Vision-Based Deformation Monitoring and Risk Analysis of Adjacent High-Speed Railway Piers Under Full Construction Process of New Bridges
Abstract
1. Introduction
2. Research Methods
2.1. Quantitative Risk Assessment of Pier Deformation
2.1.1. AHP-Based Risk Hierarchy Model
2.1.2. Weight Calculation Using Triangular Fuzzy Numbers
2.1.3. Fuzzy Comprehensive Evaluation
2.2. Principles of Digital Image Correlation (DIC) Monitoring Technology
3. Engineering Application and Analysis
3.1. Project Overview and Full Construction Process
- Pile Foundation Construction (C1): This initial stage involves preparing the site, drilling boreholes for the piles using rotary drilling rigs to minimize vibration, installing the steel reinforcement cages, cleaning the boreholes, and finally, pouring the concrete to form the piles. The drilling process is a primary source of ground disturbance, as the rotation and extraction of soil material can cause localized stress changes and ground vibrations. Furthermore, the hydrostatic pressure from the wet concrete during pouring can induce lateral soil displacement, particularly in the soft alluvial soils at this site. The magnitude of these effects depends on the pile diameter, drilling method, and the soil properties, with larger piles in softer soils generally producing greater disturbance [3].
- Pile Cap and Pier Construction (C2): This stage begins with the excavation of a foundation pit to construct the pile caps connecting the piles. The excavation process is mechanistically significant because it removes the overburden pressure (stress relief), causing the soil at the bottom of the pit to heave and the surrounding soil to move laterally towards the excavation. This lateral ground movement is the primary mechanism by which adjacent pile foundations can be subjected to additional bending moments and horizontal displacements [17,19]. Following excavation, the pile heads are broken and prepared, and the steel reinforcement for the cap is placed. The subsequent large-volume concrete pour for the pile cap, followed by the segmental pouring of the hollow pier shaft up to its full height (exceeding 30 m in this project), constitutes a major and sustained loading event on the foundation soil. This new load induces both immediate and long-term consolidation settlement in the soft clay layers, with the potential for differential settlement that can cause tilting or lateral displacement of adjacent pier foundations. The combination of stress relief from excavation and stress increase from concrete makes this stage the most geotechnically impactful.
- Temporary Pier Construction (C3): To facilitate superstructure installation, temporary steel piers are erected. This involves foundation treatment, erection of the steel structure, and stability verification. While less massive than the permanent piers, their construction still imposes loads and activity near the operational line.
- Assembly Platform Construction (C4): A large platform is constructed at the launching end of the bridge to assemble the steel box girder segments. This involves foundation preparation, frame erection, and load testing, creating a concentrated area of activity and ground loading.
- Incremental Launching of Superstructure (C5): The 185 m long, 1696.8-tonne steel box girder is assembled from 13 segments on the platform and pushed progressively across the piers using a hydraulic, step-by-step (incremental) launching system. An 85 m long lightweight launching nose, fabricated from 6 segments, is attached to the front of the girder to reduce cantilever moments during launch. This is a dynamic, multi-step process involving lifting, welding, pushing, and alignment correction, transferring a complex, cyclically varying load pattern to the piers and foundation soil over an extended period. Unlike the preceding stages, where loads are applied once, the incremental launching process subjects the piers to a series of loading and unloading cycles as the girder advances, which can cause progressive soil deformation and requires sustained monitoring attention.
3.2. Risk Assessment Calculation
3.3. DIC Data Acquisition
3.3.1. System Architecture and Field Deployment
- Data Acquisition Module: The core of this module consisted of eight BJC-V3 industrial-grade DIC instruments (Manufacturer: Shanghai Lingtian Intelligent Technology Co., Ltd., Shanghai, China), each equipped with a 5-megapixel CMOS sensor (2448 × 2048 pixels) and a high-quality optical lens with a focal length selected to optimize the field of view for the monitoring distance at each pier. These instruments integrate the camera, lens, environmental protection housing (IP67 rated), and onboard processing capabilities into a single ruggedized unit designed for long-term outdoor deployment. To capture the 3D deformation of the four adjacent HSR piers (100# to 103#), two DIC units were assigned to each pier in an orthogonal configuration: one positioned facing the front of the pier to measure longitudinal (y-direction) and vertical (z-direction) displacements, and another positioned at the side to measure transverse (x-direction) and vertical (z-direction) displacements. This dual-camera arrangement per pier effectively decomposes the 3D displacement field into two independent 2D measurement planes, providing comprehensive spatial coverage. A total of 16 high-contrast target markers (black-and-white circular coded targets, diameter 200 mm) were installed on the piers—four per pier, at the top and bottom of both the front and side faces—to serve as distinct, high-contrast features for the DIC tracking algorithm (Figure 11). The markers were affixed using high-strength structural adhesive to ensure long-term stability.
- Data Transmission and Processing Module: The digital signals from the eight DIC instruments were transmitted via armored optical fiber cables (to ensure signal integrity and electromagnetic interference resistance in the railway environment) to an industrial-grade network switch located in a field control cabin approximately 100 m from the monitoring site. The data were then aggregated and sent to a central server equipped with a multi-core processor and dedicated GPU for accelerated image correlation processing. The server performed the final correlation calculations, converting the pixel displacements into metric units (millimeters) using pre-calibrated scaling factors derived from a rigorous field calibration procedure. The calibration involved placing targets of known dimensions at the monitoring distance and computing a pixel-to-millimeter conversion factor for each camera, which was periodically verified throughout the monitoring campaign to account for any potential drift.
- Visualization and Warning Platform: A custom software platform was developed to provide an intuitive interface for project engineers and railway safety managers. The platform featured four key functions: (a) real-time display of deformation data overlaid on a 3D BIM model of the bridge, allowing engineers to visualize the spatial distribution of deformations at a glance; (b) a historical data query function with automated plotting capabilities for generating time-history curves and trend analyses; (c) an automated, multi-level early warning system that compared real-time data against the TB 10303-2020 [33] thresholds and triggered color-coded alerts (yellow for Warning, orange for Alarm, red for Control Limit) via both the platform interface and SMS notifications to designated personnel; and (d) a data archiving and reporting module for generating periodic monitoring reports. This integrated platform transformed the raw DIC data into actionable intelligence for real-time safety decision-making.
3.3.2. Monitoring Scheme and Control Standards
3.4. Deformation Analysis and Risk Validation
3.4.1. Monitored Deformation Time-History
3.4.2. Validation of the Risk Assessment Model
3.4.3. Accuracy and Reliability of the DIC System
4. Discussion
5. Conclusions
- A comprehensive risk assessment model, integrating AHP, Triangular Fuzzy Numbers, and Fuzzy Comprehensive Evaluation, was successfully developed and applied. The model quantitatively deconstructed the risks associated with the entire five-stage construction process into a three-level hierarchy with 24 individual risk sources. The model accurately identified the pile cap and pier construction stage (C2) as the phase with the highest potential to induce deformation in the adjacent HSR piers, with a risk weight of 0.311 (31.1% of total risk). This model prediction was subsequently validated by field monitoring data (Spearman’s rank correlation = 1.0). The combined risk weight of the substructure stages (C1 and C2) was 0.578, accounting for nearly 58% of the total project risk.
- A non-contact, real-time monitoring system based on Digital Image Correlation (DIC) technology was effectively deployed using eight industrial-grade instruments monitoring 16 target points across four HSR piers. The system provided continuous, high-frequency (up to 15 min intervals during critical phases), and high-accuracy (sub-millimeter level) 3D deformation data throughout 31 construction stages. The system proved to be a robust and efficient solution for safety assurance in a challenging field environment, operating reliably over the entire multi-month construction period.
- The empirical monitoring data provided a dual validation. Firstly, the DIC system’s accuracy was confirmed through comparison with 45 independent total station measurements, yielding a coefficient of determination (R2) of 0.987, an RMSE of 0.028 mm, and relative errors consistently below 5%. Secondly, the measured deformation patterns, which showed the most significant changes during the C2 phase (accounting for over 50% of the total cumulative deformation), directly validated the predictive capability of the risk assessment model, with a perfect Spearman rank correlation between predicted risk rankings and measured deformation rankings.
- Results of the monitoring campaign demonstrated that the impact of the new bridge construction on the existing HSR piers was successfully managed within safe operational limits. The maximum cumulative deformations in all directions were kept below the ±1.2 mm early warning threshold specified in TB 10303-2020, with the largest recorded values being 0.48 mm (transverse), −0.81 mm (longitudinal), and −0.58 mm (vertical), all on Pier 102#, which was closest to the construction activities. A clear spatial attenuation pattern was observed, with deformations decreasing with increasing distance from the construction site.
- The successful outcome of this project underscores the value of a proactive, risk-informed monitoring strategy that integrates predictive risk assessment with empirical monitoring. The proposed framework provides a validated paradigm for ensuring the safety of similar adjacent-line construction projects worldwide.
Author Contributions
Funding
Institutional Review Board Statement
Data Availability Statement
Conflicts of Interest
References
- Wang, C.; Chen, J.; Li, B.; Chen, N.; Wang, W. Impact of high-speed railway construction on spatial patterns of regional economic development along the route: A case study of the Shanghai-Kunming high-speed railway. Socio-Econ. Plan. Sci. 2023, 87, 101583. [Google Scholar] [CrossRef] [Scilit]
- Chen, L.; Jiang, L.; Kang, X.; Hu, X.; Huang, X.; Xu, L.; Sun, L.; Wang, L.; Tian, Y.; Zhai, C. Seismic response of benchmark high-speed rail (HSR) round-ended rectangular-shaped cross-section solid (RERSCSS) concrete pier based on the shaking table tests. Sci. Rep. 2022, 12, 19611. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Zhang, Q.; Zhang, X.; Zhou, S.; Zhang, K.; Chen, F. Effect and evaluation model of adjacent pile construction on high-speed railway piers in soft soils. Structures 2024, 70, 107687. [Google Scholar] [CrossRef] [Scilit]
- Gong, T.H.; Yao, Y.L. Effect of pier bearing construction on nearby high-speed rail line bridges. Vibroeng. Procedia 2024, 55, 118–124. [Google Scholar] [CrossRef] [Scilit]
- Xu, Q.; Zhu, Y.; Xu, S.; Fan, H.; Wang, D.; Wang, C.; Zhang, M.; Xing, D.; Li, Y. Dynamic response of pile-soil foundation with an adjacent tunnel under the high-speed train loads: A case study. Appl. Sci. 2022, 12, 7170. [Google Scholar] [CrossRef] [Scilit]
- Liyanapathirana, D.S.; Nishanthan, R. Influence of deep excavation induced ground movements on adjacent piles. Tunn. Undergr. Space Technol. 2016, 52, 168–181. [Google Scholar] [CrossRef] [Scilit]
- Huang, J.; Liu, J.; Guo, K.; Wu, C.; Yang, S.; Luo, M.; Lu, Y. Numerical simulation study on the impact of deep foundation pit excavation on adjacent rail transit structures—A case study. Buildings 2024, 14, 1853. [Google Scholar] [CrossRef] [Scilit]
- Qian, W.; Qi, T.; Zhao, Y.; Le, Y.; Yi, H. Deformation characteristics and safety assessment of a high-speed railway induced by undercutting metro tunnel excavation. J. Rock Mech. Geotech. Eng. 2019, 11, 88–98. [Google Scholar] [CrossRef] [Scilit]
- Ouyang, X.H.; Li, Z.Y.; Zheng, Z.E.; Wu, X. Integrated identification and assessment method for construction risks of bridge engineering. Highw. Eng. 2013, 38, 30–33. [Google Scholar]
- Lai, L. Research and design of data security risk assessment model based on fusion of deep learning and analytic hierarchy process (AHP). Procedia Comput. Sci. 2025, 262, 747–756. [Google Scholar] [CrossRef] [Scilit]
- Zhao, J.; Wang, Y.; Li, H.; Fan, J.; Cao, Y.; Li, H.; Yang, Y.; Sun, B. Analysis of construction safety risk management for cold region concrete gravity dams based on fuzzy VIKOR-LEC. Buildings 2025, 15, 1981. [Google Scholar] [CrossRef] [Scilit]
- Han, J.; Lu, G.; Yang, J. The risk assessment of bridge pile foundation construction in karst regions based on the fuzzy analytic hierarchy process. Buildings 2025, 15, 1059. [Google Scholar] [CrossRef] [Scilit]
- Peng, C.; Wang, J.; Chen, H.; Tang, R. Application of Fuzzy-ISM-MICMAC in the risk analysis affecting swivel bridge construction spanning existing railway lines: A case study. Buildings 2023, 14, 52. [Google Scholar] [CrossRef] [Scilit]
- Sutton, M.A.; Orteu, J.J.; Schreier, H.W. Image Correlation for Shape, Motion and Deformation Measurements: Basic Concepts, Theory and Applications; Springer Science Business Media: New York, NY, USA, 2009. [Google Scholar]
- Yang, Y.; Chen, C.; Liu, C.; Huang, L.; Chen, W.; Lin, N.; Cui, J.; Xie, W. Performance of a deep excavation and the influence on adjacent piles: A case history in karst region covered by clay and sand. Undergr. Space 2023, 8, 45–60. [Google Scholar] [CrossRef] [Scilit]
- Zhang, Y.M.; Wang, H.; Mao, J.X.; Wang, F.Q.; Hu, S.T.; Zhao, X.X. Monitoring-based assessment of the construction influence of Benoto pile on adjacent high-speed railway bridge: Case study. J. Perform. Constr. Facil. 2019, 33, 04018096. [Google Scholar] [CrossRef] [Scilit]
- Yang, Y.; Li, J.; Liu, C.; Ma, J.; Zheng, S.; Chen, W. Influence of deep excavation on adjacent bridge piles considering underlying karst cavern: A case history and numerical investigation. Acta Geotech. 2022, 17, 545–562. [Google Scholar] [CrossRef] [Scilit]
- Wu, B.; Ge, C.; Li, P.; Yang, M.; Li, L. Influence of deep foundation pit excavation on adjacent pipelines: A case study in Nanjing, China. Appl. Sci. 2024, 14, 572. [Google Scholar] [CrossRef] [Scilit]
- Yan, X.; Tong, L.; Li, H.; Liu, W.; Xiao, Y.; Wang, W. Effects of the excavation of deep foundation pits on an adjacent double-curved arch bridge. Undergr. Space 2025, 21, 164–177. [Google Scholar] [CrossRef] [Scilit]
- Liu, C.; Jiang, Z.; Yu, H. Safety analysis for bridge pier under nearby road construction and operation. Measurement 2020, 151, 107169. [Google Scholar] [CrossRef] [Scilit]
- Ng, C.W.W.; Wei, J.; Poulos, H.; Liu, H. Effects of multipropped excavation on an adjacent floating pile. J. Geotech. Geoenviron. Eng. 2017, 143, 04017021. [Google Scholar] [CrossRef] [Scilit]
- Sun, L.; Shang, Z.; Xia, Y.; Bhowmick, S.; Nagarajaiah, S. Review of bridge structural health monitoring aided by big data and artificial intelligence: From condition assessment to damage detection. J. Struct. Eng. 2020, 146, 04020073. [Google Scholar] [CrossRef] [Scilit]
- Mousa, M.A.; Yussof, M.M.; Udi, U.J.; Nazri, F.M.; Kamarudin, M.K.; Parke, G.A.R.; Assi, L.N.; Ghahari, S.A. Application of digital image correlation in structural health monitoring of bridge infrastructures: A review. Infrastructures 2021, 6, 176. [Google Scholar] [CrossRef] [Scilit]
- Niezrecki, C.; Baqersad, J.; Sabato, A. Digital image correlation techniques for non-destructive evaluation and structural health monitoring. In Handbook of Advanced Non-Destructive Evaluation; Springer: Cham, Switzerland, 2018; pp. 1–46. [Google Scholar]
- Pan, B.; Qian, K.; Xie, H.; Asundi, A. Two-dimensional digital image correlation for in-plane displacement and strain measurement: A review. Meas. Sci. Technol. 2009, 20, 062001. [Google Scholar] [CrossRef] [Scilit]
- Ye, X.W.; Dong, C.Z.; Liu, T. A review of machine vision-based structural health monitoring: Methodologies and applications. J. Sens. 2016, 2016, 7103039. [Google Scholar] [CrossRef] [Scilit]
- Fang, Q.; Grosman, S.; Pullen, A.; Macorini, L.; Izzuddin, B.A. 3D digital image correlation for field assessment of masonry arch bridges. Constr. Build. Mater. 2025, 494, 143338. [Google Scholar] [CrossRef] [Scilit]
- Nonis, C.; Niezrecki, C.; Yu, T.Y.; Ahmed, S.; Su, C.F.; Schmidt, T. Structural health monitoring of bridges using digital image correlation. In Health Monitoring of Structural and Biological Systems; SPIE: Bellingham, WA, USA, 2013; Volume 8695, p. 869507. [Google Scholar]
- Brownjohn, J.M.W.; De Stefano, A.; Xu, Y.L.; Wenzel, H.; Aktan, A.E. Vibration-based monitoring of civil infrastructure: Challenges and successes. J. Civ. Struct. Health Monit. 2011, 1, 79–95. [Google Scholar] [CrossRef] [Scilit]
- Winkler, J.; Hendy, C. Improved structural health monitoring of London’s Docklands Light Railway bridges using digital image correlation. Struct. Eng. Int. 2017, 27, 435–440. [Google Scholar] [CrossRef] [Scilit]
- Malesa, M.; Szczepanek, D.; Kujawinska, M.; Swiercz, A.; Kolodziejczyk, P. Monitoring of civil engineering structures using digital image correlation technique. EPJ Web Conf. 2010, 6, 31014. [Google Scholar] [CrossRef] [Scilit]
- Taylan, O.; Bafail, A.O.; Abdulaal, R.M.S.; Kabli, M.R. Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Appl. Soft Comput. 2014, 17, 105–116. [Google Scholar] [CrossRef] [Scilit]
- TB 10303-2020; Technical Specification for Construction Safety of Railway Bridge and Culvert. China Railway Publishing House: Beijing, China, 2020.
- Xi, M.; Liu, Y.; Li, M.; Bo, H.; Ma, Q.; Rahman, M.G. Bridge construction risks in complex environments—A hybrid analytic hierarchy process and optimised neural network model. Aust. J. Struct. Eng. 2026, 27, 34–49. [Google Scholar] [CrossRef] [Scilit]
- Tian, Y.; Huang, Y.; Zhang, J.; Shao, J.; Zhan, Y. Noncontact vision-based deformation measurement of a large-span prestressed concrete rigid-frame bridge under object occlusion. Mech. Syst. Signal Process. 2025, 232, 112774. [Google Scholar] [CrossRef] [Scilit]
- Dong, C.Z.; Catbas, F.N. A review of computer vision-based structural health monitoring at local and global levels. Struct. Health Monit. 2021, 20, 692–743. [Google Scholar] [CrossRef] [Scilit]


















| C21 | C22 | C23 | C24 | C25 | |
|---|---|---|---|---|---|
| C21 | (1, 1, 1) | (5, 7, 9) | (3, 5, 7) | (5, 7, 9) | (3, 5, 7) |
| C22 | (1/9, 1/7, 1/5) | (1, 1, 1) | (1/5, 1/3, 1) | (3, 5, 7) | (1/5, 1/3, 1) |
| C23 | (1/7, 1/5, 1/3) | (1, 3, 5) | (1, 1, 1) | (5, 7, 9) | (1/5, 1/3, 1) |
| C24 | (1/9, 1/7, 1/5) | (1/7, 1/5, 1/3) | (1/9, 1/7, 1/5) | (1, 1, 1) | (1/9, 1/7, 1/5) |
| C25 | (1/7, 1/5, 1/3) | (1, 3, 5) | (1, 3, 5) | (5, 7, 9) | (1, 1, 1) |
| First-Level Source (Criterion) | Weight | Second-Level Source (Index) | Weight |
|---|---|---|---|
| C1: Pile Foundation | 0.267 | C11: Site preparation | 0.176 |
| C2: Pile Cap & Pier | 0.311 | C21: Foundation pit excavation | 0.334 |
| C3: Temporary Pier | 0.177 | C31: Foundation treatment | 0.324 |
| C4: Assembly Platform | 0.089 | C41: Foundation treatment | 0.334 |
| C5: Incremental Launching | 0.156 | C51: Girder segment lifting | 0.311 |
| Control Level | Threshold (mm) | Required Action |
|---|---|---|
| Warning Level | ±1.2 | Increase monitoring frequency; notify construction team |
| Alarm Level | ±1.6 | Suspend construction; conduct safety review |
| Control Limit | ±2.0 | Immediately halt all construction; implement emergency measures |
| Pier | Transverse (x) | Longitudinal (y) | Vertical (z) | Distance to Nearest New Pier (m) |
|---|---|---|---|---|
| 100# | −0.22 | 0.05 | −0.11 | ~45 |
| 101# | −0.13 | 0.14 | −0.13 | ~38 |
| 102# | 0.25 | −0.81 | −0.43 | ~32 |
| 103# | 0.48 | 0.42 | −0.58 | ~40 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Jia, X.; Xu, L.; Cui, F.; Wang, X.; Yao, J. Vision-Based Deformation Monitoring and Risk Analysis of Adjacent High-Speed Railway Piers Under Full Construction Process of New Bridges. Buildings 2026, 16, 2393. https://doi.org/10.3390/buildings16122393
Jia X, Xu L, Cui F, Wang X, Yao J. Vision-Based Deformation Monitoring and Risk Analysis of Adjacent High-Speed Railway Piers Under Full Construction Process of New Bridges. Buildings. 2026; 16(12):2393. https://doi.org/10.3390/buildings16122393
Chicago/Turabian StyleJia, Xuena, Liang Xu, Fengkun Cui, Xingyu Wang, and Jin Yao. 2026. "Vision-Based Deformation Monitoring and Risk Analysis of Adjacent High-Speed Railway Piers Under Full Construction Process of New Bridges" Buildings 16, no. 12: 2393. https://doi.org/10.3390/buildings16122393
APA StyleJia, X., Xu, L., Cui, F., Wang, X., & Yao, J. (2026). Vision-Based Deformation Monitoring and Risk Analysis of Adjacent High-Speed Railway Piers Under Full Construction Process of New Bridges. Buildings, 16(12), 2393. https://doi.org/10.3390/buildings16122393
