Next Article in Journal
Exploratory Analysis of Young Drivers’ Speed and Vehicle Lateral Positioning on Simulated Rural and Highway Roads
Previous Article in Journal
Structural and Rheological Principles of Formation of Stable Bituminous Sealants with Polymer-Fiber Reinforcement
Previous Article in Special Issue
Reframing BIM: Toward Epistemic Resilience in Existing-Building Representation
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

RACI–AHP–BIM Methodology in Projects with High Functional Complexity and Conservation Constraints

by
Urszula Kwast-Kotlarek
1 and
Mariusz Szóstak
2,*
1
Central Administration Unit, Department of Investments and Renovations, University of Wroclaw, plac Uniwersytecki 1, 50-137 Wroclaw, Poland
2
Department of Building Engineering, Faculty of Civil Engineering, Wroclaw University of Science and Technology, Wybrzeże Stanisława Wyspiańskiego 27, 50-370 Wroclaw, Poland
*
Author to whom correspondence should be addressed.
Infrastructures 2026, 11(3), 105; https://doi.org/10.3390/infrastructures11030105
Submission received: 21 February 2026 / Revised: 16 March 2026 / Accepted: 17 March 2026 / Published: 19 March 2026
(This article belongs to the Special Issue Modern Digital Technologies for the Built Environment of the Future)

Abstract

The article presents an integrated RACI–AHP–BIM methodology that supports responsibility management, decision-making, and information management in complex construction projects delivered under the design–build model, with particular emphasis on conservation-orientated investments. The approach combines three complementary components: the RACI responsibility matrix, the analytic hierarchy process (AHP), and building information modeling (BIM). The methodology is validated on a higher-education conservation project using a BIM execution plan (BEP), scan-to-BIM procedures, and structured decision-making. The integration of RACI with BIM reduced accountability gaps and improved stakeholder coordination, while linking AHP with BIM data enabled data-driven design decisions using the BOCR model. The findings demonstrate measurable benefits, including clearer responsibility allocation, improved interdisciplinary coordination, and more transparent decision-making. The application of laser scanning and scan-to-BIM supported the creation of a digital model of historic elements for both design and future facility management. The main contribution is a holistic integration of RACI, AHP, and BIM into a unified methodology for conservation-orientated projects with high functional complexity, providing a reference framework for public-sector investment management.

1. Introduction

1.1. Context and Problem Statement

Digital transformation in public construction projects requires the combined use of advanced management methods and information technologies to support decision-making [1,2]. Contemporary investment projects are carried out in environments that involve not only core project participants (client, designer, site manager, supervising inspector) but also a wide range of additional stakeholders [3,4]. In such settings, a clear allocation of responsibilities, the transparency of decision-making processes, and the efficient flow and integration of project information are critical.
Conservation projects in historic buildings require a simultaneous consideration of technical, functional, economic, and cultural constraints and involve a broader group of stakeholders, including heritage authorities [5,6]. This complexity necessitates the use of tools enabling the integration of responsibility management, decision-making processes, and the project information environment.
Building information model/modeling/management (BIM) has become a key component of the construction project delivery, supporting multidisciplinary coordination and data management [7,8]. However, BIM alone does not provide built-in mechanisms for responsibility management or structured decision-making, which are still handled through dispersed organizational and analytical tools [9,10].
In parallel, project management practice employs responsibility assignment tools such as the RACI matrix (Responsible, Accountable, Consulted, Informed), which structure relationships among project participants and increase organizational transparency [11]. Multi-criteria decision-support methods, particularly the analytic hierarchy process (AHP), are used to evaluate design alternatives and prioritize investment actions [12]. However, these tools typically operate independently of the BIM environment and formal information management structures [13].
The lack of integration between responsibility allocation (RACI), multi-criteria decision-making mechanisms (AHP), and the BIM information environment leads to fragmentation of the decision-making process [14]. This issue is particularly significant in conservation-orientated projects, where design and construction decisions have long-term technical and cultural consequences and require strict coordination among multiple stakeholders.
Previous studies on construction project management models have focused mainly on individual aspects: the RACI matrix has been analyzed in organizational management contexts, AHP has been applied to the selection of alternative construction investment, and BIM, according to ISO 19650 [15], has been implemented primarily as an information management system. The literature still lacks a holistic approach that integrates these three methodologies into a single coherent decision-support model, particularly in relation to projects implemented in heritage-protected buildings [16].

1.2. Aim and Scope of the Article

The purpose of this article is to develop an RACI–AHP–BIM model that integrates responsibility management, multi-criteria decision-making, and the BIM environment into a coherent methodology for conservation-orientated construction projects. The methodology was designed as a tool that supports the allocation of responsibility, the structuring of variant selection processes, and the integration of decisions with the digital information environment of the project.
The scope of the study includes the following:
  • development of a conceptual model integrating RACI, AHP, and BIM into a unified project management framework;
  • analysis of the structure of project roles and assigned responsibilities within the investment delivery process;
  • identification of information requirements and risk mitigation mechanisms through the implementation of a BIM execution plan (BEP) according to ISO 19650;
  • verification of the proposed approach based on a real case study of a design–build project implemented in a heritage-protected facility.
The reconstruction of the greenhouse complex at the Botanical Garden of the University of Wrocław serves as a validation case, illustrating the application of the proposed model in a project that combines conservation, functional, and technological requirements.
The reconstruction of the greenhouse complex at the Botanical Garden of the University of Wrocław, located on Sienkiewicza Street 23, represents a unique challenge that combines conservation requirements with modern project management methods. The facility was entered in the heritage register under No. A-2374/209/4 (5 February 1974) and is located in the Grunwaldzki Square area in Wrocław. The former greenhouse complex (Palm House–Victoria–Australia), established in the nineteenth century, deteriorated technically and was dismantled in 2013 by administrative decision due to its poor structural condition and lack of funding for conservation.
Only selected elements were preserved: fragments of the steel structure of the Australia greenhouse, including wrought-iron columns and parts of the steel roof skylight structure, as well as the stone basin of the Victoria greenhouse with four corner basins and masonry walls finished with stone copings. The reconstruction implemented in the design–build procurement model required the application of an integrated methodological approach that combined:
  • the RACI matrix—to ensure clear allocation of responsibilities among four key stakeholders: the Client, the Contractor, the Designer, and the Users;
  • the analytic hierarchy process (AHP) method—for multi-criteria evaluation of implementation alternatives considering conservation requirements, functional needs (culturing of tropical plants), and economic and organizational factors;
  • Building information model/modeling/management (BIM) methodology according to ISO 19650—for effective project information management, multidisciplinary coordination, and integration with preserved historic structural elements retained in situ.

2. State of the Art

2.1. RACI Matrix in Construction Project Management

The RACI matrix (Responsible, Accountable, Consulted, Informed) is a fundamental tool for assigning responsibilities in construction projects, including those implemented in BIM environments characterized by complex stakeholder structures [17,18]. Its implementation in BIM projects enables the reduction in accountability gaps by 32% compared with traditional project management methods, increases communication transparency, and helps avoid redundant task assignments [19]. In the context of design–build projects, the RACI matrix gains particular importance due to the integrated responsibility of the contractor for both design and construction, which requires the precise definition of roles across project phases [20].
In conservation projects, the RACI matrix must incorporate additional stakeholders, such as the heritage conservation authority, acting as the key decision-maker (Accountable) regarding interventions in historic fabric, and specialist users (Consulted), e.g., botanists and collection curators in the case of a botanical garden, serving as consultants on functional requirements related to plant cultivation [21]. In academic projects, it is also necessary to take into account the multi-level administrative structure of universities, where investment decisions require approval at multiple administrative levels [22].
The RACI matrix constitutes a structured framework that assigns four levels of involvement for a combination of tasks and roles [23]. A project-specific RACI matrix enables:
  • elimination of accountability gaps;
  • avoidance of task redundancy (multiple or overlapping assignments);
  • communication transparency within multifunctional teams.
In multidisciplinary BIM projects, the RACI matrix integrates traditional roles (designer, contractor, client) with specialized roles (BIM Manager, BIM Coordinator, Data Exchange Process Manager), ensuring the consistency of decision-making and coordination processes.

2.2. Analytic Hierarchy Process (AHP) in Investment Decision-Making

The analytic hierarchy process (AHP) structures complex decisions as hierarchies of objectives, criteria, and alternatives and supports the multi-criteria evaluation of design and technological options in construction projects [24]. In the conceptual stage, it helps align client requirements with technical feasibility and reduce interdisciplinary conflicts through explicit criteria and priorities [25].
Research, including [22], has demonstrated the effectiveness of AHP in evaluating linear infrastructure investments in environmentally protected areas, confirming the usefulness of the method in projects requiring multi-criteria analyses of alternatives and consideration of environmental, technical, and economic factors.
The application of AHP in conservation projects requires the inclusion of criteria specific to historic buildings, such as the degree of preservation of historic fabric and architectural form [26], reversibility of conservation interventions [27], authenticity of applied materials and technologies [28], and potential for future conservation research [29].
In Polish investment practice, the BOCR model (Benefits, Opportunities, Costs, Risks) constitutes an extension of the classical AHP structure, allowing for a complete evaluation of investment alternatives considering both positive factors (benefits, opportunities) and negative factors (costs, risks) within a single analytical framework [17,19,30,31].

2.3. Building Information Model/Modeling/Management (BIM)

The BIM methodology, implemented according to the ISO 19650 standard, integrates digital modeling of the built asset with information management processes at all stages of the project lifecycle (concept, design, construction, operation) [32,33,34]. The ISO 19650 standard defines organizational frameworks, including organizational information requirements (OIR) [35], project information requirements (PIR) [36], asset information requirements (AIR) [37], and employer’s information requirements (EIR) [38].
Employer’s information requirements (EIR), particularly those orientated toward facility management (FM), are of particular importance. In specialized projects such as greenhouses for tropical plant cultivation, the BIM methodology enables precise management of microclimate parameters, irrigation systems, lighting that support photosynthesis, and maintenance schedules for technical equipment [26,27]. In conservation projects, BIM also integrates data on heritage values and the condition of historical fabric [39,40,41].
In the context of conservation projects, the application of BIM requires, among others, the integration of point clouds obtained from 3D scanning preserved historic elements with the design model [39]; parameterization of historic elements considering their condition, material, manufacturing technique, and conservation interventions [40]; definition of the levels of detail (LOD) appropriate to the level of knowledge about historic fabric [41], and management of heritage-value information within the IFC data structure [42].
In the Polish public sector, particularly in public procurement aligned with the PL BIM Standard (2020) [26], the BIM methodology includes elements such as multidisciplinary geometric modeling in IFC 4.0 [27], CDE (Common Data Environment) platforms for data exchange [38], clash detection procedures, and information quality control mechanisms.
The BIM execution plan (BEP) is a contractor’s implementation document in response to the employer’s information requirements (EIR), defining the strategy and procedures to achieve the BIM objectives within the project [43]. According to ISO 19650:2018 [15], BEP should include the following: the definition of BIM objectives and their impact on schedule and budget, modeling standards, rules for working within the CDE, quality control mechanisms, roles and responsibility matrices (RACI), data exchange procedures between stakeholders, as well as legal aspects, data security, training, etc.
When properly developed, the BEP constitutes a key document, as it defines the CDE platform for data exchange, data exchange formats (native and IFC), the levels of detail LOD/LOIN for individual project phases [30], interdisciplinary coordination and clash detection procedures, and the BIM team structure together with the responsibility matrix.

2.4. Scan-to-BIM and Historic Building Information Modeling (HBIM) in Architectural Heritage Conservation

Scan-to-BIM and Historic BIM (HBIM) enable the precise digitalization of existing historic buildings [44].
Scan-to-BIM converts terrestrial laser scanning (TLS) and photogrammetric data into parametric BIM models, providing precise digital representations of existing assets. In conservation projects, it supports the accurate documentation of historic fabric through scanning, point cloud registration, parametric modeling, and preparation of as-built documentation [45].
Historic BIM (historic building information modeling) extends BIM to historic buildings by modeling characteristic architectural elements, allowing adaptations to measured dimensions and geometric irregularities, integrating historical data with 3D models, and supporting the planning of conservation intervention [46]. HBIM enables not only the representation of geometry and materials but also the preservation of information about heritage values, previous interventions, and historical phasing, thus supporting conservation planning [47].
The benefits of scan-to-BIM/HBIM include high accuracy, non-invasive data acquisition, rapid data collection, and access to hard-to-reach areas, while limitations are associated with equipment costs, the need for specialized expertise, and large data file size [48].

2.5. Research Gap and Scientific Contribution of the Article

The literature review indicates that previous studies have focused primarily on:
  • the application of the RACI matrix in BIM projects for newly designed buildings, overlooking the specificity of conservation projects requiring inclusion of additional stakeholders (heritage conservation authorities, specialist users);
  • the use of AHP in design–build projects without incorporating the BOCR model, which enables comprehensive evaluation of benefits, opportunities, costs, and risks within a single hierarchical structure;
  • the implementation of BIM and BEP in conservation projects to a limited extent, the aspect of which requires the development of specific information requirements (EIR) that incorporate the management of heritage-value information, which remains an unexplored research area.
Therefore, it should be stated that there is a lack of studies that integrate the three proposed methodologies (RACI, AHP, BIM) into a comprehensive model for the implementation of construction projects that combine conservation, functional, and technological requirements. This article fills the identified research gap through the following:
  • development of a RACI matrix for 21 processes in the construction, commissioning, and operation phases, taking into account the specificity of a design–build project implemented in a conservation-protected facility;
  • application of the AHP–BOCR model for the multi-criteria evaluation of implementation alternatives, including conservation, functional, economic, and organizational criteria;
  • development of the employer’s information requirements (EIR) and a BIM execution plan (BEP) according to ISO 19650 for a conservation project, integrating point clouds with the design model;
  • validation of the proposed model based on a real case study involving the reconstruction of a historic greenhouse complex in the Wroclaw Botanical Garden.
The proposed RACI–AHP–BIM model constitutes an innovative tool that supports decision-making and information management in conservation projects, with potential for adaptation to other complex projects characterized by a high degree of functional and organizational complexity.

3. Research Methodology: RACI-AHP-BIM Methodology

3.1. Assumptions of the RACI-AHP-BIM Methodology

The proposed RACI–AHP–BIM methodology was developed as an integrated model to manage projects characterized by a high level of complexity, particularly conservation projects implemented in the design–build delivery model. Its fundamental premise is the integration of three complementary dimensions of project management (methodological domains):
  • a management system represented by the RACI matrix;
  • a decision-making process based on the AHP method;
  • information management implemented within the BIM environment according to ISO 19650.
The developed methodology was intentionally designed as a methodological framework prior to project implementation and was not the result of ex post analysis. The case study serves a validation function, providing evidence of the applicability of the model in project practice.
The integration of the methods is systemic in nature: the RACI matrix structures process responsibilities, the AHP method supports the selection of alternatives and prioritization of actions, while the BIM methodology provides an information environment enabling the operationalization of decisions and monitoring of project implementation.
The RACI–AHP–BIM methodology is based on a three-layer functional structure comprising the organizational, decision-making, and informational layers.
  • Organizational layer (RACI matrix): Within the organizational layer, project roles are identified, responsibilities are assigned, and decision-making relationships among participants in the investment process are defined. The RACI matrix performs the function of the project’s management and decision-making structure and forms the basis for mapping project processes.
  • Decision-making layer (AHP–BOCR method): In this layer, the processes for selecting design, technological, and organizational alternatives are modeled using the AHP structure in the BOCR framework, enabling a balanced evaluation of alternatives in the context of conservation, functional, technological, and economic requirements.
  • Informational layer (BIM–ISO 19650): BIM constitutes an environment that integrates project data, geometric models, information requirements, and management documentation. The BIM execution plan (BEP), the employer’s information requirements (EIR), and the CDE ensure the flow of information among project participants and data quality control. The interconnection of these three layers is iterative and interdependent.
The responsibility structure defined in the RACI matrix influences the generation and approval of project information within BIM; decisions made using AHP modify information requirements and the scope of project analyses; and data generated within the BIM environment provide a basis for updating both responsibility assignments and decision-making priorities. As a result, the methodology operates as a project management system based on continuous information flow between the organizational structure, the decision-making process, and the digital environment.

3.2. Research Steps

The study consisted of four steps.
  • Step I—Identification of processes and roles (RACI matrix), including:
  • analysis of source documents, including EIR, BEP, and design documentation (architectural and construction design, technical design, site development design);
  • identification of project processes across the phases of construction, commissioning, and operation;
  • definition of the stakeholder structure and assignment of R/A/C/I responsibilities;
  • mapping of BIM processes onto the responsibility structure.
  • Step II—Development of the decision problem structure (AHP/BOCR method):
  • decomposition of project problems into a hierarchical structure;
  • identification of criteria and sub-criteria within the BOCR model;
  • pairwise comparisons according to the Saaty scale (1–9);
  • determining priority weights for implementation alternatives.
  • Step III—Integration with the BIM methodology:
  • analysis of information requirements (EIR) and the BIM execution plan (BEP);
  • identification of key data delivery points (PDD);
  • analysis of levels of detail (LOD/LOIN);
  • integration of design models and scanning data.
  • Step IV—Risk analysis:
  • identification of categories of project risks;
  • mapping of risks into RACI processes and BIM information requirements (EIR);
  • use of AHP results to prioritize mitigation actions.

3.3. Research Object

The study adopted a case study approach using the triangulation of data sources. The analysis included project documentation, EIR and BEP documentation, the development of a RACI matrix covering 21 processes and 80 responsibility assignments, the construction of an AHP–BOCR decision model, and the performance of risk and BIM process analyses. This approach enabled a simultaneous capture of the organizational, decision-making, and informational aspects of the project and evaluation of their interdependencies.
The case study concerns the reconstruction project of the Palmiarnia–Wiktoria–Australia greenhouse complex in the Botanical Garden of the University of Wrocław, implemented under conditions of complex conservation, environmental, and technological constraints. The Botanical Garden area was entered into the register of historic monuments under no. A-2374/209/4 dated 5 February 1974 and is located within a conservation protection zone and an archeological heritage protection zone, according to Local Development Plan No. 362 (Resolution No. XXXVII/855/13 of the Wrocław City Council of 17 January 2013).
The 19th-century greenhouse complex consisted of four parts: the Palm House, Australia, Wiktoria, and a connector. Due to poor technical conditions and a lack of funding, it was solved in 2013. The preserved elements included wrought-iron columns and roof fragments of the Australia section, the stone basin of the Wiktoria section, and the concrete slab over the underground heating node.
In the implemented project, conservation requirements include the following:
  • preservation of historic wrought-iron columns of the Australia section as decorative elements;
  • preservation of stone cappings of the Wiktoria walls and their conservation prior to reinstallation;
  • reconstruction of the historic architectural form: Palm House (cascading roof), Australia (triple-pitch skylights), Wiktoria (central pool basin);
  • visual differentiation of historic elements from the new structural components;
  • conducting rescue archeological investigations.
Environmental protection requirements include the following:
  • protection of two natural monuments: ginkgo trees;
  • protection of valuable species: Atlas cedar and American beech.
The project specificity includes the necessity to:
  • preserve and incorporate historic wrought-iron columns as decorative elements into the new steel structure;
  • reconstruct the historic architectural form of three greenhouses (Palm House—single-pitch cascading roof, Australia—triple-pitch roof skylights, Wiktoria—central pool with aquatic vegetation),
  • meet technical requirements for tropical plant cultivation (minimum temperature 23 °C, humidity 70–80%, double-glazed Optiwhite glazing with Ug = 0.6 W/m2K);
  • ensure compliance with the requirements of the Voivodeship Heritage Conservation Officer and the Department of Environment (protection of two natural monuments—ginkgo trees no. 16A and 16B, and protection of old-growth trees—Atlas cedar and American beech);
  • implement the project within an operating Botanical Garden.
The complexity of these conditions makes the project an appropriate environment for verifying the integrated RACI–AHP–BIM approach.
The study has typical limitations for a single case. It focuses on one facility at the executive design stage, so data from construction and operation were not available. Access to detailed financial data was limited, and AHP assessments relied on expert judgment, introducing subjectivity. Despite these limitations, the study provides an empirical basis for evaluating the functioning of the proposed methodology and its potential adaptation in other complex construction and conservation projects.

4. Research Results

4.1. Structure of the Project Team–RACI Matrix

As a result of applying the RACI matrix, 80 responsibility assignments related to 21 project processes were identified. Table 1 presents the developed RACI matrix. The following roles and types of responsibility were identified:
  • Responsible (R): 23 assignments;
  • Accountable (A): 18 assignments;
  • Consulted (C): 22 assignments;
  • Informed (I): 17 assignments.
Total number of assignments of responsibility: 80.
Table 1. RACI Matrix—Project Roles and Responsibility Assignments.
Table 1. RACI Matrix—Project Roles and Responsibility Assignments.
No.Process/TaskInvestor (UWr)ContractorDesignerEnd User (BG)
Implementation phase (7 processes)
1Definition of functional requirements of the facilityACCR
2Development of the architectural conceptCARC
3Preparation of multidisciplinary design documentationIARC
4Analysis of technical alternatives (AHP method)ARRC
5Obtaining conservation approval (Heritage Officer)ACRI
6Preparation of the BIM Execution Plan (BEP)CARI
73D scanning of historic elements (scan-to-BIM)IARC
Commissioning phase (4 processes)
8Verification of compliance between construction and designARCC
9Quality control of the BIM model (clash detection)IARI
10Technical acceptance of the facilityARCR
11Handover of as-built documentationARRI
Operation phase (10 processes)
12Preparation of HVAC system operation manualsCARC
13Training of BG personnel in the operation of technical systemsIRCA
14Management of microclimate parameters (temp. 23 °C, humidity 70–80%)ICIA
15Monitoring of the technical condition of historic elementsCCIA
16Maintenance of irrigation systems for tropical plantsICIA
17Planning of technical inspections according to BEPARCR
18Updating the BIM model (LOD 500) for facility managementCRRC
19Reporting failures and corrective interventionsIRCA
20Management of plant collections (cultivation requirements)IIIA
21Archiving operational data in the CDEARCR
Role abbreviations:
  • UWr—Investor (University of Wrocław)
  • Contractor—Design–build contractor
  • Designer—Design team (part of the contractor’s team)
  • BG—End user (Botanical Garden of the University of Wrocław)
  • External stakeholders, such as the heritage conservation authority (Provincial Heritage Conservation Officer-WKZ), were assigned to specific processes (e.g., Task 5: “Obtaining conservation approval”—A: Investor, R: Contractor, C: Designer, I: Facility User) but were not included as formal columns in the matrix. The WKZ acts as an administrative authority outside the design–build contract, issuing mandatory decisions without direct operational responsibilities within the contractual responsibility chain.
The RACI matrix underwent a two-stage internal consistency validation to ensure organizational rigor:
  • Completeness check: Each of the 21 processes was verified to ensure the presence of at least one Responsible role (R) responsible for task execution and one Accountable role (A) acting as the decision owner. This procedure eliminated potential accountability gaps. The criterion was satisfied for all tasks, resulting in 23 R assignments and 18 A assignments (Table 2).
  • Redundancy minimization: For each task, the number of Responsible roles was limited in order to avoid overlapping responsibilities. As a standard rule, a single R role was assigned. Multiple R roles (>1) were allowed only for inherently collaborative processes within the design–build (DB) delivery model, such as Task 4 (“Analysis of technical alternatives using the AHP method”) and Task 18 (“Updating the BIM model to LOD 500 for facility management”), where the Contractor and Designer shared operational responsibility while maintaining a single Accountable role. This logic is consistent with established design–build project management practices.
After validation, no accountability gaps or excessive redundancy were identified, confirming the suitability of the matrix to coordinate complex stakeholder structures.
The RACI structure confirms the dominant role of the investor as the entity ultimately responsible for key strategic decisions. The high number of Accountable (A) assignments for the University of Wrocław shows that functional requirements, organizational frameworks, and design solutions remain under its authority, which is typical for public clients. At the same time, the significant share of Informed (I) roles on the investor’s side suggests a deliberately shaped position of an “information guardian” who does not perform operational tasks but supervises their progress and results.
The high share of Responsible (R) and Accountable (A) roles for the contractor indicates a concentration of responsibility for the preparation, coordination, and implementation of technical solutions, reflecting the design–build delivery model. At the same time, the presence of Consulted (C) roles in areas related to functional and conservation requirements reflects the need to coordinate technical solutions with specialized stakeholders, including the end user and heritage protection authorities.
The assignment profile for the designer is characterized by a predominance of Consulted (C) roles while maintaining a significant share of Responsible (R) roles for the preparation of documentation and BIM models. This configuration indicates that the designer performs the function of a specialized technical advisor, whose expert knowledge is used both at the stage of formulating design solutions and in assessing their consequences within multi-criteria analyses (AHP–BOCR). The limited number of Accountable (A) roles on the designer’s side confirms that the ultimate responsibility for decisions lies with the investor and the contractor, while the designer co-shapes these decisions by providing structured technical information.
The configuration of the RACI matrix indicates that the end user, the Botanical Garden, primarily performs the Consulted (C) and Informed (I) roles during the implementation phase, while its importance increases during the operational phase, where the Responsible (R) and Accountable (A) roles emerge in processes related to microclimate management, infrastructure maintenance, and facility use organization. This distribution of roles reflects a typical model for conservation projects, in which the user is not responsible for structural and construction solutions but assumes the key responsibility for their proper use and maintenance according to the intended functional program.
The balanced distribution of R, A, C, and I roles and the absence of tasks without Accountable (A) assignments indicate effective mitigation of so-called accountability gaps, typical for complex projects involving multiple stakeholders. The dominance of active participation (R + C) over passive participation (A + I) suggests that the project process was designed as collaborative, focusing on information exchange and shared decision-making rather than a linear command flow. This is particularly important in the context of projects with high functional and conservation complexity, where the quality of decisions depends on integrating technical, operational, and conservation perspectives.
In the analyzed project, the RACI matrix performed the function of a superior organizational and decision-making structure that was consistently reflected in the BIM environment and the CDE platform. The assignment of the roles R, A, C, and I to the processes of generating, verifying, and approving information in the BEP enabled clear identification of responsibility for data quality and completeness at specific data delivery points (PDD). Thus, the RACI matrix served not only as an organizational tool but also as a foundation for the project’s information governance, ensuring the coherence of integration with the AHP methodology and scan-to-BIM procedures.
The largest share in the RACI matrix consisted of Responsible (R) and Consulted (C) assignments, accounting for 23 (29%) and 22 (28%) entries, respectively. Accountable (A) roles were recorded in 18 cases (23%), while Informed (I) roles appeared in 17 cases (21%). This means that more than half of the matrix (R + C = 56%) concerns the active engagement of project participants rather than passive information flow alone (A + I = 44%), which is characteristic of complex projects implemented in the design–build model for construction undertakings. The distribution of responsibilities is presented in Figure 1; Figure 2 shows the percentage share of engagement types; and Figure 3 presents the distribution of RACI roles by stakeholder.
Distribution of all RACI roles:
  • I (Informed): 17 (21%)—dominance of information flow
  • C (Consulted): 22 (28%)—consultative structure
  • A (Accountable): 18 (23%)—decision-making structure
  • R (Responsible): 23 (29%)—execution structure
The distribution of RACI roles by stakeholders shows differentiated engagement profiles: the investor performs a decision-making function (dominance of A and I roles), the contractor an implementation function (predominance of R and A roles), the designer an advisory function (dominance of C roles), and the end user acts primarily as an information recipient and co-creator of functional requirements (predominance of I and C roles).
The distributed responsibilities obtained (presented in Figure 1) indicates a collaborative character of the investment process with active participation of all parties—from the investor, through the heritage conservation authority, to the specialists of the Botanical Garden—typical for complex projects implemented in the design–build model. The responsibility structure promotes participation in the decision-making process and limits the concentration of responsibility within a single entity. Figure 4 presents a comparison of active versus passive engagement.
Analysis of stakeholder roles showed that Accountable (A) functions were mainly assigned to the investor and the heritage protection authority (heritage conservation officer), while Responsible (R) functions were concentrated on the designer and the construction contractor. End users (Botanical Garden) primarily performed Consulted (C) and Informed (I) roles, particularly in the areas of functional, cultivation, and operational requirements.
Based on the analyses conducted, the identified structure indicates:
  • an even distribution of responsibilities (no dominance of any single group);
  • clear assignment of decision-making roles (elimination of accountability gaps—each task has both R and A);
  • structured communication relationships.
The RACI matrix constituted the basis for further mapping of BIM processes and AHP decision structures.

4.2. Information Management Structure—BIM Execution Plan (BEP)

The results of the BIM environment analysis showed that information management was organized according to the employer’s requirements (EIR) and the ISO 19650 standard. The BIM execution plan (BEP) includes seven main information management domains that define:
  • the structure of project data;
  • procedures for their generation and validation;
  • data delivery points;
  • collaboration rules within the CDE.
Table 3 presents the structure of the document and the defined information management domains.
In the project, a common data environment (CDE) platform compliant with ISO 19650-2 was implemented, serving as a central data repository for all project participants. The CDE platform was divided into four zones:
  • WIP (Work in Progress)—working area for design teams;
  • SHARED—area for consultation and verification;
  • PUBLISHED—approved documentation area;
  • ARCHIVE—historical version archiving area.
The implementation of the CDE contributed to the following:
  • reduction in document search time by 65%;
  • elimination of work on outdated versions (100% version consistency);
  • reduction in document approval time by 40%;
  • increased transparency of the decision-making process (complete history of changes);
  • statistical data on the use of the CDE platform are presented in Table 4.
The values presented in Table 4 are derived from workflow analysis and repeated measurements of task execution time, covering both the period prior to the implementation of the common data environment (CDE) (based on the reference project of the project team) and the implementation phase within the analyzed project.
The measurements were based on 150 document retrieval operations performed on the Dalux platform, with average task durations of approximately 45 min in the traditional document management model and 5 min in the CDE-based workflow. The analysis was not based on a single survey but on a combination of CDE system logs (document publication and retrieval records) and benchmarks from previous projects executed without a formalized CDE, validated by the project team.
The reported indicators (e.g., approximately 89% reduction in document search time and approximately 40% reduction in approval time) should therefore be interpreted as project-based estimates derived from CDE logs and operational experience, rather than full statistical results aggregated across multiple independent projects. A limitation of the analysis is the lack of operational-phase data and the use of a single validation case study.
In Table 4, a clear distinction is made between measured data and expert estimates. Measured data include the number of detected clashes (61, Navisworks reports) and operation times within the CDE (document search: 45 → 5 min; approval time 40% shorter—Dalux workflow operations), as well as actual costs of design corrections (approximately PLN 12,000—based on change registers).
Expert estimates and hypothetical scenarios refer to potential savings (approximately PLN 168,000—estimated cost of resolving clashes during construction based on benchmark data) and error reduction levels (60–80%—based on the literature and the team’s experience from reference projects). A limitation of the study is the lack of financial data from the construction and operational phases, as well as the use of a single validation case study.
Linking the BEP structure with the RACI matrix allowed the assignment of responsibility for generating, verifying, and approving project information to specific participants in the investment process. As a result, the BIM environment performed an operational function in relation to the organizational layer, ensuring the practical implementation of assigned roles.

4.3. Implementation of the Analytic Hierarchy Process (AHP): Selection of Technical Alternatives

The application of the AHP method in the analyzed project aimed to structure the process of selecting technical alternatives for the glass façade of the greenhouse complex, taking into account simultaneous conservation, functional, economic, and organizational requirements. Decision problems were represented as a hierarchy comprising four levels:
  • main objective—selection of the façade alternative;
  • main criteria groups within the BOCR model (Benefits, Opportunities, Costs, Risks);
  • detailed sub-criteria;
  • analyzed technical façade alternatives.
Three technical alternatives were adopted for the evaluation:
  • Variant A—stainless steel frame + tempered safety glass;
  • Variant B—painted carbon steel frame + laminated glass;
  • Variant C—prefabricated modular system.
At the level of BOCR criteria groups, pairwise comparisons were conducted using the Saaty scale (1–9), involving experts representing the investor, designer, contractor, user, and heritage conservation authority. The global weights obtained for the BOCR groups were as follows:
wB = 0.35 (Benefits);
wO = 0.25 (Opportunities);
wC = 0.25 (Costs);
wR = 0.15 (Risks),
which reflects the priority assigned to conservation and functional aspects while simultaneously considering costs and implementation risks.
For each technical alternative, pairwise comparison matrices were constructed with respect to individual BOCR groups, and local priority vectors were determined. In the next step, these values were aggregated into a BOCR-type decision index calculated according to the formula:
Score = wB ⋅ B + wO ⋅ O − wC ⋅ C − w R ⋅ R,
where B, O, C, R denote normalized evaluation values of alternatives in the groups of benefits, opportunities, costs, and risks.
In the baseline analysis, with the above set of weights, Variant B achieved the highest aggregated result (Score = 0.145), indicating its advantage as a compromise between relatively lower investment costs and an acceptable level of implementation risk. Variant A and Variant C obtained score values close to zero (approx. 0.002 and −0.002, respectively), indicating no clear advantage in the baseline proportions between benefits, costs, and risks.
However, a key element of the decision-making process was the sensitivity analysis of AHP results to changes in the weights of the criterion, conducted during stakeholder workshops. Increasing the importance of conservation-related sub-criteria (including the degree of preservation of historic fabric, material compatibility with cast-iron elements, and reversibility of interventions) and long-term risk criteria led to a shift in preference toward Variant A. Variant B remained economically more advantageous, whereas Variant A, despite higher initial costs, ensured better protection of heritage values and greater durability with a lower risk of future repair interventions.
Therefore, the final selection of Variant A as the solution adopted for implementation represents a deliberate departure from the “economically optimal” alternative in favor of a “conservation-safer” alternative, consistent with the priorities of the client and the requirements of the heritage protection authority. The AHP method, supported by quantitative and qualitative data derived from BIM models and conservation documentation, enabled transparent documentation of this compromise and clear communication to all participants in the decision-making process.
For the purpose of synthetic presentation of the results in the article, Table 5 presents the aggregated AHP priority values for the alternatives analyzed and their decision status (preferred, alternative, rejected), Table 6 presents the threshold for weight changes in the AHP-BOCR sensitivity analysis, while Figure 5 and Figure 6 present, respectively, the distribution of alternative priorities and the score values for the BOCR model.
The final selection of Variant A was made after a deliberate adjustment of priorities by the Investor and the heritage conservation authority (WKZ) during project coordination meetings, favoring the conservation-focused scenario presented in Table 6.
This decision does not contradict the AHP methodology. In contrast, the sensitivity analysis confirms that AHP functions as a decision-support tool that flexibly responds to changes in weighting assumptions aligned with the strategic objectives of the project.
The baseline result (preference for Variant B) primarily reflected an economic perspective, while the final priorities adopted in Table 5 incorporated heritage conservation requirements and long-term operational considerations.
Values represent the geometric mean of the judgments of from five experts. All aggregated matrices satisfy the CR < 0.10 consistency requirement, while two individual expert matrices exceeding CR > 0.12 were recalibrated during a second evaluation round.
Table 7 presents example pairwise comparison matrices used in the AHP analysis. The procedure for aggregation and verification of expert judgment involved five experts representing the Investor, Designer, Contractor, User of the Facility, and the Heritage/Environmental Authority (WKZ).
Expert judgments were aggregated using the geometric mean of individual pairwise comparisons, which represents the standard aggregation method of decision-making of the AHP group according to Saaty. Each expert independently completed pairwise comparison matrices using the Saaty scale 1–9 for the four-level hierarchy (BOCR → sub-criteria → alternatives).
Individual consistency was verified using the criterion CR < 0.12 for each expert matrix. Two individual assessments that exceeded this threshold (CR = 0.15 and CR = 0.14) were rejected and recalibrated through a second evaluation round after clarification of the inconsistencies.
For the aggregated group matrices, the consistency was verified using the stricter threshold CR < 0.10 at each hierarchy level, generating the following results:
  • BOCR level: CR = 0.045
  • Sub-criteria matrices: average CR = 0.062
  • Alternative comparison matrices: CR = 0.067
The fourth stage of the procedure involved the calculation of synthetic priorities by multiplying local priorities through the hierarchy, according to Equation (1). The overall consistency ratio of the model (CR = 0.067) confirms an acceptable level of consistency in the final decision model.
The AHP model supported the process as an analytical tool, responding to a deliberate shift in priorities introduced by stakeholders. Figure 7 presents the scheme of the decision-making process that was applied.
As shown in Figure 7, the decision path was iterative, starting from the baseline BOCR result (preference for Variant B under economically oriented weights), followed by sensitivity analysis, stakeholder workshops, and finally leading to the adjusted AHP priorities presented in Table 5. The final selection of Variant A resulted from a conscious shift in priorities by the Investor and the Provincial Heritage Conservation Officer (WKZ) toward a “conservation-focused” scenario. This outcome is consistent with the role of AHP as a decision-support tool, rather than an automatic ranking mechanism.

4.4. Integration of Spatial Data: Scan-to-BIM

As part of the preparation of historical documentation for the preservation of heritage elements of the Australian system (cast-iron columns and beams), terrestrial laser scanning technology (TLS) (Leica ScanStation P50) was applied, enabling the acquisition of high-resolution geometric data of preserved structural fragments with an accuracy of ±3–5 mm (in according to ISO 17123 [50]). The obtained point clouds (eight scans, 360° coverage, resolution of 5 million points) were subjected to registration, filtering, and modeling processes. Point cloud data was stored in the E57 format (ASTM E2807), an open standard for laser scanning data exchange. The BIM model was shared in the IFC 4.0 format, compliant with buildingSMART standards [51], enabling software-independent information exchange among project participants.
The scan-to-BIM process included the following:
  • point cloud processing (registration, noise filtering, cleaning);
  • geometry extraction (semi-automatic modeling in CloudCompare);
  • enrichment of the model with material attributes and conservation information;
  • integration with the coordination model (IFC 4.0).
A level of detail (LOD) of 4 was achieved for historic elements (geometric accuracy + full attribute documentation), and a data structure was prepared that allowed the development of the model to an LOD of 6 (as-built) for facility management and conservation purposes.
During the geometric extraction process, differential tolerances appropriate for the project phase were applied. Table 8 presents the objective quality indicators for reconstruction. Manual segmentation in CloudCompare used a tolerance of approximately ±2 mm for precise edges (e.g., profiles of cast-iron columns), while semi-automatic extraction procedures (Segment/Mesh operations) used tolerances of approximately ±6 mm for irregular surfaces such as deformations or welded joints.
The general uncertainty of the modeling of approximately ±8–12 mm does not limit the applicability of the model to facility management (FM) purposes, such as planning conservation interventions or monitoring environmental conditions.
To ensure transparency for future facility managers, an additional parameter heritage_uncertainty = ±10 mm was included in the IFC Property Sets, indicating the expected geometric uncertainty of the reconstructed heritage elements.
In the case of the Australia Hall cast-iron columns, which represent key heritage components, the BIM geometry was intentionally modeled with a +5 mm dimensional margin relative to the measured geometry and subsequently validated in situ through physical verification, ensuring that the model remained safe for operational use despite minor scanning uncertainties.

4.5. Relationships Between the Layers of the RACI–AHP–BIM Methodology

The research results indicate strong interconnections between the three layers of the methodology:
  • the responsibility structure (RACI matrix) determined the way information was generated and approved within the BIM environment;
  • the BIM environment constituted the data source for AHP decision analyses;
  • decisions made within the AHP model influenced the scope of project analyses and information requirements.
These relationships were iterative in nature, with changes in one layer triggering modifications in the others. As a result, the methodology functioned as a coherent project management system based on information flow between the organizational, decision-making, and informational layers.

5. Discussion

Previous research on BIM has focused primarily on technological and information-related aspects, less frequently integrating them with organizational and analytical management methods [52]. Similarly, the literature on AHP most often treats this method as a decision-support tool, without integration with project information systems [53,54]. In turn, the RACI matrix is generally applied as an organizational tool independent of digital environments.
The presented study indicates that only the integration of these three approaches creates a coherent model for managing projects of high functional complexity and conservation constraints. The results confirm the following:
  • the BIM environment can function as a platform integrating decision-making processes;
  • the AHP method can be fed with data derived from digital models;
  • the RACI matrix constitutes a mechanism institutionalizing decision-making and communication processes.
Such an approach aligns with the growing research trend on the digital transformation of project management, in which the integration of organizational, informational and analytical processes is recognized as a key direction of development.

5.1. Synergistic Effects of Integrating RACI–AHP–BIM

The research conducted indicates that the integration of three approaches—organizational structure (RACI matrix), AHP decision analysis, and the BIM information environment—generates synergistic effects that go beyond the sum of benefits resulting from their separate application. Unlike fragmented approaches, the proposed methodology functions as a system of interconnected layers: organizational, decision-making and informational.
Table 9 presents the specific linkages showing how the clash detection data, the geometric parameters, and the TLS results fed the decision variables in the AHP-BOCR model. The data flow is operational and fully documented.
The first identified mechanism of synergy is the link between the RACI matrix and the BIM processes. In traditional BIM projects, there is often the problem of ambiguous assignment of responsibility for actions within the model environment, including clash management and data validation. Incorporating the RACI matrix into the BIM execution plan (BEP) structure enables the assignment of responsibility for generating, verifying and approving project information to specific roles, which reduces decision ambiguity and structures communication [55,56]. For example, in a traditional design process (without a BIM-based methodology), the following question may arise: who is responsible for resolving a clash detected in the federated model between the HVAC installation (MEP designer) and the structural system (structural designer)? By linking the RACI matrix with BIM, it becomes possible to identify the person responsible on the contractor’s side for the detection of a clash, who initiates the resolution process and moderates the discussion, while the discipline designers (C) present possible alternatives, and the BIM Manager (A) grants the final approval.
The second area of synergy is the integration of AHP with BIM-derived data. Multi-criteria analysis based on data extracted directly from the digital model enables decision-making grounded in actual technical, cost and spatial parameters [25]. Automatic information extraction (e.g., cost data) from the IFC model and the possibility of simulating design variants directly from BIM geometry reduce subjectivity in assessments and increase the transparency of the decision-making process [57]. In the analysis of the investment project, the use of model-derived data enabled the identification of installation clashes (61: hard—8, soft—4, clearance—49), allowing the precise determination of collision risks in the installation interfaces and their inclusion in the variant analysis, which is of direct importance to reduce implementation risks.
The third element of synergy is the link between the RACI matrix and the AHP analysis. The responsibility matrix indicates which stakeholders should participate in evaluating particular decision criteria, thereby structuring the expert process and reducing arbitrariness in assigning weights. As a result, the AHP model becomes not only a mathematical tool but also a component of the project governance structure.
The results obtained confirm that the value of the methodology stems not from individual tools but from their systemic interconnection.

5.2. Importance of the BEP Structure in Reducing Project Risks

The analysis of results indicates that the BIM execution plan functions as a key mechanism for managing informational and process-related risks [58]. Identified risks related to unclear information requirements, inconsistencies in data standards and the lack of procedures for information exchange can be mitigated through process formalization within the BEP framework. Table 10 presents potential risks and mitigation mechanisms, while Figure 8 illustrates the effects of BEP risk reduction through mitigation mechanisms proposed by buildingSMART [51].
The research results indicate that integrating BEP with the RACI matrix and AHP analysis leads to risk reduction in three areas: informational, process-related and organizational. The BIM literature emphasizes that the lack of a coherent information management structure is one of the main causes of inefficiencies in digital projects; the results obtained confirm this relationship in a project of high functional complexity and conservation constraints.

5.3. Role of BEP in Systemic Risk Management

In the context of project management, BIM documents (EIR and BEP) play a key role in transferring the client’s requirements to the contractor and in harmonizing the design and construction processes [59]. This document, updated across successive phases of the project lifecycle, enables the maintenance of information consistency between the design, construction and operation stages.
The research results indicate that, in terms of risk management, the application of BEP enables the reduction in:
  • informational risks—through the precise definition of requirements and levels of information detail (formal EIR + BEP structure);
  • process-related risks—through the formalization of cooperation and communication procedures;
  • organizational risks—through linking the competencies of the participants with the assigned roles.
In the literature on BIM project management, BEP is increasingly perceived as a strategic management tool rather than merely an operational document. The findings of this study confirm this interpretation.
The experience of the project team indicates the following expected range of effects for projects of similar scale (public infrastructure, design–build delivery, heritage constraints):
  • Reduction in accountability gaps from approximately 32% to 0% through the implementation of RACI in a BIM environment.
  • Reduction in construction errors by approximately 60–80% due to clash detection and the use of a Common Data Environment (CDE).
  • Potential cost savings of approximately PLN 500,000–800,000 resulting from optimized definition of LOIN/LOD (internal benchmark data).
These values should be interpreted as hypothetical benchmark estimates, which cannot yet be verified using empirical data from the analyzed investment because the construction and operational phases have not been completed. Full validation of these effects will only be possible after the completion of the project (planned after 2027).

5.4. Role of the RACI Matrix in Limiting Project Conflicts

The results obtained confirm that the application of the RACI matrix contributes to structuring decision-making and communication relationships within the project. Clear assignment of Responsible and Accountable roles reduces the risk of interdisciplinary conflicts, which often arise from competency ambiguities, through:
  • elimination of “black holes,” where each task has at least one Responsible (R) and one Accountable (A) role,
  • reduction in redundancy by preventing multiple assignments of the same task to two roles,
  • communication transparency by clearly indicating who should be informed (I) versus consulted (C).
In the analysis project, a significant outcome of applying the RACI matrix was the extension of the project team structure with new roles related to facility operation management, indicating a shift in perspective from the design phase to the entire investment lifecycle.

6. Summary

The study conducted confirmed that the integration of the RACI matrix, the AHP method, and the BIM methodology in accordance with ISO 19650 constitutes an effective and comprehensive approach to the management of complex construction projects implemented in the design–build delivery model, particularly in the context of conservation-oriented and academic construction projects.
The application of the integrated methodology enabled the structuring of organizational relationships, decision-making processes, and information management within a single coherent project management system. The developed RACI matrix (21 processes × 80 responsibility assignments) allowed the clear allocation of executive and decision-making roles in all key tasks, reducing the appearance of accountability gaps and shortened decision-making processes in critical stages of the project.
The application of the AHP method within the BOCR model enabled a multi-criteria evaluation of design alternatives and the selection of a solution that accounted not only for economic criteria but also for conservation, functional, and risk-related considerations. The results of the analysis indicated a preference for the structural variant with the highest compatibility with the historic fabric of the facility, confirming the suitability of the decision-making model for projects subject to specific cultural and environmental constraints.
The implementation of BIM, supported by the BIM execution plan (BEP) and the common data environment (CDE), enabled the integration of project data, automation of quality control processes, and reduction in interdisciplinary clashes prior to the commencement of construction works. The use of laser scanning technology and the scan-to-BIM procedure made it possible to develop a digital model of preserved historic elements and to prepare operational documentation based on facility management (FM) data.
The findings indicate that the value of the proposed methodology is primarily the results of the integration of the organizational, decision-making, and information layers, rather than the separate application of individual tools.
This study fills a significant gap in the scientific literature:
  • It provided a holistic integration of three approaches into a single RACI-AHP-BIM methodology. Previous research have analyzed RACI, AHP, and BIM as independent methodologies. This article represents one of the first comprehensive studies that integrates these three approaches into a coherent methodological framework. Integration is systemic in nature and demonstrates the mutual reinforcement of methods: RACI structures the organizational framework, AHP supports the decision-making process, and BIM constitutes the operational environment for information management;
  • It extended the application of the RACI matrix to conservation projects, in which heritage protection institutions and future facility users played a significant role. The introduction of roles related to conservation supervision and operational management indicates the possibility of applying RACI throughout the lifecycle of the facility. The proposed adaptation is also of particular relevance for the Polish public sector, where conservation projects constitute a substantial share of construction investments undertaken by higher-education institutions;
  • It provided empirical verification of the application of the BOCR model within the AHP method in design–build projects implemented under conservation and environmental constraints. Although the AHP method has been widely recognized for decades, its application with the BOCR model in design–build projects carried out in protected heritage contexts has not been systematically examined to date. The article offers empirical confirmation of the suitability of the BOCR model for the simultaneous evaluation of conservation benefits, development opportunities, construction costs, and technical risks within a single integrated decision hierarchy;
  • It presented an operational implementation of the ISO 19650 standard in a public project, indicating practical mechanisms for integrating BEP, RACI, and the CDE; documenting the application of scan-to-BIM technology in a conservation project, including technical parameters, data integration procedures; and the potential use of the model during the operational phase (HBIM/digital twin).
The article represents one of the few examples of the comprehensive integration of RACI, AHP, and BIM in the specific context of academic facilities delivered under the design–build system. The proposed RACI-AHP-BIM methodology may serve as a tool supporting the management of construction projects implemented in the public sector, particularly in cases involving a large number of stakeholders and complex formal and conservation constraints. Integration of RACI, AHP, and BIM increases transparency in responsibility allocation and communication, supports data-driven decision-making, reduces informational and organizational risks, and enables a life-cycle-oriented approach to project management. The methodology may be used as a reference framework in the development of BIM execution plans in construction and infrastructure projects, particularly under public procurement conditions.
The results of the study indicate the need for further research in several areas. First, it is necessary to verify the effectiveness of the methodology during the construction phase and the operational period of the facility, including the analysis of cost, time, and operational data. Second, it is justified to assess the potential adaptation of the RACI–AHP–BIM methodology in other types of projects, including infrastructure, linear, and public utility projects. Third, future research should focus on the integration of BIM models with facility management systems and on the development of the digital twin concept in conservation projects. Comparative studies involving a larger number of public projects are also recommended to evaluate the scalability and repeatability of the proposed methodology.

Author Contributions

Conceptualization, U.K.-K.; methodology, U.K.-K.; software, U.K.-K.; validation, U.K.-K.; formal analysis, U.K.-K.; investigation, U.K.-K.; resources, U.K.-K.; data curation, U.K.-K.; writing—original draft preparation, U.K.-K.; writing—review and editing, M.S.; visualization, M.S.; supervision, M.S. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Dataset available on request from the authors.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Rinchen, S.; Banihashemi, S.; Alkilani, S. Driving Digital Transformation in Construction: Strategic Insights into Building Information Modelling Adoption in Developing Countries. Proj. Leadersh. Soc. 2024, 5, 100138. [Google Scholar] [CrossRef]
  2. Zhao, S.; Guan, Y.; Zhou, H.; Hu, F. Accelerating Digital Transformation in Construction: Best Practices for the Successful Implementation of Integrated Digital Delivery. Autom. Constr. 2025, 178, 106417. [Google Scholar] [CrossRef]
  3. Meng, J.; Ye, Z.; Wang, Y. Financing and Investing in Sustainable Infrastructure: A Review and Research Agenda. Sustain. Futures 2024, 8, 100312. [Google Scholar] [CrossRef]
  4. Hadfield, P.; Coenen, L. Contemporary Financial Capitalism and Sustainability Transitions in Urban Built Environments. Environ. Innov. Soc. Transit. 2022, 42, 285–300. [Google Scholar] [CrossRef]
  5. Ripp, M.; Gustafsson, C.; Jones, Z.; Majumdar, S.; Ginzarly, M. Historic Urban Landscapes and Heritage Systems as the Basis for Sustainable Urban Development. Land 2025, 14, 1783. [Google Scholar] [CrossRef]
  6. Lanciotti, A. Preservation of Historical Buildings through the Lens of International Law. Real Estate 2024, 1, 198–211. [Google Scholar] [CrossRef]
  7. Wang, T.; Chen, H.M. Integration of Building Information Modeling and Project Management in Construction Project Life Cycle. Autom. Constr. 2023, 150, 104832. [Google Scholar] [CrossRef]
  8. Kaur, R.; Mwambegele, B.J.; Abraham, A.G.; Basheer, S.A.; Garia, S. A Comprehensive Review on Building Information Modelling (BIM), Its Implementations and Applications. Discov. Civ. Eng. 2025, 2, 177. [Google Scholar] [CrossRef]
  9. Morin, X.; Romero-Torres, A. How Does Building Information Modeling Influence Decision-Making Process in the Project Design? An Input, Process and Output Analysis. Proj. Leadersh. Soc. 2024, 5, 100160. [Google Scholar] [CrossRef]
  10. Abanda, F.H.; Oti, A.H.; Tah, J.H.M. Sustainability and Building Information Modelling: Integration, Research Gaps, and Future Directions. Autom. Constr. 2024, 163, 105420. [Google Scholar] [CrossRef]
  11. Lee, W.Y.; Lee, S.H.; Jin, C.; Hyun, C.T. Development of the RACI Model for Processes of the Closure Phase in Construction Programs. Sustainability 2021, 13, 1806. [Google Scholar] [CrossRef]
  12. Cinelli, M.; Kadziński, M.; Miebs, G.; Gonzalez, M.; Słowiński, R. Recommending Multiple Criteria Decision Analysis Methods with a New Taxonomy-Based Decision Support System. Eur. J. Oper. Res. 2022, 302, 633–651. [Google Scholar] [CrossRef]
  13. Madanchian, M.; Taherdoost, H. Applications of Multi-Criteria Decision Making in Information Systems for Strategic and Operational Decisions. Computers 2025, 14, 208. [Google Scholar] [CrossRef]
  14. Costa, A.P.d.A.; Choren, R.; Pereira, D.A.d.M.; Terra, A.V.; Costa, I.P.d.A.; Junior, C.d.S.R.; Santos, M.d.; Gomes, C.F.S.; Moreira, M.Â.L. Integrating Multicriteria Decision Making and Principal Component Analysis: A Systematic Literature Review. Cogent Eng. 2024, 11, 2374944. [Google Scholar] [CrossRef]
  15. ISO 19650-1:2018; Organization and Digitization of Information About Buildings and Civil Engineering Works, Including Building Information Modelling (BIM)—Information Management Using Building Information Modelling—Part 1: Concepts and Principles. ISO: Geneva, Switzerland, 2018.
  16. Blavier, C.L.S.; Huerto-Cardenas, H.E.; Aste, N.; Del Pero, C.; Leonforte, F.; Della Torre, S. Adaptive Measures for Preserving Heritage Buildings in the Face of Climate Change: A Review. Build. Environ. 2023, 245, 110832. [Google Scholar] [CrossRef]
  17. Dziadosz, A. Estimation and Selection of Building Investment Using the AHP. Czas. Techniczne. Bud. 2008, 105, 41–51. [Google Scholar]
  18. Pan, N.F. Fuzzy AHP Approach for Selecting the Suitable Bridge Construction Method. Autom. Constr. 2008, 17, 958–965. [Google Scholar] [CrossRef]
  19. El-Abbasy, M.S.; Zayed, T.; Ahmed, M.; Alzraiee, H.; Abouhamad, M. Contractor Selection Model for Highway Projects Using Integrated Simulation and Analytic Network Process. J. Constr. Eng. Manag. 2013, 139, 755–767. [Google Scholar] [CrossRef]
  20. Dikmen, I.; Birgonul, M.T.; Han, S. Using Fuzzy Risk Assessment to Rate Cost Overrun Risk in International Construction Projects. Int. J. Proj. Manag. 2007, 25, 494–505. [Google Scholar] [CrossRef]
  21. Saaty, T.L.; Ozdemir, M.S. Why the Magic Number Seven plus or Minus Two. Math. Comput. Model. 2003, 38, 233–244. [Google Scholar] [CrossRef]
  22. Kwast-Kotlarek, U.; Hełdak, M. Evaluation of the Construction and Investment Process of a High-Pressure Gas Pipeline with Use of the Trenchless Method and Open Excavation Method. Analytic Hierarchy Process (AHP). Sustainability 2019, 11, 2438. [Google Scholar] [CrossRef]
  23. Cheung, S.O.; Suen, H.C.H. A Multi-Attribute Utility Model for Dispute Resolution Strategy Selection. Constr. Manag. Econ. 2002, 20, 557–568. [Google Scholar] [CrossRef]
  24. Saaty, R.W. The Analytic Hierarchy Process—What It Is and How It Is Used. Math. Model. 1987, 9, 161–176. [Google Scholar] [CrossRef]
  25. Aladayleh, K.J.; Aladaileh, M.J. Applying Analytical Hierarchy Process (AHP) to BIM-Based Risk Management for Optimal Performance in Construction Projects. Buildings 2024, 14, 3632. [Google Scholar] [CrossRef]
  26. BIM Standard PL—Urząd Zamówień Publicznych—Portal Gov.Pl. Available online: https://www.gov.pl/web/uzp/bim-standard-pl (accessed on 18 February 2026).
  27. Kacprzyk, Z. Polskie Normy BIM—Norma IDM. Bud. Praw. 2017, 20, 1–243. [Google Scholar]
  28. Project BIM Execution Planning (BEP) Standard—National Institute of Building Sciences. Available online: https://nibs.org/nbims/v4/bep/ (accessed on 18 February 2026).
  29. Borkowski, A.S. A Literature Review of BIM Definitions: Narrow and Broad Views. Technologies 2023, 11, 176. [Google Scholar] [CrossRef]
  30. Borrmann, A.; König, M.; Koch, C.; Beetz, J. Building Information Modeling: Technology Foundations and Industry Practice; Springer Nature: Berlin/Heidelberg, Germany, 2018; pp. 1–584. [Google Scholar] [CrossRef]
  31. Borkowski, A.; Michalak, M. Błędy Poznawczei Nowa Emfatyczna Definicja BIM. BUILDER 2024, 322, 54–60. [Google Scholar] [CrossRef]
  32. Osello, A.; Lucibello, G.; Morgagni, F. HBIM and Virtual Tools: A New Chance to Preserve Architectural Heritage. Buildings 2018, 8, 12. [Google Scholar] [CrossRef]
  33. Sacks, R.; Eastman, C.; Lee, G.; Teicholz, P. BIM Handbook; Wiley: Hoboken, NJ, USA, 2018. [Google Scholar] [CrossRef]
  34. Shawky, K.A.; Abdelalim, A.M.; Sherif, A.G. Standardization of BIM Execution Plans (BEP’s) for Mega Construction Projects; A Comparative and Scientometric Study. Trans. Mach. Learn. Artif. Intell. 2024, 12, 103–129. [Google Scholar] [CrossRef]
  35. Construction to Operations Building Information Exchange (COBie) V3—National Institute of Building Sciences. Available online: https://nibs.org/nbims/v3/cobie (accessed on 18 February 2026).
  36. Mapa Drogowa Dla Wdrożenia Metodyki BIM w Zamówieniach Publicznych—Ministerstwo Rozwoju i Technologii—Portal Gov.Pl. Available online: https://www.gov.pl/web/rozwoj-technologia/mapa-drogowa-dla-wdrozenia-metodyki-bim-w-zamowieniach-publicznych (accessed on 18 February 2026).
  37. Kensek, K.M.; Noble, D. Building Information Modeling: BIM in Current and Future Practice; Wiley: Hoboken, NJ, USA, 2015; pp. 1–415. [Google Scholar]
  38. Godager, B.; Mohn, K.; Merschbrock, C.; Klakegg, O.J.; Huang, L. Towards an Improved Framework for Enterprise BIM: The Role of ISO 19650. J. Inf. Technol. Constr. 2022, 27, 1075–1103. [Google Scholar] [CrossRef]
  39. Al Khalil, M.I. Selecting the Appropriate Project Delivery Method Using AHP. Int. J. Proj. Manag. 2002, 20, 469–474. [Google Scholar] [CrossRef]
  40. Al-Harbi, K.M.A.S. Application of the AHP in Project Management. Int. J. Proj. Manag. 2001, 19, 19–27. [Google Scholar] [CrossRef]
  41. Barzilai, J. Deriving Weights from Pairwise Comparison Matrices. J. Oper. Res. Soc. 1997, 48, 1226. [Google Scholar] [CrossRef]
  42. Barzilai, J. On the Decomposition of Value Functions. Oper. Res. Lett. 1998, 22, 159–170. [Google Scholar] [CrossRef]
  43. Knitter-Piątkowska, A.; Kotlarek, U. Znaczenie i Struktura Dokumentu BIM Execution Plan (BEP) w Procesie Inwestycyjno-Budowlanym. BUILDER 2025, 342, 20–25. [Google Scholar] [CrossRef]
  44. Salah, R.; Károlyfi, K.A.; Szép, J.; Géczy, N. A Structured Framework for HBIM Standardization: Integrating Scan-to-BIM Methodologies and Heritage Conservation Standards. Digit. Appl. Archaeol. Cult. Herit. 2025, 37, e00420. [Google Scholar] [CrossRef]
  45. Rocha, G.; Mateus, L.; Fernández, J.; Ferreira, V. A Scan-to-BIM Methodology Applied to Heritage Buildings. Heritage 2020, 3, 47–67. [Google Scholar] [CrossRef]
  46. Lovell, L.J.; Davies, R.J.; Hunt, D.V.L. The Application of Historic Building Information Modelling (HBIM) to Cultural Heritage: A Review. Heritage 2023, 6, 6691–6717. [Google Scholar] [CrossRef]
  47. Javier Sánchez Aparicio, L.; Luis Del Blanco García, F.; Martín Talaverano, R.; Klapa, P.; Pepe, M. 3D Heritage Reconstruction Through HBIM and Multi-Source Data Fusion: Geometric Change Analysis Across Decades. Appl. Sci. 2025, 15, 8929. [Google Scholar] [CrossRef]
  48. Abd ElWahab, H.A.; Bakr, A.F.; Raslan, R.A. Heritage Building Information Modeling (HBIM) for Heritage Conservation: Framework of Challenges, Gaps, and Existing Limitations of HBIM. Digit. Appl. Archaeol. Cult. Herit. 2024, 35, e00366. [Google Scholar] [CrossRef]
  49. PN-EN ISO/IEC 27001:2023-08; Bezpieczeństwo Informacji, Cyberbezpieczeństwo i Ochrona Prywatności—Systemy Zarządzania Bezpieczeństwem Informacji—Wymagania. Polski Komitet Normalizacyjny: Warsaw, Poland, 2024. (In Polish)
  50. PN-ISO 17123-3:2005; Optyka i Instrumenty Optyczne—Terenowe Procedury Testowania Instrumentów Geodezyjnych i Pomiarowych. Polski Komitet Normalizacyjny: Warsaw, Poland, 2005. (In Polish)
  51. buildingSMART Solutions and Standards. Available online: https://www.buildingsmart.org/standards/ (accessed on 20 February 2026).
  52. Turk, Ž. Reflections on Three Decades of Building Information Modeling. Buildings 2025, 15, 231. [Google Scholar] [CrossRef]
  53. Madzík, P.; Falát, L. State-of-the-Art on Analytic Hierarchy Process in the Last 40 Years: Literature Review Based on Latent Dirichlet Allocation Topic Modelling. PLoS ONE 2022, 17, e0268777. [Google Scholar] [CrossRef]
  54. Vaidya, O.S.; Kumar, S. Analytic Hierarchy Process: An Overview of Applications. Eur. J. Oper. Res. 2006, 169, 1–29. [Google Scholar] [CrossRef]
  55. Farouk, A.M.; Zulhisham, A.Z.; Lee, Y.S.; Rajabi, M.S.; Rahman, R.A. Factors, Challenges and Strategies of Trust in BIM-Based Construction Projects: A Case Study in Malaysia. Infrastructures 2023, 8, 13. [Google Scholar] [CrossRef]
  56. Da Silva, T.F.L.; Vieira, D.R.; De Carvalho, M.M. Exploring the Challenges in Building Information Modeling (BIM) During the Design Phase: Evidence from Cross-Country Studies. IEEE Trans. Eng. Manag. 2024, 71, 14846–14860. [Google Scholar] [CrossRef]
  57. Wong Chong, O.; Zhang, J. Automated Extraction of Locational Information from IFC-Based Building Information Models. In Proceedings of the Construction Research Congress 2024, Des Moines, IA, USA, 20–23 March 2024; pp. 148–156. [Google Scholar] [CrossRef]
  58. Panagiotidou, N.; Pitt, M.; Lu, Q. Building Information Modelling Execution Plans: A Global Review. Proc. Inst. Civ. Eng. Smart Infrastruct. Constr. 2023, 176, 126–147. [Google Scholar] [CrossRef]
  59. Chapter 4—BIM Project Implementation. OpenBIM KnowledgeBase. Available online: https://openbim-knowledgebase.org/en/docs/bimcert-manual-2024/chapter-4-bim-project-implementation/ (accessed on 20 February 2026).
Figure 1. Distribution of responsibilities in the RACI matrix by engagement type.
Figure 1. Distribution of responsibilities in the RACI matrix by engagement type.
Infrastructures 11 00105 g001
Figure 2. RACI matrix: Percentage share of engagement types.
Figure 2. RACI matrix: Percentage share of engagement types.
Infrastructures 11 00105 g002
Figure 3. RACI matrix: Distribution of RACI roles by stakeholders.
Figure 3. RACI matrix: Distribution of RACI roles by stakeholders.
Infrastructures 11 00105 g003
Figure 4. RACI matrix: Division into active vs. passive engagement of project participants.
Figure 4. RACI matrix: Division into active vs. passive engagement of project participants.
Infrastructures 11 00105 g004
Figure 5. Results of the AHP analysis—priorities of technical alternatives for the glass façade (CR = 0.067).
Figure 5. Results of the AHP analysis—priorities of technical alternatives for the glass façade (CR = 0.067).
Infrastructures 11 00105 g005
Figure 6. Evaluation of AHP–BOCR.
Figure 6. Evaluation of AHP–BOCR.
Infrastructures 11 00105 g006
Figure 7. Decision path from the BOCR baseline result to the selection of option A.
Figure 7. Decision path from the BOCR baseline result to the selection of option A.
Infrastructures 11 00105 g007
Figure 8. Effects of BEP risk reduction through mitigation mechanisms proposed by buildingSMART [51].
Figure 8. Effects of BEP risk reduction through mitigation mechanisms proposed by buildingSMART [51].
Infrastructures 11 00105 g008
Table 2. Statistical summary.
Table 2. Statistical summary.
RoleRACITotalEngagement Profile
UWr (Investor)192921DECISION-MAKER (A: 40%, I: 43%)
Contractor1064121IMPLEMENTER (R: 48%, A: 29%)
Designer819321TECHNICAL ADVISOR (C: 43%, R: 38%)
BG (End user)427417INFORMATION RECIPIENT (C: 41%, I: 24%)
TOTAL2318221780
Table 3. BEP structure and information management domains.
Table 3. BEP structure and information management domains.
BEP AreaContentDocument FormResponsible
1. BIM ObjectivesIncrease management efficiency, reduce design errors (clash detection), improve interdisciplinary collaboration, prepare for FM LOD 6.Text description + objectives tableBIM Manager
2. Modeling StandardsIFC 4.0, LOIN (LOD 3 → 4 → 6 according to EN 17412), GIS catalogs, element attributes, parametric relationships.Technical specification + schedulesBIM Modeler + Lead Designer
3. CDE Work Rules (DALUX)Workflow: WIP → Shared → Published → Archived, naming convention, backup (10 years), access control, version management.Operational proceduresCDE Coordinator
4. Quality Control Procedures (MQC)Model verification after each update, clash detection at least once per month, data audit, non-conformance reports.Quality Control Plan (QCP)Clash Detection Specialist
5. Roles and ResponsibilitiesRACI matrix 21 × 80, escalation processes, interdisciplinary communication, coordination meetings every 2 weeks.RACI matrix + CP/RM proceduresBIM Coordinator
6. Data SecurityPN-EN ISO/IEC 27001 [49], IP confidentiality, archiving, encryption, role-based access control.ISMS policyIT/CDE Manager
7. Training and Competencies4 DALUX training sessions, BIM certification (minimum 40 h), tool updates.Training plan (CDP)HR + BIM Manager
Table 4. Statistical data on the use of the CDE platform in the project.
Table 4. Statistical data on the use of the CDE platform in the project.
CategoryIndicatorValueData TypeComment
CDE structureNumber of zones in CDE4Measured 1WIP, SHARED, PUBLISHED, ARCHIVE—according to ISO 19650 and BEP
Access to informationAverage time to locate a required document45 → 5 min
(89%)
Measured (CDE)Reduction of approx. 45 min in the traditional model (approx. 89% time savings)
Approval processReduction in documentation approval timeapprox. 40%Measured (CDE)Compared with projects without formalized CDE/BEP (based on team experience)
Interdisciplinary coordinationNumber of clashes detected in the BIM model (pre-construction)61 (8 hard, 4 soft, 49 clearance)Measured (Navisworks reports)8 hard, 4 soft, 49 clearance—identified in the CDE/BIM environment
Interdisciplinary coordinationActual cost of resolving clashes (in the project)approx. 12,000 PLNMeasured (order records)Corrective work performed at the design stage in the CDE
Interdisciplinary coordinationEstimated cost savingsapprox. 168,000 PLNExpert estimate 2Difference between the traditional scenario and the implemented RACI–AHP–BIM + CDE methodology; PLN 2500/collision on site
Error reductionEstimated60–80%Literature + experienceLiterature, projects ref.
1 Measured = system actions/reports; Expert estimate = benchmarks + team experience. 2 Scenario: costs of resolving conflicts on the construction site (team reference projects).
Table 5. Results of the AHP analysis—selection of technical alternatives for the glass façade of the greenhouse complex. AHP priorities for variants A, B, and C after workshops and sensitivity analysis.
Table 5. Results of the AHP analysis—selection of technical alternatives for the glass façade of the greenhouse complex. AHP priorities for variants A, B, and C after workshops and sensitivity analysis.
Technical AlternativeWeight (AHP Priority)Status and Justification
Variant A: Stainless steel frame + tempered safety glass0.42 (42%)PREFERRED—Highest conservation compatibility, durability > 50 years, compliance with heritage authority requirements
Variant B: Painted carbon steel frame + laminated glass0.35 (35%)ALTERNATIVE—Lower costs (~20%), lower durability (30–40 years), requires maintenance every 5 years
Variant C: SCHÜCO modular prefabricated system0.23 (23%)REJECTED—Lack of compatibility with historic cast-iron elements, unacceptable to the heritage authority
Table 8. Objective quality indicators of the scanning-to-BIM reconstruction.
Table 8. Objective quality indicators of the scanning-to-BIM reconstruction.
Quality IndicatorValueMeasurement MethodAccepted ToleranceComment
Point cloud registration error (RMS)3–5 mmCloudCompare (ICP registration)<6 mm (ISO 17123 [50])8 scans, full 360° coverage
BIM model deviation vs. point cloud82% (0–5 mm) 15% (5–10 mm) 3% (>10 mm)CloudCompare Distance analysis±10 mm for LOD 4Main structural elements and heritage components
Completeness of historic elements95%Comparison with heritage inventory>90%Inventory catalog: 42 heritage elements
Extraction uncertainty (semi-automatic)±4 mmCloudCompare Segment/Mesh analysisManual: ±2 mm Semi-automatic: ±6 mmIrregular edges and complex geometry
Table 6. Threshold for weight changes in AHP-BOCR sensitivity analysis.
Table 6. Threshold for weight changes in AHP-BOCR sensitivity analysis.
ScenarioChanged Key Weights Variant AVariant BVariant CRank
Baseline (economic)B = 0.35; O = 0.25; C = 0.25; R = 0.150.0020.145–0.002B > A > C
Conservation (±15% on B/R maintenance)B = 0.42; O = 0.22; C = 0.20; R = 0.160.1520.140–0.010A > B > C
Cost (±15% on C/O)B = 0.30; O = 0.28; C = 0.30; R = 0.12–0.0150.1320.008B > C > A
Reversal threshold (conservation > 55–60%)Maintenance criterion
+risk > 0.55
>0.145<0.145A > B
Note: Reversal of rank (A > B) occurs when the combined weight of conservation and risk criteria (B/R) exceeds approximately 55–60%, while the weight assigned to cost criteria decreases below approximately 20–22%. Under these conditions, Variant A remains stable across a relatively wide range of weight variations (approximately ±15%).
Table 7. Example pairwise comparison matrices in AHP (Saaty 1–9 scale).
Table 7. Example pairwise comparison matrices in AHP (Saaty 1–9 scale).
(a) BOCR Level Matrix (5 Experts—Geometric Mean Aggregation)
BOCRBenefits (B)Opportunities (O)Costs (C)Risks (R)Local Priority
Benefits (B)13570.642
Opportunities (O)1/31350.248
Costs (C)1/51/3130.088
Risks (R)1/71/51/310.022
Column sum1.674.539.3316.00CR = 0.045
(b) Sub-Criterion Matrix: “Compatibility with Historic Fabric” (Benefits Group)
Sub-criterion BDurabilityAuthenticityReversibilityPriority
Durability11/350.385
Authenticity3170.579
Reversibility1/51/710.036
CR = 0.062 1.000
Table 9. Mapping of BIM/CDE with AHP–BOCR decision variables.
Table 9. Mapping of BIM/CDE with AHP–BOCR decision variables.
BIM/CDE Data SourceSpecific ValueBOCR CriterionSub-CriterionInfluence on Variant Evaluation
Clash detection results61 clashes (8 hard, 4 soft, 49 clearance)Risks (R)Implementation riskVariant C: −15% (highest number of MEP conflicts)
Design correction costsapprox. 12,000 PLNCosts (C)Cost of design modificationsAll variants: real correction costs observed during the design phase
Façade geometry parametersGlazing area: 1250 m2 Ug = 0.6 W/m2KCosts (C)Material costsVariant B: +12% advantage due to cheaper profiles
Durability parametersEstimated service life: 25 yearsBenefits (B)Structural durabilityVariant A: +18% advantage (Optiwhite glazing system)
TLS scan-to-BIM dataColumn accuracy ±5 mm Completeness: 95%Benefits (B)Compatibility with historic fabricVariant A: +25% (preservation of original cast-iron columns)
TLS reconstruction parametersOversize modeling margin +5 mmRisks (R)Reversibility of interventionVariants A/B: low intervention risk
Table 10. Effects of the RACI–AHP–BIM methodology according to the literature and professional experience.
Table 10. Effects of the RACI–AHP–BIM methodology according to the literature and professional experience.
No.Risk CategorySymptomMitigation Mechanism in the ProjectEffect
1Unknown roles and responsibilitiesInformation gaps, errors, delaysRACI matrix 21 × 80, coordination meetings every 2 weeks, escalation proceduresElimination of accountability gaps (32% → 0%)
2Inconsistent standards and proceduresDifficulties in interdisciplinary coordination, incompatible modelsIFC 4.0, naming convention [Code][Discipline][Type][Revision][Date], LOIN EN 17412Clash detection: 3 hard + 7 soft, resolved before construction
3Inadequate LOIN levelToo high = excessive costs, too low = limited BIM usefulnessPrecise definition: LOD 3 (design) → LOD 4 (construction) → LOD 6 (as-built + FM)PLN 500k–800k saved
4Inefficient data exchange processWorking on outdated versions, conflictsCDE Dalux: WIP → Shared → Published → Archived, 10-year backup, naming convention100% model currency, zero version conflicts
5Lack of quality control proceduresErrors transferred to the construction stageMQC, detection of clash at least once per month, Data Audit, QCP (Quality Control Plan)Reduction in construction errors by 60–80%
6No link between BEP and project objectivesBEP treated as a “paper document”BEP linked to 21 RACI roles, BIM objectives (scan-to-BIM, clash detection, FM LOD 6), and the schedule100% team engagement in BIM processes
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Kwast-Kotlarek, U.; Szóstak, M. RACI–AHP–BIM Methodology in Projects with High Functional Complexity and Conservation Constraints. Infrastructures 2026, 11, 105. https://doi.org/10.3390/infrastructures11030105

AMA Style

Kwast-Kotlarek U, Szóstak M. RACI–AHP–BIM Methodology in Projects with High Functional Complexity and Conservation Constraints. Infrastructures. 2026; 11(3):105. https://doi.org/10.3390/infrastructures11030105

Chicago/Turabian Style

Kwast-Kotlarek, Urszula, and Mariusz Szóstak. 2026. "RACI–AHP–BIM Methodology in Projects with High Functional Complexity and Conservation Constraints" Infrastructures 11, no. 3: 105. https://doi.org/10.3390/infrastructures11030105

APA Style

Kwast-Kotlarek, U., & Szóstak, M. (2026). RACI–AHP–BIM Methodology in Projects with High Functional Complexity and Conservation Constraints. Infrastructures, 11(3), 105. https://doi.org/10.3390/infrastructures11030105

Article Metrics

Back to TopTop