Next Article in Journal
Conditions Driving Eco-Innovation in a Catching-Up Country—ICT vs. Industry in Poland
Previous Article in Journal
The Effect of Replacing Si-MOSFETs with WBG Transistors on the Control Loop of Voltage Source Inverters
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Reconfiguration of Electrical Distribution System Using Heuristic Methods with Geopositioning Constraints

1
Department of Posgraduate in Electricity, Universidad Politécnica Salesiana, Quito 170525, Ecuador
2
Department of Posgraduate ICT for Education, Smart Grid Research Group, Universidad Politécnica Salesiana, Quito 170525, Ecuador
*
Author to whom correspondence should be addressed.
Current address: Postgraduate Department, Girón Campus, Av. 12 de Octubre N 23-52, Quito 170525, Ecuador.
Energies 2022, 15(15), 5317; https://doi.org/10.3390/en15155317
Submission received: 29 June 2022 / Revised: 17 July 2022 / Accepted: 20 July 2022 / Published: 22 July 2022

Abstract

:
Natural disasters have great destructive power and can potentially wipe out great lengths of power lines. A resilient grid can recover from adverse conditions and restore service quickly. Therefore, the present work proposes a novel methodology to reconfigure power grids through graph theory after an extreme event. The least-cost solution through a minimum spanning tree (MST) with a radial topology that connects all grid users is identified. To this end, the authors have developed an iterative minimum-path heuristic algorithm. The optimal location of transformers and maintenance holes in the grid is obtained with the modified Prim algorithm, and the Greedy algorithm complements the process. The span distance and capacity restrictions define the transformer’s number, where larger spans and capacities reduce the number of components in the grid. The performance of the procedure has been tested in the urban zone Quito Tenis of Ecuador, and the algorithm proved to be scalable. Grid reconfiguration is pushed through a powerful tool to model distribution systems such as CYMDIST, where the voltage drops were minor than 3.5%.

Graphical Abstract

1. Introduction

The main aspects of this work are related to the reconfiguration of an electrical network that is required after an extreme event and supported by graph theory to achieve resilience. The proposed heuristic model has the potential to be applied to local utilities considering transformers and the optimal location of the maintenance hole through Prim and Greedy algorithms. Finally, the minimum spanning tree allows reconfiguring the power grid with minimum cost.
The electric power industry has helped the economic progress of the society and the country through the energy matrix [1]; therefore, electrical systems play a transcendental role in all productive activities. Power systems must be reliable to reduce the number of outages per year. They must also be resilient and recover from adverse conditions. Consequently, utilities are exploring alternatives to strengthen their electrical infrastructure [2,3]. Recently, several techniques have been developed to improve electrical distribution networks; due to resilience in the grid, fewer problems related to power quality and grid security arise in the power supply.
Power outages due to extreme conditions have been considered a significant concern by [4,5]. Natural disasters, such as earthquakes, can destroy a long stretch of the power grid. In addition, structural damage takes longer to recover from, resulting in temporary long-term failures; furthermore, resilience in power grids is essential to cope with these problems and recover service. Resilience in scientific literature has been defined as the ability of a network to withstand and reduce a disruptive event and recover the lost load supply in a short time [6]. The resilience of power systems has reduced economic losses from load shedding due to extreme events [7].
Power distribution networks can consist of overhead power lines or subway cable systems. Overhead networks have a lower degree of resilience. In contrast, cables in subway networks are more protected, and the electrical grid is resilient. Resilience criteria allow anticipating, mitigating, and recovering from adverse conditions as expressed in the following [8]. Natural catastrophes have a low probability and high impact; therefore, planning models must anticipate and design robust power grids. Damage to service infrastructure following an extreme event often results in islands. Under these conditions, mobile power generation units are often temporarily displaced until service is restored. When the grid infrastructure is unrecoverable, reconfiguration through new connection points is necessary.
A better-structured topology is easier to recover after a contingency. Grid reconfiguration improves the reliability, voltage profile, and electrical losses of electrical systems [2,9,10,11,12]. The reconfiguration optimizes the topological structure of the network without changing its radial condition [13,14,15]. In Lei et al. [6], radial constraints for power grids have been extensively investigated. A radial system has advantages such as simplifying the protection system and reducing short-circuit current. Minimum Spanning Tree (MST) concepts have been used to ensure network planning with radial topology and minimum voltage drop. Therefore, reconfiguration methods are an effective and attractive strategy for utilities.
An optimal reconfiguration is obtained through the minimum spanning tree and graph theory, where the structure of the power grid is graphically represented by vertices and links [16,17,18]. Substations, distribution transformers, and loads represent vertices; on the other hand, subway cables and overhead lines represent links [19]. The MST searches for the shortest path in a set of nodes, resulting in a subgraph with the minimum weight. Reconfiguration is related to routing and optimization problems and is classified as NP-complete. These problems are combinatorial, use many variables and considerable complexity, and lack a globally optimal solution [20,21]. A nondeterministic Turing machine solves the NP-complete problem is computationally feasible time with an approximate solution [22,23,24].
In consequence of the above, the present work proposes a heuristic model to solve the combinatorial problem from a programming platform such as Matlab. The model is tested to a georeferenced scenario. The transformers’ location with the topology of the medium and low voltage networks is presented as a solution. In addition, the reconfiguration results are exported and evaluated through a powerful tool for modeling electrical distribution systems, such as CYMDIST. A graphical summary of this work is shown in Figure 1.
The remainder of this paper is organized as follows: Section 2 presents a bibliographic review of related work. Section 3 presents the problem formulation and the methodology to solve it. Section 4 contains the results’ analysis and the proposed model’s validation. Finally, Section 5 concludes the paper.

2. Related Works

Several works have been concerned with the steady-state voltage analysis of the power grid with the penetration of renewable energies in which optimization models have been proposed on ideal models for 9 or 118 busbars. The impact has been mitigated through a relaxed model that evaluates an instance using linear programming [25]. Additionally, we present works that show the computational complexity when determining the size and location of the distributed generation or reconfiguration of the electric grid, but due to the search space, the model is relaxed to apply linear programming. The relaxation considers eliminating non-radial combinations in scenarios of 33 and 69 busbars, with a variable power factor. The method evaluates local optima using heuristics [26]. Combinatorial problems known as NP-Complete involve using heuristics to achieve local optima; the application is evidenced in scenarios of 33.85 and 295 bars, respectively, demonstrating the algorithm’s flexibility [27]. The variation of energy demand is considered in publications that evaluate flexibly in scenarios with distributed generation; however, the stochastic demand does not consider gradual population growth, a situation that includes an essential variation in achieving an efficient, reliable, and resilient network [28].
In this context, the present work evidences a methodological change since it does not use ideal scenarios based on classical IEEE models and is relaxed to be solved with linear programming. In contrast, the present work proposes scalability and growth of the user population and its respective demand for the electric resource. In this way, it is not only flexibility that is denoted by the variables evaluated, but scalability is also included in the scenario; a situation that transforms the study into an accurate and current study to solve problems of the electricity sector in the sizing and deployment of an electrical distribution network on a geo-referenced scenario as an innovation of other research related to the subject.
Several methods can be applied when an optimization problem is evaluated through heuristics; however, resolution time, geo-referenced scenarios, finite time to achieve local optima, flexibility, and scalability are the variables to determine the novelty and innovation of the method.
Distribution network reconfiguration (DNR) and network resilience have been considered excellent alternatives to improve the energy system’s performance. These subjects are widely discussed in the literature, and several methods have been proposed to solve the problem. The most critical related works are listed as follows.
In [29,30], the authors propose a witty decision tool to design and plan power distribution networks based on heuristics data. The model considers the capacity, coverage of the transformers, and the voltage drop across conductors. In addition, the transformers’ position and the conductors’ routing are located on a geo-referenced map.
In [31], the authors present a methodology to design representative distribution networks geo-referenced on actual data provided by 79 big European distribution system operators. As a result, the models realistically mimic sections of the EU system. In addition, nine representative distribution networks have been designed through the proposed methodology.
In [32], the author describes a scheduling algorithm to reduce the network feeder based on a minimum spanning tree. Furthermore, the proposed algorithm has been used as an interface for planning feeders from the GIS database and exporting them to the quasi-static analysis tool (CYMDIST). The network reconfiguration through the minimum spanning tree based on the Kruskal algorithm was proposed in [33,34].
The cable route optimization through spatial data is promising. In [35], the author describes an improved method to minimize the investment costs of electrical network construction projects. The algorithm uses a geo-referenced scheme generated by the free and open data source OpenStreetMap. The graphs obtained are used to solve the minimum Steiner tree problem.
In [36], the authors present a novel algorithm to design power distribution systems based on a minimum spanning tree. The Slime Mold inspires the model. The methodology shows lower costs for urban and suburban electrical networks. In addition, the model can optimize extensive electrical networks under a single simulation in reasonable computation time.
In [37], the author proposes a novel methodology to evaluate and enable a resilient power distribution system through graph theory. As a result, the simulation shows that network resilience is improved by increasing the number of switches; however, there are more points of failure. Furthermore, the paper presents metrics to quantify resiliency based o network structure parameters.
In [38], the authors propose a stochastic model based on proactive operational actions to improve the resilience power distribution system. In this, the power system is optimally reconfigured through the model proposed by taking advantage of available resources. The DNR and crew prepositioning are the actions considered against predictable natural hazards, and the algorithm is mathematically formulated in mixed-integer linear programming.
In [39], the authors present a methodology to restore distribution network service based on graph theory. The modified Prim’s algorithm is used to obtain the minimum spanning tree. In addition, the operation costs and switching equipment state are considered. On the other hand, in [40] research, the authors present the Prim and Greedy algorithms as restoration strategies for the power system. The power grid is represented as a weighted graph.
Table 1 summarizes the related works selected for this research. It is essential to highlight the evolution of work on a combinatorial problem, that is flexible by configurable variables and scalable to customer demand and, thus, able to achieve the reconfiguration of the electrical distribution network that contributes to the concept of a smart grid.

3. Problem Formulation

Electrical network design has many parameters to consider, such as the capacity of transformers, conductors, cables, and the geo-referenced location of each element, among other things. The sizing of equipment is usually done based on local regulations. In addition, technical requirements such as voltage drop are needed to ensure quality service for users. For network reconfiguration, the parameters to be considered are similar. Extreme events often cause severe disruption to the power system, and sometimes the original network topology cannot be reconstructed by utilities. Furthermore, if the planning model considers an underground network with higher resilience, the location of the maintenance hole is also necessary.
The coordination of medium- and low-voltage network protection is simplified. Active sites are selected from candidate sites considering an optimal location problem, where these should cover all users and are located as close to each other as possible. In these conditions, the voltage drop along conductors and cables is minimal. The reconfiguration of the distribution systems must adopt a radial topology. In addition, there is a reduction in short-circuit current, mitigating the effects on the system after a fault. Several heuristic methods have been used in the literature for routing electrical networks. Minimum spanning tree algorithms allow radial topology to be obtained. In addition, the cost associated with the total routing distance is also minimal.
Planning models use projections of distributed demand in the area to sustain the electricity projects over time. High population growth rates have forced the expansion of the electricity system. According to figures published by the UN, an increase of 84 million people annually worldwide. It is difficult to predict the number of disconnected users after an extreme event, and the number increase with the network expansion is probable over time. Therefore, the proposed planning models must be scalable. Figure 2 presents a scheme that summarizes the system model to solve the network reconfiguration.

3.1. Proposed Strategy and Methodology

The strategy for solving the reconfiguration and resilience problem based on graph theory has been presented in Figure 3. The methodology employed is summarized in 4 stages. First, the osm file of the study area is obtained from the free OpenStreetMap database. Street intersections are selected to represent the candidate points for the location of transformers and maintenance holes in the reconfiguration of the network. In addition, the scenario is limited through the geographical coordinates of latitude and longitude. The OpenStreetMap functions in Matlab allow the extraction of building and street information in matrices from the geo-referenced area. Thus, the research handles much information, and data cleaning is required. A clean and without-error database will reduce the computational times of the algorithms used.
In the second stage, active sites are selected based on search algorithms from candidate sites. Capacity and distance constraints have been posed by modifying the Prim algorithm. The distance calculations use the Haversine equation that considers the Earth’s curvature. Thus, no errors in the longitudinal measurements appear with a Euclidean plane equation. As a result, each candidate site generates a matrix with the distances between the candidate point and each user (service point). In the distance matrix, the absolute minimum is searched, repeating the process for each location. The model forms user sets for each candidate site, with the possibility of a single user being part of two or more clusters. Consequently, the Greedy algorithm obtains the smallest number of sets covering all users. The resulting groups represent the active sites and are ideal for transformers and maintenance holes.
The capacity and distance constraints serve two purposes in the model. The capacity constraint limits the number of users connected to a transformer. These supply power up to a nominal value; therefore, it is necessary to restrict the connected load. We ensure that the distribution transformers are not overloaded with the capacity constraint. We seek to ensure that the spans do not exceed a maximum distance with the distance constraint. In addition, limiting the span length allows us to control the voltage drop along conductors and cables; thus, the model ensures to stay within the maximum voltage drop range set by standard IEEE 1547.
In the third stage, the radial topology of the network is constructed based on MST techniques. The model considers a network resilient to extreme events; hence, this work proposes an underground electrical network. The trench route is oriented through the street paths to the intersections connecting all active sites. The proposed model is not exclusive to underground networks; it is applied to overhead and even mixed distribution networks that need a reconfiguration with radial topology. In addition, the proposed approach could be generalized to other types of networks, such as multi-carrier power networks, where independent network topologies can be formed for users who wish to belong to a different utility. The scenario and the network topology are exported from Matlab to Cymdist using an SHP file (vector representation format).
Finally, the performance of the modified Prim algorithm has been evaluated for different values of capacity and distance constraints. Analyzing the electrical parameters in specialized power distribution network software validates the model. In addition, the model’s scalability is verified with population growth over 6 years.

3.2. Problem Formulation

This paper presents a heuristic to find the number, capacity, and optimal location of transformers in distribution network reconfiguration based on graph theory and resilience to extreme events. In addition, the best route is identified for medium and low-voltage networks. The proposed model is scalable and is evaluated in a certain period. However, the grid reconfiguration is not performed every year; otherwise, the scalability results will show the number of transformers necessary each year to reconfigure the grid if an extreme event affects all existing users. This study considers the 6th year, when a population of 1284 users has been reached.
The primary inputs of all transformers are connected in a tree topology through a feeder that delivers power from the distribution substation to distribution transformers. The objective is to reconnect all users after the network infrastructure has been affected by an extreme event. The system requires new connection points; therefore, a new network topology is obtained based on a reconfiguration. The candidate location of transformers and utility maintenance holes are geo-referenced in a real scenario. The streets and intersections are ideal for designing the underground network. The buildings, corners, and roads are extracted from an OpenStreetMap osm file in geographic coordinates (latitude and longitude). Parameters and variables are depicted in Table 2 for the proposed methodology.
The length of conductors and cables must be optimal to minimize the indirect project costs, and the optimal routes for the medium and low-voltage networks are obtained through the graph theory concepts and minimum spanning tree (MST). The MST in the low-voltage network is found based on the modified Prim algorithm. Furthermore, the medium voltage network topology is routed through the intersection points and streets to build an underground distribution network. A distribution network with these characteristics is resilient to extreme events.
Our planet has an irregular spherical shape, and it is curved. Distances have been calculated through the Haversine equation. Consequently, the calculation of distance considers the curvature of the Earth. The length results between two points in a geo-referenced system are obtained in kilometers. Equations (1) and (2) expresses the Haversine formulation for distance calculations considering longitude and latitude.
D i j = 2 R a a s i n E
E = s i n 2 Δ l a t 2 2 + c o s l a t 1 c o s l a t 2 s i n 2 Δ l o n 2 2
The substation capacity corresponds to the power flow results obtained in the Cyme simulation and comprises the power delivered to all transformer primaries radially connected to the substation. The substation capacity is defined in Equation (3) through the network power flow. The model uses two Boolean-type decision variables to implement the modified PRIM algorithm. On the other hand, three restrictions are proposed to limit the capacity, the distance, and the voltage drop of the users connected to each transformer.
S c = | P s + j Q s |
Equation (4) expresses the capacity of the transformers through the power flow of demand and the lines losses that radially connect the transformer’s secondary with the loads.
T c k = j = 1 p | S L o a d T k j | + | S L i n e L o s s T k |
where,
S L o a d T k j = P L o a d T k j + j Q L o a d T k j
The cables losses between two nodes are calculated with the following equations:
P L i n e L o s s T k i , j = R i , j P i , j 2 + Q i , j 2 V i 2
P L i n e L o s s T k = i = 1 N j = 1 N P L i n e L o s s T k i , j
Q L i n e L o s s T k i , j = X i , j P i , j 2 + Q i , j 2 V i 2
Q L i n e L o s s T k = i = 1 N j = 1 N Q L i n e L o s s T k i , j
where,
S L i n e L o s s T k = P L i n e L o s s T k + j Q L i n e L o s s T k
The optimization model considers the indirect cost related to the driver, defined as meters of driver per unit value in the market. The proposed objective function for the model is shown in Equation (3), where this indirect cost is minimized. The variable D i s t i j represents the distance between two connected nodes. The total length of the conductor is obtained by adding up all the sections and multiplying it by their unit value to calculate the total cost.
Min : Z = i = 1 H j = 1 H C o s t i j D i s t i j
Subject to:
i = 1 m U j Δ c
D i s t i j Δ d
V r = V s [ I s ( D i s t i , j Z c ) ]
V m i n V r V m a x
Equation (12) corresponds to the transformer’s capacity constraint, where the number of users connected to each transformer is limited. Equation (13) corresponds to the maximum span distance constraint. This last parameter allows controlling the voltage drop that increases with the length of the conductor. This last parameter allows controlling the voltage drop that increases with the size of the conductor. The service voltage for each user as a function of voltage drop must remain within a normalized maximum and minimum voltage range.
The modified Prim algorithm delivers a solution matrix with the user clusters for each active site. Due to the calculation method and constraints, the solution matrix may show that a user belongs to one or more clusters. This condition is not possible; thus, the set covering problem appears; and this is solved through the Greedy algorithm. The set covering the problem is formulated as follows. Let A = { a 1 , a 2 , , a n } be a set of n elements. Let U = { u 1 , u 2 , , u m } be subset of A, i.e., each U j A . Each element in A appears in some set. A set covers C is a set such that j C U j = A . The objective function to minimize u m is defined as follows.
β i = 1 , i f s u b s e t i i s s e l e c t e d 0 , o t h e r w i s e
Min : Z = i n C i β i
Subject to:
i = 1 n β i 1 , i = 1 , , m
β i { 0 , 1 } , i = 1 , , n
The process of grid reconfiguration through modified Prim is presented in Algorithm 1, and the method to solve the set covering problem through the Greedy model is presented in Algorithm 2.
A laptop has been used to test the model with an Intel Core i5 2-core 2.40 GHz CPU and 12 GB RAM. First, the algorithm performance results through Matlab mathematical software are presented. The following section demonstrates the scalability of the model. Finally, the results of electrical parameters obtained through Cymedist are presented.
Algorithm 1 Reconfiguration  Algorithm.
  • Procedure:
  • Step:1 Scenario initialization
  • [ δ x , δ y ] Vector coordinate of users
  • [ λ x , λ y ] Vector coordinate of substation
  • [ ψ x , ψ y ] Vector coordinate of streets
  • Δ c Capacity constraint
  • Δ d Distance constraint
  • Calculate: D i s t i j h a v e r s i n e ( δ x , δ y )
  • Step:2 Modified Prim
  • ϕ i = 1; U = 0
  • while ϕ i = = 1 do
  •      α i , j = m i n ( m i n ( D i s t i , j ) )
  •     if  α i , j Δ d  then
  •         if  l e n g t h ( U ) Δ c  then
  •             [ r , c ] = f i n d ( α i , j = = D i , j )
  •             U = [ U A ( c ) ]
  •         else
  •             ϕ i = 0
  •         end if
  •     end if
  • end while
  • T k g r e e d y ( U )
  • Step:3 Primary and secondary grid MST
  • ρ Find transformers location
  • ξ p Find primary grid MST
  • ξ s Find secondary grid MST
  • Step:4 Transformer and substation sizing
  • Δ δ Load vector
  • S c Substation power flow
  • T c i Transformer power flow
Algorithm 2 Greedy Algorithm.
  • Procedure:
  • Step:1 Initialization
  • C
  • Step:2 Repeat until every element in A is covered
  • while A do
  •      L e t d ( j ) = | U j A |
  •      L e t j = argmax i { 1 , 2 , , m } d ( i )
  •      C C { j }
  •      A A U j
  • end while

3.3. Modified Prim Algorithm Performance

The optimal location and number of transformers and maintenance holes have been obtained through the modified Prim algorithm, and the Greedy algorithm complements the process. The number of transformers and maintenance holes based on the capacity and span length constraints is shown in Figure 4, where it is clear that a shorter span distance requires locating more components in the network. On the other hand, a longer span of space requires fewer components. This result was already expected because the number of users connected to each transformer changes proportionally with the span distance restriction. In addition, the number of transformers and maintenance holes decreases if the model considers higher capacity transformers that can connect more load.

4. Analysis of Results

The time of the central processing unit (CPU) when evaluating the model with the capacity and span distance constraints is shown in Figure 5. Longer processing times have been obtained when transformers’ capacity and span distance increase; otherwise, the CPU time is reduced. The difference between the minimum and maximum processing time is approximately 6000 s.
The model has been evaluated through simulation parameters presented in Table 3. All candidate locations have been circled. On the other hand, the candidate locations chosen have been marked by a green square within each circle. The radial connection of all candidate locations forms the underground network for the medium- and low-voltage networks. Consequently, Figure 6 shows the optimal location of transformers and maintenance holes in these conditions.
The radial topology connecting all the chosen sites has been obtained through MST techniques and Haversine distance calculation. Furthermore, the shortest connection distances have been routed along the trajectory of the streets existing in the geographical area to form the underground network trench route. Figure 7 shows the radial topology for the underground network in the geographical location.

4.1. Model Scalability

Distribution network planning models must be scalable; thus, the programming algorithms must be flexible to the number of users forming the network. The proposed model is evaluated for 6 years, with an increase of 214 nodes to be reconfigured if an extreme event happens in that year. Although the reconfiguration of an electrical network is not performed every year, it is difficult to predict how many users will be affected by a failure due to any extreme event. Figure 8 shows the proposed model results for different scenes considering scalability.
The results show that the number of transformers and maintenance holes required for reconfiguration reduces considerably with increasing span distance each year. As the span length increases, there is the possibility of more users connecting to the same transformer. Consequently, fewer transformers are required but have a higher capacity to supply the demand. In the first year, the result for different span distances tends to be constant due to the large dispersion of users. Therefore, the number of candidate sites is maximum to cover the maintenance hole area. In the last 3 years, a lower separation at the reconfiguration nodes; hence, similar results have been obtained for different span distances.
The CPU time when evaluating the model with span distance constraint and the increase of user number to be reconfigured per year is shown in Figure 9. Longer processing times have been obtained with the span distance increase; otherwise, the CPU time is minimum. When the span distance increases, transformers can group more users; hence, calculating all Haversine distances needed is more time-consuming.

4.2. Simulation Results in Cymdist

The topology based on the proposed heuristic process is tested in the Cymdist power network simulation software. Figure 10 shows the reconfiguration of the network in the simulation software. Power grid reconfiguration is exported from Matlab to CYME using a shape-file format Shp. These files are characterized by the fact that they store the information of the geographic systems in a geometrical form. Exporting points of interest such as the location of wells or transformers facilitates the implementation of the electrical network. It allows representing the geography of the study area in the CYME environment.
The network design must ensure that each user’s supply receives an adequate voltage level. Typical problems experienced by a customer’s supply depend on the location of each customer concerning the transformer station. When a customer’s power supply is connected close to the transformer, it is often overvoltage.
The voltage control with tap changer transformers and an adequate sizing of the conductor sizes permit the voltage regulation grid. On the other hand, a user connected far away from the transformer usually presents a considerable voltage drop. These conditions represent a poor quality of service.
Demands random vector for the network simulation has been generated. Figure 11 represents the load distribution in the heat map, and Table 4 summarizes the load distribution allocated to each group of transformers classified according to their capacity. Electrical distribution networks are unbalanced, and random demand perfectly represents the behavior of a local network. Figure 12 shows the simulation results in Cymdist of the primary feeder. In Figure 12, the per-unit voltage profile of the more extended length feeder of the network has been obtained. This section comprises approximately 2500 m from the source to the farthest transformer.
The series impedance of the feeder has a linear relationship with length; thus, the voltage drop increases with distance. Figure 12b,c show the load and current distribution along the primary feeder of the network. The conductor sections close to the source conduct most of the energy flow. Consequently, summation of all the currents flowing from the source to each concentrated load in the model. Therefore, the load and current steps decrease along the feeder. Figure 13 shows the network’s voltage profiles of four transformers. The service voltages are within the range defined by the standard IEEE 1547 of 0.917 p.u. as the minimum value.
Table 5 shows the position of transformers and wells in the geographical area. The results shown in Table 6 correspond to the power flows of the secondary network lines of each transformer. The cable used for this network is a 3/0 AWG with a rated capacity of 250 A, where line currents obtained do not exceed this capacity.

5. Conclusions

This paper proposed an algorithm capable of reconfiguring power grids through graph theory. It allows restoring power grids after an extreme event in less time. The proposed heuristic is based on a Prim-modified algorithm to determine the optimal location of transformers and maintenance holes in the distribution network. The problem of connecting all transformers primaries in a radial topology feeding to 100% of end-users is addressed throughout MST methods.
The application of the minimum spanning tree technique allows reducing the indirect costs of the model. The number of transformers for reconfiguration is directly related to distance and capacity constraints, where transformers with higher capacity and longer spans cluster more users at the same node. Under these conditions, the number of transformers required is reduced. Therefore, excavation costs, installation, equipment, and materials are reduced, resulting in a viable project.
The fundamental contribution of this research is to provide a powerful tool to be used by utilities to reconfigure resilient power grids with geographical parameters (latitude and longitude). The model has been geo-referenced and exported to CYME through a shape-file format. The specialized distribution network software simulation has verified that the model complies with the technical criteria and standards defined by the local electricity companies. Consequently, the model complies with voltage drops of less than 3.5%. Future work will include power flow studies.

Author Contributions

E.Q.: conceptualization, methodology, validation, writing—review and editing. E.I.: conceptualization, methodology, software, writing—original draft. E.Q.: data curation, formal analysis. E.I.: supervision. E.I., E.Q. writing—review and editing. All authors have read and agreed to the published version of the manuscript.

Funding

Universidad Politécnica Salesiana and Smart Grid Research Group (GIREI) founded this work under the project chargeability of the electric distribution grid considering the massive inclusion of electric vehicles.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Acknowledgments

The smart grids and smart cities group RECI-IUS, as well as the smart grids research group of the Universidad Politécnica Salesiana Sede Quito.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Yang, N.C.; Chen, H.C. Decomposed Newton algorithm-based three-phase power-flow for unbalanced radial distribution networks with distributed energy resources and electric vehicle demands. Int. J. Electr. Power Energy Syst. 2018, 96, 473–483. [Google Scholar] [CrossRef]
  2. Beza, T.M.; Huang, Y.C.; Kuo, C.C. A Hybrid Optimization Approach for Power Loss Reduction and DG Penetration Level Increment in Electrical Distribution Network. Energies 2020, 13, 6008. [Google Scholar] [CrossRef]
  3. Sultana, U.; Khairuddin, A.B.; Aman, M.M.; Mokhtar, A.S.; Zareen, N. A review of optimum DG placement based on minimization of power losses and voltage stability enhancement of distribution system. Renew. Sustain. Energy Rev. 2016, 63, 363–378. [Google Scholar] [CrossRef]
  4. Mathew, R.K.; Sankar, A.; Sundaramoorthy, K. An efficient and fast fault recovery algorithm for a resilient grid under extreme events. In Energy Sources, Part A: Recovery, Utilization and Environmental Effects; Taylor & Francis Group: Abingdon, UK, 2019; pp. 1–12. [Google Scholar] [CrossRef]
  5. Oboudi, M.H.; Mohammadi, M.; Rastegar, M. Resilience-oriented intentional islanding of reconfigurable distribution power systems. J. Mod. Power Syst. Clean Energy 2019, 7, 741–752. [Google Scholar] [CrossRef] [Green Version]
  6. Lei, S.; Chen, C.; Song, Y.; Hou, Y. Radiality Constraints for Resilient Reconfiguration of Distribution Systems: Formulation and Application to Microgrid Formation. IEEE Trans. Smart Grid 2020, 11, 3944–3956. [Google Scholar] [CrossRef] [Green Version]
  7. Shi, Q.; Li, F.; Olama, M.; Dong, J.; Xue, Y.; Starke, M.; Winstead, C.; Kuruganti, T. Network reconfiguration and distributed energy resource scheduling for improved distribution system resilience. Int. J. Electr. Power Energy Syst. 2021, 124, 106355. [Google Scholar] [CrossRef]
  8. Xu, J.; Zhang, T.; Du, Y.; Zhang, W.; Yang, T.; Qiu, J. Islanding and dynamic reconfiguration for resilience enhancement of active distribution systems. Electr. Power Syst. Res. 2020, 189, 106749. [Google Scholar] [CrossRef]
  9. Napis, N.F.; Kadir, A.F.A.; Khatib, T.; Hassan, E.E.; Sulaima, M.F. An improved method for reconfiguring and optimizing electrical active distribution network using evolutionary particle swarm optimization. Appl. Sci. 2018, 8, 804. [Google Scholar] [CrossRef] [Green Version]
  10. Kumar, S.; Sarita, K.; Vardhan, A.S.S.; Elavarasan, R.M.; Saket, R.K.; Das, N. Reliability Assessment of Wind-Solar PV Integrated Distribution System Using Electrical Loss Minimization Technique. Energies 2020, 13, 5631. [Google Scholar] [CrossRef]
  11. Azizivahed, A.; Arefi, A.; Ghavidel, S.; Shafie-Khah, M.; Li, L.; Zhang, J.; Catalao, J.P. Energy management strategy in dynamic distribution network reconfiguration considering renewable energy resources and storage. IEEE Trans. Sustain. Energy 2020, 11, 662–673. [Google Scholar] [CrossRef]
  12. Salau, A.O.; Gebru, Y.W.; Bitew, D. Optimal network reconfiguration for power loss minimization and voltage profile enhancement in distribution systems. Heliyon 2020, 6, e04233. [Google Scholar] [CrossRef]
  13. Diaaeldin, I.M.; Aleem, S.H.; El-Rafei, A.; Abdelaziz, A.Y.; Zobaa, A.F. A novel graphically-based network reconfiguration for power loss minimization in large distribution systems. Mathematics 2019, 7, 1182. [Google Scholar] [CrossRef] [Green Version]
  14. Gampa, S.R.; Das, D. Multi-Objective Approach for Reconfiguration of Distribution Systems with Distributed Generations. Electr. Power Components Syst. 2017, 45, 1678–1690. [Google Scholar] [CrossRef]
  15. Souifi, H.; Kahouli, O.; Hadj Abdallah, H. Multi-objective distribution network reconfiguration optimization problem. Electr. Eng. 2019, 101, 45–55. [Google Scholar] [CrossRef]
  16. Beyza, J.; Garcia-Paricio, E.; Yusta, J.M. Applying complex network theory to the vulnerability assessment of interdependent energy infrastructures. Energies 2019, 12, 421. [Google Scholar] [CrossRef] [Green Version]
  17. Qin, C.; Wang, L.; Han, Z.; Zhao, J.; Liu, Q. Weighted directed graph based matrix modeling of integrated energy systems. Energy 2021, 214, 118886. [Google Scholar] [CrossRef]
  18. Ustun, T.S.; Ayyubi, S. Automated network topology extraction based on graph theory for distributed microgrid protection in dynamic power systems. Electronics 2019, 8, 655. [Google Scholar] [CrossRef] [Green Version]
  19. Abeysinghe, S.; Wu, J.; Sooriyabandara, M.; Abeysekera, M.; Xu, T.; Wang, C. Topological properties of medium voltage electricity distribution networks. Appl. Energy 2018, 210, 1101–1112. [Google Scholar] [CrossRef]
  20. Pavón, W.; Inga, E.; Simani, S. Optimal routing an ungrounded electrical distribution system based on heuristic method with micro grids integration. Sustainability 2019, 11, 1607. [Google Scholar] [CrossRef] [Green Version]
  21. Heang, S.; Vai, V. Optimal Network Reconfiguration with DGs Placement and Sizing in a Distribution System Using Hybrid SOE and GA. In Proceedings of the 2022 19th International Conference on Electrical Engineering/Electronics, Computer, Telecommunications and Information Technology (ECTI-CON), Prachuap Khiri Khan, Thailand, 24–27 May 2022; pp. 2–5. [Google Scholar] [CrossRef]
  22. Corigliano, S.; Carnovali, T.; Edeme, D.; Merlo, M. Holistic geospatial data-based procedure for electric network design and least-cost energy strategy. Energy Sustain. Dev. 2020, 58, 1–15. [Google Scholar] [CrossRef]
  23. Inga, E.; Campaña, M.; Hincapié, R.; Moscoso-Zea, O. Optimal dimensioning of electrical distribution networks considering stochastic load demand and voltage levels. Commun. Comput. Inf. Sci. 2018, 833, 200–215. [Google Scholar] [CrossRef]
  24. Villacres, F.; Inga, E. Planeación y dimensionamiento de redes eléctricas de distribución soterrada mediante un método metaheurístico. Ing. Cienc. 2019, 15, 141–166. [Google Scholar] [CrossRef]
  25. Yao, M.; Molzahn, D.K.; Mathieu, J.L. An optimal power-flow approach to improve power system voltage stability using demand response. IEEE Trans. Control. Netw. Syst. 2019, 6, 1015–1025. [Google Scholar] [CrossRef]
  26. Muhammad, M.A.; Mokhlis, H.; Naidu, K.; Amin, A.; Franco, J.F.; Othman, M. Distribution Network Planning Enhancement via Network Reconfiguration and DG Integration Using Dataset Approach and Water Cycle Algorithm. J. Mod. Power Syst. Clean Energy 2020, 8, 86–93. [Google Scholar] [CrossRef]
  27. Helmi, A.M.; Carli, R.; Dotoli, M.; Ramadan, H.S. Efficient and Sustainable Reconfiguration of Distribution Networks via Metaheuristic Optimization. IEEE Trans. Autom. Sci. Eng. 2022, 19, 82–98. [Google Scholar] [CrossRef]
  28. Scarabaggio, P.; Carli, R.; Dotoli, M. Noncooperative Equilibrium Seeking in Distributed Energy Systems Under AC Power Flow Nonlinear Constraints. IEEE Trans. Control. Netw. Syst. 2022, 1, 1–12. [Google Scholar] [CrossRef]
  29. Valenzuela, A.; Montalvo, I.; Inga, E. A decision-making tool for electric distribution network planning based on heuristics and georeferenced data. Energies 2019, 12, 4065. [Google Scholar] [CrossRef] [Green Version]
  30. Valenzuela, A.; Inga, E.; Simani, S. Planning of a Resilient Underground Distribution Network Using Georeferenced Data. Energies 2019, 12, 644. [Google Scholar] [CrossRef] [Green Version]
  31. Mateo, C.; Prettico, G.; Gómez, T.; Cossent, R.; Gangale, F.; Frías, P.; Fulli, G. European representative electricity distribution networks. Int. J. Electr. Power Energy Syst. 2018, 99, 273–280. [Google Scholar] [CrossRef]
  32. Nagarajan, A.; Ayyanar, R. Application of Minimum Spanning Tree algorithm for network reduction of distribution systems. In Proceedings of the 2014 North American Power Symposium, NAPS 2014, Pullman, DC, USA, 7–9 September 2014. [Google Scholar] [CrossRef]
  33. Montoya, D.P.; Ramirez, J.M. A minimal spanning tree algorithm for distribution networks configuration. In Proceedings of the IEEE Power and Energy Society General Meeting, San Diego, CA, USA, 22–26 July 2012; pp. 1–7. [Google Scholar] [CrossRef]
  34. Sena, S.K. An Approach to Detect Islanding in Photovoltaic Based Distributed Generation Systems using Sequence Components of Voltage. In Proceedings of the 2022 IEEE International Conference on Distributed Computing and Electrical Circuits and Electronics (ICDCECE), Ballari, India, 23–24 April 2022; pp. 1–6. [Google Scholar] [CrossRef]
  35. Prossegger, M. Last mile cable route optimization using openstreetmap data-An experiment. In Proceedings of the 2015 4th International Conference on Future Generation Communication Technology, FGCT 2015, Luton, UK, 29–31 July 2015; Volume 1, pp. 74–78. [Google Scholar] [CrossRef]
  36. Püvi, V.; Millar, R.J.; Saarijärvi, E.; Hayami, K.; Arbelot, T.; Lehtonen, M. Slime Mold Inspired Distribution Network Initial Solution. Energies 2020, 13, 6278. [Google Scholar] [CrossRef]
  37. Bajpai, P.; Chanda, S.; Srivastava, A.K. A Novel Metric to Quantify and Enable Resilient Distribution System Using Graph Theory and Choquet Integral. IEEE Trans. Smart Grid 2018, 9, 2918–2929. [Google Scholar] [CrossRef]
  38. Taheri, B.; Safdarian, A.; Moeini-Aghtaie, M.; Lehtonen, M. Enhancing resilience level of power distribution systems using proactive operational actions. IEEE Access 2019, 7, 137378–137389. [Google Scholar] [CrossRef]
  39. Dimitrijevic, S.; Rajakovic, N. Service Restoration of Distribution Networks Considering Switching Operation Costs and Actual Status of the Switching Equipment. IEEE Trans. Smart Grid 2015, 6, 1227–1232. [Google Scholar] [CrossRef]
  40. Łukaszewski, A.; Nogal, Ł.; Robak, S. Weight Calculation Alternative Methods in Prime’s Algorithm Dedicated for Power System Restoration Strategies. Energies 2020, 13, 6063. [Google Scholar] [CrossRef]
Figure 1. Proposed methodology for the reconfiguration of power grids.
Figure 1. Proposed methodology for the reconfiguration of power grids.
Energies 15 05317 g001
Figure 2. Scheme of model to solve the network reconfiguration.
Figure 2. Scheme of model to solve the network reconfiguration.
Energies 15 05317 g002
Figure 3. Methodological flowchart for the reconfiguration and resilience of power grids based on graph theory.
Figure 3. Methodological flowchart for the reconfiguration and resilience of power grids based on graph theory.
Energies 15 05317 g003
Figure 4. Modified Prim algorithm with capacity and span constraints.
Figure 4. Modified Prim algorithm with capacity and span constraints.
Energies 15 05317 g004
Figure 5. CPU time of modified Prim algorithm with capacity and span constraints.
Figure 5. CPU time of modified Prim algorithm with capacity and span constraints.
Energies 15 05317 g005
Figure 6. Optimal location of transformers and manhole on the geographic area-Quito Tenis.
Figure 6. Optimal location of transformers and manhole on the geographic area-Quito Tenis.
Energies 15 05317 g006
Figure 7. Radial topology for the underground network.
Figure 7. Radial topology for the underground network.
Energies 15 05317 g007
Figure 8. Evaluation of the model with scalability in six years.
Figure 8. Evaluation of the model with scalability in six years.
Energies 15 05317 g008
Figure 9. CPU time of modified Prim algorithm with scalability in six years.
Figure 9. CPU time of modified Prim algorithm with scalability in six years.
Energies 15 05317 g009
Figure 10. Distribution network deployment in CYMDIST.
Figure 10. Distribution network deployment in CYMDIST.
Energies 15 05317 g010
Figure 11. Heat map of energy demand per user per month in Quito Tenis of Ecuador for a stratum A.
Figure 11. Heat map of energy demand per user per month in Quito Tenis of Ecuador for a stratum A.
Energies 15 05317 g011
Figure 12. (ac) Simulation results in cymdist.
Figure 12. (ac) Simulation results in cymdist.
Energies 15 05317 g012
Figure 13. Profile voltages in Cymdist.
Figure 13. Profile voltages in Cymdist.
Energies 15 05317 g013
Table 1. Summary of related works.
Table 1. Summary of related works.
Parameters ConsideredThematic
Author, YearObjectivesVoltageCapacityCostGeo-ReferencedPlanningResilienceDNRGraph Theory
Sena, 2022 [34]Electrical network evaluation----
Heang, 2022 [21]Reduces active power losses------
Łukaszewski, 2020 [40]Power system restoration--
Püvi, 2020 [36]Minimization of cost---
Taheri, 2019 [38]Load loss reduction----
Valenzuela, 2019 [29]Minimization of capacity-
Bajpai, 2018 [37]Power system restoration--
Mateo, 2018 [31]Design representative networks----
Dimitrijevic, 2015 [39]Power system restoration--
Prossegger, 2015 [35]Minimization of cost--
Nagarajan, 2014 [32]Power loss reduction----
Present workPower system restoration-
Table 2. Notation used in this article.
Table 2. Notation used in this article.
NomenclatureDescriptionUnits
D i j Distance matrix nxnkm
R a Earth curvaturekm
l a t , l o n Latitude and longitude
S c Substation capacityVA
P S , Q S Active and reactive power of the substationW, VAr
T c k Transformer capacityVA
T k Transformers vector
S L o a d T k j Load power flow of T k VA
S L i n e L o s s T k Total power flow losses in the line of T k VA
pNumber of users connected to T k
P L o a d T k j Active load power of T k W
Q L o a d T k j Reactive load power of T k Var
P L i n e L o s s T k Total active power loss in the line of T k ,W
Q L i n e L o s s T k Total reactive power loss in the line of T k ,Var
NTotal number of nodes in the line of T k
P L i n e L o s s T k i j Active power loss in the line i,j of T k ,W
Q L i n e L o s s T k i j Reactive power loss in the line i,j of T k VAr
R i , j , X i , j Resistance and reactance of line i,johm
V i Nodal voltageV
P i , j , Q i , j Active and reactive power in line i,jW, Var
ZObjective function
HTotal Number of nodes in the graph
U j Sets of users
mTotal number of sets
D i s t i j Haversine distancekm
C o s t i j Cost associated from node i to node j$
Δ c Capacity constraintVA
Δ d Distance constraintkm
V s , V r Sending and receiving end voltageV
I s Sending end currentA
Z L Line impedanceohm/km
V m a x , V m i n Maximum and minimum allowable voltageV
AUsers vector
CSet cover of G
dElements uncovered in U j
β i Decision variable
nTotal number of users
δ x , δ y Latitude and longitude coordinates of users
λ x , λ y Latitude and longitude coordinates of substation
ψ x , ψ y Latitude and longitude coordinates of streets
ϕ i Verification variable
α i , j Distance from node i to node j
r , c Indexes vector
ρ Transformers location
ξ p Primary grid MST
ξ s Secondary grid MST
Δ δ Load vector
Table 3. Simulation parameters.
Table 3. Simulation parameters.
User number1284
Geographic area1.9867 km 2
User locationGeolocated
Maximum span distance0.04 km
Transformers capacities30, 45, 50, 60, 75, 100, 125 kVA
TopologyRadial
Candidate locationStreets intersections
Voltage MV/LV22.8/0.22–0.11 kV
Substation capacity5 MVA
Table 4. Load for group of transformers.
Table 4. Load for group of transformers.
Capacity [kVA]Number of TransformersLoad [kVA]
1254409.92
100171289.37
7516971.63
6015753.39
508314.06
4515472.01
307123.4
Total824333.77
Table 5. Power flows in the low voltage network.
Table 5. Power flows in the low voltage network.
IDPhasekWkVArkVAAIDPhasekWkVArkVAAIDPhasekWkVArkVAA
A9.563.1310.0680.49 A10.513.4711.0788.70 A10.003.2710.5283.17
13B12.684.1813.35107.4116B7.352.407.7361.6218B10.403.3710.9386.47
C12.354.3914.05113.21 C14.714.8615.49125.13 C16.465.5417.37138.71
A15.144.9515.93127.03 A22.217.4723.43185.65 A8.952.929.4173.86
20B19.316.0920.24161.9522B16.965.5017.83140.3327B10.543.4111.0887.19
C22.827.2123.94192.08 C18.396.0519.36152.66 C11.273.8311.9093.88
A13.094.3213.78107.97 A6.021.946.33185.65 A17.956.0918.95148.709
31B15.505.0716.31128.0934B8.822.859.2772.7037B16.455.3517.30135.38
C21.427.2122.60178.86 C10.303.5610.8985.76 C16.435.3917.29135.37
A14.504.9915.33120.31 A18.295.9919.24149.33 A3.010.993.1625.44
39B12.654.2313.34104.2346B20.146.4321.15164.3055B5.941.966.2650.75
C11.333.5411.8792.44 C26.209.0627.72216.81 C3.821.264.0232.15
A11.743.8612.3698.89 A9.112.969.5876.68 A17.635.6118.50141.45
57B11.733.8012.3398.6461B11.323.8111.9496.1264B22.506.8421.65166.29
C17.245.7818.18146.75 C8.112.688.5468.31 C20.556.8421.65166.29
A18.646.2519.66150.59 A19.496.8720.67159.13 A9.002.999.4874.41
66B17.825.9218.77143.6670B17.095.5917.98137.9980B7.372.327.73120.81
C19.406.4120.43156.65 C18.265.7819.15147.10 C12.594.2912.30105.21
Table 6. Distribution of transformers and manhole in the grid reconfiguration.
Table 6. Distribution of transformers and manhole in the grid reconfiguration.
IDLongitudeLatitudeElementIDLongitudeLatitudeElementIDLongitudeLatitudeElement
1−78.4956626−0.1646934Manhole43−78.49283620.1634797Manhole85−78.49487100.1631814Manhole
2−78.4974442−0.1657886Manhole44−78.4940164−0.1639679Manhole86−78.4968549−0.1679038Transformer
3−78.4899543−0.1615904Manhole45−78.4935031−0.1647903Transformer87−78.4938444−0.1629662Transformer
4−78.4880987−0.1603417Manhole46−78.4930598−0.1655848Transformer88−78.4925036−0.1620917Manhole
5−78.4880939−0.1608229Manhole47−78.4941948−0.1657024Transformer89−78.4917861−0.1619892Transformer
6−78.4891653−0.1601209Manhole48−78.4949096−0.1644731Transformer90−78.4900758−0.1571579Transformer
7−78.4893812−0.1622488Manhole49−78.4933009−0.1664332Manhole91−78.4901956−0.1636273Transformer
8−78.4928925−0.1586009Transformer50−78.4923996−0.1662751Manhole92−78.4894875−0.1573314Manhole
9−78.4961826−0.1630995Transformer51−78.4918336−0.1663257Manhole93−78.4888022−0.1579755Transformer
10−78.4880654−0.1578643Transformer52−78.4932455−0.1679508Transformer94−78.4906524−0.1597648Manhole
11−78.4885943−0.1554399Manhole53−78.4936980−0.1670282Transformer95−78.4904853−0.1590306Transformer
12−78.4887144−0.1550391Manhole54−78.4943079−0.1678898Transformer96−78.4888387−0.1587112Transformer
13−78.4884037−0.1571658Transformer55−78.4950902−0.1664020Transformer97−78.4900647−0.1586148Transformer
14−78.4886084−0.1561324Manhole56−78.4956930−0.1675249Transformer98−78.4901355−0.1596422Transformer
15−78.4890271−0.1546499Transformer57−78.4955355−0.1681818Transformer99−78.4940928−0.1609178Transformer
16−78.4892213−0.1559610Transformer58−78.4915276−0.1678162Transformer100−78.4938448−0.1621520Transformer
17−78.4902326−0.1561455Transformer59−78.4933302−0.1690000Transformer101−78.4927839−0.1617755Manhole
18−78.4912875−0.1564434Transformer60−78.4907826−0.1683416Manhole102−78.4894139−0.1627426Transformer
19−78.4897407−0.1562292Transformer61−78.4899794−0.1689777Transformer103−78.4919035−0.1612675Manhole
20−78.4907806−0.1569555Transformer62−78.4948726−0.1656429Manhole104−78.4962885−0.1641469Transformer
21−78.4920208−0.1558018Transformer63−78.4919980−0.1642240Transformer105−78.4971696−0.1641925Transformer
22−78.4933554−0.1560085Transformer64−78.4909050−0.1637319Transformer106−78.4969022−0.16480630Manhole
23−78.4939884−0.1560215Transformer65−78.4906690−0.1648450Transformer107−78.4894745−0.1670606Manhole
24−78.4964113−0.1560763Transformer66−78.4897831−0.1653073Transformer108−78.4953701−0.1649071Manhole
25−78.4964728−0.1543750Transformer67−78.4909080−0.1610504Transformer109−78.4959801−0.1658317Manhole
26−78.4972670−0.1562068Transformer68−78.4911184−0.1605854Transformer110−78.4964716−0.1663340Manhole
27−78.4917217−0.1583394Transformer69−78.4930150−0.1607842Transformer111−78.4970411−0.1668148Manhole
28−78.4947161−0.1585367Transformer70−78.4947103−0.1606948Transformer112−78.4974661−0.1671899Transformer
29−78.4915596−0.1555405Transformer71−78.4879985−0.1673728Transformer113−78.4972761−0.1688342Transformer
30−78.4918981−0.1545780Manhole72−78.4888175−0.1672002Manhole114−78.4883509−0.1565264Transformer
31−78.4885502−0.1598393Transformer73−78.4879712−0.1643134Transformer115−78.4962504−0.1690394Manhole
32−78.4972270−0.1565072Manhole74−78.4884210−0.1656582Transformer116−78.4912478−0.1658375Transformer
33−78.4976677−0.1583134Manhole75−78.4887837−0.1634745Transformer117−78.4905422−0.1661531Manhole
34−78.4974770−0.1591901Transformer76−78.4899395−0.1651773Manhole118−78.4946701−0.1691961Transformer
35−78.4962615−0.1593339Manhole77−78.4940220−0.1574992Transformer119−78.4891169−0.1683271Manhole
36−78.4952144−0.1560502Transformer78−78.4923048−0.1584143Transformer120−78.4958242−0.1619287Manhole
37−78.4950746−0.1573121Transformer79−78.4956300−0.1588127Transformer121−78.4966498−0.1616657Manhole
38−78.4927642−0.1558457Transformer80−78.4949712−0.1597120Transformer122−78.4960699−0.1612378Manhole
39−78.4930390−0.1569814Transformer81−78.4937728−0.1595443Transformer123−78.4953977−0.1618972Manhole
40−78.4946240−0.1572972Manhole82−78.4923512−0.1595479Transformer124−78.4944284−0.1623681Transformer
41−78.4921408−0.1572142Transformer83−78.4937129−0.1601888Transformer125−78.4900525−0.1667893Manhole
42−78.4929395−0.164224Transformer84−78.4905600−0.1556918Transformer126−78.4898437−0.1660469Manhole
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Quintana, E.; Inga, E. Optimal Reconfiguration of Electrical Distribution System Using Heuristic Methods with Geopositioning Constraints. Energies 2022, 15, 5317. https://doi.org/10.3390/en15155317

AMA Style

Quintana E, Inga E. Optimal Reconfiguration of Electrical Distribution System Using Heuristic Methods with Geopositioning Constraints. Energies. 2022; 15(15):5317. https://doi.org/10.3390/en15155317

Chicago/Turabian Style

Quintana, Edy, and Esteban Inga. 2022. "Optimal Reconfiguration of Electrical Distribution System Using Heuristic Methods with Geopositioning Constraints" Energies 15, no. 15: 5317. https://doi.org/10.3390/en15155317

APA Style

Quintana, E., & Inga, E. (2022). Optimal Reconfiguration of Electrical Distribution System Using Heuristic Methods with Geopositioning Constraints. Energies, 15(15), 5317. https://doi.org/10.3390/en15155317

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop