4.1. Similarity Relation
Based on similarity theory, a scale model was used in this test. The physical model test was conducted to investigate the deformation response and rectification effectiveness of staged underexcavation for an existing tilted high-rise building under collapsible-loess conditions. The size, geological conditions, model type, and material of the high-rise building and the production conditions were considered comprehensively [
22]. Considering that the objective of this study was to investigate the deformation coordination mechanism during staged underexcavation rather than the bearing capacity of individual foundation components, an equivalent similarity approach was adopted [
23]. The composite foundation system was simplified while maintaining the equivalent stiffness and deformation characteristics of the foundation–soil interaction system. The length
L of the foundation soil layer, the elastic modulus
E of the superstructure, the weight
W of the foundation soil layer, and the cohesion
c of the foundation soil were selected as the basic dimensions. The geometric similarity ratio
CL = 1 × 10
2, the elastic modulus similarity ratio
CE = 10, the unit weight similarity ratio
CW = 1, the cohesion similarity ratio
Cc = 10, and the similarity ratio of the remaining physical quantities were derived from the above dimensions (see
Table 5).
4.3. Similarity Material Preparation
- (1)
Foundation Similarity Material Preparation
The prototype foundation system consists of a thick raft foundation supported by a composite foundation comprising compacted concrete piles and compacted soil piles, with the underlying geological profile mainly consisting of loess-like soil and strongly weathered mudstone. The objective of this study was to investigate the overall deformation response and correction mechanism of the building–foundation–soil interaction system during the staged underexcavation process, rather than to evaluate the load-bearing behavior of individual piles. Therefore, an equivalent simulation approach based on similarity theory was adopted to reasonably idealize the prototype foundation system. In the physical model test, the complex pile-soil composite foundation and multilayer geological structure were not reproduced individually; instead, equivalent foundation materials were employed to represent the macroscopic mechanical behavior resulting from the coupled interaction between the composite foundation and the underlying strata. Under the requirements of similarity criteria, the equivalent materials were developed by controlling key mechanical parameters, including the unit weight, cohesion, internal friction angle, and compression modulus, thereby effectively reproducing the settlement characteristics and mechanical response of the prototype foundation system.
Basic parameters such as the density and the specific gravity of the undisturbed soil were determined using the cutting ring method and the pycnometer method, respectively. The strength parameter, cohesion, was measured using the direct shear test. The test results are shown in
Table 6.
According to the similarity relationship, the target values of the model test yellow clay parameters were as follows:
W = 14.06 KN/m
3,
c = 3.3 KPa,
φ = 24°,
w = 14.35%, and
ES = 1.55 MPa. Under the premise of meeting the weight and moisture content, the yellow clay layer in the model box was proposed to be composed of fine sand, slaked lime, sawdust, and water. The proportion of each material is shown in
Table 7. The model materials meeting the target physical properties were validated using the direct shear test and confined compression test.
The physical properties of four different proportions of yellow clay similarity materials are shown in
Table 8.
It can be seen from
Table 8 that the physical properties of the similarity material in the ratio 4 model were closest to the physical properties of the target yellow clay, so this ratio was used for the foundation soil layer.
- (2)
Structurally similar material preparation
The high-rise building was a reinforced concrete shear-wall structure. The concrete had an elastic modulus of 30 GPa. According to the similarity ratio of the elastic modulus, the elastic modulus of the structurally similar material was determined to be 3.0 GPa. The elastic modulus of a mixture of fly ash/gypsum/fine sand/water at a ratio of 25:45:30:45.5 was 3.06 GPa, which was close to 3.0 GPa.
4.5. Test Scheme
Initially, after preparing the similarity materials, the foundation soil were layered in the model box, and each layer was compacted to the design height. The density was guaranteed to meet the requirements. The upper structure was cast and molded using a plywood mold. After 14 days of maintenance, the formwork was removed and assembled with the foundation. After completion of the test model, nine simulated shafts (TJ1~TJ9) were excavated with dimensions of 30 mm × 20 mm × 60 mm. Five displacement sensors (L1–L5) and three magnetic absorption dial indicators (C1–C3) were synchronously installed to construct the displacement monitoring system.
Before conducting the staged underexcavation test, an initial inclined state corresponding to the prototype-building condition was first established in the physical model based on the measured settlement distribution characteristics. Field investigations indicated that the prototype building inclination was primarily caused by insufficient compaction of the inter-pile soil and the degradation of soil mechanical properties induced by long-term water infiltration, resulting in differential foundation settlement. Therefore, the initial deformation state was introduced by reproducing the differential settlement characteristics of the prototype foundation rather than by artificially adjusting the inclination of the superstructure. After completion of the model foundation and installation of the superstructure, the local deformation characteristics of the model foundation were controlled according to the measured settlement pattern of the prototype building, ensuring consistency in inclination direction, settlement distribution, and inclination magnitude. After the initial inclined state reached stability, the staged underexcavation test was performed to reproduce the deformation evolution and mechanical response of the actual inclined building during the correction process.
The inclination of the building was not caused by an initially inclined superstructure but instead primarily resulted from differential settlement beneath the foundation. The differential settlement induced rotation of the raft foundation and shifted the line of action of the building load relative to the foundation center, thereby generating additional bending moments and a non-uniform contact pressure distribution at the foundation–soil interface. Therefore, no external eccentric load was directly applied in the present physical model test. Instead, the differential settlement pattern of the prototype foundation was reproduced, allowing the model foundation to undergo the corresponding rotational deformation and naturally reproduce the settlement-induced load eccentricity effect.
Finally, the rear side baffle of the model box was removed to provide operational space, and the shaft excavation was completed in three stages to achieve inclination correction. In the first stage, the excavation holes were arranged at equal distances of 30 cm, and the volume of soil excavated was 1.2 × 10
−4 m
3. After each stage of excavation was completed, the model was left standing for 3 days. Then, the displacement response was monitored in real time using a data acquisition instrument and magnetic displacement dial indicator. In the second stage, the excavation holes were interpolated between the first row of holes to ensure uniform coverage of the disturbance area, and the volume of soil excavated was 1.0 × 10
−4 m
3. In the third stage, the excavation holes were optimized and reinforced in the formed excavation network, and the volume of soil excavated was 0.8 × 10
−4 m
3. During the test, continuous monitoring was carried out until the settlement displacement at each measuring point stabilized (the displacement change of 24 h was less than 0.01 mm). The test process is shown in
Figure 12.
According to similarity theory, the geometric similarity ratio adopted in the physical model test was
CL = 100, and the corresponding volume similarity ratio can be expressed as follows:
To ensure consistency between the physical model test and the prototype-scale numerical simulation, the excavation volumes in the physical model were converted into prototype-scale excavation volumes based on the volume similarity relationship. During the test, the excavation volumes in the first, second, and third stages were 1.2 × 10−4 m3, 1.0 × 10−4 m3, and 0.8 × 10−4 m3, respectively. According to the volume similarity ratio, these values correspond to prototype-scale excavation volumes of 120 m3, 100 m3, and 80 m3, respectively. Therefore, the cumulative excavation volume obtained from the physical model test was converted to 300 m3 at the prototype engineering scale, which is consistent with the excavation volume adopted in the numerical simulation.
4.6. Experiment Results and Analysis
In the physical model test of staged underexcavation of high-rise buildings, the real-time monitoring and recording of the building’s back-dip deformation characteristics during the step-by-step excavation process were mainly achieved using cable displacement sensors and magnetic dial indicators. The overall deformation law of the model was quantitatively characterized by capturing the displacement changes at each measuring point. The results are shown in
Figure 13.
According to the test results, the settlement of the model building after the first stage of soil excavation (1.2 × 10
−4 m
3) was 0.85 mm. The volume of soil extracted in the second excavation stage was adjusted to 1.0 × 10
−4 m
3, and the settlement increased to 1.33 mm, which was 0.48 mm higher than in the first stage. The volume of soil extracted in the third excavation stage was further reduced to 0.8 × 10
−4 m
3, and the settlement was 1.76 mm, which was 0.43 mm higher than in the second stage. The cumulative rectification settlement of the test was 1.76 mm, and the rectification settlement was 176 mm according to the similarity relationship. The actual maximum tilt displacement of the high-rise building was 211.6 mm (
Figure 1), the correction rate was 83.17%, and the residual tilt was 16.83%. The results fell within the allowable limits of engineering control [
24].
In terms of the settlement increment of each stage, the increments of the three stages were 0.85 mm, 0.48 mm, and 0.43 mm, respectively. The increment of the second stage decreased by 43.5% compared to the first stage, and that of the third stage decreased by 10.4% compared to the second stage, showing obvious nonlinear decreasing characteristics. In the initial stage, the tilt potential energy of the building was significant, and the stress concentration of the foundation was high. The first excavation caused the sudden release of stress and generated a strong rectification driving force, so the settlement response was the most sensitive. The inclination of the building gradually decreased with advancing excavation stages. The positive moment was nonlinearly attenuated, the soil damage in the excavation area accumulated, the plastic zone was penetrated, and the effective bearing capacity was significantly reduced. In addition, the building–foundation–soil system progressively approached a new equilibrium state, and the correction increment generated by each subsequent stage was reduced. The process demonstrated the characteristics of fast initial response and progressive deceleration.
Although the rectification increment decreased with successive excavation stages, staged underexcavation enabled a progressive and controllable adjustment of the building–foundation–soil system, thereby avoiding abrupt changes in the rectification response.