1. Introduction
In recent decades, offshore wind power has become a prominent renewable energy source. It has received widespread attention from coastal nations [
1,
2,
3,
4] due to its superior efficiency over onshore wind. However, high construction costs hinder its further development. Submarine cable cost represents a significant portion of these expenses. Like a vascular system, cables in an offshore wind farm collect electricity generated by offshore wind turbines and transmit it to land. Recently, the development of nearshore wind resources has become limited. The focus of offshore wind farms is shifting toward far and deep sea, which offers higher wind energy density and fewer spatial constraints [
5,
6] than nearshore. Further offshore wind farms require longer submarine cables and subsequently more time for cable-laying operations. This leads to higher material and installation costs. Focusing on material cost reduction, Martina et al. [
7] and Jin et al. [
8] minimized the cable length among turbines in offshore wind farms through topological optimization of cable layouts. Yet, as the offshore distance increases, the proportion of the cable used to link turbines decreases. Such cost savings achieved become limited.
Cable-laying operation demands detailed planning and design onshore. The operation generally comprises three phases, i.e., first-end laying, normal laying and terminal laying. The normal laying phase typically lasts the longest. During this phase, cables designed to be laid on the seabed statically are exposed to complex dynamic loads, making them most vulnerable to structural damage or failure. Thus, the uncertainties and complexities of the environmental and loading conditions, as well as structural dynamics, often lead to conservative designs. The disproportionate increase in cable-laying duration drives overall cost escalation, with its cost impact substantially exceeding the incremental costs incurred due to the material cost of longer cables [
9].
For complex and uncertain sea environments, offshore operations like cable laying often adopt conservative decision making strategies in order to secure personnel and equipment safety. DNV [
10] recommends considering parameters like
, wind speed, and current velocity for marine operation design, which can affect system response.
is typically used as the operational limiting criterion, which is adjusted by the
factor to consider forecast uncertainties. This is typically the case for the normal laying of cable. Under this approach, once the latest forecasted
in hours reaches a predefined threshold determined by operation design, the shutdown and standby procedures have to be initiated immediately. In practice, offshore operations taking
as a sole control indicator also simplify the onboard decision-making procedure. However, this further exacerbates operational conservatism.
With respect to such conservatism, some research aimed to expand operational windows by improving environmental forecasting. Natskår et al. [
11] studied weather forecast uncertainty, particularly for
, and applied it to evaluate the reliability of weather forecasts. Wu et al. [
12] developed a hybrid multi-step prediction model for short-term wind-wave forecasting, which helps reduce forecast uncertainty. Other studies focused on improving the operating window analysis accuracy. Wilcken et al. [
13] conducted detailed studies on deriving the
factor, showing that a more reliable forecasting method could expand the operational window. Willem et al. [
14] used Markov Chain Monte Carlo based on hindcast data statistics to generate synthetic time series for engineering simulations. The use of stochastic models for offshore operation simulation enabled more informed operational window calculation. Some studies focused on specific offshore operations. Applied to offshore wind turbine installation, Wilson et al. [
15] proposed a method that assessed operational indicator limits and thresholds based on
and peak period (
). This formed the basis for a procedure to plan and analyze operational windows, while the results confirmed its positive impact on window expansion. Focusing on weather forecast uncertainty, Wu et al. [
16] proposed a response-based correction to DNV’s
-derived
factor. The corrected
factor considers sea state uncertainty more comprehensively. Recently, AI and machine learning applications have been explored. Jonathan et al. [
17] compared various machine learning methods in their effectiveness of evaluating tri-modal wave spectrum parameters (i.e.,
,
and peak angle). The study verified that machine learning could predict ship motion response statistics accurately. Overall, existing research has primarily been focused on improving weather forecasts for more efficient operations.
In the phase of normal laying operations, the cable is deployed from storage tanks onto reels or drums at a controlled speed. It then passes through a chute or tensioner into the water. With different equipment on the installation ship, the primary cable-laying methods include S-lay, J-lay and reel-lay [
18]. This paper investigates the J-lay method as a case study. Although most prior research on cable laying focused on S-lay in nearshore [
19,
20], the trend toward far and deep sea wind farms suggest a promising future for J-lay applications for cable laying. J-lay has been thoroughly investigated by numerous scholars for pipe laying in deep water. Several conclusions drawn from pipe-laying operation studies can be considered valuable to cable-laying operations. Lenci et al. [
21] proposed a static analytical model for J-lay installation based on the classical catenary theory, which provided a reliable theoretical foundation for subsequent research. For pipe J-lay operations, the top effective tension and the dynamic response at the TDP (touch down point) are critical for the pipeline during installation [
22]. The water depth [
23], ocean current [
23], and top angle of the J-lay [
23,
24] could significantly affect the effective tension of the pipe, while the influence of seabed stiffness [
21,
25] could be neglected. Furthermore, considering pipe–ship coupling could improve the prediction of pipeline tension [
26].
Due to the cable’s nonlinear structural behavior, the onshore design consumes significant resources and time. Consequently, when new information (e.g., real-time onboard load conditions, ship RAOs, etc.) becomes available offshore, real-time reassessment of the operational window is not possible within the time-domain nonlinear simulation of cable-laying operations. This limitation, combined with the forecast errors, may lead to either conservative or unsafe operations. As another significant factor, ship motion monitoring and prediction are also essential for many marine operations. Connell et al. [
27] achieved precise ship motion prediction through wave-sensing radar systems during their development of ship motion forecast systems (ESMF), which was also mentioned by Kusters et al. [
28]. Multiple studies by Han et al. [
29,
30,
31,
32] also proposed various methods to enhance the monitoring and prediction accuracy of ship motions. Leveraging these technologies, it becomes possible to accurately determine if ship dynamics are within the safe operational range.
The correlations between ship motion response and cable or flexible pipe states for operational decision making were investigated. Based on the relationship between vertical motion of the chute and cable response in S-lay cable installation, Calavia et al. [
33] proposed a limiting criterion derived from the heave velocity, with a specific focus on discussing the influence of structural response stochastics on the correlation analysis by the fitted equation. Øystein et al. [
34] verified the feasibility of the heave-velocity-based limit in operational decision making for the reel-lay. Moreover, their subsequent research [
35] indicated the significant contribution of introducing ship motion response prediction to reducing uncertainties in offshore operations. However, it was found that the calculated operation-limiting criteria rely on the fitting quality of the correlation analysis, which makes the approach lack sufficient conservatism, thereby creating potential risks in practical engineering applications [
33]. In addition, there has not been a systematic and complete approach on how to select the QoI (Quantity of Interest) of ship motions and determine the value of the limiting criteria to ensure the safety and efficiency.
This study proposes a novel and complete decision-making approach for cable-laying operations. Ship motions and their statistical characteristics (i.e., the QoI) are used to determine the limiting criteria, which are derived directly from the ship’s onsite operational conditions. A reduction factor
is introduced to calculate the final operational limit in the decision criterion establishment procedure proposed in this study, aiming to adjust the fitting results based on actual simulation data. The reduction factor renders the establishment of the decision criterion independent of the chosen fitting methodology, thereby ensuring a high degree of operational safety under the finalized criterion. Consequently, it is possible to update the operational window in real time through computations in the frequency domain. Ship motions can be predicted by the latest weather forecast. The complete algorithm of ship-motion-based limiting criteria establishment is described in
Section 2. Taking the J-lay case as an example, details about the J-lay model used for the algorithm validation are presented in
Section 3.
Section 4 demonstrates the performance of such an algorithm.
Section 5 discussed relevant critical issues observed from the case studies. The robustness of the approach under different operational conditions is also validated.
Section 6 provides conclusions and outlined directions for future work.
6. Conclusions
The present research established a novel algorithm for more efficient and effective cable-laying operations. First, numerical models incorporating different water depths and layback distances were developed by OrcaFlex. DSR and QoIs were identified via dynamic simulations under irregular waves. Then, the criteria were determined by comprehensive correlation analysis, linear fitting and reduction factor analysis for all laying and environmental conditions. The reduction factor was incorporated to ensure operational safety, thereby enhancing the robustness of the criteria. The selection of QoI based on the maximum value of also guarantees the operational efficiency as much as possible. Finally, comparative analysis between ship-motion-based and -based limiting criteria demonstrated an improvement in operational window utilization. Key conclusions are summarized as follows:
During the J-lay operation, the minimum effective tension was identified as the DSR. Negative tension always occurs first with progressive sea state deterioration.
The ship-motion-based limiting criteria prove feasible for J-lay operations, with heading-specific QoIs exhibiting optimal correlation to cable integrity. Heave velocity governs heading, while surge velocity dominates heading.
Within a suitable range, the limiting thresholds increase with layback distance, which enhances operational safety. Notably, shorter layback distances amplify splash zone effects and reduce the effectiveness of ship-motion-based criteria. This suitable range varies with the operating water depth.
By dynamically selecting ship motion indicators across different ship headings, the proposed algorithm extends the operational window by approximately up to 10% compared to conventional -based limits, while improving utilization in hazardous sea states by roughly up to 50%.
To adjust the complex sea conditions during the operation, a limiting criteria matrix including all ship headings, water depths, and layback distances determined by numerical simulations (e.g.,
Table 6) is necessary to establish ship motion-based decision making criteria. Incorporating the reduction factor
enables the establishment of a criteria matrix that expands the operational window while ensuring safety based on actual engineering conditions.
The proposed algorithm has demonstrated significant engineering value for cable-laying operations. However, this initially proposed algorithm involving candidate selection and beta factor screening is worthy of further investigation in several aspects, such as its applicable scope, robustness, and uncertainties. In particular, quantitative uncertainty analysis of the proposed framework in terms of rounding-down of , QoI ranking, and fitted thresholds is interesting and necessary to perform before broad engineering applications. Moreover, the effects of explicitly considering ship forward speed, current, and dynamic positioning system are worth investigation as well. In addition, future work could examine extending this algorithm to other marine operations, such as heavy lift operations.