Next Article in Journal
Comparison of Flame Propagation Statistics Based on Direct Numerical Simulation of Simple and Detailed Chemistry. Part 2: Influence of Choice of Reaction Progress Variable
Next Article in Special Issue
Voltage Regulation Performance Evaluation of Distributed Energy Resource Management via Advanced Hardware-in-the-Loop Simulation
Previous Article in Journal
Hydrothermal Carbonization of Chemical and Biological Pulp Mill Sludges
Previous Article in Special Issue
Development of a Smart Energy Community by Coupling Neighbouring Community Microgrids for Enhanced Power Sharing Using Customised Droop Control
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Two-Stage Stochastic Model to Invest in Distributed Generation Considering the Long-Term Uncertainties

by
Jorge Luis Angarita-Márquez
1,
Geev Mokryani
1 and
Jorge Martínez-Crespo
2,*
1
Faculty of Engineering and Informatics, University of Bradford, Bradford BD7 1DP, UK
2
Electrical Engineering Department, Universidad Carlos III de Madrid, 28911 Madrid, Spain
*
Author to whom correspondence should be addressed.
Energies 2021, 14(18), 5694; https://doi.org/10.3390/en14185694
Submission received: 21 June 2021 / Revised: 26 August 2021 / Accepted: 31 August 2021 / Published: 10 September 2021

Abstract

:
This paper used different risk management indicators applied to the investment optimization performed by consumers in Distributed Generation (DG). The objective function is the total cost incurred by the consumer including the energy and capacity payments, the savings, and the revenues from the installation of DG, alongside the operation and maintenance (O&M) and investment costs. Probability density function (PDF) was used to model the price volatility in the long-term. The mathematical model uses a two-stage stochastic approach: investment and operational stages. The investment decisions are included in the first stage and which do not change with the scenarios of the uncertainty. The operation variables are in the second stage and, therefore, take different values with every realization. Three risk indicators were used to assess the uncertainty risk: Value-at-Risk (VaR), Conditional Value-at-Risk (CVaR), and Expected Value (EV). The results showed the importance of migration from deterministic models to stochastic ones and, most importantly, the understanding of the ramifications of every risk indicator.

1. Introduction

The Distributed Generations (DGs) integration into the power grid is arising as a new paradigm in power systems to produce reliable electrical power and are becoming a part of the strategic plans of most countries to address current challenges associated with energy management [1]. The participation of households in an individual way and communities (building, districts) as partners in energy projects are transforming energy systems [2]. Energy communities, mostly microgrid based, are becoming a key stakeholder of modern electrical power grids. Thus, for example, operating a microgrid-based energy community is an inspiring topic due to uncertainties and complexities, since its flexibility can contribute to each consumer or community member’s wellbeing [3].
Nowadays, small customers at household levels can invest in DG to reduce their energy costs. However, a serious problem in energy generation planning at the household/building level is the lack of tools for decision makers or the consumers to assess the profitability of investments in DG. The adoption of solar photovoltaic (PV), wind turbines (WTs), or electrical energy storage by end users/consumers depends on the economic attractiveness, which is typically assessed through economics metrics such as Net Present Value (NPV) [4]. Ref. [5] provides a techno-economic analysis of three small-scale WTs, taking into account a nominal electrical power generation below 100 kW. The research focused on 220 residential households and used the net present cost (NPC) analysis in all cases.
However, these analyses do not consider the evolution in the short- and long-term. Ref. [6] presented a methodology to assess the technical, economic, environmental, and social benefits of a wind power plant in developing countries. The economic analysis is based on the estimated annual energy production of the optimum WTs, along with various incentive schemes, in the form of financial and fiscal incentives, and revenues from the exchange of displaced carbon emissions. Finally, the environmental impacts of the wind power plant were assessed regarding noise emissions, zones of visual influence, and shadow flickering, along with the social acceptance of the project. External factors such as low-frequency (20–200 Hz) noise from WTs must be taken into account when evaluating projects due to potential health concerns. Ref. [7] estimated the sound power level (dB) of wind turbines at 20–200 Hz, an essential aspect for estimating noise exposure of nearby residents. These environmental problems could reduce the productivity of the generation system and carefully analyzed.
Other works examined a California-based microgrid’s decision to invest in a DG unit fueled by natural gas [8]. Although the paper evaluated a fossil fuel installation, the assumptions are not very different than the case of PV or battery DG system. The paper assumed the long-term natural gas generation cost as a stochastic variable, although initially accepted that the microgrid may purchase electricity at a fixed retail rate from its utility. In the case of PV systems, the revenues generated by rooftop PV systems have several sources of uncertainty. Ref. [9] used a Monte Carlo framework to explore the sensitivity of PV investment returns to three categories of PV investment uncertainty: (1) interannual solar variability, (2) PV technical performance and maintenance costs, and (3) market risks including future electricity rates and the possibility that retail electricity rates will be restructured for PV customers.
This paper investigated the impact of the electricity market prices on DG investment decisions taken by consumers. Since the lifetime of a PV power system is typically 25 years, it is necessary to take into account the electricity market price uncertainties. Once the DG is operating, the owners receive revenue, which depends on that market price, for the net energy production delivered to the network (when the energy generation exceeds the consumption). This energy can be negotiated using bilateral trading where the traditional reference is the spot price, which vary continuously due to different factors: daily demand curve, seasonality, market power, etc.
A frequent practice to address stochastic problem is to solve a deterministic problem and then run a sensitivity analysis, where the solution found is tested over all possible scenarios. This approach provided a foresight of the situations that companies are going to face in the future when making such a decision. However, the optimization procedure has not explicitly taken any consideration about the distribution of the risk during the optimization process. Ref. [10] presented a microgrid strategy to minimize the risk of mismatch between seller and buyers, using the Expected Value. In [11], several events were used to stablish the failure probability to assess the risk of potential disturbances. Conditional Value at Risk (CVaR) was used in [12] for the risk assessment criterion.
The paper presented an algorithm to minimize the consumer energy cost considering a realistic tariff environment and the savings and revenue from investment in DG. The price paid to the consumer by the energy delivered to the network is considered a stochastic parameter represented by a discrete probability density function (PDF) through the variable P i , h D G , e x e (see Section 2). In this case, the objective function aims at finding a solution to minimize the energy cost taking into account all possible scenarios simultaneously, weighted by their probability, or to limit the worst-case scenario. The problem was solved using a two-stage stochastic model.
In the first stage, the decision variables (size and location of the DG units) do not change with every realization of the uncertainty, while in the second stage, the variables (the revenue from selling energy to the power system) do with every realization. Note that the first and second stage decision variables were taken in a coordinated manner. The algorithm finds the best solution to minimize the objective function taking into account the risk criteria. In the specific case presented here, the algorithm in the first stage finds the optimal size and place of the DG to minimize the cost incurred by the customer, including first- and second-stage variables. The second-stage problem minimizes the cost of the system for every scenario, taking into account the decisions obtained in the first stage. The prices considered in the study case are the daily market prices of the Mexican wholesale market.
The main contributions of this paper are summarized as follows:
(1)
The stochastic analysis of the DG investment problem. The price paid to the consumer is a stochastic parameter represented by a discrete probability density function.
(2)
The two-stage stochastic optimization problem and the risk decision criteria including Value at Risk (VaR), Conditional Value at Risk (CVaR), and Expected Value (EV) used for optimal decision making.
(3)
The comparison of the risk decision criteria is very important since it can prevent the occurrence of worst-case scenarios.
This paper is organized as follows. The problem formulation and the solution method are presented in the Section 2, describing the objective function, along with the techno-economical constraints of the devices and the power flow equations. Next, in Section 3, the test case is described, and the main considerations and results are presented. Finally, the main conclusions of the work are discussed and presented in Section 4.

2. Methodology

This paper presented a stochastic model to maximize the benefit of the consumer considering the payments and the cost and benefits from installing DG. Firstly, the problem was presented as a deterministic model, and then the recast of the objective function and the constraints were modelled using EV, VaR, and CVaR.

2.1. Deterministic Formulation

The objective function aims to maximize the consumer profit by minimizing the investment and energy and capacity payments while maximizing the savings and revenue. The objective function of the consumer is presented in (1).
M i n   C u s C o s t = M i n { i   {   T E i C u s + T C i C u s S E i C u s I E i C u s   }       i { O & M i D G + C A P E X i D G } }
The first and second terms of the equation include the energy T E i C u s   and capacity T C i C u s payments. The third term S E i C u s represents the saving from reducing the energy taken from the network, which alternatively denotes the reduction in the energy payment. The fourth term I E i C u s   is the revenue from delivering energy to the network, where the price paid is uncertain. The last summation represents the O&M O & M i D G and the investment costs C A P E X i D G in the new DGs.
The customers are required to pay accordingly with the energy P i , h d   and capacity C i , t b d   demand. The unit price of these services is defined by the regulatory authority; therefore, those values are parameters in the formulation. Equations (2) and (3) represent, respectively, the energy and capacity payments. In Equation (2), the tariff of the electricity price ϕ e n e , h t a r can change hourly, which is usually referred as time-of-use-tariff (ToU) model. Traditionally, the ToU considers three-time blocks prices for the energy charge (peak, base, and valley). In Equation (3), the capacity payment is calculated by using the maximum demand for each time block (tb).
T E i C u s = h P i , h d × ϕ e n e ,   h t a r     h T
T C i C u s = t b C i , t b d × ϕ c a p , t b t a r     t b T b l o c k
Customers can decide to invest in a DG to achieve savings in their energy payment. Equations (4) and (5) guarantee the energy used in this calculation, P i , h D G , l o w , is always lower than the energy consumption, P i , h d . Equation (6) computes customers’ revenue I E i C u s   when the DG production is higher than the demand.
S E i C u s = h P i , h D G , l o w × ϕ l o w ,   h t a r , D G         h T
P i , h D G , l o w P i , h d       h T
I E i C u s = h P i , h D G , e x e × ϕ e x e , h t a r , D G       h T    
Therefore, the energy production from the DG is paid depending on whether the DG’s production is lower or higher than the demand. In (7) and (8), an auxiliary binary variable σ i , t is introduced to ensure that the energy production from DG is first assigned to P i , h D G , l o w and only when the production is higher than the consumption, then this is allocated to P i , h D G , e x e . Equation (9) limits the energy delivered to the network ,   P i , h D G , e x e   , to any regulatory limit P i D G , l i m . The DG’s investment S E i C u s   and operation costs O & M i D G   are represented in (10) and (11).
P i , h D G , l o w + P i , h D G , e x e = P i , h D G       h T
P i , h d × σ i , t P i , h D G , l o w       h T
P i , h D G , e x e σ i , h × P i D G , l i m     h T
S E i C u s = h P i , h D G , l o w × ϕ l o w ,   h t a r , D G         h T
O & M i D G = C I i D G × O & M p r i c e D G     i N  
The energy generated from the DG, P i , h D G , is limited by the capacity installed and the natural resources available (solar resources, in the case of PV DG) in Equation (12). The DG reactive power Q i , h D G   is constrained by the inverter specifications. Here the DG can operate within 0.8 lagging or lead power factor (13).
0 P i , h D G C I i D G × π h D G       h T
| Q i , h D G | tan { cos 1 ( p f i D G ) } × P i D G       h T

2.2. Risk Indicators

There are several Key Performance Indicators (KPIs) to measure the risk associated with the decision under uncertainty, including VaR, CVaR, and EV. The p-Value-at-Risk (p-VaR) estimates the best value of all worse outcomes whose combined probability is at most p. For example, in the present formulation, 5%-VaR was the highest operation cost of all possible costs of the study case with a combined probability of 5%. CVaR is derived by taking a weighted average of the worst-case scenario of the distribution of possible outcomes, beyond the VaR cut-off point. The EV is the weighted average of the outcome considering all realizations (scenarios) [13].
To compare the pros and cons of each risk criterion, the proposed three approaches were compared, minimizing the VaR, CVaR, and EV of the long-term operational cost of the DG considering price uncertainty of the energy delivered to the network ϕ e x e , h t a r , D G .

2.3. Recasting the Objetive Function

In this section, the reformulation of the objective function and the constraints affected by the introduction of the uncertainty are presented.
It should be noted that the price uncertainty turns the revenue of the customer I E i C u s into a stochastic variable, i.e., the customers’ revenue changes with every price scenario; therefore, I E i , e C u s is the customer’s revenue in scenario e. Since the objective function depends on the revenue, it is also a stochastic variable, C u s C o s t e .
The optimization problem, considering the EV ( E ) as decision criterion, can be found in (14), where ρ e   is the probability of scenario e.
M i n   E { C u s C o s t e } = M i n e   C u s C o s t e × ρ e         e E
The algorithm computes the value of every variable in the second stage for each scenario e. In this case, the algorithm computes the savings and the objective function for every scenario e.
The definition of p-VaR is presented in Equation (15). The ultimate objective is limiting the objective function to be higher than p-VaR in at least (1−p) percentage of scenarios. For instance, if p is 10%, the algorithm will try to find the best 10%-VaR value to assure 90% of the objective function values are higher than 10%-VaR. Since the problem is the minimization of the customer cost, the algorithm looks for the highest p-VaR.
M a x     p V a R e ρ e p         e Y     |       C u s C o s t e p V a R         e Y   | Y E
Finally, the p-CVaR formulation is shown in (16), wherein the objective is to avoid severe depression of the customer benefit in the p worst cases. In this case, the algorithm is more conservative because it cares not only about the p-VaR but also the weighted average of the p worst case scenarios.
M a x   p C V a R = e   C u s C o s t e × ρ e         e Y   | Y E  

3. Case Study and Simulation Results

A 16-bus 33 kV radial distribution, as shown in Figure 1, was used to assess the proposed method. This distribution power system is made of 16 buses and 18 lines. The daily energy demand is 218.83 MWh, the average hourly consumption is 9.12 MWh, and the peak-demand (at hour 16) is 12.52 MW. Since it is an urban feeder, the DGs are located at buses 6, 9 and 11.
The model was implemented in General Algebraic Modelling System (GAMS). The data required for the optimization process were imported and exported using GAMS Data Exchange (GDX) tool. Since the model is defined as a bilevel model, the optimization algorithm provided the optimal solution for every single scenario. Therefore, the consumers who use the proposed method can obtain the optimal investment decision as the best operation-decisions for every possible scenario of the uncertain parameters.
Network parameters and geographical location of the network are available in [14]. The tariff used in the simulations, energy (£/MWh) and capacity (£/MW-month) prices, are shown in Table 1. The peak time was 17–20 h, valley periods were 1–4 h and 23–24 h, and base periods were 5–16 h and 21–22 h. The prices represent the behavior of the Mexican electricity market in the daily market [15] and the capacity market [16] of Valle de Mexico area. Valle de Mexico is a region in the southern-central part of the Mexican Republic where the capital, Mexico City, is located. Despite this work being developed using the Mexican spot market prices, the market model and its prices are close to any competitive market and, therefore, the results are fairly relevant to any other market.
The price of the energy delivered to the network used in the simulations was μ × ϕ e x e , h t a r , D G , where the discrete probability distribution of the price multiplier μ ranging from 0.9 to 1.1.
The first simulation was carried out considering three different approaches: deterministic model, EV, and VaR. The profit obtained by the DG unit, ProDGe, is calculated as the savings S E i , e C u s   and revenue I E i , e C u s   minus the DG expenses (17). It is relevant to note that CAPEX does not change with the price scenario   μ , since the investment problem is defined in the first-stage.
P r o D G e = { i   {   S E i , e C u s + I E i , e C u s   } i { O & M i D G + C A P E X i D G } }
Figure 2 depicts the profit, ProDGe, obtained by the DG unit. The x-axis shows the probability while y-axis indicates the benefits for every scenario. The deterministic curve, which is somehow arbitrary because its results depend on the specific price considered, was calculated using the following two steps: firstly, running the deterministic model for a specific price and finding the optimal DG size and location C I i D G ; secondly, fixing the DG solution and calculating the objective function P r o D G e   for every realization of the stochastic parameter.
The EV approach maximizes the profit considering all scenarios in the PDF. The p-VaR approach estimates the best value among all worse outcomes whose combined probability is p.
The slope of the curves is the measurement of the uncertainty that the customer can face in the long-run. When the risk is not considered explicitly (deterministic model), the benefit can be 60 k£/year in the best case or −27 k£/year in the worst case. Using the EV and 10%-VaR (stochastic approach), the benefit changes dramatically as a consequence of the price uncertainty. Table 2 presents the values of the maximum/minimum P r o D G e and the 10%-VaR and EV (in k£/year).
VaR is the most conservative approach: no big profits, no relevant losses. Therefore, the chart showing the objective function versus scenarios tends to be flatter. In this test case, the deterministic approach is not only volatile, but also it provides a lowest EV.
Utilizing either VaR or CVaR, it is always a challenge to choose the correct value of p . In order to analyze incidence p, Figure 3 shows the customer benefit using CVaR with p = 10 % and p = 20 % . Risk-averse consumers can choose higher p values since it reduces the risk exposure in the worst-case scenarios. The customer needs to be aware of this conservative approach, which lowers the expected value of the benefit. Table 3 compares the risk indicators under different risk criteria as objective function.
The Levelized Cost of Energy (LCOE) is the production cost considering the investment and the energy produced (LCOE = Investment Cost/Energy Production). In this particular case, the LCOE was calculated using annual values. Thus, LCOE assumes the following value: L C O E = 100   £ 2.473   M W h = 40.44   £ / MWh .
The decision on the optimal size of DG to be installed depends on the relation between the price of the energy delivered to the network, ϕ e x e , h t a r , D G , and LCOE. Then, it will evaluate five cases (see Table 4) with different PDFs (Figure 4), with diverse expected values of the price of the energy injected and taking lower and higher values than LCOE.
When the price paid for the energy delivered to the network, ϕ e x e , h t a r , D G , is higher than LCOE (cases 1, 2 and 3), the energy injection to the network increases as well as the customer profit, as shown in Figure 5. The higher the price (case 1), the bigger the power injected to the grid.
Otherwise, when the prices are lower than LCOE (cases 4 and 5), the energy injection does not provide benefits for the customer. It is evident from Figure 5 that the maximum power generation (case 5, hour 13) is about 10 times lower than the highest power generation in case 1. Thus, the optimal amount of DG installed is mostly intended to reduce the customer consumption, because the price of energy consumption remains unchanged.
Finally, Figure 6 shows the size of the DG installed (MW) depending at each bus (6, 9, or 11) and the price paid for the energy injected to the network (Expected Value of each case: 1–5). Obviously, the highest power installed in each bus is obtained in case 1 (high EV). Bus 11 is the best location to install the highest number of DGs.

4. Conclusions and Discussion

This paper presented the mathematical formulation of a two-stage stochastic model used by a consumer to optimize the DGs investment decision. The determinist approach has been compared with risk decision criteria like VaR, CVaR, and EV. The results showed that the lack of such criteria could lead to high-risk decisions. The results also showed that the EV provides a more conservative approach compared with the deterministic model. VaR and CVaR are even more conservative solutions, avoiding very negative scenarios but losing profit (on average).
This paper proposed a novel strategy to choose the CVaR and VaR within an optimal range p, comparing the opportunity cost versus the severity of the worst-case scenarios avoided. The impact of the price paid for the energy delivered to the network versus the capacity installed was discussed, showing the relevance of the LCOE as price reference. When the payment of the energy delivered by the DG was higher than the LCOE, the capacity installed increased drastically. The benefit for the customer under such a level of penetration must be compared with the impact of the activity of the Distribution Network Operator and the retailer.

Author Contributions

The contributions of each author were as follows: Conceptualization, J.L.A.-M. and G.M.; methodology, J.L.A.-M. and G.M.; software, J.L.A.-M.; validation, J.L.A.-M., G.M. and J.M.-C.; formal analysis, J.L.A.-M., G.M. and J.M.-C.; investigation, J.L.A.-M., G.M. and J.M.-C.; writing—original draft preparation, J.L.A.-M.; writing—review and editing, J.L.A.-M., G.M. and J.M.-C. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported in-part by Innovate UK GCRF Energy Catalyst Pi-CREST project under Grant number and in-part by British Academy GCRF COMPENSE project under Grant GCRFNGR3\1541.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

Sets and indexes
Eset of all price scenarios.
Yset of all scenarios considered in the VaR and CVaR calculation.
Tset of all period indexes in hours h.
Tbset of all period time blocks (peak, base and valley).
Nset of buses “i” of the power system.
Parameters
C A P p r i c e D G Investment price associated with DG (£/kW).
O & M p r i c e D G Operation and maintenance (O&M) cost of DG (£/kW).
P i D G , l i m Regulatory limit of power delivered to the network by DG (kWh).
P i , h d Active power demand at bus i, at hour h (kW).
p f i D G Operational limits of the power factor.
  Q i , h d Reactive power demand at bus i, at hour h (kVAr).
ϕ e n e / c a p ,   h t a r Energy/capacity tariff associated with the consumption/demand (£/kWh or £/kW).
ϕ e x e / l o w ,   h t a r , D G Price (£/kWh) for energy delivered by DG when production is higher (exe) or lower (low) than the demand.
π   h D G Maximum hourly production from DG per kW installed (kWh/kW).
Variables
C A P E X i D G Investment cost of DG at node i (£).
C i , t b d Customer’s capacity demand at time block tb (kW).
C I i D G DG’s capacity installed at bus i (kW).
C u s C o s t Is the energy cost of the system consumer (kW).
E V ( ) Expected Value of the function (£/year).
VaRValue-at-Risk (£/year)
p-VaRValue-at-Risk with probability p (£/year).
p-CVaRConditional Value-at-Risk with probability p (£/year).
I E i C u s Revenue from DG’s production delivered to the network (£).
T C i C u s Capacity customer payment (£).
T E i C u s Energy customer payment (£).
O & M i D G Operation and maintenance (O&M) cost of DG (£) at bus i.
P i D G Capacity installed of the DG at bus i (kW).
P i , h D G Active power produced by the DG at bus i, at hour h (kWh).
P i , h D G , l o w / e x e Active power produced by the DG which is lower/higher than the demand at bus i, at hour h (kWh).
S E i C u s Customer savings because of consumption from the integration of DG (£).
σ i , h Binary variable: 1 if the power output of the DG at bus i during hour t has exceeded the demand.

References

  1. Guerrero, J.M.; Blaabjerg, F.; Zhelev, T.; Hemmes, K.; Monmasson, E.; Jemei, S.; Comech, M.P.; Granadino, R.; Frau, J.I. Distributed Generation: Toward a New Energy Paradigm. IEEE Ind. Electron. Mag. 2010, 4, 52–64. [Google Scholar] [CrossRef]
  2. Caramizaru, A.; Uihlein, A. Energy Communities: An Overview of Energy and Social Innovation; EUR 30083 EN; Publications Office of the European Union: Luxembourg, 2020; ISBN 978-92-76-10713-2. [Google Scholar] [CrossRef]
  3. Mar, A.; Pereira, P.; Martins, J. Energy Community Flexibility Solutions to Improve Users’ Wellbeing. Energies 2021, 14, 3403. [Google Scholar] [CrossRef]
  4. Gissey, G.C.; Zakery, B.; Dodds, P.E.; Subkhankulova, D. Evaluating Consumer Investments in Distributed Energy Technologies. Energy Policy 2021, 149, 112008. [Google Scholar] [CrossRef]
  5. Alkawsi, G.; Baashar, Y.; Alkahtani, A.A.; Lim, C.W.; Tiong, S.K.; Khudari, M. Viability Assessment of Small-Scale On-Grid Wind Energy Generator for Households in Malaysia. Energies 2021, 14, 3391. [Google Scholar] [CrossRef]
  6. Waewsak, J.; Kongruang, C.; Gagnon, Y. Assessment of wind power plants with limited wind resources in developing countries: Application to Ko Yai in southern Thailand. Sustain. Energy Technol. Assess 2017, 19, 79–93. [Google Scholar] [CrossRef]
  7. Chiu, C.-H.; Lung, S.C. Assessment of low-frequency noise from wind turbines under different weather conditions. J. Environ. Health Sci. Eng. 2020, 18, 505–514. [Google Scholar] [CrossRef] [PubMed]
  8. Siddiqui, A.S.; Marnay, C. Distributed Generation Investment by a Microgrid under Uncertainty. Energy 2008, 33, 1729–1737. [Google Scholar] [CrossRef] [Green Version]
  9. Drury, E.; Jenkin, T.; Jordan, D.; Margolis, R. Photovoltaic Investment Risk and Uncertainty for Residential Customers. IEEE J. Photovolt. 2014, 4, 278–284. [Google Scholar] [CrossRef]
  10. Ryu, Y.; Lee, H.W. A Real-time Framework for Matching Prosumers with Minimum Risk in the Cluster of Microgrids. IEEE Trans. Smart Grid 2020, 11, 2832–2844. [Google Scholar] [CrossRef]
  11. Chen, X.; Qiu, J.; Reedman, L.; Dong, Z.Y. A Statistical Risk Assessment Framework for Distribution Network Resilience. IEEE Trans. Power Syst. 2019, 34, 4773–4783. [Google Scholar] [CrossRef]
  12. Arasteh, H.; Vahidinasab, V.; Sepasian, M.S.; Aghaei, J. Stochastic System of Systems Architecture for Adaptive Expansion of Smart Distribution Grids. IEEE Trans. Ind. Inform. 2019, 15, 377–389. [Google Scholar] [CrossRef]
  13. Malekpour, S.; Barmish, B.R. When the Expected Value Is Not Expected: A Conservative Approach. IEEE Trans. Syst. Man Cybern. Syst. 2017, 47, 2454–2466. [Google Scholar] [CrossRef]
  14. Centre for Sustainable Electricity and Distributed Generation, Imperial College. The United Kingdom Generic Distribution System (UKGDS). Available online: https://github.com/sedg/ukgds (accessed on 19 June 2021).
  15. Centro Nacional de Control de Energía CENACE. Wholesale Energy Market: Locational Marginal Prices; CENACE: Ciudad de Mexico, Mexico, 2021; Available online: https://www.cenace.gob.mx/Paginas/SIM/Reportes/PreciosEnergiaSisMEM.aspx (accessed on 19 June 2021).
  16. Centro Nacional de Control de Energía CENACE. Power Balance Market; CENACE: Ciudad de Mexico, Mexico, 2021; Available online: https://www.cenace.gob.mx/Paginas/SIM/MercadoBalance.aspx (accessed on 19 June 2021).
Figure 1. 16-bus UKGDS single-line diagram.
Figure 1. 16-bus UKGDS single-line diagram.
Energies 14 05694 g001
Figure 2. Consumer benefits from DG.
Figure 2. Consumer benefits from DG.
Energies 14 05694 g002
Figure 3. Consumer benefit using CVaR as hedge instrument.
Figure 3. Consumer benefit using CVaR as hedge instrument.
Energies 14 05694 g003
Figure 4. Probability distribution of study cases.
Figure 4. Probability distribution of study cases.
Energies 14 05694 g004
Figure 5. DG generation and demand at generation cases.
Figure 5. DG generation and demand at generation cases.
Energies 14 05694 g005
Figure 6. DG generation by bus and by case.
Figure 6. DG generation by bus and by case.
Energies 14 05694 g006
Table 1. Customer energy and capacity tariff.
Table 1. Customer energy and capacity tariff.
ToUPeakBaseValley
ϕ e n e ,   h t a r ,   D G 55.050.045.0
ϕ c a p ,   t b t a r ,   D G 4000.00.00.0
Table 2. Risk indicators (k£/year) using different approaches.
Table 2. Risk indicators (k£/year) using different approaches.
ModelMin (ProDGe)Max (ProDGe)VaREV
Deterministic−27.360−3.712.7
EV527.611.115.3
10%-VaR11.216.412.613.6
Table 3. Results from different conservative approaches.
Table 3. Results from different conservative approaches.
Optimization of
Model
Risk Indicators
EV10%-CVaR20%-CVaR
EV15.30.671.88
10%-CVaR13.61.042.54
20%-CVaR14.11.022.54
Table 4. Data of the study cases.
Table 4. Data of the study cases.
Optimization ResultsCase 1Case 2Case 3Case 4Case 5
Price (EV)( £ / MWh ) 45.241.540.839.638.7
DG installed (MW)10.895.081.591.030.9
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Angarita-Márquez, J.L.; Mokryani, G.; Martínez-Crespo, J. Two-Stage Stochastic Model to Invest in Distributed Generation Considering the Long-Term Uncertainties. Energies 2021, 14, 5694. https://doi.org/10.3390/en14185694

AMA Style

Angarita-Márquez JL, Mokryani G, Martínez-Crespo J. Two-Stage Stochastic Model to Invest in Distributed Generation Considering the Long-Term Uncertainties. Energies. 2021; 14(18):5694. https://doi.org/10.3390/en14185694

Chicago/Turabian Style

Angarita-Márquez, Jorge Luis, Geev Mokryani, and Jorge Martínez-Crespo. 2021. "Two-Stage Stochastic Model to Invest in Distributed Generation Considering the Long-Term Uncertainties" Energies 14, no. 18: 5694. https://doi.org/10.3390/en14185694

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop