4.1. Model Validation
The steady-state model developed for the dual-pressure nitric acid plant was validated using measured industrial data under nominal operating conditions.
Table 3 compares plant measurements and simulation results for key process parameters, including feed preparation, ammonia oxidation, heat recovery, compression, absorption, tail gas treatment, and utility consumption. The close agreement between measured and simulated values confirms the adequacy of the selected thermodynamic models, reaction schemes, and unit operation configurations.
The validation data set is a 72 h campaign at nominal full load, from which each parameter was averaged over the last 12 h of stable operation, stability being defined as an ammonia feed rate varying by less than 1% and a turbine inlet temperature varying by less than 5 K. The instrument uncertainties applicable to the measured column of
Table 3 are plus or minus 1.5% of reading for the Coriolis and orifice flow metres, plus or minus 1.5 K for the Class A resistance thermometers, plus or minus 0.5% of span for the pressure transmitters, and plus or minus 2% of reading for the on-line gas analysers. Over the 28 parameters compared, the mean absolute percentage deviation is 1.2%, the root mean square relative deviation is 2.4%, and the maximum absolute deviation is 9.3%. Twenty-one of the 28 parameters agree within 1.0% and 24 within 2.5%, so that most deviations fall inside the combined instrument uncertainty band and cannot be distinguished from measurement scatter. The three stack composition entries deviate by 3.8–4.5%, consistent with the 2% analyser tolerance combined with the uncertainty of the fixed catalyst conversions; only the exhaust tail gas temperature lies substantially outside the band, and it is examined below. The validation rests on a single nominal operating point, and its representativeness at part load has not been established; this limitation is stated in
Section 4.6.
Minimal deviations are observed in the primary feed and core reaction parameters. The ammonia flow rate differs by −0.1%, and the feed water flow rate deviates by −0.2%. The ammonia-to-air ratio is reproduced with a deviation of 0.1%, while the ammonia conversion ratio matches the measured value at 96.0%. The conversion reactor temperature deviates by −1.0%, which is acceptable given the highly exothermic nature of ammonia oxidation and the sensitivity of temperature to small variations in reaction enthalpy and heat capacity data. These results indicate that the conversion-based reaction model and energy-balance formulation accurately describe the oxidation stage.
The model accurately represents the waste heat recovery section. The model reproduces the waste-heat outlet gas temperature and medium-pressure steam consumption exactly, while the medium-pressure steam temperature deviates by 0.7%. These minor differences result from simplifications in heat exchanger modelling, such as neglecting external heat losses and fouling effects. The air compressor outlet pressure is predicted without deviation; however, the outlet temperature differs by 2.5%, representing one of the largest deviations in the dataset. This discrepancy is attributable to the model’s use of constant isentropic efficiency and idealised compressor performance curves, whereas actual industrial compressors operate with variable efficiency due to mechanical and thermal losses. The nitrous gas compression and washing section demonstrates strong agreement between the model and plant data. The nitrous compressor outlet pressure and temperature deviate by 0.0% and −0.2%, respectively. The gas washer top and bottom temperatures deviate by 2.2% and 0.6%, respectively. The larger deviation at the washer top temperature is due to simplifications in rate-based absorption and heat-transfer modelling, such as assuming ideal insulation and a uniform phase distribution. The predicted NO2 absorption ratio of 99.1% differs from measured data by only 0.1%, indicating that the extended NRTL thermodynamic framework and absorber configuration reliably represent mass transfer and phase equilibrium.
The tail gas treatment and turbine section maintain acceptable predictive accuracy. The tail gas temperature before the reactor is reproduced exactly, while the temperature after the reactor deviates by −0.9%. This minor difference arises from modelling catalytic conversion with fixed conversion ratios rather than from detailed kinetic expressions. The gas turbine outlet temperature deviates by 1.9%, consistent with the assumption of constant turbine efficiency and the neglect of minor mechanical and heat losses. The exhaust tail gas temperature shows the largest deviation at 9.3%, due to the combined effects of simplified heat recovery modelling, neglected external heat losses, and the absence of detailed turbine cooling-air mixing phenomena. Despite this deviation in absolute exhaust temperature, the emission composition is reproduced accurately.
The consequences of the 9.3% deviation in exhaust tail gas temperature for the reported results can be bounded quantitatively. The deviation corresponds to a simulated stack temperature 22 K above the measured value at a stack gas flow of 236,900 kg/h, which represents about 6.3 MW of sensible heat that the model assumes leaves with the stack gas rather than being recovered in the recuperative tail gas heater. The model is therefore conservative with respect to heat recovery rather than optimistic. Decisively, the recuperative exchanger is not modified in either retrofit, and the same modelling simplification is applied identically to the base case and to both options, so the error is common-mode and cancels in every differential quantity: the changes in utility consumption reported in
Table 4, the emission changes reported in
Table 5, and the payback periods reported in
Table 6. The residual differential error is bounded by the change in stack gas flow between cases. For Option 2, the stack flow falls by 1.3%, and the effect is negligible. For Option 1, the stack flow rises by 10.5%, giving a bounding error of 0.66 MW, equivalent to 66 STD m
3/h of natural gas, or 226,000 EUR/y and 1083 t CO
2/y. That represents 4.0% of the annual net benefit of Option 1 and 1.7% of its annual CO
2-equivalent reduction, and it lengthens the discounted payback period of Option 1 from 12.1 to 12.7 months. The deviation therefore affects neither the option ranking nor any conclusions drawn from it.
The stack composition is validated species by species rather than through a single aggregate NO
x figure, because the aggregate conceals the individual conversions that the retrofit is designed to change.
Table 3 therefore compares N
2O, NO, and NO
2 separately, each as a volumetric fraction of the wet stack gas, with deviations of −4.5%, −4.1%, and −3.8%, respectively.
Table 5 reports the corresponding mass concentrations referenced to dry gas at standard conditions and uses them for the regulatory comparison in
Section 4.3, with conversion based on the water content and mean molar mass of the stack gas given in that table.
4.2. Energy Performance and Plant Yield
Modifying the tail gas treatment system significantly affects the overall energy balance of the dual-pressure nitric acid plant.
Table 4 shows that the base case operates with a natural gas consumption of 3528 STD m
3/h and requires 221 STD m
3/h of the N
2/H
2 mixture for non-selective catalytic reduction. Both retrofit options eliminate the need for the N
2/H
2 mixture, indicating a fundamental change in the reduction mechanism. However, natural gas demand differs between the two scenarios: Option 1 increases consumption to 3763 STD m
3/h, while Option 2 reduces it to 3379 STD m
3/h. This variation reflects the distinct thermal management strategies implemented in each option. In Option 1, the newly installed combustion chamber requires additional fuel to reach the target turbine inlet temperature after selective catalytic purification. In contrast, Option 2 utilises residual oxygen in the tail gas for catalytic fuel oxidation within the reactor, enabling temperature control with reduced external fuel input.
Electricity consumption further differentiates the two retrofit solutions. Option 1 requires an additional 3155 kW because it installs a new air compressor to support the modified gas treatment configuration. In contrast, Option 2 does not increase electrical demand, as the catalytic reactor achieves the necessary temperature rise internally. From an energy-integration perspective, Option 2 provides a more compact, thermally integrated design. Differences in steam generation and consumption patterns further highlight these distinctions. Option 1 increases steam generation from 64.1 t/h to 70.0 t/h due to enhanced heat recovery associated with higher combustion intensity. At the same time, steam consumption decreases from 41.4 t/h to 29.0 t/h, indicating improved internal heat utilisation. Option 2 maintains steam generation at the base-case level (64.1 t/h) and slightly reduces steam consumption to 31.5 t/h. Although both options improve the steam balance, the additional electricity requirement in Option 1 partially offsets its thermal advantages when total energy costs are considered.
Figure 5 also shows the impact on plant yield. Option 1 increases nitric acid production by about 5%, a significant improvement for a plant operating near design capacity. This yield enhancement results from more stable tail gas temperature control and improved process conditions, enabling higher throughput without negatively affecting turbine operation. In contrast, Option 2 does not significantly increase plant capacity and maintains production levels similar to the base case. Therefore, although Option 2 achieves superior fuel efficiency, it does not support production intensification to the same extent as Option 1.
A critical assessment of the results indicates that Option 1 prioritises productivity and steam recovery, though at the cost of increased fuel and electricity consumption. In contrast, Option 2 emphasises fuel efficiency and reduced operational energy costs, with minimal effect on throughput. The choice between these alternatives should align with the plant’s strategic objectives. If capacity expansion and revenue growth are prioritised, Option 1 may be justified despite its higher utility requirements. Conversely, if minimising energy consumption and operating costs are the primary objectives, Option 2 offers a more energy-efficient, thermodynamically integrated solution. Both configurations improve internal heat utilisation compared to the base case, but they differ fundamentally in how they balance energy intensity with production gains.
The additional electrical load of Option 1 warrants separate examination on a primary energy and Scope 2 basis, since electricity is an energy carrier rather than a primary fuel. The 3155 kW of new compressor duty corresponds to 26,256 MWh/y, or 94.5 TJ/y of final energy; at a European average conversion efficiency of about 40%, this represents 236 TJ/y of primary energy. The increase in natural gas consumption adds a further 70 TJ/y. Against these, the improvement in the steam balance of Option 1, an increase in generation of 5.9 t/h combined with a reduction in consumption of 12.4 t/h, releases 18.3 t/h of steam, equivalent to about 419 TJ/y of boiler fuel avoided. On a primary energy basis, Option 1 is therefore favourable by roughly 110 TJ/y, and the apparent energy penalty visible in
Table 4 is an artefact of comparing carriers rather than primary energy.
The Scope 2 consequence depends on the grid emission factor and is more sensitive. At the life-cycle factor of 0.490 kg CO
2/kWh adopted in
Section 2.6, the additional electricity carries 12,865 t CO
2/y. At the present EU-27 average of about 0.21 kg CO
2/kWh, it carries 5514 t/y; on a predominantly nuclear or hydro grid at 0.05 kg CO
2/kWh, 1313 t/y; and on a coal-dominated grid at 0.70 kg CO
2/kWh, 18,379 t/y. These figures are to be compared with the direct reduction of 64,753 t CO
2-eq/y delivered by Option 1, so the Scope 2 penalty consumes between 2% and 28% of the direct benefit depending on location. Option 1 remains net beneficial on every grid examined, but its advantage narrows appreciably in carbon-intensive electricity systems, whereas Option 2, which adds no electrical load, is insensitive to the grid factor. Where the grid is carbon-intensive, this consideration alone favours Option 2.
4.3. Environmental Performance
The environmental performance of the two retrofit options is evaluated on the basis of the direct emissions of greenhouse gases and nitrogen oxides reported at the stack, as summarised in
Table 5 and illustrated in
Figure 6. The analysis quantifies changes in N
2O, NO, NO
2, CO
2, and NH
3 mass flow rates relative to the base case and interprets the cumulative effect through the CO
2-equivalent metric. The assessment is based on the full simulated stack composition rather than a selected subset of species, so it accounts for every component leaving the plant and states each greenhouse contribution explicitly. Three of the twelve species present carry a direct 100-year global warming potential: CO
2 at 1, N
2O at 298, and CH
4 at 25, the last arising from unconverted natural gas slipping through the tail gas reactor. The remaining species, namely NO, NO
2, N
2O
4, CO, NH
3, H
2O, N
2 and O
2, have no direct global warming potential defined by IPCC and fall outside the EU Emissions Trading System (EU ETS) obligation for nitric acid installations; they contribute nothing to the CO
2-equivalent totals and are reported separately as air quality indicators. Applying a greenhouse factor to nitrogen oxides, as is sometimes done, would substantially overstate the totals and is not done here. The annualization basis is 8322 operating hours per year, corresponding to the 95% plant load factor of
Section 2.6, and is applied uniformly to
Table 4,
Table 5 and
Table 6 and to
Figure 5 and
Figure 6.
N2O is the dominant environmental concern in nitric acid production and represents the primary driver for tail gas treatment retrofit. In the base case, the N2O emission rate reaches 38.61 kg/h, consistent with the typical output of a dual-pressure plant without tertiary abatement or with a non-selective catalyst. Both retrofit options achieve substantial N2O reduction: Option 1 reduces the flow to 12.36 kg/h, while Option 2 achieves 12.35 kg/h, both corresponding to a 68.0% reduction. These reductions are significant in absolute terms: on an annualised basis of 8322 operating hours per year, the N2O mass flow falls by 218.4 and 218.6 t/y respectively, equivalent to 65,096 and 65,143 t CO2-eq/y from N2O alone. Expressed per unit of production, the specific emission factor falls from 0.74 kg N2O per tonne of 100% HNO3 in the base case to 0.23 kg/t for Option 1 and 0.24 kg/t for Option 2. Option 1 reaches the marginally lower figure because its residual mass flow is spread over a 5% larger output.
The selective catalytic reduction with ammonia, common to both retrofit configurations, reduces total NO
x emissions markedly. In the base case, the combined NO and NO
2 emission is 20.20 kg/h. Option 1 reduces this to 12.00 kg/h (−40.6%), and Option 2 achieves the lowest NO
x output of 8.77 kg/h (−56.6%). The stronger NO
x reduction in Option 2 is consistent with its reactor design: the two-shelf configuration with an additional catalyst layer provides a longer gas residence time in the SCR zone, enabling more complete conversion of residual NO
x even at the elevated temperatures characteristic of this variant. Ammonia slip falls from 3.05 kg/h in the base case, which is 17.5 mg/nm
3 referenced to dry gas, to 0.01 kg/h in Option 1 and to a value indistinguishable from zero in Option 2. These simulated figures should not, however, be read as a claim that slip is eliminated: they are an artefact of the conversion-based reactor model, which consumes the dosed ammonia completely by construction, and they are not measurements. For permitting purposes, the appropriate value is the design specification of 5 ppmv, equivalent to 0.66 kg/h or 3.8 mg/nm
3 on the Option 2 stack flow, which is the guarantee customarily offered for a fresh charge at stoichiometric dosing. Achieving it under industrial flow disturbances requires closed-loop control rather than fixed dosing: the configuration assumed here doses ammonia on a feedforward molar ratio computed from the measured tail gas flow and the inlet NO
x analyser signal, trimmed by a slow feedback loop from a downstream ammonia analyser, with the ratio clamped below unity during load transients so that slip is bounded at the expense of a transient reduction in NO
x conversion. Slip will rise above the design value towards the end of catalyst life, which is one reason the catalyst replacement provision of
Section 2.7 is charged against the annual benefit.
The CO2 emission profile reflects the contrasting thermal management strategies of the two options. Option 1 increases direct CO2 emissions from 6834 kg/h (base case) to 6983 kg/h (+2.2%), which is attributable to the higher natural gas consumption in the newly installed combustion chamber required to bring the purified gas to turbine inlet temperature. Option 2, by contrast, reduces CO2 emissions to 6732 kg/h (−1.5%) by using residual oxygen in the tail gas for internal catalytic oxidation, thereby reducing net fuel combustion. This fundamental difference underscores the thermodynamic trade-off: Option 1 achieves a greater throughput gain at the cost of higher carbon intensity per unit of production, while Option 2 operates with near-base-case fuel consumption and lower direct CO2 output.
The total environmental impact, expressed as cumulative CO
2-equivalent emissions and shown in
Figure 6a, captures the dominant contribution of N
2O reduction. Despite the modest increase in direct CO
2 under Option 1, both retrofit configurations deliver substantial reductions in total CO
2-equivalent output. Option 1 achieves a 41.8% reduction and Option 2 a 43.6% reduction in CO
2-equivalent emissions relative to the base case, with the base case total at 18,618 kg CO
2-eq/h, 10,837 kg/h for Option 1, and 10,504 kg/h for Option 2. Of the base-case total, N
2O contributes 11,505 kg/h, direct CO
2 6834 kg/h, and methane slip 279 kg/h; the methane contribution, small but not negligible, falls to 173 and 92 kg/h in the two options as the selective catalyst converts the fuel gas more completely.
Across the tail gas reactor, both retrofit options convert 97.2–97.3% of the incoming N
2O, comparable to the 98–99% reported for commercially deployed systems such as the EnviNOx
® process under optimal conditions [
14]. The stack-to-stack reduction of 68.0% is smaller because the base case already incorporates non-selective tertiary abatement, so the retrofit is measured against an abated, rather than an unabated, baseline. The gap between the values obtained in this study and the upper-bound literature values reflects the specific constraints of the retrofit scenario: the selective catalyst must operate within the thermal window imposed by the existing heater and the turbine inlet temperature requirement, which limits the achievable ignition temperature and therefore the depth of N
2O decomposition. Future plant designs conceived from the outset with tertiary abatement integrated into the heat recovery network could approach the higher removal efficiencies reported in dedicated installations. From a regulatory standpoint, the CO
2-equivalent reductions demonstrated here are directly relevant to the EU ETS, under which nitric acid producers are obligated to surrender allowances for N
2O emissions. The emission cost savings of 4.79 and 4.99 million EUR/year estimated for Options 1 and 2 (
Table 6) are consistent with the scale of the environmental improvements quantified in
Table 5, confirming the internal consistency of the environmental and economic analyses. The results confirm that selective catalytic tail gas treatment, even under the constraints of retrofitting an existing dual-pressure plant, is a technically effective and environmentally meaningful abatement measure. The choice between options should therefore be informed not only by economic payback criteria but also by the plant operator’s specific emission-reduction commitments and carbon-pricing exposure.
The stack concentrations may be placed in a regulatory context. Referenced to dry gas at standard conditions, the NO
x concentration expressed as NO
2 falls from 165 mg/nm
3 in the base case to 81 mg/nm
3 for Option 1 and 76 mg/nm
3 for Option 2. Expressed on the volumetric basis used by the source, and at the same reference state, these correspond to 80, 40 and 37 ppmv as NO
2, one ppmv as NO
2 being 2.053 mg/nm
3 at 0 °C and 101.325 kPa. Table 3.15 of the reference document on best available techniques for large volume inorganic chemicals, reproduced as Table IV of its executive summary, gives 5–90 ppmv as NO
2 for existing nitric acid plants, admitting 150 ppmv only where ammonium nitrate deposits restrict the effect of selective catalytic reduction or where hydrogen peroxide is used in its place [
11]. All three cases therefore lie within the range applicable to existing plants. The base case does so with little margin, at 80 ppmv against an upper bound of 90, whereas both retrofits operate at rather less than half that bound and so retain headroom against load variation, catalyst ageing and any future tightening of the limit. Compliance is therefore not in itself a driver for the retrofit, but the operating margin it confers is. The specific N
2O emission of 0.23 to 0.24 kg per tonne of HNO
3 achieved by the two options lies within the 0.12–0.25 kg/t range associated with well-performing tertiary abatement and approaches, without reaching, the level of 0.20 kg N
2O per tonne identified in mechanism methodology A6.4-AMM-002 as the performance of the best-performing abated plants, below which the annual increase in the downward adjustment of the baseline is set to 0.01 rather than to the standard value (paragraph 40(a)) (Mechanism methodology A6.4-AMM-002, N
2O abatement from nitric acid production, which entered into force on 21 May 2026 under the Article 6.4 mechanism of the Paris Agreement, superseding the proposal cited as reference [
39]) [
39]. Carbon monoxide, formed in the base case by partial oxidation of methane over the non-selective catalyst according to Equation (13), falls from 20.7 kg/h, that is 119 mg/nm
3, to 11.3 kg/h in Option 1, where combustion takes place with excess air in a dedicated chamber, and to 5.2 kg/h in Option 2, where oxidation proceeds over a precious-metal shelf. Unconverted methane follows the same ordering, falling from 11.2 kg/h to 6.9 and 3.7 kg/h.
Section 1.2 identifies both species as by-products of the existing system, and reducing them is a secondary benefit of both retrofits.
The oxygen balance of the tail gas deserves particular attention for Option 2, because the residual oxygen in the tail gas is the resource from which the internal temperature rise is produced. The absorber delivers tail gas containing 2.40 mol% oxygen, but very little survives to the stack in the base case: the non-selective reactor consumes it by burning natural gas to reach the turbine inlet temperature, and the simulated stack composition shows only 0.265 mol% remaining. Option 2 uses the same resource more sparingly and more selectively, leaving 0.488 mol% at the stack, roughly twice the base-case residue, because the catalytic oxidation shelf converts the fuel gas at lower temperature and with less excess. Option 1 shows a markedly different profile, 2.87 mol% at the stack, because its combustion chamber is supplied with its own pressurised air and the tail gas oxygen is no longer consumed to raise temperature. The narrowness of the base-case and Option 2 margins is the binding constraint on the internal-oxidation concept: the temperature rise that can be generated within the reactor is limited by the oxygen the absorber delivers, the existing fired heater must continue to preheat the tail gas to 529 °C, and Option 2 could not be transferred to a plant operating at appreciably lower absorber-top oxygen without a supplementary air supply, at which point it would converge on the equipment count of Option 1. Tail gas oxygen consumption is also why Option 2 provides no throughput gain, as set out in
Section 2.7.
4.4. Economic Performance
The economic evaluation of the two retrofit options is structured around four principal financial components: annualised capital expenditure, changes in utility operating costs, revenue effects from changes in plant yield, and savings generated by reduced CO
2-equivalent emissions.
Table 6 synthesises these components and provides the basis for comparing the overall commercial attractiveness of each option.
Figure 7,
Figure 8 and
Figure 9 present sensitivity analyses for CAPEX uncertainty, nitric acid market price, and energy price, respectively. The annualization of capital costs applies a 10% interest rate over a five-year project lifetime, consistent with Equations (31)–(33) and the economic assumptions defined in
Section 2.6. Payback periods are reported both as simple and as discounted periods, and both with and without the emission allowance saving, because the two framings lead to materially different conclusions for Option 1.
The CAPEX estimates reflect the different scope and complexity of the two retrofit configurations. Option 1, which requires a new combustion chamber, an additional air compressor, an ammonia evaporator, an ammonia filter, and an ammonia heater, carries an equipment cost of 4,771,557 EUR, to which the first charge of deN
2O/SCR catalyst adds 480,000 EUR, giving a total capital expenditure of 5,251,557 EUR, annualised to 1,385,348 EUR/year. Option 2 introduces only an additional catalyst shelf within the reactor vessel, together with the associated ammonia dosing equipment, resulting in an equipment cost of 1,340,663 EUR; its larger catalyst inventory, comprising the same 40 m
3 deN
2O/SCR charge together with a 12 m
3 oxidation shelf, adds 636,000 EUR, giving a total capital expenditure of 1,976,663 EUR annualised to 521,439 EUR/year. The capital cost ratio between the two options is approximately 2.7:1, a difference that decisively determines relative payback performance and reflects the inherent advantage of the thermally integrated, reactor-internal approach adopted in Option 2. Both estimates were derived using the base-cost correlations of [
27], with Chemical Engineering Plant Cost Index corrections [
28] and a Lang factor of 4 applied to account for installation, interconnecting piping, instrumentation, and civil works, in accordance with AACE International Recommended Practice No. 18R-97.
The utility consumption changes introduced by each option translate directly into operating cost changes, as summarised in
Table 4 and monetised in
Table 6. Option 1 incurs an additional utility cost of +4,794,569 EUR/year, driven by three simultaneous effects: (i) an increase in natural gas consumption from 3528 to 3763 STD m
3/h (+235 STD m
3/h), attributable to the combustion chamber fuel requirement; (ii) additional electricity demand of 3155 kW from the new air compressor; and (iii) the cost of ammonia supply (127 STD m
3/h) as SCR reductant. These are partially offset by eliminating the N
2/H
2 mixture (221 STD m
3/h) previously required for non-selective catalytic reduction, and by improved steam generation (from 64.1 to 70.0 t/h) combined with reduced steam consumption (from 41.4 to 29.0 t/h). In aggregate, however, the increased fuel and electricity demand outweighs the steam-side savings, producing a net utility cost penalty for Option 1. In contrast, Option 2 achieves a utility cost reduction of 1,750,090 EUR/year. The internal catalytic oxidation of fuel gas within the two-shelf reactor eliminates the need for a combustion chamber and the associated air compressor, reduces natural gas consumption to 3379 STD m
3/h (−149 STD m
3/h relative to the base case), and requires no additional electricity. Together with the elimination of the N
2/H
2 mixture cost, Option 2 delivers a strictly favourable operating cost outcome at the utility level.
The 5% increase in nitric acid production achieved by Option 1, enabled by more stable tail gas temperature control and improved process conditions, generates an additional revenue of +5,752,166 EUR/year, calculated at the European nitric acid market price of 270 EUR/t adopted in
Section 2.6 [
36]. This revenue contribution is the single largest positive cash flow item for Option 1 and is decisive in offsetting its utility cost penalty. Option 2, which does not significantly alter plant throughput, produces a negligible capacity-related revenue change of −112,347 EUR/year, reflecting minor process interactions rather than a structural throughput effect. The contrast between the two options on this dimension is fundamental: Option 1 is essentially a combined production-expansion and abatement investment, whereas Option 2 is a pure abatement measure with an improved energy cost profile.
Both retrofit options generate significant savings under the EU ETS, where N
2O and combustion CO
2 emissions are accounted for at the allowance price of 73.90 EUR/t CO
2-equivalent [
37]. The reduction in N
2O and CO
2 emissions quantified in
Section 4.3 translates into emission cost savings of 4,785,272 EUR/year for Option 1 and 4,989,961 EUR/year for Option 2; the figures are close because the abatement performances of 41.8% and 43.6% are also close. The distinction between the two payback framings is decisive for Option 1. Excluding allowance savings, its annual net benefit is 933,597 EUR/year against a capital expenditure of 5,251,557 EUR, giving a simple payback of 67.5 months and a discounted payback of 104 months, so that on operational and production-side economics alone the investment is not recovered within the five-year evaluation horizon adopted here. Including allowance savings raises the annual net benefit to 5,718,869 EUR/year and shortens the discounted payback to 12.1 months. Option 1 is therefore an investment whose viability depends on carbon pricing. Option 2 is recovered within the horizon on either basis, with a discounted payback of 16.8 months excluding allowance savings and 3.8 months including them.
Table 6 clearly differentiates the two options. Option 2 presents the stronger financial case by every metric: lower capital expenditure (1,976,663 against 5,251,557 EUR), reduced utility operating costs (a saving of 1,750,090 EUR/year against a penalty of 4,794,569 EUR/year), and marginally higher emission cost savings (4,989,961 against 4,785,272 EUR/year), yielding a discounted payback period of 3.8 months, an exceptionally short horizon for an industrial retrofit investment. Option 1, despite its higher capital and operating costs, is viable because the 5% capacity increase (5,752,166 EUR/year) provides revenue that no other mechanism in Option 2 can replicate. The discounted payback period for Option 1 of 12.1 months remains commercially attractive for operators whose primary objective is throughput expansion and who are exposed to carbon pricing, but operators outside an emissions trading scheme should bear in mind that figure depends on allowance savings.
The robustness of the payback conclusions was assessed across three dimensions.
Figure 7 presents the sensitivity of payback period to CAPEX variation for each option. Since CAPEX estimates at the AACE Class 4–5 level can vary by a factor up to four, this sensitivity is particularly relevant. For Option 2, the discounted payback period rises from 3.8 to 16.1 months as capital expenditure is multiplied by four, remaining well within the project lifetime across the range and confirming its resilience to cost estimation uncertainty. For Option 1, the discounted payback rises from 12.1 to 57.6 months over the same range, remaining just within the five-year lifetime and crossing it at a multiplier of approximately 4.1, so that only a capital cost overrun at the extreme of the AACE band would render it unviable.
Figure 8 shows how economic performance depends on the nitric acid market price. Option 1 is more exposed to price volatility because its positive net cash flow depends on revenue from the additional 5% production capacity. Over the range from 150 to 400 EUR/t, the discounted payback of Option 1 varies from 22.9 to 8.0 months, whereas Option 2 remains at 3.8 to 3.9 months throughout, insulated from product price risk by its operating cost savings structure.
Figure 9 illustrates the impact of energy price variation. Given that Option 1 carries a net increase in natural gas and electricity costs, it is adversely affected by energy price increases. Doubling natural gas and electricity prices lengthens Option 1’s discounted payback from 12.1 months to beyond the project lifetime, with no recovery within the horizon, at approximately 1.73 times present energy prices. Option 2, conversely, benefits from higher energy prices, its discounted payback falling from 3.8 to 3.6 months as prices double, because its utility cost savings are proportionately amplified.
The economic analysis confirms that both retrofit options offer commercially viable pathways for tail gas treatment upgrade in dual-pressure nitric acid plants. Option 2 is the superior choice from a purely financial standpoint, offering minimal capital outlay, reduced operating costs, and a near-immediate payback, making it immediately attractive to investors and plant owners seeking rapid returns. Option 1 is appropriate when capacity expansion is the strategic priority, with its higher CAPEX and utility costs justified by substantial incremental revenue from increased production. Under current EU carbon pricing, emission-cost savings reinforce the financial case for both options and are indispensable to Option 1; carbon prices above the 73.90 EUR/t CO2-eq baseline assumed here would further improve the economics of both configurations, and prices materially below it would place Option 1 outside the five-year horizon.
One qualification applies to Option 1 alone and is decisive for the comparison. Its benefit stream depends on the capacity revenue of 5,752,166 EUR/y, which in turn depends on the 5% throughput increment specified in
Section 2.7 computed by the model. Withdrawing that revenue leaves an annual net benefit of −4,818,569 EUR/y excluding allowance savings and −33,297 EUR/y including them, so Option 1 would not recover its investment at all if the increment were not realised. The economics of Option 1 are therefore conditional on a debottlenecking study that this work does not provide, whereas those of Option 2 rest on utility savings at unchanged throughput and carry no equivalent condition. The simulated increase in plant yield represented the debottlenecking increment against which the retrofit could be costed, and the ammonia and air feeds were scaled by the same proportion so that the burner ratio, the absorber oxygen profile, and the acid strength remain at their validated values. The simulation then returns the corresponding heat, power and emission flows. It follows that the model demonstrates 5% is simulated increment under model constraints and additional investigation is needed on real process debottlenecking under increased capacity.
4.5. Global Impact on the Fertiliser Industry
Nitric acid is the essential intermediate in nitrogen-based fertiliser production, with global output reaching approximately 60 million tonnes per year in 2023 across roughly 500 production plants worldwide [
40]. Around 80% of this volume feeds the manufacture of ammonium nitrate, a critical nitrogen source for agricultural productivity (The downstream ammonium nitrate share is taken from the same source as the production and plant count figures, reference [
40]). The fertiliser industry as a whole is responsible for approximately 1.4% of annual global CO
2-equivalent emissions [
41]. Within this, nitric acid manufacturing is the dominant point source of industrial N
2O, with total sectoral N
2O emissions estimated at 36.1 Mt CO
2-equivalent in 2020 (The sectoral N
2O inventory of 36.1 Mt CO
2-equivalent for 2020 and the unabated share of 63% are both taken from reference [
42]). Crucially, an estimated 63% of this total, some 22.5 Mt CO
2-equivalent [
42], originates from plants operating without effective tertiary abatement and therefore constitutes a readily addressable mitigation potential.
The present study demonstrates that selective catalytic tail gas treatment applied to an existing dual-pressure nitric acid plant reduces the plant-level N
2O emission factor from 0.75 to approximately 0.24 kg N
2O per tonne of HNO
3 produced; a reduction of 66–68% depending on the retrofit configuration. Extending this performance to the global fleet of unabated plants requires contextualisation with IPCC-referenced emission factors. Medium-pressure dual-pressure plants without tertiary abatement typically operate with emission factors of 5–7 kg N
2O per tonne HNO
3 [
43]. The retrofit performance demonstrated here cannot be transferred to the unabated fleet as a percentage reduction, because the plant studied already incorporates non-selective tertiary abatement, so its base-case stack emission factor of 0.74 kg N
2O/t is far below the unabated range, even though its burner outlet at 8.37 kg N
2O/t is squarely within it. The transferable quantity is instead the absolute residual emission factor achieved after retrofit, 0.24 kg N
2O/t, set by the catalyst system and reactor conditions rather than by the inlet loading. On that basis, the extrapolation is anchored to the addressable potential itself. An unabated inventory of 22.5 Mt CO
2-eq/y at a representative emission factor of 6 kg N
2O/t implies about 12.6 Mt/y of nitric acid produced without tertiary abatement, roughly 21% of global output. Retrofitting that entire capacity to the residual factor demonstrated here would avoid 72.5 kt N
2O/y, equivalent to 21.6 Mt CO
2-eq/y, or about 96% of the addressable potential, the residual 4% being the irreducible emission at 0.24 kg/t. At the more realistic adoption rate of 30%, the saving is 21.8 kt N
2O/y, or 6.5 Mt CO
2-eq/y, worth approximately 479 million EUR per year at the allowance price of 73.90 EUR/t adopted in
Section 2.6; at 10% adoption it is 2.2 Mt CO
2-eq/y and about 160 million EUR per year. These figures rest on literature emission factors for the unabated fleet and on the assumption that the residual factor achieved in this retrofit is reproducible on plants of different pressure configuration, neither of which is demonstrated here; they are therefore indicative rather than predictive. These estimates are consistent with the order of magnitude of recently reported commercial deployments: the Clariant EnviCat
® N
2O-S catalyst alone is reported to reduce emissions by 690 kt CO
2-equivalent per year at a single large-scale nitric acid complex in China [
7], and by a further 275 kt CO
2-equivalent per year at a second facility [
8], underscoring the material scale of per-plant impact from modern tertiary abatement systems.
The long-term transformation of the fertiliser industry extends beyond incremental abatement of existing plants to structural decarbonisation of the upstream ammonia supply chain. Green ammonia, produced via electrolysis of water using renewable electricity to generate hydrogen, followed by the Haber–Bosch synthesis, currently commands a production cost of USD 700–1400 per tonne, compared to approximately USD 300–450 per tonne for conventionally produced grey ammonia [
44]. However, this premium is projected to narrow substantially: IRENA and IEA modelling indicates that with renewable electricity costs below USD 20 per MWh, green ammonia becomes cost-competitive with grey ammonia without carbon pricing, with production costs expected to converge toward USD 310–480 per tonne by 2030–2050. The IEA Sustainable Development Scenario projects that direct CO
2 emissions from the ammonia industry can be reduced by over 70% by 2050 relative to today, while a Net Zero Emissions trajectory requires a 95% reduction. Near-zero emission production capacity of approximately 8 Mt per year is scheduled to come online by 2030 [
45]. These trajectories are significant for nitric acid and fertiliser producers in two ways. First, decarbonised ammonia feedstock would substantially reduce the upstream Scope 1 and Scope 2 footprint of nitric acid synthesis, complementing the tail gas abatement measures examined in the present study. Second, ammonia is gaining traction as an e-fuel and hydrogen energy carrier, with the International Maritime Organisation projecting that ammonia could supply approximately 25% of the global shipping fuel mix by 2050 [
46]. This dual role, as fertiliser precursor and as carbon-free fuel, is expected to drive global ammonia demand to 350 million tonnes per year by 2050, up from approximately 185 million tonnes today [
45]. Nitric acid plants operating with green ammonia feedstock and equipped with selective catalytic tail gas treatment would approach near-zero lifecycle N
2O and CO
2 emission profiles, consistent with the decarbonisation requirements of the EU’s Farm to Fork Strategy and the broader Fit for 55 regulatory frameworks.
4.6. Limitations
The process model was developed exclusively in steady-state mode. It did not capture transient phenomena inherent to industrial operation, including plant start-up, scheduled and unscheduled shutdowns, load-following behaviour, and control system response. In practice, N2O and NOx emission rates are sensitive to transient conditions, particularly during catalyst warm-up and ammonia burner campaigns; peak emissions during these periods may deviate substantially from the nominal values reported here. Dynamic modelling would be required to quantify these effects and to validate the stability of the proposed retrofit configurations under real operational variability.
The catalytic reduction of N2O and NOx in the tail gas treatment reactor was modelled using fixed conversion fractions derived from literature data and validated plant measurements, rather than from detailed reaction kinetics. This approach captures steady-state performance at the design operating point but cannot represent how conversion efficiency depends on inlet concentration fluctuations, temperature gradients across the catalyst bed, or the spatial distribution of reactants. Furthermore, this study did not consider catalyst deactivation, poisoning, or ageing. Industrial iron-zeolite and vanadium-titania catalysts experience progressive activity loss over service lifetimes of several years, and the economic case for retrofit is sensitive to catalyst replacement frequency and cost factors not reflected in the current model.
We neglected heat losses from process equipment and interconnecting pipelines by assuming perfect insulation throughout. Pressure drops in connecting piping were not considered. While these simplifications are standard in steady-state comparative assessments and are unlikely to alter the relative ranking of options, they bias the energy recovery estimates. The bias is conservative rather than optimistic: the model overpredicts the stack temperature by 22 K, so it recovers less heat in the recuperative tail gas heater than the plant achieves in practice. As shown in
Section 4.1, the bias is common to the base case and both options and cancels in all differential results; its bounding differential effect is 2.0% of the annual net benefit of Option 1 and negligible for Option 2. Absolute values of stack temperature and recovered heat should nevertheless be treated with caution.
Capital cost estimates were generated using the equipment-scaling correlations of Smith, Timmerhaus, and West [
27] with a Lang factor of 4, consistent with AACE Class 4–5 accuracy (expected accuracy: −30% to +50%). Actual project costs for revamping existing plants may deviate significantly from these estimates because site-specific constraints, structural modifications, and installation complexity are not captured by the correlations. The economic analysis used single-point values for energy prices, carbon prices, and the nitric acid market price, all of which are volatile. Sensitivity analyses presented in
Figure 7,
Figure 8 and
Figure 9 partially address this, but do not account for correlated price scenarios or long-term structural shifts in the EU ETS.
The study investigates one specific dual-pressure plant configuration under nominal full-load conditions. The results’ generalisability to plants with different capacities, pressure configurations, or geographic and regulatory contexts is limited. The global impact extrapolations presented in
Section 4.5 rely on literature-derived industry-average emission factors and should be regarded as indicative rather than predictive. Validation of the retrofit options on additional plant configurations and under part-load conditions would strengthen the basis for broader recommendations.
A detailed debottlenecking study for both retrofit configurations, at the resolution of the process units, together with a hydraulic check of the absorption section and a capacity review of the nitrous gas compressor and the acid coolers, is the necessary next step before the throughput increment can be finally verified.
The validation rests on a single nominal operating point, without repeated campaigns at different loads and without formally propagating measurement uncertainty into the simulated quantities. The agreement reported in
Table 3 therefore demonstrates that the model reproduces the plant at design conditions but does not establish its accuracy across the operating envelope. In addition, the catalyst conversions imposed in the tail gas reactor are fixed inputs taken from supplier data and from the regressed base case rather than outcomes of a kinetic model, so the emission results inherit the uncertainty of those inputs directly; a variation of one percentage point in the assumed N
2O conversion changes the CO
2-equivalent reduction of either option by approximately seven percentage points. The assumption of equal catalyst life across the three configurations is a further simplification: were the selective catalyst to require replacement every three years rather than five, the annual catalyst provision would rise by about 56,000 EUR/y for Option 1 and 82,000 EUR/y for Option 2, lengthening the discounted payback periods including allowances to 13.2 and 3.9 months respectively, which does not alter the ranking of the options.
4.7. Future Works
This work evaluates tail gas treatment options within the plant’s existing thermal infrastructure, treating the heat exchanger network as fixed. A combined approach that simultaneously redesigns the heat recovery system and the tail gas treatment configuration using pinch analysis or mathematical programming would likely reveal additional energy savings not captured here. Prior work on heat integration in nitric acid plants has identified utility savings of up to 14% through network retrofit alone [
22]. Synergistic optimisation with selective catalytic abatement could amplify this potential, particularly for Option 1, in which the combustion chamber introduces a significant high-temperature heat source that could be further exploited.
Option 1 increases steam generation from 64.1 to 70.0 t/h while reducing steam consumption to 29.0 t/h, creating a substantial exportable steam surplus that the current study did not fully optimise. A detailed investigation of steam turbine performance, including off-design efficiency curves, back-pressure regulation, and the potential for additional power generation, could enhance the energy and economic case for Option 1. This is particularly relevant at sites with high electricity prices or where cogeneration incentives apply.
Nitric acid plants typically operate as part of integrated fertiliser complexes producing ammonium nitrate or other downstream products. The utility streams identified in this study, including surplus steam, hot tail gas, and recoverable heat from the combustion chamber, could serve as inputs to adjacent process units such as ammonium nitrate evaporators or granulation systems. Site-level integration could improve overall energy efficiency and reduce total utility consumption beyond what is achievable within the nitric acid unit boundary alone.
As noted in
Section 4.6, the steady-state model does not capture transient behaviour during start-up, shutdown, load variation, or catalyst ageing. A dynamic simulation model would enable the investigation of control strategies for maintaining stable catalyst ignition temperature under variable load, the quantification of peak emission events during transient periods, and the identification of operational bottlenecks that limit performance under off-design conditions. This is of direct industrial relevance given that regulatory emission limits apply continuously, not only at nominal load.
Progressively substituting conventional grey ammonia with green ammonia, produced via electrolysis-based hydrogen and renewable electricity, would substantially reduce the upstream carbon intensity of nitric acid synthesis. Combined with the tail gas treatment measures demonstrated in this study, a green ammonia feedstock pathway offers a route to near-zero lifecycle N
2O and CO
2 emissions. A techno-economic assessment of this integrated pathway, including sensitivity to renewable electricity cost and carbon pricing, would provide the quantitative basis needed to support investment decisions aligned with sustainable development goals [
47]. Policy instruments such as the EU’s Farm to Fork Strategy and climate-smart agriculture programmes increasingly incentivise such transitions, but region-specific economic analysis and reliable emissions data remain prerequisites for widespread adoption.