Next Article in Journal
Transitioning to a Circular Economy in the Energy Sector: A Systematic Review of Sustainable Business Models and Green Financing Mechanisms
Previous Article in Journal
A CFD–GPR–NSGA-II Framework for Thermal–Hydraulic Optimization of Mini-Channel Liquid Cooling Plates in Electric Vehicle Battery Thermal Management Systems
Previous Article in Special Issue
Exergy-Based Performance Evaluation of a Multi-Unit Hydropower System: A Case Study of the Upper Tamakoshi Hydropower Project in Nepal
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Maintenance Prioritization in Photovoltaic Installations Using a Hybrid Particle Swarm Optimization–Failure Mode and Effects Analysis–VIKOR Decision Framework

by
Paweł Kut
,
Katarzyna Pietrucha-Urbanik
* and
Sławomir Rabczak
Faculty of Civil, Environmental Engineering and Architecture, Rzeszow University of Technology, Al. Powstańców Warszawy 6, 35-029 Rzeszów, Poland
*
Author to whom correspondence should be addressed.
Energies 2026, 19(11), 2622; https://doi.org/10.3390/en19112622
Submission received: 7 May 2026 / Revised: 25 May 2026 / Accepted: 28 May 2026 / Published: 29 May 2026

Abstract

Photovoltaic (PV) installations require maintenance prioritization models capable of ranking technically diverse failure modes under operational, safety, and serviceability constraints. Conventional Failure Mode and Effects Analysis (FMEA) approaches often cannot integrate downtime, cost, safety, and detectability into a single transparent workflow. This study develops a hybrid Particle Swarm Optimization (PSO)-FMEA-VIseKriterijumska Optimizacija I Kompromisno Resenje (VIKOR) framework for maintenance prioritization of eight representative PV failure modes. Classical FMEA was used as a diagnostic baseline, a seven-criterion maintenance matrix was constructed, PSO calibrated criteria weights, and a criticality-oriented VIKOR compromise-ranking procedure generated the final ordering. Semi-empirical operational and service log evidence was used only to anchor the interpretation of occurrence, direct cost, and downtime; it was not treated as a real-time fault-detection dataset. The results identified inverter overvoltage shutdown/grid incompatibility, cable insulation degradation, and junction box overheating as the highest maintenance priorities. Their ordering differed from classical Risk Priority Number (RPN) results, showing that frequency alone does not adequately represent maintenance urgency. Sensitivity analysis confirmed the stability of the two leading alternatives under different VIKOR strategy parameters. The framework provides a discriminative decision support tool for inspection planning, service scheduling, and corrective-action targeting in grid-connected PV systems, while further validation on larger Supervisory Control and Data Acquisition (SCADA)- or inverter-log-based datasets remains necessary.

1. Introduction

Photovoltaic (PV) installations are among the fastest growing renewable energy technologies, yet their long-term technical value depends not only on installed capacity but also on operational reliability, continuity of service, and the effectiveness of maintenance management [1,2]. Earlier studies have shown that PV systems are exposed to heterogeneous fault mechanisms, including module degradation, hotspot-related damage, junction box malfunction, and cable insulation deterioration [3,4]. Other reported failure categories include inverter disconnection, balance-of-system faults, weather-related defects, and reliability-oriented PV failure patterns [5,6]. Because these failures differ not only in frequency but also in consequences, maintenance prioritization cannot be reduced to a single technical symptom [7,8].
From a research landscape perspective, the topic of PV failure analysis can be structured into four closely related domains: module degradation and defect mechanisms, inverter and balance-of-system failures, fault detection and diagnostic methods, and maintenance- or reliability-oriented decision support [1,3]. Inverter-related failures, weather-related defects, control-related faults, and system-level reliability issues form the remaining part of this landscape [5,8]. Predictive maintenance research further highlights the need to connect technical failure categories with maintenance decisions [9,10]. The present work is positioned at the intersection of these domains. It is not a broad bibliometric review, a monitoring study, or a predictive maintenance algorithm paper; instead, it focuses on the maintenance priority layer, where different technical, safety, and service criteria must be integrated into a single decision framework.
Methodologically, classical Failure Mode and Effects Analysis (FMEA) remains attractive because of its simplicity and engineering interpretability, but its conventional Risk Priority Number (RPN) has well-known limitations [11,12]. It may assign similar priorities to technically dissimilar faults, underrepresent downtime-related or safety-critical events, and provide insufficient discrimination when several operational dimensions must be balanced simultaneously [13,14]. In PV systems, this limitation is particularly relevant because some failures are frequent but gradual, whereas others are less frequent yet much more disruptive in terms of outage duration, fire hazard, or repair urgency. This is also relevant to low-voltage electrical networks, where rapid arc extinction and dynamic thyristor-controlled hybrid switching have been investigated as protection mechanisms for reducing arc-fault consequences [15].
To define the scope of the present study more precisely, the analysis is limited to maintenance-critical failure modes in grid-connected PV installations. Broader issues such as market diffusion, policy incentives, life-cycle carbon assessment, or portfolio-level energy planning are outside the study boundary. Within this scope, three research questions are addressed:
  • R1: Which representative PV failure modes should be prioritized from a maintenance perspective?;
  • R2: How does an optimized multi-criteria ranking differ from a classical FMEA ordering?;
  • and R3: Which criteria most strongly influence the final priority structure?
Accordingly, the aim of this study is to develop a hybrid Particle Swarm Optimization (PSO) Failure Mode and Effects Analysis (FMEA)-VIseKriterijumska Optimizacija I Kompromisno Resenje (VIKOR) framework for maintenance prioritization in photovoltaic installations.
The scientific contribution is threefold:
  • First, classical FMEA is embedded in an explicitly maintenance-oriented seven-criterion architecture rather than being used as a standalone RPN tool.
  • Second, the weighting structure is not assumed a priori, but optimized by PSO to improve ranking separation under the adopted constraints.
  • Third, the final ranking is interpreted against field-documented service cases, which strengthens the link between the decision model and real engineering consequences.
The additions are intended to move the work beyond a descriptive fault listing toward a reproducible and decision-relevant maintenance methodology.
The proposed framework is not intended to operate as a standalone real-time fault-detection system. It assumes that faults or failure categories have already been identified through inspection, monitoring, user reporting, service documentation, or diagnostic procedures. Its practical contribution lies in converting heterogeneous fault evidence into a transparent maintenance priority ranking that can support inspection planning, preventive maintenance scheduling, and corrective action targeting.

2. Materials and Methods

2.1. Methodological Framework

The study was designed as a hybrid decision support framework integrating Failure Mode and Effects Analysis (FMEA), Particle Swarm Optimization (PSO), and VIseKriterijumska Optimizacija I Kompromisno Resenje (VIKOR) [11,12,16]. PSO was included as the optimization layer because particle swarm algorithms are established tools for parameter and weight optimization in engineering problems [17,18]. The VIKOR stage was used because it provides a compromise solution under conflicting criteria and can combine overall utility with the most unfavorable criterion [16].
The methodological sequence consisted of:
  • identification of representative PV failure modes;
  • definition of a maintenance-oriented evaluation structure; baseline screening with classical FMEA;
  • optimization of criteria weights using PSO;
  • final compromise ranking using VIKOR;
  • sensitivity analysis of ranking stability. The framework was intentionally positioned as a methodological maintenance prioritization model demonstrated on representative PV failure modes.
The complete analytical workflow is summarized in Figure 1.

2.2. Failure Mode Identification

The analyzed failure modes were selected using a literature-grounded and service-informed maintenance perspective. The failure structure was aligned with categories repeatedly identified in PV failure studies, including shading and hotspot-related effects, junction box failures, aging, and cable insulation degradation [1,3]. It also reflected reported inverter disconnection, weather-related defects, balance-of-system faults, and control-related failures [5,8]. In addition, the selection was cross-checked against the authors’ semi-empirical evidence sources: a 50-case installation/user-level operational dataset and an independent database of 1000 documented PV service interventions. The service log indicators confirmed the practical relevance of inverter hardware failures, logger disconnections, DC fuse faults, melted MC4 connectors, mechanical module damage, DC automatic-switch faults, hot-spot-related claims, and arc-fault-related DC side damage. Therefore, the eight alternatives were not selected from literature alone, but from a triangulation of published PV failure categories, earlier survey-based observations [9], and documented maintenance practices.
  • A1—partial shading and hotspot formation;
  • A2—junction box overheating/failure;
  • A3—cable insulation degradation;
  • A4—cell microcracking and interconnection failure;
  • A5—glass breakage due to hail impact;
  • A6—aging-related power degradation;
  • A7—inverter overvoltage shutdown/grid incompatibility;
  • A8—tracker/control automatics failure.

2.3. Evaluation Criteria and Scope Adaptation

Seven criteria were used to evaluate the selected failure modes:
  • C1—severity of energy loss,
  • C2—occurrence frequency,
  • C3—detectability difficulty,
  • C4—maintenance cost,
  • C5—safety impact,
  • C6—downtime effect,
  • C7—environmental exposure sensitivity.
All criteria were treated as cost-type criteria, meaning that higher values represented less favorable conditions. Ratings were assigned on a 10-point ordinal scale.
Because the objective of the study was not to select the technically least problematic failure mode, but to identify the most maintenance-critical failures, the subsequent ranking was interpreted in a criticality-oriented manner. Higher scores, therefore, intentionally represented increasing maintenance burden. In the VIKOR stage, the reference direction was defined relative to the critical maintenance priority profile rather than toward the least severe technical condition.
The criteria architecture was not copied directly from the earlier Analytic Hierarchy Process (AHP)-based risk table reported in the PV failure literature, but its logic was adapted to the needs of maintenance prioritization [1]. Design and performance considerations informed the interpretation of severity and detectability; operation-informed occurrence and outage-related consequences; financial aspects were represented by maintenance costs and downtime effects; and environmental factors were retained as environmental exposure sensitivity. The previously separated social dimension was not retained as a standalone criterion because the present article focuses on maintenance-critical technical prioritization rather than stakeholder acceptance or land-use nuisance.
The seven criteria were selected to represent the main engineering dimensions that determine maintenance urgency. C1 captures the expected production consequence of a failure mode; C2 reflects how often the event is expected or observed to occur; C3 represents the difficulty of detecting the fault before escalation; C4 reflects direct intervention, replacement, or repair cost; C5 captures electrical, thermal, and fire safety relevance; C6 represents service interruption and repair cycle duration; and C7 reflects exposure to environmental stressors such as humidity, hail, wind, temperature, soiling, or shading. This structure is consistent with FMEA logic, PV reliability literature, and maintenance management requirements, while remaining sufficiently compact for a reproducible multi-criteria ranking.

2.3.1. Scoring Anchors and Consistency Protocol

To improve scoring consistency, the 10-point scale was interpreted using fixed engineering anchors. For the severity of energy loss, a score of 1 represented a negligible impact on system output, while 10 denoted a major production interruption. For detectability difficulty, lower values represented faults readily identified during routine inspection or monitoring, whereas higher values denoted hidden or progressive faults requiring dedicated diagnostics. For safety impact, a score of 10 indicated a strong electrical, thermal, or fire hazard potential.
In addition, scores in the upper range of the scale were reserved for failure modes combining severe production loss with at least one additional critical maintenance consequence, such as electrical safety implications, difficult detectability, or prolonged service interruption. This rule was introduced to ensure that high values were assigned not only to frequent events, but also to failures with high operational severity, safety relevance, or substantial service burden. In this way, the scoring logic remained consistent with the maintenance prioritization objective of the proposed framework and improved the reproducibility of future case studies (Table 1).
To further reduce scoring subjectivity, the semi-quantitative assessment followed a three-step protocol. First, scoring anchors were derived from the combined reading of PV reliability literature, maintenance studies, and field-documented service observations. Second, preliminary scores were assigned criterion-by-criterion for each failure mode and then reconciled in a consistency check focused on internal logic across severity, detectability, downtime, and safety dimensions. Third, the final matrix was screened for dominance anomalies and implausible ties before the PSO–VIKOR stage was executed. The field images used later in the article were not treated as additional quantitative cases; they were used only to support the engineering interpretation of already ranked alternatives.
The anchors were used as a common scoring protocol for all seven criteria. They were not intended to convert the semi-empirical evidence into deterministic failure rates, but to make the expert-informed ordinal scoring more transparent and repeatable.

2.3.2. Semi-Empirical Maintenance Evidence Support

The semi-empirical evidence layer consisted of two separate and non-merged data sources collected in the same regional PV-service context in south-eastern Poland. The first source was a 50-case operational dataset at the installation/user level. It covered residential and small-commercial grid-connected PV installations and included user-reported operational problems, PV system failures, warranty repair indications, inverter disconnection events during grid voltage rises, and approximate repair duration patterns. The source period was treated as a retrospective operational evidence period rather than a controlled monitoring campaign; therefore, these data were used only as contextual installation/user-level evidence.
The operational and service evidence was collected retrospectively in south-eastern Poland over a multi-season maintenance period covering both high-production and low-production PV operating conditions.
The second source was an independent service log database comprising 1000 documented PV service interventions extracted from anonymized maintenance documentation available to the authors in the same regional service context in south-eastern Poland. The database covered documented service interventions from a retrospective maintenance period and included technician notes, repair or replacement categories, cost records, service duration information, and photographic evidence where available. Due to commercial confidentiality, the service provider and detailed record-level identifiers are not disclosed. This source was used at the intervention level to determine indicative frequencies, typical direct service costs, and typical downtime/service duration for selected maintenance-event categories.
Because the evidence was collected in south-eastern Poland, the interpretation of weather-sensitive failures should be regarded as regionally contextualized. The study did not perform a separate meteorological normalization of service events; weather-related exposure was represented only through criterion C7 and through documented categories such as hail impact, soiling or shading, humidity-related degradation, and temperature-related stress, where such information was available in the records.
Fault confirmation differed between the two evidence layers. In the 50-case operational dataset, the evidence was based mainly on user-reported installation-level information and selected repair or warranty indications. In the 1000-case service log database, events were confirmed through maintenance documentation, technician diagnosis, replacement or repair notes, and photographs where available. No continuous real-time Supervisory Control and Data Acquisition (SCADA), inverter log, Internet of Things (IoT), phasor measurement unit (PMU), or micro-PMU validation was performed in the present study; this limitation is explicitly acknowledged in the Discussion.
The two sources were not statistically merged. The 50-case dataset describes installation/user-level operational evidence, whereas the 1000-case service log database describes intervention-level service evidence. Therefore, percentages derived from the 50-case dataset and indicators expressed per 1000 service interventions should not be directly compared because they refer to different observational units and different event definitions (Table 2).
Both evidence layers were used only to support the engineering interpretation of occurrence frequency (C2), maintenance cost (C4), downtime effect (C6), safety impact (C5), detectability difficulty (C3), and serviceability. They were not used as direct numerical inputs to the PSO or VIKOR calculations. The direct numerical input to the PSO-FMEA-VIKOR procedure was the semi-quantitative decision matrix developed on a 10-point ordinal scale using literature evidence, FMEA logic, engineering scoring anchors, and field/service observations.

2.4. Comparison of Multi-Criteria Decision Analysis Methods and Selection of VIKOR

The choice of a ranking method is not trivial in maintenance priority studies because different multi-criteria decision analysis (MCDA) families embody different compensation logics, threshold assumptions, and levels of decision transparency. In energy and infrastructure applications, the Analytic Hierarchy Process (AHP), the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS), and VIseKriterijumska Optimizacija I Kompromisno Resenje (VIKOR) are widely used decision support methods [16,19,20]. Outranking and ratio-based methods such as PROMETHEE II, ELECTRE, MOORA, and ARAS provide alternative decision logics [21,22]. WASPAS, EDAS, MARCOS, and fuzzy extensions further broaden the MCDA toolbox [23,24,25]. Recent energy planning studies also confirm that the suitability of a specific MCDA method depends on the problem structure, the need for pairwise comparisons, the importance of compromise ranking, the treatment of uncertainty, and the desired balance between methodological simplicity and analytical discrimination [26,27,28].
Recent PV-oriented applications show that AHP and TOPSIS have been used for PV end-of-life management and off-grid PV microgrid siting [29,30]. Other PV-related applications include solar energy implementation assessment and PV panel cleaning method selection [31,32]. VIKOR and PROMETHEE have been applied to solar panel selection, photovoltaic solar plant location analysis, and solar panel cooling system evaluation [33,34,35]. ELECTRE and MOORA have been reported in PV technology and solar power plant location selection problems [36,37,38]. ARAS and WASPAS have also been used in renewable energy and photovoltaic location selection contexts [39,40]. EDAS and related MCDA methods have been used in smart solar panel evaluation and renewable energy community configuration studies [41,42].
In the present study, VIKOR was selected as the final ranking engine because the decision problem is characterized by conflicting maintenance criteria and by the need to balance overall utility with the most unfavorable criterion. This property is important for PV maintenance because some failures are frequent but comparatively manageable, whereas others are less frequent yet highly disruptive due to safety consequences, poor detectability, or long downtime. AHP was considered more useful as a conceptual weighting benchmark, TOPSIS as a proximity-to-ideal method, and PROMETHEE II/ELECTRE as valuable outranking families; however, the compromise logic of VIKOR was judged to be the most consistent with the maintenance priority objective adopted in this article. The comparative positioning of the main MCDA families is summarized in Table 3.

2.5. FMEA-Based Preliminary Assessment

A baseline FMEA assessment was performed using severity (S), occurrence (O), and detection (D) ratings. The Risk Priority Number for the i-th failure mode was calculated as:
RPNi = Si × Oi × Di
The use of FMEA in the present study is methodologically justified for four reasons. First, FMEA provides a transparent and reproducible baseline for structuring heterogeneous PV failure knowledge when long-term fault logs are incomplete or not fully standardized [11,12]. Second, the S–O–D triad remains highly interpretable for maintenance engineers and allows rapid pre-screening of alternatives before more advanced optimization is introduced [13,14]. Third, PV-oriented FMEA studies confirm that this approach is effective for identifying technically critical events such as module degradation and inverter-related failures [13,14]. Related reliability and prognostic studies further support the need to include overheating and service-critical faults [49,50]. Maintenance planning and criticality studies also justify combining FMEA with broader prioritization criteria [51,52]. Fourth, retaining FMEA as the first analytical layer makes it possible to show explicitly how the final PSO–VIKOR ranking diverges from the classical RPN logic.
The FMEA stage served as a reference layer rather than the final ranking method. Its purpose was to determine whether the same priorities would persist once broader operational criteria were introduced. The use of FMEA in PV contexts is well established [11,12], and the limitations of classical RPN formulations have also been widely discussed [13,14].

2.6. Decision Matrix

The multi-criteria evaluation structure was represented by the decision matrix X = [xij], where m = 8 failure modes and n = 7 criteria. Each element xij denotes the rating of the i-th failure mode under the j-th criterion. The raw decision matrix is presented in Table 4.

2.7. PSO-Based Weight Optimization

Because the final ranking depends on the adopted weighting structure, the criteria weights were optimized using PSO [17,18,53]. The use of PSO for engineering model calibration and reliability-oriented updating is also supported by recent applications [54]. In this algorithm, each particle represents a candidate weight vector w = (w1, w2, …, wn), subject to normalization and non-negativity constraints.
vk+1ij = ωvkij + c1r1(pbestkijxkij) + c2r2(gbestkjxkij)
xk+1ij = xkij + vk+1ij
where xkij and vkij denote the position and velocity of particle i in dimension j at iteration k, pbestkij denotes the personal-best position, gbestkj denotes the global-best position, ω is the inertia coefficient, c1 and c2 are the cognitive and social coefficients, and r1 and r2 are random numbers uniformly distributed in [0, 1] [17,18,53].
The PSO procedure was run using a swarm size of 50, a maximum of 200 iterations, inertia weight ω = 0.70, and cognitive and social coefficients c1 = c2 = 1.50. Thirty independent runs were performed. These values were selected according to commonly used PSO practice and the parameter ranges recommended in the foundational PSO literature, where moderate inertia and balanced cognitive/social coefficients are used to maintain both exploration and convergence stability [17,18,53]. The chosen swarm size and iteration limit were also sufficient for the seven-dimensional weight search problem, because repeated runs produced the same leading priority cluster, and no further ranking changes were observed after convergence.
The optimization target was formulated to maximize the average pairwise separation of the final VIKOR compromise values, thereby discouraging near-tied rankings that would be of limited operational use. This objective was selected because the purpose of the model was to support maintenance prioritization, where ambiguous near-ties are difficult to translate into inspection or service schedules. It was not used to enforce a predefined priority order; the ranking was subsequently checked against equal weight and literature/expert-weight scenarios. The optimized weights should therefore be interpreted as discrimination-oriented decision calibration parameters for the adopted matrix, not as universal empirical failure-rate coefficients. The optimization was performed subject to the following feasibility constraints:
j = 17 wj = 1, wj ≥ 0, j = 1, …, 7
where wj denotes the weight assigned to criterion j.
The constraint ensures that PSO searches within the feasible space of criterion-weight vectors rather than assigning arbitrary weights, and improves discrimination among maintenance priorities while preserving decision matrix consistency.
To avoid over-interpreting the optimized weights, the PSO result was evaluated together with the classical FMEA baseline, the VIKOR parameter sensitivity analysis, and the semi-empirical maintenance evidence. This combined interpretation reduces the risk that the final ranking is treated as a product of the optimization function alone.
The methodological appeal of PSO in this context is also consistent with broader engineering and energy system applications, where the algorithm has been successfully used for nonlinear calibration, control tuning, and predictive model optimization in complex search spaces [48,54,55].

2.8. VIKOR Compromise Ranking

The final maintenance priority ranking was obtained using a criticality-oriented VIKOR procedure [16,19]. Because all criteria were scored so that higher values indicated higher maintenance burden, the reference direction was defined toward the most critical maintenance profile. In the present criticality-oriented interpretation, Si and Ri represent the aggregate and maximum normalized distances from the critical maintenance profile, respectively; Qi integrates these two distances into a compromise priority index. For each criterion, fj* denotes the most critical value and fj denotes the least critical value. The utility measure Si, the regret measure Ri, and the compromise index Qi were calculated as follows:
Si = ∑j = 17 wj [(fj* − fij)/(fj* − fj)]
Ri = maxj {wj [(fj* − fij)/(fj* − fj)]}
Qi = v[(SiS*)/(SS*)] + (1 − v)[(RiR*)/(RR*)]
where wj is the normalized weight of criterion j, v is the compromise strategy parameter, S* = mini Si, S = maxi Si, R* = mini Ri, and R = maxi Ri. The parameter v reflects the balance between group utility and individual regret; in this study, v = 0.50 was adopted. Alternatives were ranked in ascending order of Qi. Lower Qi values, therefore, indicate stronger proximity to the critical maintenance priority profile, not proximity to the least problematic technical condition. The choice of VIKOR as the final ranking tool is consistent with its intended use in multi-criteria compromise decisions [16,19].

2.9. Sensitivity Analysis Procedure

To test ranking robustness, the VIKOR compromise parameter v was varied over three levels: 0.25, 0.50, and 0.75. This allowed evaluation of whether the most important priorities remained stable under moderate changes in decision strategy.
From the perspective of methodological reproducibility, the sensitivity analysis was intended as a minimal robustness check rather than a full uncertainty propagation exercise. The present article, therefore, tests the stability of the priority order against preference-aggregation changes, while more advanced extensions—such as Monte Carlo perturbation of scores or probabilistic failure rate integration—are identified as future work.

3. Results

3.1. Baseline FMEA Assessment

The classical FMEA screening indicated that aging-related power degradation (A6) achieved the highest RPN value, followed by partial shading and hotspot formation (A1), junction box overheating/failure (A2), and cell microcracking/interconnection failure (A4), as shown in Table 5. The lowest RPN value was assigned to hail-induced glass damage (A5). The baseline ordering suggests that frequently occurring degradation-driven faults dominate the RPN structure, while failures with stronger downtime or safety implications may be underrepresented.

3.2. Optimized Criteria Weights

The PSO procedure converged consistently across repeated runs and produced a stable weighting structure (Table 6). The greatest importance was assigned to the severity of energy loss, occurrence frequency, and safety impact, indicating that the final prioritization was driven mainly by operational significance and hazard potential rather than by direct maintenance cost alone. Because the optimized weights might otherwise be perceived as purely separation-driven, the PSO result was also compared with equal weight and literature/expert weight benchmarks.
To reduce the risk of interpreting PSO as weight fitting to a desired result, the optimized solution was compared with two benchmark weighting scenarios. The comparison was used as a robustness check rather than as an additional calibration stage (Table 7).

3.3. Final VIKOR Ranking

The final VIKOR ranking identified inverter overvoltage shutdown/grid incompatibility (A7) as the highest-priority maintenance item within the adopted decision structure, followed by cable insulation degradation (A3) and junction box overheating/failure (A2), as reported in Table 8. This result indicates that maintenance priority is not determined by occurrence alone. Once downtime, safety, and detectability are explicitly introduced, system-level interruptions and difficult-to-detect electrical degradation gain importance.
The engineering interpretation of the three leading alternatives is also consistent with the adopted criterion structure. A7 combines immediate production interruption with repeated serviceability problems at the grid interface level. A3 receives a high priority because cable insulation degradation may remain difficult to detect, while increasing electrical and fire risk exposure. A2 is ranked highly because junction box overheating can combine localized thermal escalation, safety relevance, and corrective maintenance urgency. In the criticality-oriented formulation used here, lower Q values indicate higher maintenance priority.

3.4. Comparison of Baseline and Optimized Rankings

The most significant shift occurred for inverter overvoltage shutdown/grid incompatibility (A7), which moved from the sixth position in the classical FMEA to the first place in the final ranking (Table 9). Similarly, cable insulation degradation (A3) moved from fifth to second position, confirming the importance of safety and detectability in maintenance prioritization. By contrast, the ranking of cell microcracking dropped substantially, indicating that long-term degradation relevance does not automatically translate into immediate maintenance urgency.
Positive rank-shift values indicate that a failure mode received higher priority in the PSO–VIKOR ranking than in the classical FMEA ranking. Negative values indicate a lower priority after multi-criteria weighting and compromise ranking.

3.5. Sensitivity Analysis Results

The ranking remained fully stable for the two highest-priority alternatives, A7 and A3, while only moderate shifts appeared in the middle section of the ranking (Table 10). The stability of the highest-ranked alternatives supports the robustness of the proposed prioritization framework.
This result is important because the top of the ranking carries the greatest operational consequence for maintenance planning. The stability of A7 and A3 indicates that the main managerial conclusion is not driven only by one arbitrary value of the compromise parameter, although broader probabilistic uncertainty propagation remains a task for future work.

3.6. Semi-Empirical Maintenance Evidence

The semi-empirical evidence layer supported the decision structure from both the operational and service perspectives. In the 50-case installation/user-level dataset, at least one PV system failure was identified in 30% of cases, frequent inverter disconnections during grid-voltage rise were reported in 60% of cases, and 60% of the recorded technical failures were associated with the inverter category. Inverter disconnection during grid voltage rise was treated as an operational interruption or serviceability event rather than as a hardware failure. This distinction explains why its reported frequency may exceed the percentage of cases classified as technical PV system failures. In addition, 47% of reported repairs required one to two weeks, which confirms that service interruption is not a negligible maintenance dimension in practical PV operation.
The independent 1000-case service log database showed strong heterogeneity at the intervention level. Some events, such as logger disconnection after router or network changes, were relatively frequent but had low direct repair costs, whereas inverter hardware failure, mechanical module damage, and electrically escalated DC-side events generated substantially higher direct service burden. The aggregated evidence used for the maintenance interpretation is summarized in Table 11.

3.7. Empirical Service-Profile Comparison

To visualize the practical asymmetry between frequency, direct repair cost, and downtime, five documented service event categories with numerically usable indicators were normalized and compared. The purpose of this step was not to replace the PSO–FMEA–VIKOR ranking with a new empirical model, but to test whether maintenance burden in actual service practice behaves as a one-dimensional variable. The answer is clearly negative. The normalized comparison is summarized in Table 12.
The pattern confirms that the most frequent event is not necessarily the most burdensome from the maintenance viewpoint. Logger disconnection dominated frequency, but its direct cost and outage burden were modest. Inverter hardware failure was rare, yet it generated the longest service cycle, whereas mechanical module damage had a low incidence but the highest direct intervention cost. This decoupling strongly supports the use of a multi-criteria framework instead of any ordering based on frequency alone. The comparison shows that practical maintenance burden is structurally multi-dimensional and cannot be inferred from event frequency alone.

3.8. Engineering Interpretation of Field-Documented Failures

Field-documented service cases were used to strengthen the practical interpretation of the ranking (Table 13). Rather than treating images as illustrative additions only, they were used as engineering evidence of the kinds of faults that justify high scores for severity, safety impact, downtime effect, or detectability difficulty. In the present version of the manuscript, the selected images emphasize defects different from those already used in the authors’ earlier PV article, thereby broadening the practical fault portfolio considered here (Figure 2).
The photographs were taken from the authors’ field archive and are used as technical documentation of PV failure manifestations. Their function is interpretative and diagnostic: they connect the numerical priority structure with observable failure consequences without replacing the decision matrix or the semi-empirical service-profile comparison.
The selected cases include a mechanically damaged PV module, a thermally damaged DC automatic switch terminal, an arc-fault-damaged PV installation, and an arc-fault-damaged electrical connector. Together, these cases show how maintenance-critical PV faults can combine visible component damage with service interruption and elevated fire or electrical risk. Their role in the article is interpretative: they help explain why electrical and thermally escalated faults receive high maintenance priority even when they are not the most frequent events.

4. Discussion

The results show that the priority structure of PV maintenance tasks changes substantially when the assessment moves from a classical RPN-based formulation to an optimized multi-criteria ranking framework. In the present study, inverter overvoltage shutdown/grid incompatibility, cable insulation degradation, and junction box overheating/failure emerged as the highest-priority items within the adopted failure set and criteria structure. This indicates that maintenance urgency in photovoltaic installations should not be interpreted as a direct function of occurrence frequency only, but rather as the outcome of combined production, safety, downtime, and detectability effects [1,2]. Module- and system-level PV failure studies further support this multi-dimensional interpretation [3,4]. Predictive-maintenance and FMEA-based studies similarly support interpreting PV maintenance as a multi-criteria decision problem [10,11]. The added service evidence makes this conclusion more credible from a maintenance management perspective, because it shows directly that event frequency, direct repair cost, and outage duration are only partially correlated in practice [9].
The highest-ranked position of inverter overvoltage shutdown/grid incompatibility is technically justified. Inverter-related shutdown may immediately interrupt energy production across a large part of the installation. This interpretation is consistent with earlier PV-failure literature, where excessive grid voltage and resulting inverter disconnection were identified as important operational drawbacks affecting profitability and system operation [1,2]. More recent PV reliability reviews also emphasize inverter and grid interaction disturbances as important operational issues [3,4].
Cable insulation degradation also gained prominence after the transition from FMEA to the optimized ranking. This shift is important because cable faults may develop progressively, remain difficult to detect, and simultaneously contribute to overheating, leakage, and elevated fire risk. The broader PV failure literature identifies cable- and connection-related defects among the causes of performance loss and hazard escalation [5,6]. Fault-detection and reliability studies also emphasize the maintenance relevance of electrical connection defects and balance-of-system faults [7,8]. Operational evidence and hotspot-related PV studies further support the practical relevance of connection-related defects for maintenance prioritization [9,56,57].
A major strength of the study is the use of field-documented evidence. The selected images and service case interpretations do not replace formal diagnostic datasets, but they strengthen the engineering realism of the model by illustrating how maintenance-critical failures manifest in practice. The chosen cases—mechanical module damage, DC automatic switch thermal damage, and arc-fault-related connector deterioration—support the argument that maintenance priority should emphasize not only frequency, but also escalation potential and service consequences. The relevance of rapid arc extinction in low-voltage networks is also supported by recent work on dynamic thyristor-controlled hybrid switching for fast arc suppression [15].
The sensitivity analysis further supports the practical value of the framework. The two highest-priority alternatives remained stable across the entire tested range of the VIKOR parameter, which means that the final ranking is not excessively dependent on a single decision strategy. From a methodological perspective, the use of PSO for weight optimization is also justified, because PSO has repeatedly been shown to be efficient in uncertain engineering optimization and parameter-estimation tasks [17,18,53]. Applications in model updating, geometry fitting, and ANN-based prediction further demonstrate its suitability for uncertain engineering problems [54,58,59].
From a method selection standpoint, the expanded MCDA comparison presented in Table 3 also clarifies why VIKOR was retained as the final ranking layer. AHP remains excellent for structuring criteria but is less convenient for direct ranking when the number of alternatives grows; TOPSIS is intuitive but does not explicitly emphasize the worst-performing criterion [20,21]. PROMETHEE II or ELECTRE may offer powerful outranking logic at the price of additional threshold choices [22,23]. For the present problem, where safety, detectability, and downtime may dominate even when overall occurrence is moderate, the compromise structure of VIKOR provides a defensible balance between interpretability and decision severity [16]. Method comparison and energy planning studies confirm that the choice of MCDA technique should reflect both analytical discrimination and practical interpretability [24,45]. Further studies on fuzzy and energy-oriented MCDA applications reinforce this methodological positioning [25,46].
The broader decision-aiding literature extends beyond the subset summarized in Table 3 and also includes point scoring methods, the MAJA procedure, filtration procedures, and interactive approaches. These families remain useful in engineering and project planning contexts, especially when the analyst expects staged screening or intensive participation of the decision maker, but they are less straightforward to operationalize for a compact full ranking of PV failure alternatives than VIKOR and mainstream outranking methods [43,44].
An additional cross-method check carried out on the same decision matrix and optimized weights showed that a classical TOPSIS ranking would favor more balanced alternatives and produce a different leading order than the VIKOR solution (Table 14). This divergence is not a weakness of the present study; rather, it confirms that method choice is consequential. Distance-based logic tends to reward alternatives with evenly distributed scores, whereas the VIKOR compromise formulation more strongly penalizes failure modes with severe worst-criterion implications, especially where downtime and safety dominate maintenance urgency. For PV asset management, the latter logic is defensible because highly disruptive failures should not be obscured by otherwise moderate average performance.
The TOPSIS check used the same seven-criterion decision matrix and PSO-optimized weights as the VIKOR stage, but applied a distance-based closeness logic to the critical maintenance profile.

4.1. Practical Implementation Workflow for PV Operators

For practical deployment, the proposed framework can be implemented as a periodic maintenance prioritization module rather than as a real-time fault detector. A PV operator or maintenance company may apply the following workflow: (1) collect fault, alarm, inspection, service, warranty, and cost data from user reports, service books, inverter event logs, SCADA systems, or IoT sensors where available; (2) classify each event into an existing failure mode or create a new alternative if the event is recurrent and technically distinct; (3) assign or update scores for C1–C7 using the scoring anchors; (4) update or verify the criterion weights using PSO or a benchmark weighting scenario; (5) run the criticality-oriented VIKOR ranking; (6) translate the leading alternatives into inspection, preventive maintenance or corrective action schedules; and (7) periodically update the decision matrix when new service evidence becomes available. In this way, the framework can support both small PV service portfolios and utility-scale PV maintenance environments, provided that the input data are consistently classified and documented.

4.2. Adaptability to Unknown, Combined, or Evolving Faults

The current version of the framework uses predefined representative PV failure modes. This is appropriate for a transparent maintenance priority demonstration, but it does not automatically discover unknown faults. In practical applications, unseen or combined faults can be handled by adding new alternatives to the decision matrix once sufficient diagnostic or service evidence becomes available. A monitoring or pre-processing layer based on inverter logs, SCADA alarms, thermographic inspections, clustering, or anomaly detection could be placed before the MCDA stage. Such a layer would identify recurrent abnormal patterns, while the PSO–FMEA–VIKOR module would subsequently prioritize them from the maintenance perspective.

4.3. Limitations and Future Validation

Several limitations should be acknowledged. First, the 50-case operational dataset should be interpreted only as contextual installation/user-level evidence and not as a statistically representative fleet-level database. Second, although the 1000-case service log database provides stronger service-practice grounding, it is still an anonymized maintenance archive rather than a fully open fleet-level reliability dataset; detailed provider identifiers and record-level dates are not disclosed due to commercial confidentiality. Third, the present study does not include real-time validation using SCADA, inverter logs, IoT sensors, PMU, or micro-PMU measurements. Future validation should therefore use time-stamped inverter event logs, SCADA alarms, thermographic inspections, current and voltage monitoring, IoT-based temperature sensors, PMU or micro-PMU measurements, and long-term service records. Fourth, the decision matrix remains semi-quantitative and expert-informed, despite the use of scoring anchors and consistency checks. Future work should extend the framework toward probabilistic data fusion, Monte Carlo perturbation of scores, cross-method benchmarking, and long-term validation on larger operational datasets. Fifth, the regional character of the evidence should be considered when interpreting weather-sensitive failure modes, because local climatic and grid conditions in south-eastern Poland may differ from those of other PV markets.

5. Conclusions

This study proposed a hybrid Particle Swarm Optimization (PSO)–Failure Mode and Effects Analysis (FMEA)–VIKOR decision framework for maintenance prioritization in photovoltaic installations. By combining classical FMEA with a seven-criterion maintenance matrix, PSO-based weight calibration, and VIKOR compromise ranking, the method produced a more differentiated priority structure than the conventional Risk Priority Number (RPN) approach. The addition of semi-empirical operational and service log evidence further strengthened the practical grounding of the proposed framework by demonstrating that inverter-related interruptions, direct service costs, and downtime are not merely theoretical dimensions, but recurring managerial realities in operating PV systems. These evidence layers were used for engineering interpretation and plausibility checking, not as direct numerical inputs to the PSO or VIKOR calculations.
The final ranking identified inverter overvoltage shutdown/grid incompatibility, cable insulation degradation, and junction box overheating as the most maintenance-critical failures in the analyzed configuration. This ordering was technically more credible than the baseline FMEA ranking because it better captured downtime exposure, safety implications, and detectability-related service burden.
A key strength of the framework is that the criteria structure was not introduced arbitrarily but was adapted from established PV reliability and decision analysis literature and then operationalized through explicit scoring anchors and methodological clarification. The added field evidence did not serve as anecdotal decoration; it helped anchor the model in real service consequences.
From an engineering and asset-management perspective, the framework may support inspection planning, preventive maintenance scheduling, and corrective action targeting in grid-connected PV systems, while also supporting resilience-oriented maintenance management under resource-constrained operating conditions [60]. Nevertheless, the present results should be interpreted as a maintenance-prioritization demonstration rather than as generalized fleet-level failure-rate estimates. Future work should extend the model toward larger operational datasets, SCADA- and inverter-log-based validation, dynamic updating of failure alternatives, probabilistic uncertainty analysis, and broader utility-scale deployment testing.

Author Contributions

Conceptualization, P.K., K.P.-U. and S.R.; methodology, P.K., K.P.-U. and S.R.; software, P.K., K.P.-U. and S.R.; validation, P.K., K.P.-U. and S.R.; formal analysis, P.K., K.P.-U. and S.R.; investigation, P.K., K.P.-U. and S.R.; resources, P.K., K.P.-U. and S.R.; data curation, P.K., K.P.-U. and S.R.; writing—original draft preparation, P.K., K.P.-U. and S.R.; writing—review and editing, P.K., K.P.-U. and S.R.; visualization, P.K., K.P.-U. and S.R.; supervision, P.K., K.P.-U. and S.R.; project administration, P.K., K.P.-U. and S.R. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data presented in this study are available upon request from the corresponding author.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Kut, P.; Pietrucha-Urbanik, K. Most Searched Topics in the Scientific Literature on Failures in Photovoltaic Installations. Energies 2022, 15, 8108. [Google Scholar] [CrossRef]
  2. Jordan, D.C.; Silverman, T.J.; Wohlgemuth, J.H.; Kurtz, S.R.; VanSant, K.T. Photovoltaic Failure and Degradation Modes. Prog. Photovolt. Res. Appl. 2017, 25, 318–326. [Google Scholar] [CrossRef]
  3. Aghaei, M.; Fairbrother, A.; Gok, A.; Ahmad, S.; Kazim, S.; Lobato, K.; Oreski, G.; Reinders, A.; Schmitz, J.; Theelen, M.; et al. Review of Degradation and Failure Phenomena in Photovoltaic Modules. Renew. Sustain. Energy Rev. 2022, 159, 112160. [Google Scholar] [CrossRef]
  4. Al Mahdi, H.; Leahy, P.G.; Alghoul, M.; Morrison, A.P. A Review of Photovoltaic Module Failure and Degradation Mechanisms: Causes and Detection Techniques. Solar 2024, 4, 43–82. [Google Scholar] [CrossRef]
  5. Osmani, K.; Haddad, A.; Lemenand, T.; Castanier, B.; Alkhedher, M.; Ramadan, M. A Critical Review of PV Systems’ Faults with the Relevant Detection Methods. Energy Nexus 2023, 12, 100257. [Google Scholar] [CrossRef]
  6. El-Banby, G.M.; Moawad, N.M.; Abouzalm, B.A.; Abouzaid, W.F.; Ramadan, E.A. Photovoltaic System Fault Detection Techniques: A Review. Neural Comput. Appl. 2023, 35, 24829–24842. [Google Scholar] [CrossRef]
  7. Hong, Y.-Y.; Pula, R.A. Methods of Photovoltaic Fault Detection and Classification: A Review. Energy Rep. 2022, 8, 5898–5929. [Google Scholar] [CrossRef]
  8. Kull, K.; Zinn, M.; Husein, M.; Mavromatidis, G. Faults, Failures, Reliability, and Predictive Maintenance of Grid-Connected Solar Photovoltaic Systems: A Comprehensive Review. Appl. Sci. 2025, 15, 11461. [Google Scholar] [CrossRef]
  9. Kut, P.; Pietrucha-Urbanik, K.; Kurek, P. Comprehensive Analysis of Failures in Photovoltaic Installations—A Survey-Based Study. Energies 2024, 17, 5986. [Google Scholar] [CrossRef]
  10. Bosman, L.B.; Leon-Salas, W.D.; Hutzel, W.J.; Soto, E.A. PV System Predictive Maintenance: Challenges, Current Approaches, and Opportunities. Energies 2020, 13, 1398. [Google Scholar] [CrossRef]
  11. Colli, A. Failure Mode and Effect Analysis for Photovoltaic Systems. Renew. Sustain. Energy Rev. 2015, 50, 804–809. [Google Scholar] [CrossRef]
  12. Liu, H.-C.; Liu, L.; Liu, N. Risk Evaluation Approaches in Failure Mode and Effects Analysis: A Literature Review. Expert Syst. Appl. 2013, 40, 828–838. [Google Scholar] [CrossRef]
  13. Patil, R.B.; Khalkar, A.; Al-Dahidi, S.; Pimpalkar, R.S.; Bhandari, S.; Pecht, M. A Reliability and Risk Assessment of Solar Photovoltaic Panels Using a Failure Mode and Effects Analysis Approach: A Case Study. Sustainability 2024, 16, 4183. [Google Scholar] [CrossRef]
  14. Villarini, M.; Cesarotti, V.; Alfonsi, L.; Introna, V. Optimization of Photovoltaic Maintenance Plan by Means of a FMEA Approach Based on Real Data. Energy Convers. Manag. 2017, 152, 1–12. [Google Scholar] [CrossRef]
  15. Nowak, K.; Pietrucha-Urbanik, K.; Rabczak, S.; Nowak, K. Hybrid Switch with Dynamic Thyristor Control for Fast Arc Extinction in Three-Phase LV Networks. Energies 2025, 18, 6526. [Google Scholar] [CrossRef]
  16. Opricovic, S.; Tzeng, G.-H. Compromise Solution by MCDM Methods: A Comparative Analysis of VIKOR and TOPSIS. Eur. J. Oper. Res. 2004, 156, 445–455. [Google Scholar] [CrossRef]
  17. Kennedy, J.; Eberhart, R. Particle Swarm Optimization. In Proceedings of the IEEE International Conference on Neural Networks, Perth, Australia, 27 November–1 December 1995; pp. 1942–1948. [Google Scholar] [CrossRef]
  18. Shi, Y.; Eberhart, R.C. Parameter Selection in Particle Swarm Optimization. In Evolutionary Programming VII; Porto, V.W., Saravanan, N., Waagen, D., Eiben, A.E., Eds.; Springer: Berlin/Heidelberg, Germany, 1998; pp. 591–600. [Google Scholar] [CrossRef]
  19. Hwang, C.-L.; Yoon, K. Multiple Attribute Decision Making: Methods and Applications; Springer: Berlin, Germany, 1981. [Google Scholar]
  20. Saaty, T.L. The Analytic Hierarchy Process; McGraw-Hill: New York, NY, USA, 1980. [Google Scholar]
  21. Brans, J.P.; Vincke, P. A Preference Ranking Organisation Method: (The PROMETHEE Method for Multiple Criteria Decision-Making). Manag. Sci. 1985, 31, 647–656. [Google Scholar] [CrossRef]
  22. Roy, B. Classement et Choix en Présence de Points de Vue Multiples (La Méthode ELECTRE). Rev. Fr. Autom. Inform. Rech. Oper. 1968, 2, 57–75. [Google Scholar] [CrossRef]
  23. Brauers, W.K.M.; Zavadskas, E.K. The MOORA Method and Its Application to Privatization in a Transition Economy. Control Cybern. 2006, 35, 445–469. [Google Scholar]
  24. Zavadskas, E.K.; Turskis, Z.; Antucheviciene, J.; Zakarevicius, A. Optimization of Weighted Aggregated Sum Product Assessment. Elektron. Elektrotech. 2012, 122, 3–6. [Google Scholar] [CrossRef]
  25. Liu, Y.; Eckert, C.M.; Earl, C. A Review of Fuzzy AHP Methods for Decision-Making with Subjective Judgements. Expert Syst. Appl. 2020, 161, 113738. [Google Scholar] [CrossRef]
  26. Streimikis, J.; Siksnelyte-Butkiene, I. Equity-Oriented Decision-Making for Renewable Energy Investments. Energies 2026, 19, 463. [Google Scholar] [CrossRef]
  27. Aasa, O.P.; Musonda, I.; Phoya, S.; Monko, R.J. Suitability Framework for Selecting MCDA Methods in Energy Planning Problems. Next Energy 2025, 9, 100389. [Google Scholar] [CrossRef]
  28. Bharadwaj, M.L.; Sankargupta, R.; Elavarasan, R.M.; Devaraj, E.; Nandagopal, A. Multi-Criteria Decision Analysis Framework: Transitioning from Coal to Large-Scale Photovoltaics in Australia for Achieving SDG 7. Appl. Energy 2026, 405, 127208. [Google Scholar] [CrossRef]
  29. Alzahmi, W.; Ndiaye, M. A Multi-Criteria AHP Framework for Solar PV End-of-Life Management. Sustainability 2025, 17, 1828. [Google Scholar] [CrossRef]
  30. Tafula, J.E.; Justo, C.D.; Moura, P.; Mendes, J.; Soares, A. Multicriteria Decision-Making Approach for Optimum Site Selection for Off-Grid Solar Photovoltaic Microgrids in Mozambique. Energies 2023, 16, 2894. [Google Scholar] [CrossRef]
  31. Ponce, P.; Perez, C.; Fayek, A.R.; Molina, A. Solar Energy Implementation in Manufacturing Industry Using Multi-Criteria Decision-Making Fuzzy TOPSIS and S4 Framework. Energies 2022, 15, 8838. [Google Scholar] [CrossRef]
  32. AlMallahi, M.N.; El Haj Assad, M.; AlShihabi, S.; Alayi, R. Multi-Criteria Decision-Making Approach for the Selection of Cleaning Method of Solar PV Panels in United Arab Emirates Based on Sustainability Perspective. Int. J. Low-Carbon Technol. 2022, 17, 380–393. [Google Scholar] [CrossRef]
  33. Rani, P.; Mishra, A.R.; Mardani, A.; Cavallaro, F.; Streimikiene, D.; Khan, S.A.R. Pythagorean Fuzzy SWARA-VIKOR Framework for Performance Evaluation of Solar Panel Selection. Sustainability 2020, 12, 4278. [Google Scholar] [CrossRef]
  34. Lee, A.H.I.; Kang, H.-Y.; Liou, Y.-J. A Hybrid Multiple-Criteria Decision-Making Approach for Photovoltaic Solar Plant Location Selection. Sustainability 2017, 9, 184. [Google Scholar] [CrossRef]
  35. Rehman, A.U. Solar Panel Cooling System Evaluation: Visual PROMETHEE Multi-Criteria Decision-Making Approach. Sustainability 2023, 15, 12947. [Google Scholar] [CrossRef]
  36. Cavallaro, F. A Comparative Assessment of Thin-Film Photovoltaic Production Processes Using the ELECTRE III Method. Energy Policy 2010, 38, 463–474. [Google Scholar] [CrossRef]
  37. Haurant, P.; Oberti, P.; Muselli, M. Multicriteria Selection Aiding Related to Photovoltaic Plants on Farming Fields on Corsica Island: A Real Case Study Using the ELECTRE Outranking Framework. Energy Policy 2011, 39, 676–688. [Google Scholar] [CrossRef]
  38. Khorshidi, M.; Erkayman, B.; Albayrak, O.; Kilic, R.; Demir, H.I. Solar Power Plant Location Selection Using Integrated Fuzzy DEMATEL and Fuzzy MOORA Method. Int. J. Ambient. Energy 2022, 43, 7400–7409. [Google Scholar] [CrossRef]
  39. Ghenai, C.; Albawab, M.; Bettayeb, M. Sustainability Indicators for Renewable Energy Systems Using Multi-Criteria Decision-Making Model and Extended SWARA/ARAS Hybrid Method. Renew. Energy 2020, 146, 580–597. [Google Scholar] [CrossRef]
  40. Yucenur, G.N.; Maden, A. Location Selection for a Photovoltaic Agricultural with F-PIPRECIA and WASPAS Methods: A Case Study. Energy 2025, 314, 134179. [Google Scholar] [CrossRef]
  41. Abbas, M.Z.; Anjum, R.; Hussain, A.; Ahmad, M.; Haleemzai, I. An Integrated Neutrosophic Z-Numbers Based CRITIC-EDAS Decision Model for Smart Solar Panel Evaluation in Sustainable Energy Planning. Sci. Rep. 2025, 15, 38180. [Google Scholar] [CrossRef]
  42. Gribiss, H.; Aghelinejad, M.M.; Yalaoui, F. Configuration Selection for Renewable Energy Community Using MCDM Methods. Energies 2023, 16, 2632. [Google Scholar] [CrossRef]
  43. Jacyna, M. Decision Support in Engineering Practice: Methods, Algorithms, Examples; Wydawnictwo Naukowe PWN: Warsaw, Poland, 2022. [Google Scholar] [CrossRef]
  44. Nowak, M. Decision Support in Project Planning; Difin: Warsaw, Poland, 2014. [Google Scholar]
  45. Zavadskas, E.K.; Turskis, Z. A New Additive Ratio Assessment (ARAS) Method in Multicriteria Decision-Making. Technol. Econ. Dev. Econ. 2010, 16, 159–172. [Google Scholar] [CrossRef]
  46. Keshavarz Ghorabaee, M.; Zavadskas, E.K.; Olfat, L.; Turskis, Z. Multi-Criteria Inventory Classification Using a New Method of Evaluation Based on Distance from Average Solution (EDAS). Informatica 2015, 26, 435–451. [Google Scholar] [CrossRef]
  47. Stević, Ž.; Pamučar, D.; Puška, A.; Chatterjee, P. Sustainable Supplier Selection in Healthcare Industries Using a New MCDM Method: Measurement of Alternatives and Ranking according to COmpromise Solution (MARCOS). Comput. Ind. Eng. 2020, 140, 106231. [Google Scholar] [CrossRef]
  48. Sathish Kumar, A.; Naveen, S.; Vijayakumar, R.; Suresh, V.; Asary, A.R.; Madhu, S.; Palani, K. An Intelligent Fuzzy-Particle Swarm Optimization Supervisory-Based Control of Robot Manipulator for Industrial Welding Applications. Sci. Rep. 2023, 13, 8253. [Google Scholar] [CrossRef]
  49. Li, J.; Zhang, Y.; Fang, H.; Fang, S. Risk Evaluation of Photovoltaic Power Systems: An Improved Failure Mode and Effect Analysis under Uncertainty. J. Clean. Prod. 2023, 414, 137620. [Google Scholar] [CrossRef]
  50. Baklouti, A.; Mifdal, L.; Dellagi, S.; Chelbi, A. An Optimal Preventive Maintenance Policy for a Solar Photovoltaic System. Sustainability 2020, 12, 4266. [Google Scholar] [CrossRef]
  51. Di Lorenzo, G.; Balsamo, G.; Mazzurco, A.; Madonia, A.; Moser, D. Prognostic Methods for Photovoltaic Systems: A Review. Energies 2022, 15, 6413. [Google Scholar] [CrossRef]
  52. Sonawane, P.R.; Bhandari, S.; Patil, R.B.; Al-Dahidi, S. Reliability and Criticality Analysis of a Large-Scale Solar Photovoltaic System Using Fault Tree Analysis Approach. Sustainability 2023, 15, 4609. [Google Scholar] [CrossRef]
  53. Eberhart, R.C.; Shi, Y. Comparing Inertia Weights and Constriction Factors in Particle Swarm Optimization. In Proceedings of the 2000 Congress on Evolutionary Computation, La Jolla, CA, USA, 16–19 July 2000; pp. 84–88. [Google Scholar] [CrossRef]
  54. Tran, M.Q.; Sousa, H.S.; Matos, J.; Fernandes, S.; Nguyen, Q.T.; Dang, S.N. Finite Element Model Updating for Composite Plate Structures Using Particle Swarm Optimization Algorithm. Appl. Sci. 2023, 13, 7719. [Google Scholar] [CrossRef]
  55. Elsheikh, A.H.; Egiza, M.; Diab, M.R.; Nassar, M.; Alhosary, M.; Nassar, S.; Rozza, M.; Faisal, N.; Essa, F.A. Modelling and Optimization of an Inverted Pyramid Solar Still Using ANFIS-PSO: Predictive Analysis of Water Production, Energy, and Exergy Efficiency. Sep. Purif. Technol. 2025, 377, 134492. [Google Scholar] [CrossRef]
  56. Goudelis, G.; Lazaridis, P.; Dhimish, M. A Review of Models for Photovoltaic Crack and Hotspot Failure Mechanisms. Energies 2022, 15, 4303. [Google Scholar] [CrossRef]
  57. Wang, Y.; Itako, K.; Kudoh, T.; Koh, K.; Ge, Q. Voltage-Based Hot-Spot Detection Method for Photovoltaic String Using a Projector. Energies 2017, 10, 230. [Google Scholar] [CrossRef]
  58. Gholami, A.; Melenka, G.W. Studying the Geometrical Models of Tubular Braided Composite Using Micro Computed Tomography and Particle Swarm Optimization. Compos. Part B 2023, 260, 110758. [Google Scholar] [CrossRef]
  59. Najjar, I.; Sadoun, A.; Alam, M.N.; Fathy, A. Prediction of Wear Rates of Al-TiO2 Nanocomposites Using Artificial Neural Network Modified with Particle Swarm Optimization Algorithm. Mater. Today Commun. 2023, 35, 105743. [Google Scholar] [CrossRef]
  60. Streimikis, J. Circular Management Practices and Organizational Resilience in Resource-Constrained Environments: A Conceptual Framework. Sustainability 2026, 18, 4501. [Google Scholar] [CrossRef]
Figure 1. Integrated methodological framework of the proposed PSO–FMEA–VIKOR approach for maintenance prioritization in photovoltaic installations.
Figure 1. Integrated methodological framework of the proposed PSO–FMEA–VIKOR approach for maintenance prioritization in photovoltaic installations.
Energies 19 02622 g001
Figure 2. Field-documented PV failure cases used to support the engineering interpretation of the ranking: (a) mechanically damaged PV module; (b) thermally damaged DC automatic switch terminal; (c) PV installation damaged by arc fault; and (d) electrical connector damaged by arc fault. Source: authors’ field archive.
Figure 2. Field-documented PV failure cases used to support the engineering interpretation of the ranking: (a) mechanically damaged PV module; (b) thermally damaged DC automatic switch terminal; (c) PV installation damaged by arc fault; and (d) electrical connector damaged by arc fault. Source: authors’ field archive.
Energies 19 02622 g002
Table 1. General 10-point scoring anchors used for the semi-quantitative evaluation of PV failure modes.
Table 1. General 10-point scoring anchors used for the semi-quantitative evaluation of PV failure modes.
ScoreMaintenance ConcernOperational InterpretationScoring Implication
1NegligibleNo measurable production, safety, cost, downtime, or detectability concern.Use only when the failure mode has no practical maintenance relevance under normal operation.
2Very lowVery small local effect; event is rare and easily identified.Use for minor issues requiring only a quick check or immediate restart.
3LowSmall production or service effect; occasional event detected during routine inspection.Use for faults with limited operational relevance and low service burden.
4Low-to-moderateMinor but noticeable effect; repeatable but not highly disruptive.Use when a fault may require short service action, but does not dominate maintenance planning.
5ModerateNoticeable production loss, moderate occurrence, targeted diagnostics, or moderate service delay.Use for faults with clear maintenance relevance but limited escalation potential.
6Moderate-to-highClear production or downtime effect and technician verification is usually required.Use when the fault begins to affect inspection scheduling or corrective-maintenance planning.
7HighMajor production loss, recurrent occurrence, difficult detection, high cost, or multi-day downtime.Use for failure modes requiring priority maintenance attention.
8Very highLarge operational disruption, replacement need, extended downtime, or high safety/exposure relevance.Use when several maintenance-critical consequences occur simultaneously.
9CriticalMajor system-output interruption, hidden escalation risk, very high cost, or long service cycle.Use for failures that should be prioritized even if their occurrence is moderate.
10ExtremeSevere system-level interruption or severe electrical, thermal, fire, or environmental-risk potential.Use only for the most critical failure modes with urgent maintenance implications.
Table 2. Role and interpretation of the two semi-empirical evidence sources used in the study.
Table 2. Role and interpretation of the two semi-empirical evidence sources used in the study.
Evidence SourceUnit of ObservationSample SizeData Type and ConfirmationMain Indicators DerivedRole in This Study
Operational datasetInstallation/user50 PV installations/usersRetrospective installation/user-level operational evidence from residential and small commercial grid-connected PV systems in Poland; user-reported information plus selected repair/warranty indicationsShare of cases with failure, inverter-disconnection patterns, inverter-related technical failures, and repair duration patternsContextual operational evidence; plausibility support for occurrence, downtime, and serviceability interpretation
Service log databaseService intervention1000 documented interventionsRetrospective anonymized service log evidence from the same regional PV service context in south-eastern Poland; technician notes, repair/replacement categories, cost, and service duration records, photographs where availablePer-1000 indicators for selected service events, typical direct costs, and typical downtime/service durationMain service-practice evidence for relative intervention frequency, cost, downtime, safety, and detectability interpretation
Table 3. Comparative positioning of selected MCDA methods for maintenance priority analysis in photovoltaic systems.
Table 3. Comparative positioning of selected MCDA methods for maintenance priority analysis in photovoltaic systems.
MethodDecision LogicMain StrengthsMain LimitationsTypical Role in PV MaintenanceReferences and Methodological Relevance
AHPHierarchical structuring and pairwise comparisons.High interpretability; effective for structuring criteria and expert judgment.Large comparison burden when alternatives increase; subject to consistency issues.Useful for preliminary weighting and structured criteria design.Saaty [20]: foundational reference for the Analytic Hierarchy Process and pairwise comparison logic. Liu et al. [25]: fuzzy/AHP-related decision making background for subjective judgments. Aasa et al. [27]: recent comparative MCDA application in energy planning problems. Alzahmi and Ndiaye [29]: AHP-based prioritization in solar PV end-of-life management. Tafula et al. [30]: AHP/MCDA application in off-grid solar PV microgrid site selection. Jacyna [43]: general engineering decision support background relevant to structured criteria weighting.
TOPSISDistance from positive and negative ideal solutions.Simple computation; intuitive ranking; widely used in energy studies.Sensitive to normalization and compensation effects; weaker emphasis on worst criterion dominance.Appropriate when proximity to the ideal solution is the main decision logic.Hwang and Yoon [19]: foundational reference for TOPSIS based on distance from positive and negative ideal solutions. Opricovic and Tzeng [16]: comparative MCDA reference linking TOPSIS and VIKOR decision logic. Aasa et al. [27]: recent MCDA application in energy-planning problems. Bharadwaj et al. [28]: PV/energy-related decision analysis using modern MCDA approaches. Ponce et al. [31]: fuzzy TOPSIS-based solar energy implementation assessment. AlMallahi et al. [32]: MCDA application in solar PV panel cleaning method selection.
VIKORCompromise ranking using utility and regret measures.Balances group utility and individual regret; suitable for conflicting criteria.Requires selection of the v parameter; less intuitive than simple additive models.Well aligned with maintenance decisions where downtime and safety can dominate.Opricovic and Tzeng [16]: key reference for VIKOR compromise-ranking logic and comparison with TOPSIS. Aasa et al. [27]: recent MCDA application relevant to energy systems. Bharadwaj et al. [28]: energy/PV-oriented MCDA assessment supporting compromise-based ranking. Rani et al. [33]: VIKOR-related compromise decision making for solar panel selection. Lee et al. [34]: VIKOR-type ranking in photovoltaic solar plant location selection. Jacyna [43]: engineering decision support background supporting compromise ranking in technical prioritization.
PROMETHEE IIOutranking based on pairwise preference functions.Handles non-linear preferences; strong discrimination capability.Requires threshold definition and preference-function tuning.Useful when partial preference structures must be modeled explicitly.Brans and Vincke [21]: foundational reference for the PROMETHEE outranking family and pairwise preference functions. Aasa et al. [27]: energy planning MCDA application including comparative ranking methods. Rehman [35]: PROMETHEE-based evaluation of solar panel cooling systems. Jacyna [43]: general methodological background for engineering decision support. Nowak [44]: decision support reference relevant to planning and project-oriented prioritization.
ELECTREOutranking through concordance and discordance relations.Suitable for non-compensatory problems and veto-type logic.Can be less transparent to non-specialists; partial incomparability may appear.Relevant when unacceptable weaknesses should not be fully compensated.Roy [22]: foundational reference for the ELECTRE outranking approach based on concordance and discordance. Aasa et al. [27]: recent MCDA work relevant to energy decision problems. Cavallaro [36]: ELECTRE-based assessment of thin-film photovoltaic production processes. Haurant et al. [37]: ELECTRE-based photovoltaic plant selection in a real energy-planning case. Jacyna [43]: engineering decision support context for non-compensatory decision problems. Nowak [44]: decision support background for planning and evaluation under multiple criteria.
MOORARatio-based normalization and ranking.Computationally efficient; easy to implement.Less expressive for complex compromise trade-offs.Useful for quick screening and robustness checks.Brauers and Zavadskas [23]: foundational reference for the MOORA method and ratio-based multi-objective optimization. Aasa et al. [27]: recent MCDA application in energyplanning assessment. Bharadwaj et al. [28]: PV/energy-oriented decision analysis using comparative MCDA procedures. Khorshidi et al. [38]: fuzzy MOORA application in solar power plant location selection. Jacyna [43]: engineering decision support reference relevant to computational ranking and criteria aggregation.
ARASAdditive utility based on normalized performance ratios.Transparent and easy to reproduce; useful for beneficial/cost criteria.More compensatory than outranking methods.Useful for straightforward utility-based ranking.Zavadskas and Turskis [45]: foundational reference for the ARAS method and additive utility assessment. Aasa et al. [27]: recent MCDA application in energy decision making. Bharadwaj et al. [28]: PV/energy system MCDA application supporting comparative ranking. Ghenai et al. [39]: renewable energy decision assessment using SWARA/ARAS-type MCDA logic. Jacyna [43]: general engineering decision support background.
WASPASCombined weighted-sum and weighted-product logic.Good discrimination and hybrid aggregation logic.Depends strongly on weight quality and normalization.Useful as a hybrid additive-multiplicative comparator.Zavadskas et al. [24]: foundational reference for the WASPAS method combining weighted-sum and weighted product logic. Aasa et al. [27]: recent MCDA-based assessment in energy planning contexts. Bharadwaj et al. [28]: PV/energy-related decision analysis using modern MCDA ranking procedures. Yucenur and Maden [40]: WASPAS-related photovoltaic location- election application. Jacyna [43]: engineering decision support basis for hybrid aggregation methods.
EDASDistance from the average solution.Stable ranking under average-solution logic; simple interpretation.Results depend on data dispersion and the reference average.Useful for testing rank sensitivity with a moderate computational burden.Keshavarz Ghorabaee et al. [46]: foundational reference for EDAS based on distance from the average solution. Aasa et al. [27]: recent MCDA application in energy planning evaluation. Bharadwaj et al. [28]: energy/PV decision analysis using comparative MCDA methods. Abbas et al. [41]: EDAS-related smart solar panel evaluation in sustainable energy planning. Gribiss et al. [42]: recent MCDA application relevant to renewable energy community configuration. Jacyna [43]: engineering decision support background.
MARCOSCompromise-oriented utility relative to ideal and anti-ideal solutions.High discrimination; increasingly used in recent engineering applications.Less established in PV maintenance than AHP/TOPSIS/VIKOR.Useful as an additional robustness-oriented ranking method.Stević et al. [47]: foundational reference for the MARCOS method based on compromise utility relative to ideal and anti-ideal alternatives. Aasa et al. [27]: recent MCDA application relevant to energy systems. Bharadwaj et al. [28]: PV/energy-system decision analysis using contemporary MCDA approaches. Jacyna [43]: general engineering decision support reference supporting comparative ranking.
COPRASProportional utility assessment with benefit/cost separation.Clear utility meaning; convenient for comparative evaluation.Moderately compensatory; less expressive for veto-type effects.Useful for proportional comparison of alternatives under mixed criteria.Aasa et al. [27]: recent MCDA application in energy decision making, including proportional and comparative assessment logic. Bharadwaj et al. [28]: energy/PV-oriented MCDA application relevant to technology and maintenance prioritization. Tafula et al. [30]: renewable energy decision analysis using AHP/COPRAS or related MCDA methods. Jacyna [43]: engineering decision support background. Nowak [44]: decision support reference relevant to planning and project prioritization.
Fuzzy AHP/Fuzzy TOPSISFuzzy representation of expert judgment and ranking uncertainty.Captures linguistic ambiguity and subjective uncertainty.Higher modeling complexity and sensitivity to membership design.Useful when expert scores are imprecise rather than deterministic.Opricovic and Tzeng [16]: comparative MCDA reference supporting the methodological positioning of TOPSIS and compromise ranking. Liu et al. [25]: fuzzy/AHP-related decision making with subjective judgments. Aasa et al. [27]: recent energy MCDA application including uncertainty-aware decision methods. Ponce et al. [31]: fuzzy TOPSIS-based solar energy implementation assessment. AlMallahi et al. [32]: MCDA application in renewable-energy technology evaluation. Sathish Kumar et al. [48]: fuzzy-PSO optimization example demonstrating integration of fuzzy logic and swarm-based optimization in technical systems.
Table 4. Decision matrix for the evaluated failure modes.
Table 4. Decision matrix for the evaluated failure modes.
Failure ModeC1C2C3C4C5C6C7
A17865468
A28676876
A38587986
A47686465
A59438689
A66976357
A79757595
A87567575
Table 5. Classical FMEA scoring matrix and RPN-based prioritization of the analyzed PV failure modes.
Table 5. Classical FMEA scoring matrix and RPN-based prioritization of the analyzed PV failure modes.
ModeFailure Mode DescriptionSODRPNRPN Rank
A1Partial shading and hotspot formation7863362
A2Junction box overheating/failure8673362
A3Cable insulation degradation8583205
A4Cell microcracking and interconnection failure7683362
A5Glass breakage due to hail impact9431088
A6Aging-related power degradation6973781
A7Inverter overvoltage shutdown/grid incompatibility9753156
A8Tracker/control automatics failure7562107
Note: S—severity, O—occurrence, D—detection difficulty, RPN—risk priority number. Rank 1 denotes the highest priority according to the classical FMEA approach. Equal RPN values were assigned the same rank.
Table 6. PSO-optimized criteria weights used in the VIKOR-based prioritization procedure.
Table 6. PSO-optimized criteria weights used in the VIKOR-based prioritization procedure.
CriterionCriterion DescriptionWeight Share (%)Importance Rank
C1Severity of energy loss21.41
C2Occurrence frequency17.62
C5Safety impact15.23
C3Detectability difficulty14.14
C6Downtime effect13.25
C4Maintenance cost10.96
C7Environmental exposure sensitivity7.67
Note: The criteria weights were obtained using the PSO procedure and subsequently used as input weights in the VIKOR ranking.
Table 7. Robustness comparison of alternative weighting scenarios for the leading maintenance priorities.
Table 7. Robustness comparison of alternative weighting scenarios for the leading maintenance priorities.
ScenarioWeighting ApproachTop 3 RankingComment
S1Equal weightsA7–A3–A2Robustness benchmark; the same leading cluster remained dominant.
S2Literature/expert weightsA7–A2–A3Interpretability benchmark; only the order of A2 and A3 changed.
S3PSO weightsA7–A3–A2Final ranking; improved discrimination among close alternatives.
Note: The benchmark scenarios used the same decision matrix and criticality-oriented VIKOR procedure as the final PSO-based calculation.
Table 8. Final VIKOR compromise ranking of the analyzed PV failure modes.
Table 8. Final VIKOR compromise ranking of the analyzed PV failure modes.
ModeFailure-Mode DescriptionSRQFinal Rank
A7Inverter overvoltage shutdown/grid incompatibility0.4620.2140.0001
A3Cable insulation degradation0.5030.1520.1812
A2Junction box overheating/failure0.5280.1760.2633
A6Aging-related power degradation0.5710.1760.3894
A1Partial shading and hotspot formation0.5940.1710.4585
A8Tracker/control automatics failure0.6360.1320.5796
A5Glass breakage due to hail impact0.6480.1090.6417
A4Cell microcracking and interconnection failure0.6670.1410.7188
Note: S denotes the group utility measure, R denotes the individual regret measure, and Q denotes the VIKOR compromise index.
Table 9. Comparison between the classical FMEA ranking and the PSO-VIKOR ranking.
Table 9. Comparison between the classical FMEA ranking and the PSO-VIKOR ranking.
ModeFailure-Mode DescriptionRPN RankVIKOR RankRank Shift
A7Inverter overvoltage shutdown/grid incompatibility61+5
A3Cable insulation degradation52+3
A2Junction box overheating/failure23−1
A6Aging-related power degradation14−3
A1Partial shading and hotspot formation25−3
A8Tracker/control automatics failure76+1
A5Glass breakage due to hail impact87+1
A4Cell microcracking and interconnection failure28−6
Table 10. Sensitivity of the VIKOR ranking to different values of the strategy parameter v.
Table 10. Sensitivity of the VIKOR ranking to different values of the strategy parameter v.
ModeFailure-Mode Descriptionv = 0.25v = 0.50v = 0.75Rank RangeStability Assessment
A7Inverter overvoltage shutdown/grid incompatibility1110Stable
A3Cable insulation degradation2220Stable
A2Junction box overheating/failure3341Slight change
A6Aging-related power degradation5432Moderate change
A1Partial shading and hotspot formation4551Slight change
A8Tracker/control automatics failure6660Stable
A5Glass breakage due to hail impact7770Stable
A4Cell microcracking and interconnection failure8880Stable
Note: The rank range was calculated as the difference between the highest and lowest position obtained across the tested values of v. A lower range indicates greater ranking stability.
Table 11. Aggregated installation-level and service log evidence used to support the maintenance-oriented interpretation of the decision model.
Table 11. Aggregated installation-level and service log evidence used to support the maintenance-oriented interpretation of the decision model.
Evidence CategoryIndicative Observed FrequencyTypical Direct Service Cost [PLN]Typical Downtime/Service InterruptionMain Criteria Informed
Grid overvoltage-related inverter disconnectionrecurrent inverter disconnection during grid voltage rise in 60% of analyzed casesNot repair-centered; production loss dominantRepeated intermittent shutdownsC1, C2, C6
Inverter hardware failure5 per 1000 documented service cases920Approx. 15 d total service cycleC4, C6
Logger disconnection after router/network changes350 per 1000 documented service cases320Approx. 2 dC2, C4, C6
Blown DC fuse6 per 1000 documented service cases200–500Several hours to 1 dC2, C4, C6
Melted MC4 connector2 per 1000 documented service cases500–1000Several hours; service lead 24–48 hC4, C5, C6
Mechanical module damage3 per 1000 documented service cases2000–3000Several hours to 1 dC1, C4, C6
DC automatic switch failureSingle detailed service case800Approx. 48 hC4, C6
Hot-spot-related module claimClaim-oriented event1500–2300Several weeks to about 1 monthC1, C5, C6
Arc-fault-related DC-side damageLow-frequency, high-consequence event1500–3000Several hours to 3 dC5, C6
Note: “Per 1000 service cases” denotes the number of occurrences of a given maintenance-event category in the independent database of 1000 documented PV service interventions. These indicators should not be interpreted as fleet-level failure rates per installation; they describe the distribution of selected service-intervention categories within the service log database.
Table 12. Normalized service-profile indicators used for empirical plausibility checking of the maintenance model.
Table 12. Normalized service-profile indicators used for empirical plausibility checking of the maintenance model.
Service Event TypeIndicative Occurrence RateTypical Direct Cost [PLN]Typical Downtime [d]Normalized OccurrenceNormalized CostNormalized Downtime
Inverter hardware failure0.00592015.00.0140.3681.000
Logger disconnection0.3503202.01.0000.1280.133
Blown DC fuse0.0063500.50.0170.1400.033
Melted MC4 connector0.0027501.00.0060.3000.067
Mechanical module damage0.00325001.00.0091.0000.067
Table 13. FMEA-oriented interpretation of selected field-documented PV failure cases.
Table 13. FMEA-oriented interpretation of selected field-documented PV failure cases.
Field-Documented CaseMain Operational ImplicationMain FMEA-Relevant Dimension
Mechanically damaged PV moduleReduced output, insulation loss, and replacement needSeverity; Cost
Burnt DC automatic switch terminalDelayed restart, outage, service interruptionDowntime; Detectability
Arc-fault damage to installation wiringForced shutdown, fire hazard, corrective replacementSeverity; Safety; Downtime
Damaged electrical connector after an arc faultContact degradation, heating, and connection unreliabilitySafety; Detectability
Table 14. Cross-method comparison of leading maintenance priorities obtained from the same decision matrix.
Table 14. Cross-method comparison of leading maintenance priorities obtained from the same decision matrix.
MethodRank 1Rank 2Rank 3Main Interpretation
FMEAA6A1/A2/A4Frequency/RPN-driven baseline; second position was tied.
VIKORA7A3A2Criticality/compromise-driven final ranking.
TOPSISA3A2A7Balanced-profile preference under distance-based logic.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Kut, P.; Pietrucha-Urbanik, K.; Rabczak, S. Maintenance Prioritization in Photovoltaic Installations Using a Hybrid Particle Swarm Optimization–Failure Mode and Effects Analysis–VIKOR Decision Framework. Energies 2026, 19, 2622. https://doi.org/10.3390/en19112622

AMA Style

Kut P, Pietrucha-Urbanik K, Rabczak S. Maintenance Prioritization in Photovoltaic Installations Using a Hybrid Particle Swarm Optimization–Failure Mode and Effects Analysis–VIKOR Decision Framework. Energies. 2026; 19(11):2622. https://doi.org/10.3390/en19112622

Chicago/Turabian Style

Kut, Paweł, Katarzyna Pietrucha-Urbanik, and Sławomir Rabczak. 2026. "Maintenance Prioritization in Photovoltaic Installations Using a Hybrid Particle Swarm Optimization–Failure Mode and Effects Analysis–VIKOR Decision Framework" Energies 19, no. 11: 2622. https://doi.org/10.3390/en19112622

APA Style

Kut, P., Pietrucha-Urbanik, K., & Rabczak, S. (2026). Maintenance Prioritization in Photovoltaic Installations Using a Hybrid Particle Swarm Optimization–Failure Mode and Effects Analysis–VIKOR Decision Framework. Energies, 19(11), 2622. https://doi.org/10.3390/en19112622

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Article metric data becomes available approximately 24 hours after publication online.
Back to TopTop