Next Article in Journal
A CCP-Based Decentralized Optimization Approach for Electricity–Heat Integrated Energy Systems with Buildings
Previous Article in Journal
Typological Transcoding Through LoRA and Diffusion Models: A Methodological Framework for Stylistic Emulation of Eclectic Facades in Krakow
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Study of Carbon Emission Quota for Construction Period of Dredging Projects: Case Studies in Guangzhou, Shenzhen, and Malé

1
School of Civil and Transportation Engineering, Guangdong University of Technology, Guangzhou 510006, China
2
CCCC Guangzhou Dredging Co., Ltd., Guangzhou 518000, China
3
School of Future Transportation, Guangzhou Maritime University, Guangzhou 510725, China
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(13), 2293; https://doi.org/10.3390/buildings15132293
Submission received: 29 May 2025 / Revised: 16 June 2025 / Accepted: 27 June 2025 / Published: 29 June 2025
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

This paper develops a model to calculate carbon emissions during the construction period of dredging projects. Carbon emission quotas for various types of dredgers and auxiliary vessels in different construction conditions and geotechnical soil types during the dredging project’s construction period are established, as well as the power consumption quota for management activities. Taking the construction of the main project of the cross-river channel from Shenzhen to Zhongshan (S09)’s foundation trench excavation and channel dredging, the Thilafushi Island reclamation project in Malé, and the second phase of the southern section of the Guangzhou Port Area channel maintenance project (2022–2023) as case studies, the validity of the quotas is verified. During the construction period, under the same dredging soil quality and the same working condition level, the carbon emissions of different types of dredgers are different. Conversely, under different dredging soil qualities and different working condition levels, the carbon emissions for the same dredger or auxiliary vessel are different. The carbon emissions of each dredger or auxiliary vessel increase with the increase in the ship’s specifications. The carbon emissions of dredging projects are huge, with direct carbon emissions accounting for 97%, and indirect carbon emissions from equipment deployment and management activities accounting for 3%, among which the carbon emissions from electricity consumption in management activities account for only 0.3%.

1. Introduction

In 2020, China proposed the “3060” dual-carbon target, aiming to achieve a “carbon peak” by 2030 and “carbon neutrality” by 2060. The construction engineering field has consistently been a significant source of carbon emissions. The 2022 China Building Energy Consumption and Carbon Emission Research Report disclosed that the total carbon emissions of the whole process of the construction engineering field were 5.08 billion tons, accounting for 50.9% of the national carbon emissions in 2020 (China Association of Building Energy Efficiency (2023)) [1].
In dredging projects, a large number of dredging vessels burn diesel, liquefied natural gas, or other fuels to generate construction power, producing substantial carbon dioxide emissions that have significant environmental and societal impacts.
In recent years, numerous studies have focused on carbon emissions during the construction period of engineering projects, primarily concentrating on building construction, highway engineering, municipal engineering, and urban infrastructure development. These studies have provided valuable theoretical foundations and practical guidelines for carbon emission estimation, control, and reduction. Various research efforts have examined carbon emission measurement methods, construction stage emissions, and full life cycle carbon emission calculations. Moreover, some studies have addressed the establishment of carbon emission quotas for construction projects, tunnels, and highway projects.
For example, a random forest-based predictive method was applied to estimate construction stage carbon emissions, using data from 38 buildings in the Pearl River Delta region of China as the initial training set to explore the relationship between construction stage carbon emissions and design parameters (Fang et al., 2021) [2]. The study of cradle-to-site carbon emissions through the assessment of prefabricated rebar cages (PRC) for high-rise buildings in China found that CO2 emissions increased by 3.3 times during the transportation stage, while decreasing by 44.7% during on-site construction (Jiang et al., 2018) [3]. The empirical estimation method used to calculate CO2 emissions in three stages of four highway projects showed that over 80% of the CO2 emissions were generated from raw material production, while on-site construction and material transportation accounted for 10% and 3%, respectively. The total CO2 emissions from road, bridge, and tunnel constructions were 5229 kg/m, 35,547 kg/m, and 42,302 kg/m, respectively (Wang et al., 2015) [4].
The carbon emissions from 27 prefabricated buildings showed that the embodied and operational carbon emissions of these cases varied significantly from 105 to 864 kg CO2/m2 and from 11 to 76 kg CO2/m2/yr, respectively, with 15.6% of embodied and 3.2% of operational carbon reductions achieved through prefabrication on average (Teng et al., 2018) [5]. Li and Chen quantitatively calculated the carbon emissions of each building’s sub-project during the construction period of a residential community, finding that high-rise buildings and villas had the highest unit carbon emissions of 54.51 kg/m2, accounting for 84% of the carbon dioxide emissions produced during construction, while the unit carbon emissions for the entire residential community were approximately 54.18 kg/m2 (Li et al., 2017) [6].
The whole life cycle method was used to establish a parametric model to evaluate carbon emissions at each stage, concluding that the usage stage was the main contributor to carbon emissions (Bonamente et al., 2015) [7]. Using a process-based method to quantitatively calculate emissions generated by material consumption, transportation, and equipment usage, the study found that carbon emissions from materials, equipment, and transportation accounted for 67%, 19%, and 14% of total building emissions, respectively (Sandanayake et al., 2016) [8]. The energy performance and environmental impact of prefabricated building modules were assessed using the life cycle assessment method. Through dynamic simulation, it was found that the material production stage accounted for 72% of emissions, while the use stage accounted for 23% (Tumminia et al., 2018) [9].
Kim and Eom pointed out that carbon reduction is one of the most pressing challenges in the shipping industry. The International Maritime Organization (IMO) has strengthened carbon emission regulations, aiming to reduce emissions to 70% of 2008 levels by 2050. However, 75% of the existing fleet fails to meet these regulations. Their study proposed a novel navigation operation method to reduce carbon emissions and extend the service life of ships without modifying the propulsion system, thus complying with carbon regulations (Kim et al., 2023) [10].
Castellano et al. designed a carbon emission estimation program for the operational phase of buildings and derived a carbon emission calculation formula to simplify assessments across various cases (Castellano et al., 2015) [11]. Jun et al. proposed a BIM-based method for evaluating the total carbon emissions of buildings, improving calculation efficiency and compatibility while minimizing the impact of design changes on carbon emissions during material production, thus enabling emission predictions prior to construction (Jun et al., 2016) [12]. Cho and Chae quantified carbon emissions across the four stages of a building’s lifecycle—production, construction, operation, and demolition—and conducted comparative analyses between conventional and low-carbon buildings. Their study revealed that low-carbon buildings reduce CO2 emissions per unit area by 25% compared to conventional buildings (Cho et al., 2016) [13].
Zhang Chaohui et al. studied 39 major ports in China, using a super-efficiency SBM model to measure carbon emissions and applying a generalized difference-in-differences method to examine the impact of smart port policies on carbon emission efficiency. They found that although there is an extensive literature on carbon emissions, research specifically addressing carbon emission efficiency remains limited. The study further explored how smart port policies affect carbon emission efficiency (Zhang et al., 2016) [8].
Based on PAS2050 specifications and existing construction project consumption quotas and work shift cost quotas, some studies have developed methods to convert budget quotas into carbon emission quotas and calculate total carbon emissions (Wang et al., 2023; Zhang et al., 2024) [14,15]. Li studied the calculation of carbon emissions in the construction stage, compiled detailed carbon emission quotas in accordance with top-down decomposition principles, and summarized total carbon emission values (Li et al., 2023) [16]. Based on carbon source consumption measurements from a large-diameter shield construction project in Hengqin New District, Zhuhai, carbon emissions during construction were calculated using a carbon emission model, and a carbon emission quota for shield construction was developed (Chen, 2017) [17].
However, research focusing on carbon emission measurement methods and quotas during the construction period of dredging projects remains limited. Further theoretical and practical studies are required to better evaluate and manage carbon emissions in dredging construction activities. Furthermore, the study aligns with the global climate targets under the Paris Agreement, the International Maritime Organization (IMO) decarbonization goals, and the national climate commitments of both China and the Maldives.
Based on the concepts and theories of dredging projects and carbon emission measurement, this paper combines quota theory to construct a carbon emission measurement method and quota system for dredging projects during the construction period. The proposed method provides both a theoretical reference and practical calculation tools for carbon emission management in dredging projects, offering a scientific basis for port and marine ecological environmental protection, and promoting the sustainable development of port and waterway engineering projects.
The main contents of this paper include the following:
(1)
The establishment of a carbon emission calculation model during the construction period of dredging projects;
(2)
The compilation of carbon emission estimation quotas during the construction period of dredging projects; and
(3)
Case analysis and validation of quota effectiveness.

2. Calculation Model

2.1. Carbon Emission Factors for Dredging Projects

2.1.1. Fuel Energy

The types of fuel consumed by different types of dredgers and auxiliary equipment during the construction period of dredging projects are mainly oil, diesel, and liquefied natural gas, with carbon emission factors of 3174.40 kg CO2/t, 3099.76 kg CO2/t, and 3182.85 kg CO2/t, respectively (China’s Ministry of Housing and Urban–Rural Development (2019) [18]; Standardization Administration of China (2008)) [19].

2.1.2. Electricity

The average emission factor for the national grid, published in the Ministry of Ecology and Environment’s [20] Notice on the Work Related to the Management of Greenhouse Gas Emission Reporting by Enterprises in the Power Generation Sector (2023–2025) (Ministry of Ecology and Environment (2022)) [21] and the Guidelines on the Methodology and Reporting of Greenhouse Gas Emissions by Enterprises for Power Generation Facilities (Revised Version 2022) (Ministry of Ecology and Environment (2022)) [21], is 0.5810 t CO2/MWh.

2.2. Model for Direct Carbon Emissions

2.2.1. Model for Dredgers

Dredging vessels, such as suction hopper dredgers, cutter suction dredgers, grabs, and buckets, burn fuel energy during on-site construction, normal operation, shutdown standby, repair and maintenance, and replenishment, among other activities.
E d = i = 1 n j = 1 m ( A i × N d , i , j × E F d , j )
where Ed represents the carbon emissions from dredger energy consumption; Ai represents the quantity of work for the i element of the project; Nd,i,j represents the consumption of the j dredger for the i element of the project in a fixed unit (ship) shift; EFd,j represents the carbon emission factor for the energy consumption of the j dredger; i represents the serial number of the item content; j represents the dredger serial number.

2.2.2. Model for Auxiliary Equipment

Auxiliary equipment includes mud barges, excavators, anchor boats, tug boats, transportation vessels, and supply vessels, among others.
E e = i = 1 n j = 1 m ( A i × N e , i , j × E F e , j )
where Ee represents the carbon emissions from energy consumption of auxiliary equipment; Ai represents the quantity of work for the i element of the project; Ne,i,j represents the rated unit (ship) shift consumption of the j unit/ship of the auxiliary equipment put in place for the i element of work; EFe,j represents the carbon emission factor for the energy consumption of the auxiliary equipment; i represents the serial number of the item’s content; j represents the auxiliary equipment serial number.

2.3. Model for Indirect Carbon Emissions

2.3.1. Model for Equipment

Carbon emissions from the mobilization of ships.
E d t = j = 1 m ( D d , j × F d , j × E d , j )
where Edt represents the carbon emissions from energy consumption of ship mobilization; Dd,j represents the transfer distance of the j ship; Fd,j represents the energy consumption per unit distance during the transfer of the j ship; Ed,j represents the carbon emission factor for the energy consumption during the transfer of the j ship.

2.3.2. Model for Management Activities

This includes the carbon emissions generated by construction workers’ lodging, catering and cooking, heating and cooling, lighting, use of electrical appliances, and other activities. This paper examines the indirect carbon emission accounting based on the purchased electricity consumed by the project manager’s office (construction camp) and temporary facilities.
E m = ( E L × E e l )
where Em represents carbon emissions from management activities during the construction period. EL represents the total electricity consumption of the project manager’s office (construction camp) and temporary facilities. Eel represents the carbon emission factor for electricity.

3. Carbon Emission Measurement Quota

3.1. The Content of the Quota

The quota’s content includes quota descriptions, the carbon emission quotas for suction hopper dredgers, cutter suction dredgers, grab dredgers, bucket dredgers, and mud blowers, as well as quotas for the mobilization, preparation and finishing of dredgers, construction ship carbon emission factors, adjustment values for construction ship carbon emission factors, and quotas for management activities, among others.

3.1.1. Description of the Quota

The quota consists of two parts: a general description and descriptions of each chapter. The general description, as the first part, is positioned at the top of the quota and mainly includes the basis of compilation, scope of application, measurement boundaries, and related aspects. The chapter descriptions precede the list of items for each type of ship quota, providing explanations of measurement and applicable conditions, calculation bases, working condition coefficients, and unit consumption bases for each chapter.

3.1.2. Content of the Carbon Emission Quota

The quota includes the quota number, vessel type, specifications, dredging rock and soil grades, working conditions, quantities, carbon emission benchmarks, benchmarks for over-excavation depth, extra distances, extra ship tons, bow blowing, bow spraying, mobilization modes, mobilization distances, and preparation and finishing. The contents of the items are shown in Table 1.

3.1.3. Appendix to the Quota

The appendix of the quota includes the carbon emission factors and their adjusted values for construction vessels, as shown in Table 2.

3.2. Compilation of Direct Carbon Emission Quota

3.2.1. Quota for Dredgers

The 5000 m3 suction hopper dredger is used as an example to illustrate the process of compiling direct carbon emission quotas for dredgers.
Step 1: according to the Budget Quota for Dredging Projects (budget quota for dredging project (2021)) [22], the work shift consumption quota per ten thousand cubic meters of working quantity for the 5000 m3 suction hopper dredger is shown in Table 3.
Step 2: according to the Cost Quota of Ship Work-Shift for Dredging Projects (cost quota of ship work shift for dredging project (2019)) [23], the diesel fuel consumption for one work-shift for the 5000 m3 suction hopper dredger is 6547 kg. Thus, diesel fuel consumption per ten thousand cubic meters of working quantity can be calculated, and the results are shown in Table 4.
Step 3: combined with the fuel energy carbon emission factor, we can establish the carbon emission quota data. The results of the construction carbon emission quota for the 5000 m3 suction hopper dredger are shown in Table 5 and Table 6. Under level 4 working conditions, the 5000 m3 suction hopper dredger completes each ten thousand cubic meters of working quantity, and the carbon emissions from type 1 to type 10 geotechnical soil result in a 2.17 times change in baseline value. Type 1 (organic soil, peat, and silt) has the least carbon emissions, type 6 (loose sandy soil) comes second, and type 10 (gravelly soil) has the most.
Step 4: According to the above steps 1 to 3, the carbon emission quota for dredger preparation and finishing can be calculated using the shift quota, fuel consumption quota, and fuel consumption carbon emission factor. The results are shown in Table 7.

3.2.2. Quota for Auxiliary Equipment

The auxiliary equipment invested in dredging construction mainly includes mud barges for transporting dredged materials, tugboats, anchor boats, and traffic vessels for assisting the dredging vessels in construction. The activities of these vessels cannot be quantified by the volume of dredging works, and therefore, it is not possible to compile carbon emission quotas corresponding to the working conditions, rock and soil types, and quantity of work, as in the case of dredging vessels. The carbon emission quotas for auxiliary equipment, based on corresponding shifts and vessel specifications (such as power, capacity, towing force, etc.), can only be measured by fuel consumption. The carbon emission quota of auxiliary equipment, based on corresponding vessel specifications (such as power, cabin capacity, towing capacity, etc.), can only be calculated by fuel consumption. According to the method of compiling carbon emission quotas for dredger construction, we can determine the carbon emission quotas for tugboats, self-propelled mud barges, and anchor boats in terms of work shifts and non-work shifts. Taking the tugboat as an example, the results are shown in Table 8.

3.2.3. The Effect of Changes in Working Conditions on Quota

Based on the change in fuel consumption for each type of ship under varying working conditions, the adjusted carbon emission factor is calculated, using the suction hopper dredger as an example. The results of the quota calculation are shown in Table 9.

3.3. Compilation of Indirect Carbon Emission Quota

3.3.1. Quota for the Mobilization of Construction Equipment

Referring to the methods in the above chapters, quotas for the mobilization of construction equipment can be prepared based on work shift and non-work shift quotas, fuel consumption quotas, and fuel consumption emission factors during the transfer period. Taking the suction hopper dredgers as an example, the calculation results of the quota are shown in Table 10.

3.3.2. Managing Carbon Emission Quota for Management Activities

The carbon emissions from 100 MWh of electricity consumed are 58,100 kg CO2 (Table 11).

4. Case Studies and Quota Validation

In order to validate the applicability and accuracy of the proposed carbon emission quota system, three representative dredging projects with different scales, construction environments, soil types, and equipment configurations were selected as case studies. These include the following:
(1)
The Shenzhen–Zhongshan Cross-River Passage main project (China), representing a large-scale offshore channel dredging project;
(2)
The Thilafushi Island reclamation project in Malé (Maldives), representing a nearshore land reclamation dredging project; and
(3)
The second phase of the southern section of the Guangzhou Port maintenance project (China), representing a routine inland port channel maintenance dredging operation.
These cases comprehensively reflect diverse dredging construction scenarios, which help to verify the applicability and robustness of the proposed quota system across different engineering conditions.

4.1. Projects Overview

Case 1: Shenzhen to Zhongshan Cross-River Passage main project construction (S09). The total mileage of trench excavation and channel dredging is 28 km, with a total dredging volume of about 40 million m3. The construction period is 64 months, from July 2018 to June 2023.
Case 2: Thilafushi Island reclamation in Malé, with about 5.12 million m3 of dredging and reclamation, and a construction period of seven months from September 2023 to March 2024.
Case 3: The second phase of the southern section of the Guangzhou Port Sea Channel maintenance project (2022–2023). The total mileage of the maintenance channel is about 87 km, with a total dredging volume of about 2.34 million m3. The construction period is three months, from December 2023 to February 2024.

4.2. Data Sources

The equipment entry and exit records include the name, specification, time, etc. Records of refueling include the fuel type, quantity, date, place, etc. Electricity consumption statistics for the project camp and temporary dock include the quantity and time period, etc. Statistics of construction ships are shown in Table 12.

4.3. Calculation and Verification Analysis of Each Case

4.3.1. Shenzhen Project

(1)
Calculation results of carbon emissions during construction period.
The total carbon emissions during the construction phase of the Shenzhen–Zhongshan Cross-River Passage main project (S09) amounted to 440,500 tons of CO2. Of this, direct carbon dioxide emissions accounted for 433,300 tons (98.37%), while indirect emissions contributed 7200 tons (1.63%). Based on the emission source analysis, dredging vessels were the primary contributors, releasing 278,500 tons of CO2 (63.21%). Auxiliary equipment accounted for 160,800 tons (36.50%), whereas management activities contributed a minor 1300 tons (0.29%) (Table 13 and Figure 1).
Based on the total dredging volume of 35.97 million cubic meters, the average carbon dioxide emissions per 10,000 cubic meters of dredged material amounted to 122.47 tons, comprising 120.47 tons of direct emissions and 2.00 tons of indirect emissions. Given the 60-month construction period from July 2018 to June 2023, the average monthly carbon dioxide emissions were 7342.05 tons, including 7222.29 tons from direct sources and 119.76 tons from indirect sources.
(2)
Actual emission verification.
Since the project’s non-owned ships operate under a non-fuel leasing model, only the carbon emissions from owned vessels—including six rake suction dredgers, one cutter suction dredger, one tugboat, and two grab dredgers—were calculated and verified based on fuel consumption data and direct carbon emissions estimated using emission quotas. The results are presented in Table 14. It was found that the direct carbon emissions calculated using the quota method were 0.75% higher than those derived from actual fuel consumption. Specifically, the emission estimates were 0.21% higher for the suction hopper dredger, 1.68% higher for the cutter suction dredger, 4.76% higher for the grab dredger, and 0.80% higher for the tugboat.

4.3.2. Malé Project

(1)
Calculation results of carbon emissions during construction period.
The total carbon emissions during the construction period of the Thilafushi Island reclamation project in Malé amounted to 28,600 tons of CO2. Of this, direct carbon dioxide emissions accounted for 28,200 tons (98.61%), while indirect emissions contributed 400 tons (1.39%). Based on the emission source analysis, dredging vessels were the primary contributors, releasing 27,800 tons of CO2 (97.31%). Auxiliary equipment accounted for 752 tons (2.63%), while management activities generated 17 tons (0.06%) (Table 15 and Figure 2).
Based on the total dredging volume of 5.12 million cubic meters, the average carbon dioxide emissions per 10,000 cubic meters of dredged material amounted to 58.87 tons, comprising 55.10 tons of direct emissions and 0.78 tons of indirect emissions. Over the 7-month construction period from September 2023 to March 2024, the average monthly carbon dioxide emissions were 4086.79 tons, including 4029.85 tons from direct sources and 56.94 tons from indirect sources.
(2)
Actual emission verification.
It was found that the direct carbon emissions calculated using the quota method were 4.90% higher than those derived from actual fuel consumption in this project. Specifically, the suction hopper dredger exhibited a 4.88% higher emission estimate, while the anchor boat had a 5.74% higher estimate (Table 16).

4.3.3. Guangzhou Project

(1)
Calculation results of carbon emissions during construction period.
It was calculated that the total carbon emissions during the construction period of the second phase of the maintenance project for the southern section of the Guangzhou Port Sea Channel (2022–2023) amounted to 10,200 tons of CO2. Of these, direct carbon dioxide emissions accounted for 9600 tons (94.09%), while indirect emissions contributed 600 tons (5.91%). Based on the emission source analysis, dredging vessels were the primary contributors, releasing 9400 tons of CO2 (92.71%). Auxiliary equipment accounted for 700 tons (7.11%), while management activities generated 19 tons (0.19%) (Table 17 and Figure 3).
The total dredging volume for this project is 2.3431 million cubic meters. Accordingly, the average carbon dioxide emissions per 10,000 cubic meters of dredged material amounted to 41.55 tons, comprising 38.98 tons of direct emissions and 2.57 tons of indirect emissions. Over the construction period from December 2023 to February 2024, the average monthly carbon dioxide emissions were 3245.39 tons, including 3044.71 tons from direct sources and 200.68 tons from indirect sources.
(2)
Actual emission verification.
It was found that the direct carbon emissions calculated using the quota method were 3.65% higher than those derived from actual fuel consumption in this project. Specifically, the rake suction dredger exhibited a 3.73% higher emission estimate, while the tugboat had a 0.80% higher estimate (Table 18).

4.4. The Result Calculated by Quotas

Based on the carbon emission quotas described in the previous chapter, the carbon emissions for the three dredging projects were calculated. The results are shown in Table 19 and Table 20 and Figure 4, with a total emission of 47.89 million tons, of which 47.07 million tons are directly emitted, accounting for 98.29%, and 0.82 million tons are indirectly emitted, accounting for 1.71%. In terms of carbon emissions per 10,000 cubic meters of construction volume, the Case 1 project has the highest emissions, followed by the Case 2 project, and the Case 3 project has the lowest emissions. The monthly average carbon emissions data also show the same contrast. Carbon emissions from dredgers dominated the sources (63–97%, averaging 65.84%), followed by auxiliary equipment (3–37%, averaging 33.85%), while management activities contributed the least (0.06–0.3%, averaging 0.27%).

4.5. Validation of Actual Emissions

Since the non-owned vessels in the three cases of this paper adopt a non-fuel chartering mode, the validation of the carbon emissions for the owned vessels is verified only through fuel consumption to validate the direct carbon emissions data from the quota measurement, and the results are shown in Table 21 The difference between the direct emissions calculated by the quota and those calculated from fuel consumption in the three project cases ranged from −0.75% to −3.65%, with the direct emissions measured by the quota being slightly higher than those released by the actual fuel consumption, with an average of 1.32%. The validation data fully demonstrate that the quota data compiled in this study are reliable and practically significant.

5. Conclusions

This paper formulated the carbon emission quota during the construction period of dredging projects and verified its effectiveness using three different project cases. The principal findings of this study are summarized as follows:
(1)
The results of this study show that different types of dredging vessels emit varying amounts of carbon dioxide during the construction period even when operating under the same dredging soil types and working conditions.
(2)
The carbon dioxide emissions of the same dredging vessel exhibit significant variations when operating across different geotechnical soil types and working conditions.
(3)
The carbon emission quotas for self-propelled dredgers during the construction period are significantly higher than those for non-self-propelled dredgers. For self-propelled dredgers, carbon emissions increase with larger cabin capacities, while for towing vessels, emissions increase with the power rating of the tugboats.
(4)
Dredging construction activities generate substantial carbon emissions, which are predominantly direct emissions resulting from fuel combustion during production activities. Unlike housing and municipal engineering projects where material production and transportation dominate carbon emissions, direct emissions account for approximately 97% of total emissions during dredging construction, while indirect emissions from equipment deployment and management activities account for about 3%. The emissions from electricity consumption during management activities represent only a minor portion, approximately 0.3%.
(5)
The carbon emissions during the construction period of dredging projects primarily originate from fuel consumption of construction activities. Construction enterprises should strengthen the planning, management, and control of vessel operations during the construction phase. Prior to construction, comprehensive analysis of project conditions and soil characteristics should be conducted to facilitate reasonable equipment configuration and selection. Construction schemes and equipment combinations with optimal schedules, lower costs, and minimized carbon emissions should be adopted based on multi-scheme comparisons. During construction, vessel idling and standby periods should be strictly controlled, vessel utilization should be maximized, and overall operational efficiency should be improved to reduce unnecessary fuel consumption and associated emissions.
(6)
Based on the established quota system and analysis results, several practical emission reduction strategies are further proposed to guide carbon management in dredging projects. These include (i) optimizing equipment configuration and scheduling based on project-specific geotechnical and operational conditions; (ii) adopting advanced energy-efficient dredging equipment and low-emission engines to enhance fuel utilization; (iii) minimizing over-excavation and unnecessary dredging distances through strict control of workloads; and (iv) implementing intelligent construction management systems for real-time monitoring and dynamic scheduling of vessel operations. These measures can provide valuable technical references for achieving both effective project execution and carbon reduction targets.
It should be noted that the proposed quota system focuses on construction-phase emissions based on standard operational scenarios. Variations in fuel quality, equipment efficiency, unforeseen delays, or site-specific conditions may introduce deviations from the calculated quotas. In addition, upstream emissions from equipment manufacturing and dredged material disposal are beyond the current model scope and warrant future investigation.

Author Contributions

Writing—original draft preparation, conceptualization, S.L.; methodology, resources, writing—review and editing, W.C.; funding acquisition, software, visualization, supervision, L.L.; investigation, project administration, F.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in the study are included in the article, further inquiries can be directed to the corresponding author.

Conflicts of Interest

Author Siming Liang was employed by the company CCCC Guangzhou Dredging Co., Ltd. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. China Association of Building Energy Efficiency. 2022 Research Report of China on Buildings Energy Consumption and Carbon Emissions; China Association of Building Energy Efficiency: Beijing, China, 2023. [Google Scholar]
  2. Fang, Y.; Lu, X.; Li, H. A random forest-based model for the prediction of construction-stage carbon emissions at the early design stag. J. Clean. Prod. 2021, 328, 12965. [Google Scholar] [CrossRef]
  3. Jiang, B.; Li, H.; Dong, L.; Wang, Y.; Tao, Y. Cradle-to-site carbon emissions assessment of prefabricated rebar cages for high-rise buildings in China. J. Sustain. 2018, 11, 42. [Google Scholar] [CrossRef]
  4. Wang, X.; Duan, Z.; Wu, L.; Yang, L. Estimation of carbon dioxide emission in highway construction: A case study in southwest region of China. J. Clean. Prod. 2015, 103, 705–714. [Google Scholar] [CrossRef]
  5. Teng, Y.; Li, K.; Pan, W. Reducing building life cycle carbon emissions through prefabrication: Evidence from and gaps in empirical studies. J. Build. Environ. 2018, 132, 125–136. [Google Scholar] [CrossRef]
  6. Li, L.; Chen, K. Quantitative assessment of carbon dioxide emissions in construction projects: A case study in Shenzhen. J. Clean. Prod. 2017, 141, 394–408. [Google Scholar] [CrossRef]
  7. Bonamente, E.; Cotana, F. Carbon and energy footprints of prefabricated industrial buildings: A systematic life cycle assessment analysis. Energies 2015, 8, 12685–12701. [Google Scholar] [CrossRef]
  8. Sandanayake, M.; Zhang, G.; Setunge, S. Environmental emissions at foundation construction stage of buildings–Two case studies. J. Build. Environ. 2016, 95, 189–198. [Google Scholar] [CrossRef]
  9. Tumminia, G.; Guarino, F.; Longo, S.; Marco, F.; Maurizio, C.; Vincenzo, A. Life cycle energy performances and environmental impacts of a prefabricated building module. J. Renew. Sustain. Energy Rev. 2018, 92, 272–283. [Google Scholar] [CrossRef]
  10. Kim, S.W.; Eom, J.O. Ship carbon intensity indicator assessment via just-in-time arrival algorithm based on real-time data: Case study of Pusan New International Port. Sustainability 2023, 15, 13875. [Google Scholar] [CrossRef]
  11. Castellano, J.; Castellano, D.; Ribera, A.; Ciurana, J. Developing a simplified methodology to calculate CO2/m2 emissions per year in the use phase of newly-built, single-family houses. Energy Build. 2015, 109, 90–107. [Google Scholar] [CrossRef]
  12. Jun, H.; Lim, N.; Kim, M. BIM-based carbon dioxide emission quantity assessment method in Korea. J. Asian Archit. Build. Eng. 2015, 14, 569–576. [Google Scholar] [CrossRef]
  13. Cho, S.H.; Chae, C.U. A study on life cycle CO2 emissions of low-carbon buildings in South Korea. Sustainability 2016, 8, 579. [Google Scholar] [CrossRef]
  14. Wang, K.; Gu, L.; Lu, C.; Cao, Y.; Wang, Y.; Ren, J. Reconstruction of the carbon emission allowance measurement system of ‘pricing method’. J. Eng. Manag. 2023, 37, 42–47. [Google Scholar]
  15. Zhang, C.; Yang, Y.; Wang, N. Port governance and sustainable development: The impact of port smartization on port carbon emission efficiency. Ocean Coast. Manag. 2024, 259, 107485. [Google Scholar] [CrossRef]
  16. Li, Z.; Huang, H.; Zhang, J. Research on carbon emission measurement and quota in building construction stage. J. Brick Tile 2023, 8, 99–101. [Google Scholar]
  17. Chen, J. An example of carbon emission quota preparation for shield construction. J. Constr. Technol. Dev. 2017, 44, 142–143. [Google Scholar]
  18. China Ministry of Housing and Urban-Rural Development. Building Carbon Emission Calculation Standard; S. China Construction Industry Press: Beijing, China, 2019. [Google Scholar]
  19. Standardization Administration of China. General Rules for Calculation of Comprehensive Energy Consumption; S. China Standard Press: Beijing, China, 2008. [Google Scholar]
  20. China Ministry of Ecology and Environment. Greenhouse Gas Emission Accounting Methodology and Reporting Guidelines for Enterprises Power Generation Facilities (2022 Revision); R. Ministry of Ecology and Environment: Beijing, China, 2022. [Google Scholar]
  21. China Ministry of Ecology and Environment. Notice on the Work Related to the Management of Greenhouse Gas Emission Reporting for Enterprises in the Power Generation Sector in 2023-2025; R. Ministry of Ecology and Environment: Beijing, China, 2022. [Google Scholar]
  22. China Water Transportation Engineering Cost Quota Center. Budget Quota for Dredging Project; S. People’s Transportation Press: Beijing, China, 2019. [Google Scholar]
  23. China’s Ministry of Transport. Cost Quota of Ship Work-Shift for Dredging Project; S. People’s Transportation Press: Beijing, China, 2019. [Google Scholar]
Figure 1. Column chart of carbon emission during construction period of the Shenzhen Project (unit: 10,000 tons of CO2).
Figure 1. Column chart of carbon emission during construction period of the Shenzhen Project (unit: 10,000 tons of CO2).
Buildings 15 02293 g001
Figure 2. Column chart of carbon emission during construction period of case 2 (unit: 10,000 tons of CO2).
Figure 2. Column chart of carbon emission during construction period of case 2 (unit: 10,000 tons of CO2).
Buildings 15 02293 g002
Figure 3. Column chart of carbon emission during construction period of case 3 (unit: 10,000 tons of CO2).
Figure 3. Column chart of carbon emission during construction period of case 3 (unit: 10,000 tons of CO2).
Buildings 15 02293 g003
Figure 4. Percentage accumulation chart of carbon emissions during the construction period (unit: 10,000 tons of CO2).
Figure 4. Percentage accumulation chart of carbon emissions during the construction period (unit: 10,000 tons of CO2).
Buildings 15 02293 g004
Table 1. Contents of quota items.
Table 1. Contents of quota items.
SN.Quota Project Table NameQuota NumberShip Type and SpecificationDredged Soil and Rock ClassificationWorking ConditionQuota Project QuantityCarbon Emission BenchmarkOver-Excavation Depth BenchmarkExcess Haul Distance BenchmarkAdditional Turning Head BenchmarkBow Blowing BenchmarkBow Jet BenchmarkDeployment MethodDeployment MileageStartup Deployment and Completion Integration
1Carbon Emission Quota for Trailing Suction Hopper Dredger (TSHD) Construction
2Carbon Emission Quota for Cutter Suction Dredger (CSD) Construction
3Carbon Emission Quota for Clamshell Dredger Construction
4Carbon Emission Quota for Bucket Dredger Construction
5Carbon Emission Quota for Blow Dredger Construction
6Carbon Emission Quota for Dredger Deployment
7Carbon Emission Quota for Dredger Startup Deployment and Completion Integration
8Carbon Emission Quota for Shipbuilding
9Carbon Emission Quota for Management Activities
Table 2. Content of appendix.
Table 2. Content of appendix.
SN.Appendix Table NameShip Type and SpecificationMachine ShiftWorking ConditionCarbon Emission Factor per Machine ShiftCarbon Emission Factor for Idle Machine ShiftWorking Condition Elevation AdjustmentCarbon Emission Factor Adjustment Value
1Carbon Emission Factor for Construction Vessels
2Adjustment Value for Carbon Emission Factor of Construction Vessels
Table 3. Quota for machine shift consumption of 5000 m3 trailing suction hopper dredger. (Unit: 10,000 m3).
Table 3. Quota for machine shift consumption of 5000 m3 trailing suction hopper dredger. (Unit: 10,000 m3).
Quota NumberGeotechnical ClassificationBasic Quota Over-Excavation Depth QuotaExcess Haul Distance QuotaAdditional Turning Head QuotaAdditional Bow Blowing QuotaAdditional Bow Jet Quota
1000110.7150.0140.1110.1030.863
1000220.8940.0180.1110.1031.205
1000331.0260.0210.1110.103
1000441.1990.0240.1160.107
1000551.3230.0260.1160.1071.085
1000660.8590.0170.10.0921.1620.623
1000771.020.020.10.0921.2380.7
1000881.2890.0260.10.0921.4620.777
1000991.4930.030.1110.1031.547
10010101.5520.0310.1110.103
Table 4. Fuel consumption for 5000 m3 trailing suction hopper dredger construction.
Table 4. Fuel consumption for 5000 m3 trailing suction hopper dredger construction.
Quota NumberDredged Soil and Rock ClassificationQuota Project Quantity (10,000 m3)Fuel Consumption (kg)
BenchmarkOver-Excavation DepthExcess Haul Distance Additional Turning Head Additional Bow BlowingAdditional Bow Jet
PX100001114681.1191.66 726.72 674.34 5650.06
PX100002215853.02117.85 726.72 674.34 7889.14
PX100003316717.22137.49 726.72 674.34
PX100004417849.85157.13 759.45 700.53
PX100005518661.68170.22 759.45 700.53 7103.50
PX100006615623.87111.30 654.70 602.32 7607.61 4078.78
PX100007716677.94130.94 654.70 602.32 8105.19 4582.90
PX100008818439.08170.22 654.70 602.32 9571.71 5087.02
PX100009919774.67196.41 726.72 674.34 10,128.21
PX10001010110,160.94202.96 726.72 674.34
Table 5. Carbon emission quota for trailing suction hopper dredger (TSHD) construction.
Table 5. Carbon emission quota for trailing suction hopper dredger (TSHD) construction.
Quota NumberDredged Soil and Rock ClassificationQuota Project Quantity (10,000 m3)Benchmark (kg CO2)
Carbon Emission Over-Excavation Depth
(kg CO2)
Excess Haul Distance
(kg CO2)
Additional Turning Head
(kg CO2)
Additional Bow Blowing (kg CO2)Additional Bow Jet
(kg CO2)
PX1000011114,510.30 284.12 2252.65 2090.30 17,513.83
PX1000022118,142.95 365.29 2252.65 2090.30 24,454.43
PX1000033120,821.78 426.18 2252.65 2090.30
PX1000044124,332.66 487.06 2354.12 2171.47
PX1000055126,849.13 527.65 2354.12 2171.47 22,019.13
PX1000066117,432.66 345.00 2029.41 1867.06 23,581.78 12,643.24
PX1000077120,700.01 405.88 2029.41 1867.06 25,124.13 14,205.89
PX1000088126,159.13 527.65 2029.41 1867.06 29,670.02 15,768.54
PX1000099130,299.13 608.82 2252.65 2090.30 31,395.02
PX10001010131,496.49 629.12 2252.65 2090.30
Table 6. Carbon emission factor for construction vessels.
Table 6. Carbon emission factor for construction vessels.
SNQuota NumberShip Type and SpecificationMachine ShiftWorking ConditionCarbon Emission Factor per Machine Shift (kg CO2)Carbon Emission Factor for Idle Machine Shift (kg CO2)
1PX2010015000 m31IV20,294.13 2029.41
2PX20100210,000 m31IV40,768.04 4076.80
3PX20100312,000 m31IV45,736.96 4573.70
4PX20100413,000 m31IV48,222.97 4822.30
Table 7. Carbon emission quota for dredger startup deployment and completion integration.
Table 7. Carbon emission quota for dredger startup deployment and completion integration.
SNQuota NumberShip Type and SpecificationSub-ItemQuota Project QuantityCarbon Emission Benchmark (kg CO2)
1PXQT10015000 m3Preparation1 time60,882.39
2PXQT10025000 m3Finishing1 time60,882.39
3PXQT100310,000 m3Preparation1 time122,304.13
4PXQT100410,000 m3Finishing1 time122,304.13
5PXQT100512,000 m3Preparation1 time137,210.88
6PXQT100612,000 m3Finishing1 time137,210.88
7PXQT100713,000 m3Preparation1 time144,668.90
8PXQT100813,000 m3Finishing1 time144,668.90
Table 8. Carbon emission factor for auxiliary vessels.
Table 8. Carbon emission factor for auxiliary vessels.
SNQuota NumberShip Type and SpecificationMachine ShiftWorking ConditionCarbon Emission Factor per Machine Shift
(kg CO2)
Carbon Emission Factor for Idle Machine Shift
(kg CO2)
1TL201001200 kW1IV973.3297.33
2TL201002440 kW1IV2138.83213.88
3TL201003970 kW1IV4714.73471.47
4TL2010041440 kW1IV6999.26699.93
5TL2010051940 kW1IV9429.47942.95
6TL2010062940 kW1IV14,289.891428.99
7TL2010073860 kW1IV18,762.851876.28
8TL2010085380 kW1IV26,149.582614.96
Table 9. Adjustment value for carbon emission factor of construction vessels.
Table 9. Adjustment value for carbon emission factor of construction vessels.
SNQuota NumberShip Type and SpecificationMachine ShiftWorking ConditionWorking Condition Elevation AdjustmentCarbon Emission Factor Adjustment Value
(kg CO2)
1PX2010015000 m31IVincreasing in level I–III and decreasing in level V–VII1456.89
2PX20100210,000 m31IVincreasing in level I–III and decreasing in level V–VII2678.19
3PX20100315,000 m31IVincreasing in level I–III and decreasing in level V–VII3003.67
4PX20100420,000 m31IVincreasing in level I–III and decreasing in level V–VII3167.95
Table 10. Carbon emission quota for vessel deployment.
Table 10. Carbon emission quota for vessel deployment.
SNQuota NumberShip Type and SpecificationDeployment MethodRound-Trip Deployment MileageCarbon Emission Factor Adjustment Value
(kg CO2)
1PXDQ10015000 m3Self-propelled100 nautical miles73,515.40
2PXDQ100210,000 m3Self-propelled100 nautical miles99,212.16
3PXDQ100312,000 m3Self-propelled100 nautical miles105,257.90
4PXDQ100413,000 m3Self-propelled100 nautical miles111,303.64
Table 11. Carbon emission quota for management activities.
Table 11. Carbon emission quota for management activities.
SNQuota NumberElectricity Consumption (MWh)Carbon Emission Factor
(tCO2/MWh)
Carbon Emission Quota (kg CO2)
1GL000011000.58158,100.00
Table 12. Vessel deployment for project construction.
Table 12. Vessel deployment for project construction.
SNShips TypeShenzhen ProjectMalé ProjectGuangzhou Project
QuantitySelf-OwnedQuantitySelf-OwnedQuantitySelf-Owned
1Trailing Suction Hopper Dredger761133
2Cutter Suction Dredger11
3Clamshell Dredger442
4Mud Barge149
5Tugboat11 11
6Anchor Boat611
7Transportation Vessels2
Total210112144
Table 13. Summary of carbon emissions during the construction period of the Shenzhen project.
Table 13. Summary of carbon emissions during the construction period of the Shenzhen project.
SNItemDirect Carbon Emissions (10,000 t CO2)Indirect Carbon Emissions
(10,000 t CO2)
Total Carbon Emissions
(10,000 t CO2)
Proportion
1Dredging Vessels27.490.3527.8563.21%
2Auxiliary Equipment15.840.2416.0836.50%
3Management Activities/0.130.130.29%
Total43.330.7244.05
Proportion98.37%1.63%
Table 14. Comparison of actual fuel carbon emissions from owned vessels and quota-based direct carbon emissions calculation.
Table 14. Comparison of actual fuel carbon emissions from owned vessels and quota-based direct carbon emissions calculation.
SNShips TypeFuel Combustion Carbon Emissions
(t CO2)
Quota-Based Direct Carbon Emission Calculation (t CO2)Difference ValueDifference Percentage
1Suction hopper182,598.35182,983.22−384.87−0.21%
2Cutter suction hopper14,379.8414,625.55−245.71−1.68%
3Grab dredgers20,188.9721,196.99−1008.02−4.76%
4Tugboats1719.441733.37−13.94−0.80%
Total218,886.59220,539.131652.53−0.75%
Table 15. Summary of carbon emissions during the construction phase.
Table 15. Summary of carbon emissions during the construction phase.
SNItemDirect Carbon Emissions
(10,000 t CO2)
Indirect Carbon Emissions
(10,000 t CO2)
Total Carbon Emissions
(10,000 t CO2)
Proportion
1Dredging Vessels2.750.0372.7897.31%
2Auxiliary Equipment0.070.00140.07522.63%
3Management Activities 0.00170.00170.06%
Total2.820.042.86
Proportion98.61%1.39%
Table 16. Comparison of actual fuel carbon emissions from owned vessels and quota-based direct carbon emission calculation.
Table 16. Comparison of actual fuel carbon emissions from owned vessels and quota-based direct carbon emission calculation.
SNShips TypeFuel Combustion Carbon Emissions
(t CO2)
Quota-Based Direct Carbon Emission Calculation
(t CO2)
Difference ValueDifference Percentage
1Trailing Suction Hopper Dredger26,130.9827,471.13−1340.15−4.88%
2Anchor Boat695.46737.80−42.34−5.74%
Total26,826.4428,208.93−1382.49−4.90%
Table 17. Summary of carbon emissions during the construction phase.
Table 17. Summary of carbon emissions during the construction phase.
SNItemDirect Carbon Emissions
(10,000 t CO2)
Indirect Carbon Emissions
(10,000 t CO2)
Total Carbon Emissions
(10,000 t CO2)
Proportion
1Dredging Vessels0.890.050.9496.97%
2Auxiliary Equipment0.020.0040.032.83%
3Management Activities 0.0020.0020.19%
Total0.910.060.97
Proportion93.82%6.18%
Table 18. Comparison of actual fuel carbon emissions from construction vessels and quota-based direct carbon emission calculation.
Table 18. Comparison of actual fuel carbon emissions from construction vessels and quota-based direct carbon emission calculation.
SNShips TypeFuel Combustion Carbon Emissions
(t CO2)
Quota-Based Direct Carbon Emission Calculation
(t CO2)
Difference ValueDifference Percentage
1Trailing Suction Hopper Dredger8566.068897.63−331.57−3.73%
2Anchor Boat234.59236.49−1.90−0.80%
Total8800.659134.12−333.47−3.65%
Table 19. Summary of carbon emissions during the construction phase for three case projects.
Table 19. Summary of carbon emissions during the construction phase for three case projects.
SNProject TitleDirect Carbon Emissions
(10,000 t CO2)
Indirect Carbon Emissions
(10,000 t CO2)
Total Carbon Emissions
(10,000 t CO2)
1Shenzhen433.307.2440.5
2Malé28.200.428.6
3Guangzhou9.100.69.7
Total470.708.2478.9
Table 20. Carbon emissions per 10,000 m3 and monthly average for three case projects.
Table 20. Carbon emissions per 10,000 m3 and monthly average for three case projects.
SNProjectSoil Type Maximum Transport DistanceCarbon Emissions per 10,000 m3 of Project Volume (t CO2)Monthly Average Carbon Emissions (t CO2)
Direct EmissionsIndirect EmissionsTotalDirect EmissionsIndirect EmissionsTotal
1Shenzhen 1, 3, 6, 11, 12 110 km120.472.00122.477222.29119.767342.05
2Malé6, 710 km55.100.7855.884029.8556.944086.79
3Guangzhou1, 691 km40.892.5743.463044.71200.683245.39
Average 72.15 1.78 73.94 4765.62 125.79 4891.41
Table 21. Comparison of actual fuel carbon emissions from construction vessels and quota-based direct carbon emission calculation in three case studies.
Table 21. Comparison of actual fuel carbon emissions from construction vessels and quota-based direct carbon emission calculation in three case studies.
SnProjectNumber of Owned VesselsFuel Combustion Carbon Emissions (t CO2)Quota-Based Direct Carbon Emission Calculation (t CO2)Difference Difference Percentage
1Shenzhen10218,886.59220,539.13−1652.53−0.75%
2Malé226,826.4428,208.93−1382.49−4.90%
3Guangzhou Port48800.659134.12−333.47−3.65%
Total16.00254,513.69257,882.17−3368.49−1.32%
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Liang, S.; Chen, W.; Li, L.; Liu, F. A Study of Carbon Emission Quota for Construction Period of Dredging Projects: Case Studies in Guangzhou, Shenzhen, and Malé. Buildings 2025, 15, 2293. https://doi.org/10.3390/buildings15132293

AMA Style

Liang S, Chen W, Li L, Liu F. A Study of Carbon Emission Quota for Construction Period of Dredging Projects: Case Studies in Guangzhou, Shenzhen, and Malé. Buildings. 2025; 15(13):2293. https://doi.org/10.3390/buildings15132293

Chicago/Turabian Style

Liang, Siming, Wei Chen, Lijuan Li, and Feng Liu. 2025. "A Study of Carbon Emission Quota for Construction Period of Dredging Projects: Case Studies in Guangzhou, Shenzhen, and Malé" Buildings 15, no. 13: 2293. https://doi.org/10.3390/buildings15132293

APA Style

Liang, S., Chen, W., Li, L., & Liu, F. (2025). A Study of Carbon Emission Quota for Construction Period of Dredging Projects: Case Studies in Guangzhou, Shenzhen, and Malé. Buildings, 15(13), 2293. https://doi.org/10.3390/buildings15132293

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop