Next Article in Journal
Transfer Learning for Structural Health Monitoring in Bridges That Underwent Retrofitting
Previous Article in Journal
3D-Printed Clay Enhanced with Graphene Nanoplatelets for Sustainable and Green Construction
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Deformation and Strength Characteristics of Marine Soft Soil Treated by Prefabricated Vertical Drain-Assisted Staged Riprap under Seawall Construction

1
Faculty of Engineering, China University of Geosciences, Wuhan 430074, China
2
China Railway Eryuan Engineering Group Company Limited, Chengdu 610031, China
*
Author to whom correspondence should be addressed.
Buildings 2023, 13(9), 2322; https://doi.org/10.3390/buildings13092322
Submission received: 6 August 2023 / Revised: 2 September 2023 / Accepted: 9 September 2023 / Published: 13 September 2023
(This article belongs to the Section Building Structures)

Abstract

:
Prefabricated vertical drains (PVDs) with staged riprap preloading have been widely used in soft soil ground improvement and embankment construction. However, ground treatment effectiveness evaluation is still a difficult problem due to multiple factors. Considering this, in situ monitoring and numerical simulation were conducted to study the deformation and strength characteristics of marine soft soil ground treated by PVD-assisted staged riprap under the Lingni Seawall construction in China. Monitoring and analysis of results showed that use of PVD-assisted staged riprap resulted in a good improvement effect. In particular, in the PVD-treated zone within 10 m in depth, corresponding to a half-length of the PVD, the average radial degree of consolidation reached up to 75–100%, and the soil strength increased significantly by 200–700%. Moreover, numerical simulation showed that the linear 1-dimensional drain element of PVD closely met the engineering accuracy requirements with good consistency with the monitoring data. Compared with a totally solid element model, the numbers of elements and nodes were reduced and the calculating efficiency and model accuracy were increased by using a PVD linear element, which provides a basis for building large complex finite element models.

1. Introduction

With the development of the economy, many coastal cities need to carry out land reclamation [1]. Constructions on deep soft soils will result in significant post-construction settlement. Generally, the time allocated for treating the soft ground constitutes 30% to 40% of the overall process [2,3]. According to Terzaghi’s consolidation theory (1923) [4], the consolidation time is proportional to the square of the drainage distance. Therefore, setting vertical drainage wells in natural soil layers is a commonly used method to increase the number of drainage channels and to shorten drainage distances [5]. Prefabricated vertical drains (PVDs) have the advantages of being low carbon and of saving energy in the production process at a lower cost. Therefore, PVD-assisted preloading has been recognized as an efficient and economical soft ground improvement technique [6].
However, there is some confusion and uncertainty about PVD performance as well as appropriate project design and construction procedure due to various factors, including: (i) the smear zone [7]; (ii) bulking and clogging of the PVD [8]; (iii) soil inhomogeneity; and (iv) limitations of calculation theory. These factors have been identified in field operations and laboratory tests [9,10], and can lead to the relatively low reliability of project design [11].
In terms of facilitating PVD-assisted ground treatment, model testing, in situ monitoring, and numerical simulation are frequently used in evaluation by research and industrial communities [12,13]. Bo (2016) [10] demonstrated that current model-testing techniques for evaluating the optimal performance of PVD were limited. In situ monitoring, which involves confirming whether the required ground conditions have been achieved, can represent the actual situation considering the soil profile’s heterogeneity, the preloading, and the PVD used [14]. Consequently, it is considered a reliable method for accurately evaluating PVD performance [15].
Furthermore, numerical simulation has been widely employed to address the limitations of analytical approaches [16,17] in complex PVD-assisted preloading projects [18,19]. However, determination of the properties of the smear zone is a challenging task because of many uncertainties [20]. PVDs have usually been modeled as solid elements [21,22] in a plane-strain state [23], resulting in a large amount of calculation and a non-correspondence at the ground geometric position to the prototype model. Kan (2021) proposed a linear drain element for a PVD, representing it as a stagnant plane-strain unit cell [24]. Therefore, appropriate modeling of PVDs is very important in the numerical simulation of PVD-assisted drainage consolidation foundation treatment. It is a challenge to find a PVD model that includes consideration of the drainage consolidation effect, and, at the same time, avoids increasing the finite element nodes and the plane-strain equivalent transformation.
In this study, staged riprap loading combined with use of a PVD in the Lingni Seawall project was considered. The survey and monitoring data were extracted and used to develop a numerical model, aiming at minimizing the number of elements and nodes and increasing the computational efficiency and model accuracy without using the plane-strain equivalent transformation. The model used included a self-defined linear 1-dimensional PVD drain element by secondary development based on the UEL subroutine using the commercially available ABAQUS finite element software. The reliability of this simulation model was verified by comparing the outcomes with data obtained from the field. The consolidation, settlement, deformation, and strength characteristics of the PVD-treated soft ground were identified.

2. Project Description and Geological Characterization

2.1. Project Description

The Lingni Seawall project is located in Wenzhou, Zhejiang Province, China, as shown in Figure 1. The Lingni Seawall is a stone embankment connecting Lingkun Island and Niyu Island, with a total length of about 14.5 km (extending from N0 + 000 to N14 + 509). The embankment crest width is 10.5 m, with a crest elevation of 5.63 m according to the National Height Datum 1985 of China. The site is located in the Wenzhou Shoal of Wenzhou Bay, where the soil is often saturated. A combined PVD using a staged riprap preloading technique was adopted to reinforce the soft ground comprising the seawall foundation. The foundation treatment cross-section of the Lingni Seawall and the quincunx equilateral triangle pattern of the PVD are shown in Figure 2. The cross-section of the PVD used in this project was a rectangle of 100 mm width and 5 mm thickness.

2.2. Site Geological Characterization

The underlying ground exploration and boring data revealed that the profile was mainly comprised of soft marine soil [25,26] (Figure 3). Generally, the profile can be divided into four layers; the soil parameters corresponding to each layer are detailed in Table 1. It must be noted that, along the seawall, remarkable variations in the thicknesses and heterogeneity of the soil profile were observed. Therefore, the characteristics of each cross-section were extracted from the corresponding exploration data and used in this study. In total, 60 sections equipped with ground settlement observation out of 63 monitoring sections were selected. Furthermore, there were three in situ observation sections [27], namely, section N3 + 850, section N5 + 850, and section N11 + 050. The N5 + 850 cross-section is presented here, while sections N3 + 850 and N11 + 050 were analyzed and are discussed in the results. The soil parameters of section N5 + 850 are listed in Table 2.

3. Methods

Field monitoring and measurements were used to investigate the variations and regularity in the deformation and strength of the soft soil ground after applying the ground improvement. Moreover, numerical simulation was carried out based on the monitoring data, which can provide a reliable reference to guide similar projects during the design and construction stages [28].

3.1. In Situ Monitoring and Measurement

For controlling the riprap rate and monitoring the consolidation effectiveness of the Lingni Seawall, in situ monitoring and measurements of the ground surface settlement, the layered settlement, the horizontal displacement, the hydrostatic water level and the pore water pressure, and a field vane shear test, were performed. The layout and symbols of the monitoring sensors and measurement apparatus deployed in section N5 + 850 are shown in Figure 4. All the monitoring holes and sensors were embedded in the center of the area surrounded by the PVDs. The depth of the monitoring hole was about 30 m, equal to the thickness of the marine muck layer, which was considered the main deformation stratum. Settlement meters were set at 2 m intervals in the layered settlement monitoring hole. At the pore water pressure monitoring hole, pore water pressure piezometers were set every 3 m in the PVD-treated zone and every 5 m in the zone without PVD (the zone below the PVD-treated zone, namely, the non-PVD zone in this study).
Monitoring was performed for more than two years (about 750 days). Observations were carried out daily during the staged riprap loading until the settlement value was less than 2 mm/d. After that, monitoring was carried out once every 3 to 14 days depending on the observation results. Based on the monitoring data of the Lingni Seawall, the consolidation deformation characteristics, the dissipation regulation of the pore water pressures, and the strength improvement were analyzed both for the PVD-treated zone and for the non-PVD zone. The degree of consolidation and the consolidation coefficient of the soft marine soil were calculated and inversely evaluated using the monitoring data.

3.2. Numerical Simulation

3.2.1. Fundamental Assumptions

In this numerical simulation model, factors such as the seismic load, the traffic load, and the soil temperature sensitivity were ignored. In order to make the model calculation and analysis more straightforward, the following assumptions were made in this study: (i) the surface distribution of the riprap filling was uniform, ignoring the influence of temperature; (ii) the surface of each soil layer in the modeling section was relatively horizontal, and the soil material was isotropic; (iii) the stability of the simulated project was determined by the convergence of the model calculation results.

3.2.2. Model Scale and Boundary Conditions

A finite element model was established using ABAQUS software (Ver. 6.14, SIMULIA, Dassault, France). Considering the symmetry of the numerical model [22], only half of the Lingni Seawall was modeled. The deformation of the marine soft soil ground mainly occurred in the range of the soft soil layers under the Lingni Seawall, including the muck layer with a thickness of 30 m and the mucky clay layer with a thickness of 12 m. Furthermore, previous studies [29,30] have indicated that the horizontal width of the simulation model can be set at about two times the half-width of the embankment. Therefore, the model boundaries were set at 72 m from the embankment center in the horizontal direction and 42 m below the ground surface in the vertical direction to avoid boundary effects.
The left boundary of the model was the center line of the embankment. The left and right boundaries were undrained and fixed in the horizontal direction, while the bottom boundary was fixed in both the vertical and horizontal directions, and the upper boundary was a free surface. In the process of numerical simulation, the 3-dimensional problem was transformed into a 2-dimension plane strain problem. The mesh refinement was divided into elements by the plane strain pore pressure element type (CPE8RP), which meant that the 8-node quadrilateral element mesh was obtained by secondary reduced integration through structured mesh division. Furthermore, the meshes were more dense throughout the entire soil layers inside the range of the embankment than in the other areas. The riprap loading was applied step-by-step in the simulation process. The numerical model, assigned finite element mesh, and the boundary conditions of the embankment are illustrated in Figure 5.
Furthermore, the PVD model was constructed using a secondary development process with a self-defined drainage plate element based on the UEL subroutine provided by ABAQUS [31]. Unlike in other studies, the PVD was defined as a line element rather than a solid element [23], considering that the PVD cross-section was relatively small compared to its length and spacing. Therefore, by minimizing the number of elements and nodes, the PVD was modeled as a 1-dimensional drain element (AB) (Figure 5).

3.2.3. Constitutive Model

The materials involved in the Lingni Seawall numerical simulation included the PVD, geotextile, sand cushion, riprap, muck, and mucky clay. The PVD was modeled as a 1-dimensional linear elastic model. The geotextile was also set as an elastic material model and embedded in soils by beam element. The sand cushion and the riprap were represented by a Mohr–Coulomb elastic–plastic model. A modified Cam-Clay model was used for the muck and mucky clay.

3.2.4. Model Parameters

The elastic model parameters of the PVD were as follows: (i) the cross-sectional area of the PVD was 500 mm 2 ; (ii) the length of the PVD was 20 m; (iii) the modulus of elasticity of the PVD was 10 MPa; and (iv) the coefficient of permeability of the PVD was 0.001 cm/s.
Furthermore, as an elastic material, the geotextile was modeled using a beam element with a modulus of elasticity of 30 MPa.
The Mohr–Coulomb criterion was used to describe the sand cushion and the riprap with the parameters summarized in Table 3.
A modified Cam-Clay model was used for the muck and mucky clay [32]. The modified Cam-Clay model included the following parameters: unit weight ( γ ), coefficient of permeability (k h ), cohesion (c), internal friction angle ( ϕ ), compression index (Cc), Poisson’s ratio ( ν ), void ratio (e1), critical stress ratio (M), slope λ (compression indicator), slope κ (swelling indicator). M, λ and κ can be calculated using Equations (1) to (3), respectively. The modified Cam-Clay model parameters for all the soil layers in this numerical code are summarized in Table 4.
M = 6 sin ϕ / ( 3 sin ϕ )
λ = C c / l n 10
κ = 0.2 λ

3.2.5. PVD Modeling

A plane strain unit cell using a linear drain element of PVD was introduced by Kan (2021) [24], where the effect of drain size was converted to an equivalent reduction in the size of the smear zone surrounding the drain. In contrast, the adopted method did not assume a plane strain equivalent transformation but considered the drainage consolidation effect of the PVD, which avoided the need to increase the nodes. Only the axial force and the permeability of the PVD were included in the model, while the weight, shear, and torsion properties were not considered.
For the PVD element, the axial force and the water flow velocity along the rod length will only affect the displacement and water head of the rod end node, respectively. Therefore, it was considered that the displacement of the rod end node would not cause the PVD volume to change, and the change in the pore pressure of the node would also have no effect on the axial force of the PVD. By discretization of the continuity equation of the seepage of the PVD element, the combined matrix of mechanical stiffness and seepage for the PVD with a 2-node linear element can be obtained, as shown in Equation (4) [31]. Since the pore pressure at the node did not have a direction, the change caused by the direction of the seepage matrix did not need to be considered when the spatial transformation was performed. Therefore, Equation (4) can also be extended to the 3-dimensional matrix used for the 3-dimensional finite element simulation of the ground treatment with the PVD.
[ K ] = A L E 0 E 0 0 k t 0 k t E 0 E 0 0 k t 0 k t
where [K] is the combined stiffness matrix of the PVD; A is the cross-sectional area of the PVD; L is the length of the PVD; E is the modulus of elasticity of the PVD; k is the coefficient of permeability of the PVD; and t is the time.

4. Results and Discussion

4.1. Vertical Settlement Characteristics

The loading stages for various cross-sections were divided into four to eight levels to reliably consider the difference in the ground surface elevation and the soft soil settlement. For example, in section N5 + 850, the riprap loading process was divided into seven stages, as shown in Figure 6. The vertical settlements at the central axis of section N5 + 850 were obtained by CJP-3 and F-2 (Figure 4) monitoring data and plotted versus the results obtained numerically, as illustrated in Figure 6.
Figure 6 illustrates that the numerical simulation results agreed well with the monitoring data. Consequently, it can be concluded that the deployed model can accurately simulate the vertical settlement of soft soil ground treated by PVD-assisted staged riprap loading. The settlement of the surface and shallow soil layers had a similar stepped pattern following the applied staged loading. However, the gradual settlement pattern faded deeper in the soil profiles. Furthermore, according to the layered settlement monitoring data from three in situ observation sections, by accumulating the layered settlements in the PVD-treated zone (elevation from −1.8 m to −21.8 m) and the non-PVD zone (elevation from −21.8 m to −30.8 m), the vertical settlement in the PVD zone ( S P V D ) and the non-PVD zone ( S n o n P V D ) were determined. It was found that S P V D reached about 85% of the total settlement ( S t o t a l ), while S n o n P V D was limited to about 15% of S t o t a l , as summarized in Table 5. The comparison suggested that the consolidation settlement occurred mainly in the PVD-treated zone.

4.2. Horizontal Displacement Characteristics

The horizontal displacements at different elevations with time in CX-2 (Figure 4) of section N5 + 850, obtained from the monitoring data using an inclinometer and numerically, are plotted in Figure 7. It can be observed that the simulation results were in good agreement with the monitored data. Furthermore, the horizontal displacement mainly occurred in the PVD-treated zone, with a maximum displacement of 246 mm located at around −10 m elevation after 715 days of loading. This −10 m depth was equalt to about half of the used PVD length, while the horizontal displacement decreased sharply for the deeper soil layers and converged to zero at around −40 m elevation.
The filling height of the crest of the Lingni Seawall was higher than the berms, as shown in Figure 2. Before 130 d, the staged riprap loading was carried out simultaneously at the center and both sides (berms) of the embankment. When the berms reached the intended elevation, the riprap filling was stopped for the berms. After that, only the center part of the embankment continued to be riprap-loaded. Therefore, with the passage of construction time, the horizontal displacement curves in Figure 7 showed different variation trends due to different loading stages and time periods.
For −10 m (corresponding to the maximum displacement depth), the horizontal displacement increased with time and converged to a constant value after around 600 days. While for −26 m (representing the non-PVD zone), the horizontal displacement converged to a constant value only after 350 days, which mainly corresponded to the initial preloading stage, as shown in Figure 8.

4.3. Excess Pore Water Pressure Dissipation Regulations

The excess pore water pressure (Δu) at different elevations with time at K-2 of section N5 + 850, monitored using pore water pressure piezometers and obtained numerically, is plotted in Figure 9. It was found that the pore water pressure simulation results were consistent with the monitoring data. For the shallow soil ground in the PVD-treated zone, the pore water pressure increased quickly during the initial preloading stage and converged to zero once the loading became constant. Meanwhile, for the non-PVD zone, the excess pore water pressure increased slowly until reaching a constant value when the loading became constant for the deep soil layers and did not dissipate during the observation period. This phenomenon demonstrated the efficiency of utilizing PVDs to facilitate drainage for deep soft soils characterized by low permeability.
The deployed regulations of the excess pore water pressure dissipation utilizing the PVDs in the Lingni Seawall were investigated. Initially, the original consolidation state of the soft soil ground was analyzed under the hydrostatic water level and compared to the initial pore water pressure observations, as shown in Figure 10a. It can be observed that the initial pore water pressure almost coincided with the hydrostatic water pressure, which verified that the excess pore water pressure of the natural soil ground was almost zero. Then, by accumulating the increment in excess pore water pressure (Δu) at each staged loading (Δp), the relation curves between the cumulative excess pore water pressure ( Σ Δ u) and the load (P = Σ Δ p) could be drawn, as shown in Figure 10b. It can be seen that Σ Δ u in the muck layer increased almost linearly with the load increase. The regulations for the excess pore water pressure dissipation induced by loading with PVD were analogous to previously reported field observations and model testing reports [33,34]. Further analysis showed a remarkable variation between the pore pressure coefficient (Δup) and the cumulative load ( Σ Δ p), as shown in Figure 10c.
In Figure 10b, Σ Δ u/P shows a three-period variation that was found to be similar to the Δup variations illustrated in Figure 10c. In period 1 and period 3, the excess pore water pressure increment was less than the external load increment. During period 2, the excess pore water pressure increment was greater than or equal to the external load increment, as presented in Table 6. This was associated with the loading increment and rate during the staged loading. Among all the staged loadings, the fourth stage had the largest increment, resulting in a sharp increase in the excess pore water pressure within the muck layer, as demonstrated in Figure 9. Finally, it can be concluded that the staged loading rate and the riprap height can be controlled to ensure the safety and stability of the construction.

4.4. Influence of the PVD on the Degree of Consolidation

In this study, the average radial degree of consolidation ( U ¯ r ) was calculated using the measured excess pore water pressure ( u r e ) [35]. However, u r e corresponds to a particular point and at a specific time (t) and might not represent the average excess pore water pressure ( u ¯ r ). Therefore, to calculate U ¯ r , the coefficient ζ was introduced for conversion, as shown in Equation (5) below:
U ¯ r = u 0 u ¯ r u 0 = u 0 ζ · u r e u 0
where u 0 is the initiative excess pore water pressure; u ¯ r is the average radial excess pore water pressure at time t; u r e is the measured excess pore water pressure at a particular point in time t; and ζ = u ¯ r / u r e .
Then, coefficient ζ was obtained based on Barron’s analytical solution (1948) [36] under a constant strain condition following Equations (6) and (7):
u r = u ¯ r r e 2 F n [ r e 2 l n ( r r w ) r 2 r w 2 2 ]
F n = n 2 n 2 1 l n ( n ) 3 n 2 1 4 n 2
where u r is the radial excess pore water pressure at time t at a radial distance r; t is the consolidation time; r is the radial distance from the central axis of the vertical drain well; r e is the radius of the effective zone of drainage, as shown in Figure 2; r w is the radius of the vertical drain well; and n is the drain spacing ratio, expressed as n = r e / r w .
Furthermore, by transforming Equation (6), we can obtain Equation (8). In the Lingni Seawall monitoring plan, the pore water pressure cells were embedded in the center of the effective zone of the PVDs; so, when r = r e , u r = u r e , coefficient ζ can be calculated using Equation (9) as follows:
u ¯ r u r = r e 2 F n r e 2 l n ( r r w ) r 2 r w 2 2
ζ = u ¯ r u r e = r e 2 F n r e 2 l n ( r e r w ) r e 2 r w 2 2
where the PVD equivalent radius r w = 0.033 m adopted from Hansbo’s solution (1979) [37]. For PVDs in a quincunx equilateral triangle pattern with interval spacing (l) of 1.5 m, the radius of the effective zone of the PVDs [38] r e = 0.788 m; thus, n = 24. Finally, the coefficient ζ was found to equal 0.908.
Using Equation (5), U ¯ r at the different elevation (H) was calculated for section N5 + 850 and is plotted in Figure 11. It can be observed that U ¯ r obviously decreased with increase in the muck depth. The consolidation effect of the muck layer in the PVD zone was much better than that for the non-PVD zone. In particular, above −11.8 m elevation, corresponding to the half-length of the PVD, U ¯ r reached up to 75–100%. The results showed that the PVD was efficient for accelerating the consolidation drainage for the soft soil layers; however, the effective depth of the PVD may be different due to the complexity of the prevailing engineering conditions and of the construction process. For example, in section N5 + 850, at the range extending from −11.8 m to −21.8 m elevation, U ¯ r was limited to about 20–50%. However, in section N3 + 850 at −18 m elevation, U ¯ r reached up to 80%. The result for the consolidation effectiveness agreed, in general, with the findings of previous research [39].

4.5. Consolidation Coefficient under PVD Performance

The PVD-assisted staged riprap preloading method involved draining the excess pore water from the surrounding soil layer during the consolidation associated with the hydraulic gradients induced by the embankment preloading. Thus, the water filling the pores flowed easily toward the PVD in the horizontal direction, and then travelled freely along the PVD vertically toward the permeable drainage layer on the ground surface. The consolidation coefficient of the soil layer will change during the loading and draining process, and the actual value of the consolidation coefficient will be different from that measured in the laboratory before construction. Therefore, back-analysis was used to optimize the design and the model parameters based on the monitoring data recorded during the embankment construction [40]. According to Carrillo’s analytical solution (1942) [41] of the vertical drain model, the consolidation coefficient of the soil layers can be inversely calculated by the three-point method expressed in Equations (10) and (11) [42]. The three-point method is illustrated in Figure 12.
e β ( t 2 t 1 ) = S 2 S 1 S 3 S 2
β = 1 t 2 t 1 · l n ( S 2 S 1 S 3 S 2 ) = 2 C h F n r e 2 + π 2 C v 4 H v 2
where β is the coefficient of the drain conditions; S 1 , S 2 and S 3 are the settlements at time t 1 , t 2 and t 3 , respectively, and t 2 t 1 = t 3 t 2 ; F n and r e are annotated in Equations (6) and (7); C v and C h are the vertical and horizontal consolidation coefficients, respectively; and H v is the vertical drain distance.
Furthermore, by analyzing the experimental data from the oedometer tests using the square-root time method, the relationship between the vertical consolidation coefficient C v and the horizontal consolidation coefficient C h was determined with C h = 1.18 C v from our previous research [43]. Thus, the C v and C h values can be obtained using Equation (11) for each section, as summarized in Table 7. Comparing the back-calculation (bc) values of C v (bc) and C h (bc) to the values determined in the laboratory C v (test) and C h (test) [43], it was found that the inversely calculated value was larger than the test value. A good linear relationship was obtained by plotting the relation between the measured values versus the inversely calculated values, as shown in Figure 13.
Based on the relation illustrated in Figure 13, it was found that the drainage effect of the PVD and the riprap loading in the soft soil layers was accelerated, with the consolidation coefficient increasing by 1.4 times. The consolidation coefficient is a key parameter for consolidation calculation. It reflects the consolidation rate of soils. After PVD treatment, the consolidation rate of the soft soil ground was also obviously increased with increase in the consolidation coefficient in comparison to the non-PVD zone. Similar conclusions were also drawn in previous studies using back-analyses of the consolidation coefficient of PVD-improved soft clay from settlement data [44].

4.6. Strength Improvement under PVD Performance

A series of in situ vane shear tests were conducted on the natural muck soil before loading and at six different holes after staged loading to investigate the strength development of the reinforced ground. Holes VST-1, VST-2, and VST-3 correspond to after the berm loading stage, while holes VST-4, VST-5, and VST-6 (Figure 4) correspond to the full riprap loading conditions. The in situ vane shear strength results from section N5 + 850 are depicted in Figure 14. The strength development in the PVD zone was found to be greater than that in the non-PVD zone. Moreover, the strength improvement at the central axis was greater than that at the berms. Especially, at shallower than −11.8 m elevations, corresponding to the half-length of the PVD, the soil strength increased significantly up to 200–700%. The strength increased by 60–150% in the range of −11.8 m to −21.8 m elevation in the PVD zone. This pattern was analogous to the verified consolidation and settlement results, reflecting the strength improvement and ground stability. It must be noted that similar strength variation trends in vertical drain-improved clay deposits subjected to vacuum or surcharge loading have been reported in the literature [45,46].

4.7. Error and Evaluation Metrics Analysis of Numerical Simulation

To further evaluate the accuracy of the numerical simulation model, the mean absolute error (MAE) and the coefficient of determination or R-squared (R 2 ) were calculated, as presented in Table 8. All the simulation data had smaller MAE (1.870–7.461) and higher R 2 (0.962–0.998), which indicated that the model used and the assigned boundaries accurately estimated the vertical settlement, horizontal displacement, and excess pore water pressure. Compared with the totally solid element model, with the R 2 from 0.914 to 0.977 [30], the model accuracy and calculating efficiency were increased, and the numbers of elements and nodes were reduced by using the PVD linear element.

5. Conclusions

In situ monitoring and measurement, numerical simulation, analytical calculation and back-calculation, and theoretical analysis were conducted to assess the consolidation, settlement, deformation and strength characteristics of marine soft soil ground treated by staged riprap combined with PVD. The conclusions drawn are as follows:
(1)
The PVD-assisted riprap showed a good improvement effect for deep marine soft soil ground. In particular, in the PVD-treated zone within 10 m in depth, corresponding to the half-length of the PVD, the average radial degree of consolidation reached up to 75–100%, and the soil strength increased significantly by 200–700%.
(2)
Σ Δ u/P showed a three-period variation that was found to be similar to the Δup variations. Thus, the staged loading rate and the riprap height can be controlled to ensure the safety and stability of the seawall construction.
(3)
The numerical simulation data were closely aligned with the engineering accuracy requirements and showed a high level of consistency with the monitored data. Compared with the totally solid element model, a self-defined PVD linear 1-dimensional drain element reduced the numbers of elements and nodes, and increased the calculating efficiency and model accuracy.
(4)
However, since this study focused on a 2-dimensional embankment numerical simulation with a 1-dimensional drain element of PVD, the accuracy and applicability of 3-dimensional modeling of embankments with a linear element of PVD remains to be investigated and verified through more engineering case studies.

Author Contributions

Conceptualization, X.-T.W.; methodology, X.-T.W. and Z.-M.X.; software, J.-N.L. and Z.-M.X.; validation, J.-N.L.; formal analysis, X.-T.W.; investigation, X.-T.W. and J.-N.L.; data curation, X.-T.W., J.-N.L. and Z.-M.X.; writing—original draft preparation, X.-T.W.; writing—review and editing, X.-T.W. and J.-N.L.; visualization, J.-N.L. and Z.-M.X. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Natural Science Foundation of China (Grant Number 52178370 and 41602319), and the China Scholarship Council (Grant Number 202006415016).

Data Availability Statement

The data presented in this study are available on request from the corresponding author. The data are not publicly available due to ongoing research.

Acknowledgments

The authors are indebted to the First Highway Consultants Company Limited of the China Communications Construction Company and the Wenzhou Traffic and Transportation Bureau for their assistance in the field investigations of this project.

Conflicts of Interest

The authors declare no conflict of interest. The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript, or in the decision to publish the results.

References

  1. Nazir, R.; Moayedi, H.; Subramaniam, P.; Ghareh, S. Ground improvement using SPVD and RPE. Arab. J. Geosci. 2017, 10, 1–21. [Google Scholar] [CrossRef]
  2. Xia, C.Q.; Deng, Y.B.; Zhu, M.; Niu, J.J.; Zheng, L.K.; Chen, X.S. One-dimensional solar energy thermal consolidation model testing and analytical calculation for marine soft clays. J. Mar. Sci. Eng. 2022, 10, 1634. [Google Scholar] [CrossRef]
  3. Tang, J.F.; Xu, J.K.; Zhou, D.Z.; Huang, D.; Zeng, K.; Li, Y.H.; Chen, Z. Ground surface deformation caused by pipe jacking construction in a soft soil area: An experiment-based study. Buildings 2023, 13, 1628. [Google Scholar] [CrossRef]
  4. Terzaghi, K. Erdbaumechanik auf Bodenphysikalischer Grundlage; Franz Deuticke: Leipzig, Germany; Wien, Austria, 1925. [Google Scholar]
  5. Hore, R.; Chakraborty, S.; Ansary, M.A. A field investigation to improve soft soils using prefabricated vertical drain. Transp. Infrastruct. Geotechnol. 2020, 7, 127–155. [Google Scholar] [CrossRef]
  6. Cascone, E.; Biondi, G. A case study on soil settlements induced by preloading and vertical drains. Geotext. Geomembr. 2013, 38, 51–67. [Google Scholar] [CrossRef]
  7. Prabavathy, S.; Rajagopal, K.; Pitchumani, N. Investigation of smear zone around PVD mandrel using image-based analysis. Int. J. Geosynth. Ground Eng. 2021, 7, 1–16. [Google Scholar] [CrossRef]
  8. Deng, Y.B.; Liu, G.B.; Lu, M.M.; Xie, K.H. Consolidation behavior of soft deposits considering the variation of prefabricated vertical drain discharge capacity. Comput. Geotech. 2014, 62, 310–316. [Google Scholar] [CrossRef]
  9. Al-Homoud, A.S.; Tanash, N. Monitoring and analysis of settlement and stability of an embankment dam constructed in stages on soft ground. Bull. Eng. Geol. Environ. 2001, 59, 259–284. [Google Scholar] [CrossRef]
  10. Bo, M.W.; Arulrajah, A.; Horpibulsuk, S.; Chinkulkijniwat, A.; Leong, M. Laboratory measurements of factors affecting discharge capacity of prefabricated vertical drain materials. Soils Found. 2016, 56, 129–137. [Google Scholar] [CrossRef]
  11. Skempton, A.W.; Peck, R.B.; MacDonald, D.H. Settlement analyses of six structures in Chicago and London. Proc. Inst. Civ. Eng. 1955, 4, 525–542. [Google Scholar] [CrossRef]
  12. Liu, S.Y.; Cai, G.J.; Puppala, A.J.; Tu, Q.Z. Prediction of embankment settlements over marine clay using piezocone penetration tests. Bull. Eng. Geol. Environ. 2011, 70, 401–409. [Google Scholar] [CrossRef]
  13. Cheng, Y.; Cai, X.C.; Mo, H.Z.; Gu, M.X. Numerical analysis on the behavior of floating geogrid-encased stone column improved foundation. Buildings 2023, 13, 1609. [Google Scholar] [CrossRef]
  14. Arulrajah, A.; Bo, M.; Leong, M.; Disfani, M. Piezometer measurements of prefabricated vertical drain improvement of soft soils under land reclamation fill. Eng. Geol. 2013, 162, 33–42. [Google Scholar] [CrossRef]
  15. Park, H.I.; Kim, K.S.; Kim, H.Y. Field performance of a genetic algorithm in the settlement prediction of a thick soft clay deposit in the southern part of the Korean peninsula. Eng. Geol. 2015, 196, 150–157. [Google Scholar] [CrossRef]
  16. Namazi, E.; Mohamad, H.; Jorat, M.E.; Hajihassani, M. Investigation on the effects of twin tunnel excavations beneath a road underpass. Electron. J. Geotech. Eng. 2011, 16, 1–8. [Google Scholar]
  17. Han, K.H.; Wang, L.; Su, D.; Hong, C.Y.; Chen, X.S.; Lin, X.T. An analytical model for face stability of tunnels traversing the fault fracture zone with high hydraulic pressure. Comput. Geotech. 2021, 140, 104467. [Google Scholar] [CrossRef]
  18. Li, A.L.; Rowe, R.K. Combined effects of reinforcement and prefabricated vertical drains on embankment performance. Can. Geotech. J. 2001, 38, 1266–1282. [Google Scholar] [CrossRef]
  19. Parsa-Pajouh, A.; Fatahi, B.; Vincent, P.; Khabbaz, H. Trial embankment analysis to predict smear zone characteristics induced by prefabricated vertical drain installation. Geotech. Geol. Eng. 2014, 32, 1187–1210. [Google Scholar] [CrossRef]
  20. Chai, J.C.; Miura, N. Investigation of factors affecting vertical drain behavior. J. Geotech. Geoenviron. Eng. 1999, 125, 216–226. [Google Scholar] [CrossRef]
  21. Lu, M.M.; Sun, J.X. Analytical model for consolidation of soft ground improved by PVDs with air-boosted system. Comput. Geotech. 2022, 151, 104968. [Google Scholar] [CrossRef]
  22. Maleki, M.; Alielahi, H.; Rahmani, I. Effect of smear zone characteristics on PVD-improved soft soils using field data and numerical simulations. Indian Geotech. J. 2022, 52, 1391–1409. [Google Scholar] [CrossRef]
  23. Lin, S.; Fu, D.F.; Zhou, Z.F.; Yan, Y.; Yan, S.W. Numerical investigation to the effect of suction-induced seepage on the settlement in the underwater vacuum preloading with prefabricated vertical drains. J. Mar. Sci. Eng. 2021, 9, 797. [Google Scholar] [CrossRef]
  24. Kan, M.E.; Indraratna, B.; Rujikiatkamjorn, C. On numerical simulation of vertical drains using linear 1-dimensional drain elements. Comput. Geotech. 2021, 132, 103960. [Google Scholar] [CrossRef]
  25. GB 50021-2001; Code for Investigation of Geotechnical Engineering. China Architecture & Building Press: Beijing, China, 2009.
  26. Wu, X.T. Study on Engineering Properties and Consolidation Settlement Regularity of Soft-Soil in Wenzhou Shoal. Ph.D. Thesis, China University of Geosciences, Wuhan, China, 2010. [Google Scholar]
  27. SL 551-2012; Technical Specification for Earth-Rockfill Dam Safety Monitoring. China Water & Power Press: Beijing, China, 2012.
  28. Ye, G.B.; Xu, Y.; Zhang, Z. Performance evaluation of PVD-reinforced soft soil with surcharge and vacuum preloading. Int. J. Civ. Eng. 2018, 16, 421–433. [Google Scholar] [CrossRef]
  29. Jiang, M.; Bian, X.C.; Wu, J.G.; Jian-Wu, H.; Chen, Y.M.; Chen, R.P. Field measurement and numerical simulation of estuarine deposit settlements under embankment loads. Chin. J. Rock Mech. Eng. 2010, 29, 1060–1067. [Google Scholar]
  30. Zhan, X.J.; Gao, C.S.; Zhu, Q.F.; Yang, S.H.; Pang, B. Numerical analysis of breakwater construction on soft clay in harbor area of Lianyungang Port. Chin. J. Geotech. Eng. 2017, 39, 2109–2115. [Google Scholar]
  31. Fei, K.; Zhang, W.J. ABAQUS Application in Geotechnical Engineering; China Water & Power Press: Beijing, China, 2010. [Google Scholar]
  32. Wood, D.M. Soil Behaviour and Critical State Soil Mechanics; Cambridge University Press: Cambridge, UK, 1990. [Google Scholar]
  33. Lorenzo, G.; Bergado, D.; Bunthai, W.; Hormdee, D.; Phothiraksanon, P. Innovations and performances of PVD and dual function geosynthetic applications. Geotext. Geomembr. 2004, 22, 75–99. [Google Scholar] [CrossRef]
  34. Chen, H.; Chu, J.; Guo, W.; Wu, S.F. Land reclamation using the horizontal drainage enhanced geotextile sheet method. Geotext. Geomembr. 2023, 51, 131–150. [Google Scholar] [CrossRef]
  35. Hou, J.F. Calculation of Consolidation Degree of Soil Mass with Pore Water Pressure Measured in Vacuum Preloading Works; China Harbour Engineering: Hong Kong, China, 2005; pp. 13–15. [Google Scholar]
  36. Barron, R.A. Consolidation of fine-grained soils by drain wells by drain wells. Trans. Am. Soc. Civ. Eng. 1948, 113, 718–742. [Google Scholar] [CrossRef]
  37. Hansbo, S. Consolidation of clay by bandshaped prefabricated drains. Ground Eng. 1979, 12, 16–27. [Google Scholar]
  38. Liu, Z.; Gao, Y.; Liao, J.; Zhou, C.Y. Stochastic medium model for the settlement calculation of prefabricated vertical drains of soft soil foundations in the coastal area of south China. J. Mar. Sci. Eng. 2022, 10, 867. [Google Scholar] [CrossRef]
  39. Ong, C.Y.; Chai, J.C.; Hino, T. Degree of consolidation of clayey deposit with partially penetrating vertical drains. Geotext. Geomembr. 2012, 34, 19–27. [Google Scholar] [CrossRef]
  40. Huang, S.; Huang, J.S.; Kelly, R.; Jones, M.; Kamruzzaman, A. Predicting settlement of embankments built on PVD-improved soil using Bayesian back analysis and elasto-viscoplastic modelling. Comput. Geotech. 2023, 157, 105323. [Google Scholar] [CrossRef]
  41. Carrillo, N. Simple two and three dimensional case in the theory of consolidation of soils. J. Math. Phys. 1942, 21, 1–5. [Google Scholar] [CrossRef]
  42. Zeng, G.X.; Yang, X.L. Settlement analysis of sand-drained ground. J. Zhejiang Univ. 1959, 3, 34–72. [Google Scholar]
  43. Wu, X.T. Research on relation between consolidation coefficient and consolidation stress of silt in Wenzhou shoal. Rock Soil Mech. 2013, 34, 1675–1680. [Google Scholar]
  44. Voottipruex, P.; Bergado, D.; Lam, L.; Hino, T. Back-analyses of flow parameters of PVD improved soft Bangkok clay with and without vacuum preloading from settlement data and numerical simulations. Geotext. Geomembr. 2014, 42, 457–467. [Google Scholar] [CrossRef]
  45. Chai, J.C.; Shen, J.S.L.; Liu, M.D.; Yuan, D.J. Predicting the performance of embankments on PVD-improved subsoils. Comput. Geotech. 2018, 93, 222–231. [Google Scholar] [CrossRef]
  46. Zhang, Z.; Ye, G.B.; Xu, Y. Comparative analysis on performance of vertical drain improved clay deposit under vacuum or surcharge loading. Geotext. Geomembr. 2018, 46, 146–154. [Google Scholar] [CrossRef]
Figure 1. Location of the Lingni Seawall (Google Maps).
Figure 1. Location of the Lingni Seawall (Google Maps).
Buildings 13 02322 g001
Figure 2. Foundation treatment cross-section of the Lingni Seawall.
Figure 2. Foundation treatment cross-section of the Lingni Seawall.
Buildings 13 02322 g002
Figure 3. Typical stratum profile of marine soft soils at project site.
Figure 3. Typical stratum profile of marine soft soils at project site.
Buildings 13 02322 g003
Figure 4. Layout of monitoring sensors and measurement apparatus in section N5 + 850.
Figure 4. Layout of monitoring sensors and measurement apparatus in section N5 + 850.
Buildings 13 02322 g004
Figure 5. Finite element model with boundary conditions and mesh technology of the Lingni Seawall.
Figure 5. Finite element model with boundary conditions and mesh technology of the Lingni Seawall.
Buildings 13 02322 g005
Figure 6. Monitoring and simulation curves of vertical settlements in section N5 + 850.
Figure 6. Monitoring and simulation curves of vertical settlements in section N5 + 850.
Buildings 13 02322 g006
Figure 7. Monitoring and simulation curves of horizontal displacements in CX-2 of section N5 + 850.
Figure 7. Monitoring and simulation curves of horizontal displacements in CX-2 of section N5 + 850.
Buildings 13 02322 g007
Figure 8. Horizontal displacements with time in CX-2 of section N5 + 850.
Figure 8. Horizontal displacements with time in CX-2 of section N5 + 850.
Buildings 13 02322 g008
Figure 9. Monitoring and simulation curves of pore water pressure at K-2 of section N5 + 850.
Figure 9. Monitoring and simulation curves of pore water pressure at K-2 of section N5 + 850.
Buildings 13 02322 g009
Figure 10. Excess pore water pressure dissipation regulations at K-2 of section N5 + 850: (a) Initial pore water pressure and hydrostatic water pressure; (b) Cumulative excess pore pressure with load; (c) Pore pressure coefficient with load.
Figure 10. Excess pore water pressure dissipation regulations at K-2 of section N5 + 850: (a) Initial pore water pressure and hydrostatic water pressure; (b) Cumulative excess pore pressure with load; (c) Pore pressure coefficient with load.
Buildings 13 02322 g010
Figure 11. Degree of consolidation with elevation of section N5 + 850.
Figure 11. Degree of consolidation with elevation of section N5 + 850.
Buildings 13 02322 g011
Figure 12. Three-point method for back-calculation of the consolidation coefficient.
Figure 12. Three-point method for back-calculation of the consolidation coefficient.
Buildings 13 02322 g012
Figure 13. Relationship between back-calculation values and test values of the consolidation coefficient.
Figure 13. Relationship between back-calculation values and test values of the consolidation coefficient.
Buildings 13 02322 g013
Figure 14. In situ vane shear strength in section N5 + 850.
Figure 14. In situ vane shear strength in section N5 + 850.
Buildings 13 02322 g014
Table 1. Soil parameters of each layer at project site.
Table 1. Soil parameters of each layer at project site.
Soil LayerThickness, h (m)Allowable Bearing Capacity, F (kPa)Ultimate Friction Resistance, τ (kPa)
Muck3.8–33.545–6010–12
Mucky clay1.0–21.760–7015–18
Clay1.8–22.080–10020–25
Silty clay1.5–30.3140–18033–45
Table 2. Soil parameters of section N5 + 850 of Lingni Seawall.
Table 2. Soil parameters of section N5 + 850 of Lingni Seawall.
Soil LayerThickness, h (m)Unit Weight, γ (kN/m 3 )Natural Water Content, ω (%)Modulus of Compression, Es* (MPa)Compression Index, Cc*
Muck30.016.1765.61.880.556
Mucky clay12.017.1548.72.480.391
Clay8.517.6437.22.920.228
Silty clay>10.018.3330.93.700.121
* This value corresponds to the compressive stress between 100 kPa and 200 kPa.
Table 3. Mohr–Coulomb model parameters for the sand cushion and riprap.
Table 3. Mohr–Coulomb model parameters for the sand cushion and riprap.
Mohr–Coulomb Model ParametersSand CushionRiprap
Unit weight, γ (kN/m 3 )18.321.0
Cohesion, c (kPa)1.029.3
Internal friction angle, ϕ ( )40.036.4
Modulus of elasticity, E (MPa)2050
Table 4. Modified Cam-Clay model parameters for soil layers in numerical code.
Table 4. Modified Cam-Clay model parameters for soil layers in numerical code.
Modified Cam-Clay Model ParametersMuckMucky Clay
Unit weight, γ (kN/m 3 )16.1717.15
Coefficient of permeability, k h (10 4 m/d)8.644.23
Cohesion, c (kPa)4.08.1
Internal friction angle, ϕ ( )1525
Compression index, Cc0.5560.391
Poisson’s ratio, ν 0.350.33
Void ratio, e1 (when p = 1 kPa)1.600.78
Critical stress ratio, M0.5660.983
Slope λ (compression indicator)0.240.17
Slope κ (swelling indicator)0.0480.034
Table 5. Statistics of layered settlements in the PVD-treated zone and the non-PVD zone.
Table 5. Statistics of layered settlements in the PVD-treated zone and the non-PVD zone.
Layered Settlement Monitoring Position S PVD / S total (%) S non PVD / S total (%)
F-1 in N3 + 85084.415.6
F-2 in N3 + 85087.412.6
F-3 in N3 + 85085.614.4
F-1 in N5 + 85080.419.6
F-2 in N5 + 85085.914.1
F-3 in N5 + 85086.613.4
F-1 in N11 + 05083.216.8
F-2 in N11 + 05086.113.9
F-3 in N11 + 05082.717.3
Mean value84.715.3
Table 6. The three-period variation in excess pore water pressure with load.
Table 6. The three-period variation in excess pore water pressure with load.
Variation PeriodLoading Period Σ Δ u/P Δ u/ Δ p
Period 1Initial loading period<1<1
Period 2Mid-loading period=1≥1
period 3End-loading period<1<1
Table 7. Back-calculation of the consolidation coefficient.
Table 7. Back-calculation of the consolidation coefficient.
Section β ( 10 7  s 1 ) C v (bc) ( 10 4  cm 2 /s) C h (bc) ( 10 4  cm 2 /s)
N3 + 8501.76810.8612.82
N5 + 8501.4919.1710.82
N11 + 0501.5569.5611.28
Table 8. Error and evaluation metrics analysis of numerical simulation model.
Table 8. Error and evaluation metrics analysis of numerical simulation model.
ParameterElevation or TimeMAER 2
Vertical settlement−1.8 m2.8500.998
−13.8 m2.6900.994
−27.8 m2.1530.962
Horizontal displacement130 d7.4610.979
335 d6.4560.990
715 d5.8020.991
Excess pore water pressure−3.8 m1.8700.977
−15.8 m3.4910.983
−25.8 m3.0160.980
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Wu, X.-T.; Liu, J.-N.; Xie, Z.-M. Deformation and Strength Characteristics of Marine Soft Soil Treated by Prefabricated Vertical Drain-Assisted Staged Riprap under Seawall Construction. Buildings 2023, 13, 2322. https://doi.org/10.3390/buildings13092322

AMA Style

Wu X-T, Liu J-N, Xie Z-M. Deformation and Strength Characteristics of Marine Soft Soil Treated by Prefabricated Vertical Drain-Assisted Staged Riprap under Seawall Construction. Buildings. 2023; 13(9):2322. https://doi.org/10.3390/buildings13092322

Chicago/Turabian Style

Wu, Xue-Ting, Jun-Ning Liu, and Zhi-Min Xie. 2023. "Deformation and Strength Characteristics of Marine Soft Soil Treated by Prefabricated Vertical Drain-Assisted Staged Riprap under Seawall Construction" Buildings 13, no. 9: 2322. https://doi.org/10.3390/buildings13092322

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop