speed of construction” (ID 12) was ranked among the top five FWS selection criteria by the CO, PM/CM/SE, and PL/PR/TO groups. The CO and FD/FSL groups ranked “FWS durability” (ID 27), the PL/PR/TO and FD/FSL groups ranked “type of structural lateral loads-supporting system” (ID 2), and the PM/CM/SE and FD/FSL groups ranked “type of structural slab” (ID 1) among the top five FWS selection criteria in building construction projects. Furthermore, the CO group ranked “potential reuse of the FWS in other projects” (ID 22), the PM/CM/SE group ranked “hoisting equipment” (ID 23), and the PL/PR/TO group ranked “uniformity of building” (ID 10) among the top five FWS selection criteria.
According to Table 2, all four groups under the “field of specialization” category (e.g., PMS, ENG/DSG, FW/SCF, and GC/SC) ranked “initial cost of the FWS” (ID 18) among the top five FWS selection criteria. Moreover, “degree of repetition of the FWS” (ID 6) and “speed of construction” (ID 12) were ranked among the top five FWS selection criteria by three groups under this category. The PMS and FW/SCF groups ranked “type of structural slab” (ID 1) and “type of structural lateral loads-supporting system” (ID 2), the PMS and ENG/DSG groups ranked “potential reuse of the FWS in other projects” (ID 22), and the FW/SCF and GC/SC groups ranked “FWS durability” (ID 27) among the top five FWS selection criteria in building construction projects. “Uniformity of building” (ID 10) and “hoisting equipment” (ID 23) were ranked only by the ENG/DSG group and GC/SC group, respectively, among the top five FWS selection criteria.
The mean score analysis revealed that the “initial cost of the FWS” (ID 18) was always ranked in each of the two categories and among all the groups (e.g., “professional title” of respondents and “field of specialization” of respondent’s company) as the top five FWS selection criteria. In addition, nine (e.g., ID 1, ID2 ID 6, ID 10, ID12, ID 18, ID 22, ID 23, and ID27) out of the 35 FWS selection criteria were always ranked among the top five FWS selection criteria in one of the two categories. Although some FWS selection criteria were ranked similarly by all the groups, others were ranked differently, and some FWS selection criteria were only ranked among the top five for a certain group. In general, while similar ranking may suggest an agreement in the perspective and perception among various groups [104], variations in ranking indicate that there may be significant differences [82], thus disagreements, in the rankings for the FWS selection criteria. Hence, further analysis is necessary to evaluate the differences and similarities in the perspectives and perceptions of different groups regarding FWS selection criteria.

4.2. Results of Kruskal–Wallis Test and Mann–Whitney U Test

The Kruskal–Wallis test was used to evaluate Hypothesis 1 and Hypothesis 2, as well as to identify which of the FWS selection criteria resulted in a significant statistical difference between the four response groups in each category. The results of the Kruskal–Wallis test are presented in Table 3. Specifically, significant statistical differences (e.g., p < 0.05) in perception are observed in 16 and 13 out of the 35 FWS selection criteria for the “professional title” category and for the “field of specialization” category, respectively. Regarding Hypothesis 1, the null hypothesis (e.g., H0) may be rejected as there are a considerable number of FWS selection criteria with significant statistical differences (e.g., 16 out of 35 FWS selection criteria). Therefore, a relative difference in perception exists among the four groups under the “professional title” category in terms of the FWS selection criteria. The null hypothesis, in respect to Hypothesis 2, may also be rejected since 13 out of the 35 FWS selection criteria have shown significant statistical differences. In other words, the alternative hypothesis H1 is accepted for both hypotheses as the relative importance levels of the FWS selection criteria in building construction projects vary (e.g., there exist different means) according to the “professional title” and “field of specialization”.
However, to determine which of the response groups and which of the 35 FWS selection criteria reflect differences in ranking, the Mann–Whitney U test can be used by conducting a pair-wise comparison across these groups [98,107]. Furthermore, to test Hypothesis 3, that the “building structural parameters” have no significant effects on the FWS selection criteria in building construction projects, the Mann–Whitney U test is performed since each building structural parameter category involves only two response groups (Table A3).
First, the Mann–Whitney U test was performed for the “professional title” category. As there are four groups under this category, a total of six pair-wise comparisons were conducted. For each comparison, the null hypothesis was tested that no significant differences exist in the perception of the response groups for the 35 FWS selection criteria. The results of the Mann–Whitney U test for the “professional title” category are presented in Table 4. The Mann–Whitney U test results show that there are only a few significant statistical differences (e.g., p < 0.05) in the perception among the CO, PM/CM/SE, and PL/PR/TO groups regarding the FWS selection criteria (i.e., one out of thirty-five FWS selection criteria between the CO and PM/CM/SE groups). However, the pair-wise comparison of the FD/FSL group with the other three groups reveals a large number of FWS selection criteria with statistically significant differences. For instance, significant differences in the perception regarding FWS selection criteria exist in 11 out of the 35 between the CO and FD/FSL groups, 13 out of 35 between the PM/CM/SE and FD/FSL groups, and 23 out of 35 between the PL/PR/TO and FD/FSL groups. These findings suggest that formwork design and formwork sales engineering construction professionals may have a different perception and perspective on the significance of FWS selection criteria than other construction professionals. In addition, the results of the Mann–Whitney U test are consistent with the results of the Kruskal–Wallis test. In particular, differences in perceptions are found in both tests among the same FWS selection criteria (Table 3 and Table 4), with some additional criteria demonstrating significant differences by pair-wise comparison between FD/FSL and other groups. Subsequently, the Mann–Whitney U test was carried out for the “field of specialization” of the respondent’s company category and the results are presented in Table 5. As observed in the results for the “professional title” category, the Mann–Whitney U test findings for the “field of specialization” category indicate that there are only a few significant statistical differences (e.g., p < 0.05) in the perception regarding the FWS selection criteria among three (e.g., PMS, ENG/DSG, and GC/SC groups) out of the four groups. On the other hand, a pair-wise comparison of the FW/SCF group with the other three groups reveals a large number of FWS selection criteria with statistically significant differences (i.e., 20 out of 35 FWS selection criteria between FW/SCF and GC/SC groups). As anticipated, construction professionals working in the field of formwork engineering (e.g., FD/FSL group) demonstrate similar perceptions with the companies involved in the same field (e.g., FW/SCF group). Moreover, these construction professionals and companies working in the field of formwork engineering show significant differences regarding FWS selection criteria with the other groups.
Finally, Hypothesis 3, that the changes in the values of the “building structural parameters” have no significant effects on the importance levels of the FWS selection criteria in building construction projects, was tested using the Mann–Whitney U test. Each “building structural parameter” category (e.g., typical building floor area, typical building floor-to-floor height, total area of building construction, and total building height) consists of two groups. Hence, a pair-wise comparison among the 35 FWS selection criteria was conducted, and the results are presented in Table A4. The findings of the Mann–Whitney U test indicate that the “typical building floor area” and “typical building floor-to-floor height” categories have an impact on only two out of the thirty-five FWS selection criteria with a significant statistical difference. Therefore, the null hypothesis (e.g., H0) cannot be rejected for these two categories. However, the “total area of building construction” and “total building height” categories show significant statistical differences for sixteen and nine out of the thirty-five FWS selection criteria, respectively. Hence, the null hypothesis may be rejected, and the alternative hypothesis H1 can be accepted for both categories. In particular, the findings for the “total area of building construction” category suggest that the relative importance level of FWS selection criteria may vary between small and/or medium (e.g., < 20,000 m2) and large (e.g., > 20,000 m2) building construction projects [20]. Furthermore, the relative importance level of FWS selection criteria may also vary between low-rise (e.g., < 36.5 m) and mid and/or high-rise (e.g., > 36.5 m) building construction projects [20].

4.3. Results of Spearman’s Rank Correlation (R)

The Spearman’s rank correlation coefficients (e.g., ρ) were calculated among pairs of groups for the “professional title” and “field of specialization” categories. The Spearman’s rank correlation coefficients, the level of significance, and the degree of agreement among the respondent groups are presented in Table 6 and Table 7 for both categories, respectively.
The findings of the Spearman’s rank correlation test indicate a significant (e.g., <0.01) positive and high level of agreement among all the groups in both categories. In addition, these results confirm the reliability of this study’s findings [108]. Therefore, by using the top five FWS selection criteria among all the respondents from the mean score analysis results, the critical FWS selection criteria can be obtained.

5. Discussion

5.1. Discussion Based on Mean Score Analysis

The mean score analysis revealed that the (1) “type of structural slab”, (2) “type of structural lateral loads-supporting system“, (3) “degree of repetition of the FWS”, (4) “uniformity of building”, (5) “speed of construction”, (6) “initial cost of the FWS”, (7) ”potential reuse of the FWS in other projects”, (8) “hoisting equipment”, and (9) “FWS durability” were always ranked among the top five FWS selection criteria in either the “professional title” or “field of specialization” category. On the other hand, some of these criteria were ranked differently among the four groups of respondents in each category.
In building construction projects, “type of structural slab”, “type of structural lateral loads-supporting system”, “degree of repetition of the FWS”, and “uniformity of building” are criteria that are related to the structural design of the building [24]. Furthermore, the structural design and the selected FWS have a significant impact on the constructability of an RC building project [109]. Since there may be different types of structural slabs (e.g., one-way slab, two-way slab) and different types of structural lateral loads-supporting systems (e.g., rigid frame, shear wall, tube-in-tube), the design and selection of the FWS is highly dependent on these two criteria [2,7,110]. Formwork design is usually performed by formwork design or formwork sales engineers (i.e., FD/FSL group). In other words, employees of formwork and scaffolding companies (i.e., FW/SCF group), who are considered experts in the field of formwork engineering perform the design and detail activities of the FWS [16]. As expected, the FD/FSL group ranked the “type of structural slab” and “type of structural lateral loads-supporting system” first and second, respectively. The FW/SCF group ranked the “type of structural slab” and “type of structural lateral loads-supporting system” first and third, respectively. Moreover, some FWSs may be more difficult to adapt to significant changes in building structural design than others, particularly in buildings with a non-uniform structural design. Hence, the “uniformity of building” and “degree of repetition of the FWS” are interdependent criteria and should be considered in tandem [10]. In addition, these FWS selection criteria are among the most important criteria for the selection of the appropriate FWSs and are frequently cited in previous studies (see Figure 2). Consequently, these criteria are considered among the most significant FWS selection criteria by many construction professionals in their FWS decision-making process, which is consistent with the findings of the mean score analysis.
The “speed of construction” and “initial cost of the FWS” are two criteria that may have a significant impact on the time and cost performance of a building construction project [4]. Formwork-related activities may account for up to 75% of the total time spent on the construction of RC building structures [58]. The “speed of construction” is primarily affected by the floor cycle time [20,110] and can be measured by the time it takes to erect and strip the FWS, place and cure the concrete, and transport the FWS to the next location. The erecting, stripping, and moving times may be dependent on the characteristics of the selected FWS [111]. On the other hand, the curing time of concrete depends on concrete-related parameters (e.g., type of concrete mixture, required concrete strength) and weather conditions [112]. In addition, the “labour productivity” of formwork-related activities can be affected by weather conditions [113]; therefore, it may have an impact on the “speed of construction” as well. The “speed of construction” was ranked among the top five FWS selection criteria by all the groups in the “field of specialization category” except the FW/SCF group. The “initial cost of the FWS” and “potential reuse of the FWS in other projects” are cost criteria, which may have a substantial impact on the cost performance of building construction projects. For instance, if the selected FWS can be modified and utilized in other projects, the initial investment in the FWS may be minimized over time [10]. It should be noted that, among the 35 FWS selection criteria, “potential reuse of the FWS in other projects” was ranked first by company owners (i.e., COs) since it may affect the long-term investment of the companies. Moreover, as formwork may account for up to 60% of the overall cost of an RC building project [8], the “initial cost of the FWS” should be considered as one of the most important criteria in the selection process of FWSs. Excluding the FD/FSL group, all the other respondent groups in the “professional title category” ranked the “initial cost of the FWS” first or second among all the FWS selection criteria. In addition, the general or sub-contractors (i.e., GC/SC group) under the “field of specialization” category ranked the “initial cost of the FWS” first since the FWS is usually purchased or rented by the contractors. Therefore, “speed of construction”, “initial cost of the FWS”, and “potential reuse of the FWS in other projects” are decisive criteria in the selection of FWSs, and, as anticipated, these criteria are ranked among the most important FWS selection criteria in all the respondents’ categories.
The demand for “hoisting equipment” on the construction site regarding FWSs has been substantially decreased in recent years due to technological innovations in formwork engineering [40,114]. Modular lightweight FWSs (e.g., FWSs consisting of plastic or aluminium material components) or self-climbing FWSs do not require crane equipment since they can be transported manually by hand or lifted automatically utilizing hydraulic systems [10,115]. However, traditional FWSs (e.g., FWSs consisting of timber material components) or industrial FWSs composed of heavy structural components (e.g., FWSs consisting of steel material components) are still commonly used in the building construction industry [21]. The majority of these FWSs necessitate the presence of “hoisting equipment” on the construction site. However, this criterion was only ranked among the top five FWS selection criteria by the PM/CM/SE group and the GC/SC group. As noted earlier, the PM/CM/SE and GC/SC groups execute the project as on-site construction teams [78]. Thus, to plan and ensure the availability of “hoisting equipment” on the construction site is a task usually performed by these two groups. As a result, the availability of “hoisting equipment” is an essential criterion for the PM/CM/SE and the GC/SC groups in the selection of FWSs.
“FWS durability”, one of the FWS’s characteristics, is regarded among the top five FWS selection criteria by the CO and FD/FSL groups under the “professional title” category, as well as by the FW/SCF and GC/SC groups under the “field of specialization” category. The FWS may be replaced if its durability is inadequate to meet the required “degree of repetition of the FWS” [10]. In general, formwork design and formwork planning are conducted by the formwork design engineers (i.e., FD/FSL group) [116]. In addition, formwork and scaffolding companies (i.e., FW/SCF group) should ensure that the FWS has adequate durability to finish the project on time and budget so that the contractors (i.e., GC/SC group) can use the acquired FWS without the need for replacement or repairs. Consequently, “FWS durability” is an important criterion for these groups in the selection of the FWS, which may impact both the cost and the duration of the project.

5.2. Discussion Based on Hypotheses

In building construction projects, organisational structures may separate the design teams from the construction teams, and some construction-related decisions may be taken differently [79]. Furthermore, there may be agreements or disagreements among different groups of respondents regarding the relative importance level of some FWS selection criteria [13,17]. Hence, differences in perception and perspectives among groups of construction professionals in the decision-making process of FWSs may exist. In this study, the Kruskal–Wallis test and the Mann–Whitney U test were conducted to evaluate Hypothesis 1 and Hypothesis 2, as well as to determine which of the FWS selection criteria resulted in a statistically significant difference between the four response groups in the “professional title” and “field of specialization” categories. The findings revealed that, regarding the relative importance level of the FWS selection criteria, the CO, PM/CM/SE, and PL/PR/TO groups under the “professional title” category had only a few statistical differences among each other. This result is consistent with some of the previous studies [17]. However, the relative importance levels of the FD/FSL group differed significantly from all the other groups (e.g., 23 out of 35 FWS selection criteria between the PL/PR/TO and FD/FSL groups). Similarly, the FW/SCF group under the “field of specialization” category showed significant differences regarding FWS selection criteria with the PMS, ENG/DSG, and GC/SC groups. The differences in the perceptions were mostly observed among structural design-related criteria (e.g., “type of structural slab”, “variation in column/wall dimensions and location”) and in FWS–FWF characteristics-related criteria (e.g., “FWS flexibility”, FWF technical support”). In general, the structural design (i.e., ID1–ID10) and the FWS–FWF characteristics (i.e., ID25–ID35) -related criteria are taken into account during the design phase of the building construction project [10]. On the other hand, the cost- and time-related criteria (e.g., “transportation cost of FWS”, “speed of construction”) may be considered in the later phases of the building construction project, where other stakeholder groups are involved in the decision-making process of the FWS. As stated previously, the FD/FSL group (or FW/SCF group) is typically in charge of the FWS’s planning, designing, and detailing activities. However, other formwork-related activities may be performed by different stakeholders in the FWS supply chain depending on the project delivery system, construction method, type of structure, and capacity of the stakeholder [16]. The involvement of the formwork subcontractor (i.e., the FW/SCF group) in the formwork plan and design processes in collaboration with other groups may minimize design errors and change orders during the construction phase [117]. Therefore, to improve the cost and time performance of building construction projects, the perspective and perception of the FD/FSL and FW/SCF groups on the FWS selection criteria should be evaluated in coordination with the other groups.
In regard to Hypothesis 3, the results of the Mann–Whitney U test indicate that some of the “building structural parameters” have a significant effect on the FWS selection criteria, while others do not. The majority of the differences in the relative importance levels for the FWS selection criteria were observed between small and/or medium (i.e., <20,000 m2) and large (i.e., >20,000 m2) building construction projects. In this regard, “speed of construction”, “hoisting equipment”, and “labour productivity” were affected by the size of the building construction project (i.e., total area of building construction) in addition to the significant statistical differences observed in some structural design and FWS–FWF characteristics-related criteria. Time, or the “speed of construction” in this study’s context, is a critical factor in selecting the appropriate FWS [4]. The “speed of construction” and the need for “hoisting equipment” may vary according to the type of the selected FWS [7,21]. As the construction area increases, multiple cranes (e.g., “hoisting equipment”) may be needed to perform formwork-related tasks [118]. Hence, the project size may affect FWS selection criteria such as “speed of construction” and “hoisting equipment”. Furthermore, “the speed of construction” and “hoisting equipment” can be important factors for formwork-related activities in high-rise building construction [48,119]. Therefore, as shown in this study’s results, “hoisting equipment” is also affected by the total building height. In construction projects, “labour productivity” is another criterion that can be affected by the size of the project [108] and the type of the selected FWS [12]. The “labour productivity” of the FWS is also affected by the structural design of the building construction project [120]. As a result, the size of the project and total building height have a significant effect on the “labour productivity” of the FWS, as demonstrated by the results of this study.

5.3. Discussion Based on Critical FWS Selection Criteria

The perceptions and perspectives of the three groups in the “professional title” category (CO, PM/CM/SE, and PL/PR/TO groups) and the three groups in the “field of specialization” category (CO, PM/CM/SE, and PL/PR/TO groups) were similar regarding FWS selection criteria in building construction projects. However, the FD/FSL group and FW/SCF group had significant statistical differences in their perceptions and perspectives compared to all the other groups. Despite this result, Spearman’s rank correlation test revealed that all four groups in both categories had a strong agreement among the 35 FWS selection criteria. Therefore, based on the results of the mean score analysis (e.g., top five FWS selection criteria) and the Spearman’s rank correlation test, the “initial cost of the FWS” (ID 18), “speed of construction” (ID 12), “degree of repetition of the FWS” (ID 6), “type of structural slab” (ID 1), and “type of structural lateral loads-supporting system” (ID 2) can be regarded as the critical FWS selection criteria in building construction projects.

6. Conclusions

The purpose of this study was to analyse the FWS selection criteria by comparing the perspectives and perceptions of various construction professionals and stakeholder groups involved in building construction projects in Turkey. For this purpose, first, an intensive literature review was conducted and 35 FWS selection criteria for building construction projects were identified. Then, a questionnaire was developed to measure the relative importance level of the identified FWS selection criteria. Subsequently, the data obtained for the FWS selection criteria were analysed utilizing statistical tests based on the research questions and the demographic background of the respondent groups.
This study has revealed that different groups of construction professionals and companies involved in the decision-making process of FWSs mostly agreed on the relative importance level of FWS selection criteria. However, formwork and scaffolding companies and employees of these companies had significant statistical differences regarding FWS selection criteria, especially among structural design and FWS–FWF characteristics-related criteria. The main reason for this result is that these criteria are typically considered during the FWS’s planning, designing, and detailing phases, which are traditionally done by the FWF. Since the involvement of the FWF with other stakeholder groups during the design phase can improve the constructability of the building construction project, the perspectives and perceptions of the FD/FSL group or the FW/SCF group (i.e., FWF) should be considered in parallel with other groups of construction professionals and companies. Furthermore, the selected FWS, based on the FWS selection criteria, may have a significant impact on the cost and time performance factors in the later phases of a building construction project. In addition, this study determined that some of the “building structural parameters” had significant effects on the FWS selection criteria in building construction projects. The project size (i.e., total area of building construction) and total building height, in particular, affected the “speed of construction,” “hoisting equipment,” and “labour productivity” in the building construction projects. Therefore, decision-makers and construction professionals may need to consider these FWS selection criteria and the relevant building structural parameters in the selection process of the FWS to improve the performance factors of the project.
As the formwork-related activities and the selected FWS affect the overall performance of a building construction project, the identification of the critical FWS selection criteria can provide construction professionals with a useful guide in their decision-making process. The results of this study indicate that, although differences between the FD/FSL or FW/SCF and the other groups exist, there was a significant agreement among the overall respondents. Hence, it was determined that the “initial cost of the FWS”, “speed of construction”, “degree of repetition of the FWS”, “type of structural slab”, and “type of structural lateral loads-supporting system” are the critical FWS selection criteria in the building construction projects in Turkey. In this regard, since there are many FWS selection criteria, decision-makers and construction professionals may use these critical criteria in MCDM methods to ease computational efforts and improve the FWS selection process.
There are some limitations to this study. The first limitation is that this study was carried out only in Turkey. However, since Turkish construction professionals and companies operate in domestic as well as in international markets, the results of this study may benefit the global construction community as well. Second, this study focused on FWS selection criteria in building construction projects. For different types of projects, such as industrial or infrastructural projects, other FWS selection criteria can be identified and analysed. In addition, based on the quantitative data presented in this study, factor analysis and structural equation modelling (SEM) may be utilized to group the FWS selection criteria and determine the effects among the FWS selection criteria groupings.

Author Contributions

Conceptualization, T.T.; methodology, T.T.; software, T.T.; validation, T.T., H.T. and G.P.; formal analysis, T.T.; investigation, T.T.; resources, T.T.; data curation, T.T.; writing—original draft preparation, T.T.; writing—review and editing, G.P.; visualization, H.T.; supervision, G.P. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

Ethics Statement

The material presented in this study is the authors’ own original work, which has not been previously published elsewhere. The article is not currently being considered for publication elsewhere. The article reflects the authors’ own research and analysis in a truthful and complete manner. The article properly credits the meaningful contributions of co-authors and co-researchers. All sources used are properly disclosed. All authors have been personally and actively involved in substantial work leading to the paper and will take public responsibility for its content.

Appendix A

Table A1. Demographic information of the respondents.
Table A1. Demographic information of the respondents.
CategoryResponseFrequency of Respondents (N = 222)Percentage (%)
Educational levelBachelor’s or equivalent13661.3
Master’s or equivalent8236.9
Doctoral or equivalent41.8
Age20–292410.8
30–397433.3
40–495826.1
≥506629.7
Work experience1–105926.6
11–206830.6
21–303917.6
≥315625.2
Professional titleCompany owner (CO)5424.3
Project manager, construction manager, and site engineer (PM/CM/SE)8136.5
Planning, procurement, and technical office engineer (PL/PR/TO)4218.9
Formwork design/formwork sales engineer (FD/FSL)4520.3
Table A2. Demographic information of the respondents’ company.
Table A2. Demographic information of the respondents’ company.
CategoryResponseFrequency of Respondents (N = 222)Percentage (%)
No. of technical and administrative employees1–96730.2
10–495424.3
50–2496127.5
≥2504018.0
No. of operating years in the construction sector1–103013.5
11–204520.3
21–303515.8
≥3111250.5
Field of specializationProject management service (PMS)6629.7
Engineering and design (ENG/DSG)4319.4
Formwork and scaffolding (FW/SCF) 4821.6
General and/or sub-contractor (GC/SC)6529.3
Market region Only national projects6931.1
Mostly national and partially international projects11049.5
Mostly international and partially national projects3817.1
Only international projects52.3
Table A3. Building structural parameters of the respondent’s current construction project.
Table A3. Building structural parameters of the respondent’s current construction project.
CategoryResponseFrequency of Respondents (N = 222)Percentage (%)
Typical building floor area<1000 m26830.6
>1000 m215469.4
Total area of building construction<20,000 m29141.0
>20,000 m213159.0
Typical building floor-to-floor height<5 10446.8
>5 m11853.2
Total building height<36.5 m10848.6
>36.5 m11451.4
Table A4. Mann–Whitney U test statistics for “building structural parameters” category.
Table A4. Mann–Whitney U test statistics for “building structural parameters” category.
FWS Selection Criteria ID No.Asymp. Sig. (Two-Tailed) of Pairwise Comparison
<1000 m2 and >1000 m2<5 m and >5 m<20,000 m2 and >20,000 m2<36.5 m and >36.5 m
10.011 *0.5320.008 *0.007 *
20.6760.7390.6290.366
30.4060.7340.9330.991
40.3500.2540.6900.336
50.6380.0540.8550.351
60.2810.0910.010 *0.098
70.8490.1000.1640.546
80.4110.4170.003 *0.042 *
90.8380.8880.015 *0.515
100.0580.9860.026 *0.523
110.4500.5880.0670.558
120.1540.3880.033 *0.029 *
130.8140.8370.2820.348
140.1750.3860.020 *0.041 *
150.8660.9190.4630.339
160.5940.9610.3900.693
170.6620.8640.2800.783
180.3490.010 *0.4510.415
190.3290.9710.7400.383
200.7270.9810.1680.224
210.4500.3280.0750.178
220.4130.2380.6660.138
230.047 *0.1670.004 *0.025 *
240.9310.6580.4070.415
250.3590.4520.6490.323
260.1540.045 *<0.001 *<0.001 *
270.7850.5950.036 *0.212
280.6700.1470.042 *0.263
290.6300.3220.002 *0.300
300.7450.9400.2870.018 *
310.3810.6630.0430.084
320.3690.9600.013 *0.065
330.1480.127<0.001 *<0.001 *
340.2800.1360.012 *<0.001 *
350.5390.4100.2630.073
* The Mann–Whitney U test is significant at the 0.05 level.

References

  1. Nguyen, L.D.; Nguyen, H.T. Relationship between building floor and construction labor productivity: A case of structural work. Eng. Constr. Archit. Manag. 2013, 20, 563–575. [Google Scholar] [CrossRef]
  2. Tam, C.M.; Tong, T.K.L.; Lau, T.C.T.; Chan, K.K. Selection of vertical formwork system by probabilistic neural networks models. Constr. Manag. Econ. 2005, 23, 245–254. [Google Scholar] [CrossRef]
  3. Hurd, M.K. Formwork for Concrete, 7th ed.; American Concrete Institute: Farmington Hills, MI, USA, 2005. [Google Scholar]
  4. Safa, M.; Reinsma, S.; Haas, C.T.; Goodrum, P.M.; Caldas, C.H. A decision-making method for choosing concrete forming systems. Int. J. Constr. Manag. 2016, 18, 1–12. [Google Scholar] [CrossRef]
  5. Dikmen, S.U.; Sonmez, M. An artificial neural networks model for estimation of formwork labour. J. Civ. Eng. Manag. 2011, 17, 340–347. [Google Scholar] [CrossRef]
  6. Ko, C.H.; Kuo, J.D. Making formwork construction lean. J. Civ. Eng. Manag. 2015, 21, 444–458. [Google Scholar] [CrossRef]
  7. Shin, Y.; Kim, T.; Cho, H.H.; Kang, K.I. A formwork method selection model based on boosted decision trees in tall building construction. Autom. Constr. 2012, 23, 47–54. [Google Scholar] [CrossRef]
  8. John, S.T.; Mohan, A.; Philip, M.S.; Sarkar, P.; Davis, R. An IoT device for striking of vertical concrete formwork. Eng. Constr. Archit. Manag. 2021. [Google Scholar] [CrossRef]
  9. Zayed, T.; Mohamed, E. A case of productivity model for automatic climbing system. Eng. Constr. Archit. Manag. 2014, 21, 33–50. [Google Scholar] [CrossRef]
  10. Terzioglu, T.; Turkoglu, H.; Polat, G. Formwork systems selection criteria for building construction projects: A critical review of the literature. Can. J. Civ. Eng. 2021. [Google Scholar] [CrossRef]
  11. Elazouni, A.; Ali, A.; Abdel-Razek, R. Estimating the acceptability of new formwork systems using neural networks. J. Constr. Eng. Manag. 2005, 131, 33–41. [Google Scholar] [CrossRef]
  12. Basu, R.; Jha, K.N. An AHP based model for the selection of horizontal formwork systems in Indian residential construction. Int. J. Struct. Civ. Eng. Res. 2016, 5, 80–86. [Google Scholar] [CrossRef]
  13. Proverbs, D.G.; Holt, G.D.; Olomolaiye, P.O. Factors in formwork selection: A comparative investigation. Build. Res. Inf. 1999, 27, 109–119. [Google Scholar] [CrossRef]
  14. Jiang, L.; Leicht, R.M. Automated rule-based constructability checking: Case study of formwork. J. Manag. Eng. 2015, 31, A4014004. [Google Scholar] [CrossRef]
  15. Lee, D.; Lim, H.; Kim, T.; Cho, H.; Kang, K. Advanced planning model of formwork layout for productivity improvement in high-rise building construction. Autom. Constr. 2018, 85, 232–240. [Google Scholar] [CrossRef]
  16. Terzioglu, T.; Polat, G.; Turkoglu, H. Analysis of industrial formwork systems supply chain using value stream mapping. J. Eng. Proj. Prod. Manag. 2022, 12, 47–61. [Google Scholar] [CrossRef]
  17. Rajeshkumar, V.; Anandaraj, S.; Kavinkumar, V.; Elango, K.S. Analysis of factors influencing formwork material selection in construction buildings. Mater. Today Proc. 2021, 37, 880–885. [Google Scholar] [CrossRef]
  18. Jha, J.; Sinha, S.K. Modern Practices in Formwork for Civil Engineering Construction Works; University Science Press: New Delhi, India, 2014. [Google Scholar]
  19. Hansen, S.; Siregar, P.H.R.; Jevica, J. AHP-based decision-making framework for formwork system selection by contractors. J. Constr. Dev. Ctries. 2020, 25, 235–255. [Google Scholar] [CrossRef]
  20. Hanna, A.S. Concrete Formwork Systems; Marcel Dekker: New York, NY, USA, 1999. [Google Scholar]
  21. Elbeltagi, E.; Hosny, O.; Elhakeem, A.; Abd-Elrazek, M.; Abdullah, A. Selection of slab formwork system using fuzzy logic. Constr. Manag. Econ. 2011, 29, 659–670. [Google Scholar] [CrossRef]
  22. Hanna, A.S. An Interactive Knowledge-Based Formwork Selection System for Buildings. Ph.D. Dissertation, Department of Civil Engineering, Pennsylvania State University, State College, PA, USA, 1989. [Google Scholar]
  23. Hanna, A.S.; Sanvido, V.E. Interactive vertical formwork selection system. Concr. Int. 1990, 12, 26–32. [Google Scholar]
  24. Hanna, A.S.; Willenbrock, J.H.; Sanvido, V.E. Knowledge acquisition and development for formwork selection system. J. Constr. Eng. Manag. 1992, 118, 179–198. [Google Scholar] [CrossRef]
  25. Kamarthi, S.V.; Sanvido, V.E.; Kumara, S.R.T. Neuroform—Neural network system for vertical formwork selection. J. Comp. Civ. Eng. 1992, 6, 178–199. [Google Scholar] [CrossRef]
  26. Hanna, A.S.; Senouci, A.B. NEUROSLAB—Neural network system for horizontal formwork selection. Can. J. Civ. Eng. 1995, 22, 785–792. [Google Scholar] [CrossRef]
  27. Shin, Y. Formwork system selection model for tall building construction using the Adaboost algorithm. J. Korea Inst. Build. Constr. 2011, 11, 523–529. [Google Scholar] [CrossRef]
  28. Kim, T.H. Optimization of the Formwork Selection Process in Tall Buildings. Master’s Thesis, Korea University, Seoul, Korea, 2007. [Google Scholar]
  29. Jarkas, A. Buildability factors influencing micro-level formwork labour productivity of slab panels in building floors. Arch. Eng. Des. Manag. 2010, 6, 161–174. [Google Scholar] [CrossRef]
  30. Elbeltagi, E.; Hosny, O.; Elhakeem, A.; Abd-Elrazek, M.; El-Abbasy, M. Fuzzy logic model for selection of vertical formwork systems. J. Constr. Eng. Manag. 2012, 138, 832–840. [Google Scholar] [CrossRef]
  31. Yun, J.; Jeong, K.; Youn, J.; Lee, D. Development of Side Mold Control Equipment for Producing Free-Form Concrete Panels. Buildings 2021, 11, 175. [Google Scholar] [CrossRef]
  32. Darwish, M.; Elsayed, A.Y.; Nassar, K. Design and constructability of a novel funicular arched steel truss falsework. J. Constr. Eng. Manag. 2018, 144, 04018002. [Google Scholar] [CrossRef]
  33. Krawczyńska-Piechna, A. Application of TOPSIS method in formwork selection problem. Appl. Mech. Mater. 2015, 797, 101–107. [Google Scholar] [CrossRef]
  34. Krawczyńska-Piechna, A. An analysis of the decisive criteria in formwork selection problem. Arch. Civ. Eng. 2016, 62, 185–196. [Google Scholar] [CrossRef] [Green Version]
  35. Krawczyńska-Piechna, A. Comprehensive approach to efficient planning of formwork utilization on the construction site. Procedia Eng. 2017, 182, 366–372. [Google Scholar] [CrossRef]
  36. Lee, J.; Cho, J. An inference method of safety accidents of construction workers according to the risk factor reduction of the Bayesian network model in linear scheduling. Int. J. Manag. 2020, 11, 1–12. [Google Scholar]
  37. Hallowell, M.R.; Gambatese, J.A. Activity-based safety risk quantification for concrete formwork construction. J. Constr. Eng. Manag. 2009, 135, 990–998. [Google Scholar] [CrossRef]
  38. Jayasinghe, R.S.; Fernando, N.G. Developing labour productivity norms for aluminium system formwork in Sri Lanka. Built Environ. Proj. Asset Manag. 2017, 7, 199–211. [Google Scholar] [CrossRef]
  39. Jiang, L.; Leicht, R.M.; Kremer, G.E.O. Eliciting constructability knowledge for BIM-enabled automated, rule-based constructability review: A case study of formwork. In Proceedings of the 2014 Construction Research Congress, Atlanta, GA, USA, 19–21 May 2014. [Google Scholar] [CrossRef] [Green Version]
  40. Martinez, E.; Tommelein, I.D.; Alvear, A. Formwork system selection using choosing by advantages. In Proceedings of the Construction Research Congress 2016, San Juan, Puerto Rico, 31 May–2 June 2016; 2016; pp. 1700–1709. [Google Scholar] [CrossRef]
  41. Radziejowska, A.; Sobotka, A. Comparative analysis of slab formwork of monolithic reinforced concrete buildings. Arch. Civ. Eng. 2020, 66, 127–141. [Google Scholar] [CrossRef]
  42. Loganathan, K.; Viswanathan, K.E. A study report on cost, duration and quality analysis of different formworks in high-rise building. Int. J. Sci. Eng. Res. 2016, 7, 190–195. [Google Scholar]
  43. Rosenbaum, S.; Toledo, M.; González, V. Improving environmental and production performance in construction projects using value-stream mapping: Case study. J. Constr. Eng. Manag. 2014, 140, 1–11. [Google Scholar] [CrossRef]
  44. Vilventhan, A.; Ram, V.; Sugumaran, S. Value stream mapping for identification and assessment of material waste in construction: A case study. Waste Manag. Res. 2019, 37, 815–825. [Google Scholar] [CrossRef]
  45. Spitz, N.; Coniglio, N.; Libessart, L.; El Mansori, M.; Djelal, C. Characterizing tribological behavior of fresh concrete against formwork surfaces. Constr. Build. Mater. 2021, 303, 124233. [Google Scholar] [CrossRef]
  46. Mésároš, P.; Spišáková, M.; Mandičák, T.; Čabala, J.; Oravec, M.M. Adaptive design of formworks for building renovation considering the sustainability of construction in BIM environment—Case study. Sustainability 2021, 13, 799. [Google Scholar] [CrossRef]
  47. Singh, M.M.; Sawhney, A.; Sharma, V. Utilising building component data from BIM for formwork planning. Constr. Econ. Build. 2017, 17, 20–36. [Google Scholar] [CrossRef] [Green Version]
  48. Rajeshkumar, V.; Sreevidya, V. Performance evaluation on selection of formwork systems in high rise buildings using regression analysis and their impacts on project success. Arch. Civ. Eng. 2019, 65, 209–222. [Google Scholar] [CrossRef]
  49. Pawar, A.D.; Rajput, B.L.; Agarwal, A.L. Factors affecting selection of concrete structure formwork. In Proceedings of the 3rd International Conference on Construction, Real Estate, Infrastructure and Project Management, National Institute of Construction Management and Research, Pune, India, 23–25 November 2018; pp. 45–52. [Google Scholar]
  50. Teja, G.S.; Hanagodimath, A.V.; Naik, S.K. Fuzzy logic model for selection of concrete placement methods and formwork systems. In Proceedings of the 3rd International Conference on Construction, Real Estate, Infrastructure and Project Management, National Institute of Construction Management and Research, Pune, India, 23–25 November 2018; pp. 89–98. [Google Scholar]
  51. Lohana, Y. Analysis of productivity criteria for selection of formwork system for construction of high rise building mega projects. In Proceedings of the 3rd International Conference on Construction, Real Estate, Infrastructure and Project Management, National Institute of Construction Management and Research, Pune, India, 23–25 November 2018; pp. 140–154. [Google Scholar]
  52. Ray, P.; Bera, D.K.; Rath, A.K. Comparison between the tunnel form system formwork and the MIVAN formwork system in a multi-unit building project. In Recent Developments in Sustainable Infrastructure; Das, B.B., Barbhuiya, S., Gupta, R., Saha, P., Eds.; Springer: Singapore, 2020; pp. 891–908. [Google Scholar] [CrossRef]
  53. Huszar, Z.; Lubloy, E. Examination of the cost ratio of the formwork. Acta Tech. Jaurinensis 2021, 14, 155–177. [Google Scholar] [CrossRef]
  54. Rajeshkumar, V.; Vinoth, S.; Jayan, S.; Prakash, J.; Kavimani, K.; Praveen, M. Effective selection of formwork using computer application. AIP Conf. Proc. 2021, 2327, 020044. [Google Scholar] [CrossRef]
  55. Yiğit, P. Istanbul housing and land appraisal system reform development process and property values analysis. J. Life Econ. 2020, 7, 59–78. [Google Scholar] [CrossRef] [Green Version]
  56. Türkiye Müteahhitler Birliği. Available online: https://www.tmb.org.tr/files/doc/1623914018902-ydmh-en.pdf (accessed on 23 November 2021).
  57. Engineering News-Record. Available online: https://www.enr.com/toplists/2020-Top-250-Global-Contractors-Preview (accessed on 23 November 2021).
  58. Jha, K.N. Formwork for Concrete Structures; Tata McGraw-Hill: New Delhi, India, 2012. [Google Scholar]
  59. Al Balkhy, W.; Sweis, R.; Lafhaj, Z. Barriers to adopting lean construction in the construction industry—The case of Jordan. Buildings 2021, 11, 222. [Google Scholar] [CrossRef]
  60. Oke, A.E.; Kineber, A.F.; Albukhari, I.; Othman, I.; Kingsley, C. Assessment of cloud computing success factors for sustainable construction industry: The case of Nigeria. Buildings 2021, 11, 36. [Google Scholar] [CrossRef]
  61. Al Balkhy, W.; Sweis, R. Assessing lean construction conformance amongst the second-grade Jordanian construction contractors. Int. J. Constr. Manag. 2019, 1–13. [Google Scholar] [CrossRef]
  62. Samara, A.; Sweis, R.J.; Tarawneh, B.; Albalkhy, W.; Sweis, G.; Alhomsi, S. Sustainability management of international development projects by International Non-Governmental Organizations: The case of INGOs working with refugees in Jordan. Int. J. Constr. Manag. 2020, 1–10. [Google Scholar] [CrossRef]
  63. Preston, C.C.; Colman, A.M. Optimal number of response categories in rating scales: Reliability, validity, discriminating power, and respondent preferences. Acta Psych. 2000, 104, 1–15. [Google Scholar] [CrossRef] [Green Version]
  64. Taherdoost, H. What is the best response scale for survey and questionnaire design; review of different lengths of rating scale/attitude scale/Likert scale. Int. J. Acad. Res. Manag. 2019, 8, 1–10. [Google Scholar]
  65. Simms, L.J.; Zelazny, K.; Williams, T.F.; Bernstein, L. Does the Number of Response Options Matter? Psychometric Perspectives Using Personality Questionnaire Data. Psych. Assess. 2019, 31, 557–566. [Google Scholar] [CrossRef] [PubMed]
  66. Boge, K.; Haddadi, A.; Klakegg, O.J.; Salaj, A.T. Facilitating Building Projects’ Short-Term and Long-Term Value Creation. Buildings 2021, 11, 332. [Google Scholar] [CrossRef]
  67. Patel, T.; Bapat, H.; Patel, D.; van der Walt, J.D. Identification of Critical Success Factors (CSFs) of BIM Software Selection: A Combined Approach of FCM and Fuzzy DEMATEL. Buildings 2021, 11, 311. [Google Scholar] [CrossRef]
  68. Türkiye Istatistik Kurumu. Available online: https://data.tuik.gov.tr/Bulten/Index?p=Paid-Employee-Statistics-July-2021-37504 (accessed on 10 October 2021).
  69. Gamil, Y.; Abdullah, M.A.; Abd-Rahman, I.; Asad, M.M. Internet of things in construction industry revolution 4.0: Recent trends and challenges in the Malaysian context. J. Eng. Des. Tech. 2020, 18, 1091–1102. [Google Scholar] [CrossRef]
  70. Sharma, G. Pros and cons of different sampling techniques. Int. J. Appl. Res. 2017, 3, 749–752. [Google Scholar]
  71. Cochran, W.G. Sampling Techniques; JohnWiley & Sons: New York, NY, USA, 1977. [Google Scholar]
  72. Albuainain, N.; Sweis, G.; AlBalkhy, W.; Sweis, R.; Lafhaj, Z. Factors Affecting Occupants’ Satisfaction in Governmental Buildings: The Case of the Kingdom of Bahrain. Buildings 2021, 11, 231. [Google Scholar] [CrossRef]
  73. Bartlett, J.E.; Kotrlik, J.W.; Higgins, C.C. Organizational research: Determining appropriate sample size in survey research. Inf. Technol. Learn. Perform. J. 2001, 19, 43–50. [Google Scholar]
  74. Hoonakker, P.; Carayon, P.; Loushine, T. Barriers and benefits of quality management in the construction industry: An empirical study. Total Qual. Manag. Bus. Excell. 2010, 21, 953–969. [Google Scholar] [CrossRef]
  75. Ogunmakinde, O.E.; Sher, W.; Maund, K. An assessment of material waste disposal methods in the Nigerian construction industry. Recycling 2019, 4, 13. [Google Scholar] [CrossRef] [Green Version]
  76. Fahmy, A.; Hassan, T.M.; Bassioni, H. Improving RCPSP solutions quality with Stacking Justification–Application with particle swarm optimization. Expert Syst. Appl. 2004, 41, 5870–5881. [Google Scholar] [CrossRef]
  77. Goh, C.S.; Abdul-Rahman, H. The Identification and Management of Major Risks in the Malaysian Construction Industry. J. Constr. Dev. Ctries. 2013, 18, 19–32. [Google Scholar]
  78. Chitkara, K.K. Construction Project Management: Planning, Scheduling and Controlling; McGraw-Hill: New Delhi, India, 2014. [Google Scholar]
  79. Dossick, C.S.; Neff, G. Organizational divisions in BIM-enabled commercial construction. J. Constr. Eng. Manag. 2010, 136, 459–467. [Google Scholar] [CrossRef] [Green Version]
  80. Chen, Y.; Lu, H.; Lu, W.; Zhang, N. Analysis of project delivery systems in Chinese construction industry with data envelopment analysis (DEA). Eng. Constr. Archit. Manag. 2010, 17, 598–614. [Google Scholar] [CrossRef]
  81. Sheskin, D.J. Handbook of Parametric and Nonparametric Statistical Procedures, 5th ed.; Chapman and Hall/CRC: London, UK, 2011. [Google Scholar]
  82. Ahmed, H.; Edwards, D.J.; Lai, J.H.K.; Roberts, C.; Debrah, C.; Owusu-Manu, D.-G.; Thwala, W.D. Post occupancy evaluation of school refurbishment projects: Multiple case study in the UK. Buildings 2021, 11, 169. [Google Scholar] [CrossRef]
  83. Brewerton, P.; Millward, L. Organisational Research Methods; Sage Publications: London, UK, 2001. [Google Scholar]
  84. Sekaran, U. Research Methods for Business: A Skill Building Approach, 4th ed.; John Wiley & Sons: New York, NY, USA, 2003. [Google Scholar]
  85. Cooper, D.R.; Emory, C.W. Business Research Methods; Irwin: Chicago, IL, USA, 1995. [Google Scholar]
  86. Nunnally, J.; Bernstein, I. Psychometric Theory, 3rd ed.; McGraw-Hill: New York, NY, USA, 1994. [Google Scholar]
  87. Doloi, H.; Sawhney, A.; Iyer, K.C.; Rentala, S. Analysing factors affecting delays in Indian construction projects. Int. J. Proj. Manag. 2012, 30, 479–489. [Google Scholar] [CrossRef]
  88. Sinesilassie, E.G.; Tripathi, K.K.; Tabish, S.Z.S.; Jha, K.N. Modeling success factors for public construction projects with the SEM approach: Engineer’s perspective. Eng. Constr. Archit. Manag. 2019, 26, 2410–2431. [Google Scholar] [CrossRef]
  89. Bagozzi, R.P.; Yi, Y.; Phillips, L.W. Assessing Construct Validity in Organizational Research. Adm. Sci. Q. 1991, 36, 421–458. [Google Scholar] [CrossRef]
  90. Kaiser, H.F. An index of factorial simplicity. Psychometrika 1974, 39, 31–36. [Google Scholar] [CrossRef]
  91. Field, A. Discovering Statistics Using IBM SPSS Statistic, 4th ed.; Sage Publications: Thousand Oaks, CA, USA, 2013. [Google Scholar]
  92. Hair, J.F.; Black, W.C.; Babin, B.J.; Anderson, R.E. Multivariate Data Analysis, 7th ed.; Prentice Hall: Hoboken, NJ, USA, 2009. [Google Scholar]
  93. Manzoor, B.; Othman, I.; Gardezi, S.S.S.; Harirchian, E. Strategies for adopting building information modeling (BIM) in sustainable building projects—A case of Malaysia. Buildings 2021, 11, 249. [Google Scholar] [CrossRef]
  94. Montgomery, D.C. Design and Analysis of Experiments; Wiley: New York, NY, USA, 2005. [Google Scholar]
  95. Forza, C. Survey research in operations management: A process-based perspective. Int. J. Oper. Prod. Manag. 2002, 22, 152–194. [Google Scholar] [CrossRef] [Green Version]
  96. Fellows, R.F.; Liu, A.M. Research Methods for Construction, 4th ed.; John Wiley & Sons: Hoboken, NJ, USA, 2015. [Google Scholar]
  97. Kassem, M.A.; Khoiry, M.A.; Hamzah, N. Risk factors in oil and gas construction projects in developing countries: A case study. Int. J. Energy Sect. Manag. 2019, 13, 846–861. [Google Scholar] [CrossRef]
  98. Raouf, A.M.; Al-Ghamdi, S.G. Managerial Practitioners’ Perspectives on Quality Performance of Green-Building Projects. Buildings 2020, 10, 71. [Google Scholar] [CrossRef] [Green Version]
  99. Lam, P.T.; Javed, A.A. Comparative study on the use of output specifications for Australian and UK PPP/PFI projects. J. Perform. Constr. Facil. 2013, 29, 1–11. [Google Scholar]
  100. Siegel, S.; Castellan, N.J. Nonparametric Statistics for the Behavioral Sciences; McGraw-Hill: New York, NY, USA, 1988. [Google Scholar]
  101. Lau, C.H.; Mesthrige, J.W.; Lam, P.T.I.; Javed, A.A. The challenges of adopting new engineering contract: A Hong Kong study. Eng. Constr. Archit. Manag. 2019, 26, 2389–2409. [Google Scholar] [CrossRef]
  102. Hussain, S.; Zhu, F.; Ali, Z.; Aslam, H.D.; Hussain, A. Critical delaying factors: Public sector building projects in Gilgit-Baltistan, Pakistan. Buildings 2018, 8, 6. [Google Scholar] [CrossRef] [Green Version]
  103. Kottegoda, N.T.; Rosso, R. Applied Statistics for Civil and Environmental Engineers; McGraw-Hill: New York, NY, USA, 1997. [Google Scholar]
  104. Bajjou, M.S.; Chafi, A. Empirical study of schedule delay in Moroccan construction projects. Int. J. Constr. Manag. 2018, 20, 783–800. [Google Scholar] [CrossRef]
  105. Zhou, Y.; Yang, Y.; Yang, J.B. Barriers to BIM implementation strategies in China. Eng. Constr. Archit. Manag. 2019, 26, 554–574. [Google Scholar] [CrossRef]
  106. Olanrewaju, O.I.; Chileshe, N.; Babarinde, S.A.; Sandanayake, M. Investigating the barriers to building information modeling (BIM) implementation within the Nigerian construction industry. Eng. Constr. Archit. Manag. 2020, 27, 2931–2958. [Google Scholar] [CrossRef]
  107. Osei-Kyei, R.; Chan, A.P.C. Empirical comparison of critical success factors for public-private partnerships in developing and developed countries: A case of Ghana and Hong Kong. Eng. Constr. Archit. Manag. 2017, 24, 1222–1245. [Google Scholar] [CrossRef]
  108. Manoharan, K.; Dissanayake, P.; Pathirana, C.; Deegahawature, D.; Silva, R. Assessment of critical factors influencing the performance of labour in Sri Lankan construction industry. Int. J. Constr. Manag. 2020, 1–35. [Google Scholar] [CrossRef]
  109. Fischer, M.; Tatum, C.B. Characteristics of design-relevant constructability knowledge. J. Constr. Eng. Manag. 1997, 123, 253–260. [Google Scholar] [CrossRef]
  110. Shrivastava, A.; Chourasia, D.; Saxena, S. Planning of formwork materials. Mater. Today Proc. 2021, 47, 7060–7063. [Google Scholar] [CrossRef]
  111. Kannan, M.; Santhi, M. Automated constructability rating framework for concrete formwork systems using building information modeling. Asian J. Civ. Eng. 2018, 19, 387–413. [Google Scholar] [CrossRef]
  112. ACI Committee 308. Guide to Curing Concrete; ACI 308R-01; ACI (American Concrete Institute): Farmington Hills, MI, USA, 2001. [Google Scholar]
  113. Malara, J.; Plebankiewicz, E.; Juszczyk, M. Formula for determining the construction workers productivity including environmental factors. Buildings 2019, 9, 240. [Google Scholar] [CrossRef] [Green Version]
  114. Kannan, M.; Santhi, M. Constructability assessment of climbing formwork systems using building information modeling. Procedia Eng. 2013, 64, 1129–1138. [Google Scholar] [CrossRef] [Green Version]
  115. Abou Ibrahim, H.A.; Hamzeh, F.R. Expected lean effects of advanced high-rise formwork systems. In Proceedings of the 23rd Annual Conference of the International Group for Lean Construction, Perth, Australia, 28–31 July 2015; pp. 83–92. [Google Scholar] [CrossRef]
  116. Lee, B.; Choi, H.; Min, B.; Lee, D.-E. Applicability of formwork automation design software for aluminum formwork. Appl. Sci. 2020, 10, 9029. [Google Scholar] [CrossRef]
  117. Ko, C.H.; Kuo, J.D. Making formwork design lean. J. Eng. Proj. Prod. Manag. 2019, 9, 29–47. [Google Scholar] [CrossRef] [Green Version]
  118. Huang, R.Y.; Chen, J.J.; Sun, K.S. Planning gang formwork operations for building construction using simulations. Autom. Constr. 2004, 13, 765–779. [Google Scholar] [CrossRef]
  119. Hyun, H.; Park, M.; Lee, D.; Lee, J. Tower crane location optimization for heavy unit lifting in high-rise modular construction. Buildings 2021, 11, 121. [Google Scholar] [CrossRef]
  120. Jarkas, A.M. Buildability factors affecting formwork labour productivity of building floors. Can. J. Civ. Eng. 2010, 37, 1383–1394. [Google Scholar] [CrossRef]
Figure 1. Research flowchart.
Figure 1. Research flowchart.
Buildings 11 00618 g001
Figure 2. FWS selection criteria in building construction projects (adapted from [10]).
Figure 2. FWS selection criteria in building construction projects (adapted from [10]).
Buildings 11 00618 g002
Table 1. Mean score analysis of “professional title” of respondents.
Table 1. Mean score analysis of “professional title” of respondents.
ID No.Overall Respondents (N = 222)Professional Title of Respondents
CO (N = 54)PM/CM/SE (N = 81)PL/PR/TO (N = 42)FD/FSL (N = 45)
MeanRankMeanRankMeanRankMeanRankMeanRank
ID13.84743.648103.83923.42894.4881
ID23.84653.72273.76563.54754.4222
ID33.495133.481153.407153.285133.86614
ID43.648103.425163.60493.47674.1559
ID52.891312.666322.839312.928193.22228
ID63.86933.88833.76553.57134.3114
ID73.563123.75963.518133.190163.75516
ID83.162233.111253.13212.714243.68818
ID93.486153.537143.2469193.309104.02211
ID103.66293.592123.60483.57143.93313
ID113.189213.259193.098252.952183.48826
ID123.90523.87053.80243.73814.2886
ID133.486163.70393.4198143.214153.60021
ID143.603113.72283.543113.309113.84415
ID152.675332.666332.666342.309333.04433
ID162.455352.296352.567352.285342.60035
ID172.648342.444342.740332.333323.02234
ID183.95014.01823.86413.64224.3115
ID192.959302.944302.950302.809233.13330
ID202.968293.018283.024292.642273.11131
ID213.495143.555133.530123.238143.60022
ID223.84264.16613.580103.54764.2008
ID233.78383.629113.81433.45284.2227
ID243.243203.166213.333162.857203.53325
ID253.175223.407173.0741282.619283.60023
ID263.261193.148233.321172.857213.66619
ID273.83773.88843.75373.309124.4223
ID283.351173.240203.259183.023173.95512
ID293.090263.296183.098242.714253.17729
ID303.067283.037273.098272.690263.40027
ID313.130243.166223.098262.595293.64420
ID323.099253.074263.123222.547303.60024
ID333.279183.129243.172202.833224.06610
ID343.085272.981293.111232.476313.73317
ID352.752322.944312.790322.071353.08832
Table 2. Mean score analysis of “field of specialization” of respondents’ company.
Table 2. Mean score analysis of “field of specialization” of respondents’ company.
ID No.Overall Respondents (N = 222)Field of Specialization of Respondents’ Company
PMS (N = 66)ENG/DSG (N = 43)FW/SCF (N = 48)GC/SC (N = 65)
MeanRankMeanRankMeanRankMeanRankMeanRank
ID13.84644.00013.581124.437513.4309
ID23.84653.92423.67484.375033.4927
ID33.495133.545113.488153.8750153.16916
ID43.648103.65193.441164.125093.43010
ID52.891312.787312.767313.1667292.87626
ID63.86933.74273.88354.354243.6304
ID73.563123.515123.581133.7917163.43011
ID83.162233.151223.116213.7292182.78428
ID93.486153.318163.69774.0625113.09219
ID103.66293.590103.90734.0000123.32313
ID113.189213.106253.279173.4792263.00021
ID123.90523.77254.00024.291763.6922
ID133.486163.333153.558143.6250203.4928
ID143.603113.484133.604103.8958143.5076
ID152.675332.666332.581343.0208322.49234
ID162.455352.424342.627332.5833352.27635
ID172.648342.363352.697323.0208332.63032
ID183.95013.90933.90744.312553.7531
ID192.959303.151233.023263.1042302.61533
ID202.968293.075263.139183.0833312.66131
ID213.495143.469143.65193.6250213.32314
ID223.84263.87844.04614.187583.41512
ID233.78383.69783.76764.229273.5535
ID243.243203.212203.093223.5000253.18415
ID253.175223.197213.023273.5625232.96922
ID263.261193.227193.023283.6875193.13817
ID273.83773.77263.604114.395823.6463
ID283.351173.272173.139193.9583133.12318
ID293.090263.151243.093233.2083282.93824
ID303.067283.060272.953303.3750272.92325
ID313.130242.924303.069243.6042223.03020
ID323.099252.954293.046253.5417242.95323
ID333.279183.242183.139204.0833102.81527
ID343.085273.060282.976293.7708172.67630
ID352.752322.757322.558353.0000342.69229
Table 3. Kruskal–Wallis test statistics for “professional title” and “field of specialization” categories.
Table 3. Kruskal–Wallis test statistics for “professional title” and “field of specialization” categories.
ID No.FWS Selection Criteriap-Values of the Kruskal–Wallis Tests
Asymp. Sig. (Professional Title)Asymp. Sig. (Field of Specialization)
1Type of structural slab0.002 *0.002 *
2Type of structural lateral loads-supporting system0.003 *0.002 *
3Total building height0.1710.093
4Variation in column/wall dimensions and location 0.021 *0.016 *
5Variation in openings/inserts dimensions and location 0.2980.533
6Degree of repetition of the FWS0.044 *0.024 *
7Number of floors0.2010.456
8Floor area 0.015 *0.008 *
9Floor to floor height0.042 *0.002 *
10Uniformity of building 0.6320.038 *
11Type of concrete finish0.3040.268
12Speed of construction0.1950.091
13Labour quality0.3780.658
14Labour productivity0.5490.499
15Weather conditions0.0930.287
16Site access0.3890.681
17Size of site 0.0750.109
18Initial cost of the FWS0.1320.110
19Transportation cost of the FWS0.8050.262
20Maintenance cost of the FWS0.4070.246
21Labour cost of the FWS0.6460.493
22Potential reuse of the FWS in other projects 0.017 *0.018 *
23Hoisting equipment 0.041 *0.026 *
24In-house capability0.1310.603
25FWS sustainability 0.015 *0.180
26FWS safety0.0650.126
27FWS durability<0.001 *0.002 *
28FWS flexibility0.003 *0.003 *
29FWS compatibility0.2780.780
30FWS complexity0.1480.361
31FWS weight0.004 *0.055
32FWS size 0.009 *0.118
33FWF technical support<0.001 *<0.001 *
34FWF logistical support0.001 *0.002 *
35FWF BIM support0.019 *0.667
* The Kruskal–Wallis test is significant at the 0.05 level.
Table 4. Mann–Whitney U test statistics for “professional title” category.
Table 4. Mann–Whitney U test statistics for “professional title” category.
FWS Selection Criteria ID No.Asymp. Sig. (Two-Tailed) of Pairwise Comparison
CO and PM/CM/SECO and PL/PR/TOCO and FD/FSLPM/CM/SE and PL/PR/TOPM/CM/SE and FD/FSLPL/PR/TO and FD/FSL
10.3880.543<0.001 *0.1540.007 *<0.001 *
20.7440.768<0.001 *0.5470.001 *0.002 *
30.6930.3750.1990.5090.0710.034 *
40.3000.6130.002 *0.7800.019 *0.033 *
50.5690.3670.0620.7320.1490.355
60.7280.1750.1090.2780.046 *0.004 *
70.5770.0590.7920.1880.3740.056
80.7410.1330.027 *0.1120.0820.001 *
90.3470.4810.0790.8310.007 *0.027 *
100.8530.9910.2320.8680.2960.291
110.4220.3200.5300.6240.1100.100
120.9570.8910.0620.7910.040 *0.148
130.2180.1330.7200.4880.4380.249
140.4300.3110.9410.5620.3600.205
150.8900.1940.1930.1040.1590.014 *
160.1860.8380.2690.2200.9250.233
170.2530.6780.037 *0.1320.3290.016 *
180.5100.2410.2290.4900.0570.030 *
190.8940.6440.5640.5310.6620.308
200.8970.2080.8310.1610.9620.091
210.9910.2900.9570.2670.8950.270
220.019 *0.028 *0.9910.8510.023 *0.031 *
230.3250.7310.011 *0.2370.0810.013 *
240.5670.2250.2530.0650.4800.024 *
250.2940.013 *0.3610.1120.049 *0.005 *
260.4900.3410.0780.0870.2090.010 *
270.8310.0820.003 *0.1260.002 *<0.001 *
280.7870.3980.003 *0.2820.003 *0.001 *
290.5360.0560.6520.1750.9000.131
300.7270.2530.1630.1560.2030.032 *
310.8670.040 *0.0700.045 *0.034 *<0.001 *
320.7060.0610.039 *0.040 *0.0770.001 *
330.8270.333<0.001 *0.204<0.001 *<0.001 *
340.5300.1100.009 *0.026 *0.019 *<0.001 *
350.6970.008 *0.6310.020 *0.3830.004 *
* The Mann–Whitney U test is significant at the 0.05 level.
Table 5. Mann–Whitney U test statistics for “field of specialization” category.
Table 5. Mann–Whitney U test statistics for “field of specialization” category.
FWS Selection Criteria ID No.Asymp. Sig. (Two-Tailed) of Pairwise Comparison
PMS and FW/SCFPMS and ENG/DSGPMS and GC/SCENG/DSG and FW/SCFENG/DSG and GC/SCFW/SCF and GC/SC
10.014 *0.3570.0550.013 *0.463<0.001 *
20.006 *0.6630.0870.020 *0.391<0.001 *
30.1500.9310.1970.1890.3050.013 *
40.0900.3220.2000.010 *0.8990.002 *
50.1690.9820.7200.2830.7980.255
60.008 *0.4680.6710.1020.3250.005 *
70.2720.7580.5510.4790.4480.117
80.039 *0.9040.1420.0510.251<0.001 *
90.006 *0.1410.3530.3370.023 *<0.001 *
100.2410.4030.1830.7490.024 *0.007 *
110.2540.5160.5220.7350.2490.039 *
120.0570.4190.6210.3650.1760.016 *
130.2530.3390.5610.9930.6500.551
140.1650.4640.9260.6890.5440.186
150.1830.7470.5880.1260.8730.070
160.6040.5760.6030.9840.3080.302
170.016 *0.2560.2330.2710.8900.149
180.2130.9080.2610.2000.3460.010 *
190.8460.7490.0690.8710.2010.130
200.8690.7520.1000.7240.1010.137
210.6980.2740.5640.5270.1770.322
220.2210.2870.0760.9690.018 *0.005 *
230.031 *0.5720.3620.1700.1950.002 *
240.2670.7660.9450.2530.8770.265
250.1230.6930.4630.1320.8160.032 *
260.0780.4800.7310.038 *0.7220.048 *
270.005 *0.6650.3800.005 *0.770<0.001 *
280.003 *0.7110.6880.006 *0.872<0.001 *
290.8690.9720.4010.8710.5450.335
300.2140.7140.6270.1590.9570.098
310.008 *0.5910.6140.1160.8220.021 *
320.031 *0.7520.9740.1710.6480.023 *
33<0.001 *0.7970.1070.001 *0.266<0.001 *
340.006 *0.8320.1720.012 *0.301<0.001 *
350.4610.6340.7500.2480.7020.321
* The Mann–Whitney U test is significant at the 0.05 level.
Table 6. Spearman’s rank correlation test results for “professional title” category.
Table 6. Spearman’s rank correlation test results for “professional title” category.
Combination of GroupsρLevel of SignificanceDegree of Agreement
CO and PM/CM/SE0.893 **<0.001Positive, High
CO and PL/PR/TO0.870 **<0.001Positive, High
CO and FD/FSL0.812 **<0.001Positive, High
PM/CM/SE and PL/PR/TO0.903 **<0.001Positive, Very High
PM/CM/SE and FD/FSL0.901 **<0.001Positive, Very High
PL/PR/TO and FD/FSL0.831 **<0.001Positive, High
** Correlation is significant at the 0.01 level (2-tailed).
Table 7. Spearman’s rank correlation test results for “field of specialization” category.
Table 7. Spearman’s rank correlation test results for “field of specialization” category.
Combination of GroupsρLevel of SignificanceDegree of Agreement
PMS and FW/SCF0.913 **<0.001Positive, Very High
PMS and ENG/DSG0.889 **<0.001Positive, High
PMS and GC/SC0.886 **<0.001Positive, High
ENG/DSG and FW/SCF0.810 **<0.001Positive, High
ENG/DSG and GC/SC0.831 **<0.001Positive, High
FW/SCF and GC/SC0.822 **<0.001Positive, High
** Correlation is significant at the 0.01 level (2-tailed).
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Terzioglu, T.; Polat, G.; Turkoglu, H. Analysis of Formwork System Selection Criteria for Building Construction Projects: A Comparative Study. Buildings 2021, 11, 618. https://doi.org/10.3390/buildings11120618

AMA Style

Terzioglu T, Polat G, Turkoglu H. Analysis of Formwork System Selection Criteria for Building Construction Projects: A Comparative Study. Buildings. 2021; 11(12):618. https://doi.org/10.3390/buildings11120618

Chicago/Turabian Style

Terzioglu, Taylan, Gul Polat, and Harun Turkoglu. 2021. "Analysis of Formwork System Selection Criteria for Building Construction Projects: A Comparative Study" Buildings 11, no. 12: 618. https://doi.org/10.3390/buildings11120618

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop