1. Introduction
As a result of global warming and climate change concerns, significant changes are happening in power systems worldwide. The shutdown of fuel-based generation plants (coal, natural gas, and even nuclear) and increased penetration of renewable energy sources in the form of inverter-based resources (IBRs) are occurring in the generation side. Different from conventional synchronous generators, IBRs are not directly connected to the grid and do not provide inertia. The demand side is also evolving with the introduction of battery energy storage systems (BESSs) and electric vehicles (EVs). The rate at which distributed generation is being added is so high that some extreme cases can result in grid congestion and overloading. An example of such an occurrence was experienced in the Dutch grid, where the number of PV installations and EV charging stations have increased rapidly [
1]. Because renewable energy sources and demand patterns are intermittent and not fully controllable, generation planning must incorporate larger reserves to maintain balance. In addition to the typical demand change during the day, these reserves are now kept ready in case of an unexpected generation drop from the renewables and sudden demand increase from the prosumers. As a result, the base load has decreased and fast-responding power plants (hydroelectric, natural gas) are kept in reserve.
Another aspect is related to the protection scheme of the power systems. In the event of a fault, the conventional synchronous machines are capable of supplying high fault current during the fault. And today’s protection equipment is designed to detect these high-magnitude fault currents and then act accordingly. On the other hand, IBRs have current limitations and usually limit their fault current in order to protect the converter/inverter equipment. Recent regulations are being introduced for the fault current requirements; grid-forming IBRs should supply fault currents for protection action through and after the fault [
2]. Therefore, hydroelectric power plants will be playing an important role in future grids, not only as a balancing reserve but also as a source of inertia and fault current.
Figure 1 shows the 10-year change in the weekly generation profile of Turkey [
3]. The generation data is gathered in the form of hourly generation from the power plants throughout the day, seen from the transmission level. Then the data is separated into the given resource types. Finally, it is normalized on the generation peak of the given week. For
Figure 1a, the peak generation is at 35.5 GW, whereas the peak of
Figure 1b is at 44 GW in its peak hour. From the figures, it can be easily seen that the base load has dropped from 50% to 15% as a result of changes in the grid. Due to regulations and intentions regarding renewable energy, fuel-based generation has dropped drastically. Instead, wind and solar generation have increased. There is no significant observation in solar generation; however, it shows its effect from the distribution by reducing the off-peak percentage. The lowest generation was below 50% in 2024, whereas, it was above 60% in 2014. In the Turkey case, coal is still cheap and used effectively, but in the future, it will be decreased further to meet the zero-carbon targets. The crucial information hidden in the figures is that the remaining conventional generation is hydroelectric and it is operated more dynamically than ever.
Hydroelectric power plants are fast-responding and easy-to-control generation units. Their startup and synchronization procedures are much faster than the fuel-based plants. Therefore, they are preferred as reserve units and used in load-generation balancing throughout the day. However, resulting dynamic operation puts the plant components under stress. Their mechanical parts and water conduit systems are subject to wear and tear due to frequent startups and shutdowns, resulting in more frequent component failures or maintenance requirements. Usually, the plant components are taken into periodic maintenance once or twice a year. However, equipment faults can happen earlier than expected and cause more severe problems if not detected early. For a proper system operation with a high percentage of IBRs, the health and readiness of the hydroelectric power plants are crucial. Therefore, the condition monitoring of the power plant should be carried out in real time, and preventive control or maintenance actions should be performed to increase the lifetime of the plant components.
For a hydroelectric power plant, the plant components can be listed as the water conduit system, turbine, generator, machine transformer, excitation, governor, and cooling systems. In condition monitoring of these components, the health status of the plant equipment is monitored online via the plant measurements and dynamic simulation. A plant’s current operation is investigated and compared with both the past measurement data and the dynamic simulation results. For the same operation point, the behavioral differences like water flow rate, casing pressure, winding temperature, etc., from the power plant are analyzed and the health assessment is performed. Some of the related studies in the literature are summarized as follows: in Ref. [
4], the condition of the winding isolation in generators and transformers is monitored via partial discharge measurements. In addition to the electrical components, some studies related to the mechanical parts are presented in the literature. Ref. [
5] presents an online cavitation monitoring system for Kaplan-type hydroelectric turbines. Researchers monitored both audible and ultrasounds to detect turbine cavitations. The study in Ref. [
6] utilizes the vibration data for fault diagnosis. Furthermore, online temperature monitoring of the rotor and early detection of overheated rotor poles are introduced in Ref. [
7]. Lastly, a new maintenance information system is introduced in Ref. [
8], with vertical and horizontal integration levels to the hydropower plant components. It can be observed that the literature studies depend on the installation of new instruments and their interference with normal plant operation. Plant operators can be conservative in some of the cases.
In addition to these studies, improvements in the phasor measurement units (PMUs) enabled the system operators to perform better dynamic state and parameter estimation with more precise and frequent field measurements. Such studies are included in Refs. [
9,
10,
11,
12,
13]. These studies mainly focus on the dynamic model calibration and state estimation of the power plant with the help of PMU measurements. As indicated in the literature, PMUs give more reliable measurements (frequency, precision, and time synchronization) than those provided by the SCADA measurements. Therefore, the PMU data is preferable in the case of state and parameter estimation studies. Resulting calibrated models are then used for condition monitoring and health assessment studies of the power plants in a way that the plant’s simulation results and actual measurements are compared and the roots of the differences are investigated.
Although there are enough and well-performing studies regarding the condition monitoring and state estimation in hydroelectric power plants, the amount of studies related to the water conduit system is found to be limited. Also, the lack of enough measurements from the water conduit system makes the condition monitoring more difficult. As the water conduit systems are the parts that the mechanical power flows through, a problem in a water conduit system directly affects the hydropower plant operation since there is no second alternative to it. A general method that is applicable to all hydropower plants with access to past SCADA measurements is needed. Therefore, in this study, a data-driven method for the condition monitoring of the water conduit system is introduced. The simplicity of the method enables implementation in other plant components as well. Furthermore, the method does not require new equipment installation; it can be installed to the SCADA network and operate in real time. Briefly, the method analyzes the turbine startup sequence and obtains expected behavior with operation zones (healthy, acceptable, warning). With the available information and SCADA measurement data provided from two different power plants, the method is implemented and tested. Some discussions are done related to PMU installation to the studied power plants in this research. Considering the nature of the water conduit systems and condition monitoring methods, the measurements provided from SCADA are decided to be enough for this study. Furthermore, the method requires the extraction of the historical startup data; therefore, the already stored SCADA measurements were very useful in this study.
This paper is structured as follows:
Section 2 gives the basic modeling of the water conduit and turbine mechanics, the startup of the generating unit, and the synchronization procedure are explained. The proposed “PbyGate Analysis” method is presented in
Section 3. Separate analyses for three different turbines are implemented and tested in the related subsections. Then the test results are presented and discussed in
Section 4. Crucial information related to the power plants is concealed as requested by the plant operators. Finally, this paper is concluded with future work.
3. Proposed PbyGate Analysis
The mechanical power input is controlled by the governor that adjusts the gate position of the turbine. The targeted mechanical power is obtained with the desired gate inputs. However, in the case of a problem like a water flow decrease/increase or a pressure drop/rise on the conduit, the governor will try to correct the problem by increasing/decreasing the gate input. From the generator side, mechanical power is as expected but with an abnormal mechanical operating point. This abnormality can be detected by looking at the supplied power and gate position in the following way. Returning to the water flow velocity and mechanical power formulations,
where
and
are the proportionality multipliers. At a steady state and certain operating points, these multipliers are constant. In addition to that, the net head
H for a large power plant is also constant for an operation day. As a result of the governor action and controlled opening of the wicket gates, the net head
H does not change significantly during the startup (see
Figure 4). However, the multiplier terms are dependent on the plant-turbine design and the operating point
. For instance, during the unit startup, steady-state, or frequency changes, these multipliers change according to turbine starter/governor actions and current system variables:
The terms related to the water conduit and turbine dynamics are the proportionality multipliers and they can be easily monitored during the startup process. The ratio of power to the gate position (
) is then calculated:
The calculation of
requires the power and gate position measurements. On the right side of Equation (
13), the term
can be considered constant throughout the startup period. Therefore, it can be taken as constant for this process. The measurement of the mechanical power is not performed directly in the power plants. Rather, it is calculated from the mechanical torque and turbine speed. However, the electrical power is directly measured from the electrical quantities and the margin of error is smaller compared to the mechanical power. When the machine is in synchronous operation, its speed is nearly constant. Therefore, one can replace the mechanical power with the electrical power since the mechanical losses will be constant. The effect of losses can be put inside the normalization, and the per-unit values will be considerably similar. Resulting PbyGate calculation is given below where the time dependence of the parameters is also shown:
With this calculation, the effect of the instrument calibration is also taken into account. Note that each unit has its own characteristic due to its installment, plant configuration, instrument calibration, governor control method, etc. Therefore, the analyses are performed separately. The main difference is based on the curve fitting of the expected startup behavior. Exponential curve fitting and data averaging are utilized in Plants 1 and 2, respectively. This way, a comparison of the methods’ performances is achieved. Three turbine units from two different power plants are analyzed in this paper. The following steps are performed for the selected turbine units.
In the studied power plants, the instrument measurements are updated in their own resolution and format. But all the measurement updates are not reflected in the SCADA delivery to the control and monitoring panels. Rather, SCADA delivers the measurement data with the same timestamp, putting the current data in a single package. Therefore, the resolution of the measurements is decided by the SCADA, and it is all the same for the collected measurements unless specified otherwise. Since the study focuses on the water conduit system with time constants higher than the SCADA resolution, it will not cause a loss of information. After the synchronization is detected from the SCADA, the active power and gate position measurements are extracted. Then, the measurements are normalized on their rated value. Then, as shown above, the is calculated for each measurement instance, and the data is aligned on the synchronization moments. The aligned is used to select healthy startup data with the assistance of plant operators.
3.1. PbyGate Analysis on Units 1 and 2
For Units 1 and 2, which are from the same power plant, an exponential curve fitting is applied. The composed behavior of governor and conduit system is modeled with a piecewise exponential function
. Explicit forms of
are given in
Section 4. With the mean deviation and a properly selected decay function (being another exponential), the upper and lower health/danger limits for the operational zones are defined. The choice of
and
thresholds is based on Gaussian error limits [
15,
16]. The 99.7% confidence level implied by
is selected for the upper and lower healthy region limits. The envelopes of
define the acceptable and dangerous anomaly regions.
t is the time variable in seconds.
The region between
is specified as the healthy zone. The acceptable regions are the ones that are between
and
. The startup instances falling in these regions will be classified as acceptable. Other regions will be called the danger zones, and the startup behaviors in these regions will be marked as anomalies. The technical information on the water conduit and turbine design of Units 1 and 2 is given in
Table 1.
3.2. PbyGate Analysis on Unit 3
In Unit 3, the research team selected a different approach, where the expected behavior of the turbine is directly obtained from the averaging of the healthy startup behaviors. Also, the decay function is not utilized in this unit for comparison. Then, similar to Units 1 and 2, the upper/lower health/danger limits and the operation zones are defined accordingly.
Table 2 gives the technical information on Unit 3. The turbine type of Unit 3 is similar to Units 1 and 2; however, the rated power, speed, and gate position ratings are different. Also, one can see the difference in the governor control mechanism by looking at the figures in
Section 4.
5. Discussion and Future Work
In Units 1 and 2, the tagged anomalies are mostly due to post-maintenance trials and measurement failure. However Unit 3 results present successful detection cases. In the detected anomalous startups, the calculated variable violated the operational limits. The false detections are mostly due to post-maintenance startups where the units do not operate at rated power and the false data retrievals from the plant SCADA. The method solely depends on the SCADA measurements, and the false data injections significantly reduce the method’s accuracy. As future work, the studied power plant or a reference plant will be modeled in a simulation environment and the actual fault scenarios will be obtained synthetically. Also, the type of anomalies or which parts of the conduit system or the controller cause such anomalies will be investigated via the simulation environment. With investigation and additional measurements (water flow rate, lake water level, turbine case pressure readings, etc.), the aging and efficiency of the water conduit system and turbine can be analyzed. Also, the sudden or incoming failures can be detected. In simulation environment and detailed modeling of the power plant units, these detection and identification aspects will be further studied.
The interaction between the units is another aspect of this study. The effect of an ongoing operation of one unit on another unit’s startup will be investigated in the future. The inclusion of other measurements related to the water conduit system will increase the method’s accuracy in the early detection of faults. Co-monitoring of measurements like pressure readings, voice recording around the penstock, etc., will improve the overall assessment. Furthermore, the seasonal differences on the net head and the water flow and the compensated governor action will be further studied in upcoming work.
Although fuel-based generation units will participate less in the future, their dynamic operation against system uncertainties still matters. Therefore, the method can be useful in the condition monitoring of fuel-based power plants as well. For instance, the steam generation and turbine connection parts in the fuel-based power plants have complex structures. Similar to the water conduit system in a hydropower plant, the condition monitoring of these structures might be of importance in the future. The developed method can be modified to the steam unit measurements, and condition monitoring of the unit can be implemented.