Next Article in Journal
Exploring Socioeconomic Implications of Time-of-Use Electricity Pricing on Residential and Electric Mobility Sectors in Developing Countries
Next Article in Special Issue
From Physical Grids to Cyber-Energy Digital Twins: Modeling Power System Components for Cyberattack Assessment
Previous Article in Journal
What Shapes Regulated Electricity Contract Prices in a Hydro-Thermal Power System? Evidence from Colombia Using Quantile Regression and Autoencoders
Previous Article in Special Issue
Safety in the Operation of Electrical Networks: Inertia Compensation as a Measure of Frequency and Voltage Stability
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Coordinated Optimization of Configuration and Control for Reversible Substations Equipped with Bidirectional Converter Devices Considering Life-Cycle Cost

School of Electrical Engineering, Southwest Jiaotong University, Chengdu 611756, China
*
Author to whom correspondence should be addressed.
Electricity 2026, 7(2), 52; https://doi.org/10.3390/electricity7020052
Submission received: 13 February 2026 / Revised: 31 March 2026 / Accepted: 28 May 2026 / Published: 4 June 2026
(This article belongs to the Special Issue Stability, Operation, and Control in Power Systems)

Abstract

The growing demand for energy-efficient urban rail transit has led to the increasing deployment of reversible substations (RS) in traction power supply systems. These substations, equipped with bidirectional converter devices (BCDs), involve high initial costs and complex parameter optimization challenges. This paper presents a coordinated optimization method for BCD-equipped RS using a two-layer model. In the upper layer, the model determines the siting of RS and the capacity of BCD to minimize life-cycle cost (LCC). In the lower layer, it adjusts the control parameters of BCDs to reduce annual operating cost. An improved salp swarm algorithm (ISSA), incorporating Tent chaotic mapping and Levy flight, is developed to solve the model. A case study based on an 18.2 km subway line shows that the optimized configuration reduces overall cost by 5.12% and electricity cost by 10.53% compared with a conventional rectifier system. Moreover, it achieves a 1.19% reduction in electricity cost over a system with fixed control parameters, while maintaining rail potential and catenary voltage within safe limits. These findings demonstrate that the proposed method strikes an effective balance between initial investment and long-term operational benefits, contributing to improved energy efficiency and economic performance.

1. Introduction

Urbanization is accelerating, and the urban population is growing continuously. Urban rail transit, characterized by large capacity and high efficiency, has become an indispensable component of the modern urban public transport system [1,2,3]. However, the accompanying energy consumption and environmental impact issues have grown increasingly prominent. Thus, the green and low-carbon operation of rail transit has emerged as a key problem that the industry urgently needs to resolve [4]. As the energy artery of subway operations, the traction power supply system accounts for more than 50% of the subway’s total energy consumption [5].
Traditional DC traction power supply systems are typically equipped with diode rectifier units (RU), enabling only unidirectional energy flow [6]. When a large amount of regenerative energy generated by braking trains cannot be promptly absorbed by adjacent traction trains on the line, the catenary voltage will rise. Once the catenary voltage exceeds the threshold, the excess energy can only be dissipated as heat through braking resistors [7]. This not only results in enormous energy waste but also increases the burden of tunnel ventilation and heat dissipation [8]. Meanwhile, the severe catenary voltage fluctuations induced thereby pose a threat to the operational safety of both trains and the power supply system.
Two primary technical paths exist to enhance regenerative energy utilization and reduce system energy consumption: optimizing train operation strategies [9,10,11] and adopting energy-saving equipment [12,13,14]. For train operation strategy optimization, existing research focuses on two core dimensions: single-train energy-saving driving and multi-train timetable coordination [15]. The former targets source reduction of traction energy demand. It optimizes the train’s speed-position trajectory and rationally schedules the timing of traction and coasting phases. The latter involves fine-tuning train headways or station dwell times. It achieves temporal overlap between the regenerative braking window of on-line trains and the traction current-taking window of adjacent trains [16]. This enhances the real-time utilization of regenerative energy [17].
However, such control methods are often subject to multiple rigid constraints in practical engineering. For instance, timetable formulation must first meet passenger flow demands across different time periods [18]. This leaves extremely limited margin for energy-saving adjustments. Additionally, actual train operation is prone to uncertain disturbances. These include passenger flow fluctuations and temporary speed limits [19]. As a result, maintaining the preset “traction-braking” coordination during long-term dynamic operation becomes challenging. This presents significant challenges to the precise implementation of optimization schemes.
Compared with the complex optimization of operation strategies, configuring energy-saving equipment in the traction power supply system offers a more direct solution. Current energy-saving equipment is mainly categorized into energy storage type [20,21] and energy feedback type [22,23,24]. Ref. [25] incorporates energy storage systems into the traction power supply system, thereby achieving large-scale and efficient utilization of regenerative braking energy. Ref. [26] summarizes the applications of photovoltaic power in different types of traction power supply systems and analyzes critical issues such as power quality. Ref. [27] enables energy-efficient operation of traction power supply systems with the integration of photovoltaic generation. Ref. [28] puts forward a bi-level optimization model for the capacity configuration of photovoltaic-energy storage systems, which revises the system capacity parameters based on daily operational performance via an energy management strategy. Although on-board or ground-based energy storage devices can store regenerative energy through physical media, on-board energy storage significantly increases train weight and traction energy consumption [29]. Ground-based energy storage, on the other hand, faces issues such as high construction costs and large floor space requirements. Meanwhile, capacity attenuation with the number of charge–discharge cycles is another major factor limiting its widespread application [30].
Energy feedback type realizes bidirectional transmission between regenerative energy and the medium-voltage network by virtue of power electronic technology, with energy feedback devices and BCD being the research focuses at present. Ref. [23] proposes a joint optimization method based on RU and energy feedback devices for the optimal design of traction power supply systems with RS. Ref. [31] establishes an optimal siting and sizing model for traction power supply systems with RS, with the objectives of minimizing the investment cost of energy feedback devices and maximizing the utilization efficiency of regenerative braking energy. Ref. [32] performs optimization on the siting and control parameters of BCDs in substations to minimize the daily average cost but only optimizes the siting and droop rate of BCD. In terms of planning models for traction power supply systems, two-stage planning models have been designed from the perspectives of the “N-1” and life-cycle cost optimization [33]. In addition, integrated planning models suitable for traction power supply systems have been constructed by combining multi-energy systems including electricity, gas, heat, and photovoltaic power [34]. Meanwhile, intelligent optimization algorithms such as the improved genetic algorithm [31], dual-population fusion algorithm [32], and grey wolf optimizer [35] have been widely adopted in the planning and operation of traction power supply systems, owing to their advantages of requiring no model linearization and possessing strong global search ability.
Unlike energy storage equipment, BCDs do not require additional energy storage media and can directly achieve real-time energy conversion and transmission, enabling energy sharing between substations [36,37]. The core component of the BCD is a three-phase voltage-source PWM rectifier. Due to its limited individual power rating, it cannot directly replace megawatt-level RU. Therefore, capacity-upgrading techniques are required in practical engineering applications. Three-level topologies and power device paralleling can be adopted to equivalently increase the converter capacity. However, three-level topologies introduce higher structural complexity and potentially compromise system reliability. Direct device paralleling tends to cause severe circulating currents that degrade operational stability. At present, the scheme based on paralleling with isolation transformers is widely adopted, as shown in Figure 1.
To clearly illustrate the operating mechanism of the BCD-equipped RS system, Figure 2 presents the architecture and energy flow diagram of the BCD-equipped RS traction power supply system.
As shown in Figure 2, with the introduction of BCD, the traditional unidirectional DC power supply network is transformed into a “source-network-train” coupled system with bidirectional energy flow capability. When train A on the line operates in braking mode and generates regenerative power Preg, this energy is first transmitted via the DC catenary to supply adjacent traction train B. Regenerative energy not absorbed by adjacent trains can flow into traction substations equipped with BCD. Taking RS1 as an example, PF denotes the feedback power flowing into RS1. Through the inversion technology of BCD, this DC energy is converted into AC power after accounting for partial equipment losses. This portion of energy can be utilized by other traction substations, station loads, lighting loads, etc., via the medium-voltage network. If the feedback energy cannot be fully absorbed, it may also flow back to the main substation PR, i.e., be fed back to the power grid. Energy fed back to the power grid is regarded as ineffective energy and cannot reduce cost.
Furthermore, the efficient operation of BCD relies on a droop control strategy [38], as depicted in the output characteristic curve at the top-left corner of Figure 1. The core principle is to establish a linear correlation between voltage and output current by setting the no-load voltage and droop rate. Specifically, when the catenary voltage is lower than Ud0, the converter operates in the rectification droop region, where the output current increases linearly with decreasing voltage to provide traction energy for trains. When the voltage is higher than Ud0, the converter switches to the inversion droop region, where the output current increases linearly with increasing voltage to feed regenerative energy back to the medium-voltage network [39]. However, existing studies often assume that converters have infinite capacity or ideal linear characteristics during modeling, ignoring the operational constraints of actual physical equipment. In reality, when the system power flow demand exceeds the rated capacity of the device, the control strategy of the BCD is forced to switch from the linear region to the constant power region.
In systems where traditional diode RUs coexist with BCD, the BCDs operate in parallel with RU. Under normal traction conditions, both RUs and BCDs supply power to the DC network. During regenerative braking, when the catenary voltage rises, the BCDs operate in inversion mode to feed excess energy back to the medium-voltage network, while the RUs remain inactive due to their unidirectional power flow characteristic. This cooperative operation ensures seamless integration with legacy setups without requiring additional control. When the no-load voltage of the RU is equal to that of the BCD, the output characteristic of the traction substation is shown in Figure 3.
Despite the significant advantages of BCDs, their high initial investment cannot be overlooked [40]. Affected by line gradients, station spacing, and traffic density, regenerative energy exhibits a distinct spatial heterogeneous distribution along the line. Blindly configuring BCDs uniformly in all substations maximizes the energy-saving rate. However, it inevitably leads to unbalanced equipment utilization. This drastically increases the LCC. Additionally, there exists a non-linear coupling between the site selection of RS and characteristic parameters of BCD: location and capacity determine the potential for energy recovery, while parameter configuration dictates the actual recovery efficiency and voltage stabilization effect. Although existing studies have explored converter parameters, there remains a lack of a comprehensive optimization method that can simultaneously consider equipment capacity determination, site selection, and control parameter coordination. Such a method is essential to achieve the optimal comprehensive system benefits at the minimum economic cost while ensuring the safe operation of the system.
Most existing studies have focused on the siting and capacity configuration of RS equipped with energy feedback devices, while research on the optimization of RS with BCD—advanced power electronic equipment capable of bidirectional power regulation for rectification and inversion—remains scarce. In addition, most existing studies target the renovation of existing lines, where traditional RUs still operate in parallel with energy feedback devices. As a high-performance power electronic device, BCD can realize both rectification and inversion simultaneously and offers significant advantages in energy utilization efficiency, DC-side voltage fluctuation suppression, and rail potential limitation [41]. Most existing studies focus on the retrofitting of existing lines and only optimize the siting and droop rate of BCD without considering the capacity sizing of BCD. Furthermore, there are few studies involving the coordinated optimization of both the no-load voltage and droop rate of BCD under different headways. Therefore, this paper focuses on newly built urban rail transit lines and adopts a traction power supply architecture consisting exclusively of BCD with no traditional RU. Planning-level decisions are made regarding the siting of RS and the capacity configuration of BCD. Meanwhile, the no-load voltage and droop rate of BCD are optimized at the operation level under different headways, thereby achieving deep coordination between planning and operation. The main contributions of this paper are summarized as follows:
  • A two-layer optimization model is constructed, where the upper-level objective is to minimize the LCC, and the lower-level objective is to minimize the annual operating cost. At the upper layer, the model makes discrete decisions on the site selection of RS and the capacity of BCD. At the lower layer, it continuously optimizes the control parameters of the devices for different departure intervals. A closed loop is formed through iterative feedback, realizing a comprehensive trade-off between initial investment costs and long-term operational benefits.
  • Aiming at the mixed variable types and non-convex nature of the optimization model, ISSA is proposed as a unified solver. The improvement measures include population initialization based on Tent chaotic mapping to enhance global exploration capability and the introduction of the Levy flight strategy to enhance the global exploration capability. The superiority of the improved algorithm is verified through standard test functions.
  • Comparative experiments and result analyses were conducted on a real-world subway engineering case, which validates the effectiveness of the proposed method in reducing the LCC, decreasing the system’s operating energy consumption, and maintaining power supply reliability.
The rest of this paper is organized as follows. The two-layer optimization model is described in detail in Section 2. Section 3 presents the improved optimization algorithm and its performance tests. In Section 4, the problem is addressed and discussed based on the data from an actual subway line. Finally, conclusions are drawn in Section 5.

2. Two-Layer Optimization Model of the BCD-Equipped RS Traction Power Supply System

This section establishes the two-layer coordinated optimization model as illustrated in Figure 4. Adopting a leader–follower game logic, this model decouples the problem into two subproblems: the upper-layer planning subproblem and the lower-layer operation subproblem.
The upper layer serves as the leader layer. Its global objective is the minimization of the system’s LCC. Its decision variables are discrete. On the premise of satisfying constraints such as the N-1 operating condition, it determines the optimal configuration scheme for the installation sites and rated capacities of BCD in the traction power supply system and transmits this scheme to the lower layer.
Acting as the follower layer, the lower layer targets the minimization of the annual operating energy consumption cost, based on the configuration scheme transmitted by the upper layer. This layer mainly deals with continuous decision variables: through AC-DC hybrid power flow calculation, it optimizes the no-load voltage and droop rate of the devices. While ensuring that the catenary voltage and rail potential remain within their safe thresholds, it feeds back the optimal operating cost to the upper-layer model.
The upper and lower layers form an iterative interaction until the LCC converges to an optimal stable value, thereby achieving the coordinated optimization of BCD configuration and control parameters and realizing the optimization of the system’s long-term comprehensive benefits.

2.1. Upper-Level Model

The upper-level model optimizes traction station locations and BCD capacities to minimize LCC, as shown in Equation (1).
min F ( X T S ) = C c o n + C c a p + C r e p + C m t + C e l e
where X T S is as shown in Equation (2).
X T S = x 1 , 1 x 1 , 2 x 1 , i x 2 , 1 x 2 , 2 x 2 , i x 3 , 1 x 3 , 2 x 3 , i
x 1 , i ϵ { 0 , L }  is defined as the position of the i-th station, and L is the total line length. x 2 , i ϵ { 0,1 } is defined as the siting decision variable for the i-th traction substation, where 1 represents being selected. x 3 , i ϵ [ S m i n , S m a x ]  is defined as the capacity of BCD at the i-th traction substation, meaningful only at x 2 , i = 1 . S m i n , S m a x are the lower and upper limits for capacity.
Furthermore, C c o n represents the civil engineering cost for traction or step-down substations. C c a p represents the investment cost for BCD in traction substations.   C m t represents the annual maintenance cost of the system, and C e l e represents the annual operating cost of the entire system.
  • Civil Engineering Cost;
C c o n = i = 1 N ( x 2 , i C R S + ( 1 x 2 , i ) C S S ) b ( 1 + b ) Y 1 ( 1 + b ) Y 1 1
where N is the number of stations in the system.   C R S is the civil engineering cost for a single traction substation. C s s is the civil engineering cost for a single step-down substation. b is the discount rate. Y 1 is the entire project cycle. The term b ( 1 + b ) Y 1 ( 1 + b ) Y 1 1 represents the capital recovery factor (CRF), which is used to convert the total one-time civil engineering investment into equivalent annual costs over the project lifecycle.
2.
BCD Investment Cost;
C c a p = i = 1 N ( x 2 , i ( C b a s e + x 3 , i C B C D ) ) b ( 1 + b ) Y 2 ( 1 + b ) Y 2 1
where   C b a s e is the base cost of BCD.   C B C D represents the unit capacity cost of BCD. Y 2 is the service life of the BCD. Similarly, the factor b ( 1 + b ) Y 2 ( 1 + b ) Y 2 1 is the CRF, applied to annualize the initial BCD investment cost over its service life, aligning the cost accounting with the time value of money.
3.
BCD Maintenance Cost;
C m t = i = 1 N ( x 2 , i q m t R C x 3 , i )
where  q m t   R C is the maintenance cost per unit capacity for BCD.
4.
System Annual Operating Cost;
P ( t ) = P T ( t ) P F ( t ) + P R ( t ) W = 0 T P ( t ) d t
P T ( t ) denotes the output power of the traction substation, P F ( t ) represents the feedback power of the traction substation, and P R ( t ) stands for the power fed back to the power grid through the main substation. P R ( t ) is difficult to utilize by the power grid, so this portion of energy is regarded as ineffective energy and cannot reduce the cost of the system. The instantaneous power consumed by the traction power supply system at time t, denoted as P ( t ) , can be derived. The energy consumption at a headway of T is W, as shown in Equation (6) [42].
C e l e = m = 1 M W m × h o u r m × C E
where M denotes the number of distinct headways. W m represents the system energy consumption for the respective headway. h o u r m stands for the annual operating hours corresponding to the respective headway, and C E denotes the electricity tariff per kilowatt-hour.
5.
Upper-Level Model Constraints;
Ω R S Ω S t a t i o n S min x 3 , i = 1000 D i S max , D i +
where  Ω R S represents the set of selected traction Station positions. Ω S t a t i o n is the set of all station positions. S m i n , S m a x are the upper and lower limit capacity constraints of BCD, and considering the standardized selection of power equipment, it is ensured that the selected capacity is the specification available in the market. The capacity of BCD is selected as an integer multiple of 1000 kVA within the upper and lower limit range.
In traction power supply systems, the rail serves as the return path for traction current. Due to its inherent impedance and the influence of stray currents, a ground potential difference is generated, known as rail potential. Excessively high rail potential can pose risks to personnel safety, damage equipment insulation, and accelerate corrosion of nearby metal structures caused by stray currents. An upper limit must be imposed on rail potential under normal operating conditions to ensure it does not exceed the safety threshold, thereby guaranteeing the operational safety and reliability of the system.
U R , s ( t ) U R max , t
where U R , s ( t ) are the rail potential at any time t, and U R m a x is the maximum allowable value of the rail potential.
In the planning and design of the traction power supply system, the “N-1” safe operation criterion must be satisfied. This criterion specifies that if any traction substation in the system fails and is out of service, the remaining substations shall have sufficient power supply capacity. They shall compensate for the power support lost due to the fault. This ensures the catenary voltage along the entire line is consistently maintained within the allowable range. It also guarantees the continuous and reliable operation of trains under various operating scenarios.
U T min U T , s ( p ) ( t ) U T max , t , p Ω R S
where  U T , s ( p ) ( t )  represent the catenary voltage at any time t after the p-th traction station exits operation, and [ U T i m n ,     U T m a x ] is the safe range of the catenary voltage.

2.2. Lower-Level Model

The configuration scheme provided by the upper-layer model is input to the lower-layer model. Based on the operating characteristics of BCD, the lower-layer model reduces the system’s energy consumption by optimizing the droop rate and no-load voltage for different headways, thereby finding the optimal annual operating cost. Accordingly, the mathematical description of the lower-layer model is as follows:
min f ( U B C D , k B C D ) = C e l e
where U B C D and k B C D are shown in the following formula:
U B C D = [ U B C D , 1 , U B C D , 2 , , U B C D , Z ] k B C D = [ k B C D , 1 , k B C D , 2 , , k B C D , Z ]
U B C D , i is the no-load voltage of BCD in the i-th traction substation, and k B C D , i denotes the droop rate of BCD in the i-th traction substation, while Z represents the total number of traction substations. Each control parameter must be adjusted within the engineering feasible range. Accordingly, the constraints on the decision variables of the lower-layer model are as follows:
U B C D min U B C D , i U B C D max 0 k B C D , i k B C D max
where U B C D m i n  and U B C D m a x represent the maximum and minimum values of the no-load voltage, and k B C D m a x is the maximum value of the droop rate.
Similarly, in the lower-level model, it is also necessary to ensure that the rail potential and the catenary voltage meet the safety operation constraints.
U R , s ( t ) U R max , t U T min U T , s ( t ) U T max , t
where U T , s ( t ) represents the values of the catenary voltage at any time t under normal operating conditions.

3. ISSA-Based Solution Strategy

The upper-layer decision variables include the location and capacity of traction substations, both of which are discrete variables. The upper layer transmits the configuration information of traction substations to the lower layer. Based on the configuration of traction substations and different headways, the lower layer obtains the optimal control parameters of BCD in each traction substation, so as to achieve the objective of minimizing the annual operating cost. The involvement of power flow simulation introduces nonlinearity and non-convexity into the problem. Therefore, ISSA and traction power supply system power flow simulator are adopted to solve the optimization model.

3.1. Improved SSA Algorithm

Salps are transparent barrel-shaped marine invertebrates that move and forage in a chain-like structure in the deep sea. Based on this biological behavior, scholar Seyedali Mirjalili et al. proposed the salp swarm algorithm (SSA) [43], which simulates the swarming behavior of salps during navigation and foraging in the ocean. When establishing the mathematical model, the salp swarm is divided into leaders and followers. Leaders are located at the head of the salp chain, responsible for global exploration and moving toward the food source. Followers move following the leaders, undertaking local exploitation to perform refined search around the leaders.
The leader’s position update formula is as follows:
y j i ( t + 1 ) = F j ( t ) + c 1 [ ( u b j l b j ) c 2 + l b j ] , c 3 0.5 F j ( t ) c 1 [ ( u b j l b j ) c 2 + l b j ] , c 3 0.5
where  y j i ( t + 1 ) denotes the position of the i-th leader in the j-th dimension at the t + 1 iteration,   F j ( t ) represents the position of the food source, and u b j ,   l b j are the upper bound and lower bound in the j-th dimension, respectively. The control parameters   c 1 ,   c 2 are random numbers generated within the interval [ 0,1 ] . The formula for calculating c 1 is given as follows:
c 1 = 2 e ( 4 t / R ) 2
where  R denotes the maximum number of iterations. The position update of the followers is given as follows:
y j i ( t + 1 ) = 0.5 ( y j i 1 ( t ) + y j i ( t ) )
To enhance the search capability of the SSA, avoid falling into local optima, and explore a broader search space, this paper incorporates population initialization based on the Tent map and the Levy flight strategy into the SSA, aiming to improve the algorithm’s search performance.
  • Population Initialization Based on the Tent Map
Pseudorandom number generators (PRNGs) are the primary method for generating initial populations in most swarm intelligence algorithms, capable of covering promising regions in the search space [44]. A chaotic number generator is a type of random number generator based on chaotic technology; chaotic maps can replace pseudorandom number generators to generate chaotic numbers with inherent chaotic characteristics. Population initialization using chaotic sequences influences the entire process of the algorithm [45]. The Tent chaotic map exhibits excellent traversal uniformity and high sensitivity to initial values. It can efficiently cover all regions of the solution space without redundant traversal. Its topological mixing property generates a well-distributed, highly diverse initial population in the early iteration stage. This prevents individuals from clustering in local areas. It lays a solid foundation for subsequent global search. In this paper, the population is initialized based on the Tent chaotic map, whose mathematical expression is given as follows:
v j + 1 i = μ v j i , v j i < 0.5 μ ( 1 v j i ) , v j i 0.5 y j i ( 1 ) = ( u b j l b j ) v j i + l b j
where μ ( 0 , 2 ] and is the chaotic parameter. The larger the μ  is, the more chaotic the system will be. It is set as 2. v j i  is the chaotic sequence in [0,1].
2.
Levy Flight Strategy
The Levy flight strategy is a type of random walk strategy that simulates the non-Gaussian random walk pattern adopted by certain organisms in nature during foraging or migration [46]. Its step size distribution follows the Levy distribution, characterized by the alternation of short-distance and long-distance step sizes, and it is a probability distribution with heavy-tailed characteristics [47]. Benefiting from its heavy-tailed step distribution, the Levy flight performs frequent small-scale local exploitation with high probability, while generating rare long-distance jumps with a certain probability. This mechanism allows the algorithm to escape from local optima through large mutation steps once trapped in a limited region and quickly moves toward unexplored areas in the solution space. Thus, it effectively balances local exploitation and global exploration and strengthens the ability to jump out of local optimal solutions. The mathematical expression of the Levy flight strategy is as follows:
σ u = Γ ( 1 + α e v y ) sin ( π α e v y / 2 ) Γ ( ( 1 + α e v y ) / 2 ) × α e v y × 2 ( α e v y 1 ) / 2 , σ r = 1 L e v y = 0.01 ω r 1 / α e v y
where ω is a normally distributed random number following  N ( 0 , σ u 2 ) , and r is a normally distributed random number following  N ( 0 , σ r 2 ) .   α e v y ( 0,2 ] , the smaller its value, the heavier the tail of the distribution, the higher the probability of extremely large step sizes, and the more dispersed the distribution. The commonly used value α e v y = 1.5    can achieve a good balance between exploration (large jumps) and exploitation (small-step movements). After introducing the Levy flight strategy, the updated position formula for the leaders is given as follows:
y j i ( t + 1 ) = F j ( t ) + c 1 [ ( u b j l b j ) L e v y + l b j ] , c 3 0.5 F j ( t ) c 1 [ ( u b j l b j ) L e v y + l b j ] , c 3 0.5
The procedure of ISSA is as follows:
(1)
Population Initialization Based on the Tent Map: Initialize a salp swarm based on Equation (19) and the upper/lower bounds.
(2)
Calculate Initial Fitness: Compute the fitness value of each individual in the salp swarm.
(3)
Select the Food Source: Sort the salp swarm according to the magnitude of fitness values and set the position of the top-ranked individual as the current food source position.
(4)
Select Leaders and Followers: After determining the food source position, regard the first half of the sorted swarm as leaders and the second half as followers.
(5)
Position Update: Update the positions of leaders using Equation (20) improved by the Levy flight strategy, and update the positions of followers using Equation (17).
(6)
Re-calculate Fitness: Compute the fitness of the updated swarm. Compare the fitness value of each updated salp individual with that of the current food source to redetermine the food source position.
(7)
Repeat Steps (4)–(6) until a certain number of iterations is reached or the fitness value meets the required standard. Finally, output the current food source position as the estimated position of the target.

3.2. Comparison of Optimization Methods

To evaluate the performance of the ISSA, this paper conducts a comparative analysis of the search capability and iteration speed of the ISSA, SSA, and PSO. Specifically, 3 unimodal functions and 3 multimodal functions are selected as the test benchmark functions. The test benchmark functions are listed in Table 1, and the test results of different algorithms on these benchmark functions are presented in Figure 5 and Table 2. The mean value and variance are calculated using the fitness value obtained from the last 100 iterations of the algorithm. The convergence iteration count refers to the number of iterations required for the value of the objective function to reach 10−3.
Unimodal functions are mainly used to evaluate the computational accuracy and convergence speed of the algorithm, while multimodal functions are mainly adopted to assess its global optimization capability. The results of numerical experiments show that ISSA outperforms the other two algorithms in terms of mean value, variance, and convergence speed.

3.3. Optimization Process

To achieve the coordinated optimization of configuration and control and ensure that the proposed scheme satisfies the operational constraints under both normal and fault operating conditions, this paper constructs a two-layer closed-loop solution process as illustrated in the figure below. This process takes LCC as the upper-layer evaluation index and regards the minimization of annual operating cost as the lower-layer optimization objective. It adopts ISSA as the unified solver and finally outputs the configuration scheme with the minimum life-cycle cost, as well as the optimal control parameters for each departure interval under this configuration scheme. The process is shown in Figure 6.
The main steps are as follows:
Step 1: First, input the basic parameters of the line and trains, and define the operation scenario set, constraints, and boundaries.
Step 2: In the upper-level model, the ISSA algorithm is invoked, with the upper-level iteration number set as I and the population size as K, to generate an initial planning scheme that includes station selection and capacity configuration.
Step 3: For the planning scheme, verify the rail potential under normal operating conditions and the catenary voltage under N-1 operating condition, in accordance with the system’s maximum operational capacity. Discard the planning scheme if the verification fails; proceed to the next step if the verification is passed.
Step 4: Based on the validated planning scheme, with the objective of minimizing the annual operation cost, the ISSA algorithm is invoked again, where the lower-level iteration number is set as G and the population size as P. The control parameters of BCDs for each headway are subsequently optimized.
Step 5: Calculate the LCC based on the planning scheme provided by the upper layer and the minimum annual operating cost obtained by the lower layer, then judge whether the maximum number of iterations has been reached. If not, return to Step 2; if yes, output the optimal planning scheme and the corresponding control parameters.

4. Case Analysis

To verify the effectiveness of the two-layer optimization model and its corresponding solution algorithm proposed in this paper, which is based on LCC minimization, a real urban rail transit line is selected in this section for simulation analysis. This section is structured as follows: First, the basic parameters and simulation parameters of the case line are introduced. Second, the optimal configuration scheme and control parameters of the traction power supply system are presented. Finally, safety constraint verification, energy consumption analysis and economic analysis are performed on the obtained scheme.

4.1. System Simulation Parameters

There are eight station locations along the actual line, with their specific positions given in Table 3. Traction substations can only be sited at these station locations. The total length of the line is 18.2 km, and its overall layout is shown in Figure 7. The line adopts a typical configuration, where the main substation supplies power to each traction substation via the medium-voltage network.
The train is configured with a formation of 4 motor cars and 2 trailer cars, and its key performance parameters as well as partial electrical parameters of the power supply system are presented in Table 4. These parameters serve as the fundamental basis for conducting traction calculations and power supply calculations.
The optimization model is formulated with the objective of minimizing the LCC, and the key economic parameters involved are presented in Table 5.
The specific operational parameters of the optimization algorithm are presented in Table 6.

4.2. System Simulation Results

Due to the differences in passenger flow density across different periods, in accordance with the short-term, medium-term, and long-term operation plans, the distribution of different headways over the entire project cycle is statistically analyzed, as illustrated in Figure 8. The annual operation cost is calculated on the basis of the energy consumption and frequency distribution corresponding to each headway.
The upper-level model is formulated with the objective of minimizing the life-cycle cost, optimizing the traction substation locations and BCD capacities accordingly. The iteration process of the upper-level optimization model is illustrated in Figure 9: the objective value is continuously improved with the increase in the number of iterations, the optimal solution can be obtained at approximately 59 iterations, and the final planning scheme is presented in Table 7.
The lower-level model is formulated with the objective of minimizing the annual operation cost. Two typical headways are selected for analysis, namely, the densest headway and the headway with the highest occurrence frequency. Their iteration processes and control parameters are illustrated in Figure 10 and Figure 11, respectively.

4.3. Result Analysis

4.3.1. Power Supply Capacity and Rail Potential Analysis

Rail potential is one of the key parameters affecting the design of the traction power supply system. It is required that the maximum absolute value of rail potential across the entire line does not exceed 120 V. To verify whether the proposed configuration scheme satisfies the rail potential constraint, the headway corresponding to the maximum operational capacity required by the system is adopted for analysis. The distribution of rail potential is illustrated in Figure 12. It can be seen that the maximum absolute value of rail potential is approximately 91 V during train operation, which satisfies the constraint conditions.
The catenary voltage fluctuation range of the DC 1500 V traction power supply system shall be within 1000 V to 1800 V. To verify the power supply capacity of the optimization scheme, power flow calculations are performed under the N-1 condition. The catenary voltage is illustrated in Figure 13, with its minimum value being approximately 1288 V. This indicates that the system can still maintain its power supply capacity under the N-1 condition.

4.3.2. Energy Consumption Analysis

Case1 refers to the traditional full rectifier scheme, which only enables unidirectional energy flow, with a portion of the regenerative braking energy dissipated through brake resistors. The base cost of RU is set at 0.2 million CNY, with the unit capacity cost being 150 CNY per unit of capacity. Case2 is the BCD-equipped RS scheme with fixed control parameters, which is optimized via the upper-level model yet features unadjusted control parameters. Case3 is the BCD-equipped RS optimized by the bi-level model. The output energy, feedback energy of traction substations, and the redelivered energy from the main substation for the three schemes are statistically summarized, as presented in Figure 14. Case1 yields the lowest output energy from traction substations, which is because more regenerative braking energy can be transmitted on the DC side, leading to a greater amount of energy being directly utilized mutually between trains. For Case2 and Case3, the regenerative braking energy can be fed back to the medium-voltage network and supplied to step-down loads for utilization. In accordance with Equation (6), Case3 achieves the lowest energy consumption, which is calculated as the output energy minus the feedback energy plus the redelivered energy from the main substation.
Taking the 133s headway as an example, the output energy of the traction substation for Case 1 is 8101 kWh. For Case2, the output energy is 8396 kWh, the feedback energy is 672 kWh, and the redelivered energy from the main substation is 69 kWh, with the energy calculated in accordance with Equation (6) being 7793 kWh. For Case3, the output energy is 9093 kWh, the feedback energy is 1473 kWh, and the redelivered energy from the main substation is 72 kWh; the energy calculated in accordance with Equation (6) is 7692 kWh. The energy saving rate of Case3 relative to Case2 reaches 1.30%, and that relative to Case 1 stands at 5.05%.
Figure 15 presents a comparison of the DC-side losses and device losses between Case2 and Case3, while Figure 16 shows the maximum and minimum values of the catenary voltage as well as the proportion of the feedback energy to the regenerative braking energy. After the optimization of control parameters, the DC-side losses are reduced, whereas the device losses are increased. The reasons for the reduction in DC-side losses include the following: first, the overall network voltage of the system is raised after the optimization of control parameters, leading to a decrease in energy transmission losses; second, more regenerative braking energy is fed back to the medium-voltage network for reutilization with the optimized control parameters, and less energy is transmitted on the DC side, thus resulting in lower losses accordingly. Although the feedback energy will increase device losses, the devices feature a higher efficiency, and the losses incurred by the transmission of the same amount of energy on the DC side are higher than the device losses. Hence, the energy flow trend is that more regenerative braking energy is fed back to the medium-voltage network on the premise that the feedback energy can be accommodated.
Taking the 277 s headway as an example, the DC-side losses of Case2 are 43.9 kWh higher than those of Case3, while its device losses are 8.6 kWh lower; the proportions of feedback energy to regenerative braking energy for the two cases are 33% and 51%, respectively. As shown in Figure 12, the energy saving amount of Case3 relative to Case 2 at the 277 s headway is approximately 34 kWh. Since the energy fed back to the main substation is nearly identical under the two cases, the energy savings are highly consistent with the reduction in total power losses.

4.3.3. Economic Performance

Figure 17 presents the cost results of three different cases. It can be seen from the figure that the proposed optimization model yields a system configuration scheme with a lower LCC.
The life-cycle cost of Case3 is 37.957 million CNY per year, of which the electricity cost is 27.210 million CNY per year. Case2 and Case3 adopt the same configuration scheme, with the difference that Case3 optimizes the control parameters of BCD, resulting in a 1.19% reduction in electricity cost, which verifies the effectiveness of the lower-level model in optimizing the annual operation cost. Compared with Case1, the other cost of Case3 increases by 1.154 million CNY per year due to the higher BCD cost. However, BCD significantly reduces the operating energy consumption of the system, leading to a 3.201 million CNY per year reduction in electricity cost. Consequently, the total cost is reduced by 2.047 million CNY per year, accounting for approximately 5.12%.

5. Conclusions

A cooperative optimization method for the configuration and control of a traction power supply system with RS is proposed in this paper. It is designed to target the BCD-equipped RS traction power supply system; comprehensively consider the investment, maintenance, and operation costs; and adopt the ISSA algorithm to solve for the optimal configuration scheme with the minimum life-cycle cost and the optimal control parameters of BCD.
A simulation is carried out based on an actual metro line, and case analysis results demonstrate that the optimized scheme achieves an annual reduction of 5.12% in the comprehensive cost in comparison with the full rectifier system scheme, with a 10.53% decrease in electricity cost in particular. In contrast to the BCD-equipped RS system with fixed control parameters, it realizes a 1.19% annual reduction in electricity cost. Although the BCD-equipped RS traction power supply system leads to an increase in the initial investment cost, by virtue of the inverter technology of BCDs and the optimization of their control parameters, energy is fed back into the medium-voltage network, and DC-side losses are reduced, thereby achieving a remarkable improvement in the operational performance of the metro system.
The coordinated optimization method for the configuration and control of BCD-equipped RS proposed in this paper is an optimization scheme targeting the scenario of a newly built single urban rail transit line. Urban rail transit involves a complex traction power supply scenario with multi-line interconnection. Meanwhile, since BCDs can effectively improve the energy-saving performance of the system, the siting and sizing of BCDs are also of great significance for the renovation and upgrading of existing lines. In future research, we will establish an optimization model applicable to the complex network topology of urban rail transit systems that can also meet the engineering requirements of existing line renovation, so as to further expand the application scope of the relevant research.

Author Contributions

Writing—original draft, software, investigation, methodology, validation, data curation, J.W.; supervision, conceptualization, writing—review and editing, resources, W.L.; investigation, methodology, formal analysis, validation, J.Z.; software, visualization, data curation, formal analysis, X.Z.; validation, data curation, writing—review and editing, resources, D.X. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors on request.

Acknowledgments

During the preparation of this manuscript, the authors used ChatGPT-4 for the purposes of language polishing. The authors have reviewed and edited the output and take full responsibility for the content of this publication.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

The following abbreviations are used in this manuscript:
RSReversible substations
BCDBidirectional converter device
LCCLife-cycle cost
ISSAImproved salp swarm algorithm
RURectifier unit
CRFCapital recovery factor
SSASalp swarm algorithm
PRNGsPseudorandom number generators

References

  1. Liu, Y.; Yang, Z.; Wu, X.; Sha, D.; Lin, F.; Fang, X. An Adaptive Energy Management Strategy of Stationary Hybrid Energy Storage System. IEEE Trans. Transp. Electrif. 2022, 8, 2261–2272. [Google Scholar] [CrossRef] [Scilit]
  2. Wei, L.; Ying, L.; Jian, Z. Unified AC/DC power supply calculation taking into account urban rail inverter feedback devices. Trans. China Electrotech. Soc. 2019, 34, 4381–4391. [Google Scholar] [CrossRef]
  3. Zhao, X.-H.; Ke, B.-R.; Lian, K.-L. Optimization of train speed curve for energy saving using efficient and accurate electric traction models on the mass rapid transit system. IEEE Trans. Transp. Electrif. 2018, 4, 922–935. [Google Scholar] [CrossRef] [Scilit]
  4. Barkenbus, J.N. Eco-driving: An overlooked climate change initiative. Energy Policy 2010, 38, 762–769. [Google Scholar] [CrossRef] [Scilit]
  5. Yang, X.; Li, X.; Ning, B.; Tang, T. A survey on energy-efficient train operation for urban rail transit. IEEE Trans. Intell. Transp. Syst. 2015, 17, 2–13. [Google Scholar] [CrossRef] [Scilit]
  6. Zhang, G.; Qian, J.; Zhang, X. Application of a high-power reversible converter in a hybrid traction power supply system. Appl. Sci. 2017, 7, 282. [Google Scholar] [CrossRef] [Scilit]
  7. Khodaparastan, M.; Mohamed, A.A.; Brandauer, W. Recuperation of regenerative braking energy in electric rail transit systems. IEEE Trans. Intell. Transp. Syst. 2019, 20, 2831–2847. [Google Scholar] [CrossRef] [Scilit]
  8. González-Gil, A.; Palacin, R.; Batty, P. Sustainable urban rail systems: Strategies and technologies for optimal management of regenerative braking energy. Energy Convers. Manag. 2013, 75, 374–388. [Google Scholar] [CrossRef] [Scilit]
  9. Gu, Q.; Tang, T.; Ma, F. Energy-efficient train tracking operation based on multiple optimization models. IEEE Trans. Intell. Transp. Syst. 2015, 17, 882–892. [Google Scholar] [CrossRef] [Scilit]
  10. Liu, K.; Wang, X.; Qu, Z. Train operation strategy optimization based on a double-population genetic particle swarm optimization algorithm. Energies 2019, 12, 2518. [Google Scholar] [CrossRef] [Scilit]
  11. Su, S.; Li, X.; Tang, T.; Gao, Z. A subway train timetable optimization approach based on energy-efficient operation strategy. IEEE Trans. Intell. Transp. Syst. 2013, 14, 883–893. [Google Scholar] [CrossRef] [Scilit]
  12. Barrero, R.; Tackoen, X.; Van Mierlo, J. Stationary or onboard energy storage systems for energy consumption reduction in a metro network. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2010, 224, 207–225. [Google Scholar] [CrossRef] [Scilit]
  13. De La Torre, S.; Sánchez-Racero, A.J.; Aguado, J.A.; Reyes, M.; Martínez, O. Optimal sizing of energy storage for regenerative braking in electric railway systems. IEEE Trans. Power Syst. 2014, 30, 1492–1500. [Google Scholar] [CrossRef] [Scilit]
  14. Tzeng, Y.S.; Wu, R.-N.; Chen, N. Electric network solutions of DC transit systems with inverting substations. IEEE Trans. Veh. Technol. 1998, 47, 1405–1412. [Google Scholar] [CrossRef]
  15. Lin, F.; Liu, S.; Yang, Z.; Zhao, Y.; Yang, Z.; Sun, H. Multi-train energy saving for maximum usage of regenerative energy by dwell time optimization in urban rail transit using genetic algorithm. Energies 2016, 9, 208. [Google Scholar] [CrossRef] [Scilit]
  16. Scheepmaker, G.M.; Goverde, R.M.; Kroon, L.G. Review of energy-efficient train control and timetabling. Eur. J. Oper. Res. 2017, 257, 355–376. [Google Scholar] [CrossRef] [Scilit]
  17. Yu, H.; Zhang, G.; Wang, R.; Yang, J.; Xiong, W.; Wei, W. An online energy optimization method for urban rail flexible traction power supply system based on spatiotemporal matching of train power. IEEE Trans. Transp. Electrif. 2024, 10, 8656–8670. [Google Scholar] [CrossRef] [Scilit]
  18. Hu, Y.; Li, S.; Wang, Y.; Zhang, H.; Wei, Y.; Yang, L. Robust metro train scheduling integrated with skip-stop pattern and passenger flow control strategy under uncertain passenger demands. Comput. Oper. Res. 2023, 151, 106116. [Google Scholar] [CrossRef] [Scilit]
  19. van der Kooij, R.B.; Landmark, A.D.; Seim, A.A.; Olsson, N.O. The effect of temporary speed restrictions, analyzed by using real train traffic data. Transp. Res. Procedia 2017, 22, 580–587. [Google Scholar] [CrossRef] [Scilit]
  20. Ahmad, S.; Saeed, M.; Guerrero, J.M.; Muniategui-Aspiazu, I.; Nuñez, G.; Larrazabal, I.; Briz, F. Priority-based dc-link voltage control for railway traction chains with onboard energy storage. IEEE Open J. Ind. Appl. 2024, 6, 1–14. [Google Scholar] [CrossRef] [Scilit]
  21. Domínguez, M.; Fernández-Cardador, A.; Fernández-Rodríguez, A.; Cucala, A.; Pecharromán, R.; Sánchez, P.U.; Cortázar, I.V. Review on the use of energy storage systems in railway applications. Renew. Sustain. Energy Rev. 2025, 207, 114904. [Google Scholar] [CrossRef] [Scilit]
  22. Fu, C.; Sun, P.; Wang, Q.; Feng, X. Energy-Efficient Control Optimization of Subway Train with Bidirectional Converter Substations. IET Intell. Transp. Syst. 2025, 19, e70065. [Google Scholar] [CrossRef] [Scilit]
  23. Xu, Q.; Liu, W.; Yang, Q.; Zhang, X.; Guan, H.; Deng, H.; Xiong, P. Bi-level optimal design for DC traction power supply system with reversible substations. IEEE Trans. Transp. Electrif. 2023, 10, 7488–7500. [Google Scholar] [CrossRef] [Scilit]
  24. Ge, Z.; Yang, Y.; Zhang, J.; Li, X.; Liu, W.; Zhan, X. Optimal capacity design of energy feedback system in urban rail considering duty classes. In Proceedings of the 2020 IEEE Vehicle Power and Propulsion Conference (VPPC), Gijon, Spain, 18 November–16 December 2020; pp. 1–4. [Google Scholar] [CrossRef] [Scilit]
  25. Li, Z.; Luo, Z.; Nan, D.; Tang, J. Power control strategy of railway hybrid energy storage system based on YNd transformer-multiport converter. Energy Storage Sci. Technol. 2024, 13, 4030. [Google Scholar] [CrossRef]
  26. Deng, W.; Dai, C.; Chen, W. Application of PV generation in AC/DC traction power supply system and the key problem analysis under the background of rail transit energy internet. Proc. CSEE 2019, 39, 5692–5702. [Google Scholar] [CrossRef]
  27. Gao, F.; Song, Z.; Gao, J.; Guo, X. Day-ahead scheduling of traction power supply system with photovoltaic and energy storage access. J. Shanghai Jiao Tong Univ. 2024, 58, 760–775. [Google Scholar] [CrossRef]
  28. Yang, J.; Feng, S.; Guo, H.; Liao, K.; Xiang, Y. Optimal configuration of photovoltaic and hybrid energy storage system capacity in multi-substation interconnected traction power supply system. J. Southwest Jiaotong Univ. 2025, 60, 1537–1549. [Google Scholar] [CrossRef]
  29. Wu, C.; Lu, S.; Xue, F.; Jiang, L.; Chen, M. Optimal sizing of onboard energy storage devices for electrified railway systems. IEEE Trans. Transp. Electrif. 2020, 6, 1301–1311. [Google Scholar] [CrossRef] [Scilit]
  30. Gao, Z.; Fang, J.; Zhang, Y.; Jiang, L.; Sun, D.; Guo, W. Control of urban rail transit equipped with ground-based supercapacitor for energy saving and reduction of power peak demand. Int. J. Electr. Power Energy Syst. 2015, 67, 439–447. [Google Scholar] [CrossRef] [Scilit]
  31. Liu, W.; Zhang, H.; Zhang, J.; Li, Y.; Pan, W.; Li, Q. Optimal siting and sizing for inverter feedback devices applied in urban rail transit. J. Southwest Jiaotong Univ. 2021, 56, 1355–1362. [Google Scholar] [CrossRef]
  32. Fu, C.; Sun, P.; Wang, Q.; Feng, X. Site and Characteristic Optimization of Retrofitted Bidirectional Converters in Subway Traction Substations Considering Integrated Cost. IEEE Open J. Intell. Transp. Syst. 2025, 6, 1412–1423. [Google Scholar] [CrossRef] [Scilit]
  33. Wang, S.; Wei, Y.; Ren, L.; Lin, Y.; Guo, X.; Li, X. Capacity planning method for continuous flexible AC traction power supply system based on optimal power flow. Energy 2025, 317, 134580. [Google Scholar] [CrossRef] [Scilit]
  34. Qiu, Y.; Li, Q.; Li, S.; Deng, Q.; Chen, W.; Benbouzid, M.; Gao, F. Lifecycle Collaborative Planning for Traction Power Supply Systems with Integrated Energy Access. IEEE Trans. Transp. Electrif. 2025, 11, 5055–5068. [Google Scholar] [CrossRef] [Scilit]
  35. Yu, D.; Wu, Z.; Wang, L.; Cao, Z.; Aliev, H. Energy-efficient dc power traction network systems for urban mass transportation: A comparative study of optimization algorithms. IEEE Access 2025, 13, 45653–45668. [Google Scholar] [CrossRef] [Scilit]
  36. Davari, M.; Mohamed, Y.A.-R.I. Robust droop and DC-bus voltage control for effective stabilization and power sharing in VSC multiterminal DC grids. IEEE Trans. Power Electron. 2017, 33, 4373–4395. [Google Scholar] [CrossRef] [Scilit]
  37. Hao, F.; Zhang, G.; Chen, J.; Liu, Z.; Xu, D.; Wang, Y. Optimal voltage regulation and power sharing in traction power systems with reversible converters. IEEE Trans. Power Syst. 2020, 35, 2726–2735. [Google Scholar] [CrossRef] [Scilit]
  38. Li, H.; Li, J.; Hu, Y.; Yang, T.; Zhu, Q. Intelligent control strategy for subway overhead line substation outputs based on controllable rectifiers. J. Power Electron. 2025, 25, 2005–2017. [Google Scholar] [CrossRef] [Scilit]
  39. Lin, S.; Huang, D.; Wang, A.; Huang, Y.; Zhao, L.; Luo, R.; Lu, G. Research on the regeneration braking energy feedback system of urban rail transit. IEEE Trans. Veh. Technol. 2019, 68, 7329–7339. [Google Scholar] [CrossRef] [Scilit]
  40. Liu, J.; Guan, B. Energy Management Strategy of Urban Rail Energy Storage System Considering Life Assessment of Train Converter. Electronics 2025, 14, 722. [Google Scholar] [CrossRef] [Scilit]
  41. Liu, W.; Zeng, J.; Ma, Q.; Zhang, J.; Xiong, P.; Qi, H. Calculation of collaborative power flow for urban rail traction power supply system with bidirectional converter device. J. Southwest Jiaotong Univ. 2022, 58, 1145–1153. [Google Scholar] [CrossRef]
  42. Zhang, J.; Liu, W.; Tian, Z.; Qi, H.; Zeng, J.; Yang, Y. Urban rail substation parameter optimization by energy audit and modified salp swarm algorithm. IEEE Trans. Power Deliv. 2022, 37, 4968–4978. [Google Scholar] [CrossRef] [Scilit]
  43. Mirjalili, S.; Gandomi, A.H.; Mirjalili, S.Z.; Saremi, S.; Faris, H.; Mirjalili, S.M. Salp Swarm Algorithm: A bio-inspired optimizer for engineering design problems. Adv. Eng. Softw. 2017, 114, 163–191. [Google Scholar] [CrossRef] [Scilit]
  44. Bikos, A.; Nastou, P.E.; Petroudis, G.; Stamatiou, Y.C. Random number generators: Principles and applications. Cryptography 2023, 7, 54. [Google Scholar] [CrossRef] [Scilit]
  45. Kazimipour, B.; Li, X.; Qin, A.K. A review of population initialization techniques for evolutionary algorithms. In Proceedings of the 2014 IEEE congress on evolutionary computation (CEC), Beijing, China, 6–11 July 2014; pp. 2585–2592. [Google Scholar] [CrossRef] [Scilit]
  46. Jandhyala, V.K.; Fotopoulos, S.B. Applications of random search methods to foraging in ecological environments and other natural phenomena–A review. Environmetrics 2018, 29, e2451. [Google Scholar] [CrossRef] [Scilit]
  47. Dipierro, S.; Giacomin, G.; Valdinoci, E. Analysis of the Lévy Flight Foraging Hypothesis in and Unreliability of the Most Rewarding Strategies. SIAM J. Appl. Math. 2023, 83, 1935–1968. [Google Scholar] [CrossRef] [Scilit]
Figure 1. Main circuit of the BCD.
Figure 1. Main circuit of the BCD.
Electricity 07 00052 g001
Figure 2. BCD-equipped RS traction power supply system architecture.
Figure 2. BCD-equipped RS traction power supply system architecture.
Electricity 07 00052 g002
Figure 3. Output characteristics of substation.
Figure 3. Output characteristics of substation.
Electricity 07 00052 g003
Figure 4. Two-level planning—Operation collaboration optimization model.
Figure 4. Two-level planning—Operation collaboration optimization model.
Electricity 07 00052 g004
Figure 5. Comparison of test functions for different algorithms.
Figure 5. Comparison of test functions for different algorithms.
Electricity 07 00052 g005
Figure 6. Two-layer Model Optimization Flowchart.
Figure 6. Two-layer Model Optimization Flowchart.
Electricity 07 00052 g006
Figure 7. Layout of the candidate positions.
Figure 7. Layout of the candidate positions.
Electricity 07 00052 g007
Figure 8. Frequency distribution of different headways.
Figure 8. Frequency distribution of different headways.
Electricity 07 00052 g008
Figure 9. Upper-level iteration process.
Figure 9. Upper-level iteration process.
Electricity 07 00052 g009
Figure 10. Lower-level iteration process.
Figure 10. Lower-level iteration process.
Electricity 07 00052 g010
Figure 11. Optimized control parameters for two typical headways.
Figure 11. Optimized control parameters for two typical headways.
Electricity 07 00052 g011
Figure 12. The distribution of rail potential under the maximum operating capacity.
Figure 12. The distribution of rail potential under the maximum operating capacity.
Electricity 07 00052 g012
Figure 13. Variation of Catenary Voltage under the “N-1” Condition.
Figure 13. Variation of Catenary Voltage under the “N-1” Condition.
Electricity 07 00052 g013
Figure 14. Comparison of Energy Consumption for Each Headway.
Figure 14. Comparison of Energy Consumption for Each Headway.
Electricity 07 00052 g014
Figure 15. Comparison of Losses for Each Headway.
Figure 15. Comparison of Losses for Each Headway.
Electricity 07 00052 g015
Figure 16. Maximum and Minimum Catenary Voltage of Traction Substations and Proportion of Feedback Energy Consumption for Each Headway.
Figure 16. Maximum and Minimum Catenary Voltage of Traction Substations and Proportion of Feedback Energy Consumption for Each Headway.
Electricity 07 00052 g016
Figure 17. Economic comparison.
Figure 17. Economic comparison.
Electricity 07 00052 g017
Table 1. Benchmark test functions.
Table 1. Benchmark test functions.
FunctionNameRangeOptimal Value
f ( x ) = i = 1 D x i 2 Sphere[−100, 100]0
f ( x ) = i = 1 D 1 [ 100 ( x i + 1 x i 2 ) 2 + ( x i 1 ) 2 ] Rosenbrock[−10, 10]0
f ( x ) = i = 1 D x i 2 Step[−100, 100]0
f ( x ) = i = 1 D [ x i 2 10 cos ( 2 π x i ) + 10 ] Rastrigin[−5.12, 5.12]0
f ( x ) = 20 exp 0.2 1 D i = 1 D x i 2 exp 1 D i = 1 D cos ( 2 π x i ) + 20 + e Ackley[−32.768, 32.768]0
f ( x ) = 418.9829 D i = 1 D ( x i sin ( x i ) ) Schwefel2.26[−500, 500]0
Table 2. Numerical test results.
Table 2. Numerical test results.
FunctionIndicatorsPSOSSAISSA
SphereMean value3.72 × 10−72.28 × 10−101.00 × 10−10
Variance7.61 × 10−153.28 × 10−202.41 × 10−50
Convergence iteration count44436559
RosenbrockMean value6.53 × 10−71.00 × 10−101.00 × 10−10
Variance02.41 × 10−502.41 × 10−50
Convergence iteration count41234588
StepMean value1.00 × 10−101.00 × 10−101.00 × 10−10
Variance2.41 × 10−502.41 × 10−502.41 × 10−50
Convergence iteration count5925522
RastriginMean value5.06 × 10−51.00 × 10−101.00 × 10−10
Variance9.51 × 10−102.41 × 10−502.41 × 10−50
Convergence iteration count39549180
AckleyMean value1.66 × 10−31.87 × 10−61.00 × 10−10
Variance4.29 × 10−104.15 × 10−122.41 × 10−50
Convergence iteration count1000745104
Schwefel 2.26Mean value2.55 × 10−52.55 × 10−52.55 × 10−5
Variance7.35 × 10−401.16 × 10−210
Convergence iteration count49244452
Table 3. Candidate position.
Table 3. Candidate position.
StationLocation (km)StationLocation (km)
Station10.505Station59.040
Station22.052Station612.410
Station34.411Station715.899
Station47.647Station816.813
Table 4. Relevant parameters.
Table 4. Relevant parameters.
Train ParametersValue
Weight (t)278.60
Length (m)118.9
Structural Speed (km/h)90
Auxiliary Power (kW)75
Maximum Acceleration (m/s2)1.2
Maximum Deceleration (m/s2)1.0
Network CharacteristicsValue
Catenary Resistance0.0173 Ω/km
Rail Resistance0.02 Ω/km
AC Side CharacteristicsValue
System voltage level110 kV
Short circuit capacity1500 MVA
Main substation rated capacity40 MVA
Table 5. Economic parameters.
Table 5. Economic parameters.
ItemSymbolValue
Project Cycle Y 1 30 years
Discount Rateb3%
Civil Engineering Cost of Reversible Substation C R S 16.5 million CNY
Civil Engineering Cost of Step-down Substation C s s 7.6 million CNY
Base Cost of BCD C b a s e 0.2 million CNY
Unit Capacity Cost of BCD C B C D 700 CNY/kW
Annual Maintenance Cost per Unit Capacity of BCD q m t   R C 30 CNY/kW
Service Life of BCD Y 2 15 years
Minimum Rated Capacity of BCD S m i n , 3000 kW
Maximum Rated Capacity of BCD S m a x 12,000 kW
Table 6. Algorithm parameters.
Table 6. Algorithm parameters.
ItemSymbolValue
Upper-layer Number of IterationsI100
Upper-layer Population SizeK10
Lower-layer Number of IterationsG250
Lower-layer Population SizeP10
Chaotic Map Parameter μ 2
Levy Flight Parameter α e v y 1.5
Table 7. Optimized configuration scheme.
Table 7. Optimized configuration scheme.
Reversible SubstationLocation (km)Capacity(kW)
RS10.516000
RS22.055000
RS34.416000
RS47.477000
RS512.419000
RS615.97000
RS716.829000
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Wu, J.; Liu, W.; Zhang, J.; Zhang, X.; Xia, D. Coordinated Optimization of Configuration and Control for Reversible Substations Equipped with Bidirectional Converter Devices Considering Life-Cycle Cost. Electricity 2026, 7, 52. https://doi.org/10.3390/electricity7020052

AMA Style

Wu J, Liu W, Zhang J, Zhang X, Xia D. Coordinated Optimization of Configuration and Control for Reversible Substations Equipped with Bidirectional Converter Devices Considering Life-Cycle Cost. Electricity. 2026; 7(2):52. https://doi.org/10.3390/electricity7020052

Chicago/Turabian Style

Wu, Jiayi, Wei Liu, Jian Zhang, Xiaodong Zhang, and Dingxin Xia. 2026. "Coordinated Optimization of Configuration and Control for Reversible Substations Equipped with Bidirectional Converter Devices Considering Life-Cycle Cost" Electricity 7, no. 2: 52. https://doi.org/10.3390/electricity7020052

APA Style

Wu, J., Liu, W., Zhang, J., Zhang, X., & Xia, D. (2026). Coordinated Optimization of Configuration and Control for Reversible Substations Equipped with Bidirectional Converter Devices Considering Life-Cycle Cost. Electricity, 7(2), 52. https://doi.org/10.3390/electricity7020052

Article Metrics

Back to TopTop