Next Article in Journal
Does the Inter-Provincial Floating Population Affect Regional Economic Development in China? An Empirical Analysis
Next Article in Special Issue
A Bi-Level Optimization Model for Hydrogen Station Location Considering Hydrogen Cost and Range Anxiety
Previous Article in Journal
Reducing Ammonia Emissions in Polish Agriculture, the Implementation of the NEC Directive, and the Context of Sustainable Development—Pilot Studies
Previous Article in Special Issue
Achieving Pareto Optimum for Hybrid Geothermal–Solar (PV)–Gas Heating Systems: Minimising Lifecycle Cost and Greenhouse Gas Emissions
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Mitigation of Photovoltaics Penetration Impact upon Networks Using Lithium-Ion Batteries

by
Khalid Abdullah Bin Hudayb
1,
Abdullah M. Al-Shaalan
1 and
Hassan M. Hussein Farh
2,*
1
Electrical Engineering Department, College of Engineering, King Saud University, Riyadh 11421, Saudi Arabia
2
Electrical Engineering Department, College of Engineering, Imam Mohammad Ibn Saud Islamic University, Riyadh 11564, Saudi Arabia
*
Author to whom correspondence should be addressed.
Sustainability 2024, 16(16), 7141; https://doi.org/10.3390/su16167141
Submission received: 8 May 2024 / Revised: 18 July 2024 / Accepted: 14 August 2024 / Published: 20 August 2024
(This article belongs to the Special Issue Sustainable Energy System: Efficiency and Cost of Renewable Energy)

Abstract

:
The paper conducts a comprehensive analysis of the impact of very large-scale photovoltaic generation systems on various aspects of power systems, including voltage profile, frequency, active power, and reactive power. It specifically investigates IEEE 9-bus, 39-bus, and 118-bus test systems, emphasizing the influence of different levels of photovoltaic penetration. Additionally, it explores the effectiveness of battery energy storage systems in enhancing system stability and transient response. The transition to PV generation alters system stability characteristics, impacting frequency response and requiring careful management of PV plant locations and interactions with synchronous generators to maintain system reliability. This study highlights how high penetration of photovoltaic systems can improve steady-state voltage levels but may lead to greater voltage dips in contingency scenarios. It also explores how battery energy storage system integration supports system stability, showing that a balance between battery energy storage system capacity and synchronous generation is essential to avoid instability. In scenarios integrating photovoltaic systems into the grid, voltage levels remained stable at 1 per unit and frequency was tightly controlled between 49.985 Hz and 50.015 Hz. The inclusion of battery energy storage systems further enhanced stability, with 25% and 50% battery energy storage system levels maintaining strong voltage and frequency due to robust grid support and sufficient synchronous generation. At 75% battery energy storage system, minor instabilities arose as asynchronous generation increased, while 100% battery energy storage system led to significant instability and oscillations due to minimal synchronous generation. These findings underline the importance of synchronous generation for grid reliability as battery energy storage system integration increases.

1. Introduction

In the face of escalating climate change and its associated calamities, the urgent transition from fossil fuel-based energy systems to renewable sources stands out as a paramount endeavor for global sustainability and environmental preservation. The integration of renewable energy, notably solar and wind, into the power grid necessitates the development of robust transmission lines capable of handling increased loads and facilitating efficient energy distribution across vast regions [1]. This shift is not merely an environmental imperative but also a strategic move to ensure energy security, reduce greenhouse gas emissions, and foster economic resilience in the face of the depleting fossil fuel reserves [2]. Despite the critical benefits, the transition is fraught with challenges, including the need for substantial infrastructure overhaul, the integration of variable energy sources, and addressing the burgeoning electricity demands of modern societies [2]. The urgency to act is further compounded by the stark warnings from scientific communities regarding the irreversible impacts of climate change, highlighting the need for immediate and decisive action to safeguard our planet for future generations [3].
The existing body of research on renewable energy integration into power systems has laid a foundational understanding of the complexities involved in the transition. Modal analysis and sensitivity methods have been instrumental in assessing the effects of photovoltaic (PV) generation on power system stability, highlighting how increased PV penetration influences the damping of dominant modes and affects inter-area stability [4]. These studies have significantly contributed to understanding the dynamic behavior of power systems with high levels of PV integration [5].
Despite advancements, notable gaps persist in the research, especially regarding the comprehensive effects of very large-scale photovoltaic (VLS-PV) generation on power system performance. Although a number of studies have examined the frequency and voltage response of power systems to PV generation, there is a shortage of thorough analysis on how VLS-PV systems interact with the wider power grid. This includes investigating nonlinear behaviors, impacts on voltage stability, and overall system resilience to disturbances [6,7,8,9,10,11,12]. The literature on integrating renewable energy into power grids serves as a detailed guide for energy practitioners, emphasizing the importance of addressing key questions and conducting in-depth analyses before implementing renewable integration strategies. Katz et al. [13] highlighted the necessity of capacity expansion, production cost, and power flow analyses, taking into account various future scenarios to ensure a well-planned transition. This comprehensive approach is vital for the effective integration of renewables into the grid, stressing the need for detailed planning and scenario analysis to manage the complexities of renewable energy systems integration [14].
Moreover, the integration of Battery Energy Storage Systems (BESS) alongside PV systems opens new avenues for stabilizing the grid against the inherent intermittency of solar energy. In particular, lithium-ion batteries have emerged as a cornerstone technology due to their superior energy density, longevity, and efficiency. Despite this potential, the economic aspects, including the cost and financial viability of large-scale storage solutions, remain areas needing further exploration. Additionally, variations in study findings attributed to differences in system modeling, scenarios of renewable installation, and disturbance analysis underscore the necessity for a more standardized and holistic approach to evaluating renewable integration impacts on power system performance [13,15].
In the context of Battery Energy Storage Systems (BESS), Bowen et al. [16] provided insights into the pivotal role of BESS in enhancing grid stability and flexibility. Their study underscores the importance of scaling BESS in relation to the grid’s existing generation mix and the dynamic profiles of demand and renewables. It also delineates the critical attributes and services provided by BESS, such as energy arbitrage, firm capacity, and ancillary services, highlighting the economic and operational benefits of integrating BESS into the power system. Furthermore, Mobolaji Bello et al. [17] provided practical examples through case studies, demonstrating the optimization of storage systems in terms of size, location, and operations, thereby showcasing the tangible benefits and challenges of BESS implementation in real-world settings.
The literature also addresses the economic considerations of energy storage, with studies by the Electric Power Research Institute [18] and Kendall Mongird et al. [19] comparing the costs and performances of various battery technologies. These studies advocate for lithium-ion batteries as the most cost-effective and high-performing option, despite ongoing supply chain challenges; additionally, the integration of renewables and BESS within regulatory frameworks such as the Saudi Grid Code [20] and their impact on system stability and dynamics [21,22,23] have been extensively discussed. These discussions highlight the complex balance between technological advancements, economic feasibility, regulatory compliance, and the overarching goal of establishing a sustainable and resilient power system as renewable energy sources become increasingly integrated [24].
In summary, although substantial progress has been made in understanding the impacts of renewable energy integration on power systems, there is still a crucial need for comprehensive, detailed, and standardized research. This is vital for not only advancing technical knowledge but also guiding policy decisions, investment strategies, and infrastructure development plans to facilitate a smooth, efficient, and sustainable shift to renewable energy.
This paper aims to bridge the identified gaps through the following main contributions and objectives:
  • Comprehensive analysis of PV and BESS integration: We conduct an exhaustive study on the integration of PV systems and BESS into existing transmission systems across selected case studies (IEEE Test bus systems 9, 39, and 118), emphasizing dynamic effects and stability implications.
  • Impact assessment at various PV penetration levels: We evaluate the effects of varying PV penetration levels on power system parameters, including voltage, frequency, and power stability, while integrating BESS to mitigate stability issues.
  • Dynamic stability exploration: We investigate the dynamic stability of power systems under high PV penetration scenarios, focusing on frequency response and voltage stability as well as the role of BESS in enhancing system resilience.
  • Standardization of evaluation methodologies: We propose a standardized approach for assessing the impacts of PV system integration on power systems while considering the variability in system modeling and disturbance responses.
These objectives are designed to advance the understanding of PV, both integration with and without BESS, into transmission power systems in the context of the outstanding technical challenges in order to ensure a stable, efficient, and sustainable energy transition.
This paper’s structure beyond the introduction is as follows: Section 2 delves into power system dynamics, covering models for transmission lines, PV systems, BESS, and analyses of power flow and dynamic stability; Section 3 outlines a nine-step methodology for assessing PV and BESS integration into power systems; Section 4 describes the simulation setup; Section 5 examines the effects of varied PV penetration and BESS integration through IEEE 9, 39, and 118 bus system case studies, focusing on system stability and performance; Section 6 presents case study results, showing how PV and BESS levels affect system voltage, frequency, and stability, especially under fault conditions; finally, Section 7 concludes by advocating for PV and BESS integration as a strategy for enhancing grid stability and supporting renewable energy transition, stressing the importance of continued research to address challenges and optimize future grid operations.

2. Mathematical Modeling

The behaviour of electrical power systems is characterized mathematically by nonlinear differential–algebraic equations (DAEs), which offer a comprehensive framework for simulating and analysing system dynamics [25].

2.1. Transmission Line Model

Transmission lines within transmission systems are commonly represented using the two-port network concept, which incorporates two sets of terminals. This two-port network is sometimes referred to as a four-terminal network or quadrupole network. In this framework, port 1 typically functions as the input port, while port 2 serves as the output port. A two-port network model is employed to analyze electrical circuits mathematically by breaking down larger circuits into smaller and more manageable segments. Conceptually, the two-port operates as a ‘black box’, with its properties defined by an input/output matrix. These networks are inherently linear, allowing the principle of superposition to be applied [26]. The mathematical representation of the ABCD parameters is strongly dependent on the length of the transmission lines, as summarised in Table 1.

2.2. PV System Model

This research utilizes Large-Scale Solar Photovoltaic (LSPV) plants, drawing insights from various sources. A key assumption of the model is the exclusion of dynamics associated with the DC side of the inverter system, including the PV array, the inverter’s DC link, and the voltage regulator. This simplification is made on the grounds that the time constants of these components are relatively short, requiring integration time constants that are impractically small for simulations, which complicates maintaining numerical stability in positive-sequence simulation environments. For load flow analysis, the model consolidates the AC side of the inverters into a single generator representation at a low voltage level. This voltage is then stepped up to match the internal medium-voltage collector grid and further elevated to integrate with the grid at the point of connection through one or more main step-up transformers, as shown in Figure 1. This approach simplifies the simulation of LSPV plant interactions with the larger power system, making it more manageable and less computationally intensive [27].
In this context, the inverters are typically modeled using a standard method in which they act as controllable sources of power injection for each individual phase. Overall, this approach outlines the inverter’s model as [28]
S p v = P p v + j Q p v ,
where S p v stands for the three-phase apparent power of the PV system and P p v and Q p v represent the active AC and reactive PV powers.
A basic inverter lacking an intelligent controller solely supplies active power while maintaining a unity power factor, leading to the equation S p v = P p v . The determination of P p v involves a couple of assumptions. Initially, the inverter efficiency can be ascertained for every given value of P p v . η i n v e r t e r as specified in the inverter’s datasheet. This efficiency is then multiplied by the DC PV power at the maximum power point ( P p v , m p p ) value, formulated as follows [28]:
P p v = ϕ ϕ P p v , ϕ = ϕ ϕ P ϕ p v , m p p . η i n v e r t e r ϕ .

2.3. BESS Model

The Exact-MILP (Mixed Integer Linear Programming) formulation provides a comprehensive approach for managing a Battery Energy Storage System (BESS) within the power grid, emphasizing critical operational parameters for optimal utilization. It incorporates backlog energy, ensuring that unused energy is efficiently stored for future use, thereby managing the battery’s storage capacity. The model regulates charging and discharging rates to keep the BESS operating within its technical limits while optimizing performance. Additionally, it enforces minimum and maximum energy states to protect battery health and prolong lifespan. The operational modes of the BESS—charging, discharging, and idle—are controlled by the binary variables z and y, where z = 1 , y = 0 represents charging, z = 0 , y = 1 represents discharging, and z = 0 , y = 0 represents an idle state. Importantly, the model includes a constraint to prevent simultaneous charging and discharging, ensuring that such physically impossible conditions are excluded from operational planning.
As an MILP this formulation introduces additional complexity; however, it is crucial for nuanced BESS management in the power system, ensuring strategic and efficient operation. The mathematical representation of the BESS state of charge (e) can be provided as follows [29]:
e = E 0 + η c p c 1 η d p d
where E 0 stands for the initial energy in the BESS, p c and p d represent the charging and discharging powers, and η c and η d are the charging and discharging efficiencies.

2.4. Power Flow Analysis

In modern power systems, managing bus voltages and power flow is essential. Because power flow is proportional to the square of the voltage, controlling both variables presents a nonlinear challenge. Power engineering employs power flow studies or load flow studies to numerically analyze the electric power flow within interconnected systems.
These studies typically involve steady-state analysis using simplified notation such as one-line diagrams and per-unit systems. They address various aspects of AC power parameters such as voltages, voltage angles, active power, and reactive power. Power flow analysis (PFA) is crucial during power system planning as well as during expansion and modifications to meet current and future load demands.
PFA helps to determine power flows and voltage levels under normal operating conditions, providing valuable insights into system operation and control setting optimization. This optimization aims to maximize capacity while minimizing operating costs. PFA is usually conducted under balanced three-phase steady-state conditions using specialized software such as PSSE, ETAP, CYME, Power World, or CAPE.
Such software calculates voltage magnitudes and phases at each bus in a power system along with real and reactive power flows (P and Q) for all loads, buses, and equipment losses. Load flow analysis is essential for optimizing existing system operations, planning future expansions, and designing new power systems, as it ensures efficient and reliable electricity transmission and distribution. The complex power equation can be represented as
S k = P k + j Q k = V k e j θ k m = 1 n Y k m e j δ k m V m e j θ m * ,
where S k is the complex power at bus k, P k is the active power at bus k, Q k is the reactive power at bus k, V k is the voltage at bus k, Y k m is the admittance between bus k and bus m, δ k m is the angle difference between bus k and bus m, V m is the voltage at bus m, and θ m is the voltage angle at bus m.
Expanding the complex power summation into real and imaginary parts and associating these with P and Q, respectively, provides the fundamental PFA equations
P k = m = 1 n V k V m Y k m cos θ k θ m + δ k m ,
Q k = m = 1 n V k V m Y k m sin θ k θ m + δ k m ,
where θ k is the voltage phase angle at bus k.

2.5. Dynamic Stability Analysis

Dynamic stability refers to a system’s ability to remain stable amid sudden changes or disturbances such as short-circuits, generator losses, load fluctuations, or line tripping. In large-scale PV systems, significant power oscillations may occur but gradually dissipate. These oscillations mainly arise from imbalances between power demand and generation. In the local plant mode, a single generator oscillates relative to the rest of the system, affecting both the generator and the connecting grid line. For modeling, the system is often represented as a constant voltage source connected to the grid. Extensive simulations were conducted to evaluate the impact of the large-scale PV system on power system voltage stability. Dynamic stability analysis is essential for assessing the network’s stability amid continuous small disturbances, with load switching being a common example [30].
Mathematical modeling for dynamic voltage stability analysis typically involves a set of differential and algebraic equations [31], denoted as Equation (7) and Equation (8), respectively, where the system’s state vector is represented by ‘x’ (state variable) and the bus voltages vector by ‘y’ (algebraic variable). Additionally, the control variable is represented as λ . These equations are dynamically solved using numerical integration and power flow analysis methods, providing insights into the system’s behavior under various conditions [24].
d y d x = f x , y , λ
g x , y , λ = 0
To determine the steady-state equilibrium values ( x 0 , y 0 ) for small disturbances in the dynamic system, we set the derivative in Equation (7) to zero. Equation (7) and Equation (8) are then expressed as shown in Equation (9) and Equation (10) [32]. By eliminating Δ y , the linearized state equation can be represented as shown in Equation (11) and Equation (12). Dynamic voltage stability is achieved by minimizing the oscillation of the state and network variables. The magnitude of these oscillations can be expressed using the output vector in Equation (13), where y r is the reference value of y and the A ˜ matrix has distinct eigenvalues. Then, Δ x is expressed by modes in Equation (14), where S j is the jth eigenvalue of A ˜ and u j and v j are the corresponding n × 1 and 1 × n eigenvectors. The output vector can be represented as shown in Equation (15) and Equation (16).
Δ X d t = A Δ x + B Δ y
0 = C Δ x + D Δ y
d Δ x d t = A B D 1 C Δ x = A ˜ Δ x
Δ y = D 1 C Δ x = C ˜ Δ x
z t = C ˜ Δ x + y s y r
Δ x t = j = 1 n v j Δ x u u j . e S j t
z t = j = 1 n C ˜ j Δ x j t + z 0 = j = 1 n z j t + z 0
z j t = j = 1 n z j . i t = C ˜ j j = 1 n v i Δ x 0 . u j . i . e S j t
The error trajectory z t is decomposed into several system modes [33]. The voltage characteristics at each bus depend solely on the internal voltages and rotor angles, encapsulated in the matrix A ˜ [34]. The system’s performance can be evaluated as follows:
J p = j = 0 n J j ,
where,
J j = 0 T z j , i t W j Z j , i * d t ,
where T is the integration time interval, W is the weighting matrix for the jth state, t denotes transpose, and ∗ signifies conjugate. This equation focuses on the model components related to internal voltage and rotor angle in order to streamline the calculations and reduce the computational time.
Dynamic voltage stability can be assessed by analyzing the eigenvalues of A ˜ . To ensure practical results, dynamic stability is observed by simulating various parameters, including the network terminal voltage of the PV bus, generator’s angle, generator’s current and output electrical power, and terminal voltage at the weakest bus.

3. Methodology

The research methodology to address the objectives of this research work are carried out through nine steps, which can be summarised as follows:
Step 1.
Data Collection and Cleaning
Gather relevant data, including system parameters, load profiles, generation data, PV characteristics, and any other pertinent information. Clean the collected data to ensure accuracy and consistency.
Step 2.
Creating SLD based on the SAV case data
Develop a one-line diagram representation of the power system incorporating generators, loads, transmission lines, transformers, and proposed PV and BESS installations.
Step 3.
Run Power Flow
Conduct a power flow analysis to determine the steady-state operating conditions of the system under normal circumstances.
  • Identification of Weak Buses
    Begin by identifying weak buses within the power system network. Weak buses typically refer to nodes or points in the network where voltage regulation and stability are challenging due to factors such as high impedance, long transmission lines, or the point at which major loads are connected.
  • Assessment of Voltage Levels
    Evaluate the voltage levels at identified weak buses under normal operating conditions. This assessment should consider both steady-state and dynamic voltage behaviour in order to understand potential voltage fluctuations and stability issues.
Step 4.
Model the PV system
Incorporate the PV system into the power system model, considering its location, capacity, generation profile, and other relevant parameters.
  • Integration of Step-up Transformers
    Analyze the necessity and effectiveness of integrating step-up transformers at weak buses to mitigate voltage issues. Evaluate the impact of transformer parameters such as turns ratio, tap settings, and impedance on voltage regulation and system performance.
  • Add PV Penetration Level
    Increase the penetration level of PV systems in the model according to predefined scenarios:
    -
    Increase PV penetration level by 10% by decreasing the synchronous generation.
    -
    Increase the load by 5% to simulate increased demand.
    -
    Decrease conventional generation by 10% to reflect reduced reliance on traditional power sources due to increased PV penetration.
Step 5.
Evaluation of PV Plant Operation at Full Capacity
Analyze the behaviour of the PV plant when operating at full capacity without any output restrictions. Assess the impact of unrestricted PV generation on system voltage and frequency dynamics, especially during power contingencies or disturbances.
Step 6.
Impact of Load Increase and Conventional Generation Decrease
Simulate a 5% increase in load demand and a 10% decrease in conventional generation capacity based on specified objectives. Assess the resulting changes in voltage levels, power flow distribution, and system stability, particularly at weak buses.
Step 7.
Assessment of PV Plant Contribution to Voltage Stability
Determine the extent to which the PV plant contributes to voltage regulation and stability during various operating scenarios. Evaluate whether the PV generation alone is sufficient to maintain acceptable voltage levels or if additional measures such as Battery Energy Storage Systems (BESS) are necessary.
Step 8.
Integrate the Battery Energy Storage Systems (BESS)
Integrate BESS units into the power system model, considering their capacity, charge and discharge rates, efficiency, and control strategies.
Step 9.
Integration of PV and BESS Findings and Recommendations
Synthesize the analysis results to identify key findings, including the effectiveness of step-up transformers, the impact of PV generation on voltage stability, and the potential need for additional measures such as BESS units. Provide recommendations for system enhancements or operational strategies to improve voltage regulation and overall system performance.

4. Simulation Setup

All of the studies were conducted using PSS/E software developed by Siemens. The network elements were modeled using PSS/E library models, with the Battery Energy Storage System (BESS) represented by the “CBEST“ and “PAUX1“ models as detailed in the manual [35]. The “CBEST“ model, which simulates the battery, includes both an active power path and a reactive power path. The active power path accounts for power inefficiencies during energy storage and retrieval as well as AC current limitations on the part of the converter. This model requires an external input to define the battery’s function, provided by the frequency-sensitive “PAUX1“ model, which adjusts power output based on frequency deviations from the nominal value.
This research focuses on developing and performing stability assessments of grid-connected solar PV and BESS using three IEEE test systems. The studies were executed in PSSE, where bus systems were developed and analysed to determine their capacity for maintaining stability when integrated with solar PV. Both steady-state and dynamic stability analyses were conducted, and the PV system size was modeled in PSSE to assess stability. The goal was to identify the maximum possible PV power injection and the potential output of the PV plant. The PV generator bus was connected to the modeled bus system, and dynamic stability was evaluated to observe the PV generator’s behavior under various power generation scenarios.
In PSSE, the initial step involves determining the number of buses and their base KV in the grid system. Voltage limits must be set between 0.95 and 1.05 to prevent undervoltage issues. Buses are classified as either non-generator buses or generator buses depending on whether they are connected to generators. Loads can be placed on buses based on user requirements, representing factories and residential areas, but should not be placed near solar farms or conventional plants. This ensures stable output in the final analysis. The active and reactive loads can be adjusted to accurately represent these areas.
Generator parameters such as Pgen (power generation) and Pmax (maximum power output) can be set by the user. Each generator in this study was configured with different Pgen values, all of which were above 250 MW. During transient stability processes, Pgen can be gradually increased to determine the maximum potential output of the PV generator. This comprehensive approach ensures a thorough evaluation of the network’s stability and the impact of high PV penetration.
A short circuit study was performed to identify the fault level at each bus and determine the connection point of the PV system that was ideally the buses where the loads are connected. We used the ASCC Short Circuit method for performing short circuit studies, as mentioned in the System Strength and Inertia Report. As per the methodology, the short circuit fault level is always calculated on the three phase-to-ground fault, as this is the most onerous scenario resembling a bolted fault. The short circuit current calculated for the three phase-to-ground fault will be the highest, which helps in developing protection devices to withstand that level of current [36].

5. Case Studies

In order to investigate issues around high PV penetration in the distribution network, IEEE 9, 39, and 118 bus systems were modeled using PSS/E software. The complete study was carried out using PSS/E software.

5.1. Case Study 1: IEEE 9-Bus System

The simulations were conducted using the IEEE 9-Bus Benchmark system. This system is composed of three conventional generators, six transmission lines, and three loads. The total power demand from these loads amounts to 321 MW, a figure used to calculate the level of wind power penetration [37]. The Slack Bus is located at Generator 1 (G1), and the single-line diagram of the system is presented in Figure 2.
The PV and BESS system were modeled based on the total load demand. The total load demand was around 305 MW. The PV inverters were modeled as generic photovoltaic inverters with high R and X values, as they do not contribute towards the short-circuit current during a fault. PV sizes were calculated based on the total load available. However, the BESS was added only for the 75% PV dispatch case. Table 2 shows the power ranges of the machines at different PV penetration levels in the IEEE 9-bus system case.
Based on Table 2, the PV system has been modeled in two machines in the 50% and 75% cases in order to understand the behavior of the network under two-machine response. In comparison, 100% PV was designed as a single machine in order to better understand the single machine response. The active and reactive power of the machines displayed here are for a single machine. The dispatch of the machines was based on the total load of the network. Based on the load, the machine dispatch was tuned to test dispatches at 10%, 25%, 50%, 75%, and 100%. The machines were tuned based on the power generation (Pgen). The QMax, QMin, and Mbase were calculated based on the Pgen of the machine. The Qmax and Qmin are usually 39.5% of the Pgen [37].
With increasing PV penetration and existing synchronous generation, the MVA rating of the line during high demand seasons is pushed to its limits. PV dispatch during the day ensures that the batteries are being charged during the day.
At night, when there is no contribution from PV, the battery is used as a suitable replacement to meet demands. Batteries are also sometimes used to provide frequency support to the grid in case of a synchronous generator being out of service, or for any other special requirement.
The PV dispatch was based on the load of the system. For each scenario, the PV design was such that the PV dispatched a certain percentage of output, with the same amount being curtailed from the synchronous generators to maintain the balance in the system. With increasing MW dispatch, the active power and reactive power react independently. The reactive power is affected by the dip in voltage. The response was simulated when PV was added and any abruptness or instability was recorded.

5.2. Case Study 2: IEEE 39-Bus System

The IEEE 39-bus system shown in Figure 3, commonly referred to as the ten-machine New England Power System, features Generator 1 as a representative example of a large aggregation of generators.
The PV and BESS system were both modeled based on the total load demand, which was around 5800 MW. The PV inverters were modeled as generic photovoltaic inverters with high R and X values, as they do not contribute towards the short-circuit current during a fault. PV sizes were calculated based on the total available load. The BESS was added for all PV dispatch cases. Table 3 shows the BESS dispatch at different PV penetration levels in the IEEE 39-bus system case.
With the increase in PV and BESS penetration along with existing synchronous generation, the MVA rating of the line during high-demand seasons is pushed to its limits. PV dispatch during the day ensure that the batteries are being charged during the day.
At night, when there is no contribution from PV, the battery is used as a suitable replacement to meet demands. Batteries are also sometimes used to provide frequency support to the grid in case of a synchronous generator being out of service, or for any other special requirement. The PV dispatch was based on the load of the system. For each scenario, the PV and BESS were designed such that the PV dispatches a certain percentage of output, with the same amount being curtailed from the synchronous generators to maintain the balance in the system. With increasing MW dispatch, the active power and reactive power react independently. The reactive power is affected by the dip in voltage. The response when the PV and BESS were added was simulated and any abruptness or instability was recorded.

5.3. Case Study 3: IEEE 118-Bus System

The IEEE 118-bus test case serves as a simplified model of the American Electric Power system as it was in December 1962, focusing on the US Midwest region. This model includes 19 generators, 35 synchronous condensers, 177 lines, 9 transformers, and 91 loads. It is important to note that the base kilovolt (KV) levels assigned to the bus names are based on estimates [38]. Moreover, the line megavolt–ampere (MVA) limits were not originally provided with the data, and have been subsequently approximated [39]. As a test case, this system features numerous voltage control devices, demonstrating robust performance and the ability to converge within approximately five iterations using a fast decoupled power flow method. The single-line diagram of the IEEE 118-bus system case is illustrated in Figure 4.
The PV and BESS unit were modeled based on the total load demand, which was around 3817 MW. The PV inverters were modeled as generic photovoltaic inverters with high R and X values, as they do not contribute towards the short-circuit current during a fault. PV sizes were calculated based on the total available load. The BESS was added for all PV dispatch cases. Table 4 shows the BESS dispatch at different PV penetration levels.
With the increase in PV and BESS penetration and existing synchronous generation, the MVA rating of the line during high-demand seasons is pushed to its limits. The PV dispatch during the day ensures that the batteries are being charged during the day. At night, when there is no contribution from PV, the battery is used as a suitable replacement to meet demands. Batteries are also sometimes used to provide frequency support to the grid in case of a synchronous generator being out of service, or for any other special requirement.
The PV dispatch was based on the load of the system. For each scenario, the PV and BESS were designed such that the PV dispatches a certain percentage of output, with the same amount curtailed from the synchronous generators to maintain the balance in the system. With increasing MW dispatch, the active power and reactive power react independently. The reactive power is affected by the dip in voltage. The response when the PV and BESS were added was simulated and any abruptness or instability was recorded.

6. Results and Discussions

This section delves into the comprehensive results derived from the case studies conducted on the IEEE 9-bus, 39-bus, and 118-bus systems. The investigations primarily focus on the dynamic and steady-state performance of these systems under varying levels of PV penetration and the integration of BESS units. Through meticulous modeling and simulation, the analysis provides insights into the impacts of renewable integration on power system stability, voltage levels, and frequency response, highlighting the challenges and benefits of transitioning towards more sustainable energy solutions.

6.1. Case Study 1: IEEE 9-Bus System

This study evaluates the system’s behavior under different scenarios of PV and BESS penetration in the IEEE 9-bus system, assessing key parameters such as voltage stability, thermal loading, and dynamic response to grid disturbances. Through detailed simulations, the findings underscore the critical role of BESS in maintaining grid stability and the potential of PV systems to fulfill load demands while ensuring operational efficiency and reliability.

6.1.1. Modeling Scenarios

As per the methodology outlined above, with increasing PV dispatch, the load was increased by 5% and the synchronous generation was curtailed by 10% to account for future projections and identify the capability of the retirement of conventional generators towards greener grids. Here, the modeling scenarios of different PV and BESS penetration levels along with their location as well as the load and conventional generators at each scenario are listed in Table 5.

6.1.2. Steady State Assessment

Thermal overloading corresponds to the MVA capacity of the line. The line rating varies based on the temperature and ambient conditions. As the line rating varies, the overloading can increase or decrease based on the MVA ratings. The loadings shown below are within the MVA ratings of the line [36].
Under steady-state assessment, we look for line loading and thermal violations across the network as well as the voltage at the buses. For the considered scenarios, we have performed analysis of the thermal overloading and bus voltages. The following conditions should be satisfied:
  • Bus voltages move outside of the range 0.9 p.u. to 1.1 p.u.
  • Thermal loading based on the normal rating specified in the case.
In this context, the loadings for each line for different PV penetration cases are listed in Table 6. In addition, the voltage levels per unit at different PV penetration are summarized in Table 7.

6.1.3. Dynamic Assessment

To demonstrate the dynamic behavior, a bus fault was applied. The following fault types were simulated in the network surrounding the PV system.
  • Three phase-to-ground fault: The line segments from the faulted bus were opened in the local clearing times specified.
  • Disturbances were applied using “psspy.dist_3phase_bus_fault()” for balanced faults. The fault was immediately cleared in the specified protection clearance times. If the contingency involved inter-trips or caused additional network elements to disconnect, then these items were not reclosed/reconnected.
After initialization, the machine was run flat until 5 s. After 5 s, the fault was introduced for 0.12 s, then was cleared. After fault clearance, the branch associated with the bus was tripped [36]. The fault clearance times are based on the voltage levels; for voltage level above 100 kV and less than 250 kV, they have a clearance time of 0.12 s, as mentioned in the National Electricity Rules [40]. In all the cases, the fault was applied to branch 5–6, as this was the branch closest to the highest penetration of the BESS and PV machines. Using the closest fault to the machine is more prudent and makes it less onerous to examine the response of the machine to the system’s stability [36].
All of the scenarios listed in Table 5 were analysed; however, in this section we are focused on those that significantly impact the voltage and frequency stability. A summary of what our findings from each scenario can is provided in the findings section.
  • Base Case
    The base case was tested for the same contingency to analyze the response of the base system without the addition of PV or BESS in the system. The dynamics of system voltage, frequency, active power, and reactive power of the IEEE 9-bus system based case are illustrated in Figure 5.
    The voltage appears to be stable and achieves pre-fault level after the fault is cleared, as shown in Figure 5a. The frequency remains within the set frequency band of 49.985–50.015 Hz, as illustrated in Figure 5b. The active power shows instability when the fault is cleared, but attains the steady state eventually, as shown in Figure 5c. The reactive power remains stable after the fault is cleared, as illustrated in Figure 5d.
  • 75% PV penetration
    In this case, 75% PV penetration is observed, accounting for the total load demand in the system. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 6.
    The voltage appears to settle to the pre-fault level as soon as the fault clears, as shown in Figure 6a. The frequency response is within the specified limits of 49.895–50.015 Hz. The frequency becomes stable after 20 s, as illustrated in Figure 6b. The active power remains stable after the fault is cleared. The active power recovers within 100 ms, as depicted in Figure 6c. The resulting quantities reflect the total dispatch and response from each respective machine. The rise time appears to be less than 2 s, as shown in Figure 6d.
  • 75% PV penetration with 10% BESS penetration
    A Battery Storage System was added to the 75% PV dispatching case. Initially, the battery was added to the case where PVs were dispatching at 100%; however, because of the low load demand and infinite grid, the system showed instability and there was an imbalance in the swing. Following this, the 75% PV case was considered instead, as the slack bus was balanced and the battery could dispatch at 10%. The voltage, frequency, and active and reactive power were simulated, analysed, and reported, as shown in Figure 7.
    The voltage for both PV and BESS settle to the pre-fault level once the fault is cleared, as shown in Figure 7a. The battery helps in providing voltage support by injecting reactive power when the voltage dips during a fault. The battery works as a standalone unit and helps to boost the voltage at the buses. The frequency deviation after the fault looks negligible and the frequency remains stable, as illustrated in Figure 7b. The battery helps in providing inertial support and works as a virtual synchronous machine to help provide frequency support to the network. The active power dispatch for PV and BESS are both maintained at pre-fault levels, as depicted in Figure 7c. The active power support means that the battery is discharging; during this time, the battery is working as a generator, providing or injecting active power to ensure that maximum dispatch is achieved and the frequency stays in control. The reactive power recovers once the fault is cleared and the voltage returns to normal, allowing the system to exit fault ride-through, as illustrated in Figure 7d. The battery provides reactive power support in case of fault; as the voltage goes down, the battery injects reactive power, ensuring that the voltage does not go below the 0.9 pu range.
  • 100% PV penetration
    In this case, 100% PV penetration is observed, accounting for the total load demand. Here, the voltage, frequency, and active and reactive power were simulated, analysed and reported, as shown in Figure 8.
    The voltage appears to have achieved the steady state around 21 s, as shown in Figure 8a. The frequency response appears to be stable and is maintained within the specified limits, as shown in Figure 8b. The active power (MW) response settles to the pre-fault level after it reaches 20 s, as illustrated in Figure 8c. The reactive power adjusts itself after the fault is cleared, which is because of the set point calculated by the power plant controller, which is then fed to the inverters to scale their dispatch, as depicted in Figure 8d.

6.2. Case Study 2: IEEE 39-Bus System

This section investigates the IEEE 39-bus system. The analysis concentrates on understanding the impact of various levels of PV and BESS integration on the system’s voltage profiles, power flows, and stability during both steady-state and dynamic conditions. By simulating realistic scenarios, this study aims to highlight the challenges and opportunities associated with high renewables penetration, emphasizing the importance of strategic BESS deployment for enhanced grid stability.

6.2.1. Modeling Scenarios

As per the methodology mentioned above, with increasing PV dispatch, the load was increased by 5% and the synchronous generation was curtailed by 10% to account for future projections and identify the capability of the retirement of the conventional generators towards greener grids. Here, the modeling scenarios of different PV and BESS penetration along with their locations as well as the load and conventional generators for each scenario are listed in Table 8.

6.2.2. Steady-State Assessment

Steady-state assessment was carried out to calculate line ratings and voltage deviations for the buses. We observed overloading on the lines where the battery storage penetration was 50%. For cases with less than 50% penetration, no thermal overloading occurred in the surrounding network. For bus voltage deviation, all monitored network voltages remained with 0.9 p.u. to 1.1 p.u. post-contingency. The largest network voltage deviation was observed to be less than 0.05 p.u.

6.2.3. Dynamic Assessment

Dynamic assessment was carried out following the same methodology as for the 9-bus system. For a three phase-to-ground fault, the model was simulated by performing a flat run until 5 s and then following it with a fault. The fault was then cleared and the model was run until 30 s.
The fault clearance times were based on the voltage levels and had a clearance time of 0.12 s for voltage level above 100 kV and less than 250 kV, as mentioned in the National Electricity Rules [40]. In all the cases, the fault was applied to branch 5–6, as this is the closest branch to the highest penetration of the BESS and PV machines. Using the closest the fault to the machine is more prudent and makes it less onerous to examine the response of the machine to the system’s stability [36].
Every scenario outlined in Table 7 underwent thorough analysis. This section shines a spotlight on the scenarios that significantly influence voltage and frequency stability, offering critical insights. For a comprehensive overview of our discoveries across all scenarios, please refer to the findings section, where the essence of our research is distilled.
  • Base Case
    The base case was tested for the same contingency in order to analyze the response of the base system without the addition of PV or BESS in the system. In this case, the voltage, frequency, and active and reactive power were simulated, analysed and reported, as shown in Figure 9.
    The voltage remains steady and stable pre- and post-fault when applying the fault on branch 5–6 without integrating PV and BESS, as shown in Figure 9a. In the base case, the frequency response is stable at 50 Hz after removing the fault, as illustrated in Figure 9b. The active power response remains stable after the fault is cleared, as shown in Figure 9c. The reactive power settles after the fault is cleared in the base case, as shown in Figure 9d.
  • 25% PV with 10% BESS penetration
    Here, the asynchronous generation (PV) is at 25% of the load and the Battery Storage System is tuned to 10% of the PV. In this case, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 10.
    The voltage returns to its pre-fault levels. Voltages at certain buses exceed the 0.9–1.1 p.u. range, as shown in Figure 10a. The frequency remains stable and is maintained within the permitted frequency band of 48.985–50.015 Hz, as illustrated in Figure 10b. The active power returns to its pre-fault value after the fault is cleared. The response appears to be stable and achieves steady state within 5 s after fault clearance, as depicted in Figure 10c. The reactive power is maintained near 0 Mvar before pre-fault condition. This enables the plant to inject reactive power in case of a fault, as illustrated in Figure 10d.
  • 50% PV with 50% BESS penetration
    In this scenario the asynchronous generation (PV) dispatch is at 50% of the load and the Battery Storage System is tuned to 50% of the PV. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 11.
    The voltage is within the 0.9–1.1 p.u. band. The response appears to be stable and the voltage returns to its pre-fault values, as shown in the Figure 11a. The frequency remains stable and is maintained within the permitted frequency band of 48.985–50.015 Hz, as shown in Figure 11b. The reactive power is stable and appears to achieve the pre-fault level, as shown in Figure 11c. The active power returns to its pre-fault value after the fault is cleared. The response appears to be stable and achieves steady state within 5 s after fault clearance, as depicted in Figure 11d.
  • 100% PV with 50% BESS penetration
    In this scenario, the asynchronous generation (PV) dispatch is at 100% of the load and the battery storage system is tuned to 50% of the PV. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 12.
    The voltage starts to drop because of low system strength, as shown in Figure 12a. The frequency starts to fluctuate because of lack of inertia in the system because there is no synchronous generation online, as shown in Figure 12b. The active power starts to increase because of the drop in frequency. This is expected; as the frequency deviates from the set value, the active power adjusts itself, as depicted in Figure 12c. The reactive power and the voltage interact with each other. The change in voltage results in an abrupt change in the reactive power, as shown in Figure 12d.

6.3. Case Study 3: IEEE 118-Bus System

In this section, we delve into the results from the extensive analysis of the IEEE 118-bus system, exploring the effects of substantial PV and BESS integration. This study meticulously examines the system’s resilience to voltage fluctuations and dynamic stability under varying PV and BESS penetration levels. The findings contribute valuable insights into managing large-scale PV integration, showcasing the pivotal role of advanced BESS solutions in ensuring the seamless operation and stability of future power grids.

6.3.1. Modeling Scenarios

As per the methodology mentioned above, with increasing PV dispatch, the load was increased by 5% and the synchronous generation was curtailed by 10% to account for future projections and identify the capability of the retirement of the conventional generators towards greener grids. Here, the modeling scenarios of different PV and BESS penetration levels along with their location as well as the load and conventional generators for each scenario are listed in Table 9.

6.3.2. Steady-State Assessment

Steady-state assessment was carried out to calculate line ratings and voltage deviations for the buses. We observed overloading on the lines where the battery storage penetration was 50%. For cases with less than 50% penetration, no thermal overloading occurred in the surrounding network. For bus voltage deviation, all monitored network voltages remained within 0.9–1.1 p.u. post-contingency. The largest network voltage deviation was observed to be less than 0.05 p.u.

6.3.3. Dynamic Assessment

Dynamic assessment was carried out following the same methodology as for the 9-bus and 39-bus systems. For a three phase-to-ground fault, the model was simulated by performing a flat run until 5 s, then following it with a fault. The fault was cleared and the model was run until 30 s. In all the cases, the fault was applied to branch 5–6, as it was the closest branch to the highest penetration of the BESS and PV machines. Using the closest the fault to the machine is more prudent and makes it less onerous to examine the response of the machine to the system’s stability.
Every scenario outlined in Table 8 underwent thorough analysis. This section shines a spotlight on the scenarios that significantly influence voltage and frequency stability, offering critical insights. For a comprehensive overview of our discoveries across all scenarios, please refer to the findings section, where the essence of our research is distilled.
  • Base Case
    The base case was tested for the same contingency in order to analyze the response of the base system without the addition of PV or BESS in the system. In this case, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 13.
    The voltage remains steady and stable pre- and post-fault when applying the fault on branch 5–6 without integrating PV and BESS, as shown in Figure 13a. In the base case, the frequency response stable at 50 Hz after removing the fault, as illustrated in Figure 13b. The active power response remains stable after the fault is cleared, as shown in Figure 13c. The reactive power settles after the fault is cleared in the base case, as shown in Figure 13d.
  • 50% PV with 50% BESS penetration
    In this scenario, the asynchronous generation (PV) dispatch is at 50% of the load and the battery storage system is tuned to 50% of the PV. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 14.
    The voltage drop and variations of certain buses exceed the 0.9–1.1 p.u. band. The voltage returns to its pre-fault levels, as shown in Figure 14a. The frequency remains stable and is maintained within the permitted frequency band of 48.985–50.015 Hz, as shown in Figure 14b. The active power appears to settle to the pre-fault levels once the fault is cleared and reaches steady state within 5 s, as shown in Figure 14c. The reactive power returns to pre-fault values after the fault is cleared and remains stable, as illustrated in Figure 14d.
  • 75% PV with 50% BESS penetration
    In this scenario, the asynchronous generation (PV) dispatch is at 75% of the load and the battery storage system is tuned to 50% of the PV. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 15.
    The voltage response appears to be stable and within the 0.9–1.1 p.u. band post-fault, as illustrated in Figure 15a. The frequency remains stable and is maintained within the permitted frequency band of 48.985–50.015 Hz, as shown in Figure 15b. The active power appears to settle to the pre-fault levels once the fault is cleared and reaches the steady state within 5 s, as shown in Figure 15c. The reactive power returns to pre-fault values after the fault is cleared and remains stable, as illustrated in Figure 15d.
  • 100% PV with 50% BESS penetration
    In this scenario, the asynchronous generation (PV) dispatch is at 100% of the load and the battery storage system is tuned to 50% of the PV. Here, the voltage, frequency, and active and reactive power have been simulated, analysed, and reported, as shown in Figure 16.
    The voltage settles to the pre-fault value after the fault is cleared, and the steady state is achieved within 5 s of fault clearance, as shown in Figure 16a. The frequency deviates but maintains stability within the permitted frequency band of 48.985–50.015 Hz, as illustrated in Figure 16b. The active power returns to the pre-fault value, as shown in Figure 16c. The reactive power remains stable and maintains its pre-fault value after fault clearance, as depicted in Figure 16d.
In the scenarios where PV systems were integrated into the grid without additional battery storage, voltage levels remained stable at 1 per unit, enhancing voltage support across the board. Even amid minor fluctuations due to the variable output from the PV systems, the frequency stayed within a tight range of 49.985–50.015. Active power dispatch demonstrated stability without any significant spikes or instability, and reactive power was effectively managed, allowing for the injection of reactive current whenever necessary, thereby improving voltage control.
The inclusion of BESS with PV systems markedly improved the grid’s overall stability. This combination not only bolstered voltage support, contributing to a more stable transmission network, but also maintained an exceptionally stable frequency, with BESS providing critical frequency control and effectively acting as virtual synchronous machines. The ability of the batteries to store excess solar energy during low demand periods and release it during times of peak demand allowed for more efficient management of load variability. Moreover, this integration ensured a consistent supply of reactive power, facilitating a smoother incorporation of renewable energy sources by mitigating fluctuations in reactive power output.
The support provided by the BESS proved essential for rapid system stabilization and addressing power deficits. Analysis of the three case studies illustrates that increasing battery dispatch can enhance system stability in the following ways:
  • 25% BESS: Supported by a robust infinite grid and a significant presence of synchronous generation, the voltage, frequency, active power, and reactive power all remain stable, ensuring that dispatch and demand are primarily balanced by synchronous plants.
  • 50% BESS: Stability is similar to the case with 25% BESS, with a strong infinite grid and substantial synchronous generation maintaining steady voltage, frequency, active power, and reactive power.
  • 75% BESS: As asynchronous generation begins to dominate, minor signs of instability appear in voltage, frequency, active power, and reactive power due to a weakened infinite grid and reduced synchronous generation, with demand largely met by asynchronous sources.
  • 100% BESS: This scenario exhibits the greatest instability and oscillation in system parameters, resulting from a weakened infinite grid and minimal to no synchronous generation. The demand is fully met by PVs and BESS, leading to reduced reliability and sudden changes in system behaviour due to low inertia and strength.
However, the addition of more battery storage to the PV system introduced specific challenges. Voltage stability was compromised, underscoring the need for synchronous generation to be actively online within the current transmission network. Frequency stability also suffered, with significant deviations from the desired range due to reduced system inertia. Active power dispatch faced fluctuations, highlighting the absence of synchronous generation to aid in maintaining frequency stability. Likewise, reactive power experienced oscillatory responses due to voltage deviations, affecting the system’s capacity to manage reactive power effectively when voltage levels dropped below acceptable thresholds.

7. Conclusions

This study analysed the impact of high photovoltaic (PV) penetration in power networks using IEEE 9-bus, 39-bus, and 118-bus systems. Key findings show that integrating PV with Battery Energy Storage Systems (BESS) significantly enhances voltage stability and system resilience. For example, with 75% PV penetration and BESS support the voltage stability improved, effectively managing grid disturbances. BESS units are crucial for maintaining frequency stability in scenarios with high levels of renewables.
Our simulations revealed that PV penetration levels of 50% and above improve voltage profiles and reduce voltage fluctuations due to the stabilizing effect from BESS. In the IEEE 39-bus system with 50% PV and 50% BESS, voltage stability was within the operational range of 0.9-1.1 p.u. during normal and fault conditions. In the IEEE 118-bus system, 75% PV penetration with 50% BESS utilization showed rapid recovery from disturbances with minimal impacts on frequency and voltage.
Higher PV integration increases reliance on BESS for maintaining power quality and system reliability. BESS compensates for solar power intermittency and provides essential services such as peak shaving and load leveling that are crucial for managing high renewable penetration challenges.
Our results underscore the strategic importance of synchronized PV and BESS deployment to support the transition to renewable energy sources and achieve long-term energy sustainability and grid stability.
Future research should focus on optimizing BESS configuration and scaling, investigating the long-term impacts of high renewable penetration on grid infrastructure, and developing predictive models for accurate forecasting under variable renewable outputs. Additionally, integrating other renewable sources such as wind and hydro with PV systems could enhance grid resilience and sustainability.

Author Contributions

Conceptualization, K.A.B.H. and A.M.A.-S.; methodology, K.A.B.H. and A.M.A.-S.; software, K.A.B.H.; validation, K.A.B.H., A.M.A.-S. and H.M.H.F.; formal analysis, K.A.B.H. and A.M.A.-S.; investigation, K.A.B.H.; resources, K.A.B.H. and A.M.A.-S.; data curation, K.A.B.H. and A.M.A.-S.; writing—original draft preparation, K.A.B.H.; writing—review and editing, A.M.A.-S. and H.M.H.F.; visualization, K.A.B.H.; supervision, A.M.A.-S. and H.M.H.F. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by King Saud University, grant number RSP-2024R337.

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Acknowledgments

The authors would like to acknowledge the Researchers Supporting Project (number RSP-2024R337), King Saud University, Riyadh, Saudi Arabia.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Sorknæs, P.; Johannsen, R.M.; Korberg, A.D.; Nielsen, T.B.; Petersen, U.R.; Mathiesen, B.V. Electrification of the industrial sector in 100scenarios. Energy 2022, 254, 124339. [Google Scholar] [CrossRef]
  2. Nielsen, S.; ∅stergaard, P.A.; Sperling, K. Renewable energy transition, transmission system impacts and regional development—A mismatch between national planning and local development. Energy 2023, 278, 127925. [Google Scholar] [CrossRef]
  3. Kany, M.S.; Mathiesen, B.V.; Skov, I.R.; Korberg, A.D.; Thellufsen, J.Z.; Lund, H.; Sorknæs, P.; Chang, M. Energy efficient decarbonisation strategy for the Danish transport sector by 2045. Smart Energy 2022, 5, 100063. [Google Scholar] [CrossRef]
  4. Kalloe, N.; Bos, J.; Rueda Torres, J.; van der Meijden, M.; Palensky, P. A Fundamental Study on the Transient Stability of Power Systems with High Shares of Solar PV Plants. Electricity 2020, 1, 62–86. [Google Scholar] [CrossRef]
  5. Sampath Kumar, D.; Sharma, A.; Srinivasan, D.; Reindl, T. Impact analysis of large power networks with high share of renewables in transient conditions. IET Renew. Power Gener. 2020, 14, 1349–1358. [Google Scholar] [CrossRef]
  6. Shim, J.W.; Verbic, G.; Hur, K. Stochastic Eigen-Analysis of Electric Power System With High Renewable Penetration: Impact of Changing Inertia on Oscillatory Modes. IEEE Trans. Power Syst. 2020, 35, 4655–4665. [Google Scholar] [CrossRef]
  7. You, S.; Kou, G.; Liu, Y.; Zhang, X.; Cui, Y.; Till, M.J.; Yao, W.; Liu, Y. Impact of High PV Penetration on the Inter-Area Oscillations in the U.S. Eastern Interconnection. IEEE Access 2017, 5, 4361–4369. [Google Scholar] [CrossRef]
  8. Bueno, P.G.; Hernández, J.C.; Ruiz-Rodriguez, F.J. Stability assessment for transmission systems with large utility-scale photovoltaic units. IET Renew. Power Gener. 2016, 10, 584–597. [Google Scholar] [CrossRef]
  9. Kumar, D.S.; Sharma, A.; Srinivasan, D.; Reindl, T. Stability implications of bulk power networks with large scale PVs. Energy 2019, 187, 115927. [Google Scholar] [CrossRef]
  10. Quintero, J.; Vittal, V.; Heydt, G.T.; Zhang, H. The Impact of Increased Penetration of Converter Control-Based Generators on Power System Modes of Oscillation. IEEE Trans. Power Syst. 2014, 29, 2248–2256. [Google Scholar] [CrossRef]
  11. Yan, R.; Saha, T.K.; Modi, N.; Masood, N.A.; Mosadeghy, M. The combined effects of high penetration of wind and PV on power system frequency response. Appl. Energy 2015, 145, 320–330. [Google Scholar] [CrossRef]
  12. Ahmadyar, A.S.; Riaz, S.; Verbic, G.; Chapman, A.; Hill, D.J. A Framework for Assessing Renewable Integration Limits With Respect to Frequency Performance. IEEE Trans. Power Syst. 2018, 33, 4444–4453. [Google Scholar] [CrossRef]
  13. Katz, J.; Chernyakhovskiy, I. Variable Renewable Energy Grid Integration Studies: A Guidebook for Practitioners; Technical report; National Renewable Energy Laboratory (NREL): Golden, CO, USA, 2020. [Google Scholar]
  14. Yang, W.; Tu, C.; Xiao, F.; Yu, J. A Method to Improve Both Frequency Stability and Transient Stability of Virtual Synchronous Generators during Grid Faults. Sustainability 2024, 16, 1769. [Google Scholar] [CrossRef]
  15. Eriksson, R.; Modig, N.; Elkington, K. Synthetic inertia versus fast frequency response: A definition. IET Renew. Power Gener. 2018, 12, 507–514. [Google Scholar] [CrossRef]
  16. Bowen, T.; Chernyakhovskiy, I.; Denholm, P.L. Grid-Scale Battery Storage: Frequently Asked Questions; Technical report; National Renewable Energy Lab. (NREL): Golden, CO, USA, 2019. [Google Scholar]
  17. Bello, M.; Vittal, E.; Tuohy, A.; Thompson, J. Report on Energy Storage Analysis; Technical report; DOE: Washington, DC, USA, 2021. [Google Scholar]
  18. EPRI. Battery Energy Storage Cost Assessment: 2023; Technical report; EPRI: Miami, FL, USA, 2023. [Google Scholar]
  19. Mongird, K.; Viswanathan, V.V.; Balducci, P.J.; Alam, M. An Evaluation of Energy Storage Cost and Performance Characteristics Energies; Technical report; Department of Energy, DOE: Washington, DC, USA, 2020. [Google Scholar]
  20. Saudi Electric Company (SEC). Saudi Arabian Grid Code; Saudi Electric Company (SEC): Riyadh, Saudi Arabia, 2024. [Google Scholar]
  21. Spencer, T.; Rodrigues, N.; Pachouri, R.; Thakre, S.; Renjith, G. Renewable Power Pathways: Modelling the Integration of Wind and Solar in India by 2030; Technical Report; The Energy and Resources Institute: New Delhi, India, 2020. [Google Scholar]
  22. Deorah, S.; Abhyankar, N.; Arora, S.; Chawla, K.; Phadke, A. Assessing the Key Requirements for 450 GW of Renewable Capacity in India by 2030; Technical report; Lawrence Berkeley National Laboratory: Berkeley, CA, USA, 2022. [Google Scholar]
  23. Alquthami, T.; Ravindra, H.; Faruque, M.O.; Steurer, M.; Baldwin, T. Study of photovoltaic integration impact on system stability using custom model of PV arrays integrated with PSS/E. In Proceedings of the North American Power Symposium 2010, Arlington, TX, USA, 26–28 September 2010; IEEE: New York, NY, USA, 2010; pp. 1–8. [Google Scholar]
  24. Xie, Z.; Zhang, D.; Hu, W.; Han, X. Power System Transient Stability Preventive Control via Aptenodytes Forsteri Optimization with an Improved Transient Stability Assessment Model. Energies 2024, 17, 1942. [Google Scholar] [CrossRef]
  25. Milano, F. Power System Modelling and Scripting; Springer: Berlin/Heidelberg, Germany, 2010. [Google Scholar]
  26. Arshad, M. Two-Port Networks. In Network Analysis and Circuits; Jones & Bartlett: Burlington, MA, USA, 2010. [Google Scholar]
  27. He, W.; Yao, J.; Xu, H.; Zhong, Q.; Xu, R.; Liu, Y.; Li, X. Transient Synchronous Stability Analysis of Grid-Forming Photovoltaic Grid-Connected Inverters during Asymmetrical Grid Faults. Energies 2024, 17, 1399. [Google Scholar] [CrossRef]
  28. Ibrahim, I.A.; Hossain, M.J. Low Voltage Distribution Networks Modeling and Unbalanced (Optimal) Power Flow: A Comprehensive Review. IEEE Access 2021, 9, 143026–143084. [Google Scholar] [CrossRef]
  29. Nazir, N.; Almassalkhi, M. Guaranteeing a Physically Realizable Battery Dispatch Without Charge-Discharge Complementarity Constraints. IEEE Trans. Smart Grid 2023, 14, 2473–2476. [Google Scholar] [CrossRef]
  30. Refaat, S.S.; Abu-Rub, H.; Sanfilippo, A.P.; Mohamed, A. Impact of grid-tied large-scale photovoltaic system on dynamic voltage stability of electric power grids. IET Renew. Power Gener. 2018, 12, 157–164. [Google Scholar] [CrossRef]
  31. Cai, L.; Erlich, I. Dynamic voltage stability analysis in multi-machine power systems. In Proceedings of the 5th Power System Computation Conference, Liege, Belgium, 22–26 August 2005. [Google Scholar]
  32. Heetun, K.Z.; Abdel Aleem, S.H.E.; Zobaa, A.F. Voltage stability analysis of grid-connected wind farms with FACTS: Static and dynamic analysis. Energy Policy Res. 2016, 3, 1–12. [Google Scholar] [CrossRef]
  33. Paramasivam, M.; Salloum, A.; Ajjarapu, V.; Vittal, V.; Bhatt, N.B.; Liu, S. Dynamic Optimization Based Reactive Power Planning to Mitigate Slow Voltage Recovery and Short Term Voltage Instability. IEEE Trans. Power Syst. 2013, 28, 3865–3873. [Google Scholar] [CrossRef]
  34. Lee, B.; Lee, K. Dynamic and static voltage stability enhancement of power systems. IEEE Trans. Power Syst. 1993, 8, 231–238. [Google Scholar] [CrossRef]
  35. PSSE. PSS®E Model Library. 2024. Available online: https://www.siemens.com/global/en/products/energy/grid-software/planning/pss-software/psse-model-library-download-request.html (accessed on 7 May 2024).
  36. Australian Energy Market Operator (AEMO). 2023 System Strength Report; Technical report; Australian Energy Market Operator (AEMO): Sydney, NSW, Australia, 2023. [Google Scholar]
  37. Kandil, M.; El-Deib, A.A.; Elsobki, M.S. Enhancing The Power System Transient Stability by Using Storage Devices With High Penetration Of Wind Farms. In Proceedings of the 2020 6th International Conference on Electric Power and Energy Conversion Systems (EPECS), Istanbul, Turkey, 5–7 October 2020; IEEE: New York, NY, USA, 2020; pp. 13–18. [Google Scholar]
  38. Christie, R. Power Systems Test Case Archive: 118 Bus Power Flow Test Case; University of Washington: Washington, DC, USA, 1993. [Google Scholar]
  39. Illinois Center for a Smarter Electric Grid (ICSEG). IEEE 118-Bus System. 2024. Available online: https://icseg.iti.illinois.edu/ieee-118-bus-system/ (accessed on 7 May 2024).
  40. AEMC. National Electricity Rules; AEMC: Dover, NH, USA, 2024. [Google Scholar]
Figure 1. Single-machine equivalent model of PV plant.
Figure 1. Single-machine equivalent model of PV plant.
Sustainability 16 07141 g001
Figure 2. IEEE 9-bus system case.
Figure 2. IEEE 9-bus system case.
Sustainability 16 07141 g002
Figure 3. IEEE 39-bus system case.
Figure 3. IEEE 39-bus system case.
Sustainability 16 07141 g003
Figure 4. IEEE 118-bus system case.
Figure 4. IEEE 118-bus system case.
Sustainability 16 07141 g004
Figure 5. Dynamic analysis of base case without PV systems—IEEE 9-bus system.
Figure 5. Dynamic analysis of base case without PV systems—IEEE 9-bus system.
Sustainability 16 07141 g005
Figure 6. Dynamic analysis of 75% PV integration—IEEE 9-bus system.
Figure 6. Dynamic analysis of 75% PV integration—IEEE 9-bus system.
Sustainability 16 07141 g006
Figure 7. Dynamic analysis of 75% PV and 10% BESS integration—IEEE 9-bus system.
Figure 7. Dynamic analysis of 75% PV and 10% BESS integration—IEEE 9-bus system.
Sustainability 16 07141 g007
Figure 8. Dynamic analysis of 100% PV integration—IEEE 9-bus system.
Figure 8. Dynamic analysis of 100% PV integration—IEEE 9-bus system.
Sustainability 16 07141 g008
Figure 9. Dynamic analysis of the base case—IEEE 39-bus system.
Figure 9. Dynamic analysis of the base case—IEEE 39-bus system.
Sustainability 16 07141 g009
Figure 10. Dynamic analysis of 25% PV with 10% BESS integration—IEEE 39-bus system.
Figure 10. Dynamic analysis of 25% PV with 10% BESS integration—IEEE 39-bus system.
Sustainability 16 07141 g010
Figure 11. Dynamic analysis of 50% PV with 50% BESS integration—IEEE 39 bus system.
Figure 11. Dynamic analysis of 50% PV with 50% BESS integration—IEEE 39 bus system.
Sustainability 16 07141 g011
Figure 12. Dynamic analysis of 100% PV with 50% BESS integration—IEEE 39-bus system.
Figure 12. Dynamic analysis of 100% PV with 50% BESS integration—IEEE 39-bus system.
Sustainability 16 07141 g012
Figure 13. Dynamic analysis of base case—IEEE 118-bus system.
Figure 13. Dynamic analysis of base case—IEEE 118-bus system.
Sustainability 16 07141 g013
Figure 14. Dynamic analysis of 50% PV with 50% BESS integration—IEEE 118-bus system.
Figure 14. Dynamic analysis of 50% PV with 50% BESS integration—IEEE 118-bus system.
Sustainability 16 07141 g014
Figure 15. Dynamic analysis of 75% PV with 50% BESS integration—IEEE 118-bus system.
Figure 15. Dynamic analysis of 75% PV with 50% BESS integration—IEEE 118-bus system.
Sustainability 16 07141 g015
Figure 16. Dynamic analysis of 100% PV with 50% BESS integration—IEEE 118-bus system.
Figure 16. Dynamic analysis of 100% PV with 50% BESS integration—IEEE 118-bus system.
Sustainability 16 07141 g016
Table 1. Summary of the ABCD representation of different transmission lines.
Table 1. Summary of the ABCD representation of different transmission lines.
Parameter A = D BC
UnitPer UnitΩ S
Short line (less than 80 km)1Z0
Medium line—nominal π circuit (80 to 250 km) 1 + Y Z 2 Z Y 1 + Y Z 4
Long line—equivalent π circuit (80 to 250 km) cosh γ = 1 + Y Z 2 Z c sinh γ = Z 1 Z c sinh γ = Y 1 + Y Z 4
Lossless line R = G = 0 cos β j Z c sin γ j sin β Z c
Table 2. Power ranges of the machines at different PV penetration levels in the IEEE 9-bus system case.
Table 2. Power ranges of the machines at different PV penetration levels in the IEEE 9-bus system case.
CasesNo. of MachinesPgen (MW) per MachinePmax (MW) per MachinePmin (MW) per MachineQmax/Qmin (Mvar) per MachineMbase (MVA) per Machine
10% PV130.536.85500±10.395040
25% PV176.2589.21250±25.1625100
50% PV276.2589.21250±25.1625100
75% PV376.2589.21250±25.1625100
100% PV1305356.85000±100.6500400
Note: Qmax and Qmin are provided as positive/negative values, indicating the range of reactive power control capability of each machine.
Table 3. BESS dispatch at different PV penetration levels in the IEEE 39-bus system case.
Table 3. BESS dispatch at different PV penetration levels in the IEEE 39-bus system case.
CasesNo. of MachinesPgen (MW) per MachinePmax (MW) per MachinePmin (MW) per MachineQmax/Qmin (Mvar) per MachineMbase (MVA) per Machine
BESS—10% PV11001000±50100
BESS—25% PV21001000±50100
BESS—50% PV42002000±100205
BESS—75% PV52002000±100205
BESS—100% PV62002000±100205
Note: Qmax and Qmin are provided as positive/negative values, indicating the range of reactive power control capability of each machine.
Table 4. BESS dispatch at different PV penetration levels in the IEEE 118-bus system case.
Table 4. BESS dispatch at different PV penetration levels in the IEEE 118-bus system case.
CasesNo. of MachinesPgen (MW) per MachinePmax (MW) per MachinePmin (MW) per MachineQmax/Qmin (Mvar) per MachineMbase (MVA) per Machine
BESS—10% PV15001000±2550
BESS—25% PV12001000±50100
BESS— 50% PV22002000±100205
BESS—75% PV42002000±100205
BESS—100% PV52002000±100205
Note: Qmax and Qmin are provided as positive/negative values, indicating the range of reactive power control capability of each machine.
Table 5. PV and BESS penetration and locations in the IEEE 9-bus system case study.
Table 5. PV and BESS penetration and locations in the IEEE 9-bus system case study.
PV %PV Capacity (MW)Bus in PSSE (Actual Bus)BESS%BESS Capacity (MWh)Bus in PSSE (Actual Bus)Load (MW)Synchronous Generation Capacity (MW)
10%30.53018 (6)---305310
25%76.253019 (6)---320295
50%152.53018 (6), 3019 (8)---336280
75%228.753020 (6)10%22.87510 (8)352.8264
100%3053020 (6)---370250
Table 6. Lines loading in % at different PV penetration levels in the IEEE 9-bus system case.
Table 6. Lines loading in % at different PV penetration levels in the IEEE 9-bus system case.
CasesBus 1 to 4Bus 2 to 7Bus 3 to 9Bus 9 to 8Bus 9 to 6Bus 8 to 7Bus 6 to 4Bus 7 to 5Bus 5 to 4
Base Case00012.5443.8327.8612.3235.9321.31
10% PV00017.6530.6525.1915.9430.8723.61
25% PV00024.8313.9420.9311.1123.1529.47
50% PV00011.6813.821.3210.5321.9229.77
75% PV00012.025.582.3812.314.9818.11
100% PV00057.4757.478.1551.052.8454.20
Table 7. Voltage levels in p.u. at different PV penetration levels in the IEEE 9-bus system case.
Table 7. Voltage levels in p.u. at different PV penetration levels in the IEEE 9-bus system case.
CasesBus 1 to 4Bus 2 to 7Bus 3 to 9Bus 9 to 8Bus 9 to 6Bus 8 to 7Bus 6 to 4Bus 7 to 5Bus 5 to 4
Base Case1.041.021.021.031.001.011.031.041.02
10% PV1.041.021.021.020.990.991.031.041.02
25% PV1.041.021.021.021.001.011.031.041.02
50% PV1.041.021.021.031.001.011.041.041.02
75% PV1.041.021.021.041.031.021.041.041.02
100% PV1.040.991.001.010.981.010.991.040.99
Table 8. PV and BESS penetration and locations in the IEEE 39-bus system case study.
Table 8. PV and BESS penetration and locations in the IEEE 39-bus system case study.
PV%PV Capacity (MW)Bus in PSSE (Actual Bus)BESS%BESS Capacity (MWh)Bus in PSSE (Actual Bus)Load (MW)Synchronous Generation Capacity (MW)
10%585.640 (2), 41 (29), 42 (39)10%58.5650 (5)58565901
25%1537.240 (2), 41 (29), 42 (39), 30, 31, 3225%384.350 (5)6148.85605.95
25%1614.0640 (2), 41 (29), 42 (39), 30, 31, 3250%403.51550 (5)6456.245325.653
50%3389.52640 (2), 41 (29), 42 (39), 30, 31, 3225%1694.76350 (5), 60 (14)6779.0525059.37
50%3559.00240 (2), 41 (29), 42 (39), 30, 31, 3250%1779.50150 (5), 60 (14)7118.0054806.401
75%5605.42940 (2), 41 (29), 42 (39), 30, 31, 32, 33, 3425%4204.07150 (5), 60 (14), 70 (18)7473.9054566.081
75%5885.740 (2), 41 (29), 42 (39), 30, 31, 32, 33, 3450%4414.27550 (5), 60 (14), 70 (18), 80 (15)7847.64337.777
100%823940 (2), 41 (29), 42 (39), 30, 31, 32, 33, 34, 35, 36, 37, 3850%450050 (5), 60 (14), 70 (18), 80 (15), 90 (26), 101 (3), 201 (8), 301 (7)8239.984120.888
Table 9. PV and BESS penetration and locations in the IEEE 118-bus system case study.
Table 9. PV and BESS penetration and locations in the IEEE 118-bus system case study.
PV %PV Capacity (MW)Bus in PSSE (Actual Bus)BESS%BESS Capacity (MWh)Bus in PSSE (Actual Bus)Load (MW)Synchronous Generation Capacity (MW)
10%381.76510%38.179138173950
25%954.2565, 68, 6925%95.4259140083752
50%1908.565, 68, 69, 70, 71, 7250%190.8591, 944210.43564.5
75%2862.7565, 68, 69, 70, 71, 72, 73, 74, 7550%286.27591, 94, 9544213386.3
100%381765, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 7850%381.791, 94, 95, 984642.053216
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Bin Hudayb, K.A.; Al-Shaalan, A.M.; Hussein Farh, H.M. Mitigation of Photovoltaics Penetration Impact upon Networks Using Lithium-Ion Batteries. Sustainability 2024, 16, 7141. https://doi.org/10.3390/su16167141

AMA Style

Bin Hudayb KA, Al-Shaalan AM, Hussein Farh HM. Mitigation of Photovoltaics Penetration Impact upon Networks Using Lithium-Ion Batteries. Sustainability. 2024; 16(16):7141. https://doi.org/10.3390/su16167141

Chicago/Turabian Style

Bin Hudayb, Khalid Abdullah, Abdullah M. Al-Shaalan, and Hassan M. Hussein Farh. 2024. "Mitigation of Photovoltaics Penetration Impact upon Networks Using Lithium-Ion Batteries" Sustainability 16, no. 16: 7141. https://doi.org/10.3390/su16167141

APA Style

Bin Hudayb, K. A., Al-Shaalan, A. M., & Hussein Farh, H. M. (2024). Mitigation of Photovoltaics Penetration Impact upon Networks Using Lithium-Ion Batteries. Sustainability, 16(16), 7141. https://doi.org/10.3390/su16167141

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop