Two-Stage Decoupled Security-Constrained Redispatching for Hybrid AC/DC Grids
Abstract
1. Introduction
2. The Proposed Formulation
2.1. The Overall Framework
- Loss of single AC branches;
- Loss of single DC branches;
- Loss of single converters of embedded DCGs, without losing the DCG connectivity (no DC branches are tripped);
- Loss of components due to DC bus fault, namely the simultaneous loss of DCG converter and DC branches connected to the faulty DC bus;
- Loss of single AC generators (including renewable injections).
- First stage to solve active power/phase angle related issues;
- Second stage to solve reactive power/voltage magnitude related issues.
- The formulation of the two stages as Linear Programming problems makes the algorithm efficient to solve large power systems.
- The adoption of reactive/active power decoupling techniques permits to solve the two stages separately in a cascaded way.
2.2. Stage 1 (Active Power Control)
- Preventive variations of active power setpoints for AC generators and for embedded DC converters with constant P and PV droop control, as well as preventive curtailment of renewable injections and the variation of shift angle of PSTs (Phase Shifting Transformers).
- Post-contingency variations of active power setpoints for AC dispatchable generators and for DC embedded converters with constant P and PV droop controls. Ramp limitations of the devices subject to the control, notably conventional generators, are considered.
- Term represents the total cost for preventive actions.
- Term represents the costs for corrective actions for generic contingency k.
- Term indicates the “lack of security” in case of N state and in case of occurrence of contingency k with probability . The lack of security is quantified by introducing suitable feasibility variables related to the violations of grid security constraints (e.g., on the branch active power flows for stage 1) and associating large costs to the potential violations.
- The active power flows on AC branches;
- The current flows on DC branches.
- Equality constraints:
- ○
- Balance of power in AC grids (preventively modified N-state)
- ○
- Balance of power in DCGs (preventively modified N-state) for any DCG λwhere m’ = 1 … refers to the HVDC converters of DCG λ.
- ○
- Active power flow on AC branches in N state
- ○
- Current on DC branches
- ○
- Matching constraints of VSC fictitious generators (i.e., setting the equality between the active power setpoint variation on the AC side of embedded VSC and the relevant variation on the corresponding fictitious generator)
The adopted power convention for converters is that the power injection is positive when flowing from the AC to the DC grid, while the power convention for generators connected to AC grid is that the power exchange is positive when generator injects power into the AC grid, and negative in the opposite case. - Inequality constraints:
- ○
- Limits on current flows of DC branches
- ○
- Technical limits for VSCs
- ○
- Limits on active power flows of AC branches,
- ○
- Generator upward and downward redispatch margins
- ○
- RES curtailment limit
- Equality constraints:
- ○
- Balance of power in AC grids (N-1 state, contingency k = 1…Nctg)
- ○
- Final injection of VSC after k-th contingency
- ○
- Active power flow on AC branches in N-1 stateis the expected initial power flow on branch l, after contingency k, when no control actions (i.e., neither preventive nor corrective) are deployed.
- ○
- Final generation at generator j-th after the k-th contingency
- ○
- Matching constraints of VSC fictitious generators
- ○
- Current on DC branches in N-1 state
- ○
- Balance of power for DCG λ in N-1 state
- Inequality constraints:
- ○
- Limits on current flows of DC branches
- ○
- Technical limits for VSCs
- ○
- Limits on active power flows of AC branches
- ○
- Generator upward and downward redispatch margins
2.3. Stage 2 (Reactive Power Control)
- Preventive control actions, i.e., the preventive variations of the AC voltage setpoints for conventional AC generators and for DCG converters, as well as of the DC voltage setpoints of the converters;
- Corrective control actions, i.e., corrective variations of the AC voltage setpoints for conventional AC generators and for converters, as well as of the DC voltage setpoints for converters, for each contingency.
- The voltage magnitudes at AC buses;
- The voltage values at DC buses;
- The reactive power exchange of conventional AC generators and of embedded VSC converters;
- The reactive power flows along the AC branches—the enforcement of this constraint, accounting for the actual value of active power flows in stage 1, assures that the maximum apparent power allowable on the AC branches is not violated.
- Equality constraints:
- ○
- Initialization of reactive power exchange at PQ nodes
- ○
- Voltages at PQ buses in N state (preventively modified)where,
- ○
- Voltage at generator buses in N state (preventively modified)
- ○
- Total reactive power exchanged at PV nodes in N state (preventively modified)
- ○
- Reactive powers exchanged by generators in N state (preventively modified)
- ○
- Reactive power flows on the AC branches in N state
- ○
- No voltage setpoint variation at PQ nodes
- ○
- Voltages at DC buses using sensitivity in N state
- ○
- Currents on DC branches
- Inequality constraints:
- ○
- Total reactive power capability of generators at PV node z
- ○
- Reactive power flow limits (accounting for the active power flow established after stage 1)
- ○
- Technical limits for AC buses
- ○
- Technical limits for DC buses
- ○
- AC/DC voltage constraint
- ○
- Limits on current flows of DC branches
- Equality constraints:
- ○
- Initialization of reactive power exchange at PQ nodes
- ○
- Voltages at PQ buses in N-1 state (preventively modified)where,
- ○
- Voltage at PV buses in N-1 state (preventively modified)
- ○
- Total reactive power exchanged at PV nodes in N-1 state (preventively modified)
- ○
- Reactive powers exchanged by PV nodes in N-1 state (preventively modified)
- ○
- Reactive power flows on AC branches in N-1 state
- ○
- No voltage setpoint variation at PQ nodes in N-1 state
- ○
- Voltages at DC buses using sensitivity in N-1 state
- ○
- Currents on DC branches
- Inequality constraints:
- ○
- Total reactive power capability of generators at PV node z
- ○
- Technical limits for bus voltages in N-1 state
- ○
- Reactive power flow limits in N-1 state (accounting for the active power flow established after stage 1)
- ○
- Technical limits for DC buses
- ○
- AC/DC voltage constraint
- ○
- Limits on current flows of DC branches
3. Case Study
3.1. Test System and Summary of the Simulations
- A multi-terminal DCG, named DCG 1, featuring an H-shape topology, representing the following:
- ○
- A DCG connecting offshore wind farms, partially embedded into the AC grid (configuration 1, Figure 3a);
- ○
- A fully embedded DCG without wind farms (configuration 2, Figure 3b);
- ○
- The fully embedded DCG above, enhanced with a further link that creates a mesh (configuration 3, Figure 3b with dashed line);
- A point-to-point (P2P) DC link, DCG 2, representing a connection from a remote (e.g., offshore) wind farm, acting as an injection into the AC grid (see left side in Figure 1). The identifiers of the two DC nodes for this P2P link are DC 7 and DC 8.
- Scenario A—the redispatching costs for embedded VSCs are the same as the ones adopted for dispatchable generators (+100 amu/MW for upward variations and −20 amu/MW for downward variations);
- Scenario B—the redispatching costs for embedded VSCs are set equal to +10 amu/MW and −2 amu/MW.
- The costs for the deployment of the preventive actions (henceforth called “preventive action costs”).
- The costs for the conditional deployment of the corrective actions (in case contingencies occur): these costs are the simple summation of the costs for corrective control actions, irrespective of the probability of occurrence of contingencies.
- The total cost which sums the expected costs of corrective actions and of infeasibilities (due to the missing fulfillment of security criteria)—weighted by the probability of occurrence of contingencies—as well as the costs for preventive actions.
3.2. Case 1A: The Base Case
3.3. Case 1B: Effects of Redispatching Costs of VSC’s
3.4. Case 1AP: Effects of Contingency Probabilities
3.5. Cases 2B and 3B: Effect of DCG Topology Layout
3.6. Effect of DCG Configurations While Considering the Contingency Probabilities
3.7. Discussion
4. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Nomenclature
| Symbol | Meaning |
| Auxiliary matrix coefficient for AC reactive power flow computation between buses b and b1 | |
| Matrix coefficient for the reactive power exchange between PV node j and PQ node i | |
| Penalty factor for upper bound violation of AC voltage magnitude | |
| penalty factor for upper bound violations of power flow in the l-th AC branch | |
| Penalty factor for lower bound violation of AC voltage magnitude | |
| Penalty factor for lower bound violations of power flow in the l-th AC branch | |
| Current on the ldc-th DC line | |
| Initial expected current on DC cable ldc in N state, without control actions | |
| Initial expected current on DC cable ldc in N-1 state, just after the application of contingency k, without control actions | |
| Expected current on the ldc-th DC line in N state, after preventive actions | |
| Current rating for the ldc-th DC line | |
| I-V matrix coefficient for computing the contribution—in N state—to current on DC line ldc due to voltage at DC bus bdc | |
| I-V matrix coefficient for computing the contribution—in N-1 state—to current on DC line ldc due to voltage at DC bus bdc | |
| Auxiliary matrix coefficient between PV node j and PQ node i | |
| Auxiliary matrix coefficient for power flow between node i and i1 | |
| N | Number of AC buses |
| NBDC | Number of DC buses |
| Number of contingencies | |
| Number of DC Grids (DCGs) | |
| Number of DC lines | |
| Number of dispatchable generators | |
| Number of generators which go out of service during contingency k | |
| Number of generators which survive contingency k | |
| Number of HVDC converters for DCG λ | |
| Number of AC branches | |
| Number of loads | |
| Number of wind generators connected to the AC grid | |
| Number of PQ nodes | |
| Number of PV nodes | |
| Number of DC buses under DC voltage control (either fixed voltage or PV droop) | |
| Objective Function for control Stage 1 | |
| OF2 | Objective Function for control Stage 2 |
| Final generation from the j-th generator after contingency k | |
| Final power injection from the m-th HVDC converter after contingency k | |
| Maximum active power of generator j | |
| Minimum active power of generator j | |
| Initial active power setpoint for generator j | |
| Maximum active power of HVDC converter m | |
| Minimum active power of HVDC converter m | |
| Initial active power setpoint for converter m | |
| Reactive power flow between two buses (b and b1) in the AC grid | |
| Reactive power flow limit between buses b and b1 | |
| Reactive power exchanged at the z-th PV node | |
| Reactive power generated by the z-th PV node | |
| Maximum reactive power limit for the z-th PV node | |
| Minimum reactive power limit for the z-th PV node | |
| Reactive power exchange at the i-th PQ node | |
| Initial reactive power exchange at the i-th PQ node | |
| Sensitivity coefficient in N state between DC voltage at bus bdc and the s-th DC node with controlled DC voltage | |
| Sensitivity coefficient in N-1 state between DC voltage at bus bdc and the s-th DC node with controlled DC voltage | |
| Sensitivity factor for the flow of active power between branch l and generator j | |
| (k) | Sensitivity factor for the flow of active power between branch l and generator j, in case of contingency k |
| Sensitivity factor of active power flow between DC line ldc and HVDC converter m | |
| Sensitivity factor for the flow of active power between branch l and load lo | |
| (k) | Sensitivity factor for the flow of active power between branch l and load lo, in case of contingency k |
| Expected power flow on the l-th AC branch in N state, after preventive actions | |
| Maximum rating for AC branch l | |
| Initial expected power flow on the l-th AC branch in N state, without control actions | |
| Initial expected power flow on the l-th AC branch in N-1 state, just after the application of contingency k, without control actions | |
| Voltage magnitude at the bdc-th DC bus | |
| Maximum voltage limit for the bdc-th DC bus | |
| Minimum voltage limit for the bdc-th DC bus | |
| Nominal voltage of the bdc-th DC bus | |
| Starting voltage at the bdc-th DC bus | |
| Voltage magnitude at the z-th PV node | |
| Starting voltage magnitude for PV node z | |
| Voltage at the i-th PQ node | |
| Auxiliary variable at the i-th node | |
| Initial expected power generation from wind farm h connected to AC grids | |
| Cost of curtailment on the h-th wind generator | |
| Cost of load shedding at load lo in contingency k | |
| Cost of preventive control action on the j-th conventional generator | |
| Cost of preventive control action on the m-th HVDC converter | |
| Cost of corrective control action on the j-th conventional generator | |
| Cost of corrective control action on the m-th HVDC converter | |
| Active power load corrective shedding at load lo in case of contingency k | |
| Active power flow for the fictitious generator j′ | |
| Active power setpoint increase in generator j for preventive action | |
| Active power setpoint increase in generator j for corrective action in case of contingency k | |
| Active power increase in HVDC converter m for preventive action | |
| Active power setpoint decrease in generator j for preventive action | |
| Active power setpoint decrease in generator j for corrective action in case of contingency k | |
| Active power decrease in HVDC converter m for preventive action | |
| Active power setpoint increase in HVDC converter m for corrective action in case of contingency k | |
| Active power setpoint decrease in HVDC converter m for corrective action in case of contingency k | |
| Preventive increase in DC voltage reference at DC bus s under DC voltage control | |
| Preventive decrease in DC voltage reference at DC bus s under DC voltage control | |
| Preventive increase in voltage reference at PV node z in N state | |
| Preventive decrease in voltage reference at PV node z in N state | |
| Corrective increase in DC voltage reference at DC bus s under DC voltage control in case of contingency k | |
| Corrective decrease in DC voltage reference at DC bus s under DC voltage control in case of contingency k | |
| Corrective increase in voltage reference at PV node z in in case of contingency k | |
| Corrective decrease in voltage reference at PV node z in case of contingency k | |
| Wind generator power decrease in h-th wind generator for preventive action | |
| Second auxiliary matrix coefficient for AC reactive power flow computation between buses b and b1 | |
| Redistribution of active power injection on generator j in service (before any preventive or corrective actions), in response to the occurrence of contingency k | |
| Redistribution of active power injection on HVDC converter m in service, including PV converter controls (but before any preventive or corrective actions), in response to the occurrence of contingency k | |
| Feasibility variable for upper bound violation of voltage magnitude at AC bus b in N state | |
| Feasibility variable for upper bound violation of voltage magnitude at AC bus b in N-1 state, in case of contingency k | |
| Feasibility variable for lower bound violation of voltage magnitude at AC bus b in N state | |
| Feasibility variable for lower bound violation of voltage magnitude at AC bus b in N-1 state, in case of contingency k | |
| Feasibility variable representing upper bound violations of power flow in the l-th AC branch | |
| Feasibility variable for upper bound violations of power flow in the l-th AC branch in case of contingency k | |
| Feasibility variable representing lower bound violations of power flow in the l-th AC branch | |
| Feasibility variable for lower bound violations of power flow in the l-th AC branch in case of contingency k | |
| Status of generator j in case of contingency k (1 = in service, 0 = out of service) | |
| Status of HVDC converter m in case of contingency k (1 = in service, 0 = out of service) | |
| Probability of occurrence of contingency k |
References
- ENTSO-E. RDI Roadmap 2024–2034; ENTSO-E: Brussels, Belgium, 2024. [Google Scholar]
- Carlini, E.M.; Gadaleta, C.; Migliori, M.; Longobardi, F.; Luongo, G.; Lauria, S.; Maccioni, M.; Dell’Olmo, J. Offshore Network Development to Foster the Energy Transition. Energies 2025, 18, 386. [Google Scholar] [CrossRef]
- Gallo Caicedo, R.; Bastianel, G.; Ergun, H.; Van Hertem, D. Reviewing High Voltage Transmission Technologies for Future Transmission Grids. In Proceedings of the AEIT HVDC International Conference 2025 (AEIT HVDC), Genoa, Italy, 29–30 May 2025. [Google Scholar]
- MacIver, C.; Bell, K.R.W.; Nedić, D.P. A Reliability Evaluation of Offshore HVDC Grid Configuration Options. IEEE Trans. Power Deliv. 2016, 31, 810–819. [Google Scholar] [CrossRef]
- Hashemi, S.; Asprou, M.; Hadjidemetriou, L.; Panteli, M. Quantifying and Mitigating Cascading Impacts in HVdc-Interconnected Power Grids. IEEE Access 2025, 13, 154491–154507. [Google Scholar] [CrossRef]
- Luo, C.; Liang, L.; Bai, X. Review of HVDC systems for enhancing resilience after extreme natural events. J. Eng. 2021, 2021, 653–664. [Google Scholar] [CrossRef]
- Ciapessoni, E.; Cirio, D.; Pitto, A.; Panteli, M.; Harte, M.V.; Mak, C. Defining power system resilience. Electra 2019, 306, 32–34. [Google Scholar]
- Khan, A.; Foote, C.; Marshall, B.; McNamara, P.; Papangelis, L. Reliability and Resilience Needs for Future Hybrid AC/DC Grids. In Proceedings of the CIGRE Paris Session 2024, Paris, France, 25–30 August 2024. [Google Scholar]
- Hatziargyriou, N.; Milanovic, J.; Rahmann, C.; Ajjarapu, V.; Canizares, C.; Erlich, I.; Hill, D.; Hiskens, I.; Kamwa, I.; Pal, B.; et al. Definition and Classification of Power System Stability—Revisited & Extended. IEEE Trans. Power Syst. 2021, 36, 3271–3281. [Google Scholar]
- Ashrafi Niaki, S.H.; Chen, Z.; Bak-Jensen, B.; Sharifabadi, K.; Liu, Z.; Hu, S. DC protection criteria for multi-terminal HVDC system considering transient stability of embedded AC grid. Int. J. Electr. Power Energy Syst. 2024, 157, 109815. [Google Scholar] [CrossRef]
- HVDC-WISE project. EU HE Grant Agreement 101075424, UKRI grants 10041877 and 10051113. Available online: https://hvdc-wise.eu/ (accessed on 31 October 2025).
- Anhaus, S.; Düllmann, P.; Osterkamp, L.; Dimitrovski, R.; McNamara, P.; Gonzalez, J.-C. A classification framework for HVDC-based transmission grid architectures. In Proceedings of the CIGRE Paris Session 2024, Paris, France, 25–30 August 2024. [Google Scholar]
- Panteli, M.; Hashemi, S.; Bell, K.; MacIver, C.; Thams, S.; Baù, M.; Ciapessoni, E.; Cirio, D.; Pitto, A.; Stenzel, D.; et al. D6.1: Definition of the R&R-Oriented Methodology for the Use Cases. HVDC WISE, 2024; Zenodo: Geneva, Switzerland, 2025; Available online: https://zenodo.org/records/15261241 (accessed on 31 October 2025).
- Hashemi, S.; Panteli, M.; Baù, M.; Ciapessoni, E.; Cirio, D.; Pitto, A.; Bakhos, G.; Barla, N.; Benchaib, A.; Ismail, B.; et al. Tools for Reliability and Resilience-Oriented Planning and Operation of hybrid AC/DC power systems. In Proceedings of the 2024 IEEE PES Innovative Smart Grid Technologies Europe (ISGT EUROPE), Dubrovnik, Croatia, 30 September–2 October 2024. [Google Scholar]
- Saplamidis, V.; Wiget, R.; Andersson, G. Security constrained Optimal Power Flow for mixed AC and multi-terminal HVDC grids. In Proceedings of the 2015 IEEE Eindhoven PowerTech, Eindhoven, The Netherlands, 29 June–2 July 2015. [Google Scholar]
- Meng, K.; Zhang, W.; Li, Y.; Dong, Z.Y.; Xu, Z.; Wong, K.P.; Zheng, Y. Hierarchical SCOPF Considering Wind Energy Integration Through Multiterminal VSC-HVDC Grids. IEEE Trans. Power Syst. 2017, 32, 4211–4221. [Google Scholar] [CrossRef]
- Ergun, H.; Dave, J.; Van Hertem, D.; Geth, F. Optimal Power Flow for AC–DC Grids: Formulation, Convex Relaxation, Linear Approximation, and Implementation. IEEE Trans. Power Syst. 2019, 34, 2980–2990. [Google Scholar] [CrossRef]
- Bastianel, G.; Ergun, H.; Van Hertem, D. Linearised Optimal Power Flow Problem Solution using Dantzig—Wolfe decomposition. In Proceedings of the 2022 IEEE PES Innovative Smart Grid Technologies Conference Europe (ISGT-Europe), Novi Sad, Serbia, 10–13 October 2022. [Google Scholar]
- Bhardwaj, V.; Ergun, H.; Van Hertem, D. Risk-based preventive-corrective security constrained optimal power flow for ac/dc grid. In Proceedings of the 2021 IEEE Madrid PowerTech, Madrid, Spain, 28 June–2 July 2021; pp. 1–6. [Google Scholar] [CrossRef]
- Jat, C.K.; Dave, J.; Van Hertem, D.; Ergun, H. Hybrid AC/DC OPF Model for Unbalanced Operation of Bipolar HVDC Grids. IEEE Trans. Power Syst. 2024, 39, 4987–4997. [Google Scholar] [CrossRef]
- Li, H.-X.; Ergun, H.; Van Hertem, D.; Lekic, A. Scenario-Oriented Multi-Cut Generalized Benders Decomposition-Based Distributed OPF for AC/DC Hybrid Grids. In Proceedings of the 2024 IEEE PES Innovative Smart Grid Technologies Europe (ISGT EUROPE), Dubrovnik, Croatia, 30 September–2 October 2024. [Google Scholar]
- Guzmán-Feria, J.S.; Castro, L.M.; González-Cabrera, N.; Tovar-Hernández, J.H. Security constrained OPF for AC/DC systems with power rescheduling by power plants and VSC stations. Sustain. Energy Grids Netw. 2021, 27, 100524. [Google Scholar] [CrossRef]
- Sennewald, T.; Sass, F.; Westermann, D. A preventive security constrained optimal power flow for mixed AC-HVDC-systems. In Proceedings of the 13th IET International Conference on AC and DC Power Transmission, Manchester, UK, 14–16 February 2017; pp. 1–7. [Google Scholar] [CrossRef]
- Fu, C.; Zhong, Y.; Zhang, P.; He, X.; Yang, Y.; Zuo, J. VSC-HVDC Incorporated Corrective Security-Constrained Optimal Power Flow. J. Phys. Conf. Ser. 2022, 2320, 012004. [Google Scholar] [CrossRef]
- Sennewald, T.; Linke, F.; Westermann, D. Preventive and Curative Actions by Meshed Bipolar HVDC-Overlay-Systems. IEEE Trans. Power Deliv. 2020, 35, 2928–2936. [Google Scholar] [CrossRef]
- Cao, J.; Du, W.; Wang, H.F. An Improved Corrective Security Constrained OPF for Meshed AC/DC Grids With Multi-Terminal VSC-HVDC. IEEE Trans. Power Syst. 2016, 31, 485–495. [Google Scholar] [CrossRef]
- Teixeira Pinto, R.; Aragues-Penalba, M.; Gomis-Bellmunt, O.; Sumper, A. Optimal Operation of DC Networks to Support Power System Outage Management. IEEE Trans. Smart Grid 2016, 7, 2953–2961. [Google Scholar] [CrossRef]
- Chatzivasileiadis, S.; Andersson, G. Security constrained OPF incorporating corrective control of HVDC. In Proceedings of the 2014 Power Systems Computation Conference, Wroclaw, Poland, 18–22 August 2014; pp. 1–8. [Google Scholar] [CrossRef]
- Wiget, R.; Vrakopoulou, M.; Andersson, G. Probabilistic security constrained optimal power flow for a mixed HVAC and HVDC grid with stochastic infeed. In Proceedings of the 2014 Power Systems Computation Conference, Wroclaw, Poland, 18–22 August 2014; pp. 1–8. [Google Scholar] [CrossRef]
- Ciapessoni, E.; Cirio, D.; Conte, F.; Pitto, A.; Massucco, S.; Saviozzi, M. Probabilistic Security-Constrained Preventive Control under Forecast Uncertainties Including Volt/Var Constraints. Energies 2023, 16, 1812. [Google Scholar] [CrossRef]
- Wang, W.; Barnes, M. Power Flow Algorithms for Multi-Terminal VSC-HVDC With Droop Control. IEEE Trans. Power Syst. 2014, 29, 1721–1730. [Google Scholar] [CrossRef]
- Gonzalez-Longatt, F.M.; Roldan, J.; Charalambous, C.A. Solution of AC/DC Power Flow on a Multi-Terminal HVDC Systems. In Proceedings of the International Conference on Renewable Energies and Power Quality (ICREPQ), Santiago de Compostela, Spain, 28–30 March 2012. [Google Scholar]
- Zhao, Q.; García-González, J.; Gomis-Bellmunt, O.; Prieto-Araujo, E.; Echavarren, F.M. Impact of Converter Losses on the Optimal Power Flow Solution of Hybrid Networks Based on VSC-MTDC. Electr. Power Syst. Res. 2017, 151, 395–403. [Google Scholar] [CrossRef]
- Allan, R.; Al-Shakarchi, M.R.G. Probabilistic a.c. load flow. Proc. Inst. Electr. Eng. 1976, 123, 531–536. [Google Scholar] [CrossRef]
- IEEE 118 Bus System. Available online: https://icseg.iti.illinois.edu/ieee-118-bus-system/ (accessed on 9 April 2025).
- Zimmerman, R.D.; Murillo-Sanchez, C.E.; Thomas, R.J. MATPOWER: Steady-State Operations, Planning and Analysis Tools for Power Systems Research and Education. IEEE Trans. Power Syst. 2011, 26, 12–19. [Google Scholar] [CrossRef]















| Parameter | Value |
|---|---|
| 100 amu/MW | |
| −20 amu/MW | |
| 100 amu/MW | |
| −20 amu/MW | |
| 200 amu/MW | |
| 10,000 amu/MW | |
| 109 amu/MW | |
| 109 amu/MW |
| ID | DCG 1 Layout | AC Grid Nodes of DCG1 VSCs | Contingency Probability | VSC Redispatch Costs |
|---|---|---|---|---|
| 1A | H, partially embedded | 36 and 55 | Equally probable | c+,m = 100 amu/MW c−,m = −20 amu/MW |
| 1B | H, partially embedded | 36 and 55 | Equally probable | c+,m = 10 amu/MW c−,m = −2 amu/MW |
| 2B | H, fully embedded | 4, 36, 55, and 89 | Equally probable | c+,m = 10 amu/MW c−,m = −2 amu/MW |
| 3B | Meshed, fully embedded | 4, 36, 55, and 89 | Equally probable | c+,m = 10 amu/MW c−,m = −2 amu/MW |
| 1AP | H, partially embedded | 36 and 55 | Based on failure rates and MTTR | c+,m = 100 amu/MW c−,m = −20 amu/MW |
| 2AP | H, fully embedded | 4, 36, 55, and 89 | Based on failure rates and MTTR | c+,m = 100 amu/MW c−,m = −20 amu/MW |
| 3AP | Meshed, fully embedded | 4, 36, 55, and 89 | Based on failure rates and MTTR | c+,m = 100 amu/MW c−,m = −20 amu/MW |
| 2BP | H, fully embedded | 4, 36, 55, and 89 | Based on failure rates and MTTR | c+,m = 10 amu/MW c−,m = −2 amu/MW |
| 3BP | Meshed, fully embedded | 4, 36, 55, and 89 | Based on failure rates and MTTR | c+,m = 10 amu/MW c−,m = −2 amu/MW |
| OHL | Transformer | Generator | DC Line | AC/DC Converter | |
|---|---|---|---|---|---|
| failure rate [1/yr] | 0.0003 (*) | 0.024 | 0.02 | 0.0004 (*) | 0.6 |
| MTTR [h] | 20 | 5 | 5 | 50 | 15 |
| Upward Preventive Active Power Setpoint Variations [MW] | Downward Preventive Active Power Setpoint Variations [MW] | Total Renewable Preventive Curtailment [MW] | |||
|---|---|---|---|---|---|
| All Dispatchable Generators | VSCs | All Dispatchable Generators | VSCs | ||
| Case 1B | 1134 | 107 | 813 | 107 | 321 |
| Case 2B | 433 | 88 | 262 | 88 | 171 |
| Case 3B | 495 | 78 | 272 | 78 | 223 |
| Case | Total Costs for Preventive Actions (amu) | Total Expected Costs for Corrective Actions (amu) | Total Cost (amu) |
|---|---|---|---|
| 1AP | 6.068 × 101 | 1.058 × 103 | 1.143 × 103 |
| 2AP | 6.007 × 103 | 5.096 × 102 | 6.524 × 103 |
| 3AP | 5.627 × 103 | 6.069 × 102 | 6.237 × 103 |
| 1BP | 6.068 × 101 | 1.055 × 103 | 1.140 × 103 |
| 2BP | 5.543 × 103 | 4.898 × 102 | 6.040 × 103 |
| 3BP | 5.323 × 103 | 5.848 × 102 | 5.912 × 103 |
| Case | Total Shed Load (MW) | Total Corrective Redispatch for VSCs (MW) | Total Corrective Redispatch for Dispatchable Generators (MW) |
|---|---|---|---|
| 1AP | 3.209 × 102 | 2.307 × 103 | 1.446 × 104 |
| 2AP | 2.977 × 102 | 4.573 × 103 | 1.499 × 104 |
| 3AP | 3.336 × 102 | 4.780 × 103 | 1.487 × 104 |
| 1BP | 3.209 × 102 | 3.735 × 103 | 1.527 × 104 |
| 2BP | 2.977 × 102 | 7.950 × 103 | 1.692 × 104 |
| 3BP | 3.336 × 102 | 7.613 × 103 | 1.593 × 104 |
| Upward Preventive Redispatch (MW) | Downward Preventive Redispatch (MW) | Total Amount of RES Preventive Curtailment (MW) | |||
|---|---|---|---|---|---|
| Case | Dispatchable Gen. | VSC | Dispatchable Gen. | VSC | |
| 1AP | 0.78 | 0 | 0.78 | 0 | 0 |
| 2AP | 30.7 | 3.55 | 14.56 | 3.55 | 16.14 |
| 3AP | 23.17 | 3.53 | 6.025 | 3.53 | 17.15 |
| 1BP | 0.76 | 0 | 0.76 | 0 | 0 |
| 2BP | 47.85 | 25.5 | 31.71 | 25.5 | 16.14 |
| 3BP | 35.4 | 17.8 | 18.24 | 17.8 | 17.15 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Ciapessoni, E.; Cirio, D.; Pitto, A. Two-Stage Decoupled Security-Constrained Redispatching for Hybrid AC/DC Grids. Energies 2026, 19, 706. https://doi.org/10.3390/en19030706
Ciapessoni E, Cirio D, Pitto A. Two-Stage Decoupled Security-Constrained Redispatching for Hybrid AC/DC Grids. Energies. 2026; 19(3):706. https://doi.org/10.3390/en19030706
Chicago/Turabian StyleCiapessoni, Emanuele, Diego Cirio, and Andrea Pitto. 2026. "Two-Stage Decoupled Security-Constrained Redispatching for Hybrid AC/DC Grids" Energies 19, no. 3: 706. https://doi.org/10.3390/en19030706
APA StyleCiapessoni, E., Cirio, D., & Pitto, A. (2026). Two-Stage Decoupled Security-Constrained Redispatching for Hybrid AC/DC Grids. Energies, 19(3), 706. https://doi.org/10.3390/en19030706

