1. Introduction
Facing serious water shortages in the local regions of China, more and more long-distance water delivery projects for the efficient utilization and allocation of water resources have been constructed in recent years [
1,
2]. These projects not only play a crucial role in alleviating uneven water distribution but also introduce a series of new technical and management challenges [
3,
4,
5]. In particular, the long-distance water delivery tunnels built using a tunneling boring machine (TBM) have been successfully passed through the complex and variable geological conditions such as fault fracture zones and karst caves. This brings the problems of segment assembly defects during construction [
6,
7], operational challenges such as water pressure [
8], surrounding rock geology [
9,
10], and environmental conditions [
11,
12], which pose severe challenges to the safety and stability of the structure. Therefore, risk assessment during the construction and operational phases of tunnel projects is critical.
Risk assessment is a crucial systematic analysis method in engineering, and its importance has increased over time. This not only identifies and evaluates potential risk factors but also provides a scientific decision for optimizing engineering management [
10,
11,
12,
13,
14]. Specifically, in hydraulic structures, scholars frequently utilize various methods, including the analytical hierarchy process (AHP) and fuzzy comprehensive evaluation (FCE), to assess project risks to prevent high-risk events and mitigate their potential hazards [
15,
16,
17,
18].
In the multilevel assessment of the structural health of the Shanghai subway tunnels during their operational phase, a tunnel health assessment method based on a multilevel evaluation system was proposed, providing a practical assessment framework for structural health monitoring [
19]. The AHP was used to establish a risk factor evaluation index system with geology, mechanics, and operations as influencing factors during tunnel excavation. This system quantitatively assesses the risks associated with the formation of a shield tunneling face, enhances the understanding of risk factors, and proposes corresponding preventive measures [
20]. To explore the operational risks of the water lifting, water transmission, and water storage systems in the Eastern Route Project of the South-to-North Water Diversion, the AHP was employed to categorize and rank the operational risks of these three systems [
21]. Using fuzzy mathematics theory and expert evaluation methods [
22], the tunnels were assessed for risk grades, and the results were highly consistent with experimental comparisons. The improved fuzzy analytical hierarchy process was used to predict risks related to tunnel structure safety, enhancing the consistency of expert judgments and promoting its application in more complex systems [
23,
24]. The baseline weights of dynamic risk assessment indicators in engineering were also built using the AHP combined with the adjustment based on monitoring data. A fuzzy evaluation matrix for construction risk membership degrees was obtained using the FCE, and segmental value assignment was applied to analyze the results [
25]. The system reliability analysis in geotechnical engineering for the unsaturated soil nailing wall systems using random finite element methods and the slope system based on sequential compounding methods further highlight the importance and applicability of system-level risk models in complex engineering environments [
26,
27]. Although scholars have achieved the objective of risk evaluation using the AHP, FCE, or in combination with other methods, these singular approaches often fail to fully address the uncertainties and multidimensional risk factors present in complex systems.
Therefore, a risk management model for tunnels was established by integrating the AHP with fuzzy set theory, which effectively determined the priority of identified hazardous areas and provided the optimal countermeasures [
28]. To reduce the risks associated with the construction of shield tunnels in karst strata, a risk assessment framework for first-level indicators, including karst geological conditions, hydrogeological conditions, tunnel design, and shield construction, was developed using a cloud model and the fuzzy AHP [
29]. To optimize risk-grading standards in tunnel engineering, a new risk evaluation framework was proposed combing the MIVES multi-criteria decision-making method with the AHP [
30]. To enhance the safety of tunnel construction, a hybrid dynamic risk assessment method combining the AHP with a trapezoidal cloud model (TCM) and Bayesian network (BN) was developed [
31]. Additionally, fuzzy DEMATEL and AHP methods have been used to analyze geological risks in tunnel projects [
32]. To optimize the management of hydrogeological burst hazards in tunnels, the weights calculated by the AHP combined with fuzzy decision methods were used to rank management strategies [
33]. Furthermore, a risk assessment model that integrates the AHP with catastrophe theory was established to improve the prediction of extreme disasters [
34]. To enhance the precision and adaptability of assessments, the existing AHP model was improved by incorporating fuzzy theory for more flexible risk forecasting [
35]. By combining the fuzzy AHP with set pair analysis, a comprehensive risk assessment model for long highway operational tunnels was created that merges subjective weighting with objective evaluations, thereby improving the accuracy of risk assessments in long highway operational tunnels [
36]. These evaluations effectively anticipate and control issues such as lining structure damage and water leakage, ensuring the safe operation of tunnels and the long-term stability of projects [
37]. However, existing approaches still have certain limitations when dealing with complex uncertainties, making it challenging to simultaneously account for both the hierarchical weighting of risk factors and the impact of fuzziness. Therefore, further optimization of risk assessment models to enhance their accuracy and adaptability during the construction and operation phases remains a critical area for in-depth research.
In view of the backdrops, this study introduces the AHP-FCE risk assessment model that integrates the AHP and FCE to be a comprehensive evaluation method for the safety evaluation of a water delivery tunnel operation. The AHP method establishes a multilevel analytical structure, decomposes complex decision-making problems into various components, and assigns weights to these components through pairwise comparisons, facilitating the quantification of subjective judgments in the decision-making process. In contrast, the FCE method utilizes fuzzy mathematics to handle and analyze data characterized by uncertainty or ambiguity, allowing risk assessment to more comprehensively reflect the complexity and uncertainty of real situations. By combining these two methods, it is possible to establish a hierarchical structure of risk factor weights and mitigate the adverse effects of fuzzy judgments on the results. This makes it so that the risks can be identified and assessed more accurately, and targeted strategies and measures for risk prevention and treatment can be determined, thereby significantly enhancing the safety and stability of hydraulic tunnel projects.
4. Risk Assessment for Tunnel Operation
4.1. Operation Risk Factor System Set
Based on the project engineering data and operation risks identified through the risk checklist method and expert surveys, this section selects five first-level risks and fifteen second-level risks in the operation risk category as the main influencing factors for the AHP analysis of the tunnel operation. The hierarchical structural model is illustrated in
Figure 3, which means that the operation period risk A is determined by the weighted fuzzy comprehensive evaluation for B-level indicators in a parallel configuration, and the second-level risk indicators (C-level) under each B-level indicator are considered in a series configuration. This series-parallel structure reflects both the dependency within subsystems and the aggregated impact at the system level.
4.2. Evaluation Comment Set and Judgment Matrix
To ensure objectivity and accuracy, experts and management personnel from five units involved in the project, including survey, design, supervision, construction and operation, were selected, totaling 10 individuals. The experts were surveyed using questionnaires to collect evaluation scores for the second-level risk indicators of tunnel operation risks. The survey participants were all personnel directly involved in the tunnel project, each possessing solid professional expertise and industry experience.
As mentioned in
Section 3.1, the safety levels were divided into five categories that are represented by the evaluation comment set
V = {very high, high, moderate, low, very low}. After collecting the questionnaires, the results were organized and analyzed, yielding the evaluation results for the second-level risk indicators with the average score and standard deviation, as shown in
Table 6. Subsequently, the comprehensive evaluation method was used to assess the factors affecting the risks.
The established second-level risk indicators were 15 in total. Based on this, the fuzzy judgment matrix Ri for the criteria layer is calculated as follows:
The fuzzy judgment matrix for environmental impact factor B1 is
The fuzzy judgment matrix for structural impact factor B2 is
The fuzzy judgment matrix for design factor B3 is
The fuzzy judgment matrix for management personnel factor B4 is
The fuzzy judgment matrix for other factors B5 is
4.3. Weights of Evaluation Factor Set for the Tunnel
Based on the scoring performed by the 10 experts using the 1–9 scale method for the risk factors during tunnel operation, the weight values for each risk indicator were calculated. After organizing the data, the relative importance of each indicator at the criteria and indicator layers was determined using Formula (4) to obtain the normalized judgment matrix, and Formula (5) was used to obtain the weight vector W
i; the results are summarized in
Table 7. For instance, the normalized matrix yields a row average of 0.1107 for B1, which corresponds to W
1 = 0.1107.
It is noteworthy that the relative importance values in the B-level matrix were derived from expert consensus. For example, B1 was rated 2.0 times more important than B5, reflecting the belief that environmental conditions such as erosion and material degradation have a greater influence on tunnel operational risk than uncertainly external factors like policy changes. However, due to the matrix normalization and the influence of all pairwise comparisons, the final weight of B1 is only slightly higher than that of B5 after the calculations using Formulas (4) and (5). This demonstrates that the “2.0” input does not directly produce a double weight, which only contributes proportionally within a multi-criteria system.
For the B1 indicator layer, the weight calculation and consistency check are shown in
Table 8. The maximum eigenvalue
= 5.1301, and the eigenvector is
W1 = (0.1360, 0.2571, 0.3404, 0.0865, 0.1801). After performing the consistency check,
CI = 0.0325 and
CR = 0.0290 < 0.1, indicating that the calculation results met the required consistency. Finally, using
Table 8,
Table 9,
Table 10,
Table 11 and
Table 12, the weights of the various indicator factors were determined, and the statistical results of the indicator factor weights are presented in
Table 13.
From
Table 13, it can be seen that the risks with the greatest impact on risk management relates to lining cracking (C22, 0.2030), flow control and regular maintenance (C42, 0.1646), construction defects (C23, 0.1162), design defects (C32, 0.1155), and delayed operation and maintenance funding (C43, 0.0628). These factors should be prioritized in risk management.
4.4. Fuzzy Comprehensive Evaluation of the Tunnel
4.4.1. Risk Assessment of the Criteria Layer Factors
Based on the weight vector
Wi from
Table 13, there exist
Using Formula (9), the evaluation result vector is calculated as follows:
From
Table 14, which shows the evaluation results of criterion layer factors, the environmental impact factors and the design factors are evaluated as minor risks, while the structural impact factors and the management personnel factors are moderate risks and the other factors are a minor risk.
4.4.2. Fuzzy Comprehensive Evaluation of Goal Layer
Similarly, the fuzzy comprehensive evaluation matrix for the goal layer is
Based on the FCE result vector, the calculated risk score for the tunnel operation was 43.935, with the evaluation result being Level 3, that is, moderate risk. This indicates that the tunnel can be operated under normal conditions, although certain risk factors such as segment lining cracking and inadequate flow control and maintenance may raise a tangible threat to operation. However, if not properly resolved in time, in the long term, a potential cumulative vulnerability of a moderate risk level could gradually lead to structural degradation or functional impairment. Therefore, appropriate measures should be taken to treat these risks.
4.5. Risk Treatment Measures
Through analysis and calculation, the final evaluation result of the operational risk for the water delivery tunnel of the West Route Project for Anyang City is moderate risk. The structural impact factors and management personnel factors were both evaluated as moderate risk. From the evaluation process and results, it is evident that significant risks exist in lining cracking, flow control, and regular maintenance. It can be observed that the higher risk factors in the operation phase are likely to lead to tunnel leakage. Therefore, it is essential to manage and prevent these risks.
- (1)
Lining cracking
Lining cracking can lead to tunnel water leakage, which not only results in water supply loss but also adversely affects the foundation support structure. Since such defects are difficult to detect and address once the tunnel is operational, preventive measures should be implemented before the tunnel becomes operational after construction. The treatment of cracks depends on their width and can be classified into surface treatment, low-pressure grouting, and filling methods. If the crack width is less than 0.2 mm, only surface treatment is required. If the crack width is between 0.2 mm and 0.3 mm, surface treatment and grouting treatment are both necessary. When the crack is wider than 0.3 mm, a filling method should be applied.
- (2)
Flow control and regular maintenance
After the tunnel is put into operation, flow control and regular maintenance impact the proper stress distribution of the segment rings and the timely handling and repair of severe internal issues. These are critical for ensuring the normal operation of the tunnel and water conveyance capacity. Therefore, during the operation, it is important to strengthen the standardized training of operators, strictly control the amount of water flow inside the tunnel, ensure that regular maintenance is performed quickly and properly to resolve issues, and ensure the safe water supply capacity of the tunnel.