Research on the Steel Enterprise Gas–Steam–Electricity Network Hybrid Scheduling Model for Multi-Objective Optimization
Abstract
1. Introduction
2. Automatic Identification and Tracking of Operating Conditions and Energy Fluctuation Prediction Technology Based on Operating Conditions
2.1. Data Acquisition and Preprocessing
2.2. Working Condition Definition and Management
2.3. Model-Driven Volatility Prediction
2.4. Output and Application-Oriented Visualization
3. Based on Peak–Valley–Flat Electricity Price and Gas Tank Peak Shifting and Valley Filling Scheduling Model
- (1)
- The traditional gas tank scheduling model usually only focuses on the balance at the physical level, and fails to internalize the important market economy signal of “peak–flat–valley” time-of-use electricity price as the optimization goal, so it cannot make full use of the electricity price difference to achieve the economic benefits of “peak shifting and valley filling”.
- (2)
- The existing models generally regard the operating efficiency of key energy conversion equipment such as boilers and steam turbines as a fixed constant, which is seriously inconsistent with the nonlinear characteristics of the efficiency of the equipment in actual operation with the dynamic change in the load, resulting in the theoretical optimal scheduling scheme in practice. It is often difficult to implement or even counterproductive.
- (3)
- The existing model scheduling strategy is inelastic, and it is difficult to give a predictive and optimal response to typical and severe production fluctuations such as blast furnace downtime and planned maintenance, which often leads to energy dissipation or scattered or additional cost surge.
3.1. Framework Design and Innovation of Core Scheduling Model
3.2. The Generation Mechanism of Intelligent Scheduling Strategy
- (1)
- Energy translation strategy across time and space:
- (2)
- Resource dynamic preferential allocation strategy:
3.3. Simulation Verification and Analysis for Extreme Industrial Scenarios
4. Multi-Period and Multi-Medium Energy Optimal Scheduling Model
4.1. Symbol Description
4.2. Objective Function
4.3. Model Constraints
4.4. Model Development
5. Model Application
6. Conclusions
- (1)
- This paper introduces the energy fluctuation prediction and optimal scheduling technology based on the change in working conditions. Through real-time collection of production data, combined with the working condition definition management module, the equipment operation status is identified and tracked. The prediction calculation module is used to superimpose the working condition sample curve to realize the unbalance prediction of the energy medium such as the blast furnace, coke oven and converter gas holder, and generate visual prediction curves. On this basis, a peak–valley-shifting and valley-filling scheduling model of the gas tank integrated with a peak–valley–flat electricity price mechanism is constructed. By dynamically adjusting the power generation strategy, gas is stored during the valley power period, and power generation is increased during the peak power period to reduce the cost of purchased electricity. The model comprehensively considers the operation characteristics of equipment, energy coupling relationship and adjustment cost, so as to improve the scheduling accuracy and economy. The application results show that the proportion of purchased electricity in the peak period is significantly reduced after optimization, the energy cost is reduced by 3.12%, and the system energy consumption is reduced by 2.16%, which effectively improves the energy utilization efficiency and economic benefits.
- (2)
- In this paper, a multi-period and multi-medium energy optimization scheduling model is established to realize the safe and stable operation of the energy system in the steel production process and maximize the economic benefits. The model combines the fluctuation prediction curve and the peak-shifting and valley-filling mechanism of the gas holder, comprehensively considers factors such as the change in working conditions and the peak–valley price, and establishes a nonlinear programming model (MINLP) to optimize the scheduling of gas, steam, electricity and other energy media. The objective function covers minimizing operating costs and energy consumption, and the constraints include energy supply and demand balance, equipment operating limits, gas holder storage capacity, and generator ramp rate. The model uses the AUGMECON2 method to solve the multi-objective Pareto optimal solution set and uses the IPOPT solver for efficient calculation. Application results demonstrate the model’s effectiveness in achieving zero gas emission and efficient energy utilization. Comparative analysis (see Section 5, Table 7, Table 8 and Table 9) shows that the model achieves improvements in gas holder prediction accuracy (≥95%), scheduling instruction accuracy (95%), self-generation ratio, and electricity purchase cost reduction relative to benchmark models and domestic advanced levels.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Zhang, L.; Yuan, Y.X.; Xi, J.X.; Sun, J.; Yan, S.; Du, T.; Na, H. Synergistic enhancement for energy-saving, emission reduction and profit improvement in iron and steel manufacturing system: Strategies for parameter regulation and technologies integration. Energy Convers. Manag. 2024, 322, 119101. [Google Scholar] [CrossRef]
- Yuan, Y.; Na, H.; Chen, C.; Qiu, Z.; Sun, J.; Zhang, L.; Du, T.; Yang, Y. Status, challenges, and prospects of energy efficiency improvement methods in steel production: A multi-perspective review. Energy 2024, 304, 132047. [Google Scholar] [CrossRef]
- Qiu, Z.Y.; Yuan, Y.X.; Yan, T.Y.; Na, H.; Sun, J.; Wang, Y.; Du, T. Optimization of gas–steam–electricity network of typical iron and steel enterprise. J. Sustain. Metall. 2022, 8, 806–814. [Google Scholar] [CrossRef]
- Hu, Z.C.; Zheng, Z.; Hu, K.; Li, C.; Yang, Y. The dynamic evaluation and optimization model for steel enterprise’s energy flow network operations. Energy Rep. 2022, 8, 2151–2162. [Google Scholar] [CrossRef]
- Zhang, Q.; Cai, J.J.; Jun, S.; Liu, W.-c. Study on energy efficiency and energy management in integrate iron and steel works. In Proceedings of the ICEET: 2009 International Conference on Energy and Environment Technology, Guilin, China, 16–18 October 2009; pp. 341–343. [Google Scholar] [CrossRef]
- Yang, J.H.; Cai, J.J.; Sun, W.Q.; Liu, J.-Y. Optimization and scheduling of byproduct gas system in steel plant. J. Iron Steel Res. Int. 2015, 22, 408. [Google Scholar] [CrossRef]
- Sun, W.Q.; Cai, J.J.; Song, J. Plant-wide supply-demand forecast and optimization of byproduct gas system in steel plant. J. Iron Steel Res. Int. 2013, 20, 1–7. [Google Scholar] [CrossRef]
- Zhao, X.C.; Bai, H.; Lu, X.; Shi, Q.; Han, J. A MILP model concerning the optimisation of penalty factors for the short-term distribution of byproduct gases produced in the iron and steel making process. Appl. Energy 2015, 148, 142. [Google Scholar] [CrossRef]
- Zhao, X.C.; Bai, H.; Shi, Q.; Lu, X.; Zhang, Z. Optimal scheduling of a byproduct gas system in a steel plant considering time-of-use electricity pricing. Appl. Energy 2017, 195, 100. [Google Scholar] [CrossRef]
- Zhao, X.C.; Bai, H.; Li, H.X.; Wang, C.; Zheng, L.; Han, J. Dynamic optimal allocation model of surplus gas in iron and steel production process. J. Univ. Sci. Technol. Beijing 2015, 37, 97. [Google Scholar] [CrossRef]
- Shi, Q.; Zhao, X.C.; Bai, H.; Xing, W.; Zhang, Z. Short-period optimal scheduling model of by-product gas in iron and steel enterprises. Iron Steel 2016, 51, 81. [Google Scholar] [CrossRef]
- Kim, J.H.; Yi, H.S.; Han, C. A novel MILP Model for plantwide multiperiod optimization of byproduct gas supply system in the iron- and steel-making process. Trans. Inst. Chem. Eng. 2003, 81, 1015–1025. [Google Scholar] [CrossRef]
- Li, X.L.; He, D.F.; Guo, Y.Z.; Feng, K. Optimization model of steelmaking production scheduling based on time and temperature coordination. Iron Steel 2025, 60, 109–119+130. [Google Scholar] [CrossRef]
- He, D.F.; Li, X.L.; Guo, W.; Guo, Y.; Feng, K.; Yang, R.; Du, C.; Zhang, L. Online control system of molten steel temperature based on combination of reservation and prediction. China Metall. 2024, 34, 74–83. [Google Scholar] [CrossRef]
- Hu, Z.B.; He, D.F. Operation scheduling optimization of gas-steam-electricity conversion system in iron and steel enterprises. In Proceedings of the 13th China Iron and Steel Annual Conference, Online, 23–24 November 2022; p. 172. [Google Scholar]
- He, D.F.; Li, Z.H.; Hu, Z.B. Compound scheduling method for gas-steam-electricity system in iron and steel enterprises. Metall. Energy 2021, 40, 3–8+50. [Google Scholar] [CrossRef]
- He, D.F.; Liu, P.Z.; Feng, K.; Xu, A. Collaborative optimization of rolling plan and energy scheduling in iron and steel enterprises. China Metall. 2019, 29, 75–80. [Google Scholar] [CrossRef]
- Zhang, L. Research on Multi-Energy Coupling Optimization Scheduling of Gas-Steam-Electricity in Iron and Steel Enterprises. Master’s Thesis, Inner Mongolia University of Science and Technology, Baotou, China, 2025. [Google Scholar] [CrossRef]
- Tian, W.J. Research on Multi-Objective Optimization Scheduling Model for Energy Complementary Coordination in Iron and Steel Enterprises. Doctoral Dissertation, University of Science and Technology Beijing, Beijing, China, 2024. [Google Scholar] [CrossRef]
- Yao, L.; Zhang, Y.; Lv, Z.; Zhang, H. Multi-energy flow network multi-condition optimal scheduling of thermoelectric system in iron and steel enterprises. Control Theory Appl. 2022, 39, 1297–1307. [Google Scholar] [CrossRef]
- Zhao, J.; Liu, Q.; Pedrycz, W.; Li, D. Effective noise estimation-based online prediction for byproduct gas system in steel industry. IEEE Trans. Ind. Inform. 2012, 8, 953–963. [Google Scholar] [CrossRef]
- Pena, J.G.C.; De Oliveira Junior, V.B.; Salles, J.L.F. Optimal scheduling of a by-product gas supply system in the iron-and steel-making process under uncertainties. Comput. Chem. Eng. 2019, 125, 351–364. [Google Scholar] [CrossRef]
- Meng, H.; Fan, G.F. Forecasting of gas supply in self-provided power plant of iron and steel enterprises based on time series. IOP Conf. Ser. Earth Environ. Sci. 2019, 227, 042008. [Google Scholar] [CrossRef]
- Zhu, Y.; Ma, R.; Wu, D.; Shen, Y. Prediction of blast furnace gas output based on Elman neural network. In 2021 33rd Chinese Control and Decision Conference (CCDC); IEEE: New York, NY, USA, 2021; pp. 1337–1342. [Google Scholar] [CrossRef]
- Zeng, Y.J.; Xiao, X.; Li, J. A novel multi-period mixed-integer linear optimization model for optimal distribution of byproduct gases, steam and power in an iron and steel plant. Energy 2018, 143, 881–899. [Google Scholar] [CrossRef]
- Wei, Z.; Zhai, X.; Zhang, Q.; Yang, G.; Du, T.; Wei, J. A MINLP model for multi-period optimization considering couple of gas-steam-electricity and time of use electricity price in steel plant. Appl. Therm. Eng. 2020, 168, 114834. [Google Scholar] [CrossRef]
- Zhang, Q.; Zhao, T.; Ni, T.J.; Gao, J. Optimization models for operation of a steam power system in integrated iron and steel works. Energy Sources Part A Recovery Util. Environ. Eff. 2021, 43, 1100–1114. [Google Scholar] [CrossRef]
- Hu, Z.; He, D. Operation scheduling optimization of gas-steam-power conversion systems in iron and steel enterprises. Appl. Therm. Eng. 2022, 206, 118121. [Google Scholar] [CrossRef]
- Zhao, P.; Yang, J.; Li, Z.; Zhou, B. Optimization method for multi-process energy consumption in iron and steel enterprises under the coordinated use of comprehensive energy. J. Phys. Conf. Ser. 2024, 2729, 012017. [Google Scholar] [CrossRef]
- Hu, Z.B.; He, D.F.; Zhao, H.B. Multi-objective optimization of energy distribution in steel enterprises considering both exergy efficiency and energy cost. Energy 2023, 263, 125623. [Google Scholar] [CrossRef]
- Keshetti, A.R.; Ruela, V.S.P.; Chen, H.; Machado, M.R. Advanced Analytics to Improve Energy Efficiency of Steel Industry—A Systematic Review on Ladle Logistics. Clean. Eng. Technol. 2025, 25, 100907. [Google Scholar] [CrossRef]













| Category | Parameter | Value | Unit | Instruction |
|---|---|---|---|---|
| Gasometer | BFG_Cabinet capacity | 30 | 1 × 104 m3 | Blast furnace gas holder |
| BFG_Cabinet lower limit | 3 | 1 × 104 m3 | ||
| BFG_Cabinet upper limit | 27 | 1 × 104 m3 | ||
| COG_Cabinet capacity | 5 | 1 × 104 m3 | Coking oven gas holder | |
| Lower limit of COG_Cabinet | 0.5 | 1 × 104 m3 | ||
| COG_Cabinet upper limit | 4.5 | 1 × 104 m3 | ||
| LDG_Cabinet1 capacity | 15 | 1 × 104 m3 | Converter gas holder 1 | |
| Lower lower bound of LDG_Cabinet1 | 1.5 | 1 × 104 m3 | ||
| Upper limit of LDG_Cabinet1 | 13.5 | 1 × 104 m3 | ||
| LDG_Cabinet2 capacity | 15 | 1 × 104 m3 | Converter gas holder 2 | |
| Lower lower bound of LDG_Cabinet2 | 1.5 | 1 × 104 m3 | ||
| Upper limit of LDG_Cabinet2 | 13.5 | 1 × 104 m3 | ||
| Generator unit | 78 MW#1 ramp rate | 1 | MW/min | 260-ton boiler #1 |
| 78 MW#2 ramping rate | 1 | MW/min | 260-ton boiler #2 | |
| 100 MW ramp rate | 1 | MW/min | 330-ton boiler | |
| Calorific value of gas | Calorific value of blast furnace gas | 3500 | kJ/Nm3 | |
| Heat value of converter gas | 7000 | kJ/Nm3 | ||
| Calorific value of coke oven gas | 17,500 | kJ/Nm3 | ||
| Price parameters | Unit price of external coke gas | - | CNY/1 × 104 m3 | Configuration required |
| Unit price of external natural gas | - | CNY/1 × 104 m3 | Configuration required | |
| Peak hour tariff | - | CNY/1 × 104 kWh | Configuration required | |
| Peak tariff | - | CNY/1 × 104 kWh | Configuration required | |
| Normal electricity price | - | CNY/1 × 104 kWh | Configuration required | |
| Peak hour tariff | - | CNY/1 × 104 kWh | Configuration required | |
| External transmission price | 3.78 | CNY/1 × 104 kWh | ||
| Delivery blast furnace gas price | - | CNY/1 × 104 m3 | Configuration required | |
| Delivery coke oven gas price | - | CNY/1 × 104 m3 | Configuration required | |
| Delivery price of converter gas | - | CNY/1 × 104 m3 | Configuration required | |
| Penalty coefficient | Deviation penalty coefficient | 500 | - | |
| Over limit penalty coefficient | 20,000 | - | ||
| Penalty coefficient for exceeding the lower limit | 20,000 | - | ||
| High altitude discharge penalty coefficient | - | CNY/1 × 104 m3 | Configuration required | |
| Transient dissipation penalty coefficient | - | CNY/1 × 104 m3 | Configuration required | |
| Adjustment cost | Adjustment cost of 78 MW#1 blast furnace gas | 2300 | CNY | |
| Adjustment cost of 78 MW#1 coke oven gas | 2300 | CNY | ||
| 78 MW#1 converter gas adjustment cost | 2000 | CNY | ||
| 78 MW#2 blast furnace gas adjustment cost | 2300 | CNY | ||
| Adjustment cost of 78 MW#2 coke oven gas | 2300 | CNY | ||
| 78 MW#2 converter gas adjustment cost | 2000 | CNY | ||
| Adjustment cost of 100 MW blast furnace gas | 3200 | CNY | ||
| Adjustment cost of 100 MW coke oven gas | 3200 | CNY | ||
| Adjustment cost of 100 MW converter gas | 2400 | CNY | ||
| Start stop cost | 78 MW#1 start-up and shutdown cost | 50,000 | CNY | |
| 78 MW#2 start-up and shutdown cost | 50,000 | CNY | ||
| 100 MW start-up and shutdown costs | 600,000 | CNY | ||
| Calorific value constraint | Lower limit of calorific value of mixed fuel | - | kJ/Nm3 | Configuration required |
| Upper limit of calorific value of mixed stock | - | kJ/Nm3 | Configuration required | |
| Lower limit of calorific value of lime kiln | - | kJ/Nm3 | Configuration required | |
| Upper limit of lime kiln calorific value | - | kJ/Nm3 | Configuration required |
| Energy Medium | Specific Type | Key Performance Indicators | Cost Range (2025) | Consumption Trend |
|---|---|---|---|---|
| Coke | Blast Furnace Coke (for ironmaking) | Fixed carbon (FC) ≥ 85%, ash content ≤ 12%, sulfur content ≤ 0.7%, cold strength (CSR) ≥ 65%, particle size 40–80 mm; energy density ~29,300 KJ/kg | Domestic: 1800–3500 CNY/ton; international: $230–$620/ton | Dominates coke consumption (accounting for ~85% of total coke use); consumption volume shows a slow downward trend (total energy consumption of key steel enterprises down 0.54% YoY in 2025 Q1–Q3) due to blast furnace optimization and scrap steel recycling, but remains the core raw material for ironmaking |
| Foundry Coke (for casting molds) | Fixed carbon (FC) ≥ 88%, ash content ≤ 10%, sulfur content ≤ 0.5%, high mechanical strength, particle size 60–100 mm; energy density ~30,500 KJ/kg | 2200–4000 CNY/ton | Stable demand driven by casting industry development; affected by green casting policies, high-quality low-sulfur products are favored to meet emission requirements | |
| Nut Coke (auxiliary fuel) | Particle size 10–40 mm, fixed carbon ≥ 80%, ash content ≤ 13%, sulfur content ≤ 0.8%; energy density ~28,000 KJ/kg | 1300–2500 CNY/ton | Increasingly used as auxiliary fuel in blast furnaces and converters to improve energy utilization rate; consumption grows moderately with the promotion of energy-saving technologies | |
| Coke Breeze (fuel for boilers) | Particle size < 10 mm, fixed carbon ≥ 75%, ash content ≤ 15%, sulfur content ≤ 0.9%; energy density ~26,000 KJ/kg | 900–1800 CNY/ton | Widely used in boiler combustion and sintering processes; consumption remains stable with the promotion of waste resource recycling (solid waste utilization rate of key steel enterprises continues to rise) | |
| By-product Gas | Blast Furnace Gas (BFG) | Composition: CO (27–30%), CO2 (8–12%), H2 (1.5–1.8%), N2 (45–65%); energy density 3200–3800 KJ/m3; density 1.35 kg/m3; explosion limit 40–70%; ignition temperature ~750 °C | By-product (negligible direct cost); recovery and purification cost ~0.12–0.35 CNY/m3 | Utilization rate continues to improve (up 0.14% YoY in 2025 Q1–Q3) with advanced recovery technology; mainly used for power generation and heating in plants, consumption keeps growing stably |
| Coke Oven Gas (COG) | Composition: H2 (55–65%), CH4 (21–30%), CO (7%), CmHn (2%), CO2 (1.5–3.5%); energy density 16,500–18,500 KJ/m3; density 0.45–0.55 kg/m3; explosion limit 6–30%; ignition temperature 550–650 °C | By-product; recovery cost ~0.35–0.65 CNY/m3 | High energy density makes it a key fuel for power generation and chemical production; utilization rate remains high (up 0.14% YoY in 2025 Q1–Q3) with stable consumption amid coking capacity adjustment | |
| Converter Gas (LDG) | Composition: CO (45–70%), CO2 (15–20%), H2 (2–4%), N2 (23–42%); energy density 5300–7500 KJ/m3; density 1.38 kg/m3; explosion limit 18.22–83.22%; ignition temperature ~530 °C | By-product; recovery cost ~0.25–0.45 CNY/m3 | Tightly connected with converter production rhythm; recovery rate continues to improve with technological upgrading; consumption fluctuates slightly but shows an upward trend in utilization efficiency |
| Bfg Holder | Coke Oven Gas Cabinet | Converter Gas Cabinet Level | ||||||
|---|---|---|---|---|---|---|---|---|
| True Value | Predicted Value | Error Magnitude | True Value | Predicted Value | Error Magnitude | True Value | Predicted Value | Error Magnitude |
| 1 × 104 m2 | 1 × 104 m2 | % | 1 × 104 m2 | 1 × 104 m2 | % | 1 × 104 m2 | 1 × 104 m2 | % |
| 5.85 | 6.29 | 7.52 | 2.15 | 2.13 | 0.43 | 1.33 | 1.45 | 2.07 |
| 5.49 | 5.57 | 1.53 | 2.26 | 2.23 | 0.62 | 1.68 | 1.70 | 0.29 |
| 5.90 | 5.03 | 14.76 | 2.37 | 2.25 | 2.17 | 1.98 | 1.88 | 1.59 |
| 5.51 | 5.80 | 5.10 | 2.30 | 2.47 | 2.99 | 1.77 | 2.00 | 4.15 |
| 5.87 | 5.57 | 5.11 | 2.25 | 2.19 | 1.07 | 1.74 | 1.63 | 1.79 |
| 6.57 | 6.30 | 4.08 | 2.18 | 2.19 | 0.15 | 1.95 | 1.91 | 0.58 |
| 6.22 | 6.73 | 8.13 | 2.08 | 2.09 | 0.19 | 2.21 | 1.84 | 5.88 |
| 5.76 | 5.93 | 2.94 | 1.82 | 1.67 | 2.71 | 2.11 | 1.74 | 6.32 |
| 4.68 | 4.70 | 0.38 | 1.83 | 1.79 | 0.86 | 1.85 | 1.78 | 1.43 |
| 4.05 | 4.67 | 15.35 | 1.89 | 1.83 | 1.53 | 2.05 | 1.82 | 5.63 |
| 4.43 | 3.75 | 15.34 | 1.87 | 1.86 | 0.36 | 1.86 | 2.15 | 6.48 |
| 4.22 | 4.79 | 13.48 | 1.88 | 1.82 | 1.42 | 2.04 | 1.80 | 5.71 |
| 3.94 | 4.06 | 3.18 | 1.88 | 1.87 | 0.43 | 2.30 | 2.24 | 1.68 |
| 4.58 | 4.07 | 11.06 | 1.95 | 1.83 | 2.47 | 2.55 | 2.42 | 2.86 |
| Time | The Peak–Valley–Flat Electricity Price Mechanism Is Not Used | Using the Peak–Valley Electricity Price Mechanism | Contrast | ||
|---|---|---|---|---|---|
| Quantity Purchased (MWh) | Proportion (%) | Purchased Electricity (MWh) | Proportion (%) | % | |
| Electricity price peak | 543.90 | 27.26 | 248.33 | 16.96 | −10.30 |
| Electricity price valley value | 547.20 | 24.42 | 517.47 | 35.34 | 10.92 |
| Electricity price valley value | 904.34 | 45.32 | 698.66 | 47.70 | 2.38 |
| Footing | 1995.44 | 100 | 1464.48 | 100 | - |
| Project | The Peak–Valley–Flat Electricity Price Mechanism Is Not Used | Using the Peak–Valley Electricity Price Mechanism | Contrast |
|---|---|---|---|
| Energy consumption cost (million CNY) | 5.88 | 5.69 | 3.16% |
| Equipment adjustment cost (thousand CNY) | 14.26 | 14.89 | −4.45% |
| Total economic operation cost (million CNY) | 5.89 | 5.71 | 3.12% |
| System energy consumption (million kgce) | 9.62 | 9.42 | 2.16% |
| Serial Number | Sign | Meaning |
|---|---|---|
| 1 | The number of time periods contained in a scheduling cycle | |
| 2 | Number of fuel types | |
| 3 | Number of schedulable boilers | |
| 4 | The consumption cost of fuel k | |
| 5 | The kth fuel consumption of boiler bi at time t | |
| 6 | The unit steam production cost of boiler bi, CNY·t−1 | |
| 7 | The boiler bi at time t steam production, t | |
| 8 | The cost of unit power generation of steam turbine ti, CNY·kWh−1 | |
| 9 | The steam turbine ti produces electricity within time t, kWh | |
| 10 | The amount of electricity purchased at time t, kWh | |
| 11 | The electricity outsourcing price at time t, CNY·kWh−1 | |
| 12 | The penalty coefficient of boiler bi when adjusting k kinds of gas | |
| 13 | The adjustment of boiler bi to k kinds of gas in time t, km3 | |
| 14 | The release penalty price of the kth gas, CNY·km3 | |
| 15 | The emission amount of the kth gas at time t, km3 | |
| 16 | The consumption of i-type substances at time t | |
| 17 | Standard coal coefficient of medium i | |
| 18 | The amount of gas g consumed by boiler b, km3·h−1 | |
| 19 | Gas g cabinet level change, km3·h−1 | |
| 20 | The emission amount of gas g, km3·h−1 | |
| 21 | Takeaway volume of gas g, km3·h−1 | |
| 22 | The surplus of coal gas g, km3·h−1 | |
| 23 | The amount of steam s produced by each boiler b, t·h−1 | |
| 24 | The amount of steam extracted by steam turbine s, t·h−1 | |
| 25 | The demand for steam s, t·h−1 | |
| 26 | The power generation of each generator, MWh | |
| 27 | Purchasing electricity or sending electricity, MWh | |
| 28 | Power demand of energy system, MWh | |
| 29 | The calorific value of gas k, kcal·km−3 | |
| 30 | Boiler bi consumption of mixed gas calorific value lower limit, kcal·km−3 | |
| 31 | Boiler bi consumes the upper limit of the calorific value of mixed gas, kcal·km−3 | |
| 32 | Boiler b water supply, t·h−1 | |
| 33 | The amount of steam s produced by the boiler, t·h−1 | |
| 34 | Blowdown of boiler b, t·h−1 | |
| 35 | Thermal efficiency of boiler b at time t | |
| 36 | Boiler b operating load at time t | |
| 37 | Boiler gas consumption g lower limit, km3·h−1 | |
| 38 | The upper limit of gas g consumed by the boiler, km3·h−1 | |
| 39 | The lower limit of steam s produced by the boiler, t·h−1 | |
| 40 | The upper limit of steam s produced by the boiler, t·h−1 | |
| 41 | Lower limit of boiler b water supply, t·h−1 | |
| 42 | Boiler b water supply limit, t·h−1 | |
| 43 | Lower limit of steam turbine inlet, t·h−1 | |
| 44 | Upper limit of steam turbine intake, t·h−1 | |
| 45 | Lower limit of exhaust steam of steam turbine, t·h−1 | |
| 46 | Steam turbine exhaust steam upper limit, t·h−1 | |
| 47 | The lower limit of steam turbine extraction, t·h−1 | |
| 48 | The upper limit of steam turbine extraction, t·h−1 | |
| 49 | Thermal efficiency of steam turbine at time t | |
| 50 | Steam turbine operating load at time t | |
| 51 | Lower limit of gas tank capacity, km3 | |
| 52 | Upper limit of gas tank capacity, km3 | |
| 53 | The maximum variation range of gas holder i is allowed in unit time, km3·h−1 | |
| 54 | The minimum specific heat value of the total calorific value of the energy mixture consumed by the equipment i is the minimum specific heat value | |
| 55 | The maximum specific heat value of the total calorific value of the mixed energy consumed by the equipment i | |
| 56 | The instantaneously raised constraint value of device i is that the device can increase the maximum power in a period of time | |
| 57 | The instantaneous downward constraint value of device i is the maximum power that the device can reduce in a period of time |
| Technical Indicators | Multi-Period and Multi-Medium Energy Optimal Scheduling Model | Model A | Model B | Conclusion |
|---|---|---|---|---|
| Prediction accuracy of blast furnace gas cabinet level | 93% | - | 92.90% | Increased by 0.11% |
| Prediction accuracy of converter gas cabinet level | 96.70% | 94.62% | - | Increased by 2.08% |
| Technical Indicators | Enterprise A | Enterprise B |
|---|---|---|
| Self-generating rate | Increase by 1% | Increase by 2% |
| Purchased electricity expense | Reduced by 12.73 million CNY/year | Reduced by 132.17 million CNY/year |
| Technical Indicators | Advanced International Standards | Domestic Advanced Level | Indicators of This Model |
|---|---|---|---|
| Multi-period and multi-condition multi-media energy optimal scheduling | Manual collection entry | Manual collection entry | Automatic identification and tracking of working conditions |
| Converter gas recovery rate of increase | - | 2.90% | 8.30% |
| Prediction accuracy of gas tank level | - | 94.60% | >95% |
| Peak-to-valley ratio of self-generation | - | 33.30% | 34.10% |
| Correct rate of scheduling instruction | - | 92% | 95% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Sheng, G.; Sun, Y.; Feng, K.; Yang, L.; Xu, B. Research on the Steel Enterprise Gas–Steam–Electricity Network Hybrid Scheduling Model for Multi-Objective Optimization. Processes 2026, 14, 1030. https://doi.org/10.3390/pr14071030
Sheng G, Sun Y, Feng K, Yang L, Xu B. Research on the Steel Enterprise Gas–Steam–Electricity Network Hybrid Scheduling Model for Multi-Objective Optimization. Processes. 2026; 14(7):1030. https://doi.org/10.3390/pr14071030
Chicago/Turabian StyleSheng, Gang, Yanguang Sun, Kai Feng, Lingzhi Yang, and Beiping Xu. 2026. "Research on the Steel Enterprise Gas–Steam–Electricity Network Hybrid Scheduling Model for Multi-Objective Optimization" Processes 14, no. 7: 1030. https://doi.org/10.3390/pr14071030
APA StyleSheng, G., Sun, Y., Feng, K., Yang, L., & Xu, B. (2026). Research on the Steel Enterprise Gas–Steam–Electricity Network Hybrid Scheduling Model for Multi-Objective Optimization. Processes, 14(7), 1030. https://doi.org/10.3390/pr14071030
