Next Article in Journal
Beauveria bassiana Ribotoxin (BbRib) Induces Silkworm Cell Apoptosis via Activating Ros Stress Response
Previous Article in Journal
Controlling Atmospheric Corrosion of Weathering Steel Using Anodic Polarization Protection Technique
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Investigating the Impact of Economic Uncertainty on Optimal Sizing of Grid-Independent Hybrid Renewable Energy Systems

1
Queensland Micro and Nanotechnology Centre, Griffith University, Nathan 4111, QLD, Australia
2
Faculty of Engineering, Kotelawla Defence University, Kandawala Estate, Ratmalana 10390, Sri Lanka
3
Department of Mechanical Engineering, Rajshahi University of Engineering & Technology, Rajshahi 6204, Bangladesh
4
Department of Physiology, College of Medicine and King Khalid University Hospital, King Saud University, Medical City, P.O. Box 2925, Riyadh 11461, Saudi Arabia
5
Institute of Mechanical Engineering, Warsaw University of Life Sciences, 02-787 Warsaw, Poland
6
Electrical Engineering Department, Faculty of Engineering, Minia University, Minia 61519, Egypt
7
Department of Electrical Engineering, Fuzhou University, Fuzhou 350116, China
*
Authors to whom correspondence should be addressed.
Processes 2021, 9(8), 1468; https://doi.org/10.3390/pr9081468
Submission received: 7 July 2021 / Revised: 4 August 2021 / Accepted: 12 August 2021 / Published: 23 August 2021
(This article belongs to the Section Energy Systems)

Abstract

:
One of the many barriers to decarbonization and decentralization of the energy sector in developing countries is the economic uncertainty. As such, this study scrutinizes economics of three grid-independent hybrid renewable-based systems proposed to co-generate electricity and heat for a small-scale load. Accordingly, the under-study systems are simulated and optimized with the aid of HOMER Pro software. Here, a 20-year average value of discount and inflation rates is deemed a benchmark case. The techno-economic-environmental and reliability results suggest a standalone solar/wind/electrolyzer/hydrogen-based fuel cell integrated with a hydrogen-based boiler system is the best alternative. Moreover, to ascertain the impact of economic uncertainty on optimal unit sizing of the nominated model, the fluctuations of the nominal discount rate and inflation, respectively, constitute within the range of 15–20% and 10–26%. The findings of economic uncertainty analysis imply that total net present cost (TNPC) fluctuates around the benchmark value symmetrically between $478,704 and $814,905. Levelized energy cost varies from an amount 69% less than the benchmark value up to two-fold of that. Furthermore, photovoltaic (PV) optimal size starts from a value 23% less than the benchmark case and rises up to 55% more. The corresponding figures for wind turbine (WT) are, respectively, 21% and 29%. Eventually, several practical policies are introduced to cope with economic uncertainty.

1. Introduction

Energy acts as the foremost ingredient of thriving macro- and micro-economies in the world. In spite of this crucial role of energy in the communities, there have been controversial views, discussions, and debates surrounding the way that energy is yielded. This is due to the fact that conventional methods of electricity generation have long caused major damages to the environment, accordingly leading to the deteriorating issue of climate change [1,2]. As such, viable alternative means and environmentally benign solutions of energy production, by which the detrimental impacts can be alleviated to a very low level, have been introduced and implemented over the past few decades [3,4]. Among several methods available to generate clean, sustainable, and renewable energy, wind turbine (WT) and photovoltaic (PV) systems have been the most appealing ones and have been applied worldwide in suitable regions, mostly owing to the merits of cost-effectiveness, zero-or low-carbon emissions, and mature industry [5,6,7,8,9]. Apart from the aforementioned benefits of utilizing renewables, all nations should consider that the global energy demand is projected to touch the value of 38,700 TWh by the year 2050 [10]. This colossal amount of required energy implies and urges that the exploitation of renewables is of utmost prominence and priority.
The main shortcoming of renewables is the inherent issue of intermittency which can considerably decline the reliability of renewable-based systems. Fortunately, the concept of hybrid renewable energy (HRE) solutions has solved the problem to a great extent. Besides, HRE systems may impose less costs compared to single-source energy generation systems [11,12,13]. Further, to raise the reliability and also lessen the power outage, they are usually coupled with energy storage units such as a diesel generator (DG), a battery, and a fuel cell (FC) [14]. Few critical drawbacks, such as high operational and maintenance cost and harmful effects to the environment, are associated with DG power plants [15,16]. Among two other above-mentioned backups, FC can constitute an environmentally sustainable solution if the required hydrogen (H2) is provided by renewable means.
One step towards the blueprint for energy security, decarbonization, decentralization of energy sector, fulfilment of the Paris Agreement emissions targets, and sustainable energy production is to electrify remote island regions using autonomous renewable-based power generation plants. Hence, if this step is taken, then the growth of the nation and high living standards of those areas can be guaranteed [17]. These places usually suffer from frequent power shortages and are very vulnerable to disruptions due to their far-off location and high dependency on fossil fuel power sites. Additionally, connecting them to the national grid will impose significant expenses linked to either capital or regular maintenance and review costs [18,19]. Therefore, harvesting renewable resources of energy existing in the vicinity of these communities can noticeably aid corresponding countries in terms of reaching sustainable energy development. However, optimal design of HRE systems will remain a big question which requires a careful and thorough investigation. In this regard, the very first step, and the most important, is to conduct the techno-economic feasibility studies in order to avert any losses and to minimize the potential risks [20].
In this study, three configurations for a grid-independent HRE system comprising PV, WT, renewable H2-based FC, renewable H2-based boiler, natural gas (NG)-fueled boiler, and biomass generator (BMG) are scrutinized to ascertain optimal sizing and their techno-economic performance for co-supplying a touristy village, Mesr in Isfahan province of Iran, with electricity and heat. To increase sustainability and efficiency of the proposed models, the excess electricity is sent to electrolyzer for generating H2. Then, during the times when solar and wind electricity cannot meet electric and thermal demands, this stored renewable H2 is utilized to react with oxygen (O2) for electricity generation. This transition occurs in a electrochemical process within FC-engaging electrodes and electrolytes, releasing water as a by-product [21]. This effective usage of the surplus electricity implies the necessity of adding FC to the system, otherwise a great deal of electricity would be dumped without ever being exploited [22]. Additionally, in each of other two proposed systems, it is supposed that boiler consumes renewable H2 or NG for meeting thermal energy demands. Furthermore, to comprehensively examine the available resources in the area, a HRE system, which includes a BMG, is investigated. Finally, among these three systems, the most suitable one, with respect to technical, economic, environmental, and reliability aspects, is selected to be further analyzed under economic uncertainty.
Due to the volatile nature of economy in developing countries, unpredictable high fluctuations are likely to happen in the discount rate and inflation. For this reason, the study looks into the effect of economic uncertainty on optimization and economics of the chosen system in such countries. To this end, the fluctuations in the nominal discount rate and inflation are considered based on a 20-year average from mid-2000 to mid-2020, as represented by Ref. [23], which are in the range of 15–20% and 10–26%, respectively. Figure 1 illustrates the waves of the nominal discount rate and inflation in Iran during the above-mentioned period.
The main contribution of this study is that the proposed approach to optimal unit sizing of an HRE system to be applied in remote rural areas under economic uncertainty, which is inherent mostly in under-developed countries, can be deployed by other similar nations with islands and far-off villages. Additionally, a rigorous survey of literature has indicated that the the impact of economic uncertainty on optimal unit sizing of HRE systems has not been explored, which means this work could be a marked contribution to the field. Thus, interested researchers can undertake the approach of this study (Figure 2) as a guideline to scrutinize the potential of electricity and heat co-generation in the nominated regions, as well as to optimally size the units when economy is volatile. The benefits of such a scheme include (I) making the remote places self-sufficient in energy generation, (II) decentralizing electricity coverage, and finally (III) accelerating decarbonization of energy sector set to meet the Paris Agreement targets.

2. Literature Review

In terms of incorporating economic uncertainty into the process of configuration of an off-grid HRE system, a thorough survey of literature has demonstrated that economic uncertainty has not yet been investigated for optimal sizing of units for electricity and heat co-generation. Nonetheless, some studies have examined the influence of uncertainty associated with other aspects of renewable-related projects; the most recent ones are as follows. The impact of economic policy uncertainties on energy-growth-emissions nexus was assessed for countries regarding the application of renewable and non-renewable energy resources [24]. Furthermore, the difference in the impact of economic policy uncertainty on the investment of traditional and renewable energy enterprises was studied by [25]. Uncertainties in wind velocity, solar radiation, water flow speed, load demand, and electricity price were investigated for planning a stand-alone renewable energy-based micro-grid [26]. Bouchekara et al. [27] utilized a multi-objective approach to optimally configure an HRE system consisting of PV, WT, and DG for a micro-grid under load uncertainty. Blazquez et al. [28] scrutinized how policy instruments would work under different market conditions when considering the impact of price volatility and uncertainty of investments. Ebrahimi et al. [29] explored the uncertainty of renewable energy resources on optimal design of a multiple form energy in the presence of electric vehicle charging stations and the impact of this.
Similarly, Li et al. [30] performed an economic analysis on micro-grids considering renewable energy uncertainty. In another research, a model was proposed for distributed generation expansion planning problem from the viewpoint of private investors considering uncertainties of renewable generations [31]. Mirzamohammadi et al. [32] also investigated the role of renewable resources uncertainty for energy supply planning for greenhouse farming. Further, the role of uncertainty in wind and solar power was evaluated for power grid peak shaving [33]. Optimal operation of a combined cooling, heating, and power micro-grid system was studied under the impact of wind power output uncertainty using an improved two-stage robust optimization model [34]. Likewise, the potential risk and benefit of complementary operation of a large PV/WT/hydropower system were assessed under the consideration of forecast uncertainty in wind and solar power [35]. Ezbakhe and Pérez-Foguet [36] introduced a modified multi-criteria decision-making technique to incorporate uncertainty of decision environments in the prioritization of alternatives for renewable energy planning. Fitiwi et al. [37] conducted an assessment on renewable energy utilization for the Irish power system under community acceptance policies considering the uncertainty of storage costs. Scott et al. [38] carried out a study on the role of long-term uncertainty in electricity market modelling for renewable energy support policy evaluation. There are other studies that consider uncertainty in different aspects of renewable-related projects, such as load demand uncertainty [39,40]; renewable energy resources uncertainty [41,42]; uncertainties of the inflow of the hydropower plant and the PV power output [43]; wind energy uncertainty [44]; uncertainty in the costs of renewable energy [45]; uncertainties of wind speed, solar radiation intensity, and power load [46]; and uncertainties of renewable energy production and load demand [47].
Since Hybrid Optimization Model for Electric Renewables (HOMER) software has proved applicability and reliability in simulation, analysis, and optimization of renewable power generation systems leading to precise results, it has been utilized in the past few years to explore HRE systems from the techno-economic-environmental perspective. Olatomiwa et al. [48] studied the viability of different configurations of PV, WT, battery, and DG units to be used in a villages in Nigeria using HOMER software. Considering total net present cost (TNPC), levelized cost of electricity (LCOE), and renewable fraction, the combination of PV/DG/battery was identified as the best architecture. In another research conducted in Nigeria, the techno-economic feasibility of a solar-based plant for powering a mobile base transceiver station was analyzed using HOMER. The results suggested a 10-kW PV, a 5.5-kW DG, and 64 units of Trojan battery. It also ended up saving 16.4 tons of CO2 per year in comparison with an autonomous DG plant [49]. Brenna et al. [50] utilized HOMER to assess the different integrations of PV, WT, hydro, DG, battery, and H2 for electrifying a rural area in Ethiopia. Isa et al. [51] proposed an on-grid PV/FC/ battery system for co-supplying electricity and heat to a hospital in Malaysia with a TNPC of $106,551, an LCOE of 0.091 $/kWh, and an emission reduction of 25,873 kg/yr. Singh and Baredar [52] studied the electricity generation potential via an off-grid system consisting of PV, FC, BMG, and battery. Singh et al. [53] employed HOMER to verify the results of optimal sizing of an HRE system which was obtained by swarm-based artificial bee colony and particle swarm optimization. The comparison proved that these three methods had close results as to the sizing of the components. Das et al. [54] explored the techno-economic feasibility of an HRE system using HOMER. The software was employed to compare PV/FC/battery and PV/battery systems with a benchmark of the current DG plant [55]. Khemariya et al. [56] used HOMER to evaluate a PV/FC/battery/electrolyzer system to electrify a village in India. Similarly, HOMER optimized a PV/BMG/DG/battery system considering different peak loads, energy demands, and grid availability [57]. Shahzad et al. [58] designed an integrated PV/BMG/battery system for the irrigation and residential applications in Pakistan. Furthermore, HOMER assessed the techno-economic feasibility of a grid-tied PV/WT/BMG system for electrifying a village in Pakistan [59]. Duman and Guler [60] explored the utilization of an autonomous PV/WT/FC plant to supply electricity for vacation homes in Turkey. HOMER revealed that the displacement of FC with batteries would turn the system more cost-effective. Moreover, stand-alone HRE systems were scrutinized using HOMER for a nursing home in Turkey [61]. Apart from those above-mentioned studies, these papers [62,63,64,65,66,67,68,69,70,71,72,73,74,75,76,77,78,79,80,81,82,83,84,85,86,87,88] also applied HOMER for different purposes, which are helpful in learning about the software and its practicality.

3. Geographical Specifications

Mesr village, also locally called Mesr desert, is located in the province of Isfahan and is surrounded by the Great Salt Desert. This remote area is situated at coordinates 34°04′ N and 54°48′ E, with an altitude of rough 800 m above the sea level [89]. According to the latest population and housing census conducted in 2016, the village has 41 households with 183 population [90]. By virtue of Mesr’s location, many national and international tourists visit this place every year. For this, in addition to the number of personal houses, there are a dozen traditional hotels to accommodate visitors, a healthcare center, a mosque, and a small school. After collecting the information about electricity demand from Isfahan Province Electricity Distribution Company, the daily average electricity load would be approximately 366 kWh. The reason why this village consumes this amount of energy is that the number of tourists visiting this touristy rustic area is high in several months of the year. Analyzing the figures and the common electricity-consuming devices, almost 163 kWh/d of electricity would be used for heating equipment, such as space heating, water heating, and cooking. The rest, which is 203 kWh/d, would be needed by other equipment and appliances, such as air conditioning, fan, bulbs, ironing, television, washing machine, dish washer, refrigerator, etc. Thus, two types of load, electric load and thermal load, are assumed in the proposed models.

4. Materials and Methods

HOMER Pro software was developed by the National Renewable Energy Laboratory (NREL) in the USA and has the ability to evaluate HRE systems in both modes of off-grid and on-grid [91]. This software has been extensively utilized because of its suitable accuracy and high speed for optimization [92] and is comparable to meta-heuristic optimization algorithms [53]. Hence, HOMER is applied to serve the purpose of this study.

4.1. Economic Analysis

The key economic criterion via which HOMER proposes optimal sizing of HRE systems and prioritizes different configurations is T N P C . The formula to compute T N P C reads as Equation (1) [93].
T N P C = C t o t a l , a n C R F ( i , n )
where C t o t a l , a n is designated to the total annualized cost of all equipment to be purchased and installed in the system. C R F , i , and n , respectively, represent the capital recovery factor, the real yearly discount rate, and the project lifetime. Equation (2) can evaluate the term expressed as the denominator of the above-mentioned relation [94]. HOMER also uses Equation (3) in order to project the real yearly discount rate in which i and f are, respectively, the nominal discount rate and yearly inflation [95].
C R F ( i , n ) = i × ( 1 + i ) n ( 1 + i ) n 1
i = i f 1 + f
The other prominent economic factor is the average price of generating one kWh of electricity via the designed system and is called L C O E , which can be obtained using Equation (4) [51].
L C O E = C t o t a l , a n E P r i m , A C + E P r i m , D C + E g r i d , E x
Here, E P r i m , A C and E P r i m , D C signify the total amount of alternating current (AC) primary load and that of direct current (DC) primary load met by the system within a year. Additionally, E g r i d , E x is the total amount of electricity which is exported to the local/national grid.
It is worth mentioning that another economic factor relatively important to the investors is the scrap value of the apparatus at the end of the project lifetime. This salvage value is directly contingent upon the remaining life of the nominated component holding a linear relation with a corresponding replacement cost. The relations are expressed by Equation (5) [51].
S v a l   =   C r e p   ×   n c o m n
where C r e p refers to the replacement cost of the component when its lifetime, n c o m , has finished.
The other economic output variable represented by HOMER is operating cost, equating to the annualized value of all costs and revenues except for the initial capital costs. Equation (6) is the relation to project operating cost [96].
C o p = C t o t a l , a n C t o t a l , i n i × C R F ( i , n )
where C t o t a l , i n i is designated to the total initial capital costs, which equates to the summation of costs of all equipment in HRE systems.

4.2. PV Modeling

Owing to the geographical location of Iran, the country sees approximately 300 sunny days within a year, due to which the total annual solar radiation can reach 2200 kWh [83]. This high potential of solar energy is ready and available to be exploited by PV systems in most parts of the country. To model PV arrays into renewable power generation systems, the output of PV is of high importance and needs to be calculated. HOMER software utilizes Equation (7) to project power output generated by PV [97].
P P V = Y P V × f P V ( G ¯ T G ¯ T , S T C ) [ 1 + α P ( T c T c , S T C ) ]
where Y P V and f P V , respectively, denote the nominal capacity of the PV generator and the derating or reduction factor available on the technical sheet of the product. The latter is applied by HOMER to simulate the real-world operating conditions and then to acquire the most reliable and precise results. G ¯ T signifies the amount of solar radiation reaching the surface of the PV panels, and G ¯ T , S T C represents the amount under the standard test environment. α P is designated to show the temperature coefficient of power. T c and T c , S T C are, respectively, the temperature of the PV cell and that at standard test environment. In order to predict the cell temperature, Equations (8) and (9) are used [97].
T α G T = η c G T + U L   ( T c     T α )
T c =   T α + G T ( τ α U L )   ( 1   η c τ α )
where τ and α are, respectively, transmittance of PV cover and the solar absorption of the PV panels. U L means the coefficient via which heat is transferred to the surrounding environment, and T α refers to the amount of the ambient temperature. Furthermore, η c is the electrical conversion efficiency of the PV panels. HOMER uses Equation (10) in order to measure the cell temperature [85]. It should be noted that, due to the difficulty of calculating the value of τ α U L , Equation (11) is utilized to substitute the aforementioned term with the measurable one. Moreover, the software presumes that the value of τ α in Equation (9) is 0.9 [96].
T c = T α + G T ( T c , N O C T T α , N O C T G T , N O C T )   ( 1 η c 0.9 )
τ α U L = T c , N O C T T α , N O C T G T , N O C T
where T c , N O C T is the temperature usually reported by the manufacturers and called the nominal operating cell temperature. This value is obtained under the conditions of no-load operating, η c = 0 , an ambient temperature of 20   , T α , N O C T = 20   , and an incident radiation of 800 W/m2, G T , N O C T = 800 W/m2.

4.3. WT Modeling

To capture the kinetic energy of air in motion, WT units are installed and then turn mechanical energy available in wind into electricity via a rotor with two or more blades coupled to an electric generator [70]. Wind speed varies as the height changes [98]; hence, it is crucial to calculate wind velocity at the hub height. For this, HOMER applies the logarithmic law, as shown in Equation (12), to guess wind speed at the desired elevation [67].
U h u b = U a n e m ln ( h h u b / h 0 ) ln ( h a n e m / h 0 )
Here, U h u b and U a n e m are wind speed at the hub height, h h u b , and wind speed collected at the height of anemometer, h a n e m , respectively. Furthermore, h 0 refers to the surface roughness length. Finally, the power produced by the WT generator is estimated using Equation (13) [97].
P W T   = ( ρ ρ 0 ) P W T , S T C
where ρ and ρ 0 , respectively, denote the actual density of air and the density of air at standard test conditions with certain pressure and temperature. P W T , S T C is the WT output under standard test conditions which is to be computed by HOMER using the WT’s power curve. Two other important values reported on technical sheet of the turbines are cut-off and cut-out wind speeds; no power will be generated if wind speed at the hub height is less than the former or more than the latter [99].

4.4. Electrolyzer Modeling

H2 is the most favorable, futuristic energy carrier as it releases virtually zero emissions when being applied. There are no pure H2 molecules available in the surrounding environment. However, it can be obtained via several chemical processes. To this end, water electrolysis is the promising method in which an electrolyzer utilizes electricity to make the decompaction of water into H2 and O2 molecules happen [99]. The essential factor connected with modeling and sizing of an electrolyzer is the H2 production rate which can be projected via Equation (14) [79].
H P R = 96 ×   n c × I E l e 2 F ×   e x p   ( 0.09 I E l e 75.5 I E l e 2 )
Here, n c denotes the number of cells in series, F is the faraday constant, and I E l e is designated to represent the electrolyzer current. HOMER utilizes Equation (15) to evaluate the required input energy for electrolyzer [100].
E E l e = B E l e × Q N + A E l e × Q
where B E l e and A E l e are known as curve consumption coefficients. Q N and Q represent the nominal mass flowrate of H2 and the mass flowrate of H2, respectively.

4.5. FC Modeling

Renewable-based power generation systems usually suffer from a major weakness derived from the intermittent nature of renewable resources during hours when the sunshine is not available or wind in not blowing. To solve this interrupting issue, one or more types of energy storage or backup systems should be added to the plant. Among which, FC has grasped the attention of system designers especially for rural electrification purposes, as it can be fed by H2 generated via the aid of the excess electricity [16,88]. In this study, it is postulated that the type of FC is proton exchange membranes, owing to its benefits such as low-cost maintenance, high energy conversion efficiency, and low operating temperature [101]. To evaluate the output voltage of a FC, Equation (16) can be used [102].
V F C = E V a c t V o h m V c o n c
where the four variables of E , V a c t , V o h m , V c o n c refer to open circuit voltage, activation FC overvoltage, ohmic FC overvoltage, and concentration FC overvoltage, respectively. It is worth mentioning that, in HOMER software, to add a FC to the proposed system, it should be selected from the category of generators. HOMER has provided the option of modifying the characteristics of a generator to simulate and imitate the specifications of a FC [103]. Equation (17) is deployed to predict efficiency of a FC [85].
η F C = V c ¯ × n c , F C × I F C Q × H H V h y d
Here, V c ¯ , n c , F C , and I F C represent the average voltage of a cell in FC, the total number of cells in FC, and the FC current, respectively. H H V h y d is the gross calorific value existing in H2 which is considered usually between 120 and 142 MJ/kg [104].

4.6. BMG Modeling

Living in the countryside and rural areas usually associates with livestock activities, thus the waste of cattle and other animals is amply available in these particular regions. However, this invaluable resource of energy is mostly being discarded without being properly exploited. In the case study area, most villagers have cattle, including cows, goats, sheep, chickens, camels, mules, and horses, to provide organic products or recreational activities for tourists. Therefore, animal manure is assumed to be the biomass source of the generator simulated and modeled in one of the proposed systems. To turn the energy prevailing in the bio waste into electricity, a gasifier is required for transforming solid bio-residue into a gaseous fuel. Equation (18) is given to project the yearly output electricity of a BMG [53].
E b i o = P b i o × 8760 × C U F
where P b i o and C U F signify the rating of BMG and the capacity utilization factor, respectively. Equation (19) evaluates the maximum rating of BMG which is deployed in the proposed system [105].
P b i o m a x = T b i o × 1000 × C b i o × η b i o 365 × 865 × O b i o
Here, T b i o represents the total amount of biomass available to be used in the gasifier. C b i o and η b i o , respectively, denote the calorific value of the type of biomass to be applied and the efficiency of converting biomass to electricity. O b i o refers to the hours of operating BMG.

4.7. Converter Modeling

One of the indispensable components of an HRE system is the converter in which an inverter and a rectifier are essential parts in order to make the transition from AC to DC, and vice versa, occur [68]. The selection of inverter depends on AC loads and its efficiency can be calculated using Equation (20) [106].
η i n v = P i n v , o u t P i n v , i n
where P i n v , o u t and P i n v , i n are the output power and the input power of inverter, respectively.

4.8. Thermal Load Controller (TLC) Modeling

The existence of TLC is of high importance for the heat production system and so it is added to the proposed system in order to transfer the surplus electricity generated via the system to the thermal load. The main benefit brought to the designed system by TLC is improvement of renewable fraction, resulting in fewer emissions [97]. To simulate the role of TLC in the system made by HOMER, it is just required to determine the size and the cost of TLC.

4.9. H2 Tank Modeling

To store the produced H2 in excess of the amount required by FC or boiler, a storage should be incorporated in the proposed system. The most vital feature of this component is its ability to endure holding the high-pressure H2 [92]. Equation (21) can calculate the pressure of H2 stored in the tank [107].
P H 2 , t a n k = C H 2 × θ H 2 × T V H 2
Here, C H 2 , θ H 2 , and T represent the compressibility rate of H2, the gas constant, with a H2 value at 4124.18 Nm/kg·K, and temperature, respectively. V H 2 is also the specific volume. Similar to TLC, HOMER software just allows the users to set the volume of H2 tank and its price.

4.10. Boiler Modeling

In order to add a boiler into the models, the type and price of the fuel, emission factors, and efficiency should be set for the software to simulate the unit. In this regard, efficiency means the fraction of the fuel’s energy which is being turned into heat [96].

5. Technical Characteristics, Cost of Equipment and Assumptions

To simulate the electricity and heat co-generation system and optimize the size of each component, HOMER needs some technical features and the price of involved equipment. For this, Table 1 lists the technical specifications and costs of all components employed in the system.
A nominal discount rate with a mean value of 17.5% and inflation with that of 18% are deemed the benchmark case for further judgment. Then, to assess the impact of economic uncertainty on optimal sizing, the nominal discount rate and inflation are postulated to fluctuate in the range of 15–20% and 10–26%, respectively, based on the figures of a period of 20 years [23]. This consideration seems to be essential in order to obtain the most prospective results bounded by the worst-case and best-case scenarios. As mentioned, for the case when the boiler consumes NG, it is assumed that the price of fuel would equal $0.3/m3 [92]. Finally, it is presumed that the project lifespan would be 25 years.
As discussed, Mesr village is a touristy area attracting many visitors throughout the year. Therefore, electrical demand is relatively high compared to its number of residents. According to the load profile reported by Isfahan Province Electricity Distribution Company, electricity consumption for purposes other than heating possesses an average of 203.35 kWh/d with a peak of 27.44 kW. On the other side, daily average electricity requirement for thermal usage would be 163.23 kWh with a peak of 42.91 kW. It should be clarified that the figures associated with the electrical load revealed that electricity served for heating applications, such as space heating, water heating, and cooking, would be almost 80% of that served for other usages, such as lighting, cooling, kitchen appliances, etc. Figure 3 and Figure 4 depict these two profiles on an hourly, daily, and monthly basis.
In this study, the three following configurations are analyzed as illustrated in Figure 5, Figure 6 and Figure 7:
(I)
PV/WT/electrolyzer/H2-based FC/H2-based boiler
(II)
PV/WT/electrolyzer/H2-based FC/NG-based boiler
(III)
PV/WT/BMG/electrolyzer/H2-based boiler

6. Analysis

6.1. The Benchmark Case ( i = 17.5% and f   = 18%)

In the first model simulated and analyzed by HOMER, it was assumed that FC and boiler backups consume renewable H2 yielded by electrolyzer. In the second model boiler, it would use NG as fuel and just FC would consume renewable H2. In the third model, BMG would be utilized instead of FC and just boiler would run on renewable H2. LCOE and T N P C of the first model in its benchmark case would equate to 0.33 $/kWh and $647,708, respectively, which are higher than those of the two other configurations. However, at the end of the project lifetime, the salvage value of components utilized in the first model would be greater than that of the other models. Table 2 provides the results of optimal sizing and economic assessment of the models.
In relation to the technical results of these systems under the benchmark case, Table 3 demonstrates total electricity and thermal energy generation along with other findings. With regard to the unmet electric load, the first and second proposed systems showed promising figures, which would breed high reliability. Even though the third system had less TNPC compared to the two other models, its unmet electric load revealed that it could not be relied upon. Comparing the first and second models in terms of their TNPC, the latter would be more cost-efficient. Irrespective of TNPC, the second model would roughly emit 11.5 tons/year of CO2 which is its main disadvantage, as it is not being eco-friendly. Based on the findings represented in Table 3, the first model would perfectly meet all electric and thermal energy demands, and would also be the most environmentally-friendly one. Thus, in the following sub-section, this model is analyzed considering economic uncertainty.

6.2. Analysis of the First Model under Economic Uncertainty

As mentioned, predicting the future value of money in underdeveloped countries may be onerous due to the high fluctuations in the discount rate and inflation. Hence, to obtain the most likely results as to the economics of PV/WT/electrolyzer/H2-based FC/H2-based boiler system, the least and the highest prospective amounts of these rates were incorporated into the projections. To this end, the nominal discount rate and inflation were considered to vary in the range of 15–20% and 10–26%, respectively, based on the 20-year average from mid-2000 to mid-2020.
The results proved that, if the nominal discount rate,   i , rose, and the inflation rate,   f , declined, then LCOE would increase. For instance, when i   = 15% and f   = 26%, the amount of LCOE would equate to 0.102 $/kWh, which is less than one-third of the benchmark value = 0.33 $/kWh. On the other side, when i   = 20% and f   = 10%, LCOE would augment significantly over twofold of the benchmark value to 0.662 $/kWh. Figure 8 depicts the surface plot of the variations in TNPC, considering the fluctuations of these two rates.
Figure 9 demonstrates the surface plot concerned with annual electric production as a consequence of the variations in the rates. It can be inferred that, for the case when i lowered and f grew, the electric production would increase and LCOE would diminish. Furthermore, Figure 10 provides the status of annual thermal energy generation considering different values of i and f .
Finally, Figure 11, Figure 12 and Figure 13, respectively, show electricity generation via FC, via PV, and via WT units, when i and f vary.
In Figure 13, the central part of the chart shows the values related to the benchmark case.

7. Discussion and Suggestions for Implementation

One of the most vital criteria that would hinder the exploitation of renewable energies in underdeveloped nations is economic uncertainty. Owing to some unforeseeable factors impinging upon the value of currency in these countries, speculation on economics of projects seems to be difficult. For example, Iran has experienced many ups and downs in its currency value due to lifting and imposing international sanctions. However, this issue can be dealt with via considering the fluctuations in the discount rate and inflation. To this end, in this study, the mean values of these rates were first incorporated into the calculations to set a benchmark case. Then, the most possible range of changes for these two rates were taken into account.
As the results of economic uncertainty analysis indicated, LCOE of the nominated system, PV/WT/electrolyzer/H2-based FC/H2-based boiler, would not be cost-competitive to conventional methods of electricity generation under the majority of likely values of the discount rate and inflation. Here, the role of the government and its underwriting policies are extremely decisive in the implementation of the proposed system in the nominated remote area. To achieve energy security, to decarbonize and decentralize energy sector, to meet the Paris Agreement emission targets, and to sustain the environment, governments should underpin such schemes by the following.
(I)
Furnishing the investors or private companies with zero percent or low-rate loans.
(II)
Introducing carbon tax to encourage the generation and use of renewable electricity.
(III)
Setting strict rules and regulations against carbon-intensive means of generating electricity.
(IV)
Developing the concept of green tourism to attract as many national and international visitors as possible. The corresponding revenues can cover a substantial proportion of the project’s costs.
(V)
Subsidizing the price of renewable electricity for residents (can be achieved from the resource of funding allocated to operating and maintaining the transmission and distribution network as it would no longer be needed).
(VI)
Lifting tariffs on importing equipment such as PV, WT, electrolyzer, FC, etc.
It is less doubtful that these carbon neutral remote power generation systems will be eventually valued in the marketplace, owing to their differentiated and distinguished quality of energy, if serious constraints in the energy market are imposed on carbon production.

8. Conclusions

In the first part of analysis, three models for co-supplying a touristy village with electricity and heat were proposed and analyzed in terms of technical, economic, environmental, and reliability aspects under the conditions of the benchmark case, i   = 17.5% and f   = 18%, taken from the average value of a 20-year period. The following results were obtained:
  • The first model, the PV/WT/electrolyzer/H2-based FC/H2-based boiler, had the highest TNPC ($647,708), the lowest unmet electric load, and the highest reliability without any detrimental impact on the environment.
  • The second model, the PV/WT/electrolyzer/H2-based FC/NG-based boiler, possessed the second least TNPC ($548,906), and it could meet almost all electric demand. Whereas, utilizing it would end up releasing some 11.5 tons of CO2 per year. This carbon footprint constitutes a challenging negative point for the second model which may strongly inhibit all the attempts to accomplish the Paris Agreement targets.
  • The techno-economic analysis of the third model, the PV/WT/BMG/electrolyzer/H2-based boiler, showed that it would not be reliable, as 20.5% of total electric load could not be met via this system. However, its TNPC, $488,878, was the least amongst the three analyzed configurations.
In the second part of the paper, the fluctuations in i and f were in accordance with the 20-year average from mid-2000 to mid-2020, respectively, between 15–20% and 10–26%. The results of technical and economic assessment of the first model under economic uncertainty and comparison with the related values of the benchmark case are as follows:
  • The amount of LCOE would vary from 0.102 $/kWh to 0.662 $/kWh, meaning LCOE could be between one-third of the benchmark value and two-fold that (LCOE for the benchmark case = 0.33 $/kWh). Additionally, TNPC would fluctuate between $478,704 and $814,905 from 26% less than the benchmark value up to 26% more than that (TNPC for the benchmark case = $647,708).
  • The optimal size of PV and the number of WT units would change from 25.9 to 52.5 kW and from 11 to 18, respectively. Comparing with the benchmark case (PV size = 33.8 kW and number of WT units = 14), the PV size could vary from an amount of 23% less than the benchmark case up to 55% more than that, and corresponding figures for WT would be 21% and 29%, respectively.
  • The amount of renewable H2 consumed by boiler and FC would be in the ranges of 1815–1962 kg and 559–665 kg, respectively. When comparing with the benchmark (H2 consumption in boiler = 1922 kg and that in FC = 618), the former would fluctuate from an amount of 6% less than the benchmark value up to an amount of 2% more than that, and related numbers for FC would be 10% and 8%, respectively.

9. Future Research Direction

The authors stimulate researchers to conduct a study for ascertaining the political, social, and geographical barriers to the development of such programs in developing countries and then introducing firm and applicable blueprints for eliminating these obstacles.

Author Contributions

M.R.: Conceptualization, Data curation, Formal analysis, Investigation, Methodology, Resources, Software, Validation, Visualization, Writing—original draft, Writing—review & editing; U.D.: Conceptualization, Formal analysis, Investigation, Resources, Validation, Visualization; B.K.D.: Conceptualization, Formal analysis, Investigation, Resources, Validation, Visualization; O.N.: Funding acquisition, Project administration, Validation; P.F.B.: Conceptualization, Formal analysis, Investigation, Software, Validation, Visualization; M.A.M.: Conceptualization, Data curation, Formal analysis, Investigation, Methodology, Resources, Software, Supervision, Validation, Visualization, Writing—original draft, Writing—review & editing. All authors have read and agreed to the published version of the manuscript.

Funding

This project was supported by Researchers Supporting Project number (RSP-2021/257), King Saud University, Riyadh, Saudi Arabia.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Authors acknowledge that data pertinent to this study will be provided upon request.

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

ACAlternating Current
A E l e and B E l e Curve consumption coefficients (kW/kg/h) of electrolyzer
BMGBiomass generator
C b i o Biomass’s calorific value
C H 2 Compressibility rate of hydrogen
C o p Operating cost ($)
C r e p Replacement cost ($)
C R F Capacity rate factor
C t o t a l , a n Total annualized cost ($)
C t o t a l , i n i Total initial capital cost ($)
C U F Capacity utilization factor
DCDirect Current
DGDiesel generator
E Open circuit voltage (v)
E b i o Annual output electricity of a biomass gasifier (kW)
E E l e Required electricity by the electrolyzer (kW)
E g r i d , E x Electricity sold to the grid (kWh/yr)
E P r i m , A C AC primary load served (kWh/yr)
E P r i m , D C DC primary load served (kWh/yr)
f Annual inflation rate (%)
F Faraday constant
FCFuel cell
f P V Degradation factor (%) of PV
G ¯ T Solar radiation (W/m2)
G T , N O C T Amount of solar radiation at which NOCT is defined which equals 800 W/m2
G ¯ T , S T C Standard radiation (W/m2)
h 0 Surface roughness length (m)
H 2 Hydrogen
h a n e m Anemometer height (m)
h h u b Hub height (m)
H P R Hydrogen production rate
HREHybrid renewable energy
i Real annual discount rate (%)
i Nominal discount rate (%)
I E l e Electrolyzer current (A)
I F C Fuel cell current (A)
kgKilogram
kWKilowatt
kWhKilowatt hour
LCOELevelized cost of electricity ($/kWh)
LHVLower heating value (MJ/kg)
NGNatural gas
ρ 0 Air density at standard pressure and temperature (kg/m3)
n Project lifetime (yr)
n c Number of cells in series in the electrolyzer
n c o m Lifetime of a component (yr)
n c , F C Total number of cells in the fuel cell
O b i o Hours of operating biomass gasifier (h)
O 2 Oxygen
P b i o Rating of a biomass gasifier system
P b i o m a x Maximum rating of biomass gasifier
P i n v , i n Input power of inverter
P i n v , o u t Output power of inverter
P H 2 , t a n k Pressure of hydrogen in the tank
P P V Power output of PV system (kW)
PVPhotovoltaic
P W T Power output of wind turbine (kW)
P W T , S T C Wind turbine output under STC (kW)
Q Mass flowrate of hydrogen (kg/h)
Q N Nominal mass flowrate of hydrogen (kg/h)
S v a l Salvage value of a component ($)
T Temperature
T α Ambient temperature (°C)
T α , N O C T Ambient temperature at which NOCT is defined which equals 20 °C
T b i o Total amount of biomass
T c PV cell temperature (°C)
T c , N O C T Nominal operating cell temperature (°C)
T c , S T C Standard PV cell temperature (°C)
TLCThermal load controller
TNPCTotal net present cost ($)
U a n e m Wind speed at the anemometer height (m/s)
U h u b Wind speed at the hub height (m/s)
U L The coefficient of heat transfer (kW/m2)
V c ¯ Average voltage of a cell in the fuel cell (v)
V a c t Activation fuel cell overvoltage (v)
V c o n c Concentration fuel cell overvoltage (v)
V F C Fuel cell output voltage (v)
V H 2 Volume of hydrogen in tank
V o h m Ohmic fuel cell overvoltage (v)
WWatt
WTWind turbine
Y P V Rated capacity of PV system (kW)
yrYear
αSolar absorption of PV array (%)
α P Temperature coefficient (%/°C)
°CDegree Celsius
τTransmittance of the cover over PV system
ρ Real air density (kg/m3)
η c Electrical conversion efficiency of PV system
η b i o Biomass to electricity conversion efficiency
η F C Fuel cell efficiency
η i n v Inverter efficiency
θ H 2 Hydrogen gas constant (4124.18 Nm/kg.K)

References

  1. Al-Ghussain, L.; Ahmad, A.D.; Abubaker, A.M.; Mohamed, M.A. An integrated photovoltaic/wind/biomass and hybrid energy storage systems towards 100% renewable energy microgrids in university campuses. Sustain. Energy Technol. Assess. 2021, 46, 101273. [Google Scholar]
  2. Mostafaeipour, A.; Rezayat, H.; Rezaei, M. A thorough investigation of solar-powered hydrogen potential and accurate location planning for big cities: A case study. Int. J. Hydrogen Energy 2020, 45, 31599–31611. [Google Scholar] [CrossRef]
  3. Mohamed, M.A.; Abdullah, H.M.; El-Meligy, M.A.; Sharaf, M.; Soliman, A.T.; Hajjiah, A. A novel fuzzy cloud stochastic framework for energy management of renewable microgrids based on maximum deployment of electric vehicles. Int. J. Electr. Power Energy Syst. 2021, 129, 106845. [Google Scholar] [CrossRef]
  4. Rezaei, M.; Mostafaeipour, A.; Jafari, N.; Naghdi-Khozani, N.; Moftakharzadeh, A. Wind and solar energy utilization for seawater desalination and hydrogen production in the coastal areas of southern Iran. J. Eng. Des. Technol. 2020, 18, 1951–1969. [Google Scholar] [CrossRef]
  5. Rezaei, M.; Khalilpour, K.R.; Mohamed, M.A. Co-production of electricity and hydrogen from wind: A comprehensive scenario-based techno-economic analysis. Int. J. Hydrogen Energy 2021, 46, 18242–18256. [Google Scholar] [CrossRef]
  6. Samy, M.M.; Mosaad, M.I.; Barakat, S. Optimal economic study of hybrid PV-wind-fuel cell system integrated to unreliable electric utility using hybrid search optimization technique. Int. J. Hydrogen Energy 2020, 46, 11217–11231. [Google Scholar] [CrossRef]
  7. Wang, S.; Wang, S.; Liu, J. Life-cycle green-house gas emissions of onshore and offshore wind turbines. J. Clean. Prod. 2019, 210, 804–810. [Google Scholar] [CrossRef]
  8. Sedaghat, A.; Mostafaeipour, A.; Rezaei, M.; Jahangiri, M.; Mehrabi, A. A new semi-empirical wind turbine capacity factor for maximizing annual electricity and Hydrogen production. Int. J. Hydrogen Energy 2020, 45, 15888–15903. [Google Scholar] [CrossRef]
  9. Al-Ghussain, L.; Ahmad, A.D.; Abubaker, A.M.; Abujubbeh, M.; Almalaq, A.; Mohamed, M.A. A Demand-Supply Matching-Based Approach for Mapping Renewable Resources Towards 100% Renewable Grids in 2050. IEEE Access 2021, 9, 58634–58651. [Google Scholar] [CrossRef]
  10. Alshammari, N.; Asumadu, J. Optimum unit sizing of hybrid renewable energy system utilizing harmony search, Jaya and particle swarm optimization algorithms. Sustain. Cities Soc. 2020, 60, 102255. [Google Scholar] [CrossRef]
  11. Mohamed, M.A.; Almalaq, A.; Abdullah, H.M.; Alnowibet, K.A.; Alrasheedi, A.F.; Zaindin, M.S.A. A Distributed Stochastic Energy Management Framework Based-Fuzzy-PDMM for Smart Grids Considering Wind Park and Energy Storage Systems. IEEE Access 2021, 9, 46674–46685. [Google Scholar] [CrossRef]
  12. Abbassi, A.; Dami, M.A.; Jemli, M. A statistical approach for hybrid energy storage system sizing based on capacity distributions in an autonomous PV/Wind power generation system. Renew. Energy 2017, 103, 81–93. [Google Scholar] [CrossRef]
  13. Guo, S.; He, Y.; Pei, H.; Wu, S. The multi-objective capacity optimization of wind-photovoltaic-thermal energy storage hybrid power system with electric heater. Sol. Energy 2020, 195, 138–149. [Google Scholar] [CrossRef]
  14. Attemene, N.S.; Agbli, K.S.; Fofana, S.; Hissel, D. Optimal sizing of a wind, fuel cell, electrolyzer, battery and supercapacitor system for off-grid applications. Int. J. Hydrogen Energy 2020, 45, 5512–5525. [Google Scholar] [CrossRef]
  15. Alsharif, M.; Nordin, R.; Ismail, M. Energy optimisation of hybrid off-grid system for remote telecommunication base station deployment in Malaysia. EURASIP J. Wirel. Commun. Netw. 2015, 64, 1–15. [Google Scholar] [CrossRef] [Green Version]
  16. Aris, A.M.; Shabani, B. Sustainable Power Supply Solutions for Off-Grid Base Stations. Energy 2015, 8, 10904–10941. [Google Scholar] [CrossRef] [Green Version]
  17. Rajanna, S.; Saini, R.P. Development of optimal integrated renewable energy model with battery storage for a remote Indian area. Energy 2016, 111, 803–817. [Google Scholar] [CrossRef]
  18. Samy, M.M.; Elkhouly, H.I.; Barakat, S. Multi-objective optimization of hybrid renewable energy system based on biomass and fuel cells. Int. J. Energy Res. 2020, 45, 8214–8230. [Google Scholar] [CrossRef]
  19. Rosso-Cerón, A.M.; Kafarov, V.; Latorre-Bayona, G.; Quijano-Hurtado, R. A novel hybrid approach based on fuzzy multi-criteria decision-making tools for assessing sustainable alternatives of power generation in San Andrés Island. Renew. Sustain. Energy Rev. 2019, 110, 159–173. [Google Scholar] [CrossRef]
  20. Mytilinou, V.; Kolios, A.J. Techno-economic optimisation of offshore wind farms based on life cycle cost analysis on the UK. Renew. Energy 2019, 132, 439–454. [Google Scholar] [CrossRef]
  21. Ould Amrouche, S.; Rekioua, D.; Rekioua, T.; Bacha, S. Overview of energy storage in renewable energy systems. Int. J. Hydrogen Energy 2016, 41, 20914–20927. [Google Scholar] [CrossRef]
  22. Nordin, N.D.; Rahman, H.A. Comparison of optimum design, sizing, and economic analysis of standalone photovoltaic/battery without and with Hydrogen production systems. Renew. Energy 2019, 141, 107–123. [Google Scholar] [CrossRef]
  23. Available online: tradingeconomics.com (accessed on 21 March 2021).
  24. Borowski, P.F. Significance and Directions of Energy Development in African Countries. Energy 2021, 14, 4479. [Google Scholar] [CrossRef]
  25. Borowski, P.F. Adaptation strategy on regulated markets of power companies in Poland. Energy Environ. 2019, 30, 3–26. [Google Scholar] [CrossRef]
  26. Bakhtiari, H.; Zhong, J.; Alvarez, M. Predicting the stochastic behavior of uncertainty sources in planning a stand-alone renewable energy-based microgrid using Metropolis–coupled Markov chain Monte Carlo simulation. Appl. Energy 2021, 290, 116719. [Google Scholar] [CrossRef]
  27. Bouchekara, H.R.E.-H.; Javaid, M.S.; Shaaban, Y.A.; Shahriar, M.S.; Ramli, M.A.M.; Latreche, Y. Decomposition based multiobjective evolutionary algorithm for PV/Wind/Diesel Hybrid Microgrid System design considering load uncertainty. Energy Rep. 2021, 7, 52–69. [Google Scholar] [CrossRef]
  28. Blazquez, J.; Nezamuddin, N.; Zamrik, T. Economic policy instruments and market uncertainty: Exploring the impact on renewables adoption. Renew. Sustain. Energy Rev. 2018, 94, 224–233. [Google Scholar] [CrossRef]
  29. Ebrahimi, J.; Abedini, M.; Rezaei, M.M.; Nasri, M. Optimum design of a multi-form energy in the presence of electric vehicle charging station and renewable resources considering uncertainty. Sustain. Energy Grids Netw. 2020, 23, 100375. [Google Scholar] [CrossRef]
  30. Li, J.; Huang, S.; Abedinia, O. Investigation in Economic Analysis of Microgrids based on Renewable Energy Uncertainty and Demand Response in the Electricity Market. Energy 2021, 225, 120247. [Google Scholar]
  31. Barati, F.; Jadid, S.; Zangeneh, A. Private investor-based distributed generation expansion planning considering uncertainties of renewable generations. Energy 2019, 173, 1078–1091. [Google Scholar] [CrossRef]
  32. Mirzamohammadi, S.; Jabarzadeh, A.; Shahrabi, M.S. Long-term planning of supplying energy for greenhouses using renewable resources under uncertainty. J. Clean. Prod. 2020, 264, 121611. [Google Scholar] [CrossRef]
  33. Liu, B.; Lund, J.R.; Liao, S.; Jin, X.; Liu, L.; Cheng, C. Optimal power peak shaving using hydropower to complement wind and solar power uncertainty. Energy Convers. Manag. 2020, 209, 112628. [Google Scholar] [CrossRef]
  34. Li, Y.; Zhang, F.; Li, Y.; Wang, Y. An improved two-stage robust optimization model for CCHP-P2G microgrid system considering multi-energy operation under wind power outputs uncertainties. Energy 2021, 223, 120048. [Google Scholar] [CrossRef]
  35. Tan, Q.; Wen, X.; Sun, Y.; Lei, X.; Wang, Z.; Qin, G. Evaluation of the risk and benefit of the complementary operation of the large wind-photovoltaic-hydropower system considering forecast uncertainty. Appl. Energy 2021, 285, 116442. [Google Scholar] [CrossRef]
  36. Ezbakhe, F.; Pérez-Foguet, A. Decision analysis for sustainable development: The case of renewable energy planning under uncertainty. Eur. J. Oper. Res. 2021, 291, 601–613. [Google Scholar] [CrossRef]
  37. Fitiwi, D.Z.; Lynch, M.; Bertsch, V. Power system impacts of community acceptance policies for renewable energy deployment under storage cost uncertainty. Renew. Energy 2020, 156, 893–912. [Google Scholar] [CrossRef]
  38. Scott, I.J.; Botterud, A.; Carvalho, P.M.S.; Silva, C.A.S. Renewable energy support policy evaluation: The role of long-term uncertainty in market modelling. Appl. Energy 2020, 278, 115643. [Google Scholar] [CrossRef]
  39. Tsao, Y.-C.; Thanh, V.-V. Toward blockchain-based renewable energy microgrid design considering default risk and demand uncertainty. Renew. Energy 2021, 163, 870–881. [Google Scholar] [CrossRef]
  40. Yang, J.; Su, C. Robust optimization of microgrid based on renewable distributed power generation and load demand uncertainty. Energy 2021, 223, 120043. [Google Scholar] [CrossRef]
  41. Wang, C.; Zhang, Z.; Abedinia, O.; Farkoush, S.G. Modeling and analysis of a microgrid considering the uncertainty in renewable energy resources, energy storage systems and demand management in electrical retail market. J. Energy Storage 2021, 33, 102111. [Google Scholar] [CrossRef]
  42. Xu, H.; Meng, Z.; Wang, Y. Economic dispatching of microgrid considering renewable energy uncertainty and demand side response. Energy Rep. 2020, 6, 196–204. [Google Scholar] [CrossRef]
  43. Yuan, W.; Liu, Z.; Su, C.; Wang, X. Photovoltaic capacity optimization of small and medium-sized hydro-photovoltaic hybrid energy systems considering multiple uncertainties. J. Clean. Prod. 2020, 276, 124170. [Google Scholar] [CrossRef]
  44. Zhang, H.; Hu, X.; Cheng, H.; Zhang, S.; Hong, S.; Gu, Q. Coordinated scheduling of generators and tie lines in multi-area power systems under wind energy uncertainty. Energy 2021, 222, 119929. [Google Scholar] [CrossRef]
  45. Zhang, Y.; Gu, C.; Yan, X.; Li, F. Cournot oligopoly game-based local energy trading considering renewable energy uncertainty costs. Renew. Energy 2020, 159, 1117–1127. [Google Scholar] [CrossRef]
  46. Zhang, Z.; Qin, H.; Li, J.; Liu, Y.; Yao, L.; Wang, Y.; Wang, C.; Pei, S.; Zhou, J. Short-term optimal operation of wind-solar-hydro hybrid system considering uncertainties. Energy Convers. Manag. 2020, 205, 112405. [Google Scholar] [CrossRef]
  47. Zhu, F.; Zhong, P.A.; Xu, B.; Liu, W.; Wang, W.; Sun, Y.; Chen, J.; Li, J. Short-term stochastic optimization of a hydro-wind-photovoltaic hybrid system under multiple uncertainties. Energy Convers. Manag. 2020, 214, 112902. [Google Scholar] [CrossRef]
  48. Olatomiwa, L.; Mekhilef, S.; Huda, A.S.N.; Ohunakin, O.S. Economic evaluation of hybrid energy systems for rural electrification in six geo-political zones of Nigeria. Renew. Energy 2015, 83, 435–446. [Google Scholar] [CrossRef]
  49. Olatomiwa, L.; Mekhilef, S.; Huda, A.S.N.; Sanusi, K. Techno-economic analysis of hybrid PV–diesel–battery and PV–wind–diesel–battery power systems for mobile BTS: The way forward for rural development. Energy Sci. Eng. 2015, 3, 271–285. [Google Scholar] [CrossRef]
  50. Brenna, M.; Foiadelli, F.; Longo, M.; Abegaz, T.D. Integration and Optimization of Renewables and Storages for Rural Electrification. Sustainability 2016, 8, 982. [Google Scholar] [CrossRef] [Green Version]
  51. Isa, N.M.; Das, H.S.; Tan, C.W.; Yatim, A.H.M.; Lau, K.Y. A techno-economic assessment of a combined heat and power photovoltaic/fuel cell/battery energy system in Malaysia hospital. Energy 2016, 112, 75–90. [Google Scholar] [CrossRef]
  52. Singh, A.; Baredar, P. Techno-economic assessment of a solar PV, fuel cell, and biomass gasifier hybrid energy system. Energy Rep. 2016, 2, 254–260. [Google Scholar] [CrossRef] [Green Version]
  53. Singh, S.; Singh, M.; Kaushik, S.C. Feasibility study of an islanded microgrid in rural area consisting of PV, wind, biomass and battery energy storage system. Energy Convers. Manag. 2016, 128, 178–190. [Google Scholar] [CrossRef]
  54. Das, B.K.; Hoque, N.; Mandal, S.; Pal, T.K.; Raihan, M.A. A techno-economic feasibility of a stand-alone hybrid power generation for remote area application in Bangladesh. Energy 2017, 134, 775–788. [Google Scholar] [CrossRef]
  55. Das, H.S.; Tan, C.W.; Yatim, A.H.M.; Lau, K.Y. Feasibility analysis of hybrid photovoltaic/battery/fuel cell energy system for an indigenous residence in East Malaysia. Renew. Sustain. Energy Rev. 2017, 76, 1332–1347. [Google Scholar] [CrossRef]
  56. Khemariya, M.; Mittal, A.; Baredar, P.; Singh, A. Cost and size optimization of solar photovoltaic and fuel cell based integrated energy system for un-electrified village. J. Energy Storage 2017, 14, 62–70. [Google Scholar] [CrossRef]
  57. Rajbongshi, R.; Borgohain, D.; Mahapatra, S. Optimization of PV-biomass-diesel and grid base hybrid energy systems for rural electrification by using HOMER. Energy 2017, 126, 461–474. [Google Scholar] [CrossRef]
  58. Shahzad, M.K.; Zahid, A.; ur Rashid, T.; Rehan, M.A.; Ali, M.; Ahmad, M. Techno-economic feasibility analysis of a solar-biomass off grid system for the electrification of remote rural areas in Pakistan using HOMER software. Renew. Energy 2017, 106, 264–273. [Google Scholar] [CrossRef]
  59. Ahmad, J.; Imran, M.; Khalid, A.; Iqbal, W.; Ashraf, S.R.; Adnan, M.; Ali, S.F.; Khokhar, K.S. Techno economic analysis of a wind-photovoltaic-biomass hybrid renewable energy system for rural electrification: A case study of Kallar Kahar. Energy 2018, 148, 208–234. [Google Scholar] [CrossRef]
  60. Duman, A.C.; Güler, Ö. Techno-economic analysis of off-grid PV/wind/fuel cell hybrid system combinations with a comparison of regularly and seasonally occupied households. Sustain. Cities Soc. 2018, 42, 107–126. [Google Scholar] [CrossRef]
  61. Dursun, B.; Aykut, E. An investigation on wind/PV/fuel cell/battery hybrid renewable energy system for nursing home in Istanbul. Proc. Inst. Mech. Eng. Part A J. Power Energy 2019, 233, 616–625. [Google Scholar] [CrossRef]
  62. Gebrehiwot, K.; Mondal, M.A.H.; Ringler, C.; Gebremeskel, A.G. Optimization and cost-benefit assessment of hybrid power systems for off-grid rural electrification in Ethiopia. Energy 2019, 177, 234–246. [Google Scholar] [CrossRef]
  63. Groppi, D.; Astiaso Garcia, D.; Lo Basso, G.; Cumo, F.; De Santoli, L. Analysing economic and environmental sustainability related to the use of battery and Hydrogen energy storages for increasing the energy independence of small islands. Energy Convers. Manag. 2018, 177, 64–76. [Google Scholar] [CrossRef]
  64. Karmaker, A.K.; Ahmed, M.R.; Hossain, M.A.; Sikder, M.M. Feasibility assessment & design of hybrid renewable energy based electric vehicle charging station in Bangladesh. Sustain. Cities Soc. 2018, 39, 189–202. [Google Scholar]
  65. Khare, V.; Nema, S.; Baredar, P. Optimisation of the hybrid renewable energy system by HOMER, PSO and CPSO for the study area. Int. J. Sustain. Energy 2017, 36, 326–343. [Google Scholar] [CrossRef]
  66. Pavan Kumar, Y.V.; Bhimasingu, R. Renewable energy based microgrid system sizing and energy management for green buildings. J. Mod. Power Syst. Clean Energy 2015, 3, 1–13. [Google Scholar] [CrossRef] [Green Version]
  67. Baneshi, M.; Hadianfard, F. Techno-economic feasibility of hybrid diesel/PV/wind/battery electricity generation systems for non-residential large electricity consumers under southern Iran climate conditions. Energy Convers. Manag. 2016, 127, 233–244. [Google Scholar] [CrossRef]
  68. Li, C.; Zhou, D.; Zheng, Y. Techno-economic comparative study of grid-connected PV power systems in five climate zones, China. Energy 2018, 165, 1352–1369. [Google Scholar] [CrossRef]
  69. Mandal, S.; Das, B.K.; Hoque, N. Optimum sizing of a stand-alone hybrid energy system for rural electrification in Bangladesh. J. Clean. Prod. 2018, 200, 12–27. [Google Scholar] [CrossRef]
  70. Olatomiwa, L.; Blanchard, R.; Mekhilef, S.; Akinyele, D. Hybrid renewable energy supply for rural healthcare facilities: An approach to quality healthcare delivery. Sustain. Energy Technol. Assess. 2018, 30, 121–138. [Google Scholar] [CrossRef] [Green Version]
  71. Oulis Rousis, A.; Tzelepis, D.; Konstantelos, I.; Booth, C.; Strbac, G. Design of a Hybrid AC/DC Microgrid Using HOMER Pro: Case Study on an Islanded Residential Application. Invention 2018, 3, 55. [Google Scholar] [CrossRef] [Green Version]
  72. Robert, F.C.; Gopalan, S. Low cost, highly reliable rural electrification through a combination of grid extension and local renewable energy generation. Sustain. Cities Soc. 2018, 42, 344–354. [Google Scholar] [CrossRef]
  73. Abdin, Z.; Mérida, W. Hybrid energy systems for off-grid power supply and Hydrogen production based on renewable energy: A techno-economic analysis. Energy Convers. Manag. 2019, 196, 1068–1079. [Google Scholar] [CrossRef]
  74. Abnavi, M.D.; Mohammadshafie, N.; Rosen, M.A.; Dabbaghian, A.; Fazelpour, F. Techno-economic feasibility analysis of stand-alone hybrid wind/photovoltaic/diesel/battery system for the electrification of remote rural areas: Case study Persian Gulf Coast-Iran. Environ. Prog. Sustain. Energy 2019, 38, 13172. [Google Scholar] [CrossRef]
  75. Das, B.K.; Al-Abdeli, Y.M.; Woolridge, M. Effects of battery technology and load scalability on stand-alone PV/ICE hybrid micro-grid system performance. Energy 2019, 168, 57–69. [Google Scholar] [CrossRef]
  76. Kumar, K.; Alam, M.; Dutta, V. Techno-economic analysis of metal hydride-based energy storage system in microgrid. Energy Storage 2019, 1, e62. [Google Scholar] [CrossRef] [Green Version]
  77. Li, C. Techno-economic study of off-grid hybrid photovoltaic/battery and photovoltaic/battery/fuel cell power systems in Kunming, China. Energy Sources Part A Recovery Util. Environ. Eff. 2019, 41, 1588–1604. [Google Scholar] [CrossRef]
  78. Li, C.; Zhou, D.; Wang, H.; Cheng, H.; Li, D. Feasibility assessment of a hybrid PV/diesel/battery power system for a housing estate in the severe cold zone—A case study of Harbin, China. Energy 2019, 185, 671–681. [Google Scholar] [CrossRef]
  79. Luta, D.N.; Raji, A.K. Optimal sizing of hybrid fuel cell-supercapacitor storage system for off-grid renewable applications. Energy 2019, 166, 530–540. [Google Scholar] [CrossRef]
  80. Marino, C.; Nucara, A.; Panzera, M.F.; Pietrafesa, M.; Varano, V. Energetic and economic analysis of a stand alone photovoltaic system with Hydrogen storage. Renew. Energy 2019, 142, 316–329. [Google Scholar] [CrossRef]
  81. Muh, E.; Tabet, F. Comparative analysis of hybrid renewable energy systems for off-grid applications in Southern Cameroons. Renew. Energy 2019, 135, 41–54. [Google Scholar] [CrossRef]
  82. Murugaperumal, K.; Ajay DVimal Raj, P. Feasibility design and techno-economic analysis of hybrid renewable energy system for rural electrification. Sol. Energy 2019, 188, 1068–1083. [Google Scholar] [CrossRef]
  83. Razmjoo, A.; Davarpanah, A. Developing various hybrid energy systems for residential application as an appropriate and reliable way to achieve Energy sustainability. Energy Sources Part A Recovery Util. Environ. Eff. 2019, 41, 1180–1193. [Google Scholar] [CrossRef]
  84. Tiwary, A.; Spasova, S.; Williams, I.D. A community-scale hybrid energy system integrating biomass for localised solid waste and renewable energy solution: Evaluations in UK and Bulgaria. Renew. Energy 2019, 139, 960–967. [Google Scholar] [CrossRef]
  85. Arévalo, P.; Benavides, D.; Lata-García, J.; Jurado, F. Energy control and size optimization of a hybrid system (photovoltaic-hidrokinetic) using various storage technologies. Sustain. Cities Soc. 2020, 52, 101773. [Google Scholar] [CrossRef]
  86. Azerefegn, T.M.; Bhandari, R.; Ramayya, A.V. Techno-economic analysis of grid-integrated PV/wind systems for electricity reliability enhancement in Ethiopian industrial park. Sustain. Cities Soc. 2020, 53, 101915. [Google Scholar] [CrossRef]
  87. Temiz, M.; Javani, N. Design and analysis of a combined floating photovoltaic system for electricity and Hydrogen production. Int. J. Hydrogen Energy 2020, 45, 3457–3469. [Google Scholar] [CrossRef]
  88. Vendoti, S.; Muralidhar, M.; Kiranmayi, R. Techno-economic analysis of off-grid solar/wind/biogas/biomass/fuel cell/battery system for electrification in a cluster of villages by HOMER software. Environ. Dev. Sustain. 2020, 23, 351–372. [Google Scholar] [CrossRef]
  89. Available online: Wikipedia.com (accessed on 11 February 2021).
  90. Available online: www.amar.org.ir (accessed on 19 February 2021).
  91. Sinha, S.; Chandel, S.S. Review of software tools for hybrid renewable energy systems. Renew. Sustain. Energy Rev. 2014, 32, 192–205. [Google Scholar] [CrossRef]
  92. Vaziri Rad, M.A.; Ghasempour, R.; Rahdan, P.; Mousavi, S.; Arastounia, M. Techno-economic analysis of a hybrid power system based on the cost-effective Hydrogen production method for rural electrification, a case study in Iran. Energy 2020, 190, 116421. [Google Scholar]
  93. Razmjoo, A.; Gakenia Kaigutha, L.; Vaziri Rad, M.A.; Marzband, M.; Davarpanah, A.; Denai, M.A. Technical analysis investigating energy sustainability utilizing reliable renewable energy sources to reduce CO2 emissions in a high potential area. Renew. Energy 2021, 164, 46–57. [Google Scholar] [CrossRef]
  94. Yimen, N.; Hamandjoda, O.; Meva’a, L.; Ndzana, B.; Nganhou, J. Analyzing of a Photovoltaic/Wind/Biogas/Pumped-Hydro Off-Grid Hybrid System for Rural Electrification in Sub-Saharan Africa—Case Study of Djoundé in Northern Cameroon. Energy 2018, 11, 2644. [Google Scholar] [CrossRef] [Green Version]
  95. Kasaeian, A.; Rahdan, P.; Rad, M.A.V.; Yan, W.-M. Optimal design and technical analysis of a grid-connected hybrid photovoltaic/diesel/biogas under different economic conditions: A case study. Energy Convers. Manag. 2019, 198, 111810. [Google Scholar] [CrossRef]
  96. HOMER. The HOMER Pro® Microgrid Software. Available online: http://www.homerenergy.com (accessed on 16 December 2020).
  97. Akhtari, M.R.; Baneshi, M. Techno-economic assessment and optimization of a hybrid renewable co-supply of electricity, heat and Hydrogen system to enhance performance by recovering excess electricity for a large energy consumer. Energy Convers. Manag. 2019, 188, 131–141. [Google Scholar] [CrossRef]
  98. Rezaei, M.; Naghdi-Khozani, N.; Jafari, N. Wind energy utilization for Hydrogen production in an underdeveloped country: An economic investigation. Renew. Energy 2020, 147, 1044–1057. [Google Scholar] [CrossRef]
  99. Rezaei, M.; Khalilpour, K.R.; Jahangiri, M. Multi-criteria location identification for wind/solar based Hydrogen generation: The case of capital cities of a developing country. Int. J. Hydrogen Energy 2020, 45, 33151–33168. [Google Scholar] [CrossRef]
  100. Singh, A.; Baredar, P.; Gupta, B. Techno-economic feasibility analysis of Hydrogen fuel cell and solar photovoltaic hybrid renewable energy system for academic research building. Energy Convers. Manag. 2017, 145, 398–414. [Google Scholar] [CrossRef]
  101. Krishnan, K.J.; Kalam, A.; Zayegh, A. Experimental Investigation of H2 Generator and PEM Fuel Cell as a Remote Area Back-Up Power. Procedia Eng. 2012, 49, 66–73. [Google Scholar] [CrossRef]
  102. Chong, L.W.; Wong, Y.W.; Rajkumar, R.K.; Rajkumar, R.K.; Isa, D. Hybrid energy storage systems and control strategies for stand-alone renewable energy power systems. Renew. Sustain. Energy Rev. 2016, 66, 174–189. [Google Scholar] [CrossRef]
  103. Ghenai, C.; Bettayeb, M. Modelling and performance analysis of a stand-alone hybrid solar PV/Fuel Cell/Diesel Generator power system for university building. Energy 2019, 171, 180–189. [Google Scholar] [CrossRef]
  104. Bicer, Y.; Dincer, I. Clean fuel options with Hydrogen for sea transportation: A life cycle approach. Int. J. Hydrogen Energy 2018, 43, 1179–1193. [Google Scholar] [CrossRef]
  105. Gupta, A.; Saini, R.P.; Sharma, M.P. Steady-state modelling of hybrid energy system for off grid electrification of cluster of villages. Renew. Energy 2010, 35, 520–535. [Google Scholar] [CrossRef]
  106. Cano, A.; Arévalo, P.; Jurado, F. Energy analysis and techno-economic assessment of a hybrid PV/HKT/BAT system using biomass gasifier: Cuenca-Ecuador case study. Energy 2020, 202, 117727. [Google Scholar] [CrossRef]
  107. Cumalioglu, I.; Ma, Y.; Ertas, A.; Maxwell, T. High Pressure Hydrogen Storage Tank: A Parametric Design Study. J. Press. Vessel. Technol. 2006, 129, 216–222. [Google Scholar] [CrossRef]
  108. Lau, K.Y.; Tan, C.W.; Yatim, A.H.M. Photovoltaic systems for Malaysian islands: Effects of interest rates, diesel prices and load sizes. Energy 2015, 83, 204–216. [Google Scholar] [CrossRef]
  109. Gökçek, M.; Kale, C. Techno-economical evaluation of a Hydrogen refuelling station powered by Wind-PV hybrid power system: A case study for İzmir-Çeşme. Int. J. Hydrogen Energy 2018, 43, 10615–10625. [Google Scholar] [CrossRef]
Figure 1. The fluctuations in (a) the nominal discount rate and (b) inflation from mid-2000 to mid-2020.
Figure 1. The fluctuations in (a) the nominal discount rate and (b) inflation from mid-2000 to mid-2020.
Processes 09 01468 g001
Figure 2. The approach of the study.
Figure 2. The approach of the study.
Processes 09 01468 g002
Figure 3. The hourly, daily and monthly profile of electric load.
Figure 3. The hourly, daily and monthly profile of electric load.
Processes 09 01468 g003
Figure 4. The hourly, daily and monthly profile of thermal load.
Figure 4. The hourly, daily and monthly profile of thermal load.
Processes 09 01468 g004
Figure 5. Schematic of the first model simulated by HOMER.
Figure 5. Schematic of the first model simulated by HOMER.
Processes 09 01468 g005
Figure 6. Schematic of the second model simulated by HOMER.
Figure 6. Schematic of the second model simulated by HOMER.
Processes 09 01468 g006
Figure 7. Schematic of the third model simulated by HOMER.
Figure 7. Schematic of the third model simulated by HOMER.
Processes 09 01468 g007
Figure 8. Changes of TNPC considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to LCOE).
Figure 8. Changes of TNPC considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to LCOE).
Processes 09 01468 g008
Figure 9. Changes of annual electric production considering the fluctuations of the nominal discount rate and inflation (Numbers inside the surface plot refer to LCOE).
Figure 9. Changes of annual electric production considering the fluctuations of the nominal discount rate and inflation (Numbers inside the surface plot refer to LCOE).
Processes 09 01468 g009
Figure 10. Changes of annual thermal energy generation considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the amount of H2 consumed by boiler).
Figure 10. Changes of annual thermal energy generation considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the amount of H2 consumed by boiler).
Processes 09 01468 g010
Figure 11. Changes of electricity generation via FC considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the amount of H2 consumed by FC).
Figure 11. Changes of electricity generation via FC considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the amount of H2 consumed by FC).
Processes 09 01468 g011
Figure 12. Changes of electricity generation via PV considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the optimal size of PV).
Figure 12. Changes of electricity generation via PV considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the optimal size of PV).
Processes 09 01468 g012
Figure 13. Changes of electricity generation via WT units considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the optimal number of the wind turbines).
Figure 13. Changes of electricity generation via WT units considering the fluctuations of the nominal discount rate and inflation (numbers inside the surface plot refer to the optimal number of the wind turbines).
Processes 09 01468 g013
Table 1. Technical specifications and costs of the components.
Table 1. Technical specifications and costs of the components.
ComponentModel
(Abbreviation)
Technical SpecificationsCapital CostReplacement CostOperation and Maintenance CostRef. for Costs
PVFronius Symo 4.5-3-S
(Fron4.5)
Rated capacity: 4.4 kW
Lifetime: 25 yr
Electrical bus: AC
Derating factor: 96%
Temperature coefficient: −0.41%/°C
Operating temperature: 45 °C
Efficiency at standard test conditions: 17.3%
Ground reflectance: 20%
Tracking system: no tacking
Panel type: flat plate
2000 ($/kW)2000 ($/kW)10 ($/kW.yr)[97]
WTBergey Excel 6
(XL6)
Rated capacity: 6 kW
Lifetime: 20 yr
Electrical bus: AC
Hub height: 30 m
Rotor diameter: 6.2 m
Cut-in wind speed: 2.5 m/s
Cut-out wind speed: none
2000 ($/kW)1600 ($/kW)50 ($/#.yr)[62]
BMGGeneric Biogas Genset
(Bio)
Size: 20 kW
Lifetime: 20,000 h
Electrical bus: AC
Fuel type: animal manure
LHV = 19 MJ/kg
Gasification ratio: 0.047 kg/kg
Density of biogas: 1.15 kg/m3
Carbon content: 44%
Daily available biomass: 2000 kg
Biogas fuel price: 0 $/kg
2300 ($/kW)1500 ($/kW)0.01 ($/op.h)[53]
FCGeneric Fuel Cell
(FC)
Size: 20 kW
Lifetime: 50,000 h
Electrical bus: DC
Heat recover ratio: 60%
Minimum runtime: 20 min
Fuel type: stored hydrogen
LHV = 120 MJ/kg
Carbon content: 0
Stored hydrogen price: 0 $/kg
2000 ($/kW)1860 ($/kW)0.01 ($/op.h)[92]
TLCGeneric thermal load controller (TLC)Size: 100 kW
Lifetime: 20 yr
Electrical bus: DC and AC
54 ($/kW)54 ($/kW)0 ($/kW)[97]
BoilerGeneric boilerEfficiency: 85%
Fuel type 1: stored hydrogen
LHV= 120 MJ/kg
Carbon content: 0
Stored hydrogen price: 0 $/kg
Fuel type 2: natural gas
LHV = 45 MJ/kg
Density: 0.79 kg/m3
Carbon content: 67%
Natural gas price: 0.3 $/m3
----
ConverterLeonics S-219Cp 5 kW
(Leon5)
Lifetime: 10 yr
Rectifier efficiency: 94%
Rectifier relative capacity: 80%
Inverter efficiency: 96%
550 ($/kW)550 ($/kW)10 ($/kW/yr)[108]
ElectrolyzerGeneric ElectrolyzerSize: specified in model
Lifetime: 15 yr
Electrical bus: DC
Efficiency: 85%
2000 ($/kW)2000 ($/kW)50 ($/kW/yr)[93]
H2 TankGeneric hydrogen tank
(H2Tank)
Initial tank level: 0600 ($/kg)600 ($/kg)10 ($/yr)[109]
Table 2. Optimization results of simulating the models.
Table 2. Optimization results of simulating the models.
ModelPV
(kW)
WT
(#)
FC
(kW)
BMG
(kW)
Electrolyzer
(kW)
TLC
(kW)
H2 Tank
(kg)
Converter
(kW)
TNPC
($)
LCOE
($)
Salvage Value
($)
No. 133.81420 *-40 *100 *10 *48.7647,7080.33−177,219
No. 228.4920 *-20 *100 *10 *28.8548,9060.248−139,048
No. 3438-20 *30 *100 *10 *37.1488,8780.313−131,344
The numbers with ∗ mean that HOMER does not optimize them. So, they should be determined by the user of the software. For this, the size of electrolyzer is set 20 kW in the second model in which just FC consumes H2, while in the other models is 30 and 40 kW.
Table 3. Technical results of analyzing the models.
Table 3. Technical results of analyzing the models.
Model No. 1Model No. 2Model No. 3
Total electricity production (kWh/yr)241,422180,162181,722
The share of PV (%)25.62940.9
The share of WT (%)65.956.750
The share of FC (%)8.514.3-
The share of BMG (%)--9.1
Excess electricity (kWh/yr)30,77327,86915,719
Unmet electric load (%)0.0510.06520.5
Renewable fraction43.941.753.3
Total thermal energy production (kWh/yr)85,23480,13471,153
The share of boiler (%)63.965.277.9
The share of excess electricity (%)36.134.822.1
Excess thermal energy (kWh/yr)25,65520,55611,574
H2 consumption by FC (kg/yr)618771-
Capacity factor of FC (%)11.714.7-
Biomass consumption by BMG (tonnes/yr)--730
Capacity factor of BMG (%)--9.5
Total renewable production divided by load (%)109105114
Capacity factor of PV (%)20.92119.7
Capacity factor of WT (%)21.621.621.6
H2 consumption by boiler (kg/yr)1922-1956
NG consumption by boiler (m3/yr)-6905-
Total H2 generation by electrolyzer (kg/yr)275915752167
Capacity factor of electrolyzer (%)36.541.738.3
CO2 emission (kg/yr)011,5351175
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Rezaei, M.; Dampage, U.; Das, B.K.; Nasif, O.; Borowski, P.F.; Mohamed, M.A. Investigating the Impact of Economic Uncertainty on Optimal Sizing of Grid-Independent Hybrid Renewable Energy Systems. Processes 2021, 9, 1468. https://doi.org/10.3390/pr9081468

AMA Style

Rezaei M, Dampage U, Das BK, Nasif O, Borowski PF, Mohamed MA. Investigating the Impact of Economic Uncertainty on Optimal Sizing of Grid-Independent Hybrid Renewable Energy Systems. Processes. 2021; 9(8):1468. https://doi.org/10.3390/pr9081468

Chicago/Turabian Style

Rezaei, Mostafa, Udaya Dampage, Barun K. Das, Omaima Nasif, Piotr F. Borowski, and Mohamed A. Mohamed. 2021. "Investigating the Impact of Economic Uncertainty on Optimal Sizing of Grid-Independent Hybrid Renewable Energy Systems" Processes 9, no. 8: 1468. https://doi.org/10.3390/pr9081468

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop