The ALARP Principle in the Cost-Benefit Analysis for the Acceptability of Investment Risk

1
Department of Civil Engineering, University of Salerno, 84084 Fisciano, Salerno, Italy
2
School of Economics, Shanghai University, Shanghai 200444, China
3
Megaris Ltd., Reading RG2 9FL, UK
*
Author to whom correspondence should be addressed.
Received: 30 October 2018 / Revised: 29 November 2018 / Accepted: 5 December 2018 / Published: 7 December 2018
(This article belongs to the Special Issue Real Estate Economics, Management and Investments)
Full-Text   |   PDF [3586 KB, uploaded 7 December 2018]   |  

Abstract

The process of allocating financial resources is extremely complex—both because the selection of investments depends on multiple, and interrelated, variables, and constraints that limit the eligibility domain of the solutions, and because the feasibility of projects is influenced by risk factors. In this sense, it is essential to develop economic evaluations on a probabilistic basis. Nevertheless, for the civil engineering sector, the literature emphasizes the centrality of risk management, in order to establish interventions for risk mitigation. On the other hand, few methodologies are available to systematically compare ante and post mitigation design risk, along with the verification of the economic convenience of these actions. The aim of the paper is to demonstrate how these limits can be at least partially overcome by integrating, in the traditional Cost-Benefit Analysis schemes, the As Low as Reasonably Practicable (ALARP) logic. According to it, the risk is tolerable only if it is impossible to reduce it further or if the costs to mitigate it are disproportionate to the benefits obtainable. The research outlines the phases of an innovative protocol for managing investment risks. On the basis of a case study dealing with a project for the recovery and transformation of an ancient medieval village into a widespread-hotel, the novelty of the model consists of the characterization of acceptability and tolerability thresholds of the investment risk, as well as its ability to guarantee the triangular balance between risks, costs and benefits deriving from mitigation options. View Full-Text
Keywords: economic evaluation of projects; risk-management process; investment risk; probabilistic risk analysis; ALARP logic economic evaluation of projects; risk-management process; investment risk; probabilistic risk analysis; ALARP logic
Figures

Figure 1

This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited (CC BY 4.0).
SciFeed

Share & Cite This Article

MDPI and ACS Style

Nesticò, A.; He, S.; De Mare, G.; Benintendi, R.; Maselli, G. The ALARP Principle in the Cost-Benefit Analysis for the Acceptability of Investment Risk. Sustainability 2018, 10, 4668.

Show more citation formats Show less citations formats

Note that from the first issue of 2016, MDPI journals use article numbers instead of page numbers. See further details here.

Related Articles

Article Metrics

Article Access Statistics

1

Comments

[Return to top]
Sustainability EISSN 2071-1050 Published by MDPI AG, Basel, Switzerland RSS E-Mail Table of Contents Alert
Back to Top