Next Article in Journal
The Right to the City in Practice: The Experience of Social Interest Housing Developments in Diadema, São Paulo, Brazil
Previous Article in Journal
Reducing the Environmental Footprint of Urban Housing in Sub-Saharan Africa: A Case Study of Cameroon
Previous Article in Special Issue
The Mechanical Properties and Durability of the PE-BFRP Hybrid-Fiber-Engineered Cementitious Composite (ECC)
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Construction Scheme and Influence Analysis of Horizontal Small-Clear-Distance Shield Tunnel

1
China Railway (Guangzhou) Investment & Development Co., Ltd., Guangzhou 510335, China
2
School of Urban Planning and Municipal Engineering, Xi’an Polytechnic University, Xi’an 710600, China
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(13), 2142; https://doi.org/10.3390/buildings15132142
Submission received: 9 April 2025 / Revised: 9 June 2025 / Accepted: 10 June 2025 / Published: 20 June 2025

Abstract

:
Based on the construction project of Guangzhou Metro Line 13, this paper explores the special construction scheme for the safety of horizontal small-clear-distance shield tunnel construction, which adopts the construction of a tunnel first and a station later in the actual project to reduce the impact on the tunnel segment and the existing bridge piles. At the same time, the MIDAS GTS(2022R1) geotechnical and structural finite element analysis software is used to simulate and analyze the shield excavation process by using the stratum–structure modeling method, and the effect of grouting reinforcement in the tunnel is compared and analyzed. Through the research and analysis of the displacement and deformation of the model, the rationality and effectiveness of grouting reinforcement are explored to ensure the smooth implementation of the special construction scheme. The test results show that the implementation of grouting reinforcement measures in the tunnel can effectively control the horizontal deformation of the existing bridge piles and the horizontal deformation of the left line segment of the small-clear-distance section, and the above two deformation indexes are reduced by 67.7% and 72.1%, respectively, compared with the non-reinforcement condition. The settlement deformation of the segment and the surrounding existing bridge piles meets the requirements of the code, so the construction scheme is basically feasible.

1. Introduction

With the continuous advancement and development of urban planning, during the excavation of subway tunnels, it is inevitable to encounter situations where existing buildings or preceding tunnels are located near shield tunnels. The construction of new tunnels significantly disturbs surrounding soils, affecting the safety and stability of adjacent structures and existing tunnels. Severe impacts may even create construction hazards [1]. Therefore, for small-clear-distance shield tunnel construction in practical engineering, it is crucial to establish special safety construction schemes, investigate their feasibility and effectiveness, and ensure project completion.
Since the emergence of issues related to small-clear-distance shield tunnel construction, numerous scholars have conducted extensive research and achieved remarkable results. Pan Qian et al. [2] addressed construction challenges in small-clear-distance tunnels through different lithological contact zones by combining numerical simulations to determine reasonable construction sequences and technical measures. Li Ran et al. [3,4] systematically investigated the stability characteristics of surrounding rock in three-bore small-clear-distance tunnel projects, proposed corresponding control methods, and conducted engineering applications. They also thoroughly studied the construction mechanical behaviors and control mechanisms through numerical simulations and field measurements. An Jianyong et al. [5] derived full-process surface settlement characteristics through field data analysis and proposed settlement control measures. Ning Bo [6] applied the WSS method to grout-reinforce tunnel excavation sections in high-water-level small-clear-distance tunnels, modified grid steel frames, optimized grouting procedures, and accelerated construction progress. Zhou Jingzeng et al. [7] addressed the construction challenges of small-clear-distance overlapping shield tunnels in soft soil by proposing a “lower-first-then-upper” construction sequence, reducing difficulties and improving quality control. Fu Zhao et al. [8] conducted finite element simulations to analyze mutual influences during small-clear-distance shield tunneling, performed sensitivity analysis on shield parameters, and determined optimal excavation sequences. Song Gaorui et al. [9] optimized construction methods for small-clear-distance parallel tunneling through shield and shallow buried excavation based on practical projects. Hu Ping et al. [10] simulated deformation patterns of preceding shallow buried tunnels under various small-clear-distance conditions during shield tunneling, proposing practical reinforcement measures. Wang Zhuangzhuang et al. [11] analyzed contour deformation characteristics of new and existing tunnels under four small-clear-distance conditions, along with displacement-excavation step relationships. Wu Kai et al. [12] investigated deformation and internal force distribution in adjacent soils, anti-floating slabs, and existing tunnels during shield advancement using finite element software.
Ref. [13] proposed a three-dimensional Peck formula for the Jilu Road undercrossing the Yellow River Levee, optimizing the settlement prediction model through field-measured data fitting and revealing the influence of vertical depth and tunnel spacing on settlement trough morphology. Ref. [14], focusing on the Beijing Metro Line 17 undercrossing the North Fourth Ring Road, achieved a maximum surface settlement control of 7.618 mm through test section parameter optimization and numerical simulation, verifying the effectiveness of dynamic adjustment of excavation parameters. Ref. [15] for the Shanghai Metro Line 18 undercrossing ballasted railway tracks in soft soil developed a “fine shield construction control method,” coordinating soil chamber pressure and grouting volume to limit subgrade deformation within ±10 mm. Ref. [16] adopted advanced large pipe shed, composite three-layer lining, and interlayer soil grouting reinforcement in the Chengdu Metro Line 13 mining method tunnel to suppress the “horizontal oval” deformation of existing tunnels during ultra-small-clear-distance undercrossing, ensuring structural safety. Ref. [17] proposed a collaborative bearing technology of advanced pipe shed and deep-hole grouting for the Beijing Metro Line 12 double-interval undercrossing project, locking key disturbance areas via numerical simulation and controlling deformation of existing shield structures within 5.0 mm.
Ref. [18] analyzed the influence of pile–tunnel spacing on pile foundation internal forces using Midas-GTS 3D modeling for the Hefei Metro Line 7 shield undercrossing existing piles, validating safety assessment methods through field monitoring. Ref. [19] innovatively applied post-wall compensation grouting, Clayshock grouting method, and fully automated monitoring in the Wuhan Metro Line 7 ultra-close undercrossing project, achieving micro-settlement control (<1 mm) and optimizing traditional advanced pipe shed schemes. Ref. [20] revealed the soil–structure interaction mechanism during a metro tunnel undercrossing an underground passage via numerical simulation, identifying the barrier effect of existing structures on soil arching and the lagging deformation in the trailing side. Ref. [21] controlled the inclination rate of high-voltage transmission towers within −0.1‰~0.14‰ by staging propulsion parameter adjustment, synchronous grouting, and Clayshock injection for the Shanghai Airport Link large-diameter shield project. Ref. [22], for the Chengdu Metro Line 30 undercrossing an expressway in composite strata, confirmed through 3D numerical modeling that radial reinforcement depth is more effective than circumferential angle for settlement control, validating the scheme via field measurements.
Current research on small-clear-distance shield tunneling primarily focuses on optimizing construction techniques and soil reinforcement through grouting. This paper presents a special safety construction scheme for horizontal small-clear-distance shield tunneling based on practical engineering experience. By employing grouting reinforcement to reduce overall deformation, Midas GTS(2022R1) finite element software was utilized to simulate construction processes and analyze grouting effectiveness. Combined with field monitoring data, the scheme was comprehensively evaluated to ensure feasibility. The work presented herein provides valuable references for research on horizontal small-clear-distance shield tunneling technologies.

2. Project Overview

2.1. Design Overview

The tunnel design for the Congbian Road Station to Jiansheliu Road Station section of Guangzhou Metro Line 13 adopts double-track circular tunnels. As shown in Figure 1. The shield tunnel has an excavation diameter of 6680 mm. The lining rings utilize universal wedge rings with a “3 + 2 + 1” segmented configuration, assembled in a staggered joint pattern. Simultaneous grout back-filling is applied behind the segments. The tunnel segments are constructed using C50 high-performance concrete with an impermeability grade of P12. Key segment specifications include an outer diameter of 6400 mm, inner diameter of 5800 mm, ring width of 1500 mm, and a double-sided taper with a total lining taper amount of 48 mm.
The tunnel alignment features a maximum downhill gradient of 20‰ and a minimum gradient of 3.237‰. The minimum overburden depth at the tunnel crown is approximately 18.0 m, while the maximum overburden depth reaches 26.3 m.

2.2. Engineering Geological Conditions

This section features a landscape of clastic rock low hill platforms and inter-hill alluvial valleys, with slightly undulating terrain and a ground elevation of 8–12 m. The alignment primarily follows East Fengdong Road, intersects with multiple subway lines, and exhibits highly complex alignment conditions. The bedrock consists of sedimentary rocks, while the residual soil is predominantly silty clay in a plastic-to-hard-plastic state, demonstrating favorable engineering properties. The completely weathered layer presents as hard silty clay-like or dense silt-like material, also with good engineering properties. The highly weathered rock exhibits a semi-rock and semi-soil mass or fragmented blocks with developed weathering fissures, classified as extremely soft rock with poor rock mass integrity. It is prone to softening upon water absorption and desiccation-induced cracking when dehydrated. Due to variations in cementing materials and the degree of structural plane development, the weathered rocks display uneven weathering. Vertically, interlayered zones of differing weathering grades frequently occur, leading to significant variations and disparities in the mechanical strength of the rock mass.
The tunnel section exhibits a stable water table depth ranging from 1.9 to 4.9 m, with an average depth of 3.23 m. The groundwater primarily consists of Quaternary pore water aquifers, bedrock fissure water aquifers, and relatively impermeable layers. It maintains a hydraulic connection with surface water, sharing a unified free water surface. Overall, the groundwater is confined, though localized unconfined water zones exist in certain segments. Based on comprehensive observations from monitoring wells, the water head elevation can be conservatively estimated at 1 m below the ground surface.

2.3. Project Highlights and Difficulties

2.3.1. The Shield Machine Cutterhead Is Prone to Mud Cake Formation

The tunnel section at Congbian Road Station traverses moderately weathered and slightly weathered argillaceous siltstone formations. Historical construction experience indicates that argillaceous siltstone—characterized by its high content of clay mineral particles and fine powder—exhibits significant susceptibility to mud cake formation during shield tunneling operations.

2.3.2. The Deformation Risk of Shield Tunneling with a Small Clear Distance Passing by Existing Buildings and Structures on the Side and Passing Under Groups of Buildings and Structures

In the section between Cang and Jian, there is a range of approximately 130 m where the horizontal clear distance between the left and right line tunnels is less than 3 m. The right line passes by the underpinning piles of the ramp of the Donghaochong Elevated Bridge with small horizontal clear distances of 1.90 m and 0.99 m, respectively, and the left line passes by the bridge piles of the Dongfeng Road–Yuexiu North Road Overpass with small horizontal clear distances of 1.46 m and 1.02 m, respectively. During the shield tunneling process, there is a risk of deformation of the segment of the left line shield tunnel and the existing bridge piles. When passing through buildings (structures), shield construction will cause disturbance to the stratum, which may lead to the deformation of buildings (structures), affect the traffic, and even endanger the structural safety of the elevated bridge and pedestrian overpass. Ensuring the stability of the pile foundation during the shield tunneling process is a key point of the construction control of this project.

3. Construction Plan for Shield Tunneling with Small Clear Distance Through Existing Structures

3.1. Tunneling Scheme for Test Section

The Tunneling Parameters for the Trial Section Are Shown in Table 1.

3.1.1. Shield Tunnel Attitude Control

Adjust the tunneling direction of the shield machine according to the tunnel axis and measurement positioning, and maintain a stable posture during tunneling. The adjustment amount for each ring’s posture should be within 5 mm, and the posture should be controlled within a range of plus or minus 50 mm. Based on the analysis of the shield machine’s posture since tunneling in the test section and the actual manual review of the posture, the posture is basically consistent.

3.1.2. Segment Type Selection and Assembly

Segment selection and installation must adhere to two principles: compatibility with the tunnel design alignment and adaptation to the shield machine’s orientation. The assembly process involves 16 predefined positions, determined by the on-duty engineer based on shield tail clearance and alignment requirements of the fitted tunnel profile. In the shield-driven section, segments are installed using an interlocking staggered joint method. Installation begins with the bottommost segment, followed by the immediate connection of longitudinal bolts. The remaining segments are then symmetrically positioned from bottom to top, alternating left and right, with both longitudinal and annular bolts connected and tightened progressively as each segment is placed. For the closure (key) segment, a three-step process is applied: partial engagement (1/3 length), radial insertion with positional adjustments, and slow longitudinal pushing. Upon full ring assembly, all bolts are tightened using pneumatic wrenches, and grouting hole plugs are securely fastened. Completion of these steps allows the shield machine to advance to the next excavation cycle.

3.1.3. Synchronous Grouting

Cement mortar is used as the synchronous grouting material, with P.O.42.5 ordinary Portland cement. The synchronous grouting adopts two-component grout. Based on previous construction experience and trial mixing in the laboratory, several different mix ratios are determined. During construction, different mix ratios are selected according to stratum conditions, groundwater conditions, surrounding conditions, etc., and the optimal mix ratio is determined through field tests, as shown in Table 2.
The gelation time typically falls between 3 and 6 h. Depending on the stratum conditions and the tunneling speed, the gelation time can be adjusted by adding accelerators and altering the mixture ratio through on-site tests. For areas with highly permeable strata or those requiring relatively high early-stage strength, the mixture ratio can be further tweaked, or additives can be incorporated via field trials to further reduce the gelation time.
The pressure for synchronous grouting generally ranges from 1.1 to 1.2 times the sum of the static earth pressure and the static water pressure. The pressure for secondary reinforcing grouting is set at 0.1–0.3 MPa. The grouting volume is 1.3–1.8 times the theoretical volume of the annular gap, with the grouting volume per ring (Q) being 5.6–7.8 m3. The synchronous grouting speed should match the tunneling speed, and its average speed is determined based on completing the grouting volume for the current ring within the time it takes the shield machine to finish tunneling one ring. A dual-index control standard is adopted for grouting, meaning that the quality requirements are considered met when the grouting pressure reaches the set value and the grouting volume is over 90% of the designed volume.

3.1.4. The Synchronous Grouting Method

Synchronous grouting is conducted simultaneously with shield advancement through the grouting system and built-in grouting pipes at the shield tail, filling the annular void formed during excavation. The process employs dual-pump, four-pipeline (four injection points) symmetrical grouting. Grouting control operates in either automatic or manual mode: automatic mode presets the grouting pressure, with the control program adjusting the grouting rate until reaching the preset pressure threshold, then automatically stopping; manual mode allows real-time adjustment of the grouting flow, rate, and pressure based on excavation conditions.

3.1.5. Equipment Configuration

Design and build a mortar mixing station with a capacity of 14 m3/h on your own. Equip it with 4 hydraulic grouting pumps (already installed on the shield machine), with a grouting capacity of 4 × 12 m3/h, 8 grouting ports at the shield tail (4 of which are reserved), and their supporting pipelines. There are mortar tank trucks (7 m3) with self-mixing functions and mortar transfer pumps, which are transported along with the marshaling train.

3.1.6. Secondary Reinforcing Grouting

The secondary reinforcing grouting uses two-component grout, with ordinary Portland cement and water glass (concentration 40 Be) as materials. The volume ratio of cement slurry to water glass is 1:1. According to on-site mixing containers, the cement slurry mixing ratio is cement:water = 1:1.
The retarder dosage is 0–1.5% of cement content. The mixed slurry has a density of approximately 1.44 g/cm3, with initial setting time controlled at 20–48 s. Supplementary grouting is conducted through segment grouting holes using a KBY-50/70 two-component grouting pump. The grouting pressure is controlled at 0.3–0.6 MPa with a flow rate not exceeding 10 L/min. The grouting completion criterion is based solely on pressure control. The grouting volume is determined according to site conditions, while the grouting frequency is adjusted based on groundwater seepage and segment alignment monitoring.

3.1.7. Muck Removal Volume Management

In the test section, the muck removal volume per ring is controlled within 4.8 trucks (78 m3 loose volume). The duty engineer monitors the muck removal volume every 310 mm of tunneling progress and promptly reminds the chief driver to control the muck removal volume. Based on analysis of muck removal volumes for rings 1100 to 1200, the average muck removal volume in the test section was 78 m3, which did not exceed the design value.

3.2. Crossing Critical Structures

The left line of the Jiannong section passes laterally by the Medical Research Building of Sun Yat-sen University Cancer Center, which employs hand-dug piles with diameters of Φ1.0 m, Φ1.2 m, Φ1.3 m, and Φ1.8 m, and pile lengths of 7.6–25.8 m. The building is approximately 14.8 m horizontally from the shield tunnel. The Sun Yat-sen University Cancer Center utilizes 800 mm-thick diaphragm walls (height: 28.5 m), rock anchors (diameter: 0.15 m, length: 26–36 m), located 9.1 m horizontally and −0.9 m vertically from the tunnel. The Phase II five-story basement of the center employs bored piles (diameters: 0.7 m, 0.8 m, 0.9 m; lengths: 8–24 m), with the basement structure 2.2 m horizontally and 5.7 m vertically from the tunnel. Adjacent mined tunnels parallel the left-line shield tunnel over a long distance, with structural clearances of 2.4–8.7 m. The undercrossing zone primarily consists of highly weathered argillaceous siltstone, locally transitioning to slightly weathered argillaceous siltstone.

3.3. Shield Construction Measures for Small-Clearance Crossings

3.3.1. Survey Control

When the shield machine enters the protection zone, adjust tunneling parameters promptly based on monitoring data to ensure safe passage through structures. During the crossing phase, perform daily manual verification of shield machine alignment and segment positioning. Compare manual measurements with automatic guidance system data to identify and resolve discrepancies immediately. Determine tunneling mode through a comprehensive analysis of geological conditions, burial depth, and shield operation parameters when passing beneath structures.
The tunnel section primarily traverses moderately weathered and slightly weathered argillaceous siltstone with good self-stability, though with minimal clearance from adjacent structures. Maintain appropriate earth pressure during excavation while retaining suitable muck volume in the chamber. Based on real-time monitoring data and excavated material analysis, ensure earth pressure in the excavation chamber remains within specific parameters during undercrossing operations to guarantee smooth and stable tunneling beneath structures. Particular attention should be paid to coordinating pressure control with actual muck discharge quantities to achieve an optimal balance between ground settlement prevention and construction efficiency.

3.3.2. Muck Discharge Control

Strictly limit muck discharge to ≤78.8 m3 per ring.

3.3.3. Grouting Control

During the undercrossing of structures, synchronous grouting must be timely coordinated. Based on empirical formulas, the grouting volume is set at 1.3–1.8 times the theoretical annular gap volume, resulting in a grouting quantity of Q = 5.2–7.6 m3 per ring. Considering stratum permeability, a higher coefficient is adopted, with the actual grouting volume taken as 1.5 times the theoretical value (≥6.5 m3/ring). Based on shield construction experience, parameters are optimized through field trials according to geological conditions, groundwater status, and surrounding environments. The grout’s key physico-mechanical properties must meet specified criteria.
Synchronous grouting must strictly adhere to the principle of “simultaneous excavation and grouting; no grouting, no advancement,” implementing dual control of grouting pressure and volume to ensure adequacy and timeliness. Specific grouting parameters are further refined through real-time feedback from ground and stratum settlement monitoring.
During shield crossing of structures, secondary grouting using cement-sodium silicate grout is implemented as needed. Grouting locations, quantities, and pressures are executed in strict compliance with the undercrossing technical directive.

3.3.4. Alignment Control

Strictly manage shield deviation correction. Maintain rigorous control over shield machine alignment during tunneling, minimizing per-ring correction amplitude to ensure it does not exceed 9 mm. Based on measurement results from each ring and clearance conditions around the segments, provide precise guidance for the advancement of the next ring. Adjust jack extension lengths in each zone promptly to correct minor deviations at their initial stage. This approach prevents “snake-like” shield movement, reduces ground disturbance, and creates optimal conditions for segment assembly.

3.3.5. Segment Anti-Floating Measures

To prevent tunnel segment flotation, the following measures shall be implemented: master geological conditions including stratum strength, depth, moisture content, and soil distribution along the tunnel alignment, adopting differentiated tunneling methods based on geological characteristics; strictly control shield attitude to minimize deviation from the tunnel axis; rigorously execute precision measurement and control with appropriate verification frequency; employ optimized grouting methods and materials for anti-floating synchronous grouting; and select grout with appropriate performance parameters. For floated segments, immediately conduct secondary grouting using dual-component grout, prioritizing injection at tunnel haunches followed by the invert.

3.4. Additional Measures for Under-Crossing Structures

Increase monitoring frequency to 4 h intervals during under-crossing. Adjust earth pressure in real-time based on pile–tunnel positional relationships during advancement, maintaining appropriate muck accumulation in the chamber. Conduct specialized equipment inspections pre-crossing, dynamically adjust parameters per excavation conditions, and provide immediate feedback on anomalies. Ensure synchronous grouting volume reaches 6.5 m3, strictly meeting single-index grouting requirements.
Further intensify monitoring: 4 h intervals within pre-crossing influence zones, 2 h intervals during direct crossing. Maintain 1/2 chamber muck volume while real-time adjusting earth pressure. Implement equipment inspections and conduct technical/safety training. Enforce strict compliance with 6.5 m3/ring grouting volume. During crossing, perform secondary tracking grouting for insufficient segment backfill. Prepare for secondary and sleeve valve pipe grouting both underground and surface level. Replace worn components promptly through dedicated equipment inspections.

4. Establishment of Numerical Model and Analysis Calculation

4.1. Calculation Model and Parameters

The model size is set as 350 m × 200 m × 50 m. The stratum and ramp underpinning beams are simulated by solid elements, the tunnel segments and in-tunnel grouting reinforcement are simulated by 2D plate elements, and the bridge piles are simulated by 1D beam elements. Bridge piles were modeled as 1D beam elements with material properties matching C35 concrete (E = 31,500 MPa), while grouted zones used a homogenized stiffness (E = 3000 MPa) to simulate improved soil–pile interaction, reducing lateral deformation through increased radial confinement. As shown in Figure 2 and Figure 3.
Select relatively unfavorable boreholes to divide the strata. The specific parameters of geotechnical and structural materials are summarized in Table 3.

4.2. Result Analysis and Verification

To address the dynamic effects of vehicle loads on bridge piles during shield tunneling, a supplementary simulation was conducted by introducing equivalent static loads based on the AASHTO (2017) [23] The design traffic load was simplified as a uniformly distributed static load of 50 kPa on pile caps, which accounts for the combined effects of dead load, live load, and impact factors. This equivalence is justified by previous studies [13] showing that dynamic loads in urban bridge structures can be conservatively approximated by static loads with a safety factor of 1.3–1.5 under low-frequency tunneling-induced vibrations.
In the finite element model, the 50 kPa load was applied as a surface pressure on the pile cap elements, simulating the vertical and horizontal stress transmission from moving vehicles. Dynamic effects were indirectly considered through the grouting-induced soil stiffness enhancement (Table 3), which reduces soil–pile dynamic interaction coefficients by 20–30% [21]. The simulation results showed the following:
(1)
Without grouting, pile horizontal deformation under combined static-tunnel loads reached 2.89 mm (an increase of 13.8% compared to pure tunneling loads).
(2)
With in-tunnel grouting, deformation was reduced to 0.91 mm (a 68.5% reduction), consistent with the baseline trend under pure tunneling conditions.

4.2.1. Bridge Pile Deformation

Extract the overall deformation contour plot of the bridge piles in the model for analysis, as shown in Figure 4 and Figure 5.
Extract the peak values of bridge pile deformation from the model for analysis. The specific results are shown in Table 4.
From the calculation results, the overall settlement of the bridge piles is very small, and the shield excavation of the tunnel has little impact on the safe operation of the bridge. The overall deformation of the bridge piles is mainly horizontal displacement, supplemented by vertical displacement. The deformation of the Donghaochong bridge piles is relatively larger. The main reason is that the Donghaochong bridge piles are approximately perpendicular to the shield excavation direction of the tunnel, and the influence degrees of the left and right bridge piles by the excavation are different, resulting in larger overall deformation. After adopting the in-tunnel grouting reinforcement measures, the effect of controlling the horizontal deformation of the bridge piles is good. Therefore, it is necessary to adopt the in-tunnel grouting reinforcement measures.
While the peak settlement of bridge piles decreased from 0.05 mm (no grouting) to 0.01 mm (grouting), the more pronounced reduction in horizontal deformation—from 2.54 mm to 0.82 mm (67.7% decrease)—highlights grouting’s critical role in mitigating lateral soil displacement, which is the primary deformation mode in small-clearance tunneling.

4.2.2. Deformation of Left-Line Tunnel Segments

Since there is a long section in the Cangjian section where the horizontal clear distance between the left- and right-line tunnels is small, the shield excavation of the right-line tunnel may affect the previously constructed left-line tunnel. Therefore, extract the deformation of the left-line tunnel segments from the model for summary and analysis. The specific results are shown in Figure 6.
For active bridges, equivalent static loads (e.g., 50 kPa traffic load) were conservatively applied to pile caps in supplementary simulations (not presented here), based on the AASHTO LRFD Bridge Design Code. The results showed that grouting still reduced pile horizontal deformation by 65–70% under combined static–dynamic loading, aligning with the baseline trend and validating the scheme’s applicability to operational bridges.
Extract and compare the deformation values of left-line tunnel segments in different sections from the model. The specific results are shown in Table 5.

5. Field Monitoring Analysis

Surface settlement monitoring points are implemented as manhole-type markers, installed through manual excavation or drilling methods that penetrate the pavement structural layer. The locations of these monitoring points are shown in Figure 7. Each point is equipped with a protective cover, requiring a minimum 150 mm borehole diameter. Monitoring points on roads and surfaces must be installed flush with the surrounding area to prevent tripping hazards or vehicle obstruction while ensuring secure installation and clear marking for long-term preservation. Field monitoring settlement curves are presented in Figure 8.
Analysis of settlement curves demonstrates that maximum subsidence occurs along the shield tunnel centerline, gradually decreasing symmetrically toward both sides. Excavation of the right-line shield tunnel induces lateral unloading on the left-line tunnel, resulting in vertical convergence and horizontal dilation of segments, necessitating monitoring and analysis of these deformations. To evaluate the deformation impacts of the “tunnel-first-station-later” construction method on segments and bridge piles, 300-day long-term monitoring data were analyzed. Daily maximum deformation values were extracted to generate the deformation curve shown in Figure 9.
As shown in Figure 9, both horizontal displacement and clearance convergence values remained within 2 mm throughout the entire right-line shield tunneling process, aligning with numerical simulation results. Grouting reinforcement significantly mitigated excavation-induced disturbances to the originally stable surrounding rock, slowing stress release and minimizing segment deformation. The overall bridge pile deformation stabilized at approximately 1.3 mm, consistent with model verification and meeting code requirements.

6. Conclusions

This paper summarizes a safety-specific construction scheme for horizontal small-clearance shield tunneling, reducing overall deformation through grouting reinforcement. Midas GTS(2022R1) finite element software was used to simulate the construction process, analyze grouting effectiveness, and evaluate the scheme via field monitoring. Key conclusions include the following:
The “tunnel-first, station-later” construction method meets horizontal small-clearance shield tunneling requirements, with impacts on existing bridge piles and pre-constructed tunnels within acceptable limits.
Grouting reinforcement effectively controls horizontal deformation of existing bridge piles (67.7% reduction) and left-line segments in small-clearance sections (72.1% reduction) compared to non-reinforced conditions.
Field monitoring confirms segment deformations comply with code requirements and bridge pile settlements do not compromise safety or normal operations.
This study explores the feasibility of the “tunnel-first, station-later” method for horizontal small-clearance shield tunneling, providing practical engineering references through numerical simulation and field validation.
Grouting reinforcement increases the shear strength and elastic modulus of the surrounding soil (see Table 3, grouting E = 3000 MPa vs. silty clay E = 10 MPa), reducing soil displacement during shield excavation. This minimizes lateral earth pressure on bridge piles, particularly critical for piles with small clear distances (1.02–1.90 m), where soil–structure interaction is amplified. As shown in Figure 5, grouting reduces pile horizontal deformation by 67.7% by constraining the plastic flow of weathered argillaceous siltstone, a stratum prone to softening under tunneling disturbance.

Author Contributions

Conceptualization, H.L.; Data curation, Y.C.; Formal analysis, B.Z.; Writing—original draft, M.Q.; Writing—review & editing, T.Y.; Validation, H.L.; Visualization, X.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the Ministry of Housing and Urban-Rural Development’s Prefabricated Building Technology Demonstration Project: “Research on Key Technologies for Environmental Micro-Disturbance Design and Construction and Risk Early-Warning Methods in Metro Engineering” (Grant Number. 2022-KY-044).

Data Availability Statement

The original contributions presented in the study are included in the article, further inquiries can be directed to the corresponding author.

Conflicts of Interest

Authors Xujie Li, Hui Li, Yabin Cheng, Bing Zhang and Ming Qiao were employed by the company China Railway (Guangzhou) Investment & Development Co., Ltd. The remaining author declares that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Gan, X.; Yu, J.; Gong, X.; Zhu, M.; Cheng, K. Effects of twin tunneling underneath on existing shield tunnels. Chin. J. Rock Mech. Eng. 2020, 39, 3586–3594. [Google Scholar] [CrossRef]
  2. Pan, Q.; Chen, X. Construction Technology Research on Short-distance Intercity Tunnel Under Lithologic Contact Zones. Constr. Technol. 2022, 51, 85–88+100. [Google Scholar]
  3. Li, R.; Chen, P.; Zhang, D.L.; Wang, S.T.; Shen, Z.J.; Pan, H.G. Study on Surface Settlement Characteristics and Control Technology of Shield Tunnel Parallel to Overlap Construction. J. Civ. Eng. 2022, 55, 83–95. [Google Scholar] [CrossRef]
  4. Li, R. Mechanical behavior and stability control of deeply buried closely spaced triple tunnels. Chin. J. Rock Mech. Eng. 2023, 42, 1560. [Google Scholar]
  5. An, J.; Lei, H.; Wang, R.; Zhang, J.; Ding, H.; Ren, S.; Yu, K.; Yang, X.; Guan, X. Study on Surface Settlement Characteristics and Control Technology of Shield Tunnel Parallel to Overlap Construction. Constr. Tech. 2023, 52, 97–101. [Google Scholar]
  6. Ning, B. Key Technology of Grouting Reinforcement and Rapid Construction for High Water Level and Small Clear Distance Tunnel. Constr. Technol. 2023, 52, 38–42+56. [Google Scholar]
  7. Zhou, J.; Wang, J.; Yan, Z.; Wang, J.; Zhang, Q. Mutual disturbance effects of different construction sequence on overlapping shield tunnels with small net distance in soft soil layer and its control methods. Hazard Control. Tunn. Undergr. Eng. 2021, 3, 61–68. [Google Scholar]
  8. Fu, Z.; Ke, N.; Lu, K.; Guo, X.; Zhang, M. An analysis of interaction of deep buried close approaching multi-line parallel shield tunneling. Hydrogeol. Eng. Geol. 2021, 48, 44–54. [Google Scholar]
  9. Song, G.; Wang, W.; Wang, G.; Li, S.; Lü, X. Optimization of Shield Tunneling and Shallow Buried Tunnel with Small Clear Distance in Parallel Construction. Sci. Technol. Eng. 2021, 21, 6472–6478. [Google Scholar]
  10. Hu, P.; Ma, L.; Li, M.; Wang, J.P.; Zhang, J.P. Deformation Effect of Subsequent Holes Excavation on Advanced Holes in Small Clear Distance Tunnel. J. Jinan Univ. 2022, 36, 246–251+272. [Google Scholar] [CrossRef]
  11. Wang, Z.; Wang, X.; Zhao, Y.; Chen, B. Numerical Analysis on the Interaction of Excavation of Full Section of Deep Buried Parallel Tunnel with Small Net Distance. J. Hydraul. Archit. Eng. 2023, 21, 213–219. [Google Scholar]
  12. Wu, K.; Bi, Y.; Yang, X.; Chu, X.Q. Simulation Analysis of Advanced Tubal Curtain Support for Shield Tunneling Passing over the Operation Line with Small Spacing under Ultra-shallow Covering. J. Roadbed Eng. 2023, 130–136. [Google Scholar] [CrossRef]
  13. Qin, F. Study on Settlement of Super-Large-Diameter Shield Tunnel Undercrossing the Yellow River Levee. Urban Roads Bridges Flood Control 2024, 11, 207–212+32. [Google Scholar] [CrossRef]
  14. Zhang, C. Research on Key Construction Technologies for Shield Tunnel Undercrossing Urban Loop Highway. Transp. Sci. Technol. Manag. 2024, 5, 142–144. [Google Scholar]
  15. Lu, L. Study on Deformation Influence of Soft Soil Metro Shield Undercrossing Ballasted Railway. Build. Constr. 2024, 46, 1654–1659. [Google Scholar] [CrossRef]
  16. Hu, R. Analysis of Influence of Mine Tunneling with Ultra-Small Clear Distance Crossing Existing Metro Structure. Railw. Stand. Des. 2025, 1–12. [Google Scholar] [CrossRef]
  17. Tang, X. Analysis of Structural Deformation Control Measures and Effects for Double-Interval Subway Tunnel Undercrossing Existing Shield Tunnels. Build. Struct. 2023, 53, 148–153. [Google Scholar] [CrossRef]
  18. Chen, X.; Liao, W.; Luo, G.; Xiao, C.; Liu, Z. Influence Analysis of Subway Shield Construction Crossing Pile Foundation. Constr. Mech. 2023, 44, 22–26. [Google Scholar]
  19. Zhu, S.; Huang, P.; Jiao, W.; Zhang, K. Research on Micro-Settlement Control Technology for Shield Closely Undercrossing Existing Metro Tunnels. Tunn. Constr. 2022, 42, 372–380. [Google Scholar]
  20. Song, J.; Wan, L.; Zhang, C.; Sun, C.; Han, X. Analysis of Interaction Mechanism between Stratum and Structure in Tunnel Undercrossing Construction. Highway 2023, 68, 426–431. [Google Scholar]
  21. Li, Y. Micro-Disturbance Construction Control Technology for Large Shield Closely Undercrossing High-Voltage Transmission Tower. Mod. Tunn. Technol. 2022, 59, 941–950. [Google Scholar] [CrossRef]
  22. Liu, B.; Zhao, D.; Li, D. Study on Grouting Reinforcement Range of Shield Tunnel Undercrossing Expressway in Composite Stratum. Mod. Tunn. Technol. 2022, 59, 187–196. [Google Scholar] [CrossRef]
  23. AASHTO, AASHTO LRFD Bridge Design Specifications, 8th ed.; with 2019 Interim Revisions; American Association of State Highway and Transportation Officials: Washington, DC, USA, 2017.
Figure 1. Interval layout plan.
Figure 1. Interval layout plan.
Buildings 15 02142 g001
Figure 2. Relationship between foundation pit and station space position.
Figure 2. Relationship between foundation pit and station space position.
Buildings 15 02142 g002
Figure 3. Finite element three-dimensional calculation model.
Figure 3. Finite element three-dimensional calculation model.
Buildings 15 02142 g003
Figure 4. Vertical displacement cloud images: (a) vertical displacement of bridge piles under the condition without in-tunnel grouting (mm); (b) vertical displacement of bridge piles under the condition of in-tunnel grouting (mm).
Figure 4. Vertical displacement cloud images: (a) vertical displacement of bridge piles under the condition without in-tunnel grouting (mm); (b) vertical displacement of bridge piles under the condition of in-tunnel grouting (mm).
Buildings 15 02142 g004
Figure 5. Horizontal displacement cloud images: (a) horizontal displacement of bridge piles under the condition without in-tunnel grouting reinforcement (mm); (b) horizontal displacement of bridge piles under the condition of in-tunnel grouting reinforcement (mm).
Figure 5. Horizontal displacement cloud images: (a) horizontal displacement of bridge piles under the condition without in-tunnel grouting reinforcement (mm); (b) horizontal displacement of bridge piles under the condition of in-tunnel grouting reinforcement (mm).
Buildings 15 02142 g005
Figure 6. Segment displacement cloud images: (a) horizontal displacement of segments in the case of no in-tunnel grouting reinforcement (mm); (b) horizontal displacement of segments under the condition of in-tunnel grouting reinforcement (mm).
Figure 6. Segment displacement cloud images: (a) horizontal displacement of segments in the case of no in-tunnel grouting reinforcement (mm); (b) horizontal displacement of segments under the condition of in-tunnel grouting reinforcement (mm).
Buildings 15 02142 g006
Figure 7. Location of surface settlement monitoring points.
Figure 7. Location of surface settlement monitoring points.
Buildings 15 02142 g007
Figure 8. Surface and tunnel settlement curve.
Figure 8. Surface and tunnel settlement curve.
Buildings 15 02142 g008
Figure 9. Deformation curve of segment and pile.
Figure 9. Deformation curve of segment and pile.
Buildings 15 02142 g009
Table 1. Driving parameters of the test section.
Table 1. Driving parameters of the test section.
ParametersParameter Design Value
Excavation thrust≤1800 t
Shield tunneling machine thrust1500~1800 t
Knife disc torque2200~2500 KN·m
Upper soil silo pressure2.0~2.2 bar
Slag output≤70 m3
Cutterhead speed2.0~2.1 rpm
Advance rate10~25 mm/min
Table 2. Synchronous grouting material ratio.
Table 2. Synchronous grouting material ratio.
Cement/kgFly Ash/kgBentonite/kgSand/kgWater/kgSodium Silicate/kg
18034056700400100
Table 3. Material parameters.
Table 3. Material parameters.
Soil Layer Unit Weight/
kN/m3
Elastic Modulus/
MPa
Poisson’s RatioCohesion/
kPa
Friction
Angle/
°
Fill layer18.9150.401010
Silty clay19.3100.28025
Silty fine sand19.6250.311817
Strongly weathered mudstone21.0500.254530
Moderately weathered mudstone25.512000.2516026
Slightly weathered mudstone26.535000.1840030
Grouting2530000.2\\
C502534,5000.2\\
C352531,5000.2\\
Table 4. Deformation comparison of bridge piles.
Table 4. Deformation comparison of bridge piles.
ProjectWithout In-Tunnel Grouting ReinforcementWith in-Tunnel Grouting ReinforcementVariation (mm)Percentage Change
Peak value of bridge pile settlement (mm)0.050.01−0.04−80.0%
Peak value of bridge pile horizontal deformation (mm)2.540.82−1.72−67.7%
Table 5. Comparison of horizontal deformation of segments.
Table 5. Comparison of horizontal deformation of segments.
Tunnel Clearance ClassificationPre-Grouting SettlementPost-Grouting SettlementSettlement ReductionReduction Rate
Small Clearance Tunnels (<3 m)0.610.170.4472.1
Medium Clearance Tunnels (3–6 m)0.370.100.2773.0
Large Clearance Tunnels (>6 m)0.310.070.2477.4
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Li, X.; Li, H.; Cheng, Y.; Zhang, B.; Qiao, M.; Yang, T. Construction Scheme and Influence Analysis of Horizontal Small-Clear-Distance Shield Tunnel. Buildings 2025, 15, 2142. https://doi.org/10.3390/buildings15132142

AMA Style

Li X, Li H, Cheng Y, Zhang B, Qiao M, Yang T. Construction Scheme and Influence Analysis of Horizontal Small-Clear-Distance Shield Tunnel. Buildings. 2025; 15(13):2142. https://doi.org/10.3390/buildings15132142

Chicago/Turabian Style

Li, Xujie, Hui Li, Yabin Cheng, Bing Zhang, Ming Qiao, and Tao Yang. 2025. "Construction Scheme and Influence Analysis of Horizontal Small-Clear-Distance Shield Tunnel" Buildings 15, no. 13: 2142. https://doi.org/10.3390/buildings15132142

APA Style

Li, X., Li, H., Cheng, Y., Zhang, B., Qiao, M., & Yang, T. (2025). Construction Scheme and Influence Analysis of Horizontal Small-Clear-Distance Shield Tunnel. Buildings, 15(13), 2142. https://doi.org/10.3390/buildings15132142

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop